This document summarizes a project to construct a spectrophotometer. It lists the activities required and their durations, predecessors, resource needs, and costs. It constructs a network diagram and identifies critical paths. Time and cost are analyzed through crashing activities on the critical paths. The optimal completion time is 19 days at a cost of 14718 Birr. Resource leveling is also discussed to smooth resource usage before time crashing.