Scheduling Problems
Complete the following problems covering project scheduling
methods.
1. Put the following project management activities in order, by
defining immediate predecessors by placing one or more letters
in the column labeled “Immediate predecessor”. One of them
has been done for you.
Activity
Immediate predecessor
a) Calculate durations along all project paths
b) Calculate Te
c) Define immediate predecessors
h
d) Develop WBS
e) Draw a network diagram
f) Estimate task durations
g) Find the critical paths
h) Generate a complete, detailed task list
i) Identify project objectives
j) Write project scope statement
2. Draw network diagram for the following list of activities and
their immediate predecessors. Draw start and end nodes.
Activity
Immediate predecessor
A
--
B
--
C
A, B
D
C
E
C
F
D
G
E
H
F, G
I
C
3. Given the following detailed task list, draw a network
diagram, including starting and ending nodes.
Task
Immediate predecessor
A
--
B
A
C
A
D
B
E
C
F
D, E
4. Identify all paths and their summed durations from the
following detailed task list.
Task
Estimated duration
Immediate Predecessors
A-define info req
2 wks
-
B- analyze existing infrastruc
1.5 wks
-
C-define network req
1 wk.
B
D-design database
3 wks.
A
E-design network
2.5 wks.
C
F-implement
7 wks.
D, E
G-test
4 wks.
F
H-document database
1 wk.
D
I-user documentation
2 wks.
C
5. What is/are the critical path(s) amongst the following paths
through a project?
Path 1: A-B-D = 8.5 mos.
Path 2: B-C-I-J = 10 mos.
Path 3: A-B-E = 5.5 mos.
Path 4: B-F-G-J = 12 mos.
6. What is the shortest possible completion time for a project,
given the following paths through a project from start to finish?
A-B-D-F = 14 weeks
A-G = 22 weeks
A-C-H-I-J = 19 weeks
7. Identify all non-critical activities in the project with the
following paths:
A-B-C = 22 weeks
B-J-K = 18 weeks
A-B-D-E = 22 weeks
A-B-I = 14 weeks
B-L = 20 weeks
8. Identify all non-critical activities for a project with the
following paths
A-B-C = 10 days
A-B-D = 8 days
A-B-E-F = 8 days
A-B-G = 9 days
9. Develop an early start early finish (ES/EF) schedule for the
following project.
Activity
Duration
Predecessor
ES
EF
A
Develop specifications
2 wks
B
Design
4
A
C
Documentation
5
A
D
Implementation
8
B, C
E
Testing
4
D
10. Develop an early start, early finish (ES/EF) schedule for the
following project.
Activity
Duration
Predecessor
ES
EF
A
Develop specifications
6 wks
B
Design
5 wks
A
C
User Documentation
7 wks
A
D
Implementation
11 wks
B, C
E
Acceptance Testing
8 wks
D
F
Develop marketing literature
8 wks
A
G
Technical documentation
7 wks
B, C, F
PAGE
3
Example Scheduling Problem 1 v3
Before we can schedule a project, we will need to have done the
following, in order:
- Identify project objectives
- Write project scope statement
- Develop a WBS
- Generate a complete detailed task list
The above can be considered progressive elaboration of scope,
And then we need to:
- Define immediate predecessors
If we do all of these things, we can then define a network
diagram that illustrates the interrelationship among activities,
and the various paths throughout the project.
Before we can develop a schedule, using the critical path
method, we also have to:
- Estimate task durations
The three (3) inputs to using the critical path method for
scheduling are, therefore, (a) develop a detailed activity list
with (b) immediate predecessors and (c) estimated task
durations.
What I am going to show you now is how to develop a project
schedule, in the following basic steps:
- Draw a network diagram
- Calculate durations along all project paths
- Find the critical path(s)
- Calculate Te
1. Draw network diagram for the following list of activities and
their immediate predecessors. Draw start and end nodes. The
project is to put a consulting company’s marketing plan on the
Internet. (Olson 2004, p. 207 #12).
Activity Immediate predecessor
A none
B none
C D
D A
E A, B
F A, B
G E, F
H C
I C, G
J H, I
K J
L K
( See Network Diagram on Next)
2. Identify all paths from the network diagram above.
Paths
Path 1 – A-D-C-H-J-K-L
Path 2 – A-D-C-I-J-K-L
Path 3 – A-E-G-I-J-K-L
Path 4 – A-F-G-I-J-K-L
Path 5 – B-E-G-I-J-K-L
Path 6 – B-F-G-I-J-K-L
2. Identify all paths and their summed durations from the
following
detailed task list.
Activity
Predecessor(s) Duration
A-obtain your boss’s approval of your plan
none 8 days
B-obtain budget approval
none 12 days
C-obtain systems development approval D
10 days
D-develop user specifications A
1 day
E-obtain a marketing program from mktg A, B
120 days
F-obtain a mktg program from consultant A, B
60 days
G-review and select mktg program E,
F 5 days
H-perform systems dev of module contents
C 80 days
I-design system interface C,
G 50 days
J-review and approve systems development H,
I 5 days
K-test prototype
J 10 days
L-revision and final systems development K
20 days
Path = Summed duration
Path 1 – A-D-C-H-J-K-L = 8+1+10+80+5+10+20 = 19 +
80 + 35 = 134 days
Path 2 – A-D-C-I-J-K-L = 19 + 50 + 35 = 104 days
Path 3 – A-E-G-I-J-K-L = 8 + 120 + 5 + 50 + 35 = 218
days
Path 4 – A-F-G-I-J-K-L = 8 + 60 + 5 + 50 + 35 = 158
days
Path 5 – B-E-G-I-J-K-L = 12+120+5+50+35 = 222 days
Path 6 – B-F-G-I-J-K-L = 222 – 120 + 60 = 162 days
3. What is/are the critical path(s) from the paths above?
Path 5 – B-E-G-I-J-K-L = 12+120+5+50+35 = 222 days
4. What is the shortest possible completion time for the project,
Te?
222 days
5. Identify all non-critical activities in the project:
Activities A, C, D, and H do not fall on the critical path.
6. Develop an early start, early finish (ES/EF) schedule for the
following project.
Activity
Predecessor
Duration
ES
EF
A
obtain your boss’s approval of your plan
none
8
0
8
B
obtain budget approval
none
12
0
12
C
obtain systems development approval
D
10
9
19
D
develop user specifications
A
1
8
9
E
obtain a marketing program from mktg
A, B
120
12
132
F
obtain a mktg program from consultant
A, B
60
12
72
G
review and select mktg program
E, F
5
132
137
H
perform systems dev of module contentS
C
80
19
99
I
design system interface
C, G
50
137
187
J
review and approve systems development
H, I
5
187
192
K
test prototype
J
10
192
202
L
revision and final systems development
K
20
202
222
Example Problem - Network Diagram :

More Related Content

PPTX
actitvity_scheduling ppt for activity planning
DOCX
Critical Path MethodIntroductionOnce you have the network diag.docx
PDF
Project Management dksfjhksjdhfwfjsd.pdf
PPTX
PertGanttchart
PPTX
CPM NETWORK
PPTX
Critical Path(Re-visited)
PPT
Project Time Management
DOCX
Hospital Management System Network Diagram
actitvity_scheduling ppt for activity planning
Critical Path MethodIntroductionOnce you have the network diag.docx
Project Management dksfjhksjdhfwfjsd.pdf
PertGanttchart
CPM NETWORK
Critical Path(Re-visited)
Project Time Management
Hospital Management System Network Diagram

Similar to Scheduling Problems Complete the following problems covering pro.docx (20)

PDF
PPTX
Software Project Scheduling Diagrams
PPTX
Lec 9 & 10 chapter 5 project scheduling
PDF
Unit.6. network analysis with cpm and pert
PDF
Lecture - Project, Planning and Control.pdf
PPTX
PPTX
Primavera Project Management P6 Course session 4
PPTX
PERT-CPM PPT.pptx
PPTX
Scheduling_09.pptx
PPT
06 project time management
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPTX
Pert cpm SIDDANNA M BALAPGOL
PPTX
Methods for critical path method and numerical
PPTX
Software Engineering and Project Management - Activity Planning
PPTX
Pert analysis
PPTX
Program Evalution and Review Rechnical Path Method.pptx
PPTX
PM-Problems.pptx
PPTX
Unit 3 PERT.pptx in related to supply chain
PPTX
Week-4 GDPPD-project planning ad design pattern.pptx
PPTX
Time --updated 60b084af4f5af-
Software Project Scheduling Diagrams
Lec 9 & 10 chapter 5 project scheduling
Unit.6. network analysis with cpm and pert
Lecture - Project, Planning and Control.pdf
Primavera Project Management P6 Course session 4
PERT-CPM PPT.pptx
Scheduling_09.pptx
06 project time management
PROJECT-SCHEDULING-pptx.pptx
Pert cpm SIDDANNA M BALAPGOL
Methods for critical path method and numerical
Software Engineering and Project Management - Activity Planning
Pert analysis
Program Evalution and Review Rechnical Path Method.pptx
PM-Problems.pptx
Unit 3 PERT.pptx in related to supply chain
Week-4 GDPPD-project planning ad design pattern.pptx
Time --updated 60b084af4f5af-
Ad

More from kenjordan97598 (20)

DOCX
You are the Nursing Director for the medical-surgical area of a .docx
DOCX
You are the newly appointed director of the Agile County Airport.docx
DOCX
You are working on an address book database with a table called Cont.docx
DOCX
You are the new Security Manager for a small bank in Iowa. They are .docx
DOCX
You are working in a rural Family Planning Health clinic and a 16 y.docx
DOCX
You are working in a family practice when your newly diagnosed T.docx
DOCX
You are working for the Chief of Staff (CoS) for a newly elected Gov.docx
DOCX
You are working at Johnson and Cohen law firm and have recently .docx
DOCX
You are working for a community counseling agency, and you are taske.docx
DOCX
You are working as the software tester for a big enterprise comp.docx
DOCX
You are working as HelpDesk Support for an organization where your u.docx
DOCX
You are working as an APRN in your local primary care office. Th.docx
DOCX
You are the new Public Information Officer (PIO) assigned by the.docx
DOCX
You are welcome to go to the San Diego Zoo any time you would li.docx
DOCX
You are visiting one of your organization’s plants in a poor nation..docx
DOCX
You are to write a four-page (typed, double-spaced) essay addressing.docx
DOCX
You are to write a 7-page Biographical Research Paper of St Franci.docx
DOCX
You are to write a 1050 to 1750 word literature review (in a.docx
DOCX
You are to take the uploaded assignment and edit it. The title shoul.docx
DOCX
You are to use a topic for the question you chose.WORD REQUIRE.docx
You are the Nursing Director for the medical-surgical area of a .docx
You are the newly appointed director of the Agile County Airport.docx
You are working on an address book database with a table called Cont.docx
You are the new Security Manager for a small bank in Iowa. They are .docx
You are working in a rural Family Planning Health clinic and a 16 y.docx
You are working in a family practice when your newly diagnosed T.docx
You are working for the Chief of Staff (CoS) for a newly elected Gov.docx
You are working at Johnson and Cohen law firm and have recently .docx
You are working for a community counseling agency, and you are taske.docx
You are working as the software tester for a big enterprise comp.docx
You are working as HelpDesk Support for an organization where your u.docx
You are working as an APRN in your local primary care office. Th.docx
You are the new Public Information Officer (PIO) assigned by the.docx
You are welcome to go to the San Diego Zoo any time you would li.docx
You are visiting one of your organization’s plants in a poor nation..docx
You are to write a four-page (typed, double-spaced) essay addressing.docx
You are to write a 7-page Biographical Research Paper of St Franci.docx
You are to write a 1050 to 1750 word literature review (in a.docx
You are to take the uploaded assignment and edit it. The title shoul.docx
You are to use a topic for the question you chose.WORD REQUIRE.docx
Ad

Recently uploaded (20)

PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PPTX
master seminar digital applications in india
PDF
O7-L3 Supply Chain Operations - ICLT Program
PDF
Classroom Observation Tools for Teachers
PPTX
Cell Structure & Organelles in detailed.
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
RMMM.pdf make it easy to upload and study
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
Cell Types and Its function , kingdom of life
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
GDM (1) (1).pptx small presentation for students
PPTX
Pharma ospi slides which help in ospi learning
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Supply Chain Operations Speaking Notes -ICLT Program
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
master seminar digital applications in india
O7-L3 Supply Chain Operations - ICLT Program
Classroom Observation Tools for Teachers
Cell Structure & Organelles in detailed.
VCE English Exam - Section C Student Revision Booklet
2.FourierTransform-ShortQuestionswithAnswers.pdf
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
Microbial disease of the cardiovascular and lymphatic systems
RMMM.pdf make it easy to upload and study
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Abdominal Access Techniques with Prof. Dr. R K Mishra
Cell Types and Its function , kingdom of life
Anesthesia in Laparoscopic Surgery in India
102 student loan defaulters named and shamed – Is someone you know on the list?
GDM (1) (1).pptx small presentation for students
Pharma ospi slides which help in ospi learning
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape

Scheduling Problems Complete the following problems covering pro.docx

  • 1. Scheduling Problems Complete the following problems covering project scheduling methods. 1. Put the following project management activities in order, by defining immediate predecessors by placing one or more letters in the column labeled “Immediate predecessor”. One of them has been done for you. Activity Immediate predecessor a) Calculate durations along all project paths b) Calculate Te c) Define immediate predecessors h d) Develop WBS e) Draw a network diagram f) Estimate task durations g) Find the critical paths h) Generate a complete, detailed task list i) Identify project objectives j) Write project scope statement 2. Draw network diagram for the following list of activities and their immediate predecessors. Draw start and end nodes. Activity Immediate predecessor
  • 3. 3. Given the following detailed task list, draw a network diagram, including starting and ending nodes. Task Immediate predecessor A -- B A C A D B E C F D, E 4. Identify all paths and their summed durations from the following detailed task list. Task
  • 4. Estimated duration Immediate Predecessors A-define info req 2 wks - B- analyze existing infrastruc 1.5 wks - C-define network req 1 wk. B D-design database 3 wks. A E-design network 2.5 wks. C F-implement 7 wks.
  • 5. D, E G-test 4 wks. F H-document database 1 wk. D I-user documentation 2 wks. C 5. What is/are the critical path(s) amongst the following paths through a project? Path 1: A-B-D = 8.5 mos. Path 2: B-C-I-J = 10 mos. Path 3: A-B-E = 5.5 mos.
  • 6. Path 4: B-F-G-J = 12 mos. 6. What is the shortest possible completion time for a project, given the following paths through a project from start to finish? A-B-D-F = 14 weeks A-G = 22 weeks A-C-H-I-J = 19 weeks 7. Identify all non-critical activities in the project with the following paths: A-B-C = 22 weeks B-J-K = 18 weeks A-B-D-E = 22 weeks A-B-I = 14 weeks B-L = 20 weeks 8. Identify all non-critical activities for a project with the following paths A-B-C = 10 days A-B-D = 8 days A-B-E-F = 8 days A-B-G = 9 days 9. Develop an early start early finish (ES/EF) schedule for the following project.
  • 7. Activity Duration Predecessor ES EF A Develop specifications 2 wks B Design 4 A C Documentation 5 A D Implementation 8 B, C E Testing 4 D 10. Develop an early start, early finish (ES/EF) schedule for the
  • 8. following project. Activity Duration Predecessor ES EF A Develop specifications 6 wks B Design 5 wks A C User Documentation 7 wks A D Implementation 11 wks B, C E Acceptance Testing 8 wks D
  • 9. F Develop marketing literature 8 wks A G Technical documentation 7 wks B, C, F PAGE 3 Example Scheduling Problem 1 v3 Before we can schedule a project, we will need to have done the following, in order: - Identify project objectives - Write project scope statement - Develop a WBS - Generate a complete detailed task list The above can be considered progressive elaboration of scope, And then we need to: - Define immediate predecessors If we do all of these things, we can then define a network diagram that illustrates the interrelationship among activities, and the various paths throughout the project.
  • 10. Before we can develop a schedule, using the critical path method, we also have to: - Estimate task durations The three (3) inputs to using the critical path method for scheduling are, therefore, (a) develop a detailed activity list with (b) immediate predecessors and (c) estimated task durations. What I am going to show you now is how to develop a project schedule, in the following basic steps: - Draw a network diagram - Calculate durations along all project paths - Find the critical path(s) - Calculate Te 1. Draw network diagram for the following list of activities and their immediate predecessors. Draw start and end nodes. The project is to put a consulting company’s marketing plan on the Internet. (Olson 2004, p. 207 #12). Activity Immediate predecessor A none B none C D D A E A, B F A, B G E, F H C I C, G J H, I K J
  • 11. L K ( See Network Diagram on Next) 2. Identify all paths from the network diagram above. Paths Path 1 – A-D-C-H-J-K-L Path 2 – A-D-C-I-J-K-L Path 3 – A-E-G-I-J-K-L Path 4 – A-F-G-I-J-K-L Path 5 – B-E-G-I-J-K-L Path 6 – B-F-G-I-J-K-L 2. Identify all paths and their summed durations from the following detailed task list. Activity Predecessor(s) Duration A-obtain your boss’s approval of your plan none 8 days B-obtain budget approval none 12 days C-obtain systems development approval D 10 days D-develop user specifications A 1 day E-obtain a marketing program from mktg A, B 120 days F-obtain a mktg program from consultant A, B
  • 12. 60 days G-review and select mktg program E, F 5 days H-perform systems dev of module contents C 80 days I-design system interface C, G 50 days J-review and approve systems development H, I 5 days K-test prototype J 10 days L-revision and final systems development K 20 days Path = Summed duration Path 1 – A-D-C-H-J-K-L = 8+1+10+80+5+10+20 = 19 + 80 + 35 = 134 days Path 2 – A-D-C-I-J-K-L = 19 + 50 + 35 = 104 days Path 3 – A-E-G-I-J-K-L = 8 + 120 + 5 + 50 + 35 = 218 days Path 4 – A-F-G-I-J-K-L = 8 + 60 + 5 + 50 + 35 = 158 days Path 5 – B-E-G-I-J-K-L = 12+120+5+50+35 = 222 days Path 6 – B-F-G-I-J-K-L = 222 – 120 + 60 = 162 days 3. What is/are the critical path(s) from the paths above? Path 5 – B-E-G-I-J-K-L = 12+120+5+50+35 = 222 days 4. What is the shortest possible completion time for the project, Te? 222 days
  • 13. 5. Identify all non-critical activities in the project: Activities A, C, D, and H do not fall on the critical path. 6. Develop an early start, early finish (ES/EF) schedule for the following project. Activity Predecessor Duration ES EF A obtain your boss’s approval of your plan none 8 0 8 B obtain budget approval none 12 0 12 C obtain systems development approval D 10 9 19 D develop user specifications A 1
  • 14. 8 9 E obtain a marketing program from mktg A, B 120 12 132 F obtain a mktg program from consultant A, B 60 12 72 G review and select mktg program E, F 5 132 137 H perform systems dev of module contentS C 80 19 99 I design system interface C, G 50 137 187 J review and approve systems development H, I 5
  • 15. 187 192 K test prototype J 10 192 202 L revision and final systems development K 20 202 222 Example Problem - Network Diagram :