Project Scheduling
Models
2
• A project is a collection of tasks that must be
completed in minimum time or at minimal cost.
• Objectives of Project Scheduling
– Completing the project as early as possible by
determining the earliest start and finish of each activity.
– Calculating the likelihood a project will be completed
within a certain time period.
– Finding the minimum cost schedule needed to complete
the project by a certain date.
Introduction
3
• A project is a collection of tasks that must be
completed in minimum time or at minimal cost.
• Objectives of Project Scheduling
– Investigating the results of possible delays in activity’s
completion time.
– Progress control.
– Smoothing out resource allocation over the duration of
the project.
Introduction
4
• Tasks are called “activities.”
– Estimated completion time (and sometimes costs)
are associated with each activity.
– Activity completion time is related to the amount of
resources committed to it.
– The degree of activity details depends on the
application and the level of specificity of data.
Task Designate
5
Identifying the Activities of a Project
• To determine optimal schedules we need to
– Identify all the project’s activities.
– Determine the precedence relations among activities.
• Based on this information we can develop managerial
tools for project control.
6
Identifying Activities, Example
KLONE COMPUTERS, INC.
• KLONE Computers manufactures personal computers.
• It is about to design, manufacture, and market the
Klonepalm 2000 palmbook computer.
7
• There are three major tasks to perform:
– Manufacture the new computer.
– Train staff and vendor representatives.
– Advertise the new computer.
• KLONE needs to develop a precedence relations
chart.
• The chart gives a concise set of tasks and their
immediate predecessors.
KLONE COMPUTERS, INC
8
Activity Description
A Prototype model design
B Purchase of materials
Manufacturing C Manufacture of prototype model
activities D Revision of design
E Initial production run
F Staff training
Training activities G Staff input on prototype models
H Sales training
Advertising activities I Pre-production advertising
campaign
J Post-redesign advertising campaign
KLONE COMPUTERS, INC
9
From the activity description chart, we
can determine immediate predecessors
for each activity.
Activity A is an immediate predecessor
of activity B, because it must be competed
just prior to the commencement of B.
A B
KLONE COMPUTERS, INC
10
Immediate Estimated
Activity Predecessor Completion Time
A None 90
B A 15
C B 5
D G 20
E D 21
F A 25
G C,F 14
H D 28
I A 30
J D,I 45
Precedence Relationships Chart
KLONE COMPUTERS, INC
11
3 The PERT/CPM Approach for
Project Scheduling
• The PERT/CPM approach to project scheduling
uses network presentation of the project to
– Reflect activity precedence relations
– Activity completion time
• PERT/CPM is used for scheduling activities such
that the project’s completion time is minimized.
12
KLONE COMPUTERS, INC. - Continued
• Management at KLONE would like to schedule the activities
so that the project is completed in minimal time.
• Management wishes to know:
– The earliest and latest start times for each activity which will not
alter the earliest completion time of the project.
– The earliest finish times for each activity which will not alter this
date.
– Activities with rigid schedule and activities that have slack in their
schedules.
13
Earliest Start Time / Earliest Finish Time
• Make a forward pass through the network as follows:
– Evaluate all the activities which have no immediate predecessors.
• The earliest start for such an activity is zero ES = 0.
• The earliest finish is the activity duration EF = Activity duration.
– Evaluate the ES of all the nodes for which EF of all the
immediate predecessor has been determined.
• ES = Max EF of all its immediate predecessors.
• EF = ES + Activity duration.
– Repeat this process until all nodes have been evaluated
• EF of the finish node is the earliest finish time of the project.
14
Earliest Start / Earliest Finish –
Forward Pass
A
90
B
15
C
5
F
25
I
30
G
14
D
20
E
21
H
28
J
45
90,105
90,115
90,120
105,110
110,124
115,129 129,149
149,170
149,177
120,165
149,194
170
194
A
0,90
B
I
F
C
G D
E
H
J
177
194
EARLIEST FINISH
15
Latest start time / Latest finish time
• Make a backward pass through the network as follows:
– Evaluate all the activities that immediately precede the finish
node.
• The latest finish for such an activity is LF = minimal project completion
time.
• The latest start for such an activity is LS = LF - activity duration.
– Evaluate the LF of all the nodes for which LS of all the immediate
successors has been determined.
• LF = Min LS of all its immediate successors.
• LS = LF - Activity duration.
– Repeat this process backward until all nodes have been
evaluated.
16
B
F
C
A
I
E
D
G H
H
28
166,194
J
J
45
149,194
E
21
173,194
90,105
90,115
90,120
105,110
115,129 129,149
149,170
149,177
149,194
153,173
146,166
194
129,149
0,90
129,149
D
20
129,149
129,149
129,149
129,149
129,149
129,149
129,149
G
14
115,129
I
30
119,149
29,119
C
5
110,115
B
15
95,110
5,95
F
25
90, 115
0,90
A
90
Latest Start / Latest Finish –
Backward Pass
17
• Activity start time and completion time may be
delayed by planned reasons as well as by
unforeseen reasons.
• Some of these delays may affect the overall
completion date.
• To learn about the effects of these delays, we
calculate the slack time, and form the critical path.
Slack Times
18
– Slack time is the amount of time an activity can be delayed
without delaying the project completion date, assuming no
other delays are taking place in the project.
Slack Time = LS - ES = LF - EF
Slack Times
19
Critical activities
must be rigidly
scheduled
Activity LS - ES Slack
A 0 -0 0
B 95 - 90 5
C 110 - 105 5
D 119 - 119 0
E 173 - 149 24
F 90 - 90 0
G 115 - 115 0
H 166 - 149 17
I 119 - 90 29
J 149 - 149 0
Slack time in the Klonepalm 2000 Project
20
• The critical path is a set of activities that have no slack,
connecting the START node with the FINISH node.
• The critical activities (activities with 0 slack) form
at least one critical path in the network.
• A critical path is the longest path in the network.
• The sum of the completion times for the activities
on the critical path is the minimal completion time
of the project.
The Critical Path
21
B
F
C
A
I
E
D
G H
H
28
166,194
J
J
45
149,194
E
21
173,194
90,105
90,115
90,120
105,110
115,129 129,149
149,170
149,177
149,194
D
20
0,90
129,149
G
14
115,129
I
30
119,149
A
90
C
5
110,115
B
15
95,110
F
25
90, 115
0,90
The Critical Path
22
The Probability Approach to
Project Scheduling
• Activity completion times are seldom known with
100% accuracy.
• PERT is a technique that treats activity completion
times as random variables.
• Completion time estimates are obtained by the
Three Time Estimate approach
23
• The Three Time Estimate approach provides
completion time estimate for each activity.
• We use the notation:
a = an optimistic time to perform the activity.
m = the most likely time to perform the activity.
b = a pessimistic time to perform the activity.
The Probability Approach –
Three Time Estimates
24


=
t
h
e
m
e
a
n
c
o
m
p
l
e
t
i
o
n
t
i
m
e
=
a
+
4
m
+
b
6
=
t
h
e
s
t
a
n
d
a
r
d
d
e
v
i
a
t
i
o
n
=
b
-
a
6
Approximations for the mean and the
standard deviation of activity completion
time are based on the Beta distribution.
The Distribution, Mean, and Standard
Deviation of an Activity
25
To calculate the mean and standard
deviation of the project completion time
we make some simplifying assumptions.
The Project Completion Time Distribution -
Assumptions
26
• Assumption 2
– The time to complete one activity is independent of the time
to complete any other activity.
• Assumption 3
– There are enough activities on the critical path so that the
distribution of the overall project completion time can be
approximated by the normal distribution.
The Project Completion Time Distribution -
Assumptions
• Assumption 1
– A critical path can be determined by using the mean
completion times for the activities.
– The project mean completion time is determined solely by the
completion time of the activities on the critical path.
27
Mean = Sum of mean completion times along
the critical path.
The three assumptions imply that the overall project
completion time is normally distributed, the following
parameters:
The Project Completion Time Distribution
Variance = Sum of completion time variances
along the critical path.
Standard deviation = Variance
28
A c tiv ity O p tim is tic M o s t L ik e ly P e s s im is tic
A 7 6 8 6 1 2 0
B 1 2 1 5 1 8
C 4 5 6
D 1 5 1 8 3 3
E 1 8 2 1 2 4
F 1 6 2 6 3 0
G 1 0 1 3 2 2
H 2 4 1 8 3 2
I 2 2 2 7 5 0
J 3 8 4 3 6 0
The Probability Approach –
KLONE COMPUTERS
29
• Management at KLONE is interested in
information regarding the completion time of the
project.
• The probabilistic nature of the completion time
must be considered.
The Probability Approach –
KLONE COMPUTERS
30
A = [76+4(86)+120]/6 = 90
A = (120 - 76)/6 = 7.33 A
2 = (7.33)2 = 53.78
Activity  
A 90 7.33 53.78
B 15 1.00 1.00
C 5 0.33 0.11
D 20 3.00 9.00
E 21 1.00 1.00
F 25 2.33 5.44
G 14 2.00 4.00
H 28 1.33 1.78
I 30 4.67 21.78
J 45 3.67 13.44
2
KLONE COMPUTERS –
Finding activities’ mean and variance
31
• The mean times are the same as in the CPM
problem, previously solved for KLONE.
• Thus, the critical path is A - F- G - D – J.
– Expected completion time = A +F +G +D +J=194.
– The project variance =A
2 +F
2 +G
2 +D
2 +J
2 = 85.66
– The standard deviation = = 9.255
2
KLONE COMPUTERS –
Finding mean and variance for the critical path
Steps in PERT
(From the exam perspective)
• Step1: Calculate µi and σi for each activity i
• Step 2: Draw Network Diagram
• Step 3: Calculate ES/EF by forward pass for each activity i
• Step 4: Calculate LS/LF by backward pass for each activity i
• Step 5: Calculate Slack Time Si for each activity i
• Step 6: Identify critical activities and critical path
• Step 7: Calculate µ (Expected project completion time). 2
(Project variance) and σ (Standard Deviation) for entire project
32
33
Gantt Charts
• Gantt charts are used as a tool to monitor and control the
project progress.
• A Gantt Chart is a graphical presentation that displays
activities as follows:
– Time is measured on the horizontal axis. A horizontal bar is drawn
proportionately to an activity’ s expected completion time.
– Each activity is listed on the vertical axis.
• In an earliest time Gantt chart each bar begins and ends at
the earliest start/finish the activity can take place.
34
Here‘s how we build
an Earliest Time Gantt Chart
for KLONEPALM 2000
35
Im m e d ia te E s tim a te d
A c tiv ity P r e d e c e s s o r C o m p le tio n T im e
A N o n e 9 0
B A 1 5
C B 5
D G 2 0
E D 2 1
F A 2 5
G C ,F 1 4
H D 2 8
I A 3 0
J D ,I 4 5
Im m e d ia te E s tim a te d
A c tiv ity P r e d e c e s s o r C o m p le tio n T im e
A N o n e 9 0
B A 1 5
C B 5
D G 2 0
E D 2 1
F A 2 5
G C ,F 1 4
H D 2 8
I A 3 0
J D ,I 4 5
A
90
90
B
15
F
25
I
30
105
C
5
115
G
14
129
D
20
149
E
21
H
28
J
45
194
194
36
• Gantt chart can be used as a visual aid for tracking the
progress of project activities.
• Appropriate percentage of a bar is shaded to document the
completed work.
• The manager can easily see if the project is progressing on
schedule (with respect to the earliest possible completion
times).
Gantt Charts-
Monitoring Project Progress
37
A
90
B
15
F
25
I
30
C
5
G
14
D
20
E
21
H
28
J
45
194
194
135
Monitoring Project Progress
The shaded bars represent
completed work BY DAY 135.
Do not conclude that the
project is behind schedule.
Activity “I” has a slack and
therefore can be delayed!!!
38
• Advantages.
– Easy to construct
– Gives earliest completion date.
– Provides a schedule of earliest possible start and finish times of
activities.
• Disadvantages
– Gives only one possible schedule (earliest).
– Does not show whether the project is behind schedule.
– Does not demonstrate the effects of delays in any one activity on the
start of another activity, thus on the project completion time.
Gantt Charts –
Advantages and Disadvantages

More Related Content

PPT
PROJECT SCHEDULING
PPT
Project Scheduling.ppt
PPTX
Cpm pert
PPT
Cpm n pert lecture 1
PPTX
Lec 9 & 10 chapter 5 project scheduling
PPTX
PMP Project Management Basics Tutorial For Beginners
PPTX
Pertcpm projectmanagement SIDDANNA M BALAPGOL
PPTX
Pertcpm projectmanagement-120628224438-phpapp02
PROJECT SCHEDULING
Project Scheduling.ppt
Cpm pert
Cpm n pert lecture 1
Lec 9 & 10 chapter 5 project scheduling
PMP Project Management Basics Tutorial For Beginners
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement-120628224438-phpapp02

Similar to Unit 3 PERT.pptx in related to supply chain (20)

PPTX
Project Management & Engineering Economics
PPTX
Pert and CPM
PPTX
PERT_CPM and other relevant points .pptx
PPTX
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
PDF
PERT AND CPM PROJECT MANAGEMENT
PPTX
Ch 5.pptx
PDF
L2_Project_Management.pdf
PPTX
cpmpertmy (1)
PPT
13 lecture project management
PPT
EMGT5220 C8uhuuhuhuuuuuuuhuhuhuhuh-6.ppt
PPTX
PPTX
CPM AND PERT(critical path method) .pptx
PPT
08. Project Time Management Upload
PPTX
pert-cpm.pptx
PPT
2._ETA_-PTM-30-0kkliynkkkdoi5-08_FFF.ppt
PPTX
project network
PPTX
Quantitative analysis for business decision- Program Evaluation and Review Te...
PPTX
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
PPTX
PPT
Pert cpm
Project Management & Engineering Economics
Pert and CPM
PERT_CPM and other relevant points .pptx
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
Ch 5.pptx
L2_Project_Management.pdf
cpmpertmy (1)
13 lecture project management
EMGT5220 C8uhuuhuhuuuuuuuhuhuhuhuh-6.ppt
CPM AND PERT(critical path method) .pptx
08. Project Time Management Upload
pert-cpm.pptx
2._ETA_-PTM-30-0kkliynkkkdoi5-08_FFF.ppt
project network
Quantitative analysis for business decision- Program Evaluation and Review Te...
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
Pert cpm
Ad

Recently uploaded (20)

PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
VCE English Exam - Section C Student Revision Booklet
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Institutional Correction lecture only . . .
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
Insiders guide to clinical Medicine.pdf
PDF
Complications of Minimal Access Surgery at WLH
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
FourierSeries-QuestionsWithAnswers(Part-A).pdf
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Sports Quiz easy sports quiz sports quiz
PPTX
Lesson notes of climatology university.
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
master seminar digital applications in india
PPTX
Pharma ospi slides which help in ospi learning
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
VCE English Exam - Section C Student Revision Booklet
Supply Chain Operations Speaking Notes -ICLT Program
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Institutional Correction lecture only . . .
O5-L3 Freight Transport Ops (International) V1.pdf
Insiders guide to clinical Medicine.pdf
Complications of Minimal Access Surgery at WLH
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
FourierSeries-QuestionsWithAnswers(Part-A).pdf
Module 4: Burden of Disease Tutorial Slides S2 2025
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Sports Quiz easy sports quiz sports quiz
Lesson notes of climatology university.
Abdominal Access Techniques with Prof. Dr. R K Mishra
TR - Agricultural Crops Production NC III.pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
master seminar digital applications in india
Pharma ospi slides which help in ospi learning
Ad

Unit 3 PERT.pptx in related to supply chain

  • 2. 2 • A project is a collection of tasks that must be completed in minimum time or at minimal cost. • Objectives of Project Scheduling – Completing the project as early as possible by determining the earliest start and finish of each activity. – Calculating the likelihood a project will be completed within a certain time period. – Finding the minimum cost schedule needed to complete the project by a certain date. Introduction
  • 3. 3 • A project is a collection of tasks that must be completed in minimum time or at minimal cost. • Objectives of Project Scheduling – Investigating the results of possible delays in activity’s completion time. – Progress control. – Smoothing out resource allocation over the duration of the project. Introduction
  • 4. 4 • Tasks are called “activities.” – Estimated completion time (and sometimes costs) are associated with each activity. – Activity completion time is related to the amount of resources committed to it. – The degree of activity details depends on the application and the level of specificity of data. Task Designate
  • 5. 5 Identifying the Activities of a Project • To determine optimal schedules we need to – Identify all the project’s activities. – Determine the precedence relations among activities. • Based on this information we can develop managerial tools for project control.
  • 6. 6 Identifying Activities, Example KLONE COMPUTERS, INC. • KLONE Computers manufactures personal computers. • It is about to design, manufacture, and market the Klonepalm 2000 palmbook computer.
  • 7. 7 • There are three major tasks to perform: – Manufacture the new computer. – Train staff and vendor representatives. – Advertise the new computer. • KLONE needs to develop a precedence relations chart. • The chart gives a concise set of tasks and their immediate predecessors. KLONE COMPUTERS, INC
  • 8. 8 Activity Description A Prototype model design B Purchase of materials Manufacturing C Manufacture of prototype model activities D Revision of design E Initial production run F Staff training Training activities G Staff input on prototype models H Sales training Advertising activities I Pre-production advertising campaign J Post-redesign advertising campaign KLONE COMPUTERS, INC
  • 9. 9 From the activity description chart, we can determine immediate predecessors for each activity. Activity A is an immediate predecessor of activity B, because it must be competed just prior to the commencement of B. A B KLONE COMPUTERS, INC
  • 10. 10 Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 Precedence Relationships Chart KLONE COMPUTERS, INC
  • 11. 11 3 The PERT/CPM Approach for Project Scheduling • The PERT/CPM approach to project scheduling uses network presentation of the project to – Reflect activity precedence relations – Activity completion time • PERT/CPM is used for scheduling activities such that the project’s completion time is minimized.
  • 12. 12 KLONE COMPUTERS, INC. - Continued • Management at KLONE would like to schedule the activities so that the project is completed in minimal time. • Management wishes to know: – The earliest and latest start times for each activity which will not alter the earliest completion time of the project. – The earliest finish times for each activity which will not alter this date. – Activities with rigid schedule and activities that have slack in their schedules.
  • 13. 13 Earliest Start Time / Earliest Finish Time • Make a forward pass through the network as follows: – Evaluate all the activities which have no immediate predecessors. • The earliest start for such an activity is zero ES = 0. • The earliest finish is the activity duration EF = Activity duration. – Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined. • ES = Max EF of all its immediate predecessors. • EF = ES + Activity duration. – Repeat this process until all nodes have been evaluated • EF of the finish node is the earliest finish time of the project.
  • 14. 14 Earliest Start / Earliest Finish – Forward Pass A 90 B 15 C 5 F 25 I 30 G 14 D 20 E 21 H 28 J 45 90,105 90,115 90,120 105,110 110,124 115,129 129,149 149,170 149,177 120,165 149,194 170 194 A 0,90 B I F C G D E H J 177 194 EARLIEST FINISH
  • 15. 15 Latest start time / Latest finish time • Make a backward pass through the network as follows: – Evaluate all the activities that immediately precede the finish node. • The latest finish for such an activity is LF = minimal project completion time. • The latest start for such an activity is LS = LF - activity duration. – Evaluate the LF of all the nodes for which LS of all the immediate successors has been determined. • LF = Min LS of all its immediate successors. • LS = LF - Activity duration. – Repeat this process backward until all nodes have been evaluated.
  • 17. 17 • Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons. • Some of these delays may affect the overall completion date. • To learn about the effects of these delays, we calculate the slack time, and form the critical path. Slack Times
  • 18. 18 – Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project. Slack Time = LS - ES = LF - EF Slack Times
  • 19. 19 Critical activities must be rigidly scheduled Activity LS - ES Slack A 0 -0 0 B 95 - 90 5 C 110 - 105 5 D 119 - 119 0 E 173 - 149 24 F 90 - 90 0 G 115 - 115 0 H 166 - 149 17 I 119 - 90 29 J 149 - 149 0 Slack time in the Klonepalm 2000 Project
  • 20. 20 • The critical path is a set of activities that have no slack, connecting the START node with the FINISH node. • The critical activities (activities with 0 slack) form at least one critical path in the network. • A critical path is the longest path in the network. • The sum of the completion times for the activities on the critical path is the minimal completion time of the project. The Critical Path
  • 22. 22 The Probability Approach to Project Scheduling • Activity completion times are seldom known with 100% accuracy. • PERT is a technique that treats activity completion times as random variables. • Completion time estimates are obtained by the Three Time Estimate approach
  • 23. 23 • The Three Time Estimate approach provides completion time estimate for each activity. • We use the notation: a = an optimistic time to perform the activity. m = the most likely time to perform the activity. b = a pessimistic time to perform the activity. The Probability Approach – Three Time Estimates
  • 24. 24   = t h e m e a n c o m p l e t i o n t i m e = a + 4 m + b 6 = t h e s t a n d a r d d e v i a t i o n = b - a 6 Approximations for the mean and the standard deviation of activity completion time are based on the Beta distribution. The Distribution, Mean, and Standard Deviation of an Activity
  • 25. 25 To calculate the mean and standard deviation of the project completion time we make some simplifying assumptions. The Project Completion Time Distribution - Assumptions
  • 26. 26 • Assumption 2 – The time to complete one activity is independent of the time to complete any other activity. • Assumption 3 – There are enough activities on the critical path so that the distribution of the overall project completion time can be approximated by the normal distribution. The Project Completion Time Distribution - Assumptions • Assumption 1 – A critical path can be determined by using the mean completion times for the activities. – The project mean completion time is determined solely by the completion time of the activities on the critical path.
  • 27. 27 Mean = Sum of mean completion times along the critical path. The three assumptions imply that the overall project completion time is normally distributed, the following parameters: The Project Completion Time Distribution Variance = Sum of completion time variances along the critical path. Standard deviation = Variance
  • 28. 28 A c tiv ity O p tim is tic M o s t L ik e ly P e s s im is tic A 7 6 8 6 1 2 0 B 1 2 1 5 1 8 C 4 5 6 D 1 5 1 8 3 3 E 1 8 2 1 2 4 F 1 6 2 6 3 0 G 1 0 1 3 2 2 H 2 4 1 8 3 2 I 2 2 2 7 5 0 J 3 8 4 3 6 0 The Probability Approach – KLONE COMPUTERS
  • 29. 29 • Management at KLONE is interested in information regarding the completion time of the project. • The probabilistic nature of the completion time must be considered. The Probability Approach – KLONE COMPUTERS
  • 30. 30 A = [76+4(86)+120]/6 = 90 A = (120 - 76)/6 = 7.33 A 2 = (7.33)2 = 53.78 Activity   A 90 7.33 53.78 B 15 1.00 1.00 C 5 0.33 0.11 D 20 3.00 9.00 E 21 1.00 1.00 F 25 2.33 5.44 G 14 2.00 4.00 H 28 1.33 1.78 I 30 4.67 21.78 J 45 3.67 13.44 2 KLONE COMPUTERS – Finding activities’ mean and variance
  • 31. 31 • The mean times are the same as in the CPM problem, previously solved for KLONE. • Thus, the critical path is A - F- G - D – J. – Expected completion time = A +F +G +D +J=194. – The project variance =A 2 +F 2 +G 2 +D 2 +J 2 = 85.66 – The standard deviation = = 9.255 2 KLONE COMPUTERS – Finding mean and variance for the critical path
  • 32. Steps in PERT (From the exam perspective) • Step1: Calculate µi and σi for each activity i • Step 2: Draw Network Diagram • Step 3: Calculate ES/EF by forward pass for each activity i • Step 4: Calculate LS/LF by backward pass for each activity i • Step 5: Calculate Slack Time Si for each activity i • Step 6: Identify critical activities and critical path • Step 7: Calculate µ (Expected project completion time). 2 (Project variance) and σ (Standard Deviation) for entire project 32
  • 33. 33 Gantt Charts • Gantt charts are used as a tool to monitor and control the project progress. • A Gantt Chart is a graphical presentation that displays activities as follows: – Time is measured on the horizontal axis. A horizontal bar is drawn proportionately to an activity’ s expected completion time. – Each activity is listed on the vertical axis. • In an earliest time Gantt chart each bar begins and ends at the earliest start/finish the activity can take place.
  • 34. 34 Here‘s how we build an Earliest Time Gantt Chart for KLONEPALM 2000
  • 35. 35 Im m e d ia te E s tim a te d A c tiv ity P r e d e c e s s o r C o m p le tio n T im e A N o n e 9 0 B A 1 5 C B 5 D G 2 0 E D 2 1 F A 2 5 G C ,F 1 4 H D 2 8 I A 3 0 J D ,I 4 5 Im m e d ia te E s tim a te d A c tiv ity P r e d e c e s s o r C o m p le tio n T im e A N o n e 9 0 B A 1 5 C B 5 D G 2 0 E D 2 1 F A 2 5 G C ,F 1 4 H D 2 8 I A 3 0 J D ,I 4 5 A 90 90 B 15 F 25 I 30 105 C 5 115 G 14 129 D 20 149 E 21 H 28 J 45 194 194
  • 36. 36 • Gantt chart can be used as a visual aid for tracking the progress of project activities. • Appropriate percentage of a bar is shaded to document the completed work. • The manager can easily see if the project is progressing on schedule (with respect to the earliest possible completion times). Gantt Charts- Monitoring Project Progress
  • 37. 37 A 90 B 15 F 25 I 30 C 5 G 14 D 20 E 21 H 28 J 45 194 194 135 Monitoring Project Progress The shaded bars represent completed work BY DAY 135. Do not conclude that the project is behind schedule. Activity “I” has a slack and therefore can be delayed!!!
  • 38. 38 • Advantages. – Easy to construct – Gives earliest completion date. – Provides a schedule of earliest possible start and finish times of activities. • Disadvantages – Gives only one possible schedule (earliest). – Does not show whether the project is behind schedule. – Does not demonstrate the effects of delays in any one activity on the start of another activity, thus on the project completion time. Gantt Charts – Advantages and Disadvantages