EXTENSION OF
KUALA LUMPUR
TWIN TOWER
PROCUREMENT
PROCUREMENT METHOD
Client’s requirements:
● Have full control of the design and able to introduce
changes from beginning till the completion
● Not interested in the daily dealing with too many
parties except the few key members of the project
● Complete project on time
● Minimum variation to the contract price during the
construction
RECOMMENDATION:
TRADITIONAL
PROCUREMENT
METHOD
TRADITIONAL PROCUREMENT METHOD
How does it work?
● Design phase to Construction phase
● Consultant teams are appointed at the
early stage to carry out the design process.
● Work will then tender out to the suitable
contractor only after design process is
completed.
● Client can involved in the design stage to
ensure it is within their requirements.
TRADITIONAL PROCUREMENT METHOD
TRADITIONAL PROCUREMENT METHOD
● TIME
1. Priority of this project fall into
quality and cost due to time is not
constraints.
2. Provides medium time risk to the
client because it requires longer
time frame for the Pre and Post
Tender Stage.
Duration of the project is 5
years
WHY THIS METHOD?
Time given is sufficient for
this Kuala Lumpur Twin
Tower Mega project
TRADITIONAL PROCUREMENT METHOD
1. Client can be involved in the design
process with the consultant team to
ensure that it is within the their
requirement.
2. Client able to make decision,
changes and provide instruction
during the designing stage with the
consultant team
Have full control of the design and able
to introduce changes from beginning till
the completion
WHY THIS METHOD?
Kuala Lumpur Twin Tower is a tourist area and
the landmark of Malaysia, quality of the work
must be taken into consideration.
● QUALITY
TRADITIONAL PROCUREMENT METHOD
Construction cost given is RM 1.2 billion.
1. This method is the most suitable as it provide lower cost risk to the
client due to the use of lump sum contract.
2. Any overcharging fees will be bear by contractor.
3. The amount is agreed between the parties in the contract before the
construction start.
4. Having a completed design of the project before tendering process
can provide the client certainty of the construction cost and the
design quality.
● COST
Minimum variation to the contract price during the construction
TRADITIONAL PROCUREMENT METHOD
1. The client only have to communicate with the consultant team
and only have contractual relationship with the main contractor
and consultants.
2. This form of procurement is also suitable for both experience
and inexperienced client because client can get advice from the
consultant team regarding to the project.
3. Subcontractors are dealt directly by the main contractor.
The client is not interest to deal with too many parties except the
few key members of the project.
CONCLUSION
TRADITIONAL METHOD
- Longer time frame but ensures better quality and cost delivered
- Does not need to deal with multiple parties but only key players
- Price certainty of construction cost unlike other methods
- For experience and inexperience clients unlike other methods
TENDER METHOD
TENDER METHOD
Client’s requirements:
● Reasonably transparent
selection process
● Eliminate potentially
non-performing contractor
RECOMMENDATION:
TWO STAGE
SELECTIVE TENDERING
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers
to submit their company
profiles for evaluation in the
Pre-qualification Form
2. A list of pre-qualified
contractors will then be
included in the final tender list
and invited to collect the
tender documents.
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers
to submit their company
profiles for evaluation in the
Pre-qualification Form
2. A list of pre-qualified
contractors will then be
included in the final tender list
and invited to collect the
tender documents.
Eliminate potentially
non-performing
contractors.
Reasonably transparent
selection process
SELECTIVE TENDERING
Tender Procedure
3. The list of pre-qualified contractors will
proceed on to the tendering process.
4. Evaluation process of tender
submissions from the list of pre-qualified
contractors takes place.
5. The most competent and suitable
contractor will be selected.
Quality
Assured
SELECTIVE TENDERING
Tender Procedure
6. The selected contractor will proceed on to the
negotiation process.
7. The price negotiation would take place until an
agreement is reached and both parties are satisfied,
leading them to enter into contract for construction
works to commence.
SELECTIVE TENDERING
(TWO STAGE)
Reasonably transparent selection process
Eliminate potentially non-performing contractor
Quality Assurance
CONTRACTUAL
ARRANGEMENT
CONTRACTUAL ARRANGEMENT
WHAT IS LUMP SUM CONTRACT ?
“Lump sum” price for all the work agreed before the work begin whereby
contractor is required to submit a total and global price.
Contractor is responsible for executing the complete contract work for a stated
total sum of money.
TYPE OF CONTRACT
LUMP SUM CONTRACT
CONTRACTUAL ARRANGEMENT
WHY LUMP SUM CONTRACT ?
Based on client’s condition and consideration :
1) Unfamiliar with construction industry
2) Not interested on dealing with too many parties
3) Minimum variation
TYPE OF CONTRACT
LUMP SUM CONTRACT
CONTRACTUAL ARRANGEMENT
PAM CONTRACT 2006 (WITH QUANTITIES)
WHY PAM CONTRACT 2006 ?
- private sector project
- traditional procurement method
FORM OF CONTRACT
CONTRACTUAL ARRANGEMENT
● TIME
● QUALITY
● HEALTH AND SAFETY
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● TIME
1. Clause 21.1
Possession of the site for execution of the works on the Date of Commencement
2. Article 7
Completion Date
3. Clause 22.1
Certificate of Non-Completion
4. Clause 22.2
Pay for the agreed Liquidated Damages (RM 250,000.00 a day)
5. Clause 15.2
Written notice for practically completed.
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● QUALITY
Clauses 6.0
Material, Goods and Workmanship To Conform to Description, Testing And
Inspection supports the requirement of good workmanship
Clauses 6.3
Inspection and testing
Clauses 6.5
Work not in accordance with the contract
Clauses 6.8
Warranties in respect of materials and goods
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● HEALTH AND SAFETY
A) GENERAL ITEMS IN PRELIMINARIES
B) EMPLOYEE’S SOCIAL SECURITY ACT 1969
C) WORKMEN’S COMPENSATION ACT 1952
D) PAM CONTRACT 2006 (WITH QUANTITIES)
E) OCCUPATIONAL SAFETY AND HEALTH 1994 ( OSHA 1994)
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONCLUSION
THANK YOU!
KENNETH TAN SIN KWANG 0322482
CHAN YI FUNG 0323057
LEE FONG YEN 0321976
LEE LIN HUI 0322797
LEONG LI JING 0323628
LEONG MIN HUI 0327596
ADELE LU KHAI SYN 0323151
LEW QUO MING 0322884
WONG JIA JING 0327221
YEAP PHAY SHIAN 0322243
YEE JYH LIN 0322408
THANK YOU!
KENNETH TAN SIN KWANG 0322482
CHAN YI FUNG 0323057
LEE FONG YEN 0321976
LEE LIN HUI 0322797
LEONG LI JING 0323628
LEONG MIN HUI 0327596
ADELE LU KHAI SYN 0323151
LEW QUO MING 0322884
WONG JIA JING 0327221
YEAP PHAY SHIAN 0322243
YEE JYH LIN 0322408

More Related Content

PPTX
Final pp1
PDF
Professional Practice I Assignment
PPSX
The big 5 saudi ppt slide batran
PDF
Types of Tender and their Process
PPTX
Mega project
PDF
Assignment - Report
PPT
Cpm ch 2tender
PDF
Final pp1
Professional Practice I Assignment
The big 5 saudi ppt slide batran
Types of Tender and their Process
Mega project
Assignment - Report
Cpm ch 2tender

What's hot (20)

PDF
Contract
PPTX
Tender & Tender Notice
PPTX
Measurement 4:presentation slides
DOC
gas pipe line project report.
PDF
Tender and tender document
PPTX
QUANTITY SURVEYING
PDF
Tendering-professional practices-jamia millia islamia
PDF
Professional practice 1
PPSX
Tendering Document for the Procurement of Works
DOCX
Project Management Report
PPTX
Basement remodel rev eh
PDF
Project management final report
PPTX
Estimating tender presentation
DOCX
Eco friendly electricity generating tiles project
PPTX
Tenders contract -arti
PPTX
Civil tenders and contracts spce
PDF
Michelle Simpson Assignment #2
PDF
CV- AMAL
PPTX
Professional practce
PPTX
Beach house construction desktop 02 29
Contract
Tender & Tender Notice
Measurement 4:presentation slides
gas pipe line project report.
Tender and tender document
QUANTITY SURVEYING
Tendering-professional practices-jamia millia islamia
Professional practice 1
Tendering Document for the Procurement of Works
Project Management Report
Basement remodel rev eh
Project management final report
Estimating tender presentation
Eco friendly electricity generating tiles project
Tenders contract -arti
Civil tenders and contracts spce
Michelle Simpson Assignment #2
CV- AMAL
Professional practce
Beach house construction desktop 02 29
Ad

Similar to Professional Practice I Assignment Slides (20)

DOCX
Pp1 group assignment
PDF
Pp1 report
PPTX
Pp1 group assignment presentation slides
DOCX
Professional Practice 1 Proposal Report
PDF
Pp1 assignment group 8
DOCX
Pp1 assignment
DOCX
Pp1 assignment
PDF
PP1 presentation
PDF
PP1 presentation
PPTX
DOCX
Pp 1-report-complete
DOCX
Pp1 final
DOCX
Professional Practice 1 Assignment
PDF
estimate procurement and contract in const.pdf
DOCX
Traditional procurement method
PPTX
Types of contracts
PPTX
PP1 assignment presentation slides
PDF
PP1 Tutorial 3 Presentation
PPTX
Types of Contract in Construction Management
PPTX
types-170309142854.pptx
Pp1 group assignment
Pp1 report
Pp1 group assignment presentation slides
Professional Practice 1 Proposal Report
Pp1 assignment group 8
Pp1 assignment
Pp1 assignment
PP1 presentation
PP1 presentation
Pp 1-report-complete
Pp1 final
Professional Practice 1 Assignment
estimate procurement and contract in const.pdf
Traditional procurement method
Types of contracts
PP1 assignment presentation slides
PP1 Tutorial 3 Presentation
Types of Contract in Construction Management
types-170309142854.pptx
Ad

More from ashleyyeap (20)

PDF
CSI JOURNAL cover page
PDF
CSI JOURNAL
PDF
Fm group assignment
PDF
Pp2 assignment-final
PDF
PP2 final account assignment calculations
DOCX
Fm august 2018 group assignment brief
PDF
Building Economics Assignment Report
PDF
Building Economics Preliminary Cost Appraisal
PDF
PP2 Seminar Presentation
PDF
Pp2 final account assignment excel
PDF
Pp2 assignment-final
PDF
Pp2 coursework 2 201808
PDF
Measurement Assignment
PDF
Professional Practice 1 Tutorial 3
PDF
Professional Practice 1 Tutorial 7
PDF
Estimating Assignment
PDF
Software Assignment
PDF
Management Science Assignment
PDF
People Dynamics Individual Assignment - Case Study
PDF
Building Services II Presentation Slides
CSI JOURNAL cover page
CSI JOURNAL
Fm group assignment
Pp2 assignment-final
PP2 final account assignment calculations
Fm august 2018 group assignment brief
Building Economics Assignment Report
Building Economics Preliminary Cost Appraisal
PP2 Seminar Presentation
Pp2 final account assignment excel
Pp2 assignment-final
Pp2 coursework 2 201808
Measurement Assignment
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 7
Estimating Assignment
Software Assignment
Management Science Assignment
People Dynamics Individual Assignment - Case Study
Building Services II Presentation Slides

Recently uploaded (20)

PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
RMMM.pdf make it easy to upload and study
PPTX
Presentation on HIE in infants and its manifestations
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PPTX
master seminar digital applications in india
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PPTX
Pharma ospi slides which help in ospi learning
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
Complications of Minimal Access Surgery at WLH
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
FourierSeries-QuestionsWithAnswers(Part-A).pdf
STATICS OF THE RIGID BODIES Hibbelers.pdf
RMMM.pdf make it easy to upload and study
Presentation on HIE in infants and its manifestations
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf
master seminar digital applications in india
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Final Presentation General Medicine 03-08-2024.pptx
human mycosis Human fungal infections are called human mycosis..pptx
Pharma ospi slides which help in ospi learning
VCE English Exam - Section C Student Revision Booklet
Complications of Minimal Access Surgery at WLH
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS

Professional Practice I Assignment Slides

  • 3. PROCUREMENT METHOD Client’s requirements: ● Have full control of the design and able to introduce changes from beginning till the completion ● Not interested in the daily dealing with too many parties except the few key members of the project ● Complete project on time ● Minimum variation to the contract price during the construction
  • 5. TRADITIONAL PROCUREMENT METHOD How does it work? ● Design phase to Construction phase ● Consultant teams are appointed at the early stage to carry out the design process. ● Work will then tender out to the suitable contractor only after design process is completed. ● Client can involved in the design stage to ensure it is within their requirements.
  • 7. TRADITIONAL PROCUREMENT METHOD ● TIME 1. Priority of this project fall into quality and cost due to time is not constraints. 2. Provides medium time risk to the client because it requires longer time frame for the Pre and Post Tender Stage. Duration of the project is 5 years WHY THIS METHOD? Time given is sufficient for this Kuala Lumpur Twin Tower Mega project
  • 8. TRADITIONAL PROCUREMENT METHOD 1. Client can be involved in the design process with the consultant team to ensure that it is within the their requirement. 2. Client able to make decision, changes and provide instruction during the designing stage with the consultant team Have full control of the design and able to introduce changes from beginning till the completion WHY THIS METHOD? Kuala Lumpur Twin Tower is a tourist area and the landmark of Malaysia, quality of the work must be taken into consideration. ● QUALITY
  • 9. TRADITIONAL PROCUREMENT METHOD Construction cost given is RM 1.2 billion. 1. This method is the most suitable as it provide lower cost risk to the client due to the use of lump sum contract. 2. Any overcharging fees will be bear by contractor. 3. The amount is agreed between the parties in the contract before the construction start. 4. Having a completed design of the project before tendering process can provide the client certainty of the construction cost and the design quality. ● COST Minimum variation to the contract price during the construction
  • 10. TRADITIONAL PROCUREMENT METHOD 1. The client only have to communicate with the consultant team and only have contractual relationship with the main contractor and consultants. 2. This form of procurement is also suitable for both experience and inexperienced client because client can get advice from the consultant team regarding to the project. 3. Subcontractors are dealt directly by the main contractor. The client is not interest to deal with too many parties except the few key members of the project.
  • 11. CONCLUSION TRADITIONAL METHOD - Longer time frame but ensures better quality and cost delivered - Does not need to deal with multiple parties but only key players - Price certainty of construction cost unlike other methods - For experience and inexperience clients unlike other methods
  • 13. TENDER METHOD Client’s requirements: ● Reasonably transparent selection process ● Eliminate potentially non-performing contractor
  • 15. SELECTIVE TENDERING Tender Procedure Pre-qualification Stage 1. Advertisement in newspaper to invite interested tenderers to submit their company profiles for evaluation in the Pre-qualification Form 2. A list of pre-qualified contractors will then be included in the final tender list and invited to collect the tender documents.
  • 16. SELECTIVE TENDERING Tender Procedure Pre-qualification Stage 1. Advertisement in newspaper to invite interested tenderers to submit their company profiles for evaluation in the Pre-qualification Form 2. A list of pre-qualified contractors will then be included in the final tender list and invited to collect the tender documents. Eliminate potentially non-performing contractors. Reasonably transparent selection process
  • 17. SELECTIVE TENDERING Tender Procedure 3. The list of pre-qualified contractors will proceed on to the tendering process. 4. Evaluation process of tender submissions from the list of pre-qualified contractors takes place. 5. The most competent and suitable contractor will be selected. Quality Assured
  • 18. SELECTIVE TENDERING Tender Procedure 6. The selected contractor will proceed on to the negotiation process. 7. The price negotiation would take place until an agreement is reached and both parties are satisfied, leading them to enter into contract for construction works to commence.
  • 19. SELECTIVE TENDERING (TWO STAGE) Reasonably transparent selection process Eliminate potentially non-performing contractor Quality Assurance
  • 21. CONTRACTUAL ARRANGEMENT WHAT IS LUMP SUM CONTRACT ? “Lump sum” price for all the work agreed before the work begin whereby contractor is required to submit a total and global price. Contractor is responsible for executing the complete contract work for a stated total sum of money. TYPE OF CONTRACT LUMP SUM CONTRACT
  • 22. CONTRACTUAL ARRANGEMENT WHY LUMP SUM CONTRACT ? Based on client’s condition and consideration : 1) Unfamiliar with construction industry 2) Not interested on dealing with too many parties 3) Minimum variation TYPE OF CONTRACT LUMP SUM CONTRACT
  • 23. CONTRACTUAL ARRANGEMENT PAM CONTRACT 2006 (WITH QUANTITIES) WHY PAM CONTRACT 2006 ? - private sector project - traditional procurement method FORM OF CONTRACT
  • 24. CONTRACTUAL ARRANGEMENT ● TIME ● QUALITY ● HEALTH AND SAFETY EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 25. CONTRACTUAL ARRANGEMENT ● TIME 1. Clause 21.1 Possession of the site for execution of the works on the Date of Commencement 2. Article 7 Completion Date 3. Clause 22.1 Certificate of Non-Completion 4. Clause 22.2 Pay for the agreed Liquidated Damages (RM 250,000.00 a day) 5. Clause 15.2 Written notice for practically completed. EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 26. CONTRACTUAL ARRANGEMENT ● QUALITY Clauses 6.0 Material, Goods and Workmanship To Conform to Description, Testing And Inspection supports the requirement of good workmanship Clauses 6.3 Inspection and testing Clauses 6.5 Work not in accordance with the contract Clauses 6.8 Warranties in respect of materials and goods EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 27. CONTRACTUAL ARRANGEMENT ● HEALTH AND SAFETY A) GENERAL ITEMS IN PRELIMINARIES B) EMPLOYEE’S SOCIAL SECURITY ACT 1969 C) WORKMEN’S COMPENSATION ACT 1952 D) PAM CONTRACT 2006 (WITH QUANTITIES) E) OCCUPATIONAL SAFETY AND HEALTH 1994 ( OSHA 1994) EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 29. THANK YOU! KENNETH TAN SIN KWANG 0322482 CHAN YI FUNG 0323057 LEE FONG YEN 0321976 LEE LIN HUI 0322797 LEONG LI JING 0323628 LEONG MIN HUI 0327596 ADELE LU KHAI SYN 0323151 LEW QUO MING 0322884 WONG JIA JING 0327221 YEAP PHAY SHIAN 0322243 YEE JYH LIN 0322408
  • 30. THANK YOU! KENNETH TAN SIN KWANG 0322482 CHAN YI FUNG 0323057 LEE FONG YEN 0321976 LEE LIN HUI 0322797 LEONG LI JING 0323628 LEONG MIN HUI 0327596 ADELE LU KHAI SYN 0323151 LEW QUO MING 0322884 WONG JIA JING 0327221 YEAP PHAY SHIAN 0322243 YEE JYH LIN 0322408