SlideShare a Scribd company logo
LNG Nigeria EPCF
Bonny trains 4, 5 and 6
01 2005
01 2005
Date of last change Reference/Name of Presentation/SN 2
EPCF description
Electrical Network
Electrical Network
Train 4 Train 5 Train 6
C1 B1
A1 D1
D2
33kV;
50Hz
CC EPCF
GS
C3
MS
MR
10kV;
60HZ
C2 B2
D3 A2
D4
33kV;
50Hz
CC EPCF
GS
C3
MS
MR
10kV;
60HZ
C3 B3
D5 A3
33kV;
50Hz
CC
EPCF
GS
C3
MS
MR
10kV;
60HZ
LCI
LCI
LCI
D6
Date of last change Reference/Name of Presentation/SN 3
EPCF description
Trains EPCF complete architecture
Trains EPCF complete architecture
D.C.S.
F8000 redundant FIP network
Electrical equipment
Workstation
PLC
Redundant
C80-75
Normal
Modbus
standby
Modbus
protection
relays
C3 excit.
PEC
LCI PEC
MR
excit.
PEC
TRAIN 6
P1200NT
I/O
CE80-35
Remote
I/O Nest
CE80-35
Remote
I/O Nest
I/O
D.C.S.
F8000 redundant FIP network
Electrical equipment
Workstation
PLC
Redundant
C80-75
Normal
Modbus
standby
Modbus
protection
relays
C3 excit.
PEC
MR
excit
PEC
TRAIN 4
P1200NT
I/O
CE80-35
Remote
I/O Nest
CE80-35
Remote
I/O Nest
I/O
SW
SW SW
LEVEL 2
LEVEL 1
LEVEL 0
GPS
clock
GPS
clock
LCI PEC
dual medium
ethernet optical ring sw : ethernet repeater
D.C.S.
F8000 redundant FIP network
Workstation
PLC
Redundant
C80-75
Normal
Modbus
standby
Modbus
protection
relays
C3 excit.
PEC
MR
excit
PEC
TRAIN 5
P1200NT
I/O
CE80-35
Remote
I/O Nest
CE80-35
Remote
I/O Nest
I/O
SW
SW
GPS
clock
LCI PEC
I/O
CE80-35
Electrical equipment
SW
Date of last change Reference/Name of Presentation/SN 4
EPCF description
Complete FIP network architecture
Complete FIP network architecture
I/O rack I/O rack
I/O rack
I/O rack I/O rack
I/O rack I/O rack
I/O rack
I/O rack I/O rack
I/O rack
I/O rack I/O rack
I/O rack I/O rack
common
I/O
Train 4
Train 5
Train 6
FIP network architecture
common
I/O
common
I/O
common
I/O
common
I/O
common
I/O
standby PLC
normal PLC
standby PLC
normal PLC
standby PLC
normal PLC
I/O rack I/O rack
common
I/O
common
I/O
Date of last change Reference/Name of Presentation/SN 5
EPCF description
Complete Ethernet network architecture
Complete Ethernet network architecture
Supervisor
LCI
SW SW
Supervisor
LCI
SW SW
Supervisor
LCI
SW SW
Train 4 Train 5
Train 6
Ethernet network architecture
optical ring
SW switch
C3 machine
exitation
MR machine
excitation
standby PLC
normal PLC
C3 machine
exitation
MR machine
excitation
standby PLC
normal PLC
C3 machine
exitation
MR machine
excitation
standby PLC
normal PLC
Date of last change Reference/Name of Presentation/SN 6
EPCF description
Normal configuration
Normal configuration
Jacking oil, low voltage CB
train 4 Auxiliaries+MCC
50/60 Hz frequency
converter
train 4 LCI
C3 m otor variable
speed excitation
control
train 4 C3 exciter
MR m otor variable
speed excitation
control
train 4 MR exciter
60 Hz Protection and
Control
train 4 EPCF
orders
start/
stop
status/
faults
status
faults
orders
status/faults
MR Gas Turbine
control
train 4 MR m ark VI
C3 Gas Turbine
control
train 4 C3 m ark VI
status/faults 60 Hz
Circuit Breaker
and
synchronisers
train 4 10 kV switchgear
orders
status/
faults
status/
faults
status/
faults
orders
orders orders
orders
MS MS
External cooler
train 4 LCI
50/60 Hz Transform ers
train 4 LCI
50 Hz
Circuit Breaker
33 kV switchgear
status/faults
orders
DCS system
m aster
Custom er
status/faults
orders
pressures
levels
tem peratures
serial link RS485 m odbus RTU
synchronisation signals
synchronisation signals
ENMC system
Custom er
status/faults
Date of last change Reference/Name of Presentation/SN 7
EPCF description
Degraded configuration
Degraded configuration
Jacking oil, low voltage CB
train 4 Auxiliaries+MCC
50/60 Hz frequency
converter
train 5 LCI
C3 m otor variable
speed excitation
control
train 4 C3 exciter
MR m otor variable
speed excitation
control
train 4 MR exciter
60 Hz Protection and
Control
train 5 EPCF
orders
start/
stop
status/
faults
status
faults
orders
status/faults
MR Gas Turbine
control
train 4 MR m ark VI
C3 Gas Turbine
control
train 4 C3 m ark VI
status/faults 60 Hz
Circuit Breaker
and
synchronisers
train 4 10 kV switchgear
orders
status/
faults
status/
faults
status/
faults
orders
orders orders
orders
MS MS
External cooler
train 5 LCI
50/60 Hz Transform ers
train 5 LCI
50 Hz
Circuit Breaker
33 kV switchgear
status/faults
orders
DCS system
m aster
Custom er
status/faults
orders
pressures
levels
tem peratures
serial link RS485 m odbus RTU
synchronisation signals
synchronisation signals
ENMC system
Custom er
status/faults
Date of last change Reference/Name of Presentation/SN 8
EPCF description
Normal configuration
Normal configuration
CB A1
CB D1
train 4 C3 train 4 MR
train 4 LCI
CB C1
CB B1
CB D3
train 5 C3 train 5 MR
CB D2
Normal positions
CB A2
train 5 LCI
CB C2
CB B2
CB A3
train 6 LCI
CB C3
CB B3
CB D4
train 6 C3 train 6 MR
CB D5
CB D6
Date of last change Reference/Name of Presentation/SN 9
EPCF description
Train 4 fed by train 5
Train 4 fed by train 5
CB A1
CB D1
train 4 C3 train 4 MR
train 4 LCI
CB C1
CB B1
CB D3
train 5 C3 train 5 MR
CB D2
Train 4 LCI or EPCF breakdown
CB A2
train 5 LCI
CB C2
CB B2
CB A3
train 6 LCI
CB C3
CB B3
CB D4
train 6 C3 train 6 MR
CB D5
CB D6
Date of last change Reference/Name of Presentation/SN 10
EPCF description
Train 5 fed by train 4
Train 5 fed by train 4
CB A1
CB D1
train 4 C3 train 4 MR
train 4 LCI
CB C1
CB B1
CB D3
train 5 C3 train 5 MR
CB D2
Train 5 LCI or EPCF breakdown
CB A2
train 5 LCI
CB C2
CB B2
CB A3
train 6 LCI
CB C3
CB B3
CB D4
train 6 C3 train 6 MR
CB D5
CB D6
Date of last change Reference/Name of Presentation/SN 11
EPCF description
Train 5 fed by train 6
Train 5 fed by train 6
CB A1
CB D1
train 4 C3 train 4 MR
train 4 LCI
CB C1
CB B1
CB D3
train 5 C3 train 5 MR
CB D2
Train 5 LCI or EPCF breakdown
CB A2
train 5 LCI
CB C2
CB B2
CB A3
train 6 LCI
CB C3
CB B3
CB D4
train 6 C3 train 6 MR
CB D5
CB D6
Date of last change Reference/Name of Presentation/SN 12
EPCF description
Train 6 fed by train 5
Train 6 fed by train 5
CB A1
CB D1
train 4 C3 train 4 MR
train 4 LCI
CB C1
CB B1
CB D3
train 5 C3 train 5 MR
CB D2
Train 6 LCI or EPCF breakdown
CB A2
train 5 LCI
CB C2
CB B2
CB A3
train 6 LCI
CB C3
CB B3
CB D4
train 6 C3 train 6 MR
CB D5
CB D6
Date of last change Reference/Name of Presentation/SN 13
EPCF description
Menu view
Menu view
Date of last change Reference/Name of Presentation/SN 14
EPCF description
General diagram
General diagram
Date of last change Reference/Name of Presentation/SN 15
EPCF description
Train detail diagram
Train detail diagram
Date of last change Reference/Name of Presentation/SN 16
EPCF description
LCI fault detail view
LCI fault detail view
Date of last change Reference/Name of Presentation/SN 17
EPCF description
Symbols and inset
Symbols and inset
Tag of Equipment
Inset indicator Red rectangle means at least one alarm
Date of last change Reference/Name of Presentation/SN 18
EPCF description
Alarm view
Alarm view
Date of last change Reference/Name of Presentation/SN 19
EPCF description
Events view
Events view
Date of last change Reference/Name of Presentation/SN 20
EPCF description
Trends view
Trends view
Date of last change Reference/Name of Presentation/SN 21
EPCF description
System view
System view
www.alstom.com

More Related Content

PDF
INPUT OUTPUT LIST.pdf
PDF
1902 01_SouthSide Works_Sheet - E400 - ELECTRICAL RISER DIAGRAM
PPT
INTERFACING.ppt
PDF
MWAPE KAMPILIMBA FINAL REPORT
PPTX
ppt on industrial training of final year studen from ptcul 132kv substation ...
PPTX
Electic locomotivesder PPT 18.07.24.pptx
PDF
Knowing the Mitsubishi Obsolete Protection Relays
PPTX
GHY & KYQ Coaching depot Performance for Conference-1.pptx
INPUT OUTPUT LIST.pdf
1902 01_SouthSide Works_Sheet - E400 - ELECTRICAL RISER DIAGRAM
INTERFACING.ppt
MWAPE KAMPILIMBA FINAL REPORT
ppt on industrial training of final year studen from ptcul 132kv substation ...
Electic locomotivesder PPT 18.07.24.pptx
Knowing the Mitsubishi Obsolete Protection Relays
GHY & KYQ Coaching depot Performance for Conference-1.pptx

Similar to presentation on LCI Load Commutative Inverter nigeria.ppt (20)

PPT
variable frequency drive fundamental and circuit
PDF
120A beb PE occupation plans
PPT
Catalog busbar ls 06. busduct presentation e series rev 2
PPT
Catalog busbar ls 06. busduct presentation e series rev 2
PDF
Busbar configuarations
PDF
Appron feeder common ckt-diagram
PPTX
electropneumlocomotive_info_fo_allr.pptx
PPT
DEMU - Power distribution final of indian railways
PDF
A Novel Three-Phase Three-Leg AC/AC Converter Using Nine IGBTS
PPTX
Indian Railway locomotive ppt
PDF
Electrical abbreviations
PDF
PPT
132kv Substation
PPTX
Multi-KilowattFlybackConverters.pptx
PDF
Iai pcon controller_specsheet
PDF
Crane drawing swl 20/5 ton used for hoisting application in rolling mills and...
PPTX
Electrical loco tripshed,sawai madhopur
PDF
60015688 ashish-loco-summer (1)
PDF
773F EED plano cat serie baja muy bueno
PPT
electrical.ppt
variable frequency drive fundamental and circuit
120A beb PE occupation plans
Catalog busbar ls 06. busduct presentation e series rev 2
Catalog busbar ls 06. busduct presentation e series rev 2
Busbar configuarations
Appron feeder common ckt-diagram
electropneumlocomotive_info_fo_allr.pptx
DEMU - Power distribution final of indian railways
A Novel Three-Phase Three-Leg AC/AC Converter Using Nine IGBTS
Indian Railway locomotive ppt
Electrical abbreviations
132kv Substation
Multi-KilowattFlybackConverters.pptx
Iai pcon controller_specsheet
Crane drawing swl 20/5 ton used for hoisting application in rolling mills and...
Electrical loco tripshed,sawai madhopur
60015688 ashish-loco-summer (1)
773F EED plano cat serie baja muy bueno
electrical.ppt
Ad

More from rotimiadedayo1 (7)

PDF
678177833-KPIs-and-Performance-Helmut-Salsland-BRCE2016.pdf
PDF
Emergency-of-Consulting-Engineering-in-Nigeria.pdf
PDF
Implementing an Effective Risk Management Appetite.pdf
PPT
Enterprise Risk Management : Hollow Tree Giant Redwood.ppt
PPT
Risk-Analysis for Good Corporate Governance.ppt
PPTX
132kV GIS Tie-in Scope which is a HV Switchgear Modification project.pptx
PPTX
fy11_sh-22311-11_Mod5-TrainingAdultLearners (1).pptx
678177833-KPIs-and-Performance-Helmut-Salsland-BRCE2016.pdf
Emergency-of-Consulting-Engineering-in-Nigeria.pdf
Implementing an Effective Risk Management Appetite.pdf
Enterprise Risk Management : Hollow Tree Giant Redwood.ppt
Risk-Analysis for Good Corporate Governance.ppt
132kV GIS Tie-in Scope which is a HV Switchgear Modification project.pptx
fy11_sh-22311-11_Mod5-TrainingAdultLearners (1).pptx
Ad

Recently uploaded (20)

PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
communication and presentation skills 01
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PPTX
UNIT - 3 Total quality Management .pptx
PDF
737-MAX_SRG.pdf student reference guides
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
communication and presentation skills 01
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
COURSE DESCRIPTOR OF SURVEYING R24 SYLLABUS
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Exploratory_Data_Analysis_Fundamentals.pdf
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Analyzing Impact of Pakistan Economic Corridor on Import and Export in Pakist...
Fundamentals of safety and accident prevention -final (1).pptx
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
Fundamentals of Mechanical Engineering.pptx
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
UNIT - 3 Total quality Management .pptx
737-MAX_SRG.pdf student reference guides
R24 SURVEYING LAB MANUAL for civil enggi
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx

presentation on LCI Load Commutative Inverter nigeria.ppt

  • 1. LNG Nigeria EPCF Bonny trains 4, 5 and 6 01 2005 01 2005
  • 2. Date of last change Reference/Name of Presentation/SN 2 EPCF description Electrical Network Electrical Network Train 4 Train 5 Train 6 C1 B1 A1 D1 D2 33kV; 50Hz CC EPCF GS C3 MS MR 10kV; 60HZ C2 B2 D3 A2 D4 33kV; 50Hz CC EPCF GS C3 MS MR 10kV; 60HZ C3 B3 D5 A3 33kV; 50Hz CC EPCF GS C3 MS MR 10kV; 60HZ LCI LCI LCI D6
  • 3. Date of last change Reference/Name of Presentation/SN 3 EPCF description Trains EPCF complete architecture Trains EPCF complete architecture D.C.S. F8000 redundant FIP network Electrical equipment Workstation PLC Redundant C80-75 Normal Modbus standby Modbus protection relays C3 excit. PEC LCI PEC MR excit. PEC TRAIN 6 P1200NT I/O CE80-35 Remote I/O Nest CE80-35 Remote I/O Nest I/O D.C.S. F8000 redundant FIP network Electrical equipment Workstation PLC Redundant C80-75 Normal Modbus standby Modbus protection relays C3 excit. PEC MR excit PEC TRAIN 4 P1200NT I/O CE80-35 Remote I/O Nest CE80-35 Remote I/O Nest I/O SW SW SW LEVEL 2 LEVEL 1 LEVEL 0 GPS clock GPS clock LCI PEC dual medium ethernet optical ring sw : ethernet repeater D.C.S. F8000 redundant FIP network Workstation PLC Redundant C80-75 Normal Modbus standby Modbus protection relays C3 excit. PEC MR excit PEC TRAIN 5 P1200NT I/O CE80-35 Remote I/O Nest CE80-35 Remote I/O Nest I/O SW SW GPS clock LCI PEC I/O CE80-35 Electrical equipment SW
  • 4. Date of last change Reference/Name of Presentation/SN 4 EPCF description Complete FIP network architecture Complete FIP network architecture I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack I/O rack common I/O Train 4 Train 5 Train 6 FIP network architecture common I/O common I/O common I/O common I/O common I/O standby PLC normal PLC standby PLC normal PLC standby PLC normal PLC I/O rack I/O rack common I/O common I/O
  • 5. Date of last change Reference/Name of Presentation/SN 5 EPCF description Complete Ethernet network architecture Complete Ethernet network architecture Supervisor LCI SW SW Supervisor LCI SW SW Supervisor LCI SW SW Train 4 Train 5 Train 6 Ethernet network architecture optical ring SW switch C3 machine exitation MR machine excitation standby PLC normal PLC C3 machine exitation MR machine excitation standby PLC normal PLC C3 machine exitation MR machine excitation standby PLC normal PLC
  • 6. Date of last change Reference/Name of Presentation/SN 6 EPCF description Normal configuration Normal configuration Jacking oil, low voltage CB train 4 Auxiliaries+MCC 50/60 Hz frequency converter train 4 LCI C3 m otor variable speed excitation control train 4 C3 exciter MR m otor variable speed excitation control train 4 MR exciter 60 Hz Protection and Control train 4 EPCF orders start/ stop status/ faults status faults orders status/faults MR Gas Turbine control train 4 MR m ark VI C3 Gas Turbine control train 4 C3 m ark VI status/faults 60 Hz Circuit Breaker and synchronisers train 4 10 kV switchgear orders status/ faults status/ faults status/ faults orders orders orders orders MS MS External cooler train 4 LCI 50/60 Hz Transform ers train 4 LCI 50 Hz Circuit Breaker 33 kV switchgear status/faults orders DCS system m aster Custom er status/faults orders pressures levels tem peratures serial link RS485 m odbus RTU synchronisation signals synchronisation signals ENMC system Custom er status/faults
  • 7. Date of last change Reference/Name of Presentation/SN 7 EPCF description Degraded configuration Degraded configuration Jacking oil, low voltage CB train 4 Auxiliaries+MCC 50/60 Hz frequency converter train 5 LCI C3 m otor variable speed excitation control train 4 C3 exciter MR m otor variable speed excitation control train 4 MR exciter 60 Hz Protection and Control train 5 EPCF orders start/ stop status/ faults status faults orders status/faults MR Gas Turbine control train 4 MR m ark VI C3 Gas Turbine control train 4 C3 m ark VI status/faults 60 Hz Circuit Breaker and synchronisers train 4 10 kV switchgear orders status/ faults status/ faults status/ faults orders orders orders orders MS MS External cooler train 5 LCI 50/60 Hz Transform ers train 5 LCI 50 Hz Circuit Breaker 33 kV switchgear status/faults orders DCS system m aster Custom er status/faults orders pressures levels tem peratures serial link RS485 m odbus RTU synchronisation signals synchronisation signals ENMC system Custom er status/faults
  • 8. Date of last change Reference/Name of Presentation/SN 8 EPCF description Normal configuration Normal configuration CB A1 CB D1 train 4 C3 train 4 MR train 4 LCI CB C1 CB B1 CB D3 train 5 C3 train 5 MR CB D2 Normal positions CB A2 train 5 LCI CB C2 CB B2 CB A3 train 6 LCI CB C3 CB B3 CB D4 train 6 C3 train 6 MR CB D5 CB D6
  • 9. Date of last change Reference/Name of Presentation/SN 9 EPCF description Train 4 fed by train 5 Train 4 fed by train 5 CB A1 CB D1 train 4 C3 train 4 MR train 4 LCI CB C1 CB B1 CB D3 train 5 C3 train 5 MR CB D2 Train 4 LCI or EPCF breakdown CB A2 train 5 LCI CB C2 CB B2 CB A3 train 6 LCI CB C3 CB B3 CB D4 train 6 C3 train 6 MR CB D5 CB D6
  • 10. Date of last change Reference/Name of Presentation/SN 10 EPCF description Train 5 fed by train 4 Train 5 fed by train 4 CB A1 CB D1 train 4 C3 train 4 MR train 4 LCI CB C1 CB B1 CB D3 train 5 C3 train 5 MR CB D2 Train 5 LCI or EPCF breakdown CB A2 train 5 LCI CB C2 CB B2 CB A3 train 6 LCI CB C3 CB B3 CB D4 train 6 C3 train 6 MR CB D5 CB D6
  • 11. Date of last change Reference/Name of Presentation/SN 11 EPCF description Train 5 fed by train 6 Train 5 fed by train 6 CB A1 CB D1 train 4 C3 train 4 MR train 4 LCI CB C1 CB B1 CB D3 train 5 C3 train 5 MR CB D2 Train 5 LCI or EPCF breakdown CB A2 train 5 LCI CB C2 CB B2 CB A3 train 6 LCI CB C3 CB B3 CB D4 train 6 C3 train 6 MR CB D5 CB D6
  • 12. Date of last change Reference/Name of Presentation/SN 12 EPCF description Train 6 fed by train 5 Train 6 fed by train 5 CB A1 CB D1 train 4 C3 train 4 MR train 4 LCI CB C1 CB B1 CB D3 train 5 C3 train 5 MR CB D2 Train 6 LCI or EPCF breakdown CB A2 train 5 LCI CB C2 CB B2 CB A3 train 6 LCI CB C3 CB B3 CB D4 train 6 C3 train 6 MR CB D5 CB D6
  • 13. Date of last change Reference/Name of Presentation/SN 13 EPCF description Menu view Menu view
  • 14. Date of last change Reference/Name of Presentation/SN 14 EPCF description General diagram General diagram
  • 15. Date of last change Reference/Name of Presentation/SN 15 EPCF description Train detail diagram Train detail diagram
  • 16. Date of last change Reference/Name of Presentation/SN 16 EPCF description LCI fault detail view LCI fault detail view
  • 17. Date of last change Reference/Name of Presentation/SN 17 EPCF description Symbols and inset Symbols and inset Tag of Equipment Inset indicator Red rectangle means at least one alarm
  • 18. Date of last change Reference/Name of Presentation/SN 18 EPCF description Alarm view Alarm view
  • 19. Date of last change Reference/Name of Presentation/SN 19 EPCF description Events view Events view
  • 20. Date of last change Reference/Name of Presentation/SN 20 EPCF description Trends view Trends view
  • 21. Date of last change Reference/Name of Presentation/SN 21 EPCF description System view System view