SlideShare a Scribd company logo
Date
Nme
ID
Date
Kandy Stadium Project
1
CONTENT
List of Figures ……………………………………………………………………………… 04
List of Tables ………………………………………………………………………………. 05
Introduction ………………………………………………………………………………... 06
Project
❖ Task 01 …………………………………………………………………………...… 07
❖ Task 02 ……………………………………………………………………………... 15
❖ Task 03 ……………………………………………………………………………... 17
❖ Task 04 ……………………………………………………………………………... 20
❖ Task 05 ……………………………………………………………………………... 21
❖ Task 06 ……………………………………………………………………………... 25
❖ Task 07 ……………………………………………………………………………... 26
Conclusion …………………………………………………………………………………. 27
2
LIST OF FIGURES
Figure 01 - Gantt Chart for WBS Civil Engineering…………………………………......08
Figure 02 - Gantt Chart for WBS Mechanical Engineering…………………………......10
Figure 03 - Gantt Chart for WBS Electrical Engineering…………………………….... 12
Figure 04 - Gantt Chart for WBS Communication and IT Engineering…………….... 14
Figure 05 – AOA Diagram for WBS Electrical Engineering……………………….…...15
Figure 06 - Gantt Chart for WBS Master Plan……...…………………………………...18
Figure 07 - Gantt Chart for Full Project…………….……………………………………19
Figure 08 – Pre-Tax Cash Flow Diagram………………………………………………...24
3
LIST OF TABLES
Table 01 - WBS for Civil Engineering Scope of Work…………………………………...07
Table 02 - WBS for Mechanical Engineering Scope of Work…………………………...09
Table 03 - WBS for Electrical Engineering Scope of Work……………………………...11
Table 04 - WBS for Communication and IT Engineering Scope of Work……………...13
Table 05 – Critical Path Analysis and Slacks………...…………………………………...16
Table 06 - WBS for Master Plan Scope of Work……….………………………………...17
Table 07 – Loan Drawdown for the Project………….…………………………………...21
Table 08 – Annual Operations and Maintenance Costs...………………...……………...22
Table 09 – Annual Cash Inflows and Outflows…………………………………………...23
4
INTRODUCTION
Through the project management process, business needs and requirements are transformed
into deliverables or deliverables that the project should satisfy. This conversion process
consists of application of constraints such as time, cost, quality, motivation, application of
project management tools and technologies. It aims to introduce the principle of a project
management framework that supports various management such as construction, environment,
information technology. The principles of the project management framework include not only
proven practices that are widely applied but also innovative practices that appear in professions
demonstrated by case studies.
5
PROJECT
❖ TASK 01
➢ Civil Engineering
Table 01 – WBS for Civil Engineering Scope of Work
Activity Description Predecessors Weeks
AC Order all materials from the designed bill of quantities
and state that all materials are to be delivered to site
F 3
BC Mobilize equipment, machinery and personnel to site
offices
AC 4
CC Commence site preparation works AC 3
DC Carry out final surveying requirements CC 2
EC Pouring of the concrete footings DC 3
FC Start construction of the main stadium shell EC 26
GC Install the drainage systems for the main structure and
for the playing field area
FC 8
HC Begin construction of the roof canopy including the
retractable roof section
FC 15
IC Install the extensive plumbing network requirements EC 30
JC Install all door and window fittings IC 25
KC Start the construction if the six main concrete lighting
towers
GC 14
LC Commissioning of the complete civil works IC, GC, JC 6
6
Figure 01
16
12
9
12
8
22
3
4
3
2
3
26
8
15
30
25
14
6
1 21 41 61 81 101 121 141 161
A
B
C
D
E
F
AC
BC
CC
DC
EC
FC
GC
HC
IC
JC
KC
LC
Weeks
Activity Gantt Chart For WBS Civil Engineering
7
➢ Mechanical Engineering
Table 02 - WBS for Mechanical Engineering Scope of Work
Activity Description Predecessors Weeks
AM Order all materials from the design bill of quantities
and state that are to be delivered to site
F 3
BM Mobilize personnel to site office LC, AM 4
CM Install Air-conditioning Chillers BM 6
DM Install Condensers CM 6
EM Build the water reticulation network CM 7
FM Install all air conditioning ducting throughout
stadium
BM 18
GM Install and fine tune the motors for the retractable
roof
BM 8
HM Install the fire sprinkler system network throughout
the complex
EM 12
IM Ensure no leakage in all the air-conditioning ducts FM 4
JM Install the exhaust fans for the carpark as per the
design
FM 8
KM
Commissioning – Test all air-conditioning outlets to
ensure correct temperature, air speed and noise level.
Test fire sprinkler systems. Ensure that the retractable
roof functions as per the design.
EM, JM 6
8
Figure 02
16
12
9
12
8
22
3
4
3
2
3
26
8
15
30
25
14
6
3
4
6
6
7
18
8
12
4
8
6
1 21 41 61 81 101 121 141 161 181 201
A
B
C
D
E
F
AC
BC
CC
DC
EC
FC
GC
HC
IC
JC
KC
LC
AM
BM
CM
DM
EM
FM
GM
HM
IM
JM
KM
Weeks
Activity Gantt Chart For WBS Mechanical Engineering
9
➢ Electrical Engineering
Table 03 - WBS for Electrical Engineering Scope of Work
Activity Description Predecessors Weeks
AE Order all materials from the design bill of quantities
and state that are to be delivered to site
F 5
BE Mobilize personnel to site office LC, AE 4
CE Build concrete footings for the on-site mini sub-station
design
BE 4
DE Transport and install the two 15MVA transformers CE 5
EE Terminate the incoming 132kV overhead feeders from
Western Power
DE, GE 4
FE Terminate the second 132kV cable for from Western
Power for power robustness. This diverse cable is for
power reliability in the event of a fault on the primary
cable
EE 3
GE Equip the switch room with the main switchboard and
protection fuses and circuit breakers
BE 10
HE Install all sub switchboards GE 4
IE Install the uninterruptable power supply equipment in
the main switch room
FE 8
JE Install all the wiring reticulation throughout the
complex
HE 14
KE Install the protection equipment in the mini sub station IE 6
LE Install the dual diesel motors for stand-by power
generation in the event of a black out
JE, KE 6
ME Install all lighting throughout the complex including
the four hundred 300W globes for the main stadium
light towers and security lighting
GE 26
NE Commissioning – Check that we have power to all outlets, that all
lights work and that the protection works. Ensure that the under
an outage condition the diesel generators will start and provide
emergency power within 20 seconds.
ME, LE 9
10
Figure 03
16
12
9
12
8
22
3
4
3
2
3
26
8
15
30
25
14
6
5
4
4
5
4
3
10
4
8
14
6
6
26
9
1 51 101 151 201 251
A
B
C
D
E
F
AC
BC
CC
DC
EC
FC
GC
HC
IC
JC
KC
LC
AE
BE
CE
DE
EE
FE
GE
HE
IE
JE
KE
LE
ME
NE
Weeks
Activity Gantt Chart For WBS Electrical Engineering
11
➢ Communication and IT Engineering
Table 04 - WBS for Communications and IT Engineering Scope of Work
Activity Description Predecessors Weeks*
AT Order all materials from the design bill of quantities
and state that are to be delivered to site
F 3
BT Mobilize to site office LC, AT 2
CT Install main distribution frame to terminate copper
pairs in the communications room
BT 3
DT Install optic fiber termination racks to interface to
incoming main fibers from the Telstra network
CT 4
ET Install the router system for internet access CT 6
FT Install the battery backup supply for the total comms
network
BT, CT 6
GT Installation of the two mobile towers and antennas BT, DT 4
HT Install GSM4 mobile equipment racks GT 2
IT Install 4 large LED TV screens remotely controlled DT 3
JT Setup the comms for the main control room for media
use
ET, DT 8
KT Provide internet access to the public via WIFI hotspot ET 4
LT Install microphones and main speakers JT 3
MT Install the perimeter LED display for advertising
space
JT 4
NT Final test and Commissioning MT, LT, JT 8
12
Figure 04
16
12
9
12
8
22
3
4
3
2
3
26
8
15
30
25
14
6
3
2
3
4
6
6
4
2
3
8
4
3
4
8
1 21 41 61 81 101 121 141 161 181 201
A
B
C
D
E
F
AC
BC
CC
DC
EC
FC
GC
HC
IC
JC
KC
LC
AT
BT
CT
DT
ET
FT
GT
HT
IT
JT
KT
LT
MT
NT
Weeks
Activity Gantt Chart For WBS Communications and IT
Engineering
13
❖ Task 02
➢ Electrical Engineering
This AOA diagram obtained according to the table 03.
Figure 05
S
4BE
4CE
5DE
4EE
3FE
8IE
6KE
6LE
E
4HE
10GE
14JE
9NE
26ME
14
• Calculations according to above AOA diagram.
Table 05 – Critical Path Analysis and Slacks
Path Total weeks
for path
Slacks
BE-CE-DE-EE-FE-IE-KE-LE-NE 49 1
BE-GE-EE-FE-IE-KE-LE-NE 50 0(critical)
BE-GE-HE-JE-LE-NE 47 3
BE-GE-ME-NE 49 1
a. Critical path is BE-GE-EE-FE-IE-KE-LE-NE path.
b. Slacks for each path is given above table 05.
c. Delivery of the two 15MVA transformers which corresponds to the activity DE in the
work breakdown structure, could be delayed by 1 week without affecting the overall
completion time of the electrical engineering part of the project. Because this activity
DE is a part of 1st
Path and is not related to the critical path in the AOA diagram of
figure 5.
d. The installation of the protection equipment in the mini substation which corresponds
to activity KE in the work breakdown structure, could not be delayed by any weeks
without affecting to the project because activity KE is a part of the 2nd
Path which is
the critical path in the AOA diagram of figure 5. Therefore, activity KE cannot be
delayed as it will disrupt the total allowable weeks of the critical path and hence affect
the total project duration.
15
❖ Task 03
➢ Master Plan
Table 06 - WBS for Master Plan Scope of Work
Activity Description Predecessors Weeks
A Prepare Broad Scope of the Project Start
1/Jan/2016
16
B Seek Public Consultation A 12
C Prepare Business Case and Obtain Environmental
Approvals
B 9
D Commence and Close the Tender Period C 12
E Analyze and award contract to the winning tenderer. D 8
F Finalize and submit the detailed design of the Civil,
Electrical, Mechanical and the Comms IT
engineering works and wait for final approvals.
E 22
G The complete Construction Phase – for all Civil,
Electrical, Mechanical and the Comms IT
engineering scope of works
F TBD^
H Final Commissioning and Project Handover of the
total project and commemorate with the Premier at a
ribbon cutting ceremony
LC, KM, NE
and NT
7
• Total weeks to complete Civil Engineering works = 72 weeks
• Total weeks to complete Mechanical Engineering works = 36 weeks
• Total weeks to complete Electrical Engineering works = 50 weeks
• Total weeks to complete Communication and IT Engineering works = 31 weeks
• Total weeks to complete Master plan construction = 208 weeks
• Since Civil Engineering is necessary to be completed for the remaining construction
work to begin, Electrical Engineering is the next construction work which consumes
most amount of time.
Total number of weeks to complete activity G = 72 + 50 = 122 weeks.
16
Figure 06
16
12
9
12
8
22
122
7
1 51 101 151 201 251
A
B
C
D
E
F
G
H
Weeks
Activity Gantt Chart For WBS Master Plan
17
Figure 07
16
12
9
12
8
22
122
3
4
3
2
3
26
8
15
30
25
14
6
3
4
6
6
7
18
8
12
4
8
6
5
4
4
5
4
3
10
4
8
14
6
6
26
9
3
2
3
4
6
6
4
2
3
8
4
3
4
8
7
1 51 101 151 201 251
A
C
E
G
BC
DC
FC
HC
JC
LC
BM
DM
FM
HM
JM
AE
CE
EE
GE
IE
KE
ME
AT
CT
ET
GT
IT
KT
MT
H
Weeks
Activity Gantt Chart For Full Project
18
❖ Task 04
• Total weeks to complete master plan of project = 208 weeks
• Weeks per year = 52 weeks
Total years to complete the project = 208/52 = 4 years
Revenue equation:
• Maximum number of people per event = 70,000 people
• Expected number of people per year = 2,500,000 people
Total revenue for one event = (Premium cooperate) + (Under cover) + (Exposed)
Total revenue for one event = {(4N x 0.02) + (2N x 0.84) + (N x 0.14)} x 70,000
= (5,600N) + (117,600N) + (9,800N)
= 133,000N
• Assume, that the stadium is always with the maximum capacity at each event.
Number of events per year = 2,500,000/70,000
= 35.7
≈ 36 events
Hence revenue per year = 36 x 133,000N
= 4,788,000N $/year
= 4.788N m$/year
• m = millions (x106
).
19
❖ Task 05
• Assume,
a. Annual interest is calculated as a Simple Interest.
b. The loan with interest is paid back after the construction.
c. Since it is mentioned that the loan is to be financed over a 25-year period, it must
be noted that over the construction years, the interest will be accumulated.
Table 07 – Loan Drawdown for the Project
Year Percentage Drawdown Value
1 16% 136m
2 26% 221m
3 34% 289m
4 18% 153m
5 6% 51m
Total number of years taken to complete the construction phase = 4 years
Total number of payable years for the loan with interest = 25 – 4
= 21 years
Annual Interest rate = 8.5%
Annual Interest = $850m x 8.5%
= $72.25m /=
Total Interest (considering accumulation) = $72.25m x 25
= $1806.25m /=
20
Total payable loan with interest = $850m + $1806.25m
= $2656.25m /=
Annual loan instalment after construction = $2656.25m/ 21
= $126.5m /=
Table 08 – Annual Operations and Maintenance Costs
Operations and Maintenance Item Expected Annual Costs
Playing Field Turf up keep $2m
Painting $1m
General repairs from public damage $2m
General Maintenance and replacement of
used items- i.e. light globe replacement as
required
$2m
Office Staff Wages $3m
Security Personnel $3m
Event Management $2m
Total $15m
• After the 4-year construction, stadium will be started to conduct the events annually.
• When conducting events, there will be annual maintenance and operational costs for
the stadium.
• According to the above table, the expected annual maintenance and operation cost is
$15m.
• That annual maintenance and operation cost added with the annual loan instalment as
an annual expense for next 21 years.
• Hence the expected annual expense for next years is $141.5m.
• The expected annual income for next years is $4.788Nm.
• Considering all above expenses and incomes, the cash flow table and cash flow
diagrams for next 25 years are given below.
21
Table 09 – Annual Cash Inflows and Outflows
Year Cash Inflows ($) Cash Outflows ($)
0 850m 0
1 0 (136m)
2 0 (221m)
3 0 (289m)
4 0 (153m)
5 4.788mN (51m + 15m + 126.5m) = (192.5m)
6 4.788mN (141.5m)
7 4.788mN (141.5m)
8 4.788mN (141.5m)
9 4.788mN (141.5m)
10 4.788mN (141.5m)
11 4.788mN (141.5m)
12 4.788mN (141.5m)
13 4.788mN (141.5m)
14 4.788mN (141.5m)
15 4.788mN (141.5m)
16 4.788mN (141.5m)
17 4.788mN (141.5m)
18 4.788mN (141.5m)
19 4.788mN (141.5m)
20 4.788mN (141.5m)
21 4.788mN (141.5m)
22 4.788mN (141.5m)
23 4.788mN (141.5m)
24 4.788mN (141.5m)
25 4.788mN (141.5m)
• For simplicity and to better visualize the diagram clearly, N is substituted $25
(maximum pricing constraint by the government).
Assumed Revenue = $4.788m x 25 = $119.7 /=
22
• Assuming that the proposed borrowed funds as a capital for the project and the
drawdowns as expenditure distribution it is possible to illustrate the pre-tax cash flow
diagram for the project.
Figure 08
23
❖ Task 06
• Total Revenue = Total Expenses – Total Profit
• At the breakeven point, total profit should be zero.
Hence,
Total Revenue = Total Expenses
4.788Nm x 21 = (15m + 126.5m) x 21
N = (15m + 126.5m)/4.788
N = 29.55
The price of the exposed seating = $N
= $29.55/=
• The calculated value for exposed seating exceeds the $25 constraint imposed by the
government. Hence the ticket prices are not approvable.
24
❖ Task 07
• Power tactic
Power is a measure of a person's ability to control the environment around group, including the
behavior of group members. The use of power need not involve coercion. our team leader is
Yasiru. As a leader, he involves influence over us and power is always given to us. He has
ability to influence us through his knowledge and skills. Our leader essentially honest and
ethical man. And also, neutral with respect to ethics and manipulative. He always used logical
arguments to influence us and request us to do workable things and try to achieve goals. As a
group member, I think Yasiru is a good leader.
25
CONCLUSION
Based on the result of the study carried out for our project management report, we have realized
that project management has an important role in the construction industry. It means that an
effect of project management is all about planning, scheduling, monitoring, controlling and
reporting as well as about making decisions on required changes and the performance during
construction project. Every construction project must be able to provide a good planning to
achieve their goals. It will easily affect the cost, time to use and other activities in a construction
project. Therefore, the project management is a vital part in construction industry.
26
END OF REPORT

More Related Content

PPTX
ميادين الذكاء الاصطناعي
PDF
Brand Analysis: The North Face
PPTX
Ready mix concrete
PDF
PMP PMBOK 6th
PDF
The North Face - Advertising Strategy Plan
PDF
الذكاء الاصطناعى و تعلم الآلة
PPTX
Design of Football Stadium - Design Project for Civil Engineers
PDF
Construction Project Management
ميادين الذكاء الاصطناعي
Brand Analysis: The North Face
Ready mix concrete
PMP PMBOK 6th
The North Face - Advertising Strategy Plan
الذكاء الاصطناعى و تعلم الآلة
Design of Football Stadium - Design Project for Civil Engineers
Construction Project Management

What's hot (20)

PPT
Stadium Project
PDF
Construction Company Profile To Attract Clients Powerpoint Presentation Slides
DOC
project on construction of house report.
PPTX
Operational Management in steel plant
PPTX
Atal Rohtang Tunnel - construction process ,challenges and features
PPTX
Internship final presentation
PDF
Industrial training report
PDF
Jr. Civil Engineer Portfolio
DOCX
internship report report
PDF
50727481 checklist-for-site-works
PPTX
LARSEN AND TOUBRO
PPTX
Writing and Presenting an Industrial Training Report
DOCX
internship report
PPTX
Pestel analysis of steel industry
PPTX
My internship experience
PDF
Final Report for Summer internship at Software House
DOCX
Construction Planning and Scheduling of Residential Building by MS Project by...
PDF
Epc project interdepency and Work Flow- promo
PPTX
Stakeholder’s Involvement in Construction Industry
PPTX
Tender Process | A Complete Procurement Guide
Stadium Project
Construction Company Profile To Attract Clients Powerpoint Presentation Slides
project on construction of house report.
Operational Management in steel plant
Atal Rohtang Tunnel - construction process ,challenges and features
Internship final presentation
Industrial training report
Jr. Civil Engineer Portfolio
internship report report
50727481 checklist-for-site-works
LARSEN AND TOUBRO
Writing and Presenting an Industrial Training Report
internship report
Pestel analysis of steel industry
My internship experience
Final Report for Summer internship at Software House
Construction Planning and Scheduling of Residential Building by MS Project by...
Epc project interdepency and Work Flow- promo
Stakeholder’s Involvement in Construction Industry
Tender Process | A Complete Procurement Guide
Ad

Similar to Project management report of stadium (20)

DOCX
ICI FINAL REPORT
PDF
ICI FINAL REPORT PDF
PPTX
Antara Dashboard-002.pptx
PPTX
Projects Review Report
PPTX
Colt Hayes Planning Approach v1 220121.pptx
PPTX
Colt Hayes Planning Approach v1 220121.pptx
PDF
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
PDF
PDR Presentation
PPTX
Presentation for DHA on project progress(08-09-22).pptx
PPTX
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
PPTX
Presentation Project Review Meeting 25.4.25.pptx
DOCX
Coxwell Substation.docx
PDF
Buildings so r 14 15
PPTX
REVISED PRESENTATION According to a 2022 report by the International Forum fo...
PPTX
RS17 Contract and Depot Remodelling_28.03.2025.pptx
PPTX
Pune metro kickoff stage before starting phase
PDF
8015-0151-LM11-22-320-EL-WP-0278_00
PPTX
peneyediaan air minum regional perpipaan
PDF
IRJET- Structural Analysis and Design of Pump House
PPTX
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
ICI FINAL REPORT
ICI FINAL REPORT PDF
Antara Dashboard-002.pptx
Projects Review Report
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
PDR Presentation
Presentation for DHA on project progress(08-09-22).pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Presentation Project Review Meeting 25.4.25.pptx
Coxwell Substation.docx
Buildings so r 14 15
REVISED PRESENTATION According to a 2022 report by the International Forum fo...
RS17 Contract and Depot Remodelling_28.03.2025.pptx
Pune metro kickoff stage before starting phase
8015-0151-LM11-22-320-EL-WP-0278_00
peneyediaan air minum regional perpipaan
IRJET- Structural Analysis and Design of Pump House
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
Ad

Recently uploaded (20)

PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PPTX
Computer Architecture Input Output Memory.pptx
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
Indian roads congress 037 - 2012 Flexible pavement
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
History, Philosophy and sociology of education (1).pptx
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
My India Quiz Book_20210205121199924.pdf
PDF
Trump Administration's workforce development strategy
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
advance database management system book.pdf
PPTX
Introduction to Building Materials
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
1_English_Language_Set_2.pdf probationary
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Share_Module_2_Power_conflict_and_negotiation.pptx
Computer Architecture Input Output Memory.pptx
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
AI-driven educational solutions for real-life interventions in the Philippine...
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Indian roads congress 037 - 2012 Flexible pavement
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
LDMMIA Reiki Yoga Finals Review Spring Summer
History, Philosophy and sociology of education (1).pptx
202450812 BayCHI UCSC-SV 20250812 v17.pptx
My India Quiz Book_20210205121199924.pdf
Trump Administration's workforce development strategy
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
advance database management system book.pdf
Introduction to Building Materials
FORM 1 BIOLOGY MIND MAPS and their schemes
1_English_Language_Set_2.pdf probationary

Project management report of stadium

  • 2. 1 CONTENT List of Figures ……………………………………………………………………………… 04 List of Tables ………………………………………………………………………………. 05 Introduction ………………………………………………………………………………... 06 Project ❖ Task 01 …………………………………………………………………………...… 07 ❖ Task 02 ……………………………………………………………………………... 15 ❖ Task 03 ……………………………………………………………………………... 17 ❖ Task 04 ……………………………………………………………………………... 20 ❖ Task 05 ……………………………………………………………………………... 21 ❖ Task 06 ……………………………………………………………………………... 25 ❖ Task 07 ……………………………………………………………………………... 26 Conclusion …………………………………………………………………………………. 27
  • 3. 2 LIST OF FIGURES Figure 01 - Gantt Chart for WBS Civil Engineering…………………………………......08 Figure 02 - Gantt Chart for WBS Mechanical Engineering…………………………......10 Figure 03 - Gantt Chart for WBS Electrical Engineering…………………………….... 12 Figure 04 - Gantt Chart for WBS Communication and IT Engineering…………….... 14 Figure 05 – AOA Diagram for WBS Electrical Engineering……………………….…...15 Figure 06 - Gantt Chart for WBS Master Plan……...…………………………………...18 Figure 07 - Gantt Chart for Full Project…………….……………………………………19 Figure 08 – Pre-Tax Cash Flow Diagram………………………………………………...24
  • 4. 3 LIST OF TABLES Table 01 - WBS for Civil Engineering Scope of Work…………………………………...07 Table 02 - WBS for Mechanical Engineering Scope of Work…………………………...09 Table 03 - WBS for Electrical Engineering Scope of Work……………………………...11 Table 04 - WBS for Communication and IT Engineering Scope of Work……………...13 Table 05 – Critical Path Analysis and Slacks………...…………………………………...16 Table 06 - WBS for Master Plan Scope of Work……….………………………………...17 Table 07 – Loan Drawdown for the Project………….…………………………………...21 Table 08 – Annual Operations and Maintenance Costs...………………...……………...22 Table 09 – Annual Cash Inflows and Outflows…………………………………………...23
  • 5. 4 INTRODUCTION Through the project management process, business needs and requirements are transformed into deliverables or deliverables that the project should satisfy. This conversion process consists of application of constraints such as time, cost, quality, motivation, application of project management tools and technologies. It aims to introduce the principle of a project management framework that supports various management such as construction, environment, information technology. The principles of the project management framework include not only proven practices that are widely applied but also innovative practices that appear in professions demonstrated by case studies.
  • 6. 5 PROJECT ❖ TASK 01 ➢ Civil Engineering Table 01 – WBS for Civil Engineering Scope of Work Activity Description Predecessors Weeks AC Order all materials from the designed bill of quantities and state that all materials are to be delivered to site F 3 BC Mobilize equipment, machinery and personnel to site offices AC 4 CC Commence site preparation works AC 3 DC Carry out final surveying requirements CC 2 EC Pouring of the concrete footings DC 3 FC Start construction of the main stadium shell EC 26 GC Install the drainage systems for the main structure and for the playing field area FC 8 HC Begin construction of the roof canopy including the retractable roof section FC 15 IC Install the extensive plumbing network requirements EC 30 JC Install all door and window fittings IC 25 KC Start the construction if the six main concrete lighting towers GC 14 LC Commissioning of the complete civil works IC, GC, JC 6
  • 7. 6 Figure 01 16 12 9 12 8 22 3 4 3 2 3 26 8 15 30 25 14 6 1 21 41 61 81 101 121 141 161 A B C D E F AC BC CC DC EC FC GC HC IC JC KC LC Weeks Activity Gantt Chart For WBS Civil Engineering
  • 8. 7 ➢ Mechanical Engineering Table 02 - WBS for Mechanical Engineering Scope of Work Activity Description Predecessors Weeks AM Order all materials from the design bill of quantities and state that are to be delivered to site F 3 BM Mobilize personnel to site office LC, AM 4 CM Install Air-conditioning Chillers BM 6 DM Install Condensers CM 6 EM Build the water reticulation network CM 7 FM Install all air conditioning ducting throughout stadium BM 18 GM Install and fine tune the motors for the retractable roof BM 8 HM Install the fire sprinkler system network throughout the complex EM 12 IM Ensure no leakage in all the air-conditioning ducts FM 4 JM Install the exhaust fans for the carpark as per the design FM 8 KM Commissioning – Test all air-conditioning outlets to ensure correct temperature, air speed and noise level. Test fire sprinkler systems. Ensure that the retractable roof functions as per the design. EM, JM 6
  • 9. 8 Figure 02 16 12 9 12 8 22 3 4 3 2 3 26 8 15 30 25 14 6 3 4 6 6 7 18 8 12 4 8 6 1 21 41 61 81 101 121 141 161 181 201 A B C D E F AC BC CC DC EC FC GC HC IC JC KC LC AM BM CM DM EM FM GM HM IM JM KM Weeks Activity Gantt Chart For WBS Mechanical Engineering
  • 10. 9 ➢ Electrical Engineering Table 03 - WBS for Electrical Engineering Scope of Work Activity Description Predecessors Weeks AE Order all materials from the design bill of quantities and state that are to be delivered to site F 5 BE Mobilize personnel to site office LC, AE 4 CE Build concrete footings for the on-site mini sub-station design BE 4 DE Transport and install the two 15MVA transformers CE 5 EE Terminate the incoming 132kV overhead feeders from Western Power DE, GE 4 FE Terminate the second 132kV cable for from Western Power for power robustness. This diverse cable is for power reliability in the event of a fault on the primary cable EE 3 GE Equip the switch room with the main switchboard and protection fuses and circuit breakers BE 10 HE Install all sub switchboards GE 4 IE Install the uninterruptable power supply equipment in the main switch room FE 8 JE Install all the wiring reticulation throughout the complex HE 14 KE Install the protection equipment in the mini sub station IE 6 LE Install the dual diesel motors for stand-by power generation in the event of a black out JE, KE 6 ME Install all lighting throughout the complex including the four hundred 300W globes for the main stadium light towers and security lighting GE 26 NE Commissioning – Check that we have power to all outlets, that all lights work and that the protection works. Ensure that the under an outage condition the diesel generators will start and provide emergency power within 20 seconds. ME, LE 9
  • 11. 10 Figure 03 16 12 9 12 8 22 3 4 3 2 3 26 8 15 30 25 14 6 5 4 4 5 4 3 10 4 8 14 6 6 26 9 1 51 101 151 201 251 A B C D E F AC BC CC DC EC FC GC HC IC JC KC LC AE BE CE DE EE FE GE HE IE JE KE LE ME NE Weeks Activity Gantt Chart For WBS Electrical Engineering
  • 12. 11 ➢ Communication and IT Engineering Table 04 - WBS for Communications and IT Engineering Scope of Work Activity Description Predecessors Weeks* AT Order all materials from the design bill of quantities and state that are to be delivered to site F 3 BT Mobilize to site office LC, AT 2 CT Install main distribution frame to terminate copper pairs in the communications room BT 3 DT Install optic fiber termination racks to interface to incoming main fibers from the Telstra network CT 4 ET Install the router system for internet access CT 6 FT Install the battery backup supply for the total comms network BT, CT 6 GT Installation of the two mobile towers and antennas BT, DT 4 HT Install GSM4 mobile equipment racks GT 2 IT Install 4 large LED TV screens remotely controlled DT 3 JT Setup the comms for the main control room for media use ET, DT 8 KT Provide internet access to the public via WIFI hotspot ET 4 LT Install microphones and main speakers JT 3 MT Install the perimeter LED display for advertising space JT 4 NT Final test and Commissioning MT, LT, JT 8
  • 13. 12 Figure 04 16 12 9 12 8 22 3 4 3 2 3 26 8 15 30 25 14 6 3 2 3 4 6 6 4 2 3 8 4 3 4 8 1 21 41 61 81 101 121 141 161 181 201 A B C D E F AC BC CC DC EC FC GC HC IC JC KC LC AT BT CT DT ET FT GT HT IT JT KT LT MT NT Weeks Activity Gantt Chart For WBS Communications and IT Engineering
  • 14. 13 ❖ Task 02 ➢ Electrical Engineering This AOA diagram obtained according to the table 03. Figure 05 S 4BE 4CE 5DE 4EE 3FE 8IE 6KE 6LE E 4HE 10GE 14JE 9NE 26ME
  • 15. 14 • Calculations according to above AOA diagram. Table 05 – Critical Path Analysis and Slacks Path Total weeks for path Slacks BE-CE-DE-EE-FE-IE-KE-LE-NE 49 1 BE-GE-EE-FE-IE-KE-LE-NE 50 0(critical) BE-GE-HE-JE-LE-NE 47 3 BE-GE-ME-NE 49 1 a. Critical path is BE-GE-EE-FE-IE-KE-LE-NE path. b. Slacks for each path is given above table 05. c. Delivery of the two 15MVA transformers which corresponds to the activity DE in the work breakdown structure, could be delayed by 1 week without affecting the overall completion time of the electrical engineering part of the project. Because this activity DE is a part of 1st Path and is not related to the critical path in the AOA diagram of figure 5. d. The installation of the protection equipment in the mini substation which corresponds to activity KE in the work breakdown structure, could not be delayed by any weeks without affecting to the project because activity KE is a part of the 2nd Path which is the critical path in the AOA diagram of figure 5. Therefore, activity KE cannot be delayed as it will disrupt the total allowable weeks of the critical path and hence affect the total project duration.
  • 16. 15 ❖ Task 03 ➢ Master Plan Table 06 - WBS for Master Plan Scope of Work Activity Description Predecessors Weeks A Prepare Broad Scope of the Project Start 1/Jan/2016 16 B Seek Public Consultation A 12 C Prepare Business Case and Obtain Environmental Approvals B 9 D Commence and Close the Tender Period C 12 E Analyze and award contract to the winning tenderer. D 8 F Finalize and submit the detailed design of the Civil, Electrical, Mechanical and the Comms IT engineering works and wait for final approvals. E 22 G The complete Construction Phase – for all Civil, Electrical, Mechanical and the Comms IT engineering scope of works F TBD^ H Final Commissioning and Project Handover of the total project and commemorate with the Premier at a ribbon cutting ceremony LC, KM, NE and NT 7 • Total weeks to complete Civil Engineering works = 72 weeks • Total weeks to complete Mechanical Engineering works = 36 weeks • Total weeks to complete Electrical Engineering works = 50 weeks • Total weeks to complete Communication and IT Engineering works = 31 weeks • Total weeks to complete Master plan construction = 208 weeks • Since Civil Engineering is necessary to be completed for the remaining construction work to begin, Electrical Engineering is the next construction work which consumes most amount of time. Total number of weeks to complete activity G = 72 + 50 = 122 weeks.
  • 17. 16 Figure 06 16 12 9 12 8 22 122 7 1 51 101 151 201 251 A B C D E F G H Weeks Activity Gantt Chart For WBS Master Plan
  • 18. 17 Figure 07 16 12 9 12 8 22 122 3 4 3 2 3 26 8 15 30 25 14 6 3 4 6 6 7 18 8 12 4 8 6 5 4 4 5 4 3 10 4 8 14 6 6 26 9 3 2 3 4 6 6 4 2 3 8 4 3 4 8 7 1 51 101 151 201 251 A C E G BC DC FC HC JC LC BM DM FM HM JM AE CE EE GE IE KE ME AT CT ET GT IT KT MT H Weeks Activity Gantt Chart For Full Project
  • 19. 18 ❖ Task 04 • Total weeks to complete master plan of project = 208 weeks • Weeks per year = 52 weeks Total years to complete the project = 208/52 = 4 years Revenue equation: • Maximum number of people per event = 70,000 people • Expected number of people per year = 2,500,000 people Total revenue for one event = (Premium cooperate) + (Under cover) + (Exposed) Total revenue for one event = {(4N x 0.02) + (2N x 0.84) + (N x 0.14)} x 70,000 = (5,600N) + (117,600N) + (9,800N) = 133,000N • Assume, that the stadium is always with the maximum capacity at each event. Number of events per year = 2,500,000/70,000 = 35.7 ≈ 36 events Hence revenue per year = 36 x 133,000N = 4,788,000N $/year = 4.788N m$/year • m = millions (x106 ).
  • 20. 19 ❖ Task 05 • Assume, a. Annual interest is calculated as a Simple Interest. b. The loan with interest is paid back after the construction. c. Since it is mentioned that the loan is to be financed over a 25-year period, it must be noted that over the construction years, the interest will be accumulated. Table 07 – Loan Drawdown for the Project Year Percentage Drawdown Value 1 16% 136m 2 26% 221m 3 34% 289m 4 18% 153m 5 6% 51m Total number of years taken to complete the construction phase = 4 years Total number of payable years for the loan with interest = 25 – 4 = 21 years Annual Interest rate = 8.5% Annual Interest = $850m x 8.5% = $72.25m /= Total Interest (considering accumulation) = $72.25m x 25 = $1806.25m /=
  • 21. 20 Total payable loan with interest = $850m + $1806.25m = $2656.25m /= Annual loan instalment after construction = $2656.25m/ 21 = $126.5m /= Table 08 – Annual Operations and Maintenance Costs Operations and Maintenance Item Expected Annual Costs Playing Field Turf up keep $2m Painting $1m General repairs from public damage $2m General Maintenance and replacement of used items- i.e. light globe replacement as required $2m Office Staff Wages $3m Security Personnel $3m Event Management $2m Total $15m • After the 4-year construction, stadium will be started to conduct the events annually. • When conducting events, there will be annual maintenance and operational costs for the stadium. • According to the above table, the expected annual maintenance and operation cost is $15m. • That annual maintenance and operation cost added with the annual loan instalment as an annual expense for next 21 years. • Hence the expected annual expense for next years is $141.5m. • The expected annual income for next years is $4.788Nm. • Considering all above expenses and incomes, the cash flow table and cash flow diagrams for next 25 years are given below.
  • 22. 21 Table 09 – Annual Cash Inflows and Outflows Year Cash Inflows ($) Cash Outflows ($) 0 850m 0 1 0 (136m) 2 0 (221m) 3 0 (289m) 4 0 (153m) 5 4.788mN (51m + 15m + 126.5m) = (192.5m) 6 4.788mN (141.5m) 7 4.788mN (141.5m) 8 4.788mN (141.5m) 9 4.788mN (141.5m) 10 4.788mN (141.5m) 11 4.788mN (141.5m) 12 4.788mN (141.5m) 13 4.788mN (141.5m) 14 4.788mN (141.5m) 15 4.788mN (141.5m) 16 4.788mN (141.5m) 17 4.788mN (141.5m) 18 4.788mN (141.5m) 19 4.788mN (141.5m) 20 4.788mN (141.5m) 21 4.788mN (141.5m) 22 4.788mN (141.5m) 23 4.788mN (141.5m) 24 4.788mN (141.5m) 25 4.788mN (141.5m) • For simplicity and to better visualize the diagram clearly, N is substituted $25 (maximum pricing constraint by the government). Assumed Revenue = $4.788m x 25 = $119.7 /=
  • 23. 22 • Assuming that the proposed borrowed funds as a capital for the project and the drawdowns as expenditure distribution it is possible to illustrate the pre-tax cash flow diagram for the project. Figure 08
  • 24. 23 ❖ Task 06 • Total Revenue = Total Expenses – Total Profit • At the breakeven point, total profit should be zero. Hence, Total Revenue = Total Expenses 4.788Nm x 21 = (15m + 126.5m) x 21 N = (15m + 126.5m)/4.788 N = 29.55 The price of the exposed seating = $N = $29.55/= • The calculated value for exposed seating exceeds the $25 constraint imposed by the government. Hence the ticket prices are not approvable.
  • 25. 24 ❖ Task 07 • Power tactic Power is a measure of a person's ability to control the environment around group, including the behavior of group members. The use of power need not involve coercion. our team leader is Yasiru. As a leader, he involves influence over us and power is always given to us. He has ability to influence us through his knowledge and skills. Our leader essentially honest and ethical man. And also, neutral with respect to ethics and manipulative. He always used logical arguments to influence us and request us to do workable things and try to achieve goals. As a group member, I think Yasiru is a good leader.
  • 26. 25 CONCLUSION Based on the result of the study carried out for our project management report, we have realized that project management has an important role in the construction industry. It means that an effect of project management is all about planning, scheduling, monitoring, controlling and reporting as well as about making decisions on required changes and the performance during construction project. Every construction project must be able to provide a good planning to achieve their goals. It will easily affect the cost, time to use and other activities in a construction project. Therefore, the project management is a vital part in construction industry.