Special Railways Phase III  Proposed approach to regulatory changes Jakarta 16 May 2011
Overview of IndII Special Railway Program Identify need for changes in rail sector regulations to encourage private sector investment (Phase I – early 2010) Identify specific policy and regulatory changes needed to achieve desired results (Phase II – late 2010) Assist GoI to develop and implement regulatory reforms (Phase III – April to June 2011).
Key Objectives of Phase III Clarify and improve current Special Railway provisions through a draft Ministerial Regulation (Permen) Expand railway investment opportunities through targeted amendments to existing Government Regulations (PP 56/2009 and PP 72/2009)
Timing of Phase III Initial term sheets submitted on 21 April 2011 Inception Report finalized on 26 April 2011 Draft regulatory proposals submitted on 13 May 2011 Final draft regulatory proposals to be submitted by 15 June 2011 Final Technical Report due by late June
The Main Challenges Lack of clarity over who can operate a special railway Restrictions on the scope of special railways Uncertainty over interconnection Need for public tender under the PPP process Complexity of licensing system Lack of coordination between special railways and other regulatory licensing schemes
The Main Constraints Lack of clarity over who can operate a special railway This affects both the willingness of investors to invest and the willingness of administrators to issue licenses
The Main Constraints 2. Restrictions on the scope of special railways The ‘point to point’ rule appears to restrict railways from serving intermediate customers or terminals The ‘one customer’ rule appears to prevent a special railway from serving a group of similar industries
The Main Constraints 3.  Uncertainty over interconnection There is concern that if a special railway connects to another special railway or to a public railway, the rights of the investor may be compromised.  This discourages the creation of efficient railway networks.
The Main Constraints 4.  The need for tenders under the PPP process Private sector interests are discouraged from promoting railways because they need to be tendered under the PPP provisions.
The Main Constraints 5.  Complexity of the licensing system The process of getting all the required licences appears overly complex and time consuming
The Main Constraints 6.  Lack of coordination between special railways and other regulatory licensing schemes Proper linkages between special railway licensing and other relevant licensing schemes (e.g., mining, agriculture) must be put in place to avoid delays or inconsistent results
Proposed Solutions A new Permen will clarify the Railway Law and the existing Government Regulations (PP 56 and PP 72) Some minor changes to existing government regulations are also desirable but not strictly necessary to implement the proposed Permen No changes to the Railway Law are needed – all of the proposed regulations are consistent with the Railway Law
We propose that the Permen describe more precisely the permitted relationship between the operator and the business it serves It is suggested that the Permen require the main business to have a controlling interest in, or be under common control with, the operator Control can be defined to include ownership of a majority of the voting shares or the ability to appoint or remove a majority of the directors of a company 1. Lack of clarity as to who can operate a Special Railway
2. Restrictions to the scope of the railway  We propose three solutions to this issue defining client to permit a consortium of users defining rules for interconnection relaxing the point-to-point rule
Definition of Client Define Special Railway client to include a consortium of businesses, essentially allowing them to form and operate a common special railway serving their respective businesses.
Defining the interconnect rules Define interconnection rules under Article 374 of PP 56 to enable several special railway operators (each serving their respective client) to share infrastructure and rolling stock without losing the status of special railway
Amending the point to point rule  Amend article 350 of PP 56/2009 to relax existing ‘point-to-point’ restrictions so that several terminal points can be served (so long as such service remains related to the client’s main business) This would require an amendment to PP 56/2009
3. What happens if railways interconnect  For the most part, we can define what happens in a Permen.  Interconnection should not affect the status of a special railway (see previous comments on Article 374 of PP 56/2009). However, an amendment to Article 161(3) of PP 72/2009 would also be useful to eliminate any confusion on this point.
What happens if railways interconnect  We propose that an interconnection agreement should allow the first operator to: access the infrastructure of the other operator for the purpose of providing services in support of the first operator’s client arrange for the other operator (if it is a public operator) to provide services in support of the first operator’s client grant the other operator access to the first operator’s infrastructure for any purpose consistent with the other operator’s business
4. The need for tender under the PPP process Concern about the need to use a PPP process (with its requirement for the rail concession to be tendered) arises because this is seen as the only way of serving multiple customers This restriction can be loosened by allowing special railways to interconnect and by allowing a single special railway to serve a consortium of businesses
5. Complexity of the licensing system The procedures for obtaining licences are overly complex We think they can be simplified and streamlined without reducing their effectiveness or limiting regional autonomy Much of this simplification can be done through a Permen, though minor amendments to PP 56/2009 would also be desirable.
Proposals to Simplify the licensing system Planning issues should be addressed and resolved at in-principle approval stage (not later) Reviews by various levels of government should be coordinated and conducted simultaneously to avoid delays and inconsistent decisions Operator should be able to ‘pre-qualify’ itself during construction stage to ensure that operating permit will be issued later, subject only to meeting clear conditions
6. C oordination between special railways and other regulatory licensing schemes Proposed reforms includes option for special railway client to use an affiliate as operator (to facilitate financing) Restrictions on affiliated transactions in certain industries (e.g., mining) must be taken into account If special railway licensee must also obtain other licenses, proper coordination among relevant agencies must be ensured to avoid delays and inconsistent results
Conclusions The objective of increased private sector involvement is not being achieved because of a number of constraints We believe these constraints can effectively be addressed through regulatory provisions within the current Railway Law Most can be achieved through a new Permen, though targeted amendments of the existing PP 56/2009 and PP 72/2009 would also be desirable.
The way forward Term sheets – set out the broad principles for drafting the Permen and amendments to PP 56/2009 and PP 72/2009 Draft Permen and Amendments to PPs – the consultant team’s initial proposal for reform, based on the term sheets and initial discussions with MoT Working group – established to coordinate government input to the process and achieve broad consensus Close liaison – between our legal team and the MoT

More Related Content

PDF
Infrastructure regulation - exploring the key models (Australia)
PDF
112/2009 1-
PPT
Tprc2007
PPTX
Australian telecoms licensing - An overview
PDF
CP_on_Review_of_Network_related_QoS
PDF
Consumer Guide
PPTX
Local Loop Unbundling Final
PDF
Presentation on captive power plants
Infrastructure regulation - exploring the key models (Australia)
112/2009 1-
Tprc2007
Australian telecoms licensing - An overview
CP_on_Review_of_Network_related_QoS
Consumer Guide
Local Loop Unbundling Final
Presentation on captive power plants

What's hot (17)

PPTX
Focus group discussion on national railways master plan, jakarta, 6 may 2010
PDF
Mo p electricity rules, 2005
PDF
callcentre_guidelines
DOCX
From centralised long-term planning to market-based access: Proposed change i...
PDF
Liberalization Policies
PDF
Telecoms spectrum licensing - regulation of radiofrequency spectrum
PDF
King County ERP 1999 Finalrep
PDF
Carlo Cambini and Steffen Hoernig - Trends in Electronic Communications - Eco...
PDF
Annual Report 2009
PDF
Annual Report 2005
PDF
Solar net metering policy
PDF
Claire Bury - A New Telecoms Regulatory Framework
PPT
K a-sivaram-chitale-policy-framework-for-transmission-distribution
DOCX
Open access in india
PPT
BD Telecom Policy (ETE 521 L4)
PPT
Trai Mix Of Ngn And Others
PDF
Legislative developments in the aviation sector in 2011 in poland
Focus group discussion on national railways master plan, jakarta, 6 may 2010
Mo p electricity rules, 2005
callcentre_guidelines
From centralised long-term planning to market-based access: Proposed change i...
Liberalization Policies
Telecoms spectrum licensing - regulation of radiofrequency spectrum
King County ERP 1999 Finalrep
Carlo Cambini and Steffen Hoernig - Trends in Electronic Communications - Eco...
Annual Report 2009
Annual Report 2005
Solar net metering policy
Claire Bury - A New Telecoms Regulatory Framework
K a-sivaram-chitale-policy-framework-for-transmission-distribution
Open access in india
BD Telecom Policy (ETE 521 L4)
Trai Mix Of Ngn And Others
Legislative developments in the aviation sector in 2011 in poland
Ad

Similar to Presentation fgd (20)

PPT
Indonesia Infrsatructure Initiative - World Experience Railway Restructuring
PPT
Strategic future of indonesia's railways
PPTX
Connectivity
PDF
Legislative and jurisprudential developments in the telecommunications sector...
PDF
VM_ Comments Power Market Regulations 2020.pdf
PDF
LEK - Rail industry cost and revenue sharing.pdf
PDF
Converged & Efficient Licensing Framework
PDF
[Block exemption2011.711]
PDF
2007 - Public Private Partnership-Four Year Review
PDF
FuTRO briefing document
DOC
Mms current rules 11 23-09 1
DOC
Progress Of Interoperability
PDF
Legislative developments in rail transport in 2011 in poland
PDF
SLAs the heart of Outsourcing
PDF
Technical qo s and kpi lebanon
PDF
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
DOCX
report on completion of internship period
PDF
COMPETITIVE MARKET
PDF
Introduction to network regulation - Principles of Price Regulation
Indonesia Infrsatructure Initiative - World Experience Railway Restructuring
Strategic future of indonesia's railways
Connectivity
Legislative and jurisprudential developments in the telecommunications sector...
VM_ Comments Power Market Regulations 2020.pdf
LEK - Rail industry cost and revenue sharing.pdf
Converged & Efficient Licensing Framework
[Block exemption2011.711]
2007 - Public Private Partnership-Four Year Review
FuTRO briefing document
Mms current rules 11 23-09 1
Progress Of Interoperability
Legislative developments in rail transport in 2011 in poland
SLAs the heart of Outsourcing
Technical qo s and kpi lebanon
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
report on completion of internship period
COMPETITIVE MARKET
Introduction to network regulation - Principles of Price Regulation
Ad

More from Indonesia Infrastructure Initiative (20)

PPTX
Presentasi Sanitasi INDII
PPTX
Balikpapan Public Diplomacy 25 May 2015
PPT
World experience-in-railway-restructuring
PPT
Indonesian railways revitalisation bambang susantono, vice minister for tra...
PPTX
WS2 Infrastructure Issues
PPTX
Development of multimodal transport in north java corridor
PPTX
Railway function in developing multimodal transportation in java
PDF
The role of ipc in developing multimodal transportation in java
PDF
Government strategy in developing multimodal transportation
PDF
The role of ferry in developing multimodal transportation
PDF
Development of multimodal transportation and inter regional connectivitiy
PPTX
Ws3 safe system approach (bahasa version)
PPTX
Ws3 safe system supporting vru (english version)
PPTX
Ws3 safe system supporting vru (bahasa version)
PPTX
Ws3 infrastructure related to pedestrian safety
PPTX
Ws3 gender and disability presentation
PPT
Workshop #2 safe system approach
Presentasi Sanitasi INDII
Balikpapan Public Diplomacy 25 May 2015
World experience-in-railway-restructuring
Indonesian railways revitalisation bambang susantono, vice minister for tra...
WS2 Infrastructure Issues
Development of multimodal transport in north java corridor
Railway function in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
Government strategy in developing multimodal transportation
The role of ferry in developing multimodal transportation
Development of multimodal transportation and inter regional connectivitiy
Ws3 safe system approach (bahasa version)
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (bahasa version)
Ws3 infrastructure related to pedestrian safety
Ws3 gender and disability presentation
Workshop #2 safe system approach

Presentation fgd

  • 1. Special Railways Phase III Proposed approach to regulatory changes Jakarta 16 May 2011
  • 2. Overview of IndII Special Railway Program Identify need for changes in rail sector regulations to encourage private sector investment (Phase I – early 2010) Identify specific policy and regulatory changes needed to achieve desired results (Phase II – late 2010) Assist GoI to develop and implement regulatory reforms (Phase III – April to June 2011).
  • 3. Key Objectives of Phase III Clarify and improve current Special Railway provisions through a draft Ministerial Regulation (Permen) Expand railway investment opportunities through targeted amendments to existing Government Regulations (PP 56/2009 and PP 72/2009)
  • 4. Timing of Phase III Initial term sheets submitted on 21 April 2011 Inception Report finalized on 26 April 2011 Draft regulatory proposals submitted on 13 May 2011 Final draft regulatory proposals to be submitted by 15 June 2011 Final Technical Report due by late June
  • 5. The Main Challenges Lack of clarity over who can operate a special railway Restrictions on the scope of special railways Uncertainty over interconnection Need for public tender under the PPP process Complexity of licensing system Lack of coordination between special railways and other regulatory licensing schemes
  • 6. The Main Constraints Lack of clarity over who can operate a special railway This affects both the willingness of investors to invest and the willingness of administrators to issue licenses
  • 7. The Main Constraints 2. Restrictions on the scope of special railways The ‘point to point’ rule appears to restrict railways from serving intermediate customers or terminals The ‘one customer’ rule appears to prevent a special railway from serving a group of similar industries
  • 8. The Main Constraints 3. Uncertainty over interconnection There is concern that if a special railway connects to another special railway or to a public railway, the rights of the investor may be compromised. This discourages the creation of efficient railway networks.
  • 9. The Main Constraints 4. The need for tenders under the PPP process Private sector interests are discouraged from promoting railways because they need to be tendered under the PPP provisions.
  • 10. The Main Constraints 5. Complexity of the licensing system The process of getting all the required licences appears overly complex and time consuming
  • 11. The Main Constraints 6. Lack of coordination between special railways and other regulatory licensing schemes Proper linkages between special railway licensing and other relevant licensing schemes (e.g., mining, agriculture) must be put in place to avoid delays or inconsistent results
  • 12. Proposed Solutions A new Permen will clarify the Railway Law and the existing Government Regulations (PP 56 and PP 72) Some minor changes to existing government regulations are also desirable but not strictly necessary to implement the proposed Permen No changes to the Railway Law are needed – all of the proposed regulations are consistent with the Railway Law
  • 13. We propose that the Permen describe more precisely the permitted relationship between the operator and the business it serves It is suggested that the Permen require the main business to have a controlling interest in, or be under common control with, the operator Control can be defined to include ownership of a majority of the voting shares or the ability to appoint or remove a majority of the directors of a company 1. Lack of clarity as to who can operate a Special Railway
  • 14. 2. Restrictions to the scope of the railway We propose three solutions to this issue defining client to permit a consortium of users defining rules for interconnection relaxing the point-to-point rule
  • 15. Definition of Client Define Special Railway client to include a consortium of businesses, essentially allowing them to form and operate a common special railway serving their respective businesses.
  • 16. Defining the interconnect rules Define interconnection rules under Article 374 of PP 56 to enable several special railway operators (each serving their respective client) to share infrastructure and rolling stock without losing the status of special railway
  • 17. Amending the point to point rule Amend article 350 of PP 56/2009 to relax existing ‘point-to-point’ restrictions so that several terminal points can be served (so long as such service remains related to the client’s main business) This would require an amendment to PP 56/2009
  • 18. 3. What happens if railways interconnect For the most part, we can define what happens in a Permen. Interconnection should not affect the status of a special railway (see previous comments on Article 374 of PP 56/2009). However, an amendment to Article 161(3) of PP 72/2009 would also be useful to eliminate any confusion on this point.
  • 19. What happens if railways interconnect We propose that an interconnection agreement should allow the first operator to: access the infrastructure of the other operator for the purpose of providing services in support of the first operator’s client arrange for the other operator (if it is a public operator) to provide services in support of the first operator’s client grant the other operator access to the first operator’s infrastructure for any purpose consistent with the other operator’s business
  • 20. 4. The need for tender under the PPP process Concern about the need to use a PPP process (with its requirement for the rail concession to be tendered) arises because this is seen as the only way of serving multiple customers This restriction can be loosened by allowing special railways to interconnect and by allowing a single special railway to serve a consortium of businesses
  • 21. 5. Complexity of the licensing system The procedures for obtaining licences are overly complex We think they can be simplified and streamlined without reducing their effectiveness or limiting regional autonomy Much of this simplification can be done through a Permen, though minor amendments to PP 56/2009 would also be desirable.
  • 22. Proposals to Simplify the licensing system Planning issues should be addressed and resolved at in-principle approval stage (not later) Reviews by various levels of government should be coordinated and conducted simultaneously to avoid delays and inconsistent decisions Operator should be able to ‘pre-qualify’ itself during construction stage to ensure that operating permit will be issued later, subject only to meeting clear conditions
  • 23. 6. C oordination between special railways and other regulatory licensing schemes Proposed reforms includes option for special railway client to use an affiliate as operator (to facilitate financing) Restrictions on affiliated transactions in certain industries (e.g., mining) must be taken into account If special railway licensee must also obtain other licenses, proper coordination among relevant agencies must be ensured to avoid delays and inconsistent results
  • 24. Conclusions The objective of increased private sector involvement is not being achieved because of a number of constraints We believe these constraints can effectively be addressed through regulatory provisions within the current Railway Law Most can be achieved through a new Permen, though targeted amendments of the existing PP 56/2009 and PP 72/2009 would also be desirable.
  • 25. The way forward Term sheets – set out the broad principles for drafting the Permen and amendments to PP 56/2009 and PP 72/2009 Draft Permen and Amendments to PPs – the consultant team’s initial proposal for reform, based on the term sheets and initial discussions with MoT Working group – established to coordinate government input to the process and achieve broad consensus Close liaison – between our legal team and the MoT