SlideShare a Scribd company logo
Chapter 9:
Project Communications
      Management
       adopted from PMI’s PMBOK 2000 and
Textbook : Information Technology Project Management




                                                       1
Contents
• Importance of Good Communications
• Project Communications Management Processes
   – Communications planning (planning phase)
   – Information distribution (executing phase)
   – Performance reporting (control phase)
   – Administrative closure (control phase)
• Creating a stakeholder analysis


                      Chapter 9                   2
Importance of Good Communications
• The greatest threat to many projects is a failure to
  communicate
   – Our culture does not portray IT professionals as being good
     communicators
   – Research shows that IT professionals must be able to communicate
     effectively to succeed in their positions
   – Strong verbal skills are a key factor in career advancement for IT
     professionals
• covering processes to ensure timely development,
  collection, disseminations, storage, and disposition of
  project information.
   – major output is the communications management plan.

                                Chapter 9                            3
Project Communications
         Management Processes
• There are 4 processes in Project Communications
  Management
   – Communications planning (planning)
      • determining the information and communications needs of
        the stakeholders
   – Information distribution (execution)
      • making needed information available in a timely manner
   – Performance reporting (control)
      • collecting and disseminating performance information
   – Administrative closure (closing)
      • generating, gathering, and disseminating information to
        formalize phase or project completion
                                                                  4
Communications Planning
• 14th of 21 planning phase process
• incorporates all planning required to ensure
  timely and appreciate development, collection,
  dissemination, storage, and disposition of project
  information.
• Every project should include some type of
  communications management plan, a document
  that guides project communications
• Creating a stakeholder analysis for project
  communications also aids in communications
  planning              Chapter 9                      5
Inputs to Communications
              Planning
• Communications requirement
   – include who needs what type of information, when they need the
     information, how to distribute the information (i.e. who, what,
     when how)
• Communications technology
   – methods and tools used to transfer information among
     stakeholders
   – face-to-face conversation, knowledge repository database, on-line
     schedules, email, video-conference, voice mail, stream video,
     newsletters and web sites.
• Constraints
   – restriction that affect the performance of the project.
• Assumptions
   – factors that for planning purposes                                6
Tools and techniques
• Stakeholder analysis
  – provides the methods and techniques to
    determine a systematic and logical view of the
    information requirements of stakeholders, and
    how to meet those needs.




                                                     7
Outputs from Communications
               Planning
•   Communications management plan (CMP)
    – An evolving document and a subsidiary component of the project plan,
      the CMP describes how to handle all communication on the project
    – It can be formal or informal, detailed or high-level, depending on the
      needs of the project.
•   CMP Contents
    – A description of a collection and filing structure for gathering and
      storing various types of information
    – A distribution structure describing what information goes to whom,
      when, and how
    – A format for communicating key project information
    – A project schedule for producing the information
    – Access methods for obtaining the information
    – A method for updating the communications management plans as the
      project progresses and develops
                                                                               8
Information Distribution
• 4th of 7 executing phase process
• involves making information that stakeholders
  need on a timely basis
   – Getting the right information to the right people at the
     right time and in a useful format is just as important
     as developing the information in the first place
• By properly executing the communications
  management plan
   – using the information retrieval and distribution tools
   – responding to unexpected requests for information
   – ensure all stakeholders have the information they
     need.                 Chapter 9                            9
The Impact of the Number of People on
      Communications Channels




                                        10
Inputs to Information
             Distribution
• Work results
   – results of activities performed to accomplish the
     project. Information on work results – completed and
     incomplete scheduled assignments and deliverables,
     actual and committed budget cost, how QA standards
     map to the result….
• Communications management plan (CMP)
   – describe all communication on the project is handled.
• Project plan
   – formal, approved document used to guide project
     execution and control.
                                                             11
Tools and techniques
• Communications skills
   – skills involving information exchanges. They are also part of the
     general management skills.
• Information retrieval system
   – tools in information distribution process
       • simple paper files, bound notebook, or they can be stored
         electronically as files or in a database
   – Retrieval systems are either filing system or software.
       • Commercial products such as Lotus Notes and Microsoft SharePoint
         are examples of applications software.
• Info distribution methods
   – distribution system (tools) include project meetings,
     correspondence, databases stored in a data warehouse, and video
     or audio conferences.
                                                                         12
Outputs from Information
            Distribution
• Project records
   – organized for easy access
       • includes correspondence, documents, and memos
   – Team will keep their own personal records for their assigned
     areas
   – Their personal records are often more detailed than the official
     project records.
• Project reports
   – formal reports on status and issues
• Project presentations
   – describe how the reports and records are presented to
     stakeholders
   – formal or informal. A great deal of a project manager’s job
                                                                        13
Performance Reporting
• 6th of 8 controlling phase process
   – collecting and distributing information to stakeholders on how
     the project is performing
• Performance reporting keeps stakeholders informed about
  how resources are being used to achieve project
  objectives
   – This process involves progress reports, status reports, and
     forecasts.
   – Status reports describe where the project stands at a specific
     point in time
   – Progress reports describe what the project team has accomplished
     during a certain period of time
   – Project forecasting predicts future project status and progress
     based on past information and trends
   – Status review meetings often include performance reporting
                                 Chapter 9                           14
Inputs to Performance Reporting
• Project plan
   – formal, approved document used to guide project execution and
     control.
   – includes subsidiary plans such as the communications plan, risk
     management plan, and quality plan. The plan sets a baseline to
     measure progress.
• Work result
   – results of activities performed to accomplish the project.
     Information on work results – completed and incomplete
     scheduled assignments and deliverables, actual and committed
     budget cost, how QA standards map to the result….
• Other project records
   – other documents such as blueprints, technical documents, or
     specifications documents.
                                                                       15
Tools and techniques
• Performance reviews
   – project meetings are held to evaluate status and progress.
• Variance analysis
   – compares results to planned results. Generally, the analysis is
     cost- and schedule-related.
• Trend analysis
   – examines project results over the dimension of time to see if
     pattern show performance improvement or deterioration.
• Earned value analysis
   – Integrates scope, cost and schedule measures. It compares actual
     results to planned result. Calculations are based on three key
     measures: Planned value, Actual cost, Earned value.
• Info distribution tools & techniques
   – includes all the tools and technique mentioned in Information      16
     distribution process.
Outputs from Performance
           Reporting
• Performance reports
  – contain organized and summarized results of project
    reports, correspondence, documents, and memos
  – If possible, use charts and graphs to summarize
    information
  – Some key documents are status report, progress
    report, trend report and forecast report.
• Change requests
  – ask for modifications to some deliverable or objective
  – These formal documents can also involve changes to
    a contract, even include contract termination.
                                                             17
Administrative Closure
• 1st of 2 closing phase process
• A project or phase of a project requires closure
   – closing the administrative functions takes place at the
     end of the project.
   – Because projects are temporary, project closure
     briefings and lessons-learned documents provide
     important feedback
   – They keep valuable knowledge inside the organization
     and contribute to improvements in the next cycle of
     project.

                           Chapter 9                       18
Inputs to Administrative Closure
• Performance measurements documents
   – includes all the performance-related documents used to guide,
     record, and analyze project planning, execution and control
   – Other documents such as status, progress, and forecast report
• Product documentation
   – show result of activities performed to create the product or
     service that the project was chartered to achieve
   – These include plans, technical documents, design documents,
     specifications, blueprints, drawings, and electronic files.
• Other project records
   – other related documents

                                                                     19
Tools and techniques
• Performance reporting tools and techniques
   – provide a feedback loop, solving the information needs of the
     various stakeholders and showing the interaction of all the tools
     used during the Performance Reporting phase just described.
   – Tools and techniques include performance reviews, variance
     analysis, trend analysis, and earned value analysis.
• Project reports
   – formal reports on status and issues
• Project presentations
   – describe how the reports and records are presented to
     stakeholders.
   – It can be formal or informal
   – A great deal of a project manager’s job involves doing this
     stakeholder presentation.                                           20
Outline for a Final Project Report




               Chapter 9             21
Sample Template for a Project
         Web Site




             Chapter 9          22
Outputs from Administrative
             Closure
• Project archives
   – this is the long-term storage of all project activity records
   – The information should be complete and indexed for easy
     retrieval.
• Formal acceptance
   – confirms by customer by formally accepts the completion of the
     project
       • all requirements have been fulfilled
   – These require may include staff performance reviews,
     budget/cost reports, and lessons-learned documents.
• Lessons learned
   – includes detailed information on how common and usual project
     events were resolved.
   – part of the organization’s knowledge base so the information can23
     be applied to future projects.
Suggestions for Improving Project
            Communications
•   Manage conflicts effectively
•   Develop better communication skills
•   Run effective meetings
•   Use templates for project communications




                      Chapter 9                24
Conflict Handling Modes, In Preference
                Order
• Problem-solving
   – also known as confrontation
   – directly face a conflict and resolve it at once
• Compromise
   – use a give-and-take approach
• Smoothing
   – de-emphasize areas of differences and emphasize areas of
     agreement
• Forcing
   – the win-lose approach
• Withdrawal
   – retreat or withdraw from an actual or potential disagreement
                                 Chapter 9                          25
Benefits of Problem-solving
• Problem solving often produces important
  results, such as new ideas, better
  alternatives, and motivation to work harder
  and more collaboratively
• Research by Karen Jehn suggests
  – task-related conflict often improves team
    performance
  – emotional conflict often depresses team
    performance
                       Chapter 9                26
Developing Better
        Communication Skills
• Companies and formal degree programs for IT
  professionals often neglect the importance of
  developing speaking, writing, and listening skills
• As organizations become more global, they
  realize they must invest in ways to improve
  communication with people from different
  countries and cultures
• It takes leadership to improve communication

                        Chapter 9                      27
Running Effective Meetings
• Determine if a meeting can be avoided
• Define the purpose and intended outcome of the
  meeting
• Determine who should attend the meeting
• Provide an agenda to participants before the
  meeting
• Prepare handouts, visual aids, and make logistical
  arrangements ahead of time
• Run the meeting professionally
• Build relationships
                        Chapter 9                  28
Developing a Communications
              Infrastructure
• A communications infrastructure is a set of tools,
  techniques, and principles that provide a foundation for
  the effective transfer of information
   – Tools include e-mail, project management software, groupware,
     fax machines, telephones, teleconferencing systems, document
     management systems, and word processors
   – Techniques include reporting guidelines and templates, meeting
     ground rules and procedures, decision-making processes,
     problem-solving approaches, and conflict resolution and
     negotiation techniques
   – Principles include using open dialog and an agreed upon work
     ethic

                               Chapter 9                              29
Using Software to Assist in Project
          Communications
• There are many software tools to aid in
  project communications
• The What Went Right? example describes
  several new web-based and wireless
  communications tools
• Microsoft Project 2000 includes several
  features to enhance communications

                   Chapter 9                30
Summary
• Importance of Good Communications
   – lack of good communications is one of the biggest threats to
     many project
   – strong verbal skill is a key factor
• Project Communications Management Processes
   – Communications planning:determining the information and
     communications needs of the stakeholders
   – Information distribution: making needed information available in
     a timely manner
   – Performance reporting: collecting and disseminating
     performance information
   – Administrative closure: generating, gathering, and disseminating
     information to formalize phase or project completion
                               Chapter 9                            31
Summary (2)
• Creating a stakeholder analysis
• Suggestions for Improving Project Communications
     – Manage conflicts effectively
     – Develop better communication skills
     – Run effective meetings
     – Use templates for project communications
•   Developing a Communications Infrastructure
     – Tools: e-mail, project management software,
       groupware, fax machines, telephones
     – Techniques: reporting guidelines and templates,
       meeting ground rules and procedures
     – Principles: open dialog and work ethic
                                Chapter 9                32

More Related Content

PPTX
Communication management
PDF
PMP_Project Communication Management
PPTX
Project communication management
PPTX
Project communications management
PDF
Project Management Concepts
PPTX
Project communication management
PPTX
Project communications management
PPTX
Project Risk Management
Communication management
PMP_Project Communication Management
Project communication management
Project communications management
Project Management Concepts
Project communication management
Project communications management
Project Risk Management

What's hot (20)

PPTX
Project communications management
PDF
Introduction to Project Management
PPT
Project communication management
PPTX
Planning phase of project
PPTX
Real example of PMO deployment
PPTX
Importance of Communication in Project Managment
PPTX
PMP Training - 10 project communication management
PPT
11. Project Communication Management
PPTX
Project management life cycle
PDF
Fundamentals of project management
PPT
Project Planning
PPTX
Project communication management
PPTX
Practical Project Management - full course
PPT
Project Management Tools and Techniques
PPTX
project management
PDF
Introduction to Project Management by Javid Hamdard
PPTX
Project Stakeholder Management - PMBOK6
PPTX
Project Management
PPT
How to set up a project management office (PMO)
Project communications management
Introduction to Project Management
Project communication management
Planning phase of project
Real example of PMO deployment
Importance of Communication in Project Managment
PMP Training - 10 project communication management
11. Project Communication Management
Project management life cycle
Fundamentals of project management
Project Planning
Project communication management
Practical Project Management - full course
Project Management Tools and Techniques
project management
Introduction to Project Management by Javid Hamdard
Project Stakeholder Management - PMBOK6
Project Management
How to set up a project management office (PMO)
Ad

Viewers also liked (18)

PPT
Communication. chpt 17
PPT
Coordination
PPTX
Coordination
 
PPTX
Principle of Management jbb 2
PPTX
Principle of Management - Communication Management & Interpersonal Skills
PPTX
Coordination presentation
PPT
Control techniques
PPT
Unit 7 controlling
PDF
PPT
Co ordination.ppt
PPTX
control techniques
PPTX
Techniques of controlling
PPT
Communications Management Presentation
PPT
Controlling ppt
PDF
Project communications management (PMBOK 5th Edition)
PPTX
Priciples of management ppt final
PPTX
14 Principles Of Management
Communication. chpt 17
Coordination
Coordination
 
Principle of Management jbb 2
Principle of Management - Communication Management & Interpersonal Skills
Coordination presentation
Control techniques
Unit 7 controlling
Co ordination.ppt
control techniques
Techniques of controlling
Communications Management Presentation
Controlling ppt
Project communications management (PMBOK 5th Edition)
Priciples of management ppt final
14 Principles Of Management
Ad

Similar to Project management communication (20)

PDF
Project Communications Management
PDF
ENGINEERING PROJECT COMMUNICATION MANAGEMENT.pdf
PPTX
Introduction to ict project management
PPT
LECTURE ONE _Introduction computer sience .ppt
PPTX
10.2 Manage Communication
PDF
PMP PMBOK5 Ch4 integration management
PPT
04 project integration management
PDF
C05.03-Communication.key.pdf
PPTX
10. Project Communications Management.pptx
PPTX
Communication Management
PPTX
10.3 Monitor Communication
PPSX
DISE - Introduction to Project Management
PPTX
10.1 Plan Communication Management
PPTX
10.1 Plan Communication Management
PDF
Chapter 1 - Intro to Software Project Management.pdf
PPTX
Chapter 1 Project Managertyement Framework.pptx
PPT
PPTX
Creating value from Software Development though Project management
PPT
Managing the information system project
PDF
Project Management Body of Knowledge. Chapters 1-3
Project Communications Management
ENGINEERING PROJECT COMMUNICATION MANAGEMENT.pdf
Introduction to ict project management
LECTURE ONE _Introduction computer sience .ppt
10.2 Manage Communication
PMP PMBOK5 Ch4 integration management
04 project integration management
C05.03-Communication.key.pdf
10. Project Communications Management.pptx
Communication Management
10.3 Monitor Communication
DISE - Introduction to Project Management
10.1 Plan Communication Management
10.1 Plan Communication Management
Chapter 1 - Intro to Software Project Management.pdf
Chapter 1 Project Managertyement Framework.pptx
Creating value from Software Development though Project management
Managing the information system project
Project Management Body of Knowledge. Chapters 1-3

Recently uploaded (20)

PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PDF
Indian roads congress 037 - 2012 Flexible pavement
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
History, Philosophy and sociology of education (1).pptx
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Indian roads congress 037 - 2012 Flexible pavement
FORM 1 BIOLOGY MIND MAPS and their schemes
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
202450812 BayCHI UCSC-SV 20250812 v17.pptx
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
Computing-Curriculum for Schools in Ghana
Share_Module_2_Power_conflict_and_negotiation.pptx
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Weekly quiz Compilation Jan -July 25.pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
B.Sc. DS Unit 2 Software Engineering.pptx
Introduction to pro and eukaryotes and differences.pptx
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf

Project management communication

  • 1. Chapter 9: Project Communications Management adopted from PMI’s PMBOK 2000 and Textbook : Information Technology Project Management 1
  • 2. Contents • Importance of Good Communications • Project Communications Management Processes – Communications planning (planning phase) – Information distribution (executing phase) – Performance reporting (control phase) – Administrative closure (control phase) • Creating a stakeholder analysis Chapter 9 2
  • 3. Importance of Good Communications • The greatest threat to many projects is a failure to communicate – Our culture does not portray IT professionals as being good communicators – Research shows that IT professionals must be able to communicate effectively to succeed in their positions – Strong verbal skills are a key factor in career advancement for IT professionals • covering processes to ensure timely development, collection, disseminations, storage, and disposition of project information. – major output is the communications management plan. Chapter 9 3
  • 4. Project Communications Management Processes • There are 4 processes in Project Communications Management – Communications planning (planning) • determining the information and communications needs of the stakeholders – Information distribution (execution) • making needed information available in a timely manner – Performance reporting (control) • collecting and disseminating performance information – Administrative closure (closing) • generating, gathering, and disseminating information to formalize phase or project completion 4
  • 5. Communications Planning • 14th of 21 planning phase process • incorporates all planning required to ensure timely and appreciate development, collection, dissemination, storage, and disposition of project information. • Every project should include some type of communications management plan, a document that guides project communications • Creating a stakeholder analysis for project communications also aids in communications planning Chapter 9 5
  • 6. Inputs to Communications Planning • Communications requirement – include who needs what type of information, when they need the information, how to distribute the information (i.e. who, what, when how) • Communications technology – methods and tools used to transfer information among stakeholders – face-to-face conversation, knowledge repository database, on-line schedules, email, video-conference, voice mail, stream video, newsletters and web sites. • Constraints – restriction that affect the performance of the project. • Assumptions – factors that for planning purposes 6
  • 7. Tools and techniques • Stakeholder analysis – provides the methods and techniques to determine a systematic and logical view of the information requirements of stakeholders, and how to meet those needs. 7
  • 8. Outputs from Communications Planning • Communications management plan (CMP) – An evolving document and a subsidiary component of the project plan, the CMP describes how to handle all communication on the project – It can be formal or informal, detailed or high-level, depending on the needs of the project. • CMP Contents – A description of a collection and filing structure for gathering and storing various types of information – A distribution structure describing what information goes to whom, when, and how – A format for communicating key project information – A project schedule for producing the information – Access methods for obtaining the information – A method for updating the communications management plans as the project progresses and develops 8
  • 9. Information Distribution • 4th of 7 executing phase process • involves making information that stakeholders need on a timely basis – Getting the right information to the right people at the right time and in a useful format is just as important as developing the information in the first place • By properly executing the communications management plan – using the information retrieval and distribution tools – responding to unexpected requests for information – ensure all stakeholders have the information they need. Chapter 9 9
  • 10. The Impact of the Number of People on Communications Channels 10
  • 11. Inputs to Information Distribution • Work results – results of activities performed to accomplish the project. Information on work results – completed and incomplete scheduled assignments and deliverables, actual and committed budget cost, how QA standards map to the result…. • Communications management plan (CMP) – describe all communication on the project is handled. • Project plan – formal, approved document used to guide project execution and control. 11
  • 12. Tools and techniques • Communications skills – skills involving information exchanges. They are also part of the general management skills. • Information retrieval system – tools in information distribution process • simple paper files, bound notebook, or they can be stored electronically as files or in a database – Retrieval systems are either filing system or software. • Commercial products such as Lotus Notes and Microsoft SharePoint are examples of applications software. • Info distribution methods – distribution system (tools) include project meetings, correspondence, databases stored in a data warehouse, and video or audio conferences. 12
  • 13. Outputs from Information Distribution • Project records – organized for easy access • includes correspondence, documents, and memos – Team will keep their own personal records for their assigned areas – Their personal records are often more detailed than the official project records. • Project reports – formal reports on status and issues • Project presentations – describe how the reports and records are presented to stakeholders – formal or informal. A great deal of a project manager’s job 13
  • 14. Performance Reporting • 6th of 8 controlling phase process – collecting and distributing information to stakeholders on how the project is performing • Performance reporting keeps stakeholders informed about how resources are being used to achieve project objectives – This process involves progress reports, status reports, and forecasts. – Status reports describe where the project stands at a specific point in time – Progress reports describe what the project team has accomplished during a certain period of time – Project forecasting predicts future project status and progress based on past information and trends – Status review meetings often include performance reporting Chapter 9 14
  • 15. Inputs to Performance Reporting • Project plan – formal, approved document used to guide project execution and control. – includes subsidiary plans such as the communications plan, risk management plan, and quality plan. The plan sets a baseline to measure progress. • Work result – results of activities performed to accomplish the project. Information on work results – completed and incomplete scheduled assignments and deliverables, actual and committed budget cost, how QA standards map to the result…. • Other project records – other documents such as blueprints, technical documents, or specifications documents. 15
  • 16. Tools and techniques • Performance reviews – project meetings are held to evaluate status and progress. • Variance analysis – compares results to planned results. Generally, the analysis is cost- and schedule-related. • Trend analysis – examines project results over the dimension of time to see if pattern show performance improvement or deterioration. • Earned value analysis – Integrates scope, cost and schedule measures. It compares actual results to planned result. Calculations are based on three key measures: Planned value, Actual cost, Earned value. • Info distribution tools & techniques – includes all the tools and technique mentioned in Information 16 distribution process.
  • 17. Outputs from Performance Reporting • Performance reports – contain organized and summarized results of project reports, correspondence, documents, and memos – If possible, use charts and graphs to summarize information – Some key documents are status report, progress report, trend report and forecast report. • Change requests – ask for modifications to some deliverable or objective – These formal documents can also involve changes to a contract, even include contract termination. 17
  • 18. Administrative Closure • 1st of 2 closing phase process • A project or phase of a project requires closure – closing the administrative functions takes place at the end of the project. – Because projects are temporary, project closure briefings and lessons-learned documents provide important feedback – They keep valuable knowledge inside the organization and contribute to improvements in the next cycle of project. Chapter 9 18
  • 19. Inputs to Administrative Closure • Performance measurements documents – includes all the performance-related documents used to guide, record, and analyze project planning, execution and control – Other documents such as status, progress, and forecast report • Product documentation – show result of activities performed to create the product or service that the project was chartered to achieve – These include plans, technical documents, design documents, specifications, blueprints, drawings, and electronic files. • Other project records – other related documents 19
  • 20. Tools and techniques • Performance reporting tools and techniques – provide a feedback loop, solving the information needs of the various stakeholders and showing the interaction of all the tools used during the Performance Reporting phase just described. – Tools and techniques include performance reviews, variance analysis, trend analysis, and earned value analysis. • Project reports – formal reports on status and issues • Project presentations – describe how the reports and records are presented to stakeholders. – It can be formal or informal – A great deal of a project manager’s job involves doing this stakeholder presentation. 20
  • 21. Outline for a Final Project Report Chapter 9 21
  • 22. Sample Template for a Project Web Site Chapter 9 22
  • 23. Outputs from Administrative Closure • Project archives – this is the long-term storage of all project activity records – The information should be complete and indexed for easy retrieval. • Formal acceptance – confirms by customer by formally accepts the completion of the project • all requirements have been fulfilled – These require may include staff performance reviews, budget/cost reports, and lessons-learned documents. • Lessons learned – includes detailed information on how common and usual project events were resolved. – part of the organization’s knowledge base so the information can23 be applied to future projects.
  • 24. Suggestions for Improving Project Communications • Manage conflicts effectively • Develop better communication skills • Run effective meetings • Use templates for project communications Chapter 9 24
  • 25. Conflict Handling Modes, In Preference Order • Problem-solving – also known as confrontation – directly face a conflict and resolve it at once • Compromise – use a give-and-take approach • Smoothing – de-emphasize areas of differences and emphasize areas of agreement • Forcing – the win-lose approach • Withdrawal – retreat or withdraw from an actual or potential disagreement Chapter 9 25
  • 26. Benefits of Problem-solving • Problem solving often produces important results, such as new ideas, better alternatives, and motivation to work harder and more collaboratively • Research by Karen Jehn suggests – task-related conflict often improves team performance – emotional conflict often depresses team performance Chapter 9 26
  • 27. Developing Better Communication Skills • Companies and formal degree programs for IT professionals often neglect the importance of developing speaking, writing, and listening skills • As organizations become more global, they realize they must invest in ways to improve communication with people from different countries and cultures • It takes leadership to improve communication Chapter 9 27
  • 28. Running Effective Meetings • Determine if a meeting can be avoided • Define the purpose and intended outcome of the meeting • Determine who should attend the meeting • Provide an agenda to participants before the meeting • Prepare handouts, visual aids, and make logistical arrangements ahead of time • Run the meeting professionally • Build relationships Chapter 9 28
  • 29. Developing a Communications Infrastructure • A communications infrastructure is a set of tools, techniques, and principles that provide a foundation for the effective transfer of information – Tools include e-mail, project management software, groupware, fax machines, telephones, teleconferencing systems, document management systems, and word processors – Techniques include reporting guidelines and templates, meeting ground rules and procedures, decision-making processes, problem-solving approaches, and conflict resolution and negotiation techniques – Principles include using open dialog and an agreed upon work ethic Chapter 9 29
  • 30. Using Software to Assist in Project Communications • There are many software tools to aid in project communications • The What Went Right? example describes several new web-based and wireless communications tools • Microsoft Project 2000 includes several features to enhance communications Chapter 9 30
  • 31. Summary • Importance of Good Communications – lack of good communications is one of the biggest threats to many project – strong verbal skill is a key factor • Project Communications Management Processes – Communications planning:determining the information and communications needs of the stakeholders – Information distribution: making needed information available in a timely manner – Performance reporting: collecting and disseminating performance information – Administrative closure: generating, gathering, and disseminating information to formalize phase or project completion Chapter 9 31
  • 32. Summary (2) • Creating a stakeholder analysis • Suggestions for Improving Project Communications – Manage conflicts effectively – Develop better communication skills – Run effective meetings – Use templates for project communications • Developing a Communications Infrastructure – Tools: e-mail, project management software, groupware, fax machines, telephones – Techniques: reporting guidelines and templates, meeting ground rules and procedures – Principles: open dialog and work ethic Chapter 9 32