Proctor Compaction Test
A Basic Guide
Proctor Compaction Test History
 In the early 1930s, University of California, Berkeley student Ralph R. Proctor
developed a method for determining the maximum density of soils. He established
a laboratory procedure to define the moisture-density relationship of compacted,
cohesive soils.
 Values from the Standard Proctor Test could be compared to unit weights and
moistures of the same soils compacted in the field as structural earth fills to
determine their degree of density and predict future performance.
 In 1958, the Modified Proctor Test was developed as an ASTM standard and it’s still
used today concurrently with the standard test. This blog post will focus on the
significance of soil compaction (particularly the Proctor Test), how the test is
performed, necessary equipment and helpful tips.
Proctor Compaction Test Importance
Compaction is a method of mechanically increasing the density of soil, and it’s
especially valuable in construction applications. If this process is not performed
properly, soil settlement can occur, resulting in unnecessary maintenance costs or
failure of the pavement or structure. Compacting soil:
 Increases load capacity and stability
 Decreases permeability
 Prevents settlement of the soils or damage from frost
 Reduces water seepage, expansion and heaving
Proctor Test
 The Proctor Compaction Test and its variants are used to determine optimal
moisture content for soils. This test is especially useful when determining the
relationship between water content and the dry unit weight of soils to establish the
maximum density of a soil needed for a fill area.
 The laboratory test serves a two-fold purpose by first determining the maximum
density achievable for the materials in the field, as a reference.
 Secondly, it measures the effect moisture has on soil density. These values are
often determined before earthwork begins to provide reference values for field
testing.
Sample Preparation
 A representative bulk sample is obtained for each type of material proposed for use in the
earthwork operation. Back in the lab, processing of the samples begins with gradual air-drying to
the desired moisture, usually around 10% or more below the anticipated optimum moisture. For
cohesive soils, this can be expedited by breaking down clumps and spreading the sample out on
open trays.
 Once the soil is friable enough, the breakdown can continue more thoroughly. It is important to
read and understand your particular test method carefully as there are a number of variables that
can affect this stage of sample preparation.
 For most standard and modified Proctor variations, this means reducing the finer materials to pass
through either a 4.75mm (#4) or 9.5mm (3/8in) sieve.
 Coarser materials are set aside for particle size determinations and in some cases for adding
proportionally back into the final test specimens. At this stage, sample breakdown and coarse
particle sizing are often performed concurrently.
Sample Preparation
 Four or five specimens are prepared for the compaction points with increasing moisture
contents and bracketing the estimated optimum water content. This requires some
guesswork and experience is always helpful.
 Approximate optimum moisture of most cohesive soils can be estimated by manually
squeezing a portion into a lump that will stick together, yet break cleanly into two
sections when “bent”.
 Weight of the specimens should be about 5lb (2.3kg) each for 4in (102mm) molds and
13lb (5.9kg) for 6in (152mm) molds to ensure enough compacted volume to properly fill
the molds. Water is added incrementally to increase the individual moisture contents
by about 2% for each specimen and mixed thoroughly.
 The prepared specimens are set aside in closed containers for a prescribed amount of
standing time ranging up to 16 hours for proper moisture conditioning. The containers
can be sealed metal cans, but heavy-duty zip-closure bags work well for this step.
Sample Compaction
 For each Proctor point, the operator compacts the specimen into the pre-weighed empty Proctor Mold in
three to five layers (lifts) according to the method required. Special Manual Rammers of 5.5lb (2.5kg)
dropped from a 12in (305mm) height, or 10lb Rammers with 18in (457mm) drop height are used for
compaction.
 Automatic Compactors are also available to make this process easier. The collar is removed and any excess
is carefully trimmed with a straightedge tool so the compacted soil is flush with the top of the mold. Small
voids can be manually filled with excess sample.
 The mold with sample is then weighed and recorded and the soil is extruded from the mold. A sample of
the specimen is obtained to determine exact moisture content by oven drying, and the process is repeated
for subsequent samples.
 For each of the initial points, the mass and the unit weight of the soil will increase as the increased
moisture lubricates particles and allows them to be consolidated into a denser state from the same
compactive effort.
 By about the fourth point (if you’re lucky and your estimates were correct) the mass of the sample will
decrease as the volume of water reaches a point where it displaces soil particles in a given volume. This
indicates that optimum moisture has been exceeded and having another point beyond that will make it a
bit easier when constructing the final compaction curve.
Calculation and Plotting
 The weight of each specimen is used to calculate wet unit weights and the oven-
dried moistures are used to determine a dry unit weight for each point.
 The results are plotted on a graph as dry unit weight vs. moisture content and will
show the curvilinear relationship that allows the maximum dry weight and
optimum moisture for each type of soil to be established.
 These results are applied directly during field compaction tests to express the
percent compaction of each test and determine if project design requirements are
being met.
Proctor Compaction Curve
Equipment
 Soil Molds with either 4in or 6in diameters to hold compacted samples
 Manual Soil Compactors enables compaction of an individual 4in Marshall asphalt
sample into a stationary mold using a manually operated drop hammer
 Mechanical Soil Compactors automatically count the number of hammer blows and shut
off when a preset number is reached for improved accuracy, operation and reliability
 Balance compliant with D4753 and 1-g readability to weigh the dry unit sample after
compaction
 Drying Oven that maintains uniformity to 230 ± 9°F (110 ± 5°C), to dry sample prior to
testing
 Straightedge to level and trim specimens held in the molds
 E11 Sieves for particle size determinations
 Pans for air drying, processing and mixing
Tips
 Heavy duty plastic freezer bags are convenient for storage and moisture conditioning of
individual compaction specimens.
 When preparing individual compaction specimens, it takes little time to prepare a
couple of extra, in case your estimates are a bit off. Set up one on the drier side and one
on the wet side to cover the bases.
 Some methods and materials require adding coarse material back into the final
specimen. Set aside your plus size material as you break down the bulk sample. It’s also
convenient to sieve the coarse material now to reduce handling.
 Using a Sample Ejector expedites removal of compacted soil from the mold, increasing
speed and efficiency and making it easier to obtain a representative moisture sample.
 Running five or six points of a proctor test can be physically demanding, especially with
a Modified Proctor using a 10lb hammer to compact five layers. If you didn’t qualify for
Rio this summer, consider a Mechanical Soil Compactor. This device reduces effort and
greatly enhances repeatability and accuracy.

More Related Content

PDF
Permeability of Soil
PPTX
Atterberg limits
PPTX
Phase System of Soil
PPTX
Field compaction methods
PPTX
Unconfined Compression Test
PDF
Class 8 Triaxial Test ( Geotechnical Engineering )
PDF
Particle Size Distribution & Classification of Soil
PPTX
Shear strength of soil
Permeability of Soil
Atterberg limits
Phase System of Soil
Field compaction methods
Unconfined Compression Test
Class 8 Triaxial Test ( Geotechnical Engineering )
Particle Size Distribution & Classification of Soil
Shear strength of soil

What's hot (20)

PDF
Stability of Slopes
PPTX
Shear strength of soil
PPTX
Soil compaction and effects on soil properties
PPTX
Method of-slices
PDF
Goetech. engg. Ch# 03 settlement analysis signed
PPT
Mass haul diagram
PDF
Class 3 (a) Soil Plasticity (Atterberg Limits) ( Geotechenical Engineering )
PPTX
3) sampling
PPTX
Determination of in situ density of soil
DOCX
Chapter 3 compaction and consolidation
PPTX
Compaction test of soil ASTM-D698
PPTX
Proctor compaction test
PPT
7 vertical stresses below applied loads (1)
PPTX
Index property of soil
PPTX
Field identification tests
PPTX
TYPES OF SOIL SAMPLE AND SAMPLERS .
PPTX
Vane shear test
PPTX
PPTX
Plate load test
Stability of Slopes
Shear strength of soil
Soil compaction and effects on soil properties
Method of-slices
Goetech. engg. Ch# 03 settlement analysis signed
Mass haul diagram
Class 3 (a) Soil Plasticity (Atterberg Limits) ( Geotechenical Engineering )
3) sampling
Determination of in situ density of soil
Chapter 3 compaction and consolidation
Compaction test of soil ASTM-D698
Proctor compaction test
7 vertical stresses below applied loads (1)
Index property of soil
Field identification tests
TYPES OF SOIL SAMPLE AND SAMPLERS .
Vane shear test
Plate load test
Ad

Viewers also liked (20)

DOCX
Proktor compaction
PPTX
Proctor compaction test
PDF
Class 4 Soil Compaction ( Geotechnical Engineering )
DOCX
Sand replacement
PPT
Soil Compaction - Civil Engineering
PPTX
proctor test and compaction
PDF
Lecture 5 soil compaction
PPT
Lecture soil compaction
PPTX
Compaction of soil
PPTX
Soil compaction
PDF
CBR Test
PDF
Class 6 Shear Strength - Direct Shear Test ( Geotechnical Engineering )
PPTX
Compaction tests
PDF
CBR Test
PPTX
Subgrade soil test, by Micotol
PDF
Class 7 Consolidation Test ( Geotechnical Engineering )
PDF
Soil mechanics note
PPTX
Soil MEchanics
PPTX
Sieve analysis test report
Proktor compaction
Proctor compaction test
Class 4 Soil Compaction ( Geotechnical Engineering )
Sand replacement
Soil Compaction - Civil Engineering
proctor test and compaction
Lecture 5 soil compaction
Lecture soil compaction
Compaction of soil
Soil compaction
CBR Test
Class 6 Shear Strength - Direct Shear Test ( Geotechnical Engineering )
Compaction tests
CBR Test
Subgrade soil test, by Micotol
Class 7 Consolidation Test ( Geotechnical Engineering )
Soil mechanics note
Soil MEchanics
Sieve analysis test report
Ad

Similar to Proctor Compaction Test: A Basic Guide (20)

PDF
Bearing ratio capacity of compacted soil
PDF
Chapter Seven soil mechanics-I.pdf
DOCX
Liquid limit & plastic limit test
PDF
D 425 – 88 R01 ;RDQYNQ__.pdf
PPTX
Construction of High Speed Highway and Test track
DOCX
Standard proctor test
PPTX
Soil Compaction slide.pptx
PPT
Compaction and Drain-ability
PPTX
COMPACTION CONTROL TESTS made by hassan iraq.pptx
PDF
CT-233 SOIL MECHANICS LAB MANUAL BSC Civil
DOCX
Ex 8 standard proctor test
PPTX
Atterberg limit test
PPTX
Cbr aashto t193 plus proctor t180
PDF
compaction test
PPTX
Soil Mechanics Presentation 3 Group 3.pptx
PDF
ASTM D5030.pdf
PDF
Highway Engineering Common Laboratory Tests.pdf
PDF
compaction test poster presentation
PDF
Chapter 3 soil compaction and field density
Bearing ratio capacity of compacted soil
Chapter Seven soil mechanics-I.pdf
Liquid limit & plastic limit test
D 425 – 88 R01 ;RDQYNQ__.pdf
Construction of High Speed Highway and Test track
Standard proctor test
Soil Compaction slide.pptx
Compaction and Drain-ability
COMPACTION CONTROL TESTS made by hassan iraq.pptx
CT-233 SOIL MECHANICS LAB MANUAL BSC Civil
Ex 8 standard proctor test
Atterberg limit test
Cbr aashto t193 plus proctor t180
compaction test
Soil Mechanics Presentation 3 Group 3.pptx
ASTM D5030.pdf
Highway Engineering Common Laboratory Tests.pdf
compaction test poster presentation
Chapter 3 soil compaction and field density

Recently uploaded (20)

PPTX
additive manufacturing of ss316l using mig welding
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
PPT on Performance Review to get promotions
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
web development for engineering and engineering
PPTX
Artificial Intelligence
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
composite construction of structures.pdf
PDF
Digital Logic Computer Design lecture notes
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
additive manufacturing of ss316l using mig welding
Internet of Things (IOT) - A guide to understanding
Safety Seminar civil to be ensured for safe working.
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
CYBER-CRIMES AND SECURITY A guide to understanding
PPT on Performance Review to get promotions
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
OOP with Java - Java Introduction (Basics)
R24 SURVEYING LAB MANUAL for civil enggi
Embodied AI: Ushering in the Next Era of Intelligent Systems
web development for engineering and engineering
Artificial Intelligence
UNIT-1 - COAL BASED THERMAL POWER PLANTS
composite construction of structures.pdf
Digital Logic Computer Design lecture notes
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Model Code of Practice - Construction Work - 21102022 .pdf

Proctor Compaction Test: A Basic Guide

  • 2. Proctor Compaction Test History  In the early 1930s, University of California, Berkeley student Ralph R. Proctor developed a method for determining the maximum density of soils. He established a laboratory procedure to define the moisture-density relationship of compacted, cohesive soils.  Values from the Standard Proctor Test could be compared to unit weights and moistures of the same soils compacted in the field as structural earth fills to determine their degree of density and predict future performance.  In 1958, the Modified Proctor Test was developed as an ASTM standard and it’s still used today concurrently with the standard test. This blog post will focus on the significance of soil compaction (particularly the Proctor Test), how the test is performed, necessary equipment and helpful tips.
  • 3. Proctor Compaction Test Importance Compaction is a method of mechanically increasing the density of soil, and it’s especially valuable in construction applications. If this process is not performed properly, soil settlement can occur, resulting in unnecessary maintenance costs or failure of the pavement or structure. Compacting soil:  Increases load capacity and stability  Decreases permeability  Prevents settlement of the soils or damage from frost  Reduces water seepage, expansion and heaving
  • 4. Proctor Test  The Proctor Compaction Test and its variants are used to determine optimal moisture content for soils. This test is especially useful when determining the relationship between water content and the dry unit weight of soils to establish the maximum density of a soil needed for a fill area.  The laboratory test serves a two-fold purpose by first determining the maximum density achievable for the materials in the field, as a reference.  Secondly, it measures the effect moisture has on soil density. These values are often determined before earthwork begins to provide reference values for field testing.
  • 5. Sample Preparation  A representative bulk sample is obtained for each type of material proposed for use in the earthwork operation. Back in the lab, processing of the samples begins with gradual air-drying to the desired moisture, usually around 10% or more below the anticipated optimum moisture. For cohesive soils, this can be expedited by breaking down clumps and spreading the sample out on open trays.  Once the soil is friable enough, the breakdown can continue more thoroughly. It is important to read and understand your particular test method carefully as there are a number of variables that can affect this stage of sample preparation.  For most standard and modified Proctor variations, this means reducing the finer materials to pass through either a 4.75mm (#4) or 9.5mm (3/8in) sieve.  Coarser materials are set aside for particle size determinations and in some cases for adding proportionally back into the final test specimens. At this stage, sample breakdown and coarse particle sizing are often performed concurrently.
  • 6. Sample Preparation  Four or five specimens are prepared for the compaction points with increasing moisture contents and bracketing the estimated optimum water content. This requires some guesswork and experience is always helpful.  Approximate optimum moisture of most cohesive soils can be estimated by manually squeezing a portion into a lump that will stick together, yet break cleanly into two sections when “bent”.  Weight of the specimens should be about 5lb (2.3kg) each for 4in (102mm) molds and 13lb (5.9kg) for 6in (152mm) molds to ensure enough compacted volume to properly fill the molds. Water is added incrementally to increase the individual moisture contents by about 2% for each specimen and mixed thoroughly.  The prepared specimens are set aside in closed containers for a prescribed amount of standing time ranging up to 16 hours for proper moisture conditioning. The containers can be sealed metal cans, but heavy-duty zip-closure bags work well for this step.
  • 7. Sample Compaction  For each Proctor point, the operator compacts the specimen into the pre-weighed empty Proctor Mold in three to five layers (lifts) according to the method required. Special Manual Rammers of 5.5lb (2.5kg) dropped from a 12in (305mm) height, or 10lb Rammers with 18in (457mm) drop height are used for compaction.  Automatic Compactors are also available to make this process easier. The collar is removed and any excess is carefully trimmed with a straightedge tool so the compacted soil is flush with the top of the mold. Small voids can be manually filled with excess sample.  The mold with sample is then weighed and recorded and the soil is extruded from the mold. A sample of the specimen is obtained to determine exact moisture content by oven drying, and the process is repeated for subsequent samples.  For each of the initial points, the mass and the unit weight of the soil will increase as the increased moisture lubricates particles and allows them to be consolidated into a denser state from the same compactive effort.  By about the fourth point (if you’re lucky and your estimates were correct) the mass of the sample will decrease as the volume of water reaches a point where it displaces soil particles in a given volume. This indicates that optimum moisture has been exceeded and having another point beyond that will make it a bit easier when constructing the final compaction curve.
  • 8. Calculation and Plotting  The weight of each specimen is used to calculate wet unit weights and the oven- dried moistures are used to determine a dry unit weight for each point.  The results are plotted on a graph as dry unit weight vs. moisture content and will show the curvilinear relationship that allows the maximum dry weight and optimum moisture for each type of soil to be established.  These results are applied directly during field compaction tests to express the percent compaction of each test and determine if project design requirements are being met.
  • 10. Equipment  Soil Molds with either 4in or 6in diameters to hold compacted samples  Manual Soil Compactors enables compaction of an individual 4in Marshall asphalt sample into a stationary mold using a manually operated drop hammer  Mechanical Soil Compactors automatically count the number of hammer blows and shut off when a preset number is reached for improved accuracy, operation and reliability  Balance compliant with D4753 and 1-g readability to weigh the dry unit sample after compaction  Drying Oven that maintains uniformity to 230 ± 9°F (110 ± 5°C), to dry sample prior to testing  Straightedge to level and trim specimens held in the molds  E11 Sieves for particle size determinations  Pans for air drying, processing and mixing
  • 11. Tips  Heavy duty plastic freezer bags are convenient for storage and moisture conditioning of individual compaction specimens.  When preparing individual compaction specimens, it takes little time to prepare a couple of extra, in case your estimates are a bit off. Set up one on the drier side and one on the wet side to cover the bases.  Some methods and materials require adding coarse material back into the final specimen. Set aside your plus size material as you break down the bulk sample. It’s also convenient to sieve the coarse material now to reduce handling.  Using a Sample Ejector expedites removal of compacted soil from the mold, increasing speed and efficiency and making it easier to obtain a representative moisture sample.  Running five or six points of a proctor test can be physically demanding, especially with a Modified Proctor using a 10lb hammer to compact five layers. If you didn’t qualify for Rio this summer, consider a Mechanical Soil Compactor. This device reduces effort and greatly enhances repeatability and accuracy.