Extending Earned Value Methodology To Track
ScopeAnd Performance For Key Labour
Categories and Commodity Usage for Small To
Large Industrial Projects
Project	
  Controls	
  Expo	
  -­‐	
  31st	
  Oct	
  2012	
  
Twickenham	
  Stadium,	
  London	
  	
  
	
  
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
About the Speaker
Roland Horat, Managing Director of Supertech Project
Management (Australia) Pty Ltd. an international project
management consulting company.
Roland is a specialist in Earned Value (EVPM) Based
Project Management and Control systems.
Roland’s company has developed the EVENGINE range of
earned value based project control and reporting
software in compliance with international and industry
best practice. The software is featured at this Expo.
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
To illustrate the process, we draw on Supertech’s participation in the development and
maintenance of a number of industry projects such as:
Case Studies:
Jindal Steel and Power’s (JSPL)
12.5 MTA Steel Plant Project
Control System.
http://www.jindalsteelpower.com/
facilities/domestic/orissa/angul.aspx
We consider this to be a Large
Industrial Project (Mega Project).
Industrial Plants and
Refineries etc.
Commercial High Rise
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Case Study To Illustrate Coding Practice – JSPL Phase 1 (1.5 MTA) the work is divide into
controllable and trackable work packs:
Nine (9) Technology Based Work Packs:
1.  CGP - Coal to Gasification Plant
2.  LDP - Lime & Dolomite Plant
3.  DRI - Direct Reduced Iron Plant
4.  OXP - Oxygen, Nitrogen Plant
5.  PB - Process Boilers
6.  CAW - Coal Washery
7.  SMS - Steel Melt Shop
8.  SLC - Slab Caster
9.  PML - Plate Mill
How does this translate into a workable control system – the Software used?
•  The Work Packs are represented in the Control System as Projects.
•  Projects are collectively represented in the Master Schedule to L3 using Microsoft Project 2007,
with Units of Work and Material (Commodity) Usage held within the EVENGINE Project Control
Software
•  Projects are represented to L5 in Detailed Stand Alone Schedules using Primavera P6 Version 7
with assigned activity selected Labour & Non-Labour resources for daily weekly scheduling
purposes.
Eight (8) Supporting Infrastructure Work Packs:
1.  PWR - HV Power
2.  GDS - Gas Distribution System
3.  RMHS - Raw Material Handling System
4.  CTU - Central Utilities (Water Supply)
5.  CCV - Central Civil (Earthworks, Roads &
Drainage)
6.  HSE - Housing
7.  FGS - Liquid Fuel & Gas Storage
8.  CMA – Compressed Air Plant
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
The Master schedule forms the basis of the Report Period Control
And Tracking System For Units of Cost, Labour & Commodity
Usage to WBS Level 3. Where:
•  L1 = Project/Facility
•  L2 = Engineering, Procurement, Fabrication and Sub-facility
Construction
•  L3 = Trade Based Construction – Excavation, Concrete,
Structural Steel, Mechanical, Piping, Electrical &
Instrumentation, Pre-Commissioning & Commissioning Control
Units
The Detailed Stand Alone Schedule forms
the basis of the Day To Day Detailed
Activity Control System. Where:
•  L1 = Project/Facility
•  L2 = Engineering, Procurement,
Fabrication and Sub-facility
Construction
•  L3 & L4 = Sub-facilities Construction
Detail
•  L5 = Trade Based Sequential Activity
Execution (Resource Allocation)
Case Study - Master and Detailed Schedule Level Purpose
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Case Study - The Master Schedule > Project Control Software Link
•  Primary key used is the Project and Activity Unique
ID
•  Microsoft Project maintains all of the scheduling
information: Current and Baseline
•  EVENGINE refreshes by report period current and
baseline schedule data
•  EVENGINE holds
and maintains all
current and baseline
Earned Value Units
for Cost, Work and
Material
(Commodity)
Usage
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Project Control Data Requirements by Activity to undertake Earned Value Performance
Measurement (EVPM) and Cost Engineering Reporting:
Combined data requirements for cost,
work and material usage based
productivity Indicator analysis:
Mandated data fields are marked (Yes)
and optional marked (No).
Additional data requirements for Cost
Engineering:
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Key Data Coding Requirements For Reporting
•  The (WBS) Work Breakdown Structure code for defining the Scope of Work and for mapping
imported actual units of cost, work and material usage to WBS elements
•  The (CA) Control Account code for defining work packages (contractual lumps of work) and for
mapping imported actual units of cost, work and material usage to CA groupings of tasks
•  The (OBS) Organizational Breakdown Structure code for defining departmental and organizational
responsibility
•  The Stage/Phase code used group tasks into project development and approval gates mirroring the
development lifecycle
•  The Area/Facility code used to identify and group dispersed facilities for complex mega projects and
used to identify sub-facility work breakdown
•  The User Defined Fields 1 & 2 codes used to further group tasks for specific tracking and reporting
purposes
•  Resource Code to track and group labour and material with common characteristics across the project
Additional Cost Engineering Specific CA Coding for Type Classification
•  Awarded or Un-Awarded status – used for commercial and finance control
•  Commercial Type: Contract or Purchase Order – used for commercial and finance control
•  Committed or Un-committed status – used for finance control
To facilitate reporting and control the project the following activity and resource codes are required:
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Case Study - Project Codes For Managing Data:
CA - Control Accounts – Identifies
some 250 Contractors & Suppliers,
Code describes both facility, contract
number Description and Type.
OBS - Organizational
Breakdown Structure-
Identifies some 19
Departments
responsible for project
implementation and
control.
Stage/Phase -
identifies three
phases to the
project.
Area/Facility -
Identifies some 19
vertical technology
and common
horizontal areas and
facilities to the
project.
User Defined Code 1 – List
of some 292 Sub-facilities
User Defined Code 2 – lists
some 158 major contractors
and suppliers tracked for
the project.
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Case Study - Resource Codes for Managing Labour and Material (Commodity) Units
Resource Code – Lists some 25 labour and commodity codes being
tracked.
•  Step 1 - Decide on Key Labour and Commodities for Tracking
including their unit of measure
•  Step 2 - Define the code list
•  Step 3 - Assign code and BAC and EAC units to activities for
tracking and reporting
“LIST OF NIGP COMMODITY CODES” http://www.peelregion.ca/finance/purchasing/biddocs/vendapp/comcodes.pdf
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Application of Combined Filter Codes for Reporting
•  User Defined
1&2
•  Cost Account (CA)
•  WBS
•  OBS
•  Resource
•  Area/Facility
•  Project
•  Stage/Phase
Purpose of filters is to drill down and focus on selected data depending on the report requirements
Type of report are characterised by:
•  Contractor Reports
•  Commodity Specific Reports
•  Project Progress Reports
•  Financial Reports
•  Schedule Based Report
•  Multiple Filtering Options:
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Selecting and Grouping Filtered Data for Focusing Reports
User Defined 1&2
Cost Account (CA)
Task
OBS
Resource
Area/Facility
Stage/Phase
Project
Committed/Uncommitted
Awarded/Not Awarded
Purchase Order/Contract
Multiple Data Selection:
•  Metrics
•  Indicators
•  Predictors
Multiple Grouping Options:
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Project Wide Commodity Specific Time Displacement Specific % S-Curves
Representative Examples of Productivity Analysis Reports
•  Commodity Time displacement Curves
allows analysis of trade separation
•  Identification of congestion with
possible delay effects
•  Identification of acceleration
measures for early completion
for mechanical, Piping &
Electrical Disciplines
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
Project Wide Commodity Specific – Concrete & Steel S-Curves & Histograms
•  Commodity Concrete Placement -
Actual Versus Planned
•  Commodity Steel Erection with S-
curve in % Completion - Actual
Versus Planned
•  Other commodity curves would be
related to: Plate-work, Platforms,
Hand Rail, Mechanical Installation,
Piping Installation, Electrical Cable
Tray, Cable, Terminations,
Instrument Installation •  Used to assess period performance and feasibility of
production rates to completion
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
Project Wide Commodity Specific Budgeted Concrete By Facility
•  Identifies the allocation of concrete quantities for placement to contractors by facility
•  Percentage Distribution identifies over or under allocation of work to contractors
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
Project Wide Commodity Specific – Concrete – Remaining Work by Facility
•  Identify the remaining quantity of work to be completed by facility by contractor
•  Identifies over or under loading of contractors, used for redistribution of work
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
Project Wide Commodity Specific Concrete Remaining Quantity Period Targets and Placement Rates.
•  Used to analyse Contractor Performance against Baseline (Target) Values
•  Used to assess the feasibility of meeting remaining target quantities for remaining periods
•  Totals can be used to assess the requirement for consumables to be held in stock to sustain the work to
completion
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Productivity Analysis Reports
Using Filters for Facility Specific – Time Displacement Specific % S-Curves
•  Details the production history and planned work to completion by % and discipline
•  Identifies trade separation, congestion or acceleration
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Productivity Analysis Reports
Facility Specific – Concrete & Steel S-Curves & Histograms
•  Commodity Concrete Placement -
Actual Versus Planned
•  Commodity Steel Erection with S-
curve in % Completion - Actual
Versus Planned
•  Other commodity curves would be
related to: Plate-work, Platforms,
Hand Rail, Mechanical Installation,
Piping Installation, Electrical Cable
Tray, Cable, Terminations,
Instrument Installation.
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
Facility Specific – Production Reports
•  Contractor allocation of budgeted work for key
commodity groupings
•  Time phased Actual and Forecast to Completion
Quantities against baseline or target period
quantities for commodity based contracts
•  Data is used to set and track period actuals
against targets.
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
•  Productivity reports measure and benchmark
project performance against industry published
Key Performance Indicators [KPIs].
•  Benchmarking identifies where improvements
can be made to lower costs, increase
productivity and profitability.
•  Publications with Productivity Constants:
Representative Examples of Productivity Analysis Reports
Facility Specific – Commodity Specific Productivity Reports
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Representative Examples of Productivity Analysis Reports
•  Graph illustrating productivity
period and average rates over
time for comparison against
industry constants
•  Performance index period and
average over the life of the
project for specific
commodities.
 	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  	
  Copyright	
  @	
  2011.	
  All	
  rights	
  reserved	
  
Q & A
Conclusion
Contact Details - Local and Internationally
For Today Visit Our Stand

More Related Content

PDF
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
PDF
Session T2 - Best Practice Project Controls with EcoSys
PDF
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
PDF
M3 - An overview of High Speed 2
PDF
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
PDF
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
PDF
Project Controls Expo - 31st Oct 2012 - Accurate Management Reports on 1me, e...
PDF
Session T4 - Deliverables Management - A strategic Opportunity
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Session T2 - Best Practice Project Controls with EcoSys
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
M3 - An overview of High Speed 2
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
Session M6 - BIM –Building Information Modellingfood for thought -Chef Master...
Project Controls Expo - 31st Oct 2012 - Accurate Management Reports on 1me, e...
Session T4 - Deliverables Management - A strategic Opportunity

What's hot (20)

PDF
Session T6 - Artificial Intelligence Meets Project Controls
PDF
Session M1- The Challenges of Tracking Earned Value on The SV Scout Project
PDF
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
PDF
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
PDF
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
PPTX
Advanced Work Packaging - CCT Solutions at a Glance
PDF
Epc project interdepency and Work Flow- promo
PPTX
Epc projects and cad tools
PDF
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
PPSX
Why EPC
PDF
A Journey into the Digital World
PPTX
Advanced Work Packaging - Real Life Implementation
PDF
Construction Project Management Powerpoint Presentation Slides
PDF
Engineering & Construction 4.0 – A Digital pathway to a more profitable future
PDF
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
PDF
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
PDF
Promo_Epc project rule of credit and progress measurement
PDF
Advanced Work Packaging (AWP): An Illustration of the Mortar Concept(c)
PPTX
Advanced Work Packaging (AWP) - Reduction to Practice
Session T6 - Artificial Intelligence Meets Project Controls
Session M1- The Challenges of Tracking Earned Value on The SV Scout Project
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Advanced Work Packaging - CCT Solutions at a Glance
Epc project interdepency and Work Flow- promo
Epc projects and cad tools
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Why EPC
A Journey into the Digital World
Advanced Work Packaging - Real Life Implementation
Construction Project Management Powerpoint Presentation Slides
Engineering & Construction 4.0 – A Digital pathway to a more profitable future
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Think Differently when Executing Capital Projects by Sandy Vasser, formerly ...
Promo_Epc project rule of credit and progress measurement
Advanced Work Packaging (AWP): An Illustration of the Mortar Concept(c)
Advanced Work Packaging (AWP) - Reduction to Practice
Ad

Similar to Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To Track Scope And Performance For Key Labour Categories and Commodity Usage for Small To Large Industrial Projects By Roland Horat (20)

PPSX
Project network scheduling and S-curve
PDF
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
PDF
Project Controls Expo 18th Nov 2014 - Introduction and key note presentation ...
PDF
P6 brief
PDF
Presentation Classification Of Schedule Types
PPT
notes_Lecture7.ppt
PDF
Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...
PPT
Week 9-performance-management-1222266539427090-9
PDF
The final frontier
PDF
Infrastructure project and responsibility break down
PDF
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PDF
Data warehousing change in a challenging environment
PPT
EO notes Lecture 27 Project Management 2.ppt
PDF
Integrating Quality into Portfolio Management, PMI Silicon Valley Chapter Din...
PPTX
Power Point For Cmgt 410
PDF
Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What sh...
ODP
Tracking Changes and requirements in SAP Systems with UML
PDF
Adapting data warehouse architecture to benefit from agile methodologies
PDF
Paul Capello Cerner Health Conference
PDF
Paul Capello CHC 2010 Final
Project network scheduling and S-curve
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo 18th Nov 2014 - Introduction and key note presentation ...
P6 brief
Presentation Classification Of Schedule Types
notes_Lecture7.ppt
Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...
Week 9-performance-management-1222266539427090-9
The final frontier
Infrastructure project and responsibility break down
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
Data warehousing change in a challenging environment
EO notes Lecture 27 Project Management 2.ppt
Integrating Quality into Portfolio Management, PMI Silicon Valley Chapter Din...
Power Point For Cmgt 410
Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What sh...
Tracking Changes and requirements in SAP Systems with UML
Adapting data warehouse architecture to benefit from agile methodologies
Paul Capello Cerner Health Conference
Paul Capello CHC 2010 Final
Ad

More from Project Controls Expo (20)

PDF
National Grids Project Controls Journey – past, present and future
PDF
Case study in Company Project Controls Transformation By Rod Whiting - Region...
PDF
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
PDF
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
PDF
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
PDF
Managing the risk of change by "Simon White - Risk Management Consultant for ...
PDF
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
PDF
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
PDF
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
PDF
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
PDF
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
PDF
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
PDF
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
PDF
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
PDF
Governance and Assurance for Nationally Significant Infrastructure Projects b...
PDF
A review of whether interdependency exists in effective Project Control Metho...
PDF
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
PDF
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
PDF
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
PDF
Enterprise Project Management Solutions - Install and train, job done? by "Da...
National Grids Project Controls Journey – past, present and future
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
A review of whether interdependency exists in effective Project Control Metho...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Project Management Solutions - Install and train, job done? by "Da...

Recently uploaded (20)

PPTX
Introduction to Effective Communication.pptx
PPTX
Tablets And Capsule Preformulation Of Paracetamol
PPTX
Non-Verbal-Communication .mh.pdf_110245_compressed.pptx
PPTX
Relationship Management Presentation In Banking.pptx
PPTX
Project and change Managment: short video sequences for IBA
PPTX
Tour Presentation Educational Activity.pptx
PPTX
Impressionism_PostImpressionism_Presentation.pptx
PPTX
Introduction-to-Food-Packaging-and-packaging -materials.pptx
PPTX
English-9-Q1-3-.pptxjkshbxnnxgchchxgxhxhx
PDF
Tunisia's Founding Father(s) Pitch-Deck 2022.pdf
PPTX
BIOLOGY TISSUE PPT CLASS 9 PROJECT PUBLIC
DOCX
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
PPTX
Intro to ISO 9001 2015.pptx wareness raising
PPTX
nose tajweed for the arabic alphabets for the responsive
PPTX
S. Anis Al Habsyi & Nada Shobah - Klasifikasi Hambatan Depresi.pptx
PDF
Presentation1 [Autosaved].pdf diagnosiss
PPTX
Emphasizing It's Not The End 08 06 2025.pptx
PPTX
The spiral of silence is a theory in communication and political science that...
PDF
Parts of Speech Prepositions Presentation in Colorful Cute Style_20250724_230...
PPTX
Role and Responsibilities of Bangladesh Coast Guard Base, Mongla Challenges
Introduction to Effective Communication.pptx
Tablets And Capsule Preformulation Of Paracetamol
Non-Verbal-Communication .mh.pdf_110245_compressed.pptx
Relationship Management Presentation In Banking.pptx
Project and change Managment: short video sequences for IBA
Tour Presentation Educational Activity.pptx
Impressionism_PostImpressionism_Presentation.pptx
Introduction-to-Food-Packaging-and-packaging -materials.pptx
English-9-Q1-3-.pptxjkshbxnnxgchchxgxhxhx
Tunisia's Founding Father(s) Pitch-Deck 2022.pdf
BIOLOGY TISSUE PPT CLASS 9 PROJECT PUBLIC
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
Intro to ISO 9001 2015.pptx wareness raising
nose tajweed for the arabic alphabets for the responsive
S. Anis Al Habsyi & Nada Shobah - Klasifikasi Hambatan Depresi.pptx
Presentation1 [Autosaved].pdf diagnosiss
Emphasizing It's Not The End 08 06 2025.pptx
The spiral of silence is a theory in communication and political science that...
Parts of Speech Prepositions Presentation in Colorful Cute Style_20250724_230...
Role and Responsibilities of Bangladesh Coast Guard Base, Mongla Challenges

Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To Track Scope And Performance For Key Labour Categories and Commodity Usage for Small To Large Industrial Projects By Roland Horat

  • 1.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Extending Earned Value Methodology To Track ScopeAnd Performance For Key Labour Categories and Commodity Usage for Small To Large Industrial Projects Project  Controls  Expo  -­‐  31st  Oct  2012   Twickenham  Stadium,  London      
  • 2.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   About the Speaker Roland Horat, Managing Director of Supertech Project Management (Australia) Pty Ltd. an international project management consulting company. Roland is a specialist in Earned Value (EVPM) Based Project Management and Control systems. Roland’s company has developed the EVENGINE range of earned value based project control and reporting software in compliance with international and industry best practice. The software is featured at this Expo.
  • 3.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   To illustrate the process, we draw on Supertech’s participation in the development and maintenance of a number of industry projects such as: Case Studies: Jindal Steel and Power’s (JSPL) 12.5 MTA Steel Plant Project Control System. http://www.jindalsteelpower.com/ facilities/domestic/orissa/angul.aspx We consider this to be a Large Industrial Project (Mega Project). Industrial Plants and Refineries etc. Commercial High Rise
  • 4.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Case Study To Illustrate Coding Practice – JSPL Phase 1 (1.5 MTA) the work is divide into controllable and trackable work packs: Nine (9) Technology Based Work Packs: 1.  CGP - Coal to Gasification Plant 2.  LDP - Lime & Dolomite Plant 3.  DRI - Direct Reduced Iron Plant 4.  OXP - Oxygen, Nitrogen Plant 5.  PB - Process Boilers 6.  CAW - Coal Washery 7.  SMS - Steel Melt Shop 8.  SLC - Slab Caster 9.  PML - Plate Mill How does this translate into a workable control system – the Software used? •  The Work Packs are represented in the Control System as Projects. •  Projects are collectively represented in the Master Schedule to L3 using Microsoft Project 2007, with Units of Work and Material (Commodity) Usage held within the EVENGINE Project Control Software •  Projects are represented to L5 in Detailed Stand Alone Schedules using Primavera P6 Version 7 with assigned activity selected Labour & Non-Labour resources for daily weekly scheduling purposes. Eight (8) Supporting Infrastructure Work Packs: 1.  PWR - HV Power 2.  GDS - Gas Distribution System 3.  RMHS - Raw Material Handling System 4.  CTU - Central Utilities (Water Supply) 5.  CCV - Central Civil (Earthworks, Roads & Drainage) 6.  HSE - Housing 7.  FGS - Liquid Fuel & Gas Storage 8.  CMA – Compressed Air Plant
  • 5.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   The Master schedule forms the basis of the Report Period Control And Tracking System For Units of Cost, Labour & Commodity Usage to WBS Level 3. Where: •  L1 = Project/Facility •  L2 = Engineering, Procurement, Fabrication and Sub-facility Construction •  L3 = Trade Based Construction – Excavation, Concrete, Structural Steel, Mechanical, Piping, Electrical & Instrumentation, Pre-Commissioning & Commissioning Control Units The Detailed Stand Alone Schedule forms the basis of the Day To Day Detailed Activity Control System. Where: •  L1 = Project/Facility •  L2 = Engineering, Procurement, Fabrication and Sub-facility Construction •  L3 & L4 = Sub-facilities Construction Detail •  L5 = Trade Based Sequential Activity Execution (Resource Allocation) Case Study - Master and Detailed Schedule Level Purpose
  • 6.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Case Study - The Master Schedule > Project Control Software Link •  Primary key used is the Project and Activity Unique ID •  Microsoft Project maintains all of the scheduling information: Current and Baseline •  EVENGINE refreshes by report period current and baseline schedule data •  EVENGINE holds and maintains all current and baseline Earned Value Units for Cost, Work and Material (Commodity) Usage
  • 7.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Project Control Data Requirements by Activity to undertake Earned Value Performance Measurement (EVPM) and Cost Engineering Reporting: Combined data requirements for cost, work and material usage based productivity Indicator analysis: Mandated data fields are marked (Yes) and optional marked (No). Additional data requirements for Cost Engineering:
  • 8.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Key Data Coding Requirements For Reporting •  The (WBS) Work Breakdown Structure code for defining the Scope of Work and for mapping imported actual units of cost, work and material usage to WBS elements •  The (CA) Control Account code for defining work packages (contractual lumps of work) and for mapping imported actual units of cost, work and material usage to CA groupings of tasks •  The (OBS) Organizational Breakdown Structure code for defining departmental and organizational responsibility •  The Stage/Phase code used group tasks into project development and approval gates mirroring the development lifecycle •  The Area/Facility code used to identify and group dispersed facilities for complex mega projects and used to identify sub-facility work breakdown •  The User Defined Fields 1 & 2 codes used to further group tasks for specific tracking and reporting purposes •  Resource Code to track and group labour and material with common characteristics across the project Additional Cost Engineering Specific CA Coding for Type Classification •  Awarded or Un-Awarded status – used for commercial and finance control •  Commercial Type: Contract or Purchase Order – used for commercial and finance control •  Committed or Un-committed status – used for finance control To facilitate reporting and control the project the following activity and resource codes are required:
  • 9.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Case Study - Project Codes For Managing Data: CA - Control Accounts – Identifies some 250 Contractors & Suppliers, Code describes both facility, contract number Description and Type. OBS - Organizational Breakdown Structure- Identifies some 19 Departments responsible for project implementation and control. Stage/Phase - identifies three phases to the project. Area/Facility - Identifies some 19 vertical technology and common horizontal areas and facilities to the project. User Defined Code 1 – List of some 292 Sub-facilities User Defined Code 2 – lists some 158 major contractors and suppliers tracked for the project.
  • 10.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Case Study - Resource Codes for Managing Labour and Material (Commodity) Units Resource Code – Lists some 25 labour and commodity codes being tracked. •  Step 1 - Decide on Key Labour and Commodities for Tracking including their unit of measure •  Step 2 - Define the code list •  Step 3 - Assign code and BAC and EAC units to activities for tracking and reporting “LIST OF NIGP COMMODITY CODES” http://www.peelregion.ca/finance/purchasing/biddocs/vendapp/comcodes.pdf
  • 11.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Application of Combined Filter Codes for Reporting •  User Defined 1&2 •  Cost Account (CA) •  WBS •  OBS •  Resource •  Area/Facility •  Project •  Stage/Phase Purpose of filters is to drill down and focus on selected data depending on the report requirements Type of report are characterised by: •  Contractor Reports •  Commodity Specific Reports •  Project Progress Reports •  Financial Reports •  Schedule Based Report •  Multiple Filtering Options:
  • 12.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Selecting and Grouping Filtered Data for Focusing Reports User Defined 1&2 Cost Account (CA) Task OBS Resource Area/Facility Stage/Phase Project Committed/Uncommitted Awarded/Not Awarded Purchase Order/Contract Multiple Data Selection: •  Metrics •  Indicators •  Predictors Multiple Grouping Options:
  • 13.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Project Wide Commodity Specific Time Displacement Specific % S-Curves Representative Examples of Productivity Analysis Reports •  Commodity Time displacement Curves allows analysis of trade separation •  Identification of congestion with possible delay effects •  Identification of acceleration measures for early completion for mechanical, Piping & Electrical Disciplines
  • 14.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports Project Wide Commodity Specific – Concrete & Steel S-Curves & Histograms •  Commodity Concrete Placement - Actual Versus Planned •  Commodity Steel Erection with S- curve in % Completion - Actual Versus Planned •  Other commodity curves would be related to: Plate-work, Platforms, Hand Rail, Mechanical Installation, Piping Installation, Electrical Cable Tray, Cable, Terminations, Instrument Installation •  Used to assess period performance and feasibility of production rates to completion
  • 15.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports Project Wide Commodity Specific Budgeted Concrete By Facility •  Identifies the allocation of concrete quantities for placement to contractors by facility •  Percentage Distribution identifies over or under allocation of work to contractors
  • 16.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports Project Wide Commodity Specific – Concrete – Remaining Work by Facility •  Identify the remaining quantity of work to be completed by facility by contractor •  Identifies over or under loading of contractors, used for redistribution of work
  • 17.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports Project Wide Commodity Specific Concrete Remaining Quantity Period Targets and Placement Rates. •  Used to analyse Contractor Performance against Baseline (Target) Values •  Used to assess the feasibility of meeting remaining target quantities for remaining periods •  Totals can be used to assess the requirement for consumables to be held in stock to sustain the work to completion
  • 18.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Productivity Analysis Reports Using Filters for Facility Specific – Time Displacement Specific % S-Curves •  Details the production history and planned work to completion by % and discipline •  Identifies trade separation, congestion or acceleration
  • 19.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Productivity Analysis Reports Facility Specific – Concrete & Steel S-Curves & Histograms •  Commodity Concrete Placement - Actual Versus Planned •  Commodity Steel Erection with S- curve in % Completion - Actual Versus Planned •  Other commodity curves would be related to: Plate-work, Platforms, Hand Rail, Mechanical Installation, Piping Installation, Electrical Cable Tray, Cable, Terminations, Instrument Installation.
  • 20.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports Facility Specific – Production Reports •  Contractor allocation of budgeted work for key commodity groupings •  Time phased Actual and Forecast to Completion Quantities against baseline or target period quantities for commodity based contracts •  Data is used to set and track period actuals against targets.
  • 21.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   •  Productivity reports measure and benchmark project performance against industry published Key Performance Indicators [KPIs]. •  Benchmarking identifies where improvements can be made to lower costs, increase productivity and profitability. •  Publications with Productivity Constants: Representative Examples of Productivity Analysis Reports Facility Specific – Commodity Specific Productivity Reports
  • 22.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Representative Examples of Productivity Analysis Reports •  Graph illustrating productivity period and average rates over time for comparison against industry constants •  Performance index period and average over the life of the project for specific commodities.
  • 23.                                                                                                                                                                                  Copyright  @  2011.  All  rights  reserved   Q & A Conclusion Contact Details - Local and Internationally For Today Visit Our Stand