Project
Network
Project
• “A project is a series of activities directed to
accomplishment of a desired objective.”
Plan your work first…..then work your plan
Network analysis
Introduction
Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects.
One definition of a project:
“A project is a temporary endeavour undertaken to create a "unique" product
or service”
4
• Graphical portrayal of activities and event
• Shows dependency relationships between
tasks/activities in a project
• Clearly shows tasks that must precede
(precedence) or follow (succeeding) other tasks
in a logical manner
• Clear representation of plan – a powerful tool for
planning and controlling project
NETWORK
CPM - Critical Path Method
• Definition: In CPM activities are shown as a network of precedence
relationships using activity-on-node network construction
– Single estimate of activity time
– Deterministic activity times
USED IN : Production management - for the jobs of repetitive in
nature where the activity time estimates can be predicted with
considerable certainty due to the existence of past experience.
PERT -
Project Evaluation & Review Techniques
• Definition: In PERT activities are shown as a network of precedence
relationships using activity-on-arrow network construction
– Multiple time estimates
– Probabilistic activity times
USED IN : Project management - for non-repetitive jobs (research and
development work), where the time and cost estimates tend to be
quite uncertain. This technique uses probabilistic time estimates.
Originated by H.L.Gantt in 1918
Gantt chart
Advantages
- Gantt charts are quite commonly
used. They provide an easy graphical
representation of when activities
(might) take place.
Limitations
- Do not clearly indicate details
regarding the progress of activities
- Do not give a clear indication of
interrelation ship between the
separate activities
CPM/PERT
These deficiencies can be eliminated to a large extent by showing the
interdependence of various activities by means of connecting arrows
called network technique.
• Overtime CPM and PERT became one technique
• ADVANTAGES:
– Precedence relationships
– large projects
– more efficient
NETWORK TECHNIQUES
PERT CPM
-Program Evaluation and
Review Technique
- developed by the US
Navy with Booz
Hamilton Lockheed
- on the Polaris
Missile/Submarine
program 1958
Critical Path Method
Developed by El Dupont
for Chemical Plant
Shutdown Project- about
same time as PERT
Both use same calculations, almost similar
Main difference is probabilistic and deterministic in time estimation
Gantt Chart also used in scheduling
10
BENEFITS OFCPM / PERT NETWORK
Consistent framework for planning, scheduling,
monitoring, and controlling project.
• Shows interdependence of all tasks, work packages,
and work units.
• Helps proper communications between departments
and functions.
• Determines expected project completion date.
• Identifies so-called critical activities, which can delay
the project completion time.
11
• Identified activities with slacks that can be
delayed for specified periods without penalty, or
from which resources may be temporarily
borrowed
• Determines the dates on which tasks may be
started or must be started if the project is to stay in
schedule.
• Shows which tasks must be coordinated to avoid
resource or timing conflicts.
• Shows which tasks may run in parallel to meet
project completion date
BENEFITS OFCPM / PERT NETWORK (cont.)
Questions Answered by CPM & PERT
• Completion date?
• On Schedule?
• Within Budget?
• Critical Activities?
• How can the project be finished early at the least cost?
13
Example of Simple Network –
Survey
14
DEFINITION OF TERMS IN A NETWORK
• Activity : any portions of project (tasks) which required
by project, uses up resource and consumes
time – may involve labor, paper work,
contractual negotiations, machinery operations
Activity on Arrow (AOA) showed as arrow, AON
– Activity on Node
• Event : beginning or ending points of one or more
activities, instantaneous point in time, also
called ‘nodes’
• Network : Combination of all project activities and the events
ACTIVITY
PRECEEDING SUCCESSOR
EVENT
15
Emphasis on Logic in Network Construction
• Construction of network should be based on logical or
technical dependencies among activities
• Example - before activity ‘Approve Drawing’ can be
started the activity ‘Prepare Drawing’ must be
completed
Activity on Node & Activity on Arrow
Activity on Node
- A completion of an activity is
represented by a node
Activity on Arrow
- An arrow represents a task,
while a node is the completion
of a task
- Arrows represent order of events
Activity Slack
Each event has two important times associated with it :
- Earliest time , Te , which is a calendar time when a event can occur when all
the predecessor events completed at the earliest possible times
- Latest time , TL , which is the latest time the event can occur with out
delaying the subsequent events and completion of project.
• Difference between the latest time and the earliest time of an event is the
slack time for that event
Positive slack : Slack is the amount of time an event can be delayed without
delaying the project completion
Critical Path
• Is that the sequence of activities and events where there is no “slack” i.e..
Zero slack
• Longest path through a network
• minimum project completion time
19
Example 1- A simple network
Consider the list of four activities for making a simple product:
Activity Description Immediate
predecessors
A Buy Plastic Body -
B Design Component -
C Make Component B
D Assemble product A,C
Immediate predecessors for a particular activity are the activities
that, when completed, enable the start of the activity in question.
20
Sequence of activities
• Can start work on activities A and B anytime, since
neither of these activities depends upon the
completion of prior activities.
• Activity C cannot be started until activity B has been
completed
• Activity D cannot be started until both activities A and
C have been completed.
• The graphical representation (next slide) is referred to
as the PERT/CPM network
21
Network of Four Activities
1 3 4
2
A
B C
D
Arcs indicate project activities
Nodes correspond to the beginning
and ending of activities
22
Example 2
Develop the network for a project with following activities and
immediate predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
Try to do for the first five (A,B,C,D,E) activities
23
Network of first five activities
1 3 4
2
A
B
C
D
5
E
We need to introduce
a dummy activity
24
•Note how the network correctly identifies D, E, and F as the
immediate predecessors for activity G.
•Dummy activities is used to identify precedence relationships
correctly and to eliminate possible confusion of two or more
activities having the same starting and ending nodes
•Dummy activities have no resources (time, labor, machinery, etc) –
purpose is to PRESERVE LOGIC of the network
Network of Seven Activities
1 3 4
2
A
B
C
D
5
E
7
6
F
G
dummy
25
1 1
2 2
3 3
4
a d
b e
c f
a d
b
e
f
c
WRONG!!! RIGHT!!!
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
26
Scheduling with activity time
Activity Immediate Completion
predecessors Time (week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
This information indicates that the total time required to complete
activities is 51 weeks. However, we can see from the network that several
of the activities can be conducted simultaneously (A and B, for example).
Activity Relationships
Activity Relationship
AOA AON
Figure 4.1
Activity Relationships
Activity Relationship
S precedes T, which precedes U.
AOA AON
1 2
S
3
T
4
U
S T U
Figure 4.1
Activity Relationships
Activity Relationship
S and T must be completed before U can be started.
AOA AON
S
T
U
1
2
3
T
S
4
U
Figure 4.1
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed.
AOA AON
T
U
S
3
4
1
T
U
2
S
Figure 4.1
Activity Relationships
Activity Relationship
U and V cannot begin until both S and T have been completed.
AOA AON
1
2
4
5
U
V
S
T 3
S
T
U
V
Figure 4.1
Activity Relationships
Activity Relationship
U cannot begin until both S and T have been completed; V cannot
begin until T has been completed.
AOA AON
S
T
U
V
1 3
Dummy
5
2 4 6
S U
T V
Figure 4.1
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed; V cannot begin
until both T and U have been completed.
AOA AON
1 2 4
3
S T
5
V
U
Dummy
S T V
U
Figure 4.1

More Related Content

PDF
Organizational project maturity model (opm3)
PPTX
An Introduction to Project Management
PDF
Business Process Management Training 1
PDF
Setting up a Project Management Office (PMO)
PPTX
Project Schedule Management - Sequence Activities - PMP Workgroup
PPTX
Lec 03 project life cycle
PPTX
Project Management PERT and CPM
PPTX
PMP-Schedule Management area
Organizational project maturity model (opm3)
An Introduction to Project Management
Business Process Management Training 1
Setting up a Project Management Office (PMO)
Project Schedule Management - Sequence Activities - PMP Workgroup
Lec 03 project life cycle
Project Management PERT and CPM
PMP-Schedule Management area

What's hot (20)

PPTX
7.3 Determine Budget
PPT
How to set up a project management office (PMO)
PPSX
Business Process Management
PPTX
Project Management: Project Schedule Management Knowledge Area
PDF
PMBOK GUIDE 7th Summary
PDF
PPTX
Project management
PDF
Business Process Management PowerPoint Presentation Slides
PDF
Ppt results based-monitoring-and-evaluation-g-dela-cruz
PPTX
Project Scope Management - PMBOK6
PDF
Develop Project Management Plan Data Flow Diagram
PPTX
2011 business process management
PPTX
How to Assess the Maturity of your PMO
PDF
PMP_Project Time Management
PDF
Project risk management focus on risk identification techniques
PPT
Taking the Creep Out of Scope Creep
PDF
Business Process Management 101 Training
PDF
Business Process Modeling
PPTX
Pert,cpm, resource allocation and gert
7.3 Determine Budget
How to set up a project management office (PMO)
Business Process Management
Project Management: Project Schedule Management Knowledge Area
PMBOK GUIDE 7th Summary
Project management
Business Process Management PowerPoint Presentation Slides
Ppt results based-monitoring-and-evaluation-g-dela-cruz
Project Scope Management - PMBOK6
Develop Project Management Plan Data Flow Diagram
2011 business process management
How to Assess the Maturity of your PMO
PMP_Project Time Management
Project risk management focus on risk identification techniques
Taking the Creep Out of Scope Creep
Business Process Management 101 Training
Business Process Modeling
Pert,cpm, resource allocation and gert
Ad

Similar to project network (20)

PPTX
Ch 5.pptx
PPTX
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
PDF
Chapter 6 Scheduling CPM PERT Classes.pdf
PPT
Network Analysis : Pert & C P Management
PDF
Lect-6&7: Network Diagrams, PERT and CPM
PPT
Cpm n pert lecture 1
DOCX
Ii. pert cpm
PPTX
Chap 4- CPM & PERT.pptx
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPTX
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
PPTX
cpmpertmy (1)
PDF
NETWORK 1 & 2.pdf
PPTX
pert-cpm.pptx
PPT
49091291-PERT and CPM topic of industrial .ppt
PPTX
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
PDF
project managment lesson mechanical engineering
PPTX
Unit-V-PERT-and-CPM-PPT Proj Manage.pptx
PPTX
Project Management Methods PERT-and-CPM.pptx
PPT
06_Pert cpmugfhghfhxr justify gfghhhhhhh
PPT
PERT CPM Intro
Ch 5.pptx
Ch 5.pptx IS ALL ABOUT PROJECT MANAGMENT AND EVALUATION
Chapter 6 Scheduling CPM PERT Classes.pdf
Network Analysis : Pert & C P Management
Lect-6&7: Network Diagrams, PERT and CPM
Cpm n pert lecture 1
Ii. pert cpm
Chap 4- CPM & PERT.pptx
PROJECT-SCHEDULING-pptx.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
cpmpertmy (1)
NETWORK 1 & 2.pdf
pert-cpm.pptx
49091291-PERT and CPM topic of industrial .ppt
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
project managment lesson mechanical engineering
Unit-V-PERT-and-CPM-PPT Proj Manage.pptx
Project Management Methods PERT-and-CPM.pptx
06_Pert cpmugfhghfhxr justify gfghhhhhhh
PERT CPM Intro
Ad

More from Sougata Das (6)

PPTX
JGP PROFILE civil engineering deptartment
PPT
76107373-Waste-Water-Treatment-Process.ppt
PPTX
Direct-Bendng-Stress-pptx IMP.pptx
PPT
Wind-Analysis-Building Sdas.ppt
PPTX
CENTROID & MI.pptx
PPTX
tall.pptx
JGP PROFILE civil engineering deptartment
76107373-Waste-Water-Treatment-Process.ppt
Direct-Bendng-Stress-pptx IMP.pptx
Wind-Analysis-Building Sdas.ppt
CENTROID & MI.pptx
tall.pptx

Recently uploaded (20)

PPTX
Feature types and data preprocessing steps
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Artificial Intelligence
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
Nature of X-rays, X- Ray Equipment, Fluoroscopy
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPTX
Current and future trends in Computer Vision.pptx
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
737-MAX_SRG.pdf student reference guides
Feature types and data preprocessing steps
Fundamentals of Mechanical Engineering.pptx
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
Information Storage and Retrieval Techniques Unit III
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Artificial Intelligence
Safety Seminar civil to be ensured for safe working.
Soil Improvement Techniques Note - Rabbi
Nature of X-rays, X- Ray Equipment, Fluoroscopy
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Current and future trends in Computer Vision.pptx
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Automation-in-Manufacturing-Chapter-Introduction.pdf
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
"Array and Linked List in Data Structures with Types, Operations, Implementat...
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
737-MAX_SRG.pdf student reference guides

project network

  • 2. Project • “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan
  • 3. Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project: “A project is a temporary endeavour undertaken to create a "unique" product or service”
  • 4. 4 • Graphical portrayal of activities and event • Shows dependency relationships between tasks/activities in a project • Clearly shows tasks that must precede (precedence) or follow (succeeding) other tasks in a logical manner • Clear representation of plan – a powerful tool for planning and controlling project NETWORK
  • 5. CPM - Critical Path Method • Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 6. PERT - Project Evaluation & Review Techniques • Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 7. Originated by H.L.Gantt in 1918 Gantt chart Advantages - Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place. Limitations - Do not clearly indicate details regarding the progress of activities - Do not give a clear indication of interrelation ship between the separate activities
  • 8. CPM/PERT These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique. • Overtime CPM and PERT became one technique • ADVANTAGES: – Precedence relationships – large projects – more efficient
  • 9. NETWORK TECHNIQUES PERT CPM -Program Evaluation and Review Technique - developed by the US Navy with Booz Hamilton Lockheed - on the Polaris Missile/Submarine program 1958 Critical Path Method Developed by El Dupont for Chemical Plant Shutdown Project- about same time as PERT Both use same calculations, almost similar Main difference is probabilistic and deterministic in time estimation Gantt Chart also used in scheduling
  • 10. 10 BENEFITS OFCPM / PERT NETWORK Consistent framework for planning, scheduling, monitoring, and controlling project. • Shows interdependence of all tasks, work packages, and work units. • Helps proper communications between departments and functions. • Determines expected project completion date. • Identifies so-called critical activities, which can delay the project completion time.
  • 11. 11 • Identified activities with slacks that can be delayed for specified periods without penalty, or from which resources may be temporarily borrowed • Determines the dates on which tasks may be started or must be started if the project is to stay in schedule. • Shows which tasks must be coordinated to avoid resource or timing conflicts. • Shows which tasks may run in parallel to meet project completion date BENEFITS OFCPM / PERT NETWORK (cont.)
  • 12. Questions Answered by CPM & PERT • Completion date? • On Schedule? • Within Budget? • Critical Activities? • How can the project be finished early at the least cost?
  • 13. 13 Example of Simple Network – Survey
  • 14. 14 DEFINITION OF TERMS IN A NETWORK • Activity : any portions of project (tasks) which required by project, uses up resource and consumes time – may involve labor, paper work, contractual negotiations, machinery operations Activity on Arrow (AOA) showed as arrow, AON – Activity on Node • Event : beginning or ending points of one or more activities, instantaneous point in time, also called ‘nodes’ • Network : Combination of all project activities and the events ACTIVITY PRECEEDING SUCCESSOR EVENT
  • 15. 15 Emphasis on Logic in Network Construction • Construction of network should be based on logical or technical dependencies among activities • Example - before activity ‘Approve Drawing’ can be started the activity ‘Prepare Drawing’ must be completed
  • 16. Activity on Node & Activity on Arrow Activity on Node - A completion of an activity is represented by a node Activity on Arrow - An arrow represents a task, while a node is the completion of a task - Arrows represent order of events
  • 17. Activity Slack Each event has two important times associated with it : - Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times - Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project. • Difference between the latest time and the earliest time of an event is the slack time for that event Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion
  • 18. Critical Path • Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack • Longest path through a network • minimum project completion time
  • 19. 19 Example 1- A simple network Consider the list of four activities for making a simple product: Activity Description Immediate predecessors A Buy Plastic Body - B Design Component - C Make Component B D Assemble product A,C Immediate predecessors for a particular activity are the activities that, when completed, enable the start of the activity in question.
  • 20. 20 Sequence of activities • Can start work on activities A and B anytime, since neither of these activities depends upon the completion of prior activities. • Activity C cannot be started until activity B has been completed • Activity D cannot be started until both activities A and C have been completed. • The graphical representation (next slide) is referred to as the PERT/CPM network
  • 21. 21 Network of Four Activities 1 3 4 2 A B C D Arcs indicate project activities Nodes correspond to the beginning and ending of activities
  • 22. 22 Example 2 Develop the network for a project with following activities and immediate predecessors: Activity Immediate predecessors A - B - C B D A, C E C F C G D,E,F Try to do for the first five (A,B,C,D,E) activities
  • 23. 23 Network of first five activities 1 3 4 2 A B C D 5 E We need to introduce a dummy activity
  • 24. 24 •Note how the network correctly identifies D, E, and F as the immediate predecessors for activity G. •Dummy activities is used to identify precedence relationships correctly and to eliminate possible confusion of two or more activities having the same starting and ending nodes •Dummy activities have no resources (time, labor, machinery, etc) – purpose is to PRESERVE LOGIC of the network Network of Seven Activities 1 3 4 2 A B C D 5 E 7 6 F G dummy
  • 25. 25 1 1 2 2 3 3 4 a d b e c f a d b e f c WRONG!!! RIGHT!!! a precedes d. a and b precede e, b and c precede f (a does not precede f)
  • 26. 26 Scheduling with activity time Activity Immediate Completion predecessors Time (week) A - 5 B - 6 C A 4 D A 3 E A 1 F E 4 G D,F 14 H B,C 12 I G,H 2 Total …… 51 This information indicates that the total time required to complete activities is 51 weeks. However, we can see from the network that several of the activities can be conducted simultaneously (A and B, for example).
  • 28. Activity Relationships Activity Relationship S precedes T, which precedes U. AOA AON 1 2 S 3 T 4 U S T U Figure 4.1
  • 29. Activity Relationships Activity Relationship S and T must be completed before U can be started. AOA AON S T U 1 2 3 T S 4 U Figure 4.1
  • 30. Activity Relationships Activity Relationship T and U cannot begin until S has been completed. AOA AON T U S 3 4 1 T U 2 S Figure 4.1
  • 31. Activity Relationships Activity Relationship U and V cannot begin until both S and T have been completed. AOA AON 1 2 4 5 U V S T 3 S T U V Figure 4.1
  • 32. Activity Relationships Activity Relationship U cannot begin until both S and T have been completed; V cannot begin until T has been completed. AOA AON S T U V 1 3 Dummy 5 2 4 6 S U T V Figure 4.1
  • 33. Activity Relationships Activity Relationship T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed. AOA AON 1 2 4 3 S T 5 V U Dummy S T V U Figure 4.1