PROJECT MANAGEMENT
CPM & PERT TECHNIQUES
FLOW OF PRESENTATION
 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project Management
Project
• A project is an interrelated set of activities that has a definite
starting and ending point and that results in a unique product
or service.
Project management
• Project management is a scientific way of planning, implementing,
monitoring & controlling the various aspects of a project such as time,
money, materials, manpower & other resources.
Network Planning Methods
 Methods used for network planning are:
CPM
PERT
 Managing a project with network planning methods involves four steps:
1. Describing the Project.
2. Diagramming the Network.
3. Estimating time of completion.
4. Monitoring Project Progress.
Network Diagram
Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram
1. Before an activity can begin, its preceding
activities must be completed.
2. Arrows indicate logical precedence.
3. Flow of the diagram is from left to right.
4. Arrows should not intersect.
5. Dangling should be avoided.
APPRAOCHES FOR
NETWORK DIAGRAM
ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
to represent events.
• It is Event Oriented.
1 876
54
3
2
DUMMY ACTIVITY
AOA approach requires the addition of a Dummy
Activity to clarify the precedence relationships between
the two activities. It is a zero time activity and
consumes no resources.
Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
nodes
1 3
2
2) When two or more activities share the same
precedence activity but not all the precedence are
shared.
1 53
6
7
2 4
Uses nodes to represent activities and arcs indicate
precedence relationships between them.
It is Activity Oriented.
ACTIVITY ON NODE(AON):
ESTIMATING TIME
OF
COMPLETION
Planning the schedule of the project
Time estimates include:
1) Total time for completion.
2) ES- Earliest start time: the earliest time at which the activity
can start given that its precedent activities must be completed first.
3) EF-Earliest finish time: equals to the earliest start time for the activity
plus the time required to complete the activity.
4) LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
5) LS- Latest start time: equal to the latest finish time minus the time
required to complete the activity.
6) FORWARD PASS:
The early start and early finish times are calculated by
moving forward through the network and considering the
predecessor activities Considers maximum
7) BACKWARD PASS:
The latest start and finish times are calculated by moving backward through the
network.
Considers minimum
8) SLACK TIME:
Slack time for an activity is the difference between its earliest and latest start
time or between the earliest and latest finish time.
Critical path is the path of activities having zero Slack time.
A Simple Project
Activity Immediate
Predecessor
Expected
Time
A - 5
B - 6
C A 4
D A, B 2
Precedence Diagram
ES Earliest Starting (time)
EF Earliest Finishing
LS Latest Starting
LF Latest Finishing
Slack Difference Time
Pertcpm projectmanagement SIDDANNA M BALAPGOL
CRITICAL PATH
METHODS(CPM)
HISTORY :
It was developed by J.E.KELLY of REMINGTON-RAND
and M.R.WALKER of DU PONT and the emphasis was
on the trade-off between the cost of project and its overall
completion time. The first test was made in 1958,when CPM
was applied to the construction of a new chemical plant.
DEFINITION:
Critical path is the sequence of activities between a project’s
start and finish that takes the longest time to complete.
STEPS IN DETERMINING
CRITICAL PATH
• Specify the individual activities.
• Determine the sequence of the activities.
• Draw the network diagram.
• Estimate the activity completion time.
• Identify the critical path.
• Update the CPM diagram.
Activit
y
Preceden
ce
Normal time
(week)
Normal
Cost (Rs)
A - 3 300
B A 3 30
C A 7 420
D A 9 720
E D 5 250
F B,C,E 6 320
G F 4 400
H F 13 780
I G 10 1000
Total 4220
1
8
7
6
3
5
4
2
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
1
8
7
6
3
5
4
2
TIME ESTIMATES
o Optimistic time (to) – It is the shortest time in which the
activity can be completed.
o Most likely time (tm) – It is the probable time
required to perform the activity.
o Pessimistic time (tp) – It is the longest estimated time
required to perform an activity.
o Expected time
te = to + 4tm + tp
6
STEPS IN PERT
1. Identify the specific activities.
2. Determine proper sequence of the activities.
3. Construct the network diagram.
4. Estimate the time required for each activity.
5. Determine the critical path.
6. Update the PERT chart.
Activity Descrip
tion
Preced
ence
Optimis
tic time
Most
Likely
time
Pessimi
stic
time
Expecte
d time
A Initial
design
- 12 16 26 17
B Survey
market
A 6 9 18 10
C Build
prototype
A 8 10 18 11
D Test
prototype
C 2 3 4 3
E Redesign
ing
B,D 3 4 11 5
F Market
testing
E 6 8 10 8
G Set up
productio
n
F 15 20 25 20
1 7652
3
4
A-B-E-F-G = 60
A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT
• Expected project completion time.
• Probability of completion before a specified date.
• The critical path activities that directly impact the completion
time.
• The activities that have slack time and that can lend resources
to critical path activities.
• Activity start and end dates.
LIMITATIONS
• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
activities.
• Updating of the project is time consuming and requires high
costs.
• Emphasis is laid only on time factors and cost factors are
neglected.
Difference between
CPM & PERT
CPM PERT
• CPM works with fixed
deterministic time
• PERT works with probabilistic
time
• CPM is useful for repetitive and
non complex projects with a
certain degree of time estimates.
• PERT is useful for non repetitive
and complex projects with
uncertain time estimates.
• CPM includes time-cost trade off. • PERT is restricted to time
variable.
• CPM- for construction projects. • PERT- used for R&D programs.
Thank You…

More Related Content

PPTX
Project Management & Engineering Economics
PPTX
PPTX
CPM - Critical Path Method
PPTX
Critical path method
PPTX
The Critical Path Method
PPTX
Critical Path Method/ Program Evaluation and Review Technique
PDF
PERT AND CPM PROJECT MANAGEMENT
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
Project Management & Engineering Economics
CPM - Critical Path Method
Critical path method
The Critical Path Method
Critical Path Method/ Program Evaluation and Review Technique
PERT AND CPM PROJECT MANAGEMENT
CPM, Network Analysis A-O-A, A-O-N, Resource management

What's hot (19)

PPTX
Project presentation
PPTX
CPM - Critical Path Method
PPTX
Project networks
PPT
13 lecture project management
PPTX
Project Management - Critical path method
PPTX
Critical path method
PDF
Network construction
PPTX
Per tand project crashing
PPTX
Critical Path Method
PPTX
Critical path method
PPTX
Pert analysis
PDF
05 critical path analysis
PPT
Project management
PDF
Cpm (critical path method)
PPTX
Pb602 operation management chapter 7
PPT
Critical path method (cpm)
PPT
06 pert cpm
PPTX
Critical Path Method: Activities And Events, Float/Slacks
PPT
Critical Path Analysis
Project presentation
CPM - Critical Path Method
Project networks
13 lecture project management
Project Management - Critical path method
Critical path method
Network construction
Per tand project crashing
Critical Path Method
Critical path method
Pert analysis
05 critical path analysis
Project management
Cpm (critical path method)
Pb602 operation management chapter 7
Critical path method (cpm)
06 pert cpm
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Analysis
Ad

Similar to Pertcpm projectmanagement SIDDANNA M BALAPGOL (20)

PPTX
CPM AND PERT(critical path method) .pptx
PPTX
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
PPTX
Project Networking Techniques
PPTX
Network Techniques
PDF
Cpm n pert
PDF
CPM AND PERT
PPTX
MPA/BPA/TU-Project managemen PERT VS CPM
PPTX
Pert cpm
PPTX
Programme evaluation & review technique (pert)
PPT
CPM and PERT Presentation.ppt
PDF
project managment lesson mechanical engineering
PPT
PERT CPM Intro
PPT
06 pert cpm
PPT
Pert 182
PPT
chapter 6.ppt
PPT
PPT
Pert -cpm
PPT
Pert -cpm
PPT
06 pert cpm
PPTX
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
CPM AND PERT(critical path method) .pptx
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
Project Networking Techniques
Network Techniques
Cpm n pert
CPM AND PERT
MPA/BPA/TU-Project managemen PERT VS CPM
Pert cpm
Programme evaluation & review technique (pert)
CPM and PERT Presentation.ppt
project managment lesson mechanical engineering
PERT CPM Intro
06 pert cpm
Pert 182
chapter 6.ppt
Pert -cpm
Pert -cpm
06 pert cpm
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
Ad

More from Siddanna Balapgol (20)

PDF
Sitting is killing you siddanna Balapgol
PDF
SIDDANNA BALAPGOL
PDF
Vision life-income-plan-08-01-13
DOC
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
DOC
Sample mba final year project
PPT
Pride marketing14e basic_SIDDANNA M BALAPGOL
PPTX
Postpurchaseconsumerbehaviour 100318121357-phpapp02
PPT
Post purchasebehavior-SIDDANNA M BALAPGOL
PPT
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
PPT
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
PPT
Microencapsulation SIDDANNA M BALAPGOL
DOC
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
DOCX
Kotaklifeinsurance SIDDANNA M BALAPGOL
DOCX
Kotaklifeinsurance SIDDANNA M BALAPGOL
PPTX
Insuarancesector SIDDANNA M BALAPGOL
PDF
Forum the employeeorthecompany SIDDANNA M BALAPGOL
PPTX
Finalcommonwealthscam SIDDANNA M BALAPGOL
PPTX
Final presentation of scams SIDDANNA M BALAPGOL
PDF
Empower pension-plan-SIDDANNA M BALAPGOL
PPTX
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL
Sitting is killing you siddanna Balapgol
SIDDANNA BALAPGOL
Vision life-income-plan-08-01-13
Surveyquestionnaireformatforproject SIDDANNA M BALAPGOL
Sample mba final year project
Pride marketing14e basic_SIDDANNA M BALAPGOL
Postpurchaseconsumerbehaviour 100318121357-phpapp02
Post purchasebehavior-SIDDANNA M BALAPGOL
Optimizationtechniquesinpharmaceuticalprocessing SIDDANNA M BALAPGOL
Optimizationinpharmaceuticsprocessing SIDDANNA M BALAPGOL
Microencapsulation SIDDANNA M BALAPGOL
Lifeinsuranceprojectreport SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
Kotaklifeinsurance SIDDANNA M BALAPGOL
Insuarancesector SIDDANNA M BALAPGOL
Forum the employeeorthecompany SIDDANNA M BALAPGOL
Finalcommonwealthscam SIDDANNA M BALAPGOL
Final presentation of scams SIDDANNA M BALAPGOL
Empower pension-plan-SIDDANNA M BALAPGOL
Consumersatisfactionordissatisfactionf SIDDANNA M BALAPGOL

Recently uploaded (20)

PDF
Blood Collected straight from the donor into a blood bag and mixed with an an...
PDF
1911 Gold Corporate Presentation Aug 2025.pdf
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...
PDF
IFRS Notes in your pocket for study all the time
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
Comments on Crystal Cloud and Energy Star.pdf
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
Cours de Système d'information about ERP.pdf
PPTX
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
PDF
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
PDF
Introduction to Generative Engine Optimization (GEO)
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
Technical Architecture - Chainsys dataZap
Blood Collected straight from the donor into a blood bag and mixed with an an...
1911 Gold Corporate Presentation Aug 2025.pdf
Principles of Marketing, Industrial, Consumers,
Building a Smart Pet Ecosystem: A Full Introduction to Zhejiang Beijing Techn...
IFRS Notes in your pocket for study all the time
NEW - FEES STRUCTURES (01-july-2024).pdf
Module 2 - Modern Supervison Challenges - Student Resource.pdf
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Comments on Crystal Cloud and Energy Star.pdf
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Daniels 2024 Inclusive, Sustainable Development
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Cours de Système d'information about ERP.pdf
Sales & Distribution Management , LOGISTICS, Distribution, Sales Managers
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
Introduction to Generative Engine Optimization (GEO)
Charisse Litchman: A Maverick Making Neurological Care More Accessible
Technical Architecture - Chainsys dataZap

Pertcpm projectmanagement SIDDANNA M BALAPGOL

  • 1. PROJECT MANAGEMENT CPM & PERT TECHNIQUES
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress.
  • 5. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 6. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 7. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 1 876 54 3 2
  • 8. DUMMY ACTIVITY AOA approach requires the addition of a Dummy Activity to clarify the precedence relationships between the two activities. It is a zero time activity and consumes no resources. Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 9. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 53 6 7 2 4
  • 10. Uses nodes to represent activities and arcs indicate precedence relationships between them. It is Activity Oriented. ACTIVITY ON NODE(AON):
  • 11. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 12. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 13. A Simple Project Activity Immediate Predecessor Expected Time A - 5 B - 6 C A 4 D A, B 2
  • 15. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 17. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 18. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 19. Activit y Preceden ce Normal time (week) Normal Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 21. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 22. Critical path – A-D-F-G-I = 32 1 8 7 6 3 5 4 2
  • 23. TIME ESTIMATES o Optimistic time (to) – It is the shortest time in which the activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 24. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 25. Activity Descrip tion Preced ence Optimis tic time Most Likely time Pessimi stic time Expecte d time A Initial design - 12 16 26 17 B Survey market A 6 9 18 10 C Build prototype A 8 10 18 11 D Test prototype C 2 3 4 3 E Redesign ing B,D 3 4 11 5 F Market testing E 6 8 10 8 G Set up productio n F 15 20 25 20
  • 26. 1 7652 3 4 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH)
  • 27. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 28. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.
  • 29. Difference between CPM & PERT CPM PERT • CPM works with fixed deterministic time • PERT works with probabilistic time • CPM is useful for repetitive and non complex projects with a certain degree of time estimates. • PERT is useful for non repetitive and complex projects with uncertain time estimates. • CPM includes time-cost trade off. • PERT is restricted to time variable. • CPM- for construction projects. • PERT- used for R&D programs.