SlideShare a Scribd company logo
Applied Science University
                       Faculty of Engineering
                   Civil Engineering Department


       Project Management Using Primavera Project Planner




Subject:- Graduation Project Presented to the Civil Engineering Department.
Names:- Rashad Abulhaija - 200710466, Mohammed Abulebda - 200730024.
Supervised by:- Dr. Ghanem Baker.
Date: - May, 2012.
Table of Contents
Abstract                              1
Introduction                          4
Statement of the project              5
Objectives                            8
Importance of the project            17
Determining the Project Structure    18
Preparing the BoQ                   22
WBS                                 23
Project Management                  24
Generating Primavera                25
Conclusions & Recommendations       30
References                          31
Abstract


•   The main purpose of this study is to manage a residential building
    using Primavera Project Planner, by connecting activities through
    several relationships and by managing the duration of this project.

•   The expected results of this study is to be able to compress the
    duration using Work Breakdown Structure chart, and to reduce the
    overall cost.
Introduction

•   A project is a unique, one-time endeavour with a specific start and
    end, and a strict budget. Generally, projects are performed by
    people who have limited experience working together as a team. It’s
    also likely that some project participants will work off-site at
    several locations. These constraints often make project
    management difficult and complex.
•   At the conceptual level, project management is the process of
    thinking carefully about what you want to accomplish, laying out all
    the steps, and obtaining the resources required to carry out those
    steps. At the practical level, project management is your response
    to the problems, delays, changes, and obstacles—and, sometimes,
    opportunities—that arise during the course of a project.
•   Planning a project is fun: working out who does what, when, where,
    and with whom. The crucial part of successful project management,
    however, is the actions you take after the plan is created.
•   Successful project management requires dedication and constant
    vigilance: finding out what really happened, how much was actually
    accomplished, what remains to be done, and who will be available
    to do it. You must be prepared for the future. You need contingency
    plans that can handle the inevitable everyday realities of running
    the project.
•   Although no shortcuts exist for managing projects, some tools and
    practices can help prepare you for the job. Using project
    management software can organize your thinking and identify
    potential problems. Following established project procedures
    ensures that you inform the team about options, alternatives, and
    workarounds efficiently and in time. And presenting your project to
    upper management clearly and convincingly makes it easier to
    obtain their support when you need it.
•   The most important reason that P3 was created for was to make
    managing projects easier, especially when you encounter
    difficulties.
•   Primavera Project Planner (P3) provides an easy-to-use approach to
    project planning with an intuitive interface that makes project
    planning and control easy and fun, without sacrificing the powerful
    sophistication of high-end project-management software that you
    expect from Primavera.
•   P3 is a multiuser product that operates on popular local area
    networks such as Novell or Banyan Vines; it is compatible with
    SureTrakproject files, allowing you to share data with other
    network users, and with anyone who manages projects using
    Primavera software.
•   Thousands of serious project managers use Primavera Project
    Planner (P3) every day. It gives them the control they need to
    accomplish their projects on time, within the budget, and at a high
    level of technical quality.
Statement of the problem

•   After entering the activities to the primavera program and linking
    them by (Finish to start) relationships, we have faced a problem
    that the project will need 241 working days to finish which is too
    long for a two story building. This has occurred for us because of
    the FS relationship connections, which means that when the
    predecessor finishes start working on the successor activity.
•   So we will use the Primavera Project Planner to compress the
    project by connecting the activities with several relationship like:
    F.S, S.S, S.F, F.F, to result in compressed project consisting of 186
    working days.
Importance of the Study

•   The management of a project, is known as the organiser of the
    resources (primarily, but not exclusively, people and equipment) to
    achieve the goals of the project (critically timeliness).
•   In our study we are going to apply project management on a
    residential building using Primavera Project Planner P3, to show how
    can we compress a project duration, which will result in reducing
    costs & earning more time for our activities.
Objectives

•   To calculate a Bill of Quantities regarding a Residential Building.
•   To handle a WBS chart and to estimate the duration of the
    activities.
•   To Compress the duration of a project, so it results in reduction of
    the cost & the time.
•   To link activities through multiple and several types of
    relationships.
Determining the Project Structure

•   We will cover in our project the main roots of project planning using
    Primavera.
•   In our 1st chapter, we are going to discuss (Grad. Project 1) which
    indicates how did we calculate the BoQ. In the next chapter we are
    going to handle the levels of management. After that we will show
    how did we construct the WBS chart. Then taking place the activity
    insertion to the program with linking them. Finally we will add a
    conclusion & recommendations. Following that the references we
    looked back at.
Preparing the BoQ

•    The first level of our graduation project was to prepare the BoQ
     using hand calculation, the one attached in the appendix of the
     graduation book.
•    The BoQ is a table that shows the quantity and the cost of
     materials and equipment's demanded by a specified project.
•    In our study, we have took in consideration the calculation of the
     main materials demanded by a residential building such as:
a)    Excavation work.
b)    Casting Reinforced Concrete.
c)     Ribs.
d)    Finishing work.

In the following figures presented we will show you our projects BoQ.
No.    Description of Item            Qty      Unit   Rate     Rate in     Amount
                                                       in      Words
                                                      FIG
 1    Earthwork                                                            5454.8
                                                                             JD
1.1   Excavation under the           1125.84   M3     3.25      Three      4636 JD
      footing and tie beam to                          JD      Jordan
      the level of B.F., including                            Dinars and
      the removal of excess                                   a quarter.
      soil out of the site.
1.2   Filling the opposite side        96      M2     3 JD     Three       288 JD
      of the B.F. divided by the                               Jordan
      retaining wall, including                                Dinars.
      the compaction of soil
      every 30cm height with
      the needed materials.
1.3   Filling above the B.F.          177.6    M2     3 JD     Three       532.8 JD
      footing to a height of 1m,                               Jordan
      including the compaction                                 Dinars.
      of soil every 30cm height
      with the needed
      materials.
 2    Casting R.C.                                                         19048.6
                                                                              JD
2.1   For footings, columns, tie     174.75    M3     60 JD     Sixty       10,485
      beams, beams, SH, DR,                                    Jordan         JD
      stairs and slab with                                     Dinars.
      fc = 30N, including the
      formwork and the needed
      support system.
2.2   For blinding cast layer         54.7     M3     40 JD     Forty      2188 JD
      with fc = 17N, under                                    Jordan
      footings and tie beams,                                  Dinars.
      and above them.
2.3   For walls with fc =20N,       115.92    M3     55 JD   Fifty-five   6375.6
      including the formwork                                   Jordan        JD
      and the needed support                                   Dinars.
      system.
No.    Description of Item         Qty      Unit   Rate     Rate in     Amount
                                                    in      Words
                                                   FIG
 3    Ribs                                                              1309.1
                                                                           JD
3.1   18cm height, including       2014     Per    0.65    Sixty-five    1309.1
      the lifting and the                   unit    JD       Jordan        JD
      arranging.                                            Piasters.




 4    Plastering                                                        3900.26
                                                                          JD
4.1   Including two rough          1200.8   M2     3.25      Three      3900.26
      layers (1:4), and two soft                    JD      Jordan        JD
      layers (1:2).                                        Dinars and
                                                           a quarter.
 5    Painting                                                          3600.24
                                                                          JD
5.1   Cleaning the walls and       1200.8   M2     3 JD     Three       3600.24
      ceiling, then painting one                            Jordan        JD
      layer of basis to prevent                             Dinars.
      humidity, and two layers
      of paste, and one layer of
      Ameltion.
 6    Tiles                                                             7076.54
                                                                          JD
6.1   Ceramics for Bathrooms       148.54   M2     15 JD    Fifteen      2228.1
      and Kitchens walls,                                   Jordan        JD
      including the necessary                               Dinars.
      mortar and grout.
      Minimum dimension of
      ceramic is (25*25cm),
      and it`s a Jordanian first
      class.
6.2   Ceramics for bathrooms       39.57    M2     20 JD    Twenty      791.4 JD
      and kitchens floors,                                  Jordan
      including the necessary                               Dinars.
      mortar and grout, with a
      dimension of (45*45cm),
      and it should be a
      Jordanian first class.
No.    Description of Item        Qty      Unit   Rate    Rate in    Amount
                                                   in     Words
                                                  FIG
6.3   Mosaic for all floors       507.13   M2     8 JD     Eight     4057.04
      except for the stairs,                              Jordan       JD
      including the necessary                             Dinars.
      aggregate, mortar and
      grout.
      With a dimension of
      (30*30cm) and it should
      be a Jordanian first
      class.
 7    Marble                                                          524.4
                                                                       JD
7.1   Mosaic marble for stairs,    27.6    M2     19 JD   Nineteen   524.4 JD
      including the necessary                              Jordan
      mortar and grout.                                    Dinars.
      And It should be a
      Jordanian first class.
Merging WBS Chart

•   After we have calculated the BoQ, we had to settle down the levels
    of planning the project.
•   Planning a project is all about how to convert the processes into
    activities that could be managed technically by connecting these
    activities through critical timeliness relationships.
•   These activities could be managed by a Work Breakdown Structure
    method which in its turn we could divide the activities into main
    activities and secondary activities and so on. By that we could
    manage each activity duration and we can easily connect them by a
    PERT chart, which we could connect the activities through arrows
    that shows the relationships between them.
•   In the following WBS & relationship charts, we will show you how
    did we connect our project activities & estimated their duration
    based on the experiences of professional engineers through our
    first level of research which accounts for Finish to Start
    relationships.
Residential
                                                  Building

         1. Engineering                                                           2. Constructional
             Work                                                                         Work

   1.1        1.2 Shop Drawing           2.1 Structural                                                    2.3 Architechtural         2.4 Handing
                                                                                  2.2 MEP Work
 Material        Submittals                  Work                                                                Work                    Over
Submittals                                                                    2.2.1
                             2.1.1          2.1.2            2.1.3 Slab:                     2.2.2              2.3.1              2.4.1         2.4.2
                                                                            Electrical:    Mechanical:
                          Foundation:      Column &                                                            Finishing          Testing &     Cleaning
                                                             - Form work
                                             Wall:                          - Wall 1st       - Wall &           Work:           commissioning
                             - Site                               &
                                                                               fix           floor fix.
                            layout.       - Form work        scaffolding.                                       - Block
                                                                            (conduit).
                                               (1).          - Ribs                          - Final fix         work.
                          - Excavation
                                                                            - Floor 1st      (sanitary,
                             work.          - Steel       arrangement.                                          - Plaster
                                                                                fix         defusers..).
                                             work.        - Steel work.                                           work.
                           -Blinding                                         (conduit).
                           concrete.       - MEP 1st          - MEP 1st                                       - Tile work.
                                                                            - 2nd fix
                          - Form work.        fix.               fix.                                            - Paint
                                                                            (wiring).
                                          - Form work        - Concreting                                         work.
                      - Steel work.                                         - Final fix
                                              (2).               work.                                           - False
                           - MEP 1st                                        (fixtures).
                                          -Concreting.                                                           ceiling
                              fix.
                                                                                                                  work.
                      - Concreting.
                                                                                                                - Wood
                                                                                                                 work.
                                                                                                              - Aluminum
                                                                                                                 work.
Engineering   Foundation    Column &                                                                   Finishing
Milestone                                              Slab work      Block work    Electrical     Mechanical                         Handing
                work          work       wall work                                                                    work

                                                            Basement Floor

                 Shop      Site layout   Form work 1   Form work &                  Wall & floor   Wall & floor
                                                                       Block work                                  Plaster work
               drawing        1 day         5 days      scaffolding                     fix            fix
Start date                                                               7 days                                       5 days
              submittals                                   work                       2 days         1 day
               30 days                                    3 days

                           Excavation    Steel work
                             work                                                                                    Tile work
                                           5 days                                                                     4 days
                            3 days
               Material                                    Ribs
              submittals                               arrangement
                5 days                                    1 day
                                         MEP 1st fix                                                                Paint work
                             Blinding      1 day                                                                      5 days
                            concrete
                              1 day
                                                        Steel work
                                                          5 days
                                         Form work 2                                                              Electrical wiring
                                            2 days                                                                     1 day
                           Form work
                             4 days
                                                       MEP 1st fix
                                                         1 day
                                                                                                                    Mechanical
                                          Concreting
                                                                                                                     final fix
                           Steel work       1 day
                                                                                                                      1 day
                             6 days
                                                        Concreting
                                                          1 day

                                                                                                                    Wood work
                            MEP 1st                                                                                   1 day
                              fix
                                                        Curing time
                             1 day
                                                         10 days

                                                                                                                   Aluminim work
                                                                                                                      3 days
                           Concreting
                             1 day




                           Curing time
                            10 days
Block

              Engineering   Foundation     Column &                                 Electrical      Mechanical       Finishing          Handing
Milestone                                               Slab work      Block work
                 work          work        wall work                                  work            work             work              over

                                                              Ground Floor


                               Filling    Form work 1   Form work &                 Wall & floor   Wall & floor
                                                                       Block work                                  Plaster work         Testing &
                               work          7 days      scaffolding                    fix            fix
                                                                        10 days                                       7 days          commissioning
                              3 days                        work                      4 days         2 days
                                                                                                                                         1 day
                                                           5 days

                                          Steel work                                                                 Tile work
                            Form work       7 days                                                                    6 days            Cleaning
                              2 days                        Ribs
                                                                                                                                        2 days
                                                        arrangement
                                                           1 day
                                          MEP 1st fix                                                               Paint work
                            Steel work
                                            2 days                                                                    7 days
                              4 days
                                                        Steel work
                                                          7 days
                                          Form work 2                                                             Electrical wiring
                             MEP 1st                                                                                   2 days
                                             2 days
                               fix
                              1 day
                                                        MEP 1st fix
                                                          1 day
                                                                                                                    Mechanical
                                           Concreting
                                                                                                                     final fix
                            Concreting       1 day
                                                                                                                      2 days
                              1 day
                                                         Concreting
                                                           1 day

                                                                                                                    Wood work
                            Curing time                                                                              3 days
                             10 days                    Curing time
                                                         10 days

                                                                                                                   Aluminim work
                                                                                                                      3 days




Finish date
•   In the following charts we will show you the compressed
    relationships we have linked them through our second level of
    research, to reduce the total duration of the project.
Engineering   Foundation    Column &                                  Electrical     Mechanical       Finishing         Handing
Milestone                                              Slab work      Block work
                work          work       wall work                                   work           work             work             over

                                                            Basement Floor

                 Shop      Site layout   Form work 1   Form work &                 Wall & floor   Wall & floor
                                                                      Block work                                  Plaster work
               drawing        1 day         5 days      scaffolding                    fix            fix
Start date                                                              7 days                                       5 days
              submittals                                   work                      2 days         1 day
               30 days                                    3 days

                           Excavation
                                         Steel work                                                                 Tile work
                             work
                                           5 days                                                                    4 days
                            3 days
               Material                                    Ribs
              submittals                               arrangement
                5 days                                    1 day
                                         MEP 1st fix                                                               Paint work
                             Blinding      1 day                                                                     5 days
                            concrete
                              1 day
                                                       Steel work
                                                         5 days
                                         Form work 2                                                             Electrical wiring
                                            2 days                                                                    1 day
                           Form work
                             4 days
                                                       MEP 1st fix
                                                         1 day
                                                                                                                   Mechanical
                                          Concreting
                                                                                                                    final fix
                           Steel work       1 day
                                                                                                                     1 day
                             6 days
                                                        Concreting
                                                          1 day

                                                                                                                   Wood work
                            MEP 1st                                                                                  1 day
                              fix
                                                       Curing time
                             1 day
                                                        10 days

                                                                                                                  Aluminim work
                                                                                                                     3 days
                           Concreting
                             1 day




                           Curing time
                            10 days
Block work                                       Block

Milestones    Engineering   Foundation    Column &      Slab work      Block work        Electrical      Mechanical       Finishing          Handing
                 work          work       wall work                                        work            work             work              over

                                                              Ground Floor


                               Filling    Form work 1   Form work &                      Wall & floor   Wall & floor
                                                                       Block work                                       Plaster work         Testing &
                               work          7 days      scaffolding                         fix            fix
                                                                        10 days                                            7 days          commissioning
                              3 days                        work                           4 days         2 days
                                                                                                                                              1 day
                                                           5 days

                                          Steel work
                                                                                                                          Tile work
                            Form work       7 days
                                                                                                                           6 days            Cleaning
                              2 days                        Ribs
                                                                                                                                             2 days
                                                        arrangement
                                                           1 day
                                          MEP 1st fix                                                                    Paint work
                            Steel work      2 days                                                                         7 days
                              4 days
                                                        Steel work
                                                          7 days
                                          Form work 2                                                                  Electrical wiring
                             MEP 1st                                                                                        2 days
                                             2 days
                               fix
                              1 day
                                                        MEP 1st fix
                                                          1 day
                                                                                                                         Mechanical
                                           Concreting
                                                                                                                          final fix
                            Concreting       1 day
                                                                                                                           2 days
                              1 day
                                                         Concreting
                                                           1 day

                                                                                                                         Wood work
                            Curing time                                                                                   3 days
                             10 days
                                                        Curing time
                                                         10 days

                                                                                                                        Aluminim work
                                                                                                                           3 days




Finish date
Project Management

•   Project management is the discipline of planning, organizing,
    securing, managing, leading and controlling resources to achieve
    specific goals. A project is a temporary endeavour with a defined
    beginning and end (usually time-constrained, and often constrained
    by funding or deliverables), undertaken to meet unique goals and
    objectives, typically to bring about beneficial change or added value.
•   The temporary nature of projects stands in contrast with business
    as usual (or operations), which are repetitive, permanent or semi-
    permanent functional activities to produce products or services. In
    practice, the management of these two systems is often quite
    different, and as such requires the development of distinct
    technical skills and management strategies.
•   The primary challenge of project management is to achieve all of
    the project goals and objectives while honouring the preconceived
    constraints. Typical constraints are scope, time and budget. The
    secondary—and more ambitious—challenge is to optimize the
    allocation of necessary inputs and integrate them to meet pre-
    defined objectives.
Generating Primavera

•   P3 is special because project managers designed it for project
    managers. Project managers ask many questions—it seems to be
    their one common characteristic: “When will this be finished?”
    “Who’s doing the work?” “What happens if...?” “Suppose we...”
•   P3 answers questions quickly, easily, and accurately. You can select
    information from the database, sort data in dozens of different
    ways, condense details, and prepare graphic presentations—all
    without knowing anything about computers or database languages.
•   P3 helps you build a project network quickly and graphically.
•   P3 helps you from the moment you begin thinking about a project.
    Building the original network and organizing the project data in P3
    are simple. Use PERT to quickly add activities in a logic or flow
    diagram format, where boxes represent each activity; then use the
    Bar chart, which is a time scaled spread sheet, to review the
    schedule. If you prefer to remain in PERT, you can organize
    activities using a time scaled PERT layout to review the schedule by
    early start date.
•   After we had linked & estimated the durations of the project, we
    initiated inserting the activities into the program and we linked
    them through the first & second level of research.
•   In the following figures we will show you the three layouts of each
    level of research that we have managed to draw through the
    Primavera Project Planner. These layouts are customized each to
    meet with the criteria of their demanders.
•   The first figure shows all the main, the secondary and the
    subdivided activities which is always presented to the project
    managers.
•   The second figure shows only the main & the secondary activities
    only without including the subdivided activities, which is always
    presented to other co-worker engineers to secure the privacy of
    your linking method.
•   Finally the third figure shows only the main activities, which could
    be presented to the owner of the project because mainly they need
    the primary activities durations.
Project management using primavera project planner
Project management using primavera project planner
Project management using primavera project planner
Project management using primavera project planner
Project management using primavera project planner
Project management using primavera project planner
Conclusions & Recommendations

•   After settling down our study, we have been able to get onto the
    right track of the project management process, and actually it’s not
    as easy as it seems it’s more likely to be a science itself.
•   Through our research we have been able to expense the quantities
    of a residential building and to place the expenses in an standard
    BoQ table.
•   Then we have created a WBS chart to organise our activities
    through determining the primary activities and the secondary
    activities and by subdividing them.
•   After that we have created a relationship charts to link the
    activities through several relationships to result in critical
    timeliness activities.
•   Then we have initiated the Primavera Project Planner P3 to insert
    the activities and to link them as associated before.
•   Finally we have compressed the activities through crucial
    relationships to reduce the total duration of the project to result in
    reduction of the total cost.
•   After we have finished inserting the activities into the program, we
    have found that we could work through the program choosing a
    different method work. Like for our project, we have worked
    through this program using activity codes. But we have found that it
    could be done using the WBS style instead which in it’s turn can
    export the file to Primavera Project Planner P6, which in its turn is
    more easy to handle than the version we used.
References

More Related Content

PDF
KAFD Design Manual Guidelines
PDF
Techno-economic feasibility report (SSCP) Aug. 2004
PPT
Wbs For Building Project
PDF
A Course Material On Estimation And Quantity Surveying
PDF
PPTX
BIM Based Project Controls
KAFD Design Manual Guidelines
Techno-economic feasibility report (SSCP) Aug. 2004
Wbs For Building Project
A Course Material On Estimation And Quantity Surveying
BIM Based Project Controls

Similar to Project management using primavera project planner (20)

DOCX
Full report roman numbering combined
PDF
DADA - BIM Execution Plan (BEP) Template.pdf
PDF
Computer aided analysis_and_design_of_multi-storeyed_buildings
PPT
ie550capp.ppt
PDF
Partners in T Pluribus Unum, Sea of Glass V1, V2, V3.pdf
PPTX
FINAL PROJECT PPT PPT BINDU AND BATCH.pptx
PDF
Ar2615 report
PDF
Estimatingandcosting
PDF
Book estimating and-costing
PDF
Estimating and-costing
PDF
Estimating and-costing
PDF
Design of Pre-Engineered Building (PEB) Structure
PDF
Structural Design and Rehabilitation of Reinforced Concrete Structure
PPT
Contract adminstration and planning
PDF
Construction Project Schedule Example- Residential Building
PDF
Analysis of Geodesic dome structure
PDF
PLANNING AND DESIGN OF NET ZERO ENERGY RESIDENTIAL BUILDING
PDF
Estimating and costing
PDF
Estimating and-costing book
PDF
0wot6yjcrvypei6okja1 140601231108-phpapp02
Full report roman numbering combined
DADA - BIM Execution Plan (BEP) Template.pdf
Computer aided analysis_and_design_of_multi-storeyed_buildings
ie550capp.ppt
Partners in T Pluribus Unum, Sea of Glass V1, V2, V3.pdf
FINAL PROJECT PPT PPT BINDU AND BATCH.pptx
Ar2615 report
Estimatingandcosting
Book estimating and-costing
Estimating and-costing
Estimating and-costing
Design of Pre-Engineered Building (PEB) Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
Contract adminstration and planning
Construction Project Schedule Example- Residential Building
Analysis of Geodesic dome structure
PLANNING AND DESIGN OF NET ZERO ENERGY RESIDENTIAL BUILDING
Estimating and costing
Estimating and-costing book
0wot6yjcrvypei6okja1 140601231108-phpapp02
Ad

Recently uploaded (20)

PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
SBI Securities Weekly Wrap 08-08-2025_250808_205045.pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
IFRS Notes in your pocket for study all the time
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPT
Chapter four Project-Preparation material
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Digital Marketing & E-commerce Certificate Glossary.pdf.................
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Tata consultancy services case study shri Sharda college, basrur
PDF
Cours de Système d'information about ERP.pdf
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
Ôn tập tiếng anh trong kinh doanh nâng cao
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Daniels 2024 Inclusive, Sustainable Development
Deliverable file - Regulatory guideline analysis.pdf
SBI Securities Weekly Wrap 08-08-2025_250808_205045.pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx
Charisse Litchman: A Maverick Making Neurological Care More Accessible
IFRS Notes in your pocket for study all the time
ICG2025_ICG 6th steering committee 30-8-24.pptx
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Chapter four Project-Preparation material
Nidhal Samdaie CV - International Business Consultant
Digital Marketing & E-commerce Certificate Glossary.pdf.................
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Tata consultancy services case study shri Sharda college, basrur
Cours de Système d'information about ERP.pdf
Ad

Project management using primavera project planner

  • 1. Applied Science University Faculty of Engineering Civil Engineering Department Project Management Using Primavera Project Planner Subject:- Graduation Project Presented to the Civil Engineering Department. Names:- Rashad Abulhaija - 200710466, Mohammed Abulebda - 200730024. Supervised by:- Dr. Ghanem Baker. Date: - May, 2012.
  • 2. Table of Contents Abstract 1 Introduction 4 Statement of the project 5 Objectives 8 Importance of the project 17 Determining the Project Structure 18 Preparing the BoQ 22 WBS 23 Project Management 24 Generating Primavera 25 Conclusions & Recommendations 30 References 31
  • 3. Abstract • The main purpose of this study is to manage a residential building using Primavera Project Planner, by connecting activities through several relationships and by managing the duration of this project. • The expected results of this study is to be able to compress the duration using Work Breakdown Structure chart, and to reduce the overall cost.
  • 4. Introduction • A project is a unique, one-time endeavour with a specific start and end, and a strict budget. Generally, projects are performed by people who have limited experience working together as a team. It’s also likely that some project participants will work off-site at several locations. These constraints often make project management difficult and complex. • At the conceptual level, project management is the process of thinking carefully about what you want to accomplish, laying out all the steps, and obtaining the resources required to carry out those steps. At the practical level, project management is your response to the problems, delays, changes, and obstacles—and, sometimes, opportunities—that arise during the course of a project.
  • 5. Planning a project is fun: working out who does what, when, where, and with whom. The crucial part of successful project management, however, is the actions you take after the plan is created. • Successful project management requires dedication and constant vigilance: finding out what really happened, how much was actually accomplished, what remains to be done, and who will be available to do it. You must be prepared for the future. You need contingency plans that can handle the inevitable everyday realities of running the project. • Although no shortcuts exist for managing projects, some tools and practices can help prepare you for the job. Using project management software can organize your thinking and identify potential problems. Following established project procedures ensures that you inform the team about options, alternatives, and workarounds efficiently and in time. And presenting your project to upper management clearly and convincingly makes it easier to obtain their support when you need it.
  • 6. The most important reason that P3 was created for was to make managing projects easier, especially when you encounter difficulties. • Primavera Project Planner (P3) provides an easy-to-use approach to project planning with an intuitive interface that makes project planning and control easy and fun, without sacrificing the powerful sophistication of high-end project-management software that you expect from Primavera. • P3 is a multiuser product that operates on popular local area networks such as Novell or Banyan Vines; it is compatible with SureTrakproject files, allowing you to share data with other network users, and with anyone who manages projects using Primavera software. • Thousands of serious project managers use Primavera Project Planner (P3) every day. It gives them the control they need to accomplish their projects on time, within the budget, and at a high level of technical quality.
  • 7. Statement of the problem • After entering the activities to the primavera program and linking them by (Finish to start) relationships, we have faced a problem that the project will need 241 working days to finish which is too long for a two story building. This has occurred for us because of the FS relationship connections, which means that when the predecessor finishes start working on the successor activity. • So we will use the Primavera Project Planner to compress the project by connecting the activities with several relationship like: F.S, S.S, S.F, F.F, to result in compressed project consisting of 186 working days.
  • 8. Importance of the Study • The management of a project, is known as the organiser of the resources (primarily, but not exclusively, people and equipment) to achieve the goals of the project (critically timeliness). • In our study we are going to apply project management on a residential building using Primavera Project Planner P3, to show how can we compress a project duration, which will result in reducing costs & earning more time for our activities.
  • 9. Objectives • To calculate a Bill of Quantities regarding a Residential Building. • To handle a WBS chart and to estimate the duration of the activities. • To Compress the duration of a project, so it results in reduction of the cost & the time. • To link activities through multiple and several types of relationships.
  • 10. Determining the Project Structure • We will cover in our project the main roots of project planning using Primavera. • In our 1st chapter, we are going to discuss (Grad. Project 1) which indicates how did we calculate the BoQ. In the next chapter we are going to handle the levels of management. After that we will show how did we construct the WBS chart. Then taking place the activity insertion to the program with linking them. Finally we will add a conclusion & recommendations. Following that the references we looked back at.
  • 11. Preparing the BoQ • The first level of our graduation project was to prepare the BoQ using hand calculation, the one attached in the appendix of the graduation book. • The BoQ is a table that shows the quantity and the cost of materials and equipment's demanded by a specified project. • In our study, we have took in consideration the calculation of the main materials demanded by a residential building such as: a) Excavation work. b) Casting Reinforced Concrete. c) Ribs. d) Finishing work. In the following figures presented we will show you our projects BoQ.
  • 12. No. Description of Item Qty Unit Rate Rate in Amount in Words FIG 1 Earthwork 5454.8 JD 1.1 Excavation under the 1125.84 M3 3.25 Three 4636 JD footing and tie beam to JD Jordan the level of B.F., including Dinars and the removal of excess a quarter. soil out of the site. 1.2 Filling the opposite side 96 M2 3 JD Three 288 JD of the B.F. divided by the Jordan retaining wall, including Dinars. the compaction of soil every 30cm height with the needed materials. 1.3 Filling above the B.F. 177.6 M2 3 JD Three 532.8 JD footing to a height of 1m, Jordan including the compaction Dinars. of soil every 30cm height with the needed materials. 2 Casting R.C. 19048.6 JD 2.1 For footings, columns, tie 174.75 M3 60 JD Sixty 10,485 beams, beams, SH, DR, Jordan JD stairs and slab with Dinars. fc = 30N, including the formwork and the needed support system. 2.2 For blinding cast layer 54.7 M3 40 JD Forty 2188 JD with fc = 17N, under Jordan footings and tie beams, Dinars. and above them. 2.3 For walls with fc =20N, 115.92 M3 55 JD Fifty-five 6375.6 including the formwork Jordan JD and the needed support Dinars. system.
  • 13. No. Description of Item Qty Unit Rate Rate in Amount in Words FIG 3 Ribs 1309.1 JD 3.1 18cm height, including 2014 Per 0.65 Sixty-five 1309.1 the lifting and the unit JD Jordan JD arranging. Piasters. 4 Plastering 3900.26 JD 4.1 Including two rough 1200.8 M2 3.25 Three 3900.26 layers (1:4), and two soft JD Jordan JD layers (1:2). Dinars and a quarter. 5 Painting 3600.24 JD 5.1 Cleaning the walls and 1200.8 M2 3 JD Three 3600.24 ceiling, then painting one Jordan JD layer of basis to prevent Dinars. humidity, and two layers of paste, and one layer of Ameltion. 6 Tiles 7076.54 JD 6.1 Ceramics for Bathrooms 148.54 M2 15 JD Fifteen 2228.1 and Kitchens walls, Jordan JD including the necessary Dinars. mortar and grout. Minimum dimension of ceramic is (25*25cm), and it`s a Jordanian first class. 6.2 Ceramics for bathrooms 39.57 M2 20 JD Twenty 791.4 JD and kitchens floors, Jordan including the necessary Dinars. mortar and grout, with a dimension of (45*45cm), and it should be a Jordanian first class.
  • 14. No. Description of Item Qty Unit Rate Rate in Amount in Words FIG 6.3 Mosaic for all floors 507.13 M2 8 JD Eight 4057.04 except for the stairs, Jordan JD including the necessary Dinars. aggregate, mortar and grout. With a dimension of (30*30cm) and it should be a Jordanian first class. 7 Marble 524.4 JD 7.1 Mosaic marble for stairs, 27.6 M2 19 JD Nineteen 524.4 JD including the necessary Jordan mortar and grout. Dinars. And It should be a Jordanian first class.
  • 15. Merging WBS Chart • After we have calculated the BoQ, we had to settle down the levels of planning the project. • Planning a project is all about how to convert the processes into activities that could be managed technically by connecting these activities through critical timeliness relationships. • These activities could be managed by a Work Breakdown Structure method which in its turn we could divide the activities into main activities and secondary activities and so on. By that we could manage each activity duration and we can easily connect them by a PERT chart, which we could connect the activities through arrows that shows the relationships between them. • In the following WBS & relationship charts, we will show you how did we connect our project activities & estimated their duration based on the experiences of professional engineers through our first level of research which accounts for Finish to Start relationships.
  • 16. Residential Building 1. Engineering 2. Constructional Work Work 1.1 1.2 Shop Drawing 2.1 Structural 2.3 Architechtural 2.4 Handing 2.2 MEP Work Material Submittals Work Work Over Submittals 2.2.1 2.1.1 2.1.2 2.1.3 Slab: 2.2.2 2.3.1 2.4.1 2.4.2 Electrical: Mechanical: Foundation: Column & Finishing Testing & Cleaning - Form work Wall: - Wall 1st - Wall & Work: commissioning - Site & fix floor fix. layout. - Form work scaffolding. - Block (conduit). (1). - Ribs - Final fix work. - Excavation - Floor 1st (sanitary, work. - Steel arrangement. - Plaster fix defusers..). work. - Steel work. work. -Blinding (conduit). concrete. - MEP 1st - MEP 1st - Tile work. - 2nd fix - Form work. fix. fix. - Paint (wiring). - Form work - Concreting work. - Steel work. - Final fix (2). work. - False - MEP 1st (fixtures). -Concreting. ceiling fix. work. - Concreting. - Wood work. - Aluminum work.
  • 17. Engineering Foundation Column & Finishing Milestone Slab work Block work Electrical Mechanical Handing work work wall work work Basement Floor Shop Site layout Form work 1 Form work & Wall & floor Wall & floor Block work Plaster work drawing 1 day 5 days scaffolding fix fix Start date 7 days 5 days submittals work 2 days 1 day 30 days 3 days Excavation Steel work work Tile work 5 days 4 days 3 days Material Ribs submittals arrangement 5 days 1 day MEP 1st fix Paint work Blinding 1 day 5 days concrete 1 day Steel work 5 days Form work 2 Electrical wiring 2 days 1 day Form work 4 days MEP 1st fix 1 day Mechanical Concreting final fix Steel work 1 day 1 day 6 days Concreting 1 day Wood work MEP 1st 1 day fix Curing time 1 day 10 days Aluminim work 3 days Concreting 1 day Curing time 10 days
  • 18. Block Engineering Foundation Column & Electrical Mechanical Finishing Handing Milestone Slab work Block work work work wall work work work work over Ground Floor Filling Form work 1 Form work & Wall & floor Wall & floor Block work Plaster work Testing & work 7 days scaffolding fix fix 10 days 7 days commissioning 3 days work 4 days 2 days 1 day 5 days Steel work Tile work Form work 7 days 6 days Cleaning 2 days Ribs 2 days arrangement 1 day MEP 1st fix Paint work Steel work 2 days 7 days 4 days Steel work 7 days Form work 2 Electrical wiring MEP 1st 2 days 2 days fix 1 day MEP 1st fix 1 day Mechanical Concreting final fix Concreting 1 day 2 days 1 day Concreting 1 day Wood work Curing time 3 days 10 days Curing time 10 days Aluminim work 3 days Finish date
  • 19. In the following charts we will show you the compressed relationships we have linked them through our second level of research, to reduce the total duration of the project.
  • 20. Engineering Foundation Column & Electrical Mechanical Finishing Handing Milestone Slab work Block work work work wall work work work work over Basement Floor Shop Site layout Form work 1 Form work & Wall & floor Wall & floor Block work Plaster work drawing 1 day 5 days scaffolding fix fix Start date 7 days 5 days submittals work 2 days 1 day 30 days 3 days Excavation Steel work Tile work work 5 days 4 days 3 days Material Ribs submittals arrangement 5 days 1 day MEP 1st fix Paint work Blinding 1 day 5 days concrete 1 day Steel work 5 days Form work 2 Electrical wiring 2 days 1 day Form work 4 days MEP 1st fix 1 day Mechanical Concreting final fix Steel work 1 day 1 day 6 days Concreting 1 day Wood work MEP 1st 1 day fix Curing time 1 day 10 days Aluminim work 3 days Concreting 1 day Curing time 10 days
  • 21. Block work Block Milestones Engineering Foundation Column & Slab work Block work Electrical Mechanical Finishing Handing work work wall work work work work over Ground Floor Filling Form work 1 Form work & Wall & floor Wall & floor Block work Plaster work Testing & work 7 days scaffolding fix fix 10 days 7 days commissioning 3 days work 4 days 2 days 1 day 5 days Steel work Tile work Form work 7 days 6 days Cleaning 2 days Ribs 2 days arrangement 1 day MEP 1st fix Paint work Steel work 2 days 7 days 4 days Steel work 7 days Form work 2 Electrical wiring MEP 1st 2 days 2 days fix 1 day MEP 1st fix 1 day Mechanical Concreting final fix Concreting 1 day 2 days 1 day Concreting 1 day Wood work Curing time 3 days 10 days Curing time 10 days Aluminim work 3 days Finish date
  • 22. Project Management • Project management is the discipline of planning, organizing, securing, managing, leading and controlling resources to achieve specific goals. A project is a temporary endeavour with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables), undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. • The temporary nature of projects stands in contrast with business as usual (or operations), which are repetitive, permanent or semi- permanent functional activities to produce products or services. In practice, the management of these two systems is often quite different, and as such requires the development of distinct technical skills and management strategies.
  • 23. The primary challenge of project management is to achieve all of the project goals and objectives while honouring the preconceived constraints. Typical constraints are scope, time and budget. The secondary—and more ambitious—challenge is to optimize the allocation of necessary inputs and integrate them to meet pre- defined objectives.
  • 24. Generating Primavera • P3 is special because project managers designed it for project managers. Project managers ask many questions—it seems to be their one common characteristic: “When will this be finished?” “Who’s doing the work?” “What happens if...?” “Suppose we...” • P3 answers questions quickly, easily, and accurately. You can select information from the database, sort data in dozens of different ways, condense details, and prepare graphic presentations—all without knowing anything about computers or database languages. • P3 helps you build a project network quickly and graphically. • P3 helps you from the moment you begin thinking about a project. Building the original network and organizing the project data in P3 are simple. Use PERT to quickly add activities in a logic or flow diagram format, where boxes represent each activity; then use the Bar chart, which is a time scaled spread sheet, to review the schedule. If you prefer to remain in PERT, you can organize activities using a time scaled PERT layout to review the schedule by early start date.
  • 25. After we had linked & estimated the durations of the project, we initiated inserting the activities into the program and we linked them through the first & second level of research. • In the following figures we will show you the three layouts of each level of research that we have managed to draw through the Primavera Project Planner. These layouts are customized each to meet with the criteria of their demanders. • The first figure shows all the main, the secondary and the subdivided activities which is always presented to the project managers. • The second figure shows only the main & the secondary activities only without including the subdivided activities, which is always presented to other co-worker engineers to secure the privacy of your linking method. • Finally the third figure shows only the main activities, which could be presented to the owner of the project because mainly they need the primary activities durations.
  • 32. Conclusions & Recommendations • After settling down our study, we have been able to get onto the right track of the project management process, and actually it’s not as easy as it seems it’s more likely to be a science itself. • Through our research we have been able to expense the quantities of a residential building and to place the expenses in an standard BoQ table. • Then we have created a WBS chart to organise our activities through determining the primary activities and the secondary activities and by subdividing them. • After that we have created a relationship charts to link the activities through several relationships to result in critical timeliness activities. • Then we have initiated the Primavera Project Planner P3 to insert the activities and to link them as associated before. • Finally we have compressed the activities through crucial relationships to reduce the total duration of the project to result in reduction of the total cost.
  • 33. After we have finished inserting the activities into the program, we have found that we could work through the program choosing a different method work. Like for our project, we have worked through this program using activity codes. But we have found that it could be done using the WBS style instead which in it’s turn can export the file to Primavera Project Planner P6, which in its turn is more easy to handle than the version we used.