PROJECT
CONTROLS
PROCESSES
Jerry Klanac
Managing Director
PMA Consultants
Why do we need Project Controls?
• Owner always has limited financial
resources.
• Owner wants to get the most out of the
amounts of capital invested.
• Financial decision to execute a project
implies a given investment completed at a
given time…the classic “return on
investment model.”
• Owner wants to know of problems in such a
time to be able to take appropriate
corrective actions.
• In today’s business climate, “real time”
information is essential to make better
decisions.
Owner’s Perspective Slide 1 of 2
-2 -1 0 1 2 3 n - 1 n
$8m
$7m
$10m
$60m
$80m
$75m
$60m $60m
Capital investment of $25 million
over three year period .
Positive cash flows (revenue
streams) for “n” periods.
Return on Investment Model
Why do we need Project Controls?
• Return of Investment Model becomes
successful when:
– Estimated costs for capital outlays and
future cash flows are accurate.
– NPV (net present value) for future cash
flows is greater than NPV of capital
outlays.
– Project Controls efforts are needed to
ensure the actual capital outlays stay
within the bounds of the estimate used in
the Return on Investment Model. If cost
overruns or schedule delays occurs, it can
erode the financial benefit of the project.
Owner’s Perspective Slide 2 of 2
-2 -1 0 1 2 3 n - 1 n
$8m
$7m
$10m
$60m
$80m
$75m
$60m $60m
Capital investment of $25 million
over three year period .
Positive cash flows (revenue
streams) for “n” periods.
Return on Investment Model
Project Life Cycle
• Kerzner: “Every program, project or product has certain
phases of development known as life-cycle phases.”
• Project Management – A Systems Approach to Planning,
Scheduling and Controlling, Harold Kerzner, PhD, 10th Edition,
pg. 68
• Bennett: “Every project, not just those in construction
industry, goes through a series of identifiable phases,
wherein it is ‘born’, it matures, it carries through ‘old
age’ and it expires.”
• The Management of Construction – A Project Life Cycle
Approach, F. Lawrence Bennett, PE, PhD, pg. 7
Aka Project Management Process
Examples of Project Life Cycles
Oil & Gas Industry
ImplementationDefinitionFeasibilityConceptual01 02 03 04
Choose the right project Develop the project right Deliver the project right
Plan the work 
Start-up/
Close Out05
ExecuteDefinitionSelectAppraise01 02 03 04 Operate05
Work the Plan 
COMPANY A
COMPANY B
Detailed
Design
Comm.Constr.
Examples of Project Life Cycles
Pharma Industry Slide 1 of 2
Basic DesignPre-Justify
Front-end Loading
CAPITAL MANAGEMENT PROCESS
Plan the work 
Close Out
DeliverApproveDevelopAllocation01 02 03 04 Asses05
Work the Plan 
PROJECT MANAGEMENT PROCESS
01 02 03 04 05
Justify
Feasibility /
Concept Design
Examples of Project Life Cycles
Pharma Industry Slide 2 of 2
Feasibility Concept
Gate
(Capital Plan)
Preliminary
Design
Detailed Design
Construction
Startup
Commissioning
Qualification
Validation
Project Turnover
Gate
(Project Close)
Administrative
Close
FRONT-END PLANNING
EXECUTION
PROJECT CLOSURE
Project Planning & Control System
Kerzner Perspective
Source: Project Management – A Systems
Approach to Planning, Scheduling and Controlling,
Harold Kerzner, PhD, 10th Edition, pg. 413
Management
of Change
Management
Decision-making
Strategies, states of nature,
payoff tables
BudgetsSystem Reports
Time, cost, performance,
reliability, maintainability,
effectiveness
Time/Cost/
Performance
Tracking
Feedback
Network Scheduling
PERT/CPM
Goals/Objectives
System and company level
Work Descriptions
Specs, SOW, WBS
Master Detailed
Schedules
Change procedure, review &
approval of changes
Project Controls Process
Hollmann Perspective
Hallmarks of Good Project Controls Process
• Organization of data (structure)
• Ongoing cost and schedule data collection systems that is near “real-time”
• Establish appropriate baselines, with contingency, that considers possible effects of risks
– Project targeting is doable; scope of project is what is needed
• Application of earned value concepts
• Sufficient time for trend analysis and developing forecasts
– Going beyond reporting data, but also suggesting corrective actions
• Effective Reports/Graphics (use of dashboards)
Owner’s Project Control Specialist
View of Distribution of Time
Project Cost Forecasting Process
Theoretical Best Practice
Project
Schedule
Update
Contractor
Progress
Reports
Contractor
Cost
Reports
Project
Accounting
Change
Management
System
Part of Ongoing Project
Controls Function on Project;
Sub-Processes Interlinked
Initial Cost
Baseline
Approved
Change Orders
Current Cost
Baseline
Cost Forecast
Based on
Above Analyses
Vendor Invoices
Contractor Invoices
Payroll (timesheet systems)
Project Purchasing (POs) &
Contract Awards
Resource Use During
Reporting Period
Starting Point
for All Analysis
Deviations that
become trends
Variation
Analysis
Trend
Analysis
Review
Actual Costs
Review
Committed
Costs
Earned
Value
Analysis
THANK YOU
Jerry Klanac
Managing Director
PMA Consultants
info@pmaconsultants.com

More Related Content

PPTX
Project Cost Management
PPTX
Project Initiation Document
PPTX
Project management
PPTX
Project Risk Management
PPTX
project management concepts
PPTX
Project Management Process and Its Phases
PPT
Project risk management
PPT
Project Management Overview
Project Cost Management
Project Initiation Document
Project management
Project Risk Management
project management concepts
Project Management Process and Its Phases
Project risk management
Project Management Overview

What's hot (20)

PPTX
Real example of PMO deployment
PPT
PMI-RMP Exam Prep Presentation
PDF
Session - 8 Everything about PgMP & PfMP Certifications
PDF
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
PDF
1_PMI-RMP_Project Risk Management Plan
PPT
Churrasco da GP19!
PDF
PMP Lecture 1: Introduction to Project Management
PPTX
Project Management
PPTX
Evolution of project management
PPTX
Presentation on Project Risk Management
PDF
PMP PMBOK 6th
PPTX
Effective project management skills
PPT
Project Manangement Introduction
PDF
Exploration of risks and risk management in construction project delivery
PDF
PMP Lecture 3: Project Management Processes
PPTX
Project Management Best Practices - Tips and Techniques
PDF
Introduction to contract management
PPTX
11.1 Plan Risk Management
PDF
Project Management Framework
Real example of PMO deployment
PMI-RMP Exam Prep Presentation
Session - 8 Everything about PgMP & PfMP Certifications
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
1_PMI-RMP_Project Risk Management Plan
Churrasco da GP19!
PMP Lecture 1: Introduction to Project Management
Project Management
Evolution of project management
Presentation on Project Risk Management
PMP PMBOK 6th
Effective project management skills
Project Manangement Introduction
Exploration of risks and risk management in construction project delivery
PMP Lecture 3: Project Management Processes
Project Management Best Practices - Tips and Techniques
Introduction to contract management
11.1 Plan Risk Management
Project Management Framework
Ad

Similar to Project Controls Processes (20)

PPT
Capitalbudgeting
PPTX
PETROLEUM PROJECT MANAGEMENT COURSE PART ONE.pptx
PPT
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
PPT
Project Mgt.- (Mod)..ppt
PPTX
Capital Budgeting
PDF
Mining Project Management Systems: Driving Predictable Project Outcomes
PPT
L 12 capital budgeting
PPT
Project Intro
DOCX
340Capital BudgetingTechniquesCertainty and Risk.docx
PPT
LavaCon Best Practices For Multiple Technical Projects V1R2
PPTX
Chapter iii capital budget
PPT
Capital Budgeting
PPT
Capital budgeting
PDF
Project Execution in Changing Times - Focus on the Essentials
PPT
02_lecture 8.ppt
PDF
Value chain analysis 4
PPTX
Project Costs, Budgeting and Appraisal
PPTX
Project management- Operation Management
PPTX
Practitioner’s Guide Building and Sustaining an Effective IT Demand Managemen...
DOCX
This task contains portions of material that were originally submi.docx
Capitalbudgeting
PETROLEUM PROJECT MANAGEMENT COURSE PART ONE.pptx
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
Project Mgt.- (Mod)..ppt
Capital Budgeting
Mining Project Management Systems: Driving Predictable Project Outcomes
L 12 capital budgeting
Project Intro
340Capital BudgetingTechniquesCertainty and Risk.docx
LavaCon Best Practices For Multiple Technical Projects V1R2
Chapter iii capital budget
Capital Budgeting
Capital budgeting
Project Execution in Changing Times - Focus on the Essentials
02_lecture 8.ppt
Value chain analysis 4
Project Costs, Budgeting and Appraisal
Project management- Operation Management
Practitioner’s Guide Building and Sustaining an Effective IT Demand Managemen...
This task contains portions of material that were originally submi.docx
Ad

More from PMA Consultants (20)

PDF
Practical Application of Value Engineering in Capital Projects
PDF
Project Cost & Schedule Integration Lessons Learnt
PDF
PANDEMIC RESILIENTSCHOOLS
PDF
BioPharma Projects: Essentials in Project Controls
PDF
How to Implement a Project Management Information System
PDF
Top Five Metrics for Measuring Schedule Reliability
PDF
What are the disadvantages of Gantt charts?
PDF
BIM and VDC for Megaproject Construction Projects
PDF
Setting up Filters & Layouts in P6
PDF
How to Choose a Project Delivery Method
PDF
Risk Management Processes from Jerry Klanac
PDF
Work Breakdown Structure Planning in NetPoint
PDF
How to Import/Export a Schedule between NetPoint and Microsft Excel
PDF
Smarter Planning with Microsoft Excel
PDF
In Pursuit of Reliable Schedules
PDF
Leveraging NetPoint & Excel for Template-Based Project Planning
PDF
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
PDF
The Value of Project Risk Management
PDF
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
PDF
P6 tips tricks-client
Practical Application of Value Engineering in Capital Projects
Project Cost & Schedule Integration Lessons Learnt
PANDEMIC RESILIENTSCHOOLS
BioPharma Projects: Essentials in Project Controls
How to Implement a Project Management Information System
Top Five Metrics for Measuring Schedule Reliability
What are the disadvantages of Gantt charts?
BIM and VDC for Megaproject Construction Projects
Setting up Filters & Layouts in P6
How to Choose a Project Delivery Method
Risk Management Processes from Jerry Klanac
Work Breakdown Structure Planning in NetPoint
How to Import/Export a Schedule between NetPoint and Microsft Excel
Smarter Planning with Microsoft Excel
In Pursuit of Reliable Schedules
Leveraging NetPoint & Excel for Template-Based Project Planning
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
The Value of Project Risk Management
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
P6 tips tricks-client

Recently uploaded (20)

PPTX
TCoE_IT_Concrete industry.why is it required
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
Project Management Methods PERT-and-CPM.pptx
PDF
Organisational Behaviour And it's concepts
PDF
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
PDF
40.-Rizal-And-Philippine-Identity-Formation.pdf
PPTX
Mangeroal Finance for Strategic Management
PDF
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
PDF
The-Power-of-Communication (1).pdf......
PPTX
Empowering Project Management Through Servant Leadership - PMI UK.pptx
PPTX
Strategic Plan 2023-2024 Presentation.pptx
PPTX
Press Release Importance & Structure.pptx
PDF
Contemporary management and it's content
PDF
Case study -Uber strategic plan and management
PPTX
MY GOLDEN RULES la regla de oro jhonatan requena
PPTX
Chapter Three for international political
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
Effective_communication._(strategy).pptx
PPTX
Five S Training Program - Principles of 5S
PPTX
Chapter One an overview of political economy
TCoE_IT_Concrete industry.why is it required
_ISO_Presentation_ISO 9001 and 45001.pptx
Project Management Methods PERT-and-CPM.pptx
Organisational Behaviour And it's concepts
CHAPTER 15- Manageement of Nursing Educational Institutions- Staffing and st...
40.-Rizal-And-Philippine-Identity-Formation.pdf
Mangeroal Finance for Strategic Management
Timeless Leadership Principles from History’s Greatest Figures by Alfonso Ken...
The-Power-of-Communication (1).pdf......
Empowering Project Management Through Servant Leadership - PMI UK.pptx
Strategic Plan 2023-2024 Presentation.pptx
Press Release Importance & Structure.pptx
Contemporary management and it's content
Case study -Uber strategic plan and management
MY GOLDEN RULES la regla de oro jhonatan requena
Chapter Three for international political
Human Resource Management | Introduction,Meaning and Definition
Effective_communication._(strategy).pptx
Five S Training Program - Principles of 5S
Chapter One an overview of political economy

Project Controls Processes

  • 2. Why do we need Project Controls? • Owner always has limited financial resources. • Owner wants to get the most out of the amounts of capital invested. • Financial decision to execute a project implies a given investment completed at a given time…the classic “return on investment model.” • Owner wants to know of problems in such a time to be able to take appropriate corrective actions. • In today’s business climate, “real time” information is essential to make better decisions. Owner’s Perspective Slide 1 of 2 -2 -1 0 1 2 3 n - 1 n $8m $7m $10m $60m $80m $75m $60m $60m Capital investment of $25 million over three year period . Positive cash flows (revenue streams) for “n” periods. Return on Investment Model
  • 3. Why do we need Project Controls? • Return of Investment Model becomes successful when: – Estimated costs for capital outlays and future cash flows are accurate. – NPV (net present value) for future cash flows is greater than NPV of capital outlays. – Project Controls efforts are needed to ensure the actual capital outlays stay within the bounds of the estimate used in the Return on Investment Model. If cost overruns or schedule delays occurs, it can erode the financial benefit of the project. Owner’s Perspective Slide 2 of 2 -2 -1 0 1 2 3 n - 1 n $8m $7m $10m $60m $80m $75m $60m $60m Capital investment of $25 million over three year period . Positive cash flows (revenue streams) for “n” periods. Return on Investment Model
  • 4. Project Life Cycle • Kerzner: “Every program, project or product has certain phases of development known as life-cycle phases.” • Project Management – A Systems Approach to Planning, Scheduling and Controlling, Harold Kerzner, PhD, 10th Edition, pg. 68 • Bennett: “Every project, not just those in construction industry, goes through a series of identifiable phases, wherein it is ‘born’, it matures, it carries through ‘old age’ and it expires.” • The Management of Construction – A Project Life Cycle Approach, F. Lawrence Bennett, PE, PhD, pg. 7 Aka Project Management Process
  • 5. Examples of Project Life Cycles Oil & Gas Industry ImplementationDefinitionFeasibilityConceptual01 02 03 04 Choose the right project Develop the project right Deliver the project right Plan the work  Start-up/ Close Out05 ExecuteDefinitionSelectAppraise01 02 03 04 Operate05 Work the Plan  COMPANY A COMPANY B
  • 6. Detailed Design Comm.Constr. Examples of Project Life Cycles Pharma Industry Slide 1 of 2 Basic DesignPre-Justify Front-end Loading CAPITAL MANAGEMENT PROCESS Plan the work  Close Out DeliverApproveDevelopAllocation01 02 03 04 Asses05 Work the Plan  PROJECT MANAGEMENT PROCESS 01 02 03 04 05 Justify Feasibility / Concept Design
  • 7. Examples of Project Life Cycles Pharma Industry Slide 2 of 2 Feasibility Concept Gate (Capital Plan) Preliminary Design Detailed Design Construction Startup Commissioning Qualification Validation Project Turnover Gate (Project Close) Administrative Close FRONT-END PLANNING EXECUTION PROJECT CLOSURE
  • 8. Project Planning & Control System Kerzner Perspective Source: Project Management – A Systems Approach to Planning, Scheduling and Controlling, Harold Kerzner, PhD, 10th Edition, pg. 413 Management of Change Management Decision-making Strategies, states of nature, payoff tables BudgetsSystem Reports Time, cost, performance, reliability, maintainability, effectiveness Time/Cost/ Performance Tracking Feedback Network Scheduling PERT/CPM Goals/Objectives System and company level Work Descriptions Specs, SOW, WBS Master Detailed Schedules Change procedure, review & approval of changes
  • 10. Hallmarks of Good Project Controls Process • Organization of data (structure) • Ongoing cost and schedule data collection systems that is near “real-time” • Establish appropriate baselines, with contingency, that considers possible effects of risks – Project targeting is doable; scope of project is what is needed • Application of earned value concepts • Sufficient time for trend analysis and developing forecasts – Going beyond reporting data, but also suggesting corrective actions • Effective Reports/Graphics (use of dashboards)
  • 11. Owner’s Project Control Specialist View of Distribution of Time
  • 12. Project Cost Forecasting Process Theoretical Best Practice Project Schedule Update Contractor Progress Reports Contractor Cost Reports Project Accounting Change Management System Part of Ongoing Project Controls Function on Project; Sub-Processes Interlinked Initial Cost Baseline Approved Change Orders Current Cost Baseline Cost Forecast Based on Above Analyses Vendor Invoices Contractor Invoices Payroll (timesheet systems) Project Purchasing (POs) & Contract Awards Resource Use During Reporting Period Starting Point for All Analysis Deviations that become trends Variation Analysis Trend Analysis Review Actual Costs Review Committed Costs Earned Value Analysis
  • 13. THANK YOU Jerry Klanac Managing Director PMA Consultants info@pmaconsultants.com