1. Background
Sound Public Procurement Policies and
Practices are among the essential elements of good
governance. Good practices reduce cost and produce
timely results in efficient manner. Poor practices
lead to wastage and delays and often become the
cause of allegations in corruption and government
inefficiencies. It is government’s duty to take
measures to ensure adequate principles and practices
are followed in public works and services. Sufficient
regulatory provisions have been made; meanwhile
sufficient threats and weep holes have been
identified along with in our procurement practices.
Prevailing Public Procurement Act 2063,
along with previous FAR had, has adopted the
competitive bidding process for procuring works,
goods and services. It is aimed to acquire the
reasonable standard of delivery in the least cost
through capable deliverer/supplier. Despite such
provision, current practices have not attained
sufficient satisfactory result as aimed in the
regulatory provisions. It has been a big challenge for
every public authority to get the reasonable standard
of delivery. Manipulations are often found both from
contracting parties during bid preparation as well as
procuring authority during the evaluation process.
During bidding process major alterations the bidders
make is the faulty information about the work
experience, financial turnover, faulty equipment and
manpower capability information. It is often
observed that the bidders have a wide tendency to
make fake documents to show that they meet the
qualifying criteria mentioned in the bidding
documents. Likewise, during evaluation process
public authoritarians have often found to have vested
interest to make certain bidder successful
prejudicially and alterations in the posted documents
of bidders have taken place with motive of unethical
financial gain.
All such unfair practices have made the
procurement practices unfaithful and government
works and services ineffective compared to their
objectives. So, there is urgent need of adopting a
smart system which minimizes the chances of
alteration and manipulation before, during and after
bidding process. To make procurements efficient
and unaltered, Procurement Management
Information System (PMIS) can be a smart remedy
in reducing inefficiencies, manipulations and fraud
& corruption during tendering and contract
execution.
2. What is PMIS?
Procurement Management Information
System (PMIS) is a smart system which collects,
stores and synthesizes the procurement related
information all over the country. It is an online based
central and integrated data management system
concerning to the procurement activities. PMIS uses
centrally updated data warehouse to track, record
and verify the procurement history and current
capabilities of the contracting parties’ viz.
contractors/suppliers/ consultants. During bidding,
bid evaluation and contract execution PMIS serves
as necessary source of transformation of authentic
information and bridges between the bidders and
procuring authority. PPMO can be an appropriate
authority to undertake the central data management
system.
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
3. Components of PMIS and Registration
Components of PMIS are more similar to that of
e-submission system being adopted till date. The
difference lies in the continuous receiving and
updating of the capabilities and procurement
information by PMIS unlike to e-submission system.
Following are the component units of PMIS.
a. Central Data server- a data warehouse
b. Online Service Package
c. System Members
i. System administrator, say
PPMO
ii. Procuring Authorities
iii. Bidding Parties i.e. contractors/
suppliers/consultants
iv. Scheduled Banks
4. Work Flow Steps in PMIS
Work flow of adopting PMIS should take in
the following sequential order.
a. Registration of Users
Registration of different users
should follow different methods.
Adequate review and verification
should be done prior to the
registration since the users are made
authorized, with designated powers
according to the type of user, to
participate in the public
procurement by registering them in
the system. Registration of users’
takes place with following
hierarchical order.
i. Registration of System
administrator:- This is a single
entity type of user. PPMO (or
any central authority) is a single
and one time registration
process.
ii. Registration of Procuring
Authorities:- All the procuring
entities should enter into the
system by certifying their
procurement needs by the
government departments with
authorized lettering.
iii. Registration of
contractors/suppliers/consultant
s: - Registration of bidding
parties in PMIS should be
managed in such a way that they
are bound to enter in the PMIS
by written request with
supporting documents rightly
after they are registered in the
firm/company registration
authority. At the time of
registration the current
capabilities i.e. Manpower,
equipments, financial resources
and other technical capabilities
should be registered along with.
iv. Registration of Scheduled Banks: -
Registration of Banks takes place on
demand to the system by bidding parties
(for presenting bid charge amount, bid
security guaranty or performance
guaranty during bidding process) or by
procuring authorities (during payments).
b. Electronic Bidding
Invitation of bids, quotations, RFPs
etc should be called officially through
electronic bidding process. For doing so
every procuring authority should keep
online based centralized service
package/software. Preparation of bid
documents can be simplified by already
prepared templates by administrator where
necessary entries can be made pertaining to
the unique details of that contract. Posting of
bid notice to the system automatically
generates email notification to every
members registered to the system.
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
On receiving the notification,
bidders can prepare his bid by providing his
necessary entries of item rates and other
required customization to the provided bid
template. Also the bidding parties have to
manage the appropriate bank to issue bid
security guaranty which too, gets submitted
through online in the PMIS system along
with the bid. There is no need to mention the
experience information, manpower and
equipment capabilities and financial
turnover etc. by the bidders on their own as
these things are automatically stored and
updated continuously in the system. Bidding
by that time only indicates the willingness of
the particular bidder.
c. Bid Opening and Evaluation
Opening of bid will not be a big deal
after going online system of PMIS as there
is no chance of manipulations and
alterations as like in case of hard copy
submission. So, it follows a regular office
day process. Bidding period can also be
reduced as online system gives a reduced
effort on bid preparation. After opening of
bids on the specified date and time, it can be
automated in the PMIS system to send the
abstract details of submitted bids to all the
bidders as bid opening checklist (muchulka
as we say).
After opening of bids evaluation of
the bid takes place. This section in the
system is only accessible from the terminal
of procuring authority (the buyer). Through
this section the buyer generates the checklist
of Requirement Details of the contract as
indicated in the bid document already
prepared and also the detail capability of the
bidders though the PMIS central data
warehouse. On comparison of both, system
automatically indicates the eligible and
ineligible bidders. After generating the
Comparative Chart of proposed item rates in
the BOQ provided by the eligible bidders
along with the bid document template,
Lowest Eligible Bidder is easily determined.
The case of responsive and non responsive
bidders can be omitted by filtering during
the bidding process i.e. not allowing the
non-responsive bids for particular contract
during bidding.
d. Contract Award and Monitoring
After evaluation of bid, contract is
awarded to the successful bidder through the
system. Going through the contract award
terminal by the buyer, contract agreement
template document already created in the
system is modified and customized in the
required field only (i.e name and ID of
contract, SCC, Priced BOQ, time of
execution, milestones etc) which gets
entered in the data warehouse. It can be
utilized by the system for real-time tracking
of contract.
By the help of set data in the system
(or say in the contract document) PMIS
regulated and notifies the necessary
information like milestones, time frame,
guaranty times, and progress and suggests
action to the concerned party. Mandatory
actions cannot be modified or altered by
none of the registered users (neither buyer
nor the administrator). For example, if the
milestone provisioned in the contract is not
achieved, it suggests charging Liquidated
Damage as in the contract document and it
has to be done by the buyer otherwise
payment order by the system does not
proceed. Hence the chance of manipulations
in the contract execution is highly reduced.
e. Payments and Completion of
Contract
During or on completion of contract
execution series of payment shall be
released. The payments can be released to
the contracting parties upon the billing of
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
executing works through the billing section
of the PMIS accessible only to the buyer.
Payment can be issued through the
scheduled banks upon the online request
order through the system. On completion of
works or services, completion report is
prepared with contract execution details and
final payment is released.
f. Updating the Contract Execution
Report
Since every action is preceded
through the online based software package
of PMIS connected to the central server it is
gets automatically saved to server. On
termination of contract, summary of contract
execution, milestones, progress record,
billing information and payment history is
recorded by the system removing the other
tracking histories.
Compilation of such executive
summaries of all contracts handled by a
particular contracting party, yearly work
experience and financial turnover can be
easily generated by the system. Turnover
Report of all the registered contracting
parties can be published in the system in the
yearly basis. Such reports are usable for
future bidding actions and contract
management.
g. Updating the Increased Capability of
Bidders
The system should support the
update of the increased capability of bidding
parties. Increment in the resources,
manpower, equipment and other capital
assets etc should be updated with written
request by the contracting parties on
verification of the requested update with
supporting documents (i.e. purchase receipt
and departmental registration slip etc.) by
the system administrator.
5. Advantages of PMIS over Traditional
System
Adoption of PMIS can make vast difference
in the current procurement practices. There
is very little or no chance of manipulations
during the bidding process as well as
contract execution. Following are some of
the advantages.
i. During bidding process, bidders
cannot present the fake
information of experience,
turnover and equipment as in
the current hard copy
submission system since tracked
factual data are given by the
system server.
ii. One equipment, manpower or
vehicles allocated by bidder for
particular contract in the bid can
be made used for that contract
only making unable to allocate
for other contracts.
iii. Opening and evaluation of bids
is highly simplified work in
PMIS. There is no chance of
manipulations and alterations in
the documents by evaluation
team. Chance of unethical
processing is reduced.
iv. PMIS timely informs and
alarms about the milestones,
critical activities and time
frames which we often forget
during contract execution in our
present practice.
v. Every detail of all ongoing as
well as completed contracts is
tracked by the system server
enabling the generation of status
of contracts overally, particular
to a contract or particular record
of a contracting party. Helps in
taking necessary action.
A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4,
2013 pp 209-213
vi. Since PMIS eliminated major
alterations, it greatly reduces the
cases of fraud and corruption as
procurement is the major source
of corruption.
6. Current Challenges of Adopting PMIS
Every new starts faces some challenges.
Adoption of PMIS too, will not be free from
hindrances and obstacles at its start.
Following are our challenges to go for
adopting PMIS in public procurements.
i. Reluctance of public authorities
and political circle to adopt a
smart and alteration –free
system.
ii. PMIS is fully online based.
Lack of continuous electricity
supply and internet connections
every places of country.
iii. Limitation of proper level of
computer skills among public
personnel’s and contracting
parties.
iv. Proper mechanism of data
encryption in online system
should be established.
v. Without clearly stating in the
procurement act and until detail
regulations and guidelines to go
for an online based system is
made, it is difficult to adopt
PMIS.
7. Emerging from the Challenges and
Way Forward
Despite a nos. of limitations and
reluctance in our current system, we are
bound to correct them as we are, now or
then, bound to rise from our misery. It’s
only we and our generation to make our
environment a better place. If we sought for
a dynamic and well mechanized system in
our governance, the result is efficient service
delivery with a lesser operation cost. Since
procurement sector is a major area of
corruption; a properly controlled, dynamic
and smart system in our procurement
practice is urgently needed. Procurement
Management Information System plays a
vital role in curbing corruption eliminating
the chances of manipulations.
PMIS does not make the
procurement different but makes it proceed
differently. The reduced effort, lesser
chances in alterations, elimination of
unhealthy competition, reduction in chances
of undue benefits are the results PMIS
provides. Many of the countries in the world
including Bangladesh, whom we used to call
a major country of procurement mishmash
in South Asia, has already gone for complete
online based procurement system. So, it’s
our time to leap into a prosperous and
mechanized country through procurement
reforms and good-governance. It’s a crucial
time that PPMO is undertaking the process
of replacing of the current Public
Procurement Act with a new one and is a
better instance to quest for an efficient and
smart system. The recent budget speech of
FY 2070 has too, proclaimed its
commitment for electronic government
procurement i.e. e-GP system, which should
be advocated to make happened in real.
References
i. World Bank Country Procurement
Assessment Report (October 2002)
ii. Asian Development Bank, “Curbing
Corruption in Public Procurement in Asia
and the Pacific, Progress and Challenges in
25 Countries”,2006
iii. E-GP Guidelines of Government of Peoples
Republic of Bangladesh, 2009
iv. E-procurement Portal of DoLIDAR,
Nepal,<https://www.edolidar.gov.np>

More Related Content

PDF
OpenProcurement toolkit
DOCX
E - Procurement Report
PPT
Order Management Overview
PDF
Procure-to-Pay Process Framework
PPTX
Outsourcing and Vendor management
PDF
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
PDF
Case study: Camunda BPM in PwC project
PPT
E Procurement
OpenProcurement toolkit
E - Procurement Report
Order Management Overview
Procure-to-Pay Process Framework
Outsourcing and Vendor management
Project Plan ERP Sample by ijaz haider malik weboriez@hotmail
Case study: Camunda BPM in PwC project
E Procurement

What's hot (20)

PDF
B/oss BOSS Bss oss b.oss telecom ppt by ijaz haider malik
PPT
Supply chain management
PPT
Demand management
PPT
IT & SCM BY Zaki from Ajay Kumar Garg Institue Of Management
PPTX
The role of technology in procurement
PPTX
Strategic Lead Time Management
PDF
Procurement Powerpoint Presentation Slides
PPTX
Category management and procurement planning
PPT
A view of procurement best practice
PPT
Procurement
PPTX
Procurement Strategy by Derek Hendrikz
PDF
Process architecture - Part II
PPTX
Procurement ai is artificial intelligence real in procurement
PPSX
Procurement system
PDF
Purchasing and Procurement management
PDF
Logistics management & supply chain strategy
PPTX
How Gartner Helps Across the Entire IT Cost Optimization Life Cycle
PPSX
Project Procurement - Principles and Case Study
PPT
E businnes and the supply chain
PDF
Understand your Business processes
B/oss BOSS Bss oss b.oss telecom ppt by ijaz haider malik
Supply chain management
Demand management
IT & SCM BY Zaki from Ajay Kumar Garg Institue Of Management
The role of technology in procurement
Strategic Lead Time Management
Procurement Powerpoint Presentation Slides
Category management and procurement planning
A view of procurement best practice
Procurement
Procurement Strategy by Derek Hendrikz
Process architecture - Part II
Procurement ai is artificial intelligence real in procurement
Procurement system
Purchasing and Procurement management
Logistics management & supply chain strategy
How Gartner Helps Across the Entire IT Cost Optimization Life Cycle
Project Procurement - Principles and Case Study
E businnes and the supply chain
Understand your Business processes
Ad

Similar to Procurement Management Information System (PMIS) for Improving Public Procurements in Nepal (20)

DOCX
CHAPTER 6 APPLICATIONS OF ICT IN PROCUREMENT.docx
PPTX
A primer on bid management b2 b_egovernance_biswa.prakash@hotmail.com
PDF
Framework to monitor and evaluate e gp systems in india (v3.5)
PPTX
e-GP overview and bidding process for NASC_0.pptx
PDF
Muehle ochieng 6ippc_p2p_presentation
PPTX
Project Management Information System.pptx
PPTX
Edcil Techncial PPT_V1.0.pptx
DOC
Report on e procurement
PPTX
Purchase information system
PPTX
Bidding The Right Way
PDF
Failure in construction due to ineffective project management information.final
PDF
A Novel Intelligence-based e-Procurement System to offer Maximum Fairness Ind...
PDF
A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...
PDF
PMI's Certified Associate in Project Management, CAPM Training India
PDF
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
PPTX
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
PPT
Ashok Kumar Singh
PDF
Factors Affecting E-Procurement Adoption in Minimizing Risks in the Supply Ch...
PPTX
Tendering process, Bid Evaluation & Award Process
PDF
Proposal for e-Procurement System for Developing Country
CHAPTER 6 APPLICATIONS OF ICT IN PROCUREMENT.docx
A primer on bid management b2 b_egovernance_biswa.prakash@hotmail.com
Framework to monitor and evaluate e gp systems in india (v3.5)
e-GP overview and bidding process for NASC_0.pptx
Muehle ochieng 6ippc_p2p_presentation
Project Management Information System.pptx
Edcil Techncial PPT_V1.0.pptx
Report on e procurement
Purchase information system
Bidding The Right Way
Failure in construction due to ineffective project management information.final
A Novel Intelligence-based e-Procurement System to offer Maximum Fairness Ind...
A RATIONAL APPROACH FOR ASSESSING THE COMPETITIVE BIDDING OF INFRASTRUCTURE P...
PMI's Certified Associate in Project Management, CAPM Training India
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Prajwal Bhattarai - Role and Importance of Project Management Information sys...
Ashok Kumar Singh
Factors Affecting E-Procurement Adoption in Minimizing Risks in the Supply Ch...
Tendering process, Bid Evaluation & Award Process
Proposal for e-Procurement System for Developing Country
Ad

Recently uploaded (20)

PPT
Data mining for business intelligence ch04 sharda
PPT
Chapter four Project-Preparation material
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
Business model innovation report 2022.pdf
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
DOCX
Euro SEO Services 1st 3 General Updates.docx
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Training And Development of Employee .pdf
PDF
Types of control:Qualitative vs Quantitative
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Data mining for business intelligence ch04 sharda
Chapter four Project-Preparation material
Power and position in leadershipDOC-20250808-WA0011..pdf
New Microsoft PowerPoint Presentation - Copy.pptx
Principles of Marketing, Industrial, Consumers,
Unit 1 Cost Accounting - Cost sheet
Business model innovation report 2022.pdf
COST SHEET- Tender and Quotation unit 2.pdf
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Euro SEO Services 1st 3 General Updates.docx
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Nidhal Samdaie CV - International Business Consultant
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Training And Development of Employee .pdf
Types of control:Qualitative vs Quantitative
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh

Procurement Management Information System (PMIS) for Improving Public Procurements in Nepal

  • 1. A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013 pp 209-213 Urgent Need of Procurement Management Information System (PMIS) For Improving Public Procurements Shree Ram Dhakal Consulting Engineer PDE, Rural Access Improvement and Decentralization Project (RAIDP) District Technical Office, Surkhet dhakal.shreeram@gmail.com 1. Background Sound Public Procurement Policies and Practices are among the essential elements of good governance. Good practices reduce cost and produce timely results in efficient manner. Poor practices lead to wastage and delays and often become the cause of allegations in corruption and government inefficiencies. It is government’s duty to take measures to ensure adequate principles and practices are followed in public works and services. Sufficient regulatory provisions have been made; meanwhile sufficient threats and weep holes have been identified along with in our procurement practices. Prevailing Public Procurement Act 2063, along with previous FAR had, has adopted the competitive bidding process for procuring works, goods and services. It is aimed to acquire the reasonable standard of delivery in the least cost through capable deliverer/supplier. Despite such provision, current practices have not attained sufficient satisfactory result as aimed in the regulatory provisions. It has been a big challenge for every public authority to get the reasonable standard of delivery. Manipulations are often found both from contracting parties during bid preparation as well as procuring authority during the evaluation process. During bidding process major alterations the bidders make is the faulty information about the work experience, financial turnover, faulty equipment and manpower capability information. It is often observed that the bidders have a wide tendency to make fake documents to show that they meet the qualifying criteria mentioned in the bidding documents. Likewise, during evaluation process public authoritarians have often found to have vested interest to make certain bidder successful prejudicially and alterations in the posted documents of bidders have taken place with motive of unethical financial gain. All such unfair practices have made the procurement practices unfaithful and government works and services ineffective compared to their objectives. So, there is urgent need of adopting a smart system which minimizes the chances of alteration and manipulation before, during and after bidding process. To make procurements efficient and unaltered, Procurement Management Information System (PMIS) can be a smart remedy in reducing inefficiencies, manipulations and fraud & corruption during tendering and contract execution. 2. What is PMIS? Procurement Management Information System (PMIS) is a smart system which collects, stores and synthesizes the procurement related information all over the country. It is an online based central and integrated data management system concerning to the procurement activities. PMIS uses centrally updated data warehouse to track, record and verify the procurement history and current capabilities of the contracting parties’ viz. contractors/suppliers/ consultants. During bidding, bid evaluation and contract execution PMIS serves as necessary source of transformation of authentic information and bridges between the bidders and procuring authority. PPMO can be an appropriate authority to undertake the central data management system.
  • 2. A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013 pp 209-213 3. Components of PMIS and Registration Components of PMIS are more similar to that of e-submission system being adopted till date. The difference lies in the continuous receiving and updating of the capabilities and procurement information by PMIS unlike to e-submission system. Following are the component units of PMIS. a. Central Data server- a data warehouse b. Online Service Package c. System Members i. System administrator, say PPMO ii. Procuring Authorities iii. Bidding Parties i.e. contractors/ suppliers/consultants iv. Scheduled Banks 4. Work Flow Steps in PMIS Work flow of adopting PMIS should take in the following sequential order. a. Registration of Users Registration of different users should follow different methods. Adequate review and verification should be done prior to the registration since the users are made authorized, with designated powers according to the type of user, to participate in the public procurement by registering them in the system. Registration of users’ takes place with following hierarchical order. i. Registration of System administrator:- This is a single entity type of user. PPMO (or any central authority) is a single and one time registration process. ii. Registration of Procuring Authorities:- All the procuring entities should enter into the system by certifying their procurement needs by the government departments with authorized lettering. iii. Registration of contractors/suppliers/consultant s: - Registration of bidding parties in PMIS should be managed in such a way that they are bound to enter in the PMIS by written request with supporting documents rightly after they are registered in the firm/company registration authority. At the time of registration the current capabilities i.e. Manpower, equipments, financial resources and other technical capabilities should be registered along with. iv. Registration of Scheduled Banks: - Registration of Banks takes place on demand to the system by bidding parties (for presenting bid charge amount, bid security guaranty or performance guaranty during bidding process) or by procuring authorities (during payments). b. Electronic Bidding Invitation of bids, quotations, RFPs etc should be called officially through electronic bidding process. For doing so every procuring authority should keep online based centralized service package/software. Preparation of bid documents can be simplified by already prepared templates by administrator where necessary entries can be made pertaining to the unique details of that contract. Posting of bid notice to the system automatically generates email notification to every members registered to the system.
  • 3. A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013 pp 209-213 On receiving the notification, bidders can prepare his bid by providing his necessary entries of item rates and other required customization to the provided bid template. Also the bidding parties have to manage the appropriate bank to issue bid security guaranty which too, gets submitted through online in the PMIS system along with the bid. There is no need to mention the experience information, manpower and equipment capabilities and financial turnover etc. by the bidders on their own as these things are automatically stored and updated continuously in the system. Bidding by that time only indicates the willingness of the particular bidder. c. Bid Opening and Evaluation Opening of bid will not be a big deal after going online system of PMIS as there is no chance of manipulations and alterations as like in case of hard copy submission. So, it follows a regular office day process. Bidding period can also be reduced as online system gives a reduced effort on bid preparation. After opening of bids on the specified date and time, it can be automated in the PMIS system to send the abstract details of submitted bids to all the bidders as bid opening checklist (muchulka as we say). After opening of bids evaluation of the bid takes place. This section in the system is only accessible from the terminal of procuring authority (the buyer). Through this section the buyer generates the checklist of Requirement Details of the contract as indicated in the bid document already prepared and also the detail capability of the bidders though the PMIS central data warehouse. On comparison of both, system automatically indicates the eligible and ineligible bidders. After generating the Comparative Chart of proposed item rates in the BOQ provided by the eligible bidders along with the bid document template, Lowest Eligible Bidder is easily determined. The case of responsive and non responsive bidders can be omitted by filtering during the bidding process i.e. not allowing the non-responsive bids for particular contract during bidding. d. Contract Award and Monitoring After evaluation of bid, contract is awarded to the successful bidder through the system. Going through the contract award terminal by the buyer, contract agreement template document already created in the system is modified and customized in the required field only (i.e name and ID of contract, SCC, Priced BOQ, time of execution, milestones etc) which gets entered in the data warehouse. It can be utilized by the system for real-time tracking of contract. By the help of set data in the system (or say in the contract document) PMIS regulated and notifies the necessary information like milestones, time frame, guaranty times, and progress and suggests action to the concerned party. Mandatory actions cannot be modified or altered by none of the registered users (neither buyer nor the administrator). For example, if the milestone provisioned in the contract is not achieved, it suggests charging Liquidated Damage as in the contract document and it has to be done by the buyer otherwise payment order by the system does not proceed. Hence the chance of manipulations in the contract execution is highly reduced. e. Payments and Completion of Contract During or on completion of contract execution series of payment shall be released. The payments can be released to the contracting parties upon the billing of
  • 4. A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013 pp 209-213 executing works through the billing section of the PMIS accessible only to the buyer. Payment can be issued through the scheduled banks upon the online request order through the system. On completion of works or services, completion report is prepared with contract execution details and final payment is released. f. Updating the Contract Execution Report Since every action is preceded through the online based software package of PMIS connected to the central server it is gets automatically saved to server. On termination of contract, summary of contract execution, milestones, progress record, billing information and payment history is recorded by the system removing the other tracking histories. Compilation of such executive summaries of all contracts handled by a particular contracting party, yearly work experience and financial turnover can be easily generated by the system. Turnover Report of all the registered contracting parties can be published in the system in the yearly basis. Such reports are usable for future bidding actions and contract management. g. Updating the Increased Capability of Bidders The system should support the update of the increased capability of bidding parties. Increment in the resources, manpower, equipment and other capital assets etc should be updated with written request by the contracting parties on verification of the requested update with supporting documents (i.e. purchase receipt and departmental registration slip etc.) by the system administrator. 5. Advantages of PMIS over Traditional System Adoption of PMIS can make vast difference in the current procurement practices. There is very little or no chance of manipulations during the bidding process as well as contract execution. Following are some of the advantages. i. During bidding process, bidders cannot present the fake information of experience, turnover and equipment as in the current hard copy submission system since tracked factual data are given by the system server. ii. One equipment, manpower or vehicles allocated by bidder for particular contract in the bid can be made used for that contract only making unable to allocate for other contracts. iii. Opening and evaluation of bids is highly simplified work in PMIS. There is no chance of manipulations and alterations in the documents by evaluation team. Chance of unethical processing is reduced. iv. PMIS timely informs and alarms about the milestones, critical activities and time frames which we often forget during contract execution in our present practice. v. Every detail of all ongoing as well as completed contracts is tracked by the system server enabling the generation of status of contracts overally, particular to a contract or particular record of a contracting party. Helps in taking necessary action.
  • 5. A Journal on Rural Infrastructure Development, Society of Engineers for Rural Development, Nepal Vol.4 Issue 4, 2013 pp 209-213 vi. Since PMIS eliminated major alterations, it greatly reduces the cases of fraud and corruption as procurement is the major source of corruption. 6. Current Challenges of Adopting PMIS Every new starts faces some challenges. Adoption of PMIS too, will not be free from hindrances and obstacles at its start. Following are our challenges to go for adopting PMIS in public procurements. i. Reluctance of public authorities and political circle to adopt a smart and alteration –free system. ii. PMIS is fully online based. Lack of continuous electricity supply and internet connections every places of country. iii. Limitation of proper level of computer skills among public personnel’s and contracting parties. iv. Proper mechanism of data encryption in online system should be established. v. Without clearly stating in the procurement act and until detail regulations and guidelines to go for an online based system is made, it is difficult to adopt PMIS. 7. Emerging from the Challenges and Way Forward Despite a nos. of limitations and reluctance in our current system, we are bound to correct them as we are, now or then, bound to rise from our misery. It’s only we and our generation to make our environment a better place. If we sought for a dynamic and well mechanized system in our governance, the result is efficient service delivery with a lesser operation cost. Since procurement sector is a major area of corruption; a properly controlled, dynamic and smart system in our procurement practice is urgently needed. Procurement Management Information System plays a vital role in curbing corruption eliminating the chances of manipulations. PMIS does not make the procurement different but makes it proceed differently. The reduced effort, lesser chances in alterations, elimination of unhealthy competition, reduction in chances of undue benefits are the results PMIS provides. Many of the countries in the world including Bangladesh, whom we used to call a major country of procurement mishmash in South Asia, has already gone for complete online based procurement system. So, it’s our time to leap into a prosperous and mechanized country through procurement reforms and good-governance. It’s a crucial time that PPMO is undertaking the process of replacing of the current Public Procurement Act with a new one and is a better instance to quest for an efficient and smart system. The recent budget speech of FY 2070 has too, proclaimed its commitment for electronic government procurement i.e. e-GP system, which should be advocated to make happened in real. References i. World Bank Country Procurement Assessment Report (October 2002) ii. Asian Development Bank, “Curbing Corruption in Public Procurement in Asia and the Pacific, Progress and Challenges in 25 Countries”,2006 iii. E-GP Guidelines of Government of Peoples Republic of Bangladesh, 2009 iv. E-procurement Portal of DoLIDAR, Nepal,<https://www.edolidar.gov.np>