Primary Sedimentation
Dr. Akepati S. Reddy
School of Energy and Environment
Thapar University, Patiala
PUNJAB, INDIA
Flocculent Particle Settling
• Particles do not settle as discrete particles – instead during
sedimentation they coalesce and flocculate
• Extent of coalescence or flocculation depend on
– Overflow rate
– Depth of settling basin
– Velocity gradients in the system
– Concentration of particles
– Range of particle sizes
• Settling characteristics of a suspension of flocculent particles
can be obtained by a settling column test
• Settling column
– Height: equal to the depth of the proposed settling tank
– Diameter can be anything – influences of the wall should be
taken care off – sample required should be small enough
– Provided with sampling ports
• Settling column test
– To begin with ensure uniform distribution of particle size from
top to bottom of the column
– Duration of test should be equal to the settling time in the
proposed tank
– Draw samples from the ports at various time intervals, analyze
for TSS and compute % removal
– Plot % removal against time and depth and construct curves of
equal % removal
– Overflow rates for various settling are determined by noting
where the curve intersect the x-axis
Flocculent Particle Settling





 





 
 


2
(%) 1
1
nn
n
h
n RR
H
h
R
Settling Column Settling Profile Graph
Primary sedimentation
Primary Sedimentation Tank
• Purpose is removal of readily settleable solids and floating
material from wastewater
• Usually give 50-70% suspended solids removal efficiency and
25-40% BOD removal (for municipal sewage)
• Rectangular or circular sedimentation tanks are used
– Two or more cylindrical or rectangular sedimentation tanks may
be used for allowing maintenance and repair
– Multiple rectangular tanks require less land area than multiple
circular tanks and common walls reduce construction cost
• Sedimentation tanks should include
– Inlet section and Outlet section
– Facilities and provisions for the settled sludge scrapping,
collection and removal
– Facilities and provisions for the floating material entrapment,
skimming, collection and removal
• Sedimentation tank can be considered to include Settling
zone and Sludge zone
Flow pattern is radial with central feed arrangement
• Has a center well of 15-20% of the tank diameter and 1.0 to 2.5 m
depth is used
• Center well has a tangential energy dissipating inlet
• wastewater is discharged into the well within the upper 0.5-0.7 m
at 0.3 to 0.45 m/sec flow velocity
Solids removal mechanisms
• Smaller tanks have hopper bottom with >45 inclination with the
horizontal
• 3.6-9.0 m diameter tanks have solids removal equipment supported
on beams spanning the tank
• Larger diameter tanks have a central pier supporting the
mechanism and is reached by a walkway or bridge
• Bottom of the tank is sloped at 1 in 12 to 64 or lesser
• Solids are scrapped to the center and removed
Clarified liquid is skimmed off over weirs into a collection trough
Circular Primary Sedimentation Tank
Primary sedimentation
Clarified sewage
Collection trough
Scum retaining baffle
Distribution baffle
of central well
Scrapper arm
Skimmer bladeCentral well
Central pier
Influent pipe Sludge draw-off pipe
Central rotating
equipment
Sludge trough
Tangential openings in the pier
for the distribution of the influent
Slope 1 in 12
Side wall
of clarifier
0.5m
0.3m
0.3m
0.3m
0.6m Central pier Sludge trough
0.5 m
1.5 m
0.5 m
Sludge draw-off pipe
Influent pipe
Primary clarifier
Section to show side wall with
clarified sewage collection trough Bottom sludge trough and outlet
3.0 m
Inlet
• Full width inlet channels with inlet weirs – can introduce vertical
velocity component spreading into the sludge hoppers (provided at
the inlet end)
• Inlets with submerged ports/orifices (velocities in the ports/orifices
are in the range of 3-9 m/min.)
• Inlet channels with wide gates and slotted baffles
• Inlet baffles can be used to reduce high initial velocities and
distribute flow width wise – usually extend from 150 mm below and
300 mm above the water surface
Outlet
• Clarified effluent is collected into a collection trough through an
overflow weir
• Floating material or settled suspended solids should not be washed
out with the clarified effluent
• Floating material retaining or entrapping baffle is provided
• Weir length is designed to avoid washout out of sludge
Rectangular
Primary Sedimentation Tanks
Facilities and provisions for the settled sludge scrapping,
collection and removal
• Settled sludge is collected at the inlet end
• Chain and flight solids collectors
– Have a pair of endless conveyor chains
– Scraper flights of wood or fiberglass, running full width of the
tank and attached to the chains at 3 m interval
– The settled solids are scrapped
• to solids hoppers In case of small tanks – multiple hoppers are
used in larger tanks
• to a transverse trough in case of large tanks - troughs in turn have
cross collectors
Rectangular
Primary Sedimentation Tank
Traveling bridge type collectors
– Travel up and down the tank on rubber wheels or on rails
supported on the sidewalls
– Scrapper blades are suspended from the bridge (returning
scraper blades lifted free of the solids blanket)
Facilities and provisions for floating material entrapment,
skimming, collection and removal
• Floating scum is collected at the effluent end
• Floating scum is skimmed and carried to the effluent end and
entrapped for avoiding overflow into the clarified effluent trough
– Flights returning at the liquid surface can be used
– Water showers can be used to push forward the floating scum
– Baffle is provided in front of the overflow weir for the scum
entrapment until removed
Rectangular
Primary Sedimentation Tank
• In small tanks scum draw-down facility consisting of a
horizontal, slotted pipe that can be rotated by a lever or screw
can be used
– Limitation - creates large volume of scum liquor
• Transverse rotating helical wiper attached to a shaft can also
be used for scum removal
– Scum is removed from the water surface and moved over an
inclined apron for discharge to a cross-collecting scum trough
Other provisions and facilities
• Tanks may sloping bottom towards the influent end
• Influent end has sludge hoppers or sludge trench
• Scum pit is provided for storing the scum liquid removed
• Sludge pump, piping and tank may be there to remove the collected
sludge from the sludge hopper or trench
Rectangular
Primary Sedimentation Tank
Primary sedimentation
Design of Primary Clarifier
• Overflow rate and hydraulic retention time obtained from the
settling test and settling profile diagram are used to find
surface area and depth of the clarifier
• Safety factors of 1.25 is usually used to take into account
– Inlet and outlet disturbances
– Disturbances created by the rotating mechanism to scrap the
settled sludge and to collect the floating scum
– Wind blow effects
– Temperature variations
– Flow short-circuiting
• Design also takes into account the following:
– Horizontal flow velocity (below the scour velocity)
– Weir overflow rate (below a limit to avoid density currents)
– Weir overflow balancing to avoid short-circuiting problems
– Flooding of collection trough
Detention time 1.5 to 2.5 hours (2.0 hr.)
Overflow rate
Average flow 30-50 m3/m2.day (40) – 24-32 (26)
Peak flow 80-120 m3/m2.day (100) – 48-70 (60)
Weir loading 125-500 m3/m.day (250)
Rectangular tanks
Depth 3-4.9 (4.3)
Length 15-90 (24-40)
Width 3-24 (4.9-9.8)
Flight speed 0.6-1.2 m/min (0.9)
Circular tank
Diameter 3-60 (12-45)
Bottom slope 1 in 16 to 1 in 6 (1 in 12)
Flight speed 0.02-0.05 rpm (0.03)
Primary Sedimentation Tank
Short circuiting and hydraulic stability
• Tracer studies can be used for determining short-circuiting
problems
• Method of influent flow distribution can also affect short circuiting
Temperature difference of 1C between incoming wastewater
and wastewater of the tank can cause density current
Wind blowing across the top of an open sedimentation tank can
cause circulation cell to form – this reduces effective
volumetric capacity of the tank
Surface loading rates (overflow rates)
• There can be regulations prescribing limits to surface loading rates
• Overflow rates must be set low enough to ensure satisfactory
performance at peak rates of flow
Primary Sedimentation Tank
Detention time
• Solids reaching the settling tank are susceptible to flocculation
• Flocculation is aided by eddying motion of fluid within the tank
• Level of flocculation depends on the time elapsed (detention time)
• In cold climates because of increase in water viscosity detention
time required also increases (1.38 time more HRT for 10C water
that when temperature is 20C)
Weir loading rates
• Have little effect on efficiency of primary settlign tanks
Primary sludge scum characteristics and quantities
• Factors influencing are
– Characteristics of untreated water (strength and freshness)
– Period of sedimentation
– Conditions of the deposited solids
– Period between solids removal operations
Primary Sedimentation Tank
Primary Sludge
• Primary clarifier is designed for a specified % removal of TSS
• From knowing the TSS and flow rate of the influent sewage
primary sludge generated can be quantified
• TSS of the sewage is comprised of inorganic TSS, VSS and
Biodegradable VSS
– Biodegradable VSS contributes BOD and this is 50-60% of the
total BOD for municipal sewage
• Primary clarifier through removing the Biodegradable VSS
contributes to BOD removal
– BOD removal in the primary clarifier is typically 35-45%
• If BOD removal in the primary clarifier is known, one can find
out the biodegradable fraction of the primary sludge
– BOD removal can be expressed as BODu removal and BODu
removal as TSS equivalent removal
– The fraction of biodegradable VSS in the TSS is assumed to
remain the same even in the clarified effluent
• If consistency of the primary sludge is known even volume of
the primary sludge can be calculated

More Related Content

PDF
Water treatment
PDF
Plain sedimentation tanks ,Types & Design considerations
PDF
L 18 trickling filter
PDF
L 10 sedimentation
PPT
Treatment of water
PPTX
Plain sedimentation
PDF
L 13 grit chamber
PDF
3. grit chamber
Water treatment
Plain sedimentation tanks ,Types & Design considerations
L 18 trickling filter
L 10 sedimentation
Treatment of water
Plain sedimentation
L 13 grit chamber
3. grit chamber

What's hot (20)

PPTX
Sedimentation tanks in water treatment
PDF
L 11 screen chamber
PDF
L 24 filtration
PPTX
Grit chambers
PDF
PDF
L 4 wastewater flow rates
PPTX
Waste water treatment
PPTX
Unit operations; processes in waste water treatment
PPTX
Physical Unit Operation- Screening, Grit Removal, Equalization
PDF
L 17 coagulation and flocculation
PPTX
Sludge thickening and stabilization processes
PDF
L 7 waste volume reduction
PPTX
Service Reservoirs 111001110634-phpapp02
PPTX
Collection and estimation of sewage
PPTX
Types of sedimentation tank
PDF
L 8 equalization and proportioning
PPTX
2. screen chamber
PPT
Sludge digestion process
PPT
Estimation of storm sewage
PPTX
Design of sewers
Sedimentation tanks in water treatment
L 11 screen chamber
L 24 filtration
Grit chambers
L 4 wastewater flow rates
Waste water treatment
Unit operations; processes in waste water treatment
Physical Unit Operation- Screening, Grit Removal, Equalization
L 17 coagulation and flocculation
Sludge thickening and stabilization processes
L 7 waste volume reduction
Service Reservoirs 111001110634-phpapp02
Collection and estimation of sewage
Types of sedimentation tank
L 8 equalization and proportioning
2. screen chamber
Sludge digestion process
Estimation of storm sewage
Design of sewers
Ad

Viewers also liked (20)

PPTX
Sewage Treatment: Primary Treatment
PDF
water treatment slides
PPT
Primary and secondary wastewater treatment..
PPT
Industrial wastewater treatment
PPTX
Waste water treatment processes
PPTX
07 coagulation-flocculation-settling
PPT
Wastewater treatment
PDF
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
PDF
B Tech R-13 Regulation Syllabus of JNTUH 2013
PPT
Sewage Treatment and Recycle Presentation
PDF
Ag wastewater treatment by ag.pdf 2
PPTX
Atmospheric Water
PPTX
Radiation and atmospheric temperature
PPTX
Aerobic attached growth systems
PPTX
Solid waste biomethanation plants
PPTX
Anaerobic ponds
PPT
15 secondary sedimentation
PPTX
Regulatory Requirements of Solid Waste Management, Indian Context
PPT
Biological n and p removal
PPTX
biomass fuels and cook stoves
Sewage Treatment: Primary Treatment
water treatment slides
Primary and secondary wastewater treatment..
Industrial wastewater treatment
Waste water treatment processes
07 coagulation-flocculation-settling
Wastewater treatment
Simulation in Action: Fatigue Analysis on 1243 Scraper Tail
B Tech R-13 Regulation Syllabus of JNTUH 2013
Sewage Treatment and Recycle Presentation
Ag wastewater treatment by ag.pdf 2
Atmospheric Water
Radiation and atmospheric temperature
Aerobic attached growth systems
Solid waste biomethanation plants
Anaerobic ponds
15 secondary sedimentation
Regulatory Requirements of Solid Waste Management, Indian Context
Biological n and p removal
biomass fuels and cook stoves
Ad

Similar to Primary sedimentation (20)

PPTX
Plain sedimentation tanks sewage
PPTX
A Lecture notes on Sedimentation a perspective
PDF
Plain sedimentation
PPTX
SEDIMENTATION
PPTX
Etp(EFFLUENT TREATMNT Plant)
PPTX
Sedimentation ( Settling ) Defination, Types, Design
PDF
Sedimentation
PPTX
sedimentation
PPTX
L7- Sedimentation.pptx
PPTX
Water purification process
PPTX
Introduction of Effluent Treatment Plant
PPTX
Coagulation and flocculation
PPT
UNIT -II Treatment of water- aeration and sedimentation.ppt
PPTX
Chapter_3.pptx on waste water treatment course
PPTX
etpfinal-150227030930-co-gate02 (1).pptx
PPTX
C-3_Sedimentation process of water treatment
PPTX
Water Resources Engineering (CVE 728)--Slide 4.pptx
PPT
Industrialwastewatertreatment
PDF
Industrial Microbiology
PPTX
Design of effluent treatment plant
Plain sedimentation tanks sewage
A Lecture notes on Sedimentation a perspective
Plain sedimentation
SEDIMENTATION
Etp(EFFLUENT TREATMNT Plant)
Sedimentation ( Settling ) Defination, Types, Design
Sedimentation
sedimentation
L7- Sedimentation.pptx
Water purification process
Introduction of Effluent Treatment Plant
Coagulation and flocculation
UNIT -II Treatment of water- aeration and sedimentation.ppt
Chapter_3.pptx on waste water treatment course
etpfinal-150227030930-co-gate02 (1).pptx
C-3_Sedimentation process of water treatment
Water Resources Engineering (CVE 728)--Slide 4.pptx
Industrialwastewatertreatment
Industrial Microbiology
Design of effluent treatment plant

More from Akepati S. Reddy (20)

PPT
PH,acidity and alkanity
PPT
Td sand tss
PPT
Asr wastewater characteristics
PPTX
Asr flow measurement
PPT
Asr= nutrients
PPT
Asr mp ntest
PPTX
02b priliminary treatment
PPTX
02d secondary treatment
PPTX
Wastewater characteristics
PDF
Chapter2activestudge process
PPT
acticated sluge process
PPTX
Atmospheric Pressure and Winds
PPTX
Atmosphere: Composition and Strucutre
PPT
Biological sludge digestion
PPTX
Geothermal energy technologies
PPTX
UASB reactors
PPT
Activated sludge process
PPTX
Scrubbing Systems
PPTX
biomass gasification
PPTX
Sewer Appurtanances
PH,acidity and alkanity
Td sand tss
Asr wastewater characteristics
Asr flow measurement
Asr= nutrients
Asr mp ntest
02b priliminary treatment
02d secondary treatment
Wastewater characteristics
Chapter2activestudge process
acticated sluge process
Atmospheric Pressure and Winds
Atmosphere: Composition and Strucutre
Biological sludge digestion
Geothermal energy technologies
UASB reactors
Activated sludge process
Scrubbing Systems
biomass gasification
Sewer Appurtanances

Recently uploaded (20)

PPTX
Delivery census may 2025.pptxMNNN HJTDV U
PDF
Blue Economy Development Framework for Indonesias Economic Transformation.pdf
PPTX
Green and Cream Aesthetic Group Project Presentation.pptx
PPTX
Plant_Cell_Presentation.pptx.com learning purpose
PDF
Insitu conservation seminar , national park ,enthobotanical significance
DOCX
Epoxy Coated Steel Bolted Tanks for Crude Oil Large-Scale Raw Oil Containment...
PPTX
Topic Globalisation and Lifelines of National Economy (1).pptx
PPT
PPTPresentation3 jhsvdasvdjhavsdhsvjcksjbc.jasb..ppt
PDF
Lecture 2 investigation of renal diseses.pdf
PDF
School Leaders Revised Training Module, SCB.pdf
PPTX
ser tico.pptxXYDTRRRRRRRRRRRRRRRRRRRRRRRRRRRRRRY
PDF
The Role of Non-Legal Advocates in Fighting Social Injustice.pdf
DOCX
Epoxy Coated Steel Bolted Tanks for Beverage Wastewater Storage Manages Liqui...
PPTX
Conformity-and-Deviance module 7 ucsp grade 12
PDF
Ornithology-Basic-Concepts.pdf..........
PPTX
UN Environmental Inventory User Training 2021.pptx
PPTX
Disposal Of Wastes.pptx according to community medicine
PDF
Effective factors on adoption of intercropping and it’s role on development o...
PDF
Earthquake, learn from the past and do it now.pdf
PPTX
structure and components of Environment.pptx
Delivery census may 2025.pptxMNNN HJTDV U
Blue Economy Development Framework for Indonesias Economic Transformation.pdf
Green and Cream Aesthetic Group Project Presentation.pptx
Plant_Cell_Presentation.pptx.com learning purpose
Insitu conservation seminar , national park ,enthobotanical significance
Epoxy Coated Steel Bolted Tanks for Crude Oil Large-Scale Raw Oil Containment...
Topic Globalisation and Lifelines of National Economy (1).pptx
PPTPresentation3 jhsvdasvdjhavsdhsvjcksjbc.jasb..ppt
Lecture 2 investigation of renal diseses.pdf
School Leaders Revised Training Module, SCB.pdf
ser tico.pptxXYDTRRRRRRRRRRRRRRRRRRRRRRRRRRRRRRY
The Role of Non-Legal Advocates in Fighting Social Injustice.pdf
Epoxy Coated Steel Bolted Tanks for Beverage Wastewater Storage Manages Liqui...
Conformity-and-Deviance module 7 ucsp grade 12
Ornithology-Basic-Concepts.pdf..........
UN Environmental Inventory User Training 2021.pptx
Disposal Of Wastes.pptx according to community medicine
Effective factors on adoption of intercropping and it’s role on development o...
Earthquake, learn from the past and do it now.pdf
structure and components of Environment.pptx

Primary sedimentation

  • 1. Primary Sedimentation Dr. Akepati S. Reddy School of Energy and Environment Thapar University, Patiala PUNJAB, INDIA
  • 2. Flocculent Particle Settling • Particles do not settle as discrete particles – instead during sedimentation they coalesce and flocculate • Extent of coalescence or flocculation depend on – Overflow rate – Depth of settling basin – Velocity gradients in the system – Concentration of particles – Range of particle sizes • Settling characteristics of a suspension of flocculent particles can be obtained by a settling column test • Settling column – Height: equal to the depth of the proposed settling tank – Diameter can be anything – influences of the wall should be taken care off – sample required should be small enough – Provided with sampling ports
  • 3. • Settling column test – To begin with ensure uniform distribution of particle size from top to bottom of the column – Duration of test should be equal to the settling time in the proposed tank – Draw samples from the ports at various time intervals, analyze for TSS and compute % removal – Plot % removal against time and depth and construct curves of equal % removal – Overflow rates for various settling are determined by noting where the curve intersect the x-axis Flocculent Particle Settling                   2 (%) 1 1 nn n h n RR H h R
  • 4. Settling Column Settling Profile Graph
  • 6. Primary Sedimentation Tank • Purpose is removal of readily settleable solids and floating material from wastewater • Usually give 50-70% suspended solids removal efficiency and 25-40% BOD removal (for municipal sewage) • Rectangular or circular sedimentation tanks are used – Two or more cylindrical or rectangular sedimentation tanks may be used for allowing maintenance and repair – Multiple rectangular tanks require less land area than multiple circular tanks and common walls reduce construction cost • Sedimentation tanks should include – Inlet section and Outlet section – Facilities and provisions for the settled sludge scrapping, collection and removal – Facilities and provisions for the floating material entrapment, skimming, collection and removal • Sedimentation tank can be considered to include Settling zone and Sludge zone
  • 7. Flow pattern is radial with central feed arrangement • Has a center well of 15-20% of the tank diameter and 1.0 to 2.5 m depth is used • Center well has a tangential energy dissipating inlet • wastewater is discharged into the well within the upper 0.5-0.7 m at 0.3 to 0.45 m/sec flow velocity Solids removal mechanisms • Smaller tanks have hopper bottom with >45 inclination with the horizontal • 3.6-9.0 m diameter tanks have solids removal equipment supported on beams spanning the tank • Larger diameter tanks have a central pier supporting the mechanism and is reached by a walkway or bridge • Bottom of the tank is sloped at 1 in 12 to 64 or lesser • Solids are scrapped to the center and removed Clarified liquid is skimmed off over weirs into a collection trough Circular Primary Sedimentation Tank
  • 9. Clarified sewage Collection trough Scum retaining baffle Distribution baffle of central well Scrapper arm Skimmer bladeCentral well Central pier Influent pipe Sludge draw-off pipe Central rotating equipment Sludge trough Tangential openings in the pier for the distribution of the influent Slope 1 in 12 Side wall of clarifier 0.5m 0.3m 0.3m 0.3m 0.6m Central pier Sludge trough 0.5 m 1.5 m 0.5 m Sludge draw-off pipe Influent pipe Primary clarifier Section to show side wall with clarified sewage collection trough Bottom sludge trough and outlet 3.0 m
  • 10. Inlet • Full width inlet channels with inlet weirs – can introduce vertical velocity component spreading into the sludge hoppers (provided at the inlet end) • Inlets with submerged ports/orifices (velocities in the ports/orifices are in the range of 3-9 m/min.) • Inlet channels with wide gates and slotted baffles • Inlet baffles can be used to reduce high initial velocities and distribute flow width wise – usually extend from 150 mm below and 300 mm above the water surface Outlet • Clarified effluent is collected into a collection trough through an overflow weir • Floating material or settled suspended solids should not be washed out with the clarified effluent • Floating material retaining or entrapping baffle is provided • Weir length is designed to avoid washout out of sludge Rectangular Primary Sedimentation Tanks
  • 11. Facilities and provisions for the settled sludge scrapping, collection and removal • Settled sludge is collected at the inlet end • Chain and flight solids collectors – Have a pair of endless conveyor chains – Scraper flights of wood or fiberglass, running full width of the tank and attached to the chains at 3 m interval – The settled solids are scrapped • to solids hoppers In case of small tanks – multiple hoppers are used in larger tanks • to a transverse trough in case of large tanks - troughs in turn have cross collectors Rectangular Primary Sedimentation Tank
  • 12. Traveling bridge type collectors – Travel up and down the tank on rubber wheels or on rails supported on the sidewalls – Scrapper blades are suspended from the bridge (returning scraper blades lifted free of the solids blanket) Facilities and provisions for floating material entrapment, skimming, collection and removal • Floating scum is collected at the effluent end • Floating scum is skimmed and carried to the effluent end and entrapped for avoiding overflow into the clarified effluent trough – Flights returning at the liquid surface can be used – Water showers can be used to push forward the floating scum – Baffle is provided in front of the overflow weir for the scum entrapment until removed Rectangular Primary Sedimentation Tank
  • 13. • In small tanks scum draw-down facility consisting of a horizontal, slotted pipe that can be rotated by a lever or screw can be used – Limitation - creates large volume of scum liquor • Transverse rotating helical wiper attached to a shaft can also be used for scum removal – Scum is removed from the water surface and moved over an inclined apron for discharge to a cross-collecting scum trough Other provisions and facilities • Tanks may sloping bottom towards the influent end • Influent end has sludge hoppers or sludge trench • Scum pit is provided for storing the scum liquid removed • Sludge pump, piping and tank may be there to remove the collected sludge from the sludge hopper or trench Rectangular Primary Sedimentation Tank
  • 15. Design of Primary Clarifier • Overflow rate and hydraulic retention time obtained from the settling test and settling profile diagram are used to find surface area and depth of the clarifier • Safety factors of 1.25 is usually used to take into account – Inlet and outlet disturbances – Disturbances created by the rotating mechanism to scrap the settled sludge and to collect the floating scum – Wind blow effects – Temperature variations – Flow short-circuiting • Design also takes into account the following: – Horizontal flow velocity (below the scour velocity) – Weir overflow rate (below a limit to avoid density currents) – Weir overflow balancing to avoid short-circuiting problems – Flooding of collection trough
  • 16. Detention time 1.5 to 2.5 hours (2.0 hr.) Overflow rate Average flow 30-50 m3/m2.day (40) – 24-32 (26) Peak flow 80-120 m3/m2.day (100) – 48-70 (60) Weir loading 125-500 m3/m.day (250) Rectangular tanks Depth 3-4.9 (4.3) Length 15-90 (24-40) Width 3-24 (4.9-9.8) Flight speed 0.6-1.2 m/min (0.9) Circular tank Diameter 3-60 (12-45) Bottom slope 1 in 16 to 1 in 6 (1 in 12) Flight speed 0.02-0.05 rpm (0.03) Primary Sedimentation Tank
  • 17. Short circuiting and hydraulic stability • Tracer studies can be used for determining short-circuiting problems • Method of influent flow distribution can also affect short circuiting Temperature difference of 1C between incoming wastewater and wastewater of the tank can cause density current Wind blowing across the top of an open sedimentation tank can cause circulation cell to form – this reduces effective volumetric capacity of the tank Surface loading rates (overflow rates) • There can be regulations prescribing limits to surface loading rates • Overflow rates must be set low enough to ensure satisfactory performance at peak rates of flow Primary Sedimentation Tank
  • 18. Detention time • Solids reaching the settling tank are susceptible to flocculation • Flocculation is aided by eddying motion of fluid within the tank • Level of flocculation depends on the time elapsed (detention time) • In cold climates because of increase in water viscosity detention time required also increases (1.38 time more HRT for 10C water that when temperature is 20C) Weir loading rates • Have little effect on efficiency of primary settlign tanks Primary sludge scum characteristics and quantities • Factors influencing are – Characteristics of untreated water (strength and freshness) – Period of sedimentation – Conditions of the deposited solids – Period between solids removal operations Primary Sedimentation Tank
  • 19. Primary Sludge • Primary clarifier is designed for a specified % removal of TSS • From knowing the TSS and flow rate of the influent sewage primary sludge generated can be quantified • TSS of the sewage is comprised of inorganic TSS, VSS and Biodegradable VSS – Biodegradable VSS contributes BOD and this is 50-60% of the total BOD for municipal sewage • Primary clarifier through removing the Biodegradable VSS contributes to BOD removal – BOD removal in the primary clarifier is typically 35-45% • If BOD removal in the primary clarifier is known, one can find out the biodegradable fraction of the primary sludge – BOD removal can be expressed as BODu removal and BODu removal as TSS equivalent removal – The fraction of biodegradable VSS in the TSS is assumed to remain the same even in the clarified effluent • If consistency of the primary sludge is known even volume of the primary sludge can be calculated