PRJ101XL – Project Libre
Basic
www.ocdatabases.com
slides.1@ocdatabases.com
949-489-1472
Project Libre Basic
Note: The basic outline for this course and
much of the material was adapted from a
similar Microsoft Project course (which we
also offer) by Logical Operations, formerly
Element K.
Project Libre
 Open Source alternative to Microsoft
Project
 Can read and write Microsoft Project
files
PRJ101XL Project Libre Basic
 Introduction (s)
 Facilities
 Course Packet (May vary by course and class)
– Student Questionnaire
– Collaterals (Maps, Catalog, Etc.)
– Copy of PowerPoint slides used
– Evaluation form
– Training certificate
5
Project Libre: Basic
1. Getting started
2. Tasks
3. Task scheduling
4. Resource management
5. Views and tables
6. Filters, groups, and sorting
7. Finalizing the task plan
GETTING STARTED
Topic 1
Project constraints
Links between project phases
Initial
phase
Planning
phase
Close-out
phase
Implementation
phase
Monitoring
phase
Initiating
tasks
Planning
tasks
Executing
tasks
Monitoring
tasks
Closing
tasks
Controlling phases and communication
Typical project management tasks
Project management tasks
Planning tasks
Monitoring and
tracking tasks
Build the plan
Fine-tune the plan
Link tasks
Assign resources and costs
Set a project start date
Enter task names and duration
Set a baseline
Communicate with the team
Enter actuals
Track variance
Adjust the schedule
Print reports
Gantt Chart view
A task list in Gantt Chart view
Resource Sheet view
The Project Libre interface
Ribbon
T
a
s
k
e
n
t
r
y
G
a
n
n
t
c
h
a
r
t
File commands
A sample file in Gantt Chart view
Indicator column Column heading chart pane
Sheet pane
timescale
Gantt bar
Open a Project file
1. Click the File Tab
2. Click Open in the ribbon File Group
3. Navigate to and select the Project file
that you want to open
4. Click Open (or double-click the file)
Set the project start date
1. Click the File Tab
2. In the ribbon Project Group, click
Information
3. Set the start date
Project Information dialog box
Save a new project file
1. On the ribbon, click the Save button
(or press Ctrl+S)
2. In the Save As dialog box, navigate to
the location where you want to save
the project file
3. Enter a file name
4. Click Save (or press Enter)
TASKS
Topic 2
Add tasks to a task list
1. In the Task Name column, select the
cell below the location where you
want to insert the task
2. On the Task tab, click Insert Task
(Or right-click the cell below where you
want to insert the task and choose New)
3. Type the task information in the new
row
Delete tasks
 Click Delete on the task tab, or
 Right-click the task and choose
Delete Task
Cut and paste a task
1. Click a row number to select the row
2. Click Cut
3. Click the row number below where
you want to insert the cut task
4. Click Paste
Drag selected tasks
1. Click the row number to select the
row, or drag across row numbers to
select sequential tasks
2. Drag the selected rows to a new
position in the task list
Summary tasks
Convert a task into a milestone
1. In the Sheet pane, double-click the
task to open the Task Information
dialog box
2. Click the Advanced tab
3. Check “Display task as milestone”
4. Click Close
TASK SCHEDULING
Topic 3
When you link tasks:
 Project Libre automatically applies a
Finish-to-Start task dependency
 The start of the second task depends
on the completion of the first task
Linking tasks
1. Select the tasks
2. On the Task tab, click the Link button
Change a task’s predecessor
1. In the Sheet pane, locate the task
whose predecessor you want to
change
2. In the predecessor column, enter the
task ID of the task that you want to
set as the predecessor
Lag time
 A delay that adds time after the
completion of a task
 Example: “Install trim”
– If you add lag time to its predecessor,
“Paint,” the paint will have time to dry
before the trim installation begins
Lead time
 The overlap between dependent tasks
(when a task can start before its
predecessor finishes)
Lead and Lag Time
Apply lead time or lag time
1. Double-click a task in the Sheet pane
2. Click the Predecessors tab
3. To apply lag time, enter a positive
value in the Lag field for the
predecessor
To apply lead time, enter a negative
value
4. Click OK
Nodes in Network Diagram view
Dependencies
Dependency Gantt bar example Description
Finish-to-Start (FS) Task B cannot start
unless Task A is finished.
Start-to-Start (SS) Task B cannot start
unless Task A starts.
Finish-to-Finish
(FF)
Task B cannot finish
unless Task A is finished.
Start-to-Finish (SF) Task B cannot finish
unless Task A starts.
Task Dependency dialog box
Task types
Type Description
Fixed Duration Has a constant time value
Fixed Work Has a constant value for
the total work to be
performed
Fixed Unit Has a constant quantity or
units-of-resource value
Task Types
Task constraints
Constraint Description
As Late As Possible Schedules a task to start
as late as possible
As Soon As Possible Schedules a task to begin
as early as possible
Finish No Earlier Than Schedules a task to finish
on or after a specified date
Finish No Later Than Schedules a task to finish
on or before a specified
date
continued
Task constraints, continued
Constraint Description
Must Finish On Schedules a task to finish
on the specified date
Must Start On Schedules a task to start on
a specified date
Start No Earlier Than Schedules a task to start on
or after a specified date
Start No Later Than Schedules a task to start on
or before a specified date
Task Constraints
RESOURCE MANAGEMENT
Topic 4
Calendars
Create a base calendar
1. On the File tab, click Calendar
2. Click Create New Calendar
3. Type a name for the calendar
4. Select “Create new base calendar” and click OK
5. Make the necessary changes in the calendar
6. Specify the calendar exceptions and working times
for the work days
7. Click OK
8. On the Ribbon, click Information
9. Select the new base calendar and click OK
Change Working Time
This change made Saturdays a work day
Resource types
 Work resource
– Performs work on a task
– Examples: people, equipment
 Material resource
– Item used to perform work on a task
– Examples: paint, wood, steel, fuel
Create a resource calendar
1. In Resource Sheet view, in the Name
field, select the resource to which you
want to assign a calendar
2. On the Resource tab, click Calendar
3. Make the necessary changes in the
calendar and click OK
4. Click OK
Assign resources
1. Switch to Gantt Chart view
2. Select the task to which you want to
assign a resource
3. On the Task tab, click Assign
Resources
4. Select a resource and click Assign
5. Click Close
Assign Resources
Assign a resource to multiple tasks
1. Hold down Ctrl and select the tasks
to which you want to assign a
resource
2. Open the Assign Resources dialog
box
(Or open the dialog box first and then
select tasks in the Sheet pane)
3. Select the resource name and click
Assign
4. Click Close
Assign multiple resources to a task
1. Open the Assign Resources dialog
box
2. Select the task to which you want to
assign multiple resources
3. Select the resource you want to
assign
4. Press and hold Ctrl, and select the
other resource name(s) that you want
to assign to the task
5. Click Assign, and then click Close
Task Calendars
 Create a new calendar
 Open Task Information Dialogue
 Assign task calendar under advanced
tab
VIEWS AND TABLES
Topic 5
Views
 Click the View Tab
 Select the view
 Select a sub-view if desired
Insert a column
1. Right-click the column heading that’s
to the right of where you want to
insert the column
2. Choose Insert Column
3. Select the column name and click OK
4. Resize the column as needed
FILTERS, GROUPS AND
SORTING
Topic 6
Filter a view
1. Click the View tab
2. From the Filter list, select a filter
3. To return to an unfiltered view,
choose [No Filter] from the Filter list
Find
1. In the Sheet pane right click the
column header
2. Do either of the following:
– Select the field
– Type in the search term and click Find
A grouped task list
Grouped Task List
Group a task list
1. Click the View tab
2. Click grouping select list and select a
group option
Sort a task list
1. Click the View tab
2. Click Sorting select list and select a
sort option
FINALIZING THE TASK PLAN
Topic 7
Slack
 The amount of time you can delay
tasks without affecting the project
schedule
– Free slack — The amount of time a task
can be delayed before it delays another
task
– Total slack — The amount of time a task
can slip without delaying the project
completion date
Make a task non-effort-driven:
1. Double-click the task name to open
the Task Information dialog box
2. Click the Advanced tab
3. Clear Effort driven and click OK
Resource Usage view
Options to level resources manually
 Replace the over-allocated resource
with an under-allocated resource
 Assign an additional resource to the
task
 Reduce the work assignments for a
task, and increase the duration for its
completion
 Increase the working time of the
resource
Project Libre Basic
 Please fill out your evaluations and
submit them to your instructor
 Enjoy using Project Libre!
 If you want to know more: PRJ102XL
(Project Libre Advanced - monitoring & tracking
projects)

More Related Content

PDF
Microsoft Project - MSP | 2013-2016
PDF
Google Forms ppt
PPT
MS Word Advanced Training
PDF
CSS Best practice
PPTX
10 Amazing Things You Could Do With Google Drive
PDF
How to use google sheets
PPT
PRJ101a Project 2013 Accelerated
PDF
class-notes-5-tutorial-ms-project-28042025-101858am.pdf
Microsoft Project - MSP | 2013-2016
Google Forms ppt
MS Word Advanced Training
CSS Best practice
10 Amazing Things You Could Do With Google Drive
How to use google sheets
PRJ101a Project 2013 Accelerated
class-notes-5-tutorial-ms-project-28042025-101858am.pdf

Similar to PRJ101xl Project Libre Basic Training (20)

PDF
PM Lab7
PPTX
02 Creating A Task List
PDF
sMs project tutorial_iit
PDF
Ms project tutorial
PPTX
Project management software
DOCX
Project NameCommunication PlanOverviewEffective and .docx
PPTX
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
PDF
Omni plan 2-manual
DOCX
CSCI 714 Software Project Planning and EstimationLec.docx
PPTX
MICROSOFT PROJECT
PPTX
2009 ms project 2010 (2)
PPTX
2010 ms project 2010 (2)
PPTX
2eee22222w811-Microsoft-Project-2016.pptx
PDF
Ms project 2000 tutorial
PDF
Project management by MS Project 2010
PPTX
Lesson 2 PMT Getting Started with Project 2013.pptx
PPTX
Microsoft Project Foundations Course.pptx
PDF
MProjectTutorial.pdf
PPSX
How to Create S Curve by MS Project 2013
PPSX
How to create S-Curve by MS Project 2013
PM Lab7
02 Creating A Task List
sMs project tutorial_iit
Ms project tutorial
Project management software
Project NameCommunication PlanOverviewEffective and .docx
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Omni plan 2-manual
CSCI 714 Software Project Planning and EstimationLec.docx
MICROSOFT PROJECT
2009 ms project 2010 (2)
2010 ms project 2010 (2)
2eee22222w811-Microsoft-Project-2016.pptx
Ms project 2000 tutorial
Project management by MS Project 2010
Lesson 2 PMT Getting Started with Project 2013.pptx
Microsoft Project Foundations Course.pptx
MProjectTutorial.pdf
How to Create S Curve by MS Project 2013
How to create S-Curve by MS Project 2013
Ad

More from Dan D'Urso (20)

PPT
SQL201S Accelerated Introduction to MySQL Queries
PPT
LCD201d Database Diagramming with Lucidchart
PPTX
Database Normalization
PPT
VIS201d Visio Database Diagramming
PPT
Introduction to coding using Python
PPTX
Stem conference
PDF
SQL200A Microsoft Access SQL Design
PPTX
Microsoft access self joins
PDF
SQL302 Intermediate SQL
PDF
AIN106 Access Reporting and Analysis
PPT
SQL302 Intermediate SQL Workshop 3
PPT
SQL302 Intermediate SQL Workshop 2
PDF
Course Catalog
PPT
SQL302 Intermediate SQL Workshop 1
PDF
SQL212 Oracle SQL Manual
PDF
SQL201W MySQL SQL Manual
PDF
AIN100
PPT
SQL206 SQL Median
PPT
SQL202.3 Accelerated Introduction to SQL Using SQL Server Module 3
PPT
SQL202.2 Accelerated Introduction to SQL Using SQL Server Module 2
SQL201S Accelerated Introduction to MySQL Queries
LCD201d Database Diagramming with Lucidchart
Database Normalization
VIS201d Visio Database Diagramming
Introduction to coding using Python
Stem conference
SQL200A Microsoft Access SQL Design
Microsoft access self joins
SQL302 Intermediate SQL
AIN106 Access Reporting and Analysis
SQL302 Intermediate SQL Workshop 3
SQL302 Intermediate SQL Workshop 2
Course Catalog
SQL302 Intermediate SQL Workshop 1
SQL212 Oracle SQL Manual
SQL201W MySQL SQL Manual
AIN100
SQL206 SQL Median
SQL202.3 Accelerated Introduction to SQL Using SQL Server Module 3
SQL202.2 Accelerated Introduction to SQL Using SQL Server Module 2
Ad

Recently uploaded (20)

PDF
Digital Systems & Binary Numbers (comprehensive )
PDF
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
PPTX
Embracing Complexity in Serverless! GOTO Serverless Bengaluru
PDF
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
PDF
Internet Downloader Manager (IDM) Crack 6.42 Build 41
PDF
17 Powerful Integrations Your Next-Gen MLM Software Needs
PDF
iTop VPN Crack Latest Version Full Key 2025
PDF
Cost to Outsource Software Development in 2025
PDF
Design an Analysis of Algorithms I-SECS-1021-03
PPTX
Oracle Fusion HCM Cloud Demo for Beginners
PDF
Tally Prime Crack Download New Version 5.1 [2025] (License Key Free
PDF
Product Update: Alluxio AI 3.7 Now with Sub-Millisecond Latency
PDF
AutoCAD Professional Crack 2025 With License Key
PDF
Adobe Premiere Pro 2025 (v24.5.0.057) Crack free
PDF
Complete Guide to Website Development in Malaysia for SMEs
PDF
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
PDF
How AI/LLM recommend to you ? GDG meetup 16 Aug by Fariman Guliev
PDF
CapCut Video Editor 6.8.1 Crack for PC Latest Download (Fully Activated) 2025
PPTX
Reimagine Home Health with the Power of Agentic AI​
PPTX
Weekly report ppt - harsh dattuprasad patel.pptx
Digital Systems & Binary Numbers (comprehensive )
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
Embracing Complexity in Serverless! GOTO Serverless Bengaluru
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
Internet Downloader Manager (IDM) Crack 6.42 Build 41
17 Powerful Integrations Your Next-Gen MLM Software Needs
iTop VPN Crack Latest Version Full Key 2025
Cost to Outsource Software Development in 2025
Design an Analysis of Algorithms I-SECS-1021-03
Oracle Fusion HCM Cloud Demo for Beginners
Tally Prime Crack Download New Version 5.1 [2025] (License Key Free
Product Update: Alluxio AI 3.7 Now with Sub-Millisecond Latency
AutoCAD Professional Crack 2025 With License Key
Adobe Premiere Pro 2025 (v24.5.0.057) Crack free
Complete Guide to Website Development in Malaysia for SMEs
Internet Downloader Manager (IDM) Crack 6.42 Build 42 Updates Latest 2025
How AI/LLM recommend to you ? GDG meetup 16 Aug by Fariman Guliev
CapCut Video Editor 6.8.1 Crack for PC Latest Download (Fully Activated) 2025
Reimagine Home Health with the Power of Agentic AI​
Weekly report ppt - harsh dattuprasad patel.pptx

PRJ101xl Project Libre Basic Training

  • 1. PRJ101XL – Project Libre Basic www.ocdatabases.com slides.1@ocdatabases.com 949-489-1472
  • 2. Project Libre Basic Note: The basic outline for this course and much of the material was adapted from a similar Microsoft Project course (which we also offer) by Logical Operations, formerly Element K.
  • 3. Project Libre  Open Source alternative to Microsoft Project  Can read and write Microsoft Project files
  • 4. PRJ101XL Project Libre Basic  Introduction (s)  Facilities  Course Packet (May vary by course and class) – Student Questionnaire – Collaterals (Maps, Catalog, Etc.) – Copy of PowerPoint slides used – Evaluation form – Training certificate
  • 5. 5
  • 6. Project Libre: Basic 1. Getting started 2. Tasks 3. Task scheduling 4. Resource management 5. Views and tables 6. Filters, groups, and sorting 7. Finalizing the task plan
  • 9. Links between project phases Initial phase Planning phase Close-out phase Implementation phase Monitoring phase Initiating tasks Planning tasks Executing tasks Monitoring tasks Closing tasks Controlling phases and communication
  • 10. Typical project management tasks Project management tasks Planning tasks Monitoring and tracking tasks Build the plan Fine-tune the plan Link tasks Assign resources and costs Set a project start date Enter task names and duration Set a baseline Communicate with the team Enter actuals Track variance Adjust the schedule Print reports
  • 12. A task list in Gantt Chart view
  • 14. The Project Libre interface Ribbon T a s k e n t r y G a n n t c h a r t
  • 16. A sample file in Gantt Chart view Indicator column Column heading chart pane Sheet pane timescale Gantt bar
  • 17. Open a Project file 1. Click the File Tab 2. Click Open in the ribbon File Group 3. Navigate to and select the Project file that you want to open 4. Click Open (or double-click the file)
  • 18. Set the project start date 1. Click the File Tab 2. In the ribbon Project Group, click Information 3. Set the start date
  • 20. Save a new project file 1. On the ribbon, click the Save button (or press Ctrl+S) 2. In the Save As dialog box, navigate to the location where you want to save the project file 3. Enter a file name 4. Click Save (or press Enter)
  • 22. Add tasks to a task list 1. In the Task Name column, select the cell below the location where you want to insert the task 2. On the Task tab, click Insert Task (Or right-click the cell below where you want to insert the task and choose New) 3. Type the task information in the new row
  • 23. Delete tasks  Click Delete on the task tab, or  Right-click the task and choose Delete Task
  • 24. Cut and paste a task 1. Click a row number to select the row 2. Click Cut 3. Click the row number below where you want to insert the cut task 4. Click Paste
  • 25. Drag selected tasks 1. Click the row number to select the row, or drag across row numbers to select sequential tasks 2. Drag the selected rows to a new position in the task list
  • 27. Convert a task into a milestone 1. In the Sheet pane, double-click the task to open the Task Information dialog box 2. Click the Advanced tab 3. Check “Display task as milestone” 4. Click Close
  • 29. When you link tasks:  Project Libre automatically applies a Finish-to-Start task dependency  The start of the second task depends on the completion of the first task
  • 30. Linking tasks 1. Select the tasks 2. On the Task tab, click the Link button
  • 31. Change a task’s predecessor 1. In the Sheet pane, locate the task whose predecessor you want to change 2. In the predecessor column, enter the task ID of the task that you want to set as the predecessor
  • 32. Lag time  A delay that adds time after the completion of a task  Example: “Install trim” – If you add lag time to its predecessor, “Paint,” the paint will have time to dry before the trim installation begins Lead time  The overlap between dependent tasks (when a task can start before its predecessor finishes)
  • 33. Lead and Lag Time
  • 34. Apply lead time or lag time 1. Double-click a task in the Sheet pane 2. Click the Predecessors tab 3. To apply lag time, enter a positive value in the Lag field for the predecessor To apply lead time, enter a negative value 4. Click OK
  • 35. Nodes in Network Diagram view
  • 36. Dependencies Dependency Gantt bar example Description Finish-to-Start (FS) Task B cannot start unless Task A is finished. Start-to-Start (SS) Task B cannot start unless Task A starts. Finish-to-Finish (FF) Task B cannot finish unless Task A is finished. Start-to-Finish (SF) Task B cannot finish unless Task A starts.
  • 38. Task types Type Description Fixed Duration Has a constant time value Fixed Work Has a constant value for the total work to be performed Fixed Unit Has a constant quantity or units-of-resource value
  • 40. Task constraints Constraint Description As Late As Possible Schedules a task to start as late as possible As Soon As Possible Schedules a task to begin as early as possible Finish No Earlier Than Schedules a task to finish on or after a specified date Finish No Later Than Schedules a task to finish on or before a specified date continued
  • 41. Task constraints, continued Constraint Description Must Finish On Schedules a task to finish on the specified date Must Start On Schedules a task to start on a specified date Start No Earlier Than Schedules a task to start on or after a specified date Start No Later Than Schedules a task to start on or before a specified date
  • 45. Create a base calendar 1. On the File tab, click Calendar 2. Click Create New Calendar 3. Type a name for the calendar 4. Select “Create new base calendar” and click OK 5. Make the necessary changes in the calendar 6. Specify the calendar exceptions and working times for the work days 7. Click OK 8. On the Ribbon, click Information 9. Select the new base calendar and click OK
  • 46. Change Working Time This change made Saturdays a work day
  • 47. Resource types  Work resource – Performs work on a task – Examples: people, equipment  Material resource – Item used to perform work on a task – Examples: paint, wood, steel, fuel
  • 48. Create a resource calendar 1. In Resource Sheet view, in the Name field, select the resource to which you want to assign a calendar 2. On the Resource tab, click Calendar 3. Make the necessary changes in the calendar and click OK 4. Click OK
  • 49. Assign resources 1. Switch to Gantt Chart view 2. Select the task to which you want to assign a resource 3. On the Task tab, click Assign Resources 4. Select a resource and click Assign 5. Click Close
  • 51. Assign a resource to multiple tasks 1. Hold down Ctrl and select the tasks to which you want to assign a resource 2. Open the Assign Resources dialog box (Or open the dialog box first and then select tasks in the Sheet pane) 3. Select the resource name and click Assign 4. Click Close
  • 52. Assign multiple resources to a task 1. Open the Assign Resources dialog box 2. Select the task to which you want to assign multiple resources 3. Select the resource you want to assign 4. Press and hold Ctrl, and select the other resource name(s) that you want to assign to the task 5. Click Assign, and then click Close
  • 53. Task Calendars  Create a new calendar  Open Task Information Dialogue  Assign task calendar under advanced tab
  • 55. Views  Click the View Tab  Select the view  Select a sub-view if desired
  • 56. Insert a column 1. Right-click the column heading that’s to the right of where you want to insert the column 2. Choose Insert Column 3. Select the column name and click OK 4. Resize the column as needed
  • 58. Filter a view 1. Click the View tab 2. From the Filter list, select a filter 3. To return to an unfiltered view, choose [No Filter] from the Filter list
  • 59. Find 1. In the Sheet pane right click the column header 2. Do either of the following: – Select the field – Type in the search term and click Find
  • 62. Group a task list 1. Click the View tab 2. Click grouping select list and select a group option
  • 63. Sort a task list 1. Click the View tab 2. Click Sorting select list and select a sort option
  • 64. FINALIZING THE TASK PLAN Topic 7
  • 65. Slack  The amount of time you can delay tasks without affecting the project schedule – Free slack — The amount of time a task can be delayed before it delays another task – Total slack — The amount of time a task can slip without delaying the project completion date
  • 66. Make a task non-effort-driven: 1. Double-click the task name to open the Task Information dialog box 2. Click the Advanced tab 3. Clear Effort driven and click OK
  • 68. Options to level resources manually  Replace the over-allocated resource with an under-allocated resource  Assign an additional resource to the task  Reduce the work assignments for a task, and increase the duration for its completion  Increase the working time of the resource
  • 69. Project Libre Basic  Please fill out your evaluations and submit them to your instructor  Enjoy using Project Libre!  If you want to know more: PRJ102XL (Project Libre Advanced - monitoring & tracking projects)