Reducing Risk in Agile Projects
Jeremy Jarrell
@jeremyjarrell
What is Risk?
Building the wrong
thing
Not working as a
team
Festering
problems
“This project is too risky
for agile.”
Frequent demos to
the customer
Daily stand ups
Regular
retrospectives
Reducing Risk in Agile Projects
Iteration
Project
Project Risk.
Features Deadline
Team
Features
Deadline
Iteration Risk.
Reducing Risk in Agile Projects
What could
happen?
How likely is it?
P×I=E
P×I=E.Mmm,
Reducing Risk in Agile Projects
Reducing Risk in Agile Projects
As a customer,
I want to review my transactions,
so I can see where I’m spending my money.
There’s too many transactions to pull quickly.
Some transactions are delayed.
Some transactions are delayed.
Probability = 3
Impact = 1
Exposure = Probability × Impact= 3
There’s too many transactions to pull quickly.
Probability = 2
Impact = 3
Exposure = Probability × Impact= 6
There’s too many transactions to pull quickly.
Invest time in performance tuning.
Pre-aggregate the transactions.
Reducing Risk in Agile Projects
As a customer,
I want to view how my current spending
compare against my budget,
so I can see how I’m pacing for the month.
The graph doesn’t work in IE6.
The ‘UI Guy’ gets sick mid-sprint.
The graph doesn’t work in IE6.
Probability = 3
Impact = 1
Exposure = 3
The ‘UI Guy’ gets sick mid-sprint.
Probability = 3
Impact = 3
Exposure = 9
The ‘UI Guy’ gets sick mid-sprint.
Pair with another developer.
Peer code reviews.
P×I=E
What’s next?
Tackle high risk
stories first
Beware of stories
with many risks
Look for patterns
Reducing Risk in Agile Projects

More Related Content

PPTX
Ahmad Mahel. No Estimate approach for Agile Teams
PDF
Getting To Product Market Fit Quickly
PPTX
Improving Task Estimates - Rich Butkevic, PMP, CSM
PPTX
Meetup 16 dec data driven process to optimization
PPT
Project Success
PPTX
Stop using spreadsheets to monitor quality in your call centre!
PDF
How to use software house to get the most out of it?
PDF
[VFS 2019] Project Management for AI-based Product - A Better Approach
Ahmad Mahel. No Estimate approach for Agile Teams
Getting To Product Market Fit Quickly
Improving Task Estimates - Rich Butkevic, PMP, CSM
Meetup 16 dec data driven process to optimization
Project Success
Stop using spreadsheets to monitor quality in your call centre!
How to use software house to get the most out of it?
[VFS 2019] Project Management for AI-based Product - A Better Approach

Viewers also liked (6)

PPTX
Taming the Butterfly presentation at ARGFest-O-Con
PDF
2013 scrum guide changes - Edwin Dando
PDF
Code campiasi qa-in-agile-projects-ana-figher-embarcadero
PPT
Quality Assurance in Agile
PDF
Agile india 2012 sonali bhasin
PDF
Agile QA Process
Taming the Butterfly presentation at ARGFest-O-Con
2013 scrum guide changes - Edwin Dando
Code campiasi qa-in-agile-projects-ana-figher-embarcadero
Quality Assurance in Agile
Agile india 2012 sonali bhasin
Agile QA Process
Ad

Similar to Reducing Risk in Agile Projects (20)

PPT
Agile estimation and planning
PDF
Predictability at Axial
PDF
Being Right Starts By Knowing You're Wrong
PPTX
Risk management
PPTX
Agile budget v1.01
PPTX
Bm Unit 3.2 Investment Appraisal
PPTX
Project Financial Benefits with Matt Hansen at StatStuff
PDF
Increasing The Probability Of Success For Your Project
PPTX
Client Expectations.pptx
DOCX
How to Achieve Per-Project Profitability
PPTX
Product Development -The Great Unknown
PDF
The Leader's Guide Workshop - Pivotal Labs Tokyo
PDF
Financial projections for investment presentations
PPT
Tapping Your Inner CEO: Management Tips to Stay on Budget and Deadline
PDF
Whose project is it anyway?
PDF
The five most critical project metrics
PDF
Front End of Innovation Worlshop: Strategy tools - in action. Expanded version
PDF
Stop Flying Blind! Quantifying Risk with Monte Carlo Simulation
PDF
Lean advertising 101 - Paid Acquisition for Startups
PDF
Egg3 | Agile CRM Deployment
Agile estimation and planning
Predictability at Axial
Being Right Starts By Knowing You're Wrong
Risk management
Agile budget v1.01
Bm Unit 3.2 Investment Appraisal
Project Financial Benefits with Matt Hansen at StatStuff
Increasing The Probability Of Success For Your Project
Client Expectations.pptx
How to Achieve Per-Project Profitability
Product Development -The Great Unknown
The Leader's Guide Workshop - Pivotal Labs Tokyo
Financial projections for investment presentations
Tapping Your Inner CEO: Management Tips to Stay on Budget and Deadline
Whose project is it anyway?
The five most critical project metrics
Front End of Innovation Worlshop: Strategy tools - in action. Expanded version
Stop Flying Blind! Quantifying Risk with Monte Carlo Simulation
Lean advertising 101 - Paid Acquisition for Startups
Egg3 | Agile CRM Deployment
Ad

Recently uploaded (20)

PDF
MCP Security Tutorial - Beginner to Advanced
PPTX
WiFi Honeypot Detecscfddssdffsedfseztor.pptx
PDF
Topaz Photo AI Crack New Download (Latest 2025)
PDF
How AI/LLM recommend to you ? GDG meetup 16 Aug by Fariman Guliev
PDF
Ableton Live Suite for MacOS Crack Full Download (Latest 2025)
PDF
EaseUS PDF Editor Pro 6.2.0.2 Crack with License Key 2025
PDF
Microsoft Office 365 Crack Download Free
PDF
Wondershare Recoverit Full Crack New Version (Latest 2025)
PPTX
Monitoring Stack: Grafana, Loki & Promtail
PPTX
Trending Python Topics for Data Visualization in 2025
PPTX
assetexplorer- product-overview - presentation
PDF
Designing Intelligence for the Shop Floor.pdf
PPTX
Advanced SystemCare Ultimate Crack + Portable (2025)
PPTX
Oracle Fusion HCM Cloud Demo for Beginners
PDF
Top 10 Software Development Trends to Watch in 2025 🚀.pdf
PDF
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
PPTX
Weekly report ppt - harsh dattuprasad patel.pptx
PDF
How Tridens DevSecOps Ensures Compliance, Security, and Agility
PDF
DuckDuckGo Private Browser Premium APK for Android Crack Latest 2025
DOCX
Modern SharePoint Intranet Templates That Boost Employee Engagement in 2025.docx
MCP Security Tutorial - Beginner to Advanced
WiFi Honeypot Detecscfddssdffsedfseztor.pptx
Topaz Photo AI Crack New Download (Latest 2025)
How AI/LLM recommend to you ? GDG meetup 16 Aug by Fariman Guliev
Ableton Live Suite for MacOS Crack Full Download (Latest 2025)
EaseUS PDF Editor Pro 6.2.0.2 Crack with License Key 2025
Microsoft Office 365 Crack Download Free
Wondershare Recoverit Full Crack New Version (Latest 2025)
Monitoring Stack: Grafana, Loki & Promtail
Trending Python Topics for Data Visualization in 2025
assetexplorer- product-overview - presentation
Designing Intelligence for the Shop Floor.pdf
Advanced SystemCare Ultimate Crack + Portable (2025)
Oracle Fusion HCM Cloud Demo for Beginners
Top 10 Software Development Trends to Watch in 2025 🚀.pdf
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
Weekly report ppt - harsh dattuprasad patel.pptx
How Tridens DevSecOps Ensures Compliance, Security, and Agility
DuckDuckGo Private Browser Premium APK for Android Crack Latest 2025
Modern SharePoint Intranet Templates That Boost Employee Engagement in 2025.docx

Reducing Risk in Agile Projects

Editor's Notes

  • #3: This talk is about how to mitigate risk in agile projects But first, let’s think about what risk is
  • #4: Software projects are fraught with risk Wrong thing Not what the customer wants Not working as a team Duplicated work Incompatible work Thrashing Festering problems No clear vision from the product owner Engineering problems Broken builds Bad code
  • #5: Ever heard this? Agile is sometimes considered ‘high risk’ because is moves fast and defers much up-front planning
  • #6: But, much of agile is designed to shake out this risk Frequent checkpoints between the team and stakeholders (demos) Frequent interactions between teams (stand-ups) Frequently bringing problems to a the forefront (retrospectives) Every project has risk The difference is that agile identifies and reacts to the risk as they emerge, Rather than trying to simply ‘plan them out’ at the beginning
  • #7: Iterative methodologies, like scrum, are often represented by two overlapping circles Agile projects are often made up of a large iterative process (project or releases) Made up of smaller iterative processes (sprints)
  • #8: We can think of risk management in the same way High level (project) risk – What would make or break the project as a whole Low level (iteration) risk – What day to day risks will we encounter while building the features that make up the app The two are related If we can get a feel for the high level risks, Then that will help us plan for and react to the lower level risks So, we’ll start with the high level
  • #9: Risks at the project level can best be thought of as constraints It’s important to know these constraints, since they tell us what levers we can pull when things go wrong
  • #10: Constraints are often captured as the ‘Iron Triangle’ of software development Features (scope) Deadline (schedule) Team (budget) The idea is that these constraints control the outcome of an project, and that you can always improve one factor by tweaking the others Need to hit a deadline? Reduce features and increase the team. Need more features? Push the deadline and increase the team. The problem with this is that it implies the Team is also a lever that can be pulled at any point during the project. We know better than this Don’t ever let resources enter the discussion
  • #11: Instead, think of this as a fulcrum between We balance between Features as Deadline. If we increase features, then the deadline must slip Or, we can accelerate the deadline by pulling back features These are the only two constraints that you have any semblance of control over in a project But they’re incredibly powerful ones to have What do we do with this? We need to establish which of these two constraints in the most critical early in the project Priorities change Market Political Periodically revisit them throughout the project Make sure your hand is still on the right level in case you need to pull it This isn’t always as easy as simply asking your business owner every 30 days “things are going great, but if things happen do you want to ship less or ship late” Instead, you often just need to ‘listen’ to what’s happening inside of your company What pressures do people seem the most sensitive to? What’s happening in the industry, with the customer base or competitors that could influence a decision?
  • #12: The iteration level is where we really tackle risk
  • #13: Risk analysis is hard It’s a very big subject Complex theories involving probability and statistics Lots of books devoted to it Entire sections of project management training devoted to it Risk analysis doesn’t need to be hard Most of our risk analysis techniques are borrowed from less forgiving fields of engineering i.e., designing bridge that must stand for 200 years
  • #14: It really boils down to two questions: What could happen? How likely is it to happen?
  • #15: It’s easy as P*I=E
  • #16: PIE is a very simple risk analysis technique, which lets us quickly identify and rank risks that could affect the work a team tackles during an iteration This helps us quickly identify which risks are important enough to start thinking about how to mitigate
  • #17: Let’s look at PIE from a high level We start with a story Then we think of any risks which may affect that story Not necessarily security risks, but risks to completing the story to the customer’s satisfaction For the risk, we think about how likely it is to occur And we give it a score between 1 and 3 Then we think about how severe the impact would be, if it occurred And we give that a score between 1 and 3 Then, we multiply those two number together, and if the score is over 6 We think of at least one option to mitigate the risk, should it happen Note that we don’t need to solve the problem here, we just want to think of some options to have on the table if the risk occurs Then we repeat for as many risks as we can think of, for that story Note that the scores for both probability don’t include anything that could ‘never’ happen or that’s ‘guaranteed’. If it could never happen, then we don’t need to waste time thinking about it. If it’s guaranteed, than it should be built into the story at the outset. This is designed to focus our efforts.
  • #18: Let’s look at some examples using Mint.com
  • #19: Imagine we’re building a banking app, like Mint.com Let’s try this with some stories we may encounter Such as being able to view recent transactions Risks Some of my transactions may be delayed up to 24 hours. There’s too many transactions to pull in a reasonable time.
  • #20: At least some transactions are likely to be delayed, so we score this as probability of 3 But those transactions are likely from smaller providers that the average Mint user isn’t concerned about, so we score the impact as a 1 Multiplying these together gives us an exposure score of 3, so we can consider this risk low
  • #21: We can’t predict whether the transactions can pull quickly or not, it’s a flip of a coin. So we give this risk a score of 2. The impact of this would be significant since it prevents the story from being usable. So we give it an impact score of 3. This gives us an exposure score of 6. I like to use 6 as a threshold for risks I like to have some strategies ready for. Use a threshold that makes sense for you.
  • #22: How to we handle this risk? This is basically a performance issue. How do we handle performance issues? Either by addressing the issue directly Or working around it with tricks like pre-aggregating or caching Remember the constraints from the project? These will influence which strategy is right for you. If real time data is an important feature then you’ll probably want to be ready to invest additional time to fix the problem. But, if deadlines are more important, then simply pre-aggregating and caching the data may be the right choice. Remember that you’re not trying to come up with the best solution for mitigation strategies, just starting points. You don’t need to solve the problem here, you just want some options on the table in the event something happens. “It’s easier to plan your fire exits, before your house is on fire.”
  • #23: Imagine we want to a display a graph that allows us to capture how our spending is pacing against our budget for the month
  • #24: The story would capture that we want to view how our current spending is pacing against our monthly budget. Risks The graph doesn’t work in certain browsers. Only one developer is familiar with the UI (The UI Guy), and he gets sick in the middle of the sprint.
  • #25: The likelihood of the graph not working in IE6 is almost a certainty, so we score its probability at 3 IE6 has very few users though, so we score its impact as a 1 This gives us an exposure score of 3, which means a risk that originally seemed important isn’t that important at all
  • #26: The likelihood of the UI getting sick mid-sprint isn’t guaranteed, but wouldn’t be surprising, so we give it a probability score of 3 The impact of this would be significant as no one else can do this work, so the impact score is also 3 This gives us an exposure score of 9, which tells us that this is a very serious risk to our story
  • #27: How do we handle this? This is really an issue of cross-pollination across the team, or a low bus factor. How do we improve a bus factor? Pair programming. Peer code reviews. Not formal code reviews, but simply pull requests between members of the team. Note that these mitigation strategies are different than those for our previous risk The previous mitigation strategies were options to have ready on the table, but not to use until the risk actually occurred These are options we would need to start using immediately to get out in front of the risk if it occurs If we wait until the UI Guy gets sick to start doing pair programming, then it’s too late Some mitigation strategies will be options in your pocket that you don’t pull the trigger on until you need them Others will be strategies you start immediately to get out in front of risk before they occur
  • #28: PIE is iterative Put this together at the beginning of an iteration Review it each morning before the standup Are there any risks to the stories currently in flight that you need to listen for? Update it after the standup Add new risks as they emerge Remove old risks as they fall off Rescore it at anytime. Like most things in agile, the power in this is in the iterative nature This only works if it’s kept up to date, otherwise, it becomes stale, and then ignored
  • #29: So, where do we go from here?
  • #30: We can take the information we learn from risk analysis, and let it influence our planning Tackle high risk stories first If a story scores high risk it should be moved to the top of the sprint This will let you get out in front of these stories early You don’t want to wait until the last few days of the sprint to find out you were right If story has a lot of risks, especially diverse risks, this may be sign it needs to be broken down further At the very least, this will let you spread your risk out rather than having it concentrated in a single chunk You’ll likely see trends and patterns emerge that accompany certain types of stories I call these risk archetypes Things like ‘UI is always risky because only one developer knows UI’, or ‘every time we touch the budget data the system gets really slow’ Once you start to recognize these trends think about what you can do to get out in front of them These may be candidates for investing some TLC in the system
  • #31: I love this quote, because it really captures how we should think of risk. Risk will always be there, we shouldn’t be afraid of it. It’s not something we can ‘plan out’. Instead, we need to: Recognize it Embrace it And learn from it And then, we can ship awesome products.