SlideShare a Scribd company logo
 




     Removal Action Summary Report
     WAIMANALO GULCH SANITARY
             LANDFILL
            KAPOLEI, O‘AHU, HAWAI‘I

                 AUGUST 2011




                        
 

                           CONTENTS  

     ACRONYMS  AND  ABBREVIATIONS                                                                     iii  
     CERTIFICATION                                                                                    iv  
     I.       SUMMARY  OF  EVENTS                                                                     1  
              A.     Site  Conditions  and  Background                                                1  
                     1.       Initial  Situation                                                      1  
                     2.       Cause  of  Release  or  Discharge                                       1  
              B.     Organization  of  the  Response                                                  8  
              C.     Chronological  Narrative  of  Response  Actions                                  9  
                     1.       Threat  Abatement  Actions  Taken                                       9  
                     2.       Treatment/Disposal/Alternative  Technology  Approaches  Pursued        14  
                     3.       Public  Information  and  Community  Relations  Activities             16  
              D.     Resources  Committed                                                            18  
     II.      EFFECTIVENESS  OF  REMOVAL  ACTIONS                                                    18  
              A.     Actions  Taken  By  Operator                                                    18  
              B.     Actions  Taken  by  State  and  Local  Forces                                   19  
              C.     Actions  Taken  by  Federal  Agencies  and  Special  Teams                      19  
              D.     Actions  Taken  by  Contractors,  Private  Groups,  and  Volunteers             19  
     III.     RECOMMENDATIONS                                                                        19  
              A.     Means  to  Prevent  a  Recurrence  of  the  Discharge  or  Release              19  

     APPENDIXES  
     A        Correspondence  
     B        Work  Plans  
     C        Heath  and  Safety  Plan  
     D        Letter  Reports/CQA  Reports  
     E        Invoices  

     FIGURES  
     1        Site  Location  Map                                                                     3  
     2        Site  Layout  Map                                                                       4  
     3        Daily  Sum  of  Precipitation  Measured  at  On-­Site  Rain  Gauge                      5  
     4        Daily  Sum  of  Precipitation  Measured  at  Up-­Canyon  Rain  Gauge                    6  
     5        Daily  Sum  Comparison  of  Precipitation  Measured  at  On-­Site  and  Up-­Canyon  
              Rain  Gauges                                                                            7  

     TABLES  
     1        Major  Rain  Event  Summary                                                             1  
     2        Monthly  Precipitation  Summary                                                         1  
     3        Organization  of  Response                                                              8  
     4        Response  Action  Activities                                                           10  
     5        Materials/Quantities  Pumped  during  Removal  Action                                  14  
     6        Total  Liquid  Disposed  of  at  WWTP                                                  16  
     7        Costs  Incurred  to  WMH  during  Response  Activities                                 18  


                                                   ii  
 

            ACRONYMS  AND  ABBREVIATIONS  

AECOM       AECOM  Technical  Services,  Inc.  
CERCLA      Comprehensive  Environmental  Response,  Compensation,  and  Liability  Act  
City        City  and  County  of  Honolulu  
CQA         Construction  Quality  Assurance  
DOH         Department  of  Health,  State  of  Hawaii  
EPA         Environmental  Protection  Agency,  United  States  
GBI         Goodfellow  Brothers,  Inc.  
GCL         geosynthetic  clay  liner  
GEI         GEI  Consultants,  Inc.  
MSW         municipal  solid  waste  
Order       Administrative  Order  on  Consent  for  Removal  Action,  CERCLA  Docket  No.  
            09-­2011-­0007    
PCS         Pacific  Commercial  Services,  LLC  
RCRA        Resource  Conservation  and  Recovery  Act  
WGSL        Waimanalo  Gulch  Sanitary  Landfill  
WMH         Waste  Management  of  Hawaii,  Inc.  
WWTF        wastewater  treatment  facility  
   3  
yd          cubic  yards    
  




                                    iii  
Removal Action Summary Report (pages 1-1015)
                                          Removal  Action  Summary  Report  
August  2011                       Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                       Page  1  of  19  
  

I.          SUMMARY  OF  EVENTS  
A.          SITE  CONDITIONS  AND  BACKGROUND  
1.          Initial  Situation  
The  Waimanalo  Gulch  Sanitary  Landfill  (WGSL)  is  an  active  municipal  solid  waste  (MSW)  disposal  
facility  located  at  92-­460  Farrington  Highway  in  Kapolei,  Oahu,  Hawai’i  and  is  owned  by  the  City  and  
County   of   Honolulu   (City).   Waste   Management   of   Hawaii,   Inc.   (WMH)   is   contracted   by   the   City   to  
manage  and  operate  the  landfill.  WGSL  is  the  only  operating  municipal  solid  waste  landfill  (MSW)  on  
the  island  of  Oahu  and  receives  commercial  and  residential  wastes  generated  within  Oahu,  as  well  
as  ash  and  residue  from  the  H-­Power  power  plant.  See  Figure  1  for  a  site  location  map  and  Figure  2  
for  a  site  layout  map.  

A  series  of  storm  events  occurring  in  late  December  2010  through  mid-­January  2011  resulted  in  high  
surface  stormwater  run-­on  flows  that  flooded  one  of  the  MSW  cells  (Cell  E6)  and  damaged  portions  
of   the   liner   system.   The   resultant   runoff   from   the   January   12th   and   13th   storm   may   have   carried  
waste  materials  into  the  WGSL  storm  water  conveyance  system,  which  flows  into  the  sedimentation  
basin  prior  to   leaving  the  site   at  the   permitted   discharge  point  and   onward  to   the  Pacific  Ocean.  A  
removal   action   was   required   by   the   Administrative   Order   on   Consent   for   Removal   Action,  
Comprehensive   Environmental   Response,   Compensation,   and   Liability   Act   (CERCLA)   Docket  
Number  09-­2011-­0007  (Order).  While  stormwater  flowing  from  Cell  E6  likely  entrained  some  waste  
materials,   waste   materials   from   other   areas   of   the   landfill   could   also   have   been   dislodged   and  
entrained  in  stormwater  that  also  flowed  to  the  conveyance  system.  

2.          Cause  of  Release  or  Discharge  
In  late  December  2010,  a  series  of  storms  produced  high  stormwater  run-­on  at  the  site  resulting  in  
damage   to   the   northeastern   edge   of   the   MSW   Cell   E6   liner   where   it   joins   with   Cell   E4.   An   even  
larger   storm   arrived   on   the   evening   of   January   12,   2011   that   resulted   in   additional   flooding   of   the  
landfill   and   damaged   the   exposed   portion   of   the   western   sideslope   area   of   the   MSW   Cell   E6   liner  
system.  

Table   1   summarizes   the   daily   precipitation   of   the   major   storm   events   prior   to   the   release   from   the  
site.   Rain   data   is   provided   for   an   on-­site   down   gradient   rain   gauge   located   at   the   administration  
building  and  a  rain  gauge  located  up-­canyon  of  the  site.  Monthly  summaries  for  the  December  2010  
and   January   2011   daily   precipitation   is   presented   in   Table   2.   Daily   summaries   of   the   rain  
precipitation  for  the  period  of  December  1,  2010  to  June  21,  2011  are  presented  in  Figure  3  –  5.    

Table  1:  Major  Rain  Event  Summary    

                                             Daily  Precipitation  (in)  
Date                                             On-­Site  Gauge                     Daily  Precipitation  (in)  Up-­Canyon  Gauge  
12/19/2010                                              5.4                                               8.4  
12/27/2010                                              2.2                                               4.3  
1/12/2011                                               5.0                                               9.2  
1/13/2011                                               2.0                                               10.3  
  

Table  2:  Monthly  Precipitation  Summary    

                                             Daily  Precipitation  (in)  
Month                                            On-­Site  Gauge                     Daily  Precipitation  (in)  Up-­Canyon  Gauge  
December                                                11.9                                              27.4  
January                                                 7.3                                               20.9  
  



                                                                   
                                       Removal  Action  Summary  Report  
August  2011                    Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                     Page  2  of  19  
  
                                                      th    th
The  high  water  flows  during  the  January  12 -­13   storm  resulted  in  erosion  of  the  Cell  E6  termination  
bench  and  exposed  the  operations  layer  soils  covering  the  sideslope  liner,  thereby  exposing  the  liner  
to  subsequent  damage  by  falling  rocks  in  addition  to  allowing  sections  of  the  liner  to  pull  down  from  
the  termination  bench  creating  wrinkles.  Due  to  numerous  holes  in  the  exposed  sideslope  liner  at  the  
northern  end  of  the  cell  caused  by  falling  rocks,  water  and  sediment  were  able  to  flow  between  the  
geotextile,  60-­mil  geomembrane,  and  geosynthetic  clay  liner  (GCL)  layers.  Portions  of  the  GCL  in  the  
middle   area   of   the   sideslope   area   were   hydrated   and   covered   with   sediment   due   to   the   water   and  
sediment  flow.  

A   Severe   Storm   Damage   Report   (included   in   Appendix   D)   documents   the   inspection   that   followed  
the   January   12-­13,   2011   storm   event.   The   inspection   found   several   damaged   areas   including  
flooding  of  the  MSW  Cell  E6  and  damage  to  the  drainage  structures,  landfill  liner,  drainage  swales,  
and  access  roads.  




                                                               
LEGEND




PROJECT LOCATION
Removal Action Summary Report (pages 1-1015)
6



                                    5



                                    4
     Daily  Precipitation  (in)  




                                    3



                                    2



                                    1



                                    0




                                        Figure  3:  Daily  Sum  of  Precipitation  Measured  at  On-­‐Site  Rain  Gauge




Source:  WGSL  on-­‐site  rain  gauge  located  at  the  administration  building.
12




                                       10




                                        8
          Daily  Precipitation  (in)




                                        6




                                        4




                                        2




                                        0




                                            Figure  4:  Daily  Sum  of  Precipitation  Measured  at  Up-­‐Canyon  Rain  Gauge  




Source:  Data  from  rain  gauge  “MPLHHL”  located  up-­‐canyon  of  the  WGSL.
Weather  Underground.  2011.  http://www.wunderground.com/cgi-­‐bin/findweather/getForecast?query=Kapolei,  Hawaii.  June  (6/23/11).
12




                               10




                                8
Daily  Precipitation  (in)  




                                6




                                4                                                                                                On-­‐Site
                                                                                                                                 Up-­‐Canyon


                                2




                                0




                                    Figure  5:  Daily  Sum  Comparison  of  Precipitation  Measured  at  On-­‐Site  and  Up-­‐
                                                                   Canyon  Rain  Gauges  
                                           Removal  Action  Summary  Report  
August  2011                        Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                        Page  8  of  19  
  

B.         ORGANIZATION  OF  THE  RESPONSE  
Response   actions   were   conducted   in   accordance   with   the   timeline   mandated   by   the   Order.   As  
specified  in  the  Order,  WMH  retained  several  contractors  to  perform  the  work  required  by  the  EPA,  
and  notified  the  EPA  and  DOH  of  the  names  and  qualifications  of  the  contractors  within  two  days  of  
the   Effective  Date.  The  Effective  Date  of  the  Order   was  January  25,  2011  and  the  submittal   of  the  
contractors   was   made   on   the   same   day,   correspondence   is   presented   in   Appendix   A.   Contractors  
used  during  the  removal  action  are  identified  in  Table  3.  WMH  designated  Joseph  Whelan  as  Project  
Coordinator.   As   required   by   the   Order,   Mr.   Whelan   was   present   on   site   and/or   readily   available  
during   site   work.   Correspondence   between   the   Project   Coordinator   and   the   EPA   is   presented   in  
Appendix  A.  

Table  3:  Organization  of  Response  

Agencies  or  Parties  Involved                                        Contact                   Description  of  Participation    
EPA  –  Region  9  (SFD-­9)                                       Bret  Moxley                 EPA  On-­Scene  Coordinator  (OSC)  
                                                             75  Hawthorne  Street  
                                                           San  Francisco,  CA  94105  
EPA  –  Region  9  (WST-­5)                                    Katherine  Baylor                  RCRA  Action  Officer  (RAO)  
                                                             75  Hawthorne  Street  
                                                           San  Francisco,  CA  94105  
DOH,  Environmental  Management  Division                Stuart  Yamada,  P.E.,  Chief              State  Agency  Oversight    
                                                         919  Ala  Moana  Blvd.,  Room  
                                                                      300  
                                                          Honolulu,  HI  96814-­4920  
City  and  County  of  Honolulu,  Department  of        Wilma  Namumnart,  P.E.  Acting                  Landfill  Owner  
Environmental  Services,  Refuse  Division                           Chief  
                                                        1000  Uluohia  Street,  Suite  212  
                                                              Kapolei,  HI  96707  
WMH                                                     Joe  Whelan,  General  Manager                Project  Coordinator/  
                                                         92-­460  Farrington  Highway                  Landfill  Operator  
                                                              Kapolei,  HI  96707  
GEI                                                       William  A.  Rettberg,  P.E.         Western  Drainage  Project  Design  
                                                          180  Grand  Ave,  Ste  1410               Engineer  Contractor    
                                                          Oakland,  California  94612  
Geosyntec  Consultants,  Inc.                            Hari  D.  Sharma,  Ph.D.,  P.E.         Liner  System  Design  Engineer  
                                                          180  Grand  Ave,  Ste  1410                       Contractor    
                                                             Oakland,  CA  94612  
PCS                                                          Jingbo  Chang,  Ph.D.              Storm  Water/Leachate  Disposal  
                                                                PO  Box  235117                           Contractor    
                                                              Honolulu,  HI  96823  
GBI                                                              Matt  Heahlke                 Earthwork/Construction  Contractor    
                                                         93-­061  Waipio  Point  Access  
                                                                     Road  
                                                              Waipahu,  HI  96797  
AECOM                                                          Ron  Boyle,  P.E.                Construction  Quality  Assurance  
                                                           1001  Bishop  St,  Ste  1600                   Contractor    
                                                             Honolulu,  HI  96813  
AECOM      AECOM  Technical  Services,  Inc.  
DOH        Department  of  Health,  State  of  Hawaii  
EPA        Environmental  Protection  Agency,  United  States  
GBI        Goodfellow  Brothers,  Inc.  
GEI        GEI  Consultants,  Inc.  
PCS        Pacific  Commercial  Services,  LLC  
  




                                                                    
                                        Removal  Action  Summary  Report  
August  2011                     Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                         Page  9  of  19  
  

C.        CHRONOLOGICAL  NARRATIVE  OF  RESPONSE  ACTIONS  
The  follow  sections  detail  the  response  actions  taken.  The  response  was  performed  in  accordance  
with  the  Order,  under  the  authority  of  CERCLA.  

1.        Threat  Abatement  Actions  Taken  
Measures  taken  to  prevent  future  storm  damage  at  the  site  and  to  document  efforts  to  further  contain  
potential   storm   water   and   prevent   waste   material   from   exiting   the   facility   in   the   event   of   additional  
storm   events   are   described   in   the   Stormwater   Management   Update   and   Contingency   Plan.   This  
document   was   updated   several   times   throughout   the   response   action;;   the   three   versions   dated  
January  27,  2011,  February  1,  2011  and  February  18,  2011  are  presented  in  Appendix  B.  

Table  4  presents  the  response  actions  completed  during  the  removal  action,  in  chronological  order,  
as  outlined  in  Section  VIII  of  the  Order.  




                                                                 
                                                                 Removal  Action  Summary  Report  
August  2011                                              Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                                                   Page  10  of  19  
  


Table  4:  Response  Action  Activities  

     Item                Subject              Administrative  Order  Action  Requirement  
     19g.         Operation  of  Cell  E6     Respondent  shall  not  operate  cell  #E6  without  further  approval  from  EPA.  

Action  Taken:  In  an  e-­mail  dated  January  28,  2011  the  EPA  approved  WMH  to  resume  operations  on  the  east  side  of  Cell  E6,  correspondence  is  presented  in  
Appendix  A.  
     19c.        Storm  Water  Discharge   Respondent  shall  ensure  the  termination  of  discharges  of  liquid  originated  from  cell  #E6  to  the  Pacific  Ocean,  except  as  in  
                                           compliance  with  any  applicable  permit.  
Action  Taken:  Storm  water  discharges  were  in  compliance  with  the  applicable  permits,  or  were  approved  by  the  DOH.  
     20.             Work  Plans  and         Respondent   shall   submit   to   EPA   for   approval   a   draft   Work   Plan   or   individual   Work   Plans   for   performing   the   response  
                     Implementation           actions  generally  described  in  Paragraph  19  of  the  Order.  
                                              EPA   may   approve,   disapprove,   require   revision   to   or   modify   any   draft   Work   Plan   in   whole   or   in   part.   If   EPA   requires  
                                              revisions,  Respondents  hall  submit  a  revised  draft  Work  Plan  within  fifteen  (15)  days  of  receipt  of  EPA’s  notification  of  the  
                                              required  revision.  Respondent  shall  implement  each  respective  Work  Plan  as  approved  in  writing  by  EPA  in  accordance  
                                              with  its  schedule  approved  by  EPA.  Once  approve,  or  approved  with  modifications,  each  Work  Plan,  its  schedule,  and  any  
                                              subsequent  modifications  shall  be  incorporated  into  and  become  fully  enforceable  under  this  Order.  
                                              Respondent  shall  not  conduct  any  Work  except  in  conformance  with  the  terms  of  this  Order,  or  as  directed  by  EPA.  
Action  Taken:  All  work  plans  were  submitted  to  the  EPA  for  approval  and  revised  according  to  schedule.  Correspondence  for  submittals  and  work  plans  are  
presented  in  Appendix  A  and  Appendix  B,  respectively.  
     22.         Quality  Assurance  and   Although  none  is  presently  anticipated,  all  sampling  and  analyses  performed  pursuant  to  this  Order  shall  conform  to  EPA  
                        Sampling           direction,   approval,   and   guidance   regarding   sampling,   quality   assurance/quality   control   ("QA/QC"),   data   validation,   and  
                                           chain  of  custody  procedures.    
                                             
Action  Taken:  Sampling  was  not  performed  for  EPA  reporting  purposes  and  as  part  of  the  removal  action.    
     24.                Reporting             Beginning  two  (2)  days  after  the  Effective  Date,  Respondent  shall  submit  by  e-­mail  to  EPA  and  DOH  daily,  until  agreed  
                                              otherwise  by  the  Parties,  progress  reports  (Monday  through  Friday  only,  unless  otherwise  requested  by  EPA)  concerning  
                                              actions   undertaken   pursuant   to   this   Order,   until   receipt   of   the   Notice   of   Completion   pursuant   to   this   Order,   unless  
                                              otherwise   directed   in   writing   by   the   OSC   or   RAO.   These   reports   shall   describe   all   significant   developments   during   the  
                                              preceding   period,   including   the   actions   performed   and   any   problems   encountered,   analytical   data   received   during   the  
                                              reporting  period,  and  the  developments  anticipated  during  the  next  reporting  period,  including  a  schedule  of  actions  to  be  
                                              performed  under  any  approved  Work  Plan,  anticipated  problems,  and  planned  resolutions  of  past  or  anticipated  problems.  
                                              Respondent  shall  submit  copies  of  all  plans,  reports  (other  than  progress  reports)  or  other  submissions  required  by  this  
                                              Order,  or  any  approved  Work  Plan,  to  both  EPA  and  DOH  in  electronic  form  (Word  or  pdf  -­  minimum  300  dpi).  




                                                                                                 
                                                                     Removal  Action  Summary  Report  
August  2011                                                  Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                                                     Page  11  of  19  
  


     Item                  Subject                Administrative  Order  Action  Requirement  
Action  Taken:  WMH  submitted  Daily  Progress  Reports  as  required  by  the  EPA.  All  e-­mail  correspondence  is  presented  chronologically  in  Appendix  A.  Copies  of  all  
documents  required  by  the  Order  were  submitted  electronically.  The  documents  included:  
  
           Stability  analysis  of  temporary  earthen  berm  by  a  Civil/Geotechnical  Engineer  (Appendix  D)  
           Work  Plans  (Appendix  B):  
                  o   Collection  and  Transport  of  Liquid  Behind  Temporary  Berm  
                  o   Slope  Stability  Analysis  and  Work  Plan  for  Temporary  Earthen  Berm  Integrity  
                  o   Work  Plan  for  Managing  Potential  Cell  E6  Hydraulic  Head  
                  o   Work  Plan  for  Liner  Evaluation  and  Repair  
                  o   Work  Plan  for  Restoration  of  Sedimentation  Basin  
                  o   Work  Plan  For  Beach  Assessment  and  Material  Recovery  Effort  
           Written  description  of  collection/treatment  activities  of  liquids  (presented  in  the  Daily  Progress  Reports  in  Appendix  A)  
           Health  and  Safety  Plan  (Appendix  C)  
              
In  an  e-­mail  dated  March  17,  2011,  the  EPA  granted  the  WMH  request  to  replace  daily  progress  reports  with  a  weekly  report  submitted  by  noon  every  Wednesday,  
documenting  work  completed  during  the  period  of  the  prior  Monday  thru  Sunday.  In  an  e-­mail  dated  June  22,  2011,  the  EPA  granted  the  WMH  request  to  
terminate  the  weekly  progress  reports.    
     19d.         Storm  water  Removal           Respondent  shall  continue  to  collect  and  transport  to  a  local  treatment  facility  the  liquids  at  the  site  retained  behind  the  
                                                  temporary   earthen   berm   in   cell   #E6.   Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   a   written  
                                                  description  of  the  collection  and  treatment  activities,  the  current  permitting  and  the  chemical  parameters  of  the  liquids,  and  
                                                  transportation  methods  to  the  local  treatment  facility.  
Action  Taken:  Storm  water  was  pumped  and  transported  to  a  WWTP  in  Kailua,  HI.  The  first  work  plan  was  submitted  on  February  1,  2011.  In  an  e-­mail  dated  
February  10,  2011,  the  EPA  noted  that  the  description  of  collection  and  treatment  associated  with  liquid  located  behind  the  temporary  berm  were  acceptable  with  
incorporation  of  the  provided  comments;;  revisions  and  resubmission  were  required.  The  revised  work  plan  was  submitted  on  February  25,  2011  and  is  included  in  
Appendix  B.  
     21.         Health  and  Safety  Plan   Within  seven  (7)  days,  Respondent  shall  submit  for  EPA  review  and  comment  a  Site  Health  and  Safety  Plan  that  ensures  
                                             the   protection   of   the   public   health   and   safety   during   performance   of   on-­Site   Work.   This   plan   shall   be   prepared   in  
                                             accordance   with   EPA's   Standard   Operating   Safety   Guide   (PUB   9285.1-­03,   PB   92-­963414,   June   1992),   if   applicable.   In  
                                             addition,   the   plan   shall   comply   with   all   currently   applicable   Occupational   Safety   and   Health   Administration   ("OSHA")  
                                             regulations  found  at  29  CRF  Part  1910.  
Action  Taken:  A  site  Health  and  Safety  Plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  C.    
     19e.        Work  Plan  for  Hydraulic   Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   to   EPA   and   DOH   a   Work   Plan   and   schedule,  
                          Head                subject  to  modification  based  on  further  field  analysis,  for  managing  the  hydraulic  head  between  cell  #E6  and  the  fluids  
                                              outside   of   cell   #E6   in   order   to   maintain   the   integrity   of   the   cell   liner   as   the   fluids   are   drawn   down   and   the   leachate  
                                              collection  system  is  returned  to  normal  functions.  




                                                                                                      
                                                                   Removal  Action  Summary  Report  
August  2011                                                Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                                                Page  12  of  19  
  


     Item                  Subject              Administrative  Order  Action  Requirement  
Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  approved  the  work  
plan.  The  Evaluation  of  Hydraulic  Head  Below  Liner  System  Summary  Report  was  submitted  to  the  EPA  on  February  25.  The  e-­mail  submittal  is  included  in  
Appendix  A  and  a  copy  of  the  summary  report  is  included  in  Appendix  D.    
  
    19h.             Work  Plan  and         Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   to   EPA   and   DOH   a  Work   Plan   and   schedule   to  
                Schedule  for  Sediment   restore   the   sediment   basin   system   to   its   intended   capacity   and   function.   This   shall   include   removal   of   the   sediment  
                   Basin  Restoration        collected  in  the  basin(s)  and  the  proposed  disposal  location  for  the  collected  sediments  

Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the  
submitted  work  plan  was  acceptable  with  incorporation  of  provided  comments;;  revision  and  resubmissions  were  required.  In  e-­mail  dated  March  4,  2011,  the  work  
plan  was  approved,  and  suggested  a  completion  date  of  March  14,  2011.  However,  due  to  continued  rain  events  during  the  restoration  of  the  basin,  WMH  
requested  a  later  deadline  of  May  15,  2011.  After  continued  rain  events,  WMH  requested  an  additional  extension  via  e-­mail  on  May  5,  2011.  In  an  e-­mail  dated  
May  6,  2011,  the  EPA  approved  an  extension  to  June  15,  2011.  
  
In  an  e-­mail  dated  June  15,  2011  WMH  submitted  the  Sedimentation  Basin  Restoration  Observation  Report.  Following  comments  provided  by  the  EPA,  additional  
work  was  conducted  on  the  sediment  basin  and  an  Addendum  report  was  submitted  on  August  4,  2011.  The  submittal  correspondence  is  presented  in  Appendix  A  
and  the  reports  are  included  in  Appendix  D.  
     19i.            Work  Plan  and       Within   seven   (7)  days   of   the  Effective   Date,   Respondent  shall   provide   to   EPA   and   DOH   a  Work   Plan   and  schedule   for  
                  Schedule  for  Beach   ongoing  daily  beach  assessment  and  recovery  of  Waste  Material  released  from  the  WGSL.  
                 Assessment  and  Debris  
                       Recovery  
Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the  
submitted  work  plan  was  acceptable  with  incorporation  of  provided  comments;;  revision  and  resubmissions  were  required.  In  an  e-­mail  dated  March  4,  2011,  the  
EPA  approved  the  work  plan.  The  work  plan  is  presented  in  Appendix  B.  After  a  final  beach  assessment  on  January  24,  2011,  WMH  noted  that  the  daily  beach  
assessment  phase  was  complete;;  no  calls  were  received  at  the  established  beach  waste  hot  line  during  the  subsequent  reporting  periods.  
     19a.           Temporary  Earthen          Within  ten  (10)  days  of  the  Effective  Date,  Respondent  shall  provide  to  EPA  and  DOH  an  analysis  by  a  qualified  Civil  or  
                         Berm                   Geotechnical  Engineer  of  the  stability  and  suitability  of  the  temporary  earthen  berm,  which  is  currently  retaining  liquid  in  
                                                cell  #E6,  to  retain  liquid  when  full  to  within  one  (1)  foot  of  the  top  for  up  to  six  (6)  weeks,  and  a  Work  Plan  to  ensure  the  
                                                integrity  of  the  temporary  earthen  berm  so  long  as  it  is  holding  liquid  
Action  Taken:  A  report  entitled  Slope  Stability  Analysis  and  Work  Plan  for  Temporary  Earthen  Berm  Integrity  was  submitted  to  the  EPA  on  February  4,  2011  by  e-­
mail  and  Certified  Mail.  The  report  found  that  the  temporary  berm  met  and/or  exceeded  minimum  accepted  factors  of  safety  and  no  modifications  were  necessary.  
The  e-­mail  and  report  can  be  found  in  Appendix  A  and  Appendix  B,  respectively.  
     19f.            Work  Plan  and            Within  fourteen  (14)  days  of  the  Effective  Date,  Respondent  shall  provide  to  EPA  and  DOH  a  Work  Plan  and  schedule  to  
                  Schedule  for  E6  Liner      evaluate  and  demonstrate  or  restore  the  integrity  of  the  liner  system  in  cell  #E6  
                        Repair  




                                                                                                  
                                                                     Removal  Action  Summary  Report  
August  2011                                                  Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                                                    Page  13  of  19  
  


     Item                   Subject               Administrative  Order  Action  Requirement  
Action  Taken:  The  work  plan  was  submitted  to  the  EPA  on  February  4,  2011.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the  submitted  work  plan  
was  acceptable;;  revision  and  resubmissions  were  not  required.  Submittal  correspondence  is  included  in  Appendix  A  and  a  copy  of  the  work  plan  is  presented  in  
Appendix  B.    
  
CQA  reports  documenting  the  liner  repairs  related  to  the  storm  damage  was  submitted  under  separate  cover  as  specific  areas  were  repaired.  Copies  of  the  CQA  
repair  reports  are  included  in  Appendix  D.  
     19b.          Storm  water  Diversion   Within   twenty-­one   (21)   days   of   the   Effective   Date,   Respondent   shall   complete   construction   of   a   functional   storm   water  
                          Structure          diversion  structure  on  the  west  side  above  cell  #E6.  
Action  Taken:  In  an  e-­mail  dated  February  15,  2011,  WMH  confirmed  that  construction  of  a  functional  storm  water  diversion  structure  located  on  the  west  side  
above  Cell  E6  was  functionally  complete.  In  an  e-­mail  dated  February  16,  2011,  the  EPA  concurred  that  WMH  completed  construction  of  a  functional  storm  water  
diversion  structure  as  required  by  paragraph  19b.    
  
In  addition,  in  an  e-­mail  dated  March  11,  2011,  WMH  submitted  a  revised  Surface  Water  Management  Plan  to  the  EPA  and  DOH.  All  correspondence  is  presented  
in  Appendix  A,  and  the  Surface  Water  Management  Plan  is  in  Appendix  D.  
      25.                  Final  Report         Within   sixty   (60)   days   after  completion   of  all  Work   required  by   this   Order,   Respondent  shall  submit   for   EPA  review   and  
                                                 approval   a   final   report   summarizing   the   actions   taken   to   comply   with   this   Order.   The   final   report   shall   conform,   at   a  
                                                 minimum,   with   the   requirements   set   forth   in   Section   300.165   of   the   NCP   entitled   "OSC   Reports."   The   final   report   shall  
                                                 include  a  good  faith  estimate  of  total  costs  or  a  statement  of  actual  costs  incurred  in  complying  with  the  Order,  a  listing  of  
                                                 quantities   and   types   of   materials   removed   off-­Site   or   handled   on-­Site,   a   discussion   of   removal   and   disposal   options  
                                                 considered  for  those  materials,  a  listing  of  the  ultimate  destination(s)  of  those  materials,  a  presentation  of  the  analytical  
                                                 results   of   all   sampling   and   analyses   performed,   and   accompanying   appendices   containing   all   relevant   documentation  
                                                 generated   during   the   removal   action   (e.g.,   manifests,   invoices,   bills,   contracts,   and   permits).   The   final   report   shall   also  
                                                 include  the  following  certification  signed  by  a  person  who  supervised  or  directed  the  preparation  of  that  report:  

                                                  "Under  penalty  of  law,  I  certify  that  to  the  best  of  my  knowledge,  after  appropriate  inquiries  of  all  relevant  persons  involved  
                                                  in   the   preparation   of   the   report,   the   information   submitted   is   true,   accurate,   and   complete.   I   am   aware   that   there   are  
                                                  significant   penalties   for   submitting   false   information,   including   the   possibility   of   fine   and   imprisonment   for   knowing  
                                                  violations."  
Action  Taken:  This  report  fulfills  the  requirements  described  in  Paragraph  25.  
      26.            Off-­site  Shipments    Respondent   shall,   prior   to   any   off-­Site   shipment   of  Waste   Material   from   the   Site   to   an   out-­of-­state   waste   management  
                                             facility,  provide  written  notification  of  such  shipment  of  Waste  Material  to  the  appropriate  state  environmental  official  in  the  
                                             receiving  facility's  state  and  to  the  OSC  and  RAO.  
Action  Taken:  No  Waste  Material,  as  defined  in  Section  III.r  of  the  Order,  was  shipped  off-­site  during  the  response  activities.    

CQA    Construction  Quality  Assurance    
WWTP   wastewater  treatment  plant  




                                                                                                     
                                      Removal  Action  Summary  Report  
August  2011                   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                          Page  14  of  19  
  

2.          Treatment/Disposal/Alternative  Technology  Approaches  Pursued  
WMH  contracted  Pacific  Commercial  Services,  LLC  (PCS)  to  pump  and  transfer  storm  water  to  the  
wastewater   treatment   plant   (WWTP)   in   Kailua,   HI.   A   summary   of   the   materials   pumped   during   the  
removal  action  is  presented  in  Table  5.  In  addition  to  the  material  shown  in  Table  5,  WMH  removed  
                                                                                            3
approximately   806,500   gallons   of   storm   water   and   14,610   cubic   yards   (yd )   of   sediment   from   the  
sedimentation   basin   during   the   restoration   activities,   as   discussed   in   the   Sedimentation   Basin  
Restoration   Observation   Report   dated   June   15,   2011   (included   in   Appendix   D).   A   summary   of   the  
liquid  transported  and  disposed  of  at  the  WWTP  is  presented  in  Table  6.  Note  that  quantities  of  liquid  
pumped  and  transported  by  the  City  during  the  removal  action  are  not  included  in  this  report.    

Table  5:  Materials/Quantities  Pumped  during  Removal  Action  

Reporting  Date              Location               Amount  Pumped  (gallons)          Material               Disposal  Area  
1/27/11               Cell  E6  Leachate  Riser              12,000                      mud                      On-­site  
1/27/11                Sedimentation  Basin                  60,000                     Water                     WWTP  
1/28/11               Cell  E6  Leachate  Riser              20,321                       Silt                    On-­site  
1/28/11                Sedimentation  Basin                  60,000                     Water                     WWTP  
1/31/11               Cell  E6  Leachate  Riser                2  ft                      Silt                    On-­site  
1/31/11                Sedimentation  Basin                  274,000                    Water                     WWTP  
2/1/11                Cell  E6  Leachate  Riser              16,500                     Water                     WWTP  
2/1/11                Cell  E6  Leachate  Riser              16,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/1/11                 Sedimentation  Basin                  56,000                     Water                     WWTP  
2/2/11                Cell  E6  Leachate  Riser              16,500                     Water                     WWTP  
2/2/11                Cell  E6  Leachate  Riser              10,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/2/11                 Sedimentation  Basin                  105,800                    Water                     WWTP  
2/3/11                Cell  E6  Leachate  Riser              12,500               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/3/11                 Sedimentation  Basin                  55,800                     Water                     WWTP  
2/4/11                Cell  E6  Leachate  Riser              10,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/4/11                 Sedimentation  Basin                  61,500                     Water                     WWTP  
2/7/11                Cell  E6  Leachate  Riser               2,500               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/7/11                 Sedimentation  Basin                  24,700                     Water                     WWTP  
2/8/11                 Sedimentation  Basin                  44,800                     Water                     WWTP  
2/9/11                  Sedimentation  basin                 52,277                     Water                     WWTP  
2/10/11               Cell  E6  Leachate  Riser              19,350               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/10/11                     Frac  Tanks                      16,500                     Water                     WWTP  
2/10/11                Sedimentation  Basin                  41,249                     Water                     WWTP  
2/11/11               Cell  E6  Leachate  Riser               9,675               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/11/12                Sedimentation  Basin                  19,350                     Water                     WWTP  
2/14/11                       Cell  E6                       32,818                     Water                     WWTP  
2/14/11               Cell  E6  Leachate  Riser              27,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/14/11                Sedimentation  Basin                  32,700                     Water                     WWTP  
2/15/11                       Cell  E6                       47,759                     Water                     WWTP  
2/15/11               Cell  E6  Leachate  Riser              44,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/15/11                Sedimentation  Basin                  17,318                     Water                     WWTP  
2/16/11                       Cell  E6                       18,100                     Water                     WWTP  
2/16/11               Cell  E6  Leachate  Riser              33,200                     Water                     WWTP  
2/16/11               Cell  E6  Leachate  Riser              27,700               Mud/Water  Mixture   Frac  Tanks  for  Separation  
2/17/11               Cell  E6  Leachate  Riser              55,000               Mud/Water  Mixture   Frac  Tanks  for  Separation  




                                                                 
                                    Removal  Action  Summary  Report  
August  2011                 Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                           Page  15  of  19  
  

Reporting  Date            Location               Amount  Pumped  (gallons)          Material               Disposal  Area  
2/17/11              Sedimentation  Basin                  31,675                     Water                      WWTP  
2/1711               Sedimentation  Basin                         -­-­               Silt/Rock         Lined  portion  of  Cell  E6  
2/18/11                   Frac  Tanks                      56,700                     Water                      WWTP  
2/18/11              Sedimentation  Basin                  57,718                     Water                      WWTP  
2/18/11              Sedimentation  Basin                         -­-­               Silt/Rock         Lined  portion  of  Cell  E6  
2/21/11                   Frac  Tanks                      108,000                    Water                      WWTP  
2/21/11              Sedimentation  Basin                         -­-­               Silt/Rock         Lined  portion  of  Cell  E6  
2/22/11                   Frac  Tanks                      33,900                     Water                      WWTP  
2/22/11              Sedimentation  Basin                         -­-­               Silt/Rock         Lined  portion  of  Cell  E6  
2/23/11              Sedimentation  Basin                  41,700                     Water                      WWTP  
2/24/11              Sedimentation  Basin                  54,900                     Water                      WWTP  
2/25/11              Sedimentation  Basin                  56,800                     Water                      WWTP  
2/28/11                   Frac  Tanks                      105,300                    Water                      WWTP  
2/28/11             Cell  E6  Leachate  Riser              33,200                     Water                      WWTP  
                      South  Pond  Area  
2/28/11             Cell  E6  Leachate  Riser              30,772               Mud/Water  Mixture   Frac  Tanks  for  Separation  
                      South  Pond  Area  
2/28/11              Sedimentation  Basin                   8,700                     Water                      WWTP  
3/1/11                    Frac  Tanks                      30,700                     Water                      WWTP  
3/1/11              Cell  E6  Leachate  Riser              11,000                     Water                      WWTP  
                      South  Pond  Area  
3/1/11               Sedimentation  Basin                  15,500                     Water                      WWTP  
3/2/11                    Frac  Tanks                      13,000                     Water                      WWTP  
3/2/11               Sedimentation  Basin                  40,000                     Water                      WWTP  
3/3/11                    Frac  Tanks                      12,018                     Water                      WWTP  
3/3/11              Cell  E6  Leachate  Riser              25,000                     Water                      WWTP  
                      South  Pond  Area  
3/3/11               Sedimentation  Basin                  51,000                     Water                      WWTP  
3/4/11                    Frac  Tanks                      14,949                     Water                      WWTP  
3/4/11               Sedimentation  Basin                  59,700                     Water                      WWTP  
3/7/11                    Frac  Tanks                      36,200                     Water                      WWTP    
3/7/11               Sedimentation  Basin                  113,000                    Water                      WWTP  
3/8/11               Sedimentation  Basin                  76,200                     Water                      WWTP  
3/9/11                    Frac  Tanks                      15,100                     Water                      WWTP  
3/9/11               Sedimentation  Basin                  75,300                     Water                      WWTP  
3/10/11                   Frac  Tanks                       6,359                     Water                      WWTP  
3/10/11              Sedimentation  Basin                  84,000                     Water                      WWTP  
3/11/11                   Frac  Tanks                       3,159                     Water                      WWTP  
3/11/11              Sedimentation  Basin                  26,500                     Water                      WWTP  
3/14/11                   Frac  Tanks                      20,677                     Water                      WWTP  
3/14/11              Sedimentation  Basin                  126,000                    Water                      WWTP  
3/15/11                   Frac  Tanks                       8,769                     Water                      WWTP  
3/15/11             Cell  E6  Leachate  Riser               1,518                     Water                      WWTP  
                      South  Pond  Area  
3/15/11              Sedimentation  Basin                  71,476                     Water                      WWTP  
3/16/11                   Frac  Tanks                       6,318                     Water                      WWTP  
3/16/11             Cell  E6  Leachate  Riser               1,300                     Water                      WWTP  




                                                               
                                              Removal  Action  Summary  Report  
August  2011                           Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                  Page  16  of  19  
  

Reporting  Date                      Location             Amount  Pumped  (gallons)                 Material                  Disposal  Area  
                                 South  Pond  Area  
3/16/11                         Sedimentation  Basin                   91,400                          Water                      WWTP  
Week  Ending  3/20/11               Frac  Tanks                        31,698                          Water                      WWTP  
Week  Ending  3/20/11   Sedimentation  Basin                          221,300                          Water                      WWTP  
Week  Ending  3/27/11               Frac  Tanks                        52,434                          Water                      WWTP  
Week  Ending  3/27/11   Sedimentation  Basin                          105,900                          Water                      WWTP  
Week  Ending  4/3/11                Frac  Tanks                        51,663                          Water                      WWTP  
Week  Ending  4/10/11               Frac  Tanks                        35,586                          Water                      WWTP  
Week  Ending  4/10/11   Sedimentation  Basin                           15,000                          Water             On-­Site  (Dust  Control)a  
Week  Ending  4/17/11               Frac  Tanks                        26,006                          Water                      WWTP  
Week  Ending  4/24/11               Frac  Tanks                        4,159                           Water                      WWTP  
Week  Ending  5/1/11                Frac  Tanks                        1,000                           Water                      WWTP  
Week  Ending  5/8/11                Frac  Tanks                        63,611                          Water                      WWTP  
Week  Ending  5/15/11               Frac  Tanks                        9,477                           Water                      WWTP  
Week  Ending  5/22/11               Frac  Tanks                        56,914                          Water                      WWTP  
Week  Ending  5/29/11                Frac  Tank                        25,216                          Water                      WWTP  
Week  Ending  6/3/11                 Frac  Tank                        34,075                          Water                        WWTP  
Week  Ending  6/12/11               Frac  Tanks                        33,343                          Water                      WWTP  
Notes:  
a
    Approval  via  e-­mail  from  DOH  dated  3/23/11  to  use  sedimentation  basin  storm  water  for  onsite  dust  control  and  irrigation.  
    The  quantity  of  water  pumped  was  no  longer  recorded  after  this  date.  
  

Table  6:  Total  Liquid  Disposed  of  at  WWTP  

Origin                                               Total  Liquid  Disposed  of  between  1/28/2011  –  6/12/2011  (gallons)  c  
Cell  E6                                                                                   98,677  
                           a
Cell  6  Leachate  Riser                                                                   138,218  
Frac  Tanks                                                                                853,540  
Sedimentation  Basin  b                                                                   2,314,263  
TOTAL                                                                                     3,306,021  
Notes:  
a
     Does  not  include  mud/water  mixture  pumped  into  frac  tanks  on  site.  
b
     Does  not  include  storm  water  pumped  to  use  for  onsite  dust  control  and  irrigation.  
c
     Quantities  of  liquid  do  not  include  liquid  pumped  by  the  City  from  Cell  E6  and  the  sedimentation  basin.  
  

3.           Public  Information  and  Community  Relations  Activities  
WMH   and   the   City   published   several   press   releases   summarizing   the   response   activities.   Press  
releases   are   included   in   Appendix   A   for   the   following   dates:   January   24,   2011,   January   25,   2011,  
January  31,  2011,  February  8,  2011,  and  February  15,  2011.    

As   presented   in   the   January   24,   2011   press   release,   a   summary   of   the   public   notices,   shoreline  
cleanup  activities,  and  reporting  hotline  includes  the  following:    

             Thursday,  January  13  —  WMH  evaluated  storm  water  conditions  throughout  the  day  of  the  
             storm  event  and  determined  that  a  large  body  of  storm  water  had  collected  in  the  area  of  the  
             new   cell   construction.   Working   in   collaboration   with   the   DOH,   WM,   and   the   City   installed  
             warning   signs   in   the   shoreline   area   of   the   Ko   Olina   Resort,   where   the   landfill   outfall   is  
             located,  and  along  the  associated  beach  shoreline.  Additionally,  WMH  and  the  City  began  a  
             water   quality   sampling   program   that   same   day.   Later   on   January   13,   WMH   began   debris  


                                                                           
                                       Removal  Action  Summary  Report  
August  2011                    Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                        Page  17  of  19  
  

          cleanup  at  the  overflow  and  the  storm  water  sedimentation  basin  once  the  flood  waters  had  
          subsided   enough   to   perform   this   operation   safely.   At   that   time,   it   was   determined   that   the  
          debris  also  contained  sterilized  medical  waste.  
          Friday,  January  14  —  WMH  dispatched  an  evaluation  and  cleanup  team  to  the  ocean  side  of  
          the   landfill’s  permitted  storm  water  outfall,  located  on  the   north  end  of  the   Ko  Olina  Resort  
          property  across  Farrington  Highway  from  the  landfill.  The  crew  spent  several  hours  cleaning  
          debris   from   this   area.   At   the   time,   there   was   no   apparent   evidence   of   remaining   medical  
          waste  material.  WMH  continued  to  clean  up  areas  located  between  the  sediment  basin  and  
          the  permitted  outfall.  Also  on  January  14,  representatives  of  WMH,  the  City,  and  DOH  held  a  
          press  conference  at  the  landfill  to  further  inform  the  public  of  potential  concerns  associated  
          with   the   storm   events,   and   to   provide   an   update   on   the   cleanup   efforts,   warning   sign  
          postings,   and   water   quality   sampling   being   performed   by   WMH   and   the   City.   Numerous  
          news  interviews  and  media  announcements   were  provided  by  all  parties  over  the  following  
          several  days  in  order  to  keep  the  public  fully  informed.  
          Saturday,  January  15  —  WMH  personnel  continued  evaluation  of  the  shoreline  area.  In  the  
          afternoon,   additional   medical   waste   material   was   reported   in   the  WMH   outfall   area   located  
          near  the  Ko  Olina  Resort  area.  
          Sunday,   January   16   —   At   7   a.m.,   WMH   sent   its   cleanup   crew   back   to   the   area   and  
          evaluated  an  approximate  one-­half  to  three-­quarters  of  a  mile  section  of  the  beach,  including  
          a  return  to  the  outfall   area.  No  further  medical  waste  was  noted  by  WMH  personnel  at  this  
          time.   Additionally,   a   hotline   was   also   set   up   to   provide   the   public   with   the   opportunity   to  
          report   any   observations   of   medical   waste   material   found   on   local   beaches.   The   DOH  
          announced  the  hotline  to  the  public  via  news  media,  and  WMH  representatives  continued  to  
          remind   news   media   to   include   the   hotline   in   any   further   media   updates.   WMH  
          representatives  used  reports  provided  via  the  hotline  to  evaluate  information  and  determine  
          where   to   concentrate   its   ongoing   daily   cleanup   efforts.   Subsequently,   in   the   afternoon   of  
          January  16,  WMH  was  notified  that  some  plastic  syringes  (absent  needles)  had  been  found  
          at  the  White  Plains  beach  located  farther  south  on  the  shoreline.  WMH  dispatched  cleanup  
          crews   to   this   beach,   as   well   as   the   Kahe   public   beach   located   to   the   north   of   the   WMH  
          permitted  outfall.  
          Monday,   January   17   —   By   8   a.m.,   WMH   cleanup   crews   were   sent   to   all   three   of   the  
          aforementioned   areas   and   collected   additional   debris   from   the   shoreline,   including   what  
          appeared  to  be  a  lessening  amount  of  medical  waste.  
          Tuesday,   January   18   —   By   8   a.m.,   WMH   dispatched   cleanup   crews,   initially   focusing  
          attention  at  Nimitz  beach,  followed  by  White  Plains,  and  then  the  storm  water  outfall.  
          Wednesday,  January  19  —  By  8  a.m.,  the  cleanup  team  returned  to  Kahe  beach,  the  storm  
          water  outfall,  and  then  Nimitz  and  White  Plains  beaches,  in  order.  Crews  also  continued  to  
          be  responsive  to  reported  findings  from  the  public.  
          Thursday,  January  20  —  By  8  a.m.,  personnel  split  into  two  teams,  with  one  team  returning  
          to  Kahe  beach  and  the  storm  water  outfall,  and  the  other  team  returning  to  Nimitz  and  White  
          Plains  beaches.  Crews  also  continued  to  be  responsive  to  reported  findings  from  the  public.  
          Friday,  January  21  —  Beginning  at  8  a.m.,  the  cleanup  team  returned  to  Kahe,   Nimitz  and  
          White  Plains  beaches,  as  well  as  the  storm  water  outfall.  The  WMH  team  found  no  medical  
          waste.  
          Monday,  January  24  —  WMH  performed  a  final  beach  assessment  and  observed  no  waste  
          attributed  to  the  WGSL.    




                                                                 
                                         Removal  Action  Summary  Report  
August  2011                      Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                                Page  18  of  19  
  

D.          RESOURCES  COMMITTED  
Table  7  summarizes  WMH’s  good  faith  estimate  of   the  costs  incurred  by  WMH  during  the  removal  
action.   During   the   removal   action,   WMH   spent   approximately   $2,252,501.64   on   third   party   costs.  
This  cost  estimate  does  not  include  internal  costs  (e.g.,  labor)  incurred  by  WMH  or  the  City.  Invoices  
and  backup  for  the  costs  incurred  area  are  presented  in  Appendix  E.  

Table  7:  Costs  Incurred  to  WMH  during  Response  Activities  

Invoice  
No.               Date                Contractor                                     Description                                 Amount  
2248             2/11/11                 PCS                          Vacuum  truck  and  misc.  storm  clean  up               $11,580.12  
2249  R          2/11/11                 PCS                                       E6  South  Pond                             $168,604.33  
                (Revised  
                5/19/11)  
2261             4/15/11                  GBI                                 Storm  Water  Response                           $103,322.45  
2262             4/15/11                  GBI               Storm  Water  Response,  Repair  liner  in  E6,  E6  Sump          $220,761.00  
                                                                                   work  
2263             4/15/11                  GBI               Storm  Water  Response,  Repair  liner  in  E6,  E6  Sump          $353,526.73  
                                                                                   work  
2267             4/30/11              American                              Storm  Related  Liner  Repairs                      $78,901.26  
                                Environmental  Group,  
                                        LTD  
2268             4/30/11         Watanabe  Ing,  LLP                          Storm  Event  Legal  Fees                         $45,126.86  
2269             4/30/11               AECOM                                   Storm  Event  Sampling                           $17,935.67  
2270             4/30/11                  GEI                                 Storm  Event  Work  Plans                         $19,204.75  
2274             5/19/11                  GBI                 Storm  Related  Costs  including  Repair  Liner,  E6             $125,918.41  
                                                           Leachate  sump,  repair  damage  to  slope  of  West  Berm  
                                                                                  Phase  III  
2277             5/23/11               AECOM                                CQA  for  Storm  Event  Costs                       $40,008.62  
2278             5/26/11                                                       Security  Cost  Increase                         $10,502.62  
2279             5/24/11                 PCS                                          Leachate                                 $242,562.88  
2280             5/23/11                 PCS                           Miscellaneous  Storm  Event  Charges                      $4,867.67  
2282             5/24/11                 PCS                          Storm  Water,  Sediment  Pond  Pumping                   $226,465.28  
2283             5/24/11                 PCS                 Storm  Water,  Sediment  Pond  and  Cell  E6  Pumping              $32,565.76  
2286             5/24/11                  GBI                 Storm  Related  Costs  including  Repair  Liner,  E6             $250,564.30  
                                                           Leachate  sump,  repair  damage  to  slope  of  West  Berm  
                                                                                  Phase  III  
2291             6/13/11                  GBI                 Storm  Related  Costs  including  Repair  Liner,  E6             $160,328.86  
                                                           Leachate  sump,  repair  damage  to  slope  of  West  Berm  
                                                                                  Phase  III  
6705             7/31/11                  GBI                            Sedimentation  Basin  Restoration                     $139,754.07  
                                                                                                                      TOTAL   $2,252,501.64  
Note:  
 Costs  do  not  include  WMH  markup  and  Hawaii  general  excise  tax  (GET).  
  

II.         EFFECTIVENESS  OF  REMOVAL  ACTIONS  
A.          ACTIONS  TAKEN  BY  OPERATOR    
WMH   executed   all   requirements   of   the   Order   in   a   timely   manner.   When   unable   to   meet   initial  
deadlines,   extensions   were   requested   and   granted   by   the   EPA.   WMH   hired   subcontractors   to  
perform  the  required  activities  on  site  and  communicated  regularly  with  the  regulators.  




                                                                   
                                       Removal  Action  Summary  Report  
August  2011                    Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI                     Page  19  of  19  
  

B.        ACTIONS  TAKEN  BY  STATE  AND  LOCAL  FORCES  
The  DOH  Clean  Water  Branch  performed   storm  water  sampling  at  the  site   on  January   13,  2011  in  
conjunction   with   samples   collected   for   WMH   by   AECOM.   Sampling   included   storm   water   from   the  
site  outfall  location,  the  ocean  outfall  location,  and  an  up-­canyon  location.  

The  City  provided  storm  water  pumping  and  transportation  to  the  WWTP,  conducted  various  beach  
cleanup  activities,  posted  warning  signs  surrounding  beaches,  and  provided  public  notices  via  press  
releases  of  the  activities  going  on  at  WGSL.    

C.        ACTIONS  TAKEN  BY  FEDERAL  AGENCIES  AND  SPECIAL  TEAMS  
The  EPA  Region  9  office  provided  oversight  of  all  response  action  activities  including  the  On-­Scene  
Coordinator  and  the  RCRA  Action  Officer  including  review  of  the  daily  and  weekly  progress  reports,  
and  review/approval  of  all  work  plans  and  reports  that  were  initiated  as  a  result  of  the  Order.  

D.        ACTIONS  TAKEN  BY  CONTRACTORS,  PRIVATE  GROUPS,  AND  VOLUNTEERS  
GEI  Consultants,  Inc.  and  Geosyntec  Consultants,  Inc.  provided  work  plans  for  the  activities  required  
by   the   Order.   PCS   provided   pumping   and   transport   services   for   the   storm   water.   GBI   performed  
general   earthwork   and   construction   services   during   the   execution   of   the   work   plans.   AECOM  
provided  Construction  Quality  Assurance  oversight  of  the  activities  including  documentation  of  work  
performed.    

Volunteers   were   not   present   on   site   during   the   removal   action;;   however,   some   volunteers   in   the  
surrounding   community   helped   clear   storm   drains,   sewer   lines,   and   City   beaches   after   the   storm.  
However,  these  activities  were  not  part  of  the  response  action.  

III.      RECOMMENDATIONS  
A.        MEANS  TO  PREVENT  A  RECURRENCE  OF  THE  DISCHARGE  OR  RELEASE  
The  amount  of  rain  that  fell  in  December  2010  and  January  2011  was  extremely  unusual  and  not  a  
typical  rainfall  pattern  for  the  area.  The  storm  event  concluding  on  January  13th  was  described  as  a  
“100-­year   storm”   event.   Based   on   rainfall   data   from   the   up-­canyon   Palehua   rain   gauge,   the   first  
major   storm   that   occurred   on   December   19-­20,   2010   generated   a   total   recorded   rainfall   at   the  
Palehua  station  of  10.44  inches.  The  second  significant  rain  event  occurred  on  December  26-­27  and  
generated  a  total  recorded  rainfall  at  the   nearby   Palehua   weather  station  of  station   of  5.68   inches.  
The  storm  was  significant  because  it  occurred  less  than  one  week  after  the  December  19-­20  storm.  
The  third  and  largest  storm  occurred  on  January  12-­13,  2011.  The  storm  produced  12.21  inches  of  
rain  in  total,  with  10.68  inches  of  rain  falling  in  a  24-­hour  period.  Most  significant  was  the  short-­term  
intensity  of  this  storm,  which  generated  7.63  inches  of  rain  during  a  6-­hour  period,  6.23  inches  of  rain  
over  a  3-­hour  period,  and  3.65  inches  of  rain  over  a  1-­hour  period.  

Prior  to  completion  of  the  western  storm  water  diversion  system,  run-­on  to  the  WGSL  was  managed  
with   on-­site   surface   water   conveyance   systems   which   routed   storm   water   through   the   site.   The  
western   storm   water   diversion   system   (also   described   as   the   offsite   surface   water   conveyance)   is  
designed   bypass   the   24-­hour,   25-­year   storm   flows   and   can   handle   flow   from   a   100-­year,   24-­hour  
storm   with   minimal   or   no   damage   occurring.   When   all   portions   of   the   system   are   completed,   the  
system   will   bypass   run-­on   around   the   landfill   and   discharge   to   a   stilling   basin   to   be   constructed  
below  the  existing  sedimentation  basin.    

The   upper   portion   of   the   western   storm   water   diversion   system   was   functionally   complete   on  
February   15,   2011   and   constructed   per   the   approved   design   specifications.   A   Surface   Water  
Management  Plan  has  been  submitted  to  and  approved  by  the  EPA  that  describes  the  surface  water  
management   features   present   at   WGSL.   More   information   can   be   found   in   the   Surface   Water  
Management  Plan,  located  in  Appendix  D.    


                                                                
 
 




              Appendix  A  
          Correspondence    
  




       
 
FOR IMMEDIATE RELEASE
Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com


  WASTE MANAGEMENT: UPDATE ON BEACH CLEANUP POST STORM
                    Public Hotline Remains Open for Reports of Any Further Findings

HONOLULU – Jan. 24, 2011 – Waste Management of Hawaii (WM) provided an update following the “100-year
storm” that hit Oahu on Jan. 13.

The downpour made it necessary for the Waimanalo Gulch Sanitary Landfill, operated by WM for the City and
County of Honolulu, to discharge storm water into the ocean. The extreme nature of the Jan. 13 floodwaters
resulted in an unusual amount of debris.

The following is a summary of WM shoreline cleanup activities. The WM cleanup team was also continuously
responsive to reported findings from the public. WM established a hotline for individuals to report waste on
beaches near the landfill.

        Thursday, Jan. 13 — WM evaluated storm water conditions throughout the day of the storm event and
        determined that a large body of storm water had collected in the area of the new cell construction.
        Working in collaboration with the state Department of Health (DOH), WM and the city installed warning
        signs in the shoreline area of the Ko Olina Resort, where the landfill outfall is located, and along the
        associated beach shoreline. Additionally, WM and the city began a water-quality sampling program that
        same day. Later on Jan. 13, WM began debris cleanup at the overflow and the storm water
        sedimentation basin once the flood waters had subsided enough to perform this operation safely. At
        that time, it was determined that the debris also contained sterilized medical waste.

        Friday, Jan. 14 — WM dispatched an evaluation and cleanup team to the ocean side of the landfill’s
        permitted storm water outfall, located on the north end of the Ko Olina Resort property across
        Farrington Highway from the landfill. The crew spent several hours cleaning debris from this area. At
        the time, there was no apparent evidence of remaining medical waste material. WM continued to clean
        up areas located between the sediment basin and the permitted outfall. Also on Jan. 14,
        representatives of WM, the city and DOH held a press conference at the landfill to further inform the
        public of potential concerns associated with the storm events, and to provide an update on the cleanup
        efforts, warning sign postings and water quality sampling being performed by WM and the city.
        Numerous news interviews and media announcements were provided by all parties over the following
        several days in order to keep the public fully informed.

        Saturday, Jan. 15 — WM personnel continued evaluation of the shoreline area. In the afternoon,
        additional medical waste material was reported in the WM outfall area located near the Ko Olina Resort
        area.

        Sunday, Jan. 16 — At 7 a.m., WM sent its cleanup crew back to the area and evaluated an
        approximate one-half to three-quarters of a mile section of the beach, including a return to the outfall
        area. No further medical waste was noted by WM personnel at this time. Additionally, a hotline was also
        set up to provide the public with the opportunity to report any observations of medical waste material



                                                    (more)
Waste Management Provides Update on Beach Cleanup following Jan. 13 Storm
Page 2 of 2


        found on local beaches. The DOH announced the hotline to the public via news media, and WM
        representatives continued to remind news media to include the hotline in any further media updates.
        WM representatives used reports provided via the hotline to evaluate information and determine where
        to concentrate its ongoing daily cleanup efforts. Subsequently, in the afternoon of Jan. 16, WM was
        notified that some plastic syringes (absent needles) had been found at the White Plains beach located
        farther south on the shoreline. WM dispatched cleanup crews to this beach, as well as the Kahe public
        beach located to the north of the WM permitted outfall.

        Monday, Jan. 17 — By 8 a.m., WM cleanup crews were sent to all three of the aforementioned areas
        and collected additional debris from the shoreline, including what appeared to be a lessening amount of
        medical waste.

        Tuesday, Jan. 18 — By 8 a.m., WM dispatched cleanup crews, initially focusing attention at Nimitz
        beach, followed by White Plains and then the storm water outfall.

        Wednesday, Jan. 19 — By 8 a.m., the cleanup team returned to Kahe beach, the storm water outfall,
        and then Nimitz and White Plains beaches, in order. Crews also continued to be responsive to reported
        findings from the public.

        Thursday, Jan. 20 — By 8 a.m., personnel split into two teams, with one team returning to Kahe beach
        and the storm water outfall, and the other team returning to Nimitz and White Plains beaches. Crews
        also continued to be responsive to reported findings from the public.

        Friday, Jan. 21 — Beginning at 8 a.m., the cleanup team returned to Kahe, Nimitz and White Plains
        beaches, as well as the storm water outfall. The WM team found no medical waste.

WM is working closely with city and state officials to monitor the beaches until water testing in the area shows
normal levels and they are free of landfill debris. That determination will be made in cooperation with city and
state health officials. These officials, along with the U.S. Environmental Protection Agency, have approved WM
processes and procedures to clean up these areas.

In addition, a diversion channel that would have averted the debris discharge caused by the Jan. 13 storm is
mere weeks from completion.

WM will continue to maintain its hotline for the foreseeable future. WM encourages anyone who finds waste on
beaches near the landfill to report it by calling (808) 668-2985.

Waste Management of Hawaii operates Waimanalo Gulch, West Hawaii and Kekaha Landfills as an integral
part of each county's solid waste management infrastructure. The facilities handle municipal solid waste, which
is heavily regulated, monitored and controlled by local, state and federal government agencies. For more
information, visit www.keepinghawaiiclean.com.

                                                      ###
FOR IMMEDIATE RELEASE
Media Contact:
Keith DeMello
McNeil Wilson Communications
808-539-3482
keith.demello@mwc-anthology.com


   WAIMANALO GULCH LANDFILL AGREES TO WORK PLANS WITH U.S. EPA
HONOLULU, Jan. 25, 2011 – Waste Management of Hawaii (WM) today announced it has entered
into a formal agreement with the United States Environmental Protection Agency (EPS) regarding
several work plans needed to alleviate damage to the Waimanalo Gulch Landfill caused by the 100-
year storm of Jan. 13, 2011.

The intense storm that hit Oahu made it necessary for the Waimanalo Gulch Landfill, operated by
WM for the City and County of Honolulu, to discharge large volumes of storm water from the landfill
into the ocean. Some limited amounts of solid waste were swept along with the storm water and
discharged. WM is working with the EPA, the City and County of Honolulu and the state Department
of Health to develop written plans that detail the steps that will be taken to clean up the landfill.

“In the interest of keeping all parties informed, we want to let everyone know that we are working with
the EPA on a consent agreement, which is a formal document dedicated to memorializing the work
we need to do to get the landfill back into pre-storm shape,” said Joe Whelan, general manager of the
Waimanalo Gulch Landfill. “While much of the work identified in the agreement is already underway,
the agreement will serve to memorialize those commitments.”

Whelan added that the WM clean-up team was out every day on the beaches picking up debris and
that WM established a hotline (668-2985) for people to report waste they found on the beaches near
the landfill. As of Jan. 25, the beaches were reopened for swimming but the landfill remained closed.

Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City
and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility
is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by
local, state and federal government agencies. The facility's staff includes 31 full-time employees,
many of whom are active in the local community. In addition to its community contributions and
significant volunteer efforts, Waste Management provides a benefit to the local economy of more than
$2.9 million annually. To learn more about Waste Management’s commitment to the beautification of
the islands, visit www.keepinghawaiiclean.com.

                                                 ###
 
From:              Kenefick, Andrew M
 To:                Helmlinger.Andrew@epamail.epa.gov
 Cc:                dviola@honolulu.gov
 Subject:           WGSL Contractors
 Date:              Tuesday, January 25, 2011 11:36:00 AM



Andrew,

The following is a list of the contractors being used by WMH. After execution of the AOC
we will submit these names, as requried. If EPA thinks that it will not waive the
requirements in paragraph 15 relating to the QMP, please let me know ASAP so that the
Work will not be delayed. Thanks.

            AECOM: CQA firm for construction activities

            AEG: Liner installation/repair contractor

            Goodfellow Bros. Inc: General Contractor

            Pacific Commercial Services: Pumping contractor

            GeoSyntec: Design Engineer for landfill construction

            GEI: Design Engineer for drainage construction

  
Andrew  M.  Kenefick
Senior  Legal  Counsel
Waste  Management
Western  Group  Legal  Department
801  2nd  Avenue,  Suite  614
Seattle,  WA  98104
206-­‐264-­‐3062  (direct)
866-­‐863-­‐7961  (direct  fax-­‐toll  free)
206-­‐264-­‐8212  (main  fax)
akenefick@wm.com
admitted  in  Washington
  
Our  renewable  energy  projects  create  enough  energy  to  power  more  than  one  million  homes.
The  recovery  of  landfill  gas,  coupled  with  the  power  generated  from  the  conversion  of  solid  waste
at  our  waste-­to-­energy  plants,  saves  the  equivalent  of  more  than  13  million  barrels  of  oil.
  
The  information  contained  in  this  e-­mail  message  may  be  privileged,  
confidential  and  protected  from  disclosure.    If  you  are  not  the  intended  
recipient,  any  dissemination,  distribution  or  copying  is  strictly  prohibited.    
If  you  think  that  you  have  received  this  e-­mail  message  in  error,
  please  e-­mail  the  sender  at  akenefick@wm.com
  
From:          Helmlinger.Andrew@epamail.epa.gov
To:            Kenefick, Andrew M
Cc:            Baylor.Katherine@epamail.epa.gov; Moxley.Bret@epamail.epa.gov
Subject:       Confirmation of contractors at WGSL
Date:          Wednesday, January 26, 2011 7:23:18 AM



Andrew;

I write to confirm that both of EPA's project contacts have noted to me, at your request,
that they are comfortable with the existing contractors at the WGSL site. The list of
contractors that you provided satisfies the requirement for names and certifications of the
contractors in the Jan. 25, 2011 AOC. If concerns arise, EPA will notify WM per the AOC.



____________________________________

J. Andrew Helmlinger
Attorney Advisor
U.S. Environmental Protection Agency
75 Hawthorne Street (ORC-3)
San Francisco, CA 94105
Telephone: (415) 972-3904
Facsimile: (415) 947-3570
From:                      Whelan, Joseph
Sent:                      Thursday, January 27, 2011 12:30 PM
To:                        Kabei.Arlene@epamail.epa.gov; Armann.Steve@epamail.epa.gov;
                           Vaille.Rich@epamail.epa.gov; Tyahla.Stephen@epamail.epa.gov;
                           Moxley.Bret@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov;
                           Wall.Steve@epamail.epa.gov; baylor.katherine@epa.gov;
                           stuart.yamada@doh.hawaii.gov; Steven.chang@doh.hawaii.gov
Subject:                   WGSL Cell 6 Operations Report

Greetings all.

          Please find attached a copy of the QC report documenting the evaluation and repairs made to
waste disposal cell E6 located at WGSL. As noted, this cell has been cleared to resume waste placement
per the terms of the report. Also attached is the requested contingency plan that addresses potential
future storm events. We would appreciate your earliest review of these documents and approval to
resume operations in Cell E6. As you know, there is a significant buildup of solid waste that requires
landfill disposal at this time. Thank you for your quick response and your continued support during this
ordeal. We appreciate your efforts.


        Best regards,




                                 Letter Report Cell Cell E6 MSW Area      WGSL SW
                                   E6 and E4 R...       1-26-11.pdf  ntingency Plan 1-26-
        Joe




Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile

Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; alec.wong@doh.hawaii.gov
Subject:          WGSL Daily Progress Report - AOC
Date:             Thursday, January 27, 2011 7:27:00 PM




Greetings  all.

      Please  find  below  the  initial  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

              1)East  side  assessment  and  repair  report  submitted  to  all  parties  on  1-­‐27-­‐11.

              2)South  portion  of  west  side  assessment  to  commence  1-­‐28-­‐11




        Western  Storm  water  Diversion  Project  (to  render  functional):

            1) Diversion Structure: Poured half of walls 1-26-11, curing today, strip walls & clean
storm mud tomorrow (Friday)

              2) Box Culvert: Continue forming and placing steel for invert. Friday pour 250 lf of invert
              & place steel for invert.

              3) Pipe: Remove over burden for final trench blast 1-26-11, today, final blast for pipe
              trench & excavated previous blast material, Friday, excavate pipe trench

        Cell  6  Leachate  Riser  Restoration:

            1)The  controls  for  the  cell  6  leachate  riser  were  re-­‐established  today  at  the
generator  and  storage  area.

              2)Contractors  investigated  options  for  removal  of  the  silt  deposits  in  the
leachate  riser  area  on  1-­‐26-­‐11  In  order  to  connect  the  riser  pumps.

                      Removed  approximately  4  feet  of  mud  (12,000  gallons)  today,  Friday
continue  to  pump  down  mud

        Sediment  Basin:
               1)pumped  60,000  gallons  today  and  sent  to  the  WWTP  for  treatment  and
disposal,  Friday,  continue  pumping

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.

Best  regards,

       Joe

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          WGSL Daily Progress Report - AOC
Date:             Friday, January 28, 2011 6:49:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                1)   EPA  approval was received  today allowing  WM to  resume  operations  in the
east  side  of  cell E6.

              2)    The  south  portion  of the west  side  assessment of  cell  E6 is  ongoing.



        Western  Storm  water  Diversion  Project  (to  render  functional):

                             1) Diversion Structure:        The contractor stripped
                                                                             forms  from
                             Wednesday’s concrete pour  and  began cleaning  storm  mud  and
                             debris  from  the  rebar  supports.   From Saturday thru  Monday
                             the forms  will  be  reset  for the next  pour.

                             2) Box Culvert:       The contractor p oured  200  lf  of  invert
                                                                                        concrete  in
                             the  open  box channel, and  continued  placing  structural  steel
                             forms.   From Saturday thru  Monday additional forming  and
                             placement  of  structural  steel  will  continue  in  preparation  for
                             invert   pours  on  Tuesday  and  Friday.

                             3) Pipe:     The contractor continued  excavating
                                                                            the  Hobas  pipe
                             trench  and  placing  bedding  (aggregate  below  pipe).   These  same
                             operations will  continue through  early  next  week  when  pipe  can
                             be  placed.

        Cell  6  Leachate  Riser  Restoration:

                             1 )  
                                 Electricians  are   preparing the controls  and  generator  for
                             the  leachate pump  at the  storage tank.     The pumping
                             contractor continues removing  water  from  pond  surface.  
2)    The  contractor pumped  20,321  gallons  of  silt  from the south  pond  area.  
From   Saturday  thru  Monday the  contractor  will continue  to  pump  silt  from  south  pond.

                    

       Sediment  Basin:

                            1)The  contractor pumped  60,000  gallons of storm  water again
                            today which  was  sent  to  the  WWTP  for  treatment  and  disposal.  
                            From Saturday  thru  Monday the  contractor  will  continue     this
                            pumping.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                         Kabei.Arlene@epamail.epa.gov
Sent:                         Friday, January 28, 2011 10:56 AM
To:                           Whelan, Joseph
Cc:                           gary.gill@doh.hawaii.gov; stuart.yamada@doh.hawaii.com;
                              Takata.Keith@epamail.epa.gov; Diamond.Jane@epamail.epa.gov;
                              Scott.Jeff@epamail.epa.gov; Baylor.Katherine@epamail.epa.gov;
                              Moxley.Bret@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov;
                              Wampler.David@epamail.epa.gov; Barroll.Hugh@epamail.epa.gov;
                              armann.steve@epa.gov; Vaille.Rich@epamail.epa.gov;
                              Wall.Steve@epamail.epa.gov; Sheehan.Eileen@epamail.epa.gov;
                              Huetteman.Tom@epamail.epa.gov; Higuchi.Dean@epamail.epa.gov;
                              Ryerson.Teddy@epamail.epa.gov;
                              Johnson.Kathleen@epamail.epa.gov; Glenn.William@epamail.epa.gov;
                              Arlene_Kabei/Janice.Okubo@doh.hawaii.gov;
                              tsteinberger@honolulu.gov
Subject:                      Notice of EPA Approval to Operate Cell E6 at Waimanalo Gulch Landfill,
                              Oahu HI

Dear Mr. Whelan:

We have reviewed and accept the Construction Quality Assurance Report submitted for the liner
installation at Cell #E6. We have also reviewed your "Stormwater Management Update and Contingency
Plan," Version 4, dated 1/27/2011, which supports your belief that the measures described in the
document "will prevent waste material and stormwater that may come into contact with waste from exiting
the facility in the event of a major storm."

While WM has not yet completed the tasks yet due in the Administrative Order on Consent, dated
January 25, 2011, USEPA recognizes that WM has made progress in improving the situation at the
landfill and that the continued closure of the landfill may create a risk to public health from accumulating
wastes, in particular sewer sludge, throughout Oahu. We encourage WM to continue to forge ahead
quickly on completing the upper valley stormwater diversion system ("Western Drainage System") and
continue enhancements to the temporary stormwater systems. It is our expectation that the Western
Drainage System will be functional in 15 days. Until the system is functional, please continue to enhance
the capabilities of the temporary stormwater control systems to manage the quantity of water experienced
on January 13, 2011.

Therefore, pursuant to Section VIII (g) of the Administrative Order on Consent, USEPA hereby approves,
with conditions noted below, the operation of Cell #E6 to accept wastes at the Waimanalo Gulch Sanitary
Landfill (WGSL). We understand that the Hawaii Department of Health has also notified you that they do
not object to reopening of landfill Cell #E6.

The reopening of WGSL is the best alternative to minimize the risks to human health and the environment
associated with the handling of solid wastes on Oahu. This approval is not a determination WM's
operation of WGSL has been or is currently in compliance with applicable laws governing the
management of solid waste including, but not limited to, the Clean Water Act and the Resource
Conservation and Recovery Act. Nor is it a determination that reopening the landfill is consistent with
these laws.

We approve reopening with the following conditions:

    With regard to Cell E6:
1) Waste is disposed only within the footprint designated on your hand-annotated drawing
submitted with your Petition for Re-Opening;
        2) As recommended by AECOM, waste placement operations should be kept a minimum of 50
feet away from the damaged western edge of E6; and
         3) The western edge of Cell E6 should be repaired as expeditiously as practicable, with plan
and schedule for repair provided to EPA within one week.

     With regard to the facility:
     4) Waste Management must submit a revised stormwater contingency plan by February 1, 2011 that
describes how WM will manage stormwater on the site in response to storm events to prevent the
discharge to waters of the United State of solid wastes, leachate, and/or stormwater contaminated by
pollutants generated at WGSL pending completion of the stormwater diversion system ("Western
Drainage System") currently under construction. The contingency plan must list and/or describe, at
minimum, the following:

           - type and quantity of on-site mobile heavy equipment WM employees can use to maintain
stormwater systems in response to storm events, including, pumps, tractors, back-hoes;
           - names of the Waste Management point of contact, or points of contact, available at any time,
and the number of WM employees who can be deployed if storm water management systems or
   equipment fail or are not properly operating;
           - how WM will monitor storm events and the process WM will follow to deploy employees on-
site in response to storm events;
           - name and location of storm water management equipment or systems (e.g., retention basins,
pipes, drains, etc.) that will be monitored and/or maintained by on-site employees in response to
   storm events;
           - types of corrective actions or maintenance activities that on-site employees should take in
response to storm events to ensure storm water conveyance systems remain operational;
           - beach monitoring activities (including posting signs, and performing clean-up) that will occur if
un-permitted storm water discharge from the landfill occurs.

    5) No later than fifteen (15 days) after the completion of a functional storm water division structure
(Western Drainage System) as required in 19.b. of EPA's Order, WM must revise and submit to EPA its
  SWPCP to incorporate the functional Western Drainage System and all ancillary storm water
connections into its revised SWPCP consistent with the requirements of its storm water general permit.


EPA sincerely appreciates your responsiveness to the information we requested for making this Approval
determination. We recognize that much work and improvements at the site have been accomplished in
short order since January 13th, 2011.


Arlene Kabei
Associate Director
Waste Management Division
USEPA, Region 9
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          WGSL AOC Daily Progress Report
Date:             Monday, January 31, 2011 5:30:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  will  be
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   The  assessment
                                                              should  be  completed  by  this  Saturday.



        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1) Diversion Structure: The contractor is
                                                              resetting the wall forms and continues installing
                                                              reinforcing steel rebar, in anticipation of pouring
                                                              additional concrete wall material on Wednesday.

                                                              2) Box Culvert:      The contractor has
                                                              continued  placing  structural  steel  forms
                                                              in  the  bottom  and  walls  of  the open  box
                                                              culvert  in  preparation  for  invert   pours
                                                              on  Tuesday  and  Friday.

                                                              3) Pipe:     The contractor completed
                                                              excavating the  Hobas  pipe trench  and
                                                              continues placing  bedding  (aggregate
                                                              below  pipe).     Pipe  placement  will
                                                              commence  on  Tuesday.

        Cell  6  Leachate  Riser  Restoration:
1 )    The  pumping  contractor
                                                                                        continues
                                                            removing  water  from the  water surface.  

                                 2)    The  contractor has  lowered  the   silt  from  the  south  pond  area
by  an  additional  2  feet.  

                     

       Sediment  Basin:

                                                            1)The  contractor pumped 274,000  gallons
                                                            of  storm  water from  the  sedimentation
                                                            basin  from  Saturday  thru  Monday, which
                                                            was  sent  to  the  WWTP  for  treatment  and
                                                            disposal.  

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
FOR IMMEDIATE RELEASE
Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com


      WASTE MANAGEMENT OF HAWAII PROVIDES UPDATE
             Recaps EPA Milestones Achieved for Waimanalo Gulch Sanitary Landfill

HONOLULU – Jan. 31, 2011 – Waste Management of Hawaii (WM) today provided an update on
the progress of work to alleviate damage to the Waimanalo Gulch Sanitary Landfill resulting from
recent severe rainstorms and the company’s ongoing efforts with the City and County of Honolulu to
fully restore landfill services to Oahu.

The U.S. Environmental Protection Agency (EPA) approved WM resuming operations in the eastern
portion of cell E6, which was damaged in the Jan. 13 storm. While the landfill remains closed to the
public, on Friday the landfill began accepting limited city deliveries of critical waste items, such as H-
POWER residue and wastewater sludge.

The storm water that collected in the area of cell E6 has been removed. On Thursday alone,
contractors removed approximately 4 feet of mud (12,000 gallons) and pumped 60,000 gallons from
the sediment basin, sending it to the wastewater treatment plant for proper treatment and disposal.

Furthermore, half of the walls for the new storm water diversion channel have been poured and set to
cure.

“As of today, WM has met all milestone deadlines for the Waimanalo Gulch Sanitary Landfill outlined
in our Jan. 25 consent agreement with the EPA,” said Joe Whelan, general manager of the landfill.
“We are making progress in meeting those that remain according to the agreed upon calendar. This
includes the completion of the new storm water diversion channel, already in progress.”

WM began filing regular progress reports every weekday to EPA and state Department of Health, as
outlined in the company’s agreement with the EPA. While much of the work identified in the
agreement was already underway, the agreement served to memorialize commitments.

Although beaches were declared on Jan. 25 to be safe for swimming, WM continues to encourage
those who find debris appearing to be from the landfill to report it by calling (808) 668-2985.

Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City
and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility


                                                  (more)
Waste Management of Hawaii Provides Update
Page 2 of 2


is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by
local, state and federal government agencies. The facility's staff includes 31 full-time employees, many
of whom are active in the local community. In addition to its community contributions and significant
volunteer efforts, Waste Management provides a benefit to the local economy of more than $2.9
million annually. To learn more about Waste Management’s commitment to the beautification of the
islands, visit www.keepinghawaiiclean.com

                                                 ###
From:                      Whelan, Joseph
Sent:                      Tuesday, February 01, 2011 4:52 PM
To:                        'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov';
                           'stuart.yamada@doh.hawaii.gov'
Subject:                   EPA AOC Work Plan Submittals

Greetings all.

        Please find attached an electronic version of the various work plans and reports that are due
today as a result of the terms of the Administrative Order on Consent (AOC). Hard copies of each
submittal were sent to you by certified mail dated February 1, 2011. Please let me know if you have any
questions. We look forward to receiving your approval.


        Best regards,




Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.




DOC admin order
  consent.pdf
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          WGSL AOC Daily Progress Report
Date:             Tuesday, February 01, 2011 5:26:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench is  being
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   The  assessment
                                                              should  be  completed  by  this  Saturday.



        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1) Diversion Structure: The contractor
                                                              continues to place the wall forms and reinforcing
                                                              steel rebar, in anticipation of pouring additional
                                                              concrete wall material on Wednesday.

                                                              2) Box Culvert: The contractor poured
                                                              concrete today to place the invert box
                                                              culvert, Tomorrow he will resume
                                                              placing  structural  steel  forms  in  the
                                                              bottom  and  walls  of  the open  box  culvert
                                                              in  preparation  for  invert   pours  on
                                                              Friday.

                                                              3) Pipe: Placement of  the large diameter
                                                              Hobas pipe resumed today.   The contractor
                                                              continues placing  bedding  (aggregate
                                                              below  pipe).

        Cell  6  Leachate  Riser  Restoration:
1 )    The  pumping  contractor   continues
                                                           skimming water  from the  surface  of  the
                                                           area  south  of Cell  E6,  and  transported
                                                           16,500  gallons  today  to  the  waste  water
                                                           treatment  plant.   These activities are
                                                           ongoing.

                                                           2)    The  contractor removed  16,000  gallons
                                                           of  mud  and  water  mixture  from  the  area
                                                           south  of  Cell  E6  and  placed  into  frac  tanks
                                                           in  order  to allow  them  to  separate.    These
                                                           activities  are  ongoing.

                    

       Sediment  Basin:

                                                           1)The  contractor pumped 56,000  gallons
                                                           of  storm  water from  the  sedimentation
                                                           basin today, which  was  sent  to  the  WWTP
                                                           for  treatment  and  disposal.   These
                                                           activities are ongoing.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                   Whelan, Joseph
To:                     Tyahla.Stephen@epamail.epa.gov
Subject:                FW: AGSL Additional Submittal under AOC - H&S Plan
Date:                   Tuesday, February 01, 2011 6:00:00 PM
Attachments:            WGSL IIPP JAN 2009.pdf
                        Bloodborne Pathogen Plan.pdf
                        020_Confined_Space_Program.pdf
                        PART E_ Emer_Action_Plan_Jan2011.pdf
                        035_Hazard_Communication.pdf
                        025_Lock-Out_Tag-Out.pdf
                        015_Personal_Protective_Equipment.pdf
                        055_Respiratory_Protection.pdf
                        021_Substance_Abuse_Program_for_Employees_and_Candidates.pdf
                        065_Forklift_Training.pdf
                        050_Welding,_Burning,_and_Hot_Works.pdf
                        030_Hearing_Conservation.pdf




Round  two

_____________________________________________
From: Whelan, Joseph
Sent: Tuesday, February 01, 2011 4:59 PM
To: 'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov'; 'stuart.yamada@doh.hawaii.gov'
Subject: AGSL Additional Submittal under AOC - H&S Plan

Greetings  all.

Please  find  an  electronic  version  of  the  facility  Health  &  Safety  Plan,  per  the  terms  of  the
AOC.    A  hard  copy  of  this  plan  is  being  sent  to  you  under  separate  cover,  as  the  file  size
was  too  large  to  send  with  the  other  submittal.

       Best  regards,                    




Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               Tyahla.Stephen@epamail.epa.gov
Subject:          FW: EPA AOC Work Plan Submittals
Date:             Tuesday, February 01, 2011 5:59:00 PM
Attachments:      DOC admin order consent.pdf




Hi  Steve.    Welcome  back!!

_____________________________________________
From: Whelan, Joseph
Sent: Tuesday, February 01, 2011 4:52 PM
To: 'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov'; 'stuart.yamada@doh.hawaii.gov'
Subject: EPA AOC Work Plan Submittals

Greetings  all.

       Please  find  attached  an  electronic  version  of  the  various  work  plans  and  reports  that
are  due  today  as  a  result  of  the  terms  of  the  Administrative  Order  on  Consent  (AOC).    Hard
copies  of  each  submittal  were  sent  to  you  by  certified  mail  dated  February  1,  2011.    Please
let  me  know  if  you  have  any  questions.    We  look  forward  to  receiving  your  approval.



       Best  regards,




Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for 2-2-11
Date:             Wednesday, February 02, 2011 7:06:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  is  being
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   A temporary fill
                                                              road was placed today to allow the
                                                              excavator to access the side wall liner.
                                                              The  assessment  should  be  completed  by
                                                              this  Saturday.



        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:      The  contractor
                                                              continues  to  place  the  wall  forms  and
                                                              reinforcing  steel  rebar,  in  anticipation  of
                                                              pouring  additional  concrete  wall  material
                                                              on Thursday.    

                                                              2)    Box  Culvert:     Placement  of  reinforcing
                                                              steel  continued.   The  final  invert  pour is
                                                              scheduled  for  Friday.

                                                               3)    Pipe:    Placement  of  the  large  diameter
                                                              Hobas  pipe continued  today.   The
                                                              contractor continues placing  bedding
                                                              (aggregate  below and  around  the pipe),
and  began  pressure  testing the  joints of
                                                           placed  pipe.

       Cell  6  Leachate  Riser  Restoration:

                                                           1 )    The  pumping  contractor    continues
                                                           skimming  water  from the  surface  of  the
                                                           area  south  of  Cell  E6,  and  transported
                                                           16,500  gallons again today  to  the  waste
                                                           water  treatment  plant.   These activities
                                                           are ongoing.

                                                           2)    The  contractor removed  10,000
                                                           gallons  of  mud  and  water  mixture  from  the
                                                           area  south  of  Cell  E6 today, and  placed
                                                           into  frac  tanks  in  order  to  allow  them  to
                                                           separate.    These  activities  are  ongoing.

                    

       Sediment  Basin:

1)           The  contractor pumped 105,800  gallons of  storm  water from  the  sedimentation
basin  today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities
are ongoing.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for 2-3-11
Date:             Thursday, February 03, 2011 8:00:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  is  being
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   A temporary fill
                                                              road was placed to allow the excavator
                                                              to access the side wall liner. The
                                                              assessment  should  be  completed  by  this
                                                              Saturday.



        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     Concrete  wall
                                                              material was  poured  today, and the
                                                              contractor continues  to  place  the final wall
                                                              forms  and  reinforcing  steel  rebar.

                                                              2)    Box  Culvert:     The  contractor  completed
                                                              placement  of the  invert reinforcing  steel.  
                                                              The  final  invert  pour  is  scheduled  for
                                                              Friday.

                                                                3)    Pipe:    Placement  of  the  large  diameter
                                                              Hobas  pipe and  backfilling continued
                                                              today.   The  contractor continues pressure
testing the  joints of  placed  pipe.    Pipe
                                                           work  will  be  complete  Friday.

       Cell  6  Leachate  Riser  Restoration:

                                                           1 )    The  pumping  contractor   continues
                                                           skimming  water  from the  surface  of  the
                                                           area  south  of  Cell  E6.   These activities
                                                           are ongoing.

                                                           2)    The  contractor removed 12,500  gallons
                                                           of  mud  and  water  mixture  from  the  area
                                                           south  of  Cell  E6  today,  and  placed  into  frac
                                                           tanks  in  order  to  allow  them  to  separate.  
                                                           These  activities  are  ongoing.
                                                                 

       Sediment  Basin:

1)           The  contractor pumped 55,800  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for 2-4-11
Date:             Friday, February 04, 2011 5:20:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  is  being
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   A temporary fill
                                                              road was placed to allow an excavator
                                                              to remove over burden from the storm
                                                              in order to access the side wall liner,
                                                              which was exposed today. Operations
                                                              layer sand will be placed on Saturday.
                                                              Liner crews have begun their evaluation
                                                              of this area.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:    The  contractor
                                                              closed all remaining forms today  in
                                                              anticipation  of  the  final wall pour  on
                                                              February  8 th .

                                                              2)    Box  Culvert:     The  contractor  completed
                                                              pouring the channel invert  today.   Next
                                                              weeks  efforts  will  concentrate  on forming
                                                              the  transition  structure  from  box  culvert
                                                              invert  to  pipe  invert.

                                                                3)    Pipe:    The  contractor  completed  laying
                                                              the  Hobas  Pipe  today,  and continues
pressure  testing the  joints of  placed  pipe.  
                                                           Backfilling  of  the  pipe  trench  will  continue
                                                           thru  next  week.

       Cell  6  Leachate  Riser  Restoration:

                                                           1 )    The  pumping  contractor  continues
                                                           skimming  water  from the  surface  of  the
                                                           area  south  of  Cell  E6.   We anticipate Cell
                                                           E6 riser connections to commence on
                                                           Monday or Tuesday.

                                                           2)    The  contractor removed 10,000  gallons
                                                           of  mud  and  water  mixture  from  the  area
                                                           south  of  Cell  E6  today,  and  placed  into  frac
                                                           tanks  in  order  to  allow  them  to  separate.  
                                                           These  activities  are  ongoing.
                                                                 

       Sediment  Basin:

1)           The  contractor pumped 61,500  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                      Whelan, Joseph
Sent:                      Friday, February 04, 2011 11:06 AM
To:                        'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov';
                           'stuart.yamada@doh.hawaii.gov'
Subject:                   EPA AOC Submission No. 2

Greetings all.

         Please find attached an electronic version of the work plans and reports that are due today as a
result of the terms of the Administrative Order on Consent (AOC). Hard copies of each submittal were
sent to you by certified mail dated February 4, 2011. Please let me know if you have any questions. We
look forward to receiving your approval.




                                         DOCWGSL EPA              DOCWGSL EPA
                                       OC SUBMISSION 2.p        OC SUBMISSION 2 s
        Best regards,



Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile

Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                    Whelan, Joseph
To:                      Tyahla.Stephen@epamail.epa.gov
Subject:                 RE: Near-term storm preparation at WGSL
Date:                    Friday, February 04, 2011 2:51:00 PM



Greetings  Steve.
  
                                Please  find  our  responses  to  your  referenced  request.
  
                                Best  regards,
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Friday, February 04, 2011 9:41 AM
To: Whelan, Joseph
Cc: Moxley.Bret@epamail.epa.gov; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov;
steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; Wampler.David@epamail.epa.gov;
Blake.Ellen@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov
Subject: Near-term storm preparation at WGSL

Joe,

We are reviewing the submittals you provided on 1 February 2011 in response to our Administrative
Order on Consent ("AOC") and our 28 January 2011 e-mail that conditionally approved re-opening of
cell E6 at the Waimanalo Gulch Sanitary Landfill ("WGSL"). I anticipate sending you our detailed
feedback on those work plans and schedules by the latter part of next week.

However, in light of "heavy rain" being forecasted by NOAA for the vicinity of the WGSL this coming
weekend, we are providing the below interim comments on your "Revised Storm Water Management
Update & Contingency Plan," ("contingency plan") and would like your written response to these today.
  These particular comments generally concern near-term preparation for storm events and are either
items that lack detail or are absent in the contingency plan Waste Management of Hawaii ("WMH")
submitted on 1 February.

(1) Please provide details on WMH's process for deciding when Cell E6 operations are to be shut-
down due to rain storm events and how such a shut-down would be executed. [Whelan, Joe] The
facility is currently closed to the public, which means our daily volumes are fairly small. Our
normal procedures call for us to stop operations if rainfall amounts create either a safety,
environmental or operations concern. If unloading or processing operations are severely
affected, we would suspend operations, and begin covering the waste material placed that
day. As you know, we only create a working face disposal area large enough to accept the
predicted days waste receipts. Therefore, this area is very small now until we reopen to the
public. Once operations are ceased, we will place daily cover over all exposed waste. This
cover would meet interim cover requirements, which is one foot of soil, which is compacted
after placement.
(2) Please provide a description of how WMH would secure waste within Cell E6 in anticipation of a
significant rain event. [Whelan, Joe] We have already evaluated and reinforced the existing DI-
1 interceptor manhole by placing a mound of large boulders in front of this manhole to
prevent silt from washing over and covering the opening. Additionally, we have increased
the height and breadth of the berm placed below this manhole in an effort to create a damned
area in order to keep it from clogging with silt. Today we are also constructing a second
berm located just above the northern leading edge of Cell E6 in order to dam up any water
that fell in this area, and prevent it from entering Cell E6. This berm is slightly angled to
divert water towards the northwest, so that in the event that this new berm over topped, storm
water would be diverted into the previous Cell E6 lake area, but around any exist waste
material. This berm would also be covered with liner material in order to prevent any
breakthroughs.
(3) Please inform us of the status (e.g., flanged or otherwise shut and secured) of the 36-inch diameter
fiberglass manhole that connects to the 78-inch Hobas pipe, that is located just upstream of the
temporary earthen berm that is directly downstream of Cell E6. [Whelan, Joe] This manhole is
flanged off and covered by several feet of road base material, and not accessible to any storm
water.
(4) The contingency plan states, under item 5), that "The sedimentation basin, temporary berm in the
Cell E6 area, 36 inch storm water diversion piping, and general facility drainage ditches will be
monitored and maintained during potential storm events." Please describe the type and frequency of
monitoring that will be performed, who will perform the monitoring, including after normal work hours
(WMH's security service?). [Whelan, Joe] Waste Management and contractor employees are on
site performing normal duties from approximately 6:00AM thru 7:00PM daily. We have a 24
hour 7 day per week security service who are trained to phone WM on call personnel in the
event that a storm event hits the facility. Our employees would then provide an assessment
of current conditions.

I will give you a call in approximately an hour to discuss, but feel free to call me sooner.

We appreciate your cooperation.

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for 2-7-11
Date:             Monday, February 07, 2011 5:21:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench has  been
                                                              removed  to  allow  the  liner  material to  be
                                                              further  investigated.   Rains on Sunday
                                                              kept the liner crew from re-installing
                                                              the liner in this area within the anchor
                                                              trench. This work will be addressed on
                                                              Wednesday, weather permitting. A
                                                              temporary fill road was placed to allow
                                                              an excavator to remove over burden
                                                              from the storm in order to access the
                                                              side wall liner, which was exposed
                                                              Friday and Saturday. Operations layer
                                                              sand will be placed on Wednesday.


        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:    The  contractor
                                                              closed all remaining forms  in  anticipation
                                                              of  the  final  wall  pour  on  February  8 th .  
                                                              Sunday  rains  prevented  work  in  this  area
                                                              on  Monday  due  to  muddy  conditions.

                                                              2)    Box  Culvert:     The  contractor  completed
                                                              pouring the  channel  invert on  Friday.   This
                                                              weeks  efforts  will  concentrate  on  forming
                                                              the  transition  structure  from  box  culvert
invert  to  pipe  invert.

                                                              3)    Pipe:    The  contractor  completed  laying
                                                            the  Hobas  Pipe on  Friday,   and completed
                                                            pressure  testing the  joints of  placed  pipe.  
                                                            Backfilling  of  the  pipe  trench  will  continue
                                                            thru this  week.

       Cell  6  Leachate  Riser  Restoration:

                                                            1 )   We anticipate Cell E6 riser
                                                            connections to commence on Tuesday
                                                            and Wednesday.

                                                            2)    The  contractor removed 2500  gallons
                                                            of  mud  and  water  mixture  from  the  area
                                                            south  of  Cell  E6  today,  and  placed  into  frac
                                                            tanks  in  order  to  allow  them  to  separate.  
                                                            These  activities  are  ongoing. Rain all
                                                            day Sunday hampered removal activity
                                                            in this area.                    

       Sediment  Basin:

1)           The  contractor pumped 24,700  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager
Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 8, 2011
Date:             Tuesday, February 08, 2011 5:16:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  was
                                                              removed  to  allow  the  liner  material  to  be
                                                              further  investigated. Assessment  of
                                                              damage  in  southern  area  was  made  on
                                                              Saturday  2/6.  Areas  to  be  repaired  have
                                                              been  identified.  Repair  work  was  able  to
                                                              commence  on  the  southern  portion  of  the
                                                              E6  liner  slope  beginning  today.  The  repair
                                                              work  seems  to  be  limited  to  restoring  the
                                                              geotextile  to  its  originally  constructed
                                                              condition.  Access  issues  will  cause  the
                                                              repairs  to  be  ongoing  through  Thursday  if
                                                              no  additional  damage  is  discovered  in  this
                                                              area.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     Due  to  access
                                                              issues  for  the  concrete  trucks  caused  by
                                                              mud,  the  final  wall  pour  will  occur  on  2/9.

                                                              2)    Box  Culvert:     The  contractor continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
Rebar  work  on  box  culvert  walls  is  ongoing.

                                                              3)    Pipe:     Backfilling  of  HOBAS  pipe  will
                                                            continue  through  this  week.  Backfill
                                                            consists  of  CLSM  concrete.

       Cell  6  Leachate  Riser  Restoration:

                                                            1 )    
                                                                 Today  the  contractor  spread
                                                            additional  wet  weather road  base
                                                            material  in  this  area to  improve  access  to
                                                            the  leachate  risers.   We anticipate Cell
                                                            E6 riser connections to commence on
                                                            Wednesday.

                                                            2)    The  contractor was not able to
                                                            remove    mud  and  water  mixture  from  the
                                                            area  south  of  Cell  E6  today, as  a  result  of
                                                            the spreading  activities  noted  in  section  1.

       Sediment  Basin:

1)           The  contractor pumped 44,800  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii
808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                  Whelan, Joseph
To:                    Tyahla.Stephen@epamail.epa.gov
Subject:               RE: Daily Progress Report for February 8, 2011
Date:                  Wednesday, February 09, 2011 10:19:00 AM



Hi  Steve.
  
                                Yes,  the  area  being  referenced  is  on  the  southern  end  of  the  west  side,  where  there  was
only  minimal  pulling  of  the  liner.    We  do  inspect  it.    The  northern  area  has  not  been  further
investigated  because  the  contractor  is  working  directly  above  it,  posing  a   potential  safety  concern.
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Wednesday, February 09, 2011 8:06 AM
To: Whelan, Joseph
Cc: alec.wong@doh.hawaii.gov; Moxley.Bret@epamail.epa.gov; Baylor.Katherine@epamail.epa.gov;
Armann.Steve@epamail.epa.gov; Wall.Steve@epamail.epa.gov; Steven.chang@doh.hawaii.gov
Subject: Re: Daily Progress Report for February 8, 2011

Joe,

Thanks for keeping the daily reports coming.
In the future, you no longer need to include Kathy Baylor on your cc: list.

I do have one clarifying question regarding the Cell 6 assessment work:

You say below that "The  repair  work  seems  to  be  limited  to  restoring  the  geotextile  to  its
originally  constructed  condition." In this statement, by "geotextile" are you referring to the 16 oz/sy
cushion geotextile that lies immediately beneath the Operations Layer? If yes, I'm a bit surprised since
the photos of damage included your 27 Jan work plan seem a bit more severe; at a minimum, there
seems to be buckling along most of the west side length.     However, I recognize it's difficult to tell
which photos are form the northern vs. southern portions of that western edge.
In areas where damage does appear to be limited to the cushion geotextile, as reassurance, please in
subsequent daily reports, ensure us that the systematic inspection of the underlying 60-mil HDPE in
such areas, and as needed, underlying GCL and 40-mil HDPE geomembrane will be accomplished in
accordance with the provided work plan.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:    "Whelan, Joseph" <JWhelan1@wm.com>
To:      Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
         Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
         Wall/R9/USEPA/US@EPA, Katherine Baylor/R9/USEPA/US@EPA, <stuart.yamada@doh.hawaii.gov>,
         <Steven.chang@doh.hawaii.gov>, <alec.wong@doh.hawaii.gov>
Date:    02/08/2011 07:16 PM
Subject: Daily Progress Report for February 8, 2011




Greetings  all.

    Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

          Cell  6  assessment:

1)    The  south  portion  of the west  side  assessment of  cell  E6  is  ongoing.   The  operations
layer  of  protective  stone  located  above  the  anchor  trench  was  removed  to  allow  the  liner
material  to  be  further  investigated. Assessment  of  damage  in  southern  area  was  made  on
Saturday  2/6.  Areas  to  be  repaired  have  been  identified.  Repair  work  was  able  to
commence  on  the  southern  portion  of  the  E6  liner  slope  beginning  today.  The  repair  work
seems  to  be  limited  to  restoring  the  geotextile  to  its  originally  constructed  condition.
Access  issues  will  cause  the  repairs  to  be  ongoing  through  Thursday  if  no  additional
damage  is  discovered  in  this  area.    

          Western  Storm  water  Diversion  Project  (to  render  functional):

1)  
   Diversion  Structure:     Due  to  access  issues  for  the  concrete  trucks  caused  by  mud,  the
final  wall  pour  will  occur  on  2/9.

2)    Box  Culvert:     The  contractor continued  working  on  forming  the  transition  structure
from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.

  3)    Pipe:     Backfilling  of  HOBAS  pipe  will  continue  through  this  week.  Backfill  consists  of
CLSM  concrete.

          Cell  6  Leachate  Riser  Restoration:

1 )       Today  the  contractor  spread  additional  wet  weather road  base  material  in  this  area
to  improve  access  to  the  leachate  risers.   We anticipate Cell E6 riser connections to
commence on Wednesday.

2)    The  contractor was not able to remove    mud  and  water  mixture  from  the  area  south  of
Cell  E6  today, as  a  result  of  the spreading  activities  noted  in  section  1.

      Sediment  Basin:

1)           The  contractor pumped 44,800  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-668-2985, ext. 15 Office

808-668-1366 Fax

808-479-4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.




Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
FOR IMMEDIATE RELEASE (DRAFT)
Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com


      WASTE MANAGEMENT OF HAWAII PROVIDES UPDATE
           First Phase Complete, New Storm Water Diversion Channel Nears Completion

HONOLULU – Feb. 8, 2011 – Waste Management of Hawaii (WM) today provided an update on the
progress of work to repair damage to the Waimanalo Gulch Sanitary Landfill resulting from recent
severe rainstorms and ongoing efforts with the City and County of Honolulu to fully restore landfill
services to Oahu.

While the landfill remains closed to the public, it continues to accept city deliveries of treated
wastewater sludge and H-POWER ash residue, along with limited amounts of residential and bulky
waste that are required to be mixed in for disposal.

WM has completed the first of the three phases of work required before the landfill can be fully
reopened. This first phase consisted of repairs to the eastern side of cell E6, damaged in the Jan. 13
storm. These repairs allowed for the partial reopening of the landfill on Jan. 28.

The second and third phases consist of an ongoing assessment of the landfill liner on the west side of
cell E6. Throughout each of the severe rainstorms of December and January, the liner remained in
place; however, in the severest storm on Jan. 13, the edge of the liner that meets the side of the gulch
wall was damaged by falling rock. The assessment will determine what repairs are needed before full
use of the cell is restored.

The new storm water diversion channel, already in progress at the time of the storms, is projected to be
effectively complete on Feb. 15. WM has double shifts in place to facilitate the expeditious
completion of the diversion channel.

“While the new storm water diversion channel is not yet effectively complete, we are pleased to report
that the channel redirected an amount of rain water around the landfill on Sunday, as designed,” said
Joe Whelan, general manager of the landfill.

Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent
agreement with the U.S. Environmental Protection Agency, which served to memorialize and
document much of the work that was already being implemented by WM. The document was
symbolic of the EPA’s approval of WM and the City and County of Honolulu’s plan to address post-


                                                 (more)
Waste Management of Hawaii Provides Update
Page 2 of 2


storm events and landfill repairs. WM is also filing daily progress reports to the EPA and state
Department of Health.

Although beaches were declared on Jan. 25 to be safe for swimming, WM continues to encourage
those who find debris appearing to be from the landfill to report it by calling (808) 668-2985.

Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City
and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility
is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by
local, state and federal government agencies. The facility's staff includes 31 full-time employees, many
of whom are active in the local community. In addition to its community contributions and significant
volunteer efforts, Waste Management provides a benefit to the local economy of more than $2.9
million annually. To learn more about Waste Management’s commitment to the beautification of the
islands, visit www.keepinghawaiiclean.com

                                                 ###
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 9, 2011
Date:             Wednesday, February 09, 2011 5:25:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  assessment:

                                                              1)    The  south  portion  of the west  side
                                                              assessment of  cell  E6  is  ongoing.   The
                                                              operations  layer  of  protective  stone
                                                              located  above  the  anchor  trench  was
                                                              removed  to  allow  the  liner  material  to  be
                                                              further  investigated.   Areas  to  be  repaired
                                                              have  been  identified. Repair  work
                                                              continued  on  the  southern  portion  of  the
                                                              E6  liner  slope  today,  and  should  be
                                                              completed  by  Thursday  or  Friday.    No
                                                              additional  damage was discovered  in  this
                                                              area  today.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     The  final  wall
                                                              section of  the  diversion  structure  was
                                                              poured  today.  

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.

                                                                3)    Pipe:     Backfilling  of  HOBAS  pipe  will
                                                              continue  through  this  week.  Backfill
                                                              consists  of  CLSM  concrete.
Cell  6  Leachate  Riser  Restoration:

                                                            1 )      Today  the  contractor
                                                                                        was  able  to
                                                            resume  excavation around  the  leachate
                                                            risers.   We anticipate Cell E6 riser
                                                            connections to commence on Thursday
                                                            or Friday. This work was delayed due
                                                            to the muddy access conditions as a
                                                            result of the Sunday rain event.

       Sediment  Basin:

1)           The  contractor pumped 52,277  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                   Whelan, Joseph
To:                     Tyahla.Stephen@epamail.epa.gov
Subject:                RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011
Date:                   Thursday, February 10, 2011 1:59:00 PM



Hi  Steve.
  
                                I  am  requesting  the  delay  in  submitting  the  revised  SWPCP    per  condition  #5.
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, February 10, 2011 1:03 PM
To: Whelan, Joseph
Subject: RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011

Joe,

That's a shame, my condolences to him and his family.

I'm fine with the ten-day extension, but need clarification on the precise deliverable your referring to.
Are you referring to resubmission of the "revised stromwater contingency plan" that was required as
Condition #4 of our 28 January re-opening approval letter, or the revised "SWPCP" per Condition #5 of
that same letter? The SWPCP deadline is 15 days after getting the diversion structure functional ( by
15 Feb, as you know), so 2 March.

Thanks.

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:          "Whelan, Joseph" <JWhelan1@wm.com>
To:            Stephen Tyahla/R9/USEPA/US@EPA
Date:          02/10/2011 02:42 PM
Subject:       RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011
Thanks  Steve.
  
                                We  will  begin  working  on  the  requested  changes  right  away.    On  another  matter,  the  primary
contributor  with  GEI  Consultants,    who  is  providing  our  modified  storm  water  plan  update,  has  experienced  a
death  in  his  immediate  family,  and  will  be  out  of  pocket  for  a  short  period.    We  would  very  much  appreciate  your
granting  a  ten  day  extension  to  submit  this  revised  plan.    We  still  anticipate  having  the  storm  water  diversion
channel  functionally  complete  by  February  15 th ,  as  stated  in  the  AOC.    This  request  for  delay  would  only  affect
the  submission  due  date  for  the  revised  storm  water  plan.    Thank  you  for  your  consideration  of  this  request.
  
                                Best  regards,
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, February 10, 2011 11:28 AM
To: Whelan, Joseph
Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov;
alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov;
Blake.Ellen@epamail.epa.gov; Wampler.David@epamail.epa.gov
Subject: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011

Joe,

EPA has completed it's review of the five deliverables you submitted on 1 February and one of the two
deliverables you provided on 4 February in accordance with our 25 January 2011 Administrative Order
on Consent ("AOC") concerning the Waimanalo Gulch Sanitary Landfill ("WGSL"). We also completed
our review of the “Revised Storm Water Management Update & Contingency Plan” you submitted on 1
February 2011 per Condition # 4 of EPA’s 28 January 2011 e-mail that conditionally approved re-
opening of Cell E6.

Our detailed comments are provided in the attached table. Revised work plans or items requiring
revision are to be submitted to EPA within 15 days of your receipt of these comments (therefore, by
Friday, 25 February 2011).

Here is a summary of the results of our review:

[1] “Description of collection & treatment associated with liquid located behind the temporary berm”
(submitted per AOC paragraph 19.d.)-Acceptable with incorporation of the provided comments;
revision and resubmission required.

[2] “Work plan for managing potential Cell E6 hydraulic head” (Geosyntec Consultants’ letter of January
31, 2011; submitted per AOC paragraph 19.e.)-Approved, resubmission is not required;
concurrence on due date (March 7, 2011) is required.

[3] “Work plan for restoration of sedimentation basin” (GEI Consultants’ letter of January 31, 2011;
submitted per AOC paragraph 19.h.)-Acceptable with incorporation of the provided comments;
revision and resubmission required.

[4] “Work plan for beach assessment & material recovery effort” (submitted per AOC paragraph
19.i.)-Acceptable with incorporation of the provided comments; revision and resubmission
required.
[5] “Revised Storm Water Management Update & Contingency Plan” (submitted per Condition 4) of
EPA’s 28 January 2011 e-mail that conditionally approved re-opening of Cell E6)-Acceptable with
incorporation of the provided comments; revision and resubmission required.

[6] “Facility Health & Safety Plan” (submitted per AOC paragraph 21.)-Plan is accepted;
resubmission is not required.

[7] "Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter
of January 27, 2011); (submitted per AOC paragraph 19.f.)-Plan is accepted; resubmission is not
required, there are no comments on attached table for this workplan. However, concurrence by
WMH on a deadline for completing the repair work, including completion of the CQA Report, is
necessary. Based on the schedule provided and allowing 14 days for completion of the CQA
report, EPA proposes a due date of 25 April 2011.

EPA is in the process of retaining outside technical support to review the "Waimanalo Gulch Landfill
Slope Stability Analysis and Work Plan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter
of February 2, 2011; submitted by WMH on 4 February per AOC paragraph 19.a.). We will respond to
that submission as soon as practicable.

Please don't hesitate to contact me if you have any questions on the above or attached comments.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
From:                 Whelan, Joseph
To:                   Tyahla.Stephen@epamail.epa.gov
Subject:              RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011
Date:                 Thursday, February 10, 2011 12:42:00 PM



Thanks  Steve.
  
                                We  will  begin  working  on  the  requested  changes  right  away.    On  another  matter,  the
primary  contributor  with  GEI  Consultants,    who  is  providing  our  modified  storm  water  plan  update,
has  experienced  a   death  in  his  immediate  family,  and  will  be  out  of  pocket  for  a   short  period.    We
would  very  much  appreciate  your  granting  a   ten  day  extension  to  submit  this  revised  plan.    We  still
anticipate  having  the  storm  water  diversion  channel  functionally  complete  by  February  15 th ,  as
stated  in  the  AOC.    This  request  for  delay  would  only  affect  the  submission  due  date  for  the  revised
storm  water  plan.    Thank  you  for  your  consideration  of  this  request.
  
                                Best  regards,
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, February 10, 2011 11:28 AM
To: Whelan, Joseph
Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov;
alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov;
Blake.Ellen@epamail.epa.gov; Wampler.David@epamail.epa.gov
Subject: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011

Joe,

EPA has completed it's review of the five deliverables you submitted on 1 February and one of the two
deliverables you provided on 4 February in accordance with our 25 January 2011 Administrative Order
on Consent ("AOC") concerning the Waimanalo Gulch Sanitary Landfill ("WGSL"). We also completed
our review of the “Revised Storm Water Management Update & Contingency Plan” you submitted on 1
February 2011 per Condition # 4 of EPA’s 28 January 2011 e-mail that conditionally approved re-
opening of Cell E6.

Our detailed comments are provided in the attached table. Revised work plans or items requiring
revision are to be submitted to EPA within 15 days of your receipt of these comments (therefore, by
Friday, 25 February 2011).

Here is a summary of the results of our review:

[1] “Description of collection & treatment associated with liquid located behind the temporary berm”
(submitted per AOC paragraph 19.d.)-Acceptable with incorporation of the provided comments;
revision and resubmission required.

[2] “Work plan for managing potential Cell E6 hydraulic head” (Geosyntec Consultants’ letter of January
31, 2011; submitted per AOC paragraph 19.e.)-Approved, resubmission is not required;
concurrence on due date (March 7, 2011) is required.
[3] “Work plan for restoration of sedimentation basin” (GEI Consultants’ letter of January 31, 2011;
submitted per AOC paragraph 19.h.)-Acceptable with incorporation of the provided comments;
revision and resubmission required.

[4] “Work plan for beach assessment & material recovery effort” (submitted per AOC paragraph
19.i.)-Acceptable with incorporation of the provided comments; revision and resubmission
required.

[5] “Revised Storm Water Management Update & Contingency Plan” (submitted per Condition 4) of
EPA’s 28 January 2011 e-mail that conditionally approved re-opening of Cell E6)-Acceptable with
incorporation of the provided comments; revision and resubmission required.

[6] “Facility Health & Safety Plan” (submitted per AOC paragraph 21.)-Plan is accepted;
resubmission is not required.

[7] "Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter
of January 27, 2011); (submitted per AOC paragraph 19.f.)-Plan is accepted; resubmission is not
required, there are no comments on attached table for this workplan. However, concurrence by
WMH on a deadline for completing the repair work, including completion of the CQA Report, is
necessary. Based on the schedule provided and allowing 14 days for completion of the CQA
report, EPA proposes a due date of 25 April 2011.

EPA is in the process of retaining outside technical support to review the "Waimanalo Gulch Landfill
Slope Stability Analysis and Work Plan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter
of February 2, 2011; submitted by WMH on 4 February per AOC paragraph 19.a.). We will respond to
that submission as soon as practicable.

Please don't hesitate to contact me if you have any questions on the above or attached comments.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 10, 2011
Date:             Thursday, February 10, 2011 3:45:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6 Assessment:

                                                              1)   Repair  work continued  on  the
                                                              southwestern  portion  of  the  E6  liner  slope,
                                                              and  should  be  completed  by  Friday.   The
                                                              protective  geomembrane is  being  placed
                                                              over  the  liner  today.   No  additional
                                                              damage was discovered  in  this  area.   Once
                                                              completed, select  stone  will  be  placed
                                                              against  the  geomembrane.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured on  Wednesday.   These  forms  will
                                                              be  removed  once  the  curing  process  is
                                                              complete.

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.

                                                                3)    Pipe:     Backfilling  of  HOBAS  pipe  will
                                                              continue  through  this  week.  Backfill
                                                              consists  of  CLSM  concrete  followed  by
                                                              select  stone.

        Cell  6  Leachate  Riser  Restoration:
The  contractor continued  excavation  around  the  leachate  risers  today.   We
1)          
anticipate Cell E6 riser connections to commence on Friday. This work was delayed
due to the muddy access conditions as a result of the Sunday rain event.

     The contractor pumped 19,350 gallons of mud/water from the area around the
2)          
risers today, and placed in on site frac tanks for separation purposes. 16,500
gallons of water was pumped from these frac tanks and transported to the waste
water treatment plant.

               Sediment  Basin:

1)           The  contractor pumped 41,249  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 11, 2011
Date:             Friday, February 11, 2011 5:06:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

                                                              1)   Repairs  were  made  to  the
                                                              southwestern  portion  of  the  E6  liner
                                                              system  today.  The  repairs  consisted
                                                              primarily  of  removing  2  horizontal  wrinkles
                                                              approximately  80  feet  long  that  had
                                                              formed  in  the  upper  layer  of  60-­‐mil  HDPE
                                                              geomembrane  near  the  top  of  slope.  The
                                                              wrinkles  were  repaired  by  cutting  along  the
                                                              wrinkle,  removing  the  slack,  and  extrusion
                                                              welding  the  cut  area.  The  underlying  GCL
                                                              layer  was  inspected  in  this  area  and  no
                                                              damage  or  significant  hydration  was
                                                              observed.   After  repairs  were  tested  by
                                                              AEG  and  observed  by  AECOM,  the
                                                              geomembrane  was  covered  with  a  16  oz/sy
                                                              geotextile  protective  layer.  Inspection  and
                                                              repair  of  the  E6 side  slope  just  north  of
                                                              this  area  will  be  initiated  tomorrow  once
                                                              the  area  has  had  a  chance  to  dry  out  from
                                                              last  night’s  rain.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured  on  Wednesday.    These  forms  will
                                                              be  removed  once  the  curing  process  is
complete.

                                                            2)    Box  Culvert:     The  contractor  continued
                                                            working  on  forming  the  transition  structure
                                                            from  box  culvert  invert  to  pipe  invert.
                                                            Rebar  work  on  box  culvert  walls  is  ongoing.

                                                              3)    Pipe:     Backfilling  of  HOBAS  pipe  will
                                                            continue  through  this  week.  Backfill
                                                            consists  of  CLSM  concrete  followed  by
                                                            select  stone.

               Cell  6  Leachate  Riser  Restoration:

     The  contractor was  not  able  to continue  excavation  around  the  leachate  risers
1)          
today,  as  a  result  of  local  rain  last  night  which  caused  additional  rain  water  to
accumulate  in  this  area. This  water  is  being  pumped  out  today.   We anticipate Cell E6
riser connections to commence as soon as the water is removed and the top of the
risers are exposed.

     The contractor pumped 9,675 gallons of mud/water from the area around the
2)          
risers today, and placed in on site frac tanks for separation purposes.

               Sediment  Basin:

1)           The  contractor pumped 19,350  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager
Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 14, 2011
Date:             Monday, February 14, 2011 5:19:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.   A limited rain event affected the facility Sunday evening.
There was no damage, however activities today were curtailed due to muddy
conditions.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.     Mud was discovered  between  the  geomembrane  layers  in  this
area,  which hydrated  the  GCL  locally.  The  impacted  area  appears  to  extend  20  feet  up
from  the  toe  of the existing  trash  slope.   For  the  rest  of  today,  AEG  will  be  water  proofing
the  area  in  case  it  rains  tonight.  Tomorrow  they  will  begin  replacing  the  GCL  and  covering
with  60-­‐mil  HDPE  as  they  go.  This  work  should  take  approximately  2  to  3  days  to  complete.

2)    The contractor pumped 32,818 gallons of storm water from Cell E6 over the
weekend, which was transported to the WWTP for treatment and disposal. These
activities are ongoing.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured  on  Wednesday.    These  forms  will
                                                              be  removed  once  the  curing  process  is
                                                              complete.

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.

                                                                3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                              channel  is  now  complete.
Cell  6  Leachate  Riser  Restoration:

     The  contractor  was  not  able  to  continue  excavation  around  the  leachate  risers
1)          
today,  as  a  result  of  local  rain  last  night  which  caused  additional  rain  water  to
accumulate  in  this  area.    This  water  is  being  pumped  out  today.   We anticipate Cell E6
riser connections to commence as soon as the water is removed and the top of the
risers are exposed.

     The contractor pumped 27,000 gallons of mud/water from the area around the
2)          
risers over the weekend, and placed in on site frac tanks for separation purposes.

               Sediment  Basin:

1)           The  contractor pumped 32,700  gallons of  storm  water from  the  sedimentation  basin
over  the  weekend, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These
activities are ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed. The  contractor  will  attempt  to  drill  PZ1  on  Tuesday,  assuming  there  are  no
weather  related  access  issues.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:             Whelan, Joseph
To:               "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov";
                  "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov"
Subject:          WGSL Diversion Channel Functionally Complete
Date:             Tuesday, February 15, 2011 4:14:00 PM
Attachments:      DSCF4895.jpg
                  DSCF4900.jpg
                  DSCF4892.jpg




Greetings  all.

      Please  be  advised  that  as  of  today, construction  of  a  functional  storm  water  diversion
structure located on  the west  side  above  Cell  #E6  is  complete,  per  Section  19.6,  of  the
Administrative  Order  on  Consent  (AOC)  signed  on  January  25,  2010.   I  have  included
supportive  pictures  for  your  review.   Pictures  1  &  2  depict  the  diversion  wall  showing  the
water  pathway  into  the  open  channel,  picture  3  depicts  the bottom  of  the  diversion
channel  showing  the  tie  in  to  the  in  place  Hobas  pipe.   Please  contact  me  if  you  have  any
questions.



        Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 15th
Date:             Tuesday, February 15, 2011 5:16:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.     Mud was  discovered  between  the  geomembrane  layers  in  this
area,  which hydrated  the  GCL  locally. The  contractor  began  replacing  the affected GCL
today, and  covering  with  60-­‐mil  HDPE  as  they  go.  This  work  should  take  approximately  2  to
3  days  to  complete.

2)   The contractor pumped 47,759 gallons of storm water from Cell E6 today,
which was transported to the WWTP for treatment and disposal. These activities are
ongoing.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured last  Wednesday.    These  forms are
                                                              now  being  removed.

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.

                                                                3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                              channel  is  now  complete.

                                                              4)    The  diversion  structure  is  now
                                                              functionally  complete  per  the  terms  of
                                                              Section  19.b.  of  the  AOC.
Cell  6  Leachate  Riser  Restoration:

     The  contractor resumed  excavation  around  the  leachate  risers  today.   We
1)          
anticipate Cell E6 riser connections to commence as soon as the water is removed
and the top of the risers are exposed.

     The contractor pumped 44,000 gallons of mud/water from the area around the
2)          
risers today, and placed in on site frac tanks for separation purposes.

               Sediment  Basin:

1)           The  contractor pumped 17,318  gallons of  storm  water from  the  sedimentation  basin
today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are
ongoing.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor completed  installation  of  PZ1   today,  no  water  was encountered
during  the drilling process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
FOR IMMEDIATE RELEASE
Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com


                    STORM WATER DIVERSION CHANNEL
                      NOW FUNCTIONAL AT LANDFILL
HONOLULU – Feb. 15, 2011 – Waste Management of Hawaii (WM), which operates the
Waimanalo Gulch Sanitary Landfill on behalf of the City and County of Honolulu, today announced
the functional completion of a new $15 million storm water diversion channel that can now direct
potential floodwaters around the active area of the landfill. The completion of this portion of the storm
water diversion channel is an important milestone and meets the schedule and requirements of WM’s
agreement with the U.S. EPA.

The primary portion of the diversion channel system, the Western Drainage Project, is designed for a
peak flow of 1,751 cubic feet per second within a 24-hour period. Over the next several months, WM
will complete the lower portion of the system, including several thousand more feet of large diameter
pipe and a separate “stilling basin” to contain excess storm water originating from above the landfill.

The storm water conveyance system consists of a diversion wall that directs storm water into a 10 by
10 foot box culvert, followed by a series of large diameter centrifugally cast fiberglass-reinforced
polymer pipe ranging from 78 to 102 inches in diameter.

The channel’s construction was already in progress at the time of the Jan. 13 storm and two earlier,
unusually heavy rainstorms occurring in December. The storm water diversion channel project began
in November 2009. WM identified the need for the diversion channel years ago and proceeded with
construction as soon as the necessary approvals were received. Double shifts where put in place before
the winter season to facilitate the expeditious completion of the diversion channel.

Other Ongoing Work Continues
In addition to the diversion channel, evaluation and repairs continue to be made to the southwestern
portion of the E6 liner system, with progress moving north. Most recent repairs primarily consisted of
the removal of two approximately 80-foot “wrinkles” that had formed in the liner system’s upper layer
near the top of the cell slope.

Further inspection and repair remain and are ongoing, despite interruptions caused by this week’s rain
and resulting rainwater accumulation. Any rainwater removed from the cell or sedimentation basin is
being sent to the wastewater treatment plant for treatment and disposal.



                                                 (more)
STORM WATER DIVERSION CHANNEL NOW FUNCTIONAL AT LANDFILL
Page 2 of 2


The landfill remains closed to the public but continues to accept city deliveries of treated wastewater
sludge and H-POWER ash and residue, along with limited amounts of residential and bulky waste that
are required to be mixed in for disposal.

Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent
agreement with the EPA, which served to memorialize and document the work that was already being
implemented by WM.

                                                 ###

Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com
MEDIA ADVISORY

                   Landfill’s Diversion Channel Functional Tomorrow
                         (B-roll, photos to be provided by 3 p.m.)
What:         Functional Completion of New Storm Water Diversion Channel

When:         Tuesday, Feb. 15, 2011
              B-roll and photos to be provided by 3 p.m.

Where:        Waimanalo Gulch Sanitary Landfill

Why:          The new $15 million storm water diversion channel is designed to direct floodwaters,
              just like those that deluged the landfill over the last two months — most drastically on
              Jan. 13 — around the main area of the landfill instead of through it.

Waste Management of Hawaii (WM), which operates the Waimanalo Gulch Sanitary Landfill for the
City and County of Honolulu, anticipates the functional completion of the landfill’s storm water
diversion channel tomorrow. This is a major milestone in WM’s consent agreement with the U.S.
EPA.

The channel’s construction was already in progress at the time of the storms. WM identified the need
for the diversion channel years ago and proceeded as soon as the necessary approvals were received.
Double shifts where put in place to facilitate the expeditious completion of the diversion channel.

Last week, WM reported that the not-yet-completed diversion channel effectively redirected a portion
of rainwater from a storm on Super Bowl Sunday.

Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent
agreement with the EPA, which served to memorialize and document the work that was already being
implemented by WM.

                                                ###

Media Contact:
Keith DeMello
McNeil Wilson Communications
(808) 542-5343
keith.demello@mwc-anthology.com
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 16, 2011
Date:             Wednesday, February 16, 2011 5:06:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.     Mud was  discovered  between  the  geomembrane  layers  in  this
area,  which hydrated  the  GCL  locally.   The  contractor  began  replacing  the affected GCL
and  covering it with  60-­‐mil  HDPE on  Tuesday.  This  work is  ongoing  and should  take
approximately  2  to  3  days  to  complete.

2)   The contractor pumped 18,100 gallons of storm water from Cell E6 today,
which was transported to the WWTP for treatment and disposal. These activities are
ongoing.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured  last  Wednesday.    These  forms  are
                                                              now  being  removed.

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                  The  contractor  began  pouring the box
                                                              culvert walls  today.

                                                                3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                              channel  is  now  complete.

                                                              4)    The  diversion  structure  is  now
                                                              functionally  complete  per  the  terms  of
Section  19.b.  of  the  AOC.

               Cell  6  Leachate  Riser  Restoration:

     The  contractor continued  excavation  around  the  leachate  risers  today,  and  was
1)          
successful  in  exposing  the entry  flanges.   We are in the process of re-connecting the
electricity and plumbing at this time.

     The contractor pumped 33,200 gallons of water, which was transported to the
2)          
WWTP, and 27,700 gallons of mud/water from the area around the risers today, and
placed in on site frac tanks for separation purposes.

               Sediment  Basin:

1)           The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin
today  due  to  the  low  level  of  free standing water. We  have  begun  removing  silt/rock
material  from  the  northern  portion  of  the  sedimentation  basin.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1   on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                   Whelan, Joseph
To:                     Tyahla.Stephen@epamail.epa.gov
Subject:                FW: Daily Progress Report for February 16, 2011
Date:                   Friday, February 18, 2011 5:20:00 PM



Hi  Steve,
  
                                I  was  off  island  yesterday,  please  find  my  response  to  your  inquiry.    Have  a   great  weekend.
  
                                Best  regards,
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, February 17, 2011 7:00 AM
To: Whelan, Joseph
Subject: Re: Daily Progress Report for February 16, 2011

Joe,

Thanks for the report.

I have a couple of clarifying questions for you below, in red bold. Just making sure I understand.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:    "Whelan, Joseph" <JWhelan1@wm.com>
To:      Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
         Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
         Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
         "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
         <alec.wong@doh.hawaii.gov>
Date:    02/16/2011 07:06 PM
Subject: Daily Progress Report for February 16, 2011
Greetings  all.
      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
      Cell  6  Assessment:
1.      Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.    Mud  was  discovered  between  the  geomembrane  layers  in  this
area,  which  hydrated  the  GCL  locally.  The  contractor  began  replacing  the  affected  GCL  and
covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing  and  should  take
approximately  2  to  3  days  to  complete.
  
  
2.     The contractor pumped 18,100 gallons of storm water from Cell E6 today, which was
transported to the WWTP for treatment and disposal. Am I correct in thinking that this
18k gallons came from water accumulated on top of Cell E6, basically a separate pond,
if you will, from the pond that's immediately upstream of the large temporary earthen
berm? [Whelan, Joe] Yes. These activities are ongoing.
  
        Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last
Wednesday.    These  forms  are  now  being  removed.
2)    Box  Culvert:      The  contractor  continued  working  on  forming  the  transition  structure
from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.      The
contractor  began  pouring  the  box  culvert  walls  today.
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of
the  AOC.
        Cell  6  Leachate  Riser  Restoration:
1.        The  contractor  continued  excavation  around  the  leachate  risers  today,  and  was
successful  in  exposing  the  entry  flanges.    We are in the process of re-connecting the
electricity and plumbing at this time. Great news!!! [Whelan, Joe] This was made
operational today and we are pumping from this riser

2.     The contractor pumped 33,200 gallons of water, which was transported to the WWTP,
and 27,700 gallons of mud/water from the area around the risers today, and placed in on site
frac tanks for separation purposes. Am I correct in thinking that this water was pumped
from the pond immediately upstream of the large temporary earthen berm? Thus, the
E6 pond where the 18.1K gals was pumped is a separate pond further upstream
(basically like when I was there). Actually, a current photo of the whole area from
above would be helpful. [Whelan, Joe] yes, This is what was previously referred to as the
“south pond”.
      Sediment  Basin:
1.     The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin
today  due  to  the  low  level  of  free  standing  water.  We  have  begun  removing  silt/rock
material  from  the  northern  portion  of  the  sedimentation  basin.      How  is  the  silt/rock  being
removed  and  where  is  it  going  (for  dewatering  I  suppose)? [Whelan, Joe] Only the fairly
dry material is being removed by an excavator and placed into cell 6. This process allows the
remaining silt and water mixture to further separate, the water to be pumped out and the silt
to further dry.
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know if  you  have  any  questions.      

Best  regards,
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
  


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
<alec.wong@doh.hawaii.gov>
     Date:    02/16/2011 07:06 PM
     Subject: Daily Progress Report for February 16, 2011




Greetings  all.
      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
      Cell  6  Assessment:
1.      Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.    Mud  was  discovered  between  the  geomembrane  layers  in  this
area,  which  hydrated  the  GCL  locally.  The  contractor  began  replacing  the  affected  GCL  and
covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing  and  should  take
approximately  2  to  3  days  to  complete.
  
  
2.     The contractor pumped 18,100 gallons of storm water from Cell E6 today, which was
transported to the WWTP for treatment and disposal. Am I correct in thinking that this
18k gallons came from water accumulated on top of Cell E6, basically a separate pond,
if you will, from the pond that's immediately upstream of the large temporary earthen
berm? [Whelan, Joe] Yes. These activities are ongoing.
  
        Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last
Wednesday.    These  forms  are  now  being  removed.
2)    Box  Culvert:      The  contractor  continued  working  on  forming  the  transition  structure
from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.      The
contractor  began  pouring  the  box  culvert  walls  today.
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of
the  AOC.
        Cell  6  Leachate  Riser  Restoration:
1.        The  contractor  continued  excavation  around  the  leachate  risers  today,  and  was
successful  in  exposing  the  entry  flanges.    We are in the process of re-connecting the
electricity and plumbing at this time. Great news!!! [Whelan, Joe] This was made
operational today and we are pumping from this riser

2.     The contractor pumped 33,200 gallons of water, which was transported to the WWTP,
and 27,700 gallons of mud/water from the area around the risers today, and placed in on site
frac tanks for separation purposes. Am I correct in thinking that this water was pumped
from the pond immediately upstream of the large temporary earthen berm? Thus, the
E6 pond where the 18.1K gals was pumped is a separate pond further upstream
(basically like when I was there). Actually, a current photo of the whole area from
above would be helpful. [Whelan, Joe] yes, This is what was previously referred to as the
“south pond”.
                Sediment  Basin:
1.               The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin
today  due  to  the  low  level  of  free  standing  water.  We  have  begun  removing  silt/rock
material  from  the  northern  portion  of  the  sedimentation  basin.      How  is  the  silt/rock  being
removed  and  where  is  it  going  (for  dewatering  I  suppose)? [Whelan, Joe] Only the fairly
dry material is being removed by an excavator and placed into cell 6. This process allows the
remaining silt and water mixture to further separate, the water to be pumped out and the silt
to further dry.
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know if  you  have  any  questions.      

Best  regards,
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
  


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
From:                 Whelan, Joseph
To:                   Tyahla.Stephen@epamail.epa.gov
Subject:              RE: WGSL Diversion Channel Functionally Complete - EPA Concurrence
Date:                 Wednesday, February 16, 2011 8:49:00 AM



Thanks  Steve.    Will  do.
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Wednesday, February 16, 2011 8:37 AM
To: Whelan, Joseph
Cc: 'alec.wong@doh.hawaii.gov'; Moxley.Bret@epamail.epa.gov; 'Steven.chang@doh.hawaii.gov';
'stuart.yamada@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov;
Wampler.David@epamail.epa.gov
Subject: WGSL Diversion Channel Functionally Complete - EPA Concurrence

Joe,

EPA concurs that, as evidenced below, WMH has completed construction of a functional storm water
diversion structure on the west side above cell #E6 as required by paragraph 19.b. of our AOC of January
25, 2011.

While your progress on the Western Surface Water Drainage Project has met this AOC-required milestone,
request that you please continue to provide status updates of the remaining construction work on this
project in your daily progress reports.

Also, as I mentioned on the phone yesterday, I will be making a trip to Oahu the week of 7 March to visit a
remedial site in the Campbell Industrial Park, and would like to spend either a morning or afternoon
inspecting the work at your facility. As my schedule now stands, my visit to the landfill will most likely be
on Thursday, 10 March, but I will keep you posted as the time comes nearer so we can coordinate.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential information
solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an
intended recipient, please delete this email and its attachments immediately. The unauthorized use,
dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]




From:      "Whelan, Joseph" <JWhelan1@wm.com>
To:        Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'"
           <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>,
           "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov>
Date:      02/15/2011 06:14 PM
Subject: WGSL Diversion Channel Functionally Complete
Greetings  all.
  
                Please  be  advised  that  as  of  today,  construction  of  a  functional  storm  water  diversion  structure  located  on  the
west  side  above  Cell  #E6  is  complete,  per  Section  19.6,  of  the  Administrative  Order  on  Consent  (AOC)  signed  on
January  25,  2010.    I  have  included  supportive  pictures  for  your  review.    Pictures  1  &  2  depict  the  diversion  wall
showing  the  water  pathway  into  the  open  channel,  picture  3  depicts  the  bottom  of  the  diversion  channel  showing  the
tie  in  to  the  in  place  Hobas  pipe.    Please  contact  me  if  you  have  any  questions.
  
  
                Best  regards,                                      
             
 
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
 


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
From:                  Whelan, Joseph
 To:                    Tyahla.Stephen@epamail.epa.gov
 Subject:               FW: Daily Progress Report for February 16, 2011
 Date:                  Friday, February 18, 2011 5:21:00 PM



  
  
From: Whelan, Joseph
Sent: Friday, February 18, 2011 5:20 PM
To: Tyahla.Stephen@epamail.epa.gov
Subject: FW: Daily Progress Report for February 16, 2011

Hi  Steve,
  
                                I  was  off  island  yesterday,  please  find  my  response  to  your  inquiry.    Have  a   great  weekend.
  
                                Best  regards,
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, February 17, 2011 7:00 AM
To: Whelan, Joseph
Subject: Re: Daily Progress Report for February 16, 2011

Joe,

Thanks for the report.

I have a couple of clarifying questions for you below, in red bold. Just making sure I understand.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]

 From:      "Whelan, Joseph" <JWhelan1@wm.com>
 To:        Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
            Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
            Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
            "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
 
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Daily Progress Report for February 17th
Date:             Thursday, February 17, 2011 3:39:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6
liner  system  moving  north.      Mud  was  discovered  between  the  geomembrane  layers  in  this
area,  which  hydrated  the  GCL  locally.    The  contractor  began  replacing  the  affected  GCL  and
covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing ,  but  should  be  complete  on
Friday.

2)   Due to declining volumes, the contractor was not able to pump storm water
from Cell E6 today.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                              1)  
                                                                 Diversion  Structure:     The  final  wall
                                                              section  of  the  diversion  structure  was
                                                              poured  last  Wednesday.    These  forms  are
                                                              now  being  removed.

                                                              2)    Box  Culvert:     The  contractor  continued
                                                              working  on  forming  the  transition  structure
                                                              from  box  culvert  invert  to  pipe  invert.
                                                              Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                  The  contractor continued  pouring  the  box
                                                              culvert  walls  today.

                                                                3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                              channel  is  now  complete.

                                                              4)    The  diversion  structure  is  now
                                                              functionally  complete  per  the  terms  of
                                                              Section  19.b.  of  the  AOC.
Cell  6  Leachate  Riser  Restoration:

1)           The  contractor continued  excavation  around  the  leachate  risers on  Wednesday,
and  was  successful  in  exposing  the  entry  flanges.   We are in the process of re-
connecting the electricity and plumbing at this time.

     The contractor pumped 55,000 gallons of mud/water from the area around the
2)          
risers today, and placed in on site frac tanks for separation purposes.

               Sediment  Basin:

1)           The  contractor pumped  31,675  gallons    of  storm  water  from  the  sedimentation  basin
today.    We  have  begun  removing  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin,  and  placing  this  material  into  the lined  portion  of  Cell  E6.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                    Whelan, Joseph
To:                      "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                         "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                         "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                         "alec.wong@doh.hawaii.gov"
Subject:                 Daily Progress Report for February 18th
Date:                    Friday, February 18, 2011 5:18:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

               Cell  6  Assessment:

1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are
now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work.

               Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     1)  
                                                                        Diversion  Structure:     The  final  wall
                                                                     section  of  the  diversion  structure  was
                                                                     poured  last  Wednesday.    These  forms  are
                                                                     now  being  removed.

                                                                     2)    Box  Culvert:     The  contractor  continued
                                                                     working  on  forming  the  transition  structure
                                                                     from  box  culvert  invert  to  pipe  invert.
                                                                     Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                         The  contractor  continued  pouring  the  box
                                                                     culvert  walls  today.

                                                                       3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                                     channel  is  now  complete.

                                                                     4)    The  diversion  structure  is  now
                                                                     functionally  complete  per  the  terms  of
                                                                     Section  19.b.  of  the  AOC.

               Cell  6  Leachate  Riser  Restoration:

      The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
1)          
E6  leachate  riser  today and  initiated  the  pumping  process.  
56,700 gallons was pumped from the E6 riser today and placed into the on site
2)          
frac tanks.

               Sediment  Basin:

1)           The  contractor  pumped 57,718  gallons    of  storm  water  from  the  sedimentation  basin
today,  which  was  transported  to  the  local  waste  water  treatment  plant.    We  have  begun
removing  silt/rock  material  from  the  northern  portion  of  the  sedimentation  basin,  and
placing  this  material  into  the  lined  portion  of  Cell  E6.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                    Whelan, Joseph
To:                      "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                         "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                         "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                         "alec.wong@doh.hawaii.gov"
Subject:                 Daily Progress Report for February 21st
Date:                    Monday, February 21, 2011 2:47:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

               Cell  6  Assessment:

1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are
now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work.

               Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     1)  
                                                                        Diversion  Structure:     The  final  wall
                                                                     section  of  the  diversion  structure  was
                                                                     poured  last  Wednesday.    These  forms  are
                                                                     now  being  removed.

                                                                     2)    Box  Culvert:     The  contractor has
                                                                     completed  forming  the  transition  structure
                                                                     from  box  culvert  invert  to  pipe  invert. This
                                                                     is  scheduled  to  be  poured  this        week.  
                                                                     Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                       

                                                                       3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                                     channel  is  now  complete.

                                                                     4)    The  diversion  structure  is  now
                                                                     functionally  complete  per  the  terms  of
                                                                     Section  19.b.  of  the  AOC.

               Cell  6  Leachate  Riser  Restoration:

      The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
1)          
E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    
108,000 gallons was pumped from the E6 riser since Friday and placed into the
2)          
on site frac tanks.

               Sediment  Basin:

1)           We continue  to  remove  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                       Whelan, Joseph
To:                         Tyahla.Stephen@epamail.epa.gov
Subject:                    RE: Daily Progress Report for February 21st
Date:                       Tuesday, February 22, 2011 5:59:00 PM



Hi  Steve.
  
                                Please  see  my  responses  below.
  
                                Thanks.
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Tuesday, February 22, 2011 7:59 AM
To: Whelan, Joseph
Subject: Re: Daily Progress Report for February 21st

Joe,

A couple of question/comments in blue, below.
Generally, thinking ahead to the Final Report, one thing we'll want included in that report are quantities
and disposition of the various waste streams.

Thanks!

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:    "Whelan, Joseph" <JWhelan1@wm.com>
To:      Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
         Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
         Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
         "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
         <alec.wong@doh.hawaii.gov>
Date:    02/21/2011 04:48 PM
Subject: Daily Progress Report for February 21st
Greetings  all.
      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
      Cell  6  Assessment:
1.      The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system  are
now  complete.      Our  consultant  is  assembling  the  CQA  report  for  this  work.  
Please  provide  status  of  assessment  and  repair  work  for  the  northern  portion  of  the  west
side  E6  liner  as  it  progresses;  including  a  brief  "look-­‐ahead"  for  work  planned  in  the
upcoming  days  or  week. [Whelan, Joe] The contractor is in the process of removing the
overburden from the side slope area directly above the northwestern section of the Cell E6
liner. This over burden is the result of excavating the diversion channel in this area. Once
the overburden is removed, and all of it is relocated from above the liner, we can then begin
the liner repairs to this area. We expect removal process to take about an additional 25 days
to complete, at which time we will commence the liner repairs.
  
        Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last
Wednesday.    These  forms  are  now  being  removed.
2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box
culvert  invert  to  pipe  invert.  This  is  scheduled  to  be  poured  this          week.    Rebar  work  on
box  culvert  walls  is  ongoing.      
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of
the  AOC.
        Cell  6  Leachate  Riser  Restoration:
1.        The  contractor  completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.      

2.               108,000 gallons was pumped from the E6 riser since Friday and placed into the on site
frac tanks. 56.7k gals pumped on 18th and 108k gals on 21st. Please include in updates
quantities removed from Frac tanks and taken to WWTP. The Frac tanks are 20k gals
each, correct? I'm presuming that you're not holding a bunch of full Frac tanks on site.
[Whelan, Joe] Sorry, these are the volumes that were transported and disposed of at the
wwtp.
                Sediment  Basin:
1.               We  continue  to  remove  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know if  you  have  any  questions.      

Best  regards,
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
  


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
From:                     Whelan, Joseph
To:                       "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                          "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                          "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                          "alec.wong@doh.hawaii.gov"
Subject:                  Daily Progress Report for February 22, 2011
Date:                     Tuesday, February 22, 2011 5:57:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are
now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                      1)  
                                                                         Diversion  Structure:     The  final  wall
                                                                      section  of  the  diversion  structure  was
                                                                      poured  last  Wednesday.    These  forms have
                                                                      been  removed  except  for  the  tie  in  to  the
                                                                      open  box  culvert  wall.

                                                                      2)    Box  Culvert:     The  contractor  has
                                                                      completed  forming  the  transition  structure
                                                                      from  box  culvert  invert  to  pipe  invert.   This
                                                                      is  scheduled  to  be  poured  this          week.  
                                                                      Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                         Rains  today  resulted  in a  temporary  set
                                                                      back  to  this  effort.

                                                                        3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                                      channel  is  now  complete.

                                                                      4)    The  diversion  structure  is  now
                                                                      functionally  complete  per  the  terms  of
                                                                      Section  19.b.  of  the  AOC.

                Cell  6  Leachate  Riser  Restoration:

1)             The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    

     33,900 gallons was pumped from the E6 riser storage tank today and
2)          
transported to the waste water treatment plant.

               Sediment  Basin:

1)           We  continue  to  remove  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.  

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                    Whelan, Joseph
To:                      "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                         "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                         "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                         "alec.wong@doh.hawaii.gov"
Subject:                 Daily Progress Report for February 23, 2011
Date:                    Wednesday, February 23, 2011 5:07:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

               Cell  6  Assessment:

1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are
now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work.

               Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     1)  
                                                                        Diversion  Structure:     The  final  wall
                                                                     section  of  the  diversion  structure is  now  in
                                                                     place.  

                                                                     2)    Box  Culvert:     The  contractor  has
                                                                     completed  forming  the  transition  structure
                                                                     from  box  culvert  invert  to  pipe  invert.   This
                                                                     is  scheduled  to  be  poured next          week.  
                                                                     Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                         Rains again today  resulted  in  a  temporary
                                                                     set  back  to  these  efforts.

                                                                       3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                                     channel  is  now  complete.

                                                                     4)    The  diversion  structure  is  now
                                                                     functionally  complete  per  the  terms  of
                                                                     Section  19.b.  of  the  AOC.

               Cell  6  Leachate  Riser  Restoration:

      The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
1)          
E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    
There was no volume pumped from the E6 riser storage tank today due to a
2)          
localized rain event.

               Sediment  Basin:

1)           Rain  out  today  resulting  in  no  removal  of  silt/rock  material  from  the  northern  portion
of  the  sedimentation  basin.

2)           The contractor pumped 41,700 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report February 24, 2011
Date:              Thursday, February 24, 2011 4:55:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are
now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work.

2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert ties  into  the  Hobas  pipe.   Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   This
                                                               is  scheduled  to  be  poured  next          week.  
                                                               Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                  Afternoon  showers  again  today  resulted
                                                               in  a further  set  back  to  these  efforts.

                                                                 3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                               channel  is  now  complete.

                                                               4)    The  diversion  structure  is  functionally
complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

      The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
1)          
E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    

    There was no volume pumped from the E6 riser storage tank or the mud/water
2)          
separation tanks again today due to afternoon showers all week, which created truck
access issues.

               Sediment  Basin:

1)           Daily  showers  this  week  have  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The contractor pumped 54,900 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time
during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.   The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
encountered  during  the  drilling  process.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

  Waste Management's landfills provide over 17,000 acres of
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for February 25, 2011
Date:              Friday, February 25, 2011 4:51:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The QCA  report  documenting  the evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted February  25,  2011.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   This
                                                               is  scheduled  to  be  poured  next          week.  
                                                               Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                   Afternoon  showers received earlier  in  the
                                                               week  resulted  in  a temporary  set  back  to
                                                               these  efforts.

                                                                 3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                               channel  is  now  complete.
4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

       Cell  6  Leachate  Riser  Restoration:

1)           There was no volume pumped from the Cell E6 leachate riser storage tank or
the mud/water separation tanks again today due to afternoon showers all week,
which created truck access issues.

       Sediment  Basin:

1)           Daily  showers earlier this  week  have  prevented  removal  of  silt/rock  material  from
the  northern  portion  of  the  sedimentation  basin.  

2)           The contractor pumped 56,800 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations PZ-­‐1, PZ-­‐5  and  PZ-­‐6. No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.     The  documentation  report  was  submitted  on  February  25,  2011.  

       Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax
From:                        Whelan, Joseph
Sent:                        Friday, February 25, 2011 4:57 PM
To:                          'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov';
                             'stuart.yamada@doh.hawaii.gov'; 'Steven.chang@doh.hawaii.gov';
                             'alec.wong@doh.hawaii.gov'
Subject:                      AOC Response to EPA Comments on WGSL February 1, 2011 Submittals

Greetings all:

        EPA provided comments to several work plans required by the Administrative Order on Consent
(AOC) on February 10, 2011. Please find attached the revised work plans and reports that are due
today, February 25th. Our responses are included within the revised documents as requested.
Additionally, EPA requested a proposed due date for the submission of the report documenting
completion of the Cell E6 liner evaluation and repair. We have provided the parties with CQA reports
documenting repairs to both the northeast and southwestern portions of this cell. As noted within our
daily progress report of February 24, 2011, evaluation and repair to the liner within the northwestern
section of Cell E6 will be delayed pending removal of the soil/rock over burden produced by the storm
water diversion system construction. WMH proposes to provide this CQA report by May 15, 2011.
Please let me know if you have any questions.


        Best regards,




                                            DOCAOC         Collection and      Hydraulic Head Sedimentation Basin
                                        PONSE LETTER 2 25 Transport of Li...   Letter of Findi... Workplan r...




Beach Assessment WGSL Revised SW
 Workplan Revi... Contingency Pl...




Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                      Whelan, Joseph
Sent:                      Friday, February 25, 2011 2:55 PM
To:                        'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov';
                           'stuart.yamada@doh.hawaii.gov'; 'Steven.chang@doh.hawaii.gov';
                           'alec.wong@doh.hawaii.gov'
Subject:                   CQA Report for Liner Repairs to the Southwestern Section of Cell E6

Greetings all.

         Please find attached the CQA report for the recently completed evaluation and repair to the
liner located in the southwestern section of Cell E6. We would appreciate your timely review and
approval of this report. Approval to place waste in this area is necessary in order for the landfill to
reopen to the general public. Please contact me with any questions. Thank you.


        Best regards,


                                 Letter Report Cell        MSW Placement
                                   E6 West Slo...          Area_022111.pdf



Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile

Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for February 28, 2011
Date:              Monday, February 28, 2011 5:02:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted  February  25,  2011.    Approval  to  resume  operations  in
this  area  is  pending.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   This
                                                               is  scheduled  to  be  poured  next          week.  
                                                               Rebar  work  on  box  culvert  walls  is  ongoing.
                                                                 

                                                                 3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                               channel  is  now  complete.
4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

     105,300 gallons was pumped from the Cell E6 leachate riser storage tank since
1)          
Friday and transported to the waste water treatment plant.

     33,200 gallons of water was pumped from the south pond area since Friday and
2)          
transported to the local waste water treatment plant.

     30,772 gallons of mud/water was pumped from the south pond area since
3)          
Friday and placed within the onsite separation tanks.

               Sediment  Basin:

1)           Daily  showers  earlier  this  week  have  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The contractor pumped 8,700 gallons of storm water from the sedimentation
basin since Friday and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii
808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                    Whelan, Joseph
To:                      Tyahla.Stephen@epamail.epa.gov
Subject:                 RE: Daily Progress Report for February 28, 2011
Date:                    Tuesday, March 01, 2011 9:24:00 AM



Hi  Steve.
  
                                We  are  pouring  the  first  section  of  this  today.    Sorry  about  the  over  site.
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Tuesday, March 01, 2011 7:02 AM
To: Whelan, Joseph
Cc: 'alec.wong@doh.hawaii.gov'; Vaille.Rich@epamail.epa.gov; Armann.Steve@epamail.epa.gov;
Wall.Steve@epamail.epa.gov; 'Steven.chang@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov
Subject: Re: Daily Progress Report for February 28, 2011

Joe,

Thanks for the update.

One question: In your daily report for last Friday the 25th you said that concrete for the transition
structure from box culvert to Hobas pipe was being poured "next week" which is now this week. But
below you still refer to "next week." Confusing, I know. But is it actually getting poured this week?

I'm looking forward to seeing the site on Thursday, 10 March, just after lunch, as we planned. I'm
sure I'll be taking lots of pics and some video.
Thankfully, it's looking good for a short continuing resolution to pass!

This week I'll be reviewing all your resubmitted plans and will get back to you on those as quickly as
practicable.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:      "Whelan, Joseph" <JWhelan1@wm.com>
To:        Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
              Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
              "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
              <alec.wong@doh.hawaii.gov>
     Date:    02/28/2011 07:02 PM
     Subject: Daily Progress Report for February 28, 2011




  
Greetings  all.
       Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
       Cell  6  Assessment:
1.       The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern  portion
of  the  E6  liner  system  was  submitted  February  25,  2011.    Approval  to  resume  operations  in
this  area  is  pending.
  
2.       The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.    
  
        Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in  place.      
2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box
culvert  invert  to  pipe  invert.  This  is  scheduled  to  be  poured  next  week.    Rebar  work  on  box
culvert  walls  is  ongoing.      
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  is  functionally  complete  per  the  terms  of  Section  19.b.  of  the
AOC.
        Cell  6  Leachate  Riser  Restoration:
1.        105,300 gallons was pumped from the Cell E6 leachate riser storage tank since Friday
and transported to the waste water treatment plant.

2.    33,200 gallons of water was pumped from the south pond area since Friday and
transported to the local waste water treatment plant.
  

3.    30,772 gallons of mud/water was pumped from the south pond area since Friday and
placed within the onsite separation tanks.
Sediment  Basin:
1.     Daily  showers  earlier  this  week  have  prevented  removal  of  silt/rock  material  from
the  northern  portion  of  the  sedimentation  basin.    

2.               The contractor pumped 8,700 gallons of storm water from the sedimentation basin
since Friday and transported to the waste water treatment plant.
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.    
                Beach Assessment Update:
1.               The daily beach assessment phase of this task is complete. There were no calls
received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know if  you  have  any  questions.      

Best  regards,
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
  


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for March 1, 2011
Date:              Tuesday, March 01, 2011 5:33:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted  February  25,  2011.   We  received notification from
DOH  today  concurring that  the  CQA report was  adequate  documentation  of  the  liner
repairs,  which allows  WMH to  resume  operations  in  this  area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert. Half
                                                               of  the  concrete  for  this  structure  was
                                                               poured  today,  the  remainder  to  be  poured
                                                               towards  the  end  of  the  week.   Rebar  work
                                                               on  box  culvert  walls  is  ongoing.     

                                                                 3)    Pipe:     Backfilling  of the HOBAS  pipe
channel  is  now  complete.

                                                            4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

    30,700 gallons was pumped from the Cell E6 leachate riser storage tank today
1)          
and transported to the waste water treatment plant.

     11,000 gallons of water was pumped from the south pond area today and
2)          
transported to the local waste water treatment plant.

3)           Zero gallons of mud/water was pumped from the south pond area today and
placed within the onsite separation tanks.

               Sediment  Basin:

1)           Showers  Tuesday  and  Wednesday  last  week  have resulted  in  the  accumulation  of
storm  water  which prevented  removal  of  silt/rock  material  from  the  northern  portion  of
the  sedimentation  basin.  

2)           The contractor pumped 15,500 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for March 2, 2011
Date:              Wednesday, March 02, 2011 5:11:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  on  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from
DOH on  March  1,  2011 concurring  that  the  CQA  report  was  adequate  documentation  of
the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be
removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing
and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.  

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   Half
                                                               of  the  concrete  for  this  structure  was
                                                               poured on  March  1,  2011,  the  remainder
                                                               to  be  poured  towards  the  end  of  the
                                                               week.   Rebar  work  on  box  culvert  walls  is
                                                               ongoing.     
 3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                            channel  is  now  complete.

                                                            4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

    13,000 gallons was pumped from the Cell E6 leachate riser storage tank today
1)          
and transported to the waste water treatment plant.

     Zero gallons of water was pumped from the south pond area today and
2)          
transported to the local waste water treatment plant.

3)           Zero gallons of mud/water was pumped from the south pond area today and
placed within the onsite separation tanks. 31,000 gallons of water was pumped
today from these separation tanks and and transported to the waste water
treatment plant.

               Sediment  Basin:

1)           Showers  Tuesday  and  Wednesday  last  week  have  resulted  in  the  accumulation  of
storm  water  which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of
the  sedimentation  basin.  

2)           The contractor pumped 40,000 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    

Best  regards,
Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                Whelan, Joseph
To:                  "Tyahla.Stephen@epamail.epa.gov"
Subject:             Photos of WGSL
Date:                Wednesday, March 02, 2011 11:24:00 AM
Attachments:         CIMG0555.JPG
                     CIMG0551.JPG
                     CIMG0558.JPG
                     CIMG0559.JPG
                     CIMG0564.JPG
                     CIMG0560.JPG
                     Request to allow Stormwater Discharge.pdf




Hi  Steve.

        Please  find  attached  photos  taken  yesterday  at  the  WGSL  related  to  the  construction
status  of  the  storm  water  diversion  structure  and  the  sedimentation  basin.   A  copy  of  the
letter  to  DOH  requesting  approval  to  begin  active  discharging  from  the  sedimentation  basin
is  attached.   Also,  this  email  is  intended  to  confirm  our  phone  conversation  yesterday,
where  in you  concurred  that  EPA  is  not  required  to  provide  any  further  approvals  of  our
CQA reports  documenting  liner  repairs  to  the  Cell  E6  area  of  the  site.    As  we  discussed,  we
received  the DOH “no  objection”  letter  yesterday  that  allows  us  to  resume  operations  in
the  southwestern  portion  of  this  cell.    Thank  you  for  your  continued  assistance  in  these
matters.



       Best  regards,




       Joe        




Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

Waste Management's landfills provide over 17,000 acres of
 
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for March 3,2011
Date:              Thursday, March 03, 2011 7:13:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report for  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from
DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the
liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the January  storm  event  and  the construction  of  the  diversion
system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This
removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,
weather  permitting.   Rain  last  night  has  hampered  this  effort  temporarily.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   Half
                                                               of  the  concrete  for  this  structure  was
                                                               poured  on  March  1,  2011,  the  remainder
                                                               to  be  poured  towards  the  end  of  the
                                                               week.   Rebar  work  on  box  culvert  walls  is
ongoing.     

                                                              3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                            channel  is  now  complete.

                                                            4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

    12,018 gallons was pumped from the Cell E6 leachate riser storage tank today
1)          
and transported to the waste water treatment plant.

     25,000 gallons of water was pumped from the south pond area today and
2)          
transported to the local waste water treatment plant, due to an overnight rain event.

     Zero gallons of mud/water was pumped from the south pond area today and
3)          
placed within the onsite separation tanks. Zero gallons of water was pumped today
from these separation tanks, due to the muddy conditions resulting from the rain
event last night.

               Sediment  Basin:

1)           Showers  last night  has  resulted  in  the additional accumulation  of  storm  water  which
prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation
basin.  

2)           The contractor pumped 51,000 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know if  you  have  any  questions.    
Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:              Whelan, Joseph
To:                "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                   "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                   "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                   "alec.wong@doh.hawaii.gov"
Subject:           Daily Progress Report for March 4, 2011
Date:              Friday, March 04, 2011 4:24:00 PM




Greetings  all.

      Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

        Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion
of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from
DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the
liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011
storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system
where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil
material  generated  from  the  January  storm  event  and  the  construction  of  the  diversion
system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This
removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,
weather  permitting.    Rain again last  night  has  hampered  this  effort  temporarily.

        Western  Storm  water  Diversion  Project  (to  render  functional):

                                                               1)  
                                                                  Diversion  Structure:     The  final  wall
                                                               section  of  the  diversion  structure  is  now  in
                                                               place.    

                                                               2)    Box  Culvert:     The  contractor  has
                                                               completed  forming  the  transition  structure
                                                               from  box  culvert  invert  to  pipe  invert.   Half
                                                               of  the  concrete  for  this  structure  was
                                                               poured  on  March  1,  2011,  the  remainder
                                                               was to  be  poured  today,  Friday,  however
                                                               muddy  conditions  as  a  result  of  last  nights
rain has  postponed  this  to  early  next
                                                            week.   Rebar  work  on  box  culvert  walls  is
                                                            ongoing.     

                                                              3)    Pipe:     Backfilling  of the HOBAS  pipe
                                                            channel  is  now  complete.

                                                            4)    The  diversion  structure  is  functionally
                                                            complete  per  the  terms  of  Section  19.b.  of
                                                            the  AOC.

               Cell  6  Leachate  Riser  Restoration:

    14,949 gallons was pumped from the Cell E6 leachate riser storage tank today
1)          
and transported to the waste water treatment plant.

     Zero gallons of water was pumped from the south pond area today and
2)          
transported to the local waste water treatment plant.

3)           Zero gallons of mud/water was pumped from the south pond area today and
placed within the onsite separation tanks. Zero gallons of water was pumped today
from these separation tanks, due to the muddy conditions resulting from the rain
event again last night.

               Sediment  Basin:

1)           Showers this  week  have  resulted  in  the  additional  accumulation  of  storm  water  which
prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation
basin.  

2)           The contractor pumped 59,700 gallons of storm water from the sedimentation
basin today and transported to the waste water treatment plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during
the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not
installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach Assessment Update:

1)     The daily beach assessment phase of this task is complete. There were no
calls received at the established beach waste siting hot line today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Frey, Jesse
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              Daily Progress Report for March 7, 2011




Greetings  all.
                On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today.
Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
                                        1.   The  QCA  report  documenting  the  evaluation  and  repair
                                             of  the  southwestern  portion  of  the  E6  liner  system  was
                                             submitted  February  25,  2011.    We  received  notification
                                             from  DOH  on  March  1,  2011  concurring  that  the  CQA
                                             report  was  adequate  documentation  of  the  liner  repairs,
                                             which  allows  WMH  to  resume  operations  in  this  area.
                                               
                                        2.   The  northwest  section  of  the  Cell  E6  liner  was  also
                                             damaged  in  the  January  13,  2011  storm.    This  area  is
                                             located  directly  below  the  section  of  the  storm  water
                                             diversion  system  where  the  open  box  culvert  ties  into
                                             the  Hobas  pipe.    Consequently,  any  rock  and  soil
                                             material  generated  from  the  January  storm  event  and
                                             the  construction  of  the  diversion  system  in  this  area
                                             must  be  removed  prior  to  the  evaluation  and  repair  of
                                             the  liner.    This  removal  activity  is  ongoing  and  is
                                             expected  to  be  completed  within  the  next  2  weeks,
                                             weather  permitting.
                                               
                Western  Storm  water  Diversion  Project  (to  render  functional):
                                        1)    Diversion  Structure:      The  final  wall  section  of  the
                                        diversion  structure  is  now  in  place.    
                                        2)    Box  Culvert:      The  contractor  has  completed  forming  the
                                        transition  structure  from  box  culvert  invert  to  pipe  invert.  
                                        Half  of  the  concrete  for  this  structure  was  poured  on  March
                                        1,  2011.  The  remainder  is  scheduled  to  be  poured  on
                                        3/10/2011.    Rebar  work  on  box  culvert  walls  is  ongoing.      
                                        3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now
                                        complete.
4)    The  diversion  structure  is  functionally  complete  per  the
                                    terms  of  Section  19.b.  of  the  AOC.
                Cell  6  Leachate  Riser  Restoration:
                                     1.   36,200  gallons  were  pumped  from  the  Cell  E6  leachate
                                          riser  storage  tank  today  and  transported  to  the  waste
                                          water  treatment  plant.
                                           
                                     2.   Zero  gallons  of  water  was  pumped  from  the  south  pond
                                          area  today  and  transported  to  the  local  waste  water
                                          treatment  plant.
                                           
                                     3.   Zero  gallons  of  mud/water  was  pumped  from  the  south
                                          pond  area  today  and  placed  within  the  onsite
                                          separation  tanks.  Zero  gallons  of  water  was  pumped
                                          today  from  these  separation  tanks.
            
                Sediment  Basin:
                                     1.   Showers  this  week  have  resulted  in  the  additional
                                          accumulation  of  storm  water  which  prevented  removal
                                          of  silt/rock  material  from  the  northern  portion  of  the
                                          sedimentation  basin.  
                                           
                                     2.   The  contractor  pumped  113,000  gallons  of  storm  water
                                          from  the  sedimentation  basin  today  and  transported  to
                                          the  waste  water  treatment  plant.
                Evaluating  possible  hydraulic  head  below  liner  system:
                                     1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we
                                          have  drilled  to  depth  at  temporary  piezometer  locations
                                          PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
                                          during  the  drilling  process.  Since  no  water  was
                                          observed,  temporary  piezometers  were  not  installed.    
                                          The  documentation  report  was  submitted  on  February
                                          25,  2011.  
                Beach  Assessment  Update:
                                     1.   The  daily  beach  assessment  phase  of  this  task  is
                                          complete.    There  were  no  calls  received  at  the
                                          established  beach  waste  hot  line  today.
  
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    
Best  regards,
Jesse  Frey
Engineer
Waste  Management  of  Hawaii
92-­‐460  Farrington  Hwy.
Kapolei,  HI  96707
Ph:  808-­‐250-­‐0574
Fax:  808-­‐668-­‐1366
  
  
  
 
From:                 Frey, Jesse
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              Daily Progress Report for March 8, 2011




Greetings  all.
                On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today.
Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
                                        1.   The  QCA  report  documenting  the  evaluation  and  repair
                                             of  the  southwestern  portion  of  the  E6  liner  system  was
                                             submitted  February  25,  2011.    We  received  notification
                                             from  DOH  on  March  1,  2011  concurring  that  the  CQA
                                             report  was  adequate  documentation  of  the  liner  repairs,
                                             which  allows  WMH  to  resume  operations  in  this  area.
                                               
                                        2.   The  northwest  section  of  the  Cell  E6  liner  was  also
                                             damaged  in  the  January  13,  2011  storm.    This  area  is
                                             located  directly  below  the  section  of  the  storm  water
                                             diversion  system  where  the  open  box  culvert  ties  into
                                             the  Hobas  pipe.    Consequently,  any  rock  and  soil
                                             material  generated  from  the  January  storm  event  and
                                             the  construction  of  the  diversion  system  in  this  area
                                             must  be  removed  prior  to  the  evaluation  and  repair  of
                                             the  liner.    This  removal  activity  is  ongoing  and  is
                                             expected  to  be  completed  within  the  next  2  weeks,
                                             weather  permitting.
                                               
                Western  Storm  water  Diversion  Project  (to  render  functional):
                                        1)    Diversion  Structure:      The  final  wall  section  of  the
                                        diversion  structure  is  now  in  place.    
                                        2)    Box  Culvert:      The  contractor  has  completed  forming  the
                                        transition  structure  from  box  culvert  invert  to  pipe  invert.  
                                        Half  of  the  concrete  for  this  structure  was  poured  on  March
                                        1,  2011.  The  remainder  is  scheduled  to  be  poured  on
                                        3/10/2011.    Rebar  work  on  box  culvert  walls  is  ongoing.      
                                        3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now
                                        complete.
4)    The  diversion  structure  is  functionally  complete  per  the
                                    terms  of  Section  19.b.  of  the  AOC.
                Cell  6  Leachate  Riser  Restoration:
                                     1.   0  gallons  were  pumped  from  the  Cell  E6  leachate  riser
                                          storage  tank  today  and  transported  to  the  waste  water
                                          treatment  plant.
                                           
                                     2.   Zero  gallons  of  water  was  pumped  from  the  south  pond
                                          area  today  and  transported  to  the  local  waste  water
                                          treatment  plant.  This  area  currently  contains  no  ponded
                                          water  and  is  being  prepped  for  the  next  phase  of  the
                                          Western  Berm  Construction.
  
                                     3.   Zero  gallons  of  mud/water  was  pumped  from  the  south
                                          pond  area  today  and  placed  within  the  onsite
                                          separation  tanks.  Zero  gallons  of  water  was  pumped
                                          today  from  these  separation  tanks.
            
                Sediment  Basin:
                                     1.   Showers  this  week  have  resulted  in  the  additional
                                          accumulation  of  storm  water  which  prevented  removal
                                          of  silt/rock  material  from  the  northern  portion  of  the
                                          sedimentation  basin.  
                                           
                                     2.   The  contractor  pumped  76,200  gallons  of  storm  water
                                          from  the  sedimentation  basin  today  and  transported  to
                                          the  waste  water  treatment  plant.
                Evaluating  possible  hydraulic  head  below  liner  system:
                                     1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we
                                          have  drilled  to  depth  at  temporary  piezometer  locations
                                          PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
                                          during  the  drilling  process.  Since  no  water  was
                                          observed,  temporary  piezometers  were  not  installed.    
                                          The  documentation  report  was  submitted  on  February
                                          25,  2011.  
                Beach  Assessment  Update:
                                     1.   The  daily  beach  assessment  phase  of  this  task  is
                                          complete.    There  were  no  calls  received  at  the
                                          established  beach  waste  hot  line  today.
 
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    
Best  regards,
Jesse  Frey
Engineer
Waste  Management  of  Hawaii
92-­‐460  Farrington  Hwy.
Kapolei,  HI  96707
Ph:  808-­‐250-­‐0574
Fax:  808-­‐668-­‐1366
  
  
  
  
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              Daily Progress Report for March 9, 2011
Date:                 Wednesday, March 09, 2011 5:18:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing  and  is  expected  to
be  completed  within  the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)  Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor  has
                                                                  completed  forming  the  transition
                                                                  structure  from  box  culvert  invert  to  pipe
                                                                  invert.    Half  of  the  concrete  for  this
                                                                  structure  was  poured  on  March  1,  2011.
                                                                  The  remainder  is  scheduled  to  be  poured
                                                                  on  3/10/2011.    Rebar  work  on  box
                                                                  culvert  walls  is  ongoing.      
 3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure  is
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC.

                Cell  6  Leachate  Riser  Restoration:

      15,100  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today
1)          
and  transported  to  the  waste  water  treatment  plant.

2)           Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm
Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water
which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin.  

2)           The  contractor  pumped 75,300  gallons  of  storm  water  from  the  sedimentation
basin  today  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              Daily Progress Report for March 10, 2011
Date:                 Thursday, March 10, 2011 4:41:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.   This material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently removing  the  material  that  fell  directly
on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within
the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor  has
                                                                  completed  forming  the  transition
                                                                  structure  from  box  culvert  invert  to  pipe
                                                                  invert.    Half  of  the  concrete  for  this   
                                                                  structure  was  poured  on  March  1,  2011.
                                                                  The  remainder was  poured  on
3/9/2011.    Rebar  work  on  box  culvert
                                                         walls  is  ongoing.     The  contractor  has
                                                         also  begun  assembling  the  wall plate
                                                         forms.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

     6,359  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and
1)          
transported  to  the  waste  water  treatment  plant.

     Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm
Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water
which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the
sedimentation  basin.  

2)           The  contractor  pumped 84,000  gallons  of  storm  water  from  the  sedimentation
basin  today  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                  Whelan, Joseph
To:                    Tyahla.Stephen@epamail.epa.gov
Cc:                    steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov;
                       lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov;
                       Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Wall.Steve@epamail.epa.gov;
                       Moxley.Bret@epamail.epa.gov
Subject:               RE: EPA Review of 25 February 2011 Deliverables for WGSL
Date:                  Friday, March 11, 2011 3:42:00 PM



Steve,
  
                                Please  see  WMH  response  to  your  requests  for  information  contained  within  sections  3  &   4
below.    Let  me  know  if  you  have  any  questions.
  
                                Best  regards,
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Friday, March 04, 2011 2:47 PM
To: Whelan, Joseph
Cc: steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov;
lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov;
Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Wall.Steve@epamail.epa.gov;
Moxley.Bret@epamail.epa.gov
Subject: EPA Review of 25 February 2011 Deliverables for WGSL

Joe,

We have reviewed the revised plans and documents you provided by e-mail on February 25,
2011, under cover of your letter of the same date. We also received and reviewed the CQA
report for the southwestern portion E6 liner repair that you sent by a separate e-mail that
same date. Thank you for your prompt submissions.

Our response to each is as follows:

1) “Description of collection & treatment associated with liquid located behind the
temporary berm” (AOC paragraph 19.d.)—APPROVED

2) “Work plan for managing any potential hydraulic head in the Cell E6 location”
(AOC paragraph 19.e.) —Report is APPROVED; this item of the Work is now considered
complete.

3) “Work plan for restoration of the existing sedimentation basin” (AOC paragraph
19.h.) —APPROVED; but need WMH concurrence on completion schedule. WMH’s revised
plan (GEI letter of February 21, 2011) suggests work should be completed by March 14,
2011. Please confirm if this is your proposed deadline or if you wish to propose another date
for completing this item of the Work. [Whelan, Joe] Due to the continuing sporadic rain
events over the past few weeks, rehabilitation of the sedimentation basin has been delayed by
storm water accumulating within said basin. WMH proposes a new deadline of May 15,
2011 to have this work completed. This date should account for the expected end of the rainy
season.

4) “Work plan for the beach assessment and material recovery actions” (AOC paragraph
19.i.)—APPROVED; however, please provide the “hotline” phone number and a list of who
it was given to or how it was posted or otherwise advertised so that the general public is
aware of the hotline. [Whelan, Joe] The hot line number is 808 668 2985, and has been
published in our printed and televised news releases.

5) “Updated Storm Water Management & Contingency Plan” (per Condition 4 of EPA’s
January 28, 2011 e-mail that provided conditional approval for re-opening Cell E6)—
APPROVED

6) E6 Liner Repair Deadline: EPA concurs with WMH’s request of May 15, 2011 as the
deadline for completing the liner repairs in accordance with the previously-approved
“Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair” (Geosyntec
Consultants’ letter of January 27, 2011) per AOC paragraph 19.f. EPA has reviewed and
approves the CQA report provided by WMH under separate cover for completion of repairs
to the “middle sideslope liner area” (AECOM letter of February 25, 2011). [In WMH daily
reports, this same area has been referred to as the “southwestern” portion.]

For your convenience, I have attached an updated deliverables tracking spreadsheet that
reflects all the above. Again, it does not supersede any order requirements, but is provided as
a convenient tool.

Please don’t hesitate to contact me with any questions. I look forward to seeing you at the
facility the afternoon of 10 March.

Thanks,

Steve Tyahla
Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]
From:             Whelan, Joseph
To:               "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                  "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                  "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                  "alec.wong@doh.hawaii.gov"
Subject:          Updated Storm Water Management Plan
Date:             Friday, March 11, 2011 3:29:00 PM
Attachments:      SWM Plan 031111.pdf




Greetings  all.

       Please  find  attached  the  recently  updated  Storm  Water  Management  Plan  for  the
Waimanalo  Gulch  Sanitary  Landfill,  as  required  by Condition  5)  of  EPA  28-­‐Jan-­‐11  Approval
to  Operate  Cell  #E6:   “No  later  than  fifteen  (15 25 days [Extension  granted  to  WMH  by  EPA
on  2/10/11])  after  the  completion  of  a  functional  storm  water  division  structure  (Western
Drainage  System)  as  required  in  19.b.  of  EPA's  Order,  WM  must revise  and  submit  to  EPA
its  SWPCP to  incorporate  the  functional  Western  Drainage  System  and  all  ancillary  storm
water  connections  into  its  revised  SWPCP  consistent  with  the  requirements  of  its  storm
water  general  permit.”    Please  let  me  know  if  you  have  any  questions.

        Best  regards,



Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              Daily Progress Report for March 11, 2011
Date:                 Friday, March 11, 2011 4:24:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly
on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within
the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor  has
                                                                  completed  forming  the  transition
                                                                  structure  from  box  culvert  invert  to  pipe
                                                                  invert.    Half  of  the  concrete  for  this   
                                                                  structure  was  poured  on  March  1,  2011.
                                                                  The  remainder was  poured  on
3/9/2011.    Rebar  work  on  box  culvert
                                                         walls  is  ongoing.     The  contractor  has
                                                         also  begun  assembling  the  wall  plate
                                                         forms.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

     3,159  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and
1)          
transported  to  the  waste  water  treatment  plant.

     Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm
Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional
accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The  contractor  pumped 26,500  gallons  of  storm  water  from  the  sedimentation
basin  today  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL Daily Progress Report for March 14, 2011
Date:                 Monday, March 14, 2011 5:26:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly
on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within
the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor
                                                                  completed the transition  from  the  box
                                                                  culvert  to  the  Hobas  pipe on  3/9/2011.  
                                                                  Rebar  work  on  box  culvert  walls  is
                                                                  ongoing.     The  contractor  has  also  begun
                                                                  assembling  the  wall  plate  forms.
 3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

1)           20,677  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank since
Friday  and  transported  to  the  waste  water  treatment  plant.

     Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm
Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional
accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The  contractor  pumped 126,000  gallons  of  storm  water  from  the  sedimentation
basin since  Friday  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL Daily Progress Report for March 15, 2011
Date:                 Tuesday, March 15, 2011 5:28:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly
on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within
the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor
                                                                  completed the transition  from  the  box
                                                                  culvert  to  the  Hobas  pipe on  3/9/2011.  
                                                                  Rebar  work  on  box  culvert  walls  is
                                                                  ongoing.     The  contractor  has  also  begun
                                                                  assembling  the  wall  plate  forms.
 3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

1)           8,768  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank today  and
transported  to  the  waste  water  treatment  plant.

      1,518  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water (other  than  overnight  rainfall), and  is  being  prepped  for  the  next  phase
of  the  Western  Berm  Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional
accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The  contractor  pumped 71,476  gallons  of  storm  water  from  the  sedimentation
basin today  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL Daily Progress Report for March 16, 2011
Date:                 Wednesday, March 16, 2011 5:05:00 PM




Greetings  all.

       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the
recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly
on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within
the  next  2  weeks,  weather  permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.    

                                                                  2)    Box  Culvert:      The  contractor
                                                                  completed the transition  from  the  box
                                                                  culvert  to  the  Hobas  pipe on  3/9/2011.  
                                                                  Rebar  work  on  box  culvert  walls  is
                                                                  ongoing.     The  contractor  has  also  begun
                                                                  assembling  the  wall  plate  forms.
 3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

1)           6,318  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank today  and
transported  to  the  waste  water  treatment  plant.

      1,300  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water (other  than  overnight  rainfall), and  is  being  prepped  for  the  next  phase
of  the  Western  Berm  Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional
accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.  

2)           The  contractor  pumped 91,400  gallons  of  storm  water  from  the  sedimentation
basin today  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Tyahla.Stephen@epamail.epa.gov"
Subject:          Request to Replace Daily Progress Reports to Weekly
Date:             Wednesday, March 16, 2011 5:14:00 PM




Hello  Steve.

        Waste  Management  of  Hawaii (WMH) has  provided  the  noticed  parties  daily
progress  reports  according  to  the  terms  of  the  Administrative  Order  on  Consent (AOC)  with
USEPA  signed  on  January  25,  2011.    Most  of  the  requirements  associated  with  the  AOC
have  now  been substantially met.    Section VIII.  24.  A.  of  the  AOC  specifies  that “Beginning
two  (2)  days  after  the  Effective  Date,  Respondent  shall  submit  by  e-­‐mail  to  EPA  and  DOH
daily,  until  agreed  otherwise  by  the  Parties,  progress  reports  (Monday  through  Friday  only,
unless  otherwise  requested  by  EPA)  concerning  actions  undertaken  pursuant  to  this  Order
…….”.   WMH  is  hereby  requesting  your  approval  to  replace  the  daily  progress  reports  with
weekly reports.   WMH  proposes  to  provide  you  with  a  weekly  report  similar  to  the  daily
reports  in  content  that  would  run  from  Monday  thru  Sunday,  and  be  delivered  to  all  parties
by  Wednesday summarizing the  previous  weeks  information.    Please  review  this  request
and  provide  your  approval  to move  to  weekly  progress  reports.    Thank  you.



       Best  regards,



       Joe



Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:              Whelan, Joseph
To:                "Tyahla.Stephen@epamail.epa.gov"
Subject:           Re: Request to Replace Daily Progress Reports to Weekly
Date:              Thursday, March 17, 2011 9:02:06 AM



Thank  you  Steve!  I  really  appreciate  your  quick  turn  around.

Joe




From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Thursday, March 17, 2011 12:39 PM
To: Whelan, Joseph
Cc: alec.wong@doh.hawaii.gov <alec.wong@doh.hawaii.gov>; Steven.chang@doh.hawaii.gov
<Steven.chang@doh.hawaii.gov>; stuart.yamada@doh.hawaii.gov <stuart.yamada@doh.hawaii.gov>;
Moxley.Bret@epamail.epa.gov <Moxley.Bret@epamail.epa.gov>; Armann.Steve@epamail.epa.gov
<Armann.Steve@epamail.epa.gov>; Kabei.Arlene@epamail.epa.gov <Kabei.Arlene@epamail.epa.gov>;
Helmlinger.Andrew@epamail.epa.gov <Helmlinger.Andrew@epamail.epa.gov>;
Higuchi.Dean@epamail.epa.gov <Higuchi.Dean@epamail.epa.gov>; Vaille.Rich@epamail.epa.gov
<Vaille.Rich@epamail.epa.gov>; Wall.Steve@epamail.epa.gov <Wall.Steve@epamail.epa.gov>
Subject: Re: Request to Replace Daily Progress Reports to Weekly

Joe,

Your request to issue weekly in lieu of daily progress reports is hereby granted.
Please make your first submission by noon (Hawaii time) on Wednesday, 23 March, to
cover the period of 17 March through Sunday, 20 March 2011. Subsequent reports
covering Monday through Sunday as you describe in your request should be provided by
noon (Hawaii time) each Wednesday.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or
confidential information solely intended to be conveyed to the designated recipient(s). If
you receive this email and are not an intended recipient, please delete this email and its
attachments immediately. The unauthorized use, dissemination, distribution, or
reproduction of this email and its attachments is strictly prohibited by law.]

-----"Whelan, Joseph" <JWhelan1@wm.com> wrote: -----

  To: Stephen Tyahla/R9/USEPA/US@EPA
  From: "Whelan, Joseph" <JWhelan1@wm.com>
  Date: 03/16/2011 08:14PM
  Subject: Request to Replace Daily Progress Reports to Weekly
Hello  Steve.
  
                Waste  Management  of  Hawaii  (WMH)  has  provided  the  noticed  parties  daily  progress  reports
according  to  the  terms  of  the  Administrative  Order  on  Consent  (AOC)  with  USEPA  signed  on
January  25,  2011.    Most  of  the  requirements  associated  with  the  AOC  have  now  been
substantially  met.    Section  VIII.  24.  A.  of  the  AOC  specifies  that  “Beginning  two  (2)  days  after  the
Effective  Date,  Respondent  shall  submit  by  e -­‐mail  to  EPA  and  DOH  daily,  until  agreed  otherwise
by  the  Parties,  progress  reports  (Monday  through  Friday  only,  unless  otherwise  requested  by
EPA)  concerning  actions  undertaken  pursuant  to  this  Order  …….”.      WMH  is  hereby  requesting
your  approval  to  replace  the  daily  progress  reports  with  weekly  reports.    WMH  proposes  to
provide  you  with  a   weekly  report  similar  to  the  daily  reports  in  content  that  would  run  from
Monday  thru  Sunday,  and  be  delivered  to  all  parties  by  Wednesday  summarizing  the  previous
weeks  information.    Please  review  this  request  and  provide  your  approval  to  move  to  weekly
progress  reports.    Thank  you.
  
                Best  regards,
  
                Joe

  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-­668-­2985, ext. 15 Office
808-­668-­1366 Fax
808-­479-­4610 Mobile
  
Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
  
  
  
From:                    Whelan, Joseph
To:                      Tyahla.Stephen@epamail.epa.gov
Subject:                 RE: Proposed due date for Revised SWPCP
Date:                    Tuesday, March 22, 2011 11:27:00 AM



Thank  you  Steve!
  
                                The  existing  ash  cells  comprise  cells  1-­‐8.    You  were  observing  ash  cells  4  &   5.    We  refer  to
the  small  roadway  as  the  HECO  bridge  road  as  it  connects  our  main  access  road  to  the  HECO  power
plant  communications  tower  located  on  the  top  of  the  ridge.    Hope  all  is  well.
  
                                Best  regards,
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Tuesday, March 22, 2011 11:00 AM
To: Whelan, Joseph
Cc: Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Wampler.David@epamail.epa.gov;
Vaille.Rich@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov;
steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov
Subject: Re: Proposed due date for Revised SWPCP

Joe,

Your request is approved. The revised SWPCP is to be submitted to EPA by Monday, 2 May 2011
(as the 1st is a Sunday).

I have   updated the attached Deliverables Tracking spreadsheet to reflect this change as well as all
others   to date.
Again,   the tracking spreadsheet in no way replaces or supersedes any of our AOC requirements, but is
simply   a convenient tool.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]
From:              "Whelan, Joseph" <JWhelan1@wm.com>
     To:                Stephen Tyahla/R9/USEPA/US@EPA
     Date:              03/22/2011 12:23 PM
     Subject:           Proposed due date for Revised SWPCP




Hello  Steve,
  
                We  just  heard  back  from  our  consultant  that  is  revising  the  SWPCP.    In  addition  to  upgrading  the  plan  by
including  that  portion  of  the  constructed  storm  water  diversion  structure  that  renders  it  “functionally  complete”,
WMH  has  requested  that  the  entire  plan  be  updated.    We  are  requesting  a  due  date  of  May  1st   for  this  submittal
to  USEPA.    Please  let  me  know  if  this  date  is  acceptable.    Thank  you.
  
                Best  regards,
  
                Joe
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:              Whelan, Joseph
To:                "Tyahla.Stephen@epamail.epa.gov"
Subject:           Proposed due date for Revised SWPCP
Date:              Tuesday, March 22, 2011 9:23:00 AM




Hello  Steve,

      We  just  heard  back  from  our  consultant  that  is  revising  the  SWPCP.    In  addition  to
upgrading  the  plan  by  including  that  portion  of  the  constructed  storm  water  diversion
structure  that  renders  it “functionally  complete”,  WMH  has  requested  that  the  entire  plan
be  updated.    We  are  requesting  a  due  date  of  May  1 st   for  this  submittal  to  USEPA.    Please
let  me  know  if  this  date  is  acceptable.    Thank  you.



       Best  regards,



       Joe

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending March 20, 2011
Date:                 Tuesday, March 22, 2011 5:52:00 PM




Greetings  all.

       The  USEPA  granted  our  request  to replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and document  work  completed  during the period  of  the  prior
Monday  thru  Sunday.    This  initial  weekly  progress  report  covers  March  17th  (the  day
after  the  last  daily  report)  thru  Sunday  March  20th.   Please  find  below  the weekly
progress  report  for  work  items  contained  within  the  recently  approved  AOC.      

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly
on  the  liner.    This  removal  activity  is  expected  to  be  completed by  March  26th,  and
replacement  of  any  damaged  liner should  be  completed  by  April  9th,  weather
permitting.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)  Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.     The  contractor  expects  to
                                                                  complete  the  concrete  pour  on  the
middle  section  of  the  weir  on
                                                             Wednesday  March  23,  2011.

                                                             2)    Box  Culvert:      The  contractor
                                                             completed the transition  from  the  box
                                                             culvert  to  the  Hobas  pipe on  3/9/2011.  
                                                             Rebar  work  on  box  culvert  walls  is
                                                             ongoing.     The  contractor  has  also  begun
                                                             assembling  the  wall  plate  forms.    The
                                                             next  concrete  wall  pour  is  scheduled  for
                                                             Monday  March  28th.

                                                               3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                             channel  is  now  complete.

                                                             4)    The  diversion  structure was
                                                             functionally  complete  per  the  terms  of
                                                             Section  19.b.  of  the  AOC  as  of  February
                                                             10,  2011.

                Cell  6  Leachate  Riser  Restoration:

1)             31,698  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank since
March  16th, and  transported  to  the  waste  water  treatment  plant.

     zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and
2)          
transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no
ponded  water, and  is  being  prepped  for  the  next  phase  of  the  Western  Berm
Construction.

     Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and
3)          
placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today
from  these  separation  tanks.

                Sediment  Basin:

1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional
accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the
northern  portion  of  the  sedimentation  basin.

2)           The  contractor  pumped 221,300  gallons  of  storm  water  from  the  sedimentation
basin since  March  16th,  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:
1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  today.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending March 27, 2011
Date:                 Tuesday, March 29, 2011 7:37:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  March 21 thru  Sunday
March  27th.  

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  damaged  liner is  expected  to  be  completed  by
March  30th,  and  the  CQA  report  submitted  by  April  1st.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.     The  contractor has completed
                                                                  the  concrete  pour  on  the  middle  section
                                                                  of  the  weir.
2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         has  also  begun  assembling  the  wall  plate
                                                         forms.    The most  recent   concrete  wall
                                                         pour was  performed  on  Monday  March
                                                         28th.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

    52,434  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
March 21,  and  transported  to  the  waste  water  treatment  plant.

    The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.

                Sediment  Basin:

1)           105,900  gallons  of  storm  water were  pumped from  the  sedimentation  basin
during  this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    
Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                                          Whelan, Joseph
To:                                            Tyahla.Stephen@epamail.epa.gov
Subject:                                       FW: WGSL, CQA Report Documenting Repairs to the Final Section of Cell E6 Liner
Date:                                          Tuesday, April 05, 2011 2:33:00 PM
Attachments:                                   Ltr Rpt Cell E6 West Slope Repair 040411.pdf




Hi  Steve,

      Just  checking  in  to  see  if  you  had  a  chance  to  review  and  approve  this  CQA  report.  
We  need  the  airspace.    Thanks.



                  Joe

_____________________________________________
From: Whelan, Joseph
Sent: Monday, April 04, 2011 2:54 PM
To: 'Steven.chang@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov; Miyashiro, Thomas;
'Tyahla.Stephen@epamail.epa.gov'
Subject: WGSL, CQA Report Documenting Repairs to the Final Section of Cell E6 Liner

Greetings  all.

                                Please  find  the  CQA  report  documenting  the  liner  repairs  related  to  the  storm
damage  located  within  the  northwest  portion  of  Cell  E6.    This  submission  documents  the
final  section  of  the  Cell  E6  liner  repairs.    We  would  appreciate  your  timely  review  and
approval  of  this  report.      Thank  you  in  advance  for  your  assistance  with  this  most  important
project.



                                Best  regards,



                                Joe                                                        




Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending April 3, 2011
Date:                 Tuesday, April 05, 2011 5:07:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28 thru  Sunday April
3rd.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    Completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of the  final  piece  of  the damaged  liner  was
completed on  April  1st,  and  the  CQA  report  submitted on  April 4th.  

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.     The  contractor  has  completed
                                                                  the  concrete  pour  on  the  middle  section
                                                                  of  the  weir.  
2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

    51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
March  28,  and  transported  to  the  waste  water  treatment  plant.

    The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.

                Sediment  Basin:

1)           Zero  gallons  of  storm  water were  pumped from  the  sedimentation  basin during
this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug
sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm
water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry it  out  prior  to  removal.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  
Completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending April 3, 2011
Date:                 Tuesday, April 05, 2011 5:07:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28 thru  Sunday April
3rd.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    Completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of the  final  piece  of  the damaged  liner  was
completed on  April  1st,  and  the  CQA  report  submitted on  April 4th.  

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                  1)   Diversion  Structure:     The  final  wall
                                                                  section  of  the  diversion  structure  is  now
                                                                  in  place.     The  contractor  has  completed
                                                                  the  concrete  pour  on  the  middle  section
                                                                  of  the  weir.  
2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         10,  2011.

                Cell  6  Leachate  Riser  Restoration:

    51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
March  28,  and  transported  to  the  waste  water  treatment  plant.

    The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.

                Sediment  Basin:

1)           Zero  gallons  of  storm  water were  pumped from  the  sedimentation  basin during
this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug
sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm
water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry it  out  prior  to  removal.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  
Completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
From:                Whelan, Joseph
To:                  Tyahla.Stephen@epamail.epa.gov
Cc:                  Armann.Steve@epamail.epa.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov;
                     alec.wong@doh.hawaii.gov; Wampler.David@epamail.epa.gov
Subject:             RE: WGSL AOC Progress Report for Week Ending April 3, 2011
Date:                Wednesday, April 06, 2011 4:45:00 PM



Greetings,
  
                                I  will  change  the  date  on  item  4  of  the  weekly  progress  reports.    Concerning  the
sedimentation  basin,  we  used  an  excavator  bucket  to  dig  a   small  sump  in  the  south  and  north  ends
of  the  basin  in  two  small  areas  that  continue  to  hold  water  but  are  shallow  enough  to  prevent
pumping.    Therefore  the  sumps  are  under  water  at  this  time  and  pictures  would  not  reveal
meaningful  data.    These  sumps  merely  allow  the  water  entrapped  within  the  sediment  to  bleed  out
and  provide  us  with  a   location  from  which  to  pump  the  free  standing  water.    Neither  sump  is  deep
enough  to  affect  the  bottom  area  of  the  basin,  each  is  probably  5x5x5  feet.
  
                                Best  regards,
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Wednesday, April 06, 2011 12:03 PM
To: Whelan, Joseph
Cc: Armann.Steve@epamail.epa.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov;
alec.wong@doh.hawaii.gov; Wampler.David@epamail.epa.gov
Subject: Re: WGSL AOC Progress Report for Week Ending April 3, 2011

Hi Joe,

A minor correction on your weekly report, and a request.

Item 4) under Western Storm water Diversion Project (to render functional), an apparent typo- the
actual date was 15 February (sorry, I missed that before). Your e-mail notifying it was functional is
dated the 15th and my concurrence was on the 16th. Please correct in future reports.

Sedimentation Basin-you say you dug sumps in the north and south ends to help water infiltrate; what
are their rough dimensions? Is south one into any of the existing sub-drain system? And, can you
send me a photo of these sumps? Just trying to get a better sense of them.

Thanks,

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov
[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:    "Whelan, Joseph" <JWhelan1@wm.com>
To:      Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
         Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
         Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
         "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
         <alec.wong@doh.hawaii.gov>
Date:    04/05/2011 08:07 PM
Subject: WGSL AOC Progress Report for Week Ending April 3, 2011




Greetings  all.
        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28  thru  Sunday  April
3rd.
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
1.               The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    Completed.
  
2.               The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell
directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    
                Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in
place.      The  contractor  has  completed  the  concrete  pour  on  the  middle  section  of  the
weir.    
2)    Box  Culvert:      Rebar  work  on  box  culvert  walls  is  ongoing.      The  contractor
continues  assembling  the  wall  plate  forms  and  completing  the  associated  concrete
pours.
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  was  functionally  complete  per  the  terms  of  Section  19.b.  of
the  AOC  as  of  February  10,  2011.
                Cell  6  Leachate  Riser  Restoration:
1.               51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
March  28,  and  transported  to  the  waste  water  treatment  plant.
2.               The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the
next  phase  of  the  Western  Berm  Construction.  
                Sediment  Basin:
1.               Zero  gallons  of  storm  water  were  pumped  from  the  sedimentation  basin  during
this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug
sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm
water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry  it  out  prior  to  removal.
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered
  during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.
  Completed.
                Beach  Assessment  Update:
1.               The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.      
Best  regards,
  
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending April 10, 2011
Date:                 Tuesday, April 12, 2011 4:18:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers April  4 thru  Sunday  April
10.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.   This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.   This  project  is
completed.

3)           All  liner  repairs resulting  from  the  December/January  storm  event  damage  have
now been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete,
clean  up  and back  fill  of  native  stone  and
                                                         soil  are  scheduled  for  next  week.

                                                         2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.    Wall  pours  are
                                                         scheduled  for  this  Thursday  and  Friday,
                                                         weather  permitting.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     35,586  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
April 4th,  and  transported  to  the  waste  water  treatment  plant.

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  418.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.   15,000 gallons  of  storm  water
were  pumped from  the  sedimentation  basin during  this  reporting  period,  and   used  on
site  for  dust  control  and  irrigation.    WM  dug  sumps  into  the  north  and  south  end  of  the
sedimentation  basin  in  order  to  allow  storm  water  to  bleed  out  of  the  sediment,  in  an
effort  to  dry  it  out  prior  to  removal.  

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.
              Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                          Whelan, Joseph
To:                            Tyahla.Stephen@epamail.epa.gov
Subject:                       RE: WGSL AOC Progress Report for Week Ending April 10, 2011
Date:                          Wednesday, April 13, 2011 5:00:00 PM



Hi  Steve,
  
                                Within  the  next  few  days.
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Wednesday, April 13, 2011 6:05 AM
To: Whelan, Joseph
Subject: Re: WGSL AOC Progress Report for Week Ending April 10, 2011

Thanks Joe.
I'm anxious to hear when you're able to get the sed basin water level low enough to start de-mucking.



Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]


From:    "Whelan, Joseph" <JWhelan1@wm.com>
To:      Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
         Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve
         Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>,
         "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
         <alec.wong@doh.hawaii.gov>
Date:    04/12/2011 07:18 PM
Subject: WGSL AOC Progress Report for Week Ending April 10, 2011




Greetings  all.
        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  April  4  thru  Sunday  April  10.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
1.               The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.
  
2.               The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell
directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.
  
3.               All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.
                Western  Storm  water  Diversion  Project  (to  render  functional):
1)    Diversion  Structure:      The  diversion  structure  concrete  work  is  complete,  clean  up
and  back  fill  of  native  stone  and  soil  are  scheduled  for  next  week.
2)    Box  Culvert:      Rebar  work  on  box  culvert  walls  is  ongoing.      The  contractor
continues  assembling  the  wall  plate  forms  and  completing  the  associated  concrete
pours.    Wall  pours  are  scheduled  for  this  Thursday  and  Friday,  weather  permitting.
3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.
4)    The  diversion  structure  was  functionally  complete  per  the  terms  of  Section  19.b.  of
the  AOC  as  of  February  15,  2011.
                Cell  6  Leachate  Riser  Restoration:
1.               35,586  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
April  4th,  and  transported  to  the  waste  water  treatment  plant.
2.               The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next
phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  418.
                Sediment  Basin:
1.               DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.    15,000  gallons  of  storm  water  were
pumped  from  the  sedimentation  basin  during  this  reporting  period,  and  used  on  site
for  dust  control  and  irrigation.    WM  dug  sumps  into  the  north  and  south  end  of  the
sedimentation  basin  in  order  to  allow  storm  water  to  bleed  out  of  the  sediment,  in  an
effort  to  dry  it  out  prior  to  removal.    
                Evaluating  possible  hydraulic  head  below  liner  system:
1.               Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered
  during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This
project  is  completed.
                Beach  Assessment  Update:
1.               The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.      
Best  regards,
  
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.

  
  


Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending April 17, 2011
Date:                 Tuesday, April 19, 2011 5:45:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  April 11 thru  Sunday  April
17.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete,
clean  up  and  back  fill  of  native  stone  and
                                                         soil  are ongoing.

                                                         2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.   Two  wall  pours were
                                                         completed  last  Thursday  and  Friday.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     26,006  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
April 11th,  and  transported  to  the  waste  water  treatment  plant.   Additionally,  this
week  the  leachate  riser  was  extended  vertically  to  the  final  elevation located at  the
intersection  of  the western  drainage  pipe  access  road.

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  420.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.   This  week  we completed  free
water  removal  from  the  basin,  and began daily  removal  of  sediment  contained  within
this  basin,  placing it within  Cell  E6.    Friday  evening  rains   resulted  in accumulation  of
stormwater  within  the  northern  portion  of  the  sedimentation  basin.    We  are  currently
removing  this  water,  prior  to  resuming  sediment  removal  activities.  

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.
              Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending April 24, 2011
Date:                 Monday, April 25, 2011 5:03:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  April  18 thru  Sunday  April
24.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete,
clean  up  and  back  fill  of  native  stone  and
                                                         soil  are  ongoing.

                                                         2)    Box  Culvert:     Rebar  work  on  box
                                                         culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.  

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     4,159  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
April  18th,  and  transported  to  the  waste  water  treatment  plant.  

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  420.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.     WMH  has  completed  free  water
removal  from  the  basin,  and continue  daily  removal  of the sediment,  placing  it  within
Cell  E6.   We  have  removed  approximately  30%  of  the  silty  material  from  the  north  end
of  the  basin  and  20%  of  the  silt  from  the  south  end.   However,  it  should  be  noted  that
future rain  events  will  cause  delays  in  completing  this  process.       

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending May 1, 2011
Date:                 Tuesday, May 03, 2011 5:15:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  April 25 thru  Sunday May  1.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.

                                                                  2)    Box  Culvert:     Rebar  work  on  box
culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.    

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     1,000  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
April 25th,  and  transported  to  the  waste  water  treatment  plant.        

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  435.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.      WMH  has  completed  free  water
removal  from  the  basin,  and  continues  daily  removal  of  the  sediment,  placing  it  within
Cell  E6.    We  have  removed  approximately 90%  of  the  silty  material  from  the  north  end
of  the  basin  and 20%  of  the  silt  from  the  south  end.    However,  it  should  be  noted  that
future  rain  events  will  cause  delays  in  completing  this  process.        

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:             Whelan, Joseph
To:               "Tyahla.Stephen@epamail.epa.gov"
Subject:          WGSL Request to Extend Completion Deadline - AOC
Date:             Thursday, May 05, 2011 4:51:00 PM
Attachments:      CIMG0618.JPG
                  CIMG0619.JPG
                  CIMG0615.JPG
                  CIMG0620.JPG




Hello  Steve.

       Per  our  phone  conversation  on May  4,  2011,  recent  rain  events  occurring  at  the
Waimanalo  Gulch  Sanitary  Landfill  (WGSL)  have  caused  delays  in  completing  the  cleanout
of  the  on  site  sedimentation  basin.   This  clean  out  is  the  last  project  associated  with  the
EPA AOC. Currently,  the  north  end  of  the  basin  is  approximately  90%  empty  of  sediment,
and  we  continue  to  remove  sediment  from  the  southern  portion.    Recent  rains  have  added
about  4  feet  of  storm  water  to  the  northern  end  of  the  basin,  which  is  currently  being
pumped  out  and  used  for  on  site  irrigation  and  dust  control.    This  rain  will  cause  delays  in
completing  the  full  restoration  of  the  sediment  basin.    Please  see  the  pictures  taken  on  May
4,  2011.    We  are  requesting  approval  to  move  the  due  date  for  completion  of  this  project
from  May  15 th   to  June  15 th .    The  normal  wet  season  for  this  area  usually  ends  by  mid
March,  however  we  still could experience  localized  rain  events  which may impede  our
progress.    Please  provide  your  approval  to  move  the  completion  date  to  June  15,  2011.  
Thank  you.

       Best  regards,



       Joe



Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                  Whelan, Joseph
To:                    Tyahla.Stephen@epamail.epa.gov
Subject:               RE: WGSL Request to Extend Completion Deadline - AOC
Date:                  Friday, May 06, 2011 8:11:00 AM



Thanks  Steve,
  
                                We  really  appreciate  your  working  with  us  and  being  receptive  to  local  conditions  affecting
this  project.
  
  
                                Joe
  
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Friday, May 06, 2011 7:02 AM
To: Whelan, Joseph
Cc: stuart.yamada@doh.hawaii.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov;
alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov;
Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov
Subject: Re: WGSL Request to Extend Completion Deadline - AOC

Joe,

Your request to extend the completion date for restoration of the sedimentation basin (per
paragraph 19.h. of the AOC) from the current deadline of 15 May to 15 June 2011 is hereby granted.

(For the cc's I have attached a PDF file containing the pictures you provided.)

As we discussed, please keep me apprised, with as much advance notice as possible, as to when you
believe you will be completing that work.

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential
information solely intended to be conveyed to the designated recipient(s). If you receive this email and
are not an intended recipient, please delete this email and its attachments immediately. The
unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly
prohibited by law.]




From:              "Whelan, Joseph" <JWhelan1@wm.com>
To:                Stephen Tyahla/R9/USEPA/US@EPA
Date:              05/05/2011 07:52 PM
Subject:           WGSL Request to Extend Completion Deadline - AOC
Hello  Steve.
  
                Per  our  phone  conversation  on  May  4,  2011,  recent  rain  events  occurring  at  the  Waimanalo  Gulch  Sanitary
Landfill  (WGSL)  have  caused  delays  in  completing  the  cleanout  of  the  on  site  sedimentation  basin.    This  clean  out
is  the  last  project  associated  with  the  EPA  AOC.  Currently,  the  north  end  of  the  basin  is  approximately  90%
empty  of  sediment,  and  we  continue  to  remove  sediment  from  the  southern  portion.    Recent  rains  have  added
about  4  feet  of  storm  water  to  the  northern  end  of  the  basin,  which  is  currently  being  pumped  out  and  used  for
on  site  irrigation  and  dust  control.    This  rain  will  cause  delays  in  completing  the  full  restoration  of  the  sediment
basin.    Please  see  the  pictures  taken  on  May  4,  2011.    We  are  requesting  approval  to  move  the  due  date  for
completion  of  this  project  from  May  15 th   to  June  15 th .    The  normal  wet  season  for  this  area  usually  ends  by  mid
March,  however  we  still  could  experience  localized  rain  events  which  may  impede  our  progress.    Please  provide
your  approval  to  move  the  completion  date  to  June  15,  2011.    Thank  you.
  
  
                Best  regards,
  
                Joe
  
Joe Whelan
  
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile


Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
  

Waste Management recycles enough paper every year to save 41 million trees.
Please recycle any printed emails.
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending May 8, 2011
Date:                 Tuesday, May 10, 2011 8:56:00 AM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers May  1 thru  Sunday  May 8.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.

                                                                  2)    Box  Culvert:     Rebar  work  on  box
culvert  walls  is  ongoing.     The  contractor
                                                         continues  assembling  the  wall  plate
                                                         forms  and  completing  the  associated
                                                         concrete  pours.     There  were  several  rain
                                                         delay  days  during  this  reporting  period
                                                         due  to  heavy  rains.   No  damage  was
                                                         incurred.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     63,611  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
May  1st,  and  transported  to  the  waste  water  treatment  plant.       Leachare  riser
restoration  is  complete.

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  440.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.     We  have  removed  approximately
90%  of  the  silty  material  from  the  north  end  of  the  basin  and 30%  of  the  silt  from  the
south  end.     Rain  events this  week  have  caused  several  feet  of  storm  water
accumulation  in  the  sedimentation  basin,  which is currently being  removed.   Sediment
removal will  resume  once  this  process  is  complete.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.

               Beach  Assessment  Update:
1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending May 15, 2011
Date:                 Monday, May 16, 2011 5:09:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  May 9 thru  Sunday  May 15.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.

                                                                  2)    Box  Culvert:     Rebar  work  on the box
culvert  walls and  ceiling is  ongoing.    
                                                         The  contractor  continues  assembling  the
                                                         wall &  ceiling plate  forms  and
                                                         completing  the  associated  concrete
                                                         pours.      There  were  several  rain  delays
                                                         during  this  reporting  period.    No  damage
                                                         was  incurred.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

      9,477  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since May
1)          
9th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser  restoration  is
complete.

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  445.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.        We  have  removed  approximately
90%  of  the  silty  material  from  the  north  end  of  the  basin  and 35%  of  the  silt  from  the
south  end.      Rain  events last week  have  caused  several  feet  of  storm  water
accumulation  in  the  sedimentation  basin,  which  is  currently  being  removed.   Sediment
removal  has  resumed  in  the  south  end  of  the  basin,  and  we  continue  to  remove storm
water  from  the  north  end.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.

               Beach  Assessment  Update:
1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.

ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending May 22, 2011
Date:                 Monday, May 23, 2011 5:00:00 PM




Greetings  all.

        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  May 16 thru  Sunday  May
22.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell
directly  on  the  liner.   Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.
2)    Box  Culvert:     Rebar  work  on the box
                                                         culvert  walls and  ceiling is  ongoing.    
                                                         The  contractor  continues  assembling  the
                                                         wall  &  ceiling  plate  forms  and  completing
                                                         the  associated  concrete  pours.    

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     56,914  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
May 16th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser
restoration  is  complete.

      The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.     Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  445.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin
storm  water  for  on  site  dust  control  and  irrigation.        We  have  removed  approximately
90%  of  the  silty  material  from  the  north  end  of  the  basin  and 100%  of  the  silt  from
the  south  end.     Crushed  stone  and  silt  from  the  under  drain  system  will  be  replaced
this  week.    Prior  rain  events  have  caused  several  feet  of  storm  water  accumulation  in
the north  end  of the sedimentation  basin,  which  is  currently  being  removed.  

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This
project  is  completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line during  this  reporting  period.
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Best  regards,

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Lottig, Justin
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending May 29, 2011




Aloha,  Joe  Whelan  is  out  of  the  office  this  week,  so  I  am  sending  the  weekly  progress
report.
The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  May  23  thru  Sunday  May  29.
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
                                        1.   The  QCA  report  documenting  the  evaluation  and  repair
                                             of  the  southwestern  portion  of  the  E6  liner  system  was
                                             submitted  February  25,  2011.    We  received  notification
                                             from  DOH  on  March  1,  2011  concurring  that  the  CQA
                                             report  was  adequate  documentation  of  the  liner  repairs,
                                             which  allows  WMH  to  resume  operations  in  this  area.  
                                             This  project  is  completed.
                                               
                                        2.   The  northwest  section  of  the  Cell  E6  liner  was  also
                                             damaged  in  the  January  13,  2011  storm.    This  area  is
                                             located  directly  below  the  section  of  the  storm  water
                                             diversion  system  where  the  open  box  culvert  ties  into
                                             the  Hobas  pipe.    Consequently,  any  rock  and  soil
                                             material  generated  from  the  January  storm  event  and
                                             the  construction  of  the  diversion  system  in  this  area
                                             had  to  be  removed  prior  to  the  evaluation  and  repair  of
                                             the  liner.    This  material  has  now  been  removed  from
                                             the  side  slope  of  the  gulch.    The  contractor  has
                                             completed  removing  the  material  that  fell  directly  on
                                             the  liner.    Replacement  of  the  final  piece  of  the
                                             damaged  liner  was  completed  on  April  1st,  and  the  CQA
                                             report  submitted  on  April  4th .    This  project  is  completed.
             
                                        3.   All  liner  repairs  resulting  from  the  December/January
                                             storm  event  damage  have  now  been  completed.
                Western  Storm  water  Diversion  Project  (to  render  functional):
                                        1)    Diversion  Structure:      The  diversion  structure  concrete
                                        work  is  complete.
2)    Box  Culvert:        Rebar  work  on  the  box  culvert  walls  and
                                    ceiling  is  ongoing.      The  contractor  continues  assembling
                                    the  wall  &  ceiling  plate  forms  and  completing  the
                                    associated  concrete  pours.      
                                    3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now
                                    complete.
                                    4)    The  diversion  structure  was  functionally  complete  per
                                    the  terms  of  Section  19.b.  of  the  AOC  as  of  February  15,
                                    2011.
                Cell  6  Leachate  Riser  Restoration:
                                     1.   25,216  gallons  were  pumped  from  the  Cell  E6  leachate
                                          riser  storage  tank  since  May  22nd,  and  transported  to
                                          the  waste  water  treatment  plant.        Leachate  riser
                                          restoration  is  complete.
                                     2.   The  south  pond  area  contains  no  ponded  water,  and
                                          was  prepped  for  the  next  phase  of  the  Western  Berm
                                          Construction.      Phase  III  of  the  western  berm
                                          construction  is  now  complete  to  elevation  445.  
                                          Additional  berm  placement  is  ongoing.
                Sediment  Basin:
                                     1.   DOH  provided  approval  on  March  24th   to  begin  using
                                          the  sedimentation  basin  storm  water  for  on  site  dust
                                          control  and  irrigation.        We  have  removed
                                          approximately  90%  of  the  silty  material  from  the  north
                                          end  of  the  basin  and  100%  of  the  silt  from  the  south
                                          end.      Crushed  stone  and  silt  from  the  under  drain
                                          system  was  replaced  during  the  past  week.    Prior  rain
                                          events  have  caused  several  feet  of  storm  water
                                          accumulation  in  the  north  end  of  the  sedimentation
                                          basin,  which  is  currently  being  removed.    
                Evaluating  possible  hydraulic  head  below  liner  system:
                                     1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we
                                          have  drilled  to  depth  at  temporary  piezometer  locations
                                          PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
                                          during  the  drilling  process.  Since  no  water  was
                                          observed,  temporary  piezometers  were  not  installed.    
                                          The  documentation  report  was  submitted  on  February
                                          25,  2011.    This  project  is  completed.
                Beach  Assessment  Update:
                                     1.   The  daily  beach  assessment  phase  of  this  task  is
complete.    There  were  no  calls  received  at  the
                                    established  beach  waste  hot  line  during  this  reporting
                                    period.
  
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    
  
Justin H. Lottig
Environmental Protection Manager
Waste Management of Hawaii
92-460 Farrington Highway
Kapolei, HI 96707
808.668.2985
  
 
From:                 Lottig, Justin
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending June 5, 2011




Aloha,  Joe  Whelan  was  out  of  the  office  last  week,  so  I  am  sending  the  weekly  progress
report.
The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly
report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by
noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
Monday  thru  Sunday.      This  weekly  progress  report  covers  May  30  thru  Sunday  June  5.
ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED
                Cell  6  Assessment:
                                        1.   The  QCA  report  documenting  the  evaluation  and  repair
                                             of  the  southwestern  portion  of  the  E6  liner  system  was
                                             submitted  February  25,  2011.    We  received  notification
                                             from  DOH  on  March  1,  2011  concurring  that  the  CQA
                                             report  was  adequate  documentation  of  the  liner  repairs,
                                             which  allows  WMH  to  resume  operations  in  this  area.  
                                             This  project  is  completed.
                                               
                                        2.   The  northwest  section  of  the  Cell  E6  liner  was  also
                                             damaged  in  the  January  13,  2011  storm.    This  area  is
                                             located  directly  below  the  section  of  the  storm  water
                                             diversion  system  where  the  open  box  culvert  ties  into
                                             the  Hobas  pipe.    Consequently,  any  rock  and  soil
                                             material  generated  from  the  January  storm  event  and
                                             the  construction  of  the  diversion  system  in  this  area
                                             had  to  be  removed  prior  to  the  evaluation  and  repair  of
                                             the  liner.    This  material  has  now  been  removed  from
                                             the  side  slope  of  the  gulch.    The  contractor  has
                                             completed  removing  the  material  that  fell  directly  on
                                             the  liner.    Replacement  of  the  final  piece  of  the
                                             damaged  liner  was  completed  on  April  1st,  and  the  CQA
                                             report  submitted  on  April  4th .    This  project  is  completed.
             
                                        3.   All  liner  repairs  resulting  from  the  December/January
                                             storm  event  damage  have  now  been  completed.
                Western  Storm  water  Diversion  Project  (to  render  functional):
                                        1)    Diversion  Structure:      The  diversion  structure  concrete
                                        work  is  complete.
2)    Box  Culvert:        Rebar  work  on  the  box  culvert  walls  and
                                    ceiling  is  ongoing.      The  contractor  continues  assembling
                                    the  wall  &  ceiling  plate  forms  and  completing  the
                                    associated  concrete  pours.      
                                    3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now
                                    complete.
                                    4)    The  diversion  structure  was  functionally  complete  per
                                    the  terms  of  Section  19.b.  of  the  AOC  as  of  February  15,
                                    2011.
                Cell  6  Leachate  Riser  Restoration:
                                     1.   34,075  gallons  were  pumped  from  the  Cell  E6  leachate
                                          riser  storage  tank  since  May  30th,  and  transported  to
                                          the  waste  water  treatment  plant.        Leachate  riser
                                          restoration  is  complete.
                                     2.   The  south  pond  area  contains  no  ponded  water,  and
                                          was  prepped  for  the  next  phase  of  the  Western  Berm
                                          Construction.      Phase  III  of  the  western  berm
                                          construction  is  now  complete  to  elevation  445.  
                                          Additional  berm  placement  is  ongoing.
                Sediment  Basin:
                                     1.   DOH  provided  approval  on  March  24th   to  begin  using
                                          the  sedimentation  basin  storm  water  for  on  site  dust
                                          control  and  irrigation.        We  have  removed
                                          approximately  95%  of  the  silty  material  from  the  north
                                          end  of  the  basin  and  100%  of  the  silt  from  the  south
                                          end.      Crushed  stone  and  silt  from  the  under  drain
                                          system  has  been  replaced.    All  previously  accumulated
                                          storm  water  in  the  north  end  of  the  sedimentation
                                          basin  has  been  removed.
                Evaluating  possible  hydraulic  head  below  liner  system:
                                     1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we
                                          have  drilled  to  depth  at  temporary  piezometer  locations
                                          PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
                                          during  the  drilling  process.  Since  no  water  was
                                          observed,  temporary  piezometers  were  not  installed.    
                                          The  documentation  report  was  submitted  on  February
                                          25,  2011.    This  project  is  completed.
                Beach  Assessment  Update:
                                     1.   The  daily  beach  assessment  phase  of  this  task  is
                                          complete.    There  were  no  calls  received  at  the
established  beach  waste  hot  line  during  this  reporting
                                    period.
  
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
Please  let  me  know  if  you  have  any  questions.    
  
Justin H. Lottig
Environmental Protection Manager
Waste Management of Hawaii
92-460 Farrington Highway
Kapolei, HI 96707
808.668.2985
  
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending June 12, 2011
Date:                 Monday, June 13, 2011 4:53:00 PM




Greetings  All.

       The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a
weekly  report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be
submitted  by  noon  each  Wednesday  and  document  work  completed  during  the  period
of  the  prior  Monday  thru  Sunday.      This  weekly  progress  report  covers June  6  thru
Sunday  June 12th.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell
directly  on  the  liner.    Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.
2)    Box  Culvert:        Rebar  work  on  the  box
                                                         culvert  walls  and  ceiling  is  ongoing.      The
                                                         contractor  continues  assembling  the  wall
                                                         &  ceiling  plate  forms  and  completing  the
                                                         associated  concrete  pours.  
                                                         Approximately  150  feet  remains  to  be
                                                         installed.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure  was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     33,343  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
June  6th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser
restoration  is  complete.

      The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  450.    Additional  berm  placement  is  ongoing.

                Sediment  Basin:

1)           We  have  removed  the remainder  of  the silty  material  from  the  north  and  south
ends  of  the  basin.      Crushed  stone  and  perforated  pipe from  the  under  drain  system
has  been  replaced.   This  project  was  physically  complete  on  Thursday  June  9th.    The
documentation  report  will  be  submitted  on  June  15th.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This
project  is  completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  during  this  reporting  period.
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                           Whelan, Joseph
To:                             "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                                "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                                "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                                "alec.wong@doh.hawaii.gov"
Subject:                        WGSL Final Report for Sedimentation Basin Restoration
Date:                           Wednesday, June 15, 2011 12:58:00 PM
Attachments:                    WMH Ltr Rpt Sedimentation Basin Repair_061511.pdf




Greetings  all.

     Please  find  a  copy  of  the  final  report  documenting  the  restoration  of  the
sedimentation  basin  located  at  the  Waimanalo  Gulch  Sanitary  Landfill.  

        Best  regards,



        Joe                        

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:                 Whelan, Joseph
To:                   "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov";
                      "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov";
                      "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov";
                      "alec.wong@doh.hawaii.gov"
Subject:              WGSL AOC Progress Report for Week Ending June 19, 2011
Date:                 Monday, June 20, 2011 5:01:00 PM




Greetings  All.

       The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a
weekly  report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be
submitted  by  noon  each  Wednesday  and  document  work  completed  during  the  period
of  the  prior  Monday  thru  Sunday.      This  weekly  progress  report  covers June 13  thru
Sunday  June 19th.

ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED

                Cell  6  Assessment:

1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern
portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received
notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate
documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this
area.    This  project  is  completed.



2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,
2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water
diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,
any  rock  and  soil  material  generated  from  the  January  storm  event  and  the
construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the
evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side
slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell
directly  on  the  liner.    Replacement  of  the  final  piece  of  the  damaged  liner  was
completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is
completed.

3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have
now  been  completed.

                Western  Storm  water  Diversion  Project  (to  render  functional):

                                                                     Diversion  Structure:     The  diversion
                                                                  1)  
                                                                  structure  concrete  work  is  complete.
2)    Box  Culvert:        Rebar  work  on  the  box
                                                         culvert  walls  and  ceiling  is  ongoing.      The
                                                         contractor  continues  assembling  the  wall
                                                         &  ceiling  plate  forms  and  completing  the
                                                         associated  concrete  pours.  
                                                         Approximately  50  feet  remains  to  be
                                                         installed,  which  should  be  completed
                                                         within  two  weeks.

                                                           3)    Pipe:      Backfilling  of  the  HOBAS  pipe
                                                         channel  is  now  complete.

                                                         4)    The  diversion  structure  was
                                                         functionally  complete  per  the  terms  of
                                                         Section  19.b.  of  the  AOC  as  of  February
                                                         15,  2011.

                Cell  6  Leachate  Riser  Restoration:

     20,092  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since
1)          
June 13th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser
restoration  is  complete.

      The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next
2)          
phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction
is  now  complete  to  elevation  450.   This  project  is  completed.

                Sediment  Basin:

1)           This  project  was  physically  complete  on  Thursday  June  9th.    The  documentation
report was  submitted  on  June  15th.

                Evaluating  possible  hydraulic  head  below  liner  system:

1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at
temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  
during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were
not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This
project  is  completed.

               Beach  Assessment  Update:

1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
received  at  the  established  beach  waste  hot  line  during  this  reporting  period.
ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None

ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None

Please  let  me  know  if  you  have  any  questions.    

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From:              Whelan, Joseph
To:                "Tyahla.Stephen@epamail.epa.gov"
Subject:           Request to cease submission of weekly progress reports - WGSL
Date:              Wednesday, June 22, 2011 9:37:00 AM




Hello  Steve,

       The  most  recent  progress  report  noted  that  all  items  under  the AOC  task  list  are  now
complete,  and  we  are  working  on  the  final  documentation  report.    Waste  Management  is
requesting  EPA  approval  to  cease  the submission  of  the  weekly  progress  reports.   The  only
item  that is still uncompleted  is  the  final  50  feet  of  the  box  culvert,  which  is  not  part  of  the
AOC  requirements.   Since  the  report  documenting  completion  of  the  sedimentation  basin
retrofit  was  submitted  on  June  15 th ,  and  the  AOC  requires  submission  of  the  final  report
within  60  days,  WMH  believes  the  final  report  is  due  on  August  14,  2010.    Please  also
acknowledge  that  this  date  is  correct.    Thank  you.



       Best  regards,



       Joe

Joe Whelan
General Manager

Waste Management of Hawaii

808-­668-­2985, ext. 15 Office

808-­668-­1366 Fax

808-­479-­4610 Mobile

 Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov]
Sent: Wednesday, June 22, 2011 1:29 PM
To: Whelan, Joseph
Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; alec.wong@doh.hawaii.gov;
stuart.yamada@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov
Subject: Re: Request to cease submission of weekly progress reports - WGSL

Joe,

Concur with your request to cease submitting Progress Reports.
While we concur that you have substantially completed the sedimentation basin restoration work, we are
gathering what I'll term a punch list of items for you to address. I'm still awaiting some input so am unable
to forward that punch list to you at this time, but should be able to within the next few business days.

Concur that the Final Report, per paragraph 25 of the Order, shall be due on or before 14 August.

Stephen F. Tyahla, P.E.,CHMM
Project Manager, RCRA Corrective Action Office
Waste Management Division
U.S. EPA Region IX
75 Hawthorne Street (WST-5)
San Francisco, CA 94105
Ph. 415.972.3466 / Fax 415.947.3533
tyahla.stephen@epa.gov

[This email, including any attachments, may contain non-public, privileged and/or confidential information
solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an
intended recipient, please delete this email and its attachments immediately. The unauthorized use,
dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]

From:            "Whelan, Joseph" <JWhelan1@wm.com>
To:              Stephen Tyahla/R9/USEPA/US@EPA
Date:            06/22/2011 12:37 PM
Subject:         Request to cease submission of weekly progress reports - WGSL




Hello Steve,

    The most recent progress report noted that all items under the AOC task list are now complete, and we are
working on the final documentation report. Waste Management is requesting EPA approval to cease the
submission of the weekly progress reports. The only item that is still uncompleted is the final 50 feet of the box
culvert, which is not part of the AOC requirements. Since the report documenting completion of the
sedimentation basin retrofit was submitted on June 15th, and the AOC requires submission of the final report
within 60 days, WMH believes the final report is due on August 14, 2010. Please also acknowledge that this date is
correct. Thank you.

        Best regards,

        Joe
 
From:                      Whelan, Joseph
Sent:                      Thursday, August 04, 2011 4:45 PM
To:                        'Kabei.Arlene@epamail.epa.gov'; 'Armann.Steve@epamail.epa.gov';
                           'Vaille.Rich@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov';
                           'Moxley.Bret@epamail.epa.gov'; 'Helmlinger.Andrew@epamail.epa.gov';
                           'Wall.Steve@epamail.epa.gov'; 'stuart.yamada@doh.hawaii.gov';
                           'Steven.chang@doh.hawaii.gov'; 'alec.wong@doh.hawaii.gov'
Subject:                   WGSL Sedimentation Basin Restoration Addendum Report

Greetings all.

        The final individual project report required by the Administrative Order on Consent (AOC), which
documented the restoration of the storm water sedimentation basin was submitted to you on June 15,
2011. WMH received comments from EPA on June 28, 2011. Please find attached the report
documenting additional work performed to address these comments. We would appreciate your
concurrence that this project is now complete. This project report will be included in the final AOC
report to be submitted by August 15, 2011. Please contact me with any questions.


        Best regards,




                               Sedimentation Basin
                                   Repair Add...
        Joe


Joe Whelan
General Manager
Waste Management of Hawaii
808-668-2985, ext. 15 Office
808-668-1366 Fax
808-479-4610 Mobile

Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.
 
 




          Appendix  B  
          Work  Plans  
  




       
 
Waimanalo Gulch Sanitary Landfill
                    Stormwater Management Update and Contingency Plan
                                        1/27/2011
  
         Following  the  recent  major  storm  events,  Waste  Management  of  Hawaii  (WMH)  has  assessed  
and  evaluated  its  stormwater  control  systems  for  effectiveness.  Below  is  an  update  of  ongoing  measures  
being  taken  to  prevent  future  storm  damage  at  the  site,  and  document  efforts  to  further  contain  
potential  storm  water  and  prevent  waste  material  from  exiting  the  facility  in  the  event  of  a  major  storm.  
  
    1) The  36-­‐inch  drain  was  designed  to  handle  water  falling  within  the  landfill  footprint,  upstream  of  
         the  waste  disposal  area,  during  landfilling  operations.    It  was  also  intended  to  mitigate  runon  
         during  small  storms  until  the  diversion  channels  are  in  place.    The  west  side  drainage  channel  
         has  been  designed  to  control  the  100-­‐year  storm  and  will  mitigate  the  impact  of  storms  with  
         higher  return  periods.      
                   The  effectiveness  of  36-­‐inch  inlet  structure  for  the  up  canyon  drainage  system  has  been  
                   restored  and  improved.  The  area  immediately  surrounding  the  inlet  structure  has  been  
                   re-­‐graded  and  armored  with  large  boulders  to  prevent  high  sediment  loading  from  
                   clogging  the  inlet.  A  diversion  berm  immediately  downstream  of  this  diversion  structure  
                   has  been  reinforced  and  re-­‐built  to  further  direct  any  stormwater  into  the  inlet  
                   structure.    
                   The  area  surrounding  the  future  Cell  E-­‐8  is  being  excavated  down  to  the  elevation  of  the  
                   36-­‐inch  pipe  inlet  structure.  This  effort  will  help  to  create  stormwater  retention,  
                   dissipate  stormwater  velocities,  and  drop  out  sediment  as  it  moves  from  the  upper  

                   ongoing  since  1/18.      
  
     2) Establish  a  functioning  Western  Drainage  System.  
                In  order  to  establish  a  functioning  Western  Drainage  System,  the  up  canyon  conveyance  
                structure  must  be  in  place  to  divert  storm  water  into  the  box  culvert  and  fiberglass  
                piping  system.  Additionally,  the  box  culvert  invert  that  originates  at  the  diversion  
                                                                          ss  piping  located  on  the  upper  bench  
                above  Cell  E-­‐
                A  functioning  Western  Drainage  System  will  be  in  place  within  2  weeks,  barring  any  
                additional  large  rainfall  events  that  would  prevent  this  work  from  being  safely  
                completed.        
                  
     3) Temporary  containment  berm  directly  south  of  Cell  E6  
                                                                                         12-­‐19-­‐10  storm  to  contain  
                large  stormwater  flows  originating  from  up  canyon  and  prevent  a  catastrophic  discharge  
                from  the  site.  The  berm  did  safely  contain  this  storm,  and  was  subsequently  
                substantially  reinforced  prior  to  the  storm  that  occurred  on  1-­‐13-­‐11.      The  storm  water  
                that  was  contained  behind  the  berm  has  now  been  removed,  creating  a  storage  area  
                capable  of  containing  water  from  a  similar  rainfall  event.  Preliminary  stability  analysis  
                indicates  the  berm  has  adequate  strength  to  contain  the  runoff.  
                  
  
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
475 - 14th Street, Suite 400
                                                                                                                                            Oakland, California 94612
                                                                                                                                                      PH 510.836.3034
                                                                                                                                                   FAX 510.836.3036
                                                                                                                                                  www.geosyntec.com




31 January 2011


Mr. Richard T. Von Pein, P.E.
Waste Management
9081 Tujunga Avenue
Sun Valley, CA 91352


RE:           Waimanalo Gulch Landfill
              Work Plan for Evaluating Hydraulic Head Below Liner System


Dear Mr. Von Pein:

As requested by Waste Management of Hawaii, Inc. (WMH), Geosyntec Consultants, Inc.
(Geosyntec) has prepared a Work Plan to evaluate the possibility of excess pressure below the
liner system in areas of Cell E6 where water ponded after the storms in December 2010 and
January 2011. This Work Plan is a required element of the “Work” pursuant to Section 19.e of
the Administrative Order on Consent for Removal Action, CERCLA Docket No. 09-20111-
0007/RCRA Docket No. 7003-09-2011-0001.

For reference, the liner system on the side slopes of the expansion area of the Landfill, from
bottom to top, consists of:

              Subgrade;
              Soil cushion layer;
              Encapsulated geosynthetic clay liner (GCL) composite liner system consisting of:
              (i) 40-mil-thick high density polyethylene (HDPE) geomembrane (textured on both
              sides),
              (ii) GCL (reinforced, needle-punched, with 2 nonwoven geotextile carriers), and
              (iii) 60-mil-thick HDPE geomembrane (textured on both sides);
              16-ounce nonwoven cushion geotextile; and
              Operations layer.

For the floor areas, all the components are the same as for the side slopes, except that a 1-foot-
thick gravel layer overlain by a separator nonwoven geotextile is between the cushion geotextile
and the operations layer.




P:PRJ2003GeoWMIWaimanaloWL0770Related to USEPA (2011)Workplan to Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.doc
Mr. Richard T. Von Pein, P.E.
Waimanalo Gulch Landfill
Work Plan for Evaluating Hydraulic Head Below Liner System
31 January 2011
Page 2

WORK PLAN

To evaluate hydraulic head below the liner, the drilling of up to 6 temporary piezometers to
various depths below the existing ground surface is proposed. Figure 1 shows the approximate
locations of the piezometers and a table with the estimated ground elevation and the estimated
drilling depth to reach below the liner level. These drilling depths will need to be confirmed at
the time of drilling to verify that the appropriate elevation will be achieved. Piezometer
locations may be adjusted in the field as needed with concurrence by the engineer.

As can be observed, the piezometers are located around the perimeter of Cell E6. The locations
of the piezometers will need to be located away from buried utilities such as the 18-inch and 36-
inch HDPE surface water conveyance pipes. The borings are planned to be outside the lined area
except where the liner has been damaged and must be replaced. The as-built locations of the
utilities (buried or on the surface) will need to be established before drilling begins.

After the drilling has been performed, and if saturated conditions are encountered, piezometers
will be installed under the supervision of either a geotechnical engineer or a hydrogeologist who
will also monitor the water levels. If saturated conditions are not encountered, the number of
borings/piezometers may be reduced.

DOCUMENTATION

At each temporary piezometer location, documentation should consist of the following:

      1) Water level (if any) at the time of drilling when water first encountered.
      2) Water level after stabilization/construction of any temporary piezometers.
      3) Piezometer construction log (only required if saturated conditions are encountered) (i.e.,
         surveyed ground surface elevation, depth of casing below the ground surface, perforated
         length or gravel pack area, stickup above the ground surface, etc.). The installer of the
         standpipe needs to have an adequate supply of pipe and the ability to maintain it vertical
         to accommodate artesian conditions if encountered.
      4) Photographic documentation of the various piezometers.
      5) Monitoring of water level at each piezometer during a 24-hour period after installation.
         The objective is to record increases, decreases, or no movement of the water level with
         time. If the water level does not change, the piezometer can be decommissioned after 72
         hours or after obtaining approval from the engineer. If hydraulic heads are observed, the
         locations will need to be monitored for longer periods and a plan will need to be prepared
         to relieve these pressures over time.
      6) After the monitoring period is finished, the temporary piezometers will need to be
         decommissioned by filling in the boring with a cement/bentonite mix.
P:PRJ2003GeoWMIWaimanaloWL0770Related To USEPA (2011)Workplan To Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.Doc
Mr. Richard T. Von Pein, P.E.
Waimanalo Gulch Landfill
Work Plan for Evaluating Hydraulic Head Below Liner System
31 January 2011
Page 3


A report summarizing the findings will need to be prepared by the professional under whose
supervision the work was performed. Based on water levels, if any are encountered, WMH will
develop needed remedial measures, which could include temporary extraction wells.

SCHEDULE

Installation of the piezometers will depend on the progress of the ongoing slope excavation and
cleanup of the lower portion of the E-6 cell. At this time, only piezometers PZ-5 and PZ-6 will
be installed. WMH anticipates drilling in this area within 5 days. Due to a potential rockfall
hazard in this area related to the west diversion channel construction, this work will need to be
coordinated with diversion channel construction. As soon as WMH can gain access to the
southern portion of cell E-6, following removal of mud in this area, WMH will drill PZ-1 and if
necessary install a piezometer at this location. WMH anticipates that installation of this boring
would be in approximately 20 days.

If WMH does not encounter water in PZ-1, PZ-5, or PZ-6, no additional borings would be
completed. If needed, PZ-2, PZ-3 and PZ-4 would be installed after loose rock is removed from
the slopes above this area. WMH anticipates that completion of the western diversion channel
and removal of loose rock from the slope will take approximately 45 days.

Please contact us if there are further questions.

Sincerely yours,




Hari D. Sharma, Ph.D., P.E.
Principal

ATTACHMENT

Figure 1 – Proposed Temporary Piezometer Locations

COPY TO

Mr. Joseph Whelan (WMH)
Mr. Jesse Frey (WMH)


P:PRJ2003GeoWMIWaimanaloWL0770Related To USEPA (2011)Workplan To Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.Doc
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
 
Beach Assessment and Recovery - 19(i)




EPA Order:     WM shall provide to EPA and DOH a work plan and schedule for ongoing daily beach
assessment and recovery of waste material released from WGSL.




In response to the stormwater release that carried waste material from the WGSL on January 13, 2011,
WM has implemented a beach assessment and cleanup. On January 13,2010, "Potentially
Contaminated Water" warning signs were posted near the outfall and the surrounding beaches by the
City and County of Honolulu. The initial assessment on January 14, 2011 was focused on the stormwater
outfall that carries the waters of the WGSL drainage basin. WM continued assessment on January 15 at
the outfall and on January 16, WM began covering several nearby beaches that had reports of observed
waste. WM performed daily assessments and cleanup as necessary daily until January 21, 2011 and
because the amount of waste observed diminished drastically, suspended the daily assessment. On
January 24, WM performed one final assessment and observed no waste that could have been
attributed to the WGSL. WM will continue to respond and track reports of waste on the nearby beaches.
Attached is a log of recovered waste from the beaches and the WGSL outfall and a log of phone reports
of waste.
MEDICAL WASTE SIGHTING lOG:

                                   PHONE 1/                  WHEN, WHAT AND WHERE SEEN

                                                  1/16/11 seen a syringe on the beach in Nanakulu
1/17/2011      Sue Ellen           673-1922       directly across Hakimo Rd.

                                                  1/17/11 seen syringes and cotton at all 4 lagoons at
1/17/2011     John Merritt         864-7482       Ko'Olina


                                                  1/17/11 seen syringes with and without needles and
1/18/2011       Lawton             368-2004       some sediment at Ko'Olina lagoon 3



                                                  1/20/11 seen a syringe without needle on beach
1/20/2011   Wayne Yamamoto         388-1236       fronting Paradise Cove ... prefers not to handle himself




                                                1/17/11lifegaurds at Pokai Bay found 4 -5 syringes ... he
                                                heard from a reliable source of his that medical waste
                                                trucks were seen dumping their waste in sewer lines in
                               696-3069 or 333- Maile and Pokai Bay ... is that true? AWould like to
1/24/2011    Charles Lopez
                                     7075       know if the City has documentation regarding disposal
                                                whereabouts? Why were no signs posted at Pokai Bay
                                                that beach was closed, there were signs at the Army
                                                Rest Camp Beach a couple miles away? Army Rest
                                                Camp took samples and found lots of bacteria. He tried
                                                  contacting City via phone/email ... got no response.



                                                  Someone (Carroll Cox) reported seeing medical waste at
1/26/2011     Lene of DOH          586-4226
                                                  WGSL stormwater outlet at Ko'Olina ... don't know when
                                                  it was seen or if it had already been cleaned-up.
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Beach Assessment and Recovery –– 19(i)


EPA Order: WM shall provide to EPA and DOH a work plan and schedule for ongoing daily
beach assessment and recovery of waste material released from WGSL.



WM Response:            In response to the stormwater release that carried waste material from
the WGSL on January 13, 2011, WM implemented a beach assessment and cleanup program.
On January 13, 2010, ““Potentially Contaminated Water”” warning signs were posted near the
outfall and the surrounding beaches by the City and County of Honolulu. The initial assessment
on January 14, 2011 was focused on the stormwater outfall that carries the waters of the WGSL
drainage basin. WM continued assessment on January 15 at the outfall and on January 16, WM
began covering several nearby beaches that had reports of observed waste. On January 16, WM
set up a hotline to enable the public to report waste observed on the beaches near the landfill
to the proper personnel for cleanup. This hotline remains active and the phone number is
directed to our landfill office receptionist. The receptionist maintains a call log to document
incoming calls. WM performed daily assessments and cleanup of all identified beaches until
January 21, 2011, at which time the amount of waste observed diminished drastically, and the
daily assessment was suspended. On January 24, WM performed one final assessment and
observed no waste that could have been attributed to the WGSL. WM continues to respond and
track reports of waste on the nearby beaches. Attached is a log of recovered waste from the
beaches and the WGSL outfall (Attachment 1) and a log of phone reports of waste (Attachment
2). WM will also report via email as part of the Daily Progress Report to the EPA and DOH any
response performed by our staff or authorized parties on beaches or shorelines in response to
either reports received or any WM inspections.
 
Attachment 1
 
Waimanalo Gulch Sanitary Landfill
                                                       Storm Response Beach Cleanup Summary Log


                                                                                         Debris/Typical Ocean Trash (No.
 Date                                    Location                                               of 40 gallon bags)           Medical Waste
13 Jan               Stormwater Sampling, and Warning Signs Placed                                       0                           0
14 Jan                          WGSL Storm Drain Outlet                                                 20                 1 gallon bucket full
15 Jan                          WGSL Storm Drain Outlet                                                 10                  2 syringes, 1 vial
16 Jan                              White Plains Beach                                                   5                      1 syringe
16 Jan                          WGSL Storm Drain Outlet                                                 0.5                     7 syringes
17 Jan                              White Plains Beach                                                   2                  2 syringes, 1 vial
17 Jan                      White Plains Beach/Nimitz Beach                                              1                      2 syringes
18 Jan                                   Pokai Bay                                                       0                           0
18 Jan                      White Plains Beach/Nimitz Beach                                              4                           0
18 Jan                      White Plains Beach/Nimitz Beach                                             10                      2 syringes
19 Jan                      White Plains Beach/Nimitz Beach                                              0                      1 syringe
19 Jan                                   Pokai Bay                                                       0                           0
19 Jan             Kahe Beach/Tracks/WGSL Discharge/HECO Discharge                                       0                   1 syringe, 1 vial
20 Jan             Kahe Beach/Tracks/WGSL Discharge/HECO Discharge                                       0                           0
20 Jan                           Ko'Olina (Paradise Cove)                                                0                      1 syringe
20 Jan                      White Plains Beach/Nimitz Beach                                              0                           0
21 Jan                      White Plains Beach/Nimitz Beach                                              0                           0
21 Jan             Kahe Beach/Tracks/WGSL Discharge/HECO Discharge                                       0                           0
24 Jan     Kahe Beach/Tracks/WGSL Discharge/HECO Discharge/Paradise Cove                                 0                           0
24 Jan                      White Plains Beach/Nimitz Beach                                              0                           0
26 Jan   WGSL Storm Drain Outlet (at request of DOH in response to personal report)                      0                           0
 3 Feb                     KoOlina Lagoon #4 (response to call)                                          0                      6 syringes
18 Feb                     KoOlina Lagoon #4 (response to call)                                          0                           0
 
Attachment 2
 
MEDICAL WASTE SIGHTING LOG:
  DATE               NAME                REPRESENTING / PHONE #                  WHEN, WHAT AND WHERE SEEN
                                                                    Reported that lifeguard at White Plains Beach found 2
1/14/2011         Arlene Kabai                 EPA Region 9         syringes in the water.

                                                                    Reported that lifeguard at White Plains Beach found
                                                                    syringes that had washed onshore. Joe Whelan called
                                                                    lifeguard (Moku) who found 6 syringes w/o needles and
1/15/2011         Arlene Pang               State of HI AG Office   2 needles

                                                                    Got call regarding syringes found at Pokai Bay. Turned
1/17/2011      Terrence Johnson                     EPA             them in to Tulsi Gabbard.

                                                                    1/16/11 seen a syringe on the beach in Nanakulu
1/17/2011           Sue Ellen                    673 1922           directly across Hakimo Rd.

                                                                    1/17/11 seen syringes and cotton at all 4 lagoons at
1/17/2011         John Merritt                   864 7482           Ko'Olina

                                                                    1/17/11 seen syringes with and without needles and
                                                                    some sediment at Ko'Olina lagoon 3 (Found to be clean
1/17/2011           Lawton                       368 2004           needles)


                                                                    1/20/11 seen a syringe without needle on beach
1/20/2011      Wayne Yamamoto                    388 1236           fronting Paradise Cove …… prefers not to handle himself




                                                                    1/17/11 lifegaurds at Pokai Bay found 4 5 syringes …… he
                                                                    heard from a reliable source of his that medical waste
                                                                    trucks were seen dumping their waste in sewer lines in
                                                                    Maile and Pokai Bay …… is that true? AWould like to know
1/24/2011        Charles Lopez            696 3069 or 333 7075
                                                                    if the City has documentation regarding disposal
                                                                    whereabouts? Why were no signs posted at Pokai Bay
                                                                    that beach was closed, there were signs at the Army
                                                                    Rest Camp Beach a couple miles away? Army Rest Camp
                                                                    took samples and found lots of bacteria. He tried
                                                                    contacting City via phone/email ... got no response.


                                                                    Someone (Carroll Cox) reported seeing medical waste at
1/26/2011         Lene of DOH                    586 4226
                                                                    WGSL stormwater outlet at Ko'Olina …… don’’t know when
                                                                    it was seen or if it had already been cleaned up.
                                                                    medical waste found by lagoon 4 , items not confirmed.
                                                                    Nat called Left mssg. For Caroline WM will be onsite to
1/31/2011 Caroline KoOlina sports clu            679 3723           search for more waste.

                                                                    2/2/11 syringe without needle (he has it) seen at
                                                                    Ko'olina jetty at lagoon 4 in front of the marina. Also
                                                                    reports seeing a lot of garbage (he's thinks may have
                                                                    come from landfill) along the shore line. Rick confirmed
                                                                    medical at location + rubbish mixed, he brought 3/4 of
  2/3/2011 Sam/Sue Rakes                512 250 8141                trash bag back to site.

                                                                    found 2 more syringes at lagoon 4 area LM on VM; Smith
                                                                    arrived to Ko'Olina on 2/18, Sam confirm he threw away
2/15/2011 Sam Rakes                     512 250 8141                already.
 
Collection and Transport of Liquid Behind Temporary Berm –– Order 19 (d)


EPA Order:      WM shall continue to collect and transport to a local treatment facility the liquids
retained behind the temporary berm in cell E6. WM shall provide a written description of the
collection and treatment activities, the current permitting and the chemical parameters of the liquids,
and transportation methods to the local treatment facility.

WM Response: WM began removing storm water that was stored behind the temporary berm in cell
E6 via tanker trucks and transported the water to permitted treatment facilities operated by the City
and County of Honolulu on January 19, 2011. Attached is a copy of sample results from the storm water
collected at the sediment pond outfall on January 13th (Attachment 1). Also attached is a summary copy
of the hauling logs that detail the volume of transported liquid, and the name of the waste water
treatment plant (Attachment 2). WM is unaware of any pretreatment standards for discharging
stormwater to these wastewater treatment plants. Samples from the sediment basin were also
collected on February 2, 2010 and those results are summarized in an attached table (Attachment 3).

 After removing the water impounded behind the temporary berm, some amount of mud and sediment
remained near the E6 sump area. This mud was not solid enough to load out and haul away, so liquid is
skimmed off from the mud surface with a vacuum truck to help facilitate the removal of the remaining
mud material.

The remaining sediment will be excavated and hauled to a bermed area on the landfill so that it can dry.
The attached figure shows the location where this sediment is being stored (Attachment 4). Each area is
located within lined areas of the MSW portion of the landfill.

Samples of the sediment were collected to determine its ultimate use in the landfill. Results of those
samples were compared to our solid waste permit requirements, and the soil has been approved for use
as daily cover. The laboratory report from those samples is attached (Attachment 5). Some of the
remaining sediment will be placed in several 20,000 gallon mobile storage tanks to attempt to separate
the liquid phase from the sediment phase of the material. Any liquid removed through this process will
be hauled via a third party hauling company to a County of Honolulu permitted wastewater treatment
plant. This process will continue until all recoverable sediment and liquids are removed.
 
Attachment 1
 
Waimanalo Gulch Sanitary Landfill Storm Water Monitoring
                                 13 January 2011 Discharge Event
                               Laboratory Final Data Summary Table

        Method             Analyte             Unit       Screening       Benchmark        CULVERT
                                                                     a            b
                                                          Criteria          Level
1664A              HEM (Oil and Grease)        mg/L           15               15               5.1
                   Alpha Terpineol             mg/L         0.016              NA             < 0.01
                   Benzoic acid                mg/L         0.071              NA             < 0.05
40CFR136A 625      p Cresol                    mg/L         0.014              NA             < 0.01
                   Pentchlorophenol            mg/L          0.02              NA          < 0.021 *
                   Phenol                      mg/L         0.015              1.0            < 0.01
                   Arsenic                     mg/L          0.36           0.16854          < 0.015
                   Cadmium                     mg/L         0.003           0.0159        < 0.00045 *
                   Calcium                     mg/L           NA               NA               24
                   Iron                        mg/L           1.0              1.0              8.6
                   Lead                        mg/L         0.029           0.0816          0.0034 J
EPA 200.7 Rev 4.4 Magnesium                    mg/L           NA            0.0636              13
                   Potassium                   mg/L           NA               NA                7
                   Selenium                    mg/L          0.02           0.2385          0.0078 J
                   Silver                      mg/L         0.001           0.0318        < 0.00093 *
                   Sodium                      mg/L           NA               NA              73 B
                   Zinc                        mg/L         0.022            0.117           0.017 J
EPA 245.1          Mercury                     mg/L        0.0024            0.0024         < 0.0002
EPA 7196           Hexavalent Chromium         µg/L           16               NA              < 10
EPA 365.1          Phosphorus, Total           mg/L           NA               2.0           0.38 B
MCAWW 350.1        Ammonia                     mg/L           4.9              19              0.11
MCAWW 353.2        Nitrate Nitrite as Nitroge mg/L            NA              0.68              2.9
EPA Total Nitrogen Nitrogen, Total             mg/L           NA               NA               4.8
EPA 405.1          BOD (5 Day)                 mg/L           NA               30              8.91
MCAWW 410.4        Chemical Oxygen Deman       mg/L           NA              120               45
SM 2540D           Total Suspended Solids      mg/L          100              100               57
MCAWW 300.0A       Bromide                     mg/L           NA               NA              0.73
                   Chloride                    mg/L           NA              860               95
                   Sulfate                     mg/L           NA               NA              45 B
SM 2320B           Bicarbonate Alkalinity      mg/L           NA               NA               77
                   Carbonate Alkalinity        mg/L           NA               NA               <5
                   Total Alkalinity            mg/L           NA               NA               77
Bac T              Total Coliform            MPN/100 mL       NA               NA            > 1,600
                   E. coli                   MPN/100 mL       NA               NA              < 2.0
Field Method       pH                           SU         5.5 8.0          6.0 9.0            8.14

Note:
          a        screening criteria are based on the requirements in the Waimanalo Gulch Storm Water Discharge Permit
          b        benchmark levels are developed by EPA for storm water discharge
           <       not detected above the reporting limits
           >       greater than
          *        not detected above the method detection limits
         µg/L      micrograms per liter
         mg/L      milligrams per liter
           B       compound was found in the blanks (0.221 J mg/L for Sodium, 0.0115 J mg/L for Total Phosphorus; and 0.245 J mg/L for Sulfate)
         BOD       biochemical oxygen demand
         HEM       n hexane extractable material
          NA       no limitation at this time
           J       estimated result is less than the reporting limit but greater than or equal to the method detection limit
          SU       standard unit
Removal Action Summary Report (pages 1-1015)
Attachment 2
 
Waimanalo Gulch Sanitary Landfill
Stormwater from Behind Temporary Berm Below the E6 Cell
                 Pumping Log Summary

                             Volume
         Date     Waianae     Kailua     Total
      1/13/2011      0           0            0
      1/14/2011      0           0            0
      1/15/2011      0           0            0
      1/16/2011      0           0            0
      1/17/2011      0           0            0
      1/18/2011   150,000    45,000     195,000
      1/19/2011   150,000    72,000     222,000
      1/20/2011   148,000        0      148,000
      1/21/2011   136,000    79,000     215,000
      1/22/2011   150,000    68,300     218,300
      1/23/2011
       / /        132,000
                     ,       11,000
                                ,       143,000
                                           ,
      1/24/2011      0           0            0
      1/25/2011      0       21,867      21,867
      1/26/2011      0           0            0
      1/27/2011      0           0            0
      1/28/2011      0           0            0
      1/29/2011      0           0            0
      1/30/2011      0       22 000
                             22,000      22 000
                                         22,000
      1/31/2011      0       16,500      16,500
      2/1/2011       0       16,500      16,500
      2/2/2011       0       22,000      22,000
      2/3/2011       0           0            0
      2/4/2011       0           0            0
      2/5/2011       0           0            0
      2/6/2011       0           0            0
      2/7/2011       0           0            0
      2/8/2011       0           0            0
      2/9/2011       0           0            0
      2/10/2011      0       11,000      11,000
      2/11/2011      0           0            0
      2/12/2011      0       28 318
                             28,318      28 318
                                         28,318
      2/13/2011      0       21,000      21,000
      2/14/2011      0       14,159      14,159
      2/15/2011      0       70,005      70,005
      2/16/2011      0       48,430      48,430
      2/17/2011      0       50,034      50,034
      2/18/2011      0       34,000      34,000
      2/19/2011      0           0            0
      2/20/2011      0           0            0
      2/21/2011      0           0            0
      2/22/2011      0           0            0
      2/23/2011      0           0            0

         Total    866,000    651,113   1,517,113
 
Attachment 3
 
Waimanalo Gulch Sanitary Landfill Sediment Pond Water Sample
                                                    Collected on 2/2/2011
                                                     Laboratory Final Data Summary Table
Method               Analyte                              Unit         Screening Criteria
                                                                                          a
                                                                                                     Benchmark Level b           SED POND
1664A                HEM (Oil and Grease)                   mg/L                    15                         15                     2J
                     Alpha Terpineol                        mg/L                  0.016                        NA                   < 0.01
                     Benzoic acid                           mg/L                  0.071                        NA                   < 0.05
40CFR136A 625        p Cresol                               mg/L                  0.014                        NA                   < 0.01
                     Pentchlorophenol                       mg/L                   0.02                        NA                 < 0.021 *
                     Phenol                                 mg/L                  0.015                         1                   < 0.01
                     Arsenic                                mg/L                   0.36                     0.16854                0.0057 J
                     Cadmium                                mg/L                  0.003                     0.0159                 < 0.005
                     Calcium                                mg/L                    NA                         NA                     48
                     Iron                                   mg/L                     1                          1                     4.6
                     Lead                                   mg/L                  0.029                     0.0816                 < 0.009
EPA 200.7 Rev 4.4    Magnesium                              mg/L                    NA                       0.0636                   25
                     Potassium                              mg/L                    NA                         NA                     5.8
                     Selenium                               mg/L                   0.02                     0.2385                 < 0.015
                     Silver                                 mg/L                  0.001                     0.0318               < 0.00093 *
                     Sodium                                 mg/L                    NA                         NA                    110
                     Zinc                                   mg/L                  0.022                      0.117                  0.019 J
EPA 245.1            Mercury                                mg/L                  0.0024                    0.0024               0.000055 J
EPA 7196             Hexavalent Chromium                    µg/L                    16                        NA                     < 10
EPA 365.1            Phosphorus, Total                      mg/L                    NA                         2                     0.21
MCAWW 350.1          Ammonia                                mg/L                    4.9                       19                     0.3 B
MCAWW 353.2          Nitrate Nitrite as Nitrogen            mg/L                    NA                       0.68                   0.072 J
EPA Total Nitrogen   Nitrogen, Total                        mg/L                    NA                        NA                      1.9
EPA 405.1            BOD (5 Day)                            mg/L                    NA                        30                     4.18
MCAWW 410.4          Chemical Oxygen Demand                 mg/L                    NA                        120                     36
SM 2540D             Total Suspended Solids                 mg/L                    100                       100                     26
MCAWW 300.0A         Bromide                                mg/L                    NA                        NA                     0.85
                     Chloride                               mg/L                    NA                        860                    120
                     Sulfate                                mg/L                    NA                        NA                     110
SM 2320B             Bicarbonate Alkalinity                 mg/L                    NA                        NA                     170
                     Carbonate Alkalinity                   mg/L                    NA                        NA                     4.7 J
                     Total Alkalinity                       mg/L                    NA                        NA                     170
Bac T                Total Coliform                      MPN/100 mL                 NA                        NA                      170
                     E. coli                             MPN/100 mL                 NA                        NA                     < 2.0
Field Method         pH                                      SU                   5.5 8.0                   6.0 9.0                 7.22



Note:
            a        screening criteria are based on the requirements in the Waimanalo Gulch Storm Water Discharge Permit
            b        benchmark levels are developed by EPA for storm water discharge
         Bold        exceed screening criteria
           <         not detected above the reporting limits
          *          not detected above the method detection limits
         µg/L        micrograms per liter
         mg/L        milligrams per liter
           B         compound was found in the method blank (0.0241 J mg/L for Ammonia)
         BOD         biochemical oxygen demand
         HEM         n hexane extractable material
         MPN         most probable number
          NA         no limitation at this time
           J         estimated result is less than the reporting limit but greater than or equal to the method detection limit
          SU         standard unit
Removal Action Summary Report (pages 1-1015)
Attachment 4
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Attachment 5
 
ANALYTICAL REPORT
                                                  Job Number: 280-12120-1
                                        Job Description: 995|Waimanalo Gulch LF

                                                             For:
                                                     Waste Management
                                                   Waimanalo Gulch Landfill
                                                  92-460 Farrington Highway
                                                      Kapolei, HI 96707
                                                  Attention: Mr. Justin Lottig




                                                                                                     Approved for release.
                                                                                                     Betsy A Sara
                                                                                                     Project Manager II

                              _____________________________________________                          2/16/2011 1:05 PM




                                                       Betsy A Sara
                                                     Project Manager II
                                              betsy.sara@testamericainc.com
                                                        02/16/2011

cc:   Mr. John Fong
      Mr. Pete LaPlaca


 The test results in this report relate only to the samples in this report and meet all requirements of NELAC, with any
 exceptions noted. Pursuant to NELAP, this report shall not be reproduced except in full, without the written approval of
 the laboratory. All questions regarding this report should be directed to the TestAmerica Denver Project Manager.



 The Lab Certification ID# is E87667.



 Reporting limits are adjusted for sample size used, dilutions and moisture content if applicable.




 TestAmerica Laboratories, Inc.
 TestAmerica Denver 4955 Yarrow Street, Arvada, CO 80002
 Tel (303) 736-0100 Fax (303) 431-7171 www.testamericainc.com


                                                          Page 1 of 110
Table of Contents
Cover Title Page . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Report Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .     3
Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .          5
Method Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .         8
Method / Analyst Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Sample Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .         10
Sample Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Sample Datasheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Data Qualifiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .    58
QC Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   59
Qc Association Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             60
Surrogate Recovery Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .              67
Qc Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   73
Laboratory Chronicle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
Client Chain of Custody . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .          108
Sample Receipt Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110




                                                 Page 2 of 110


                                                                    

                                                             

                                                                





























































                                                                       Page 3 of 110





































                                                                      Page 4 of 110


                                                         




                           
                                                     


        
                                                                  
                                        
                                               
                                            
                                                                        
                                                                     
                                                                       
                                                           
                                                                      
                                                                      
                                                                      
                                                                    
                                                                      
                                                                  
                                                                 
                                                            
                                                             
                                                                        
                                                               
                                                           
                                                                    
                                                            
                                                                  
                                                          
                                                                       
                                               
                                                                     
                                                                      
                                                                       
                                                                  
                                                                          
                                                                     
                                                                     
                                                                        
                                                                        
                                                                         
                                                                 
                                                                       
                                                                     
                                                                     
                                                                        
                                                                       
                                                                 


                                                                 






                                                  Page 5 of 110


                                                         




                           
                                                     


          
                                        
                                              
                                             
                                                           
                                                                   
                                                                   
                                                                        
                                                                  
                                                                        
                                                                   
                                                                      
                                                                        
                                                                        
                                                                        
                                                                        
                                                                     
                                                                         
                                                                        
                                                                 



          
                                                                   
                                     
                                              
                                             
                                                           
                                                                   
                                                                        
                                                                  
                                                                        
                                                                   
                                                                      
                                                                        
                                                                        
                                                                        
                                                                        
                                                                      
                                                                         
                                                                        
                                                                 






                                                  Page 6 of 110


                                                         




                           
                                                     


          
                                        
                                              
                                             
                                                           
                                                                    
                                                                        
                                                                   
                                                                        
                                                                   
                                                                      
                                                                        
                                                                        
                                                                        
                                                                        
                                                                      
                                                                         
                                                                        
                                                                 



          
                                     
                                              
                                             
                                                                
                                                           
                                                                   
                                                                   
                                                                        
                                                                  
                                                                        
                                                                   
                                                                      
                                                                        
                                                                        
                                                                        
                                                                        
                                                                      
                                                                         
                                                                        
                                                                 






                                                  Page 7 of 110


                                                                                       

                                                                           
   

                                             
                                                                     

                                                 
                                                                                   

                                               
                                                                            

                                                 
                                                                            

                         
                                                                            

                                                                
                                                                          

                                                                   
                                                                             

                                                                   
                                                                                  
                                                                       

                                                                 
                                                                             

                                                               














                                         Page 8 of 110


                                   




                                                         

                                        

                                          

                                        

                                              

                                         

                                               

                                             

                                              

                                         






                                  Page 9 of 110


                                                   

                                                                             
                                     
                                                
                                                 
                                                 
                                                 
                                                 




                       Page 10 of 110







                        Page 11 of 110


                                                                                   


       

                                                                                
                                                                         

                                             

                                                               
                                                                 
                                                                                
                                                                
       

                                                                   
                                                                                                      
                                                                                                    
                                                                                                           
                                                                                                
                                                                                              
                                                                                                         
                                                                                                      
                                                                                                 
                                                                                              
                                                                                                  
                                                                                              
                                                                                                     
                                                                                              
                                                                                                      
                                                                                                        
                                                                                                     
                                                                                      
                                                                                                    
                                                                                              
                                                                                               
                                                                                               
                                                                                       
                                                                                                
                                                                                                
                                                                                            
                                                                                          
                                                                                                
                                                                                               
                                                                                           
                                                                                         
                                                                                        
                                                                                                      
                                                                                                       
                                                                                                       
                                                                                                
                                                                                      
                                                                                           
                                                                                                       
                                                                                                           
                                                                                         
                                                                                         
                                                                                                 
                                                                                                           
                                                                                             
                                                                                             
                                                                                                   

                                      Page 12 of 110


                                                                                       


        

                                                                                   
                                                                            

                                                

                                                                  
                                                                    
                                                                                   
                                                                   
       

                                                                       
                                                                                                
                                                                                                
                                                                                                        
                                                                                                        
                                                                                                        
                                                                                                     

                                                                                     
                                                                             
                                                                                        
                                                                              
                                                                              




                                         Page 13 of 110


                                                                                   


       

                                                                                  
                                                                         

                                             

                                                               
                                                                 
                                                                                
                                                                
       

                                                                   
                                                                                                          
                                                                                                    
                                                                                                           
                                                                                                
                                                                                              
                                                                                                         
                                                                                                      
                                                                                                 
                                                                                              
                                                                                                  
                                                                                              
                                                                                                     
                                                                                              
                                                                                                      
                                                                                                        
                                                                                                     
                                                                                      
                                                                                                    
                                                                                              
                                                                                               
                                                                                               
                                                                                       
                                                                                                
                                                                                                
                                                                                            
                                                                                          
                                                                                                
                                                                                               
                                                                                           
                                                                                         
                                                                                        
                                                                                                      
                                                                                                       
                                                                                                       
                                                                                               
                                                                                      
                                                                                           
                                                                                                       
                                                                                                           
                                                                                         
                                                                                         
                                                                                                 
                                                                                                           
                                                                                             
                                                                                             
                                                                                                   

                                      Page 14 of 110


                                                                                       


        

                                                                                     
                                                                            

                                                

                                                                  
                                                                    
                                                                                   
                                                                   
       

                                                                       
                                                                                                
                                                                                                
                                                                                                        
                                                                                                        
                                                                                                        
                                                                                                     

                                                                                     
                                                                             
                                                                                        
                                                                              
                                                                              




                                         Page 15 of 110


                                                                                   


       

                                                                                  
                                                                         

                                             

                                                               
                                                                 
                                                                                
                                                                
       

                                                                   
                                                                                                       
                                                                                                    
                                                                                                           
                                                                                                
                                                                                              
                                                                                                         
                                                                                                      
                                                                                                 
                                                                                              
                                                                                                 
                                                                                              
                                                                                                     
                                                                                              
                                                                                                      
                                                                                                        
                                                                                                     
                                                                                      
                                                                                                    
                                                                                              
                                                                                               
                                                                                               
                                                                                       
                                                                                                
                                                                                                
                                                                                            
                                                                                          
                                                                                                
                                                                                               
                                                                                           
                                                                                         
                                                                                        
                                                                                                      
                                                                                                       
                                                                                                       
                                                                                               
                                                                                      
                                                                                           
                                                                                                       
                                                                                                           
                                                                                         
                                                                                         
                                                                                                 
                                                                                                           
                                                                                             
                                                                                             
                                                                                                   

                                      Page 16 of 110


                                                                                       


        

                                                                                     
                                                                            

                                                

                                                                  
                                                                    
                                                                                   
                                                                   
       

                                                                       
                                                                                                
                                                                                                
                                                                                                        
                                                                                                        
                                                                                                        
                                                                                                     

                                                                                     
                                                                             
                                                                                        
                                                                              
                                                                              




                                         Page 17 of 110


                                                                                   


       

                                                                                  
                                                                         

                                             

                                                               
                                                                 
                                                                                
                                                                
       

                                                                   
                                                                                                         
                                                                                                    
                                                                                                          
                                                                                               
                                                                                             
                                                                                                         
                                                                                                     
                                                                                                 
                                                                                              
                                                                                                 
                                                                                              
                                                                                                     
                                                                                              
                                                                                                     
                                                                                                       
                                                                                                    
                                                                                      
                                                                                                    
                                                                                              
                                                                                              
                                                                                               
                                                                                      
                                                                                               
                                                                                                
                                                                                            
                                                                                         
                                                                                               
                                                                                              
                                                                                           
                                                                                        
                                                                                        
                                                                                                      
                                                                                                       
                                                                                                       
                                                                                               
                                                                                      
                                                                                          
                                                                                                      
                                                                                                           
                                                                                         
                                                                                         
                                                                                                 
                                                                                                          
                                                                                             
                                                                                             
                                                                                                   

                                      Page 18 of 110


                                                                                       


        

                                                                                     
                                                                            

                                                

                                                                  
                                                                    
                                                                                   
                                                                   
       

                                                                       
                                                                                               
                                                                                               
                                                                                                        
                                                                                                        
                                                                                                       
                                                                                                     

                                                                                     
                                                                             
                                                                                       
                                                                             
                                                                             




                                         Page 19 of 110


                                                                                   


       

                                                                                  
                                                                         

                                             

                                                               
                                                                 
                                                                                
                                                                
       

                                                                   
                                                                                                          
                                                                                                    
                                                                                                           
                                                                                                
                                                                                              
                                                                                                         
                                                                                                      
                                                                                                 
                                                                                              
                                                                                                  
                                                                                              
                                                                                                     
                                                                                              
                                                                                                      
                                                                                                        
                                                                                                     
                                                                                      
                                                                                                    
                                                                                              
                                                                                               
                                                                                               
                                                                                       
                                                                                                
                                                                                                
                                                                                            
                                                                                          
                                                                                                
                                                                                               
                                                                                           
                                                                                         
                                                                                        
                                                                                                      
                                                                                                       
                                                                                                       
                                                                                               
                                                                                      
                                                                                           
                                                                                                       
                                                                                                           
                                                                                         
                                                                                         
                                                                                                 
                                                                                                           
                                                                                             
                                                                                             
                                                                                                   

                                      Page 20 of 110


                                                                                       


        

                                                                                     
                                                                            

                                                

                                                                  
                                                                    
                                                                                   
                                                                   
       

                                                                       
                                                                                                
                                                                                                
                                                                                                        
                                                                                                        
                                                                                                        
                                                                                                     

                                                                                     
                                                                             
                                                                                        
                                                                              
                                                                              




                                         Page 21 of 110


                                                                                     


           

                                                                                 
                                                                          

                                                 

                                                                
                                                       
                                                                                   
                                                                    
                                                                         

                                                                     
                                                                            

                                                                                   
                                                                                 




                                      Page 22 of 110


                                                                                     


           

                                                                                   
                                                                          

                                                 

                                                                
                                                       
                                                                                   
                                                                    
                                                                         

                                                                     
                                                                            

                                                                                   
                                                                                 




                                      Page 23 of 110


                                                                                     


           

                                                                                   
                                                                          

                                                 

                                                                
                                                       
                                                                                   
                                                                    
                                                                         

                                                                     
                                                                         

                                                                                   
                                                                                 




                                      Page 24 of 110


                                                                                     


           

                                                                                   
                                                                          

                                                 

                                                                
                                                       
                                                                                   
                                                                    
                                                                         

                                                                     
                                                                            

                                                                                   
                                                                                




                                      Page 25 of 110


                                                                                     


           

                                                                                   
                                                                          

                                                 

                                                                
                                                       
                                                                                   
                                                                    
                                                                         

                                                                     
                                                                         

                                                                                   
                                                                                 




                                      Page 26 of 110


                                                                                        


       

                                                                                    
                                                                             

                                                  

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                      
                                                                                   

                                                                                      
                                                                                               
                                                                                             




                                        Page 27 of 110


                                                                                        


       

                                                                                      
                                                                             

                                                  

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                     
                                                                                    

                                                                                      
                                                                                               
                                                                                              




                                        Page 28 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                  

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                     
                                                                                   

                                                                                     
                                                                                              
                                                                                             




                                        Page 29 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                  

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                     
                                                                                    

                                                                                     
                                                                                              
                                                                                             




                                        Page 30 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                  

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                     
                                                                                   

                                                                                     
                                                                                              
                                                                                             




                                        Page 31 of 110


                                                                                      


       

                                                                                  
                                                                           

                                                   

                                                                 
                                                        
                                                                                     
                                                                     
                                                                          

                                                                      
                                                                                                              
                                                                                                           
                                                                                                             
                                                                                                 
                                                                                                            
                                                                                                            
                                                                                                            
                                                                                                          
                                                                                                            
                                                                                                        
                                                                                                       
                                                                                                  
                                                                                                   
                                                                                                              
                                                                                                     
                                                                                                 
                                                                                                          
                                                                                                  
                                                                                                        
                                                                                                
                                                                                                           

                                                                                    
                                                                                 
                                                                                   




                                        Page 32 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                   

                                                                  
                                                         
                                                                                     
                                                            
                                                                           

                                                                       
                                                                                                              
                                                                                                           
                                                                                                            
                                                                                                 
                                                                                                            
                                                                                                            
                                                                                                            
                                                                                                           
                                                                                                         
                                                                                                        
                                                                                                       
                                                                                                  
                                                                                                   
                                                                                                              
                                                                                                     
                                                                                                 
                                                                                                          
                                                                                                  
                                                                                                        
                                                                                                   
                                                                                                             

                                                                                     
                                                                                   
                                                                                     




                                        Page 33 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                   

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                                              
                                                                                                           
                                                                                                            
                                                                                                 
                                                                                                            
                                                                                                            
                                                                                                            
                                                                                                           
                                                                                                         
                                                                                                        
                                                                                                       
                                                                                                  
                                                                                                   
                                                                                                              
                                                                                                     
                                                                                                 
                                                                                                          
                                                                                                  
                                                                                                        
                                                                                                   
                                                                                                             

                                                                                     
                                                                                   
                                                                                     




                                        Page 34 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                   

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                                              
                                                                                                           
                                                                                                             
                                                                                                 
                                                                                                             
                                                                                                            
                                                                                                             
                                                                                                            
                                                                                                          
                                                                                                        
                                                                                                       
                                                                                                  
                                                                                                   
                                                                                                              
                                                                                                     
                                                                                                  
                                                                                                          
                                                                                                   
                                                                                                         
                                                                                                   
                                                                                                             

                                                                                     
                                                                                   
                                                                                     




                                        Page 35 of 110


                                                                                       


       

                                                                                     
                                                                            

                                                   

                                                                  
                                                         
                                                                                     
                                                                      
                                                                           

                                                                       
                                                                                                              
                                                                                                      
                                                                                                            
                                                                                                 
                                                                                                            
                                                                                                            
                                                                                                            
                                                                                                           
                                                                                                         
                                                                                                        
                                                                                                       
                                                                                                  
                                                                                                   
                                                                                                              
                                                                                                     
                                                                                                 
                                                                                                          
                                                                                                  
                                                                                                        
                                                                                                   
                                                                                                             

                                                                                     
                                                                                   
                                                                                     




                                        Page 36 of 110


                                                                                         


       

                                                                                     
                                                                              

                                        

                                                                     
                                                           
                                                                                       
                                                                        
                                                                             

                                                                         
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                               
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                       

                                                                                       
                                                                                     
                                                                                       




                                           Page 37 of 110


                                                                                         


       

                                                                                       
                                                                              

                                        

                                                                     
                                                           
                                                                                       
                                                                        
                                                                             

                                                                         
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                               
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                       

                                                                                       
                                                                                     
                                                                                       




                                           Page 38 of 110


                                                                                         


       

                                                                                       
                                                                              

                                        

                                                                     
                                                           
                                                                                       
                                                                        
                                                                             

                                                                         
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                               
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                       

                                                                                       
                                                                                     
                                                                                       




                                           Page 39 of 110


                                                                                         


       

                                                                                       
                                                                              

                                        

                                                                     
                                                           
                                                                                       
                                                                        
                                                                             

                                                                         
                                                                                                                
                                                                                                                
                                                                                                                
                                                                                                                
                                                                                                                
                                                                                                                
                                                                                                               
                                                                                                                
                                                                                                                
                                                                                       

                                                                                       
                                                                                     
                                                                                       




                                           Page 40 of 110


                                                                                         


       

                                                                                       
                                                                              

                                        

                                                                     
                                                           
                                                                                       
                                                                        
                                                                             

                                                                         
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                                               
                                                                                                               
                                                                                                                
                                                                                                               
                                                                                       

                                                                                       
                                                                                     
                                                                                       




                                           Page 41 of 110


                                                                                        


       

                                                                                    
                                                                             

                                                            

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                                                  
                                                                                                               
                                                                                                               
                                                                                                     
                                                                                                               

                                                                                      
                                                                             




                                          Page 42 of 110


                                                                                        


       

                                                                                      
                                                                             

                                                            

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                                                  
                                                                                                               
                                                                                                               
                                                                                                     
                                                                                                               

                                                                                      
                                                                             




                                          Page 43 of 110


                                                                                        


       

                                                                                      
                                                                             

                                                            

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                                                  
                                                                                                               
                                                                                                               
                                                                                                     
                                                                                                               

                                                                                      
                                                                             




                                          Page 44 of 110


                                                                                        


       

                                                                                      
                                                                             

                                                            

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                                                  
                                                                                                               
                                                                                                               
                                                                                                     
                                                                                                               

                                                                                      
                                                                             




                                          Page 45 of 110


                                                                                        


       

                                                                                      
                                                                             

                                                            

                                                                   
                                                          
                                                                                      
                                                                       
                                                                            

                                                                        
                                                                                                                  
                                                                                                               
                                                                                                               
                                                                                                     
                                                                                                               

                                                                                      
                                                                             




                                          Page 46 of 110


                                                                                        


       

                                                                                     
                                                                              

                                                              

                                                                    
                                                                     
                                                                                     
                                                                     
      

                                                                        
                                                                                                            
                                                                                                              
                                                                                                         
                                                                                                            
                                                                                                           
                                                                                                               
                                                                                                               
                                                                                                                 
                                                                                                        
                                                                                                              
                                                                                                            
                                                                                                            
                                                                                                               


                                                                    
                                                                     
                                                                                     
                                                                     
      

                                                                        
                                                                                                              
                                                                                                                 
                                                                                                              
                                                                                                              



                                                           

                                                                    
                                                                     
                                                            
                                                                     
      
       

                                                                         
                                                                                                      



                                                            




                                          Page 47 of 110


                                                                                       


       

                                                                                    
                                                                             

                                                            

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                             




                                          Page 48 of 110


                                                                                       


       

                                                                                      
                                                                             

                                                              

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                         
                                                                                                             
                                                                                                        
                                                                                                         
                                                                                                           
                                                                                                              
                                                                                                              
                                                                                                               
                                                                                                          
                                                                                                              
                                                                                                              
                                                                                                           
                                                                                                               


                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                             
                                                                                                              
                                                                                                             
                                                                                                            



                                                            

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                              




                                          Page 49 of 110


                                                                                       


       

                                                                                      
                                                                             

                                                              

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                            
                                                                                                              
                                                                                                        
                                                                                                         
                                                                                                           
                                                                                                              
                                                                                                              
                                                                                                               
                                                                                                          
                                                                                                              
                                                                                                              
                                                                                                            
                                                                                                               


                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                             
                                                                                                              
                                                                                                             
                                                                                                            



                                                            

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                              




                                          Page 50 of 110


                                                                                       


       

                                                                                      
                                                                             

                                                              

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                             
                                                                                                              
                                                                                                         
                                                                                                          
                                                                                                            
                                                                                                              
                                                                                                              
                                                                                                               
                                                                                                          
                                                                                                              
                                                                                                              
                                                                                                            
                                                                                                                


                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                              
                                                                                                              
                                                                                                             
                                                                                                             



                                                            

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                               




                                          Page 51 of 110


                                                                                       


       

                                                                                      
                                                                             

                                                              

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                         
                                                                                                              
                                                                                                        
                                                                                                         
                                                                                                           
                                                                                                              
                                                                                                              
                                                                                                               
                                                                                                          
                                                                                                              
                                                                                                              
                                                                                                            
                                                                                                               


                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                             
                                                                                                              
                                                                                                             
                                                                                                            



                                                            

                                                                   
                                                                    
                                                                                    
                                                                    
      

                                                                       
                                                                                                              




                                          Page 52 of 110


                                                                      


                                                            

       

                                                                   
                                                                           

                                                                                
                                                                               
                                                    




                                        Page 53 of 110


                                                                      


                                                            

       

                                                                     
                                                                           

                                                                                
                                                                               
                                                    




                                        Page 54 of 110


                                                                      


                                                            

       

                                                                     
                                                                           

                                                                                
                                                                               
                                                    




                                        Page 55 of 110


                                                                      


                                                            

       

                                                                     
                                                                           

                                                                                
                                                                               
                                                    




                                        Page 56 of 110


                                                                      


                                                            

       

                                                                     
                                                                           

                                                                                
                                                                               
                                                    




                                        Page 57 of 110


                                                                      




                          



                                             

                                             
                                              
                                             




                                             

                                             

                                             
                                              
                                             




                                             

                                             

                                             
                                              
                                             
                                              
                                              
                                             
                                              




                                             

                                             

                                             
                                              






                                               Page 58 of 110







                             Page 59 of 110



                                                                          




                                                                 
                                                       




                                                 
                                      
                                                        
                                                                     
                                                                      
                                                                      
                                                                      
                                                                      


                                                              
                                                   
                                                                     
                                                                                  
                                                                                   
                                                                                   
                                                                                   
                                                                                   











                                                        Page 60 of 110



                                                                          




                                                                 
                                                       




                                                 
                                      
                                                        
                                                                     
                                                           
                                                
                                                                      
                                                                      
                                                                      
                                                                      


                                                              
                                                   
                                                                     
                                                                                  
                                                                        
                                                             
                                                                                   
                                                                                   
                                                                                   
                                                                                   












                                                        Page 61 of 110



                                                                         




                                                                
                                                      




                                                
                                                       
                                                                    
                                                                     
                                                                     
                                                                     
                                                          
                                               
                                                                     


                                                
                                                
                                                       
                                                                    
                                                          
                                               
                                                                     
                                                          
                                               
                                                                     
                                                                     
                                                                     


                                                
                                                       
                                                                    
                                                                     
                                                                     
                                                          
                                               
                                                                     
                                                                     


                                                             
                                                                    
                                                                                 
                                                                       
                                                            
                                                                                  
                                                                                  
                                                                                  
                                                                                  






                                                       Page 62 of 110



                                                                         




                                                                
                                                      




                                                             
                                                                    
                                                                                 
                                                                                  
                                                                                  
                                                                       
                                                            
                                                                                  
                                                                                  


                                                              
                                                                     
                                                                                  
                                                                                   
                                                                        
                                                             
                                                                                   
                                                                                   
                                                                                   


                                                             
                                                                    
                                                                                 
                                                                                  
                                                                                  
                                                                                  
                                                                       
                                                            
                                                                                  











                                                       Page 63 of 110



                                                                         




                                                                
                                                      




                                                
                                                       
                                                                    
                                                          
                                               
                                                                     
                                                                     
                                                                     
                                                                     


                                                
                                                       
                                                                    
                                                                     
                                                          
                                               
                                                                     
                                                                     
                                                                     


                                                             
                                                                    
                                                                                 
                                                                       
                                                            
                                                                                  
                                                                                  
                                                                                  
                                                                                  


                                                             
                                                                    
                                                                                 
                                                                       
                                                            
                                                                                  
                                                                                  
                                                                                  
                                                                                  







                                                       Page 64 of 110



                                                                         




                                                                
                                                      




                                                             
                                                                    
                                                                                 
                                                                                  
                                                                       
                                                            
                                                                                  
                                                                                  
                                                                                  


                                                
                                         
                                                                    
                                                     
                                          


                                                             
                                                      
                                                                                 
                                                                  
                                                       


                                                             
                                                      
                                                                                 
                                                                  
                                                       












                                                       Page 65 of 110



                                                                  




                                                       
                                               




                                                           
                                                    
                                                            
                                                            
                                                            
                                                            











                                              Page 66 of 110


                                                             










                                                                      
                                      
                                                            
                                                           
                                                           
                                                         
                                                           
                                                       
                                                       
                                                      




                                                  
                             
                                        
                              
                             






                                                  Page 67 of 110


                                                    










                                             
                
                                
                               
                               
                               
                               
                             
                            
                           
                          
                        




                                                
                                 






                                                   Page 68 of 110


                                                       










                                                  
                      
                                       
                                       
                                       
                                       
                                       
                                     
                                    
                                
                               




                                                   
                                               
                                              






                                                   Page 69 of 110


                                                    










                                                
                   
                                    
                                    
                                    
                                    
                                    
                                  
                                 
                              
                            




                                                
                                 
                                    






                                                Page 70 of 110


                                                       










                                                   
                      
                                        
                                       
                                       
                                       
                                       
                                   
                                   
                                 
                               




                                                   
                                    
                                      






                                                  Page 71 of 110


                                                   










                                            
                
                                
                               
                               
                               
                               
                            
                            
                         
                       




                                               
                        






                                                  Page 72 of 110


                                                                 



                                         
                                                                         


                 
                                     
                                                     
                                                
   



                                                                                  

                                                                                       
                                                                                   
                                                                                          
                                                                               
                                                                             
                                                                                        
                                                                                     
                                                                                
                                                                             
                                                                                 
                                                                             
                                                                                    
                                                                             
                                                                                     
                                                                                       
                                                                                    
                                                                      
                                                                                   
                                                                              
                                                                              
                                                                              
                                                                      
                                                                               
                                                                               
                                                                           
                                                                         
                                                                               
                                                                              
                                                                          
                                                                        
                                                                       
                                                                                     
                                                                                      
                                                                                      
                                                                               
                                                                     
                                                                          
                                                                                      
                                                                                          
                                                                        
                                                                        
                                                                                
                                                                                          


                          Page 73 of 110


                                                                  



                                         
                                                                         


                 
                                     
                                                     
                                                
   



                                                                                  

                                                                            
                                                                            
                                                                                  
                                                                           
                                                                           
                                                                                    
                                                                                   
                                                                                   
                                                                                


                                                              
                                                  
                                                             
                                                    
                                                   




                          Page 74 of 110


                                                                          


                                                                  
                     


                        
                                               
                                                                
                                                           
        



                      
                                                 
                                                                 
                                                            
        


                                                   
                                                                               

                                                                      
                                                        
                                                       
                                                                
                                                                  
                                                          
                                                          
                                                           
                                                     
                                                          
                                                          
                                                                 
                                                          
                                                             
                                                                     
                                                      
                                                              

                                                                    

                                                                   
                                                                                
                                                                      
                                                                     




                                  Page 75 of 110


                                                                          


                                                             
                            



                                       
                                                                     
                                                                                 
                                                          
                                                          




                                                                                  

                                                                                    

                                                                                         
                                                                            
                                                                            
                                                                                   
                                                                                      
                                                                             
                                                                             
                                                                              
                                                                        
                                                                              
                                                                             
                                                                                    
                                                                              
                                                                               
                                                                                         
                                                                           
                                                                                 




                                     Page 76 of 110


                                                                                           



                                                                 
                                                                                                 


                                         
                                                             
                                                                             
                                                                        
                                                                           
                                                                                                            


                                                                                                            

                                                                                  


                                                                                      
                                                                                 

                                                                               
                                  


                                     
                                                            
                                                                             
                                                                        
                                                                           
                                                                                                            

                                   
                                                              
                                                                              
                                                                         
                                                                            
                                                                                                             

                                                      
                                                                                                

                                                      

                                                                                   

                                                                                          




                                      Page 77 of 110


                                                                                          


                                                                      
                                     



                                                      
                                                                                    
                                                                                                
                                                                         
                                                                         




                                                                                                      

                                                                                                        

                                                                                

                                                                                    
                                       


                                           
                                                             
                                                                                        
                                                                          
                                                                           
                                                                                                              

                                          
                                                             
                                                                                         
                                                                         
                                                                            
                                                                                                              

                                                    
                                                                                                   

                                                                                  

                                                                                     
                                                                                         




                                      Page 78 of 110


                                                                           


                                                                        
                           


                                                   
                                                                       
                                                                                   
                                                            
                                                            




                                                                                     
                                                                     
                                                                    




                                  Page 79 of 110


                                                                             



                                                 
                                                                                 


                         
                                             
                                                             
                                                        
                                                           
                                                                                            


                                                                                            

                                                                           
                                                                         


                                                                       
                                                                             
                                                                            


                                              
                                                                                    


                           
                                                
                                                                
                                                           
                                                              
                                                                                               

                                                                                     
                                                        

                                                                         
                                                                               
                                                                              




                                Page 80 of 110


                                                                                   


                                                                                
                                   


                                       
                                                         
                                                                                    
                                                                      
                                                                       
                                                                                                          

                                      
                                                         
                                                                                     
                                                                     
                                                                        
                                                                                                           

                                                 
                                                                                          

                                                     

                                                                                
                                                                                              
                                                                                            


                                                                              
                                 


                                                         
                                                                             
                                                                                         
                                                                  
                                                                  




                                                                                               
                                                                               
                                                                             




                                  Page 81 of 110


                                                                  



                                         
                                                                         


                 
                                     
                                                     
                                                
                                                   
                                                                                    


                                                                                  

                                                                                          
                                                                                       
                                                                                        
                                                                              
                                                                                        
                                                                                        
                                                                                        
                                                                                       
                                                                                        
                                                                                    
                                                                                   
                                                                              
                                                                               
                                                                                          
                                                                                 
                                                                             
                                                                                      
                                                                              
                                                                                    
                                                                              
                                                                                         


                                                              
                                                         
                                                           




                          Page 82 of 110


                                                                           



                                            
                                                                                  


                         
                                              
                                                              
                                                         
                                                            
                                                                                             

                                                                                
                                                                               
                                                                            
                                                                             
                                                                             
                                                                             
                                                                             
                                                                           
                                                                            
                                                                         
                                                                       
                                                                  
                                                                              
                                                                      
                                                                  
                                                                          
                                                                         

                                                                       
                                                                  
                                                                    




                                Page 83 of 110


                                                                                  


                                                                               
                                  


                                      
                                                        
                                                                                    
                                                                     
                                                                      
                                                                                                         

                                     
                                                        
                                                                                     
                                                                    
                                                                       
                                                                                                         

                                                  
                                                                                         

                                                                                                     
                                                                                                    
                                                                                                     
                                                                                                   
                                                                                                   
                                                                                                    
                                                                                                   
                                                                                                  
                                                                                               
                                                                                               
                                                                                         
                                                                                                     
                                                                                            
                                                                                          
                                                                                                  
                                                                                             

                                                                               
                                                                                
                                                                                  




                                   Page 84 of 110


                                                                           


                                                                        
                           


                                                  
                                                                       
                                                                                    
                                                            
                                                            




                                                                                     
                                                                     
                                                                                                   
                                                                                                
                                                                                                 
                                                                                                 
                                                                                                 
                                                                                                 
                                                                                                
                                                                                                 
                                                                                             
                                                                                            
                                                                                       
                                                                                                   
                                                                                          
                                                                                      
                                                                                               
                                                                                             




                                  Page 85 of 110


                                                                             



                                                  
                                                                                  


                          
                                              
                                                              
                                                         
                                                            
                                                                                             


                                                                                            

                                                                                                   
                                                                                                    
                                                                                                   
                                                                                                   
                                                                                                   
                                                                                                   
                                                                                                   
                                                                                                    
                                                                                                   
                                                                           


                                                                       
                                                                 
                                                                   


                                              
                                                                                    


                           
                                                
                                                                
                                                           
                                                              
                                                                                               

                                                                                    
                                                                                
                                                                                

                                                                         
                                                                    
                                                                     




                                Page 86 of 110


                                                                                   


                                                                                
                                   


                                       
                                                         
                                                                                    
                                                                      
                                                                       
                                                                                                          

                                      
                                                         
                                                                                     
                                                                     
                                                                        
                                                                                                          

                                                 
                                                                                          

                                                                                                    
                                                                          

                                                                                
                                                                                   
                                                                                     


                                                                              
                                 


                                                         
                                                                             
                                                                                         
                                                                  
                                                                  




                                                                                               
                                                                               
                                                                                                              
                                                                                                    




                                  Page 87 of 110


                                                                             



                                                 
                                                                                 


                         
                                             
                                                             
                                                        
                                                           
                                                                                            


                                                                                            

                                                                                                       
                                                                                                    
                                                                                                    
                                                                                          
                                                                                                    


                                                                       
                                                          


                                              
                                                                                    


                           
                                                
                                                                
                                                           
                                                              
                                                                                               

                                                                                   
                                                                                                    
                                                                                   
                                                                                                  
                                                                        
                                                                                  

                                                                         
                                                             




                                Page 88 of 110


                                                                                   


                                                                                
                                   


                                       
                                                         
                                                                                    
                                                                      
                                                                       
                                                                                                          

                                      
                                                         
                                                                                     
                                                                     
                                                                        
                                                                                                          

                                                
                                                                                           

                                                                               
                                                                              
                                                                             
                                                                  
                                                                             

                                                                                
                                                                            


                                                                               
                                  


                                                          
                                                                              
                                                                                          
                                                                   
                                                                   




                                                                                               
                                                                               
                                                                                                        
                                                                                                      
                                                                                                     
                                                                                            
                                                                                                      




                                  Page 89 of 110


                                                                  



                                         
                                                                         


                 
                                     
                                                     
                                                
   



                                                                                  

                                                                                       
                                                                                        
                                                                                     
                                                                                       
                                                                                      
                                                                                         
                                                                                         
                                                                                           
                                                                                     
                                                                                         
                                                                                         
                                                                                      
                                                                                       


                                         
                                                                         


                 
                                     
                                                     
                                                
   



                                                                                  

                                                                                        
                                                                                          
                                                                                       
                                                                                       




                          Page 90 of 110


                                                                          



                                           
                                                                                 


                        
                                             
                                                             
                                                        
   



                                                                                 
                                                                           
                                                                                
                                                                           
                                                                             
                                                                           
                                                                              
                                                                             
                                                                               
                                                                           
                                                                              
                                                                              
                                                                            
                                                                                


                                           
                                                                                 


                        
                                             
                                                             
                                                        
   



                                                                                 
                                                                              
                                                                                
                                                                              
                                                                             




                                Page 91 of 110


                                                                         


                                                                      
                         


                             
                                               
                                                                          
                                                            
       



                            
                                               
                                                                           
                                                           
       



                                                 
                                                                               

                                                                                          
                                                                    
                                                                 
                                                                   
                                                                  
                                                                    
                                                                    
                                                                                                
                                                                                        
                                                                   
                                                                    
                                                                  
                                                                                               




                                  Page 92 of 110


                                                                         


                                                                      
                         


                             
                                               
                                                                          
                                                            
       



                            
                                               
                                                                           
                                                           
       



                                                
                                                                               

                                                                  
                                                                     
                                                                                           
                                                                 




                                  Page 93 of 110


                                                                           


                                                                        
                           


                                                   
                                                                       
                                                                                   
                                                            
                                                            




                                                                                     
                                                                     
                                                                                                
                                                                                            
                                                                                     
                                                                                        
                                                                                        
                                                                                          
                                                                                           
                                                                                                        
                                                                                               
                                                                                          
                                                                                       
                                                                                        
                                                                                                      

                                                                        
                           


                                                   
                                                                       
                                                                                   
                                                            
                                                            




                                                                                     
                                                                     
                                                                                           
                                                                                              
                                                                                                      
                                                                                           




                                  Page 94 of 110


                                                                                     



                                             
                                                                                          
                                                                                          
                                 
                                                      
                                                                       
                                                                 
   
    


                                                                                                    

                                                                                                        


                                                      
                                                                                            
                                                                                            
                                   
                                                        
                                                                         
                                                                   
   
    

                                                                                            
                                                                                       

                                                                               
                                  
                                                                                            

                               
                                                        
                                                                                   
                                                                    
        
         


                             
                                                        
                                                                                    
                                                                    
        
         

                                                 
                                                                                           

                                                                           




                                   Page 95 of 110


                                                                          


                                                                       
                          
                                                                                    

                                            
                                                                      
                                                                                  
                                                           
                                                           
                                                             




                                                                                    
                                                                    
                                                                                  




                                  Page 96 of 110


                                                                                    



                                                         
                                                                                         


                                 
                                                     
                                                                     
                                                                
   



                                                                                                   

                                                                                                           


                                                     
                                                                                           


                                  
                                                       
                                                                       
                                                                  
   



                                                                                            
                                                                                            

                                                                              
                                 


                                     
                                                       
                                                                                  
                                                                    
        



                                    
                                                       
                                                                                   
                                                                   
        



                                                  
                                                                                           

                                                                          




                                   Page 97 of 110


                                                                          


                                                                       
                          


                                                  
                                                                      
                                                                                  
                                                           
                                                           




                                                                                    
                                                                    
                                                                                           




                                  Page 98 of 110


                                                                    



                                                
                                                                             


                          
                                                 
                                                          
                                               
     



                                                                         

                                                                           




                               Page 99 of 110



                                                                                           



                              

                                                               

                                                                              
                                                                                      
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                   
                                                                   
                                                                    
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                            


                           

                                                               

                                                                              
                                                                                      
                                                                 
                                                                 
                                                                
                                                                
                                                                 
                                                                 
                                                                 
                                                                 




                                                                                 

                                                          Page 100 of 110



                                                                                         



                        

                                                             

                                                                            
                                                                                    
                                                                 
                     
                                                                 
                     
                                                                
                     
                                                                
                     
                                                                 
                     
                                                                 
                     
                                                                 
                     
                                                                 
                     

                         

                                                             

                                                                            
                                                                                    
                                                                       




                                                                               

                                                        Page 101 of 110



                                                                                           



                              

                                                               

                                                                              
                                                                                      
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                            


                           

                                                               

                                                                              
                                                                                      
                                                                 
                                                                  
                                                                 
                                                                 


                          

                                                               

                                                                              
                                                                                      
                                                                   
                     
                                                                    
                     
                                                                   
                     
                                                                   
                     




                                                                                 

                                                          Page 102 of 110



                                                                                           



                              

                                                               

                                                                              
                                                                                      
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                            


                           

                                                               

                                                                              
                                                                                      
                                                                 
                                                                 


                          

                                                               

                                                                              
                                                                                      
                                                                   
                     
                                                                   
                     




                                                                                 

                                                          Page 103 of 110



                                                                                           



                              

                                                               

                                                                              
                                                                                      
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                     
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                    
                                                                            


                           

                                                               

                                                                              
                                                                                      
                                                                 
                                                                 


                          

                                                               

                                                                              
                                                                                      
                                                                   
                     
                                                                   
                     




                                                                                 

                                                          Page 104 of 110



                                                                                         



                            

                                                             

                                                                            
                                                                                    
                                                                   
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                   
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                  
                                                                          


                                     

                                                                           

                                                                            
                                                                                    
                                                                  
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                  
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 
                                                                 



                                                                               

                                                        Page 105 of 110



                                                                                      



                                      

                                                                        

                                                                         
                                                                                 
                                                             
                                                             


                                      

                                                                        

                                                                         
                                                                                 
                                                              
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                              
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             
                                                             


                                     

                                                                        

                                                                         
                                                                                 
                                                             
                                                            
                                                            
                                                            




                                                                            

                                                          Page 106 of 110



                                                                                            



                                        

                                                                

                                                                               
                                                                                       
                                                                  
                                                                  


                                       

                                                                

                                                                               
                                                                                       
                                                                 
                                                                 








                                                                                  

                                                           Page 107 of 110
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)



                                                                                            



                                                                                           



                                                                             

           

                                
                 

                                                    
                                                
                                                  
                                                                  
                                            
                                
                                      
         

                                        
                                           
                                                    
                                                                                              
                                       
                                          
                                            
                                                     
        

              

      

                                             
                                 
                                                       
                                    
              
                                                       




                                                    Page 110 of 110
180 Grand Ave, Ste 1410
                                                                    Oakland, California 94612
                                                                               510-350-2900
                                                                          FAX 510-350-2901


February 21, 2011
Project Number 070181

Waste Management
Richard T. Von Pein, P. E.
Director of Engineering, Western Group
6640 Amber Lane
Pleasanton, CA 94566

Subject:       Work Plan for Sedimentation Basin Restoration- Waimanalo Gulch
               Sanitary Landfill, Ewa Beach, Oahu, HI

Dear Mr. Von Pein,

As requested, GEI Consultants (GEI) has prepared a work plan to restore the sediment
basin system to its intended capacity and function after the occurrence of the recent storm
events in December 2010 and January 2011.

Sedimentation Basin Features

The sedimentation basin was originally designed and constructed in the late 1980’s.
Recently (2006-2007), there were several modifications made to the basin including the
placement of an interior pond retention berm, swale energy dissipation improvements,
installation of a subdrain system, and replacement of the two 42-inch corrugated metal
riser pipes with concrete risers. Attachment A includes a copy of the design drawings by
Shimabukuro, Endo, and Yoshizaki, Inc. showing the original basin design, and
EarthTech drawings showing the recent modifications. Attachment B includes
photographs of the basin in October 2007 after construction of the basin modifications.

The sedimentation basin currently receives drainage that is collected in the western
concrete-lined drainage channel immediately upstream of the basin. The sedimentation
basin consists of the following elements, described in an upstream to downstream
direction:

       Sedimentation Basin Inlet Apron - The inlet located at the downstream end of
       the western concrete lined drainage channel consists of a 30-foot long rock riprap
       apron. The rock riprap sizes are approximately 18 to 24 inches in diameter.
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill               2                                      2/21/11

        Northern Basin and Interior Berm Area – A riprapped interior berm is located
        in the northern (upstream) portion of the basin. The interior berm is
        approximately 4 feet high. The northern basin area and interior berm function as
        a pre-holding area to reduce the amount of coarser sediment that will continue to
        travel downstream in the basin, and possibly reduce the hydraulic mixing and
        churning of the finer sediment in the southern basin. The approximate elevation
        of the basin floor in this area is El. 65. The basin side slopes adjacent to the floor
        are inclined at 2 horizontal to 1 vertical (H: V), and the total depth of the basin in
        this area is approximately 18 feet. There is also a riprapped energy dissipator at
        the northeast corner of the basin to reduce exit velocities from 18-inch and 42-
        inch storm water pipes exiting into the basin at this location.

        Southern Basin Area - The southern portion of the basin contains a subdrain
        system beneath the basin floor to lower and discharge the standing water in the
        basin during low flow events. The subdrain system and consists of 6-inch,
        perforated high density polyethylene (HPDE) pipes placed in an 18-inch wide by
        24-inch deep infiltration trench wrapped in a filter cloth. The trench is backfilled
        with ½ to ¾-inch drain rock with an overlying 6-inch sand bedding layer at the
        base of the sedimentation basin. The HDPE pipes are connected directly to the
        CMP outlet pipes (described below) to allow for conveyance of drainage from the
        subdrain system.

        The basin side slopes adjacent to the floor are inclined at 2 horizontal to 1
        vertical, and the total depth of the basin in this area is approximately 18 feet.
        However, the earthen embankment at the downstream end of the pond is
        approximately 4.5 to 5 feet lower, to form an emergency spillway crest for the
        sedimentation basin (see riprapped embankment and spillway description below).

        Outlet Riser Pipes - There are two reinforced 48-inch diameter concrete inlet
        riser pipes that function as principal outlets for the sedimentation basin. The riser
        pipes were constructed without intermediate orifice openings, so drainage of basin
        inflow will be through the overflow outlet at the top of the riser or through the
        underlying subdrain system described previously. The vertical riser pipes outlets
        connect via a concrete box to 42-inch diameter horizontal corrugated metal pipes
        (CMP’s) located at the base of the embankment at the downstream end of the
        sedimentation basin. The CMP’s outlet on the spillway apron at the downstream
        toe of the embankment.

        Riprapped Embankment and Spillway - An earthfill embankment was
        constructed at the south end of the basin to provide containment on the
        downstream side of the pond. The embankment is armored with a 2’ thick layer
        of grouted riprap. The crest and downstream slope of the embankment functions
        as an emergency spillway apron to discharge storm water downstream from the
        basin. The embankment was constructed with 2 H to 1 V sideslopes and a crest
        width of approximately 19 feet. The inboard sideslope of the embankment is
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill                3                                    2/21/11

        approximately 14 feet high.             The outboard side of the embankment is
        approximately 21 feet high.

        Vegetated Drainage Corridor - A vegetated area is located downstream of the
        spillway apron and the 42-inch CMP pipe outlets. The vegetated area is
        approximately 200 feet long by 50 to 100 feet wide and conveys storm water
        flows downstream to three CMP culvert outfalls beneath Farrington Highway.

Work Plan Activities

In order to restore the basin to its intended capacity and function, specific activities will
be performed for the features described previously. These activities are described in
more detail and are currently being implemented or will be implemented as soon as
possible after the basin is dewatered.

        Basin Pumping - Prior to cleaning and inspection of the sedimentation basin
        features, all standing water will be pumped from the basin and discharged at a
        POTW designated by the City and County of Honolulu.

        Basin Inlet Apron - All sediment and debris on top of the energy dissipator and
        interior berm will be removed until the underlying riprap apron and berm
        armoring are exposed. Any riprap missing from this area will be replaced with
        18-inch to 24-inch diameter rock. The riprap will consist of basalt material with
        good rock quality obtained from the on-site excavation activities within the
        landfill.

        Northern Basin and Interior Berm Area - The sediment and debris from the
        basin will be removed to restore the basin floor to the design elevation of El.65.0.
        Any sediment that collected against the toe or side slopes of the basin will be
        removed to restore the basin slopes to their design 2 H to 1V inclination and the
        basin floor width to the design dimensions shown in Attachment A. The riprap
        armoring on the interior berm and energy dissipation swales will be fully
        uncovered and inspected to determine if there are areas of dislodged or missing
        riprap. Any areas of missing riprap will be replaced. The riprap will consist of
        on-site material as described previously. After drying, sediment will be used for
        daily cover and debris will be disposed in the landfill.

        Southern Basin Area - The sediment and debris from the basin will be removed
        to restore the basin floor to the design elevation of El.65.0. Any sediment that
        collected against the toe or side slopes of the basin will be removed to restore the
        basin slopes to their design 2 H to 1V inclination and the basin floor width to the
        dimensions shown in Attachment A. After removing sediment from the basin
        floor the subdrain trenches will be located and the 6” washed sand layer on the
        basin floor covering the subdrain system should be replaced. The concrete inlet
        riser pipes and steel trash racks will be visually inspected for debris or sediment
        blockage. If blockages are observed, they will be removed from the risers and
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill               4                                  2/21/11

        trash racks. The 42-inch CMP outfall beneath the embankment will be visually
        inspected for debris or sediment blockage. All sediment and debris should be
        removed from the CMP outfall pipes. After drying, sediment will be used for
        daily cover and debris will be disposed in the landfill

        Riprapped Embankment and Spillway - As a result of the December 2010-
        January 2011 storm events, sediment may have accumulated against the grouted
        riprap on the inboard and outboard faces of the embankment and spillway area.
        Any accumulated sediment in these areas will be removed and disposed properly
        in the landfill. Disposal may include using the material for daily cover. The
        overflow spillway will also be visually inspected for signs of debris that is
        blocking the overflow weir or that has migrated on the downstream face of the
        weir. All debris in the spillway will be collected and deposited in the landfill.

        Vegetated Drainage Corridor - The area immediately downstream of 42-inch
        CMP pipe outfalls and riprap apron was protected in the past with rock riprap.
        The riprap was placed to allow for storm water discharge to dissipate and spread
        throughout the vegetated area before leaving the site. These riprap areas will be
        inspected, and any missing or dislodged riprap will be replaced. On-site rock
        material will be used as described previously. All debris that migrated into the
        drainage corridor will be removed and disposed in the landfill.

        There may be bare soils areas within the vegetated drainage corridor that require
        short term erosion protection measures. These areas will be protected by seeding
        with erosion resistant vegetation and placement of temporary erosion control
        matting where necessary. We note that surface soils in the vegetated drainage
        corridor will be disturbed in order to construct the stilling basin outlet for the
        Western Surface Water Drainage System. Longer term erosion control measures
        for the vegetated drainage corridor will be considered during construction of the
        stilling basin structure.

        Sediment and Debris Disposal - All sediment and debris removed from the areas
        described previously should be disposed in the landfill. Sediment will be
        stockpiled and allowed to dry. The dried sediment material can then be utilized as
        daily and intermediate cover during landfilling operations.

        Implementation of Work Plan - Waste Management will implement the work
        plan described using available site personnel and contractors. Inspection will be
        performed by AECOM engineers as required.

        Documentation of Work Plan Activities - Photo-documentation and field
        reports will be prepared by landfill personnel during and after restoration
        activities to support final reporting efforts of work plan implementation to the
        USEPA.
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill               5                                  2/21/11

Schedule – Liquids are scheduled to be removed from the pond by February 14th
provided there is no additional rainfall. After liquids are removed removing sediment,
debris and silted-in underdrain material will occur. As soon as all material is removed
from the pond, the underdrain will be reconstructed, other necessary repairs made and the
pond put back into service. We anticipate removing the sediment and debris, and
reconstructing the pond will take approximately 4 weeks and should be completed by
March 14, provided we do not receive significant additional rainfall. If storm water
enters the basin prior to the removal of the sediments, we would not discharge it as storm
water, except in an emergency and only after consultation with the Hawaii Department of
Health and the USEPA. The water will be removed and transported to a POTW
designated by the City and County of Honolulu.


Very truly yours,
GEI Consultants, Inc.




William A. Rettberg, P.E.
Vice President



Attachment A:            Drawings by Shimabukuro, Endo, &Yoshizaki, Inc. and Earth
                         Tech Depicting Basin Configuration and Features

Attachment B:            Photographs of the Sedimentation Basin Area in October 2007
                         After Construction of Modifications
 
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill


ATTACHMENT A


Drawings by Shimabukuro, Endo & Yoshizaki, Inc. and EarthTech
Depicting Basin Configuration and Features
 
42-Inch CMP
        Outfall
        Locations
                              48-Inch RCP
                              Risers




                                                 Northern Basin
                                                 and Interior
                                Southern Basin                  Riprap Energy
                                                 Berm Area
                                Area                            Dissipator and
                                                                Outfall Pipes
            Riprapped
            Embankment
            and Spillway

Vegetated Drainage Corridor
(Farrington Hwy. Culverts
Approx. 200 Ft. Downstream)
Removal Action Summary Report (pages 1-1015)
Riprapped
              Embankment and
              Spillway




                                        Original CMP Riser
                                        Pipe Replaced with
                                        Concrete Riser (See
                                        EarthTech Drawing
                                        C-11)


42-inch CMP
Outlet




                               Typical Section
                               Across
                               Sedimentation Basin
Removal Action Summary Report (pages 1-1015)
Work Plan for Sedimentation Basin Restoration
Waimanalo Gulch Sanitary Landfill


ATTACHMENT B


Photographs of Sedimentation Basin Area in October 2007 After
Construction of Modifications
 
View of Basin Looking South Along the Western Concrete Lined Drainage Channel
Western Drainage
                                                                  Channel
                                        Northern Basin and
Southern Basin Area                     Interior Berm
With Subdrains
                          Inlet Riser




                      View of Sedimentation Basin Looking North
42 Inch CMP Pipe Outlets




View along Riprapped Embankment Crest Looking West
Riprapped Interior Berm
                                                 Riprap Energy Dissipator




            Southern Basin Area




                            48 inch Concrete Riser on
                            West Side f Basin
                            W t Sid of B i




View of Basin Looking Northeast from Riprapped Embankment Crest
Waimanalo Gulch Sanitary Landfill
                    Stormwater Management Update and Contingency Plan
                                              2-1-11 (Revised 2-18-11)
  
         Following  the  recent  major  storm  events,  Waste  Management  of  Hawaii  (WMH)  has  assessed  
and  evaluated  its  stormwater  control  systems  for  effectiveness.    Below  is  an  update  of  ongoing  
measures  being  taken  to  prevent  future  storm  damage  at  the  site,  and  document  efforts  to  further  
contain  potential  storm  water.    WM  believes  that  these  measures  will  prevent  waste  material  and  storm  
water  that  may  have  come  into  contact  with  waste  from  exiting  the  facility  in  the  event  of  a  major  
storm.  
  
    1) The  36-­‐inch  drain  was  designed  to  handle  water  falling  within  the  landfill  footprint,  upstream  of  
         the  waste  disposal  area,  during  landfilling  operations.    It  was  also  intended  to  mitigate  runon  
         during  small  storms  until  the  diversion  channels  are  in  place.    The  west  side  drainage  channel  
         has  been  designed  to  control  the  100-­‐year  storm  and  will  mitigate  the  impact  of  storms  with  
         higher  return  periods.      
                  The  effectiveness  of  36-­‐inch  inlet  structure  for  the  up  canyon  drainage  system  has  been  
                  restored  and  improved.  The  area  immediately  surrounding  the  inlet  structure  has  been  
                  re-­‐graded  and  armored  with  large  boulders  to  prevent  high  sediment  loading  from  
                  clogging  the  inlet.  A  diversion  berm  immediately  downstream  of  this  diversion  structure  
                  has  been  reinforced  and  re-­‐built  to  further  direct  any  stormwater  into  the  inlet  
                  structure.    
                  The  area  surrounding  the  future  Cell  E-­‐8  is  being  excavated  down  to  the  elevation  of  the  
                  36-­‐inch  pipe  inlet  structure.  This  effort  will  help  to  create  stormwater  retention,  
                  dissipate  stormwater  velocities,  and  drop  out  sediment  as  it  moves  from  the  upper  

                   ongoing  since  1/18.      
  
                
     2) Temporary  containment  berm  directly  south  of  Cell  E6  
                                                                                        12-­‐19-­‐10  storm  to  contain  
                large  stormwater  flows  originating  from  up  canyon  and  prevent  a  catastrophic  discharge  
                from  exiting  the  site.  The  berm  did  safely  contain  this  storm,  and  was  subsequently  
                substantially  reinforced  prior  to  the  storm  that  occurred  on  1-­‐13-­‐11.      The  storm  water  
                that  was  contained  behind  the  berm  has  now  been  removed,  creating  a  storage  area  
                capable  of  containing  water  from  a  similar  rainfall  event.  Preliminary  stability  analysis  
                indicates  the  berm  has  adequate  strength  to  contain  the  runoff.  
                  
     3) Establish  a  functioning  Western  Drainage  System.  
                In  order  to  establish  a  functioning  Western  Drainage  System,  the  up  canyon  conveyance  
                structure  must  be  in  place  to  divert  storm  water  into  the  box  culvert  and  fiberglass  
                piping  system.  Additionally,  the  box  culvert  invert  that  originates  at  the  diversion  

                   above  Cell  E-­‐
                   A  functioning  Western  Drainage  System  is  now  in  place  and  successfully  diverting  
                   potential  storm  water  originating  from  up  canyon  around  the  active  portion  of  the  
                   landfill.      
                     
 
4) WM  employees  monitor  weather  conditions  routinely,  in  order  to  prepare  for  and  take  
   emergency  action  in  the  event  of  a  major  storm  event  affecting  the  site.      Storm    preparations  
   include,  but  not  limited  to  the  following:  

              Inspect  existing  storm  water  culverts  and  drains  to  verify  that  they  are  working  properly.  

              Inspect  and  verify  that  the  newly  constructed  up  canyon  diversion  channel  is  functional.  

              Inspect  and  verify  that  all  pumps  and  associated  storm  water  support  related  equipment  
              are  in  place  and  functional.  

              Relocate  non  essential  construction  equipment  to  a  location  outside  of  the  influence  of  
              the  potential  storm.  

         Inspect  and  verify  that  daily  cover  in  the  working  area  has  been  placed  properly  .  WMH  has  
         reviewed  our  Storm  water  Pollution  Control  Plan  (SPCC)  and  will  update  accordingly  as  the  
         western  storm  water  diversion  project  progresses.  

5)     Interim    storm  event    management  

                                                                               resumption  of  landfill  
    operations  within  specified  areas  of  Cell  E6,  contains  a  requirement  that  WMH  list  available  
    equipment  and  personnel  to  be  deployed  in  response  to  major  storm  events  that  may  occur  
    prior  to  the  functional  completion  of  the  west  side  drainage  diversion  project.    These  capabilities  
    are  listed  below.  

                The  WMH  general  contractor  for  the  west  side  drainage  diversion  project  maintains  on  
              site  six  excavators,  six  articulated  dump  trucks,  four  bulldozers,  three  front  end  loaders,  
              two  8  inch  diameter  and  one  twelve  inch  diameter  pumps.    In  addition  WMH  maintains  
              three  bull  dozers,  one  front  end  loader,  one  road  grader,  two  articulated  dump  trucks,  
              one  backhoe,  one  fuel  truck,  one  lube  truck,  and  one  six  inch  diameter  pump.  

              Joe  Whelan,  Justin  Lottig,  Jesse  Frey,  and  Rick  Kahalewai  are  available  to  assist  in  
              managing  storm  water  management,  in  addition  to  four  equipment  operators  and  two  
              maintenance  technicians.    Additionally,  the  general  contractor  maintains  appropriate  
              operators  for  all  equipment  listed  above.  

              WMH  employs  a  security  service  which  is  on  site  after  business  hours    seven  days  per  
              week    who  are  responsible  for  alerting  WMH  management  in  the  event  of  a  major  after  
              hours  storm  event.    During  business  hours  the  above  listed  WMH  employees  and  the  
              general  contractor  maintain  sufficient  trained  employees  to  respond  to  storm  events.  

              The  sedimentation  basin,  temporary  berm  in  the  Cell  E6  area,  36  inch  storm  water  
              diversion  piping,  and  general  facility  drainage  ditches  will  be  monitored  and  maintained  
              during  potential  storm  events.    These  activities  include,  but  are  not  limited  to:  

                    i. Inspect  the  sedimentation  basin  for  available  free  board,  and  verify  that  the  
                       existing  floating  debris  skimming  barrier  is  in  place  and  functional.  
ii. Inspect  the  termporary  berm  in  the  cell  6  area    for  damage  and  general  
         structural  integrity.      

    iii. Inspect  the  existing  storm  water  culverts  and  drains  to  verify  that  they  are  
         working  properly.  

    iv. Inspect  and  verify  that  the  newly  constructed  up  canyon  diversion  channel  is  
        functional.  

     v. Inspect  and  verify  that  all  pumps  and  associated  storm  water  support  related  
        equipment  are  in  place  and  functional.  

These  measures  will  be  performed  by  site  personnel  and  representatives  of  the  on  site  
contractor  responsible  for  new  cell  and  storm  water  construction,  prior  to  the  onset  of  a  
major  storm  and  throughout  the  storm  event,  as  long  as  conditions  remain  safe.  

In  the  event  of  a  major  storm  event,  WMH  employees  and  contractors  will  assess  on  site  
conditions  to  determine  if  there  is  a  potential  threat  to  human  life  or  injury,  as  well  as  
equipment  damage,  or  environmental  harm  as  a  result  of  the  storm.    WMH  will  take  
appropriate  actions  to  keep  all  ditches  and  storm  water  conveyance  structures  
operational  and  free  of  debris,  once  it  is  determined  that  these  activities  can  be  
performed  safely.    WMH  will  monitor  the  condition  of  the  Cell  E6  berm  in  relation  to  the  
amount  of  storm  water  that  may  have  ponded  behind  this  dam.  

Operations  within  the  Cell  6  area  may  be  suspended  due  to  a  severe  storm  event  if  
conditions    jeopardize  the  safety  of  employees  or  customers,  such  as,  roadways  into  or  
out  of  the  cell  become  impassible  or  WMH  employee  are  not  able  to  process  and  
compact  the  waste  material  in  a  safe  and  efficient  manner.    Should  a  shut  down  of  
operations  be  deemed  necessary,  WMH  will  complete  unloading  of  trucks  located  in  the  
off  loading  area,  compact  the  waste,  and  initiate  daily  cover  of  the  in  place  waste,  as  
quickly  as  possible.    As  previously  noted,  WMH  will  inspect  and  maintain  the  various  
storm  water  conveyance  systems  in  order  to  minimize  the  exposure  of  any  waste  
material.  

Should  a  release  of  solid  waste  material  occur,  WMH  employees  will  monitor  the  
existing  storm  water  outfall  location  and  initiate  beach  assessments,  clean  up  activities,  
and  post  signs  in  those  areas  likely  to  be  affected  by  a  release.    
 
 




                     Appendix  C  
          Heath  and  Safety  Plan    




       
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
SECTION I - PART E

EMERGENCY ACTION PLAN
Removal Action Summary Report (pages 1-1015)
Program:            EMERGENCY ACTION PLAN
Facility:           Waimanalo Gulch Sanitary Landfill (WGSL)
Location:           92-460 Farrington Highway, Kapolei, HI 96707
Date:               February 2011




                                               TABLE OF CONTENTS

1.0     INTRODUCTION .............................................................................................. 1

        1.1     EMERGENCY RESPONSE PERSONNEL .................................................................... 1
        1.2     RELEASE OF INFORMATION TO THE PUBLIC / MEDIA................................................ 1
        1.3     SITE MAP ............................................................................................................. 1
        1.4     ALTERNATE WASTE DISPOSAL PLAN...................................................................... 2
2.0     EMERGENCY RESPONSE AGENCIES / TELEPHONE NUMBERS:........... 17

3.0     EMERGENCY PROCEDURES ...................................................................... 21

        3.1  EVACUATION PROCEDURE................................................................................... 21
        3.2  FIRE PROCEDURE ............................................................................................... 22
             3.2.1 Structure Fire or Surface Fire ................................................................ 22
             3.2.2 Buffer Zone or Brush Fire ...................................................................... 23
             3.2.3 Incoming Waste Load Fires ................................................................... 23
             3.2.4 Vehicle or Equipment Fire ..................................................................... 24
             3.2.5 Landfill Subsurface Fire ......................................................................... 24
        3.3 MEDICAL EMERGENCY PROCEDURE .................................................................... 26
             3.3.1 Injury Accident Response Procedures ................................................... 26
        3.4 SPILL/RELEASE RESPONSE PROCEDURE ............................................................. 27
             3.4.1 Minor Spill .............................................................................................. 27
             3.4.2 Major Spill .............................................................................................. 27
        3.5 EARTHQUAKE ..................................................................................................... 28
        3.6 SEVERE STORM RESPONSE PROCEDURES .......................................................... 30
        3.7 HURRICANES ...................................................................................................... 30
        3.8 BOMB THREAT (PHONE CALL) ............................................................................. 33
        3.9 CIVIL DISTURBANCE/DEMONSTRATION................................................................. 33
        3.10 ARMED ROBBERY ............................................................................................... 34
        3.11 TERRORIST THREATS .......................................................................................... 37
4.0     EMERGENCY EQUIPMENT & PPE .............................................................. 39

5.0     ADMINISTRATIVE PROCEDURES............................................................... 41

        5.1     EMERGENCY REPORTING .................................................................................... 41
        5.2     TRAINING ............................................................................................................ 41
        5.3     PLAN UPDATE AND DISTRIBUTION ........................................................................ 42

©2011, Waste Management

                                                              Page i
Figures

FIGURE 1:    WGSL SITE LOCATION MAP
FIGURE 2:    EVACUATION ROUTE MAP
FIGURE 2A:   SHOP FLOOR PLAN
FIGURE 2b:   EMPLOYEE LOUNGE
FIGURE 2c:   ADMINISTRATION BUILDING – FIRST FLOOR
FIGURE 2d:   ADMINISTRATION BUILDING – SECOND FLOOR
FIGURE 2e:   SCALE HOUSE
FIGURE 3:    DIRECTIONS TO ST. FRANCIS MEDICAL CENTER
APPENDIX A: FIRE PREVENTION PLAN

 TABLE A-1: SITE LOCATIONS WITH POTENTIAL FIRE HAZARDS AND
            POTENTIAL IGNITION SOURCES
 TABLE A-2: CONTROL PROCEDURES AND FIRE PROTECTION EQUIPMENT FOR
            POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES

APPENDIX B: POST EARTHQUAKE FORMS & POST HURRICANE / SEVERE
            STORM FORMS




©2011, Waste Management

                                 Page ii
1.0   INTRODUCTION
This Emergency Action Plan was prepared by Waste Management of Hawaii (WMH) for the
Waimanalo Gulch Sanitary Landfill (WGSL) and contains procedures to be implemented in the
event of an emergency at the WGSL. All personnel on-site at the WGSL, including contractors and
subcontractors, will be informed of the procedures and requirements of this Plan, as they relate to
potential fire, explosion, health, safety, or other hazards.

A Fire Prevention Plan is included in Appendix A that evaluates and identifies potential fire
hazards, ignition sources, on-site fire fighting equipment, and the proper handling of combustible
materials.
If there are any questions regarding the procedures described in these plans, please contact
WGSL / WMH Management.


1.1 EMERGENCY RESPONSE PERSONNEL

In the event of an emergency, the Emergency Coordinator (EC) has primary responsibility for
responding to correcting, and documenting and reporting emergency situations. This includes
taking appropriate measures to ensure the safety of WGSL personnel and the public. Possible
actions may involve evacuation from the site or evacuation of adjacent residents.

Section 2.0 contains a list of emergency response telephone numbers, including the EC and key
WGSL / WMH personnel (alternate ECs). This list is posted in the lounge, main administration
office (upstairs and downstairs), in the scale house, and in the parts container at the maintenance
shop. The first person on the scene will follow the normal procedures for emergency response, as
outlined in this Plan, until the designated EC (or alternate) arrives at the scene. All EC's will be
properly trained in this procedure.

In some cases, Waste Management, Inc. (WM) West Group personnel will need to be called upon
for assistance during emergency situations. Refer to Section 2.0 below, for a list of key WM West
Group personnel who may be notified in the event of an emergency at the WGSL, if deemed
necessary.


1.2 RELEASE OF INFORMATION TO THE PUBLIC / MEDIA
Inquires from the media are likely in the event of an emergency. The WMH Vice President /
General Manger or other designated spokesperson will coordinate all media relations and
responses to any media request, as well as contact the necessary WM West Group personnel. If
approached or contacted by the press, unauthorized personnel should not answer any questions or
make any statement to the media – please refer them to the general manager.



1.3 SITE MAP

©2011, Waste Management

                                              Page 1
A WGSL site location map (Figure 1), evacuation route map (Figure 2), and building floor plans for
the maintenance shop area (Figure 2a), employee lounge (Figure 2b) main administration office
(Figures 2c & 2d), and scale house (Figure 2e) and are attached to this Plan. These figures detail
exits, evacuation routes, fire extinguisher and fire alarm locations, emergency shut-offs, and the
designated WGSL evacuation area, which is currently THE GRASS AREA BY THE GUARD SHACK, NEAR
FARRINGTON HIGHWAY (see Figure 1).


1.4 ALTERNATE WASTE DISPOSAL PLAN
In the event the liner associated with any landfill cell is damaged, the alternate waste disposal plan
is to seek authorization to temporarily landfill MSW and ash in other areas of the landfill that will
have minimal impact on the damaged portion of the landfill, and if that alternative is not available,
to temporarily utilize other landfills and off-island shipping options as appropriate.




©2011, Waste Management

                                               Page 2
Figure 1
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
2.0   EMERGENCY RESPONSE AGENCIES / TELEPHONE NUMBERS:
       AMBULANCE                                            911
       FIRE DEPARTMENT                                      911
       POLICE DEPARTMENT                                    911
       HOSPITAL:              St. Francis Medical Center - West
                              91-2141 Ft. Weaver Road
                              Ewa Beach, HI 96706
                              (808) 678-7000
A map and driving directions to St. Francis Medical Center are included in this Plan (see Figure 3).

WGSL / WMH KEY PERSONNEL:

PRIMARY EMERGENCY COORDINATOR (EC):
               Joseph R. Whelan (WMH Vice President / General Manager)
                     Office:       (808) 668-2985 ext 15
                     Mobile:       (808) 479-4612
       ALTERNATE ECS:
               Justin Lottig (WMH Environmental Protection Manager)
                       Office:        (808) 668-2985 ext 16
                       Mobile:        (808) 479-0749

               Jesse Frey (WMH Engineer)
                      Office:       (808) 668-2985 ext 22
                      Mobile:       (808) 250-0574

               Rick Kahalewai (WGSL Foreman)
                      Mobile:         (808) 368-4717
                      Direct Connect: 184*2*54571

               Natalie Corella (WGSL Operations Specialist)
                       Office:       (808) 668-2985 ext 10
                       Mobile:       (808) 306-5419




©2011, Waste Management

                                              Page 17
WM WEST GROUP KEY PERSONNEL:

           Donny Carder (Safety Manager)
                        Office:      (616) 810-9270
           Rodney Walter (Director of Engineering)
                        Office:         (480) 624-8480
                        Mobile:         (661) 645-7665
           Christian Colline (Director of Air Programs)
                           Mobile:         (925) 890-2746
           Brian Bowen (Director of Environmental Protection)
                        Office:         (916) 552-5859
                        Mobile:         (916) 704-0971

     OTHER AGENCIES, UTILITIES AND RESPONSE SUPPORT PROVIDERS:
           State Civil Defense:                                    (808) 733-4300
           Oahu Civil Defense:                                     (808) 527-5476
           American Red Cross:                                     (808) 734-2101
           U.S. Coast Guard Terrorist Incident Reporting:          (808) 541-2450
           Poison Center:                                          (800) 222-1222
           Gas Company:                                            (808) 526-0066
           Hawaiian Electric Company:                              (808) 548-7961
           EPA:                                                    (415) 947-8000
           FBI:                                                    (808) 566-4300
           Board of Water Supply:                                  (808) 748-5010
           Environmental Response (Pacific Commercial Services):   (808) 545-4599 Ext. # 2
           National Spill Response Center:                         (800) 424-8802
           State of Hawaii -
                  Clean Air Branch:                                (808) 586-4200
                  Clean Water Branch:                              (808) 586-4309
                  Environmental Management:                        (808) 586-4337
                  Solid & Hazardous Waste:                         (808) 586-4266
                  Hazard Evaluation & Emergency Response (HEER): (808) 586-4249
                    After hours HEER number:                       (808) 247-2191




©2011, Waste Management

                                          Page 18
Figure 3: Directions to St. Francis Medical Center




©2011, Waste Management

                                               Page 19
Removal Action Summary Report (pages 1-1015)
3.0    EMERGENCY PROCEDURES
Listed below are specific types of emergencies and detailed procedures to be followed by site
personnel in the event of an emergency. After an emergency, waste disposal will resume at the
WGSL only after key WM personnel have deemed the situation to be safe. WMH will ensure that
human health and the environment are protected prior to restoring disposal services / operations in
the aftermath of an emergency or disaster.


3.1 EVACUATION PROCEDURE
All personnel on-site will be notified of the evacuation via telephones, cell phones, and/or hand-held
two-way radios. If radios/phones are not operational, personnel will be alerted verbally (the EC and/or
EC alternates will verbally alert all WGSL personnel).

 EVACUATING THE BUILDINGS:
      Walk, don't run to the nearest exit. Personnel and visitors will be directed to immediately
      reconvene at the WGSL evacuation area (via the safest route), which is the GRASS AREA BY
      THE GUARD SHACK, NEAR FARRINGTON HIGHWAY (see Figure 1).

      Upon evacuation, the Operations Specialist will bring the contractor sign-in log to the evacuation
      point (located in the office reception area, on the counter in front of the Operations Specialist).
      This to identify any visitors present on-site.
      EC Alternates will be responsible for checking the facilities to insure that everyone leaves the
      buildings.
      If outside emergency support is required, call 911 and report the emergency. Inform the 911
      operator that there is an emergency and give the following information:
               Caller’s name and location.
               Type of emergency.
               Type of emergency aid required.
       Answer any questions that the emergency operator asks. Stay on the phone with the
       operator until told to hang up.

 EVACUATING THE LANDFILL:
       Administration personnel will contact the on-site Goodfellow Bros. construction office at via
       cellular phones and Goodfellow Bros. will then radio their personnel & give the order to
       evacuate.
       Site personnel will coordinate movement of landfill customers/ waste haulers from the
       disposal area onto the main haul road. Construction personnel will do the same. All persons
       will then proceed to the designated evacuation area at the GRASS AREA BY THE GUARD
       SHACK, NEAR FARRINGTON HIGHWAY (see Figure 1).



©2011, Waste Management

                                               Page 21
The EC (or Alternate EC) will be responsible for:
                   Coordinate evacuation of the WGSL including notification of adjacent property
                   owners/tenants, as required.
                   Coordinate with incoming emergency response personnel.
                   Conduct a head count at the designated assembly area/evacuation point.
                   Notify incoming drivers/haulers via radio or cell phone to avoid the site.
                   Notify WGSL / WMH Management of the emergency.
                   Notify WM Safety personnel of the emergency (if appropriate) - determine if a 24-
                   Hour Report is required.
                   Determine when the “all clear” signal can be given to return to the site.

3.2 FIRE PROCEDURE
Procedures outlined below will be followed for emergencies involving fire, including structure of
large surface fires, buffer zone fires, incoming waste load fires, landfill subsurface fires, and
equipment fires. A 2,000-gallon water truck and bulldozers are available 24-hours a day to aid in
fire fighting. Fire extinguishers are provided in all buildings and site vehicles for use in
extinguishing small fires.

  3.2.1        STRUCTURE FIRE OR SURFACE FIRE
The EC will notify all personnel on-site at the WGSL of the fire via oral information and/or hand-
held radios. If possible, cell phone communication will be established.

In the event of a LARGE STRUCTURE FIRE or SURFACE FIRE:
          1)    Assess the fire - Identify its location, source and size.
          2)    If the fire is SMALL (less than 1 cubic yard), can be approached safely with an
                evacuation route, and available personnel are trained in the appropriate use of fire
                equipment, an attempt can be made to put it out with a fire extinguisher. DO NOT
                ATTEMPT TO FIGHT THE FIRE ALONE.
          3)    If the fire is LARGE, EVACUATE THE BUILDING IMMEDIATELY and proceed to the
                designated evacuation area. Avoid entering a burning structure for any reason.
          4)    Call 911 to report the fire. Inform the 911 operator that there is a fire emergency and
                give the following information:
                       Caller’s name and location.
                       Location of fire.
                       Materials involved, if known.
                       Whether medical aid is required.
          5)    Limit access to area and isolate electrical power at main breaker
          6)    Remove vehicles from the area if time allows and does not present a risk to personnel.

©2011, Waste Management

                                                   Page 22
7)    Remove fuel sources (i.e. flammables from shop) if time allows and does not present
                risk personnel.

Upon arrival of local Fire Department personnel, direct them to the fire and provide assistance as
appropriate.

  3.2.2        BUFFER ZONE OR BRUSH FIRE
If a brush fire / buffer zone fire exists in the area surrounding the landfill, maximum effort will be
made to prevent the fire from reaching refuse fill areas by utilizing on-site assets.


IN THE EVENT OF A BUFFER ZONE OR BRUSH FIRE:
          1)    Maintain existing firebreaks between waste fill areas and surrounding vegetation.
                Roads are maintained on the landfill perimeters, which also serve as a firebreak.
          2)    Excavate additional firebreaks between the landfill and the oncoming fire. Excavated
                soils will be bermed on the fire side of the firebreak for additional protection.
          3)    Water down areas between the firebreak and the disposal area using the on-site water
                trucks.
          4)    If fire threatens the landfill, daily cover will be put on the active face and it will be
                wetted down to prevent a landfill fire caused from flying cinders.
          5)    Equipment and fuel sources will be moved to safe locations as practicable
          6)    Unnecessary personnel will be evacuated from the site/area.
          7)    The local Fire Department will be summoned if site personnel and equipment cannot
                extinguish the fire.

  3.2.3        INCOMING WASTE LOAD FIRES
Scale house attendants and WGSL operations personnel are trained and directed to notice any
smoke, steam, heat, or burning material in incoming waste loads, and prevent it from contacting
combustible materials or being buried at the working face before all combustion is extinguished.

If there is a FIRE IN AN INCOMING WASTE LOAD or if a FIRE OCCURS AT THE DISPOSAL AREA:
          1)    Determine the source of the fire.
          2)    If fire is small put out with fire extinguisher.
          3)    Cut the fire out the active face with a dozer (excavate) and move (separate) burning
                waste from the disposal area to the table. Isolate the fire before it spreads.
          4)    Smother the fire by covering it with soil. The faster that soil can be placed over the fire,
                the more effective this method will be in controlling and extinguishing the fire.
          5)    If necessary, apply water from the on-site water truck to soak the fire.
          6)    Spread the to ensure fire is out and does not reflash.



©2011, Waste Management

                                                     Page 23
7)     Call 911 and summon the local Fire Department if site personnel and equipment
                 cannot extinguish the fire.

  3.2.4        VEHICLE OR EQUIPMENT FIRE
To avoid equipment fires, do not operate equipment with trash, paper or other objects in or near
the engine compartment. Always stay alert – watch for hot spots in the equipment, blistering paint,
or other signs of a fire (smoke or the smell of smoke). If detected, contact WGSL Management or
other operations personnel via two-way radio immediately.

In the event of a VEHICLE OR EQUIPMENT FIRE, the operator will:
     1)        Alert WGSL Management / personnel via two-way radio immediately.
     2)        Bring the vehicle or equipment to a safe stop. If safe to do so, the vehicle/equipment
               should be parked away from fuel supplies, uncovered solid wastes, or other machinery.
     3)        Immediately (or as soon as possible) shut off the engine and engage the brake to prevent
               movement of the vehicle / equipment.
     4)        Get out of the equipment.
     5)        Attempt to control the fire using fire extinguishers or an on-site water truck (depending on
               the size of the fire). If unable to control the fire, follow the procedures for calling 911 as
               detailed in Section 3.2.1 above, and summon the help of the local fire department.

      In the event of any of the above-mentioned fires, the EC will:
                    Assess the situation and possible hazards that may result.
                    Order evacuations, medical care, shutdowns, etc. (as necessary).
                    Notify adjacent property owners/tenants (as necessary).
                    Coordinate with incoming emergency response personnel.
                    Conduct a head count at the designated evacuation point.
                    Notify incoming drivers/haulers via radio or cell phone to avoid the site.
                    Notify WGSL / WMH Management of the emergency.
                    Notify WM Safety personnel of the emergency (if appropriate) - determine if a 24-
                    Hour Report is required.
                    Determine when the “all clear” signal can be given to return to the site.

  3.2.5        LANDFILL SUBSURFACE FIRE
 There are two primary causes of subsurface fires at landfills:
   1) When smoldering waste is buried at the working face. Typically, this occurs at relatively
      shallow depths and is detected by surface expression such as visible smoke or depressions
      forming in recently placed waste.
   2) When excess oxygen is allowed to enter the waste mass. This may occur at any depth
      depending on the oxygen source. At relatively shallow depths, visible smoke and surface
      depressions are likely. If the fire is deep, it is more likely to burn slowly without visible flame
©2011, Waste Management

                                                    Page 24
or large quantities of smoke, and is characterized by rapid oxidation of an organic waste.
       The only evidence may be elevated temperatures within the landfill gas (LFG) collection
       wells, which are generally accompanied by elevated carbon monoxide levels, high balance
       gas-to-methane ratios, low methane-to-carbon dioxide ratios, and increased oxygen levels.
       Underground combustion/oxidation may go undetected until a sinkhole or smoke appears.

 The methods used to EXTINGUISH THE NEAR SURFACE FIRE may include:
       (1) Cutting off the oxygen supply by smothering with fine-grained soil and/or the use of
           plastic membranes; or
       (2) Physically putting the fire out, which involves excavating down to the fire, removing and
           extinguishing burning material, confirming that all burning material is extinguished, and
           placing waste back into the excavation area. This procedure should only be done under
           supervision of personnel experienced with extinguishing landfill fires.
 The primary method used to EXTINGUISH SUBSURFACE COMBUSTION WITHIN THE LANDFILL is to
 smother the smoldering area. Typically this can be accomplished by reducing or cutting off
 vacuum to any affected LFG control well(s). Normally this is sufficient to suffocate the fire and no
 further steps are required. At the same time, the landfill surface should be inspected to verify that
 cover thickness is adequate and that excess air is not entering the landfill. If excess air entry is
 suspected, additional cover should be placed or a reinforced geomembrane liner used. The
 geomembrane, once installed, will significantly reduce the flow of air into the landfill.
 Combustion is considered extinguished when temperatures begin to decrease, coupled with a
 decreasing balance gas-to-methane ratio, and an increasing methane-to-carbon dioxide ratio.
 Due to a decreasing oxygen supply, carbon monoxide levels may increase during this period.
 In the event of deep combustion, limiting access to the affected area is not necessary provided
 there are no visible surface indications of the fire (subsidence or smoke). No new waste may be
 placed within 250 feet of the suspected combustion area, unless separated from the surrounding
 waste by 3 feet of soil or other nonflammable material.
 If a landfill subsurface fire is suspected at the WGSL, WM’s West Group Director of Engineering,
 Director of Environmental Protection, and Director of Air Programs will be notified.

CRITERIA FOR INTERNAL& DOH NOTIFICATION:
       The presence of smoke coming from the landfill (requires immediate notification).
       The presence of visible fire (requires immediate notification).
       Sudden subsidence, typically less than 25 feet across, particularly in areas recently filled.
       Irregular subsidence due to factors other than fires is common at landfills. When there is
       any doubt regarding why an area has subsided, WM West Group Engineering and
       Environmental Protection will be consulted to determine whether the presence of a fire is
       likely.
       Carbon monoxide concentrations > 200 ppm in any LFG collection well.
       Methane-to-carbon dioxide ratio less than 1.0.

©2011, Waste Management

                                              Page 25
LFG well head temperatures over 160 °F.
         Balance gas-to-methane levels above 0.6.

Once a fire has been verified, the Hawaii Department of Health (DOH) shall be notified orally
within 24 hours and a detailed plan outlining steps to control the fire shall be provided, in writing,
within 7 days.
The response required will be determined by the location of the fire. No personnel shall be
permitted within the area until it is confirmed that the fire is extinguished, and the area is
determined to be safe. No waste may be placed within 200 feet of the suspected fire area (without
Group Engineering approval) until it is confirmed that a fire is not present or that the fire has been
extinguished.


3.3 MEDICAL EMERGENCY PROCEDURE

 3.3.1    INJURY ACCIDENT RESPONSE PROCEDURES
 If an accident occurs, WGSL Management should be notified immediately. First aid kits are
 maintained in all buildings on-site, at the maintenance shop, and in all site vehicles (see Figures
 2a-2e). If you are properly certified, begin first aid (e.g. stop bleeding, begin CPR, etc.). Do not
 move the victim unless necessary to prevent further injury. If the nature of an injury requires
 additional treatment, the local emergency response provider is to be notified by dialing 911. The
 person making the call should inform the operator of:
   a) The nature and location of the emergency;
   b) What first aid measures have been initiated;
   c) The need for any special equipment, i.e. hazardous materials response, confined space
      rescue, or vehicle extrication.
 Persons with major injuries should never be moved without professional assistance. Major
 injuries include second or third degree burns, unconsciousness, severe bleeding, broken limbs,
 and any head, back, or neck injury.
 Records of all site accidents and first aid treatments will be maintained at the WGSL office.
 Accident reports will be filed with insurance companies and State agencies as required.
 After the situation has stabilized, WGSL Management will arrange for investigation of the cause
 of the accident. A complete investigation report should be completed within seven days of the
 incident. The report should include a review of the actions leading up to the incident, factors that
 contributed to or mitigated the severity of the incident, and recommendations to prevent
 reoccurrence.

 The EC will be responsible for:
               Coordinating with incoming emergency response personnel.
               Notifying WGSL / WMH Management of the emergency.

©2011, Waste Management

                                              Page 26
Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24
                 Hour Report is required.
                 Notifying OSHA or other regulatory agency if required.


3.4 SPILL/RELEASE RESPONSE PROCEDURE
In the event of a spill/release, immediately alert all personnel in the area and notify the EC (WGSL
District Manager) and/or WGSL Management. If necessary, secure the facility and evacuate to an
upwind area or designated evacuation point. The WGSL has a low potential for spills of hazardous
materials, but incidents are possible in the event of vehicle accidents or malfunctions that could
cause spills of coolant, fuel, or lubricants.

  3.4.1     MINOR SPILL
 A release is considered “minor” if it extends outside the secondary containment provisions and
 the spill/release is limited to the immediate area with no potential for it to enter into the existing
 drainage facilities or for it to present an immediate fire hazard or exposure danger.
 In the event of a minor spill/release, WGSL personnel will:
          1. Secure the area to protect all personnel and public from any immediate danger.
          2. Extinguish any sources of ignition. Vehicles should be turned off. Avoid sparks,
             movement, or any activity that may create static electricity.
          3. ENSURE THAT NO DANGER TO HUMAN HEALTH EXISTS, and then stop the flow at the source
             only if it is safe to do so (e.g., shut off power, turn off valves, plug leaks). No site
             personnel shall come into contact with unknown or hazardous substances that have
             been brought into the facility.
          4. If it is safe to do so and available personnel are trained in the proper use of required
             personal protective equipment (PPE), contain the spill with soil berms, equipment from
             the spill kit (i.e., absorbent pads, particulate sorbent, shovels, hand tools, etc.) and /or
             block off drains downstream. Used sorbent pads will be collected in a drum for proper
             disposal.

  3.4.2     MAJOR SPILL
 WGSL personnel are not trained as first responders in the event of a major spill/release. A
 spill/release is considered “major” if it extends outside the secondary containment provisions and
 the spill has traveled beyond the immediate area or if the spill/release has entered the existing
 drainage facilities.
 In the event of a major spill/release of petroleum products, WGSL personnel will:
          1. Secure the area to protect all employees and public from any immediate danger.
          2. Extinguish any sources of ignition. Vehicles should be turned off. Avoid sparks,
             movement, or any activity that may create static electricity.



©2011, Waste Management

                                                 Page 27
3. ENSURE THAT NO DANGER TO HUMAN HEALTH EXISTS, and then stop the flow at the source
          only if it is safe to do so (e.g., shut off power, turn off valves, plug leaks).
       4. Call 911 to alert the fire department or the emergency response clean-up contractor
          (Pacific Commercial Services): (808) 545-4599 Ext. # 2 and give the following information:

                  Caller’s name and location.
                  Location of spill.
                  If known, materials and volumes involved.
                  Whether medical aid is required.
                  Whether fire hazard exists.


       The EC (or manager in charge) will be responsible for:
              Coordinating with incoming emergency response personnel.
              Notifying WGSL / WMH Management of the emergency.
              Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24
              Hour Report is required.
              Notifying the WMH Environmental Protection Manager who will then report the
              incident to the proper regulatory agencies and arrange for the proper disposal of any
              waste materials (if necessary). The waste material from the cleanup will be
              characterized, transported, and disposed of according to State and Federal
              Regulations. Refer to the WGSL SPCC Plan (Volume I – Section IV) for more
              information regarding spills and spill response.

3.5 EARTHQUAKE
A “significant earthquake” is defined here as one that produces any sign of damage to on-site
structures, including but not limited to, overturned furniture, wall cracks, or structural shifts.
DURING A SIGNIFICANT EARTHQUAKE:
           Remain calm.
           Immediately cease or limit landfilling operations.
           If indoors, stay there. Hazards and injuries are generally caused by objects that fall due
           to the shaking. Move quickly away from windows, shelves, cabinets and glass
           partitions. Get under a desk or table, or sit in an interior doorway or corner. Do not
           leave the building unless the building is unsafe.
           If outdoors, get to an open area away from structures, power lines, and trees.
           If driving, pull over to the side of the road and stop. Avoid overpasses and power lines.
           Stay inside vehicle until shaking has stopped.
           If in a crowded public place, do not rush for the doors. Crouch and cover head with
           hands and arms.



©2011, Waste Management

                                              Page 28
AFTER THE EARTHQUAKE:
         Unless there is an immediate life-threatening emergency, do not attempt to use the
         telephone.
         Promptly (when it is safe to do so) conduct a visual survey of the site to identify any
         slope failures, downed power lines, gas and water leaks, broken electrical wiring or
         sewage lines fires, LFG system failures, tank leaks/spills, or other conditions that could
         threaten worker or public safety.
                 If there is damage, turn the utility off at the source. Immediately report gas leaks
                 to the utility company. Do not re-open gas valve until the utility company has
                 checked the system.
                 Warn others to stay away.
                 If fires occur, follow the procedures set forth in Section 3.2.
                 If injuries occur, follow the procedures set forth in Section 3.3.
                 In the event of inoperable telephone systems, notification of the appropriate
                 agencies/businesses will be accomplished in the most expedient manner
                 available (cellular/mobile phones, person to person, overnight mail, etc.).
         Check buildings for cracks and damage including the roof and foundation.
         Turn on portable radio for instructions and news reports. Cooperate fully with public
         safety officials and instructions.
         Do not use vehicles unless there is an emergency. Keep the streets clear for
         emergency vehicles.
         Be prepared for aftershocks.
         Remain calm and lend a hand to others.
         If the site is evacuated, leave a message telling others where personnel can be found.


 The EC (or manager in charge) will be responsible for:
             Coordinating evacuation of the WGSL including notification of adjacent property
             owners/tenants, as required.
             Coordinating with incoming emergency response personnel.
             Conducting a head count at the designated evacuation point.
             Notifying incoming drivers/haulers via radio or cell phone to avoid the site.
             Notifying WGSL / WMH Management of the emergency.
             Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24-
             Hour Report is required.
             Determining when the “all clear” signal can be given to return to the site.
             Notifying the WMH Environmental Protection Manager who will fill out Post-
             Earthquake Forms (Appendix B) and report the incident to the proper regulatory
             agencies (if necessary).


©2011, Waste Management

                                             Page 29
3.6 SEVERE STORM RESPONSE PROCEDURES
The WGSL is not located within a 100-year floodplain area as delineated by the Federal
Emergency Management Agency (FEMA) of the Federal Insurance Administration (Floodplains), or
within a tsunami hazard or floodway. The following measures will be taken to protect against
excessive erosion, flooding, and wind damage before and during severe storms.
PRIOR TO A FORECASTED STORM:
        WGSL personnel will inspect all drainage on-site structures to verify that they are in
        working order.
        Excessive silt in ditches and basins will be removed and the condition of pipes and
        discharge structures from basins will be verified.
        Diversion berms will be constructed around the current disposal area as needed to prevent
        run-on from entering the waste fill, and to prevent runoff from the waste fill areas of the
        site.
        Interim cover will be placed over exposed waste at the end of the working day prior to the
        forecasted beginning of a severe storm.
At the discretion of WMH Management, the site may be closed for business during storm periods.
In this event, the working face will be closed and covered with interim cover and graded to direct
run-off to the drainage features of the surface water management system.
The WMH Environmental Protection Manager conducts monthly surface water and storm water
inspections, which include checking and monitoring the integrity of the site’s drainage systems. A
Severe Storm Inspection (Post-Hurricane / Severe Storm Forms [Appendix B]) will be conducted, if
necessary, during any prolonged storm event to correct or repair any conditions that have been
damaged or that may cause damage to on-site or off-site facilities. Excessive silt/sediment will be
excavated out of the sedimentation basin and drainage channel/ditches as necessary.


3.7 HURRICANES
Hurricane season occurs from June through November in the northern hemisphere. Typically, the
National Weather Service provides 24 to 48 hour warnings before a hurricane is likely to approach.
There are two types of warnings – “Hurricane Watch” is notice that is given when hurricane
conditions threaten within 24 to 26 hours; “Hurricane Warning” is notice that is given when
hurricane conditions are expected within 24 hours or less. Typically, waste management facilities
support cleanup efforts by providing disposal capacity for debris and other solid wastes generated
by the hurricane. Demands on solid waste management facilities are highest immediately following
the hurricane and through the early phase of recovery. Local authorities and emergency
coordinators rely on waste management facilities to provide capabilities and capacities for waste
management so a prioritized and coordinated cleanup can begin as quickly as possible.


©2011, Waste Management

                                             Page 30
ONCE A “HURRICANE WATCH” IS ISSUED:
 Hurricanes and storms may generate contaminated debris or other atypical wastes that require
 special handling, processing, or disposal procedures that are not addressed by the facility permit
 and require special approval for disposal from the DOH SWS. After the potential effects of a
 hurricane are verified by local authorities (i.e., severe flooding, storm surge, high winds, etc.), the
 WGSL will consider acquiring supplies and materials (fuel, additional soil cover or alternate
 material, vehicles, heavy equipment, grinder/chippers, auxiliary lighting, pumps, generators, fire
 suppressant equipment, rain gear, personnel protective equipment, etc.) to ensure adequate
 equipment to handle the increase in waste and ensure airspace availability.
 In the event of a hurricane making landfall on the island of Oahu, WGSL personnel will perform
 the following as preparation:
       Conduct a briefing to entire staff on the status of conditions & severity of the hurricane and
       how it may impact the facility and service area / region. Discuss emergency operating
       procedures for facility.
       Power outages should be anticipated and procedures will be employed (when the WGSL
       re-opens to accept waste) as needed to manually track the date the waste was received,
       the quantity by weight or volume, and the origin of the waste.
       Inspect all drainage on-site structures to verify that they are in working order.
       Excessive silt in ditches and basins will be removed and the condition of pipes and
       discharge structures from basins will be verified.
       Diversion berms will be constructed around the current disposal area as needed to prevent
       run-on from entering the waste fill, and to prevent runoff from the waste fill areas of the
       site.
       Interim cover will be placed over exposed waste at the end of the working day.
       Holding capacity of leachate tanks and/or ponds will be increased to ensure additional
       volumes added during storm events can be accommodated.

ONCE A “HURRICANE WARNING” IS ISSUED:
       The EC (or manager in charge) will track the hurricane front (via radio, television, internet,
       etc.) and implement the following procedures to properly shutdown all operations at the
       WGSL:
             If possible, all electrical lines/breakers/gas valves should be shut down to prevent
             any potential fires. Unplug all appliances.
             Secure facility property, structures, landfill equipment, and office (preserve records
             and data [electronic and hard copies]) in case of flooding or power failure. Anything
             that is not secured may become a damaging projectile in the event of high winds.
             Cover all windows with wood panels (if possible).
             Check batteries and stock up on canned food, first aid supplies, and drinking water.
             Gas up vehicles, generators, and emergency tanks.
©2011, Waste Management

                                               Page 31
WGSL Management will require that site personnel return to their homes. If on-site,
      evacuate to the main office building and stay there (shelter in place) – stay away from
      windows.


AFTER THE HURRICANE:
      WGSL / WMH Management will promptly (when it is safe to do so) conduct a visual survey
      & damage assessment of the site to identify any compromised building structures, slope
      failures, downed power lines, gas and water leaks, broken electrical wiring or sewage lines
      fires, LFG system failures, tank leaks/spills, or other conditions that could threaten worker
      or public safety.
                If you smell gas, leave the area immediately, notify the utility company, and warn
                others to stay away. Do not re-open gas valve until the utility company has
                checked the system. Do not go wading through high waters – power / electrical
                lines may be down in the water.
                If fires occur, follow the procedures set forth in Section 3.2.
                If injuries occur, follow the procedures set forth in Section 3.3.
      Turn on portable radio for instructions and news reports. Cooperate fully with public safety
      officials and instructions.
      Do not use vehicles unless there is an emergency. Keep the streets clear for emergency
      vehicles.
      Remain calm and lend a hand to others.
      If the site is evacuated, leave a message telling others where personnel can be found.


   The EC (or manager in charge) will be responsible for:
             Ensuring that WGSL safety programs are fully implemented.
             Coordinating evacuation of the WGSL including notification of adjacent property
             owners/tenants, as required.
             Communicating with the City & County of Honolulu and the State of Hawaii, as well
             as local authorities and emergency response personnel to inform them:
                    1) When the WGSL becomes operational after the storm;
                    2) The situation at the WGSL, such as waste storage capacity, transportation
                       coordination, site conditions, personnel status, etc.
             In the event of inoperable telephone systems, notification of the appropriate
             agencies/businesses will be accomplished in the most expedient manner available
             (cellular/mobile phones, person to person, overnight mail, etc.).
             Notifying incoming drivers/haulers via radio or cell phone to avoid the site.
             Notifying WM Safety personnel of the emergency - determine whether a 24-Hour
             Report is required.

©2011, Waste Management

                                            Page 32
Conducting a Post-Hurricane Inspection (Post-Hurricane / Severe Storm Forms
               [Appendix B]).
Hurricanes leave behind debris made up of construction materials, damaged buildings, sediments,
green waste, and personal property. Hurricane debris obstructs roads and disables electrical
power and communication systems over wide areas. The goals of post-hurricane efforts will be to
increase debris diversion rates, minimize environmental impacts, reduce waste management costs,
minimize threats to health and safety, and shorten the duration of the cleanup effort. WMH may
be asked to provide assistance at collection sites across the island to monitor incoming debris.
These efforts will be coordinated with the DOH or emergency response personnel.


3.8 BOMB THREAT (PHONE CALL)
The most basic preventative measures are properly securing a facility so that an explosive device
cannot be easily placed without detection.
A higher probability of bomb threats due to a history of past threats, a neighborhood or community
trend, or a situation involving a particularly vengeful individual may warrant more extensive
measures such as more stringent security, training programs, package instructions, more involved
search and evacuation procedures, and recorders on appropriate telephones. Such a high
probability will also warrant more contact with local law enforcement authorities. The WGSL does
not have a high probability of bomb threats.

  WHEN THE THREAT IS CALLED IN:
       a) Listen while the caller talks and fill out the attached bomb threat call checklist.
       b) Inform the caller that the building is occupied and that the detonation of a bomb could
          result in death or serious injury to many innocent people.
       c) Attempt to determine the location and description of the bomb and time of detonation.
          Obtain as much information as possible including time of call, background noise, etc.
       d) Notify the WGSL District Manager or other on-site manager.
       e) WGSL Management will report the bomb threat to local police department.
       f)   Search the area if time permits. Do not touch any suspicious items. Report any
            suspicious items to the WGSL District Manager and the local police department.
       g) Evacuate the area where any suspicious items are located.


3.9 CIVIL DISTURBANCE/DEMONSTRATION
     Do not become a spectator. Leave the area of the disturbance to avoid injury or arrest.
     Lock all doors, gates, and windows. Close all drapes and avoid window areas. Do not argue
     with or agitate the participants.
     Remain calm, be courteous and do not do anything to provoke an incident.


©2011, Waste Management

                                               Page 33
Contact the WGSL District Manager and local police department as soon as possible.
       If required to protect employees and company property, service may have to be limited
       and/or access to the building may have to be restricted.
       Keep telephone lines open and avoid unnecessary inquiries regarding the incident.


3.10    ARMED ROBBERY
       If confronted by an armed robber, do not argue with the individual.
       Give the individual what he wants. Do not block his option to escape.
       Remember what you can about the incident including individual’s height, weight, hair length,
       color of eyes, color of hair, race, distinguishing marks or scars. If a weapon or vehicle is
       visible, try to remember as much detail about it as possible.
       After the incident is over, call the police immediately.
       Under no circumstances should you try to intercede or stop the robbers involved in the
       incident.




©2011, Waste Management

                                                 Page 34
BOMB THREAT CALL CHECKLIST:

 Date: _______________       Time: _______________    A.M. / P.M.

 Call Received by: ____________________________________________________________

 Exact words of caller: ________________________________________________________

 ___________________________________________________________________________

 ___________________________________________________________________________

 ___________________________________________________________________________

 Questions to Ask:

      When will bomb explode? ______________________________________________

      Where is the bomb located? _______________________________________________

      What does the bomb look like? _____________________________________________

      What kind of bomb is it? __________________________________________________

      Why did you place the bomb? ______________________________________________

      What do you hope to accomplish by this action? ________________________________

      What is your name? ______________________________________________________

      Where are you calling from? _______________________________________________

Voice Characteristics:

 Male ____     Female ____     Child ____     Loud ____       Soft ____          Nasal ____

 Raspy ____    High ____       Low ____       Familiar ____   Pleasant ____

 Other ______________________________________________________________________

Speech Characteristics:

 Fast ____     Slow ____       Stutter ____   Slurred ____    Intoxicated ____

©2011, Waste Management

                                          Page 35
Other ______________________________________________________________________

Accent Characteristics:

 Local ____       Region ____     Foreign ____

 Other _____________________________________________________________________

Manner of Caller:

 Calm ____           Angry ____           Deliberate ____        Emotional ____

 Laughing ____       Incoherent ____      Other ______________________________________

Background Noises:

 Office Machines ____ Street Traffic ____        Factory Machines ____   Music ____

 Airplanes ____           Trains ____            Trucks ____             Animals ____

 Other ______________________________________________________________________

Origin of Call:

 Internal ____ External ____      Local ____     Long Distance ____

 Did caller appear to be familiar with the facility? ____________________________________

 Number/extension at which call was received: ______________________________________

Contacts Made:

 Operations/District Manager:          Date __________________ @ _______ am / pm

 Police Department:                    Date __________________ @ _______ am / pm

 Fire Department:                      Date __________________ @ _______ am / pm

 Other:                                Date __________________ @ _______ am / pm

 Other:                                Date __________________ @ _______ am / pm

©2011, Waste Management

                                            Page 36
3.11   TERRORIST THREATS
 IN THE OFFICE:
        Close business.
        If there are customers or visitors in the building, provide for their safety by asking them
        to stay – not leave. When authorities provide directions to shelter-in-place*, they want
        everyone to take those steps immediately, where they are, and not drive or walk
        outdoors.
             *Note: One of the instructions you may be given in an emergency where hazardous
             materials may have been released into the atmosphere is to shelter-in-place. This is a
             precaution aimed to keep you safe while remaining indoors (this is not the same thing as
             going to a shelter in case of a storm). Shelter-in-place means selecting a small, interior
             room, with no or few windows, and taking refuge there. It does not mean sealing off your
             entire home or office building.

        Unless there is an imminent threat, ask employees, customers, and visitors to call their
        emergency contact to let them know were they are and that they are safe. Turn on call-
        forwarding or alternative telephone answering systems. Change the recording on voice
        mail to indicate that the business is closed, and that staff and visitors are remaining in
        the building until authorities advise it is safe to leave.
        Close and lock all windows, exterior doors, and any other openings to the outside. If
        you are told there is danger of explosion, close window shades, blinds, or curtains.
        Have employees familiar with your building’s mechanical systems turn off all fans and
        heating and air conditioning systems. Some systems automatically provide for
        exchange of inside air with outside air – these systems in particular need to be turned
        off, sealed, or disabled.
        Gather essential disaster supplies, such as nonperishable food, bottled water, battery-
        powered radios, first aid supplies, flashlights, batteries, duct tape, plastic sheeting, and
        plastic garbage bags.
        Select interior room(s) above the ground floor, with the fewest windows or vents. The
        room(s) should have adequate space for everyone to be able to sit in. Avoid
        overcrowding by selecting several rooms if necessary. Large storage closets, utility
        rooms, pantries, copy and conference rooms without exterior windows will work well.
        Avoid selecting a room with mechanical equipment like ventilation blowers or pipes,
        because this equipment may not be able to be sealed from the outdoors.
        It is ideal to have a hard-wired telephone in the room(s) you select. Call emergency
        contacts and have the phone available if you need to report a life-threatening
        condition. Cellular telephone equipment may be overwhelmed or damaged during an
        emergency.
        Use duct tape and plastic sheeting (heavier than food wrap) to seal all cracks around
        the door(s) and any vents into the room.

©2011, Waste Management

                                             Page 37
Bring everyone into the room(s). Shut and lock the door(s).
        Write down the names of everyone in the room, and call your business’ designated
        emergency contact to report who is in the room with you, and their affiliation with your
        business (employee, visitor, customer).
        Keep listening to the radio or television until you are told all is safe or you are told to
        evacuate. Local officials may call for evacuation in specific areas at greatest risk in
        your community.

 IN A VEHICLE:
 If you are driving a vehicle and hear advice to shelter-in-place on the radio, take these steps:
        If you are very close to home, your office, or a public building, go there immediately
        and go inside. Follow the shelter-in-place recommendations for the place you pick
        described above.
        If you are unable to get to a home or building quickly and safely, pull over to the side
        of the road. Stop your vehicle in the safest place possible. If it is sunny outside, it is
        preferable to stop under a bridge or in a shady spot, to avoid being overheated.
        Turn off the engine. Close windows and vents.
        If possible, seal the heating/air conditioning vents with duct tape.
        Listen to the radio regularly for updated advice and instructions.
        Stay where you are until you are told it is safe to get back on the road. Be aware that
        some roads may be closed or traffic detoured. Follow the directions of law
        enforcement officials.

 Local officials on the scene are the best source of information for your particular situation.
 Following their instructions during and after emergencies regarding sheltering, food, water,
 and clean up methods is your safest choice.

 Remember that instructions to shelter-in-place are usually provided for a duration of a few
 hours, not days or weeks. There is little danger that the room in which you are taking shelter
 will run out of oxygen – suffocation is not likely.




©2011, Waste Management

                                             Page 38
4.0   EMERGENCY EQUIPMENT & PPE
The EC monitors and stores all emergency equipment and PPE supplies stocked. Any
deficiencies in supply or operation are corrected as soon as possible.

      WGSL emergency equipment (and locations [see Figures 2a-2e]) consists of:
              Eye wash station (maintenance shop)
              Shovels
              Spill kit - contains absorbent (kitty litter), containment booms, sorbent pads
              (maintenance shop & mobile tank trucks)
              First aid kits (site vehicles & buildings)
              Fire extinguishers (all buildings, site vehicles & landfill equipment)


      WGSL PPE includes:
              Hard hats
              High visibility safety vests dust masks
              Ear plugs
              Steel toe work boots
              Safety glasses (as needed)
              Gloves




©2011, Waste Management

                                              Page 39
Removal Action Summary Report (pages 1-1015)
5.0   ADMINISTRATIVE PROCEDURES
The WMH Environmental Protection Manager will work with the EC to ensure that corrective
measures (if necessary) are implemented, follow-up reports / inspections are completed, and
that the appropriate agencies and parties are notified.


5.1 EMERGENCY REPORTING
  Emergency reporting will be in compliance with federal, state, local and WM requirements.
  WGSL reporting includes:
          Reporting of significant events/emergency incidents to the EC (or manager in
          charge), WMH Market Area Management, and to the WM Safety & Environmental
          Protection representatives.
          Reporting of significant events/emergency incidents to the proper agencies (if
          necessary) as soon as possible.
  If it is determined that the WGSL has had a release, fire, or explosion involving hazardous
  materials that could threaten human health, or the environment outside the facility, the
  following actions should be taken:
          The EC shall immediately notify the appropriate local authorities and help these local
          officials decide whether local areas should be evacuated.
          The Environmental Protection Manager will immediately notify the DOH HEER
          Office. This report shall include: name and telephone number of reporter; name and
          address of facility; time and type of incident; name and quantity of material(s)
          involved to the extent known; the extent of injuries, if any; and the possible hazards
          to human health, or the environment, outside the facility.


5.2 TRAINING
  In accordance with federal, state, local and WM requirements, WGSL personnel are trained
  annually on the Emergency Action Plan and what their roles/responsibilities are in the event
  of an emergency. The WGSL emergency training requirements include:
               As required, testing of the plan by key staff.
               Semi-annual drills with all employees (documentation form attached).
               Location of all emergency shut down and main electrical power switches.
               Fire hazards of the materials and hazards to which employees are exposed.
               Location and operation of fire extinguishers.
               Proper and safe handling of gasoline and other petroleum products including
               cleanup of minor spills.

©2011, Waste Management

                                             Page 41
Location of the WGSL Emergency Action Plan.
             Location of evacuation routes and re-assembly/evacuation points for the site.

 All trainings and drills are documented and placed in the WGSL Operating Record/Files.


5.3 PLAN UPDATE AND DISTRIBUTION
                The Emergency Action Plan is a living document and will be reviewed at least
                annually for accuracy and relevance and updated as warranted by changes in
                site conditions or procedures. Updates to this plan will be submitted to
                appropriate agencies in a timely manner. -

 The Emergency Action Plan is part of the WGSL Site Operations Manual, of which there are
 four controlled copies - Two (2) copies remain on-site at the WGSL, one (1) copy will be
 submitted to the DOH, and one (1) copy will be submitted to the City & County of Honolulu.
 Copies of the Plan will also be distributed to the following personnel/locations:

                  WGSL District Manager
                  WGSL Operations Specialist (Reception desk)
                  WMH Environmental Protection Manager
                  A copy will be placed in the lounge




©2011, Waste Management

                                          Page 42
APPENDIX A

                          FIRE PREVENTION PLAN




©2011, Waste Management

                                Page A-1
Removal Action Summary Report (pages 1-1015)
APPENDIX A - FIRE PREVENTION PLAN

This Fire Prevention Plan for the Waimanalo Gulch Sanitary Landfill (WGSL) designates:
                   Housekeeping procedures that help to prevent fires
                   Potential fire hazards
                   Proper handling and storage procedures for combustible materials
                   Potential ignition sources and their control procedures
                   Type of fire protection equipment available to control fire hazards

  The names and job titles of personnel responsible for maintenance of equipment and systems
  installed to prevent or control ignition of fires and control of accumulation of flammable or
  combustible waste materials are:

         WGSL District Manager
         WGSL Emergency Coordinator
         WGSL Mechanic
         WMH Director of Operations
         WMH Environmental Protection Manager


HOUSEKEEPING PROCEDURES FOR FIRE PREVENTION:

         Avoid the accumulation of combustible materials.
         Keep flammable and combustible materials away from ignition sources.
         Keep all stairways, fire fighting equipment locations, and exit paths clear.
         Report spill/leaks promptly to management to assure corrective action is taken.
         Remove all waste at the end of each shift and placing it in the appropriate waste
           receptacles.
         Store all oily rags in an approved receptacle.
         Store flammables in an approved flammable cabinet a minimum of 25 feet from
           sources of ignition;
         Store work clothes in metal lockers;
         Use correct cleaning agents and avoiding the use of flammable/combustible materials
           for cleaning.
         Contain and clean up fuel spills immediately. Soil contaminated with spilled fuel will be
           excavated and, if authorized, disposed of at the working face.


POTENTIAL FIRE HAZARDS, POTENTIAL IGNITION SOURCES, PROPER HANDLING/STORAGE
PROCEDURES, AND FIRE PROTECTION EQUIPMENT

Tables 1 and 2 list the potential fire hazards, potential ignition sources, proper handling/storage
procedures, and fire protection equipment that can control these hazards.

©2011, Waste Management
                                            Page A-3
Removal Action Summary Report (pages 1-1015)
EMERGENCY ACTION PLAN




                                                                        TABLE A-1

                SITE LOCATIONS WITH POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES


 LOCATION                 POTENTIAL FIRE HAZARDS                                                      POTENTIAL IGNITION SOURCES

 Administrative Offices   Combustible materials (e.g. paper, cardboard, etc.)                         Open flames (e.g. smoking materials, etc.)
                          Electrical cords/outlets/wiring                                             Hot surfaces (e.g. appliances, electrical wiring, etc.)
                          Flammable/combustible liquids (e.g. aerosol cans, solvents, etc.)           Open flames (e.g. smoking materials, etc.)
                          Flammable/oxidizing gases (e.g. hydrogen, methane, etc.)                    Static electricity



 Maintenance Shop         Flammable/combustible liquids (e.g. diesel, solvents, product oils, etc.)   Open flames (e.g. welding, smoking materials, etc.)
                          Combustible materials (e.g. paper, cardboard, etc.)                         Sparks from friction (e.g. grinding)
                          Electrical cords/outlets/wiring                                             Hot surfaces (e.g. power tools, electrical wiring, etc.)
                          Flammable/oxidizing gases (e.g. acetylene, oxygen, etc.)                    Static electricity
                          Open flames (e.g. welding, cutting, etc.)                                   Internal combustion engines (e.g. vehicles, forklifts, etc.)
                          Contaminated materials (e.g. oily rags, etc.)                               Open flames (e.g. welding, smoking materials, etc.)



 Storage Containers       Flammable/combustible liquids (e.g. paints, solvents, etc.)                 Open flames (e.g. welding, smoking materials, etc.)
                          Combustible materials (e.g. paper, cardboard, etc.)                         Sparks from friction (e.g. grinding)
                          Electrical cords/outlets/wiring                                             Hot surfaces (e.g. power tools, electrical wiring, etc.)
                          Flammable/oxidizing gases (e.g. acetylene, oxygen, etc.)                    Static electricity
                          Open flames (e.g. welding, cutting, etc.)                                   Internal combustion engines (e.g. vehicles, forklifts, etc.)
                          Contaminated materials (e.g. oily rags, etc.)                               Open flames (e.g. welding, smoking materials, etc.)




©2011, Waste Management
                                                                         Page A-5
EMERGENCY ACTION PLAN



                                                                    TABLE A-2


                                      CONTROL PROCEDURES AND FIRE PROTECTION EQUIPMENT
                                   FOR POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES



 POTENTIAL FIRE HAZARDS/
 IGNITION SOURCES                          CONTROL PROCEDURE/FIRE PROTECTION EQUIPMENT



 Combustible materials                     Avoid accumulation of combustible materials (e.g. empty boxes, cartons, loose paper, etc.)
                                           Keep combustible materials away from ignition sources including establishment/enforcement of no smoking/no open
                                               flame areas
                                           Keep all stairways, firefighting equipment locations and exit paths clear
                                           Remove all waste (e.g. dust, lint, loose paper, etc.) at the end of each shift in each work area (including floors,
                                               ceilings, walls, ledges, beams, and equipment) and place in appropriate waste receptacle
                                           Store work clothes in metal lockers
                                           Maintain fire extinguishing equipment capable of handling Class A fires within 75 feet of combustible materials
                                           Perform annual maintenance and monthly inspections on fire extinguishing equipment
                                           Train personnel in use of fire extinguishing equipment




 Electrical cords/outlets/wiring           Inspect power cords for damaged insulation and damaged plugs
                                           Discontinue use of a power cord that gets warm
                                           Maintain electrical motors in good operating condition
                                           Do not overload motors, cords or other electrical equipment
                                           Maintain fire-extinguishing equipment capable of handling Class C fires near electrical equipment
                                           Perform annual maintenance and monthly inspections on fire extinguishing equipment
                                           Train personnel in use of fire extinguishing equipment




©2011, Waste Management
                                                                    Page A-6
EMERGENCY ACTION PLAN



 Flammable/combustible liquids       Keep materials in covered containers when not in use
                                     Do not transport materials in open containers
                                     Store flammable liquids in containers with appropriate warning labels
                                     Do not store near sources of heat/ignition
                                     Inert and verify inert atmosphere of containers, piping, tanks that have contained flammable/combustible liquids
                                     prior to exposure to heat/flame
                                     Maintain fire-extinguishing equipment capable of handling Class B fires within 50 feet of flammable/combustible
                                         liquids
                                     Perform annual maintenance and monthly inspections on fire extinguishing equipment
                                     Train personnel in use of fire extinguishing equipment


 Welding/cutting operations          Establish approved areas for cutting and welding
                                     Establish approved procedures for a hot work program to restrict cutting/welding in all other areas along with a
                                          designated individual for approving such cutting/welding
                                     Utilize only approved equipment for cutting/welding
                                     Train all personnel that perform cutting/welding
                                     Verify training of contractors who perform cutting/welding
                                     Provide contractor orientation of potential fire hazards on-site
                                     Do not perform cutting/welding within 35 feet of combustible materials
                                     Implement hot work permit program
                                     Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near the welding operation
                                     Perform annual maintenance and monthly inspections on fire extinguishing equipment
                                     Train personnel in use of fire extinguishing equipment



 Flammable/oxidizing gas cylinders   Do not store cylinders near sources of heat/flame
                                     Cylinders stored inside buildings will be in a well-protected, well-ventilated, dry location at least 20 feet from highly
                                         combustible materials
                                     Cylinders storage will be located where passing/falling objects will not damage cylinders
                                     Do not sore cylinders where they could be subject to tampering by unauthorized personnel
                                     Do not store cylinders near elevators, stairs or passageways
                                     Do not store cylinders in unventilated enclosures
                                     Do not store oxygen cylinders near highly combustible materials such as oil/grease




©2011, Waste Management
                                                                Page A-7
EMERGENCY ACTION PLAN


                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires within 75 feet of welding areas


 Open flames                   Keep sources of ignition including open flames away from combustible materials
                               Establish and enforce no smoking/no open flame areas
                               Establish and enforce a hot work program
                               Maintain fire extinguishing equipment capable of handling Class A, B, C fire near areas with open flames

 Contaminated materials        Keep sources of ignition away from contaminated materials
                               Store contaminated materials in appropriate waste receptacle (e.g. oil rag container)
                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires where contaminated materials
                                  are stored

 Hot surfaces                  Keep sources of ignition including hot surfaces away from combustible materials
                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near areas with hot surfaces


 Sparks from friction          Keep sources of ignition including sparks from friction away from combustible materials
                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near areas where sparks from
                                  friction may occur


 Static electricity            Utilize proper grounding/bonding procedures when moving volatile liquids
                               Verify continuity of grounds on a regular basis
                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires within 50 feet of
                                    flammable/combustible liquid storage


 Internal combustion engines   Maintain internal combustion engines in good repair
                               Clean up spills/leaks from internal combustion engines promptly and store contaminated material safely
                               Report spills/leaks from internal combustion engines promptly to supervision to assure corrective action is taken
                               Maintain fire extinguishing equipment capable of handling Class A, B, and C fires on all vehicles




©2011, Waste Management
                                                         Page A-8
EMERGENCY ACTION PLAN




©2011, Waste Management
                          Page A-9
EMERGENCY ACTION PLAN



FIRE PROTECTION EQUIPMENT
The WGSL is equipped with fire extinguishers that are fully charged and ready for use at all
times. Each extinguisher is inspected on an annual basis and recharged as necessary. A
qualified service company performs the annual inspections, and all extinguishers display a
current inspection tag. Inspection and recharging will be performed following each use. The
main office, scale house, all landfill equipment, and landfill vehicles are equipped with fire
extinguishers.

The fire prevention plan and fire control procedures for the WGSL will be revisited following the
occurrence of a significant fire to determine if modifications are warranted.


FIRE EXTINGUISHER USE
All WGSL equipment operators are trained annually on the proper usage of fire extinguishers.
Documentation of training sessions are kept on-site as part of the WGSL Operating
Record/Files.

All landfill equipment has a charged ABC fire extinguisher with at least a 20-pound rating. This
type of extinguisher is good for:

       A – Ordinary combustibles (paper, leaves, general trash, etc.)
       B – Flammable liquids (diesel fuel, hydraulic oil, motor oil, etc.)
       C – Electrical equipment (electrical wiring system on the equipment)

Use the P.A.S.S. method for extinguishing a small fire:

P ull the pin.
A im at the base of the flame.
S queeze the handle.
S weeping motion from side-to-side.

If the fire has grown beyond a small fire, clear the area and allow the fire department to
extinguish the fire.




©2011, Waste Management
                                            Page A-10
EMERGENCY ACTION PLAN




                               APPENDIX B

                          POST EARTHQUAKE FORMS

                                    &

                POST HURRICANE / SEVERE STORM FORMS




©2011, Waste Management
                                 Page B-1
Removal Action Summary Report (pages 1-1015)
EMERGENCY ACTION PLAN




                      WAIMANALO GULCH SANITARY LANDFILL
                      POST EARTHQUAKE INSPECTION SHEET

Date of Earthquake:
Date of Inspection:

Distance from Epicenter:
Epicenter Location:
.
Time of Earthquake:
Time of Inspection:

Person(s) Conducting Inspection:




                                                        Damage Evident
                                                        Yes        No
Drainage Structures
             west side rip-rap
             head of drainage channel
             interceptor drains
             down drains
             sedimentation basin
             inlet/outlet structures (risers)




Fueling / Maintenance Area
              600-gallon (diesel) mobile lube truck
              5000-gallon (diesel) truck (stationary)
              maintenance buildings/containers
              360-gallon waste oil AST (Above
                 Ground Storage Tank)
              360-gallon hydraulic oil AST
              miscellaneous 55-gallon drums

       Any leaks/spills?_______________



©2011, Waste Management
                                         Page B-3
EMERGENCY ACTION PLAN




Side Slopes
Landfill Cover
Access Roads
Landfill Heavy Equipment
Fencing



                                                    Damage Evident
                                                    Yes        No
Facility Buildings
               admin office
               scale house
               telephones
               lounge/ breaker trailer
               computers
               scales
              parking lot

Water Supply
              main water meter
              mainline
              water truck
              backflow preventer

Sewer Line(s)
Power Line(s)

Leachate Collection Systems
             E1 riser
         o frac tank
         o sump/riser
         o transducer system/panel
         o pipes/hoses
         o pumps
         o power
         o berms

           Ash riser
           o frac tank

©2011, Waste Management
                                         Page B-4
EMERGENCY ACTION PLAN

          o   sump/riser
          o   transducer system/panel
          o   pipes/hoses
          o   pumps
          o   power
          o   berms

          4B riser
          o frac tank
          o sump/riser
          o transducer system/panel
          o pipes/hoses
          o pumps
          o power
          o berms

          E6 riser
          o frac tank
          o sump/riser
          o transducer system/panel
          o pipes/hoses
          o pumps
          o power
          o berms

       Any leaks/spills?_______________
       Any vapors evident?______________



                                                    Damage Evident
                                                    Yes        No

Flare Station /System
           concrete pad/skid
           condensate injection system
           condensate poly tank(s)
           gas header pipe
           gas wells
           power supply
           system panel
           flare stack
Any leaks/spills?_______________

©2011, Waste Management
                                         Page B-5
EMERGENCY ACTION PLAN




Any evidence of physical change around the gas wells such as:
          differential settlement? ___________________
          compromised seal integrity?_________________


Perimeter Gas Probes

Groundwater Wells
        concrete pads
        housing
        casing
        guard posts/fencing

Any evidence of damage to wells such as:
          ponded water?________________
          settlement around the wells? ____________

Was there any damage to landfill structures, cover or systems caused by the above
seismic event?
YES                  NO

 If yes, complete an Earthquake Damage Report Form.




©2011, Waste Management
                                      Page B-6
EMERGENCY ACTION PLAN

                     WAIMANALO GULCH SANITARY LANDFILL
                           92-460 Farrington Highway
                               Kapolei, HI 96707
                      EARTHQUAKE DAMAGE REPORT FORM



Date / Time of Seismic Event:
Date / Time of Inspection:

Note: Fill out one form for each damage observation.



1. What is damaged?

2. Location of damage:

3. Description of Damage:



Log of Corrective Actions Implemented:




Date damage was repaired:

Damage repaired by:




©2011, Waste Management
                                         Page B-7
EMERGENCY ACTION PLAN




©2011, Waste Management
                          Page B-8
EMERGENCY ACTION PLAN

                   WAIMANALO GULCH SANITARY LANDFILL
             POST HURRICANE / SEVERE STORM INSPECTION SHEET

Type of Storm (Depression, Tropical Storm, Hurricane):   ______________________
Date of Storm:                                                             ____
Date of Inspection:                                                        ____

Category of Hurricane (if applicable):                                    ____
Recorded Wind Speed(s):
.
Time of Hurricane:
Time of Inspection:

Person(s) Conducting Inspection:




                                                         Damage Evident
                                                         Yes        No
Drainage Structures
             west side drainage rip-rap
             head of drainage channel
             interceptor drains
             down drains
             sedimentation basin
             inlet/outlet structures (risers)




Fueling / Maintenance Area
              600-gallon (diesel) mobile lube truck
              5000-gallon (diesel) truck (stationary)
              maintenance buildings/containers
              360-gallon waste oil AST (Above
                 Ground Storage Tank)
              360-gallon hydraulic oil AST
              miscellaneous 55-gallon drums

       Any leaks/spills?_______________




©2011, Waste Management
                                         Page B-9
EMERGENCY ACTION PLAN

Side Slopes
Landfill Cover
Access Roads
Landfill Heavy Equipment
Fencing



                                                     Damage Evident
                                                     Yes        No
Facility Buildings
               admin office
               scale house
               telephones
               lounge/ breaker trailer
               computers
               scales
              parking lot

Water Supply
              main water meter
              mainline
              water truck
              backflow preventer

Sewer Line(s)
Power Line(s)

Leachate Collection Systems
         E1 riser
         o frac tank
         o sump/riser
         o transducer system/panel
         o pipes/hoses
         o pumps
         o power
         o berms




©2011, Waste Management
                                         Page B-10
EMERGENCY ACTION PLAN

          Ash riser
          o frac tank
          o sump/riser
          o transducer system/panel
          o pipes/hoses
          o pumps
          o power
          o berms

          4B riser
          o frac tank
          o sump/riser
          o transducer system/panel
          o pipes/hoses
          o pumps
          o power
          o berms

          E6 riser
          o frac tank
          o sump/riser
          o transducer system/panel
          o pipes/hoses
          o pumps
          o power
          o berms

       Any leaks/spills?_______________
       Any vapors evident?______________

                                                 Damage Evident
                                                 Yes        No
Flare Station /System
           concrete pad/skid
           condensate injection system
           condensate poly tank(s)
           gas header pipe
           gas wells
           power supply
           system panel
           flare stack



©2011, Waste Management
                                     Page B-11
EMERGENCY ACTION PLAN

Any leaks/spills?_______________


Any evidence of physical change around the gas wells such as:
          differential settlement? ___________________
          compromised seal integrity?_________________




Perimeter Gas Probes

Groundwater Wells
        concrete pads
        housing
        casing
        guard posts/fencing

Any evidence of damage to wells such as:
          ponded water?________________
          settlement around the wells? ____________

Was there any damage to landfill structures, cover or systems caused by the above
storm event?
YES                  NO

 If yes, complete a Hurricane / Severe Storm Damage Report Form.




©2011, Waste Management
                                     Page B-12
EMERGENCY ACTION PLAN

                     WAIMANALO GULCH SANITARY LANDFILL
                           92-460 Farrington Highway
                               Kapolei, HI 96707
          POST HURRICANE / SEVERE STORM DAMAGE REPORT FORM


Type of Storm (Depression, Tropical Storm, Hurricane):   ______________________
Date / Time / Duration:                                       ________________
Date / Time of Inspection:                                    ________________

Note: Fill out one form for each damage observation.



1. What is damaged?

2. Location of damage:

3. Description of Damage:



Log of Corrective Actions Implemented:




Date damage was repaired:

Damage repaired by:




©2011, Waste Management
                                      Page B-13
EMERGENCY ACTION PLAN




©2011, Waste Management
                          Page B-14
EMERGENCY ACTION PLAN




TRAINING



 Training will be per the “Training” subsection of the Emergency Action Plan and Fire
 Prevention Plan.



 This Program is hereby approved:




 _________________________________               ____________________________
           SIGNATURE                                         DATE




©2011, Waste Management
                                    Page B-15
Removal Action Summary Report (pages 1-1015)
EMERGENCY ACTION PLAN




DOCUMENTATION OF SEMI-ANNUAL DRILL



Date Performed_________________________________________________________

Facility Name___________________________________________________________

Certified By __________________________   Title ____________________________

Comments_____________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________

______________________________________________________________________




©2011, Waste Management
                                 Page B-17
Removal Action Summary Report (pages 1-1015)
EMERGENCY ACTION PLAN




ACKNOWLEDGEMENT FORM



I, (print name) ________________________________________ have received training

on the Waimanalo Gulch Sanitary Landfill Emergency Action Plan Program. I had the

opportunity to have questions answered pertaining to the training material and

instructions that were presented to me by the Company. I understand the training I have

received and agree to abide by the standards presented.




_________________________________________
            (Employee) Print Name


_________________________________________
            (Employee) Signature


_________________________________________
            (Instructor) Print Name


_________________________________________
            (Instructor) Signature


_________________________________________
                  Date




©2011, Waste Management
                                      Page B-19
Removal Action Summary Report (pages 1-1015)
Personal Protective Equipment Program

Program: Personal Protective Equipment

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707



Introduction

Personal protective equipment (PPE) is used in the workplace to protect employees from hazards to the
eyes, face, hands, skin, head, and feet when engineering and administrative controls are not feasible.
PPE can also provide protection against heat or cold and hazardous chemicals. It can act as a shield or
barrier between the worker and the hazardous chemical.

PPE does not remove the hazard from the workplace, so it is the last line of defense before the hazard
reaches the employee. Do not rely on PPE alone to provide protection against hazards. PPE should be
used in conjunction with guards, engineering controls, and sound operational practices.

PPE is only as good as the consistency with which employees wear it. PPE effectiveness relies on the fit,
use and maintenance by the employees. PPE is effective only if it is properly selected based on the
hazards present and it is worn in the way it has been designed to be used.

Performed by a person who can assess the hazards carefully, it is important for everyone to know the
hazards in their area, and to use and take care of the PPE that is selected to protect them.

OSHA regulations 29 CFR 1910.132-133 and 135-138 cover personal protective equipment.

CORE PROGRAM
Responsibility
Joe Whelan, Donny Carder or designee, is responsible for administering the personal protective
equipment program. These duties include:

        Implementing the program.
        Ensuring that a hazard assessment is conducted.
        Ensuring that personal protective equipment is available.
        Reviewing the program on an annual basis.
        Ensuring that employee training is conducted.

Supervisors are responsible for ensuring employees wear personal protective equipment in required areas
and that they wear their personal protective equipment properly.

Employees must wear personal protective equipment where required. They must learn how to wear it
properly, and keep it clean and well maintained.



Job Hazard Assessment (JHA)
The general requirements for personal protective equipment are in 29 CFR 1910.132. This standard
requires the completion of a Job Hazard Assessment, sometimes referred to as a Job Safety Analysis


Personal Protective Equipment                                                                   Page 1
©2011, Waste Management                                                                   January 2011
Personal Protective Equipment Program
(JSA). The Job Hazard Assessment identifies hazards present or likely to be present that require the use
of personal protective equipment (PPE).


The written Job Hazard Assessment, must include the following:

       The specific tasks evaluated
       The name of the person verifying that the hazard assessment was performed
       The date of the hazard assessment
       Indication that the purpose of the hazard assessment is determining PPE requirements
       Perform a hazard assessment using the PPE assessment form in the appendix or an equivalent
       form. Use this form to select
PPE based on the identified hazards.

(See Attachment A: Job Hazard Analysis 2004)

Once the facility performs the Job Hazard Assessment and selects and makes available
PPE, training must be conducted to:

        Inform the affected employees of the PPE required for each hazard and its limitations.
        Select PPE that properly fits each employee.
        Inform of the proper use, care, cleaning and maintenance of the PPE.

It is important to remember that anyone who enters the area where employees are required to wear PPE
must wear the same type of PPE. For example, office personnel should be required to wear traffic safety
vests and appropriate footwear whenever they enter the tipping floor, as they are exposed to similar
vehicle traffic and material hazards as the workers who are spotting trucks.
Similarly, supervisors and contractors should be required to wear, at a minimum, the same PPE as the
other workers in their immediate work area.

A good practice is to have boxes with at least eye and hearing protection located at the entrance to shop
areas, tipping floor, landfill office. Office personnel or visitors can don the PPE and return it when
finished.

Eye and Face Protection
OSHA requires the use of eye and face protection (29 CFR 1910.133). Employees exposed to flying
materials must use eye protection, such as safety glasses with side protection Permanently attached side
shields are preferred, however, slide on side shields are acceptable if they meet the ANSI standards.

Employees must use safety glasses with side shields for the following hazards:

        Flying particles
        Compressed air
        Impact

Safety glasses and a face shield are required when exposed to:

        Liquid chemicals
        Acids or other chemicals that can burn, corrode, or dissolve
        Debris as in construction and/or demolition




Personal Protective Equipment                                                                   Page 2
©2011, Waste Management                                                                   January 2011
Personal Protective Equipment Program
Goggles to protect against:
                Chemical gases or vapors
                Light radiation (with the proper filter shade)


All eye and face protection must:

        Provide adequate protection for the hazards in the work area.
        Fit properly and comfortably.
        Be kept in a clean condition.
        Be kept in good repair.
        Meet the American National Standard practice for occupational and educational eye protection.

If exposed to light radiation, use the appropriate eye PPE, as indicated in the table under 29 CFR
1910.133 (a) 5. A copy of the table can be found in the Appendices.

If employees must wear corrective lenses and eye/face protection, provide them with:

        Eye protection that has corrective lenses built in, or
        Eye protection that can be worn over corrective lenses without interfering with the position of the
        lenses or the protection.

All eye and face protection purchased after July 5, 1994, must comply with ANSI
Z87.1-1989, the American National Standard practice for occupational and educational eye and face
protection. Any eye protection purchased before July 5,
1994 must comply with ANSI Z87.1-1968, the USA Standard for Occupational and
Educational Eye and Face Protection.


Head Protection
Head protection is required to be worn to prevent injury to the head from falling objects or from striking
the head against hard surfaces. Refuse can fall from elevated truck bodies, conveyors and work
platforms, creating an impact hazard. Low-hanging surfaces, such as walkways under conveyors and
roof supports on elevated sorting platforms, can present bump hazards.

Hard hats must be worn where impact and penetration hazards can occur from falling objects. They are
generally worn at landfills in the active disposal and borrow areas. Hard hats are also worn at material
recovery facilities
(MRFs) on the tipping floor and in locations where employees are assigned to work below sorting
platforms and conveyors.

Bump caps provide protection from head bumps, but do not provide impact or penetration protection.
Application of bump caps should be limited in the refuse industry. Most exposures in the industry that
involve head protection require the use of hard hats. Bump protection may be appropriate for work
performed under vehicles and in work, or passage to work areas, involving low overhead clearances.
When selecting head protection, know if there are potential electrical hazards in the work area. Special
non-conductive head protection must be worn if electrical hazards are present. All head protection must
meet the requirements of ANSI Z89.1-1986, the American National Standard for Personnel Assurance
Protection-Protective Headwear for Industrial Workers requirements.




Personal Protective Equipment                                                                    Page 3
©2011, Waste Management                                                                    January 2011
Personal Protective Equipment Program

Foot Protection
Protective footwear should be worn when working in areas where there is a danger of foot injuries due to
falling or rolling objects or objects piercing the sole, and where there may be electrical hazards. Safety
footwear is labeled to show that it meets the requirements and specifications in the "American National
Standard for Personal Protection - Protective Footwear" ANSI Z41-1991 and OSHA 29 CFR 1910.136.
Work boots with puncture and oil resistant, slip resistant soles and a minimum six-inch high lace-up ankle
support are acceptable for drivers and residential helpers. Where employees are assigned or allowed to
walk on refuse, such as when tarping a load or working in the active area of a landfill or on a transfer
station tipping floor, they should be required to wear work boots with steel mid-sole. Steel shank
protection in work boots provides limited protection of the soles and may not be used in place of steel
mid-soles.
In some cases, metatarsal protection or chemical impermeability may be prescribed for drum handling.
Steel toe safety shoes are required when it is necessary to protect an employee's feet from injury from
heavy material rolling over or dropping on toes. Mechanics, and other employees, who are involved in
work with moving heavy objects, such as commercial containers on casters, should be required to wear
steel-toed safety shoes. Minimum acceptable footwear for hauling, landfill, transfer and MRF workers is a
substantial shoe. A substantial shoe is one that is constructed of leather or leathher like materials and
covers the foot and ankle above the anklebone. Tennis shoes are not considered to be substantial shoes.

Hand Protection
Employees whose hands are exposed to hazards must be provided hand protection as required by 29 CFR
1910.138. Employees must use hand protection when conditions may cause:

        Exposure to hazardous substances, which can damage or be absorbed through the skin
        Cuts/scrapes/abrasions
        Punctures (such as needle sticks).
        Injury from extreme temperatures (hot or cold)

No single type of glove will provide protection against all hand hazards. Most glove materials provide
only limited protection against many chemicals.
Therefore, it is important to select the most appropriate glove for a particular application and to
determine how long it can be worn, and whether it can be reused. It may be more cost effective to
regularly change cheaper gloves than to clean and reuse more expensive types.


It is also important to know how the gloves perform against the specific hazard;
e.g., chemical hazards, cuts, heat, etc. Glove manufacturers have standard test procedures to assess
these performance characteristics. Before selecting gloves, request documentation from the
manufacturer that the gloves meet the appropriate test standard(s) for the hazard(s) anticipated. For
chemicals, consult the material safety data sheet or other health and safety references to identify the
compatible material.

Many refuse collection; recycling, transfer and disposal employees will be provided with or will choose to
wear leather gloves. Leather gloves generally offer durable protection for material handling tasks.
However, leather gloves do not grip well when neither wet, nor do they withstand repeated
decontamination or cleaning. Palm-dipped (canvas backed) nitrile gloves and other similar gloves coated
with synthetic and natural rubbers can provide acceptable alternatives to leather.

Arm protection is used in recycle sorting and other operations where employees may be exposed to cuts
and abrasions to the forearms. Exposure can occur when employees are reaching across conveyors, into



Personal Protective Equipment                                                                    Page 4
©2011, Waste Management                                                                    January 2011
Personal Protective Equipment Program
mixed refuse/recyclables and into refuse containers. Sleeves made of Kevlar and/or PVC can be used as
protection.
Where there is a potential for exposure to the forearms from chemicals (e.g., reaching into chemical
detergent containers), cold, or heat (e.g., from welding or cutting) appropriate protective sleeves may
also be worn.

Select hand protection based on the hazards identified.

Protective Clothing
Protective clothing can include the following:

        Uniforms
        Enhanced visibility clothing/accessories
        Chemical protective clothing
        Welders / painters cottons

Residential drivers and helpers, landfill spotters, and employees working in or near motor vehicle traffic
should wear enhanced visibility uniforms obtained through the company yellow sheet program.

Enhanced visibility elements must appear on the outer most layer of clothing to be effective. Periodic
monitoring of employee use of enhanced visibility clothing by supervisors is an important component in
ensuring that employees wear enhanced visibility clothing when it is required.

Employees potentially exposed to hazardous chemicals, extreme heat, or cold should use protective
clothing appropriate to the hazard. Selection of protective clothing requires a clear understanding of the
potential hazards and the limitations of the protective clothing. For chemicals, consult the Material
Safety Data Sheet (MSDS) or other toxicology references to identify compatible materials.

Wear rain gear as needed. Incorporate enhanced visibility into the rain gear as required.

Respiratory Protection
Refer Respiratory Protection Program.

Hearing Protection
Refer Hearing Conservation Program.
Control the Hazard
Control the hazards at the source, if possible. Rely on PPE as the last line of defense in controlling
hazards. PPE should be used as a supplement to guards, engineering controls, and sound operational
practices.

Care Of PPE
Some of the PPE, such as earplugs, coveralls, and gloves, may be disposable.
Ensure that non-disposable PPE is carefully maintained so that it continues to give full protection.

Recognize Limitations of PPE
PPE provides important protection, but it has limitations. PPE can be hot, bulky, and heavy. It can make it
harder to move freely while doing a job. It can increase fatigue and cut down on the ability to see, hear,
and feel. All of these limitations can create stress. The best PPE selection minimizes stress and maximizes
protection.




Personal Protective Equipment                                                                     Page 5
©2011, Waste Management                                                                     January 2011
Personal Protective Equipment Program
Defective PPE
Damaged, defective, or worn out PPE cannot provide the necessary protection. PPE must be inspected
before each use to see if it has been degraded or weakened by contact with a chemical, excessive wear
or abuse. Look for holes, defects, rips, or seam openings in the PPE that could let a chemical penetrate.


Training
Employee training must include the following information:

        Where and when to wear PPE
        What PPE to wear
        How to properly don, doff, adjust, and wear PPE
        How to properly care for and maintain PPE
        What the limitations of PPE are
        How to identify when PPE is no longer usable

All employees required to wear PPE must demonstrate that they understand how to properly wear, use,
clean, and maintain their PPE.

Employees require retraining when:

        They improperly wear, use, clean, or maintain PPE, or otherwise show that they lack these skills.
        Whenever there are new work practices or equipment, or requirements for PPE have changed.
        Whenever a worker is assigned to a task that requires different PPE or places additional
        limitations on the PPE that the worker is already trained to use.

Record Keeping
Document training in the employee training record. The record should include the following information:

        A statement that each employee has received and understands the PPE training
        The content of the training
        The names and signatures of the employee
        The date(s) of training
        The name of the person who provided the training

DEFINITIONS
Administrative Controls: Controls such as job rotation, different work assignments, or time away from
the hazard.

Engineering Controls: Methods of controlling employee exposures by modifying the source or reducing
the quantity of contaminants released into the work environment.

Job Hazard Assessment: A process used to identify hazards present or likely to be present, to
determine the proper PPE usage when performing job related tasks.

Personal Protective Equipment (PPE): Equipment worn by the worker to protect against hazards.
Examples include gloves, respirators, and hearing protection.




Personal Protective Equipment                                                                    Page 6
©2011, Waste Management                                                                    January 2011
Personal Protective Equipment Program
_________________________________________________________________________
Reviewed by:                            Date:

   Date of      Print Name      Signature    Comments – Changes to Program
   Review




Personal Protective Equipment                                         Page 7
©2011, Waste Management                                         January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Delivery Driver
                 Drives flat bed truck, box type truck, pick up truck with trailer, trucks adapted with
   Job
Description
                 container forks. Delivers and retrieves a variety of containers (bins, carts, toters).
                 Loads and unloads truck manually, with dollies, lift gates.
Check All That
    Apply                                                   Tasks
                 Conducts pre/post trips inspections daily on vehicles driven
                 Ascends/descends cab of vehicle throughout day for various reasons
                 Operates hydraulic control levers while seated in cab for various reasons
                 Operates hydraulic control levers while standing outside of vehicle for various reasons
                 Checks/fills fluid levels twice daily as part of pre/post trip inspections
                 Fuels vehicle
                 Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                 Communicates via two-way radio with dispatch and co-workers
                 Paperwork daily
                 Daily sequencing of route
                 Drives to various customer locations, post collection facility to/from office and route
                 Loads and unloads truck/trailer by hand, with dolly or with lift gate.
                 Places containers at customer location or at company facility
Additional Tasks




    Personal Protective Equipment                                                                Page 8
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Delivery Driver
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.



Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                             Page 9
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Driver - Commercial
                 Drives front loading truck; collects refuse from commercial customers at various
   Job           locations throughout the day; loads and compacts refuse using hand controls until
Description      truck is full then drives to post collection facility (landfill, transfer station, MRF, etc.)
                 for emptying of truck 1-3 times per day.
Check All That
    Apply                                                   Tasks
                 Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                 Ascends/descends cab of vehicle throughout day for various reasons
                 Operates hydraulic control levers while seated in cab for various reasons
                 Operates hydraulic control levers while standing outside of vehicle for various reasons
                 Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at
                 landfill to dump out truck contents
                 Cleans out behind packer blade after dumping out
                 Cleans off debris from apron or hopper area
                 Checks/fills fluid levels twice daily as part of pre/post trip inspections
                 Fuels vehicle
                 Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                 Pushes, pulls, rolls loaded/empty containers of various sizes (1yd-4yd) by hand to load onto
                 lifting forks and back to original position
                 Communicates via two-way radio with dispatch and co-workers
                 Operates MCC (onboard computer system) by hand
                 Occasionally places stickers on containers of company name/phone number and potential
                 safety hazards
                 Occasionally repairs/replaces broken/worn wheels on containers
                 Paperwork daily
                 Daily sequencing of route
                 Drives to various customer locations, dump site, to/from office and route
                 Cleans/shovels spillage at customer location
                 May also lift various types of trash cans/roller carts to dump into bin or attach to tipper on
                 lifting forks of vehicle (weight of cans/carts can be up to 60 lbs and occasionally more)
Additional Tasks




    Personal Protective Equipment                                                               Page 10
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Driver - Commercial
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling Debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 11
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Helper - Commercial
                 Assists Front End Loader Driver collecting refuse from commercial customers at
   Job
Description
                 various locations throughout the day. Pushes bins, loads and compacts refuse using
                 hand controls until truck is full. Relocates bins back to original position.
Check All That
    Apply                                                   Tasks
                 Ascends/descends cab of vehicle throughout day for various reasons
                 Operates hydraulic control levers while standing outside of vehicle for various reasons
                 Cleans off debris from apron or hopper area
                 Walks to/from office to vehicle parking lot, around vehicle at landfill , at customer location
                 Pushes, pulls, rolls loaded/empty containers of various sizes (1yd-4yd) by hand to load onto
                 lifting forks and back to original position
                 Communicates via two-way radio with dispatch and co-workers
                 Occasionally places stickers on containers of company name/phone number and potential
                 safety hazards
                 Occasionally repairs/replaces broken/worn wheels on containers
                 Paperwork daily (as required)
                 Daily sequencing of route (as required)
                 Cleans/shovels spillage at customer location
                 May also lift various types of trash cans/roller carts to dump into bin or attach to tipper on
                 lifting forks of vehicle (weight of cans/carts can be up to 60 lbs and occasionally more)
Additional Tasks




    Personal Protective Equipment                                                               Page 12
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Helper - Commercial
          Hazard                       Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 13
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program


                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Rear End Loader Driver – Residential/Commercial
                 Drives rear loading truck; collects refuse from residential and commercial customers
                 on a route throughout the day. Loads rear hopper of truck either manually or with
   Job
Description
                 tippers until truck is full. May empty commercial bins if truck is equipped. Then
                 drives to post collection facility (landfill, transfer station, MRF, etc.) for emptying of
                 truck 1-3 times per day.
Check All That
    Apply                                                    Tasks
                 Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                 Ascends/descends cab of vehicle throughout day for various reasons
                 Operates hydraulic control levers while seated in cab for various reasons
                 Operates hydraulic control levers while standing outside of vehicle for various reasons
                 Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at
                 landfill to dump out truck contents
                 Cleans out behind packer blade after dumping out
                 Cleans off debris from hopper area
                 Checks/fills fluid levels twice daily as part of pre/post trip inspections
                 Fuels vehicle
                 Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                 Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                 load into rear hopper of truck either manually or using the tipper. May also load bags, boxes
                 and other bulky items.
                 May also push/pull larger bins (1/2 to 4 yard) to rear of truck for tipping if truck is equipped
                 Communicates via two-way radio with dispatch and co-workers
                 Operates MCC (onboard computer system) by hand
                 Occasionally places stickers on containers of company name/phone number and potential
                 safety hazards
                 Occasionally repairs/replaces broken/worn wheels on containers
                 Paperwork daily
                 Daily sequencing of route
                 Drives to various customer locations, dump site, to/from office and route
                 Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                                Page 14
    ©2011, Waste Management                                                                 January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Rear End Loader Driver – Residential/Commercial
           Hazard                         Source                      Minimum Required Protection
                                Hot Objects/Fluids while
Burn Exposure                                                  Gloves, work boots
                                inspecting truck
Cuts/Lacerations/Abrasion
                                Handling containers            Gloves, work boots
s
                                Compacting materials,
                                falling and airborne debris
Eye Injury                      when outside truck on          Safety glasses
                                route or at post collection
                                facility
                                Falling debris at post
Overhead                                                       Hardhat
                                collection facilities
                                Wet, uneven surfaces,
Slips, Trips and Falls                                         Boots, gloves
                                obstacles
                                Outside of truck, high
                                traffic areas, on route, at
Traffic Exposure                                               ANSI Class II high visibility clothing
                                post collection facility and
                                in yard
Additional Hazards




                            Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


                         Certified by                              Title                Date of Assessment


              Site Name                                                  Site Address




    Personal Protective Equipment                                                               Page 15
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Rear End Loader Helper – Residential / Commercial
                 Assists driver of rear loading truck. Collects refuse from residential and commercial
                 customers on a route throughout the day. Loads rear hopper of truck either
   Job
Description
                 manually or with tippers until truck is full. May empty commercial bins if truck is
                 equipped. Helpers are not allowed to drive the truck or perform tasks requiring the
                 truck to locked and tagged out.
Check All That
    Apply                                                    Tasks
                 Ascends/descends cab of vehicle throughout day for various reasons
                 Operates hydraulic control levers while standing outside of vehicle for various reasons
                 Cleans off debris from hopper area
                 Walks to/from office to vehicle parking lot, and at customer location
                 Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                 load into rear hopper of truck either manually or using the tipper. May also load bags, boxes
                 and other bulky items
                 May also push/pull larger bins (1/2 to 4 yard) to rear of truck for tipping if truck is equipped
                 Communicates via two-way radio with dispatch and co-workers
                 Occasionally places stickers on containers of company name/phone number and potential
                 safety hazards
                 Occasionally repairs/replaces broken/worn wheels on containers
                 Paperwork daily (as required)
                 Daily sequencing of route (as required)
                 Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                                Page 16
    ©2011, Waste Management                                                                 January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Rear End Loader Helper – Residential / Commercial
          Hazard                       Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 17
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Roll Off Driver
Job Description        Drives roll off truck; delivers and/or picks up containers of various sizes (4 to 50 yard including
                       compactors) from various types of customers. Disconnects and reconnects compactor receiving boxes.
                       Operates hoist and cable controls on truck to load refuse container onto truck at each stop; drives truck
                       with full container to post collection facility (landfill, MRF, transfer station, etc.) and empties container;
                       returns emptied container to customer location; goes on to next stop and repeats process 8-12 times
                       daily.
Check All That
    Apply                                                            Tasks

                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  Loosens and detaches two turnbuckles weighing 25-50 lbs, which secure compactor to
                  container for transport to dump site; attaches compactor turnbuckles to container and
                  tightens upon return to customer location
                  Releases chain and latching device to open container doors, guides door to side of container
                  and secures in place with a chain; returns door to closed position, latches and chains upon
                  completion of dump out
                  Checks/fills fluid levels twice daily as part of pre/post trip inspections
                  Fuels vehicle
                  Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                  Communicates via two-way radio with dispatch and co-workers
                  Occasionally places stickers on containers of company name/phone number
                  Paperwork daily
                  Daily sequencing of route
                  Drives to various customer locations, dump site, to/from office and route
                  Manually (or automatically) tarps loaded container for transport
                  Climbs 3-8 feet on top of container to even out load for tarping
                  Covers compactor container ends with tarpaulin (referred to as a “diaper”)
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                                               Page 18
    ©2011, Waste Management                                                                                January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Roll Off Driver
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 19
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Side Loader Driver – Residential
Job Description        Drives side loading truck; collects refuse residential customers on a route
                       throughout the day. Loads side mounted hopper of truck either manually, with
                       tippers or with automated arm until truck is full. Then drives to post collection
                       facility (landfill, transfer station, MRF, etc.) for emptying of truck 1-3 times per
                       day.
Check All That
    Apply                                                    Tasks
                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at
                  landfill to dump out truck contents
                  Cleans out behind packer blade after dumping out
                  Cleans off debris from hopper area
                  Checks/fills fluid levels twice daily as part of pre/post trip inspections
                  Fuels vehicle
                  Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                  Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                  load into side hopper of truck either manually, using the tipper or the automated arm. May
                  also load bags, boxes and other bulky items.
                  Communicates via two-way radio with dispatch and co-workers
                  Operates MCC (onboard computer system) by hand
                  Occasionally places stickers on containers of company name/phone number and potential
                  safety hazards
                  Occasionally repairs/replaces broken/worn wheels on containers
                  Paperwork daily
                  Daily sequencing of route
                  Drives to various customer locations, dump site, to/from office and route
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                                Page 20
    ©2011, Waste Management                                                                 January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Side Loader Driver – Residential
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 21
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Side Loader Helper – Residential
Job Description        Assists side load driver; collects refuse from residential customers on a route
                       throughout the day. Loads side mounted hopper of truck either manually, with
                       tippers or with automated arm until truck is full. Helpers are not allowed to drive
                       the truck or perform tasks requiring the truck to locked and tagged out.
Check All That
    Apply                                                   Tasks
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  Cleans off debris from hopper area
                  Walks to/from office to vehicle parking lot, and at customer location
                  Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                  load into side hopper of truck either manually, using the tipper or the automated arm. May
                  also load bags, boxes and other bulky items
                  Communicates via two-way radio with dispatch and co-workers
                  Occasionally places stickers on containers of company name/phone number and potential
                  safety hazards
                  Occasionally repairs/replaces broken/worn wheels on containers
                  Paperwork daily (as required)
                  Daily sequencing of route (as required)
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                              Page 22
    ©2011, Waste Management                                                               January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Side Loader Helper – Residential
          Hazard                       Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 23
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Driver - Residential
Job Description        Drives front loading truck; collects refuse from residential customers on a route
                       throughout the day. Loads bucket attached to the front forks of truck either
                       manually or with tippers, and dumps buckets into truck until truck is full. Then
                       drives to post collection facility (landfill, transfer station, MRF, etc.) for
                       emptying of truck 1-3 times per day.
Check All That
    Apply                                                    Tasks
                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at
                  landfill to dump out truck contents
                  Cleans out behind packer blade after dumping out
                  Cleans off debris from apron or hopper area
                  Checks/fills fluid levels twice daily as part of pre/post trip inspections
                  Fuels vehicle
                  Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                  Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                  load into bin on front of truck either manually or using the tipper. May also load bags, boxes
                  and other bulky items
                  Communicates via two-way radio with dispatch and co-workers
                  Operates MCC (onboard computer system) by hand
                  Occasionally places stickers on containers of company name/phone number and potential
                  safety hazards
                  Occasionally repairs/replaces broken/worn wheels on containers
                  Paperwork daily
                  Daily sequencing of route
                  Drives to various customer locations, dump site, to/from office and route
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                               Page 24
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Driver - Residential
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 25
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Helper - Residential
Job Description        Assists residential front load driver collecting refuse and/or recyclables from
                       residential customers on a route throughout the day. Loads bucket attached to
                       the front forks of truck either manually or with tippers, and dumps buckets into
                       truck until truck is full. May also load bags, boxes or other containers manually.
Check All That
    Apply                                                    Tasks
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  Cleans off debris from apron or hopper area
                  Walks to/from office to vehicle parking lot, and at customer location
                  Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to
                  load into bin on front of truck either manually or using the tipper. May also load bags, boxes
                  and other bulky items
                  Communicates via two-way radio with dispatch and co-workers
                  Occasionally places stickers on containers of company name/phone number and potential
                  safety hazards
                  Occasionally repairs/replaces broken/worn wheels on containers
                  Paperwork daily (as required)
                  Daily sequencing of route (as required)
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                               Page 26
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Front End Loader Helper - Residential
          Hazard                       Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Handling containers             Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 27
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Transfer/Tractor Trailer Driver
Job Description        Drives tractor-trailer hauling material from post collection processing plants (transfer
                       stations, MRF’s, etc.) to landfills, other processing plants and shipping destinations.
                       Trailers vary from box type, open tops, end dumps, to live/walking floors. Some units
                       are emptied at landfills, and other destinations, on large tippers that lift the truck. Some
                       drivers operate these tippers.
Check All That
    Apply                                                     Tasks
                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates hydraulic control levers while seated in cab for various reasons
                  Operates hydraulic control levers while standing outside of vehicle for various reasons
                  May operate hydraulic control levers inside the tipper
                  Opens a variety of trailer doors by using levers, pins, latches, turn buckles, etc.
                  Checks/fills fluid levels twice daily as part of pre/post trip inspections
                  Fuels vehicle
                  Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location
                  Communicates via two-way radio with dispatch and co-workers
                  Paperwork daily
                  Daily sequencing of route
                  Drives to various customer locations, dump site, to/from office and route
                  Manually (or automatically) tarps loaded trailer for transport
                  Cleans/shovels spillage at customer location
Additional Tasks




    Personal Protective Equipment                                                                 Page 28
    ©2011, Waste Management                                                                  January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Transfer/Tractor Trailer Driver
           Hazard                      Source                       Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                                Gloves, work boots
                             inspecting truck
Cuts/Lacerations/Abrasion
                             Opening doors                   Gloves, work boots
s
                             Compacting materials,
                             falling and airborne debris
Eye Injury                   when outside truck on           Safety glasses
                             route or at post collection
                             facility
                             Falling debris at post
Overhead                                                     Hardhat
                             collection facilities
                             Wet, uneven surfaces,
Slips, Trips and Falls                                       Boots, gloves
                             obstacles
                             Outside of truck, high
                             traffic areas, on route, at
Traffic Exposure                                             ANSI Class II high visibility clothing
                             post collection facility and
                             in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 29
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Driver Vacuum Truck (Port-o-Let®)
Job Description        Drives a vacuum truck and services portable toilets at various locations. A suction
                       hose is used to transfer contents of holding tank to the truck. The driver also is
                       responsible for cleaning and replenishing the toilets. The material is discharged at
                       permitted facilities.
Check All That
    Apply                                                    Tasks
                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Operates vacuum pump
                  Suctions out portable toilets
                  Removes miscellaneous foreign objects
                  Pumps water into buckets and adds cleaning agents
                  Scrubs and cleans portable toilet
                  Replaces deodorant solution into toilet basin
                  Replaces tissues
                  Inspects units and makes simple repairs
                  Returns to facility and dumps waste into designated receptacle
                  Paperwork daily
                  Daily sequencing of route
                  Drives to various customer locations, dump site, to/from office and route
                  Transports individual units to customers
                  Lowers unit to ground and moves it to proper location
Additional Tasks




    Personal Protective Equipment                                                               Page 30
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Driver Vacuum Truck (Port-o-let®)
          Hazard                        Source                       Minimum Required Protection
                              Hot Objects/Fluids while
Burn Exposure                                                 Gloves, work boots
                              inspecting truck
Biohazards                    Portable Toilets                Chemical resistant gloves, goggles, boots
Cuts/Lacerations/Abrasion
                              Handling containers             Gloves, work boots
s
                              Splashes as a result of
Eye Injury                                                    Goggles
                              collection / discharge.
                              Wet, uneven surfaces,
Slips, Trips and Falls                                        Boots, gloves
                              obstacles
                              Outside of truck, high
                              traffic areas, on route, at
Traffic Exposure                                              ANSI Class II high visibility clothing
                              post collection facility and
                              in yard
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                 Title              Date of Assessment


Site Name                                Site Address




    Personal Protective Equipment                                                             Page 31
    ©2011, Waste Management                                                              January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Utility Maintenance Worker
Job Description        Performs non-mechanical maintenance such as cleaning, parts storage and retrieval,
                       etc.
Check All That
    Apply                                                  Tasks
                  Maintains housekeeping in maintenance shops
                  Containing and cleaning up spillage in shops
                  Facility cleaning (break rooms, rest rooms)
                  Operates fork trucks when indicated
                  Use of hand and power tools
                  Vehicle/Equipment washing
Additional Tasks




    Personal Protective Equipment                                                            Page 32
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Utility Maintenance Worker
           Hazard                     Source                     Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                                            Gloves, work boots
                             cleaning
Cuts/Lacerations/Abrasion
                             Handling containers         Gloves, work boots
s
                             Working in shop or task
Eye Injury                                               Safety glasses
                             specific
Overhead                     Overhead hazards            Hardhat
                             Wet, uneven surfaces,
Slips, Trips and Falls                                   Boots, gloves
                             obstacles
Traffic Exposure             Working in yard             ANSI Class II high visibility clothing
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                            Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                        Page 33
    ©2011, Waste Management                                                         January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Washer
Job Description        Washes containers of various sizes and styles with pressure washer and deodorizes
                       containers in preparation for customer use; organizes container storage area of yard
Check All That
    Apply                                                   Tasks
                  Operates Forklift to transport containers to/from wash area and storage yard
                  Uses container tipper to turn containers for washing
                  Washes containers (about 30 per day) with pressure washer (no soap)
                  Reorganizes yard to separate full container from empty ones
                  Stacks roller carts after washing for storage yard (stacks two carts high)
                  Shovels excess waste into yard container from containers to be washed
                  Cleans wash area of all excess waste that came out of containers
Additional Tasks




    Personal Protective Equipment                                                              Page 34
    ©2011, Waste Management                                                               January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Washer
           Hazard                      Source                    Minimum Required Protection
                             Hot Objects/Fluids while
Burn Exposure                inspecting and handling     Gloves, work boots
                             cleaning equipment
Cuts/Lacerations/Abrasion
                             Handling containers         Gloves, work boots
s
                             Airborne debris from
Eye Injury                                               Goggles
                             pressure washer
Overhead                     Overhead hazard             Hardhat
                             Wet, uneven surfaces,
Slips, Trips and Falls                                   Boots, gloves
                             obstacles
Traffic Exposure             In yard                     ANSI Class II high visibility clothing
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                            Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                        Page 35
    ©2011, Waste Management                                                         January 2011
Personal Protective Equipment Program

                 CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Maintenance Technician
     Job           Performs servicing and repairs on company vehicles and equipment at facility; makes
  Description      service calls to trucks in need of repairs at post collection facilities or on route
Check All That
    Apply                                                  Tasks
                 Changes and repairs tires
                 Adjusts brakes and clutch
                 Checks battery and starter system
                 Repairs electrical wiring system
                 Makes up and installs continuity cables
                 Replaces wheel seals and bearings
                 Replaces drive lines and U-joints
                 Replaces air lines and brake diaphragms
                 Renews hydraulic hoses
                 Exchanges components
                 Adjusts cycle speeds
                 Tunes up and overhaul engines
                 Analyzes, diagnoses, and repairs problems with fuel, air and electrical system
                 Relines brakes
                 Exchanges clutch and transmissions
                 Exchange differentials
                 Rebushes kingpins
                 Repairs suspensions
                 Rebuilds transmissions
                 Tests, diagnoses, and repairs hydraulic systems
                 Performs service calls to make repairs as needed on route or at landfill
                 Welding
                 Parts cleaning
                 Use of various hand held and electrical tools
                 Cleans up work area
                 Paperwork
                 Other miscellaneous maintenance tasks
Additional Tasks




    Personal Protective Equipment                                                             Page 36
    ©2011, Waste Management                                                              January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Maintenance Technician
        Hazard                        Source                         Minimum Required Protection
Burn Exposure               Welding, Cutting, Hot            Welding gloves, welding apron, welding
                            Liquids, Hot Objects             helmet, boots, coveralls
Chemical Exposure           Chemical use part of tasks       Safety glasses, goggles or face shields,
                                                             chemical resistant gloves, coveralls and
                                                             respirators. Protection based upon task and
                                                             MSDS.
Cuts/Lacerations/Abrasion   Working with tools on            Gloves, work boots
s                           equipment
Extreme Cold                LNG/CNG Fueling                  Cryogenic gloves, goggles, face shield, long
                                                             sleeve shirt or overalls,
Eye Injury                  Airborne debris                  Safety glasses, goggles or face shield
Noise                       Operating tools, working         Ear plugs, canal caps, ear muffs where required
                            with metal
Overhead                    Falling Debris, overhead         Hard hat
                            hazard in Shop or Yard.
Slips, Trips and Falls      Wet, uneven surfaces,            Boots, gloves
                            obstacles
Traffic Exposure            Outside of service truck on
                            route, high traffic areas, at
                                                             ANSI Class II high visibility clothing
                            post collection facility and
                            in yard
Welding Fumes               Welding                          When air testing indicates the need, a full or
                                                             half face respirator with appropriate cartridges.
                                                             Additional ventilation evaluations may be
                                                             required.
Additional Hazards




   Tasks or hazards not
 listed must be added to
         this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.

Certified by                                                Title               Date of Assessment



    Personal Protective Equipment                                                             Page 37
    ©2011, Waste Management                                                              January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Shop Repair / Welder
Job Description         Repairs refuse containers in accordance with company specifications and work
                        orders
Check All That
    Apply                                                     Tasks
                  Conducts pre/post-trip inspection on Forklift
                  Transports containers to/from shop and yard via forklift
                  Uses forklift for raising/holding, lowering containers for repair
                  Repairs casters
                  Repairs lock bars, pockets, rails, doors, walls, etc. of front load, rear load and roll-off
                  containers.
                  Repairs/replaces lids (plastic and occasionally metal lids)
                  Patches damaged metal parts
                  Repairs/replaces container bottoms
                  Use of impact wrench to remove nuts and bolts on containers
                  Uses portable grinders for grinding all surfaces to be welded
                  Repairs containers by dismantling, straightening, reshaping, or assembling parts using
                  cutting torch
                  Shapes metal using, sledgehammer, steel power saw and power shears
                  Transports and positions containers and repair parts by hand or with the use of a forklift
                  truck, cranes, hoists, etc.
                  Sets up equipment and welds parts using arc, C02, gas, or wire feed welding equipment
                  Bolts, clamps, and tack-welds parts to secure in position for welding
                  Sands containers using portable air sander
                  Paints containers
                  Uses various type electrical and hand tools
                  Paperwork
                  Occasionally performs repair work to containers at customer locations
                  Occasionally performs welding tasks to repair damaged metal parts on vehicles
Additional Tasks




    Personal Protective Equipment                                                                 Page 38
    ©2011, Waste Management                                                                  January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Container Shop Repair / Welder
        Hazard                         Source                      Minimum Required Protection
Burn Exposure                Welding, Cutting, Hot         Welding gloves, welding apron, welding
                             Liquids, Hot Objects          helmet, boots, coveralls
Chemical Exposure            Chemical use part of tasks    Safety glasses, goggles or face shields,
                                                           chemical resistant gloves, coveralls and
                                                           respirators. Protection based upon task and
                                                           MSDS.
Dust Particulate Exposure    Resulting from grinding,      Safety glasses. Nuisance dust mask available.
                             sanding, etc.                 Respirator required when applicable.
Eye Injury                   Airborne debris               Safety glasses, goggles, face shield, welding
                                                           helmet
Noise                        Operating tools, working      Ear plugs, canal caps, ear muffs where required
                             with metal
Overhead                     Falling Debris, overhead      Hard hat
                             hazard in Shop or Yard.
Paint Spray                  Spray Painting                Full and half face respirator when necessary
Slips, Trips and Falls       Wet, uneven surfaces,         Boots and gloves
                             obstacles
Traffic Exposure             Working at customer           ANSI Class II high visibility clothing
                             locations, on route or at
                             post collection facility
Welding Fumes                Welding                       When air testing indicates the need, a full or
                                                           half face respirator with appropriate cartridges.
                                                           Additional ventilation evaluations may be
                                                           required.
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                              Title               Date of Assessment


Site Name                               Site Address

     Personal Protective Equipment                                                           Page 39
     ©2011, Waste Management                                                            January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Equipment Operator
Job Description        Drives/operates mobile equipment (e.g. forklifts, loaders, dozers, compactors, scrapers)
                       to consolidate of Assessment/move waste/recyclable materials as well as landfill
                       cover/construction materials (dirt, rock, etc.)
Check All That
    Apply                                                   Tasks
                  Ascends/descends cab of vehicle throughout day for various reasons
                  Cleans out radiator as needed with compressed air
                  Communicates via two-way radio with co-workers
                  Conducts pre-trip/in-route/post trips inspections daily on vehicles driven
                  When possible, visual inspection of waste to help ensure prohibited materials are not
                  received
                  Fuels equipment
                  Operates controls, pedals and/or levers from inside of cab
                  Paperwork daily
                  Replaces equipment fluids as needed
                  Walks to and from equipment
Additional Tasks




    Personal Protective Equipment                                                              Page 40
    ©2011, Waste Management                                                               January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Equipment Operator
        Hazard                          Source                    Minimum Required Protection
Burn Exposure                Hot Objects/Fluids while      Gloves, work boots
                             inspecting equipment
Cuts/Lacerations/Abrasion    Incidental                    Gloves, work boots
s
Eye Injury                   Airborne debris               Safety glasses
Foot puncture                Walking at Post Collection    Puncture Resistant Boots
                             Facilities
Overhead                     Falling Debris                Hard hat when outside of cab or operating open
                                                           cab equipment
Slips, Trips and Falls       Wet, uneven surfaces,         Boots, gloves
                             obstacles
Traffic Exposure             Vehicular traffic at Post     ANSI Class II high visibility clothing
                             Collection facilities
Additional Hazards
                             Noise from Equipment
                             exceeding threshold levels
Noise Exposure
                             outlined in Hearing
                                                           Ear Plugs/Ear Muffs in required Equipment
                             Conservation Program




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                              Title              Date of Assessment


Site Name                                Site Address




    Personal Protective Equipment                                                          Page 41
    ©2011, Waste Management                                                           January 2011
Personal Protective Equipment Program

                    CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Laborer
Job Description        Performs routine cleanup and yard maintenance
Check All That
    Apply                                                 Tasks
                  Clean roadways
                  Pick up litter as assigned
                  Respond to specific labor needs
                  Perform weed abatement/landscaping as indicated
                  Lift and stack items

Additional Tasks




    Personal Protective Equipment                                                 Page 42
    ©2011, Waste Management                                                  January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Laborer
         Hazard                        Source                     Minimum Required Protection
Cuts/Lacerations/Abrasion    Material handling             Gloves, work boots
s
Eye Injury                   Airborne debris               Safety glasses, or goggles, or face shield
Foot puncture                Walking at Post Collection    Puncture Resistant Boots
                             Facilities
Overhead                     Falling Debris at post        Hard hat
                             collection facility
Slips, Trips and Falls       Wet, uneven surfaces,         Boots, gloves
                             obstacles
Traffic Exposure             Vehicular traffic at Post     ANSI Class II high visibility clothing
                             Collection facilities
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                              Title               Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                           Page 43
    ©2011, Waste Management                                                            January 2011
Personal Protective Equipment Program

                     CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Sorter
Job Description        Sorts recyclable materials into applicable components
Check All That
    Apply                                                    Tasks
                  Sorts materials off of conveyor or on ground
                  Places materials in appropriate chute or receptacle
                  Operates conveying equipment
                  Operates bailing equipment
                  Maintains housekeeping in active area
Additional Tasks




    Personal Protective Equipment                                                    Page 44
    ©2011, Waste Management                                                     January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Sorter
          Hazard                      Source                        Minimum Required Protection
Cuts/Lacerations/Abrasion   Material handling                Gloves and work boots
s
Eye Injury                  Airborne debris                  Safety glasses
Noise                       Sorting Equipment                Ear plugs or canal caps
Overhead                    Falling Debris                   Hard hat
Slips, Trips and Falls      Wet, uneven surfaces,            Boots, gloves
                            obstacles
Traffic Exposure            Truck and forklift traffic at    ANSI Class II high visibility clothing
                            facility.
Additional Hazards




                       Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                                Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                            Page 45
    ©2011, Waste Management                                                             January 2011
Personal Protective Equipment Program

                  CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Traffic Director
     Job           Performs traffic control at landfills, transfer stations and waste/recyclable consolidation
  Description      facilities
Check All That
    Apply                                                   Tasks
                 Interacts with truck drivers and equipment operators to direct trucks into proper areas
                 Collects unloading tickets (if necessary)
                 From a protected area, directs trucks to unloading positions based on size and content of
                 loads
                 Paperwork
                 Assists in keeping area clean
                 Monitors the activity of heavy equipment working in immediate area
                 Watches that no prohibited materials are offloaded in non-restricted areas
                 Communicates with management, equipment operators and other site personnel with 2 way
                 radios
                 Walks to and from working area
Additional Tasks




    Personal Protective Equipment                                                               Page 46
    ©2011, Waste Management                                                                January 2011
Personal Protective Equipment Program

                   CERTIFICATION OF HAZARD ASSESSMENT
Job Title: Traffic Director
         Hazard                         Source                     Minimum Required Protection
Eye Injury                   Airborne debris               Safety glasses
Foot puncture                Walking at Post Collection    Puncture Resistant Boots
                             Facilities
Overhead                     Falling debris at post
                                                           Hardhat
                             collection facilities
Slips, Trips and Falls       Wet, uneven surfaces,         Boots, gloves
                             obstacles
Traffic Exposure             Vehicular traffic at Post     ANSI Class II high visibility clothing
                             Collection facilities
Additional Hazards




                         Tasks or hazards not listed must be added to this form.
This is to certify that I have performed a hazard assessment at this workplace as required by
29CFR1910.132(d), through an observation of persons performing the above job descriptions.


Certified by                                              Title              Date of Assessment


Site Name                               Site Address




    Personal Protective Equipment                                                          Page 47
    ©2011, Waste Management                                                           January 2011
 
Confined Space Program

Program: Confined Space

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707




PURPOSE

To describe the requirements to identify, evaluate and plan for the safe entry into confined spaces
and permit-required confined spaces.

REQUIREMENTS

1. Identify and prepare a written list of all confined spaces within your operations.
2. If employees have access to confined spaces, implement the attached confined space
   program. Complete the facility-specific information.
3. Any employee, who enters the permit space, or that employee’s authorized representative,
   shall be provided any opportunity to observe all pre-entry and any subsequent testing or
   monitoring of permit spaces.
4. Using the attached evaluation form, determine which type of confined spaces and entry
   conditions constitute permit-required spaces.
5. Update the list of confined spaces on an annual basis and when a new confined space is
   introduced into the operations. Perform an evaluation for new confined spaces.
6. Provide awareness training to all employees about the hazards associated with confined
   spaces and to stay out of them unless trained as entrants.
7. Provide detailed training for employees and supervisors (entrants, attendants, and entry
   supervisors) who may be involved in permit-required confined space entries.
8. Evaluate a prospective rescuer’s ability to respond to a rescue summons in a timely manner,
   considering the hazard(s) identified.
9. Ensure that rescue personnel receive initial and annual training, including drills.


PERMIT-CONFINED SPACES
1. Label all permit-required confined spaces. An alternative means of communicating the
   danger and identifying confined spaces may be used if labeling is impossible or impractical.
   Document the rationale for utilizing the alternative methodology.
2. Develop a system to restrict entry into permit- required confined spaces.
3. Utilize the permit for all permit-required confined space entries.




Confined Space                                                                            Page 1
©2011, Waste Management                                                             January 2011
CONFINED SPACE PROGRAM (continued)

4. For locations where permit confined spaces must be entered, ensure atmospheric testing
   equipment is available, maintained, and used. Note: Under certain circumstances ventilation
   may allow reclassification of a permit space to a non-permit required confined space.
5. Make emergency rescue personnel (or local emergency responders) available during permit-
   required space entry.


GENERAL

A confined space is any space that is large enough and configured so that an employee can
bodily enter and perform assigned work, has limited means for entry or exit, and is not designed
for continuous employee occupancy. Examples are pump-pits, sewer manholes, tanker trucks and
storage tanks.

There are two types of confined spaces – permit required and non-permit required.

All confined spaces are considered to be permit required confined spaces until evaluations
determine that the space is a non-permit-required space.

A non-permit required confined space means a confined space that does not contain or have the
potential to contain any hazard capable of causing death or serious physical harm.

Under normal solid waste collection activities, we have determined that there is no potential for a
hazardous atmosphere inside truck bodies. When the physical hazards have been locked out
following proper procedures, the truck body may then be considered a non-permit required
confined space and entered without a permit. In addition, by blocking open a truck body tailgate
for entry and exit, the truck body may then be configured so that it no longer is considered a
confined space.

A permit-required confined space is a confined space that has one or more of the following
characteristics: (1) Contains or has the potential to contain a hazardous atmosphere; (2)
Contains a material that has the potential for engulfing an entrant; (3) Has an internal
configuration such that an entrant could be trapped by inwardly converging walls or by a floor
which slopes downward and tapers to a smaller cross-section, or; (4) Contains any other
recognized serious safety or health hazard, (5) has the potential to contain (1) through (4) and has
not be evaluated.

A permit-required (attendant-required) confined space is a space that has been evaluated
and engineering controls or lockout could not eliminate the hazard.
It is the policy of Waimanalo Gulch Sanitary Landfill employees to avoid entry into confined
spaces whenever possible. Employees follow this program if confined spaces must be entered.




Confined Space                                                                             Page 2
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)


CORE PROGRAM
When these hazards are not completely controlled or eliminated prior to entry, an attendant is
required before entry. Two employees are needed for entry into a permit-required confined space
(also called an attendant-required confined space), one to enter the space (Entrant), and one to
stay outside and watch over the safety of the entrant (Attendant).


Responsibility

Management is responsible for administering the confined space entry program. This person
identifies confined spaces, coordinates all training, and ensures that the program is implemented.
The confined space entry program administrator appoints an individual to be an Entry
Supervisor. The Entry Supervisor approves, issues, and signs all entry permits, authorizes entry
into permit areas, identifies additional confined spaces, and maintains documentation of all
entries. The Entry Supervisor may also act as an attendant for employees making entry into
confined spaces.

Management is responsible for conducting work area surveys to identify potential confined
spaces, ensuring permit-required confined spaces are labeled, and ensuring the program is
implemented for all work in confined spaces.

Attendants are responsible for maintaining constant contact with persons in the confined space,
and are also responsible for calling for help.

Emergency rescue team is responsible for being in a standby condition when notified by the
entry supervisor that a confined space entry is underway. In the event the rescue team must
respond to another call or cannot be on standby, the rescue team must inform the entry
supervisor. The supervisor shall terminate the confined space entry until the emergency rescue
team is available.

Employees who are trained and authorized may enter confined spaces when the requirements of
this program have been satisfied. Employees who are trained as entry supervisors or attendants
can also perform this role.


Identify and Post Signs on Confined Spaces

Management or management designees identify and evaluate confined spaces in work areas. See
the Appendices for a list of confined spaces at the facility. Post signs or apply labels identifying
confined spaces at the entry points for each space.




Confined Space                                                                             Page 3
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)

Identify the Confined Space and the Work to be done. Determine whether it is safe to remove
the cover to the confined space. If required, lockout and tagout sources of hazardous energy into
the space using the facility lockout and tagout program. If possible, test the initial air before
removing the cover. Where practical, the temperature and pressure inside the confined space
should approximate the temperature and pressure outside the confined space. Excess pressure
can blow the cover off and result in splash or injury.

Prior to the entry, put the following information on the permit:

   The confined space to be entered
   The purpose of the entry
   Hazardous materials to be taken into or hazardous work to be done in the space
   The length of time the permit is in effect.

Note: It is very important to review the hazardous materials taken into or hazardous work done
in the confined space. Atmospheric and physical hazards can arise from the work inside the
confined space. As an example, chemical solvent vapor concentration could increase and cause
someone to pass out and welding could produce a hazardous atmosphere or fire hazard.


Identify Potential Atmospheric and Physical Hazards

Evaluate the confined space for internal and external hazards. Internal hazards include both
atmospheric hazards (unsafe or lack of air) and physical hazards.

Atmospheric hazards may include:

   Hydrogen sulfide, methane, and oxygen deficiency from decaying waste, sewage, or stagnant
   water
   Air contaminants from chemicals used or stored in the space
   Excess oxygen (makes things burn easily)
   Flammable atmospheres containing methane, propane, or other explosive gases
   Combustion by-products like carbon monoxide
   Explosive dust atmospheres

Acceptable levels of atmospheric hazards are listed on the permit. Do not enter confined spaces
where air quality is different from normal air (see permit) without first investigating the cause of
the problem.

Physical hazards in confined spaces may include:

   Mechanical hazards from fans and other moving parts
   Engulfment, which is being trapped by a liquid or solid material

Confined Space                                                                             Page 4
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)

   Internal structures that could trap an entrant or impair his/her ability to exit the space quickly
   Electrical hazards from unguarded conductors or power sources
   Excessive heat or cold


Entry Procedures

The confined space entry procedures are designed to reduce or eliminate the hazards and if at all
possible, reclassify the permit space to a non-permit space. If the space cannot be reclassified to
a non-permit space, the permit identifies those items, conditions, and controls necessary to make
the entry safe.

The basic process for entry into confined spaces is to:

   Identify the confined space and the work to be done. Evaluate the feasibility of performing
   the work from outside the confined space.
   If the confined space must be entered, determine if the space is a permit required or non-
   permit required confined space by identifying potential atmospheric and physical hazards.
   Test the space for atmospheric hazards to determine the classification of the space. Also test
   before entry and regularly during entry.
   Make the space safe for entry by eliminating atmospheric and physical hazards.
   Certify control measures taken, classify the space based on whether hazards have been
   eliminated, and post the permit if a permit required space.
   Ensure additional controls for attendant-required spaces.
   Authorize entry by Entry Supervisor.
   Do the work safely and,
   End the permit if applicable.

These steps are also on the permit. The rest of this program explains each of these steps.


Permit vs. Non-Permit Confined Spaces

If any hazards remain that you cannot eliminate or control by ventilation alone, or if work
releases additional hazards, the space is classified as a permit-required confined space and
requires an Attendant. Provisions for rescue are also necessary.

If hazards remain, only authorized and trained Entrants can enter the Attendant-required
confined space. The Entry Supervisor lists the Entrants on the Confined Space Entry
Authorization Permit.




Confined Space                                                                              Page 5
©2011, Waste Management                                                               January 2011
CONFINED SPACE PROGRAM (continued)

The Entry Supervisor must inform employees of the hazards present. The Entry Supervisors
briefs the Entrant(s) and Attendant on planned emergency rescue methods and verifies that
rescue equipment, procedures, and rescue personnel are available. Entrant(s) must read the
permit and sign the permit before entry and entrants must evacuate the confined space when:

   Atmospheric monitoring alarms sound
   Respirators fail
   Forced-air ventilation stops
   The Attendant tells them to leave the space
   The Attendant informs them of problems

Entrants must promptly begin self-rescue when any of the above occurs.

Test the Space for Atmospheric Hazards before Entry
Without entering the confined space, test in the following order the internal atmosphere for the
presence of:

   Oxygen
   Flammable gas
   Toxic substances (what to test for depends on the hazard assessment)

For each atmospheric test, monitor the space at different levels and in any unusual
configurations. The shape of a space may trap gases in unexpected areas. Record test results on
the permit.

As part of the testing process, the Entry Supervisor must identify safe conditions for entry.
Hazardous conditions that prohibit entry include:

   An oxygen-deficient (less than 19.5%) atmosphere, which can cause suffocation.
   An oxygen-enriched (more than 23.5%) atmosphere, which can cause an extreme fire hazard.
   A potentially explosive atmosphere caused by the presence of combustible gases, liquids,
   vapors, or dust at greater that 10% of their lower flammable limit (LFL).
   A concentration of any hazardous substance above its OSHA permissible exposure limit
   (PEL) or above the exposure limit given on the MSDS.
   The presence of a physical hazard that is not controlled and immediately dangerous to life or
   health (IDLH) such as a liquid or solid that may engulf, exposed conductors that may
   electrocute, or uncontrolled energy that may escape.

Note: Only qualified and authorized individuals can operate monitoring instruments. Regularly
field-calibrate the instruments. Follow the manufacturers written operating instructions and
calibration procedures.



Confined Space                                                                             Page 6
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)



Make Space Safe For Entry

Do not enter the confined space if there is an uncontrolled hazardous atmosphere or physical
hazard. If any readings are out of the normal range, identify the cause and perform corrective
actions before entry. Perform tests again following the completion of control measure
implementation.

Before entry, control or isolate all energy sources. Use the facility lockout and tagout program.
Verify lockout by testing.

Drain, pump out, or otherwise empty the material in the space before entering. Use the best and
most practical method to clean it.

Do not use protective clothing and respiratory protection as substitutes for cleaning and
ventilating the confined space.

Where practical, use forced-air ventilation whenever employees are inside of any confined space.
Use only clean air supplies for continuous forced-air ventilation so you do not increase the
hazards in the confined space. Do not contaminate the air supply with engine exhaust.

Never use oxygen to purge or ventilate any confined space. Injury or death may occur from the
highly explosive atmosphere generated.

Other important control measures prior to entry include:

   Briefing entrants on hazards and control measures.
   Notifying contractors of the permit space and hazardous conditions.
   Testing and verifying lockout and tagout of known and potential hazardous energy sources.


Certify Control Measures, Obtain Approval and Post Permit

After certification by the Entry Supervisor that conditions are now acceptable, it is safe to enter
the hazard-controlled confined space. Post the permit as a certification to those entering the
confined space that the hazards have been eliminated.

Normal work activities can proceed as long as there are no hazards present in the space. Do not
take hazardous materials into the confined space or carry out welding activities or open flame
work that could introduce new hazards or cause existing hazards to intensify. Conduct
continuous air monitoring while an Entrant is in any confined space.



Confined Space                                                                              Page 7
©2011, Waste Management                                                               January 2011
CONFINED SPACE PROGRAM (continued)



Allow Entry after Supervisor Reviews and Approves Permit

The Entry Supervisor authorizes entry into the confined space only after all safeguards have been
executed. The Entry Supervisor must review the permit before allowing employees into the
permit-required confined space. In the review, the Entry Supervisor must:

   Identify the confined space and work to be done.
   Anticipate and protect against hazards that the work might create (solvent use, hot work, and
   paint/coating removal or application).
   Identify the permit-required confined space hazards.
   Determine and identify on the permit the actual and potential hazards of the entry.
   Test the atmosphere in the space before initial entry and ensure continuous monitoring.
   Ensure that a safe atmosphere is maintained inside the space by testing and inspecting.
   Make the space safe before entry.
   Ensure control measures are taken to reduce and eliminate atmospheric and physical hazards.
   Certify the control measures taken and classify the space.
   Classify the space as hazard-controlled, forced-ventilation, or attendant-required.
   List the authorized Entrants.
   Tell the Entrants of the hazards involved and precautions to follow before entry.
   List the authorized Attendant(s).
   Ensure the Attendant knows the work, can summon help, and can communicate with the
   Entrants inside.
   Ensure the availability of an emergency rescue team.
   Verify that rescue services and an operating means for summoning them are available.
   Obtain the equipment required for entry and safe work practices.
   Ensure necessary equipment and work practices are used to maintain the safe conditions the
   permit requires.
   Issue and post a confined space entry permit at the entrance of the confined space before
   allowing Entrants to enter the space.
   Notify the emergency rescue team when the confined space entry is completed.


End the Entry

The Entry Supervisor ends the entry upon work completion, if unsafe conditions are detected, or
an emergency rescue team is unavailable.

Upon work completion, the Entrant(s), retrieves tools or equipment and cleans up the space as
necessary before ending the entry. Check to make sure no one is in the confined space and all
measures required to bring the confined space back to normal service have been performed and
notifies the Entry Supervisor.
Confined Space                                                                          Page 8
©2011, Waste Management                                                           January 2011
CONFINED SPACE PROGRAM (continued)

Reversing lockout or other safety procedures may be necessary. This may include:

   Unblocking mechanical parts so they can move freely.
   Securing the hatch or manhole cover.
   Removing blinds from lines and pipes.
   Removing locks and tags from energy sources.
   Testing to be sure sources are working.

After ensuring the space has been returned to the proper conditions, the Entry Leader:

   Removes the permit.
   Signs and dates the permit.
   Documents problems encountered during the entry and provides suggestions to avoid these
   problems.
   Returns the completed permit to the Confined Space Program Administrator.
   Notifies the emergency rescue team that the confined space entry has been completed.


Perform Work Safely in Hazard-Controlled and Forced Ventilation Spaces

The Entry Supervisor may limit the number of Entrants and restrict activities within the confined
space in order to maintain the initial level of safety.

The Entrant(s) must immediately notify the Entry Supervisor and leave the confined space if the
continuous air monitoring detects a hazard or if additional hazards are discovered or created, or if
the ventilator stops operating. If any of these occur, treat the confined space as a permit-required
confined space until safe conditions can be restored and are documented on the permit.


Welding in Confined Spaces

You must use continuous forced-air ventilation whenever you weld or burn inside a permit
required confined space or use other oxygen-consuming equipment. You must also complete a
hot work permit.

When you use continuous forced-air ventilation, begin ventilation before entering and direct it to
the work area. Ventilating must continue until all employees leave the confined space.




Confined Space                                                                             Page 9
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)



Provide an Attendant During Entry

An Attendant stays outside the entrance to the confined space and performs no other tasks
whenever Entrant(s) is inside an attendant-required confined space. The Entry Supervisor lists
the Attendant on the Confined Space Entry Authorization Permit. Attendants must read and sign
the permit. Entrants and Attendants may rotate duties if trained in both designations. The Entry
Supervisor may also be the Attendant.

The Attendant’s duties include:

   Establishing and maintaining communication with the Entrant(s) at all times.
   Monitoring the Entrant(s) for signs of illness, overexposure, or other hazardous conditions.
   Informing Entrant(s) of changes in hazardous conditions so they can leave.
   Having a means to summon help in an emergency.
   Calling the rescue team when self-rescue by the Entrant(s) is not possible.
   Calling the appropriate Entry Supervisor to announce the location and the extent of the
   problem. The Attendant and/or Entry Supervisor directs the rescue team to the confined
   space location.
   Never entering the confined space for any reason.
   Informing the rescue team of the hazards present.


Provide Personal Protective Equipment, Lifeline and Harness

A non-entry rescue is the safest and fastest method for Entrant rescue because the rescuer does
not enter the confined space. To perform a non-entry rescue, attach a body harness and a retrieval
line to the Entrant(s) before he or she enters the confined space. Use a mechanical winch to raise
an Entrant out of the confined space.

Note: Although the Attendant is not allowed to enter the confined space, he or she can perform a
non-entry rescue.


Notify Contractors

Give contractors a copy of this program and hold them responsible for following an equivalent
program of their own. Ensure that contractors will not enter confined spaces without proper
precautions, or create confined space hazards for Waimanalo Gulch Sanitary Landfill
employees.




Confined Space                                                                          Page 10
©2011, Waste Management                                                            January 2011
CONFINED SPACE PROGRAM (continued)



Train Entrants, Attendants, and Entry Supervisors

Waimanalo Gulch Sanitary Landfill ensures that all affected employees receive training.
Employees who do not enter confined spaces are trained to identify confined spaces and stay out
of them unless the hazards have been eliminated.

Employees receive training prior to assignment as Attendants, Entrants, and Entry Supervisors.
Training provides the understanding, knowledge, and skills necessary for the safe performance of
the duties assigned.

Waimanalo Gulch Sanitary Landfill provides training at the following times:
  Before the employee is first assigned confined space duties.
  Whenever there is reason to believe there are inadequacies in the employee’s knowledge.

Waimanalo Gulch Sanitary Landfill documents the training using Safety Training Attendance
Form. Documentation includes:

   The date of training.
   A brief description of the material covered.
   The names and signatures of the employees trained.
   The name of the individual conducting the training.


Responsibility

Identify the name and the title of the person responsible for the facility confined space entry
program and reviewing and updating the confined space entry program annually:

Name: Joseph Whelan           Title: Site Manager

List all confined spaces present at the facility including their locations:
WGSL Flare
Condensate Tanks
Leachate Tanks
Wastewater Tank
Fuel Tanks
Petroleum Tanks




Confined Space                                                                            Page 11
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)

Briefly describe criteria used to determine if a confined space did not require permit for
entry spaces at the facility:
WM only uses contractors to perform confined space entry. Contractors will determine if confined spaces
  are permit required or non-permit required confined space.




Briefly describe the procedures followed to assure that the non-permit spaces will remain non-
permit spaces during entry procedure:
WM only uses contractors to perform confined space entry.




Identify the name(s) and title(s) of the person(s) who perform the above hazardous
assessments:
Various contractors with confined space entry experience.




The remainder of this plan must be completed for facilities with permit required confined
space only. Activities may, however, change the status of the space (permit versus non-
permit).



Acceptable Entry Conditions

Briefly describe the tests performed (or data available) to ensure that conditions in
confined spaces are acceptable for entry:
WM only uses contractors to perform confined space entry. Contractors will determine if confined spaces
  are permit required or non-permit required confined space.




Confined Space                                                                              Page 12
©2011, Waste Management                                                                January 2011
CONFINED SPACE PROGRAM (continued)



Identification and Labeling of Confined Spaces

Describe the signs, labels or markings used to identify permit required confined spaces at
the facility:
“Confined Space” signs are posted on confined spaces. All confined spaces are further evaluated by the
   contractor to determine if the space is permit required or non-permit required.




Ventilation

Identify the ventilation equipment used at the facility:
Contractor to provide.




Air Monitoring

Identify any facility-specific contaminants that are monitored in confined spaces:
Contractor to determine based on actual confined space.




List the monitor(s) that must be present in confined spaces when Authorized Entrants
occupy them:
Contractor to provide own certified and calibrated monitoring device.
Monitor:N/A                  Model:N/A              Calibration Date:N/A




Confined Space                                                                             Page 13
©2011, Waste Management                                                               January 2011
CONFINED SPACE PROGRAM (continued)




Confined Space                                        Page 14
©2011, Waste Management                          January 2011
CONFINED SPACE PROGRAM (continued)



Personnel Roles

Identify the titles used for confined space personnel if different from those used to in this
program:
Contractor to provide.




Confined Space Entry Permit

Attach the confined space entry permit used at the facility if different from the one
provided in the Appendix.



Emergency Procedures

Briefly describe emergency procedures followed at the facility for confined space accidents,
injuries or illnesses: All accidents or illnesses should be reported to a supervisor. Supervisor
will determine what if any first aid is necessary. If medical attention is necessary, supervisor or
others will call ambulance (911).




If the emergency rescue team is contacted by phone, include the phone number dialed to
reach the team:

911




Confined Space                                                                           Page 15
©2011, Waste Management                                                             January 2011
CONFINED SPACE PROGRAM (continued)



Training

Briefly describe the topics covered and materials used to train:


To be determined by confined space entry contractor.


Briefly describe simulated rescues performed as part of training for all team members:
To be performed by confined space contractor.




Contractor Provisions

Describe any facility-specific procedures or policies regarding contractors and leased
employees who perform work in confined spaces at the facility:
Contractor must have health and safety plan that includes confined space training.




Confined Space                                                                     Page 16
©2011, Waste Management                                                       January 2011
CONFINED SPACE PROGRAM (continued)

List all printed materials provided to contractors or leased employees who performed confined
space entry at the facility:
Copy of this program for contractor’s review.




Recordkeeping

Location of the confined space permit file at facility:
Contractors retain records of confined space entry.




Location of training records for the confined space program at the facility:
File cabinet on second floor of office. Contractors keep own confined space training records.


DEFINITIONS
Acceptable entry conditions: The conditions that must exist in a confined space to allow entry and to
ensure that employees involved in a permit-required confined space entry can safely enter into and
work within the space.

Forced-Ventilation Confined Space: A confined space where the only hazard remaining is one that
can be controlled by forced ventilation.

Non-Permit Confined Space: A confined space where all the hazards are controlled prior to entry,
and none are brought into the space.

Combustible Dust: A dust capable of undergoing combustion or burning when subjected to a source
of ignition.

Engulfment: the surrounding and effective capture of a person by a liquid or finely divided (flow
able) solid substance that can be aspirated to cause death by filling or plugging the respiratory system
or that can exert enough force on the body to cause death by strangulation, constriction, or crushing.




Confined Space                                                                            Page 17
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)

Entry: The action by which a person passes through an opening into a permit-required confined
space. Entry includes work activities in the space and is considered to have occurred as soon as any
part of the Entrant’s body breaks the plane of an opening into the confined space.

Entry Permit: The written or printed document that the employer provides which contains the
necessary information to allow and control entry into a permit space.

Hot Work: Any work involving burning, welding, riveting, or similar fire-producing operations, as
well as work which produces a source of ignition, such as drilling, abrasive blasting, and space
heating.

Hazardous Atmosphere: An atmosphere that may expose employees to the risk of death,
incapacitation, impairment or ability to self-rescue injury, or acute illness from one or more of the
following causes:

   A flammable atmosphere in excess of 10% of the LFL (lower flammable limit) for the material.
   Airborne combustible dust at a concentration that meets or exceeds its LFL.
   Atmospheric oxygen concentration below 19.5% or above 23.5%.
   Exposure to an atmospheric concentration of any substance that a dose or PEL is published by the
   Occupational Safety and Health Administration (OSHA) that may result in employee exposure to
   the substance in excess of that dose or PEL.
   Any other atmospheric condition that is immediately dangerous to life or health.


Isolation: A process whereby the confined space is removed from service and completely protected
against the inadvertent release of material and hazardous energy by the following: blanking off
(skillet type metal blank between flanges), misaligning sections of all lines and pipes, locking out all
sources of power, and blocking or disconnecting all mechanical linkages.

Lower Flammable Limit (LFL): The lower limit of flammability of a gas or vapor at ordinary
ambient temperature expressed in a percentage of the gas or vapor in air by volume.

Oxygen Deficiency: Refers to an atmosphere containing less than 19.5% oxygen.

Oxygen Enriched: An atmosphere containing an oxygen concentration greater than 23.5%.

Threshold Limit Value (TLV): The airborne concentration of a substance established by the
American Conference of Governmental Hygienists (ACGIH) representing a condition under which it
is believed that nearly all workers may be repeatedly exposed without adverse effect.




Confined Space                                                                            Page 18
©2011, Waste Management                                                              January 2011
CONFINED SPACE PROGRAM (continued)
District
WAIMANALO GULCH SANITARY LANDFILL
                                    Comb. by                                                                  Decay   Pressure/            Permit      Not
           Location / Description   Products   Chemical   Mechanical   Engulfment   Entrapment   Electrical   Waste     Heat      Other   Required   Required




Confined Space                                                                                Page 19
©2011, Waste Management                                                                  January 2011
Removal Action Summary Report (pages 1-1015)
PERMIT-REQUIRED CONFINED SPACE DETERMINATION
                                         WORKSHEET

Space Being Evaluated: ___________________________________________________

Work To Be Performed: ___________________________________________________

            Step 1. Is the space…
                                                                                               Yes          No
1) Large enough for a body to enter
2) Limited or restricted means of entry or exit
3) Not designated for continuous occupancy
           If the answer to ALL three questions above is “Yes,” it is a “Confined Space” - Go to Step 2.
           If the answer to any of the questions is “No,” it is not a confined space – Proceed to Step 3,
           Sign, Date and Keep On File.

            Step 2. Does the confined space have one or more of the following:
                                                                                               Yes          No
1) Contains or has a potential to contain hazardous atmosphere                   (OR)
      a)    10% LEL (Lower Explosion Limit) – Flammable/Combustible gasses
      b)    Dust Concentrations > LEL Dust
      c)    O2 level is > 19.5% or < 23.5%
      d)    OSHA PEL (Permissible Exposure Limit) Exceeded
      e)    IDLH (Immediately-Dangerous-to-life-or-Health) Atmosphere
(See Definitions for further detail)
2) Engulfment (completely surrounded by)examples – cave-in, drowning, buried
3) Trapped or asphyxiated by inwardly converging walls
4) Is there a serious safety of health hazard that cannot be completely
   eliminated through lockout/tagout? Attach Lockout/Tagout Procedure to
   this document.
           If the answer to ANY of the above questions in Step 2 is “Yes,” the space is considered to be
           a “Permit Required Confined Space.” Contact your Regional or Corporate Safety Manager to
           discuss requirements for entry into the space. If the answer to ALL of the questions is “no,”
           the space is considered to be a “Confined Space” only. In either case, proceed to Step 3 of
           the Worksheet, Sign, Date, Keep On File.
Step 3. Check the appropriate box

                                                 Not A Confined Space
                                                 Confined Space
                                                 Permit-Required Space

____________________________                        ________________________                 _____________
                      Signature                                     Print Name                       Date


Comments:____________________________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________
__________________________________________________________

Confined Space                                                                                    Page 21
©2011, Waste Management                                                                      January 2011
CONFINED SPACE ENTRY PERMIT                                     PERMIT NO.
1. Identify Space And Work To Be Done
Space to Be Entered

Location/Building

Hazardous Materials to be Taken Into or Hazardous Work to Be Done in Space

Purpose of Entry

Authorization Duration                       From               To                             From            To
of Permit                      Date:                                             Time:
2. Identify Permit Space Hazards                                4. Make Space Before Entry
     (Indicate Specific Hazards Which May be Present)                      (Check After Steps Have Been Taken)
        Unsafe to Remove Cover, Excess Pressure                          Notify Affected Department of Service
        Excess Heat                                                      Interruption
        Oxygen Deficiency (Less than 19.5%)                     Isolation Methods
        Oxygen Enrichment (Greater than 23.5%)                     Blank/Blind                    Clearance Procedure
        Flammable Gasses or Vapors                                 Inert                          Purge/Clean
        (Greater than 10% of LEL)                                  Lockout/Tagout
        Airborne Combustible Dust                                        Other:                       Atmospheric Test
        (Greater than 10% of LEL)                                         Continuous                  Barriers
        Toxic Gases or Vapors (Greater than PEL)                          Ventilation
        Mechanical Hazards
        Electrical Shock
        Materials Harmful to Skin                               Personal Awareness
        Engulfment, Falling Slag                                  Pre-entry Briefing on Specific Hazards, Control
        Other:                                                           Methods and Emergency Action Plan
                                                                       Notify Contractors of Permit and Hazard
                                                                       Conditions
                                                                       Test/Verify Hazard Energy Control
                                                                       Other

                                                                       Additional Permits Required and/or Attached
                                                                       Hot work                        Other
3. TEST SPACE BEFORE INITIAL ENTRY & REGULARLY THEREAFTER (And Before Open Flame Work)
                                              Acceptable Entry      Initial Test           Result            Result
Material                Normal Air            Conditions            : AM/PM                : AM/PM           : AM/PM
Oxygen-min/max           20.9                 > 19.5% < 23.5%                                                _________
flammability                0                 < 10% LEL/LFL                                                  _________
Hydrogen Sulfide            0                 < 10 ppm                                                       _________
Carbon monoxide             0                 < 50 ppm                                                       _________
Chlorine                    0                 < 0.5 ppm                                                      _________
Sulfur dioxide              0                 < 2 ppm                                                        _________
Other (Specify)                                                                                              _________
Tester Initials                                                                                              _________
Always investigate before entry if conditions do not match normal air.
5. Certify Control Measures Taken, Classify Space, And Post Permit
                Low Hazard – All hazards are eliminated; none to be released by work. Follow basic safety precautions
                for the work.
                Ventilation Controlled – Only environmental hazards remain or will be released by work, which are
                controllable by ventilation. Ventilate before and during entry, with regular tests to ensure safety of air in
                the space.
                Attendant Required – Atmospheric and/or physical hazard remains. SKIP SECTIONS 6 & 7 BELOW;
                GO TO PAGE 2 AND COMPLETE



Confined Space                                                                                              Page 22
©2011, Waste Management                                                                                January 2011
Entry Leader Printed Name                                                     Date




Entry Leader Signature


6. Authorization By Entry Supervisor To Enter Reclassified Nonpermit-Required Space
I certify that all required precautions have been taken and necessary equipment is provided for safe entry and work in
this confined space, and that the space is not attendant-required.
Printed Name                                                                 Date



Signature


7. End Entry (For All Spaces)
I have checked the space to make sure no one is in it, and all measures required to return it back to normal service have
been performed. I authorize the return of this space to normal service.
Problems That Occurred


Suggestions


Entry Supervisor Printed Name                                                 Date



Entry Supervisor Signature


      THIS PERMIT MUST BE POSTED AT SPACE ENTRANCE PERMIT GOOD ONLY FOR THE DURATION OF THE JOB
          NO LIMIT ON HAZARD-CONTROLLED OR FORCED-VENTILATION SPACE UNLESS HAZARDS CHANGE
                                          CHECK BEFORE ENTRY
8. List/Signature Of Authorized Entrants (List by Name or Attach Roster)




9. List/Signature of Authorized Attendants (List by Name)




10. Ensure Emergency Rescue Available
Control Room Notified Prior to Entry (Plants)

Rescue Phone Number

Method of Contact



Confined Space                                                                                            Page 23
©2011, Waste Management                                                                              January 2011
11. Authorization by Entry Supervisor to Enter Attendant-Required Space
I certify that all required precautions have been taken and necessary equipment is provided for safe entry and work in
this confined space, and that the space is not attendant-required.
Printed Name                                                                 Date

Signature


12. Obtain Equipment Required for Entry and Work
Establish Communication Procedures to be Used by Attendants and Entrants




Specify as Required:
Personal Protective Equipment

Continuous or Period Atmospheric Testing/Monitoring

Respiratory Protection Equipment

Rescue Equipment

Other


13. End Entry (For All Spaces)
I have checked the space to make sure no one is in it, and all measures required to return it back to
normal service have been performed. I authorize the return of this space to normal service.
Problems that Occurred




Suggestions




Entry Supervisor Printed Name                                                Date


Signature


THIS PERMIT MUST BE POSTED AT SPACE ENTRANCE PERMIT GOOD ONLY FOR THE DURATION
                                    OF THE JOB
NO LIMIT ON HAZARD-CONTROLLED OR VENTILATION-VENTILATION SPACE UNLESS HAZARDS
                                     CHANGE
                               CHECK BEFORE ENTRY




Confined Space                                                                                           Page 24
©2011, Waste Management                                                                             January 2011
SUBSTANCE ABUSE PROGRAM
           FOR


   COMPANY EMPLOYEES
           AND


CANDIDATES FOR EMPLOYMENT
CONTENTS
                                                                                                                              Page

Drug and Alcohol Policy Statement ................................................................................... 1
    Introduction ...............................................................................................................1
    Substance Abuse Policy .............................................................................................. 1
    Preventing Substance Abuse ....................................................................................... 4
    Where to get Help ...................................................................................................... 6
    Summary.................................................................................................................... 6

Drug Testing Policy for All Candidates ..............................................................................8
    Policy Statement ........................................................................................................8
    Drug Testing ..............................................................................................................8
    Withdrawal of Job Offer ............................................................................................. 9

Drug and Alcohol Testing Policy for Employees in DOT-Regulated Positions................. 10
    Policy Statement ...................................................................................................... 10
    DOT- Covered Employees ....................................................................................... 10
    Prohibited Conduct .................................................................................................. 11
    Drug and Alcohol Testing ........................................................................................ 11
    Refusal To Test ........................................................................................................ 14
    Consequences of a POSITIVE Drug or Alcohol Test ............................................... 14

Drug and Alcohol Testing Policy for Employees in Non-DOT Positions ......................... 17
    Policy Statement ...................................................................................................... 17
    Drug and Alcohol Testing ........................................................................................ 17
    Refusal to Test ......................................................................................................... 19
    Consequences of a POSITIVE Drug or Alcohol Test ............................................... 19
    Adulterated or Substituted Results ........................................................................... 20

Definitions ....................................................................................................................... 22

Appendix A: Non-DOT Safety Sensitive Positions

Appendix B: Physician Statement Regarding Prescription Medication




Substance A buse Program                                                                                     2002, W aste M anagement
for Company E mployees and C andidates for E mployment                                                        Revised September 2008
                                                                                                                                Page i
DRUG AND ALCOHOL POLICY STATEMENT
INTRODUCTION          Waste Management (WM or Company) is committed to providing
                      employees with a safe and healthy work environment. To ensure safety for
                      employees, customers and the communities in which it operates, WM has
                      taken a zero tolerance approach to substance abuse.

                      Substance abuse
                                   Increases the risk of workplace injuries and incidents
                                   Affects the health and well being of the user
                                   Lowers productivity and quality

                      WM uses the federal drug-testing model for its Substance Abuse Program.
                      This federal drug testing model is detailed in 49 CFR, Parts 40 and 382.

                      Some states or locales may have certain limits on drug and/or alcohol
                      testing not covered by federal drug testing policy. Where needed, this
                      policy will be changed as required by local and/or state laws.

                       W AST E M A N A G E M E N T IS C O M M I T T E D T O M A IN T A I N I N G A
                       W O R K P L A C E T H A T IS F R E E F R O M T H E I N F L U E N C E O F
                       D R U GS A N D A L C O H O L A B USE.

SUBSTANCE             No person may
ABUSE POLICY
                                    use                                     transfer
                                    sell                                    possess
                                    make                                    consume
                                    handle                                  inhale
                                    purchase                                transport
                      or otherwise be involved with drugs or alcohol while on WM property or
                      while operating WM vehicles.


                                         controlled substances
                                         illegal drugs
                                         legal drugs illegally used
                                         intoxicants
                                         drug paraphernalia
                                         alcohol

                      In addition, no employee may work while under the influence of alcohol or

                      test as determined by the testing lab.


Substance A buse Program                                                           2002, W aste M anagement
for Company E mployees and C andidates                                              Revised September 2008
                                                                                                      Page 1
MEDICATIONS           Employees taking medication that will affect their ability to work safely are
                      required to give their supervisor a statement from the doctor who
                      prescribed the medication. This statement must:
                                     say that the medication was prescribed with full knowledge
                                     of their job duties and
                                     give recommendations for appropriate work modification

                      WM does not want to know the name of the medication or why it was
                      prescribed. Employees should have their doctor sign the form included at
                      the end of this document. (See Appendix B for Physician Statement
                      Regarding Prescription Medication)

                                                                       medication. Doing so is
                      illegal. In addition, this might result in a positive drug test and corrective
                      action will result.

LEGAL DRUGS           Legal drugs illegally used means
ILLEGALLY                            drugs that are not prescribed for the employee or
USED                                 drugs that are not
                                     doctor

DRUG                  Drug Paraphernalia means any item used to perform any of the actions
PARAPHERNALIA         listed below with regard to drugs.
                                     use                                 possess
                                     sell                                consume
                                     make                                inhale
                                     handle                              transport

W ASTE       WM has the right, at all times, to inspect
MANAGEMENT S              all persons,
RIGHTS                    their property, and
                                         WM provided property

                      prior to entering, while on, and when leaving WM property. Illegal drugs
                      found in or on WM property or vehicles will be turned over to the
                      appropriate law enforcement officials.




Substance A buse Program                                                             2002, W aste M anagement
for Company E mployees and C andidates                                                Revised September 2008
                                                                                                        Page 2
DEFINITION OF
DRUGS
                                              controlled substances
                                              illegal drugs
                                              legal drugs illegally used
                                              drug paraphernalia
                                              intoxicant
                                              alcohol
                                              prescription medication
                                              over-the-counter medication
                              that if abused, may lead to physical or psychological dependence.

ADULTERATED OR Adulterated means contaminated. Substituted means replaced. If a urine
SUBSTITUTED
               Medical Review Officer (MRO) will report it to the Designated Employee
RESULTS
                              Representative (DER) as a refusal to test. A refusal to test is considered
                              the same as a positive test.

REFUSAL TO                    Employees who refuse to take a drug or alcohol test upon request or
TEST                          when scheduled are terminated.1

EXCEPTIONS                    WM may allow alcohol to be used at WM functions.

                              An employee may work while taking a drug IF the drug
                                           has been prescribed by a doctor,
                                           is being used as directed by the doctor,
                                           does not reduce the ability to work safely and efficiently,
                                           and
                                           does not pose a risk to workplace safety.

                              If the drug could prevent the employee from working safely and
                              efficiently, he or she must tell his or her supervisor or Human Resources
                              Representative without delay.

                              In some instances, the employee may be required to provide a medical
                              statement regarding their ability to safely perform job duties.

COST                          WM pays all costs for drug and alcohol testing required by WM. This
                              includes pre-employment testing for candidates.




1
    unless otherwise directed in any collective bargaining agreement



Substance A buse Program                                                                2002, W aste M anagement
for Company E mployees and C andidates                                                   Revised September 2008
                                                                                                           Page 3
PREVENTING              To maintain a workplace that is free from drugs and alcohol, WM uses a
SUBSTANCE               Substance Abuse Program. This program includes:
ABUSE                                    education,
                                         training, and
                                         drug and alcohol testing

EDUCATION               Employees learn about


                                         The health effects of drugs and alcohol.

                                      substance abuse problems.
                        See below for more information on the EFAP.

TRAINING                WM provides training for supervisors so they can recognize

                                       early warning signs,
                                       symptoms, and
                                       behavior
                        that might indicate a use/abuse problem.

                        Supervisors also learn how to address performance problems resulting from
                        substance abuse.

DRUG AND                WM has developed a drug and alcohol testing program. The basics of this
ALCOHOL                 program are described in this document.
TESTING                 Test results are confidential. The donor is identified at the testing laboratory
                        (lab) with a number only. The results are not made known to anyone except
                        WM employees with a legitimate, business-related reason to know.

                        The MRO receives the test results from the lab. An MRO is a licensed doctor
                        who knows how to read substance-abuse tests. The MRO sends the results to
                        the Designated Employee Representative (DER). The DER shares the
                        information only as corrective action is required. The results can only be
                        released outside of WM with written permission.

DRUG TESTING            Urine is tested for controlled substance use. Listed below are the substances
                        the test covers.

                                         Marijuana                              Phencyclidine (PCP)
                                         Cocaine                                Amphetamines
                                         Opiates




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                       Page 4
DRUG TESTING            The urine is sent to a lab that is certified by the Department of Health and
(CONTD.)                Human Services. The collector has been qualified according to DOT

                        Custody and Control Form (CCF) or Chain of Custody Form (COC) identifies
                        and stays with the specimen. This makes sure that no once can tamper with the
                        urine. It ensures that the urine provided is the urine that is tested.


                        Custody and Control begins when the urine is collected and ends when it is

                            1. A sample is provided.
                            2. The sample is labeled with an assigned number. The number is bar

                               It is sealed in a tamper-evident container. This kind of container shows
                               evidence of any attempt to tamper with the seal.
                            3. The sample is sent to the lab for analysis. Security is very high at the
                               lab. The lab documents everything it does with the specimen. The lab
                               computer confirms that the specimen matches its Custody and Control
                               Form (CCF)/Chain of Custody Form (COC).

                        At the lab, the urine is screened. If it is positive, then it is tested again. This
                        test is completely separate from the first test. It uses a different technique. It
                        uses a different chemical principle. If this test is negative, no further testing is
                        done. If this test is positive for drugs, a confirmation test is done. If that test
                        is positive for drugs, it will be referred to the MRO for handling. The lab
                        stores the specimen in a secure refrigerator. Negative specimens are discarded
                        within 5 days. Positive specimens are held for one year.


ALCOHOL                 The first screening is performed on saliva or breath. A qualified Saliva Test or
TESTING                 Breath Alcohol Technician collects the test sample. The technician analyzes
                        the sample right away. If the first screening is positive (at or above 0.02), a
                        second test is done after 15 minutes to confirm the result. This second test is
                        on breath only. It is done with a device approved by the federal government.
                        It shows breath alcohol concentration (BAC). If this test is negative, no further
                        testing is done.

                        Alcohol testing is done
                                       just before,
                                       during, or
                                       just after

                        on-duty or Company time.




Substance A buse Program                                                             2002, W aste M anagement
for Company E mployees and C andidates                                                Revised September 2008
                                                                                                        Page 5
IF AN EMPLOYEE          Employees with substance abuse problems should get help before those
NEEDS HELP              problems affect their job performance. Substance abuse problems can also
                        affect qualifications to operate commercial motor vehicles.

                        Employees are not penalized for seeking assistance. However, corrective
                        action up to and including termination may be taken for poor job performance,
                        regardless of the reason.

THE EFAP                The Employee Family Assistance Program (EFAP) provides

                                      assessment,
                                      counseling, and
                                      treatment services
                        for employees who have substance abuse problems. These services are
                        confidential.


                        employees recover from the illness of substance abuse while they continue to
                        meet the duties of their jobs. Getting help is the first step towards
                                       regaining control,
                                       rebuilding relationships, and
                                       resuming good performance.

                        If an employee, any of their family members, or any of their co-workers need
                        help, they should contact the EFAP at 1.800.852.7461.

EDUCATION               The EFAP also provides employees education about substance abuse.
                        Employees can learn to recognize

                                       early warning signs,
                                       symptoms, and
                                       behavior
                        that might indicate a use/abuse problem.

                        Employees can also learn about the harmful effects of substance abuse. The
                        EFAP can also provide employees with community resources and referrals for
                        help.

OTHER HELP
                        other WM policies, such as leave-of-absence policies.

SUMMARY                 The Drug and Alcohol Policy applies to all WM employees and candidates. To
                        be hired and to remain employed by WM, everyone must comply with the
                        Substance Abuse Program. This includes drug and alcohol testing when
                        requested.


Substance A buse Program                                                         2002, W aste M anagement
for Company E mployees and C andidates                                            Revised September 2008
                                                                                                    Page 6
SUMMARY                 Any employee
(CONTD.)
                                         whose test is positive for the presence of a prohibited substance,
                                         who refuses to test,
                                         who acts in a way that clearly obstructs the testing process, or
                                         who refuses to cooperate in an investigation of a policy violation


                        E M P L O Y E ES W H O V I O L A T E T H E D R U G A N D A L C O H O L PO L I C Y
                        W I L L B E SU BJ E C T T O C O R R E C T I V E A C T I O N UP T O A N D
                        I N C L U D I N G T E R M I N A T I O N.




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                       Page 7
DRUG TESTING POLICY FOR ALL CANDIDATES

POLICY                                                                                       It
STATEMENT                provides for drug testing of all candidates for all positions at WM.
                         Applicants who are offered a job with WM become job candidates.

DRUG TESTING             All candidates must pass a pre-employment urinalysis drug test before
                         being hired. This applies to all jobs at WM. Applicants are told about
                         this requirement in writing when they first apply for employment.
                         Applicants who are offered a job must submit a urine sample. This
                         sample is tested for illegal drugs. Candidates cannot begin work at WM
                         until they receive a negative test.

DOT APPLICANTS           Applicants who apply for DOT positions must provide to WM drug and
                         alcohol violations and DOT reportable accidents for the previous 36-
                         months.

                         A positive drug or alcohol result or a refusal to test within the past 36
                         months will disqualify the applicant for employment.

DILUTE SPECIMEN          A dilute specimen is one where creatinine and specific gravity levels are
                         lower than expected for human urine. WM uses the following guidelines
                         for dilute specimens

                         C reatinine L evel:       L ab Reports As:           Action Required:

                         Less than 5mg             Substituted               Same as a positive/refusal
                                                                             to test

                         2-5mg                     Cancelled-Dilute          Immediate observed re-
                                                                             test required.

                         Greater than 5mg          Negative-Dilute           Immediate non-observed
                                                                             re-test required

                         If the result of the second test is also negative dilute WM policy does not
                         allow for a third test to be conducted. A negative dilute re-test is
                         considered a negative test.




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                       Page 8
W ITHDRAWAL OF           If a candidate
JOB OFFER                               fails to provide the 36-month history of drug and alcohol
                                        violations and DOT reportable accidents,
                                        misses the appointment for collection,
                                        refuses to sign a consent form,
                                        refuses to submit to the drug test, or
                                        fails the drug test
                         any offers of employment will be withdrawn.

                         Candidates who test positive for drugs may request a copy of the test
                         result.




Substance A buse Program                                                         2002, W aste M anagement
for Company E mployees and C andidates                                            Revised September 2008
                                                                                                    Page 9
DRUG AND ALCOHOL TESTING POLICY
                      FOR EMPLOYEES IN DOT-REGULATED POSITIONS
POLICY
STATEMENT                       provides for drug and alcohol testing of WM employees who are
                                covered by the drug and alcohol testing requirements of the Federal
                                Motor Carrier Safety Administration (FMCSA), part of the U.S.
                                Department of Transportation (DOT). Its purpose is
                                               to reduce employee substance abuse and
                                               to prevent incidents in the workplace related to substance
                                               abuse.

                                All DOT employees must follow this Policy to remain employed.

                                Employees who violate this Policy are removed from performing safety
                                sensitive functions. They are also subject to corrective action up to and
                                including termination. Violation includes refusing to take a drug or
                                alcohol test upon request.1

                                All drug and alcohol tests conducted pursuant to this Policy are done in

                                procedures c
                                alcohol testing regulations.

                                This Policy may be changed without notice if necessary to comply with
                                current or future DOT regulations.

DOT COVERED                     Employees who
EMPLOYEES                                   operate commercial motor vehicles and

                                must follow this Policy.

                                DOT covered employees include the types of drivers listed below.
                                            full-time
                                            part-time
                                            casual
                                            intermittent
                                            occasional



1
    Corrective action measures described in any collective bargaining agreement may also apply.




Substance A buse Program                                                                          2002, W aste M anagement
for Company E mployees and C andidates                                                             Revised September 2008
                                                                                                                    Page 10
PROHIBITED                DOT employees must N O T
CONDUCT
                                         report to duty or remain on duty requiring the
                                         performance of safety sensitive functions while having a
                                         BAC of 0.02 or higher.
                                         be on duty or operate a commercial motor vehicle while
                                         possessing alcohol.
                                         use alcohol while performing safety sensitive functions.
                                         perform safety sensitive functions within 4 hours after
                                         using alcohol.
                                         report for duty or remain on duty requiring the
                                         performance of safety sensitive functions when the driver
                                         uses any drug.
                          This does not apply if the driver
                                         is taking medication under a doctor

                                         ability to safely operate a commercial motor vehicle.

DRUG AND                  DOT employees are required to take a urinalysis drug test and an
ALCOHOL TESTING           alcohol test under the conditions listed below:

                                         Pre-Employment (urine test only)
                                         Pre-Use (urine test only, prior to beginning or upon
                                         transfer to a DOT or non-DOT safety sensitive position)
                                         Reasonable Suspicion
                                         Post Accident
                                         Random
                                         Return-to-Duty
                                         Follow-Up

PRE-EMPLOYMENT            All candidates must pass a pre-employment urinalysis drug test before
AND PRE-USE               being hired. This applies to all jobs at WM. Applicants are told about
                          this requirement in writing when they first apply for employment.
                          Applicants who are offered a job must submit a urine sample. This
                          sample is tested for illegal drugs. All employees transferring into DOT
                          or non-DOT safety sensitive positions must pass a urinalysis drug test.

REASONABLE                Reasonable suspicion occurs when a supervisor who is trained to detect
SUSPICION                 the signs of alcohol and drug use has reason to believe that the driver
                          performed any of the actions listed under Prohibited Conduct on this
                          page.




Substance A buse Program                                                          2002, W aste M anagement
for Company E mployees and C andidates                                             Revised September 2008
                                                                                                    Page 11
BASIS OF
REASONABLE                alcohol use on observations. These observations must be about
                          appearance, behavior, speech or body odor that is
SUSPICION
                                         specific,
                                         current (happening from recent past and continuing), and
                                         can be described in words.

                          The observations may also include indications of the chronic use and/or
                          withdrawal effects of drugs or alcohol.

                          However alcohol tests are conducted only
                                         just before,
                                         while, or
                                         just after
                          the driver performs safety sensitive functions.

                          The supervisor making the observation makes a written record of those
                          observations.

POST ACCIDENT             A DOT employee must take a drug and alcohol test following an
                          accident involving a commercial motor vehicle. This applies only in the
                          situations listed below.

                              1. The driver is involved in an accident that results in a fatality.
                              2. The driver is involved in an accident that results in
                                    a citation for a moving violation and
                                    medical treatment away from the scene of the accident.
                              3. The driver is involved in an accident that results in
                                    a citation for a moving violation and
                                    one or more damaged vehicles that must be towed.

                          Employees who must take a post-accident test must remain readily
                          available for a test following the accident. If they do not, they are
                          judged to have refused to take the test.

                          DOT employees required to take a post accident test must not use
                          alcohol for eight hours after the accident or until undergoing the post
                          accident test, whichever occurs first.

                          Post accident drug and alcohol testing conducted by the authorities is
                          NOT a substitute for conducting our own post accident test (or, if
                          applicable, reasonable suspicion). In cases where the authorities have
                          conducted their own test, this will require the driver to provide a
                          separate specimen for the WM required test.


Substance A buse Program                                                             2002, W aste M anagement
for Company E mployees and C andidates                                                Revised September 2008
                                                                                                       Page 12
RANDOM                    DOT employees are required to submit to random drug and alcohol
                          testing upon request.

                          Random drug tests are unannounced and occur periodically throughout
                          the year. However, alcohol tests are conducted only
                                  just before,
                                  while, or
                                  just after
                          the driver performs safety sensitive functions.

TEST RATES                Random drug testing is conducted at the annual rate of 50% of the
                          average number of DOT positions. Random alcohol testing is
                          conducted at the annual rate of 10% of the average number of DOT
                          positions. Test rates may be adjusted by DOT.

EMPLOYEE                  Employees are selected for random testing by a scientifically valid
SELECTION FOR             method. This method ensures that each DOT employee has an equal
                          chance of being selected each time selections are made.
RANDOM TESTING

RETURN-TO-DUTY            An employee who is not terminated after a positive urine drug test or
AND FOLLOW -UP            breath alcohol test, per state law or a collective bargaining agreement,
                          must
TESTING
                                  sign a Last Chance Agreement,
                                  be evaluated by a Substance Abuse Professional (SAP),
                                  have negative test results before returning to duty, and
                                  be in compliance with whatever treatment plan the SAP requires.

                          The employee may return to duty only after a SAP releases him or her
                          for return. After the required evaluation, the SAP writes a letter
                          confirming that he or she may return to duty.

                          The employee will also be required to take random drug and alcohol
                          tests no fewer than six times throughout the next year.

                          Follow-up alcohol testing is conducted only
                                 just before,
                                 while, or
                                 just after
                          the employee performs safety sensitive functions.

                          All return-to-duty and follow-up tests must be performed using
                          observed collection.




Substance A buse Program                                                           2002, W aste M anagement
for Company E mployees and C andidates                                              Revised September 2008
                                                                                                     Page 13
REFUSAL TO TEST               Employees who refuse to take a drug or alcohol test upon request or
                              when scheduled are terminated.1

                              A refusal to test is considered the same as a positive result. Any
                              conduct that interferes with the testing process is considered a refusal to
                              test, and therefore, a positive result. Examples of this are
                                      missing the appointment and
                                      going the next day because of personal preference.

                              Refusing to sign step 4 of the Alcohol Testing Form is considered a
                              refusal to test when the employee takes an alcohol confirmation test. In
                              this case the employee will be terminated.1

CONSEQUENCES                  DOT employees will be terminated if
OF A POSITIVE
                                   alcohol test shows a BAC of 0.04 or higher or
DRUG OR
                                   urine test shows the presence of drugs as determined by the
ALCOHOL TEST1 2                    MRO.
                              DOT employees with a BAC between 0.02 and 0.039
                                   will be removed from safety sensitive duties for a minimum of 24
                                   hours and suspended, pending an evaluation and return-to-duty
                                   recommendation from a SAP.
                                   will be terminated if they refuse to go to a SAP for evaluation
                                   and comply with the follow-up recommendations an/or
                                   treatment.
                                   must pass a return-to-duty breath alcohol and urine drug test,
                                   sign a Last Chance Agreement, and undergo follow-up testing
                                   for up to 60 months if requested by the SAP, including no less
                                   than 6 random tests in the first year.

                              A second test of 0.02 or higher or a positive urine test will lead to
                              termination as required by the terms of the Last Chance Agreement.

                              An employee may take sick time, vacation time or any other accrued
                              time and/or apply for short-term disability (STD) to cover lost wages.




1
 Consequences of a positive drug or alcohol test or a refusal to test for employees covered by a collective bargaining
agreement may differ from other employees.



2
 In accordance with California State Law, all Commercial Drivers with a BAC of 0.01 or higher must be placed out of
service for 24 hours.
Substance A buse Program                                                                    2002, W aste M anagement
for Company E mployees and C andidates                                                        Revised September 2008
                                                                                                               Page 14
CONSEQUENCES              DOT candidates are also subject to the rules and regulations of the
OF A POSITIVE             Department of Transportation. These rules and regulations are
DRUG OR
ALCOHOL TEST
(CONTD.)                  WM is required by DOT regulations to obtain a three-year history of a
                                                   lcohol testing and accident history from the

                          provide and drug and alcohol testing and accident records they have
                          from previous employers. Therefore, if a DOT employee tests positive
                          on a drug or alcohol tests, that will follow the person for at least three
                          years.

                          Candidates who have tested positive for drugs or alcohol at a prior
                          employer must provide documentation that they have successfully
                          completed a SAP evaluation and are following the recommended course
                          of treatment.

DILUTE SPECIMENS A dilute specimen is one with creatinine and specific gravity levels that
                          are lower than expected for human urine. The DOT has established the
                          following guidelines for dilute specimens

                          C reatinine L evel:       L ab Reports As:          Action Required:

                          Less than 2mg             Substituted               Same as positive/refusal to
                                                                              test

                          2-5mg                     Cancelled- Dilute         Immediate observed re-
                                                                              test required

                          Greater than 5mg          Negative Dilute           Immediate non-observed
                                                                              re-test required


                          If the result of the second test is also negative dilute, WM policy does
                          not allow for a third test to be conducted. A negative dilute re-test is
                          considered a negative test.

ADULTERATED OR            Adulterated means contaminated. Substituted means replaced. If a
SUBSTITUTED               urine specimen has been contaminated, tampered with, or replaced, the
                          MRO will report it to the Designated Employee Representative (DER)
RESULTS
                          as a refusal to test. A refusal to test is considered the same as a positive
                          test.




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                      Page 15
SPLIT SAMPLE              DOT employees or candidates who have a verified positive, adulterated
TEST                      or substituted test result will be contacted by the MRO. They may
                          explain the test result or disclose any prescription medication that they
                          are taking that may have caused the result. This information will remain
                          confidential. They may also request a split sample test. The split
                          sample is a portion of the original specimen that has been stored at the
                          lab. The sample will be sent to a different lab for testing and the
                          employee or candidate is responsible for the cost of the test. The result
                          of the split sample test will be the test result of record. The employee or
                          candidate will not be able to provide a new specimen.

GETTING HELP              If the SAP determines that the employee needs assistance with a
                          substance abuse problem, the employee must follow any treatment
                          program recommended by the SAP.


                          Employees can get information from the EFAP or a SAP about available
                                experts,
                                treatment, and
                                rehabilitation programs.

FOLLOW -UP                Employees who have been identified by a SAP as needing help must
TESTING                   undergo follow-up testing when they return to safety sensitive functions.

                          Follow-up testing
                                 consists of at least six tests in the first 12 months,
                                 may continue for up to 60 months, and
                                 may include both drug and alcohol testing.

                          Per DOT regulations, all follow-up tests will be done under observed
                          collection.


                          Testing Policy may contact the Background Screening and Drug Testing
                          Unit (BDU) at 866-875-4884.




Substance A buse Program                                                             2002, W aste M anagement
for Company E mployees and C andidates                                                Revised September 2008
                                                                                                       Page 16
DRUG AND ALCOHOL TESTING POLICY
                       FOR EMPLOYEES IN NON-DOT POSITIONS


POLICY
STATEMENT                provides for the drug and alcohol testing of WM employees under certain
                         circumstances. Its purpose is
                                to reduce employee substance abuse and
                                to prevent incidents in the workplace related to substance abuse.

                         WM believes that drug and alcohol testing is a valuable and appropriate
                         way to address safety concerns. All non-DOT employees must follow
                         this Policy to remain employed. Violation includes refusing to take a
                         drug or alcohol test when scheduled or upon request.

                         Some states and locales may have certain restrictions on drug and/or
                         alcohol testing. This policy will be modified to the extent that local
                         and/or state laws require.

                         E M P L O Y E ES W H O V I O L A T E T H IS PO L I C Y A R E SU BJ E C T
                         T O C O R R E C T I V E A C T I O N UP T O A N D I N C L U D I N G
                         T E R M I N A T I O N.

DRUG AND                 Non-DOT employees are required to take a urinalysis drug test and
ALCOHOL                  alcohol breath test under the conditions listed below:
TESTING                         Pre-employment (urine test only)
                                Pre-use (urine test only, prior to beginning or upon transfer to a
                                DOT or non-DOT safety sensitive position)
                                Reasonable Suspicion
                                Post accident
                                Random
                                Return-to-duty
                                Follow-up
                         These situations are explained below.

PRE-           All candidates must pass a pre-employment urinalysis drug test before
EMPLOYMENT AND being hired. This applies to all jobs at WM. Applicants are told about
               this in writing when they first apply for employment. Applicants who are
PRE-USE
                         offered a job must submit a urine sample. This sample is tested for illegal
                         drugs. All employees transferring into DOT or non-DOT safety sensitive
                         positions must pass a urinalysis drug test.




Substance A buse Program                                                           2002, W aste M anagement
for Company E mployees and C andidates                                              Revised September 2008
                                                                                                     Page 17
REASONABLE               Reasonable suspicion occurs when a supervisor has reason to suspect
SUSPICION                that the employee
                                 has used drugs or alcohol or
                                 is under the influence of drugs or alcohol

                         performance.

BASIS OF
REASONABLE               alcohol use on observations. These observations must be about
                         appearance, behavior, speech or body odor that is
SUSPICION
                                specific,
                                current (happening in recent past and continuing), and
                                can be described in words.

                         The observations may also include indications of the chronic use and/or
                         withdrawal effects of drugs or alcohol.

POST ACCIDENT            Reasonable suspicion guidelines must be followed when deciding
                         whether a drug and/or alcohol test should be performed after an on-the-
                         job accident.
                         Post accident drug and alcohol testing conducted by the authorities is
                         NOT a substitute for conducting our own post accident (or, if applicable,
                         reasonable suspicion) test. In cases where the authorities have conducted
                         their own test, this will require the driver to provide a separate specimen
                         for the WM required test.

RANDOM                   Non-DOT employees are required to submit to random drug and alcohol
                         testing upon request.

                         Random drug tests are unannounced and occur periodically throughout
                         the year, however alcohol tests are only conducted
                                 just before,
                                 while, or
                                 just after
                         the employee performs his/her job functions.

TEST RATES               Random drug and alcohol testing is conducted at the rate of 10% of the
                         average number employees in safety sensitive positions and non-safety
                         sensitive positions. Tests rates may be adjusted by WM.

EMPLOYEE                 Employees are selected for random testing by a scientifically valid
SELECTION FOR            method. This method ensures that each safety sensitive employee has an
                         equal chance of being selected each time selections are made.
RANDOM TESTING


Substance A buse Program                                                          2002, W aste M anagement
for Company E mployees and C andidates                                             Revised September 2008
                                                                                                    Page 18
RETURN-TO-DUTY Non-DOT employees who are not terminated after a positive urine drug
AND FOLLOW -UP test or alcohol test, per state law or a collective bargaining agreement,
               must
TESTING
                                 sign a Last Chance Agreement,
                                 be evaluated by a Substance Abuse Professional (SAP),
                                 have negative test results before returning to duty, and
                                 be in compliance with whatever treatment plan the SAP requires.

                         The employee may return to duty only after a SAP releases him or her
                         for return. After the required evaluation, the SAP writes a letter
                         confirming that he or she may return to duty.

                         The employee will also be required to take random drug and alcohol tests
                         no fewer than six times throughout the next year.

                         Follow-up alcohol testing is conducted only
                                just before,
                                while, or
                                just after
                         the employee performs his/her job functions.

                         All return-to-duty and follow-up tests must be performed using observed
                         collection.

REFUSAL TO TEST Employees who refuse to take drug or alcohol random tests are
                         terminated immediately.

                         A refusal to test is considered the same as a positive result. Any conduct
                         that interferes with the testing process is considered a refusal to test, and
                         therefore a positive result. Examples are
                                 missing the appointment and
                                 going the next day because of personal preference.

                         Refusing to sign Step 4 of the Alcohol Testing Form is considered a
                         refusal to test when the employee takes an alcohol confirmation tests. In
                         this case the employee is terminated.

CONSEQUENCES             Non-DOT employees will be terminated if
OF A POSITIVE                 alcohol test shows a BAC of 0.04 or higher or
DRUG OR                       urine test shows the presence of drugs as determined by the
                              MRO.
ALCOHOL TEST




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                      Page 19
CONSEQUENCES             Non-DOT employees with a BAC between 0.02 and 0.039
OF A POSITIVE                 will be removed from duty for a minimum of 24 hours and
DRUG OR                       suspended, pending an evaluation and return-to-work
                              recommendation from a SAP.
ALCOHOL TEST
                              will be terminated if they refuse to go to a SAP for evaluation and
(CONTD.)                      comply with follow-up recommendations and/or treatment.
                              must pass return-to-duty breath alcohol and urine drug test, sign
                              a Last Chance Agreement, and undergo random testing for up to
                              60 months if requested by the SAP, including no less than 6
                              random tests in the first year.

                         A second test of 0.02 or higher or a positive urine drug test will lead to
                         termination as required by the terms of the Last Chance Agreement.

                         An employee may take sick time, vacation time or any accrued time
                         and/or apply for short-term disability (STD) to cover lost wages.

DILUTE                   A dilute specimen is one where creatinine and specific gravity levels are
SPECIMENS                lower than expected for human urine. WM has established the following
                         guidelines for dilute specimens

                         C reatinine L evel        L ab Reports As:          Action Required:

                         Less than 2mg             Substituted               Same as positive/refusal to
                                                                             test

                         2-5mg                     Cancelled-Dilute          Immediate observed re-
                                                                             test required

                         Greater than 5mg          Negative Dilute           Immediate non-observed
                                                                             re-test required

                         If the result of the second test is also negative dilute, WM policy does
                         not allow for a third test to be conducted. A negative dilute re-test is
                         considered a negative test.

ADULTERATED OR           Adulterated means contaminated. Substituted means replaced. If a urine
SUBSTITUTED              specimen has been contaminated, tampered with, or replaced, the MRO
                         will report it to the Designated Employee Representative (DER) as a
RESULTS
                         refusal to test. A refusal to test is considered the same as a positive
                         result.


                         For employees, a positive test results in corrective action up to and
                         including termination. For candidates, WM withdraws any job offer.



Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                      Page 20
SPLIT SAMPLE             Non-DOT employees or candidates who have a verified positive,
TEST                     adulterated or substituted test result will be contacted by the MRO.
                         They may explain the test result or disclose any prescription medication
                         that they are taking which may have caused the result. This information
                         will remain confidential. They may also request a split sample test. The
                         split sample is a portion of the original specimen that has been stored at
                         the lab. The sample will be sent to a different lab for testing and the
                         employee or candidate is responsible for the cost of the test. The result
                         of the split sample test will be the test result of record. The employee or
                         candidate will not be able to provide a new specimen.

                                                                        -DOT Drug and
                         Alcohol Testing Policy may contact the Background Screening and Drug
                         Testing Unit (BDU) at 866-875-4884.




Substance A buse Program                                                           2002, W aste M anagement
for Company E mployees and C andidates                                              Revised September 2008
                                                                                                     Page 21
DEFINITIONS

                      Several of the terms used throughout this Policy are defined below.

                      A chain of custody tracks the handling and storage of a urine specimen.
        CHAIN OF The tracking begins when the urine is collected. It ends when the urine is
        CUSTODY discarded. That way, the urine tested is the urine provided. This procedure
                      makes sure that no one can tamper with the specimen.

   COMMERCIAL
       MOTOR              1.   Vehicles with a gross combination weight rating of 26,001 or more
                               pounds. This includes a towed unit with a gross vehicle weight
      VEHICLE
                               rating of more than 10,000 pounds.
                          2.   Vehicles with a gross vehicle weight rating of 26,001 or more
                               pounds.
                          3.   Vehicles that are designed to transport 16 or more passengers
                               including the driver.
                          4.   Vehicles that are used in the transportation of hazardous materials
                               that require a warning placard.

                      A confirmatory test is done if the first test is positive (shows drug or alcohol
CONFIRMATORY use). Its purpose is to make sure the first test is correct. It shows the
        TEST presence of a drug or alcohol.
                      At this time, the method to confirm positive drug tests is GC/MS. This
       FOR DRUGS


                      This test is performed on all urine specimens that test positive on the first
                      test. It can detect a drug or other substances that show the drug is present
                      (drug metabolite). This test is completely separate from the first test. It
                      uses a different technique. It also uses a different chemical principle. If this
                      test is negative, no further testing is done. A positive test results in
                      corrective action up to and including termination.

     F OR A LC O H OL If a first test shows a BAC of 0.02 or higher, a second Breathalyzer test is
                      used to make sure the first test was correct. If this test is negative, no
                      further testing is done. A positive test results in corrective action up to and
                      including termination.




Substance A buse Program                                                            2002, W aste M anagement
for Company E mployees and C andidates                                               Revised September 2008
                                                                                                      Page 22
DEFINITIONS (CONTD.)


DRUG                  A drug metabolite is the specific substance produced when a given drug
METABOLITE            passes through the body and leaves in the urine. In other words, the body
                                                                    re other substances that end up
                      in the urine.

EMPLOYEE              EFAP is a program provided through a contracted service. It assists
FAMILY                employees in dealing with drug or alcohol dependency. It can also help
                      employees with other personal problems.
ASSISTANCE
PROGRAM
(EFAP)

INITIAL TEST OR See also Confirmatory Test.
SCREENING
TEST

F OR D RUG S          The fist test is a urine test. An immunoassay screen is used. If the test is
                      negative then no further testing is done. If the test is positive, a
                      Confirmatory Test is done.

F OR A LC O H OL      The first test for alcohol is a Breathalyzer test. If the test is negative, then
                      no further screening is done. If the test is positive (BAC of 0.02 or higher),
                      a Confirmatory Test is done. This second test uses a Breathalyzer.

MEDICAL               A MRO is a licensed doctor. The MRO receives the lab results from the
REVIEW                drug testing program. MROs know about substance abuse problems. They
                      also have medical training to interpret and evaluate positive test results
OFFICER
                      along wit
(MRO)

DOT SAFETY            The following functions are considered DOT safety sensitive functions when
SENSITIVE             performed by a driver of a commercial motor vehicle.
                          1. Waiting to be dispatched or to operate a commercial motor vehicle.
FUNCTIONS
                          2. Inspecting, conditioning, or servicing a commercial motor vehicle.
                          3. Driving a commercial motor vehicle.
                          4. Loading or unloading (or assisting or supervising loading or
                              unloading) a commercial motor vehicle.
                          5. Repairing, obtaining assistance, or remaining in attendance upon a
                              disabled commercial motor vehicle.



Substance A buse Program                                                             2002, W aste M anagement
for Company E mployees and C andidates                                                Revised September 2008
                                                                                                       Page 23
DEFINITIONS (CONTD.)
NON-DOT               A non-DOT safety sensitive position requires the performance of specific
SAFETY                physical or supervisory tasks. If these tasks are done incorrectly, injury or
                      death to employees or others could result. In addition, significant property
SENSITIVE
                      or environmental damage could occur.
POSITION




Substance A buse Program                                                           2002, W aste M anagement
for Company E mployees and C andidates                                              Revised September 2008
                                                                                                     Page 24
APPENDIX A: NON-DOT SAFETY-SENSITIVE POSITIONS
Definition: A non-DOT safety sensitive position requires the performance of specific physical or
supervisory tasks. If these tasks are done incorrectly, injury or death to employees or others could
result. In addition, significant property or environmental damage could occur.
L andfill                                             T ransfer Station
   Mechanic / Fueler                                      Mechanic
   Tire Replacer                                          Tire Replacer
   Parts Runner                                           Parts Runner
   Heavy Equipment Operator                               Transfer Truck Driver
   Spotter                                                Heavy Equipment Operator
   Wood Chipper / Grinder                                 Spotter
   Tipper Operator                                        Helper
   Helper

MRF                                                   H auling
   Mechanic                                               Vehicle Mechanic
   Heavy Equipment Operator                               Fabricator / Container Repair
   Spotter                                                Tire Replacer
   Helper                                                 Parts Runner
                                                          Bin Delivery
                                                          Portalet Driver
                                                          Helper


M ISC
Any employee who drives regularly and on a consistent basis as part of his or her job duties (includes
employees who receive a car allowance, are issued a company vehicle, or who participate in the
Runzheimers Program)


Workers running mobile machinery


Mechanics


Helpers



Substance A buse Program                                                          2002, W aste M anagement
for Company E mployees and C andidates                                             Revised September 2008
                                                                                                    Page 25
APPENDIX B:

PHYSICIAN STATEMENT REGARDING PRESCRIPTION MEDICATION
W AST E M A N A G E M E N T
                                                                1001 FANNIN, SUITE4000
                                                                     HOUSTON, TX 77002
                                                                          (713) 512-6000

                           Physician Statement Regar ding Prescription M edication



Supervisor completes this section.

 W M Site ________________________________ Date

 E mployee Name ________________________ A ddress

State/Zip Code ________________ Telephone Number

Job T itle ______________________ Supervisor Name



Physician Instructions: Your assistance is needed to determine if the above named individual can
safely perform the essential functions of his or her job. Please complete the section below and select
the appropriate recommendation. Thank you for your help and cooperation.
  

Physician Name
Address
State/Zip Code
Telephone Number


The employee whose name appears above is under my care. I have prescribed medication (s) for
this employee. I

     The medication(s) I have prescribed will not affect the safe performance of those job duties.

     The medication(s) I have prescribed will affect the safe performance of those job duties. The
     employee is unable to return to work at this time. Next medical evaluation is

     The medication(s) I have prescribed will affect the safe performance of those job duties;
     therefore, I am recommending the following activity restriction(s):




Expected duration of activity restrictions:

Physician
Signature_______________________________________Date__________________

Please do not reve

community.
 
LOCK-OUT/TAG-OUT PROGRAM

Program: Control of Hazardous Energy – Lock-out/tag-out

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707




PURPOSE

Requirements for the use of lock-out / tag-out techniques to protect personnel exposed to
potentially hazardous energy sources during inspection, service or maintenance of vehicles,
heavy equipment, machines or equipment (collectively referred to as equipment in this
document).


EXCLUSIONS
This standard does not apply to work on cord and plug connected electrical equipment where
exposure to the hazard is controlled by removing the plug that then remains under exclusive
control of the employee performing the service or maintenance.


REQUIREMENTS
1. Identify and prepare a list of vehicles, equipment and machine types requiring lock-out/tag-
   out.
2. Identify affected employees (those who operate or work near equipment where LO/TO may
   be used) and authorized employees (those who install LO/TO devices).
3. Ensure new or modified equipment is capable of being locked out.
4. Provide lockout devices, including uniquely keyed locks used only for lockout purposes.
   Locks must be unique in size, shape or color. Provide tag-out devices if used.
5. Develop operational and/or equipment specific energy control procedures for the equipment
   and operations, listed in the proceeding. Prepare a procedure for each group of similar
   equipment where practical (same energy sources and same energy controls).
6. Require supervisors to observe, on an annual basis, lock-out/tag-out performed by every
   authorized employee and certify their competence. Document the observation results. The
   observation record must include the machines or equipment, the names of the employees, the
   date of the observation and certification by the observer.
7. Notify contractors of the lock-out/tag-out program, making them aware of the district
   requirements. Ensure contractors notify the district of the contractor’s lock-out/tag-out
   procedures.




LOCK-OUT/TAG-OUT                                                                        Page 1
©2011, Waste Management                                                           January 2011
LOCK-OUT/TAG-OUT PROGRAM

8. Review the program annually, including review of procedures and implementation.
9. Train authorized employees to properly lock-out/tag-out the specific equipment they service
    or maintain.
10. OSHA also specifies the training of “other” employees – simply, those who may walk
    through or visit an area where lock-out/tag-out is ongoing, but employees who do not fall
    under the “affected” category.
11. Provide training for supervisors and employees responsible for developing equipment-
    specific procedures.
12. Retrain employees when there are changes affecting lock-out/tag-out, or changes in job
    assignments, equipment, operations, or procedures.
13. Document training using the Safety Training Attendance Form.

INTRODUCTION

Lockout and tag-out are safety procedures to protect employees from hazardous energy during
inspecting, maintenance, servicing, and troubleshooting of equipment, machinery, vehicles and
heavy equipment.

The lock-out/tag-out program contains the following elements:

   Core program. Provides the standard method for complying with the company and regulatory
   requirements.
   Facility-specific information. Identifies information such as responsibilities, site-specific
   equipment, and location of procedures, training details, etc.

CORE PROGRAM
This program covers how to shut down equipment, isolate energy sources, apply and remove
locks and tags, and verify that stored hazardous energy is not present.

The types of energy release that could cause injury when released include:

   Air pressure                 Mechanical
   Chemical reaction            Flammability
   Hydraulic pressure           Gravity
   Electrical

Equipment can have more than a single energy source. For example, an air compressor could
have main power, control power, and stored air pressure. That is why this standard requires a
written equipment-specific procedure for equipment.

Certain types of equipment do not require equipment-specific procedures




LOCK-OUT/TAG-OUT                                                                       Page 2
©2011, Waste Management                                                          January 2011
LOCK-OUT/TAG-OUT PROGRAM

The basic protective mechanism is to shut down the equipment, set all controls in the “off”
position and lock each control. Each employee has his or her own unique key(s) and lock(s) that
must be applied to each control. Authorized employees may use a tag to warn others not to start
equipment only when controls cannot be locked. In this case, the employer has the responsibility
to secure the equipment to protect it from being accidentally energized. (For example, placing a
responsible person at the switch for the entire maintenance activity to ensure no one touches the
switch.)

Responsibility
Program Administrator:

    Ensures operational or equipment-specific energy control procedures are prepared and
    revised, as needed.
    Makes sure workers follow established lock-out/tag-out practices.
    Ensures that employees receive appropriate training.
    Performs an annual review of program effectiveness.

Authorized employees are those who directly participate in the use of lock-out/tag-out
procedures. Authorized employees:

    Are responsible for following the lock-out/tag-out procedures described in this program and
    equipment-specific energy control procedures.
    Authorized employees must place and remove their own locks. No one is allowed to place or
    remove someone else's lock.
    Are issued individual locks, tags, and lockout devices.
    Receive training in the general requirements of the program, as well as, the established
    equipment-specific procedures.

Affected employees are those who operate or use machines or equipment subject to lockout/tag-
out procedures, or those who work in an area where servicing or maintenance is being performed
under lockout/tag-out. Affected employees are responsible for staying away from equipment that
has been locked out.


Provide Uniquely Keyed Locks for Each Authorized Employee

All authorized employees are issued their own individually keyed lock(s) to lock out equipment.
When locking out equipment is not possible, employees will use a tag to warn others not to start
equipment.




LOCK-OUT/TAG-OUT                                                                         Page 3
©2011, Waste Management                                                            January 2011
LOCK-OUT/TAG-OUT PROGRAM



Prepare Equipment-Specific Procedures

Develop and provide written operational or equipment-specific procedural steps for shutting
down, isolating, blocking, and securing a machine or piece of equipment that ensures the control
of all sources of hazardous energy. District must:

   Develop written equipment-specific procedures.
   Ensure employee usage through periodic reviews.
   Written equipment-specific procedures are not required when all of the following exist:
          The machine or equipment has no potential for stored or residual or accumulation of
          energy after shutdown.
          The machine or equipment has a single energy source that can be readily identified
          and isolated.
          The isolation and locking out completely de-energizes and deactivates the machine or
          equipment.
          The machine or equipment is isolated from the energy source and locked out during
          service or maintenance.
          A single lockout device achieves a locked-out condition.
          The authorized employee has exclusive control of the lockout device.
          The servicing or maintenance does not create hazards for other employees.
          There have not been any accidents involving the unexpected activation or energizing
          of the piece of equipment or machine during service or maintenance.

If all of the above conditions exist, lock-out/tag-out must still be used, except written equipment-
specific procedures are not required.


When to Use Lockout and Tag-out

Use lockout whenever you inspect, repair or maintain equipment, machinery, vehicles, heavy
equipment that could cause injury by an unexpected start-up of the equipment or release of
stored energy. For example:

   During pre/post trip inspection
   When removing guards or other safety devices.
   When moving machinery could come in contact with employees.
   When repairing electrical circuits.
   When clearing jammed mechanisms.
   When cleaning or oiling machinery with moving parts where an employee may get caught
   within the equipment.




LOCK-OUT/TAG-OUT                                                                           Page 4
©2011, Waste Management                                                              January 2011
LOCK-OUT/TAG-OUT PROGRAM



Shutdown Preparation

Authorized employees will:

   Identify all sources of energy supplying the system, the types of hazards they present, how to
   control them, and how to verify the hazardous energy is not present.
   Notify all affected employees about the lockout.


Shut down Equipment

Authorized employees will:

   Check with the supervisor if unfamiliar with the operation and shutdown of the equipment.
   Shut down operating equipment using the normal means.
   Follow the correct equipment-specific energy control procedure for each piece of equipment.


Isolate the Equipment

Authorized employees will:

   Isolate the equipment from its energy sources by using the switch, valve, or other energy-
   isolating device.
   Isolate all energy sources, including secondary sources.


Apply Lock-out/tag-out Devices

Authorized employees will:

   Place a lock on each energy-isolating device (authorized employees may need more than one
   lock to do this).
   If the authorized employee is not identified by other means, use an identifying approved tag
   with the following information:
   a) Name of authorized employee.
   b) The date.
   c) A warning of the hazardous condition.

Ensure each worker in the crew attaches his or her personal lock if more than one person is
servicing the equipment.

Remember that the individual assigned to a lock has the only key. Workers must have their locks
and keys available at the work site.

LOCK-OUT/TAG-OUT                                                                        Page 5
©2011, Waste Management                                                           January 2011
LOCK-OUT/TAG-OUT PROGRAM


Control Stored Energy

Release or restrain any stored energy by methods such as blocking, bleeding down, and
discharging energy stored in capacitors or other effective methods. If necessary, make equipment
safe by disconnecting wiring, removing fuses, uncoupling drive shafts, removing belts, or by
using other means. Use danger tags in these cases.


Verify Isolation of Equipment

Authorized employees will:

   Make sure no one is exposed to any areas of danger.
   Verify using appropriate test equipment, or other means, that all the energy sources are
   controlled, dissipated, and disconnected, including the main disconnect switch or circuit
   breaker.
   Operate the start buttons and other equipment controls to make certain the equipment will not
   operate.
   Return all operating controls to their “off” or safe position after the test is completed.


Do the Work Safely

Each authorized employee will:
   Not do anything that could restart the equipment.
   Not bypass the lockout, for example, by putting in new wiring or piping.


Shift or Personnel Change

Each authorized employee will ensure:

   Locks and tags remain in place until the job is completed.
   At shift or personnel change, an incoming authorized employee attaches their lock or tag as
   the outgoing employee removes theirs. OR
   An OUT OF SERVICE shop Lock is used during periods of incomplete work or shift change.


Properly Remove Locks and Tags Following Maintenance Work

Each authorized employee will:

   Inspect the work area and clean up all rags, tools, and materials.
   Replace guards on machines and equipment.
   Conduct a head count and make sure all employees are in a safe position.

LOCK-OUT/TAG-OUT                                                                       Page 6
©2011, Waste Management                                                          January 2011
LOCK-OUT/TAG-OUT PROGRAM


   Notify affected employees that the lock-out or tag-out device is being removed.
   Remove only their own locks or tags. This is the key OSHA required step for preventing
   injuries.


Temporary Removal

Workers must follow all of the above procedures before temporarily removing locks and tags to
test equipment.


Emergency Removal

Only a supervisor, in the presence of another employee, can CUT another person's lock(s) and
tags. This activity is permitted only under the following conditions: see page 20 of this
program.


Notify Contractors

Give contractors a copy of this program and hold them responsible for following an equivalent
program of their own. Ensure that a contractor's employees will not bypass the protective devices
and endanger workers at the facility.


Group Lock-out/tag-out Procedures

If group lockout/tag-out procedures will be used, each authorized employee must place their own
lock and completed tag to each multiple lock hasp device used.


Exclusions from Lockout or Tag-out Permitted by OSHA

OSHA permits the exclusion of the following operations from lockout/tag-out procedures:

   Normal production operations including repetitive minor adjustments and maintenance
   covered under OSHA’s machine guarding standards.
   Work on electrical equipment containing a cord and plug as its only energy source, when it is
   unplugged and being serviced or maintained and the worker has exclusive control over the
   plug.




LOCK-OUT/TAG-OUT                                                                        Page 7
©2011, Waste Management                                                           January 2011
LOCK-OUT/TAG-OUT PROGRAM



Train Employees

Each authorized employee receives instruction in the following:
   Recognition of hazardous energy source type and magnitude.
   Methods and means for energy isolation and control.
   The purpose, procedures, and use of the energy control procedure.
   Instruction on the prohibition relating to attempts to start or energize locked or tagged out
   equipment.
   The limitations of tags.
   Methods and means for verifying no hazardous energy are present.

Each affected employee receives instruction in the purpose and use of the energy control
procedure, the prohibition of removing locks or tags or attempts to restart equipment that has
been locked out or tagged.

Authorized and affected employees are retrained whenever:

   There is a change in job assignment; or
   There is a change in equipment, machinery, or a process that could present new hazards.
   There are reasons to believe there are inadequacies in an employee’s knowledge or use of the
   energy control procedures.

Supervisors of authorized employees will be trained to the level of an authorized employee, as
well as trained in supervisor responsibilities for lock-out/tag-out compliance.


Conduct Periodic Inspections

The Program Administrator and/or Supervisor conducts periodic inspections to determine if the
authorized personnel are performing adequately. The inspection consists of:

   A review of work practices, the machines that were locked out/tagged out, names of the
   employees and dates observed.
   Deviations from procedures.
   Corrective actions taken.
   A review with each affected employee on the use and limitations of tags.
   Documentation of inspection.

Specific Information
Prepared by: Justin Lottig    Date: January 2011


Approved by: Joe Whelan       Date:                         January                          2011

LOCK-OUT/TAG-OUT                                                                         Page 8
©2011, Waste Management                                                         January 2011
LOCK-OUT/TAG-OUT PROGRAM



Responsibility


Name: Joe Whelan       Title: Site Manager



LOCK-OUT/TAG-OUT PROCEDURES AT FACILITY

Identify the equipment-specific lock-out/tag-out procedures at the facility:

See attached protocols…..


Requirements for Locks and Tags

Describe the method used to identify locks and tags used exclusively for the lock-out/tag-out
program:

Standardized lockout/tag-out devices will be used so that all employees will be able to recognize
a locked out piece of equipment. Individual tags which identify the person(s) servicing the
equipment will be used. Each person is assigned his or her own lock and it is labeled.

Describe how the identity of the employee applying the lock or tag is indicated on the lock or
tag:

The person’s name is on the tag.


Removing Locks

Identify the name(s) and title(s) of person(s) authorized to remove the locks of other employees:

Name: NONE




LOCK-OUT/TAG-OUT                                                                         Page 9
©2011, Waste Management                                                            January 2011
LOCK-OUT/TAG-OUT PROGRAM


Annual Certification

Describe the frequency and techniques to be used for the annual certification.

Annually, the Program Administrator will review the lock-out/tag-out program, procedures and
best management practices.


Training

Describe the materials used and topics covered for training authorized employees:

Attach the training material to the Safety Attendance Form


Describe the materials used and topics covered for training affected employees:

Attach the training material to the Safety Attendance Form


Describe the materials used and topics covered for training other employees:

Attach the training materials to the Safety Attendance Form

Identify location of training records WGSL Office

DEFINITIONS
Affected Employee: An employee whose job requires them to operate or use machinery,
vehicles, or heavy equipment; on which servicing or maintenance is being performed under
lockout or tag-out; or whose job requires him/her to work in an area in which such servicing or
maintenance is being performed.

Authorized Employee: A person who locks out or tags out machines, vehicles, or heavy
equipment; in order to perform servicing or maintenance on that machine or equipment.

Bleeding: To slowly empty a liquid or gas from a container or system.

Blocking/Bracing: to fasten, secure, support, or provide with a block

Energized: Connected to an energy source or containing residual or stored energy.

Chock: The use of a blocking device to prevent vehicles and equipment from moving.

Double Chocking: Any combination of – One front wheel and one set of duals, both front
wheels, or both sides of rear duals
LOCK-OUT/TAG-OUT                                                                         Page 10
©2011, Waste Management                                                             January 2011
LOCK-OUT/TAG-OUT PROGRAM

Energy Isolating Device: A mechanical device that physically prevents the transmission or
release of energy such as a manually operated circuit breaker and a disconnect switch. Push
buttons and selector switches are not energy isolating devices.

Energy Source: Any source of electrical, mechanical, hydraulic, pneumatic, chemical, thermal,
or other energy.

Isolate: To set apart from its energy sources.

Lockout: The placement of a lockout device on an energy-isolating device, in accordance with
an established procedure, ensuring that the energy isolating device and the equipment being
controlled cannot be operated until the lockout device is removed.

Lockout Device: A device that utilizes a positive means such as a lock, to hold an energy-
isolating device in the safe position and prevent the energizing of a machine or equipment.
Included are blank flanges and bolted slip blinds.

Other Employees: Those employees who may walk through or visit an area where lockout/tag-
out is ongoing, but who do not fall under the “affected” category.

Tag-out: The placement of a tag-out device on an energy-isolating device, in accordance with an
established procedure, ensuring that the energy isolating device and the equipment being
controlled cannot be operated until the tag-out device is removed.

Tag-out Device: A prominent warning device, such as a tag, which can be securely fastened to
an energy-isolating device.


BELOW ARE SOME GENERAL LO/TO PROCEDURES, YOU ARE RESPONSIBLE
FOR REVIEWING THE EQUIPMENT SPECIFIC PROCEDURES FOR EACH PIECE
OF EQUIPMENT YOU WORK ON OR OPERATE:

1. Set the parking brake.
2. Release stored energy.
3. Shut the engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Use any necessary stands for trucks with bodies or rails in the air:
       The stands on the front load trucks with tilt bodies are only approved if there is no load in
       the body. If there is a load, use additional stands.
       The stands for the rails on the roll-off trucks are only approved if there is no box on the
       truck. If there is a box on the truck use additional stands.
8. Cab-over -- secure cabs forward, if necessary.


LOCK-OUT/TAG-OUT                                                                          Page 11
©2011, Waste Management                                                              January 2011
LOCK-OUT/TAG-OUT PROGRAM

TIRE REPLACEMENT
1. Set the parking brake.
2. Release stored energy.
3. Shut off the engine and remove ignition key.
4. Place steering wheel cover over steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Use properly rated jack to lift the unit.
8. Use properly rated jack stand(s) to support the unit in the raised position.

ELECTRICAL SYSTEM REPAIRS
1. Turn engine “off” (Exception: Engine may need to be running to check alternator or other
   dependent system). Place key in pocket.
2. Place steering wheel cover on steering wheel.
3. Double chock the wheels.

PERFORM WORK IN THE BODY OF THE TRUCK
1. Set parking brake.
2. Release stored energy.
3. Shut the engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Use any necessary stands or sleeves for trucks with bodies or rails in the air:
       The stands on the front load trucks with tilt bodies are only approved if there is no load in
       the body. If there is a load, use additional stands.
       The stands for the rails on the roll-off trucks are only approved if there is no box on the
       truck. If there is a box on the truck, use additional stands.
8. Be certain that there is no force being exerted by trash on the packer blades.
9. If entering through an open tailgate or hopper, be certain they are properly braced with stands.

WORK DONE UNDERNEATH THE TRUCK
1. Set the parking brake.
2. Release stored energy.
3. Place steering wheel cover over steering wheel.
4. Turn battery disconnect off and lock/tag-out the disconnect.
5. Double chock/block the wheels.
6. Use any necessary stands for trucks with bodies or rails in the air:
       The stands on the front load trucks with tilt bodies are only approved if there is no load in
       the body. If there is a load, use additional stands.
       The stands for the rails on the roll-off trucks are only approved if there is no box on the
       truck. If there is a box on the truck, use additional stands.
       Use hydraulic jacks which may be pinned (to prevent accidents caused by leaking
       hydraulic jacks) or jack stands, if the truck is going to be off of the ground.


LOCK-OUT/TAG-OUT                                                                               Page 12
©2011, Waste Management                                                                   January 2011
LOCK-OUT/TAG-OUT PROGRAM


WORK DONE UNDERNEATH THE TAILGATE OR HOPPER
1. Set the parking brake.
2. Release stored energy.
3. Shut engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Double chock/block the wheels.
6. Use any necessary stands or sleeves for trucks with bodies or rails in the air:
   The stands on the front load trucks with tilt bodies are only approved if there is no load in the
   body. If there is a load, use additional stands.
   The stands for the rails on the roll-off trucks are only approved if there is no box on the truck.
   If there is a box on the truck, use additional stands.
   Be certain that tailgate or hopper is properly braced with stands.


WORKING ON TRUCK WITH CAB IN RAISED POSITION
1. Set the parking brake.
2. Release stored energy.
3. Shut of the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag out the disconnect.
6. Double chock/block the wheels.
7. Use hydraulic jacks which may be pinned (to prevent accidents caused by leaking hydraulic
   jacks) or jack stands if the truck is going to be off of the ground.


WORKING ON AIR COMPRESSORS
1. Turn “off” air compressor at the circuit breaker or remove plug.
2. Install a circuit breaker lockout or plug lockout device and lock/tag-out.
3. If servicing just the compressor, turn airline valve “off” and place valve lockout device and
   lock/tag-out valve.
4. Drain system (lines and tank) of any pressurized air.
5. Test the equipment to be certain there is no electricity present before working on it. Try the
   switch to be certain that it will not turn on.

PERFORMING MAINTENANCE, REPAIR, SERVICE OR INSPECTING OF D-8
DOZER
1. Set the parking brake.
2. Lower blade to floor.
3. Neutralize all hydraulics.
4. Shut off the engine and remove the ignition key.
5. Turn battery disconnect off and lock/tag out the disconnect.
6. Place warning tag on equipment.
7. Block the tracks.

LOCK-OUT/TAG-OUT                                                                          Page 13
©2011, Waste Management                                                              January 2011
LOCK-OUT/TAG-OUT PROGRAM


MECHANICS
Remember that each person working on a piece of equipment must have their own individual
lock that no one else can open, on that piece of equipment. Use a multiple lock hasp if more than
one person works on the vehicle.

WHEN ANY PART OF A DRIVER'S BODY IS GOING TO BE UNDERNEATH THE
RAISED RAILS ON A ROLL-OFF TRUCK

1.   Set the parking brake.
2.   Release stored energy.
3.   Turn the engine off and remove ignition key.
4.   Place steering wheel cover on steering wheel.
5.   Turn battery disconnect off and lock/tag-out the disconnect.
6.   Chock/block the wheels.
7.   Use the body stands attached to the body:
     The stands for the rails on the roll-off trucks are only approved if there is no box on the truck.
     If there is a box on the truck use additional stands.

SWITCHING OUT A COMPACTOR BOX
1. Disconnect and lockout and tag-out the power to the compactor before the ratchets are
   loosened. (Turn power off, Disconnect hydraulic hoses or loosen turn buckles)
2. Leave the compactors power supply Locked out and tagged out until the box is returned and
   secured. Turn power back on.

DISLODGING CARDBOARD OR OTHER DEBRIS FROM ROLL-OFF BOX WHILE
THE BOX IS ATTACHED TO THE VEHICLE IN ANY WAY
1. Set the parking brake.
2. Release stored energy.
3. Turn off the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock / tag out the disconnect.
6. Chock/block wheels.

CRAWLING UNDERNEATH A TRUCK FOR ANY REASON

1.   Set the parking brake.
2.   Release stored energy.
3.   Turn off the engine and remove the ignition key.
4.   Place steering wheel cover on steering wheel.
5.   Turn battery disconnect off and lock/tag-out the disconnect.
6.   Chock/block the wheels.




LOCK-OUT/TAG-OUT                                                                            Page 14
©2011, Waste Management                                                                January 2011
LOCK-OUT/TAG-OUT PROGRAM


CLEANING OUT FROM BEHIND THE PUSH BLADE
1. Set the parking brake.
2. Bring blade forward (towards cab) to relieve any pressure caused by compacted waste.
3. Turn the engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Chock/block the wheels.

CLEANING OUT THE TOP OF THE HOPPER

1.   Set the parking brake.
2.   Released stored energy.
3.   Turn the engine off and remove ignition key.
4.   Turn battery disconnect off and lock/tag-out the disconnect.
5.   Chock/block the wheels.
6.   Be certain that the blade is completely in the down position so that there is no stored energy
     in the blade should a hydraulic hose break.


ALL DRIVERS: PARK OVER LEVEL SURFACE - PULL PARKING BRAKE WHEN
PARKING ON A GRADE, CHOCK WHEELS

SWEEPING OUT TRAILERS AT THE LANDFILL

1.   Set the parking brake.
2.   Turn the engine off and remove ignition key.
3.   Place steering wheel cover on steering wheel.
4.   Turn battery disconnect off and lock/tag-out the disconnect.
5.   Chock/block wheels.

CRAWLING UNDERNEATH DETACHED TRAILERS OR UNLOADING TRAILERS
1. Chock at least 2 wheels
2. Place kingpin jack under trailer (do not rely on dolly legs to support trailer).


CRAWLING UNDERNEATH A TRUCK FOR ANY REASON

1.   Set the parking brake.
2.   Release stored energy.
3.   Turn off the engine and remove the ignition key.
4.   Place steering wheel cover on steering wheel.
5.   Turn battery disconnect off and lock/tag-out the disconnect.
6.   Chock/block the wheels.


LOCK-OUT/TAG-OUT                                                                         Page 15
©2011, Waste Management                                                             January 2011
LOCK-OUT/TAG-OUT PROGRAM

ALL OPERATORS: PARK VEHICLE ON LEVEL SURFACE

ANY WORK BEING DONE ON OR AROUND ONE OF THESE VEHICLES WHEN THE
FORKS OR BUCKET IS IN THE AIR

1.   Set the parking brake.
2.   Turn the engine off and remove ignition key.
3.   Turn battery disconnect off and lock/tag-out the disconnect.
4.   Put stands underneath the bucket or forks to prevent it from falling to the ground should a
     hydraulic hose break.

CRAWLING UNDERNEATH EQUIPMENT FOR ANY REASON

1.   Set the parking brake.
2.   Release stored energy.
3.   Turn off the engine and remove the ignition key.
4.   Place steering wheel cover on steering wheel.
5.   Turn battery disconnect off and lock/tag-out the disconnect.
6.   Chock/block the wheels.

WHEN BALER IS NOT IN USE

1. Lockout and tag-out the power supply in the electrical breaker room.
2. Try the on/off switch on the baler to be certain that the power is off.
3. Remove the key from the baler - put key in pocket.


WHEN BALER BECOMES JAMMED AND YOU MUST ENTER BALER
1. Lockout and tag-out the power supply in the electrical breaker room.
2. Try the on/off switch on the baler to be certain that the power is off.
3. Remove the key from the baler - put key in pocket.

WHEN NORMAL MAINTENANCE MUST BE PERFORMED ON BALER
1. Lockout and tag-out the power supply in the electrical breaker room.
2. Try the on/off switch on the baler to be certain that the power is off.
3. Remove the key from the baler - put key in pocket.




LOCK-OUT/TAG-OUT                                                                      Page 16
©2011, Waste Management                                                          January 2011
LOCK-OUT/TAG-OUT PROGRAM

AUTHORIZED EMPLOYEES INDEPENDENT AND GROUP LOCK-OUT/TAG-OUT

1.    Name:
      Title:
      Area:

2.    Name:
      Title:
      Area:

3.    Name:
      Title:
      Area:

4.    Name:
      Title:
      Area:

5.    Name:
      Title:
      Area:

6.    Name:
      Title:
      Area:

7.    Name:
      Title:
      Area:

8.    Name:
      Title:
      Area:

9.    Name:
      Title:
      Area:

10.   Name:
      Title:
      Area:

11.   Name:
      Title:
      Area:

LOCK-OUT/TAG-OUT                                        Page 17
©2011, Waste Management                            January 2011
LOCK-OUT/TAG-OUT PROGRAM

12.   Name:
      Title:
      Area:

13.   Name:
      Title:
      Area:
14.   Name:
      Title:
      Area:

15.   Name:
      Title:
      Area:

16.   Name:
      Title:
      Area:

17.   Name:
      Title:
      Area:

18.   Name:
      Title:
      Area:

19.   Name:
      Title:
      Area:

20.   Name:
      Title:
      Area:

21.   Name:
      Title:
      Area:

22.   Name:
      Title:
      Area:

23.   Name:
      Title:

LOCK-OUT/TAG-OUT                              Page 18
©2011, Waste Management                  January 2011
LOCK-OUT/TAG-OUT PROGRAM
     Area:




LOCK-OUT/TAG-OUT                              Page 19
©2011, Waste Management                  January 2011
ANNUAL OBSERVATION FORM

   ANNUAL ENERGY CONTROL (LOCK-OUT/TAG-OUT) PROCEDURE
   REVIEW/OBSERVATION


   Date of review/observation: _____________________________________________________________


   Employee implementing energy control procedure: ___________________________________________


   Responsibilities under energy control procedure reviewed: _____________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________


   Machine/equipment on which energy control was being utilized: _________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________


   Recommended follow-up: _______________________________________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________

   ____________________________________________________________________________________


   ANY DEFICIENCIES NOTED - REQUIRE IMMEDIATE RETRAINING




   I certify that this inspection was performed as described above.




_______________________________________                      __________________________________
Printed Name                                                 Signature



_______________________________
 Date

LOCK-OUT/TAG-OUT                                                                               Page 20
©2011, Waste Management                                                                   January 2011
EMERGENCY REMOVAL OF LOCKS/TAGS


EMERGENCY REMOVAL OF LOCKS/TAGS

There are occasions that require a lock/tag to be removed from equipment in the absence of the
employee that placed that particular lock/tag. The emergency lock/tag removal procedure will be
performed by a Manager/Supervisor for the following reasons:

   1. Employee calls in sick.

   2. The equipment needs to be repaired immediately.

   3. Employee sustains an injury and can’t come to work.

   4. Suspension/termination from work.

   5. Employee is disqualified from his present duties.

   6. For any other reason that the Manager/Supervisor deems necessary.

In order for a lock/tag to be removed from an equipment when the employee that placed it is not
present, the following criteria MUST be fully met:

   1. Only a Manager or a Supervisor with the consent of his Manager may remove the
      lock/tag.

   2. The employee that placed the lock/tag MUST be notified of this action prior to the
      removal if possible; otherwise an attempt has to be made to contact the employee in the
      presence of a witness and documented.

   3. A duplicate key or a master key may not be used.

   4. A lock maybe removed only by cutting it. A new lock(s) SHALL be issued when the
      affected employee returns to duty.

The procedures stated above will ensure that the Waste Management employees are fully
protected from accidental start up while performing maintenance duties.




LOCK-OUT/TAG-OUT                                                                      Page 21
©2011, Waste Management                                                          January 2011
EMERGENCY REMOVAL FORM



EMERGENCY REMOVAL FORM
In the case where it is necessary to remove an employee’s lock-out/tag-out devise from a piece of equipment
or machinery, the following procedure MUST be followed.

Only a supervisor, in the presence of another employee, can remove another person's locks and tags. This activity is
permitted only under the following conditions:

    d) Supervisor must verify the employee who put the lock or tag on the equipment is not at the facility.
    e) The supervisor must inform the employee or make 2-3 attempts by phone that their lock is going to be
         removed before the employee resumes work at the facility.
    f) The supervisor must prepare a report explaining why the protective device was removed, when and where it
         occurred, and how the affected employee was informed prior to starting work.
    The lock must be removed by way of cutting. At no time is a spare key allowed by any other person other than
    the person assigned the lock.
    The cut lock is to be placed into a baggy or envelope including documentation of emergency removal attempt
    and procedures.
    The employee must receive a new lock and key upon returning to work.

EMPLOYEE CONTACT—1st ATTEMPT
______________________________________                ________________________________________________
Time & Date                                           Phone # Called



______________________________________                ________________________________________________
Signature of manager/supervisor                       Witness signature

EMPLOYEE CONTACT—2nd ATTEMPT



______________________________________                ________________________________________________
Time & Date                                           Phone # Called


______________________________________                ________________________________________________
Signature of manager/supervisor                       Witness signature


CUTTING LOCK


______________________________________                _________________________________________________
Date Removed                                          Time Removed


______________________________________                _________________________________________________
Signature of manager/supervisor cutting lock          Witness signature


_______________________________________               _________________________________________________
District/Facility Manager Signature                   Date

LOCK-OUT/TAG-OUT                                                                                        Page 22
©2011, Waste Management                                                                            January 2011
TABLE OF CONTENTS


LOCK-OUT/TAG-OUT PROTOCOLS                                ATTACHMENT       DEPARTMENT
Pre/Post Trip Inspection (Commercial Vehicles)                  1            Operation
Working on Truck with Cab in the Raised Position               2            Maintenance
Working on Rear of a Rear Loader with the Tailgate in the      3            Maintenance
Raised Position
Working Under the Raised Tilt Frame of a Roll-Off Truck        4             Maintenance
or Trailer
Tire Replacement                                                5            Maintenance
Changing Hydraulic or Air Lines                                6             Maintenance
Working Inside the Body of a Rear Loader                        7            Maintenance
Performing Various Functions Working Under the                 8             Maintenance
Vehicle
Maintenance, Repairs, or Servicing Recycle Trucks with         9              Operation
Bins or Tailgate in the Raised Position
Performing Maintenance, Repairs, or Servicing of Trailers      10            Maintenance
(Disconnected From Tractor)
Performing Maintenance, Repairs, or Servicing of               11            Maintenance
Heavy Equipment with Hydraulic Attachments in the
Raised Position

Performing Maintenance, Repairs, or Servicing on 910,      12                Maintenance
936,966, 980, 988 or any other Loaders with the Bucket
in the Lowered Position
Performing Maintenance, Repairs, or Servicing on 910,      13                Maintenance
936, 966, 980, 988 or any other Loaders with the Bucket
in the Raised Position
Performing Maintenance, Repairs, or Servicing of D-8       14                Maintenance
Dozer
Performing Maintenance, Repairs, or Servicing of D-8       15                Maintenance
Dozer with Blade in the Raised Position
Performing Maintenance, Repairs, or Servicing of 245       16                Maintenance
Excavator
Performing Maintenance, Repairs, or Servicing of           17                Maintenance
Heavy Equipment with Hydraulic Attachments in
the Lowered Position
Performing Maintenance, Repairs, or Servicing of           18                Maintenance
HI/LO Forklift with Forks in the Lowered Position
Performing Maintenance, Repairs, or Servicing of           19                Maintenance
HI/LO Forklift with Forks in the Raised Position
Performing Maintenance, Repairs, or Servicing of Street    20                Maintenance
Sweeper
Performing Maintenance, Repairs, or Servicing              21                Maintenance
of Street Sweeper with the Hopper in the Raised (Dump)
Position

LOCK-OUT/TAG-OUT                                                              Page 23
©2011, Waste Management                                                  January 2011
TABLE OF CONTENTS
Performing Maintenance, Repairs, or Servicing Man Lifts   22         Maintenance
Performing Maintenance, Repairs, or Servicing on          23         Maintenance
Dump Body Trailers with the Box in the Lowered
Position
Performing Maintenance, Repairs, or Servicing on          24         Maintenance
Dump Body Trailers with the Box in the Raised
(Dump) Position (EMPTY ONLY)
Performing Maintenance, Repairs, or Servicing of          25         Maintenance
Wood Grinder
Cleaning out Behind the Blade On All Trucks               26          Operation
Cleaning Tailgate Seal                                    27          Operation
Cleaning Out Compactor Machine                            28          Operation
Crawling Under Detached Trailers or Unloading             29          Operation
Trailer
Roll Off/Drop Box Removing Debris from Box                30          Operation
Portable Heater                                           31         Maintenance
Performing Maintenance, Repairs, Servicing or             32         Maintenance
Cleaning of Fans
Performing Maintenance or Repairs on Building             33         Maintenance
Electrical Circuits
Ladders                                                   34         Maintenance
High PressureToilet                                       35         Maintenance
Residential One Pass Truck Mechanics                      36         Maintenance
Performing Repairs, Servicing or Cleaning of Impact       37         Maintenance
Crusher
Unjamming Conveyor Belt or Performing Maintenance,        38         Maintenance
Repair, Servicing, or Cleaning Conveyor
Pressure Washer                                           39         Maintenance
Residential One Pass Truck When Any Parts of              40          Operation
the Drivers’ Body is Going to be Underneath the
Raised Tailgate and/or Dislodging Jammed Recyclables
Residential One Pass Truck Cleaning Out the Traps on      41          Operation
Route or at Disposal
Roll Up Bay Doors                                         42         Maintenance
Performing Maintenance, Repairs, or Cleaning of           43         Maintenance
Electrical Powered Equipment
Air Compressor / Air Lines                                44         Maintenance
Baler                                                     45         Maintenance
Chop Saw                                                  46         Maintenance
Crimp Machine                                             47         Maintenance
Drill Press                                               48         Maintenance
Drop Lights                                               49         Maintenance
Filter Buggy                                              50         Maintenance
Floor Buffer                                              51         Maintenance
Floor Scrubber                                            52         Maintenance
Floor Sweeper                                             53         Maintenance
LOCK-OUT/TAG-OUT                                                      Page 24
©2011, Waste Management                                          January 2011
TABLE OF CONTENTS
Floor, Transmission & Rear Jacks                  54          Maintenance
Grinders (Air, Bench, Hand)                       55          Maintenance
Parts Cleaner                                     56          Maintenance
Steam Cleaners                                    57          Maintenance
The Fuel Island                                   58          Maintenance
Tire Brander                                      59          Maintenance
Torches                                           60          Maintenance
Vacuum Cleaner                                    61          Maintenance
Vises                                             62          Maintenance
Welders                                           63          Maintenance
Pickup & Service Trucks                           64          Maintenance
Roll Off / Drop Box Trucks                        65           Operation
Sample Lock-out/tag-out Protocol Template         66        Operation/Maint.
Training Acknowledgement for Affected Employees   67     Program Administrator
Program Review                                    68     Program Administrator




LOCK-OUT/TAG-OUT                                              Page 25
©2011, Waste Management                                  January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                    PROTOCOLS – ATTACHMENT 1

                              Pre/Post Trip Inspection (Commercial Vehicles)

POTENTIAL ENERGY SOURCES:

  air pressure                chemical reaction                   electrical                flammability
  heat                        hydraulic pressure                  mechanical                gravity

LOCKOUT METHOD(S):

  battery disconnect                  circuit lockout             handle/valve lockout
  remove air fitting/nipple           wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag            Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Chock wheels
6. Turn battery disconnect off and lock/tag-out the disconnect.
VERIFY ISOLATION OF EQUIPMENT:

Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________                   Signature: ____________________________________


LOCK-OUT/TAG-OUT                                                                                        Page 26
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 2
                              WORKING ON TRUCK WITH CAB IN THE RAISED POSITION

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout            handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)


SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
   1. Set the parking brake.
   2. Release stored energy.
   3. Shut off the engine and remove ignition key.
   4. Place steering wheel cover on steering wheel.
   5. Turn battery disconnect off and lock/tag-out the disconnect.
   6. Double chock/block the wheels.
   7. Raise the cab to its full-extended position or utilize the safety legs.


VERIFY ISOLATION OF EQUIPMENT:
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:

1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: ____________________          Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 27
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                       PROTOCOLS – ATTACHMENT 3

      WORKING ON REAR OF A REAR LOADER WITH THE TAILGATE IN THE RAISED POSITION

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                               electrical                  flammability
  heat              hydraulic pressure                              mechanical                  gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout              handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks           plug lockout

TAG-OUT METHOD(S):

  Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
  Do Not Operate Tag                   Do Not Close Tag            Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Support tailgate with an appropriately rated chain fall or; install cylinder safety lock (sleeve) or; use tailgate
   stand with adequate base or; use the tailgate props supplied by the manufacturer.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: ___________________            Signature: ________________________________________



LOCK-OUT/TAG-OUT                                                                                            Page 28
©2011, Waste Management                                                                                January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 4
                WORKING UNDER THE RAISED TILT FRAME OF A ROLL OFF TRUCK OR TRAILER.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                   flammability
  heat              hydraulic pressure                           mechanical                   gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout         plug lockout
 remove air fitting/nipple            wheel chock/blocks         lock tilt frame safety leg

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut of the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Lock tilt frame safety leg into place and place a 6” X 6” wood block between the tilt frame and the chassis; or, use the
   safety leg supplied by the manufacturer and de-energize the hydraulic cylinders.


VERIFY ISOLATION OF EQUIPMENT:
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________ Signature: ____________________________________



LOCK-OUT/TAG-OUT                                                                                         Page 29
©2011, Waste Management                                                                             January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                     PROTOCOLS – ATTACHMENT 5

                                              TIRE REPLACEMENT

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Use properly rated jack to lift the unit.
8. Use properly rated jack stand to support the unit in the raised position.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________           Signature: ____________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 30
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 6

                                         CHANGING HYDRAULIC OR AIR LINES

POTENTIAL ENERGY SOURCES:
  pneumatic         chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Lock tilt frame safety leg into place and place a 6” X 6” wood block between the tilt frame and the chassis, or; use the
   safety leg supplied by the manufacturer and de-energize the hydraulic cylinders, or; de-energize the air pressure at its
   source.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: __________________            Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 31
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                    PROTOCOLS – ATTACHMENT 7


                             WORKING INSIDE THE BODY OF A REAR LOADER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off the engine and remove the ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________          Signature: _____________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 32
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 8

                       PERFORMING VARIOUS FUNCTIONS WORKING UNDER THE VEHICLE


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE VEHICLE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________          Signature: ___________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 33
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 9

PERFORMING MAINTENANCE, REPAIRS, OR SERVICING RECYCLE TRUCKS WITH BINS OR TAILGATE IN THE RAISED
                                           POSITION


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                  flammability
  heat              hydraulic pressure                            mechanical                  gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout            handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag            Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut off engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Support bin or tailgate with: a) Appropriately rated chain fall, or; b) Install cylinder safety lock (sleeve), or; c) Use
   tailgate stand with adequate base, or; d) Block with 6 X 6 wood blocks, or; e) Use the safety pins provided by the
   manufacturer.
**UNDER NO CIRCUMSTANCES ARE DRIVERS/HELPERS ALLOWED TO GO UNDER THE SIDE BINS.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE RECYCLE TRUCK BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.

Date: ________________________________________                  Signature: ____________________________________



LOCK-OUT/TAG-OUT                                                                                          Page 34
©2011, Waste Management                                                                              January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 10

                 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF TRAILERS
                                            (Disconnected from Tractor)

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Double chock/block the wheels.
2. Place warning tag on equipment.
3. Support with additional jack stands.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE TRAILERS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________           Signature: ____________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 35
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                     PROTOCOLS – ATTACHMENT 11

  PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF ANY EQUIPMENT WITH HYDRAULIC
                      ATTACHMENTS IN THE RAISED POSITION


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                              electrical                  flammability
  heat              hydraulic pressure                             mechanical                  gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout             handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                      Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                    Do Not Close Tag            Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Shut the engine off and remove ignition key.
4. Place warning tag on equipment.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock or block wheels.
7. Support attachment with; a) appropriately rated chain fall, or; b) install cylinder safety lock (sleeve), or; c)
   safety stands/wood blocks.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE HEAVY EQUIPMENT BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.


Date: ________________________                Signature: _______________________________



LOCK-OUT/TAG-OUT                                                                                            Page 36
©2011, Waste Management                                                                                January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 12

 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING ON 910, 936, 966, 980, 988, OR ANY WHEEL LOADERS WITH
                              THE BUCKET IN THE LOWERED POSITION


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Lower bucket to the floor.
3. Release stored energy.
4. Turn the engine off and remove ignition key.
5. Place steering wheel cover on steering wheel.
6. Turn battery disconnect off and lock/tag-out the disconnect.
7. Double chock or block wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE 910,936,966,980,988 LOADERS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _______________________________________                 Signature: ____________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 37
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 13

 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING ON 910, 936, 966, 980, 988, OR ANY WHEEL
                 LOADERS WITH THE BUCKET IN THE RAISED POSITION

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Raise bucket to the desired position, put stand under bucket and lower bucket to the stand or use overhead crane
   to support the bucket.
3. Install cylinder safety lock (sleeve).
4. If necessary, de-energize all hydraulics.
5. Turn the engine off and remove ignition key.
6. Turn battery disconnect off and lock/tag-out the disconnect.
7. Place steering wheel cover on steering wheel.
8. Double chock or block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE 910,936,966,980,988 LOADERS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.


Date: ________________________               Signature: __________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 38
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 14

                       PERFORMING MAINTENANCE, REPAIR OR SERVICING OF D-8 DOZER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set parking brake.
2. Lower the blade to the floor.
3. Neutralize all hydraulics.
4. Shut off the engine and remove ignition key.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Place warning tag on equipment.
7. Block the tracks.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE D-8 DOZER BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: __________________           Signature: ___________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 39
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 15

  PERFORMING MAINTENANCE, REPAIR OR SERVICING OF D-8 DOZER WITH THE BLADE IN THE RAISED
                                      POSITION.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):

  Do Not Start Tag                   Do Not Energize Tag          Do Not Open Tag
  Do Not Operate Tag                 Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Raise blade to the desired height.
3. Block up the arms with jack stands or with wood blocks.
4. Lower the arms.
5. If necessary, neutralize the hydraulics.
6. Shut the engine off and remove ignition key.
7. Place out of service tag on equipment.
8. Turn battery disconnect off and lock/tag-out the disconnect.
9. Block the tracks.

VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE D-8 DOZER BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
3. Notify affected employees that the lock-out/tag-out is being removed.
4. Remove lockout devices along with their own locks and tags.




Date: ________________________               Signature: _________________________________


LOCK-OUT/TAG-OUT                                                                                        Page 40
©2011, Waste Management                                                                            January 2011
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 16

                    PERFORMING MAINTENANCE, REPAIR OR SERVICING OF 245 EXCAVATOR

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Lower boom to the ground.
3. Put hydraulic control level to the “off” position (down).
4. De-energize all hydraulics
5. Shut the engine off and remove the ignition key.
6. Turn battery disconnect off and lock/tag-out the disconnect.
7. Place warning tag on equipment.
8. Block tracks.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE EXCAVATOR BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
3. Notify affected employees that the lock-out/tag-out is being removed.
4. Remove lockout devices along with their own locks and tags.




Date: _____________________________________                   Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 41
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 17

 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF HEAVY EQUIPMENT WITH HYDRAULIC ATTACHMENTS
                                   IN THE LOWERED POSITION

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Lower boom, or bucket to the ground.
3. De-energize any stored pressure.
4. Shut down the engine and remove keys from the ignition.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Place warning tag on equipment.
7. Double chock/block wheels/tracks.


VERIFY ISOLATION OF EQUIPMENT

    Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE HEAVY EQUIPMENT BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: __________________           Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 42
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 18

                    PERFORMING MAINTENANCE, REPAIR OR SERVICING OF HI/LO FORKLIFT WITH
                                     FORKS IN THE LOWERED POSITION.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Lower forks to the floor.
2. De-energize all hydraulics.
3. Shut down the engine and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.
7. Shut off propane valve at the tank (if equipped).


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE HI/LO FORKLIFT BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________          Signature: ____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 43
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 19

                    PERFORMING MAINTENANCE, REPAIR OR SERVICING OF HI/LO FORKLIFT WITH
                                     FORKS IN THE RAISED POSITION.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                   flammability
  heat              hydraulic pressure                            mechanical                   gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Raise forks to the desired height.
3. Support forks with an appropriately rated chain fall, or appropriately rated jack stands.
4. De-energize the hydraulics.
5. Shut down the engine and remove the ignition key.
6. Place steering wheel cover on steering wheel.
7. Turn battery disconnect off and lock/tag-out the disconnect.
8. Double chock/block the wheels.
9. Shut off propane valve at the tank (if equipped).


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE HI/LO FORKLIFT BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date ______________________         Signature__________________________________

LOCK-OUT/TAG-OUT                                                                                         Page 44
©2005, Waste Management                                                                           January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                      PROTOCOLS – ATTACHMENT 20

                PERFORMING MAINTENANCE, REPAIR OR SERVICING OF STREET SWEEPER.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                              electrical               flammability
  heat              hydraulic pressure                             mechanical               gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout              handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks           plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set parking brake.
3. Release stored energy.
4. Shut down the engine and remove ignition key.
5. Place steering wheel cover on steering wheel.
6. Turn battery disconnect off and lock/tag-out the disconnect.
7. Double chock or block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE STREET SWEEPER IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: __________________            Signature: ___________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 45
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 21

 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF STREET SWEEPER WITH THE HOPPER IN THE
                                RAISED (DUMP) POSITION.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set parking brake.
2. Raise hopper to the dump position.
3. Install safety legs and lower to its resting position.
4. Release stored energy.
5. Turn of the engine and remove ignition key.
6. Place steering wheel cover on steering wheel.
7. Turn battery disconnect off and lock/tag-out the disconnect.
8. Double chock or block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE STREET SWEEPER IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: __________________            Signature: _____________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 46
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 22



                       PERFORMING MAINTENANCE, REPAIR OR SERVICING OF MAN LIFTS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Chock/block/block wheels.
2. Extend boom and lower to the ground.
3. If necessary, release stored energy.
4. Shut down and remove key.
5. Turn battery disconnect off and lock/tag-out the disconnect.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE MAN LIFTS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________          Signature: ___________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 47
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 23

                PERFORMING MAINTENANCE, REPAIR OR SERVICING ON DUMP BODY TRAILERS
                              WITH THE BOX IN THE LOWERED POSITION.
                                                  (Disconnected from Tractor)
POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability

  heat                       hydraulic pressure                  mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag         Steering Wheel Cover (Do Not Operate or Start)


SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Double chock/block wheels.
2. Install safety stand under fifth wheel plate.
3. Place warning tag on equipment.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE DUMP BODY TRAILERS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________          Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 48
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 24

           PERFORMING MAINTENANCE, REPAIR OR SERVICING OF DUMP BODY TRAILERS
                 WITH THE BOX IN THE RAISED (DUMP) POSITION (EMPTY ONLY)
POTENTIAL ENERGY SOURCES:
  air pressure         chemical reaction          electrical         flammability
  heat                 hydraulic pressure         mechanical         gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Raise box to the desired height.
3. Install appropriately rated stands under the body.
4. Lower the body onto the stands.
5. Shut the engine off and remove ignition key.
6. De-energize all hydraulics.
7. Place steering wheel cover on steering wheel of tractor.
8. Turn battery disconnect off and lock/tag-out the disconnect.
9. Double chock/block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE DUMP BODY TRAILERS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Signature: __________________       Date: ________________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 49
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 25
                      PERFORMING MAINTENANCE, REPAIR OR SERVICING OF WOOD GRINDER.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Shut down the unit.
2. Remove key at the control panel.
3. Shut down and lock-out/tag-out the main power disconnect.
4. Shut down and lock-out/tag-out the power disconnect at the unit.
5. Install lock-out/tag-out at the control panel.
6. Block or Brace all prime movers, drums, and gears



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE WOOD GRINDER BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Signature: ___________________ Date: _________________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 50
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 26

                                  CLEANING OUT BEHIND THE BLADE ON ALL TRUCKS

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Extend blade cylinder as far out as possible.
3. Place body on stands (Manual Side Load)
4. Shut down hydraulic pump.
5. Relieve hydraulic pressure from all cylinders.
6. Shut the engine off and remove ignition key.
7. Place steering wheel cover on steering wheel.
8. Chock/block the wheels.
9. Turn battery disconnect off and lock/tag-out the disconnect.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BLADE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _________________            Signature: _____________________________________
LOCK-OUT/TAG-OUT                                                                                       Page 51
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 27
                                               CLEANING TAILGATE SEAL


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)


SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Extend prop rod to support tailgate.
3. Lower tailgate until it is supported only by the prop rod.
4. Shut the engine off and remove ignition key.
5. Place steering wheel cover on steering wheel.
6. Chock/block the wheels
7. Turn battery disconnect off and lock/tag-out the disconnect.
8. Use a shovel, broom or stick to clean.

NEVER GO UNDER A RAISED TAILGATE FOR ANY REASON UNTIL IT IS SUPPORTED.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE: BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.


Date: ____________________         Signature: ________________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 52
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 28
                                        CLEANING OUT COMPACTOR MACHINE


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Retract ram to the home or fully retracted position.
2. Put blade in the forward position.
3. Release stored energy.
4. Shut down compactor and remove key.
5. Lock-out/tag-out all energy sources.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.
4. Turn circuit breaker “on” and/or plug in equipment.




Date: ___________________          Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 53
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 29

                        CRAWLING UNDER DETACHED TRAILERS OR UNLOADING TRAILER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                              electrical               flammability
  heat              hydraulic pressure                             mechanical               gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout             handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Chock/block at least 2 wheels.
2. Place kingpin jack under trailer (do not rely on dolly legs to support trailer).


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Signature: ____________________               Date: ________________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 54
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 30
                                                ROLL OFF /DROP BOX
                                             REMOVING DEBRIS FROM BOX

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Lower box to ground.
2. Set the parking brake.
3. Release stored energy including all tension from cable.
4. Turn the engine off and remove the ignition key.
5. Place steering wheel cover on steering wheel.
6. Turn battery disconnect off and lock/tag-out the battery disconnect.
7. Double chock/block the wheels.

NEVER ENTER ANY BOX WHILE ELEVATED


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE COMPACTOR BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.
4. Turn circuit breaker “on” and/or plug in equipment.



Date: ________________________________________                Signature: _____________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 55
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 31

                                                    PORTABLE HEATER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn “off” the heater and unplug the unit.
2. Place lockout plug device and lockout.
3. Place an “out of service” sign on unit.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
       a. All tools and other materials are removed.
       b. Machine/equipment is fully reassembled.
       c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove the plug lock out device.
4. Remove the “out of service” sign.




Date: ____________________         Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 56
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 32

                      PERFORMING MAINTENANCE, REPAIR, SERVICING, OR CLEANING OF FANS

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                    flammability
  heat              hydraulic pressure                           mechanical                    gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn “off” fan.
2. Turn “off” circuit breaker or unplug and utilize the appropriate lock-out/tag-out device.
3. Test lockout by turning fan “on” and verify that the fan is de-energized.
4. Place an “out of service” tag on the fan.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE THE FAN BACK IN SERVICE:
Inspect the equipment to be sure that:
1. All tools and other materials are removed.
2. Machine/equipment is fully reassembled.
3. Guards and other safety devices are installed.
4. Remove the lockout device and plug in or turn “on” circuit breaker for the fan.
5. Remove the “out of service” tag.




Date: ___________________           Signature: _____________________________________



LOCK-OUT/TAG-OUT                                                                                         Page 57
©2005, Waste Management                                                                           January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 33

                    PERFORMING MAINTENANCE OR REPAIR ON BUILDING ELECTRICAL CIRCUITS

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Shut off electricity at the circuit breaker.
2. Install circuit breaker lockout cleat.
3. Install lockout tag on circuit panel.
4. Test circuit breaker to ensure power is off.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BUILDING ELECTRICAL CIRCUITS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.
4. Turn circuit breaker in the “on” position.




Date: ______________________                Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 58
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                            PROTOCOLS – ATTACHMENT 34

                                                             LADDERS

    Mechanical
    Gravity


LOCKOUT METHOD(S):

    Chain
    Tape


TAG-OUT METHOD(S):

    Out of service tag/sign
    Caution tape

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:

1. Wrap a chain or tape around the ladder in such a way as to render it unusable.
2. Tag “out of service.”
****NOTE:**** If the ladder cannot be placed back in service, destroy it and throw it out.
    g)
    h)

PROCEDURES TO PLACE LADDERS BACK IN SERVICE:

    Inspect the ladder to be sure it’s safe to put back in service.
    Remove the tape or chain.
    Remove the “out of service” tag.




Signature: _____________________________________


Date: ________________________________________




LOCK-OUT/TAG-OUT                                                                                    Page 59
©2005, Waste Management                                                                      January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                                 PROTOCOLS – ATTACHMENT 35

                                                  HIGH PRESSURE TOILET


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                water pressure

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout            handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn “off” water at the valve closest to the toilet.
2. Install the valve lockout device and lockout.
3. Drain the tank.
4. Tag the toilet “out of service” or cord off the area with caution tape.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO THE TOILET BACK IN SERVICE:
1. Inspect the equipment to be sure that:
  a. All tools and other materials are removed.
  b. Machine/equipment is fully reassembled.
  c. Guards and other safety devices are installed.
2. Remove the valve lockout device and turn the valve “on”.
3. Remove the “out of service” sign and/or caution tape.




Date: _____________________ Signature: _____________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 60
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 36

                                    RESIDENTIAL ONE PASS TRUCK (MECHANICS)


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Turn the engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the disconnect.
6. Double chock/block the wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _______________________               Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 61
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 37
                       PERFORMING REPAIR, SERVICING, OR CLEANING OF IMPACT CRUSHER.


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Shut down main control panel and apply lock-out/tag-out.
2. Shut down the main electrical box and apply lock-out/tag-out.
3. Release stored energy.
4. Try the “on/off” switch on crusher to be certain power is “off”.
5. Place “out of service” sign and if necessary use caution tape.
6. Block or Brace all prime movers, drums, and gears



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE IMPACT CRUSHER BACK IN SERVICE:
1. Inspect the Crusher to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________

LOCK-OUT/TAG-OUT                                                                                       Page 62
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 38

               UNJAMMING CONVEYOR BELT OR PERFORMING MAINTENANCE, REPAIR, SERVICING OR
                                       CLEANING OF CONVEYOR.

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Shut down main control panel and apply lock-out/tag-out.
2. Shut down the main electrical box and apply lock-out/tag-out.
3. Release stored energy.
4. Try the “on/off” switch on crusher to be certain power is “off”.
5. Place “out of service” sign and if necessary use caution tape.
6. Block or Brace all prime movers, drums, and gears


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE CONVEYOR BELT BACK IN SERVICE:
1. Inspect the conveyor belt to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________                                        Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 63
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                              PROTOCOLS – ATTACHMENT 38




LOCK-OUT/TAG-OUT                             Page 64
©2005, Waste Management               January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 39



                                                   PRESSURE WASHER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                  flammability
  heat              hydraulic pressure                           mechanical                  water pressure

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout                plug lockout
 remove air fitting/nipple            wheel chock/blocks         remove spark plug and gas

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn pressure washer “off”.
2. Turn off soap and water supply valves and place valve lock-out/tag-out.
3. Relieve any existing pressure in the spray hose or nozzle.
4. Remove spark plug and, if necessary, the gas.
5. Place an “out of service” sign.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: ___________________          Signature: _____________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 65
©2005, Waste Management                                                                          January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                     PROTOCOLS – ATTACHMENT 40

                                         RESIDENTIAL ONE PASS TRUCK

     WHEN ANY PART OF THE DRIVERS’ BODY IS GOING TO BE UNDERNEATH THE RAISED TAILGATE
                         AND/OR DISLODGING JAMMED RECYCLABLES

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                              electrical                  flammability
  heat              hydraulic pressure                             mechanical                  gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks           plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                      Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                    Do Not Close Tag            Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Shut engine off and remove ignition key.
3. Place steering wheel cover on steering wheel.
4. Chock/block the wheels
5. Turn battery disconnect off and lock-out/tag-out disconnect.
6. Support bin or tailgate with: a) Appropriately rated chain fall, or; b) Install cylinder safety lock (sleeve), or; c)
   Use tailgate stand with adequate base, or; d) Block with 6 X 6 wood blocks, or; e) Use the safety pins provided
   by the manufacturer.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed
3. Remove lockout devices along with their own locks and tags.


Date: ________________________                Signature: _____________________________________

LOCK-OUT/TAG-OUT                                                                                           Page 66
©2005, Waste Management                                                                             January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 41

                                  RESIDENTIAL ONE PASS TRUCK
                         CLEANING OUT THE TRAPS ON ROUTE OR AT DISPOSAL


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                flammability
  heat              hydraulic pressure                            mechanical                gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag          Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag             Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Place the trucks safety props in the stands.
3. Release stored energy.
4. Turn of the engine and remove the ignition key.
5. Place steering wheel cover on steering wheel.
6. Chock/block the wheels.
7. Turn battery disconnect off and lock/tag-out the disconnect.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE VEHICLE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: _____________________ Signature: ___________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 67
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                                PROTOCOLS – ATTACHMENT 42

                                                    ROLL UP BAY DOORS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                              electrical                 flammability
  heat              hydraulic pressure                             mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                    circuit lockout             handle/valve lockout
 remove air fitting/nipple             wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
** Note ** Service on doors will primarily be conducted by an outside contractor.
1.   Place door in the desired servicing position.
2.   Turn “off” the circuit breaker and place a circuit breaker lockout device and lock-out/tag-out.
3.   Place a mechanical locking rod in position to stop door from moving.
4.   Place an “out of service” sign and if necessary use caution tape.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the roll up bay door to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Remove the mechanical locking rod.
3. Remove the circuit breaker lockout device and turn circuit breaker to “on.”
4. Remove “out of service” sign and caution tape.




Date: _____________________                   Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                         Page 68
©2005, Waste Management                                                                           January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                      PROTOCOLS – ATTACHMENT 43

       PERFORMING MAINTENANCE, REPAIR, OR CLEANING OF ELECTRICAL POWERED EQUIPMENT


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                                  electrical             flammability
  heat              hydraulic pressure                                 mechanical             gravity

LOCKOUT METHOD(S):
 battery disconnect                     circuit lockout                handle/valve lockout
 remove air fitting/nipple              wheel chock/blocks             plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                      Do Not Energize Tag             Do Not Open Tag
 Do Not Operate Tag                    Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Unplug equipment and/or shut down electricity at the circuit breaker.
2.   Install plug lock-out/tag-out or circuit breaker lockout cleat.
3.   Test equipment by turning switch to the “on” position.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.
4. Turn circuit breaker “on” and/or plug in equipment.




Date: ______________________ Signature: _____________________________________



LOCK-OUT/TAG-OUT                                                                                        Page 69
©2005, Waste Management                                                                          January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                    PROTOCOLS – ATTACHMENT 44

                                         AIR COMPRESSORS/AIR LINES

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                 flammability
  heat              hydraulic pressure                            mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks          plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn “off” air compressor at the circuit breaker or remove plug.
2. Install a circuit breaker lockout device or plug lockout device and lock out.
3. If servicing just the compressor, turn air line valve “off” and place valve lockout device and lock out/tag-out.
4. Drain system (lines and tank) of any pressurized air.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________         Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 70
©2005, Waste Management                                                                          January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                                 PROTOCOLS – ATTACHMENT 45




                                                              BALER
POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                               electrical               flammability
  heat              hydraulic pressure                              mechanical               gravity

LOCKOUT METHOD(S):
 battery disconnect                     circuit lockout             handle/valve lockout     plug lockout
 remove air fitting/nipple              wheel chock/blocks          remove key

TAG-OUT METHOD(S):
 Do Not Start Tag                      Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                    Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Shut down power supply and lock-out/tag-out.
2.   Try the “on/off” switch on the baler to be certain that the power is “off.”
3.   Remove the key from the baler – put key in pocket.
4.   install “out of service” tag
5.   Block or Brace all prime movers, drums, and gears


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ________________________                Signature: _____________________________________
LOCK-OUT/TAG-OUT                                                                                         Page 71
©2005, Waste Management                                                                           January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 46

                                                    CHOP SAW


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn chop saw off.
2. Unplug chop saw and place the plug into a plug lockout device. Test the lockout by depressing the trigger.
3. Place an “out of service” tag on the chop saw.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE CHOP SAW BACK IN SERVICE:
1. Inspect the equipment to be sure that:
       a. All tools and other materials are removed.
       b. Machine/equipment is fully reassembled.
       c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________                  Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 72
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 47

                                                     CRIMP MACHINE


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off the crimp machine.
2. Unplug the crimp machine and place the plug in a plug lockout device.
3. Place an “out of service” sign on the crimper.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 73
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 48
                                                  DRILL PRESS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off the drill press and let it return to the stop.
2. Unplug the press and place plug in a plug lockout device.
3. Place and “out of service” sign on the drill press.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE DRILL PRESS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________          Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 74
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 49
                                                  DROP LIGHTS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag         Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off the droplight.
2. Unplug or turn off circuit breaker and utilize the appropriate lockout device. Verify lockout by turning light on.
3. Tag the light “out of service.”



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE DROP LIGHTS BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 75
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 50
                                                 FILTER BUGGY

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off the filter buggy.
2. Unplug the filter buggy and place plug in a plug lockout device.
3. Place an “out of service” tag on the filter buggy.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE FILTER BUGGY BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ______________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 76
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 51
                                                 FLOOR BUFFER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Unplug the floor buffer and place plug in a plug lockout device.
2. Place an “out of service” tag on the floor buffer.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________          signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 77
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 52
                                               FLOOR SCRUBBER



POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout                plug lockout
 remove air fitting/nipple            wheel chock/blocks         disconnect battery cable


TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)


SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn floor scrubber off.
2. Disconnect the battery cables and place them in a plug lockout device.
3. Place an “out of service” sign on the floor scrubber.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE FLOOR SCRUBBER BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________          Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 78
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 53
                                                FLOOR SWEEPER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout                plug lockout
 remove air fitting/nipple            wheel chock/blocks         remove battery cables


TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn floor sweeper off.
2. Disconnect battery cables and place them in a plug lockout device.
3. Place an “out of service” sign on the sweeper.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE FLOOR SWEEPER BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ____________________          Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 79
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                    PROTOCOLS – ATTACHMENT 54
                                   FLOOR, TRANSMISSION & REAR JACKS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                             electrical                 flammability
  heat              hydraulic pressure                            mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout             handle/valve lockout       plug lockout
 remove air fitting/nipple            wheel chock/blocks          chain

TAG-OUT METHOD(S):
 Do Not Start Tag                     Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                   Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Lower jack all the way by opening the bleeder valve.
2. Remove the air nipple if jack is air activated. If not, wrap a chain around the jack in such a way as to make it
   impossible to use.
3. Tag the jack “out of service.”


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                        Page 80
©2005, Waste Management                                                                          January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 55
                                         GRINDERS (AIR/BENCH/HAND)


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off grinder.
2. Unplug (electric) and place plug in a plug lockout device or disconnect the air supply line (pneumatic) and
   remove the air nipple.
3. Verify that the grinder is not energized by turning on or depressing the trigger.
4. Tag grinder “out of service.”


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________         Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 81
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 56
                                                PARTS CLEANER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout       plug lockout
 remove air fitting/nipple            wheel chock/blocks         chain/tape shut

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off solvent circulator pump.
2. Unplug pump and place plug in a plug lockout device.
3. Remove parts cleaner machine from the solvent storage drum, cover drum.
4. Tag “out of service.”



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ___________________           Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 82
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 57
                                               STEAM CLEANERS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 water pressure

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn steam cleaner off.
2. Turn off the circuit breaker and the water, natural gas and soap supply valves.
3. Place a lock on the circuit breaker box and valve lockout devices on the soap and water supply valves.
4. Place an “out of service” tag on the steam cleaner.
5. Drain the system of any pressurized water.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
3. Notify affected employees that the lock-out/tag-out is being removed.
4. Remove lockout devices along with their own locks and tags.




Date: __________________            Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 83
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                               PROTOCOLS – ATTACHMENT 58
                                                    THE FUEL ISLAND


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Turn off pump and shut off circuit breaker.
2. Place a circuit breaker lockout device on the circuit breaker.
3. Verify that the pump is locked out using the pump-dispensing nozzle into an approved container. If appropriate, lockout
   dispensing nozzles.
4. Place an “out of service” sign at the fuel island.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: ______________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 84
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 59
                                                 TIRE BRANDER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Unplug tire brander and allow to cool.
2. Place the plug in a plug lockout device.
3. Place an “out of service” tag on the tire brander.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 85
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 60
                                                    TORCHES


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. install “out of service” tag
2. Remove torch head from hoses.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:

    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ______________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 86
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 61
                                              VACUUM CLEANER


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability

  heat                       hydraulic pressure                  mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. install “out of service” Tag
2. Disconnect power cord and lock out with lock out device.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _____________________ Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 87
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 62
                                                       VISES


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:

Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
   1. install “out of service” sign
   2. Remove from work area.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ________________________               Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 88
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 63
                                                    WELDERS


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Disconnect power source.
2. Place “out of service” tag
3. Test unit for any stored energy



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: ________________________               Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 89
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 64
                                          PICKUP & SERVICE TRUCKS



POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Shut the engine off and remove ignition key.
3. Place steering wheel cover on steering wheel.
4. Double chock/block wheels.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.




Date: _________________________              Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 90
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                   PROTOCOLS – ATTACHMENT 65
                                            Roll off / Drop box Trucks


POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
  Do Not Start Tag                   Do Not Energize Tag                   Do Not Open Tag
  Do Not Operate Tag                 Do Not Close Tag                      Steering Wheel Cover (Do Not Operate or
Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and
    how to verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1. Set the parking brake.
2. Release stored energy.
3. Turn the engine off and remove ignition key.
4. Place steering wheel cover on steering wheel.
5. Turn battery disconnect off and lock/tag-out the battery disconnect.
6. Double chock/block the wheels.



VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated,
    and disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.

PROCEDURES TO PLACE BACK IN SERVICE:
1. Inspect the equipment to be sure that:
   a. All tools and other materials are removed.
   b. Machine/equipment is fully reassembled.
   c. Guards and other safety devices are installed.
2. Notify affected employees that the lock-out/tag-out is being removed.
3. Remove lockout devices along with their own locks and tags.



Date: _______________________                Signature: _____________________________________


LOCK-OUT/TAG-OUT                                                                                       Page 91
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                                                              PROTOCOLS – ATTACHMENT 66
                                                           Template

POTENTIAL ENERGY SOURCES:
  air pressure      chemical reaction                            electrical                 flammability
  heat              hydraulic pressure                           mechanical                 gravity

LOCKOUT METHOD(S):
 battery disconnect                   circuit lockout            handle/valve lockout
 remove air fitting/nipple            wheel chock/blocks         plug lockout

TAG-OUT METHOD(S):
 Do Not Start Tag                    Do Not Energize Tag        Do Not Open Tag
 Do Not Operate Tag                  Do Not Close Tag           Steering Wheel Cover (Do Not Operate or Start)

SHUTDOWN PREPARATION:
Authorized employees will:
    Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to
    verify the hazardous energy is not present.
    Notify all affected employees about the lockout.

SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES:
1.
2.
3.
4.


VERIFY ISOLATION OF EQUIPMENT
Authorized employees will:
    Make sure no one is exposed to any areas of danger.
    Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and
    disconnected, including the main disconnect switch or circuit breaker.
    Operate the start buttons and other equipment controls to make certain the equipment will not operate.
    Return all operating controls to their “off” or safe position after the test is completed.


PROCEDURES TO PLACE BACK IN SERVICE:

1.
2.
3.




Date: _______________________               Signature: _____________________________________




LOCK-OUT/TAG-OUT                                                                                       Page 92
©2005, Waste Management                                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY-LOCK-OUT/TAG-OUT




                                   Lock Out Tag Out
                     Training Acknowledgement for Affected Employees


I understand that as an affected employee I have received instruction in the purpose and use of
the energy control procedure, the prohibition of removing locks or tags or attempts to restart
equipment that has been locked out or tagged.



_______________________________                     _____________________________
Employee Name                                       Employee Signature

___________________________
Date

____________________________
Trainer




CONTROL OF HAZARDOUS ENERGY-LOCK-OUT/TAG-OUT                                           Page 93
©2005, Waste Management                                                         January 1, 2005
CONTROL OF HAZARDOUS ENERGY
                                     PROTOCOLS – ATTACHMENT 66

Date of        Signature   Comments – Changes to Program
Review




LOCK-OUT/TAG-OUT                                            Page 94
©2005, Waste Management                              January 1, 2005
HEARING CONSERVATION PROGRAM

Program: Hearing Conservation Program

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707

Site Manager: Joe Whelan


PURPOSE

To describe the Hearing Conservation Program requirements when employees are exposed to
noise in excess of levels specified by OSHA 1910.95 Occupation Noise Exposure.

SCOPE

This procedure applies to all employees who may be exposed to noise levels above what OSHA
regulatory requirements specify.

EXCLUSIONS
Employees whose noise exposure is less than 85-dBA time weighted over an 8-hour day or 50%
equivalent dose.

DOT regulated drivers are excluded from requirements for wearing hearing protectors and
participating in OSHA Hearing Conservation Programs. DOT requires interior cab noise levels
to be 90 dBA or less. This does not preclude the facility from implementing appropriate
practices.

RESPONSIBILITIES

The District Manager is responsible for administering the Hearing Conservation Program. This
person:

Oversees the program.
Ensures that hearing protection is available.
Arranges for noise monitoring and audiometric tests as needed.
Reviews the program on an annual basis.
Provides employee training.
Posts notification in areas requiring hearing protection.
Checks that employees wear their hearing protection properly.

Waste Management supervisors are responsible for ensuring employees properly wears hearing
protection in required areas, ensuring noisy areas are posted and personnel are following the
requirements of this program.


Hearing Conservation Program                                                          Page 1
©2011, Waste Management                                                         January 2011
HEARING CONSERVATION PROGRAM

Waste Management employees must wear hearing protection properly where required and keep
it clean and well maintained. Employees should tell their supervisors about work areas they
believe are too noisy that may need monitoring or posting.

NOISE MONITORING

Waste Management conducts personal and/or area noise monitoring as needed to determine
which areas have noise levels above eighty-five dBA or above a fifty percent dose for an eight-
hour shift. A noise survey to determine areas of potential over-exposure should be conducted
prior to personal noise dosimetry. OSHA requires use of the A-weighted decibel scale to
determine compliance.

Area monitoring may be used to identify work areas, such as areas around pumps, motors, heavy
equipment, or compressors, where workers must wear hearing protection. Personal noise
monitoring determines which employees to include in the Hearing Conservation Program. Noise
monitoring is important in determining which type of hearing protection will best protect
hearing.

Until or unless site specific monitoring finds differently, all monitoring for site specific tasks
performed by Waste Managment that indicate exposures above or equal to 85dBA TWA or
equivalent will take precedence.

Each employee exposed at or above an 8-hour time-weighted average of 85 decibels will be
notified of the results of the monitoring.

CONTROL MEASURES

The permissible noise level for OSHA compliance is ninety decibels on the A-weighted scale for
an eight-hour, time-weighted average (TWA). If the noise levels exceed ninety dBA, Waste
Management must implement appropriate administrative or engineering controls.

The OSHA action level for noise exposure is eighty-five dBA for an eight-hour TWA. If any
Waste Management employee has a noise exposure that equals or exceeds the action level, a
Hearing Conservation Program is mandatory. The facility will maintain a list of employees
entered into the Hearing Conservation Program. The list is located with the Hearing
Conservation Program binder.

Employees in areas of the facility where the eight-hour TWA noise level equals or exceeds
eighty-five dBA, but is below ninety dBA, receive hearing protection. Use of hearing
protection is recommended. However, if annual audiometric examination reveals a decline
in the employee's hearing ability, the use of hearing protection becomes mandatory.

Any employee who is exposed to an eight-hour TWA of eighty-five dBA or greater who has
not yet had a baseline audiogram, must wear hearing protection.


Hearing Conservation Program                                                                 Page 2
©2011, Waste Management                                                                January 2011
HEARING CONSERVATION PROGRAM

Employees working in areas of the plant where the eight-hour TWA is ninety dBA or higher
must wear appropriate hearing protection at all times.

AUDIOMETRIC TESTING

TESTING

Employees exposed above the action level will be included in Waste Management Hearing
Conservation Program and given a baseline audiogram within 180 days of beginning work. An
audiogram is a chart, graph, or table that displays the results of an audiometric test. Audiograms
show an individual’s hearing threshold levels as a function of frequency.

The initial audiogram becomes a baseline against which future audiograms are compared to
determine if hearing loss has occurred. An employee’s annual audiogram is compared to the
baseline audiogram to determine if loss constitutes a standard threshold shift (STS). An STS is a
change in hearing threshold relative to the baseline audiogram of more than ten dB or more at
2000, 3000, and 4000-hertz (Hz) in either ear. OSHA requires reporting of all work-related STS's
with an average of ten dB or more at 2000, 3000, and 4000 Hz in either ear on the OSHA 300
log as an occupational illness. In determining whether a standard threshold shift has occurred,
allowance may be made for the contribution of aging (presbycusis) to the change in hearing level
by correcting the annual audiogram.

A licensed or certified audiologist, or a physician or technician who is certified by the Council of
Accreditation in Occupational Hearing Conservation, must perform the audiogram.

MAINTAINING RECORDS

Waste Management is responsible for maintaining records of noise measurements and
audiometric testing for prescribed lengths of time:

Area noise measurements—two years.
Audiometric test records—the duration of the worker’s employment. The audiometric test
provider should maintain these records for Waste Management.

Audiometric test records must include:

The name and job classification of the employee
The date of the test
The audiometric examiner’s name
The date of acoustic calibration
Measurements of background sound pressure levels in audiometric test rooms. (The testing
company usually retains this information).

If an employee incurred hearing loss prior to employment, proper medical documentation must
be on file.

Hearing Conservation Program                                                               Page 3
©2011, Waste Management                                                              January 2011
HEARING CONSERVATION PROGRAM

EMPLOYEE NOTIFICATION

Waste Management must notify all affected employees of personal and area monitoring results.
The contract physician provides interpretation of the audiometric test results to the employee.
Retain copies of this form in the employee’s personnel file.

If the comparison of the annual audiogram to the baseline audiogram indicates an STS has
occurred, Waste Management must inform the employee in writing within twenty-one days.
The audiometric tester should explain the results of the audiogram to each employee.

Any employee whose audiogram indicates an STS may be re-tested within thirty days. Waste
Management can use the results from the retest as the annual audiogram.

If a physician determines the STS is work related, the supervisor must take the following steps:

Fit and train an employee who has not been wearing hearing protectors in the use and care
of hearing protection.
Refit an employee already wearing protection with protectors with a higher level of
protection (attenuation) and retrain him or her in the proper use of hearing protection.


Refer the employee for a clinical audiological evaluation if wearing hearing protection
causes or aggravates the problem.

If subsequent audiometric testing of an employee indicates that an STS is not persistent, Waste
Management must inform the employee of this.

HEARING PROTECTORS

Waste Management employees in work areas where the noise level is over the action level
(eighty-five dBA, eight-hour TWA) receive hearing protection. Workers can select hearing
protection from a variety of types with the proper attenuation. The hearing protectors are
available at each work location.

All hearing protection devices will have a noise reduction rating (NRR) of twenty or greater.
Hearing protection must reduce employee exposure to less than eight-five dBA.

Hearing protectors are:

Supplied at no cost to employees in the Hearing Conservation Program. Replaced as
necessary.




Hearing Conservation Program                                                             Page 4
©2011, Waste Management                                                            January 2011
HEARING CONSERVATION PROGRAM

EMPLOYEE INFORMATION

As part of the Hearing Conservation Program, Waste Management will post signs at the
entrance to all rooms or work areas where the noise level exceeds eighty-five dBA. The signs
say:

Hearing Protection Required Beyond This Point, or equivalent. Waste Management will
provide access to a copy of the OSHA Noise Standard by posting it in a prominent location.
Supervisors should instruct employees who operate mobile equipment (such as drilling or
trenching equipment) to wear hearing protection.

Affected employees or their representatives have access to copies of this standard and a copy of
the standard is also posted at the work location.


TRAINING (Refer to Appendix A)

Employees exposed to noise above eighty-five dBA will be trained annually. Training is to cover
all of the requirements of the OSHA noise standard, including:

The effects of noise on hearing
The purpose, advantages, and disadvantages of various types of hearing protectors
The selection, fitting, and care of protectors
The purpose and procedures of audiometric testing
   The attenuation of different types of protection and what this means in terms of noise
   reduction.

RECORDKEEPING

RETENTION

Waste Management shall retain records required in this program for at least the following
periods:

   Noise exposure measurement records shall be retained for two (2) years.
   Audiometric tests records shall be retained for the duration of the affected employee’s
   employment.

ACCESS

All records required by this section shall be provided upon request to employees, former
employees, and representatives designated by the individual employee.




Hearing Conservation Program                                                             Page 5
©2011, Waste Management                                                            January 2011
HEARING CONSERVATION PROGRAM



ENFORCE THE PROGRAM

Consistent enforcement of the Hearing Conservation Program is important. The message needs
to be conveyed that the use of hearing protection is strictly required in some areas. All persons in
hearing protection areas, including visitors, managers, and office employees, must wear required
hearing protection devices.

REVIEW THE PROGRAM ANNUALLY

The program administrator conducts an annual review of the Hearing Conservation Program.
The review addresses the following:

Monitoring
Review previous monitoring results.
Identify areas with altered or changed equipment or processes and arrange for monitoring
in these areas.
Arrange for monitoring in these areas and areas where monitoring has not been performed
within a year.

Audiometric Testing
Review audiometric results for all employees.
Check to determine if repeat testing for employees who show an STS has been performed.
If not, arrange for repeat testing.
Arrange for all employees working in areas where the noise level is above the action level to
have audiometric testing annually.

Review Hearing Loss Patterns
Recognize jobs that seem to cause hearing loss.
List employees who show a loss of hearing above twenty-five dB (Standard Threshold
Shift) on the OSHA 300 log as an occupational illness.

Identify Potential Hearing Loss Causes
Do employees wear their hearing protection?
Do they wear hearing protection properly?
Is the protection sufficient?
Has noise increased in the work area?
Was this increase caused by the addition of new equipment?
Was this increase caused by old equipment becoming noisier?

Implement Additional Controls
Reduce noise sources with an engineering control. Document any noise abatement activity.
Get different hearing protectors.
Conduct additional training in the correct use of hearing protection.
Hearing Conservation Program                                                               Page 6
©2011, Waste Management                                                              January 2011
HEARING CONSERVATION PROGRAM
Enforce the use of hearing protection.


Retrain and issue hearing protection with a higher protection level to any employee showing
hearing loss. If these employees continue to show an occupationally related hearing loss over
two consecutive years, place them in a new job without a noise hazard.

Make a list of the names of the persons included in the Hearing Conservation Program.




Hearing Conservation Program                                                            Page 7
©2011, Waste Management                                                           January 2011
HISTORICAL NOISE LEVEL AND EXPOSURE DATA

                               Average Exposure   Exposure Range
                                    (dBA)             (dBA)        Avg. Dose %     Dose Range %
Hauling
Driver – Commercial                  86               76 – 90          79            19 - 151
Driver – Dump Truck                  78               69 – 88         27              5 – 34
Driver – Recycle                     85               81 – 91          70             9 – 138
Driver – REL                         85               83 – 87         57             42 – 81
Driver – Residential                 87               82 – 99          92             2 – 481
Driver – Roll-Off                    87               76 – 92         103            18 – 191
Driver – Semi-Truck                  86               83 – 88         68             28 – 101
Driver – Sweeper                     86               83 – 90         80             39 – 119
Drivers – Overall                    86               71 – 99         78              2 – 481
Landfill/Transfer
Driver – Site Truck                  84              78 – 89           43             18 – 85
Driver – Water Truck                 84              70 – 91          103            18 – 192
Gas Plant/Gas Recovery               90              82 – 98          102            22 – 316
Laboratory Personnel                 78              56 – 90           36            0.4 – 299
Loaders – Transfer/Tipping           86              70 – 95           71             4 – 299
Operator – Compactor                 91                91             115            96 – 134
Operator – Landfill Equip.           85              64 – 99           79             3 – 319
Spotter – Transfer / Tipping         85              71 – 93           57             6 – 131
Maintenance
Mechanic – Hauling/Landfill          81               69 – 96         35.8            3 – 236
Mechanic – MRF                       83               69 – 89          52             4 – 94
Tire Men                             83               71 – 88          57             8 – 91
Material Recovery Facility
Baler Operator                       87              76 – 104          77             13 – 200
Forklift/Bobcat Operator             87              81 – 93           73             54 – 187
Sorters                              88              72 – 103         101            1.9 – 1243
Ticket Collector MRF                 87              86 – 87           69              56 – 88


Note:

8-Hour Average Exposures of 85 dBA or Greater (or 50% of the Allowable Dose) Require
Hearing Conservation Training, Audiograms and the Availability of Hearing Protection.
8-Hour Average Exposures of 90 dBA or Greater (or 100% of the Allowable Dose) Require
Mandatory Use of Hearing Protection in Addition to Other Hearing Conservation Program
Requirements.
If the Data Above Indicates Excessive Exposures, Implement Hearing Conservation OR
Conduct Monitoring to Determine the Specific Exposures at Your Location. Send a Copy
of the Results to Corporate Safety.
DOT Drivers are Covered by 49 CFR 394 Inside of Their Cabs, and Not 29 CFR 1910.95. They
Must Not Wear Hearing Protection While Driving on Public Roadways




Hearing Conservation Program                                                           Page 8
©2011, Waste Management                                                          January 2011
HISTORICAL NOISE LEVEL AND EXPOSURE DATA


                       DOCUMENT REVIEW RECORD
Use this form to document plan reviews and plan revisions.
    Date                   Reviewer’s Signature              Plan Revisions Made




Hearing Conservation Program                                                 Page 9
©2011, Waste Management                                                January 2011
HEARING CONSERVATION PROGRAM

§29 CFR 1910.95
OCCUPATIONAL NOISE EXPOSURE.

(a) Protection against the effects of noise exposure shall be provided when the sound levels
    exceed those shown in Table G-16 when measured on the A scale of a standard sound level
    meter at slow response. When noise levels are determined by octave band analysis, the
    equivalent A-weighted sound level may be determined as follows:

   Equivalent sound level contours. Octave band sound pressure levels may be converted to the
   equivalent A-weighted sound level by plotting them on the graph and noting the A-weighted
   sound level corresponding to the point of highest penetration into the sound level contours.
   This equivalent A-weighted sound level, which may differ from the actual A-weighted sound
   level of the noise, is used to determine exposure limits from Table 1.G-16.

(b)(1) When employees are subjected to sound exceeding those listed in Table G-16, feasible
        administrative or engineering controls shall be utilized. If such controls fail to reduce
        sound levels within the levels of Table G-16, personal protective equipment shall be
        provided and used to reduce sound levels within the levels of the table.
    (2) If the variations in noise level involve maximums at intervals of 1 second or less, it is to
        be considered continuous. Table G-16. -- Permissible Noise Exposures{1}.

------------------------------------------------------------
                                      Sound
                                     level dBA
Duration per day, hours                        slow response
------------------------------------------------------------
8                                      90
6                                      92
4                                      95
3                                      97
2                                     100
1 1/2                                  102
1                                     105
1/2                                    110
1/4 or less                            115
----------------------------------------------------------------------
{1} When the daily noise exposure is composed of two or more periods of noise exposure of
     different levels, their combined effect should be considered, rather than the individual effect
     of each. If the sum of the following factions: C(1) / T(1) + C(2) / T(2) C(n) / T(n) exceeds
     unity, then the mixed exposure should be considered to exceed the limit value. C(n)
     indicates the total time of exposure at a specified noise level, and T(n) indicates the total time
     of exposure permitted at the level.

   Exposure to impulsive or impact noise should not exceed 140 dB peak sound pressure level.

(b) Hearing Conservation Program.
Hearing Conservation Program                                                                Page 10
©2011, Waste Management                                                                January 2011
HEARING CONSERVATION PROGRAM

   (1) The employer shall administer a continuing, effective Hearing Conservation Program, as
       described in paragraphs (c) through (o) of this section, whenever employee noise
       exposures equal or exceed an 8-hour time-weighted average sound level (TWA) of 85
       decibels
   (2) measures on the A scale (slow response) or, equivalently, a dose of fifty percent. For
       purposes of the Hearing Conservation Program, employee noise exposures shall be
       computed in accordance with Appendix A and Table G-16a, and without regard to any
       attenuation provided by the use of personal protective equipment.
   (3) For purposes of paragraphs (c) through (n) of this section, an 8-hour time-weighted
       average of 85 decibels or a dose of fifty percent shall also be referred to as the action
       level.

(d) Monitoring.
    (1) When information indicates that any employee's exposure may equal or exceed an 8-hour
        time-weighted average of 85 decibels, the employer shall develop and implement a
        monitoring program.
       (i) The sampling strategy shall be designed to identify employees for inclusion in the hearing
       conservation program and to enable the proper selection of hearing protectors.
       (ii) Where circumstances such as high worker mobility, significant component of
       impulse noise make area monitoring generally inappropriate, the employer shall use
       representative personal sampling to comply with the monitoring requirements of this
       paragraph unless the employer can show that area sampling produces equivalent results.
   (2) (i) All continuous, intermittent and impulsive sound levels from 80 decibels to 130 decibels shall
       be integrated into the noise measurements.
        (ii) Instruments used to measure employee noise exposure shall be calibrated to ensure
       measurement accuracy.
    (3) Monitoring shall be repeated whenever a change in production, process, equipment or
        controls increases noise exposures to the extent that:
        (i) Additional employees may be exposed at or above the action level; or
        (ii) The attenuation provided by hearing protectors being used by employees may be
        rendered inadequate to meet the requirements of paragraph (j) of this section.
(e) Employee notification. The employer shall notify each employee exposed at or above an 8-
    hour time-weighted average of 85 decibels of the results of the monitoring.
(f) Observation of monitoring. The employer shall provide affected employees or their
    representatives with an opportunity to observe any noise measurements conducted pursuant
    to this section.
(g) Audiometric testing program.
   (1) The employer shall establish and maintain an Audiometric testing program as provided in this
       paragraph by making Audiometric testing available to all employees whose exposures equal or
       exceed an 8-hour time-weighted average of 85 decibels.
   (2) The program shall be provided at no cost to employees.
   Audiometric tests shall be performed by a licensed or certified audiologist, otolaryngologist,
   or other physician, or by a technician who is certified by the Council of Accreditation in
   Occupational Hearing Conservation, or who has satisfactorily demonstrated competence in
   administering Audiometric examinations, obtaining valid Audiograms, and properly using,
   maintaining and checking calibration and proper functioning of the audiometers being used.

Hearing Conservation Program                                                                   Page 11
©2011, Waste Management                                                                   January 2011
HEARING CONSERVATION PROGRAM

   (3) A technician who operates microprocessor audiometers does not need to be certified. A
   technician who performs Audiometric tests must be responsible to an audiologist,
   otolaryngologist or physician.
   (4) All Audiograms obtained pursuant to this section shall meet the requirements of
       Appendix C: Audiometric Measuring Instruments.
   (5) Baseline Audiogram.
       (i) Within 6 months of an employee's first exposure at or above the action level, the
       employer shall establish a valid baseline Audiogram against which subsequent
       Audiograms can be compared.
       (ii) Mobile test van exception. Where mobile test vans are used to meet the Audiometric
       testing obligation, the employer shall obtain a valid baseline Audiogram within 1 year of
       an employee's first exposure at or above the action level. Where baseline Audiograms
       are obtained more than 6 months after the employee's first exposure at or above the action
       level, employees shall wearing hearing protectors for any period exceeding six months
       after first exposure until the baseline Audiogram is obtained.
       (iii) Testing to establish a baseline Audiogram shall be preceded by at least 14 hours
       without exposure to workplace noise. Hearing protectors may be used as a substitute for
       the requirement that baseline Audiograms be preceded by 14 hours without exposure to
       workplace noise.
       (iv) The employer shall notify employees of the need to avoid high levels of non-
       occupational noise exposure during the 14-hour period immediately preceding the
       Audiometric examination.
   (6) Annual Audiogram. At least annually after obtaining the baseline Audiogram, the
       employer shall obtain a new Audiogram for each employee exposed at or above an 8-
       hour time-weighted average of 85 decibels.
   (7) Evaluation of Audiogram.
       (i) Each employee's annual Audiogram shall be compared to that employee's baseline
       Audiogram to determine if the Audiogram is valid and if a standard threshold shift as
       defined in paragraph (g)(10) of this section has occurred. This comparison may be done
       by a technician.
       (ii) If the annual Audiogram shows that an employee has suffered a standard threshold
       shift, the employer may obtain a retest within 30 days and consider the retest the results
       of the retest as the annual Audiogram.
       (iii) The audiologist, otolaryngologist, or physician shall review problem Audiograms
       and shall determine whether there is a need for further evaluation. The employer shall
       provide to the person performing this evaluation the following information:
             (A) A copy of the requirements for hearing conservation as set forth in paragraphs
             (c) through (n) of this section;
             (B) The baseline Audiogram and most recent Audiogram of the employee to be
             evaluated;
             (C) Measurements of background sound pressure levels in the Audiometric test
             room as required in Appendix D; Audiometric Test Rooms.
             (D) Records of audiometer calibrations required by paragraph (h)(5) of this section.



Hearing Conservation Program                                                           Page 12
©2011, Waste Management                                                           January 2011
Appendix A

    (8) Follow-up procedures.
(i) if a comparison of the annual Audiogram to the baseline Audiogram indicates a standard threshold
shift as defined in paragraph (g)(10) of this section has occurred, the employee shall be informed of this
fact in writing, within 21 days of the determination. (ii) Unless a physician determines that the
standard threshold shift is not work related or aggravated by occupational noise exposure, the
employer shall ensure that the following steps are taken when a standard threshold shift occurs:
              (A) Employees not using hearing protectors shall be refitted and retrained in the use
              of hearing protectors and provided with hearing protectors offering greater
              attenuation if necessary.
              (B) Employees already using hearing protectors shall be refitted and retrained in the
              use of hearing protectors and provided with hearing protectors offering greater
              attenuation if necessary.
              (C) The employee shall be referred for a clinical audiological evaluation or an
              otological examination, as appropriate, if additional testing is necessary or if the
              employer suspects that a medical pathology of the ear is caused or aggravated by the
              wearing of hearing protectors.
              (D) The employee is informed of the need for an otological examination if a
              medical pathology of the ear that is unrelated to the use of hearing protectors is
              suspected.
        (iii) If subsequent Audiometric testing of an employee whose exposure to noise is less
              than an 8-hour TWA of 90 decibels indicates that a standard threshold shift is not
              persistent, the employer:
              (A) Shall inform the employee of the new Audiometric interpretation; and
              (B) May discontinue the required use of hearing protectors for that employee.
    (9) Revised baseline. An annual Audiogram may be substituted for the baseline Audiogram
        when, in the judgment of the audiologist, otolaryngologist or physician who is evaluating
        the Audiogram:
        (i) The standard threshold shift revealed by the Audiogram is persistent; or
        (ii) The hearing threshold shown in the annual Audiogram indicates significant
        improvement over the baseline Audiogram.
   (10) Standard threshold shift.
        (i) As used in this section, a standard threshold shift is a change in hearing threshold
        relative to the baseline Audiogram of an average of 10 dB or more at 2000, 3000, and
        4000 Hz in either ear.
        (ii) In determining whether a standard threshold shift has occurred, allowance may be
        made for the contribution of aging (presbycusis) to the change in hearing level by
        correcting the annual Audiogram according to the procedure described in Appendix F:
        Calculation and Application of Age Correction to Audiograms.
(h) Audiometric test requirements.
    (1) Audiometric tests shall be pure tone, air conduction, hearing threshold examinations, with
        test frequencies including as a minimum 500, 1000, 2000, 3000, 4000, and 6000 Hz.
        Tests at each frequency shall be taken separately for each ear.




Hearing Conservation Program                                                                    Page 13
©2011, Waste Management                                                                    January 2011
Appendix A

     (2) Audiometric tests shall be conducted with audiometers (including microprocessor
         audiometers) that meet the specifications of, and are maintained and used in accordance
         with, American National Standard Specification for Audiometers, S3.6-1969, which is
         incorporated by reference as specified in § 1910.6.

      (3) Pulsed-tone and self-recording audiometers, if used, shall meet the requirements specified
      in Appendix C: Audiometric Measuring Instruments.
      (4) Audiometric examinations shall be administered in a room meeting the requirements
          listed in Appendix D: Audiometric Test Rooms.
(5)     Audiometer calibration.
          (i) The functional operation of the audiometer shall be checked before each day's use by
          testing a person with known, stable hearing threshold's output to make sure that the
          output is free from distorted or unwanted sounds. Deviations of 10 decibels or greater
          require an acoustic calibration.
          (ii) Audiometer calibration shall be checked acoustically at least annually in accordance
          with Appendix E: Acoustic Calibration of Audiometers. Test frequencies below 500 Hz
          and above 6000 Hz may be omitted from this check. Deviations of 15 decibels or greater
          require an exhaustive calibration.
          (iii) An exhaustive calibration shall be performed at least every two years in accordance
          with sections 4.1.2; 4.1.3; 4.1.4.3; 4.2; 4.4.1; 4.4.2; 4.4.3; and 4.5 of the American
          National Standard Specification for Audiometers, S3.6-1969. Test frequencies below
          500 Hz and above 6000 Hz may be omitted from this calibration.
  (i) Hearing protectors.
      (1) Employers shall make hearing protectors available to all employees exposed to an 8-hour
          time-weighted average of 85 decibels or greater at no cost to the employees. Hearing
          protectors shall be replaced as necessary.
      (2) Employers shall ensure that hearing protectors are worn:
          (i) By an employee who is required by paragraph (b)(1) of this section to wear personal
          protective equipment; and
          (ii) By any employee who is exposed to an 8-hour time-weighted average of 85 decibels
          or greater, and who:
               (A) Has not yet had a baseline Audiogram established pursuant to paragraph
               (g)(5)(ii); or
               (B) Has experienced a standard threshold shift.
      (3) Employees shall be given the opportunity to select their hearing protectors from a variety
          of suitable hearing protectors provided by the employer.
      (4) The employer shall provide training in the use and care of all hearing protectors provided
          to employees.
      (5) The employer shall ensure proper initial fitting and supervise the correct use of all
          hearing protectors.
  (j) Hearing protector attenuation.
      (1) The employer shall evaluate hearing protector attenuation for the specific noise
          environments in which the protector will be used. The employer shall use one of the
          evaluation methods described in Appendix B: Methods for Estimating the Adequacy of
          Hearing Protection Attenuation.

 Hearing Conservation Program                                                             Page 14
 ©2011, Waste Management                                                             January 2011
Appendix A

    (2) Hearing protectors must attenuate employee exposure at least to an 8-hour time-weighted
        average of 90 decibels are required by paragraph (b) of this section.
    (3) For employees who have experienced a standard threshold shift, hearing protectors must
        attenuate employee exposure to an 8-hour time-weighted average of 85 decibels or
        below.
(4)     The adequacy of hearing protector attenuation shall be re-evaluated whenever employee
        noise exposures increase to the extent that the hearing protectors provided may no longer
        provide adequate attenuation. The employer shall provide more effective hearing
        protectors where necessary.
(k) Training program.
    (1) The employer shall institute a training program for all employees who are exposed to
        noise at or above an 8-hour time-weighted average of 85 decibels, and shall ensure
        employee participation in such program.
    (2) The training program shall be repeated annually for each employee included in the
        Hearing Conservation Program. Information provided in the training program shall be
        updated to be consistent with changes in protective equipment and work processes.
    (3) The employer shall ensure that each employee is informed of the following:
        (i) The effects of noise on hearing;
        (ii) The purpose of hearing protectors, the advantages, disadvantages, and attenuation of
        various types, and instructions on selection, fitting, use, and care; and
        (iii) The purposes of Audiometric testing, and an explanation of the test procedures.
(l) Access to information and training materials.
    (1) The employer shall make available to affected employees or their representatives copies
        of this standard and shall also post a copy in the workplace.
    (2) The employer shall provide to affected employees any informational materials pertaining
        to the standard that are supplied to the employer by the Assistant Secretary.
    (3) The employer shall provide, upon request, all materials related to the employer's training
        and education program pertaining to the standard to the Assistant Secretary and the
        Director.

(m) Recordkeeping
    (1) Exposure measurements. The employer shall maintain an accurate record of all
        employee exposure measurements required by paragraph (d) of this section.
    (2) Audiometric tests.
        (i) The employer shall retain all employee Audiometric test records obtained pursuant to
        paragraph (g) of this section:
        (ii) This record shall include:
             (A) Name and job classification of the employee;
             (B) Date of the Audiogram;
             (C) The examiner's name;
             (D) Date of the last acoustic or exhaustive calibration of the audiometer; and
             (E) Employee's most recent noise exposure assessment.
             (F) The employer shall maintain accurate records of the measurements of the
                 background sound pressure levels in Audiometric test rooms.


Hearing Conservation Program                                                            Page 15
©2011, Waste Management                                                            January 2011
Appendix A

   (3) Record retention. The employer shall retain records required in this paragraph (m) for at
       least the following periods.

(i) Noise exposure measurement records shall be retained for two years.
        (ii) Audiometric test records shall be retained for the duration of the affected employee's
        employment.
    (4) Access to records. All records required by this section shall be provided upon request to
        employees, former employees, representatives designated by the individual employee,
        and the Assistant Secretary. The provisions of 29 CFR 1910.20(a) - (e) and (g) - (i) apply
        to access to records under this section.
    (5) Transfer of records. If the employer ceases to do business, the employer shall transfer to
        the successor employer all records required to be maintained by this section, and the
        successor employer shall retain them for the remainder of the period prescribed in
        paragraph (m)(3) of this section.
(n) Appendices.
    (1) Appendices A, B, C, D, and E to this section are incorporated as part of this section and
        the contents of these Appendices are mandatory.
    (2) Appendices F and G to this section are informational and are not intended to create any
        additional obligations not otherwise imposed or to detract from any existing obligation.
(o) Exemptions. Paragraphs (c) through (n) of this section shall not apply to employers engaged
    in oil and gas well drilling and servicing operations.
    (p) Startup date. Baseline Audiograms required by paragraph (g) of this section shall be
    completed within six months of hire date.

Purpose
The purpose of this training is to give you the basic knowledge needed to understand why
hearing conservation is an important part of the safety and health equation.
Objectives:
By the end of this training, participants should be able to understand:
   1. The Effects of noise on hearing;
   2. The purpose of hearing protectors.
   3. The advantages, disadvantages, of various types of hearing protection.
   4. Selection, use and care of hearing protection.
   5. The purpose of audiometric testing.

                        It’s as simple as 1, 2, 3...

1) Your outer ear, called the pinna, collects sound waves and channels them down the ear canal
to a thin, tight piece of skin called the tympanic membrane (eardrum).

2) The eardrum vibrates in response to these pressure waves and pushes on the small bones of
your middle ear. These bones act like a set of levers, transferring their mechanical motion to a
fluid-filled structure in the inner ear, called the cochlea.


Hearing Conservation Program                                                             Page 16
©2011, Waste Management                                                             January 2011
Appendix A

       In the cochlea, cells with tiny sensing hairs transform the fluid movement into electrical
       signals. These signals travel along the auditory nerve to your brain. Once in the brain, the
       nerve signals are decoded and processed into what we recognize as sound.




EFFECTS OF NOISE ON HEARING

Prolonged exposure to excessive noise levels can cause a noise-induced hearing loss.

When you are exposed to excessive noise levels, the first effect usually is a temporary hearing
loss. You may have difficulty in conversation or the ears may feel “plugged and “ring.” Over a
period of time, an individual who experiences repeated temporary hearing loss will have gradual,
permanent, irreversible hearing loss.

Noise-induced hearing loss (called “acoustic trauma”) involves damage to the receptor cells in
the inner ear and is classified as sensori-neural impairment. A noise-induced hearing loss
typically begins with a drop in hearing level at the higher frequencies of sound. As the hearing
loss increases, it includes the lower sound frequencies that include speech. Early noise-induced
hearing loss normally is not detected by an individual, since it occurs above the speech range.
By the time an individual is aware of a hearing loss, the amount of loss may be significant.

Noise exposure is cumulative. So the noise at home or at play must be counted in the total
exposure during any one day. If the maximum allowable noise level is reached while on the job,
any following exposure during non-working hours, such as a noisy lawnmower or loud music
will may cause you to exceed the safe daily limit.




Hearing Conservation Program                                                             Page 17
©2011, Waste Management                                                             January 2011
Appendix A
                   PICTURE THIS: (similarity to hairs cells in your ears)
You take a shortcut across a luxuriant green lawn with tall, healthy blades of grass reaching
proudly toward the sky. Where you have walked, the blades are trampled, bent over, bruised and
damaged. You can see the outline of each of your steps in the thick carpet of grass.
Tomorrow, you decide to take the same shortcut. As you look, there is no sign you
passed this way yesterday. This time, however, some of your co-workers see you and
decide to do the same thing. Soon, many people begin taking this route, not just once a
day but throughout the day as well. Before long, bicyclists are using the path.
Eventually, the blades of grass have no time to repair themselves between uses.
Gradually, some of the blades break off, and then more as time progresses. Eventually,
where once there was a beautiful lawn, there now is a dirt trail with only a blade or two
of grass here and there.


PURPOSE OF HEARING PROTECTORS


Hearing protectors either are plugs of various shapes and sizes that are inserted into the ear
canals or muffs that are placed over the ears. In either case, their job is to reduce the intensity of
sound that reaches the ear so as to protect the ear from potentially damaging noise.

Advantage and Disadvantage of Hearing Protectors:

Foam Hearing              A cylinder of sound-attenuating foam. The foam is compressed and
Protectors:               inserted in the ear canal, where the foam expands to fill the canal.

                            Advantages: Readily available, inexpensive, disposable, adequately
                            comfortable, lightweight.
                            Disadvantages: Requires regular replacement, can become
                            uncomfortable with prolonged wear.

Ribbed Hearing            Made of rubber in a "one size fits all" shape. They are inserted in the ear
Protectors:               canal as deeply as possible.

                            Advantages: Generally available, durable, lightweight, washable.
                            Disadvantages: Slip easily, uncomfortable, may not provide tight fit.

Muff Hearing              Resemble stereo head sets that completely cover the ears.
Protectors:
                            Advantages: Good noise reduction, hard to lose, more durable with
                            infrequent replacement.
                            Disadvantages: Heavy and cumbersome, more expensive, hot,
                            uncomfortable.



Hearing Conservation Program                                                                 Page 18
©2011, Waste Management                                                                 January 2011
Appendix A
Custom Molded            Made of silicone and are molded to exactly fit the individual's ear.
Protectors:
                           Advantages: Good noise rating, durable, very comfortable for long
                           periods of time.
                           Disadvantages: Requires initial impression of ear, more expensive,
                           possible replacement.


Attenuation of Hearing Protectors (Noise Reduction by Hearing Protectors)
Manufacturers of hearing protection assign a Noise Reduction Rating (NRR) to each type of
hearing protector. The NRR is an indication of the relative level of protection provided by the
plug or muff. The higher the NRR, the more protection the equipment provides. The NRR is
determined under ideal laboratory conditions and should not be used as a direct measurement of
the protection that each wearer will receive.

Field Attenuation of Hearing Protection: To estimate the attenuation afforded to a noise-
exposed employee in an actual work environment by muffs, plugs, or a combination of both,
proceed as follows.
a. For muffs or plugs:
Determine the laboratory-based noise attenuation afforded by the given hearing protector. This is
based on laboratory testing using human subjects and is provided by the manufacturer. It is
referred to as the Noise Reduction Rating or NRR and should be on the packaging.
Subtract 7dB from the NRR to correct for using A-weighted measurements.
To adjust for workplace conditions, applying a safety factor of 50% is recommended. This
is because the field use of ear protectors does not afford the same degree of protection achieved
in the laboratory using well-trained subjects under ideal test conditions.
b. For dual protection (i.e. muffs and plugs):
Determine the laboratory-based noise attenuation (NRR) for the higher rated hearing protector,
subtract 7dB, and (it is recommended that you) apply a safety factor of 50%.
Then add 5 dB to the field-adjusted NRR to account for the use of the second hearing protector.

Example 1:     TWA = 100 dBA and Muff NRR = 19 dB
               Approximate Field Attenuation is: (19-7) × 50% = 6 dB
               100 dBA TWA - 6 dB = 94 dBA

Conclusion:    The protected TWA can be assumed to be 94 dBA. Feasible engineering controls
               must be implemented. Since the HCA does not require applying a 50% correction
               factor, the protected TWA is 88 dBA. Therefore, better hearing protection (with
               greater attenuation) is not required by the standard. If an employee exhibits an
               STS, better hearing protection may be required.

Example 2:     Given TWA = 98 dBA and Plug NRR = 29 dB
               Approximate Field Attenuation is: (29-7) × 50% = 11 dB
               98 dBA TWA - 11 dB = 87 dBA

Conclusion:    The protected TWA can be assumed to be 87 dBA. Unless the employee exhibits

Hearing Conservation Program                                                             Page 19
©2011, Waste Management                                                             January 2011
Appendix A
               an STS, the employer meets one of the necessary conditions for being excused
               from the requirement to implement engineering controls. Better hearing
               protection (with greater attenuation) is not required since the protected TWA,
               without the safety factor, is 76 dBA. If an employee exhibits an STS, better
               hearing protection should be recommended.

Example 3:     Given TWA8 = 110 dBA, Plug NRR = 29 and Muff NRR = 25 dB
               Employer requires dual protection.
               Calculate field-adjusted NRR for the higher-rated protector:
               (29-7) × 50% = 11 dB
               Add 5 dB to this field-adjusted NRR: 11+5 = 16 dB
               Calculate the protected TWA8: 110 dBA TWA8 - 16 dB = 94 dBA

Conclusion:    The protected TWA8 can be assumed to be 94 dBA. If feasible, engineering
               controls must be implemented. The protected TWA8, without using the 50% safety
               factor, is 83 dBA. Therefore, better hearing protection is not required by the HCA.
               Hearing protectors with greater attenuation should be recommended.



SELECTION OF EAR PROTECTORS


Ear protector selection should be based on employee convenience, comfort, and proper degree of
attenuation. Under attenuation would lead to excessive noise exposure. Over attenuation in
moderate noise levels can lead to a feeling of isolation and, consequently, poor acceptance of the
protectors.

Fitting

Earplugs must fit tightly to provide a good seal. Grasping the ear with the opposite hand, pulling
it up and out to open the ear canal and then inserting the plug with the other hand insert the
earplug.

Muffs will normally fit all people without any difficulty. Eyeglasses may interfere with the
proper fitting of the muff. Muffs that attach directly to hard hats are also available.

Ear stoppers are usually easy to position. The headband can be worn on top of or behind the
head, or under the chin.

When hearing protectors are initially worn, it may take a short time for the employee to adjust to
the new level of sound. The same sounds are heard, but at a lower intensity.




Hearing Conservation Program                                                             Page 20
©2011, Waste Management                                                             January 2011
Appendix A
Care and Use of Protectors

Ear protectors must be maintained in sanitary condition. It is important that earplugs be clean
when inserted into the ears. If plugs are dirty when inserted, they may cause irritation, which
could lead to infection of the ear canal. The same applies to stoppers.

Earplugs, when not in use, should be stored in some type of container that can be closed to seal
out dust or dirt. Earplugs should be replaced when they no longer can be cleaned or loose their
pliability.

Earmuffs have a replaceable seal, which should be kept clean. The seal should be replace
whenever it becomes stiff or cracked.


AUDIOMETRIC TESTING

Audiometric testing is a means of determining your hearing ability. “Normal” hearing includes
the median hearing level of a large group of American adults between 18 and 25 years of age,
having no known history of ear disease and no appreciable high-level noise exposure. The
accepted normal range of hearing is between 0 and 25 decibels.

The audiometric test consists of exposing each ear separately to sound at six different
frequencies. The audiometric test will indicate the amount of hearing loss, if any, of an
individual. The higher the decibel reading, the greater the hearing loss. As an individual ages
there is a natural hearing loss, which takes place. This is called presbycusis. A cold, an ear
infection, or recent high noise exposure can cause a temporary hearing loss, which would
produce poor test results. Tests should not be administered to anybody with a cold or an ear
infection. Test will need to be administered once cold or ear infection has passed. Audiogram
should be preceded by at least 14 hours of quiet. If audiogram is to be administered during work
shift the supervisor should require it mandatory for employees to wear hearing protectors prior to
taking audiogram test.


RIGHT TO ACCESS RECORDS

All records required by this section shall be provided upon request to employees, former
employees, representatives designated by the individual employee, and the director.


Conclusion

The more intense or louder the noise, the more likely it will contribute to hearing loss. The
longer an employee is exposed to a particular noise at work or at home, the greater the chance an
injury will occur to the auditory system. To minimize the risk of hearing loss occurring it is up
to each employee to take responsibility and wear hearing protectors at work or at home.



Hearing Conservation Program                                                            Page 21
©2011, Waste Management                                                            January 2011
Appendix A
Glossary
    (1) Audiogram - A chart, graph, or table resulting from an audiometric test showing an
individual's hearing threshold levels as a function of frequency.
    (2) Audiologist - A professional, specializing in the study and rehabilitation of hearing, who
is certified by the American Speech, Hearing, and Language Association or licensed by a state
board of examiners.

    (3) Baseline audiogram - The audiogram against which future audiograms are compared.
    (4) Criterion sound level - A sound level of 90 decibels.
    (5) Decibel (dB) - Unit of measurement of sound level.
    (6) Hertz (Hz) - Unit of measurement of frequency, numerically equal to cycles per second.
    (7) Impulsive or impact noise - Noise levels which involve maxima at intervals greater than
one second. Where the intervals are less than one second, the noise levels shall be considered
continuous.
    (8) Medical pathology - A disorder or disease. For purposes of this regulation, a condition or
disease affecting the ear, which should be treated by a physician specialist.
    (9) Noise dose - The ratio, expressed as a percentage, of (a) the time integral, over a stated
time or event, of the 0.6 power of the measured SLOW exponential time-averaged, squared A-
weighted sound pressure and (b) the product of the criterion duration (8 hours) and the 0.6 power
of the squared sound pressure corresponding to the criterion sound level (90 dB).
    (10) Noise dosimeter - An instrument that integrates a function of sound pressure over a
period of time in such a manner that it directly indicates a noise dose.
    (11) Otolaryngologist - A physician specializing in diagnosis and treatment of disorders of the
ear, nose and throat.
    (12) Representative exposure - Measurements of an employee's noise dose or 8-hour time-
weighted average sound level that the employer deems to be representative of the exposure of
other employees in the workplace.
    (13) Standard threshold shift - A hearing level change, relative to the baseline audiogram, of
an average of 10 dB or more at 2000, 3000, and 4000 Hz in either ear.
    (14) Sound level - Ten times the common logarithm of the ratio of the the square of the
measured A-weighted sound pressure to the square of the standard reference pressure of 20
micropascals. Unit: Decibels (dB). For use with this regulation, SLOW time response, in
accordance with ANSI S1.4.1971 (R1976), is required unless specifically specified otherwise.
    (15) Sound level meter - An instrument for the measurement of sound level.
    (16) Time-weighted average sound level - That sound level, which if constant over an 8-hour
period, would result in the same noise dose as if measured in the time varying noise level
environment. A sound’s volume level, which your brain perceives as loudness, is measured in
deciBels.




Hearing Conservation Program                                                             Page 22
©2011, Waste Management                                                             January 2011
Appendix A
RELATION SHIP OF THE DECIBEL TO SOUND INTENSITY IN NON-LOGARITHMIC UNITS


Decibels       Units
   0            1
  10            10
  20            100 (102=100)
  30            1,000
  40            10,000
  50            100,000
 100            10,000,000,000
 150            1,000,000,000,000,00




Hearing Conservation Program                                              Page 23
©2011, Waste Management                                              January 2011
 
HAZARD COMMUNICATION PROGRAM


Program: Hazard Communication

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707




PURPOSE

Employees at our facilities use certain materials requiring specific precautions. It is the policy of
WGSL to communicate any known hazards associated with these materials and to train our
employees in safe handling techniques.


DEFINITIONS

Chemical – any element, chemical compound or mixture of elements and/or compounds.

Chemical manufacture – an employer with a workplace where chemical(s) are produced for
distribution or us.

Combustible liquid – any liquid having a flashpoint at or above 100 degree F (37.8 degree C),
but below 200 degree F (93.3 degree C), except any mixture having components with flashpoints
of 200 degree F (93.3 degree C), or higher, the total volume of which make up 99 percent or
more the total volume of the mixture.

Common name- any designation or identification such as code name, code number, trade name,
brand name, or generic name used to identify a chemical other than by its chemical name.

Container – any bag, barrel, bottle, box, can, cylinder, drum, reaction vessel, storage tank, or the
like that contains a hazardous chemical.

Explosive – a chemical that causes a sudden, almost instantaneous release of pressure, gas, and
heat when subjected to sudden shock, pressure, or high temperature.

Exposure or exposed – an employee is subjected in the course of employment to a chemical that
is a physical or health hazard, and includes potential (e.g., accidental or possible) exposure.

Flashpoint – the minimum temperature at which a liquid gives off a vapor in sufficient
concentration to ignite when tested.

Health hazard – includes chemicals which are carcinogens, toxic or highly toxic agents,
reproductive toxins, irritants, corrosives, sensitizers, hepatotoxins, neurotoxins, agents which act
Hazard Communication Program                                                                  Page 1
   ©2011, Waste Management                                                             January 2011
HAZARD COMMUNICATION PROGRAM


on the hematopoietic system, and agents which damage the lungs, skin, eyes, or mucous
membranes.

Labels – any written, printed, or graphic material displayed on or affixed to containers of
hazardous chemicals.

Physical hazard – a chemical for which there is scientifically valid evidence that it is a
combustible liquid, a compressed gas, explosive, flammable, an organic peroxide, an oxidizer,
pyrophoric, unstable (reactive) or water-reactive.

Trade secret – any confidential formula, pattern, process, device, information or compilation of
information that is used in an employer’s business, and that gives the employer an opportunity to
obtain an advantage over competitors who do not know or use it.

Unstable – a chemical which in pure state, or as produced or transported, will vigorously
polymerize, decompose, condense, or will become self-reactive under conditions of shocks,
pressure or transfer.

Water-reactive – a chemical that reacts with water to release a gas that is either flammable or
presents a health hazard.

Work area – a room or defined space in a workplace where hazardous chemicals are produced or
used, and where employees are present.

Workplace – an establishment, job site, or project, at one geographical location containing one or
more work areas.


RESPONSIBILITIES


Management and supervisors must ensure that proper information is obtained and communicated
to appropriate employees. Employees must follow the safe work practices outlined in training
sessions, Material Safety Data Sheets, warning labels, and/or operating procedures.

The effectiveness and success of this program depend on the active support and
involvement of all personnel.

MATERIAL SAFETY DATA SHEETS (MSDS)

Material Safety Data Sheets (MSDS’s) contain information necessary to safely handle specific
materials. It is important for WGSL to obtain the MSDS’s from suppliers concerning hazardous
materials purchased. Workers are advised of the following information:

       Name, address, and telephone number of manufacturer, distributor or importer.
Hazard Communication Program                                                             Page 2
  ©2011, Waste Management                                                          January 2011
HAZARD COMMUNICATION PROGRAM
       Chemical name and/or common name of material.
       Chemical analysis or formula.
       Ingredients and hazards associated with chemicals used.
       Physical data.
       Fire and explosion hazard data.
       Reactive data.
       Health hazard data.
       Spill leak, and disposal data.
       Special protection information.
       Special precautions and comments.
       MSDS identification number.


Vendors are required to provide MSDS’s for all hazardous materials including solvents, soaps,
oils, maintenance supplies, lubricants, cleaners, compressed gases, welding and brazing wires
and rods, fluxes, etc. These sheets should be sent to the District Manager. Records should be
maintained of all verbal and written requests for MSDS’s from suppliers of hazardous
materials.

Records of verbal requests must include date of request, supplier’s name, product for which the
sheet is being requested, name of person from whom sheet is being requested, and name of the
person making the request.          Written requests can be kept in a separate file.




Hazard Communication Program                                                          Page 3
  ©2011, Waste Management                                                       January 2011
HAZARD COMMUNICATION PROGRAM

A file of location specific MSDS’s used will be maintained at the following locations:

       SHOP
       WGSL OFFice

A master copy of all MSDS’s will be maintained in the Maintenance Managers office.



STATE SPECIFIC ITEMS


Each MSDS will be maintained for at least 30 years.

These MSDS’s are available for review by any employee upon request. In addition, the
Maintenance Manager will screen all MSDS’s received to insure that the information listed
above is included. If sheets are incomplete, the supplier will be notified and an updated
and/or complete MSDS will be requested. Records of these requests will be maintained also.

Generally, the Company does not become aware of new and significant health hazards associated
with materials used in our facilities unless notified by the supplier or manufacturer. Upon receipt
of updated MSDS’s Maintenance Manager replaces outdated MSDS’s with the new ones, and
Informs employees of the changes.

WORKPLACE CHEMICAL LIST

The Maintenance Managers will be responsible for maintaining a Workplace Chemical List of all
hazardous materials used at WGSL. A separate form will be used for each facility. The
Workplace Chemical List will be available for review by employees of a facility upon request.

The Workplace Chemical List constitutes the official list of all hazardous materials approved for
use at WGSL.

The Maintenance Manager must approve materials not on the list before being received.


Once a year, each department will conduct a physical inventory of chemicals and materials
in use in its area and report the results to Joe Whelan, program manager. The results will
be compared with the Workplace Chemical List to insure that it is complete and accurate.




Hazard Communication Program                                                              Page 4
  ©2011, Waste Management                                                           January 2011
HAZARD COMMUNICATION PROGRAM


LABELS AND OTHER FORMS OF WARNING
Labels and similar forms of warning list any hazards associated with containerized materials.
Therefore, all hazardous materials will be placed in labeled containers. Labels must not be
defaced or removed. Labeled containers must always be positioned with the labels clearly
visible. If a container is without a label, it must be labeled immediately. Until the container is
properly labeled, the materials will not be use Labels are to include:

       A list of hazardous materials within the container.
       Appropriate hazard warnings.
       Name, address and phone number of the manufacturer, distributor, or importer.

Labels are to be in English, with other languages optional. Labels will contain the material’s
name. If the chemical name is used, the common name can be found by referring to the
Workplace Chemical List.

Employees are trained not to rely solely on the information inscribed on a label, but also to read
the MSDS for additional information.


TRAINING AND LOCATION OF HAZARD DATA
A program has been established to ensure that all employees are trained prior to beginning work
with hazardous materials. Procedures have also been established to train new hires and
transferred employees. This training is to inform employees of any hazardous materials known
to be present in the workplace.

       This written program and copies of MSDS’s covering hazardous materials in a specific
       work area are maintained by the Maintenance Manager and supervisors in appropriate
       places to permit ready access to employees, physicians, and employee representatives at
       all times. (A location within a locked office or filing cabinet and not readily accessible is
       unacceptable.)

       The Maintenance Manager maintains the facilities Workplace Chemical List and a master
       copy of all MSDS’s. MSDS’s from this file are not to be removed from the facility.
       Employees may review this information at any time.

       Employee training includes, as a minimum:

       -       A briefing on the OSHA Hazard Communication Standard concerning employee
               and company rights and responsibilities.
       -       Identification of hazardous materials in the employee’s work area, and potential
               dangers associated with them.
Hazard Communication Program                                                               Page 5
  ©2011, Waste Management                                                            January 2011
HAZARD COMMUNICATION PROGRAM


           Location of the written program and MSDS’s appropriate to the employee’s work
           area.
     -     How to use MSDS’s (e.g., what information they contain, where to find the
           information, how to use it).
     -     How to use labels and other forms of warning—what information they
           communicate, and how to use that information for protection.
     -     Specific training appropriate to the employee.
     -     Methods and observations that may be used to detect the presence or release of a
           hazardous chemical in the work area (such as monitoring conducted by the
           employer, continuous monitoring devices, visual appearance or odor of hazardous
           chemicals when being released, etc.)

     -     The measures employees can take to protect themselves from these hazards,
           including specific procedures the employer has implemented to protect employees
           from exposure to hazardous chemicals, such as appropriate work practices,
           emergency procedures, and PPE to be used.
     -     Employee’s protection against discharge or other discrimination due to the
           employee’s exercise of the rights afforded pursuant to the provisions of the
           Hazardous Substances Information and Training Act.
     -     Whenever WGSL receives a new or revised MSDS, such information will be
           provided on a timely basis not to exceed 30 days after receipt, if the new
           information indicates significantly increased risk to, or measures necessary to
           protect, employee health as compared to those stated on a MSDS previously
           provided.

     Schedule

     -     All new employees will be trained prior to working with hazardous materials.
     -     All transferred employees will be trained prior to assignment in an area where
           hazardous materials are used.
     -     All employees will be trained on the hazards of materials at the time they are
           introduced into their work area.
     -     All employees, prior to being assigned to a non-routine task involving hazardous
           materials, will receive special training.
     -     All employees will be retrained annually.
     -     The District Manager will schedule such annual training as a safety-meeting topic.
           Ongoing responsibility for training employees in the situations described above
           rests with the supervisor of the applicable work area.

     Documentation

     All training is to be documented and the information kept at the facility site.
     Documentation will show the following:


Hazard Communication Program                                                        Page 6
  ©2011, Waste Management                                                     January 2011
HAZARD COMMUNICATION PROGRAM

       -      Date of training session.
       -      Type of training given (brief description or outline)
       -      Name and signature of employees receiving the training.
       -      Name(s) of instructor(s).




HAZARD DETERMINATION AND EVALUATION
WGSL will accept the hazard determination and evaluation conducted by the supplier.


EMPLOYEE HAZARD COMMUNICATION REGARDING NON-
ROUTINE TASKS
 WGSL recognizes that employees will be required to perform
non-routine tasks (emergency repairs and/or clean-up of
chemical spills, etc.), which could expose them to unusual
risks from hazardous materials. Therefore, special attention
will be given by the District

Manager and supervisors to instruct employees on how to protect themselves in the performance
of these tasks.

       Instructions by the supervisor take place immediately before the employee(s) perform(s)
       the non-routine task.

       Written records are kept by the supervisor showing:

       -      Date
       -      Non-routine task involved
       -      Name(s) of employee(s) involved
       -      Name of person doing the communication and training

       Employees are issued special protective equipment and instructions for its use in the
       performance of non-routine tasks.




Hazard Communication Program                                                         Page 7
  ©2011, Waste Management                                                      January 2011
HAZARD COMMUNICATION PROGRAM


INFORMING CONTRACTORS

     The following information will be communicated to all contractors:



     -      Hazardous chemicals to which they may be exposed while on the job site.

     -      Precautions the contractor’s employees may take to lessen the possibility of
            exposure by usage of appropriate protective measures.

     It is the responsibility of the contractor to communicate this information to their
     employees and to sign and return the attached acknowledgment form.
     Contractors must provide a copy of each MSDS for chemicals they bring to our site.




Hazard Communication Program                                                       Page 8
  ©2011, Waste Management                                                    January 2011
INFORMATION SUMMARY




            ACKNOWLEDGMENT OF CONTRACTOR RESPONSIBILITY
                    FOR HAZARD COMMUNICATION



I,   ________________________________________,        representing   the   company   named

_________________________________________, do acknowledge receipt of the contractor

portion of the WGSL and Resource Recovery Facility Hazard Communication Program. I

understand the responsibility of my Company under this program.       I will insure that the

personnel of my company comply with all applicable provisions while at the WGSL.



________________________________                               ________________
      Signature                                                Date




Hazard Communication Program                                                        Page 9
  ©2011, Waste Management                                                     January 2011
INFORMATION SUMMARY

Work Area: _____________________________________              Date Prepared: _____/_____/______


    Name of        Physical Hazards          Health Hazards            Special handling Precautions
Product/Material F= Flammable             C= Cancer
(label/MSDS name,   C= Combustible        R= Reproductive Harm
if different)       R= Reactive           S= Skin Hazard
                    NA= None Applicable   T= Toxin (target organ)




Hazard Communication                                                        Page 10
©2011, Waste Management                                             January 2011
HAZARD COMMUNICATION PROGRAM

Employee Hazard Communication Regarding Non-Routine Tasks
Date     Non-routine task involved     Name(s) of      Name of
                                       employee(s)    Supervisor
                                        involved      conducting
                                                       training




Hazard Communication                                          Page 11
©2011, Waste Management                               January 2011
 
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


Program: Welding, Cutting, Brazing & Hot Work Guidelines

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707




PURPOSE

Describe the requirements when welding, burning, brazing, cutting or performing other "hot"
work.


REQUIREMENTS

1. Only trained authorized personnel may weld at WGSL or use Waste Management equipment.
2. Designate areas for welding, brazing, and cutting.
3. Use general or local exhaust ventilation to keep the concentration of toxic fumes, gases, or
   dusts below the OSHA Permissible Exposure Limits. Refer to the Industrial Hygiene
   database for information about exposures to welders.
4. Provide, and require the use of, flameproof screens or shields around designated welding or
   burning areas or move all combustible materials at least 35 feet from the welding/burning
   area or cover the materials with welding blankets.
5. Provide, and require the use of, personal protective equipment (PPE) as specified in the PPE
   hazard assessment.
6. Protect welding cables and cylinders from damage.
7. Use only approved cutting and welding equipment.
8. Use a check valve for each of the acetylene and oxygen cylinders and use a flashback arrestor
   at the acetylene or gas regulator.


COMPRESSED GASES

1. Oxygen, fuel gas and acetylene cylinders must be shut off when not in use.
2. Pressure should not remain in the hoses when not in use.
3. Store cylinders upright and away from flame and heat sources.
4. Maintain labels on cylinders.
5. Separate oxygen from acetylene or fuel gases in storage by 20 feet or a 1/2-hour fire-rated
   non-combustible barrier 5 feet in height.
6. Segregate empty and full containers in storage.




WELDING, CUTTING, BRAZING & HOT WORK                                                   Page 1
©2011, Waste Management                                                          January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


HOT WORK PERMITS

1. Hot Work means working with materials or equipment or in conditions which could result in
   fire or explosion.
2. Hot work permits must be used when welding, brazing, or cutting outside of designated
   areas.
3. Train and authorize an individual to issue hot work permits.
4. Use a fire watch when welding, burning or brazing outside of the designated welding area.
   The fire watch should man the fire extinguisher when hot work is in progress.
5. Use the hot work permit and require forced air ventilation for any welding, cutting, or
   brazing works inside confined spaces.
6. Hot work permits should be kept on file for one year.

INTRODUCTION

The Waste Management written Welding Brazing/ Cutting/Compressed Gas and "Hot Work"
guidelines include the following:

   Safety Procedures for arc welding
   Safety Procedures for gas welding and cutting
   Using compressed gas cylinders
   Fire prevention and protection
   Hot work control program
   Maintenance of welding equipment
   Welding in confined spaces
   Ventilation during welding
   Personal protective equipment (PPE)
   Respiratory and hearing protection
   Training

The following sections describe how WGSL addresses each of these topics.


HEALTH EFFECTS ASSOCIATED WITH WELDING

Welding produces different fumes and dusts depending on the metal being welded, the kind of
welding, and the electrode coatings on the metal.

Welding also produces gases. Gases such as nitrogen oxide, nitrogen dioxide, and ozone may
irritate the respiratory tract and mucous membranes. Chronic exposure can lead to respiratory
disease. Carbon monoxide may cause headaches and dizziness and at high level leads to oxygen
deprivation. Argon, carbon dioxide, helium, and nitrogen deplete the atmosphere of oxygen. Arc
welding can generate these gases as well.



WELDING, CUTTING, BRAZING & HOT WORK                                                  Page 2
©2011, Waste Management                                                         January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


Welding produces intense light and heat. Electric welding can cause electric shock and burns.
The intensely bright light produced by welding can burn the eyes and skin very quickly.

Fumes from welding steel products can irritate the lungs. The excessive breathing in of fumes
can cause the flu-like symptoms of metal fume fever. Nickel fumes also irritate the lungs, and
skin contact can produce an allergic reaction. Airborne nickel dusts can be cancer causing when
breathed in. Airborne chromium dust can be toxic. However, nickel and chromium fumes are not
considered cancer causing.


GENERAL SAFETY GUIDELINES

Follow these guidelines when welding:

   Avoid prolonged breathing of gases, fumes, and dust.
   Never weld in damp or wet areas without protective equipment.
   Wear safety glasses, leather welding gloves, a welding helmet, and protective clothing.
   Keep the area clear of combustibles (at least 35 feet from the hot work area).
   Regularly inspect all equipment to ensure that it is in good working condition.
   Use an NIOSH-approved respirator for fumes when other controls do not bring fumes, dusts,
   or other contaminants down to safe levels.
   Use fire-resistant welding curtains or shields constructed of noncombustible materials
   positioned so that others do not see the welding arc.


ARC WELDING

   Cover welding cables located on the floor or ground so they don’t cause a tripping hazard.
   Don’t overload cables.
   Don’t use worn or poorly connected cables. Inspect the cables and connections frequently.
   Don’t operate or move the polarity switch under the load of a welding current.
   Do not leave the electrode in the lead when it is not in use. Shut off the welder when not in
   use.
   Never weld on trucks that have the motor running. Disconnect the vehicle battery cables
   before welding.
   Don’t operate the range switch under load.
   Follow lockout/tagout procedures when performing servicing or maintenance on machines.
   (Note: Repairs are to be made only by qualified persons.)
   Never leave an uninsulated electrode holder or a “live” electrode on the tabletop in contact
   with a grounded metallic surface.
   Ensure that welding leads are free of cracks or cuts in the insulation.




WELDING, CUTTING, BRAZING & HOT WORK                                                    Page 3
©2011, Waste Management                                                           January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


GAS WELDING

   Use welding and cutting torches equipped with antiflashback valves.
   Follow the safe handling and use procedures for compressed gas cylinders detailed in these
   guidelines.




  NON-FLAMMABLE GAS
                             FLAMMABLE GAS


          2                        2




COMPRESSED GAS CYLINDERS

The gas in cylinders like the ones used for welding is highly pressurized and can create a
potentially hazardous situation. Cylinders exposed to heat, fire, or rough handling can explode
with great force. For this reason, store cylinders in a cool, dry place. Chain and cap them when
they are not in use. Before you use a cylinder, read the label to verify the contents. Report
illegible labels to your supervisor.




WELDING, CUTTING, BRAZING & HOT WORK                                                      Page 4
©2011, Waste Management                                                             January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


SAFE HANDLING REQUIREMENTS

Wear safety glasses and insulated neoprene gloves when transporting or exchanging cylinders, or
when connecting or disconnecting regulators.
Use a hand truck to transport cylinders.
Check hoses for leaks. Shut off the cylinders when hoses are connected but not in use.
Check regulators when changing cylinders to be sure they are free of dust and oil.
Inspect cylinders for defects, corrosion, and dents. Isolate and mark any defective cylinders, and
contact the vendor immediately for pick-up.

Store filled cylinders inside in a well-protected, well-ventilated, dry location. They must be at
least 20 feet from highly combustible materials, sparks, open flames, excessive heat, and away
from elevators, stairs, or gangways. Keep cylinders secured to prevent them from falling over.
Separate stored oxygen cylinders from stored fuel gas cylinders or combustible material
(especially oil or grease) by at least 20 feet or by a noncombustible barrier. This barrier must be
at least 5 feet high and have a fire resistance rating of one-half hour.
Mark all cylinders legibly to identify their contents. If the cylinder is unmarked, do not use it.
If a cylinder is leaking, close the valve, cap, and move to a well-ventilated area. Contact the
supplier immediately.
For cylinders that are flammable, use a non-sparking wrench when changing.
Be careful that cylinders are not placed so as to become part of an electrical circuit.
Never try to mix any gases in a cylinder.
Never try to refill a cylinder.
Mark empty tanks “MT,” close the valves, and replace valve caps securely. Separate “MT” and
full tanks.


                 FLAMM ABLE GAS   FLAMMABLE GAS
                                                  FLAMM ABLE GAS                          2
                          2               2
                                                           2        FLAMMABLE G
                                                                            2 AS   FLAMMABLE G
                                                                                             AS




ATTACHING REGULATORS

   Handle the regulator carefully at all times. Do not use pipe wrenches or pliers for attaching
   regulators to cylinders. Use an open-end wrench of the proper size instead. Use a close-fitting
   wrench to avoid stripping the threads Hammers or wrenches must not be used to open or
   close cylinder valves that are fitted with hand wheels.
   When opening the valves, never stand in front of the regulators. The tanks are under pressure
   and the regulators may explode when opened.

WELDING, CUTTING, BRAZING & HOT WORK                                                                          Page 5
©2011, Waste Management                                                                                 January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


REQUIREMENTS FOR HOSES, TORCH VALVES, AND CONNECTIONS

   Replace or repair hoses showing leaks, burns or worn places.
   Color-code hoses to avoid accidental mixing.
   Connect hoses to regulator properly. Check hose connections for proper threading. Standard
   hose connections are threaded right-hand for oxygen and left-hand for acetylene or other fuel
   gas. This helps prevent an accidental switch of oxygen and fuel-gas hoses.
   Use only approved bronze or brass fittings. Copper fittings must never be used on acetylene
   cylinders. Under certain conditions, the acetylene might react with the copper to produce an
   explosive compound.
   Do not use oil, grease, or similar substances on any torch or regulator. Oil and grease in the
   presence of oxygen may burn with explosive force, if ignited.


TESTING FOR LEAKS

To test for leaks, open the fuel and oxygen cylinder valves with the needle on the torch closed.
Adjust the regulator to normal working pressures, and apply soapy water to connections and hose
with a brush. If bubbles form, a leak is present. Correct condition as necessary. Do not try to
repair hoses with tape. Do not use any other testing method.


GAS WELDING AND CUTTING

Lighting and Shutting Off the Torch
   Ensure the proper welding or cutting tip is selected and installed.
   Purge the hoses by opening the valve on the acetylene cylinder. This should never be opened
   more than one and one-half turns. Three-fourths of a turn is preferable.
   Open the acetylene torch valve one-fourth turn.
   Adjust the acetylene to working pressure with the gas regulator screw.
   Close the acetylene torch valve.
   Slowly open the oxygen cylinder valve all the way.
   Open the oxygen torch valve one-half turn.
   Adjust the oxygen to working pressure with the gas regulator screw.
   Turn off the oxygen torch valve. The final steps are the actual lighting of the torch.
   Reopen the acetylene torch valve one-fourth to three-quarters turn and light the gas with a
   spark lighter. (NEVER USE MATCHES.)
   Increase the fuel supply until the flame has a slight tendency to jump away from the tip.
   Gradually open the oxygen needle.

Follow the procedures below for shutting off the torch:

   Close the torch valves acetylene first, then oxygen.
   Close the cylinder valves acetylene first, then oxygen.

WELDING, CUTTING, BRAZING & HOT WORK                                                    Page 6
©2011, Waste Management                                                           January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


   Open both torch valves to release the pressure.
   Shut off the regulator-adjusting handle until you no longer feel any spring tension.
   Close the torch valves. This procedure reduces the possibility of regulator fires when the
   oxygen cylinder valve is open again. It will also prevent leaks of acetylene or oxygen while
   the equipment is not in use. A leak could cause a serious fire.


FIRE PREVENTION AND PROTECTION
The site program administrator designates safe areas for welding, brazing, and cutting free of
combustible and flammable materials. Welding and cutting in these areas should not pose a
hazard to welders or workers in nearby areas. Work site preparation to avoid fires and/or
explosions includes ensuring all combustibles are at least 35 feet from the work area. If this is
not possible, protect combustibles using flameproof covers, and complete a Hot Work Permit
[HOT WORK PERMIT FORM].

Follow these safe work practices when welding to prevent fires and/or explosions:

   Know the location of nearby fire extinguishers and know how to use them.
   Do not weld in locations close to chlorinated hydrocarbon vapors coming from degreasing,
   cleaning, or spraying operations. Heat or rays from the arc can react with solvent vapors to
   form a highly toxic gas and other irritating products.
   Do not weld on containers or barrels which have held combustible or flammable materials
   or materials which, when heated, give off toxic vapors. Perform cleaning, purging, or inerting
   first.
   Do not weld on a closed container unless the contents have been identified and found to be
   non-flammable.




CLEANING CONTAINERS
  When you know the container held a gas or liquid which will readily dissolve in water, use
  the following method:
      Flush out the container with water several times, and then fill the container with water.
      Before welding, be sure there is a vent or opening on the container to provide for release
      of air pressure.

WELDING, CUTTING, BRAZING & HOT WORK                                                       Page 7
©2011, Waste Management                                                              January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


   When you know the container held a gas or liquid that will not readily dissolve in water,
   perform the following procedure:
       Clean out the container thoroughly with steam or a compatible-cleansing agent. Purge all
       air or inert materials with a gas such as carbon dioxide or nitrogen before repairing.
       Carbon dioxide is heavier than air and will tend to remain in the container if the opening
       is at the top.
       Use steam to clean out light material.
       Use a strong caustic soda solution to clean out heavy oils or grease.
   Don’t clean where there is poor ventilation. Ventilation is necessary to carry away harmful or
   explosive vapors.
   Don’t clean near any open flames. When scraping or hammering to remove heavy sludge or
   scale use a spark resistant tool and keep the tool wet to avoid sparks.
   Keep your head and arms as far away from your work as possible.


HOT WORK CONTROL PROGRAM

To minimize the potential for employee injury from fires/explosions arising from unsafe cutting
and welding practices, and in certain conditions such as confined spaces, a hot work control
program must be implemented. At a minimum, the program must include the following
elements:

   Where cutting, welding or other hot work is performed on a regular basis,      one or more
   permanent designated areas must be established for this work.
   A permit system for authorizing the temporary use of portable cutting and welding
   equipment outside of designated areas must be used.
      Document precautions on [HOT WORK PERMIT FORM].
      A permit must not be issued if the work can be moved to a designated hot work area.
      A supervisor must inspect the area to verify that all necessary precautions have been
      taken before filling out and signing the permit.
      The welder must post a signed permit in the area where the hot work will be done before
      commencing work.
      The welder must return the permit to the supervisor when the work has been completed,
      signing off on the permit to indicate that a final check-up was conducted.


HOT WORK SAFETY RULES
  Obtain a permit before performing hot work outside of designated areas.
  Check the condition of hot work equipment prior to each use. (Note: A visual inspection
  should be made with special attention to electrical cables and gas hoses. A soap solution
  should be used to check for leaks at valves and connections of oxygen-acetylene sets,
  especially after changing cylinders.)



WELDING, CUTTING, BRAZING & HOT WORK                                                    Page 8
©2011, Waste Management                                                           January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


   Protect floor and wall openings within 35 feet.
   Ensure automatic sprinklers (when installed) are functional.
   Ensure that portable fire extinguishers of the proper type are in the immediate vicinity. (Note:
   "A" rating for ordinary combustibles; "B" rating for flammable and combustible liquid and
   gases; "C" rating for energized electrical equipment.)
   Protect welding hoses against physical damage. (Note: Use UL approved welding hose reels,
   when appropriate.)
   Ensure a fire watch is present during hot work activities.
   Check the area 30 minutes after the work is completed for hazardous conditions or fire.


WHEN WELDING IS PROHIBITED

You must never weld or cut in the following situations:

   If you have not been trained and authorized by management.
   If the building you are working in has sprinkler systems that are not working.
   In the presence of explosive atmospheres.
   Near large quantities of highly ignitable materials


VENTILATION

Four main factors in arc and gas welding affect the potential for air contamination. These factors
are:

   The size of the space
   The gross volume of work
   The number of welders working at one time
   The size of the welding rod

Provide adequate ventilation for protection against potentially excessive concentrations of
airborne contaminants (for example, welding, fumes, and carbon monoxide gas) and oxygen
deficient atmospheres.

Local exhaust may be needed when welding, cutting or brazing is done on materials which
contain or are coated (treated) with fluorides, zinc, lead, copper, beryllium, cadmium, mercury,
or residual chlorinated solvents (such as perchloretheylene).

Engine-driven welding equipment used indoors is to have exhaust gases piped to suitable exhaust
ducts or directly outdoors. Never locate engine exhaust on or near an air conditioning intake.




WELDING, CUTTING, BRAZING & HOT WORK                                                      Page 9
©2011, Waste Management                                                             January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


WELDING MACHINE USE

Welding machines must meet safety and design requirements. Observe the following guidelines
when using arc-welding equipment:

   Be properly trained.
   Do not exceed voltage limits.
   Ground the frame or case of the welding machine.
   Ground the ground cable of every power circuit to prevent accidental shock by stray current.
   Do not ground to pipelines carrying gases or flammable liquids, or conduits carrying
   electrical conductors.
   Do not use chains, wire ropes, crane hoists, and elevators carry a welding current.
   Check ground connections.
   Provide disconnecting switches or controllers as part of the welding machines or have them
   near the machines.
   Do not use a welding machine to thaw out frozen water or pipes. Fire, explosion, or damage
   to the welding machine may result.

Follow safe maintenance practices. These practices include:

   Reporting all equipment defects or hazards to your supervisor.
   Remove defective equipment immediately from service.
   Have all repairs made by qualified personnel.
   Thoroughly dry and test machines that have become wet before using again.
   Replace cables with damaged insulation or exposed bare conductors.


PERSONAL PROTECTION

Welders must wear the appropriate personal protective equipment. Specific requirements are
detailed below.


EYE AND FACE PROTECTION

Select the proper eye protection based on the welding operation. During arc welding or cutting
operations, use a welding helmet. Helmets must have filter and cover plates designed for easy
removal, and be fitted with a double lens color arc ray lens inside and clear plastic outside. Flash
goggles should be used under the welding helmet, particularly while welding using a gas-
shielded arc welder.

The shaded lens used in the welder’s helmet must meet the test for transmission of radiant energy
prescribed in ANSI Z87-1-1989. Select the correct shade of filter lens using the following chart:



WELDING, CUTTING, BRAZING & HOT WORK                                                      Page 10
©2011, Waste Management                                                              January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


LENS FILTER SHADE GUIDELINES

Type of Operation                       Shade Number


Gas Torch
Light Cutting - up to one inch             3 or 4
Medium Cutting- one to six inches          4 or 5
Heavy cutting -More than six inches        5 or 6
Gas Welding - Up to 1/8” thickness         4 or 5
Gas Welding -1/8” to ½” thickness          5 or 6
Gas Welding- More than ½” thickness        6 or 8


Arc Welding
Up to 30 amps                           12 or 14
 Shielded metal arc welding
  (Greater than 5/16” Electrodes)
30 to 74 amps                                  10
 Shielded Metal Arc Welding
  (Less than 55/32” Electrodes)
75 to 200 amps                                 11
  Gas Shielded Arc Welding
  (Non Ferrous)
200 to 400 amps                                12
  Gas Shielded Arc Welding
  (Ferrous)


Helpers or others who normally work near welding operations should also wear shaded eye
protection (such as goggles). Selection of the darkness of the lens shade depends on the degree of
the helper’s exposure to the welding “flash.” Often the helper must wear shaded goggles that are
the same shade that the welder wears.
For welding, the best protection is provided by welding hoods. Welding hoods can be worn with
safety hats by adding special fittings to the safety hats. For grinding, chipping, or cleaning, use
protective goggles.

Inspect eye and face protection for welding before each use. Inspect helmets for cracks or
defects. Replace cracked or poorly fitting filter plates. Keep a cover glass in front of the filter
plate.




WELDING, CUTTING, BRAZING & HOT WORK                                                         Page 11
©2011, Waste Management                                                                 January 2011
WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES


PROTECTIVE CLOTHING

Supervisors must ensure that protective clothing is inspected, maintained, and worn properly to
preserve its effectiveness. Additionally, employees should:

   Wear long-sleeved shirts and pants.
   Keep clothing reasonably free of oil or grease.
   Not roll-up sleeves or cuffs when welding.
   Button sleeves and collars.


TRAINING

Welders and their Supervisors must be:
  Trained in the safe operation of their equipment and emergency procedures in the event of a
  fire.
  Properly trained before entering to weld in a confined space.
  Trained in health hazards associated with welding.


DEFINITIONS

Arc cutting: cutting processes that melt the metals with the heat of an arc between an electrode
and the base metal.

Gas metal arc welding (MIG): an arc welding process that produces coalescence of metals by
heating them with an arc between a continuous filler metal (consumable) electrode and the work.
Shielding is obtained entirely from an externally supplied gas or gas mixture.

Gas tungsten arc welding (TIG): an arc welding process that produces coalescence of metals by
heating them with an arc between a tungsten (non-consumable) electrode and the work.
Shielding is obtained from a gas or gas mixture. Pressure and filler metal may or may not be
used.

Welder and welder operator: any operator of electric or gas welding and cutting equipment.




WELDING, CUTTING, BRAZING & HOT WORK                                                     Page 12
©2011, Waste Management                                                             January 2011
HOT WORK PERMIT



Date

Time Started                                                Estimated Completion Time

Department                                                  Floor           Building

Work to Be Done



Permit Expires:                Date                                         Time

               All items following have been completed. Therefore, permission is granted for this work.
Signed                                                                   Title


                                                     PRECAUTIONS
Do not cut, weld, or use other open flame or spark-producing equipment until the following precautions have been taken:
Check Each Item                                                Work on Enclosed Equipment
                                                               (Tanks, Containers, Ducts, Dust Collectors, Etc.)
   Work Location has Been Personally Examined.                     Equipment Cleaned of All Combustibles.
   Sprinklers, Where Provided, are in Working Order.               Containers Purged of All Flammable Liquids.
   Cutting and Welding Equipment is in Good Condition.             Explosion Meter Used to Monitor Presence of
                                                                   Flammable Vapors.
                                                               Work on Walls or Ceiling
   Floors Swept Clean of Combustibles.                            The Construction is Non-Combustible and Without
   Combustible Floors Have Been Wet Down, Covered                  Combustible Covering or Insulation.
   with Damp Sand, Metal or Flame Resistant Sheets.                Combustibles Have Been Moved Away from Opposite
                                                                   Side of the Wall
                                                               Fire Watch
   All combustibles Have Been Located Outside a Radius             Provided for a Least 30 Minutes After Operation is
   of 35’ from the Operation.                                      Completed or Stopped
                                                                   Proper Fire Extinguishers or Small Hose at Site.
   Flame Resistant Tarp Suspended from Work to Collect             Trained in the Use of Extinguishing Equipment.
   Sparks.
   PPE and Flash Screens Erected as Required.
                                                    FINAL CHECK UP
Work areas and all adjacent areas to which sparks and heat might have spread (such as floors above and below and on
opposite side of walls) were inspected for at least 30 minutes after the work was completed, and were found fire safe.
Signed                                                                         Title


                             After Signing, Return Permit to Person Who Issued It




WELDING, CUTTING, BRAZING & HOT WORK                                                                  Page 13
©2011, Waste Management                                                                          January 2011
 
RESPIRATORY PROTECTION PROGRAM

                                  TABLE OF CONTENTS


Definitions                                                        Intro
                                                                    1, 2
Respiratory Hazards and Respirator Selection
                                                                    3
Medical Evaluation
                                                                   3, 4
Fit-Testing
                                                                    4
Training
                                                                    5
Cleaning, Storage and Maintenance of Respirators
                                                                    6
Air Quality for Self-Contained Air Line Devices
                                                                    7
Compressor Systems
                                                                    7
Voluntary Respiratory Use
                                                                    8
Change Schedule
                                                                    8
Policy of Providing Respirators and Medical Evaluation at No
Cost to the Employee
                                                                    9
Annual Program Evaluation
                                                                    10
Recordkeeping
                                                                Appendix A
Respirator Medical Evaluation Questionnaire
                                                                Appendix B
Employee Annual Respirator Fit-Test and Training Record
                                                                Appendix C
User Seal Check
                                                                Appendix D
Respirator Cleaning Procedures
                                                                Appendix E
Information for Employees Using Respirators When not Required
                                                                Appendix F
Periodic Respirator Program Evaluation
                                                                Appendix G
Respiratory Protection Based on Historical Air Monitoring



Respiratory Protection                                                            Intro
©2011, Waste Management                                                    January 2011
RESPIRATORY PROTECTION PROGRAM


Definitions

Definitions. The following definitions are important terms used in the respiratory protection
program.

Air-purifying respirator means a respirator with an air-purifying filter, cartridge, or canister that
removes specific air contaminants by passing ambient air through the air-purifying element.

Atmosphere-supplying respirator means a respirator that supplies the respirator user with
breathing air from a source independent of the ambient atmosphere, and includes supplied-air
respirators (SARs) and self-contained breathing apparatus (SCBA) units.

Canister or cartridge means a container with a filter, sorbent, or catalyst, or combination of
these items, which removes specific contaminants from the air passed through the container.

Demand respirator means an atmosphere-supplying respirator that admits breathing air to the
face piece only when a negative pressure is created inside the face piece by inhalation.

Emergency situation means any occurrence such as, but not limited to, equipment failure,
rupture of containers, or failure of control equipment that may or does result in an uncontrolled
significant release of an airborne contaminant.

Employee exposure means exposure to a concentration of an airborne contaminant that would
occur if the employee were not using respiratory protection.

End-of-service-life indicator (ESLI) means a system that warns the respirator user of the
approach of the end of adequate respiratory protection, for example, that the sorbent is
approaching saturation or is no longer effective.

Escape-only respirator means a respirator intended to be used only for emergency exit.

Filter or air purifying element means a component used in respirators to remove solid or liquid
aerosols from the inspired air.

Filtering face piece (dust mask) means a negative pressure particulate respirator with a filter as
an integral part of the face piece or with the entire face piece composed of the filtering medium.

Fit factor means a quantitative estimate of the fit of a particular respirator to a specific
individual, and typically estimates the ratio of the concentration of a substance in ambient air to
its concentration inside the respirator when worn.

Fit test means the use of a protocol to qualitatively or quantitatively evaluate the fit of a
respirator on an individual. (See also Qualitative fit test QLFT and Quantitative fit test QNFT.)


Respiratory Protection                                                                       Intro
©2011, Waste Management                                                               January 2011
RESPIRATORY PROTECTION PROGRAM


High efficiency particulate air (HEPA) filter means a filter that is at least 99.97% efficient in
removing monodisperse particles of 0.3 micrometers in diameter. The equivalent NIOSH 42
CFR 84 particulate filters are the N100, R100, and P100 filters.

Immediately dangerous to life or health (IDLH) means an atmosphere that poses an immediate
threat to life, would cause irreversible adverse health effects, or would impair an individual's
ability to escape from a dangerous atmosphere.

Loose-fitting face piece means a respiratory inlet covering that is designed to form a partial seal
with the face.

Negative pressure respirator (tight fitting) means a respirator in which the air pressure inside the
face piece is negative during inhalation with respect to the ambient air pressure outside the
respirator.

Oxygen deficient atmosphere means an atmosphere with an oxygen content below 19.5% by
volume.

Physician or other licensed health care professional (PLHCP) means an individual whose
legally permitted scope or practice (i.e., license, registration, or certification) allows him or her
to independently provide, or be delegated the responsibility to provide, some or all of the health
care services required by subsection (e).

Positive pressure respirator means a respirator in which the pressure inside the respiratory inlet
covering exceeds the ambient air pressure outside the respirator.

Powered air-purifying respirator (PAPR) means an air-purifying respirator that uses a blower to
force the ambient air through air-purifying elements to the inlet covering.

Pressure demand respirator means a positive pressure atmosphere-supplying respirator that
admits breathing air to the face piece when the positive pressure is reduced inside the face piece
by inhalation.

Qualitative fit test (QLFT) means a pass/fail fit test to assess the adequacy of respirator fit that
relies on the individual's response to the test agent.

Quantitative fit test (QNFT) means an assessment of the adequacy of respirator fit by
numerically measuring the amount of leakage into the respirator.

Respiratory inlet covering means that portion of a respirator that forms the protective barrier
between the user's respiratory tract and an air-purifying device or breathing air source, or both. It
may be a face piece, helmet, hood, suit, or a mouthpiece respirator with nose clamp.

Self-contained breathing apparatus (SCBA) means an atmosphere-supplying respirator for
which the breathing air source is designed to be carried by the user.
Respiratory Protection                                                                        Intro
©2011, Waste Management                                                                January 2011
RESPIRATORY PROTECTION PROGRAM


Service life means the period of time that a respirator, filter or sorbent, or other respiratory
equipment provides adequate protection to the wearer.

Supplied-air respirator (SAR) or airline respirator means an atmosphere-supplying respirator
for which the source of breathing air is not designed to be carried by the user.

Tight-fitting face piece means a respiratory inlet covering that forms a complete seal with the
face.

User seal check means an action conducted by the respirator user to determine if the respirator is
properly seated to the face.




Respiratory Protection                                                                        Intro
©2011, Waste Management                                                                January 2011
RESPIRATORY PROTECTION PROGRAM


Program: Respiratory Protection Program

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI96707



Respiratory Protection Program

This Respiratory Protection Program sets forth the policies and procedures implementing the
Cal/OSHA Respirator Standard [8 CCR § 5144] at Waimanalo Gulch Sanitary Landfill
(WGSL).

The Respiratory Protection Program Administrator is Joe Whelan OR Donny Carder. This
person is responsible for all facets of the program and has full authority to make necessary
decisions to ensure success of this program. His/her authority includes hiring personnel and
purchasing equipment necessary to implement and operate the program.

Respiratory Hazards and Respirator Selection

WGSL has conducted exposure monitoring and/or made reasonable estimation of potential
exposures to hazardous substances and their exposure limits in our workplace. We have selected
the following respiratory protection devices for routine operations, maintenance and other non-
routine activities, and variable situations.

Routine Operations

Work Area Operation    Chemical/Substance   PEL/STEL    Exposure Estimates       Respirator and
                                                                                   Cartridge




Respiratory Protection Program                                                         Page 1
©2011, Waste Management                                                       January 2011
RESPIRATORY PROTECTION PROGRAM




Respiratory Protection Program                                Page 2
©2011, Waste Management                              January 2011
RESPIRATORY PROTECTION PROGRAM


Maintenance and Other Non-Routine Tasks

Work Area Operation   Chemical/Substance   PEL/STEL      Exposure Estimates         Respirator and
                                                                                      Cartridge




Variable Situations

The Respirator Program Administrator will prepare a reasonable exposure estimate and select an
appropriate respirator based on the maximum, following protection factors: up to 10 X
PEL/STEL half-face air purifying; up to 50 X PEL/STEL full-face air purifying; and 50 X
PEL/STEL SCBA with pressure demand air supply.

Emergency Respirator Use

In the event of an emergency, the following respiratory protection will be used:

     Work Area/Operation               Chemical/Emergency                Respirator Required




Respiratory Protection Program                                                              Page 3
©2011, Waste Management                                                            January 2011
RESPIRATORY PROTECTION PROGRAM


Medical Evaluation

All employees who are assigned to wear respirators (except for employees who voluntarily use
filtering dust masks) will be provided and receive medical evaluation initially upon assignment
of the respiratory protection device and periodically thereafter as directed by a physician or other
licensed health care professional (PLHCP). Medical evaluations will be conducted using the
following procedures:

1) Employees will complete [Respirator Medical Evaluation Questionnaire--Appendix A]
   Assistance will be available, however WGSL will not review any of the information
   recorded on the form. We will provide the completed questionnaires to the PLHCP in a
   sealed envelope.
2) We will schedule employees for PLHCP examinations. The PLHCP will provide a
   completed Respirator User Medical Evaluation Report or its equivalent directly to the
   employer.
3) Employees will be assigned to respirator use positions based on the results of the medical
   evaluation.
4) Periodic medical evaluations will be based on Dr. TBD recommendation or whenever an
   employee answers questions 1 through 8 in Section 2 Part A of the Respirator Medical
   Evaluation Questionnaire positively.
5) The following items will be provided to the physician:
       a. The type and weight of the respirator to be used by the employee;
       b. The duration and frequency of respirator us;
       c. The expected physical work effort;
       d. Additional protective clothing and equipment to be worn;
       e. Temperature and humidity extremes that may be encountered; and
       f. A copy of this written program.

Fit-Testing

Respirators must fit properly to provide protection. If a tight seal is not maintained between the
face piece and the employee's face, contaminated air will be drawn into the face piece and be
inhaled by the employee. Fit testing seeks to protect the employee against inhaled contaminated
ambient air and is one of the core provisions of our respirator program.

In general, fit testing may be either qualitative or quantitative. Qualitative fit testing (QLFT)
involves the introduction of a gas, vapor, or aerosol test agent into an area around the head of the
respirator user. If that user can detect the presence of the test agent through subjective means,
such as odor, taste, or irritation, the respirator fit is inadequate.

In a quantitative respirator fit test (QNFT), the adequacy of respirator fit is assessed by
measuring the amount of leakage into the respirator, either by generating a test aerosol as a test
atmosphere, using ambient aerosol as a test agent, or using controlled negative pressure to
measure the volumetric leak rate. Appropriate instrumentation is required to quantify respirator
fit in QNFT.

Respiratory Protection Program                                                             Page 4
©2011, Waste Management                                                           January 2011
RESPIRATORY PROTECTION PROGRAM

Employees are fit tested at the following times with the same make, model, style, and size of
respirator that will be used:

   Before any of our employees are required to use any respirator with a negative or positive
   pressure tight-fitting face piece;
   Whenever a different respirator face piece (size, style, model, or make) is used;
   At least annually;
   Whenever the employee reports, or our company, PLHCP, supervisor, or Program
   Administrator makes visual observations of changes in the employee's physical condition that
   could affect respirator fit. Such conditions include, but are not limited to, facial scarring,
   dental changes, cosmetic surgery, or an obvious change in body weight; and
   When the employee, subsequently after passing a QLFT or QNFT, notifies the company,
   Program Administrator, supervisor, or PLHCP that the fit of the respirator is unacceptable.
   That employee will be retested with a different respirator face piece.

Employees must pass one of the following fit test types that follow the protocols and procedures:

   QLFT (Only used to fit test negative pressure air-purifying respirators that must achieve a fit
   factor of 100 or less. May be used to test tight-fitting atmosphere-supplying respirators and
   tight-fitting powered air-purifying respirators if tested in the negative pressure mode); or
   QNFT (May be used to fit test a tight-fitting half face piece respirator that must achieve a fit
   factor of 100 or greater OR a tight-fitting full face piece respirator that must achieve a fit
   factor of 500 or greater OR tight-fitting atmosphere-supplying respirators and tight-fitting
   powered air-purifying respirators if tested in the negative pressure mode).

Our workplace-specific fit testing procedures include the following:

Qualitative fit testing (QLFT)
Fit testing will be documented using [Employee Annual Respirator Fit-Test and Training
Record--Appendix B] on an annual basis.

Training

Employees who are assigned to wear respirators will be provided annual training at or about the
time of fit testing. This training will include the following elements:

   Why the respirator is necessary and how improper fit, usage, or maintenance can
   compromise the protective effect of the respirator;
   The limitations and capabilities of each respirator used;
   How to use the respirator effectively in emergency situations, including situations where the
   respirator malfunctions;
   How to inspect, don and remove, use, and check the seals of the respirator;
   The procedures for maintenance and storage of the respirator;


Respiratory Protection Program                                                            Page 5
©2011, Waste Management                                                          January 2011
RESPIRATORY PROTECTION PROGRAM

   Recognition of medical signs and symptoms that may limit or prevent the effective use of
   respirators;
   The general requirements of our company’s program and the standard.

This training will be repeated at least annually and will be documented using an Employee
Annual Respirator Fit-Test and Training Record.

Supplement training will be provided as necessary based on the following factors:
      Changes in the workplace or a new type of respirator;
      Demonstrated inadequacies in an employee’s knowledge or use of the respirator; or
      Any other situation in which retraining appears necessary to ensure safe respirator use.

Individuals using a tight-fitting respirator will be trained on [User Seal Check Procedures--
Appendix C].

Cleaning, Storage and Maintenance of Respirators

Routine-Use Respirators (individually assigned respirators)

We will provide supplies and parts necessary to assure proper sanitation and maintenance of any
respirator assigned to an individual employee.

Employees will keep their respirators clean and disinfected at all times. [Respirator Cleaning
Procedures--Appendix D].

Each respirator must be inspected before each use and during cleaning for proper functioning of
all parts and components:
1. A check of respirator function, tightness of connections, and the condition of the various
     parts including, but not limited to, the face piece, head straps, valves, connecting tube, and
     cartridges, canisters or filters; and
2. A check of elastic parts for pliability and signs of deterioration.

Non-Routine Use Respirator (emergency and non-individually assigned respirators).

WGSL will provide each respirator user with a respirator that is clean, sanitary, and in good
working order. Respirators will be cleaned and disinfected before being worn by different
individuals. Respirators maintained for emergency use will be cleaned and disinfected after each
use and respirators used in fit testing training will be cleaned and disinfected after each use.

Storage of Routine-Use Respirators

All respirators will be stored to protect them from damage, contamination, dust, sunlight,
extreme temperatures, excessive moisture, and damaging chemicals, and they will be packed or
stored to prevent deformation of the face piece and exhalation valve.



Respiratory Protection Program                                                             Page 6
©2011, Waste Management                                                           January 2011
RESPIRATORY PROTECTION PROGRAM


Storage of Emergency Respirators

Emergency respirators will be:

   Kept accessible to the work area;
   Stored in compartments or in covers that are clearly marked as containing emergency
   respirators;
   Stored in accordance with any applicable manufacture instructions;
   All respirators maintained for use in emergency situations will be inspected at least monthly
   and in accordance with the manufacture’s recommendations, and will be checked for proper
   function before and after each use;
   Emergency escape-only respirators will be inspected before being carried into the workplace
   for use; and
   Inspections are documented by a tag or written/electronic inspection record.

Inspection and Maintenance of Self-Contained Breathing Apparatus (SCBA)

SCBA devices (emergency and non-emergency) will be inspected monthly. Air and oxygen
cylinders will be maintained in a fully charged state and will be recharged when the pressure
falls to 90% of the manufacture’s recommended pressure level. WGSL will determine that the
regulator and warning devices function properly.

Air Quality for Self-Contained and Air Line Devices

  Compressed and liquid oxygen (if used) must meet the United State Pharmacopoeia
  requirements for medical or breathing oxygen.
  Compressed breathing air will meet at least the requirements for Grade D breathing air
  described in the ANSI/Compressed Gas Association Commodity Specification for
  Air, G-7.1-1989, including: oxygen content (v/v) of 19.5-23.5%; hydrocarbon (condensed)
  content of 5 milligrams per cubic meter of air or less; carbon monoxide (CO) content of 10
  ppm or less; carbon dioxide content of 1,000 ppm or less; and lack of noticeable odor.
  Compressed oxygen will not be used in atmosphere-supply respirators that have previously
  been used for compressed air.
  Oxygen concentrations greater than 23.5% are used only in equipment designed for oxygen
  service or distribution.
  Cylinders are tested and maintained as prescribed in the Shipping Container Specification
  Regulations of the Department of Transportation (49 CFR part 173 and part 178).
  Cylinders of purchased breathing air have a certificate of analysis from the supplier that the
  breathing air meets the requirements of Grade D breathing air.
  The moisture content in the cylinder does not exceed a dew point of -50 deg. F (-45.6 deg. C)
  at a 1-atmosphere pressure.



Respiratory Protection Program                                                          Page 7
©2011, Waste Management                                                        January 2011
RESPIRATORY PROTECTION PROGRAM

Compressor Systems

Compressors used to supply breathing air to respirators are constructed and situated so as to:
  Prevent entry of contaminated air into the air-supply systems.
  Minimize moisture content so that the dew point at 1 atmosphere pressure is 10 deg. F (-5.56
  deg. C) below the ambient temperature.
  Have suitable in-line air-purifying sorbent beds and filters to further ensure that the quality of
  breathing air is maintained by following the manufacturer's instructions.
  Have a tag maintained at the compressor that contains the most recent change date and the
  signature of the person authorized by the company to perform the change.
  For compressors that are not oil-lubricated, a means to assure that carbon monoxide levels in
  the breathing air do not exceed 10 ppm.
  For oil-lubricated compressors, a high-temperature or carbon monoxide alarm, or both, is used
  to monitor carbon monoxide levels. If only high-temperature alarms are used, the air supply
  will be monitored at intervals sufficient to prevent carbon monoxide in the breathing air from
  exceeding 10 ppm.
  Breathing air couplings are incompatible with outlets for non-respirable worksite air or other
  gas systems. No asphyxiating substance will be introduced into breathing air lines.
  Only breathing gas containers marked in accordance with the NIOSH respirator certification
  standard [42 CFR §84] are used.

Voluntary Respirator Use

Filtering Masks

Employees who use filtering masks in situations that do not otherwise require the use of a
respirator are not covered by this program.

Tight-fitting Respirators

Employees who use tight-fitting respirators when respirators are not otherwise required are
subject only to the following provisions of this program:
  Medical evaluation;
  Cleaning and sanitation;
  Storage; and
  [Information for Employees Using Respirators When Not Required Under the
  Standard--Appendix E]




Respiratory Protection Program                                                             Page 8
©2011, Waste Management                                                           January 2011
RESPIRATORY PROTECTION PROGRAM




Change Schedule

For vapor or gas air purifying respirators the two systems in place to warn respirator wearers of
contaminant breakthrough include using respirator cartridges equipped with an end-of-service
life indicator (ESLI) or using a cartridge replacement schedule based on manufacturer
breakthrough test data.

Employees using cartridges not equipped with ESLIs must replace cartridges in accordance with
the instruction. When air purifying respirators with cartridges are used the cartridges must be
changed out:
A minimum of every 30 days; or

Whenever an employee feels that they have become saturated and / or experiences breakthrough.
  At the beginning of each shift.
  At more frequent intervals.
  Air purifying cartridges absorb moisture and / or contaminants once they are exposed to the
  atmosphere. Respirators should not be stored with air purifying cartridges attached. Once
  opened, a package of cartridges should be considered reliable for one work shift (8 hours).

Protection for Particulates, Mists, and Fumes:

   Either atmosphere-supplying respirators or air purifying respirators with appropriate filters
   may be used for protection from particulates, mists, and fumes.

   When air purifying respirators with filters are used the filters must be changed out:
   Whenever an employee feels the filters have become clogged and / or experiences difficulty
   breathing.

For respirators worn exclusively for protection against particles, filters will be changed per the
manufacturer’s specification and whenever the wearer detects a change in breathing resistance.

Air supply unit will have filter replaced at manufacturer specified times and documented

Policy of Providing Respirators and Medical Evaluations at No Cost to the Employee

Employees will be provided respirators, medical evaluations and other requirements of the
respirator standard at no cost to them.

Annual Program Evaluation

An annual evaluation of the respirator program will be conducted by the WGSL. The evaluation
will be conducted by the Respirator Program Administrator and will consist of:


Respiratory Protection Program                                                             Page 9
©2011, Waste Management                                                           January 2011
RESPIRATORY PROTECTION PROGRAM


  A review of the written respiratory protection program to assure that it is up-to-date, effective
  and is being properly implemented;
  Observation to ensure that employees are using the respirators properly;
  Consultation with an employee representative to assess the employees' views on program
  effectiveness and to identify any problems;
  Checking respirator fit (including the ability to use the respirator without interfering with
  effective workplace performance);
  Checking appropriate respirator selection for the hazards to which employees are exposed;
  Requiring proper respirator use under the workplace conditions the employee encounters; and
  Proper respirator maintenance.

Any problems that are identified during this assessment will be corrected.

Periodic Evaluations will be documented using the [Periodic Respirator Program Evaluation
Form--Attachment F].




Respiratory Protection Program                                                          Page 10
©2011, Waste Management                                                          January 2011
RESPIRATORY PROTECTION PROGRAM



Recordkeeping

Compliance with the elements of the standard including medical evaluations, fit testing, training,
and periodic evaluation of the respirator program will be maintained for a minimum of three (3)
years.

The program will be located in the WGSL office.




Approved by:

Title:




__________________________________________
                 Print Name


___________________________________________
                  Signature


___________________________________________
                   Date




Respiratory Protection Program                                                         Page 11
©2011, Waste Management                                                         January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE

OSHA RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE (MANDATORY)

To the employer: Answers to questions in Section 1, and to question 9 in Section 2 of Part A, do not require a
medical examination.

To the employee:

Can you read (circle one): Yes/No

Your employer must allow you to answer this questionnaire during normal working hours, or at a time and place that
is convenient to you. To maintain your confidentiality, your employer or supervisor must not look at or review your
answers, and your employer must tell you how to deliver or send this questionnaire to the health care professional
who will review it.

Part A. Section 1. (Mandatory) The following information must be provided by every employee who has been
selected to use any type of respirator (please print).

1.   Today's Date: _________________________

2.   Your name: __________________________

3.   Your age (to nearest year) :______________

4.   Sex (circle one): Male/Female

5.   Your height: __________ ft. __________ in.

6.   Your weight: ____________ lbs.

7.   Your job title:_________________________

8.   A phone number where you can be reached by the health care professional who reviews this questionnaire
     (include the Area Code): ____________________

9.   The best time to phone you at this number: ________________

10. Has your employer told you how to contact the health care professional who will review this questionnaire
    (circle one): Yes/No

11. Check the type of respirator you will use (you can check more than one category):
    a. ______ N, R, or P disposable respirator (filter-mask, non- cartridge type only).
    b. ______ Other type (for example, half- or full-face piece type, powered-air purifying, supplied-air, self-
        contained breathing apparatus).

12. Have you worn a respirator (circle one): Yes/No

     If "yes," what type(s):
     __________________________________________________________________________________________

     __________________________________________________________________________________________

Part A. Section 2. (Mandatory) Questions 1 through 9 below must be answered by every employee who has been
selected to use any type of respirator (please circle "yes" or "no").

Respiratory Protection                                                                               Attachment A
©2011, Waste Management                                                                         January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE
1.   Do you currently smoke tobacco, or have you smoked tobacco in the last month: Yes/No

2. Have you ever had any of the following conditions?

     a.   Seizures (fits): Yes/No
     b.   Diabetes (sugar disease): Yes/No
     c.   Allergic reactions that interfere with your breathing: Yes/No
     d.   Claustrophobia (fear of closed-in places): Yes/No
     e.   Trouble smelling odors: Yes/No

3. Have you ever had any of the following pulmonary or lung problems?
    a. Asbestosis: Yes/No
    b. Asthma: Yes/No
    c. Chronic bronchitis: Yes/No
    d. Emphysema: Yes/No
    e. Pneumonia: Yes/No
    f. Tuberculosis: Yes/No
    g. Silicosis: Yes/No
    h. Pneumothorax (collapsed lung): Yes/No
    i. Lung cancer: Yes/No
    j. Broken ribs: Yes/No
    k. Any chest injuries or surgeries: Yes/No
    l. Any other lung problem that you've been told about: Yes/No

4.   Do you currently have any of the following symptoms of pulmonary or lung illness?
     a. Shortness of breath: Yes/No
     b. Shortness of breath when walking fast on level ground or walking up a slight hill or incline: Yes/No
     c. Shortness of breath when walking with other people at an ordinary pace on level ground: Yes/No
     d. Have to stop for breath when walking at your own pace on level ground: Yes/No
     e. Shortness of breath when washing or dressing yourself: Yes/No
     f. Shortness of breath that interferes with your job: Yes/No
     g. Coughing that produces phlegm (thick sputum): Yes/No
     h. Coughing that wakes you early in the morning: Yes/No
     i. Coughing that occurs mostly when you are lying down: Yes/No
     j. Coughing up blood in the last month: Yes/No
     k. Wheezing: Yes/No
     l. Wheezing that interferes with your job: Yes/No
     m. Chest pain when you breathe deeply: Yes/No
     n. Any other symptoms that you think may be related to lung problems: Yes/No

5.   Have you ever had any of the following cardiovascular or heart problems?
     a. Heart attack: Yes/No
     b. Stroke: Yes/No
     c. Angina: Yes/No
     d. Heart failure: Yes/No
     e. Swelling in your legs or feet (not caused by walking): Yes/No
     f. Heart arrhythmia (heart beating irregularly): Yes/No
     g. High blood pressure: Yes/No
     h. Any other heart problem that you've been told about: Yes/No

6.   Have you ever had any of the following cardiovascular or heart symptoms?
     a. Frequent pain or tightness in your chest: Yes/No
     b. Pain or tightness in your chest during physical activity: Yes/No
     c. Pain or tightness in your chest that interferes with your job: Yes/No
Respiratory Protection                                                                              Attachment A
©2011, Waste Management                                                                        January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE
     d.   In the past two years, have you noticed your heart skipping or missing a beat: Yes/No
     e.   Heartburn or indigestion that is not related to eating: Yes/ No
     f.   Any other symptoms that you think may be related to heart or circulation problems: Yes/No

7.   Do you currently take medication for any of the following problems?
     a. Breathing or lung problems: Yes/No
     b. Heart trouble: Yes/No
     c. Blood pressure: Yes/No

     d.   Seizures (fits): Yes/No

8.   If you've used a respirator, have you ever had any of the following problems? (If you've never used a respirator,
     check the following space and go to question 9:)
     a. Eye irritation: Yes/No
     b. Skin allergies or rashes: Yes/No
     c. Anxiety: Yes/No
     d. General weakness or fatigue: Yes/No
     e. Any other problem that interferes with your use of a respirator: Yes/No

9.   Would you like to talk to the health care professional who will review this questionnaire about your answers to
     this questionnaire: Yes/No

     Questions 10 to 15 below must be answered by every employee who has been selected to use either a full-face
     piece respirator or a self-contained breathing apparatus (SCBA). For employees who have been selected to use
     other types of respirators, answering these questions is voluntary.

10. Have you ever-lost vision in either eye (temporarily or permanently): Yes/No

11. Do you currently have any of the following vision problems?
    a. Wear contact lenses: Yes/No
    b. Wear glasses: Yes/No
    c. Color blind: Yes/No
    d. Any other eye or vision problem: Yes/No

12. Have you ever had an injury to your ears, including a broken ear drum: Yes/No

13. Do you currently have any of the following hearing problems?
    a. Difficulty hearing: Yes/No
    b. Wear a hearing aid: Yes/No
    c. Any other hearing or ear problem: Yes/No

14. Have you ever had a back injury: Yes/No

15. Do you currently have any of the following musculoskeletal problems?
    a. Weakness in any of your arms, hands, legs, or feet: Yes/No
    b. Back pain: Yes/No
    c. Difficulty fully moving your arms and legs: Yes/No
    d. Pain or stiffness when you lean forward or backward at the waist: Yes/No
    e. Difficulty fully moving your head up or down: Yes/No
    f. Difficulty fully moving your head side to side: Yes/No
    g. Difficulty bending at your knees: Yes/No
    h. Difficulty squatting to the ground: Yes/No
    i. Climbing a flight of stairs or a ladder carrying more than 25 lbs.: Yes/No
    j. Any other muscle or skeletal problem that interferes with using a respirator: Yes/No

Respiratory Protection                                                                                Attachment A
©2011, Waste Management                                                                          January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE
Part B Any of the following questions, and other questions not listed, may be added to the questionnaire at the
discretion of the health care professional who will review the questionnaire.

1.   In your present job, are you working at high altitudes (over 5,000 feet) or in a place that has lower than normal
     amounts of oxygen: Yes/No


     If "yes," do you have feelings of dizziness, shortness of breath, pounding in your chest, or other symptoms
     when you're working under these conditions: Yes/No

2.   At work or at home, have you ever been exposed to hazardous solvents, hazardous airborne chemicals (e.g.,
     gases, fumes, or dust), or have you come into skin contact with hazardous chemicals: Yes/No

     If "yes," name the chemicals if you know them:
     __________________________________________________________________________________________

     __________________________________________________________________________________________

     __________________________________________________________________________________________

3.   Have you ever worked with any of the materials, or under any of the conditions, listed below:
     a. Asbestos: Yes/No
     b. Silica (e.g., in sandblasting): Yes/No
     c. Tungsten/cobalt (e.g., grinding or welding this material): Yes/No
     d. Beryllium: Yes/No
     e. Aluminum: Yes/No
     f. Coal (for example, mining): Yes/No
     g. Iron: Yes/No
     h. Tin: Yes/No
     i. Dusty environments: Yes/No
     j. Any other hazardous exposures: Yes/No

         If "yes," describe these exposures:
         ______________________________________________________________________________________

     __________________________________________________________________________________________

     __________________________________________________________________________________________

4.   List any second jobs or side businesses you have: _________________________________________________

     __________________________________________________________________________________________

5.   List your previous occupations:
     __________________________________________________________________________________________

     __________________________________________________________________________________________

6.   List your current and previous hobbies: __________________________________________________________

     __________________________________________________________________________________________

7.   Have you been in the military services? Yes/No

  If "yes," were you exposed to biological or chemical agents (either in training or combat): Yes/No
Respiratory Protection                                                                             Attachment A
©2011, Waste Management                                                                           January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE
8.   Have you ever worked on a HAZMAT team? Yes/No

9.   Other than medications for breathing and lung problems, heart trouble, blood pressure, and seizures mentioned
     earlier in this questionnaire, are you taking any other medications for any reason (including over-the-counter
     medications): Yes/No

     If "yes," name the medications if you know them:________________________________

10. Will you be using any of the following items with your respirator(s)?
    a. HEPA Filters: Yes/No
    b. Canisters (for example, gas masks): Yes/No
    c. Cartridges: Yes/No

11. How often are you expected to use the respirator(s) (circle "yes" or "no" for all answers that apply to you)?:
    a. Escape only (no rescue): Yes/No
    b. Emergency rescue only: Yes/No

     c.   Less than 5 hours per week: Yes/No
     d.   Less than 2 hours per day: Yes/No
     e.   2 to 4 hours per day: Yes/No
     f.   Over 4 hours per day: Yes/No

12. During the period you are using the respirator(s), is your work effort:
    a. Light (less than 200 kcal per hour): Yes/No

     If "yes," how long does this period last during the average shift:____________hrs.____________mins.
     Examples of a light work effort are sitting while writing, typing, drafting, or performing light assembly work; or
     standing while operating a drill press (1-3 lbs.) or controlling machines.

     b.   Moderate (200 to 350 kcal per hour): Yes/No

          If "yes," how long does this period last during the average shift:____________hrs.____________mn.
          Examples of moderate work effort are sitting while nailing or filing; driving a truck or bus in urban traffic;
          standing while drilling, nailing, performing assembly work, or transferring a moderate load (about 35 lbs.)
          at trunk level; walking on a level surface about 2 mph or down a 5-degree grade about 3 mph; or pushing a
          wheelbarrow with a heavy load (about 100 lbs.) on a level surface.

     c.   Heavy (above 350 kcal per hour): Yes/No

          If "yes," how long does this period last during the average shift:____________hrs.____________mn.
          Examples of heavy work are lifting a heavy load (about 50 lbs.) from the floor to your waist or shoulder;
          working on a loading dock; shoveling; standing while bricklaying or chipping castings; walking up an 8-
          degree grade about 2 mph; climbing stairs with a heavy load (about 50 lbs.).

13. Will you be wearing protective clothing and/or equipment (other than the respirator) when you're using your
    respirator: Yes/No

     If "yes," describe this protective clothing and/or equipment: _______________________________________

     _______________________________________________________________________________________

14. Will you be working under hot conditions (temperature exceeding 77 deg. F): Yes/No

15. Will you be working under humid conditions: Yes/No
Respiratory Protection                                                                                   Attachment A
©2011, Waste Management                                                                            January 2011
RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE
16. Describe the work you'll be doing while you're using your respirator(s):
    __________________________________________________________________________________________

    __________________________________________________________________________________________

17. Describe any special or hazardous conditions you might encounter when you're using your respirator(s) (for
    example, confined spaces, life-threatening gases):
    __________________________________________________________________________________________

    __________________________________________________________________________________________

    1.   Provide the following information, if you know it, for each toxic substance that you'll be exposed to when
         you're using your respirator(s):

    Name of the first toxic substance: _____________________________________

    Estimated maximum exposure level per shift:

    _____________________________________

    Duration of exposure per shift:

    ___________________________________________________________________

    Name of the second toxic substance: _____________________________________

    Estimated maximum exposure level per shift:
    ___________________________________________________________________

    Duration of exposure per shift:
    ___________________________________________________________________

    Name of the third toxic substance:
    ___________________________________________________________________

    Estimated maximum exposure level per shift:
    ___________________________________________________________________

    Duration of exposure per shift:
    ___________________________________________________________________

    The name of any other toxic substances that you'll be exposed to while using your
    respirator:_________________________________________________________________________________

    __________________________________________________________________________________________

    __________________________________________________________________________________________

19. Describe any special responsibilities you'll have while using your respirator(s) that may affect the safety and
    well being of others (for example, rescue, security):
    __________________________________________________________________________________________

    ___________________________________________________________________________

Respiratory Protection                                                                               Attachment A
©2011, Waste Management                                                                         January 2011
EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD



District Name:       ___________________________________________________



Employee Name:       ___________________________________________________


Occupation/Job:      ___________________________________________________

Respirator Use Information
Work Area(s)
_____________________________________________________________________


_____________________________________________________________________

    Exposure Conditions

     Chemicals                                     Exposure Estimate and PEL/STEL




Emergency Use of Respirators (Member of HAZMAT Team)
   Yes                       No

Type(s) of Respirator Used
   Voluntary air purifying (     half-face or    full-face)
   Half-face air purifying
   Full-face air purifying
   Self-contained breathing apparatus (pressure demand)
   Airline breathing apparatus (pressure demand)
   Other; specify what type: ___________________________________________

Air Purifying Cartridges Used

     Contaminant                                   Cartridge Name and Color Code




Respiratory Protection                                                                 Attachment B
©2005, Waste Management                                                            January 1, 2005
EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD



Fit-Testing Record
Fit-test Protocol Used (indicate each used if more than one)
    Qualitative; Test Substance:
____________________________________________________________
    Other:
____________________________________________________________
    Quantitative; Test Method:
____________________________________________________________
    Other:
____________________________________________________________


    Respirator(s) Successfully Fitted

             Type of Respirator                   Brand                    Model                   Size
             Half-face air purifying
             Full-face air purifying
             Self-contained breathing apparatus
             Supplied-air breathing apparatus
             Other, specify:

Fit Test Certification
Respirator fit testing for the devices indicated in was successfully completed.

Employee:         ________________________________________


Signature: ________________________________________________                       Date: _______________________

Tester:           ________________________________________


Signature: ________________________________________________                       Date: _______________________




Respiratory Protection                                                                               Attachment B
©2005, Waste Management                                                                          January 1, 2005
EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD




Training Record

Training Subjects Covered
   Purpose and conditions of respirator use (nature and concentrations of air contaminants known or anticipated).
   Requirements for use--when respirator(s) are required.
   How the device operates--its components and their maintenance.
   Respirator inspection and cleaning procedures and employee obligation for cleaning and maintenance as
   applicable.
   Chemical cartridge selection criteria, change out frequency and warning signs for break-through and other
   failures. Instruction to terminate exposure if a problem is detected. [If air-supplied or self-contained, the air
   supply (pressure gauge) and low pressure alarm should be described and demonstrated.]
   How to properly don each respirator to be used.
   How to conduct self-seal check and that this is mandatory upon each use.
   An explanation of fit-testing procedures.
   An explanation of medical surveillance and procedures.
   Other warnings and precautions as set forth in the manufacturer's instruction, including emphasis that air-
   purifying respirators do not supply breathing air and must not be used in an oxygen-deficient atmosphere.

Training Certification

Training in all of the above topics was successfully completed.


Employee:        ________________________________________


Signature: ________________________________________________                      Date: _______________________


Trainer:         ________________________________________


Signature: ________________________________________________                      Date: _______________________




Respiratory Protection                                                                                    Attachment B
©2005, Waste Management                                                                              January 1, 2005
USER SEAL CHECK

Appendix B-1. to Section 5144: User Seal Check Procedures (Mandatory)




The individual who uses a tight-fitting respirator is to perform a user seal check to ensure that an
adequate seal is achieved each time the respirator is put on. Either the positive and negative
pressure checks listed in this appendix, or the respirator manufacturer's recommended user seal
check method will be used. User seal checks are not substitutes for qualitative or quantitative fit
tests.

Face piece Positive and/or Negative Pressure Checks.

1. Positive pressure check. Close off the exhalation valve and exhale gently into the face piece.
   The face fit is considered satisfactory if a slight positive pressure can be built up inside the
   face piece without any evidence of outward leakage of air at the seal. For most respirators
   this method of leak testing requires the wearer to first remove the exhalation valve cover
   before closing off the exhalation valve and then carefully replacing it after the test.

2. Negative pressure check. Close off the inlet opening of the canister or cartridge(s) by
   covering with the palm of the hand(s) or by replacing the filter seal(s), inhale gently so that
   the face piece collapses slightly, and hold the breath for ten seconds. The design of the inlet
   opening of some cartridges cannot be effectively covered with the palm of the hand. The test
   can be performed by covering the inlet opening of the cartridge with a thin latex or nitrile
   glove. If the face piece remains in its slightly collapsed condition and no inward leakage of
   air is detected, the tightness of the respirator is considered satisfactory.

   Manufacturer's Recommended User Seal Check Procedures. The respirator manufacturer's
   recommended procedures for performing a user seal check may be used instead of the
   positive and/or negative pressure check procedures provided that the employer demonstrates
   that the manufacturer's procedures are equally effective.




Respiratory Protection                                                                 Attachment C
©2005, Waste Management                                                           January 1, 2005
RESPIRATOR CLEANING PROCEDURES


Appendix B-2. to Section 5144: Respirator Cleaning Procedures (Mandatory)
Guide to Respiratory Protection at Work
These procedures are provided for employer use when cleaning respirators. They are general in
nature, and the employer as an alternative may use the cleaning recommendations provided by
the manufacturer of the respirators used by their employees, provided such procedures are as
effective as those listed here in Appendix B-2. Equivalent effectiveness simply means that the
procedures used must accomplish the objectives set forth in Appendix B-2, i.e., must ensure that
the respirator is properly cleaned and disinfected in a manner that prevents damage to the
respirator and does not cause harm to the user.

Procedures for Cleaning Respirators.
1. Remove filters, cartridges, or canisters. Disassemble face pieces by removing speaking
   diaphragms, demand and pressure-demand valve assemblies, hoses, or any components
   recommended by the manufacturer. Discard or repair any defective parts.

2. Wash components in warm (43 deg. C [110 deg. F] maximum) water with a mild detergent or
   with a cleaner recommended by the manufacturer. A stiff bristle (not wire) brush may be
   used to facilitate the removal of dirt.

3. Rinse components thoroughly in clean, warm (43 deg. C [110 deg. F] maximum), preferably
   running water. Drain.

4. When the cleaner used does not contain a disinfecting agent, respirator components should be
   immersed for two minutes in one of the following:

5. Hypochlorite solution (50 ppm of chlorine) made by adding approximately one milliliter of
   laundry bleach to one liter of water at 43 deg. C (110 deg. F); or,

6. Aqueous solution of iodine (50 ppm iodine) made by adding approximately 0.8 milliliters of
   tincture of iodine (6-8 grams ammonium and/or potassium iodide/100 cc of 45% alcohol) to
   one liter of water at 43 deg. C (110 deg. F); or,

7. Other commercially available cleansers of equivalent disinfectant quality when used as
   directed, if their use is recommended or approved by the respirator manufacturer.

8. Rinse components thoroughly in clean, warm (43 deg. C [110 deg. F] maximum), preferably
   running water. Drain. The importance of thorough rinsing cannot be overemphasized.
   Detergents or disinfectants that dry on face pieces may result in dermatitis. In addition, some
   disinfectants may cause deterioration of rubber or corrosion of metal parts if not completely
   removed.

9. Components should be hand-dried with a clean lint-free cloth or air-dried.

10. Reassemble face piece, replacing filters, cartridges, and canisters where necessary.

   Test the respirator to ensure that all components work properly.
Respiratory Protection                                                                Attachment D
©2005, Waste Management                                                          January 1, 2005
INFORMATION FOR EMPLOYEES USING RESPIRATORS WHEN NOT
                                                       REQUIREDUNDER THE STANDAR


Appendix D to Section 5144: (Mandatory) Information for Employees Using Respirators
When Not Required Under the Standard




Respirators are an effective method of protection against designated hazards when properly
selected and worn. Respirator use is encouraged even when exposures are below the exposure
limit, to provide an additional level of comfort and protection for workers. However, if a
respirator is used improperly or not kept clean, the respirator itself can become a hazard to the
worker. Sometimes, workers may wear respirators to avoid exposures to hazards, even if the
amount of hazardous substance does not exceed the limits set by OSHA standards. If your
employer provides respirators for your voluntary use, or if you provide your own respirator, you
need to take certain precautions to be sure that the respirator itself does not present a hazard.
You should do the following:

1. Read and heed all instructions provided by the manufacturer on use, maintenance, cleaning
   and care, and warnings regarding the respirators limitations.

2. Choose respirators certified for use to protect against the contaminant of concern. NIOSH,
   the National Institute for Occupational Safety and Health of the U.S. Department of Health
   and Human Services, certifies respirators. A label or statement of certification should appear
   on the respirator or respirator packaging. It will tell you what the respirator is designed for
   and how much it will protect you.

3. Do not wear your respirator into atmospheres containing contaminants for which your
   respirator is not designated to protect against. For example, a respirator designed to filter dust
   particles will not protect you against gases, vapors or very small solid particles of fumes or
   smoke.

4. Keep track of your respirator so that you do not mistakenly use someone else's respirator.




Respiratory Protection                                                               Attachment E
©2005, Waste Management                                                            January 1, 2005
PERIODIC RESPIRATOR PROGRAM EVALUATION

Person Performing Evaluation: ________________________________________

Program Administrator:           ________________________________________

Date of Last Evaluation: ____/_____/______                            Date of This Evaluation: ____/_____/_______

Review of Written Program

    Is written program up-to-date?
        Yes        No If no, what changes are needed?
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Have there been any changes in respirator use or exposure conditions since the last review?
       Yes        No If yes, summarize the changes:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Are all personnel responsible for the respirator program properly listed?
             Yes       No If no, what changes should be made?
    _________________________________________________________________________________________
    _________________________________________________________________________________________

Observation of Respirator-using Employees

    When asked, are employees satisfied and comfortable with respirator use and the employer's program?
           Yes       No If no, what problems need to be corrected?
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Are respirators in use, properly fitted (check for obvious poor fits, facial hair, other interferences)?
            Yes         No If no, fit-testing should be required:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Are respirators in use, appropriate for exposure conditions and required work?
            Yes         No If no, what problems should be corrected?
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Are respirators in use, fitted with the proper cartridges?
            Yes         No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________




Respiratory Protection                                                                                Attachment F
©2005, Waste Management                                                                             January 1, 2005
PERIODIC RESPIRATOR PROGRAM EVALUATION


    Are respirators in use, properly maintained in terms of sanitation, parts in place, etc.?
            Yes         No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

Respirators In Storage

    Are all respirators in storage in sealed plastic bags and properly stored?
             Yes         No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    If an emergency device, is the unit being inspected monthly, and is this inspection specifically documented with
         a tag or otherwise?
             Yes        No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Are all SCBA air tanks on devices not in use and tanks in storage filled to 90% of capacity?
             Yes      No If no:
    __________________________________________________________________________________________
    __________________________________________________________________________________________

Documentation Review

    Are records available indicating initial and/or respirator fit-testing and training for all users within the past 12
        months?
            Yes        No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________


    Are there initial medical evaluation documents for all employees who use respirators?
            Yes        No If no:
    _________________________________________________________________________________________
    _________________________________________________________________________________________

    Is there a need for more frequent periodic evaluations for any employee or group of employees?
              Yes       No If yes:
    _________________________________________________________________________________________
    _________________________________________________________________________________________




Signed: __________________________________________________                    Date: __________________________


Respiratory Protection                                                                                Attachment F
©2005, Waste Management                                                                             January 1, 2005
RESPIRATORY PROTECTION BASED ON HISTORICAL
                                                                          AIR MONITORING

Note: Evaluate All Operations Not Listed Below And Those Utilizing Technology Applied
      Developed After June 1998


               OPERATION                          HAZARD ASSESSED              RESPIRATORY          RESPIRATORY
                                                                               PROTECTION            PROTECTION
                                                                                REQUIRED            NOT REQUIRED
Hauling
Driver - Special Wastes                               new materials                                          X
Driver - Asbestos                                       as needed                                            X
Dusts                                                                                                        X
Landfill / Transfer
Driver site truck                                       dust/silica                                         X
Driver water truck                                      dust/silica                                         X
Gas plant / gas recovery                                                                                     X
Laboratory personnel                                methylene chloride                 NA                   NA
Loaders - transfer / tipping                            dust/silica                                         X
Operator compactor                                                                     NA                   NA
Operator landfill equipment                            dust/silica                                          X
Spotter - transfer / tipping                           dust/silica                                          X
Operator track loader/transfer                   new methods (non-friable             NA                    NA
                                                        asbestos)
Maintenance
Mechanic - hauling                                 lead in old container paint                                  X
  Container Repair
Mechanic - hauling                               fume, copper electrodes inside            X
  Truck Body Repair                                          bodies
   (inside truck bodies)
Painter - Water Reducible Paint                                                                                 X
Painter - Solvent based Paint                               solvents                       X
Mechanic -landfill                                                                                              X
Mechanic - MRF                                                                                                  X
Material Recovery Facility
Baler operator                                                dusts                       NA                   NA
Forklift/bobcat operator                                      dusts                                             X
Sorters - Recycle Line                                        dusts                       NA                   NA
Sorters - Commingle MRF                                       dusts                                             X
Ticket collector MRF                                       dusts/silica                                         X
Note:
     Data collected in over ten years of monitoring routine, non-routine and “worst case” workplace exposures show
     results of airborne concentrations of dusts, mists, fumes, vapors and gases are routinely below 10% of their
     respective PELs.
     Exposures may exceed action levels or PELs from solvent based paint, carbon arc welding inside truck bodies, and in
     dusty areas where high levels of airborne road dust contain 10% silica sand (on some landfill haul roads and on some
     tipping floors).
     Continue to assess non-routine operations and new methods to ensure sampling results are representative, adequate
     engineering controls are in place and proper PPE is selected.
     NA=SUFFICIENT DATA TO EVALUATE NOT AVAILABLE

Respiratory Protection                                                                           Attachment G
©2005, Waste Management                                                                        January 1, 2005
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM


Program: Industrial Lift Truck (Forklift)

Facility: Waimanalo Gulch Sanitary Landfill

Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707



PURPOSE

This program defines the safety requirements and responsibilities for operating forklifts and
powered industrial trucks. Safe use of industrial trucks prevents injuries, property damage, and
excessive maintenance.

The powered industrial trucks program contains method for complying with company and
regulatory requirements and explains the who, what, when, where, and how of implementing the
powered industrial trucks program.


Nameplates and Markings

   Label, or identify with a marking, all powered industrial trucks approved in a nationally
   recognized testing laboratory (DS, DY, EE and EX).
   Maintain all nameplates in legible condition and ensure they are firmly affixed to the
   powered industrial truck.
   If the powered industrial truck is equipped with front-end attachments other than factory
   installed attachments, which is approved by the manufacturer, have the truck marked to
   identify the attachments and show the approximate weight of the truck and attachment
   combination.


Inspections

   Inspect all powered industrial trucks before placing them in service.
   Do not place a truck into service if the truck inspection shows any condition that could
   adversely affect the safety of the vehicle.
   Perform an inspection of each powered industrial truck at the start of each work shift. The
   pre-operation inspection should determine the condition of the vehicle or mobile unit before
   operation by the next employee. Any damage must be noted and reported to the supervisor.
   Document all inspections. Inspect the controls, brakes, tires, load-engaging mechanism; lift
   systems, steering mechanism, lights, horn, oil and water. Keep an inspection and repair
   record for each truck.



INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                Page 1
©2011, Waste Management                                                           January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM

   Safely move any powered industrial trucks to an out of the way, safe location until repaired,
   and label it “Out-of-service, do not operate”. Caution: Moving a vehicle with an identified
   brake problem could be a safety issue.
   Inspect each industrial truck before each shift. Report and correct any defects as needed
   before using again.



Training

Train employees expected to operate a powered industrial truck, forklift, and hand-powered
trucks. Establish a facility training program to train and certify powered industrial truck
operators in the safe operation of powered industrial trucks and forklifts.

The following is a list of required subjects to cover in employee/operator training that shall
consist of formal classroom instruction, practical instruction (instructor demonstrations) and
practical exercises:

   Truck related topics shall include:
   Operating instructions, warnings and precautions for the type of truck used.
   Differences between the truck and an automobile.
   Truck controls and instrumentation, where located and how they work.
   Engine or motor operation.
   Steering and maneuvering.
   Visibility including restrictions when loaded.
   Fork and attachment adaptation.
   Vehicle capacity and vehicle stability.
   Vehicle inspection and maintenance that the operator must perform.
   Refueling, charging or recharging batteries.
   Operating limitations and other instructions or warnings peculiar to the vehicle.
   Work related topics.
   Surface conditions where the vehicle will be operated.
   Composition and stability of loads to be moved.
   Load manipulation, stacking and unstacking.
   Pedestrian traffic in the vehicle operating area.
   Narrow aisles or other restricted areas.
   Hazardous areas of operation.
   Ramps and other sloped surfaces.
   Environments where exhaust gases could build-up.
   Other unique or potentially hazardous environments.

In addition the requirements of 29 CFR 1910.178 must be covered in the training.

Supervisor training should cover the following:
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                  Page 2
©2011, Waste Management                                                             January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM


   Employee/operator training program.
   Attention to clearances, load restrictions, additional safety factors.
   Reporting of industrial lift truck problems.


Evaluate and certify employees upon completion of training. Provide written training
certification that includes the name of the operator, the date of training, the date of the
evaluation, and the name(s) of the person performing the training and evaluation.



Refresher Training

Refresher training shall be provided to the operator when:
   The operator is observed operating in an unsafe manner.
   The operator is involved in an accident or near-miss incident.
   An operator evaluation reveals deficiencies in operating techniques, skills or practices.
   The operator is assigned a different type vehicle.
   Workplace conditions change so as to affect the safe operation of the truck.


Out of Service Criteria

Take any powered industrial truck out of service that is found to be in need of repair, defective or
in any way unsafe, until it has been restored to a safe operating condition. “Out of Service”
criteria include items affecting the safety of the truck (for example, non-functional back-up
alarms, broken rollover bars or worn brakes). Lock or tag the truck out of operation.




Maintenance

   If at any time a powered industrial truck is found to be in need of repair, defective, or in any
   way unsafe, take it out of service and label “Out-of-service” until it has been restored to safe
   operating condition.
   Ensure that all repairs are made only by facility authorized personnel.
   Ensure that any repairs to the fuel and ignition systems of powered industrial trucks are conducted only in
   locations designated by the facility safety coordinator for these types of repairs.
   Disconnect the battery before making electrical system repairs to the trucks.
   Replace any parts only with parts meeting the safety requirements of the original part.




INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                           Page 3
©2011, Waste Management                                                                      January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



   Do not provide additional counterweighing of fork trucks unless approved by the powered
   industrial truck manufacturer in writing.
   When the temperature of any part of any powered industrial truck is found to be in excess of
   its normal operating temperature, remove the vehicle from service and tag “Out-of-service”.
   Do not return it to service until the cause of the overheating has been eliminated.
   Keep powered industrial trucks in a clean condition; free of dust, excess oil, and grease.




Seat Belts

Equip all vehicles that have rollover bars with seat belts and if it is a modification to install the
seat belts, obtain manufacturers approval in writing. It is required that seat belts be worn at all
times when operating a forklift or powered industrial truck equipped with seat belts.


Powered Industrial Truck Operations

Follow these safety requirements:

1. Do not allow persons to stand or pass under the elevated portion of any truck, loaded or
   empty.
2. Do not permit unauthorized personnel to ride on powered industrial trucks.
3. Set the forks to the maximum possible spread for each load to be carried.
4. Keep arms or legs inside the running lines of the truck. Do not place arms and legs between
   the uprights of the masts.

5. When a powered industrial truck is left unattended, fully lower the load engaging means,
    neutralize the controls, shut the power off, and set the brakes. It is a recommended practice to
    chock the wheels when the powered industrial truck is parked on an incline. A powered
    industrial truck is considered to be “unattended” when the vehicle is in view of the operator
    but the operator is more than 25 feet from the vehicle, or whenever the operator leaves the
    vehicle, and it is not in his or her view.
6. Keep at least two feet away from the edge of the ramps or platforms.
7. When loading and unloading a trailer, set the brakes (if coupled to the truck), and place
    chocks under the rear wheels to prevent the trailer from moving.
8. When the trailer is not coupled to the truck, use fixed jacks to support the trailer and prevent
    upending during loading or unloading.
9. Ensure that there is sufficient headroom under overhead installations, lights, entranceways,
    etc.
10. Use an overhead guard, where overhead lifting is performed, to protect against falling
    objects. The guard offers protection from impact from small packages, boxes, bagged
    material, etc.

INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                      Page 4
©2011, Waste Management                                                                 January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



11. Use a load backrest extension to minimize the possibility of part, or the entire load, falling
    rearward.
12. Slow down and sound the horn at cross aisles, corners and other locations where vision is
    obstructed.
13. Make certain the back-up alarm is in good, working order.
14. When the load being carried forward obstructs the view, turn around the forklift and travel
    with the load trailing.
15. Always look in the direction of travel.
16. Ascend or descend grades slowly. When ascending or descending slope grades in excess of
    ten percent, drive loaded trucks with the load upgrade. On all grades, tilt back and raise the
    load and load engaging means only as far as necessary to clear the road surface.
17. Properly secure dockboards or bridge plates before driving over them.
18. Slow down for wet and slippery floors.
19. Establish speed limits, where necessary, and post speed limit signs.
20. Define and mark designated travel routes.




Loading

Handle only stable and safely arranged loads. Exercise caution when handling off-center loads
that cannot be centered. Loads must not exceed the rated capacity of the truck. When carrying
loads, place the load engaging means under the load as far as possible and carefully tilt the mast
backward to stabilize the load. Carry the load as close to the floor as possible. When traveling
with a load, start and stop trucks gradually, and always look around before starting to move.

If loading or unloading a trailer connected to a vehicle, all of the following precautions must be
taken:

   Turn the vehicle engine off.
   Set the brakes of highway trucks and chock the rear wheels to prevent the trucks from rolling
   while they are boarded with powered industrial trucks.
   Set brakes and put wheel blocks in place to prevent movement of trucks, trailers, or railroad
   cars while loading or unloading. Fixed jacks may be necessary to support a semi trailer
   during loading or unloading when the trailer is not coupled to a tractor. Check the flooring of
   trucks, trailers, and railroad cars for breaks and weakness before they are driven onto.
   Secure dockboard or bridgeplates before they are driven over.
   Carefully and slowly drive over dockboard or bridgeplates and never exceed their rated
   capacity.
   Handle only stable or safely arranged loads. Use caution when handling off-center loads,
   which cannot be centered.
   Handle only loads within the rated capacity of the truck.

Also take at least one of the following precautions:
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                   Page 5
©2011, Waste Management                                                              January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM




   Place the vehicle’s ignition key in the possession of the person boarding the vehicle or trailer.
   Place the vehicle’s ignition key in a “lock box” and give the person boarding the vehicle
   possession of the “lock box” key.
   Actively secure the vehicle or trailer to a loading dock with a device that prevents powered or
   unpowered vehicle movement. The person boarding the vehicle or trailer must solely control
   the device. Note: if this option is used, tire chocks are not required.


Hazards

When operating lift trucks, the primary danger is colliding or overturning the truck. Always be
aware of obstacles in the path of the truck, especially when backing up. Make sure there is
enough clearance between the truck and other objects. When on a ramp or platform, stay at least
two feet from the edge. Lift trucks can be overturned if they are not handled correctly on steep
grades or if they are driven off the sides of platforms or ramps. Movement or collapse of bridge
plates or dockboards causes another hazardous condition.
Ensure that bags, cartons, boxes or other articles are secure. If these items fall from lift vehicles,
they can cause severe injuries to the truck drivers and pedestrians, and financial loss due to
damage.


Battery Charging

Only trained and authorized employees may change and/or charge batteries.
Wear acid-resistant clothing, acid-resistant gloves, goggles and a face shield when changing the
electrolyte solution in the battery.

Charge or install batteries only in areas designated for this purpose. These areas have facilities
for flushing and neutralizing spilled electrolytes, fire protection, protecting charging apparatus
from damage from lift trucks, ventilation to reduce the potential for hydrogen gas buildup, and
emergency drenching facilities.

When charging batteries, require these safe work practices:

   Put on personal protective equipment.
   Properly position lift trucks, and apply brakes before charging.
   Use a carboy, tilter or siphon for handling the electrolyte.
   Pour acid into water. Do not pour water into acid.
   Open the battery compartments/covers to dissipate heat.
   Ensure that the vent caps are functioning.
   Designate the charging area as a “No Smoking” area and post signs.
   Take precautions to prevent open flames, sparks, or electric arcs in the charging area.
   Keep tools and other metallic objects away from the top of uncovered batteries.
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                     Page 6
©2011, Waste Management                                                                January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



Gasoline, Diesel and Liquefied Petroleum Gas Vehicles

Gasoline, diesel or liquefied petroleum gas-powered trucks have the potential to catch fire if
repaired or refueled incorrectly. Only trained authorized personnel are permitted to refuel or
repair these trucks.
Powered industrial trucks that use gas or diesel have internal combustion engines. The exhaust
from combustion engines contains carbon monoxide, which is a chemical asphyxiant. Only use
this equipment in areas where there is good ventilation.



Fuel Storage

The storage and handling of liquid fuels such as gasoline and diesel fuel must be in accordance
with NFPA Flammable and Combustible Liquids Code (NFPA No. 30-1969).

The storage and handling of liquefied petroleum gas fuel must be in accordance with NFPA
Storage and Handling of Liquefied Petroleum Gases (NFPA No. 58-1969).


Powered Hand Trucks

There are two types of powered hand trucks: low-lift and high-lift. Low-lift trucks are used only
for moving the material horizontally. Powered hand trucks are operated by electric motors. Only
authorized personnel may charge batteries. Recharge the batteries only at a fixed battery
charging facility. See the section on battery charging for safety instructions.

The hazards of operating powered hand trucks include:

   Contact with the powered hand truck’s moving parts, such as wheels and lifting mechanisms.
   Loads falling due to incorrect operation.
   Collision between the powered hand truck and fixed objects, other trucks, or employees.
   Collision with a person caused by the operator riding the powered hand truck.

Follow these safety practices when operating the powered hand trucks:

1. Lead the truck from either the right or left side of the handle, and face the direction of travel.
2. Walk ahead of the truck, except when it must be run close to a wall or other obstruction, or
   when driven down an incline. In such instances, operate the truck in reverse and walk behind
   it, facing the direction of travel.
3. Back the truck into a confined location to avoid being caught between the truck and the
   walls.
4. Give pedestrians the right of way at all times.


INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                   Page 7
©2011, Waste Management                                                              January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



5. To prevent collisions, come to a full stop at blind corners, doorways and aisle intersections,
    and sound the warning device.
6. Operate the truck at a safe speed for existing conditions. It should never be operated at a
    speed greater than that of a normal walk.
7. Maintain a firm grip on the operating handle, keeping hands free of grease and water.
8. Never ride the truck unless it is specifically designed for the operator to ride.
9. Never permit other employees to ride the truck.
10. When going uphill on a ramp or slope, always travel with the load upgrade so it does not
    spill.
11. Keep loads low so the operator’s view is not obstructed.


Operator Safety Instructions
   Never use the equipment without instructions. See machine signs (decals) Operation &
   Maintenance Manual and Handbook.
   Fasten seat belt snugly. Always keep feet on the pedals when operating loader.
   Never use equipment as man lift or elevating device for personnel.
   Never use equipment without operator cab with ROPS and FOPS approval.
   Do not use equipment in atmosphere with explosive dust or gas or where exhaust can contact
   flammable material.
   Never carry riders.
   Keep bystanders away from work area.
   Always carry bucket or attachments as low as possible. Do not travel or turn with lift arms
   up.
   Load, unload and turn on flat level ground.
   Never exceed rated operating capacity.
   Never modify equipment.
   Use only attachments approved for the model loader.
   Never leave loader with engine running or with lift arms up. To park, engage parking brake
   and put attachment flat on the ground.

Prepare for Safe Operation

1. Check the Safety Equipment
   Falling Object Protective Structure (FOPS).
   Rollover Protective Structure (ROPS).
   Seat Belts.
   Operator Seat Bar(s).
   Side Shields, Screens or Cab.
   Grab Handles.
   Lift Arm Restraining Device(s).
   Lights.
   Anti-skid Tread/Steps.
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                Page 8
©2011, Waste Management                                                           January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



    Safety Signs.
    Horn.
    Guards.
    Back-up Alarm.
    Fire Extinguisher.
2. Never remove or disconnect any safety device.
3. Check the Machine
    Check for broken, missing or damaged parts. Make necessary repairs.
    Check the tires for cuts, bulges and correct pressure. Replace badly worn or damaged tires.
    Check the parking brake for proper operation.
    Perform all maintenance procedures outlined by the manufacturer of the machine.
    Check the hydraulic system. Have any leaks repaired.

4. Clean Machine
5. Windshield, Lights and Safety Signs.
6. Operator’s Area.
7. Steering levers.
8. Pedals steps.
9. Grab handles.
10. Remove snow, ice, mud, oil and grease.
11.
12. Use Caution when fueling
13. Don’t over fill tank.
14. Use correct type and grade of fuel.
15. Don’t fill the tank with the engine running.
16. Know the Working Area
17. Inspect the surface, ground, and floor levels.
18. Check for hidden obstacles, weak spots, and wet floors.
19. Know Clearances
20. Overhead doorway.
21. Aisles.
22. Weight limitations of machine, ramps, and floors.
23. Rules Of the Road
24. Slow moving vehicle emblem in place.
25. Check reflectors.
26. Mount Safely
27. Maintain a three-point contact with the steps and grab handles provided.
28. Face the machine.
29. Never jump on or off the machine. Never attempt to mount or dismount a moving machine.

Definitions
Approved Truck or Approved Industrial Trucks: A truck that is listed or approved, under
nationally recognized testing standards, as fire safe for its intended use.

INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                Page 9
©2011, Waste Management                                                           January 2011
INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM



Powered Hand Truck: Any self-propelled truck that is controlled by a walking operator and is
used to lift, carry, stack or tier material.

Driver: An employee trained to properly operate a powered industrial truck, and trained to
follow safety procedures and avoid hazards while operating the truck.

Load Engaging Means: The part of the powered industrial truck that picks up the load.

DS: Diesel-powered units with safeguards on the exhaust, fuel and electrical systems against
inherent fire hazards.

DY: Diesel-powered units with safeguards on the exhaust, fuel and electrical systems against
inherent fire hazards. In addition these units do not have any electrical equipment, including the
ignition, and are equipped with temperature limitation features.

EX: Electric-powered units with specially designed, constructed and assembled electrical fittings
for use in atmospheres containing flammable vapors and dusts and under certain conditions,
fibers.

EE: Electric-powered hand trucks with safeguards against inherent fire and electrical shock
hazards. In addition, these units have enclosed electrical systems to prevent emission of
hazardous sparks and to limit surface temperature.

Powered Industrial Trucks: Specialized industrial trucks powered by electric motors or internal
combustion including, but not limited to, fork trucks, tractors, platform lift trucks, and motorized
hand trucks.




INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM                                                  Page 10
©2011, Waste Management                                                              January 2011
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)

More Related Content

PDF
Estimation of Environmental Damages from Mining Pollution: The Marinduque Isl...
DOCX
Wetlands_term_paper_2015
PDF
16.02, Segalas — Lecture on indicators
PDF
Sandy Mackie on Restoration vs. Mitigation
PDF
Pinto Lake Disc Golf Course Concerns: Process for Approval, Environmental Imp...
PDF
Missouri summary ndaa
PDF
PDF
July-August 2009 Roadrunner Newsletter, Kern-Kaweah Sierrra Club
Estimation of Environmental Damages from Mining Pollution: The Marinduque Isl...
Wetlands_term_paper_2015
16.02, Segalas — Lecture on indicators
Sandy Mackie on Restoration vs. Mitigation
Pinto Lake Disc Golf Course Concerns: Process for Approval, Environmental Imp...
Missouri summary ndaa
July-August 2009 Roadrunner Newsletter, Kern-Kaweah Sierrra Club

What's hot (19)

PDF
LID adoption
PPTX
The Impacts of Dam Construction on Natural Resource Access and the Livelihood...
PDF
Dewey Loeffel Landfill EPA Superfund SIte Factsheet
PDF
Solar PV - Environmental Due Diligence
PDF
Uic Nepa
PPT
Appropriate Due Diligence of Brownfield Sites in Irelnd - In The Current Market
PPT
Cl rb outputs
PDF
Learning from the Drought - South Florida Water District
PDF
OR: Portland: Downspout Disconnection Program - Putting Stormwater into Rain ...
PDF
Australian Showcase: Theme 1: Australia and Waterined_v3
PDF
21 Design Work Shop 7.30.2009
PDF
University of Oregon Ecosystem Workforce Program
PDF
Draft Community Invol august 2010 rev2
PPT
Land Use Framework
PDF
Rainwater Tanks and Jars Construction Manual - Rainwater Harvesting
PPTX
Clean Rivers, Clean Lake 8 -- Opening Remarks -- Nancy Frank
PDF
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
PPTX
Lake Conroe Dock Fees Presentation
PDF
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
LID adoption
The Impacts of Dam Construction on Natural Resource Access and the Livelihood...
Dewey Loeffel Landfill EPA Superfund SIte Factsheet
Solar PV - Environmental Due Diligence
Uic Nepa
Appropriate Due Diligence of Brownfield Sites in Irelnd - In The Current Market
Cl rb outputs
Learning from the Drought - South Florida Water District
OR: Portland: Downspout Disconnection Program - Putting Stormwater into Rain ...
Australian Showcase: Theme 1: Australia and Waterined_v3
21 Design Work Shop 7.30.2009
University of Oregon Ecosystem Workforce Program
Draft Community Invol august 2010 rev2
Land Use Framework
Rainwater Tanks and Jars Construction Manual - Rainwater Harvesting
Clean Rivers, Clean Lake 8 -- Opening Remarks -- Nancy Frank
Challenges with implementing_gi_in_onondaga_county_nycom-pws_oct2011
Lake Conroe Dock Fees Presentation
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
Ad

Viewers also liked (8)

PDF
William Aila Questionnaire and Résume
PDF
June 27 Letter to HUD
PDF
HLRB Ruling on Motion to Strike Respondents' Opposition
PDF
City/ORI Report to HUD: August 1, 2011
PDF
Blue Planet Foundation Testimony on SB1372
PDF
FTA Record of Decision to Honolulu 2011
PDF
American jobs act_--_final
PDF
Charles Carole Letter and DTS Response
William Aila Questionnaire and Résume
June 27 Letter to HUD
HLRB Ruling on Motion to Strike Respondents' Opposition
City/ORI Report to HUD: August 1, 2011
Blue Planet Foundation Testimony on SB1372
FTA Record of Decision to Honolulu 2011
American jobs act_--_final
Charles Carole Letter and DTS Response
Ad

Similar to Removal Action Summary Report (pages 1-1015) (20)

PDF
Eacc samoa
PDF
Community response to Lake Macquarie flood and sea level projections
PPT
2011 Winter Meeting Lake Comp Plan update
PDF
ORP 2011 Cleanup Caucus Presentation
PDF
Eacc ghana
PDF
British Columbia Drought Response Plan
PDF
Shreveport Louisiana Retrofit Narrative
PPTX
Deep River-Portage Burns Waterway Initiative
PPTX
Flood planning in leeds uk
PDF
Albuquerque New Mexico Rainwater Harvesting Manual
 
PDF
Albuquerque, New Mexico Rainwater Harvesting Manual
 
PPS
Virginia TMDL Success
PPTX
master_project
PPT
Attachment a
PDF
Action Plan for Cyclone Disaster Management
PDF
Eacc bangladesh
PDF
Flood in bangladesh
PDF
Rainfall Erosivity In Soil Erosion Processes Gianni Bellocchi
PDF
James Stuart Full paper(1)
PDF
Paho Who Cville House Survey 2007
Eacc samoa
Community response to Lake Macquarie flood and sea level projections
2011 Winter Meeting Lake Comp Plan update
ORP 2011 Cleanup Caucus Presentation
Eacc ghana
British Columbia Drought Response Plan
Shreveport Louisiana Retrofit Narrative
Deep River-Portage Burns Waterway Initiative
Flood planning in leeds uk
Albuquerque New Mexico Rainwater Harvesting Manual
 
Albuquerque, New Mexico Rainwater Harvesting Manual
 
Virginia TMDL Success
master_project
Attachment a
Action Plan for Cyclone Disaster Management
Eacc bangladesh
Flood in bangladesh
Rainfall Erosivity In Soil Erosion Processes Gianni Bellocchi
James Stuart Full paper(1)
Paho Who Cville House Survey 2007

More from Honolulu Civil Beat (20)

PDF
Gov. David Ige response to U.S. Rep. Anna Eshoo
PDF
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
PDF
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
PDF
2019 Use of Force Annual Report HPD
DOC
Office of Health Equity Goals Draft 10
PDF
NHPI COVID-19 Statement
PDF
DLIR Response Language Access
PDF
Language Access Letter To DLIR
PDF
ACLU Letter to HPD regarding racial profiling
PDF
ACLU Letter to HPD regarding racial profiling
PDF
Jane Doe v. Rehab Hospital
PDF
Coronavirus HPHA
PDF
OHA Data Request
PDF
Letter from Palau to Guam
PDF
Guam Governor's Letter to Pence
PDF
OHA Analysis by Akina
PDF
Case COFA Letter
PDF
List Of Pro Bono Legal Service Providers
PDF
Arbitration Hearing Transcript December 2018
PDF
Caldwell Press Release
Gov. David Ige response to U.S. Rep. Anna Eshoo
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
2019 Use of Force Annual Report HPD
Office of Health Equity Goals Draft 10
NHPI COVID-19 Statement
DLIR Response Language Access
Language Access Letter To DLIR
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
Jane Doe v. Rehab Hospital
Coronavirus HPHA
OHA Data Request
Letter from Palau to Guam
Guam Governor's Letter to Pence
OHA Analysis by Akina
Case COFA Letter
List Of Pro Bono Legal Service Providers
Arbitration Hearing Transcript December 2018
Caldwell Press Release

Recently uploaded (20)

PDF
Keppel_Proposed Divestment of M1 Limited
PPT
Chapter four Project-Preparation material
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
Digital Marketing & E-commerce Certificate Glossary.pdf.................
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Solaris Resources Presentation - Corporate August 2025.pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PPTX
Probability Distribution, binomial distribution, poisson distribution
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
How to Get Funding for Your Trucking Business
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
PDF
Hindu Circuler Economy - Model (Concept)
PDF
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Laughter Yoga Basic Learning Workshop Manual
Keppel_Proposed Divestment of M1 Limited
Chapter four Project-Preparation material
Module 2 - Modern Supervison Challenges - Student Resource.pdf
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Digital Marketing & E-commerce Certificate Glossary.pdf.................
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
Lecture 3344;;,,(,(((((((((((((((((((((((
Solaris Resources Presentation - Corporate August 2025.pdf
Power and position in leadershipDOC-20250808-WA0011..pdf
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Probability Distribution, binomial distribution, poisson distribution
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
How to Get Funding for Your Trucking Business
Charisse Litchman: A Maverick Making Neurological Care More Accessible
Hindu Circuler Economy - Model (Concept)
Module 3 - Functions of the Supervisor - Part 1 - Student Resource (1).pdf
ICG2025_ICG 6th steering committee 30-8-24.pptx
Laughter Yoga Basic Learning Workshop Manual

Removal Action Summary Report (pages 1-1015)

  • 1.   Removal Action Summary Report WAIMANALO GULCH SANITARY LANDFILL KAPOLEI, O‘AHU, HAWAI‘I AUGUST 2011  
  • 2.   CONTENTS   ACRONYMS  AND  ABBREVIATIONS   iii   CERTIFICATION   iv   I.   SUMMARY  OF  EVENTS   1   A.   Site  Conditions  and  Background   1   1.   Initial  Situation   1   2.   Cause  of  Release  or  Discharge   1   B.   Organization  of  the  Response   8   C.   Chronological  Narrative  of  Response  Actions   9   1.   Threat  Abatement  Actions  Taken   9   2.   Treatment/Disposal/Alternative  Technology  Approaches  Pursued   14   3.   Public  Information  and  Community  Relations  Activities   16   D.   Resources  Committed   18   II.   EFFECTIVENESS  OF  REMOVAL  ACTIONS   18   A.   Actions  Taken  By  Operator   18   B.   Actions  Taken  by  State  and  Local  Forces   19   C.   Actions  Taken  by  Federal  Agencies  and  Special  Teams   19   D.   Actions  Taken  by  Contractors,  Private  Groups,  and  Volunteers   19   III.   RECOMMENDATIONS   19   A.   Means  to  Prevent  a  Recurrence  of  the  Discharge  or  Release   19   APPENDIXES   A   Correspondence   B   Work  Plans   C   Heath  and  Safety  Plan   D   Letter  Reports/CQA  Reports   E   Invoices   FIGURES   1   Site  Location  Map   3   2   Site  Layout  Map   4   3   Daily  Sum  of  Precipitation  Measured  at  On-­Site  Rain  Gauge   5   4   Daily  Sum  of  Precipitation  Measured  at  Up-­Canyon  Rain  Gauge   6   5   Daily  Sum  Comparison  of  Precipitation  Measured  at  On-­Site  and  Up-­Canyon   Rain  Gauges   7   TABLES   1   Major  Rain  Event  Summary   1   2   Monthly  Precipitation  Summary   1   3   Organization  of  Response   8   4   Response  Action  Activities   10   5   Materials/Quantities  Pumped  during  Removal  Action   14   6   Total  Liquid  Disposed  of  at  WWTP   16   7   Costs  Incurred  to  WMH  during  Response  Activities   18   ii  
  • 3.   ACRONYMS  AND  ABBREVIATIONS   AECOM   AECOM  Technical  Services,  Inc.   CERCLA   Comprehensive  Environmental  Response,  Compensation,  and  Liability  Act   City   City  and  County  of  Honolulu   CQA   Construction  Quality  Assurance   DOH   Department  of  Health,  State  of  Hawaii   EPA   Environmental  Protection  Agency,  United  States   GBI   Goodfellow  Brothers,  Inc.   GCL   geosynthetic  clay  liner   GEI   GEI  Consultants,  Inc.   MSW   municipal  solid  waste   Order     Administrative  Order  on  Consent  for  Removal  Action,  CERCLA  Docket  No.   09-­2011-­0007     PCS   Pacific  Commercial  Services,  LLC   RCRA   Resource  Conservation  and  Recovery  Act   WGSL   Waimanalo  Gulch  Sanitary  Landfill   WMH     Waste  Management  of  Hawaii,  Inc.   WWTF   wastewater  treatment  facility   3   yd cubic  yards       iii  
  • 5.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  1  of  19     I.   SUMMARY  OF  EVENTS   A.   SITE  CONDITIONS  AND  BACKGROUND   1.   Initial  Situation   The  Waimanalo  Gulch  Sanitary  Landfill  (WGSL)  is  an  active  municipal  solid  waste  (MSW)  disposal   facility  located  at  92-­460  Farrington  Highway  in  Kapolei,  Oahu,  Hawai’i  and  is  owned  by  the  City  and   County   of   Honolulu   (City).   Waste   Management   of   Hawaii,   Inc.   (WMH)   is   contracted   by   the   City   to   manage  and  operate  the  landfill.  WGSL  is  the  only  operating  municipal  solid  waste  landfill  (MSW)  on   the  island  of  Oahu  and  receives  commercial  and  residential  wastes  generated  within  Oahu,  as  well   as  ash  and  residue  from  the  H-­Power  power  plant.  See  Figure  1  for  a  site  location  map  and  Figure  2   for  a  site  layout  map.   A  series  of  storm  events  occurring  in  late  December  2010  through  mid-­January  2011  resulted  in  high   surface  stormwater  run-­on  flows  that  flooded  one  of  the  MSW  cells  (Cell  E6)  and  damaged  portions   of   the   liner   system.   The   resultant   runoff   from   the   January   12th   and   13th   storm   may   have   carried   waste  materials  into  the  WGSL  storm  water  conveyance  system,  which  flows  into  the  sedimentation   basin  prior  to   leaving  the  site   at  the   permitted   discharge  point  and   onward  to   the  Pacific  Ocean.  A   removal   action   was   required   by   the   Administrative   Order   on   Consent   for   Removal   Action,   Comprehensive   Environmental   Response,   Compensation,   and   Liability   Act   (CERCLA)   Docket   Number  09-­2011-­0007  (Order).  While  stormwater  flowing  from  Cell  E6  likely  entrained  some  waste   materials,   waste   materials   from   other   areas   of   the   landfill   could   also   have   been   dislodged   and   entrained  in  stormwater  that  also  flowed  to  the  conveyance  system.   2.   Cause  of  Release  or  Discharge   In  late  December  2010,  a  series  of  storms  produced  high  stormwater  run-­on  at  the  site  resulting  in   damage   to   the   northeastern   edge   of   the   MSW   Cell   E6   liner   where   it   joins   with   Cell   E4.   An   even   larger   storm   arrived   on   the   evening   of   January   12,   2011   that   resulted   in   additional   flooding   of   the   landfill   and   damaged   the   exposed   portion   of   the   western   sideslope   area   of   the   MSW   Cell   E6   liner   system.   Table   1   summarizes   the   daily   precipitation   of   the   major   storm   events   prior   to   the   release   from   the   site.   Rain   data   is   provided   for   an   on-­site   down   gradient   rain   gauge   located   at   the   administration   building  and  a  rain  gauge  located  up-­canyon  of  the  site.  Monthly  summaries  for  the  December  2010   and   January   2011   daily   precipitation   is   presented   in   Table   2.   Daily   summaries   of   the   rain   precipitation  for  the  period  of  December  1,  2010  to  June  21,  2011  are  presented  in  Figure  3  –  5.     Table  1:  Major  Rain  Event  Summary     Daily  Precipitation  (in)   Date     On-­Site  Gauge   Daily  Precipitation  (in)  Up-­Canyon  Gauge   12/19/2010   5.4   8.4   12/27/2010   2.2   4.3   1/12/2011   5.0   9.2   1/13/2011   2.0   10.3     Table  2:  Monthly  Precipitation  Summary     Daily  Precipitation  (in)   Month   On-­Site  Gauge   Daily  Precipitation  (in)  Up-­Canyon  Gauge   December   11.9   27.4   January   7.3   20.9      
  • 6.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  2  of  19     th th The  high  water  flows  during  the  January  12 -­13  storm  resulted  in  erosion  of  the  Cell  E6  termination   bench  and  exposed  the  operations  layer  soils  covering  the  sideslope  liner,  thereby  exposing  the  liner   to  subsequent  damage  by  falling  rocks  in  addition  to  allowing  sections  of  the  liner  to  pull  down  from   the  termination  bench  creating  wrinkles.  Due  to  numerous  holes  in  the  exposed  sideslope  liner  at  the   northern  end  of  the  cell  caused  by  falling  rocks,  water  and  sediment  were  able  to  flow  between  the   geotextile,  60-­mil  geomembrane,  and  geosynthetic  clay  liner  (GCL)  layers.  Portions  of  the  GCL  in  the   middle   area   of   the   sideslope   area   were   hydrated   and   covered   with   sediment   due   to   the   water   and   sediment  flow.   A   Severe   Storm   Damage   Report   (included   in   Appendix   D)   documents   the   inspection   that   followed   the   January   12-­13,   2011   storm   event.   The   inspection   found   several   damaged   areas   including   flooding  of  the  MSW  Cell  E6  and  damage  to  the  drainage  structures,  landfill  liner,  drainage  swales,   and  access  roads.    
  • 9. 6 5 4 Daily  Precipitation  (in)   3 2 1 0 Figure  3:  Daily  Sum  of  Precipitation  Measured  at  On-­‐Site  Rain  Gauge Source:  WGSL  on-­‐site  rain  gauge  located  at  the  administration  building.
  • 10. 12 10 8 Daily  Precipitation  (in) 6 4 2 0 Figure  4:  Daily  Sum  of  Precipitation  Measured  at  Up-­‐Canyon  Rain  Gauge   Source:  Data  from  rain  gauge  “MPLHHL”  located  up-­‐canyon  of  the  WGSL. Weather  Underground.  2011.  http://www.wunderground.com/cgi-­‐bin/findweather/getForecast?query=Kapolei,  Hawaii.  June  (6/23/11).
  • 11. 12 10 8 Daily  Precipitation  (in)   6 4 On-­‐Site Up-­‐Canyon 2 0 Figure  5:  Daily  Sum  Comparison  of  Precipitation  Measured  at  On-­‐Site  and  Up-­‐ Canyon  Rain  Gauges  
  • 12.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  8  of  19     B.   ORGANIZATION  OF  THE  RESPONSE   Response   actions   were   conducted   in   accordance   with   the   timeline   mandated   by   the   Order.   As   specified  in  the  Order,  WMH  retained  several  contractors  to  perform  the  work  required  by  the  EPA,   and  notified  the  EPA  and  DOH  of  the  names  and  qualifications  of  the  contractors  within  two  days  of   the   Effective  Date.  The  Effective  Date  of  the  Order   was  January  25,  2011  and  the  submittal   of  the   contractors   was   made   on   the   same   day,   correspondence   is   presented   in   Appendix   A.   Contractors   used  during  the  removal  action  are  identified  in  Table  3.  WMH  designated  Joseph  Whelan  as  Project   Coordinator.   As   required   by   the   Order,   Mr.   Whelan   was   present   on   site   and/or   readily   available   during   site   work.   Correspondence   between   the   Project   Coordinator   and   the   EPA   is   presented   in   Appendix  A.   Table  3:  Organization  of  Response   Agencies  or  Parties  Involved   Contact   Description  of  Participation     EPA  –  Region  9  (SFD-­9)   Bret  Moxley   EPA  On-­Scene  Coordinator  (OSC)   75  Hawthorne  Street   San  Francisco,  CA  94105   EPA  –  Region  9  (WST-­5)   Katherine  Baylor   RCRA  Action  Officer  (RAO)   75  Hawthorne  Street   San  Francisco,  CA  94105   DOH,  Environmental  Management  Division   Stuart  Yamada,  P.E.,  Chief   State  Agency  Oversight     919  Ala  Moana  Blvd.,  Room   300   Honolulu,  HI  96814-­4920   City  and  County  of  Honolulu,  Department  of   Wilma  Namumnart,  P.E.  Acting   Landfill  Owner   Environmental  Services,  Refuse  Division   Chief   1000  Uluohia  Street,  Suite  212   Kapolei,  HI  96707   WMH   Joe  Whelan,  General  Manager   Project  Coordinator/   92-­460  Farrington  Highway   Landfill  Operator   Kapolei,  HI  96707   GEI   William  A.  Rettberg,  P.E.   Western  Drainage  Project  Design   180  Grand  Ave,  Ste  1410   Engineer  Contractor     Oakland,  California  94612   Geosyntec  Consultants,  Inc.   Hari  D.  Sharma,  Ph.D.,  P.E.   Liner  System  Design  Engineer   180  Grand  Ave,  Ste  1410   Contractor     Oakland,  CA  94612   PCS   Jingbo  Chang,  Ph.D.     Storm  Water/Leachate  Disposal   PO  Box  235117   Contractor     Honolulu,  HI  96823   GBI   Matt  Heahlke   Earthwork/Construction  Contractor     93-­061  Waipio  Point  Access   Road   Waipahu,  HI  96797   AECOM   Ron  Boyle,  P.E.   Construction  Quality  Assurance   1001  Bishop  St,  Ste  1600   Contractor     Honolulu,  HI  96813   AECOM   AECOM  Technical  Services,  Inc.   DOH   Department  of  Health,  State  of  Hawaii   EPA   Environmental  Protection  Agency,  United  States   GBI   Goodfellow  Brothers,  Inc.   GEI   GEI  Consultants,  Inc.   PCS   Pacific  Commercial  Services,  LLC      
  • 13.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  9  of  19     C.   CHRONOLOGICAL  NARRATIVE  OF  RESPONSE  ACTIONS   The  follow  sections  detail  the  response  actions  taken.  The  response  was  performed  in  accordance   with  the  Order,  under  the  authority  of  CERCLA.   1.   Threat  Abatement  Actions  Taken   Measures  taken  to  prevent  future  storm  damage  at  the  site  and  to  document  efforts  to  further  contain   potential   storm   water   and   prevent   waste   material   from   exiting   the   facility   in   the   event   of   additional   storm   events   are   described   in   the   Stormwater   Management   Update   and   Contingency   Plan.   This   document   was   updated   several   times   throughout   the   response   action;;   the   three   versions   dated   January  27,  2011,  February  1,  2011  and  February  18,  2011  are  presented  in  Appendix  B.   Table  4  presents  the  response  actions  completed  during  the  removal  action,  in  chronological  order,   as  outlined  in  Section  VIII  of  the  Order.    
  • 14.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  10  of  19     Table  4:  Response  Action  Activities   Item   Subject   Administrative  Order  Action  Requirement   19g.   Operation  of  Cell  E6   Respondent  shall  not  operate  cell  #E6  without  further  approval  from  EPA.   Action  Taken:  In  an  e-­mail  dated  January  28,  2011  the  EPA  approved  WMH  to  resume  operations  on  the  east  side  of  Cell  E6,  correspondence  is  presented  in   Appendix  A.   19c.   Storm  Water  Discharge   Respondent  shall  ensure  the  termination  of  discharges  of  liquid  originated  from  cell  #E6  to  the  Pacific  Ocean,  except  as  in   compliance  with  any  applicable  permit.   Action  Taken:  Storm  water  discharges  were  in  compliance  with  the  applicable  permits,  or  were  approved  by  the  DOH.   20.   Work  Plans  and   Respondent   shall   submit   to   EPA   for   approval   a   draft   Work   Plan   or   individual   Work   Plans   for   performing   the   response   Implementation   actions  generally  described  in  Paragraph  19  of  the  Order.   EPA   may   approve,   disapprove,   require   revision   to   or   modify   any   draft   Work   Plan   in   whole   or   in   part.   If   EPA   requires   revisions,  Respondents  hall  submit  a  revised  draft  Work  Plan  within  fifteen  (15)  days  of  receipt  of  EPA’s  notification  of  the   required  revision.  Respondent  shall  implement  each  respective  Work  Plan  as  approved  in  writing  by  EPA  in  accordance   with  its  schedule  approved  by  EPA.  Once  approve,  or  approved  with  modifications,  each  Work  Plan,  its  schedule,  and  any   subsequent  modifications  shall  be  incorporated  into  and  become  fully  enforceable  under  this  Order.   Respondent  shall  not  conduct  any  Work  except  in  conformance  with  the  terms  of  this  Order,  or  as  directed  by  EPA.   Action  Taken:  All  work  plans  were  submitted  to  the  EPA  for  approval  and  revised  according  to  schedule.  Correspondence  for  submittals  and  work  plans  are   presented  in  Appendix  A  and  Appendix  B,  respectively.   22.   Quality  Assurance  and   Although  none  is  presently  anticipated,  all  sampling  and  analyses  performed  pursuant  to  this  Order  shall  conform  to  EPA   Sampling   direction,   approval,   and   guidance   regarding   sampling,   quality   assurance/quality   control   ("QA/QC"),   data   validation,   and   chain  of  custody  procedures.       Action  Taken:  Sampling  was  not  performed  for  EPA  reporting  purposes  and  as  part  of  the  removal  action.     24.   Reporting   Beginning  two  (2)  days  after  the  Effective  Date,  Respondent  shall  submit  by  e-­mail  to  EPA  and  DOH  daily,  until  agreed   otherwise  by  the  Parties,  progress  reports  (Monday  through  Friday  only,  unless  otherwise  requested  by  EPA)  concerning   actions   undertaken   pursuant   to   this   Order,   until   receipt   of   the   Notice   of   Completion   pursuant   to   this   Order,   unless   otherwise   directed   in   writing   by   the   OSC   or   RAO.   These   reports   shall   describe   all   significant   developments   during   the   preceding   period,   including   the   actions   performed   and   any   problems   encountered,   analytical   data   received   during   the   reporting  period,  and  the  developments  anticipated  during  the  next  reporting  period,  including  a  schedule  of  actions  to  be   performed  under  any  approved  Work  Plan,  anticipated  problems,  and  planned  resolutions  of  past  or  anticipated  problems.   Respondent  shall  submit  copies  of  all  plans,  reports  (other  than  progress  reports)  or  other  submissions  required  by  this   Order,  or  any  approved  Work  Plan,  to  both  EPA  and  DOH  in  electronic  form  (Word  or  pdf  -­  minimum  300  dpi).    
  • 15.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  11  of  19     Item   Subject   Administrative  Order  Action  Requirement   Action  Taken:  WMH  submitted  Daily  Progress  Reports  as  required  by  the  EPA.  All  e-­mail  correspondence  is  presented  chronologically  in  Appendix  A.  Copies  of  all   documents  required  by  the  Order  were  submitted  electronically.  The  documents  included:       Stability  analysis  of  temporary  earthen  berm  by  a  Civil/Geotechnical  Engineer  (Appendix  D)     Work  Plans  (Appendix  B):   o   Collection  and  Transport  of  Liquid  Behind  Temporary  Berm   o   Slope  Stability  Analysis  and  Work  Plan  for  Temporary  Earthen  Berm  Integrity   o   Work  Plan  for  Managing  Potential  Cell  E6  Hydraulic  Head   o   Work  Plan  for  Liner  Evaluation  and  Repair   o   Work  Plan  for  Restoration  of  Sedimentation  Basin   o   Work  Plan  For  Beach  Assessment  and  Material  Recovery  Effort     Written  description  of  collection/treatment  activities  of  liquids  (presented  in  the  Daily  Progress  Reports  in  Appendix  A)     Health  and  Safety  Plan  (Appendix  C)     In  an  e-­mail  dated  March  17,  2011,  the  EPA  granted  the  WMH  request  to  replace  daily  progress  reports  with  a  weekly  report  submitted  by  noon  every  Wednesday,   documenting  work  completed  during  the  period  of  the  prior  Monday  thru  Sunday.  In  an  e-­mail  dated  June  22,  2011,  the  EPA  granted  the  WMH  request  to   terminate  the  weekly  progress  reports.     19d.   Storm  water  Removal   Respondent  shall  continue  to  collect  and  transport  to  a  local  treatment  facility  the  liquids  at  the  site  retained  behind  the   temporary   earthen   berm   in   cell   #E6.   Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   a   written   description  of  the  collection  and  treatment  activities,  the  current  permitting  and  the  chemical  parameters  of  the  liquids,  and   transportation  methods  to  the  local  treatment  facility.   Action  Taken:  Storm  water  was  pumped  and  transported  to  a  WWTP  in  Kailua,  HI.  The  first  work  plan  was  submitted  on  February  1,  2011.  In  an  e-­mail  dated   February  10,  2011,  the  EPA  noted  that  the  description  of  collection  and  treatment  associated  with  liquid  located  behind  the  temporary  berm  were  acceptable  with   incorporation  of  the  provided  comments;;  revisions  and  resubmission  were  required.  The  revised  work  plan  was  submitted  on  February  25,  2011  and  is  included  in   Appendix  B.   21.   Health  and  Safety  Plan   Within  seven  (7)  days,  Respondent  shall  submit  for  EPA  review  and  comment  a  Site  Health  and  Safety  Plan  that  ensures   the   protection   of   the   public   health   and   safety   during   performance   of   on-­Site   Work.   This   plan   shall   be   prepared   in   accordance   with   EPA's   Standard   Operating   Safety   Guide   (PUB   9285.1-­03,   PB   92-­963414,   June   1992),   if   applicable.   In   addition,   the   plan   shall   comply   with   all   currently   applicable   Occupational   Safety   and   Health   Administration   ("OSHA")   regulations  found  at  29  CRF  Part  1910.   Action  Taken:  A  site  Health  and  Safety  Plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  C.     19e.   Work  Plan  for  Hydraulic   Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   to   EPA   and   DOH   a   Work   Plan   and   schedule,   Head   subject  to  modification  based  on  further  field  analysis,  for  managing  the  hydraulic  head  between  cell  #E6  and  the  fluids   outside   of   cell   #E6   in   order   to   maintain   the   integrity   of   the   cell   liner   as   the   fluids   are   drawn   down   and   the   leachate   collection  system  is  returned  to  normal  functions.    
  • 16.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  12  of  19     Item   Subject   Administrative  Order  Action  Requirement   Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  approved  the  work   plan.  The  Evaluation  of  Hydraulic  Head  Below  Liner  System  Summary  Report  was  submitted  to  the  EPA  on  February  25.  The  e-­mail  submittal  is  included  in   Appendix  A  and  a  copy  of  the  summary  report  is  included  in  Appendix  D.       19h.   Work  Plan  and   Within   seven   (7)   days   of   the   Effective   Date,   Respondent   shall   provide   to   EPA   and   DOH   a  Work   Plan   and   schedule   to   Schedule  for  Sediment   restore   the   sediment   basin   system   to   its   intended   capacity   and   function.   This   shall   include   removal   of   the   sediment   Basin  Restoration   collected  in  the  basin(s)  and  the  proposed  disposal  location  for  the  collected  sediments   Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the   submitted  work  plan  was  acceptable  with  incorporation  of  provided  comments;;  revision  and  resubmissions  were  required.  In  e-­mail  dated  March  4,  2011,  the  work   plan  was  approved,  and  suggested  a  completion  date  of  March  14,  2011.  However,  due  to  continued  rain  events  during  the  restoration  of  the  basin,  WMH   requested  a  later  deadline  of  May  15,  2011.  After  continued  rain  events,  WMH  requested  an  additional  extension  via  e-­mail  on  May  5,  2011.  In  an  e-­mail  dated   May  6,  2011,  the  EPA  approved  an  extension  to  June  15,  2011.     In  an  e-­mail  dated  June  15,  2011  WMH  submitted  the  Sedimentation  Basin  Restoration  Observation  Report.  Following  comments  provided  by  the  EPA,  additional   work  was  conducted  on  the  sediment  basin  and  an  Addendum  report  was  submitted  on  August  4,  2011.  The  submittal  correspondence  is  presented  in  Appendix  A   and  the  reports  are  included  in  Appendix  D.   19i.   Work  Plan  and   Within   seven   (7)  days   of   the  Effective   Date,   Respondent  shall   provide   to   EPA   and   DOH   a  Work   Plan   and  schedule   for   Schedule  for  Beach   ongoing  daily  beach  assessment  and  recovery  of  Waste  Material  released  from  the  WGSL.   Assessment  and  Debris   Recovery   Action  Taken:  The  work  plan  was  submitted  on  February  1,  2011  and  is  presented  in  Appendix  B.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the   submitted  work  plan  was  acceptable  with  incorporation  of  provided  comments;;  revision  and  resubmissions  were  required.  In  an  e-­mail  dated  March  4,  2011,  the   EPA  approved  the  work  plan.  The  work  plan  is  presented  in  Appendix  B.  After  a  final  beach  assessment  on  January  24,  2011,  WMH  noted  that  the  daily  beach   assessment  phase  was  complete;;  no  calls  were  received  at  the  established  beach  waste  hot  line  during  the  subsequent  reporting  periods.   19a.   Temporary  Earthen   Within  ten  (10)  days  of  the  Effective  Date,  Respondent  shall  provide  to  EPA  and  DOH  an  analysis  by  a  qualified  Civil  or   Berm   Geotechnical  Engineer  of  the  stability  and  suitability  of  the  temporary  earthen  berm,  which  is  currently  retaining  liquid  in   cell  #E6,  to  retain  liquid  when  full  to  within  one  (1)  foot  of  the  top  for  up  to  six  (6)  weeks,  and  a  Work  Plan  to  ensure  the   integrity  of  the  temporary  earthen  berm  so  long  as  it  is  holding  liquid   Action  Taken:  A  report  entitled  Slope  Stability  Analysis  and  Work  Plan  for  Temporary  Earthen  Berm  Integrity  was  submitted  to  the  EPA  on  February  4,  2011  by  e-­ mail  and  Certified  Mail.  The  report  found  that  the  temporary  berm  met  and/or  exceeded  minimum  accepted  factors  of  safety  and  no  modifications  were  necessary.   The  e-­mail  and  report  can  be  found  in  Appendix  A  and  Appendix  B,  respectively.   19f.   Work  Plan  and   Within  fourteen  (14)  days  of  the  Effective  Date,  Respondent  shall  provide  to  EPA  and  DOH  a  Work  Plan  and  schedule  to   Schedule  for  E6  Liner   evaluate  and  demonstrate  or  restore  the  integrity  of  the  liner  system  in  cell  #E6   Repair    
  • 17.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  13  of  19     Item   Subject   Administrative  Order  Action  Requirement   Action  Taken:  The  work  plan  was  submitted  to  the  EPA  on  February  4,  2011.  In  an  e-­mail  dated  February  10,  2011,  the  EPA  noted  that  the  submitted  work  plan   was  acceptable;;  revision  and  resubmissions  were  not  required.  Submittal  correspondence  is  included  in  Appendix  A  and  a  copy  of  the  work  plan  is  presented  in   Appendix  B.       CQA  reports  documenting  the  liner  repairs  related  to  the  storm  damage  was  submitted  under  separate  cover  as  specific  areas  were  repaired.  Copies  of  the  CQA   repair  reports  are  included  in  Appendix  D.   19b.   Storm  water  Diversion   Within   twenty-­one   (21)   days   of   the   Effective   Date,   Respondent   shall   complete   construction   of   a   functional   storm   water   Structure   diversion  structure  on  the  west  side  above  cell  #E6.   Action  Taken:  In  an  e-­mail  dated  February  15,  2011,  WMH  confirmed  that  construction  of  a  functional  storm  water  diversion  structure  located  on  the  west  side   above  Cell  E6  was  functionally  complete.  In  an  e-­mail  dated  February  16,  2011,  the  EPA  concurred  that  WMH  completed  construction  of  a  functional  storm  water   diversion  structure  as  required  by  paragraph  19b.       In  addition,  in  an  e-­mail  dated  March  11,  2011,  WMH  submitted  a  revised  Surface  Water  Management  Plan  to  the  EPA  and  DOH.  All  correspondence  is  presented   in  Appendix  A,  and  the  Surface  Water  Management  Plan  is  in  Appendix  D.   25.   Final  Report   Within   sixty   (60)   days   after  completion   of  all  Work   required  by   this   Order,   Respondent  shall  submit   for   EPA  review   and   approval   a   final   report   summarizing   the   actions   taken   to   comply   with   this   Order.   The   final   report   shall   conform,   at   a   minimum,   with   the   requirements   set   forth   in   Section   300.165   of   the   NCP   entitled   "OSC   Reports."   The   final   report   shall   include  a  good  faith  estimate  of  total  costs  or  a  statement  of  actual  costs  incurred  in  complying  with  the  Order,  a  listing  of   quantities   and   types   of   materials   removed   off-­Site   or   handled   on-­Site,   a   discussion   of   removal   and   disposal   options   considered  for  those  materials,  a  listing  of  the  ultimate  destination(s)  of  those  materials,  a  presentation  of  the  analytical   results   of   all   sampling   and   analyses   performed,   and   accompanying   appendices   containing   all   relevant   documentation   generated   during   the   removal   action   (e.g.,   manifests,   invoices,   bills,   contracts,   and   permits).   The   final   report   shall   also   include  the  following  certification  signed  by  a  person  who  supervised  or  directed  the  preparation  of  that  report:   "Under  penalty  of  law,  I  certify  that  to  the  best  of  my  knowledge,  after  appropriate  inquiries  of  all  relevant  persons  involved   in   the   preparation   of   the   report,   the   information   submitted   is   true,   accurate,   and   complete.   I   am   aware   that   there   are   significant   penalties   for   submitting   false   information,   including   the   possibility   of   fine   and   imprisonment   for   knowing   violations."   Action  Taken:  This  report  fulfills  the  requirements  described  in  Paragraph  25.   26.   Off-­site  Shipments   Respondent   shall,   prior   to   any   off-­Site   shipment   of  Waste   Material   from   the   Site   to   an   out-­of-­state   waste   management   facility,  provide  written  notification  of  such  shipment  of  Waste  Material  to  the  appropriate  state  environmental  official  in  the   receiving  facility's  state  and  to  the  OSC  and  RAO.   Action  Taken:  No  Waste  Material,  as  defined  in  Section  III.r  of  the  Order,  was  shipped  off-­site  during  the  response  activities.     CQA   Construction  Quality  Assurance     WWTP   wastewater  treatment  plant    
  • 18.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  14  of  19     2.   Treatment/Disposal/Alternative  Technology  Approaches  Pursued   WMH  contracted  Pacific  Commercial  Services,  LLC  (PCS)  to  pump  and  transfer  storm  water  to  the   wastewater   treatment   plant   (WWTP)   in   Kailua,   HI.   A   summary   of   the   materials   pumped   during   the   removal  action  is  presented  in  Table  5.  In  addition  to  the  material  shown  in  Table  5,  WMH  removed   3 approximately   806,500   gallons   of   storm   water   and   14,610   cubic   yards   (yd )   of   sediment   from   the   sedimentation   basin   during   the   restoration   activities,   as   discussed   in   the   Sedimentation   Basin   Restoration   Observation   Report   dated   June   15,   2011   (included   in   Appendix   D).   A   summary   of   the   liquid  transported  and  disposed  of  at  the  WWTP  is  presented  in  Table  6.  Note  that  quantities  of  liquid   pumped  and  transported  by  the  City  during  the  removal  action  are  not  included  in  this  report.     Table  5:  Materials/Quantities  Pumped  during  Removal  Action   Reporting  Date   Location   Amount  Pumped  (gallons)   Material   Disposal  Area   1/27/11   Cell  E6  Leachate  Riser   12,000   mud   On-­site   1/27/11   Sedimentation  Basin   60,000   Water   WWTP   1/28/11   Cell  E6  Leachate  Riser   20,321   Silt   On-­site   1/28/11   Sedimentation  Basin   60,000   Water   WWTP   1/31/11   Cell  E6  Leachate  Riser   2  ft   Silt   On-­site   1/31/11   Sedimentation  Basin   274,000   Water   WWTP   2/1/11   Cell  E6  Leachate  Riser   16,500   Water   WWTP   2/1/11   Cell  E6  Leachate  Riser   16,000   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/1/11   Sedimentation  Basin   56,000   Water   WWTP   2/2/11   Cell  E6  Leachate  Riser   16,500   Water   WWTP   2/2/11   Cell  E6  Leachate  Riser   10,000   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/2/11   Sedimentation  Basin   105,800   Water   WWTP   2/3/11   Cell  E6  Leachate  Riser   12,500   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/3/11   Sedimentation  Basin   55,800   Water     WWTP   2/4/11   Cell  E6  Leachate  Riser   10,000   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/4/11   Sedimentation  Basin   61,500   Water   WWTP   2/7/11   Cell  E6  Leachate  Riser   2,500   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/7/11   Sedimentation  Basin   24,700   Water   WWTP   2/8/11   Sedimentation  Basin   44,800   Water   WWTP   2/9/11   Sedimentation  basin   52,277   Water   WWTP   2/10/11   Cell  E6  Leachate  Riser   19,350   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/10/11   Frac  Tanks   16,500   Water   WWTP   2/10/11   Sedimentation  Basin   41,249   Water   WWTP   2/11/11   Cell  E6  Leachate  Riser   9,675   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/11/12   Sedimentation  Basin   19,350   Water   WWTP   2/14/11   Cell  E6   32,818   Water   WWTP   2/14/11   Cell  E6  Leachate  Riser   27,000   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/14/11   Sedimentation  Basin   32,700   Water   WWTP   2/15/11   Cell  E6   47,759   Water   WWTP   2/15/11   Cell  E6  Leachate  Riser   44,000   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/15/11   Sedimentation  Basin   17,318   Water   WWTP   2/16/11   Cell  E6   18,100   Water   WWTP   2/16/11   Cell  E6  Leachate  Riser   33,200   Water   WWTP   2/16/11   Cell  E6  Leachate  Riser   27,700   Mud/Water  Mixture   Frac  Tanks  for  Separation   2/17/11   Cell  E6  Leachate  Riser   55,000   Mud/Water  Mixture   Frac  Tanks  for  Separation    
  • 19.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  15  of  19     Reporting  Date   Location   Amount  Pumped  (gallons)   Material   Disposal  Area   2/17/11   Sedimentation  Basin   31,675   Water   WWTP   2/1711   Sedimentation  Basin   -­-­   Silt/Rock   Lined  portion  of  Cell  E6   2/18/11   Frac  Tanks   56,700   Water   WWTP   2/18/11   Sedimentation  Basin   57,718   Water   WWTP   2/18/11   Sedimentation  Basin   -­-­   Silt/Rock   Lined  portion  of  Cell  E6   2/21/11   Frac  Tanks   108,000   Water   WWTP   2/21/11   Sedimentation  Basin   -­-­   Silt/Rock   Lined  portion  of  Cell  E6   2/22/11   Frac  Tanks   33,900   Water   WWTP   2/22/11   Sedimentation  Basin   -­-­   Silt/Rock   Lined  portion  of  Cell  E6   2/23/11   Sedimentation  Basin   41,700   Water   WWTP   2/24/11   Sedimentation  Basin   54,900   Water   WWTP   2/25/11   Sedimentation  Basin   56,800   Water   WWTP   2/28/11   Frac  Tanks   105,300   Water   WWTP   2/28/11   Cell  E6  Leachate  Riser   33,200   Water   WWTP   South  Pond  Area   2/28/11   Cell  E6  Leachate  Riser   30,772   Mud/Water  Mixture   Frac  Tanks  for  Separation   South  Pond  Area   2/28/11   Sedimentation  Basin   8,700   Water   WWTP   3/1/11   Frac  Tanks   30,700   Water   WWTP   3/1/11   Cell  E6  Leachate  Riser   11,000   Water   WWTP   South  Pond  Area   3/1/11   Sedimentation  Basin   15,500   Water   WWTP   3/2/11   Frac  Tanks   13,000   Water   WWTP   3/2/11   Sedimentation  Basin   40,000   Water   WWTP   3/3/11   Frac  Tanks   12,018   Water   WWTP   3/3/11   Cell  E6  Leachate  Riser   25,000   Water   WWTP   South  Pond  Area   3/3/11   Sedimentation  Basin   51,000   Water   WWTP   3/4/11   Frac  Tanks   14,949   Water   WWTP   3/4/11   Sedimentation  Basin   59,700   Water   WWTP   3/7/11   Frac  Tanks   36,200   Water   WWTP     3/7/11   Sedimentation  Basin   113,000   Water   WWTP   3/8/11   Sedimentation  Basin   76,200   Water   WWTP   3/9/11   Frac  Tanks   15,100   Water   WWTP   3/9/11   Sedimentation  Basin   75,300   Water   WWTP   3/10/11   Frac  Tanks   6,359   Water   WWTP   3/10/11   Sedimentation  Basin   84,000   Water   WWTP   3/11/11   Frac  Tanks   3,159   Water   WWTP   3/11/11   Sedimentation  Basin   26,500   Water   WWTP   3/14/11   Frac  Tanks   20,677   Water   WWTP   3/14/11   Sedimentation  Basin   126,000   Water   WWTP   3/15/11   Frac  Tanks   8,769   Water   WWTP   3/15/11   Cell  E6  Leachate  Riser   1,518   Water   WWTP   South  Pond  Area   3/15/11   Sedimentation  Basin   71,476   Water   WWTP   3/16/11   Frac  Tanks   6,318   Water   WWTP   3/16/11   Cell  E6  Leachate  Riser   1,300   Water   WWTP    
  • 20.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  16  of  19     Reporting  Date   Location   Amount  Pumped  (gallons)   Material   Disposal  Area   South  Pond  Area   3/16/11   Sedimentation  Basin   91,400   Water   WWTP   Week  Ending  3/20/11   Frac  Tanks   31,698   Water   WWTP   Week  Ending  3/20/11   Sedimentation  Basin   221,300   Water   WWTP   Week  Ending  3/27/11   Frac  Tanks   52,434   Water   WWTP   Week  Ending  3/27/11   Sedimentation  Basin   105,900   Water   WWTP   Week  Ending  4/3/11   Frac  Tanks   51,663   Water   WWTP   Week  Ending  4/10/11   Frac  Tanks   35,586   Water   WWTP   Week  Ending  4/10/11   Sedimentation  Basin   15,000   Water   On-­Site  (Dust  Control)a   Week  Ending  4/17/11   Frac  Tanks   26,006   Water   WWTP   Week  Ending  4/24/11   Frac  Tanks   4,159   Water   WWTP   Week  Ending  5/1/11   Frac  Tanks   1,000   Water   WWTP   Week  Ending  5/8/11   Frac  Tanks   63,611   Water   WWTP   Week  Ending  5/15/11   Frac  Tanks   9,477   Water   WWTP   Week  Ending  5/22/11   Frac  Tanks   56,914   Water   WWTP   Week  Ending  5/29/11   Frac  Tank   25,216   Water   WWTP   Week  Ending  6/3/11   Frac  Tank   34,075   Water    WWTP   Week  Ending  6/12/11   Frac  Tanks   33,343   Water   WWTP   Notes:   a   Approval  via  e-­mail  from  DOH  dated  3/23/11  to  use  sedimentation  basin  storm  water  for  onsite  dust  control  and  irrigation.   The  quantity  of  water  pumped  was  no  longer  recorded  after  this  date.     Table  6:  Total  Liquid  Disposed  of  at  WWTP   Origin   Total  Liquid  Disposed  of  between  1/28/2011  –  6/12/2011  (gallons)  c   Cell  E6   98,677   a Cell  6  Leachate  Riser     138,218   Frac  Tanks   853,540   Sedimentation  Basin  b   2,314,263   TOTAL   3,306,021   Notes:   a   Does  not  include  mud/water  mixture  pumped  into  frac  tanks  on  site.   b   Does  not  include  storm  water  pumped  to  use  for  onsite  dust  control  and  irrigation.   c   Quantities  of  liquid  do  not  include  liquid  pumped  by  the  City  from  Cell  E6  and  the  sedimentation  basin.     3.   Public  Information  and  Community  Relations  Activities   WMH   and   the   City   published   several   press   releases   summarizing   the   response   activities.   Press   releases   are   included   in   Appendix   A   for   the   following   dates:   January   24,   2011,   January   25,   2011,   January  31,  2011,  February  8,  2011,  and  February  15,  2011.     As   presented   in   the   January   24,   2011   press   release,   a   summary   of   the   public   notices,   shoreline   cleanup  activities,  and  reporting  hotline  includes  the  following:       Thursday,  January  13  —  WMH  evaluated  storm  water  conditions  throughout  the  day  of  the   storm  event  and  determined  that  a  large  body  of  storm  water  had  collected  in  the  area  of  the   new   cell   construction.   Working   in   collaboration   with   the   DOH,   WM,   and   the   City   installed   warning   signs   in   the   shoreline   area   of   the   Ko   Olina   Resort,   where   the   landfill   outfall   is   located,  and  along  the  associated  beach  shoreline.  Additionally,  WMH  and  the  City  began  a   water   quality   sampling   program   that   same   day.   Later   on   January   13,   WMH   began   debris    
  • 21.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  17  of  19     cleanup  at  the  overflow  and  the  storm  water  sedimentation  basin  once  the  flood  waters  had   subsided   enough   to   perform   this   operation   safely.   At   that   time,   it   was   determined   that   the   debris  also  contained  sterilized  medical  waste.     Friday,  January  14  —  WMH  dispatched  an  evaluation  and  cleanup  team  to  the  ocean  side  of   the   landfill’s  permitted  storm  water  outfall,  located  on  the   north  end  of  the   Ko  Olina  Resort   property  across  Farrington  Highway  from  the  landfill.  The  crew  spent  several  hours  cleaning   debris   from   this   area.   At   the   time,   there   was   no   apparent   evidence   of   remaining   medical   waste  material.  WMH  continued  to  clean  up  areas  located  between  the  sediment  basin  and   the  permitted  outfall.  Also  on  January  14,  representatives  of  WMH,  the  City,  and  DOH  held  a   press  conference  at  the  landfill  to  further  inform  the  public  of  potential  concerns  associated   with   the   storm   events,   and   to   provide   an   update   on   the   cleanup   efforts,   warning   sign   postings,   and   water   quality   sampling   being   performed   by   WMH   and   the   City.   Numerous   news  interviews  and  media  announcements   were  provided  by  all  parties  over  the  following   several  days  in  order  to  keep  the  public  fully  informed.     Saturday,  January  15  —  WMH  personnel  continued  evaluation  of  the  shoreline  area.  In  the   afternoon,   additional   medical   waste   material   was   reported   in   the  WMH   outfall   area   located   near  the  Ko  Olina  Resort  area.     Sunday,   January   16   —   At   7   a.m.,   WMH   sent   its   cleanup   crew   back   to   the   area   and   evaluated  an  approximate  one-­half  to  three-­quarters  of  a  mile  section  of  the  beach,  including   a  return  to  the  outfall   area.  No  further  medical  waste  was  noted  by  WMH  personnel  at  this   time.   Additionally,   a   hotline   was   also   set   up   to   provide   the   public   with   the   opportunity   to   report   any   observations   of   medical   waste   material   found   on   local   beaches.   The   DOH   announced  the  hotline  to  the  public  via  news  media,  and  WMH  representatives  continued  to   remind   news   media   to   include   the   hotline   in   any   further   media   updates.   WMH   representatives  used  reports  provided  via  the  hotline  to  evaluate  information  and  determine   where   to   concentrate   its   ongoing   daily   cleanup   efforts.   Subsequently,   in   the   afternoon   of   January  16,  WMH  was  notified  that  some  plastic  syringes  (absent  needles)  had  been  found   at  the  White  Plains  beach  located  farther  south  on  the  shoreline.  WMH  dispatched  cleanup   crews   to   this   beach,   as   well   as   the   Kahe   public   beach   located   to   the   north   of   the   WMH   permitted  outfall.     Monday,   January   17   —   By   8   a.m.,   WMH   cleanup   crews   were   sent   to   all   three   of   the   aforementioned   areas   and   collected   additional   debris   from   the   shoreline,   including   what   appeared  to  be  a  lessening  amount  of  medical  waste.     Tuesday,   January   18   —   By   8   a.m.,   WMH   dispatched   cleanup   crews,   initially   focusing   attention  at  Nimitz  beach,  followed  by  White  Plains,  and  then  the  storm  water  outfall.     Wednesday,  January  19  —  By  8  a.m.,  the  cleanup  team  returned  to  Kahe  beach,  the  storm   water  outfall,  and  then  Nimitz  and  White  Plains  beaches,  in  order.  Crews  also  continued  to   be  responsive  to  reported  findings  from  the  public.     Thursday,  January  20  —  By  8  a.m.,  personnel  split  into  two  teams,  with  one  team  returning   to  Kahe  beach  and  the  storm  water  outfall,  and  the  other  team  returning  to  Nimitz  and  White   Plains  beaches.  Crews  also  continued  to  be  responsive  to  reported  findings  from  the  public.     Friday,  January  21  —  Beginning  at  8  a.m.,  the  cleanup  team  returned  to  Kahe,   Nimitz  and   White  Plains  beaches,  as  well  as  the  storm  water  outfall.  The  WMH  team  found  no  medical   waste.     Monday,  January  24  —  WMH  performed  a  final  beach  assessment  and  observed  no  waste   attributed  to  the  WGSL.      
  • 22.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  18  of  19     D.   RESOURCES  COMMITTED   Table  7  summarizes  WMH’s  good  faith  estimate  of   the  costs  incurred  by  WMH  during  the  removal   action.   During   the   removal   action,   WMH   spent   approximately   $2,252,501.64   on   third   party   costs.   This  cost  estimate  does  not  include  internal  costs  (e.g.,  labor)  incurred  by  WMH  or  the  City.  Invoices   and  backup  for  the  costs  incurred  area  are  presented  in  Appendix  E.   Table  7:  Costs  Incurred  to  WMH  during  Response  Activities   Invoice   No.   Date   Contractor   Description   Amount   2248   2/11/11   PCS   Vacuum  truck  and  misc.  storm  clean  up   $11,580.12   2249  R   2/11/11   PCS   E6  South  Pond   $168,604.33   (Revised   5/19/11)   2261   4/15/11   GBI   Storm  Water  Response   $103,322.45   2262   4/15/11   GBI     Storm  Water  Response,  Repair  liner  in  E6,  E6  Sump   $220,761.00   work   2263   4/15/11   GBI   Storm  Water  Response,  Repair  liner  in  E6,  E6  Sump   $353,526.73   work   2267   4/30/11   American   Storm  Related  Liner  Repairs   $78,901.26   Environmental  Group,   LTD   2268   4/30/11   Watanabe  Ing,  LLP   Storm  Event  Legal  Fees   $45,126.86   2269   4/30/11   AECOM   Storm  Event  Sampling   $17,935.67   2270   4/30/11   GEI   Storm  Event  Work  Plans   $19,204.75   2274   5/19/11   GBI   Storm  Related  Costs  including  Repair  Liner,  E6   $125,918.41   Leachate  sump,  repair  damage  to  slope  of  West  Berm   Phase  III   2277   5/23/11   AECOM   CQA  for  Storm  Event  Costs   $40,008.62   2278   5/26/11     Security  Cost  Increase   $10,502.62   2279   5/24/11   PCS   Leachate   $242,562.88   2280   5/23/11   PCS   Miscellaneous  Storm  Event  Charges   $4,867.67   2282   5/24/11   PCS   Storm  Water,  Sediment  Pond  Pumping   $226,465.28   2283   5/24/11   PCS   Storm  Water,  Sediment  Pond  and  Cell  E6  Pumping   $32,565.76   2286   5/24/11   GBI   Storm  Related  Costs  including  Repair  Liner,  E6   $250,564.30   Leachate  sump,  repair  damage  to  slope  of  West  Berm   Phase  III   2291   6/13/11   GBI   Storm  Related  Costs  including  Repair  Liner,  E6   $160,328.86   Leachate  sump,  repair  damage  to  slope  of  West  Berm   Phase  III   6705   7/31/11   GBI   Sedimentation  Basin  Restoration     $139,754.07   TOTAL   $2,252,501.64   Note:   Costs  do  not  include  WMH  markup  and  Hawaii  general  excise  tax  (GET).     II.   EFFECTIVENESS  OF  REMOVAL  ACTIONS   A.   ACTIONS  TAKEN  BY  OPERATOR     WMH   executed   all   requirements   of   the   Order   in   a   timely   manner.   When   unable   to   meet   initial   deadlines,   extensions   were   requested   and   granted   by   the   EPA.   WMH   hired   subcontractors   to   perform  the  required  activities  on  site  and  communicated  regularly  with  the  regulators.    
  • 23.   Removal  Action  Summary  Report   August  2011   Waimanalo  Gulch  Sanitary  Landfill,  Kapolei,  O‘ahu,  HI   Page  19  of  19     B.   ACTIONS  TAKEN  BY  STATE  AND  LOCAL  FORCES   The  DOH  Clean  Water  Branch  performed   storm  water  sampling  at  the  site   on  January   13,  2011  in   conjunction   with   samples   collected   for   WMH   by   AECOM.   Sampling   included   storm   water   from   the   site  outfall  location,  the  ocean  outfall  location,  and  an  up-­canyon  location.   The  City  provided  storm  water  pumping  and  transportation  to  the  WWTP,  conducted  various  beach   cleanup  activities,  posted  warning  signs  surrounding  beaches,  and  provided  public  notices  via  press   releases  of  the  activities  going  on  at  WGSL.     C.   ACTIONS  TAKEN  BY  FEDERAL  AGENCIES  AND  SPECIAL  TEAMS   The  EPA  Region  9  office  provided  oversight  of  all  response  action  activities  including  the  On-­Scene   Coordinator  and  the  RCRA  Action  Officer  including  review  of  the  daily  and  weekly  progress  reports,   and  review/approval  of  all  work  plans  and  reports  that  were  initiated  as  a  result  of  the  Order.   D.   ACTIONS  TAKEN  BY  CONTRACTORS,  PRIVATE  GROUPS,  AND  VOLUNTEERS   GEI  Consultants,  Inc.  and  Geosyntec  Consultants,  Inc.  provided  work  plans  for  the  activities  required   by   the   Order.   PCS   provided   pumping   and   transport   services   for   the   storm   water.   GBI   performed   general   earthwork   and   construction   services   during   the   execution   of   the   work   plans.   AECOM   provided  Construction  Quality  Assurance  oversight  of  the  activities  including  documentation  of  work   performed.     Volunteers   were   not   present   on   site   during   the   removal   action;;   however,   some   volunteers   in   the   surrounding   community   helped   clear   storm   drains,   sewer   lines,   and   City   beaches   after   the   storm.   However,  these  activities  were  not  part  of  the  response  action.   III.   RECOMMENDATIONS   A.   MEANS  TO  PREVENT  A  RECURRENCE  OF  THE  DISCHARGE  OR  RELEASE   The  amount  of  rain  that  fell  in  December  2010  and  January  2011  was  extremely  unusual  and  not  a   typical  rainfall  pattern  for  the  area.  The  storm  event  concluding  on  January  13th  was  described  as  a   “100-­year   storm”   event.   Based   on   rainfall   data   from   the   up-­canyon   Palehua   rain   gauge,   the   first   major   storm   that   occurred   on   December   19-­20,   2010   generated   a   total   recorded   rainfall   at   the   Palehua  station  of  10.44  inches.  The  second  significant  rain  event  occurred  on  December  26-­27  and   generated  a  total  recorded  rainfall  at  the   nearby   Palehua   weather  station  of  station   of  5.68   inches.   The  storm  was  significant  because  it  occurred  less  than  one  week  after  the  December  19-­20  storm.   The  third  and  largest  storm  occurred  on  January  12-­13,  2011.  The  storm  produced  12.21  inches  of   rain  in  total,  with  10.68  inches  of  rain  falling  in  a  24-­hour  period.  Most  significant  was  the  short-­term   intensity  of  this  storm,  which  generated  7.63  inches  of  rain  during  a  6-­hour  period,  6.23  inches  of  rain   over  a  3-­hour  period,  and  3.65  inches  of  rain  over  a  1-­hour  period.   Prior  to  completion  of  the  western  storm  water  diversion  system,  run-­on  to  the  WGSL  was  managed   with   on-­site   surface   water   conveyance   systems   which   routed   storm   water   through   the   site.   The   western   storm   water   diversion   system   (also   described   as   the   offsite   surface   water   conveyance)   is   designed   bypass   the   24-­hour,   25-­year   storm   flows   and   can   handle   flow   from   a   100-­year,   24-­hour   storm   with   minimal   or   no   damage   occurring.   When   all   portions   of   the   system   are   completed,   the   system   will   bypass   run-­on   around   the   landfill   and   discharge   to   a   stilling   basin   to   be   constructed   below  the  existing  sedimentation  basin.     The   upper   portion   of   the   western   storm   water   diversion   system   was   functionally   complete   on   February   15,   2011   and   constructed   per   the   approved   design   specifications.   A   Surface   Water   Management  Plan  has  been  submitted  to  and  approved  by  the  EPA  that  describes  the  surface  water   management   features   present   at   WGSL.   More   information   can   be   found   in   the   Surface   Water   Management  Plan,  located  in  Appendix  D.      
  • 24.  
  • 25.   Appendix  A   Correspondence        
  • 26.  
  • 27. FOR IMMEDIATE RELEASE Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com WASTE MANAGEMENT: UPDATE ON BEACH CLEANUP POST STORM Public Hotline Remains Open for Reports of Any Further Findings HONOLULU – Jan. 24, 2011 – Waste Management of Hawaii (WM) provided an update following the “100-year storm” that hit Oahu on Jan. 13. The downpour made it necessary for the Waimanalo Gulch Sanitary Landfill, operated by WM for the City and County of Honolulu, to discharge storm water into the ocean. The extreme nature of the Jan. 13 floodwaters resulted in an unusual amount of debris. The following is a summary of WM shoreline cleanup activities. The WM cleanup team was also continuously responsive to reported findings from the public. WM established a hotline for individuals to report waste on beaches near the landfill. Thursday, Jan. 13 — WM evaluated storm water conditions throughout the day of the storm event and determined that a large body of storm water had collected in the area of the new cell construction. Working in collaboration with the state Department of Health (DOH), WM and the city installed warning signs in the shoreline area of the Ko Olina Resort, where the landfill outfall is located, and along the associated beach shoreline. Additionally, WM and the city began a water-quality sampling program that same day. Later on Jan. 13, WM began debris cleanup at the overflow and the storm water sedimentation basin once the flood waters had subsided enough to perform this operation safely. At that time, it was determined that the debris also contained sterilized medical waste. Friday, Jan. 14 — WM dispatched an evaluation and cleanup team to the ocean side of the landfill’s permitted storm water outfall, located on the north end of the Ko Olina Resort property across Farrington Highway from the landfill. The crew spent several hours cleaning debris from this area. At the time, there was no apparent evidence of remaining medical waste material. WM continued to clean up areas located between the sediment basin and the permitted outfall. Also on Jan. 14, representatives of WM, the city and DOH held a press conference at the landfill to further inform the public of potential concerns associated with the storm events, and to provide an update on the cleanup efforts, warning sign postings and water quality sampling being performed by WM and the city. Numerous news interviews and media announcements were provided by all parties over the following several days in order to keep the public fully informed. Saturday, Jan. 15 — WM personnel continued evaluation of the shoreline area. In the afternoon, additional medical waste material was reported in the WM outfall area located near the Ko Olina Resort area. Sunday, Jan. 16 — At 7 a.m., WM sent its cleanup crew back to the area and evaluated an approximate one-half to three-quarters of a mile section of the beach, including a return to the outfall area. No further medical waste was noted by WM personnel at this time. Additionally, a hotline was also set up to provide the public with the opportunity to report any observations of medical waste material (more)
  • 28. Waste Management Provides Update on Beach Cleanup following Jan. 13 Storm Page 2 of 2 found on local beaches. The DOH announced the hotline to the public via news media, and WM representatives continued to remind news media to include the hotline in any further media updates. WM representatives used reports provided via the hotline to evaluate information and determine where to concentrate its ongoing daily cleanup efforts. Subsequently, in the afternoon of Jan. 16, WM was notified that some plastic syringes (absent needles) had been found at the White Plains beach located farther south on the shoreline. WM dispatched cleanup crews to this beach, as well as the Kahe public beach located to the north of the WM permitted outfall. Monday, Jan. 17 — By 8 a.m., WM cleanup crews were sent to all three of the aforementioned areas and collected additional debris from the shoreline, including what appeared to be a lessening amount of medical waste. Tuesday, Jan. 18 — By 8 a.m., WM dispatched cleanup crews, initially focusing attention at Nimitz beach, followed by White Plains and then the storm water outfall. Wednesday, Jan. 19 — By 8 a.m., the cleanup team returned to Kahe beach, the storm water outfall, and then Nimitz and White Plains beaches, in order. Crews also continued to be responsive to reported findings from the public. Thursday, Jan. 20 — By 8 a.m., personnel split into two teams, with one team returning to Kahe beach and the storm water outfall, and the other team returning to Nimitz and White Plains beaches. Crews also continued to be responsive to reported findings from the public. Friday, Jan. 21 — Beginning at 8 a.m., the cleanup team returned to Kahe, Nimitz and White Plains beaches, as well as the storm water outfall. The WM team found no medical waste. WM is working closely with city and state officials to monitor the beaches until water testing in the area shows normal levels and they are free of landfill debris. That determination will be made in cooperation with city and state health officials. These officials, along with the U.S. Environmental Protection Agency, have approved WM processes and procedures to clean up these areas. In addition, a diversion channel that would have averted the debris discharge caused by the Jan. 13 storm is mere weeks from completion. WM will continue to maintain its hotline for the foreseeable future. WM encourages anyone who finds waste on beaches near the landfill to report it by calling (808) 668-2985. Waste Management of Hawaii operates Waimanalo Gulch, West Hawaii and Kekaha Landfills as an integral part of each county's solid waste management infrastructure. The facilities handle municipal solid waste, which is heavily regulated, monitored and controlled by local, state and federal government agencies. For more information, visit www.keepinghawaiiclean.com. ###
  • 29. FOR IMMEDIATE RELEASE Media Contact: Keith DeMello McNeil Wilson Communications 808-539-3482 keith.demello@mwc-anthology.com WAIMANALO GULCH LANDFILL AGREES TO WORK PLANS WITH U.S. EPA HONOLULU, Jan. 25, 2011 – Waste Management of Hawaii (WM) today announced it has entered into a formal agreement with the United States Environmental Protection Agency (EPS) regarding several work plans needed to alleviate damage to the Waimanalo Gulch Landfill caused by the 100- year storm of Jan. 13, 2011. The intense storm that hit Oahu made it necessary for the Waimanalo Gulch Landfill, operated by WM for the City and County of Honolulu, to discharge large volumes of storm water from the landfill into the ocean. Some limited amounts of solid waste were swept along with the storm water and discharged. WM is working with the EPA, the City and County of Honolulu and the state Department of Health to develop written plans that detail the steps that will be taken to clean up the landfill. “In the interest of keeping all parties informed, we want to let everyone know that we are working with the EPA on a consent agreement, which is a formal document dedicated to memorializing the work we need to do to get the landfill back into pre-storm shape,” said Joe Whelan, general manager of the Waimanalo Gulch Landfill. “While much of the work identified in the agreement is already underway, the agreement will serve to memorialize those commitments.” Whelan added that the WM clean-up team was out every day on the beaches picking up debris and that WM established a hotline (668-2985) for people to report waste they found on the beaches near the landfill. As of Jan. 25, the beaches were reopened for swimming but the landfill remained closed. Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by local, state and federal government agencies. The facility's staff includes 31 full-time employees, many of whom are active in the local community. In addition to its community contributions and significant volunteer efforts, Waste Management provides a benefit to the local economy of more than $2.9 million annually. To learn more about Waste Management’s commitment to the beautification of the islands, visit www.keepinghawaiiclean.com. ###
  • 30.  
  • 31. From: Kenefick, Andrew M To: Helmlinger.Andrew@epamail.epa.gov Cc: dviola@honolulu.gov Subject: WGSL Contractors Date: Tuesday, January 25, 2011 11:36:00 AM Andrew, The following is a list of the contractors being used by WMH. After execution of the AOC we will submit these names, as requried. If EPA thinks that it will not waive the requirements in paragraph 15 relating to the QMP, please let me know ASAP so that the Work will not be delayed. Thanks. AECOM: CQA firm for construction activities AEG: Liner installation/repair contractor Goodfellow Bros. Inc: General Contractor Pacific Commercial Services: Pumping contractor GeoSyntec: Design Engineer for landfill construction GEI: Design Engineer for drainage construction   Andrew  M.  Kenefick Senior  Legal  Counsel Waste  Management Western  Group  Legal  Department 801  2nd  Avenue,  Suite  614 Seattle,  WA  98104 206-­‐264-­‐3062  (direct) 866-­‐863-­‐7961  (direct  fax-­‐toll  free) 206-­‐264-­‐8212  (main  fax) akenefick@wm.com admitted  in  Washington   Our  renewable  energy  projects  create  enough  energy  to  power  more  than  one  million  homes. The  recovery  of  landfill  gas,  coupled  with  the  power  generated  from  the  conversion  of  solid  waste at  our  waste-­to-­energy  plants,  saves  the  equivalent  of  more  than  13  million  barrels  of  oil.   The  information  contained  in  this  e-­mail  message  may  be  privileged,   confidential  and  protected  from  disclosure.    If  you  are  not  the  intended   recipient,  any  dissemination,  distribution  or  copying  is  strictly  prohibited.     If  you  think  that  you  have  received  this  e-­mail  message  in  error,  please  e-­mail  the  sender  at  akenefick@wm.com  
  • 32. From: Helmlinger.Andrew@epamail.epa.gov To: Kenefick, Andrew M Cc: Baylor.Katherine@epamail.epa.gov; Moxley.Bret@epamail.epa.gov Subject: Confirmation of contractors at WGSL Date: Wednesday, January 26, 2011 7:23:18 AM Andrew; I write to confirm that both of EPA's project contacts have noted to me, at your request, that they are comfortable with the existing contractors at the WGSL site. The list of contractors that you provided satisfies the requirement for names and certifications of the contractors in the Jan. 25, 2011 AOC. If concerns arise, EPA will notify WM per the AOC. ____________________________________ J. Andrew Helmlinger Attorney Advisor U.S. Environmental Protection Agency 75 Hawthorne Street (ORC-3) San Francisco, CA 94105 Telephone: (415) 972-3904 Facsimile: (415) 947-3570
  • 33. From: Whelan, Joseph Sent: Thursday, January 27, 2011 12:30 PM To: Kabei.Arlene@epamail.epa.gov; Armann.Steve@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Tyahla.Stephen@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; Wall.Steve@epamail.epa.gov; baylor.katherine@epa.gov; stuart.yamada@doh.hawaii.gov; Steven.chang@doh.hawaii.gov Subject: WGSL Cell 6 Operations Report Greetings all. Please find attached a copy of the QC report documenting the evaluation and repairs made to waste disposal cell E6 located at WGSL. As noted, this cell has been cleared to resume waste placement per the terms of the report. Also attached is the requested contingency plan that addresses potential future storm events. We would appreciate your earliest review of these documents and approval to resume operations in Cell E6. As you know, there is a significant buildup of solid waste that requires landfill disposal at this time. Thank you for your quick response and your continued support during this ordeal. We appreciate your efforts. Best regards, Letter Report Cell Cell E6 MSW Area WGSL SW E6 and E4 R... 1-26-11.pdf ntingency Plan 1-26- Joe Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 34.  
  • 37. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; alec.wong@doh.hawaii.gov Subject: WGSL Daily Progress Report - AOC Date: Thursday, January 27, 2011 7:27:00 PM Greetings  all. Please  find  below  the  initial  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)East  side  assessment  and  repair  report  submitted  to  all  parties  on  1-­‐27-­‐11. 2)South  portion  of  west  side  assessment  to  commence  1-­‐28-­‐11 Western  Storm  water  Diversion  Project  (to  render  functional): 1) Diversion Structure: Poured half of walls 1-26-11, curing today, strip walls & clean storm mud tomorrow (Friday) 2) Box Culvert: Continue forming and placing steel for invert. Friday pour 250 lf of invert & place steel for invert. 3) Pipe: Remove over burden for final trench blast 1-26-11, today, final blast for pipe trench & excavated previous blast material, Friday, excavate pipe trench Cell  6  Leachate  Riser  Restoration: 1)The  controls  for  the  cell  6  leachate  riser  were  re-­‐established  today  at  the generator  and  storage  area. 2)Contractors  investigated  options  for  removal  of  the  silt  deposits  in  the leachate  riser  area  on  1-­‐26-­‐11  In  order  to  connect  the  riser  pumps.        Removed  approximately  4  feet  of  mud  (12,000  gallons)  today,  Friday continue  to  pump  down  mud Sediment  Basin:
  • 38.                1)pumped  60,000  gallons  today  and  sent  to  the  WWTP  for  treatment  and disposal,  Friday,  continue  pumping ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions. Best  regards, Joe Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 39. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Daily Progress Report - AOC Date: Friday, January 28, 2011 6:49:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)   EPA  approval was received  today allowing  WM to  resume  operations  in the east  side  of  cell E6. 2)    The  south  portion  of the west  side  assessment of  cell  E6 is  ongoing. Western  Storm  water  Diversion  Project  (to  render  functional): 1) Diversion Structure: The contractor stripped forms  from Wednesday’s concrete pour  and  began cleaning  storm  mud  and debris  from  the  rebar  supports.   From Saturday thru  Monday the forms  will  be  reset  for the next  pour. 2) Box Culvert: The contractor p oured  200  lf  of  invert concrete  in the  open  box channel, and  continued  placing  structural  steel forms.   From Saturday thru  Monday additional forming  and placement  of  structural  steel  will  continue  in  preparation  for invert   pours  on  Tuesday  and  Friday. 3) Pipe: The contractor continued  excavating the  Hobas  pipe trench  and  placing  bedding  (aggregate  below  pipe).   These  same operations will  continue through  early  next  week  when  pipe  can be  placed. Cell  6  Leachate  Riser  Restoration: 1 )   Electricians  are  preparing the controls  and  generator  for the  leachate pump  at the  storage tank.    The pumping contractor continues removing  water  from  pond  surface.  
  • 40. 2)    The  contractor pumped  20,321  gallons  of  silt  from the south  pond  area.   From  Saturday  thru  Monday the  contractor  will continue  to  pump  silt  from  south  pond.       Sediment  Basin: 1)The  contractor pumped  60,000  gallons of storm  water again today which  was  sent  to  the  WWTP  for  treatment  and  disposal.   From Saturday  thru  Monday the  contractor  will  continue    this pumping. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 41. From: Kabei.Arlene@epamail.epa.gov Sent: Friday, January 28, 2011 10:56 AM To: Whelan, Joseph Cc: gary.gill@doh.hawaii.gov; stuart.yamada@doh.hawaii.com; Takata.Keith@epamail.epa.gov; Diamond.Jane@epamail.epa.gov; Scott.Jeff@epamail.epa.gov; Baylor.Katherine@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; Wampler.David@epamail.epa.gov; Barroll.Hugh@epamail.epa.gov; armann.steve@epa.gov; Vaille.Rich@epamail.epa.gov; Wall.Steve@epamail.epa.gov; Sheehan.Eileen@epamail.epa.gov; Huetteman.Tom@epamail.epa.gov; Higuchi.Dean@epamail.epa.gov; Ryerson.Teddy@epamail.epa.gov; Johnson.Kathleen@epamail.epa.gov; Glenn.William@epamail.epa.gov; Arlene_Kabei/Janice.Okubo@doh.hawaii.gov; tsteinberger@honolulu.gov Subject: Notice of EPA Approval to Operate Cell E6 at Waimanalo Gulch Landfill, Oahu HI Dear Mr. Whelan: We have reviewed and accept the Construction Quality Assurance Report submitted for the liner installation at Cell #E6. We have also reviewed your "Stormwater Management Update and Contingency Plan," Version 4, dated 1/27/2011, which supports your belief that the measures described in the document "will prevent waste material and stormwater that may come into contact with waste from exiting the facility in the event of a major storm." While WM has not yet completed the tasks yet due in the Administrative Order on Consent, dated January 25, 2011, USEPA recognizes that WM has made progress in improving the situation at the landfill and that the continued closure of the landfill may create a risk to public health from accumulating wastes, in particular sewer sludge, throughout Oahu. We encourage WM to continue to forge ahead quickly on completing the upper valley stormwater diversion system ("Western Drainage System") and continue enhancements to the temporary stormwater systems. It is our expectation that the Western Drainage System will be functional in 15 days. Until the system is functional, please continue to enhance the capabilities of the temporary stormwater control systems to manage the quantity of water experienced on January 13, 2011. Therefore, pursuant to Section VIII (g) of the Administrative Order on Consent, USEPA hereby approves, with conditions noted below, the operation of Cell #E6 to accept wastes at the Waimanalo Gulch Sanitary Landfill (WGSL). We understand that the Hawaii Department of Health has also notified you that they do not object to reopening of landfill Cell #E6. The reopening of WGSL is the best alternative to minimize the risks to human health and the environment associated with the handling of solid wastes on Oahu. This approval is not a determination WM's operation of WGSL has been or is currently in compliance with applicable laws governing the management of solid waste including, but not limited to, the Clean Water Act and the Resource Conservation and Recovery Act. Nor is it a determination that reopening the landfill is consistent with these laws. We approve reopening with the following conditions: With regard to Cell E6:
  • 42. 1) Waste is disposed only within the footprint designated on your hand-annotated drawing submitted with your Petition for Re-Opening; 2) As recommended by AECOM, waste placement operations should be kept a minimum of 50 feet away from the damaged western edge of E6; and 3) The western edge of Cell E6 should be repaired as expeditiously as practicable, with plan and schedule for repair provided to EPA within one week. With regard to the facility: 4) Waste Management must submit a revised stormwater contingency plan by February 1, 2011 that describes how WM will manage stormwater on the site in response to storm events to prevent the discharge to waters of the United State of solid wastes, leachate, and/or stormwater contaminated by pollutants generated at WGSL pending completion of the stormwater diversion system ("Western Drainage System") currently under construction. The contingency plan must list and/or describe, at minimum, the following: - type and quantity of on-site mobile heavy equipment WM employees can use to maintain stormwater systems in response to storm events, including, pumps, tractors, back-hoes; - names of the Waste Management point of contact, or points of contact, available at any time, and the number of WM employees who can be deployed if storm water management systems or equipment fail or are not properly operating; - how WM will monitor storm events and the process WM will follow to deploy employees on- site in response to storm events; - name and location of storm water management equipment or systems (e.g., retention basins, pipes, drains, etc.) that will be monitored and/or maintained by on-site employees in response to storm events; - types of corrective actions or maintenance activities that on-site employees should take in response to storm events to ensure storm water conveyance systems remain operational; - beach monitoring activities (including posting signs, and performing clean-up) that will occur if un-permitted storm water discharge from the landfill occurs. 5) No later than fifteen (15 days) after the completion of a functional storm water division structure (Western Drainage System) as required in 19.b. of EPA's Order, WM must revise and submit to EPA its SWPCP to incorporate the functional Western Drainage System and all ancillary storm water connections into its revised SWPCP consistent with the requirements of its storm water general permit. EPA sincerely appreciates your responsiveness to the information we requested for making this Approval determination. We recognize that much work and improvements at the site have been accomplished in short order since January 13th, 2011. Arlene Kabei Associate Director Waste Management Division USEPA, Region 9
  • 43. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Daily Progress Report Date: Monday, January 31, 2011 5:30:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  will  be removed  to  allow  the  liner  material to  be further  investigated.   The  assessment should  be  completed  by  this  Saturday. Western  Storm  water  Diversion  Project  (to  render  functional): 1) Diversion Structure: The contractor is resetting the wall forms and continues installing reinforcing steel rebar, in anticipation of pouring additional concrete wall material on Wednesday. 2) Box Culvert: The contractor has continued  placing  structural  steel  forms in  the  bottom  and  walls  of  the open  box culvert  in  preparation  for  invert   pours on  Tuesday  and  Friday. 3) Pipe: The contractor completed excavating the  Hobas  pipe trench  and continues placing  bedding  (aggregate below  pipe).    Pipe  placement  will commence  on  Tuesday. Cell  6  Leachate  Riser  Restoration:
  • 44. 1 )    The  pumping  contractor continues removing  water  from the  water surface.   2)    The  contractor has  lowered  the  silt  from  the  south  pond  area by  an  additional  2  feet.         Sediment  Basin: 1)The  contractor pumped 274,000  gallons of  storm  water from  the  sedimentation basin  from  Saturday  thru  Monday, which was  sent  to  the  WWTP  for  treatment  and disposal.   ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 45. FOR IMMEDIATE RELEASE Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com WASTE MANAGEMENT OF HAWAII PROVIDES UPDATE Recaps EPA Milestones Achieved for Waimanalo Gulch Sanitary Landfill HONOLULU – Jan. 31, 2011 – Waste Management of Hawaii (WM) today provided an update on the progress of work to alleviate damage to the Waimanalo Gulch Sanitary Landfill resulting from recent severe rainstorms and the company’s ongoing efforts with the City and County of Honolulu to fully restore landfill services to Oahu. The U.S. Environmental Protection Agency (EPA) approved WM resuming operations in the eastern portion of cell E6, which was damaged in the Jan. 13 storm. While the landfill remains closed to the public, on Friday the landfill began accepting limited city deliveries of critical waste items, such as H- POWER residue and wastewater sludge. The storm water that collected in the area of cell E6 has been removed. On Thursday alone, contractors removed approximately 4 feet of mud (12,000 gallons) and pumped 60,000 gallons from the sediment basin, sending it to the wastewater treatment plant for proper treatment and disposal. Furthermore, half of the walls for the new storm water diversion channel have been poured and set to cure. “As of today, WM has met all milestone deadlines for the Waimanalo Gulch Sanitary Landfill outlined in our Jan. 25 consent agreement with the EPA,” said Joe Whelan, general manager of the landfill. “We are making progress in meeting those that remain according to the agreed upon calendar. This includes the completion of the new storm water diversion channel, already in progress.” WM began filing regular progress reports every weekday to EPA and state Department of Health, as outlined in the company’s agreement with the EPA. While much of the work identified in the agreement was already underway, the agreement served to memorialize commitments. Although beaches were declared on Jan. 25 to be safe for swimming, WM continues to encourage those who find debris appearing to be from the landfill to report it by calling (808) 668-2985. Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility (more)
  • 46. Waste Management of Hawaii Provides Update Page 2 of 2 is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by local, state and federal government agencies. The facility's staff includes 31 full-time employees, many of whom are active in the local community. In addition to its community contributions and significant volunteer efforts, Waste Management provides a benefit to the local economy of more than $2.9 million annually. To learn more about Waste Management’s commitment to the beautification of the islands, visit www.keepinghawaiiclean.com ###
  • 47. From: Whelan, Joseph Sent: Tuesday, February 01, 2011 4:52 PM To: 'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov'; 'stuart.yamada@doh.hawaii.gov' Subject: EPA AOC Work Plan Submittals Greetings all. Please find attached an electronic version of the various work plans and reports that are due today as a result of the terms of the Administrative Order on Consent (AOC). Hard copies of each submittal were sent to you by certified mail dated February 1, 2011. Please let me know if you have any questions. We look forward to receiving your approval. Best regards, Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council. DOC admin order consent.pdf
  • 48.  
  • 49. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Daily Progress Report Date: Tuesday, February 01, 2011 5:26:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench is  being removed  to  allow  the  liner  material to  be further  investigated.   The  assessment should  be  completed  by  this  Saturday. Western  Storm  water  Diversion  Project  (to  render  functional): 1) Diversion Structure: The contractor continues to place the wall forms and reinforcing steel rebar, in anticipation of pouring additional concrete wall material on Wednesday. 2) Box Culvert: The contractor poured concrete today to place the invert box culvert, Tomorrow he will resume placing  structural  steel  forms  in  the bottom  and  walls  of  the open  box  culvert in  preparation  for  invert   pours  on Friday. 3) Pipe: Placement of  the large diameter Hobas pipe resumed today.   The contractor continues placing  bedding  (aggregate below  pipe). Cell  6  Leachate  Riser  Restoration:
  • 50. 1 )    The  pumping  contractor continues skimming water  from the  surface  of  the area  south  of Cell  E6,  and  transported 16,500  gallons  today  to  the  waste  water treatment  plant.   These activities are ongoing. 2)    The  contractor removed  16,000  gallons of  mud  and  water  mixture  from  the  area south  of  Cell  E6  and  placed  into  frac  tanks in  order  to allow  them  to  separate.    These activities  are  ongoing.       Sediment  Basin: 1)The  contractor pumped 56,000  gallons of  storm  water from  the  sedimentation basin today, which  was  sent  to  the  WWTP for  treatment  and  disposal.   These activities are ongoing. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 51. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: FW: AGSL Additional Submittal under AOC - H&S Plan Date: Tuesday, February 01, 2011 6:00:00 PM Attachments: WGSL IIPP JAN 2009.pdf Bloodborne Pathogen Plan.pdf 020_Confined_Space_Program.pdf PART E_ Emer_Action_Plan_Jan2011.pdf 035_Hazard_Communication.pdf 025_Lock-Out_Tag-Out.pdf 015_Personal_Protective_Equipment.pdf 055_Respiratory_Protection.pdf 021_Substance_Abuse_Program_for_Employees_and_Candidates.pdf 065_Forklift_Training.pdf 050_Welding,_Burning,_and_Hot_Works.pdf 030_Hearing_Conservation.pdf Round  two _____________________________________________ From: Whelan, Joseph Sent: Tuesday, February 01, 2011 4:59 PM To: 'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov'; 'stuart.yamada@doh.hawaii.gov' Subject: AGSL Additional Submittal under AOC - H&S Plan Greetings  all. Please  find  an  electronic  version  of  the  facility  Health  &  Safety  Plan,  per  the  terms  of  the AOC.    A  hard  copy  of  this  plan  is  being  sent  to  you  under  separate  cover,  as  the  file  size was  too  large  to  send  with  the  other  submittal. Best  regards,                     Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 52.  
  • 53. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: FW: EPA AOC Work Plan Submittals Date: Tuesday, February 01, 2011 5:59:00 PM Attachments: DOC admin order consent.pdf Hi  Steve.    Welcome  back!! _____________________________________________ From: Whelan, Joseph Sent: Tuesday, February 01, 2011 4:52 PM To: 'Moxley.Bret@epamail.epa.gov'; 'baylor.katherine@epa.gov'; 'stuart.yamada@doh.hawaii.gov' Subject: EPA AOC Work Plan Submittals Greetings  all. Please  find  attached  an  electronic  version  of  the  various  work  plans  and  reports  that are  due  today  as  a  result  of  the  terms  of  the  Administrative  Order  on  Consent  (AOC).    Hard copies  of  each  submittal  were  sent  to  you  by  certified  mail  dated  February  1,  2011.    Please let  me  know  if  you  have  any  questions.    We  look  forward  to  receiving  your  approval. Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 54.  
  • 55. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for 2-2-11 Date: Wednesday, February 02, 2011 7:06:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  is  being removed  to  allow  the  liner  material to  be further  investigated.   A temporary fill road was placed today to allow the excavator to access the side wall liner. The  assessment  should  be  completed  by this  Saturday. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:      The  contractor continues  to  place  the  wall  forms  and reinforcing  steel  rebar,  in  anticipation  of pouring  additional  concrete  wall  material on Thursday.     2)    Box  Culvert:     Placement  of  reinforcing steel  continued.  The  final  invert  pour is scheduled  for  Friday. 3)    Pipe:    Placement  of  the  large  diameter Hobas  pipe continued  today.   The contractor continues placing  bedding (aggregate  below and  around  the pipe),
  • 56. and  began  pressure  testing the  joints of placed  pipe. Cell  6  Leachate  Riser  Restoration: 1 )    The  pumping  contractor continues skimming  water  from the  surface  of  the area  south  of  Cell  E6,  and  transported 16,500  gallons again today  to  the  waste water  treatment  plant.   These activities are ongoing. 2)    The  contractor removed  10,000 gallons  of  mud  and  water  mixture  from  the area  south  of  Cell  E6 today, and  placed into  frac  tanks  in  order  to  allow  them  to separate.    These  activities  are  ongoing.       Sediment  Basin: 1)           The  contractor pumped 105,800  gallons of  storm  water from  the  sedimentation basin  today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified
  • 57. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for 2-3-11 Date: Thursday, February 03, 2011 8:00:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  is  being removed  to  allow  the  liner  material to  be further  investigated.   A temporary fill road was placed to allow the excavator to access the side wall liner. The assessment  should  be  completed  by  this Saturday. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     Concrete  wall material was  poured  today, and the contractor continues  to  place  the final wall forms  and  reinforcing  steel  rebar. 2)    Box  Culvert:     The  contractor  completed placement  of the  invert reinforcing  steel.   The  final  invert  pour  is  scheduled  for Friday.  3)    Pipe:    Placement  of  the  large  diameter Hobas  pipe and  backfilling continued today.   The  contractor continues pressure
  • 58. testing the  joints of  placed  pipe.    Pipe work  will  be  complete  Friday. Cell  6  Leachate  Riser  Restoration: 1 )    The  pumping  contractor continues skimming  water  from the  surface  of  the area  south  of  Cell  E6.   These activities are ongoing. 2)    The  contractor removed 12,500  gallons of  mud  and  water  mixture  from  the  area south  of  Cell  E6  today,  and  placed  into  frac tanks  in  order  to  allow  them  to  separate.   These  activities  are  ongoing.       Sediment  Basin: 1)           The  contractor pumped 55,800  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 59. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for 2-4-11 Date: Friday, February 04, 2011 5:20:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  is  being removed  to  allow  the  liner  material to  be further  investigated.   A temporary fill road was placed to allow an excavator to remove over burden from the storm in order to access the side wall liner, which was exposed today. Operations layer sand will be placed on Saturday. Liner crews have begun their evaluation of this area. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:    The  contractor closed all remaining forms today  in anticipation  of  the  final wall pour  on February  8 th . 2)    Box  Culvert:     The  contractor  completed pouring the channel invert  today.   Next weeks  efforts  will  concentrate  on forming the  transition  structure  from  box  culvert invert  to  pipe  invert.  3)    Pipe:    The  contractor  completed  laying the  Hobas  Pipe  today,  and continues
  • 60. pressure  testing the  joints of  placed  pipe.   Backfilling  of  the  pipe  trench  will  continue thru  next  week. Cell  6  Leachate  Riser  Restoration: 1 )    The  pumping  contractor continues skimming  water  from the  surface  of  the area  south  of  Cell  E6.   We anticipate Cell E6 riser connections to commence on Monday or Tuesday. 2)    The  contractor removed 10,000  gallons of  mud  and  water  mixture  from  the  area south  of  Cell  E6  today,  and  placed  into  frac tanks  in  order  to  allow  them  to  separate.   These  activities  are  ongoing.       Sediment  Basin: 1)           The  contractor pumped 61,500  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 61. From: Whelan, Joseph Sent: Friday, February 04, 2011 11:06 AM To: 'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov'; 'stuart.yamada@doh.hawaii.gov' Subject: EPA AOC Submission No. 2 Greetings all. Please find attached an electronic version of the work plans and reports that are due today as a result of the terms of the Administrative Order on Consent (AOC). Hard copies of each submittal were sent to you by certified mail dated February 4, 2011. Please let me know if you have any questions. We look forward to receiving your approval. DOCWGSL EPA DOCWGSL EPA OC SUBMISSION 2.p OC SUBMISSION 2 s Best regards, Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 62.  
  • 63. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: Near-term storm preparation at WGSL Date: Friday, February 04, 2011 2:51:00 PM Greetings  Steve.                                  Please  find  our  responses  to  your  referenced  request.                                  Best  regards,                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Friday, February 04, 2011 9:41 AM To: Whelan, Joseph Cc: Moxley.Bret@epamail.epa.gov; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; Wampler.David@epamail.epa.gov; Blake.Ellen@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov Subject: Near-term storm preparation at WGSL Joe, We are reviewing the submittals you provided on 1 February 2011 in response to our Administrative Order on Consent ("AOC") and our 28 January 2011 e-mail that conditionally approved re-opening of cell E6 at the Waimanalo Gulch Sanitary Landfill ("WGSL"). I anticipate sending you our detailed feedback on those work plans and schedules by the latter part of next week. However, in light of "heavy rain" being forecasted by NOAA for the vicinity of the WGSL this coming weekend, we are providing the below interim comments on your "Revised Storm Water Management Update & Contingency Plan," ("contingency plan") and would like your written response to these today. These particular comments generally concern near-term preparation for storm events and are either items that lack detail or are absent in the contingency plan Waste Management of Hawaii ("WMH") submitted on 1 February. (1) Please provide details on WMH's process for deciding when Cell E6 operations are to be shut- down due to rain storm events and how such a shut-down would be executed. [Whelan, Joe] The facility is currently closed to the public, which means our daily volumes are fairly small. Our normal procedures call for us to stop operations if rainfall amounts create either a safety, environmental or operations concern. If unloading or processing operations are severely affected, we would suspend operations, and begin covering the waste material placed that day. As you know, we only create a working face disposal area large enough to accept the predicted days waste receipts. Therefore, this area is very small now until we reopen to the public. Once operations are ceased, we will place daily cover over all exposed waste. This cover would meet interim cover requirements, which is one foot of soil, which is compacted after placement. (2) Please provide a description of how WMH would secure waste within Cell E6 in anticipation of a significant rain event. [Whelan, Joe] We have already evaluated and reinforced the existing DI- 1 interceptor manhole by placing a mound of large boulders in front of this manhole to prevent silt from washing over and covering the opening. Additionally, we have increased the height and breadth of the berm placed below this manhole in an effort to create a damned
  • 64. area in order to keep it from clogging with silt. Today we are also constructing a second berm located just above the northern leading edge of Cell E6 in order to dam up any water that fell in this area, and prevent it from entering Cell E6. This berm is slightly angled to divert water towards the northwest, so that in the event that this new berm over topped, storm water would be diverted into the previous Cell E6 lake area, but around any exist waste material. This berm would also be covered with liner material in order to prevent any breakthroughs. (3) Please inform us of the status (e.g., flanged or otherwise shut and secured) of the 36-inch diameter fiberglass manhole that connects to the 78-inch Hobas pipe, that is located just upstream of the temporary earthen berm that is directly downstream of Cell E6. [Whelan, Joe] This manhole is flanged off and covered by several feet of road base material, and not accessible to any storm water. (4) The contingency plan states, under item 5), that "The sedimentation basin, temporary berm in the Cell E6 area, 36 inch storm water diversion piping, and general facility drainage ditches will be monitored and maintained during potential storm events." Please describe the type and frequency of monitoring that will be performed, who will perform the monitoring, including after normal work hours (WMH's security service?). [Whelan, Joe] Waste Management and contractor employees are on site performing normal duties from approximately 6:00AM thru 7:00PM daily. We have a 24 hour 7 day per week security service who are trained to phone WM on call personnel in the event that a storm event hits the facility. Our employees would then provide an assessment of current conditions. I will give you a call in approximately an hour to discuss, but feel free to call me sooner. We appreciate your cooperation. Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]
  • 65. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for 2-7-11 Date: Monday, February 07, 2011 5:21:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench has  been removed  to  allow  the  liner  material to  be further  investigated.   Rains on Sunday kept the liner crew from re-installing the liner in this area within the anchor trench. This work will be addressed on Wednesday, weather permitting. A temporary fill road was placed to allow an excavator to remove over burden from the storm in order to access the side wall liner, which was exposed Friday and Saturday. Operations layer sand will be placed on Wednesday. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:    The  contractor closed all remaining forms  in  anticipation of  the  final  wall  pour  on  February  8 th .   Sunday  rains  prevented  work  in  this  area on  Monday  due  to  muddy  conditions. 2)    Box  Culvert:     The  contractor  completed pouring the  channel  invert on  Friday.   This weeks  efforts  will  concentrate  on  forming the  transition  structure  from  box  culvert
  • 66. invert  to  pipe  invert.  3)    Pipe:    The  contractor  completed  laying the  Hobas  Pipe on  Friday,  and completed pressure  testing the  joints of  placed  pipe.   Backfilling  of  the  pipe  trench  will  continue thru this  week. Cell  6  Leachate  Riser  Restoration: 1 )   We anticipate Cell E6 riser connections to commence on Tuesday and Wednesday. 2)    The  contractor removed 2500  gallons of  mud  and  water  mixture  from  the  area south  of  Cell  E6  today,  and  placed  into  frac tanks  in  order  to  allow  them  to  separate.   These  activities  are  ongoing. Rain all day Sunday hampered removal activity in this area.       Sediment  Basin: 1)           The  contractor pumped 24,700  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager
  • 67. Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 68.  
  • 69. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "baylor.katherine@epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 8, 2011 Date: Tuesday, February 08, 2011 5:16:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  was removed  to  allow  the  liner  material  to  be further  investigated. Assessment  of damage  in  southern  area  was  made  on Saturday  2/6.  Areas  to  be  repaired  have been  identified.  Repair  work  was  able  to commence  on  the  southern  portion  of  the E6  liner  slope  beginning  today.  The  repair work  seems  to  be  limited  to  restoring  the geotextile  to  its  originally  constructed condition.  Access  issues  will  cause  the repairs  to  be  ongoing  through  Thursday  if no  additional  damage  is  discovered  in  this area.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     Due  to  access issues  for  the  concrete  trucks  caused  by mud,  the  final  wall  pour  will  occur  on  2/9. 2)    Box  Culvert:     The  contractor continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.
  • 70. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of  HOBAS  pipe  will continue  through  this  week.  Backfill consists  of  CLSM  concrete. Cell  6  Leachate  Riser  Restoration: 1 )     Today  the  contractor  spread additional  wet  weather road  base material  in  this  area to  improve  access  to the  leachate  risers.   We anticipate Cell E6 riser connections to commence on Wednesday. 2)    The  contractor was not able to remove    mud  and  water  mixture  from  the area  south  of  Cell  E6  today, as  a  result  of the spreading  activities  noted  in  section  1. Sediment  Basin: 1)           The  contractor pumped 44,800  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii
  • 71. 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 72.  
  • 73. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: Daily Progress Report for February 8, 2011 Date: Wednesday, February 09, 2011 10:19:00 AM Hi  Steve.                                  Yes,  the  area  being  referenced  is  on  the  southern  end  of  the  west  side,  where  there  was only  minimal  pulling  of  the  liner.    We  do  inspect  it.    The  northern  area  has  not  been  further investigated  because  the  contractor  is  working  directly  above  it,  posing  a  potential  safety  concern.                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Wednesday, February 09, 2011 8:06 AM To: Whelan, Joseph Cc: alec.wong@doh.hawaii.gov; Moxley.Bret@epamail.epa.gov; Baylor.Katherine@epamail.epa.gov; Armann.Steve@epamail.epa.gov; Wall.Steve@epamail.epa.gov; Steven.chang@doh.hawaii.gov Subject: Re: Daily Progress Report for February 8, 2011 Joe, Thanks for keeping the daily reports coming. In the future, you no longer need to include Kathy Baylor on your cc: list. I do have one clarifying question regarding the Cell 6 assessment work: You say below that "The  repair  work  seems  to  be  limited  to  restoring  the  geotextile  to  its originally  constructed  condition." In this statement, by "geotextile" are you referring to the 16 oz/sy cushion geotextile that lies immediately beneath the Operations Layer? If yes, I'm a bit surprised since the photos of damage included your 27 Jan work plan seem a bit more severe; at a minimum, there seems to be buckling along most of the west side length. However, I recognize it's difficult to tell which photos are form the northern vs. southern portions of that western edge. In areas where damage does appear to be limited to the cushion geotextile, as reassurance, please in subsequent daily reports, ensure us that the systematic inspection of the underlying 60-mil HDPE in such areas, and as needed, underlying GCL and 40-mil HDPE geomembrane will be accomplished in accordance with the provided work plan. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and
  • 74. are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, Katherine Baylor/R9/USEPA/US@EPA, <stuart.yamada@doh.hawaii.gov>, <Steven.chang@doh.hawaii.gov>, <alec.wong@doh.hawaii.gov> Date: 02/08/2011 07:16 PM Subject: Daily Progress Report for February 8, 2011 Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side  assessment of  cell  E6  is  ongoing.   The  operations layer  of  protective  stone  located  above  the  anchor  trench  was  removed  to  allow  the  liner material  to  be  further  investigated. Assessment  of  damage  in  southern  area  was  made  on Saturday  2/6.  Areas  to  be  repaired  have  been  identified.  Repair  work  was  able  to commence  on  the  southern  portion  of  the  E6  liner  slope  beginning  today.  The  repair  work seems  to  be  limited  to  restoring  the  geotextile  to  its  originally  constructed  condition. Access  issues  will  cause  the  repairs  to  be  ongoing  through  Thursday  if  no  additional damage  is  discovered  in  this  area.     Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     Due  to  access  issues  for  the  concrete  trucks  caused  by  mud,  the final  wall  pour  will  occur  on  2/9. 2)    Box  Culvert:     The  contractor continued  working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of  HOBAS  pipe  will  continue  through  this  week.  Backfill  consists  of CLSM  concrete. Cell  6  Leachate  Riser  Restoration: 1 )     Today  the  contractor  spread  additional  wet  weather road  base  material  in  this  area
  • 75. to  improve  access  to  the  leachate  risers.   We anticipate Cell E6 riser connections to commence on Wednesday. 2)    The  contractor was not able to remove    mud  and  water  mixture  from  the  area  south  of Cell  E6  today, as  a  result  of  the spreading  activities  noted  in  section  1. Sediment  Basin: 1)           The  contractor pumped 44,800  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council. Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 76.  
  • 77. FOR IMMEDIATE RELEASE (DRAFT) Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com WASTE MANAGEMENT OF HAWAII PROVIDES UPDATE First Phase Complete, New Storm Water Diversion Channel Nears Completion HONOLULU – Feb. 8, 2011 – Waste Management of Hawaii (WM) today provided an update on the progress of work to repair damage to the Waimanalo Gulch Sanitary Landfill resulting from recent severe rainstorms and ongoing efforts with the City and County of Honolulu to fully restore landfill services to Oahu. While the landfill remains closed to the public, it continues to accept city deliveries of treated wastewater sludge and H-POWER ash residue, along with limited amounts of residential and bulky waste that are required to be mixed in for disposal. WM has completed the first of the three phases of work required before the landfill can be fully reopened. This first phase consisted of repairs to the eastern side of cell E6, damaged in the Jan. 13 storm. These repairs allowed for the partial reopening of the landfill on Jan. 28. The second and third phases consist of an ongoing assessment of the landfill liner on the west side of cell E6. Throughout each of the severe rainstorms of December and January, the liner remained in place; however, in the severest storm on Jan. 13, the edge of the liner that meets the side of the gulch wall was damaged by falling rock. The assessment will determine what repairs are needed before full use of the cell is restored. The new storm water diversion channel, already in progress at the time of the storms, is projected to be effectively complete on Feb. 15. WM has double shifts in place to facilitate the expeditious completion of the diversion channel. “While the new storm water diversion channel is not yet effectively complete, we are pleased to report that the channel redirected an amount of rain water around the landfill on Sunday, as designed,” said Joe Whelan, general manager of the landfill. Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent agreement with the U.S. Environmental Protection Agency, which served to memorialize and document much of the work that was already being implemented by WM. The document was symbolic of the EPA’s approval of WM and the City and County of Honolulu’s plan to address post- (more)
  • 78. Waste Management of Hawaii Provides Update Page 2 of 2 storm events and landfill repairs. WM is also filing daily progress reports to the EPA and state Department of Health. Although beaches were declared on Jan. 25 to be safe for swimming, WM continues to encourage those who find debris appearing to be from the landfill to report it by calling (808) 668-2985. Waste Management of Hawaii has operated Waimanalo Gulch Landfill as an integral part of the City and County of Honolulu’s solid waste management infrastructure for more than 20 years. The facility is permitted to handle municipal solid waste, which is heavily regulated, monitored and controlled by local, state and federal government agencies. The facility's staff includes 31 full-time employees, many of whom are active in the local community. In addition to its community contributions and significant volunteer efforts, Waste Management provides a benefit to the local economy of more than $2.9 million annually. To learn more about Waste Management’s commitment to the beautification of the islands, visit www.keepinghawaiiclean.com ###
  • 79. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 9, 2011 Date: Wednesday, February 09, 2011 5:25:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  assessment: 1)    The  south  portion  of the west  side assessment of  cell  E6  is  ongoing.   The operations  layer  of  protective  stone located  above  the  anchor  trench  was removed  to  allow  the  liner  material  to  be further  investigated.  Areas  to  be  repaired have  been  identified. Repair  work continued  on  the  southern  portion  of  the E6  liner  slope  today,  and  should  be completed  by  Thursday  or  Friday.    No additional  damage was discovered  in  this area  today. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section of  the  diversion  structure  was poured  today.   2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of  HOBAS  pipe  will continue  through  this  week.  Backfill consists  of  CLSM  concrete.
  • 80. Cell  6  Leachate  Riser  Restoration: 1 )      Today  the  contractor was  able  to resume  excavation around  the  leachate risers.   We anticipate Cell E6 riser connections to commence on Thursday or Friday. This work was delayed due to the muddy access conditions as a result of the Sunday rain event. Sediment  Basin: 1)           The  contractor pumped 52,277  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 81. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011 Date: Thursday, February 10, 2011 1:59:00 PM Hi  Steve.                                  I  am  requesting  the  delay  in  submitting  the  revised  SWPCP    per  condition  #5.                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, February 10, 2011 1:03 PM To: Whelan, Joseph Subject: RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011 Joe, That's a shame, my condolences to him and his family. I'm fine with the ten-day extension, but need clarification on the precise deliverable your referring to. Are you referring to resubmission of the "revised stromwater contingency plan" that was required as Condition #4 of our 28 January re-opening approval letter, or the revised "SWPCP" per Condition #5 of that same letter? The SWPCP deadline is 15 days after getting the diversion structure functional ( by 15 Feb, as you know), so 2 March. Thanks. Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Stephen Tyahla/R9/USEPA/US@EPA Date: 02/10/2011 02:42 PM Subject: RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011
  • 82. Thanks  Steve.                                  We  will  begin  working  on  the  requested  changes  right  away.    On  another  matter,  the  primary contributor  with  GEI  Consultants,    who  is  providing  our  modified  storm  water  plan  update,  has  experienced  a death  in  his  immediate  family,  and  will  be  out  of  pocket  for  a  short  period.    We  would  very  much  appreciate  your granting  a  ten  day  extension  to  submit  this  revised  plan.    We  still  anticipate  having  the  storm  water  diversion channel  functionally  complete  by  February  15 th ,  as  stated  in  the  AOC.    This  request  for  delay  would  only  affect the  submission  due  date  for  the  revised  storm  water  plan.    Thank  you  for  your  consideration  of  this  request.                                  Best  regards,                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, February 10, 2011 11:28 AM To: Whelan, Joseph Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Blake.Ellen@epamail.epa.gov; Wampler.David@epamail.epa.gov Subject: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011 Joe, EPA has completed it's review of the five deliverables you submitted on 1 February and one of the two deliverables you provided on 4 February in accordance with our 25 January 2011 Administrative Order on Consent ("AOC") concerning the Waimanalo Gulch Sanitary Landfill ("WGSL"). We also completed our review of the “Revised Storm Water Management Update & Contingency Plan” you submitted on 1 February 2011 per Condition # 4 of EPA’s 28 January 2011 e-mail that conditionally approved re- opening of Cell E6. Our detailed comments are provided in the attached table. Revised work plans or items requiring revision are to be submitted to EPA within 15 days of your receipt of these comments (therefore, by Friday, 25 February 2011). Here is a summary of the results of our review: [1] “Description of collection & treatment associated with liquid located behind the temporary berm” (submitted per AOC paragraph 19.d.)-Acceptable with incorporation of the provided comments; revision and resubmission required. [2] “Work plan for managing potential Cell E6 hydraulic head” (Geosyntec Consultants’ letter of January 31, 2011; submitted per AOC paragraph 19.e.)-Approved, resubmission is not required; concurrence on due date (March 7, 2011) is required. [3] “Work plan for restoration of sedimentation basin” (GEI Consultants’ letter of January 31, 2011; submitted per AOC paragraph 19.h.)-Acceptable with incorporation of the provided comments; revision and resubmission required. [4] “Work plan for beach assessment & material recovery effort” (submitted per AOC paragraph 19.i.)-Acceptable with incorporation of the provided comments; revision and resubmission required.
  • 83. [5] “Revised Storm Water Management Update & Contingency Plan” (submitted per Condition 4) of EPA’s 28 January 2011 e-mail that conditionally approved re-opening of Cell E6)-Acceptable with incorporation of the provided comments; revision and resubmission required. [6] “Facility Health & Safety Plan” (submitted per AOC paragraph 21.)-Plan is accepted; resubmission is not required. [7] "Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter of January 27, 2011); (submitted per AOC paragraph 19.f.)-Plan is accepted; resubmission is not required, there are no comments on attached table for this workplan. However, concurrence by WMH on a deadline for completing the repair work, including completion of the CQA Report, is necessary. Based on the schedule provided and allowing 14 days for completion of the CQA report, EPA proposes a due date of 25 April 2011. EPA is in the process of retaining outside technical support to review the "Waimanalo Gulch Landfill Slope Stability Analysis and Work Plan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter of February 2, 2011; submitted by WMH on 4 February per AOC paragraph 19.a.). We will respond to that submission as soon as practicable. Please don't hesitate to contact me if you have any questions on the above or attached comments. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 84.  
  • 85. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011 Date: Thursday, February 10, 2011 12:42:00 PM Thanks  Steve.                                  We  will  begin  working  on  the  requested  changes  right  away.    On  another  matter,  the primary  contributor  with  GEI  Consultants,    who  is  providing  our  modified  storm  water  plan  update, has  experienced  a  death  in  his  immediate  family,  and  will  be  out  of  pocket  for  a  short  period.    We would  very  much  appreciate  your  granting  a  ten  day  extension  to  submit  this  revised  plan.    We  still anticipate  having  the  storm  water  diversion  channel  functionally  complete  by  February  15 th ,  as stated  in  the  AOC.    This  request  for  delay  would  only  affect  the  submission  due  date  for  the  revised storm  water  plan.    Thank  you  for  your  consideration  of  this  request.                                  Best  regards,                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, February 10, 2011 11:28 AM To: Whelan, Joseph Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Blake.Ellen@epamail.epa.gov; Wampler.David@epamail.epa.gov Subject: EPA Review Comments on WGSL deliverables of 1 & 4 February 2011 Joe, EPA has completed it's review of the five deliverables you submitted on 1 February and one of the two deliverables you provided on 4 February in accordance with our 25 January 2011 Administrative Order on Consent ("AOC") concerning the Waimanalo Gulch Sanitary Landfill ("WGSL"). We also completed our review of the “Revised Storm Water Management Update & Contingency Plan” you submitted on 1 February 2011 per Condition # 4 of EPA’s 28 January 2011 e-mail that conditionally approved re- opening of Cell E6. Our detailed comments are provided in the attached table. Revised work plans or items requiring revision are to be submitted to EPA within 15 days of your receipt of these comments (therefore, by Friday, 25 February 2011). Here is a summary of the results of our review: [1] “Description of collection & treatment associated with liquid located behind the temporary berm” (submitted per AOC paragraph 19.d.)-Acceptable with incorporation of the provided comments; revision and resubmission required. [2] “Work plan for managing potential Cell E6 hydraulic head” (Geosyntec Consultants’ letter of January 31, 2011; submitted per AOC paragraph 19.e.)-Approved, resubmission is not required; concurrence on due date (March 7, 2011) is required.
  • 86. [3] “Work plan for restoration of sedimentation basin” (GEI Consultants’ letter of January 31, 2011; submitted per AOC paragraph 19.h.)-Acceptable with incorporation of the provided comments; revision and resubmission required. [4] “Work plan for beach assessment & material recovery effort” (submitted per AOC paragraph 19.i.)-Acceptable with incorporation of the provided comments; revision and resubmission required. [5] “Revised Storm Water Management Update & Contingency Plan” (submitted per Condition 4) of EPA’s 28 January 2011 e-mail that conditionally approved re-opening of Cell E6)-Acceptable with incorporation of the provided comments; revision and resubmission required. [6] “Facility Health & Safety Plan” (submitted per AOC paragraph 21.)-Plan is accepted; resubmission is not required. [7] "Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter of January 27, 2011); (submitted per AOC paragraph 19.f.)-Plan is accepted; resubmission is not required, there are no comments on attached table for this workplan. However, concurrence by WMH on a deadline for completing the repair work, including completion of the CQA Report, is necessary. Based on the schedule provided and allowing 14 days for completion of the CQA report, EPA proposes a due date of 25 April 2011. EPA is in the process of retaining outside technical support to review the "Waimanalo Gulch Landfill Slope Stability Analysis and Work Plan for Liner Evaluation and Repair" (Geosyntec Consultants’ letter of February 2, 2011; submitted by WMH on 4 February per AOC paragraph 19.a.). We will respond to that submission as soon as practicable. Please don't hesitate to contact me if you have any questions on the above or attached comments. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]
  • 87. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 10, 2011 Date: Thursday, February 10, 2011 3:45:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6 Assessment: 1)   Repair  work continued  on  the southwestern  portion  of  the  E6  liner  slope, and  should  be  completed  by  Friday.   The protective  geomembrane is  being  placed over  the  liner  today.   No  additional damage was discovered  in  this  area.  Once completed, select  stone  will  be  placed against  the  geomembrane. Western  Storm  water  Diversion  Project  (to  render  functional): 1)  Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured on  Wednesday.   These  forms  will be  removed  once  the  curing  process  is complete. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of  HOBAS  pipe  will continue  through  this  week.  Backfill consists  of  CLSM  concrete  followed  by select  stone. Cell  6  Leachate  Riser  Restoration:
  • 88. The  contractor continued  excavation  around  the  leachate  risers  today.   We 1)           anticipate Cell E6 riser connections to commence on Friday. This work was delayed due to the muddy access conditions as a result of the Sunday rain event. The contractor pumped 19,350 gallons of mud/water from the area around the 2)           risers today, and placed in on site frac tanks for separation purposes. 16,500 gallons of water was pumped from these frac tanks and transported to the waste water treatment plant. Sediment  Basin: 1)           The  contractor pumped 41,249  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 89. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 11, 2011 Date: Friday, February 11, 2011 5:06:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)   Repairs  were  made  to  the southwestern  portion  of  the  E6  liner system  today.  The  repairs  consisted primarily  of  removing  2  horizontal  wrinkles approximately  80  feet  long  that  had formed  in  the  upper  layer  of  60-­‐mil  HDPE geomembrane  near  the  top  of  slope.  The wrinkles  were  repaired  by  cutting  along  the wrinkle,  removing  the  slack,  and  extrusion welding  the  cut  area.  The  underlying  GCL layer  was  inspected  in  this  area  and  no damage  or  significant  hydration  was observed.  After  repairs  were  tested  by AEG  and  observed  by  AECOM,  the geomembrane  was  covered  with  a  16  oz/sy geotextile  protective  layer.  Inspection  and repair  of  the  E6 side  slope  just  north  of this  area  will  be  initiated  tomorrow  once the  area  has  had  a  chance  to  dry  out  from last  night’s  rain. Western  Storm  water  Diversion  Project  (to  render  functional): 1)  Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  on  Wednesday.    These  forms  will be  removed  once  the  curing  process  is
  • 90. complete. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of  HOBAS  pipe  will continue  through  this  week.  Backfill consists  of  CLSM  concrete  followed  by select  stone. Cell  6  Leachate  Riser  Restoration: The  contractor was  not  able  to continue  excavation  around  the  leachate  risers 1)           today,  as  a  result  of  local  rain  last  night  which  caused  additional  rain  water  to accumulate  in  this  area. This  water  is  being  pumped  out  today.   We anticipate Cell E6 riser connections to commence as soon as the water is removed and the top of the risers are exposed. The contractor pumped 9,675 gallons of mud/water from the area around the 2)           risers today, and placed in on site frac tanks for separation purposes. Sediment  Basin: 1)           The  contractor pumped 19,350  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager
  • 91. Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 92.  
  • 93. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 14, 2011 Date: Monday, February 14, 2011 5:19:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   A limited rain event affected the facility Sunday evening. There was no damage, however activities today were curtailed due to muddy conditions. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.    Mud was discovered  between  the  geomembrane  layers  in  this area,  which hydrated  the  GCL  locally.  The  impacted  area  appears  to  extend  20  feet  up from  the  toe  of the existing  trash  slope.   For  the  rest  of  today,  AEG  will  be  water  proofing the  area  in  case  it  rains  tonight.  Tomorrow  they  will  begin  replacing  the  GCL  and  covering with  60-­‐mil  HDPE  as  they  go.  This  work  should  take  approximately  2  to  3  days  to  complete. 2) The contractor pumped 32,818 gallons of storm water from Cell E6 over the weekend, which was transported to the WWTP for treatment and disposal. These activities are ongoing. Western  Storm  water  Diversion  Project  (to  render  functional): 1)  Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  on  Wednesday.    These  forms  will be  removed  once  the  curing  process  is complete. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete.
  • 94. Cell  6  Leachate  Riser  Restoration: The  contractor  was  not  able  to  continue  excavation  around  the  leachate  risers 1)           today,  as  a  result  of  local  rain  last  night  which  caused  additional  rain  water  to accumulate  in  this  area.    This  water  is  being  pumped  out  today.   We anticipate Cell E6 riser connections to commence as soon as the water is removed and the top of the risers are exposed. The contractor pumped 27,000 gallons of mud/water from the area around the 2)           risers over the weekend, and placed in on site frac tanks for separation purposes. Sediment  Basin: 1)           The  contractor pumped 32,700  gallons of  storm  water from  the  sedimentation  basin over  the  weekend, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed. The  contractor  will  attempt  to  drill  PZ1  on  Tuesday,  assuming  there  are  no weather  related  access  issues. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 95. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Diversion Channel Functionally Complete Date: Tuesday, February 15, 2011 4:14:00 PM Attachments: DSCF4895.jpg DSCF4900.jpg DSCF4892.jpg Greetings  all. Please  be  advised  that  as  of  today, construction  of  a  functional  storm  water  diversion structure located on  the west  side  above  Cell  #E6  is  complete,  per  Section  19.6,  of  the Administrative  Order  on  Consent  (AOC)  signed  on  January  25,  2010.   I  have  included supportive  pictures  for  your  review.   Pictures  1  &  2  depict  the  diversion  wall  showing  the water  pathway  into  the  open  channel,  picture  3  depicts  the bottom  of  the  diversion channel  showing  the  tie  in  to  the  in  place  Hobas  pipe.   Please  contact  me  if  you  have  any questions. Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 96.  
  • 97. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 15th Date: Tuesday, February 15, 2011 5:16:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.    Mud was  discovered  between  the  geomembrane  layers  in  this area,  which hydrated  the  GCL  locally. The  contractor  began  replacing  the affected GCL today, and  covering  with  60-­‐mil  HDPE  as  they  go.  This  work  should  take  approximately  2  to 3  days  to  complete. 2) The contractor pumped 47,759 gallons of storm water from Cell E6 today, which was transported to the WWTP for treatment and disposal. These activities are ongoing. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured last  Wednesday.    These  forms are now  being  removed. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC.
  • 98. Cell  6  Leachate  Riser  Restoration: The  contractor resumed  excavation  around  the  leachate  risers  today.   We 1)           anticipate Cell E6 riser connections to commence as soon as the water is removed and the top of the risers are exposed. The contractor pumped 44,000 gallons of mud/water from the area around the 2)           risers today, and placed in on site frac tanks for separation purposes. Sediment  Basin: 1)           The  contractor pumped 17,318  gallons of  storm  water from  the  sedimentation  basin today, which  was  sent  to  the  WWTP  for  treatment  and  disposal.   These activities are ongoing.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor completed  installation  of  PZ1  today,  no  water  was encountered during  the drilling process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 99. FOR IMMEDIATE RELEASE Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com STORM WATER DIVERSION CHANNEL NOW FUNCTIONAL AT LANDFILL HONOLULU – Feb. 15, 2011 – Waste Management of Hawaii (WM), which operates the Waimanalo Gulch Sanitary Landfill on behalf of the City and County of Honolulu, today announced the functional completion of a new $15 million storm water diversion channel that can now direct potential floodwaters around the active area of the landfill. The completion of this portion of the storm water diversion channel is an important milestone and meets the schedule and requirements of WM’s agreement with the U.S. EPA. The primary portion of the diversion channel system, the Western Drainage Project, is designed for a peak flow of 1,751 cubic feet per second within a 24-hour period. Over the next several months, WM will complete the lower portion of the system, including several thousand more feet of large diameter pipe and a separate “stilling basin” to contain excess storm water originating from above the landfill. The storm water conveyance system consists of a diversion wall that directs storm water into a 10 by 10 foot box culvert, followed by a series of large diameter centrifugally cast fiberglass-reinforced polymer pipe ranging from 78 to 102 inches in diameter. The channel’s construction was already in progress at the time of the Jan. 13 storm and two earlier, unusually heavy rainstorms occurring in December. The storm water diversion channel project began in November 2009. WM identified the need for the diversion channel years ago and proceeded with construction as soon as the necessary approvals were received. Double shifts where put in place before the winter season to facilitate the expeditious completion of the diversion channel. Other Ongoing Work Continues In addition to the diversion channel, evaluation and repairs continue to be made to the southwestern portion of the E6 liner system, with progress moving north. Most recent repairs primarily consisted of the removal of two approximately 80-foot “wrinkles” that had formed in the liner system’s upper layer near the top of the cell slope. Further inspection and repair remain and are ongoing, despite interruptions caused by this week’s rain and resulting rainwater accumulation. Any rainwater removed from the cell or sedimentation basin is being sent to the wastewater treatment plant for treatment and disposal. (more)
  • 100. STORM WATER DIVERSION CHANNEL NOW FUNCTIONAL AT LANDFILL Page 2 of 2 The landfill remains closed to the public but continues to accept city deliveries of treated wastewater sludge and H-POWER ash and residue, along with limited amounts of residential and bulky waste that are required to be mixed in for disposal. Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent agreement with the EPA, which served to memorialize and document the work that was already being implemented by WM. ### Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com
  • 101. MEDIA ADVISORY Landfill’s Diversion Channel Functional Tomorrow (B-roll, photos to be provided by 3 p.m.) What: Functional Completion of New Storm Water Diversion Channel When: Tuesday, Feb. 15, 2011 B-roll and photos to be provided by 3 p.m. Where: Waimanalo Gulch Sanitary Landfill Why: The new $15 million storm water diversion channel is designed to direct floodwaters, just like those that deluged the landfill over the last two months — most drastically on Jan. 13 — around the main area of the landfill instead of through it. Waste Management of Hawaii (WM), which operates the Waimanalo Gulch Sanitary Landfill for the City and County of Honolulu, anticipates the functional completion of the landfill’s storm water diversion channel tomorrow. This is a major milestone in WM’s consent agreement with the U.S. EPA. The channel’s construction was already in progress at the time of the storms. WM identified the need for the diversion channel years ago and proceeded as soon as the necessary approvals were received. Double shifts where put in place to facilitate the expeditious completion of the diversion channel. Last week, WM reported that the not-yet-completed diversion channel effectively redirected a portion of rainwater from a storm on Super Bowl Sunday. Waste Management continues to meet all milestone deadlines outlined in its Jan. 25 consent agreement with the EPA, which served to memorialize and document the work that was already being implemented by WM. ### Media Contact: Keith DeMello McNeil Wilson Communications (808) 542-5343 keith.demello@mwc-anthology.com
  • 102.  
  • 103. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 16, 2011 Date: Wednesday, February 16, 2011 5:06:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.    Mud was  discovered  between  the  geomembrane  layers  in  this area,  which hydrated  the  GCL  locally.  The  contractor  began  replacing  the affected GCL and  covering it with  60-­‐mil  HDPE on  Tuesday.  This  work is  ongoing  and should  take approximately  2  to  3  days  to  complete. 2) The contractor pumped 18,100 gallons of storm water from Cell E6 today, which was transported to the WWTP for treatment and disposal. These activities are ongoing. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  last  Wednesday.    These  forms  are now  being  removed. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.    The  contractor  began  pouring the box culvert walls  today.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of
  • 104. Section  19.b.  of  the  AOC. Cell  6  Leachate  Riser  Restoration: The  contractor continued  excavation  around  the  leachate  risers  today,  and  was 1)           successful  in  exposing  the entry  flanges.   We are in the process of re-connecting the electricity and plumbing at this time. The contractor pumped 33,200 gallons of water, which was transported to the 2)           WWTP, and 27,700 gallons of mud/water from the area around the risers today, and placed in on site frac tanks for separation purposes. Sediment  Basin: 1)           The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin today  due  to  the  low  level  of  free standing water. We  have  begun  removing  silt/rock material  from  the  northern  portion  of  the  sedimentation  basin.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1   on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 105. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: FW: Daily Progress Report for February 16, 2011 Date: Friday, February 18, 2011 5:20:00 PM Hi  Steve,                                  I  was  off  island  yesterday,  please  find  my  response  to  your  inquiry.    Have  a  great  weekend.                                  Best  regards,                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, February 17, 2011 7:00 AM To: Whelan, Joseph Subject: Re: Daily Progress Report for February 16, 2011 Joe, Thanks for the report. I have a couple of clarifying questions for you below, in red bold. Just making sure I understand. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 02/16/2011 07:06 PM Subject: Daily Progress Report for February 16, 2011
  • 106. Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1. Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.    Mud  was  discovered  between  the  geomembrane  layers  in  this area,  which  hydrated  the  GCL  locally.  The  contractor  began  replacing  the  affected  GCL  and covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing  and  should  take approximately  2  to  3  days  to  complete.     2. The contractor pumped 18,100 gallons of storm water from Cell E6 today, which was transported to the WWTP for treatment and disposal. Am I correct in thinking that this 18k gallons came from water accumulated on top of Cell E6, basically a separate pond, if you will, from the pond that's immediately upstream of the large temporary earthen berm? [Whelan, Joe] Yes. These activities are ongoing.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last Wednesday.    These  forms  are  now  being  removed. 2)    Box  Culvert:      The  contractor  continued  working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.      The contractor  began  pouring  the  box  culvert  walls  today. 3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 1. The  contractor  continued  excavation  around  the  leachate  risers  today,  and  was successful  in  exposing  the  entry  flanges.    We are in the process of re-connecting the electricity and plumbing at this time. Great news!!! [Whelan, Joe] This was made operational today and we are pumping from this riser 2. The contractor pumped 33,200 gallons of water, which was transported to the WWTP, and 27,700 gallons of mud/water from the area around the risers today, and placed in on site frac tanks for separation purposes. Am I correct in thinking that this water was pumped from the pond immediately upstream of the large temporary earthen berm? Thus, the E6 pond where the 18.1K gals was pumped is a separate pond further upstream (basically like when I was there). Actually, a current photo of the whole area from above would be helpful. [Whelan, Joe] yes, This is what was previously referred to as the “south pond”. Sediment  Basin: 1. The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin
  • 107. today  due  to  the  low  level  of  free  standing  water.  We  have  begun  removing  silt/rock material  from  the  northern  portion  of  the  sedimentation  basin.      How  is  the  silt/rock  being removed  and  where  is  it  going  (for  dewatering  I  suppose)? [Whelan, Joe] Only the fairly dry material is being removed by an excavator and placed into cell 6. This process allows the remaining silt and water mixture to further separate, the water to be pumped out and the silt to further dry.                Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.       Best  regards,     Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.     Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 108. <alec.wong@doh.hawaii.gov> Date: 02/16/2011 07:06 PM Subject: Daily Progress Report for February 16, 2011 Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1. Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.    Mud  was  discovered  between  the  geomembrane  layers  in  this area,  which  hydrated  the  GCL  locally.  The  contractor  began  replacing  the  affected  GCL  and covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing  and  should  take approximately  2  to  3  days  to  complete.     2. The contractor pumped 18,100 gallons of storm water from Cell E6 today, which was transported to the WWTP for treatment and disposal. Am I correct in thinking that this 18k gallons came from water accumulated on top of Cell E6, basically a separate pond, if you will, from the pond that's immediately upstream of the large temporary earthen berm? [Whelan, Joe] Yes. These activities are ongoing.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last Wednesday.    These  forms  are  now  being  removed. 2)    Box  Culvert:      The  contractor  continued  working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Rebar  work  on  box  culvert  walls  is  ongoing.      The contractor  began  pouring  the  box  culvert  walls  today. 3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 1. The  contractor  continued  excavation  around  the  leachate  risers  today,  and  was successful  in  exposing  the  entry  flanges.    We are in the process of re-connecting the electricity and plumbing at this time. Great news!!! [Whelan, Joe] This was made operational today and we are pumping from this riser 2. The contractor pumped 33,200 gallons of water, which was transported to the WWTP, and 27,700 gallons of mud/water from the area around the risers today, and placed in on site frac tanks for separation purposes. Am I correct in thinking that this water was pumped from the pond immediately upstream of the large temporary earthen berm? Thus, the E6 pond where the 18.1K gals was pumped is a separate pond further upstream
  • 109. (basically like when I was there). Actually, a current photo of the whole area from above would be helpful. [Whelan, Joe] yes, This is what was previously referred to as the “south pond”. Sediment  Basin: 1. The  contractor  was  not  able  to  pump  storm  water  from  the  sedimentation  basin today  due  to  the  low  level  of  free  standing  water.  We  have  begun  removing  silt/rock material  from  the  northern  portion  of  the  sedimentation  basin.      How  is  the  silt/rock  being removed  and  where  is  it  going  (for  dewatering  I  suppose)? [Whelan, Joe] Only the fairly dry material is being removed by an excavator and placed into cell 6. This process allows the remaining silt and water mixture to further separate, the water to be pumped out and the silt to further dry.                Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.       Best  regards,     Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.     Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 110.  
  • 111. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: WGSL Diversion Channel Functionally Complete - EPA Concurrence Date: Wednesday, February 16, 2011 8:49:00 AM Thanks  Steve.    Will  do.   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Wednesday, February 16, 2011 8:37 AM To: Whelan, Joseph Cc: 'alec.wong@doh.hawaii.gov'; Moxley.Bret@epamail.epa.gov; 'Steven.chang@doh.hawaii.gov'; 'stuart.yamada@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov Subject: WGSL Diversion Channel Functionally Complete - EPA Concurrence Joe, EPA concurs that, as evidenced below, WMH has completed construction of a functional storm water diversion structure on the west side above cell #E6 as required by paragraph 19.b. of our AOC of January 25, 2011. While your progress on the Western Surface Water Drainage Project has met this AOC-required milestone, request that you please continue to provide status updates of the remaining construction work on this project in your daily progress reports. Also, as I mentioned on the phone yesterday, I will be making a trip to Oahu the week of 7 March to visit a remedial site in the Campbell Industrial Park, and would like to spend either a morning or afternoon inspecting the work at your facility. As my schedule now stands, my visit to the landfill will most likely be on Thursday, 10 March, but I will keep you posted as the time comes nearer so we can coordinate. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 02/15/2011 06:14 PM Subject: WGSL Diversion Channel Functionally Complete
  • 112. Greetings  all.                  Please  be  advised  that  as  of  today,  construction  of  a  functional  storm  water  diversion  structure  located  on  the west  side  above  Cell  #E6  is  complete,  per  Section  19.6,  of  the  Administrative  Order  on  Consent  (AOC)  signed  on January  25,  2010.    I  have  included  supportive  pictures  for  your  review.    Pictures  1  &  2  depict  the  diversion  wall showing  the  water  pathway  into  the  open  channel,  picture  3  depicts  the  bottom  of  the  diversion  channel  showing  the tie  in  to  the  in  place  Hobas  pipe.    Please  contact  me  if  you  have  any  questions.                    Best  regards,                                      
  • 113.              
  • 114.       Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.  
  • 115.   Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 116.  
  • 117. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: FW: Daily Progress Report for February 16, 2011 Date: Friday, February 18, 2011 5:21:00 PM     From: Whelan, Joseph Sent: Friday, February 18, 2011 5:20 PM To: Tyahla.Stephen@epamail.epa.gov Subject: FW: Daily Progress Report for February 16, 2011 Hi  Steve,                                  I  was  off  island  yesterday,  please  find  my  response  to  your  inquiry.    Have  a  great  weekend.                                  Best  regards,                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, February 17, 2011 7:00 AM To: Whelan, Joseph Subject: Re: Daily Progress Report for February 16, 2011 Joe, Thanks for the report. I have a couple of clarifying questions for you below, in red bold. Just making sure I understand. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'"
  • 118.  
  • 119. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 17th Date: Thursday, February 17, 2011 3:39:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           Evaluation  and  repairs  continue  to  be  made  to  the  southwestern  portion  of  the  E6 liner  system  moving  north.      Mud  was  discovered  between  the  geomembrane  layers  in  this area,  which  hydrated  the  GCL  locally.    The  contractor  began  replacing  the  affected  GCL  and covering  it  with  60-­‐mil  HDPE  on  Tuesday.  This  work  is  ongoing ,  but  should  be  complete  on Friday. 2) Due to declining volumes, the contractor was not able to pump storm water from Cell E6 today. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  last  Wednesday.    These  forms  are now  being  removed. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.    The  contractor continued  pouring  the  box culvert  walls  today.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC.
  • 120. Cell  6  Leachate  Riser  Restoration: 1)           The  contractor continued  excavation  around  the  leachate  risers on  Wednesday, and  was  successful  in  exposing  the  entry  flanges.   We are in the process of re- connecting the electricity and plumbing at this time. The contractor pumped 55,000 gallons of mud/water from the area around the 2)           risers today, and placed in on site frac tanks for separation purposes. Sediment  Basin: 1)           The  contractor pumped  31,675  gallons    of  storm  water  from  the  sedimentation  basin today.    We  have  begun  removing  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin,  and  placing  this  material  into  the lined  portion  of  Cell  E6.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 121. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 18th Date: Friday, February 18, 2011 5:18:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  last  Wednesday.    These  forms  are now  being  removed. 2)    Box  Culvert:     The  contractor  continued working  on  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Rebar  work  on  box  culvert  walls  is  ongoing.    The  contractor  continued  pouring  the  box culvert  walls  today.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC. Cell  6  Leachate  Riser  Restoration: The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell 1)           E6  leachate  riser  today and  initiated  the  pumping  process.  
  • 122. 56,700 gallons was pumped from the E6 riser today and placed into the on site 2)           frac tanks. Sediment  Basin: 1)           The  contractor  pumped 57,718  gallons    of  storm  water  from  the  sedimentation  basin today,  which  was  transported  to  the  local  waste  water  treatment  plant.    We  have  begun removing  silt/rock  material  from  the  northern  portion  of  the  sedimentation  basin,  and placing  this  material  into  the  lined  portion  of  Cell  E6.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 123. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 21st Date: Monday, February 21, 2011 2:47:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  last  Wednesday.    These  forms  are now  being  removed. 2)    Box  Culvert:     The  contractor has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. This is  scheduled  to  be  poured  this       week.   Rebar  work  on  box  culvert  walls  is  ongoing.    3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC. Cell  6  Leachate  Riser  Restoration: The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell 1)           E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    
  • 124. 108,000 gallons was pumped from the E6 riser since Friday and placed into the 2)           on site frac tanks. Sediment  Basin: 1)           We continue  to  remove  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 125. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: Daily Progress Report for February 21st Date: Tuesday, February 22, 2011 5:59:00 PM Hi  Steve.                                  Please  see  my  responses  below.                                  Thanks.                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Tuesday, February 22, 2011 7:59 AM To: Whelan, Joseph Subject: Re: Daily Progress Report for February 21st Joe, A couple of question/comments in blue, below. Generally, thinking ahead to the Final Report, one thing we'll want included in that report are quantities and disposition of the various waste streams. Thanks! Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 02/21/2011 04:48 PM Subject: Daily Progress Report for February 21st
  • 126. Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1. The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system  are now  complete.      Our  consultant  is  assembling  the  CQA  report  for  this  work.   Please  provide  status  of  assessment  and  repair  work  for  the  northern  portion  of  the  west side  E6  liner  as  it  progresses;  including  a  brief  "look-­‐ahead"  for  work  planned  in  the upcoming  days  or  week. [Whelan, Joe] The contractor is in the process of removing the overburden from the side slope area directly above the northwestern section of the Cell E6 liner. This over burden is the result of excavating the diversion channel in this area. Once the overburden is removed, and all of it is relocated from above the liner, we can then begin the liner repairs to this area. We expect removal process to take about an additional 25 days to complete, at which time we will commence the liner repairs.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  was  poured  last Wednesday.    These  forms  are  now  being  removed. 2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box culvert  invert  to  pipe  invert.  This  is  scheduled  to  be  poured  this          week.    Rebar  work  on box  culvert  walls  is  ongoing.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  is  now  functionally  complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 1. The  contractor  completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.       2. 108,000 gallons was pumped from the E6 riser since Friday and placed into the on site frac tanks. 56.7k gals pumped on 18th and 108k gals on 21st. Please include in updates quantities removed from Frac tanks and taken to WWTP. The Frac tanks are 20k gals each, correct? I'm presuming that you're not holding a bunch of full Frac tanks on site. [Whelan, Joe] Sorry, these are the volumes that were transported and disposed of at the wwtp. Sediment  Basin: 1. We  continue  to  remove  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.                Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was
  • 127. encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.       Best  regards,     Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.     Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 128.  
  • 129. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 22, 2011 Date: Tuesday, February 22, 2011 5:57:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  was poured  last  Wednesday.    These  forms have been  removed  except  for  the  tie  in  to  the open  box  culvert  wall. 2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  This is  scheduled  to  be  poured  this          week.   Rebar  work  on  box  culvert  walls  is  ongoing.   Rains  today  resulted  in a  temporary  set back  to  this  effort.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC. Cell  6  Leachate  Riser  Restoration: 1)           The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell
  • 130. E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.     33,900 gallons was pumped from the E6 riser storage tank today and 2)           transported to the waste water treatment plant. Sediment  Basin: 1)           We  continue  to  remove  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin,  and  placing  this  material  into  the  lined  portion  of  Cell  E6.                  Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 131. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 23, 2011 Date: Wednesday, February 23, 2011 5:07:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure is  now  in place.   2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  This is  scheduled  to  be  poured next          week.   Rebar  work  on  box  culvert  walls  is  ongoing.    Rains again today  resulted  in  a  temporary set  back  to  these  efforts.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  now functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC. Cell  6  Leachate  Riser  Restoration: The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell 1)           E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.    
  • 132. There was no volume pumped from the E6 riser storage tank today due to a 2)           localized rain event. Sediment  Basin: 1)           Rain  out  today  resulting  in  no  removal  of  silt/rock  material  from  the  northern  portion of  the  sedimentation  basin. 2)           The contractor pumped 41,700 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 133. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report February 24, 2011 Date: Thursday, February 24, 2011 4:55:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  evaluation  and  repairs  to  the  southwestern  portion  of  the  E6  liner  system are now  complete.     Our  consultant  is  assembling  the  CQA  report  for  this  work. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert ties  into  the  Hobas  pipe.   Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  This is  scheduled  to  be  poured  next          week.   Rebar  work  on  box  culvert  walls  is  ongoing.   Afternoon  showers  again  today  resulted in  a further  set  back  to  these  efforts.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  functionally
  • 134. complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: The  contractor completed  re-­‐connecting  the  electricity  and  plumbing  to  the  Cell 1)           E6  leachate  riser  and  initiated  the  pumping  process  on  Friday.     There was no volume pumped from the E6 riser storage tank or the mud/water 2)           separation tanks again today due to afternoon showers all week, which created truck access issues. Sediment  Basin: 1)           Daily  showers  this  week  have  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The contractor pumped 54,900 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐5  and  PZ-­‐6.  No  water  was  encountered  at  any  time during  the  drilling.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.  The  contractor  completed  installation  of  PZ1    on  Tuesday,  no  water  was encountered  during  the  drilling  process. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of
  • 135. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 25, 2011 Date: Friday, February 25, 2011 4:51:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The QCA  report  documenting  the evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted February  25,  2011. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  This is  scheduled  to  be  poured  next          week.   Rebar  work  on  box  culvert  walls  is  ongoing.    Afternoon  showers received earlier  in  the week  resulted  in  a temporary  set  back  to these  efforts.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete.
  • 136. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 1)           There was no volume pumped from the Cell E6 leachate riser storage tank or the mud/water separation tanks again today due to afternoon showers all week, which created truck access issues. Sediment  Basin: 1)           Daily  showers earlier this  week  have  prevented  removal  of  silt/rock  material  from the  northern  portion  of  the  sedimentation  basin.   2)           The contractor pumped 56,800 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations PZ-­‐1, PZ-­‐5  and  PZ-­‐6. No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.    The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax
  • 137. From: Whelan, Joseph Sent: Friday, February 25, 2011 4:57 PM To: 'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov'; 'stuart.yamada@doh.hawaii.gov'; 'Steven.chang@doh.hawaii.gov'; 'alec.wong@doh.hawaii.gov' Subject: AOC Response to EPA Comments on WGSL February 1, 2011 Submittals Greetings all: EPA provided comments to several work plans required by the Administrative Order on Consent (AOC) on February 10, 2011. Please find attached the revised work plans and reports that are due today, February 25th. Our responses are included within the revised documents as requested. Additionally, EPA requested a proposed due date for the submission of the report documenting completion of the Cell E6 liner evaluation and repair. We have provided the parties with CQA reports documenting repairs to both the northeast and southwestern portions of this cell. As noted within our daily progress report of February 24, 2011, evaluation and repair to the liner within the northwestern section of Cell E6 will be delayed pending removal of the soil/rock over burden produced by the storm water diversion system construction. WMH proposes to provide this CQA report by May 15, 2011. Please let me know if you have any questions. Best regards, DOCAOC Collection and Hydraulic Head Sedimentation Basin PONSE LETTER 2 25 Transport of Li... Letter of Findi... Workplan r... Beach Assessment WGSL Revised SW Workplan Revi... Contingency Pl... Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 138.  
  • 139. From: Whelan, Joseph Sent: Friday, February 25, 2011 2:55 PM To: 'Moxley.Bret@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov'; 'stuart.yamada@doh.hawaii.gov'; 'Steven.chang@doh.hawaii.gov'; 'alec.wong@doh.hawaii.gov' Subject: CQA Report for Liner Repairs to the Southwestern Section of Cell E6 Greetings all. Please find attached the CQA report for the recently completed evaluation and repair to the liner located in the southwestern section of Cell E6. We would appreciate your timely review and approval of this report. Approval to place waste in this area is necessary in order for the landfill to reopen to the general public. Please contact me with any questions. Thank you. Best regards, Letter Report Cell MSW Placement E6 West Slo... Area_022111.pdf Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 140.  
  • 141. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for February 28, 2011 Date: Monday, February 28, 2011 5:02:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted  February  25,  2011.    Approval  to  resume  operations  in this  area  is  pending. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  This is  scheduled  to  be  poured  next          week.   Rebar  work  on  box  culvert  walls  is  ongoing.    3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete.
  • 142. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 105,300 gallons was pumped from the Cell E6 leachate riser storage tank since 1)           Friday and transported to the waste water treatment plant. 33,200 gallons of water was pumped from the south pond area since Friday and 2)           transported to the local waste water treatment plant. 30,772 gallons of mud/water was pumped from the south pond area since 3)           Friday and placed within the onsite separation tanks. Sediment  Basin: 1)           Daily  showers  earlier  this  week  have  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The contractor pumped 8,700 gallons of storm water from the sedimentation basin since Friday and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii
  • 143. 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 144.  
  • 145. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: Daily Progress Report for February 28, 2011 Date: Tuesday, March 01, 2011 9:24:00 AM Hi  Steve.                                  We  are  pouring  the  first  section  of  this  today.    Sorry  about  the  over  site.                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Tuesday, March 01, 2011 7:02 AM To: Whelan, Joseph Cc: 'alec.wong@doh.hawaii.gov'; Vaille.Rich@epamail.epa.gov; Armann.Steve@epamail.epa.gov; Wall.Steve@epamail.epa.gov; 'Steven.chang@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov Subject: Re: Daily Progress Report for February 28, 2011 Joe, Thanks for the update. One question: In your daily report for last Friday the 25th you said that concrete for the transition structure from box culvert to Hobas pipe was being poured "next week" which is now this week. But below you still refer to "next week." Confusing, I know. But is it actually getting poured this week? I'm looking forward to seeing the site on Thursday, 10 March, just after lunch, as we planned. I'm sure I'll be taking lots of pics and some video. Thankfully, it's looking good for a short continuing resolution to pass! This week I'll be reviewing all your resubmitted plans and will get back to you on those as quickly as practicable. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen
  • 146. Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 02/28/2011 07:02 PM Subject: Daily Progress Report for February 28, 2011   Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1. The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern  portion of  the  E6  liner  system  was  submitted  February  25,  2011.    Approval  to  resume  operations  in this  area  is  pending.   2. The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.       Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in  place.       2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box culvert  invert  to  pipe  invert.  This  is  scheduled  to  be  poured  next  week.    Rebar  work  on  box culvert  walls  is  ongoing.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  is  functionally  complete  per  the  terms  of  Section  19.b.  of  the AOC. Cell  6  Leachate  Riser  Restoration: 1. 105,300 gallons was pumped from the Cell E6 leachate riser storage tank since Friday and transported to the waste water treatment plant. 2. 33,200 gallons of water was pumped from the south pond area since Friday and transported to the local waste water treatment plant.   3. 30,772 gallons of mud/water was pumped from the south pond area since Friday and placed within the onsite separation tanks.
  • 147. Sediment  Basin: 1. Daily  showers  earlier  this  week  have  prevented  removal  of  silt/rock  material  from the  northern  portion  of  the  sedimentation  basin.     2. The contractor pumped 8,700 gallons of storm water from the sedimentation basin since Friday and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.     Beach Assessment Update: 1. The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.       Best  regards,     Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.     Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 148.  
  • 153. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 1, 2011 Date: Tuesday, March 01, 2011 5:33:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted  February  25,  2011.   We  received notification from DOH  today  concurring that  the  CQA report was  adequate  documentation  of  the  liner repairs,  which allows  WMH to  resume  operations  in  this  area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert. Half of  the  concrete  for  this  structure  was poured  today,  the  remainder  to  be  poured towards  the  end  of  the  week.   Rebar  work on  box  culvert  walls  is  ongoing.      3)    Pipe:     Backfilling  of the HOBAS  pipe
  • 154. channel  is  now  complete. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 30,700 gallons was pumped from the Cell E6 leachate riser storage tank today 1)           and transported to the waste water treatment plant. 11,000 gallons of water was pumped from the south pond area today and 2)           transported to the local waste water treatment plant. 3)           Zero gallons of mud/water was pumped from the south pond area today and placed within the onsite separation tanks. Sediment  Basin: 1)           Showers  Tuesday  and  Wednesday  last  week  have resulted  in  the  accumulation  of storm  water  which prevented  removal  of  silt/rock  material  from  the  northern  portion  of the  sedimentation  basin.   2)           The contractor pumped 15,500 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan
  • 155. General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 156.  
  • 157. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 2, 2011 Date: Wednesday, March 02, 2011 5:11:00 PM Greetings  all. Please  find  below  the  daily  progress  report  on  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from DOH on  March  1,  2011 concurring  that  the  CQA  report  was  adequate  documentation  of the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  construction  of  the  diversion  system  in  this  area  must  be removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks,  weather  permitting.   Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Half of  the  concrete  for  this  structure  was poured on  March  1,  2011,  the  remainder to  be  poured  towards  the  end  of  the week.   Rebar  work  on  box  culvert  walls  is ongoing.    
  • 158.  3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 13,000 gallons was pumped from the Cell E6 leachate riser storage tank today 1)           and transported to the waste water treatment plant. Zero gallons of water was pumped from the south pond area today and 2)           transported to the local waste water treatment plant. 3)           Zero gallons of mud/water was pumped from the south pond area today and placed within the onsite separation tanks. 31,000 gallons of water was pumped today from these separation tanks and and transported to the waste water treatment plant. Sediment  Basin: 1)           Showers  Tuesday  and  Wednesday  last  week  have  resulted  in  the  accumulation  of storm  water  which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of the  sedimentation  basin.   2)           The contractor pumped 40,000 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.     Best  regards,
  • 159. Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 160.  
  • 161. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: Photos of WGSL Date: Wednesday, March 02, 2011 11:24:00 AM Attachments: CIMG0555.JPG CIMG0551.JPG CIMG0558.JPG CIMG0559.JPG CIMG0564.JPG CIMG0560.JPG Request to allow Stormwater Discharge.pdf Hi  Steve. Please  find  attached  photos  taken  yesterday  at  the  WGSL  related  to  the  construction status  of  the  storm  water  diversion  structure  and  the  sedimentation  basin.   A  copy  of  the letter  to  DOH  requesting  approval  to  begin  active  discharging  from  the  sedimentation  basin is  attached.   Also,  this  email  is  intended  to  confirm  our  phone  conversation  yesterday, where  in you  concurred  that  EPA  is  not  required  to  provide  any  further  approvals  of  our CQA reports  documenting  liner  repairs  to  the  Cell  E6  area  of  the  site.    As  we  discussed,  we received  the DOH “no  objection”  letter  yesterday  that  allows  us  to  resume  operations  in the  southwestern  portion  of  this  cell.    Thank  you  for  your  continued  assistance  in  these matters. Best  regards, Joe         Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of
  • 162.  
  • 163. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 3,2011 Date: Thursday, March 03, 2011 7:13:00 PM Greetings  all. Please  find  below  the  daily  progress  report for  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the January  storm  event  and  the construction  of  the  diversion system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks, weather  permitting.   Rain  last  night  has  hampered  this  effort  temporarily. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Half of  the  concrete  for  this  structure  was poured  on  March  1,  2011,  the  remainder to  be  poured  towards  the  end  of  the week.   Rebar  work  on  box  culvert  walls  is
  • 164. ongoing.      3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 12,018 gallons was pumped from the Cell E6 leachate riser storage tank today 1)           and transported to the waste water treatment plant. 25,000 gallons of water was pumped from the south pond area today and 2)           transported to the local waste water treatment plant, due to an overnight rain event. Zero gallons of mud/water was pumped from the south pond area today and 3)           placed within the onsite separation tanks. Zero gallons of water was pumped today from these separation tanks, due to the muddy conditions resulting from the rain event last night. Sediment  Basin: 1)           Showers  last night  has  resulted  in  the additional accumulation  of  storm  water  which prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation basin.   2)           The contractor pumped 51,000 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know if  you  have  any  questions.    
  • 165. Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 166.  
  • 167. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 4, 2011 Date: Friday, March 04, 2011 4:24:00 PM Greetings  all. Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion of  the  E6  liner  system was  submitted  February  25,  2011.    We  received  notification  from DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the liner  repairs,  which  allows  WMH  to  resume  operations  in  this  area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011 storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  January  storm  event  and  the  construction  of  the  diversion system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2-­‐3  weeks, weather  permitting.    Rain again last  night  has  hampered  this  effort  temporarily. Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now  in place.     2)    Box  Culvert:     The  contractor  has completed  forming  the  transition  structure from  box  culvert  invert  to  pipe  invert.  Half of  the  concrete  for  this  structure  was poured  on  March  1,  2011,  the  remainder was to  be  poured  today,  Friday,  however muddy  conditions  as  a  result  of  last  nights
  • 168. rain has  postponed  this  to  early  next week.   Rebar  work  on  box  culvert  walls  is ongoing.      3)    Pipe:     Backfilling  of the HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is  functionally complete  per  the  terms  of  Section  19.b.  of the  AOC. Cell  6  Leachate  Riser  Restoration: 14,949 gallons was pumped from the Cell E6 leachate riser storage tank today 1)           and transported to the waste water treatment plant. Zero gallons of water was pumped from the south pond area today and 2)           transported to the local waste water treatment plant. 3)           Zero gallons of mud/water was pumped from the south pond area today and placed within the onsite separation tanks. Zero gallons of water was pumped today from these separation tanks, due to the muddy conditions resulting from the rain event again last night. Sediment  Basin: 1)           Showers this  week  have  resulted  in  the  additional  accumulation  of  storm  water  which prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation basin.   2)           The contractor pumped 59,700 gallons of storm water from the sedimentation basin today and transported to the waste water treatment plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were  not installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Beach Assessment Update: 1) The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­‐  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
  • 169. Please  let  me  know if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 170.  
  • 171. From: Frey, Jesse To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 7, 2011 Greetings  all.                On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today. Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1.   The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion  of  the  E6  liner  system  was submitted  February  25,  2011.    We  received  notification from  DOH  on  March  1,  2011  concurring  that  the  CQA report  was  adequate  documentation  of  the  liner  repairs, which  allows  WMH  to  resume  operations  in  this  area.   2.   The  northwest  section  of  the  Cell  E6  liner  was  also damaged  in  the  January  13,  2011  storm.    This  area  is located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  January  storm  event  and the  construction  of  the  diversion  system  in  this  area must  be  removed  prior  to  the  evaluation  and  repair  of the  liner.    This  removal  activity  is  ongoing  and  is expected  to  be  completed  within  the  next  2  weeks, weather  permitting.                  Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the diversion  structure  is  now  in  place.     2)    Box  Culvert:      The  contractor  has  completed  forming  the transition  structure  from  box  culvert  invert  to  pipe  invert.   Half  of  the  concrete  for  this  structure  was  poured  on  March 1,  2011.  The  remainder  is  scheduled  to  be  poured  on 3/10/2011.    Rebar  work  on  box  culvert  walls  is  ongoing.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now complete.
  • 172. 4)    The  diversion  structure  is  functionally  complete  per  the terms  of  Section  19.b.  of  the  AOC.                Cell  6  Leachate  Riser  Restoration: 1.   36,200  gallons  were  pumped  from  the  Cell  E6  leachate riser  storage  tank  today  and  transported  to  the  waste water  treatment  plant.   2.   Zero  gallons  of  water  was  pumped  from  the  south  pond area  today  and  transported  to  the  local  waste  water treatment  plant.   3.   Zero  gallons  of  mud/water  was  pumped  from  the  south pond  area  today  and  placed  within  the  onsite separation  tanks.  Zero  gallons  of  water  was  pumped today  from  these  separation  tanks.                  Sediment  Basin: 1.   Showers  this  week  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal of  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin.     2.   The  contractor  pumped  113,000  gallons  of  storm  water from  the  sedimentation  basin  today  and  transported  to the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we have  drilled  to  depth  at  temporary  piezometer  locations PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was observed,  temporary  piezometers  were  not  installed.     The  documentation  report  was  submitted  on  February 25,  2011.                  Beach  Assessment  Update: 1.   The  daily  beach  assessment  phase  of  this  task  is complete.    There  were  no  calls  received  at  the established  beach  waste  hot  line  today.  
  • 173. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Jesse  Frey Engineer Waste  Management  of  Hawaii 92-­‐460  Farrington  Hwy. Kapolei,  HI  96707 Ph:  808-­‐250-­‐0574 Fax:  808-­‐668-­‐1366      
  • 174.  
  • 175. From: Frey, Jesse To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 8, 2011 Greetings  all.                On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today. Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1.   The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion  of  the  E6  liner  system  was submitted  February  25,  2011.    We  received  notification from  DOH  on  March  1,  2011  concurring  that  the  CQA report  was  adequate  documentation  of  the  liner  repairs, which  allows  WMH  to  resume  operations  in  this  area.   2.   The  northwest  section  of  the  Cell  E6  liner  was  also damaged  in  the  January  13,  2011  storm.    This  area  is located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  January  storm  event  and the  construction  of  the  diversion  system  in  this  area must  be  removed  prior  to  the  evaluation  and  repair  of the  liner.    This  removal  activity  is  ongoing  and  is expected  to  be  completed  within  the  next  2  weeks, weather  permitting.                  Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the diversion  structure  is  now  in  place.     2)    Box  Culvert:      The  contractor  has  completed  forming  the transition  structure  from  box  culvert  invert  to  pipe  invert.   Half  of  the  concrete  for  this  structure  was  poured  on  March 1,  2011.  The  remainder  is  scheduled  to  be  poured  on 3/10/2011.    Rebar  work  on  box  culvert  walls  is  ongoing.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now complete.
  • 176. 4)    The  diversion  structure  is  functionally  complete  per  the terms  of  Section  19.b.  of  the  AOC.                Cell  6  Leachate  Riser  Restoration: 1.   0  gallons  were  pumped  from  the  Cell  E6  leachate  riser storage  tank  today  and  transported  to  the  waste  water treatment  plant.   2.   Zero  gallons  of  water  was  pumped  from  the  south  pond area  today  and  transported  to  the  local  waste  water treatment  plant.  This  area  currently  contains  no  ponded water  and  is  being  prepped  for  the  next  phase  of  the Western  Berm  Construction.   3.   Zero  gallons  of  mud/water  was  pumped  from  the  south pond  area  today  and  placed  within  the  onsite separation  tanks.  Zero  gallons  of  water  was  pumped today  from  these  separation  tanks.                  Sediment  Basin: 1.   Showers  this  week  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal of  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin.     2.   The  contractor  pumped  76,200  gallons  of  storm  water from  the  sedimentation  basin  today  and  transported  to the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we have  drilled  to  depth  at  temporary  piezometer  locations PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was observed,  temporary  piezometers  were  not  installed.     The  documentation  report  was  submitted  on  February 25,  2011.                  Beach  Assessment  Update: 1.   The  daily  beach  assessment  phase  of  this  task  is complete.    There  were  no  calls  received  at  the established  beach  waste  hot  line  today.
  • 177.   ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Jesse  Frey Engineer Waste  Management  of  Hawaii 92-­‐460  Farrington  Hwy. Kapolei,  HI  96707 Ph:  808-­‐250-­‐0574 Fax:  808-­‐668-­‐1366        
  • 178.  
  • 179. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 9, 2011 Date: Wednesday, March 09, 2011 5:18:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  removal  activity  is  ongoing  and  is  expected  to be  completed  within  the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)  Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor  has completed  forming  the  transition structure  from  box  culvert  invert  to  pipe invert.    Half  of  the  concrete  for  this structure  was  poured  on  March  1,  2011. The  remainder  is  scheduled  to  be  poured on  3/10/2011.    Rebar  work  on  box culvert  walls  is  ongoing.      
  • 180.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  is functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC.                Cell  6  Leachate  Riser  Restoration: 15,100  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today 1)           and  transported  to  the  waste  water  treatment  plant. 2)           Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin.   2)           The  contractor  pumped 75,300  gallons  of  storm  water  from  the  sedimentation basin  today  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
  • 181. Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 182.  
  • 183. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 10, 2011 Date: Thursday, March 10, 2011 4:41:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.   This material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently removing  the  material  that  fell  directly on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor  has completed  forming  the  transition structure  from  box  culvert  invert  to  pipe invert.    Half  of  the  concrete  for  this   structure  was  poured  on  March  1,  2011. The  remainder was  poured  on
  • 184. 3/9/2011.    Rebar  work  on  box  culvert walls  is  ongoing.     The  contractor  has also  begun  assembling  the  wall plate forms.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 6,359  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and 1)           transported  to  the  waste  water  treatment  plant. Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water which  prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the sedimentation  basin.   2)           The  contractor  pumped 84,000  gallons  of  storm  water  from  the  sedimentation basin  today  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
  • 185. received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 186.  
  • 187. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Cc: steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Wall.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov Subject: RE: EPA Review of 25 February 2011 Deliverables for WGSL Date: Friday, March 11, 2011 3:42:00 PM Steve,                                  Please  see  WMH  response  to  your  requests  for  information  contained  within  sections  3  &  4 below.    Let  me  know  if  you  have  any  questions.                                  Best  regards,                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Friday, March 04, 2011 2:47 PM To: Whelan, Joseph Cc: steven.chang@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; alec.wong@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Wall.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov Subject: EPA Review of 25 February 2011 Deliverables for WGSL Joe, We have reviewed the revised plans and documents you provided by e-mail on February 25, 2011, under cover of your letter of the same date. We also received and reviewed the CQA report for the southwestern portion E6 liner repair that you sent by a separate e-mail that same date. Thank you for your prompt submissions. Our response to each is as follows: 1) “Description of collection & treatment associated with liquid located behind the temporary berm” (AOC paragraph 19.d.)—APPROVED 2) “Work plan for managing any potential hydraulic head in the Cell E6 location” (AOC paragraph 19.e.) —Report is APPROVED; this item of the Work is now considered complete. 3) “Work plan for restoration of the existing sedimentation basin” (AOC paragraph 19.h.) —APPROVED; but need WMH concurrence on completion schedule. WMH’s revised plan (GEI letter of February 21, 2011) suggests work should be completed by March 14, 2011. Please confirm if this is your proposed deadline or if you wish to propose another date for completing this item of the Work. [Whelan, Joe] Due to the continuing sporadic rain events over the past few weeks, rehabilitation of the sedimentation basin has been delayed by storm water accumulating within said basin. WMH proposes a new deadline of May 15,
  • 188. 2011 to have this work completed. This date should account for the expected end of the rainy season. 4) “Work plan for the beach assessment and material recovery actions” (AOC paragraph 19.i.)—APPROVED; however, please provide the “hotline” phone number and a list of who it was given to or how it was posted or otherwise advertised so that the general public is aware of the hotline. [Whelan, Joe] The hot line number is 808 668 2985, and has been published in our printed and televised news releases. 5) “Updated Storm Water Management & Contingency Plan” (per Condition 4 of EPA’s January 28, 2011 e-mail that provided conditional approval for re-opening Cell E6)— APPROVED 6) E6 Liner Repair Deadline: EPA concurs with WMH’s request of May 15, 2011 as the deadline for completing the liner repairs in accordance with the previously-approved “Waimanalo Gulch Landfill Workplan for Liner Evaluation and Repair” (Geosyntec Consultants’ letter of January 27, 2011) per AOC paragraph 19.f. EPA has reviewed and approves the CQA report provided by WMH under separate cover for completion of repairs to the “middle sideslope liner area” (AECOM letter of February 25, 2011). [In WMH daily reports, this same area has been referred to as the “southwestern” portion.] For your convenience, I have attached an updated deliverables tracking spreadsheet that reflects all the above. Again, it does not supersede any order requirements, but is provided as a convenient tool. Please don’t hesitate to contact me with any questions. I look forward to seeing you at the facility the afternoon of 10 March. Thanks, Steve Tyahla Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]
  • 189. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Updated Storm Water Management Plan Date: Friday, March 11, 2011 3:29:00 PM Attachments: SWM Plan 031111.pdf Greetings  all. Please  find  attached  the  recently  updated  Storm  Water  Management  Plan  for  the Waimanalo  Gulch  Sanitary  Landfill,  as  required  by Condition  5)  of  EPA  28-­‐Jan-­‐11  Approval to  Operate  Cell  #E6:   “No  later  than  fifteen  (15 25 days [Extension  granted  to  WMH  by  EPA on  2/10/11])  after  the  completion  of  a  functional  storm  water  division  structure  (Western Drainage  System)  as  required  in  19.b.  of  EPA's  Order,  WM  must revise  and  submit  to  EPA its  SWPCP to  incorporate  the  functional  Western  Drainage  System  and  all  ancillary  storm water  connections  into  its  revised  SWPCP  consistent  with  the  requirements  of  its  storm water  general  permit.”    Please  let  me  know  if  you  have  any  questions. Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 190.  
  • 191. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: Daily Progress Report for March 11, 2011 Date: Friday, March 11, 2011 4:24:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor  has completed  forming  the  transition structure  from  box  culvert  invert  to  pipe invert.    Half  of  the  concrete  for  this   structure  was  poured  on  March  1,  2011. The  remainder was  poured  on
  • 192. 3/9/2011.    Rebar  work  on  box  culvert walls  is  ongoing.     The  contractor  has also  begun  assembling  the  wall  plate forms.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 3,159  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and 1)           transported  to  the  waste  water  treatment  plant. Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The  contractor  pumped 26,500  gallons  of  storm  water  from  the  sedimentation basin  today  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
  • 193. received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 194.  
  • 195. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Daily Progress Report for March 14, 2011 Date: Monday, March 14, 2011 5:26:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor completed the transition  from  the  box culvert  to  the  Hobas  pipe on  3/9/2011.   Rebar  work  on  box  culvert  walls  is ongoing.     The  contractor  has  also  begun assembling  the  wall  plate  forms.
  • 196.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 1)           20,677  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank since Friday  and  transported  to  the  waste  water  treatment  plant. Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water  and  is  being  prepped  for  the  next  phase  of  the  Western  Berm Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The  contractor  pumped 126,000  gallons  of  storm  water  from  the  sedimentation basin since  Friday  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
  • 197. ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 198.  
  • 199. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Daily Progress Report for March 15, 2011 Date: Tuesday, March 15, 2011 5:28:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor completed the transition  from  the  box culvert  to  the  Hobas  pipe on  3/9/2011.   Rebar  work  on  box  culvert  walls  is ongoing.     The  contractor  has  also  begun assembling  the  wall  plate  forms.
  • 200.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 1)           8,768  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank today  and transported  to  the  waste  water  treatment  plant. 1,518  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water (other  than  overnight  rainfall), and  is  being  prepped  for  the  next  phase of  the  Western  Berm  Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The  contractor  pumped 71,476  gallons  of  storm  water  from  the  sedimentation basin today  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
  • 201. ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 202.  
  • 203. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Daily Progress Report for March 16, 2011 Date: Wednesday, March 16, 2011 5:05:00 PM Greetings  all.       Please  find  below  the  daily  progress  report  for  work  items  contained  within  the recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.   This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly on  the  liner.   This  removal  activity  is  ongoing  and  is  expected  to  be  completed  within the  next  2  weeks,  weather  permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     2)    Box  Culvert:      The  contractor completed the transition  from  the  box culvert  to  the  Hobas  pipe on  3/9/2011.   Rebar  work  on  box  culvert  walls  is ongoing.     The  contractor  has  also  begun assembling  the  wall  plate  forms.
  • 204.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 1)           6,318  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank today  and transported  to  the  waste  water  treatment  plant. 1,300  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water (other  than  overnight  rainfall), and  is  being  prepped  for  the  next  phase of  the  Western  Berm  Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin.   2)           The  contractor  pumped 91,400  gallons  of  storm  water  from  the  sedimentation basin today  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
  • 205. ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 206.  
  • 207. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: Request to Replace Daily Progress Reports to Weekly Date: Wednesday, March 16, 2011 5:14:00 PM Hello  Steve. Waste  Management  of  Hawaii (WMH) has  provided  the  noticed  parties  daily progress  reports  according  to  the  terms  of  the  Administrative  Order  on  Consent (AOC)  with USEPA  signed  on  January  25,  2011.    Most  of  the  requirements  associated  with  the  AOC have  now  been substantially met.    Section VIII.  24.  A.  of  the  AOC  specifies  that “Beginning two  (2)  days  after  the  Effective  Date,  Respondent  shall  submit  by  e-­‐mail  to  EPA  and  DOH daily,  until  agreed  otherwise  by  the  Parties,  progress  reports  (Monday  through  Friday  only, unless  otherwise  requested  by  EPA)  concerning  actions  undertaken  pursuant  to  this  Order …….”.   WMH  is  hereby  requesting  your  approval  to  replace  the  daily  progress  reports  with weekly reports.   WMH  proposes  to  provide  you  with  a  weekly  report  similar  to  the  daily reports  in  content  that  would  run  from  Monday  thru  Sunday,  and  be  delivered  to  all  parties by  Wednesday summarizing the  previous  weeks  information.    Please  review  this  request and  provide  your  approval  to move  to  weekly  progress  reports.    Thank  you. Best  regards, Joe Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 208.  
  • 209. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: Re: Request to Replace Daily Progress Reports to Weekly Date: Thursday, March 17, 2011 9:02:06 AM Thank  you  Steve!  I  really  appreciate  your  quick  turn  around. Joe From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Thursday, March 17, 2011 12:39 PM To: Whelan, Joseph Cc: alec.wong@doh.hawaii.gov <alec.wong@doh.hawaii.gov>; Steven.chang@doh.hawaii.gov <Steven.chang@doh.hawaii.gov>; stuart.yamada@doh.hawaii.gov <stuart.yamada@doh.hawaii.gov>; Moxley.Bret@epamail.epa.gov <Moxley.Bret@epamail.epa.gov>; Armann.Steve@epamail.epa.gov <Armann.Steve@epamail.epa.gov>; Kabei.Arlene@epamail.epa.gov <Kabei.Arlene@epamail.epa.gov>; Helmlinger.Andrew@epamail.epa.gov <Helmlinger.Andrew@epamail.epa.gov>; Higuchi.Dean@epamail.epa.gov <Higuchi.Dean@epamail.epa.gov>; Vaille.Rich@epamail.epa.gov <Vaille.Rich@epamail.epa.gov>; Wall.Steve@epamail.epa.gov <Wall.Steve@epamail.epa.gov> Subject: Re: Request to Replace Daily Progress Reports to Weekly Joe, Your request to issue weekly in lieu of daily progress reports is hereby granted. Please make your first submission by noon (Hawaii time) on Wednesday, 23 March, to cover the period of 17 March through Sunday, 20 March 2011. Subsequent reports covering Monday through Sunday as you describe in your request should be provided by noon (Hawaii time) each Wednesday. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] -----"Whelan, Joseph" <JWhelan1@wm.com> wrote: ----- To: Stephen Tyahla/R9/USEPA/US@EPA From: "Whelan, Joseph" <JWhelan1@wm.com> Date: 03/16/2011 08:14PM Subject: Request to Replace Daily Progress Reports to Weekly
  • 210. Hello  Steve.                  Waste  Management  of  Hawaii  (WMH)  has  provided  the  noticed  parties  daily  progress  reports according  to  the  terms  of  the  Administrative  Order  on  Consent  (AOC)  with  USEPA  signed  on January  25,  2011.    Most  of  the  requirements  associated  with  the  AOC  have  now  been substantially  met.    Section  VIII.  24.  A.  of  the  AOC  specifies  that  “Beginning  two  (2)  days  after  the Effective  Date,  Respondent  shall  submit  by  e -­‐mail  to  EPA  and  DOH  daily,  until  agreed  otherwise by  the  Parties,  progress  reports  (Monday  through  Friday  only,  unless  otherwise  requested  by EPA)  concerning  actions  undertaken  pursuant  to  this  Order  …….”.      WMH  is  hereby  requesting your  approval  to  replace  the  daily  progress  reports  with  weekly  reports.    WMH  proposes  to provide  you  with  a  weekly  report  similar  to  the  daily  reports  in  content  that  would  run  from Monday  thru  Sunday,  and  be  delivered  to  all  parties  by  Wednesday  summarizing  the  previous weeks  information.    Please  review  this  request  and  provide  your  approval  to  move  to  weekly progress  reports.    Thank  you.                  Best  regards,                  Joe   Joe Whelan   General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile   Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.      
  • 211. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: Proposed due date for Revised SWPCP Date: Tuesday, March 22, 2011 11:27:00 AM Thank  you  Steve!                                  The  existing  ash  cells  comprise  cells  1-­‐8.    You  were  observing  ash  cells  4  &  5.    We  refer  to the  small  roadway  as  the  HECO  bridge  road  as  it  connects  our  main  access  road  to  the  HECO  power plant  communications  tower  located  on  the  top  of  the  ridge.    Hope  all  is  well.                                  Best  regards,                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Tuesday, March 22, 2011 11:00 AM To: Whelan, Joseph Cc: Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov; Wampler.David@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov Subject: Re: Proposed due date for Revised SWPCP Joe, Your request is approved. The revised SWPCP is to be submitted to EPA by Monday, 2 May 2011 (as the 1st is a Sunday). I have updated the attached Deliverables Tracking spreadsheet to reflect this change as well as all others to date. Again, the tracking spreadsheet in no way replaces or supersedes any of our AOC requirements, but is simply a convenient tool. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.]
  • 212. From: "Whelan, Joseph" <JWhelan1@wm.com> To: Stephen Tyahla/R9/USEPA/US@EPA Date: 03/22/2011 12:23 PM Subject: Proposed due date for Revised SWPCP Hello  Steve,                  We  just  heard  back  from  our  consultant  that  is  revising  the  SWPCP.    In  addition  to  upgrading  the  plan  by including  that  portion  of  the  constructed  storm  water  diversion  structure  that  renders  it  “functionally  complete”, WMH  has  requested  that  the  entire  plan  be  updated.    We  are  requesting  a  due  date  of  May  1st  for  this  submittal to  USEPA.    Please  let  me  know  if  this  date  is  acceptable.    Thank  you.                  Best  regards,                  Joe   Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 213. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: Proposed due date for Revised SWPCP Date: Tuesday, March 22, 2011 9:23:00 AM Hello  Steve, We  just  heard  back  from  our  consultant  that  is  revising  the  SWPCP.    In  addition  to upgrading  the  plan  by  including  that  portion  of  the  constructed  storm  water  diversion structure  that  renders  it “functionally  complete”,  WMH  has  requested  that  the  entire  plan be  updated.    We  are  requesting  a  due  date  of  May  1 st  for  this  submittal  to  USEPA.    Please let  me  know  if  this  date  is  acceptable.    Thank  you. Best  regards, Joe Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 214.  
  • 215. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending March 20, 2011 Date: Tuesday, March 22, 2011 5:52:00 PM Greetings  all.       The  USEPA  granted  our  request  to replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and document  work  completed  during the period  of  the  prior Monday  thru  Sunday.   This  initial  weekly  progress  report  covers  March  17th  (the  day after  the  last  daily  report)  thru  Sunday  March  20th.   Please  find  below  the weekly progress  report  for  work  items  contained  within  the  recently  approved  AOC.       ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  must  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  is  currently  removing  the  material  that  fell  directly on  the  liner.    This  removal  activity  is  expected  to  be  completed by  March  26th,  and replacement  of  any  damaged  liner should  be  completed  by  April  9th,  weather permitting.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)  Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     The  contractor  expects  to complete  the  concrete  pour  on  the
  • 216. middle  section  of  the  weir  on Wednesday  March  23,  2011. 2)    Box  Culvert:      The  contractor completed the transition  from  the  box culvert  to  the  Hobas  pipe on  3/9/2011.   Rebar  work  on  box  culvert  walls  is ongoing.     The  contractor  has  also  begun assembling  the  wall  plate  forms.    The next  concrete  wall  pour  is  scheduled  for Monday  March  28th.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 1)           31,698  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank since March  16th, and  transported  to  the  waste  water  treatment  plant. zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and 2)           transported  to  the  local  waste  water  treatment  plant.  This  area  currently  contains  no ponded  water, and  is  being  prepped  for  the  next  phase  of  the  Western  Berm Construction. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and 3)           placed  within  the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today from  these  separation  tanks.                Sediment  Basin: 1)           Showers over  the  past  several  weeks  have  resulted  in  the  additional accumulation  of  storm  water  which  prevented  removal  of  silt/rock  material  from  the northern  portion  of  the  sedimentation  basin. 2)           The  contractor  pumped 221,300  gallons  of  storm  water  from  the  sedimentation basin since  March  16th,  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system:
  • 217. 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  today. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 218.  
  • 219. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending March 27, 2011 Date: Tuesday, March 29, 2011 7:37:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  March 21 thru  Sunday March  27th.   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  damaged  liner is  expected  to  be  completed  by March  30th,  and  the  CQA  report  submitted  by  April  1st.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     The  contractor has completed the  concrete  pour  on  the  middle  section of  the  weir.
  • 220. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor has  also  begun  assembling  the  wall  plate forms.    The most  recent  concrete  wall pour was  performed  on  Monday  March 28th.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 52,434  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           March 21,  and  transported  to  the  waste  water  treatment  plant. The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.                Sediment  Basin: 1)           105,900  gallons  of  storm  water were  pumped from  the  sedimentation  basin during  this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.                 Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.    
  • 221. Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 222.  
  • 223. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: FW: WGSL, CQA Report Documenting Repairs to the Final Section of Cell E6 Liner Date: Tuesday, April 05, 2011 2:33:00 PM Attachments: Ltr Rpt Cell E6 West Slope Repair 040411.pdf Hi  Steve, Just  checking  in  to  see  if  you  had  a  chance  to  review  and  approve  this  CQA  report.   We  need  the  airspace.    Thanks. Joe _____________________________________________ From: Whelan, Joseph Sent: Monday, April 04, 2011 2:54 PM To: 'Steven.chang@doh.hawaii.gov'; lene.ichinotsubo@doh.hawaii.gov; Miyashiro, Thomas; 'Tyahla.Stephen@epamail.epa.gov' Subject: WGSL, CQA Report Documenting Repairs to the Final Section of Cell E6 Liner Greetings  all.                                Please  find  the  CQA  report  documenting  the  liner  repairs  related  to  the  storm damage  located  within  the  northwest  portion  of  Cell  E6.    This  submission  documents  the final  section  of  the  Cell  E6  liner  repairs.    We  would  appreciate  your  timely  review  and approval  of  this  report.      Thank  you  in  advance  for  your  assistance  with  this  most  important project.                                Best  regards,                                Joe                                                         Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office
  • 224.  
  • 225. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending April 3, 2011 Date: Tuesday, April 05, 2011 5:07:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28 thru  Sunday April 3rd. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    Completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of the  final  piece  of  the damaged  liner  was completed on  April  1st,  and  the  CQA  report  submitted on  April 4th.                  Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     The  contractor  has  completed the  concrete  pour  on  the  middle  section of  the  weir.  
  • 226. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           March  28,  and  transported  to  the  waste  water  treatment  plant. The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.                Sediment  Basin: 1)           Zero  gallons  of  storm  water were  pumped from  the  sedimentation  basin during this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry it  out  prior  to  removal.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
  • 227. Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 228. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending April 3, 2011 Date: Tuesday, April 05, 2011 5:07:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28 thru  Sunday April 3rd. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    Completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of the  final  piece  of  the damaged  liner  was completed on  April  1st,  and  the  CQA  report  submitted on  April 4th.                  Western  Storm  water  Diversion  Project  (to  render  functional): 1)   Diversion  Structure:     The  final  wall section  of  the  diversion  structure  is  now in  place.     The  contractor  has  completed the  concrete  pour  on  the  middle  section of  the  weir.  
  • 229. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 10,  2011.                Cell  6  Leachate  Riser  Restoration: 51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           March  28,  and  transported  to  the  waste  water  treatment  plant. The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.                Sediment  Basin: 1)           Zero  gallons  of  storm  water were  pumped from  the  sedimentation  basin during this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry it  out  prior  to  removal.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   Completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None
  • 230. Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 231. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Cc: Armann.Steve@epamail.epa.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; alec.wong@doh.hawaii.gov; Wampler.David@epamail.epa.gov Subject: RE: WGSL AOC Progress Report for Week Ending April 3, 2011 Date: Wednesday, April 06, 2011 4:45:00 PM Greetings,                                  I  will  change  the  date  on  item  4  of  the  weekly  progress  reports.    Concerning  the sedimentation  basin,  we  used  an  excavator  bucket  to  dig  a  small  sump  in  the  south  and  north  ends of  the  basin  in  two  small  areas  that  continue  to  hold  water  but  are  shallow  enough  to  prevent pumping.    Therefore  the  sumps  are  under  water  at  this  time  and  pictures  would  not  reveal meaningful  data.    These  sumps  merely  allow  the  water  entrapped  within  the  sediment  to  bleed  out and  provide  us  with  a  location  from  which  to  pump  the  free  standing  water.    Neither  sump  is  deep enough  to  affect  the  bottom  area  of  the  basin,  each  is  probably  5x5x5  feet.                                  Best  regards,                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Wednesday, April 06, 2011 12:03 PM To: Whelan, Joseph Cc: Armann.Steve@epamail.epa.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; alec.wong@doh.hawaii.gov; Wampler.David@epamail.epa.gov Subject: Re: WGSL AOC Progress Report for Week Ending April 3, 2011 Hi Joe, A minor correction on your weekly report, and a request. Item 4) under Western Storm water Diversion Project (to render functional), an apparent typo- the actual date was 15 February (sorry, I missed that before). Your e-mail notifying it was functional is dated the 15th and my concurrence was on the 16th. Please correct in future reports. Sedimentation Basin-you say you dug sumps in the north and south ends to help water infiltrate; what are their rough dimensions? Is south one into any of the existing sub-drain system? And, can you send me a photo of these sumps? Just trying to get a better sense of them. Thanks, Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov
  • 232. [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 04/05/2011 08:07 PM Subject: WGSL AOC Progress Report for Week Ending April 3, 2011 Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  March  28  thru  Sunday  April 3rd. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1. The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    Completed.   2. The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.                    Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in place.      The  contractor  has  completed  the  concrete  pour  on  the  middle  section  of  the weir.    
  • 233. 2)    Box  Culvert:      Rebar  work  on  box  culvert  walls  is  ongoing.      The  contractor continues  assembling  the  wall  plate  forms  and  completing  the  associated  concrete pours. 3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  was  functionally  complete  per  the  terms  of  Section  19.b.  of the  AOC  as  of  February  10,  2011.                Cell  6  Leachate  Riser  Restoration: 1. 51,663  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since March  28,  and  transported  to  the  waste  water  treatment  plant. 2. The  south  pond  area  contains  no  ponded  water,  and  is  being  prepped  for  the next  phase  of  the  Western  Berm  Construction.                  Sediment  Basin: 1. Zero  gallons  of  storm  water  were  pumped  from  the  sedimentation  basin  during this  reporting  period,  and  transported  to  the  waste  water  treatment  plant.    WM  dug sumps  into  the  north  and  south  end  of  the  sedimentation  basin  in  order  to  allow  storm water  to  bleed  out  of  the  sediment,  in  an  effort  to  dry  it  out  prior  to  removal.                Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.  Completed.                Beach  Assessment  Update: 1. The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.       Best  regards,       Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 234.  
  • 235. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending April 10, 2011 Date: Tuesday, April 12, 2011 4:18:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers April  4 thru  Sunday  April 10. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.   This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.   This  project  is completed. 3)           All  liner  repairs resulting  from  the  December/January  storm  event  damage  have now been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete,
  • 236. clean  up  and back  fill  of  native  stone  and soil  are  scheduled  for  next  week. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.    Wall  pours  are scheduled  for  this  Thursday  and  Friday, weather  permitting.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 35,586  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           April 4th,  and  transported  to  the  waste  water  treatment  plant. The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.   Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  418.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.   15,000 gallons  of  storm  water were  pumped from  the  sedimentation  basin during  this  reporting  period,  and  used  on site  for  dust  control  and  irrigation.    WM  dug  sumps  into  the  north  and  south  end  of  the sedimentation  basin  in  order  to  allow  storm  water  to  bleed  out  of  the  sediment,  in  an effort  to  dry  it  out  prior  to  removal.                  Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.
  • 237.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 238.  
  • 239. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: WGSL AOC Progress Report for Week Ending April 10, 2011 Date: Wednesday, April 13, 2011 5:00:00 PM Hi  Steve,                                  Within  the  next  few  days.                                  Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Wednesday, April 13, 2011 6:05 AM To: Whelan, Joseph Subject: Re: WGSL AOC Progress Report for Week Ending April 10, 2011 Thanks Joe. I'm anxious to hear when you're able to get the sed basin water level low enough to start de-mucking. Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Arlene Kabei/R9/USEPA/US@EPA, Steve Armann/R9/USEPA/US@EPA, Rich Vaille/R9/USEPA/US@EPA, Stephen Tyahla/R9/USEPA/US@EPA, Bret Moxley/R9/USEPA/US@EPA, Andrew Helmlinger/R9/USEPA/US@EPA, Steve Wall/R9/USEPA/US@EPA, "'stuart.yamada@doh.hawaii.gov'" <stuart.yamada@doh.hawaii.gov>, "'Steven.chang@doh.hawaii.gov'" <Steven.chang@doh.hawaii.gov>, "'alec.wong@doh.hawaii.gov'" <alec.wong@doh.hawaii.gov> Date: 04/12/2011 07:18 PM Subject: WGSL AOC Progress Report for Week Ending April 10, 2011 Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior
  • 240. Monday  thru  Sunday.      This  weekly  progress  report  covers  April  4  thru  Sunday  April  10. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1. The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed.   2. The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed.   3. All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  diversion  structure  concrete  work  is  complete,  clean  up and  back  fill  of  native  stone  and  soil  are  scheduled  for  next  week. 2)    Box  Culvert:      Rebar  work  on  box  culvert  walls  is  ongoing.      The  contractor continues  assembling  the  wall  plate  forms  and  completing  the  associated  concrete pours.    Wall  pours  are  scheduled  for  this  Thursday  and  Friday,  weather  permitting. 3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete. 4)    The  diversion  structure  was  functionally  complete  per  the  terms  of  Section  19.b.  of the  AOC  as  of  February  15,  2011.                Cell  6  Leachate  Riser  Restoration: 1. 35,586  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since April  4th,  and  transported  to  the  waste  water  treatment  plant. 2. The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  418.                Sediment  Basin: 1. DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.    15,000  gallons  of  storm  water  were pumped  from  the  sedimentation  basin  during  this  reporting  period,  and  used  on  site for  dust  control  and  irrigation.    WM  dug  sumps  into  the  north  and  south  end  of  the
  • 241. sedimentation  basin  in  order  to  allow  storm  water  to  bleed  out  of  the  sediment,  in  an effort  to  dry  it  out  prior  to  removal.                    Evaluating  possible  hydraulic  head  below  liner  system: 1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered  during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This project  is  completed.                Beach  Assessment  Update: 1. The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.       Best  regards,     Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.     Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 242.  
  • 243. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending April 17, 2011 Date: Tuesday, April 19, 2011 5:45:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  April 11 thru  Sunday  April 17. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete,
  • 244. clean  up  and  back  fill  of  native  stone  and soil  are ongoing. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.   Two  wall  pours were completed  last  Thursday  and  Friday.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 26,006  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           April 11th,  and  transported  to  the  waste  water  treatment  plant.   Additionally,  this week  the  leachate  riser  was  extended  vertically  to  the  final  elevation located at  the intersection  of  the western  drainage  pipe  access  road. The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  420.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.   This  week  we completed  free water  removal  from  the  basin,  and began daily  removal  of  sediment  contained  within this  basin,  placing it within  Cell  E6.    Friday  evening  rains  resulted  in accumulation  of stormwater  within  the  northern  portion  of  the  sedimentation  basin.    We  are  currently removing  this  water,  prior  to  resuming  sediment  removal  activities.                  Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.
  • 245.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 246.  
  • 247. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending April 24, 2011 Date: Monday, April 25, 2011 5:03:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  April  18 thru  Sunday  April 24. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete,
  • 248. clean  up  and  back  fill  of  native  stone  and soil  are  ongoing. 2)    Box  Culvert:     Rebar  work  on  box culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.    3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 4,159  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           April  18th,  and  transported  to  the  waste  water  treatment  plant.   The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  420.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.     WMH  has  completed  free  water removal  from  the  basin,  and continue  daily  removal  of the sediment,  placing  it  within Cell  E6.   We  have  removed  approximately  30%  of  the  silty  material  from  the  north  end of  the  basin  and  20%  of  the  silt  from  the  south  end.   However,  it  should  be  noted  that future rain  events  will  cause  delays  in  completing  this  process.                      Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls
  • 249. received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 250.  
  • 251. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending May 1, 2011 Date: Tuesday, May 03, 2011 5:15:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  April 25 thru  Sunday May  1. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete. 2)    Box  Culvert:     Rebar  work  on  box
  • 252. culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.      3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 1,000  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           April 25th,  and  transported  to  the  waste  water  treatment  plant.         The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  435.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.      WMH  has  completed  free  water removal  from  the  basin,  and  continues  daily  removal  of  the  sediment,  placing  it  within Cell  E6.    We  have  removed  approximately 90%  of  the  silty  material  from  the  north  end of  the  basin  and 20%  of  the  silt  from  the  south  end.    However,  it  should  be  noted  that future  rain  events  will  cause  delays  in  completing  this  process.                        Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None
  • 253. ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 254.  
  • 255. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: WGSL Request to Extend Completion Deadline - AOC Date: Thursday, May 05, 2011 4:51:00 PM Attachments: CIMG0618.JPG CIMG0619.JPG CIMG0615.JPG CIMG0620.JPG Hello  Steve. Per  our  phone  conversation  on May  4,  2011,  recent  rain  events  occurring  at  the Waimanalo  Gulch  Sanitary  Landfill  (WGSL)  have  caused  delays  in  completing  the  cleanout of  the  on  site  sedimentation  basin.   This  clean  out  is  the  last  project  associated  with  the EPA AOC. Currently,  the  north  end  of  the  basin  is  approximately  90%  empty  of  sediment, and  we  continue  to  remove  sediment  from  the  southern  portion.    Recent  rains  have  added about  4  feet  of  storm  water  to  the  northern  end  of  the  basin,  which  is  currently  being pumped  out  and  used  for  on  site  irrigation  and  dust  control.    This  rain  will  cause  delays  in completing  the  full  restoration  of  the  sediment  basin.    Please  see  the  pictures  taken  on  May 4,  2011.    We  are  requesting  approval  to  move  the  due  date  for  completion  of  this  project from  May  15 th  to  June  15 th .    The  normal  wet  season  for  this  area  usually  ends  by  mid March,  however  we  still could experience  localized  rain  events  which may impede  our progress.    Please  provide  your  approval  to  move  the  completion  date  to  June  15,  2011.   Thank  you. Best  regards, Joe Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 256.  
  • 257. From: Whelan, Joseph To: Tyahla.Stephen@epamail.epa.gov Subject: RE: WGSL Request to Extend Completion Deadline - AOC Date: Friday, May 06, 2011 8:11:00 AM Thanks  Steve,                                  We  really  appreciate  your  working  with  us  and  being  receptive  to  local  conditions  affecting this  project.                                    Joe   From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Friday, May 06, 2011 7:02 AM To: Whelan, Joseph Cc: stuart.yamada@doh.hawaii.gov; steven.chang@doh.hawaii.gov; lene.ichinotsubo@doh.hawaii.gov; alec.wong@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Wampler.David@epamail.epa.gov; Helmlinger.Andrew@epamail.epa.gov; Vaille.Rich@epamail.epa.gov; Kabei.Arlene@epamail.epa.gov Subject: Re: WGSL Request to Extend Completion Deadline - AOC Joe, Your request to extend the completion date for restoration of the sedimentation basin (per paragraph 19.h. of the AOC) from the current deadline of 15 May to 15 June 2011 is hereby granted. (For the cc's I have attached a PDF file containing the pictures you provided.) As we discussed, please keep me apprised, with as much advance notice as possible, as to when you believe you will be completing that work. Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Stephen Tyahla/R9/USEPA/US@EPA Date: 05/05/2011 07:52 PM Subject: WGSL Request to Extend Completion Deadline - AOC
  • 258. Hello  Steve.                  Per  our  phone  conversation  on  May  4,  2011,  recent  rain  events  occurring  at  the  Waimanalo  Gulch  Sanitary Landfill  (WGSL)  have  caused  delays  in  completing  the  cleanout  of  the  on  site  sedimentation  basin.    This  clean  out is  the  last  project  associated  with  the  EPA  AOC.  Currently,  the  north  end  of  the  basin  is  approximately  90% empty  of  sediment,  and  we  continue  to  remove  sediment  from  the  southern  portion.    Recent  rains  have  added about  4  feet  of  storm  water  to  the  northern  end  of  the  basin,  which  is  currently  being  pumped  out  and  used  for on  site  irrigation  and  dust  control.    This  rain  will  cause  delays  in  completing  the  full  restoration  of  the  sediment basin.    Please  see  the  pictures  taken  on  May  4,  2011.    We  are  requesting  approval  to  move  the  due  date  for completion  of  this  project  from  May  15 th  to  June  15 th .    The  normal  wet  season  for  this  area  usually  ends  by  mid March,  however  we  still  could  experience  localized  rain  events  which  may  impede  our  progress.    Please  provide your  approval  to  move  the  completion  date  to  June  15,  2011.    Thank  you.                    Best  regards,                  Joe   Joe Whelan   General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.   Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails.
  • 259. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending May 8, 2011 Date: Tuesday, May 10, 2011 8:56:00 AM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers May  1 thru  Sunday  May 8. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete. 2)    Box  Culvert:     Rebar  work  on  box
  • 260. culvert  walls  is  ongoing.     The  contractor continues  assembling  the  wall  plate forms  and  completing  the  associated concrete  pours.     There  were  several  rain delay  days  during  this  reporting  period due  to  heavy  rains.   No  damage  was incurred.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 63,611  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           May  1st,  and  transported  to  the  waste  water  treatment  plant.       Leachare  riser restoration  is  complete. The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  440.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.     We  have  removed  approximately 90%  of  the  silty  material  from  the  north  end  of  the  basin  and 30%  of  the  silt  from  the south  end.    Rain  events this  week  have  caused  several  feet  of  storm  water accumulation  in  the  sedimentation  basin,  which is currently being  removed.   Sediment removal will  resume  once  this  process  is  complete.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.               Beach  Assessment  Update:
  • 261. 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 262.  
  • 263. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending May 15, 2011 Date: Monday, May 16, 2011 5:09:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  May 9 thru  Sunday  May 15. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete. 2)    Box  Culvert:     Rebar  work  on the box
  • 264. culvert  walls and  ceiling is  ongoing.     The  contractor  continues  assembling  the wall &  ceiling plate  forms  and completing  the  associated  concrete pours.      There  were  several  rain  delays during  this  reporting  period.    No  damage was  incurred.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 9,477  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since May 1)           9th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser  restoration  is complete. The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  445.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.        We  have  removed  approximately 90%  of  the  silty  material  from  the  north  end  of  the  basin  and 35%  of  the  silt  from  the south  end.      Rain  events last week  have  caused  several  feet  of  storm  water accumulation  in  the  sedimentation  basin,  which  is  currently  being  removed.   Sediment removal  has  resumed  in  the  south  end  of  the  basin,  and  we  continue  to  remove storm water  from  the  north  end.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.               Beach  Assessment  Update:
  • 265. 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 266.  
  • 267. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending May 22, 2011 Date: Monday, May 23, 2011 5:00:00 PM Greetings  all.        The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  May 16 thru  Sunday  May 22. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area had  to be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor has  completed  removing  the  material  that  fell directly  on  the  liner.  Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete.
  • 268. 2)    Box  Culvert:     Rebar  work  on the box culvert  walls and  ceiling is  ongoing.     The  contractor  continues  assembling  the wall  &  ceiling  plate  forms  and  completing the  associated  concrete  pours.      3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 56,914  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           May 16th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser restoration  is  complete. The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.    Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  445.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           DOH  provided  approval  on  March  24th  to  begin  using  the  sedimentation  basin storm  water  for  on  site  dust  control  and  irrigation.        We  have  removed  approximately 90%  of  the  silty  material  from  the  north  end  of  the  basin  and 100%  of  the  silt  from the  south  end.     Crushed  stone  and  silt  from  the  under  drain  system  will  be  replaced this  week.    Prior  rain  events  have  caused  several  feet  of  storm  water  accumulation  in the north  end  of the sedimentation  basin,  which  is  currently  being  removed.                  Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.   This project  is  completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line during  this  reporting  period.
  • 269. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Best  regards, Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 270.  
  • 271. From: Lottig, Justin To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending May 29, 2011 Aloha,  Joe  Whelan  is  out  of  the  office  this  week,  so  I  am  sending  the  weekly  progress report. The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  May  23  thru  Sunday  May  29. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1.   The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion  of  the  E6  liner  system  was submitted  February  25,  2011.    We  received  notification from  DOH  on  March  1,  2011  concurring  that  the  CQA report  was  adequate  documentation  of  the  liner  repairs, which  allows  WMH  to  resume  operations  in  this  area.   This  project  is  completed.   2.   The  northwest  section  of  the  Cell  E6  liner  was  also damaged  in  the  January  13,  2011  storm.    This  area  is located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  January  storm  event  and the  construction  of  the  diversion  system  in  this  area had  to  be  removed  prior  to  the  evaluation  and  repair  of the  liner.    This  material  has  now  been  removed  from the  side  slope  of  the  gulch.    The  contractor  has completed  removing  the  material  that  fell  directly  on the  liner.    Replacement  of  the  final  piece  of  the damaged  liner  was  completed  on  April  1st,  and  the  CQA report  submitted  on  April  4th .    This  project  is  completed.   3.   All  liner  repairs  resulting  from  the  December/January storm  event  damage  have  now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  diversion  structure  concrete work  is  complete.
  • 272. 2)    Box  Culvert:        Rebar  work  on  the  box  culvert  walls  and ceiling  is  ongoing.      The  contractor  continues  assembling the  wall  &  ceiling  plate  forms  and  completing  the associated  concrete  pours.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now complete. 4)    The  diversion  structure  was  functionally  complete  per the  terms  of  Section  19.b.  of  the  AOC  as  of  February  15, 2011.                Cell  6  Leachate  Riser  Restoration: 1.   25,216  gallons  were  pumped  from  the  Cell  E6  leachate riser  storage  tank  since  May  22nd,  and  transported  to the  waste  water  treatment  plant.        Leachate  riser restoration  is  complete. 2.   The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next  phase  of  the  Western  Berm Construction.      Phase  III  of  the  western  berm construction  is  now  complete  to  elevation  445.   Additional  berm  placement  is  ongoing.                Sediment  Basin: 1.   DOH  provided  approval  on  March  24th  to  begin  using the  sedimentation  basin  storm  water  for  on  site  dust control  and  irrigation.        We  have  removed approximately  90%  of  the  silty  material  from  the  north end  of  the  basin  and  100%  of  the  silt  from  the  south end.      Crushed  stone  and  silt  from  the  under  drain system  was  replaced  during  the  past  week.    Prior  rain events  have  caused  several  feet  of  storm  water accumulation  in  the  north  end  of  the  sedimentation basin,  which  is  currently  being  removed.                    Evaluating  possible  hydraulic  head  below  liner  system: 1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we have  drilled  to  depth  at  temporary  piezometer  locations PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was observed,  temporary  piezometers  were  not  installed.     The  documentation  report  was  submitted  on  February 25,  2011.    This  project  is  completed.                Beach  Assessment  Update: 1.   The  daily  beach  assessment  phase  of  this  task  is
  • 273. complete.    There  were  no  calls  received  at  the established  beach  waste  hot  line  during  this  reporting period.   ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.       Justin H. Lottig Environmental Protection Manager Waste Management of Hawaii 92-460 Farrington Highway Kapolei, HI 96707 808.668.2985  
  • 274.  
  • 275. From: Lottig, Justin To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending June 5, 2011 Aloha,  Joe  Whelan  was  out  of  the  office  last  week,  so  I  am  sending  the  weekly  progress report. The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a  weekly report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be  submitted  by noon  each  Wednesday  and  document  work  completed  during  the  period  of  the  prior Monday  thru  Sunday.      This  weekly  progress  report  covers  May  30  thru  Sunday  June  5. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1.   The  QCA  report  documenting  the  evaluation  and  repair of  the  southwestern  portion  of  the  E6  liner  system  was submitted  February  25,  2011.    We  received  notification from  DOH  on  March  1,  2011  concurring  that  the  CQA report  was  adequate  documentation  of  the  liner  repairs, which  allows  WMH  to  resume  operations  in  this  area.   This  project  is  completed.   2.   The  northwest  section  of  the  Cell  E6  liner  was  also damaged  in  the  January  13,  2011  storm.    This  area  is located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into the  Hobas  pipe.    Consequently,  any  rock  and  soil material  generated  from  the  January  storm  event  and the  construction  of  the  diversion  system  in  this  area had  to  be  removed  prior  to  the  evaluation  and  repair  of the  liner.    This  material  has  now  been  removed  from the  side  slope  of  the  gulch.    The  contractor  has completed  removing  the  material  that  fell  directly  on the  liner.    Replacement  of  the  final  piece  of  the damaged  liner  was  completed  on  April  1st,  and  the  CQA report  submitted  on  April  4th .    This  project  is  completed.   3.   All  liner  repairs  resulting  from  the  December/January storm  event  damage  have  now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): 1)    Diversion  Structure:      The  diversion  structure  concrete work  is  complete.
  • 276. 2)    Box  Culvert:        Rebar  work  on  the  box  culvert  walls  and ceiling  is  ongoing.      The  contractor  continues  assembling the  wall  &  ceiling  plate  forms  and  completing  the associated  concrete  pours.       3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now complete. 4)    The  diversion  structure  was  functionally  complete  per the  terms  of  Section  19.b.  of  the  AOC  as  of  February  15, 2011.                Cell  6  Leachate  Riser  Restoration: 1.   34,075  gallons  were  pumped  from  the  Cell  E6  leachate riser  storage  tank  since  May  30th,  and  transported  to the  waste  water  treatment  plant.        Leachate  riser restoration  is  complete. 2.   The  south  pond  area  contains  no  ponded  water,  and was  prepped  for  the  next  phase  of  the  Western  Berm Construction.      Phase  III  of  the  western  berm construction  is  now  complete  to  elevation  445.   Additional  berm  placement  is  ongoing.                Sediment  Basin: 1.   DOH  provided  approval  on  March  24th  to  begin  using the  sedimentation  basin  storm  water  for  on  site  dust control  and  irrigation.        We  have  removed approximately  95%  of  the  silty  material  from  the  north end  of  the  basin  and  100%  of  the  silt  from  the  south end.      Crushed  stone  and  silt  from  the  under  drain system  has  been  replaced.    All  previously  accumulated storm  water  in  the  north  end  of  the  sedimentation basin  has  been  removed.                Evaluating  possible  hydraulic  head  below  liner  system: 1.   Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we have  drilled  to  depth  at  temporary  piezometer  locations PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was observed,  temporary  piezometers  were  not  installed.     The  documentation  report  was  submitted  on  February 25,  2011.    This  project  is  completed.                Beach  Assessment  Update: 1.   The  daily  beach  assessment  phase  of  this  task  is complete.    There  were  no  calls  received  at  the
  • 277. established  beach  waste  hot  line  during  this  reporting period.   ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.       Justin H. Lottig Environmental Protection Manager Waste Management of Hawaii 92-460 Farrington Highway Kapolei, HI 96707 808.668.2985  
  • 278.  
  • 279. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending June 12, 2011 Date: Monday, June 13, 2011 4:53:00 PM Greetings  All. The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a weekly  report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be submitted  by  noon  each  Wednesday  and  document  work  completed  during  the  period of  the  prior  Monday  thru  Sunday.      This  weekly  progress  report  covers June  6  thru Sunday  June 12th. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell directly  on  the  liner.    Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete.
  • 280. 2)    Box  Culvert:        Rebar  work  on  the  box culvert  walls  and  ceiling  is  ongoing.      The contractor  continues  assembling  the  wall &  ceiling  plate  forms  and  completing  the associated  concrete  pours.   Approximately  150  feet  remains  to  be installed.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 33,343  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           June  6th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser restoration  is  complete. The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  450.    Additional  berm  placement  is  ongoing.                Sediment  Basin: 1)           We  have  removed  the remainder  of  the silty  material  from  the  north  and  south ends  of  the  basin.      Crushed  stone  and  perforated  pipe from  the  under  drain  system has  been  replaced.   This  project  was  physically  complete  on  Thursday  June  9th.    The documentation  report  will  be  submitted  on  June  15th.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This project  is  completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  during  this  reporting  period.
  • 281. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 282.  
  • 283. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL Final Report for Sedimentation Basin Restoration Date: Wednesday, June 15, 2011 12:58:00 PM Attachments: WMH Ltr Rpt Sedimentation Basin Repair_061511.pdf Greetings  all. Please  find  a  copy  of  the  final  report  documenting  the  restoration  of  the sedimentation  basin  located  at  the  Waimanalo  Gulch  Sanitary  Landfill.   Best  regards, Joe                         Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 284.  
  • 285. From: Whelan, Joseph To: "Kabei.Arlene@epamail.epa.gov"; "Armann.Steve@epamail.epa.gov"; "Vaille.Rich@epamail.epa.gov"; "Tyahla.Stephen@epamail.epa.gov"; "Moxley.Bret@epamail.epa.gov"; "Helmlinger.Andrew@epamail.epa.gov"; "Wall.Steve@epamail.epa.gov"; "stuart.yamada@doh.hawaii.gov"; "Steven.chang@doh.hawaii.gov"; "alec.wong@doh.hawaii.gov" Subject: WGSL AOC Progress Report for Week Ending June 19, 2011 Date: Monday, June 20, 2011 5:01:00 PM Greetings  All. The  USEPA  granted  our  request  to  replace  the  daily  progress  reports  with  a weekly  report  thru  an  email  dated  March  17,  2011.    These  weekly  reports  will  be submitted  by  noon  each  Wednesday  and  document  work  completed  during  the  period of  the  prior  Monday  thru  Sunday.      This  weekly  progress  report  covers June 13  thru Sunday  June 19th. ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                Cell  6  Assessment: 1)           The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern portion  of  the  E6  liner  system  was  submitted  February  25,  2011.    We  received notification  from  DOH  on  March  1,  2011  concurring  that  the  CQA  report  was  adequate documentation  of  the  liner  repairs,  which  allows  WMH  to  resume  operations  in  this area.    This  project  is  completed. 2)           The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13, 2011  storm.    This  area  is  located  directly  below  the  section  of  the  storm  water diversion  system  where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently, any  rock  and  soil  material  generated  from  the  January  storm  event  and  the construction  of  the  diversion  system  in  this  area  had  to  be  removed  prior  to  the evaluation  and  repair  of  the  liner.    This  material  has  now  been  removed  from  the  side slope  of  the  gulch.    The  contractor  has  completed  removing  the  material  that  fell directly  on  the  liner.    Replacement  of  the  final  piece  of  the  damaged  liner  was completed  on  April  1st,  and  the  CQA  report  submitted  on  April  4th.    This  project  is completed. 3)           All  liner  repairs  resulting  from  the  December/January  storm  event  damage  have now  been  completed.                Western  Storm  water  Diversion  Project  (to  render  functional): Diversion  Structure:     The  diversion 1)   structure  concrete  work  is  complete.
  • 286. 2)    Box  Culvert:        Rebar  work  on  the  box culvert  walls  and  ceiling  is  ongoing.      The contractor  continues  assembling  the  wall &  ceiling  plate  forms  and  completing  the associated  concrete  pours.   Approximately  50  feet  remains  to  be installed,  which  should  be  completed within  two  weeks.  3)    Pipe:      Backfilling  of  the  HOBAS  pipe channel  is  now  complete. 4)    The  diversion  structure  was functionally  complete  per  the  terms  of Section  19.b.  of  the  AOC  as  of  February 15,  2011.                Cell  6  Leachate  Riser  Restoration: 20,092  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  since 1)           June 13th,  and  transported  to  the  waste  water  treatment  plant.        Leachate  riser restoration  is  complete. The  south  pond  area  contains  no  ponded  water,  and  was  prepped  for  the  next 2)           phase  of  the  Western  Berm  Construction.      Phase  III  of  the  western  berm  construction is  now  complete  to  elevation  450.   This  project  is  completed.                Sediment  Basin: 1)           This  project  was  physically  complete  on  Thursday  June  9th.    The  documentation report was  submitted  on  June  15th.                Evaluating  possible  hydraulic  head  below  liner  system: 1)           Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at temporary  piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered   during  the  drilling  process.  Since  no  water  was  observed,  temporary  piezometers  were not  installed.      The  documentation  report  was  submitted  on  February  25,  2011.    This project  is  completed.               Beach  Assessment  Update: 1)           The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls received  at  the  established  beach  waste  hot  line  during  this  reporting  period.
  • 287. ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS  –  None Please  let  me  know  if  you  have  any  questions.     Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 288.  
  • 289. From: Whelan, Joseph To: "Tyahla.Stephen@epamail.epa.gov" Subject: Request to cease submission of weekly progress reports - WGSL Date: Wednesday, June 22, 2011 9:37:00 AM Hello  Steve, The  most  recent  progress  report  noted  that  all  items  under  the AOC  task  list  are  now complete,  and  we  are  working  on  the  final  documentation  report.    Waste  Management  is requesting  EPA  approval  to  cease  the submission  of  the  weekly  progress  reports.   The  only item  that is still uncompleted  is  the  final  50  feet  of  the  box  culvert,  which  is  not  part  of  the AOC  requirements.   Since  the  report  documenting  completion  of  the  sedimentation  basin retrofit  was  submitted  on  June  15 th ,  and  the  AOC  requires  submission  of  the  final  report within  60  days,  WMH  believes  the  final  report  is  due  on  August  14,  2010.    Please  also acknowledge  that  this  date  is  correct.    Thank  you. Best  regards, Joe Joe Whelan General Manager Waste Management of Hawaii 808-­668-­2985, ext. 15 Office 808-­668-­1366 Fax 808-­479-­4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 290.  
  • 291. From: Tyahla.Stephen@epamail.epa.gov [mailto:Tyahla.Stephen@epamail.epa.gov] Sent: Wednesday, June 22, 2011 1:29 PM To: Whelan, Joseph Cc: lene.ichinotsubo@doh.hawaii.gov; steven.chang@doh.hawaii.gov; alec.wong@doh.hawaii.gov; stuart.yamada@doh.hawaii.gov; Armann.Steve@epamail.epa.gov; Moxley.Bret@epamail.epa.gov Subject: Re: Request to cease submission of weekly progress reports - WGSL Joe, Concur with your request to cease submitting Progress Reports. While we concur that you have substantially completed the sedimentation basin restoration work, we are gathering what I'll term a punch list of items for you to address. I'm still awaiting some input so am unable to forward that punch list to you at this time, but should be able to within the next few business days. Concur that the Final Report, per paragraph 25 of the Order, shall be due on or before 14 August. Stephen F. Tyahla, P.E.,CHMM Project Manager, RCRA Corrective Action Office Waste Management Division U.S. EPA Region IX 75 Hawthorne Street (WST-5) San Francisco, CA 94105 Ph. 415.972.3466 / Fax 415.947.3533 tyahla.stephen@epa.gov [This email, including any attachments, may contain non-public, privileged and/or confidential information solely intended to be conveyed to the designated recipient(s). If you receive this email and are not an intended recipient, please delete this email and its attachments immediately. The unauthorized use, dissemination, distribution, or reproduction of this email and its attachments is strictly prohibited by law.] From: "Whelan, Joseph" <JWhelan1@wm.com> To: Stephen Tyahla/R9/USEPA/US@EPA Date: 06/22/2011 12:37 PM Subject: Request to cease submission of weekly progress reports - WGSL Hello Steve, The most recent progress report noted that all items under the AOC task list are now complete, and we are working on the final documentation report. Waste Management is requesting EPA approval to cease the submission of the weekly progress reports. The only item that is still uncompleted is the final 50 feet of the box culvert, which is not part of the AOC requirements. Since the report documenting completion of the sedimentation basin retrofit was submitted on June 15th, and the AOC requires submission of the final report within 60 days, WMH believes the final report is due on August 14, 2010. Please also acknowledge that this date is correct. Thank you. Best regards, Joe
  • 292.  
  • 293. From: Whelan, Joseph Sent: Thursday, August 04, 2011 4:45 PM To: 'Kabei.Arlene@epamail.epa.gov'; 'Armann.Steve@epamail.epa.gov'; 'Vaille.Rich@epamail.epa.gov'; 'Tyahla.Stephen@epamail.epa.gov'; 'Moxley.Bret@epamail.epa.gov'; 'Helmlinger.Andrew@epamail.epa.gov'; 'Wall.Steve@epamail.epa.gov'; 'stuart.yamada@doh.hawaii.gov'; 'Steven.chang@doh.hawaii.gov'; 'alec.wong@doh.hawaii.gov' Subject: WGSL Sedimentation Basin Restoration Addendum Report Greetings all. The final individual project report required by the Administrative Order on Consent (AOC), which documented the restoration of the storm water sedimentation basin was submitted to you on June 15, 2011. WMH received comments from EPA on June 28, 2011. Please find attached the report documenting additional work performed to address these comments. We would appreciate your concurrence that this project is now complete. This project report will be included in the final AOC report to be submitted by August 15, 2011. Please contact me with any questions. Best regards, Sedimentation Basin Repair Add... Joe Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.
  • 294.  
  • 295.   Appendix  B   Work  Plans      
  • 296.  
  • 297. Waimanalo Gulch Sanitary Landfill Stormwater Management Update and Contingency Plan 1/27/2011     Following  the  recent  major  storm  events,  Waste  Management  of  Hawaii  (WMH)  has  assessed   and  evaluated  its  stormwater  control  systems  for  effectiveness.  Below  is  an  update  of  ongoing  measures   being  taken  to  prevent  future  storm  damage  at  the  site,  and  document  efforts  to  further  contain   potential  storm  water  and  prevent  waste  material  from  exiting  the  facility  in  the  event  of  a  major  storm.     1) The  36-­‐inch  drain  was  designed  to  handle  water  falling  within  the  landfill  footprint,  upstream  of   the  waste  disposal  area,  during  landfilling  operations.    It  was  also  intended  to  mitigate  runon   during  small  storms  until  the  diversion  channels  are  in  place.    The  west  side  drainage  channel   has  been  designed  to  control  the  100-­‐year  storm  and  will  mitigate  the  impact  of  storms  with   higher  return  periods.       The  effectiveness  of  36-­‐inch  inlet  structure  for  the  up  canyon  drainage  system  has  been   restored  and  improved.  The  area  immediately  surrounding  the  inlet  structure  has  been   re-­‐graded  and  armored  with  large  boulders  to  prevent  high  sediment  loading  from   clogging  the  inlet.  A  diversion  berm  immediately  downstream  of  this  diversion  structure   has  been  reinforced  and  re-­‐built  to  further  direct  any  stormwater  into  the  inlet   structure.     The  area  surrounding  the  future  Cell  E-­‐8  is  being  excavated  down  to  the  elevation  of  the   36-­‐inch  pipe  inlet  structure.  This  effort  will  help  to  create  stormwater  retention,   dissipate  stormwater  velocities,  and  drop  out  sediment  as  it  moves  from  the  upper   ongoing  since  1/18.         2) Establish  a  functioning  Western  Drainage  System.   In  order  to  establish  a  functioning  Western  Drainage  System,  the  up  canyon  conveyance   structure  must  be  in  place  to  divert  storm  water  into  the  box  culvert  and  fiberglass   piping  system.  Additionally,  the  box  culvert  invert  that  originates  at  the  diversion   ss  piping  located  on  the  upper  bench   above  Cell  E-­‐ A  functioning  Western  Drainage  System  will  be  in  place  within  2  weeks,  barring  any   additional  large  rainfall  events  that  would  prevent  this  work  from  being  safely   completed.           3) Temporary  containment  berm  directly  south  of  Cell  E6   12-­‐19-­‐10  storm  to  contain   large  stormwater  flows  originating  from  up  canyon  and  prevent  a  catastrophic  discharge   from  the  site.  The  berm  did  safely  contain  this  storm,  and  was  subsequently   substantially  reinforced  prior  to  the  storm  that  occurred  on  1-­‐13-­‐11.      The  storm  water   that  was  contained  behind  the  berm  has  now  been  removed,  creating  a  storage  area   capable  of  containing  water  from  a  similar  rainfall  event.  Preliminary  stability  analysis   indicates  the  berm  has  adequate  strength  to  contain  the  runoff.      
  • 298.  
  • 304.  
  • 316.  
  • 318.  
  • 338.  
  • 339. 475 - 14th Street, Suite 400 Oakland, California 94612 PH 510.836.3034 FAX 510.836.3036 www.geosyntec.com 31 January 2011 Mr. Richard T. Von Pein, P.E. Waste Management 9081 Tujunga Avenue Sun Valley, CA 91352 RE: Waimanalo Gulch Landfill Work Plan for Evaluating Hydraulic Head Below Liner System Dear Mr. Von Pein: As requested by Waste Management of Hawaii, Inc. (WMH), Geosyntec Consultants, Inc. (Geosyntec) has prepared a Work Plan to evaluate the possibility of excess pressure below the liner system in areas of Cell E6 where water ponded after the storms in December 2010 and January 2011. This Work Plan is a required element of the “Work” pursuant to Section 19.e of the Administrative Order on Consent for Removal Action, CERCLA Docket No. 09-20111- 0007/RCRA Docket No. 7003-09-2011-0001. For reference, the liner system on the side slopes of the expansion area of the Landfill, from bottom to top, consists of: Subgrade; Soil cushion layer; Encapsulated geosynthetic clay liner (GCL) composite liner system consisting of: (i) 40-mil-thick high density polyethylene (HDPE) geomembrane (textured on both sides), (ii) GCL (reinforced, needle-punched, with 2 nonwoven geotextile carriers), and (iii) 60-mil-thick HDPE geomembrane (textured on both sides); 16-ounce nonwoven cushion geotextile; and Operations layer. For the floor areas, all the components are the same as for the side slopes, except that a 1-foot- thick gravel layer overlain by a separator nonwoven geotextile is between the cushion geotextile and the operations layer. P:PRJ2003GeoWMIWaimanaloWL0770Related to USEPA (2011)Workplan to Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.doc
  • 340. Mr. Richard T. Von Pein, P.E. Waimanalo Gulch Landfill Work Plan for Evaluating Hydraulic Head Below Liner System 31 January 2011 Page 2 WORK PLAN To evaluate hydraulic head below the liner, the drilling of up to 6 temporary piezometers to various depths below the existing ground surface is proposed. Figure 1 shows the approximate locations of the piezometers and a table with the estimated ground elevation and the estimated drilling depth to reach below the liner level. These drilling depths will need to be confirmed at the time of drilling to verify that the appropriate elevation will be achieved. Piezometer locations may be adjusted in the field as needed with concurrence by the engineer. As can be observed, the piezometers are located around the perimeter of Cell E6. The locations of the piezometers will need to be located away from buried utilities such as the 18-inch and 36- inch HDPE surface water conveyance pipes. The borings are planned to be outside the lined area except where the liner has been damaged and must be replaced. The as-built locations of the utilities (buried or on the surface) will need to be established before drilling begins. After the drilling has been performed, and if saturated conditions are encountered, piezometers will be installed under the supervision of either a geotechnical engineer or a hydrogeologist who will also monitor the water levels. If saturated conditions are not encountered, the number of borings/piezometers may be reduced. DOCUMENTATION At each temporary piezometer location, documentation should consist of the following: 1) Water level (if any) at the time of drilling when water first encountered. 2) Water level after stabilization/construction of any temporary piezometers. 3) Piezometer construction log (only required if saturated conditions are encountered) (i.e., surveyed ground surface elevation, depth of casing below the ground surface, perforated length or gravel pack area, stickup above the ground surface, etc.). The installer of the standpipe needs to have an adequate supply of pipe and the ability to maintain it vertical to accommodate artesian conditions if encountered. 4) Photographic documentation of the various piezometers. 5) Monitoring of water level at each piezometer during a 24-hour period after installation. The objective is to record increases, decreases, or no movement of the water level with time. If the water level does not change, the piezometer can be decommissioned after 72 hours or after obtaining approval from the engineer. If hydraulic heads are observed, the locations will need to be monitored for longer periods and a plan will need to be prepared to relieve these pressures over time. 6) After the monitoring period is finished, the temporary piezometers will need to be decommissioned by filling in the boring with a cement/bentonite mix. P:PRJ2003GeoWMIWaimanaloWL0770Related To USEPA (2011)Workplan To Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.Doc
  • 341. Mr. Richard T. Von Pein, P.E. Waimanalo Gulch Landfill Work Plan for Evaluating Hydraulic Head Below Liner System 31 January 2011 Page 3 A report summarizing the findings will need to be prepared by the professional under whose supervision the work was performed. Based on water levels, if any are encountered, WMH will develop needed remedial measures, which could include temporary extraction wells. SCHEDULE Installation of the piezometers will depend on the progress of the ongoing slope excavation and cleanup of the lower portion of the E-6 cell. At this time, only piezometers PZ-5 and PZ-6 will be installed. WMH anticipates drilling in this area within 5 days. Due to a potential rockfall hazard in this area related to the west diversion channel construction, this work will need to be coordinated with diversion channel construction. As soon as WMH can gain access to the southern portion of cell E-6, following removal of mud in this area, WMH will drill PZ-1 and if necessary install a piezometer at this location. WMH anticipates that installation of this boring would be in approximately 20 days. If WMH does not encounter water in PZ-1, PZ-5, or PZ-6, no additional borings would be completed. If needed, PZ-2, PZ-3 and PZ-4 would be installed after loose rock is removed from the slopes above this area. WMH anticipates that completion of the western diversion channel and removal of loose rock from the slope will take approximately 45 days. Please contact us if there are further questions. Sincerely yours, Hari D. Sharma, Ph.D., P.E. Principal ATTACHMENT Figure 1 – Proposed Temporary Piezometer Locations COPY TO Mr. Joseph Whelan (WMH) Mr. Jesse Frey (WMH) P:PRJ2003GeoWMIWaimanaloWL0770Related To USEPA (2011)Workplan To Address Hydraulic Head Below Liner - Jan 2011Letter-Hydraulic Head Workplan-31Jan11.Doc
  • 342.  
  • 348.  
  • 352.  
  • 358.  
  • 372.  
  • 374.  
  • 375. Beach Assessment and Recovery - 19(i) EPA Order: WM shall provide to EPA and DOH a work plan and schedule for ongoing daily beach assessment and recovery of waste material released from WGSL. In response to the stormwater release that carried waste material from the WGSL on January 13, 2011, WM has implemented a beach assessment and cleanup. On January 13,2010, "Potentially Contaminated Water" warning signs were posted near the outfall and the surrounding beaches by the City and County of Honolulu. The initial assessment on January 14, 2011 was focused on the stormwater outfall that carries the waters of the WGSL drainage basin. WM continued assessment on January 15 at the outfall and on January 16, WM began covering several nearby beaches that had reports of observed waste. WM performed daily assessments and cleanup as necessary daily until January 21, 2011 and because the amount of waste observed diminished drastically, suspended the daily assessment. On January 24, WM performed one final assessment and observed no waste that could have been attributed to the WGSL. WM will continue to respond and track reports of waste on the nearby beaches. Attached is a log of recovered waste from the beaches and the WGSL outfall and a log of phone reports of waste.
  • 376. MEDICAL WASTE SIGHTING lOG: PHONE 1/ WHEN, WHAT AND WHERE SEEN 1/16/11 seen a syringe on the beach in Nanakulu 1/17/2011 Sue Ellen 673-1922 directly across Hakimo Rd. 1/17/11 seen syringes and cotton at all 4 lagoons at 1/17/2011 John Merritt 864-7482 Ko'Olina 1/17/11 seen syringes with and without needles and 1/18/2011 Lawton 368-2004 some sediment at Ko'Olina lagoon 3 1/20/11 seen a syringe without needle on beach 1/20/2011 Wayne Yamamoto 388-1236 fronting Paradise Cove ... prefers not to handle himself 1/17/11lifegaurds at Pokai Bay found 4 -5 syringes ... he heard from a reliable source of his that medical waste trucks were seen dumping their waste in sewer lines in 696-3069 or 333- Maile and Pokai Bay ... is that true? AWould like to 1/24/2011 Charles Lopez 7075 know if the City has documentation regarding disposal whereabouts? Why were no signs posted at Pokai Bay that beach was closed, there were signs at the Army Rest Camp Beach a couple miles away? Army Rest Camp took samples and found lots of bacteria. He tried contacting City via phone/email ... got no response. Someone (Carroll Cox) reported seeing medical waste at 1/26/2011 Lene of DOH 586-4226 WGSL stormwater outlet at Ko'Olina ... don't know when it was seen or if it had already been cleaned-up.
  • 378.  
  • 380.  
  • 388.  
  • 390.  
  • 396.  
  • 399. Beach Assessment and Recovery –– 19(i) EPA Order: WM shall provide to EPA and DOH a work plan and schedule for ongoing daily beach assessment and recovery of waste material released from WGSL. WM Response: In response to the stormwater release that carried waste material from the WGSL on January 13, 2011, WM implemented a beach assessment and cleanup program. On January 13, 2010, ““Potentially Contaminated Water”” warning signs were posted near the outfall and the surrounding beaches by the City and County of Honolulu. The initial assessment on January 14, 2011 was focused on the stormwater outfall that carries the waters of the WGSL drainage basin. WM continued assessment on January 15 at the outfall and on January 16, WM began covering several nearby beaches that had reports of observed waste. On January 16, WM set up a hotline to enable the public to report waste observed on the beaches near the landfill to the proper personnel for cleanup. This hotline remains active and the phone number is directed to our landfill office receptionist. The receptionist maintains a call log to document incoming calls. WM performed daily assessments and cleanup of all identified beaches until January 21, 2011, at which time the amount of waste observed diminished drastically, and the daily assessment was suspended. On January 24, WM performed one final assessment and observed no waste that could have been attributed to the WGSL. WM continues to respond and track reports of waste on the nearby beaches. Attached is a log of recovered waste from the beaches and the WGSL outfall (Attachment 1) and a log of phone reports of waste (Attachment 2). WM will also report via email as part of the Daily Progress Report to the EPA and DOH any response performed by our staff or authorized parties on beaches or shorelines in response to either reports received or any WM inspections.
  • 400.  
  • 402.  
  • 403. Waimanalo Gulch Sanitary Landfill Storm Response Beach Cleanup Summary Log Debris/Typical Ocean Trash (No. Date Location of 40 gallon bags) Medical Waste 13 Jan Stormwater Sampling, and Warning Signs Placed 0 0 14 Jan WGSL Storm Drain Outlet 20 1 gallon bucket full 15 Jan WGSL Storm Drain Outlet 10 2 syringes, 1 vial 16 Jan White Plains Beach 5 1 syringe 16 Jan WGSL Storm Drain Outlet 0.5 7 syringes 17 Jan White Plains Beach 2 2 syringes, 1 vial 17 Jan White Plains Beach/Nimitz Beach 1 2 syringes 18 Jan Pokai Bay 0 0 18 Jan White Plains Beach/Nimitz Beach 4 0 18 Jan White Plains Beach/Nimitz Beach 10 2 syringes 19 Jan White Plains Beach/Nimitz Beach 0 1 syringe 19 Jan Pokai Bay 0 0 19 Jan Kahe Beach/Tracks/WGSL Discharge/HECO Discharge 0 1 syringe, 1 vial 20 Jan Kahe Beach/Tracks/WGSL Discharge/HECO Discharge 0 0 20 Jan Ko'Olina (Paradise Cove) 0 1 syringe 20 Jan White Plains Beach/Nimitz Beach 0 0 21 Jan White Plains Beach/Nimitz Beach 0 0 21 Jan Kahe Beach/Tracks/WGSL Discharge/HECO Discharge 0 0 24 Jan Kahe Beach/Tracks/WGSL Discharge/HECO Discharge/Paradise Cove 0 0 24 Jan White Plains Beach/Nimitz Beach 0 0 26 Jan WGSL Storm Drain Outlet (at request of DOH in response to personal report) 0 0 3 Feb KoOlina Lagoon #4 (response to call) 0 6 syringes 18 Feb KoOlina Lagoon #4 (response to call) 0 0
  • 404.  
  • 406.  
  • 407. MEDICAL WASTE SIGHTING LOG: DATE NAME REPRESENTING / PHONE # WHEN, WHAT AND WHERE SEEN Reported that lifeguard at White Plains Beach found 2 1/14/2011 Arlene Kabai EPA Region 9 syringes in the water. Reported that lifeguard at White Plains Beach found syringes that had washed onshore. Joe Whelan called lifeguard (Moku) who found 6 syringes w/o needles and 1/15/2011 Arlene Pang State of HI AG Office 2 needles Got call regarding syringes found at Pokai Bay. Turned 1/17/2011 Terrence Johnson EPA them in to Tulsi Gabbard. 1/16/11 seen a syringe on the beach in Nanakulu 1/17/2011 Sue Ellen 673 1922 directly across Hakimo Rd. 1/17/11 seen syringes and cotton at all 4 lagoons at 1/17/2011 John Merritt 864 7482 Ko'Olina 1/17/11 seen syringes with and without needles and some sediment at Ko'Olina lagoon 3 (Found to be clean 1/17/2011 Lawton 368 2004 needles) 1/20/11 seen a syringe without needle on beach 1/20/2011 Wayne Yamamoto 388 1236 fronting Paradise Cove …… prefers not to handle himself 1/17/11 lifegaurds at Pokai Bay found 4 5 syringes …… he heard from a reliable source of his that medical waste trucks were seen dumping their waste in sewer lines in Maile and Pokai Bay …… is that true? AWould like to know 1/24/2011 Charles Lopez 696 3069 or 333 7075 if the City has documentation regarding disposal whereabouts? Why were no signs posted at Pokai Bay that beach was closed, there were signs at the Army Rest Camp Beach a couple miles away? Army Rest Camp took samples and found lots of bacteria. He tried contacting City via phone/email ... got no response. Someone (Carroll Cox) reported seeing medical waste at 1/26/2011 Lene of DOH 586 4226 WGSL stormwater outlet at Ko'Olina …… don’’t know when it was seen or if it had already been cleaned up. medical waste found by lagoon 4 , items not confirmed. Nat called Left mssg. For Caroline WM will be onsite to 1/31/2011 Caroline KoOlina sports clu 679 3723 search for more waste. 2/2/11 syringe without needle (he has it) seen at Ko'olina jetty at lagoon 4 in front of the marina. Also reports seeing a lot of garbage (he's thinks may have come from landfill) along the shore line. Rick confirmed medical at location + rubbish mixed, he brought 3/4 of 2/3/2011 Sam/Sue Rakes 512 250 8141 trash bag back to site. found 2 more syringes at lagoon 4 area LM on VM; Smith arrived to Ko'Olina on 2/18, Sam confirm he threw away 2/15/2011 Sam Rakes 512 250 8141 already.
  • 408.  
  • 409. Collection and Transport of Liquid Behind Temporary Berm –– Order 19 (d) EPA Order: WM shall continue to collect and transport to a local treatment facility the liquids retained behind the temporary berm in cell E6. WM shall provide a written description of the collection and treatment activities, the current permitting and the chemical parameters of the liquids, and transportation methods to the local treatment facility. WM Response: WM began removing storm water that was stored behind the temporary berm in cell E6 via tanker trucks and transported the water to permitted treatment facilities operated by the City and County of Honolulu on January 19, 2011. Attached is a copy of sample results from the storm water collected at the sediment pond outfall on January 13th (Attachment 1). Also attached is a summary copy of the hauling logs that detail the volume of transported liquid, and the name of the waste water treatment plant (Attachment 2). WM is unaware of any pretreatment standards for discharging stormwater to these wastewater treatment plants. Samples from the sediment basin were also collected on February 2, 2010 and those results are summarized in an attached table (Attachment 3). After removing the water impounded behind the temporary berm, some amount of mud and sediment remained near the E6 sump area. This mud was not solid enough to load out and haul away, so liquid is skimmed off from the mud surface with a vacuum truck to help facilitate the removal of the remaining mud material. The remaining sediment will be excavated and hauled to a bermed area on the landfill so that it can dry. The attached figure shows the location where this sediment is being stored (Attachment 4). Each area is located within lined areas of the MSW portion of the landfill. Samples of the sediment were collected to determine its ultimate use in the landfill. Results of those samples were compared to our solid waste permit requirements, and the soil has been approved for use as daily cover. The laboratory report from those samples is attached (Attachment 5). Some of the remaining sediment will be placed in several 20,000 gallon mobile storage tanks to attempt to separate the liquid phase from the sediment phase of the material. Any liquid removed through this process will be hauled via a third party hauling company to a County of Honolulu permitted wastewater treatment plant. This process will continue until all recoverable sediment and liquids are removed.
  • 410.  
  • 412.  
  • 413. Waimanalo Gulch Sanitary Landfill Storm Water Monitoring 13 January 2011 Discharge Event Laboratory Final Data Summary Table Method Analyte Unit Screening Benchmark CULVERT a b Criteria Level 1664A HEM (Oil and Grease) mg/L 15 15 5.1 Alpha Terpineol mg/L 0.016 NA < 0.01 Benzoic acid mg/L 0.071 NA < 0.05 40CFR136A 625 p Cresol mg/L 0.014 NA < 0.01 Pentchlorophenol mg/L 0.02 NA < 0.021 * Phenol mg/L 0.015 1.0 < 0.01 Arsenic mg/L 0.36 0.16854 < 0.015 Cadmium mg/L 0.003 0.0159 < 0.00045 * Calcium mg/L NA NA 24 Iron mg/L 1.0 1.0 8.6 Lead mg/L 0.029 0.0816 0.0034 J EPA 200.7 Rev 4.4 Magnesium mg/L NA 0.0636 13 Potassium mg/L NA NA 7 Selenium mg/L 0.02 0.2385 0.0078 J Silver mg/L 0.001 0.0318 < 0.00093 * Sodium mg/L NA NA 73 B Zinc mg/L 0.022 0.117 0.017 J EPA 245.1 Mercury mg/L 0.0024 0.0024 < 0.0002 EPA 7196 Hexavalent Chromium µg/L 16 NA < 10 EPA 365.1 Phosphorus, Total mg/L NA 2.0 0.38 B MCAWW 350.1 Ammonia mg/L 4.9 19 0.11 MCAWW 353.2 Nitrate Nitrite as Nitroge mg/L NA 0.68 2.9 EPA Total Nitrogen Nitrogen, Total mg/L NA NA 4.8 EPA 405.1 BOD (5 Day) mg/L NA 30 8.91 MCAWW 410.4 Chemical Oxygen Deman mg/L NA 120 45 SM 2540D Total Suspended Solids mg/L 100 100 57 MCAWW 300.0A Bromide mg/L NA NA 0.73 Chloride mg/L NA 860 95 Sulfate mg/L NA NA 45 B SM 2320B Bicarbonate Alkalinity mg/L NA NA 77 Carbonate Alkalinity mg/L NA NA <5 Total Alkalinity mg/L NA NA 77 Bac T Total Coliform MPN/100 mL NA NA > 1,600 E. coli MPN/100 mL NA NA < 2.0 Field Method pH SU 5.5 8.0 6.0 9.0 8.14 Note: a screening criteria are based on the requirements in the Waimanalo Gulch Storm Water Discharge Permit b benchmark levels are developed by EPA for storm water discharge < not detected above the reporting limits > greater than * not detected above the method detection limits µg/L micrograms per liter mg/L milligrams per liter B compound was found in the blanks (0.221 J mg/L for Sodium, 0.0115 J mg/L for Total Phosphorus; and 0.245 J mg/L for Sulfate) BOD biochemical oxygen demand HEM n hexane extractable material NA no limitation at this time J estimated result is less than the reporting limit but greater than or equal to the method detection limit SU standard unit
  • 416.  
  • 417. Waimanalo Gulch Sanitary Landfill Stormwater from Behind Temporary Berm Below the E6 Cell Pumping Log Summary Volume Date Waianae Kailua Total 1/13/2011 0 0 0 1/14/2011 0 0 0 1/15/2011 0 0 0 1/16/2011 0 0 0 1/17/2011 0 0 0 1/18/2011 150,000 45,000 195,000 1/19/2011 150,000 72,000 222,000 1/20/2011 148,000 0 148,000 1/21/2011 136,000 79,000 215,000 1/22/2011 150,000 68,300 218,300 1/23/2011 / / 132,000 , 11,000 , 143,000 , 1/24/2011 0 0 0 1/25/2011 0 21,867 21,867 1/26/2011 0 0 0 1/27/2011 0 0 0 1/28/2011 0 0 0 1/29/2011 0 0 0 1/30/2011 0 22 000 22,000 22 000 22,000 1/31/2011 0 16,500 16,500 2/1/2011 0 16,500 16,500 2/2/2011 0 22,000 22,000 2/3/2011 0 0 0 2/4/2011 0 0 0 2/5/2011 0 0 0 2/6/2011 0 0 0 2/7/2011 0 0 0 2/8/2011 0 0 0 2/9/2011 0 0 0 2/10/2011 0 11,000 11,000 2/11/2011 0 0 0 2/12/2011 0 28 318 28,318 28 318 28,318 2/13/2011 0 21,000 21,000 2/14/2011 0 14,159 14,159 2/15/2011 0 70,005 70,005 2/16/2011 0 48,430 48,430 2/17/2011 0 50,034 50,034 2/18/2011 0 34,000 34,000 2/19/2011 0 0 0 2/20/2011 0 0 0 2/21/2011 0 0 0 2/22/2011 0 0 0 2/23/2011 0 0 0 Total 866,000 651,113 1,517,113
  • 418.  
  • 420.  
  • 421. Waimanalo Gulch Sanitary Landfill Sediment Pond Water Sample Collected on 2/2/2011 Laboratory Final Data Summary Table Method Analyte Unit Screening Criteria a Benchmark Level b SED POND 1664A HEM (Oil and Grease) mg/L 15 15 2J Alpha Terpineol mg/L 0.016 NA < 0.01 Benzoic acid mg/L 0.071 NA < 0.05 40CFR136A 625 p Cresol mg/L 0.014 NA < 0.01 Pentchlorophenol mg/L 0.02 NA < 0.021 * Phenol mg/L 0.015 1 < 0.01 Arsenic mg/L 0.36 0.16854 0.0057 J Cadmium mg/L 0.003 0.0159 < 0.005 Calcium mg/L NA NA 48 Iron mg/L 1 1 4.6 Lead mg/L 0.029 0.0816 < 0.009 EPA 200.7 Rev 4.4 Magnesium mg/L NA 0.0636 25 Potassium mg/L NA NA 5.8 Selenium mg/L 0.02 0.2385 < 0.015 Silver mg/L 0.001 0.0318 < 0.00093 * Sodium mg/L NA NA 110 Zinc mg/L 0.022 0.117 0.019 J EPA 245.1 Mercury mg/L 0.0024 0.0024 0.000055 J EPA 7196 Hexavalent Chromium µg/L 16 NA < 10 EPA 365.1 Phosphorus, Total mg/L NA 2 0.21 MCAWW 350.1 Ammonia mg/L 4.9 19 0.3 B MCAWW 353.2 Nitrate Nitrite as Nitrogen mg/L NA 0.68 0.072 J EPA Total Nitrogen Nitrogen, Total mg/L NA NA 1.9 EPA 405.1 BOD (5 Day) mg/L NA 30 4.18 MCAWW 410.4 Chemical Oxygen Demand mg/L NA 120 36 SM 2540D Total Suspended Solids mg/L 100 100 26 MCAWW 300.0A Bromide mg/L NA NA 0.85 Chloride mg/L NA 860 120 Sulfate mg/L NA NA 110 SM 2320B Bicarbonate Alkalinity mg/L NA NA 170 Carbonate Alkalinity mg/L NA NA 4.7 J Total Alkalinity mg/L NA NA 170 Bac T Total Coliform MPN/100 mL NA NA 170 E. coli MPN/100 mL NA NA < 2.0 Field Method pH SU 5.5 8.0 6.0 9.0 7.22 Note: a screening criteria are based on the requirements in the Waimanalo Gulch Storm Water Discharge Permit b benchmark levels are developed by EPA for storm water discharge Bold exceed screening criteria < not detected above the reporting limits * not detected above the method detection limits µg/L micrograms per liter mg/L milligrams per liter B compound was found in the method blank (0.0241 J mg/L for Ammonia) BOD biochemical oxygen demand HEM n hexane extractable material MPN most probable number NA no limitation at this time J estimated result is less than the reporting limit but greater than or equal to the method detection limit SU standard unit
  • 424.  
  • 428.  
  • 429. ANALYTICAL REPORT Job Number: 280-12120-1 Job Description: 995|Waimanalo Gulch LF For: Waste Management Waimanalo Gulch Landfill 92-460 Farrington Highway Kapolei, HI 96707 Attention: Mr. Justin Lottig Approved for release. Betsy A Sara Project Manager II _____________________________________________ 2/16/2011 1:05 PM Betsy A Sara Project Manager II betsy.sara@testamericainc.com 02/16/2011 cc: Mr. John Fong Mr. Pete LaPlaca The test results in this report relate only to the samples in this report and meet all requirements of NELAC, with any exceptions noted. Pursuant to NELAP, this report shall not be reproduced except in full, without the written approval of the laboratory. All questions regarding this report should be directed to the TestAmerica Denver Project Manager. The Lab Certification ID# is E87667. Reporting limits are adjusted for sample size used, dilutions and moisture content if applicable. TestAmerica Laboratories, Inc. TestAmerica Denver 4955 Yarrow Street, Arvada, CO 80002 Tel (303) 736-0100 Fax (303) 431-7171 www.testamericainc.com Page 1 of 110
  • 430. Table of Contents Cover Title Page . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Report Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Method Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 Method / Analyst Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Sample Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Sample Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Sample Datasheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Data Qualifiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 QC Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59 Qc Association Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 Surrogate Recovery Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 Qc Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Laboratory Chronicle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100 Client Chain of Custody . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108 Sample Receipt Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110 Page 2 of 110
  • 431.                                            Page 3 of 110
  • 432.                         Page 4 of 110
  • 433.                                                                                                                                                                                                                                                  Page 5 of 110
  • 434.                                                                                                                                                                                                                          Page 6 of 110
  • 435.                                                                                                                                                                                                                          Page 7 of 110
  • 436.                                                                            Page 8 of 110
  • 437.                                   Page 9 of 110
  • 438.                                     Page 10 of 110
  • 440.                                                                                                                                                                                                                                   Page 12 of 110
  • 441.                                                                                  Page 13 of 110
  • 442.                                                                                                                                                                                                                                  Page 14 of 110
  • 443.                                                                                  Page 15 of 110
  • 444.                                                                                                                                                                                                                                   Page 16 of 110
  • 445.                                                                                  Page 17 of 110
  • 446.                                                                                                                                                                                                                                  Page 18 of 110
  • 447.                                                                                     Page 19 of 110
  • 448.                                                                                                                                                                                                                                  Page 20 of 110
  • 449.                                                                                  Page 21 of 110
  • 450.                                                        Page 22 of 110
  • 451.                                                        Page 23 of 110
  • 452.                                                        Page 24 of 110
  • 453.                                                         Page 25 of 110
  • 454.                                                        Page 26 of 110
  • 455.                                                              Page 27 of 110
  • 456.                                                              Page 28 of 110
  • 457.                                                              Page 29 of 110
  • 458.                                                              Page 30 of 110
  • 459.                                                              Page 31 of 110
  • 460.                                                                                                                                             Page 32 of 110
  • 461.                                                                                                                                          Page 33 of 110
  • 462.                                                                                                                                           Page 34 of 110
  • 463.                                                                                                                                           Page 35 of 110
  • 464.                                                                                                                                            Page 36 of 110
  • 465.                                                                                              Page 37 of 110
  • 466.                                                                                              Page 38 of 110
  • 467.                                                                                              Page 39 of 110
  • 468.                                                                                              Page 40 of 110
  • 469.                                                                                              Page 41 of 110
  • 470.                                                                       Page 42 of 110
  • 471.                                                                       Page 43 of 110
  • 472.                                                                       Page 44 of 110
  • 473.                                                                       Page 45 of 110
  • 474.                                                                       Page 46 of 110
  • 475.                                                                                                                                                                               Page 47 of 110
  • 476.                                              Page 48 of 110
  • 477.                                                                                                                                                                           Page 49 of 110
  • 478.                                                                                                                                                                          Page 50 of 110
  • 479.                                                                                                                                                                          Page 51 of 110
  • 480.                                                                                                                                                                           Page 52 of 110
  • 481.                                Page 53 of 110
  • 482.                                Page 54 of 110
  • 483.                                Page 55 of 110
  • 484.                                Page 56 of 110
  • 485.                                Page 57 of 110
  • 486.                                                 Page 58 of 110
  • 488.                                                                                                          Page 60 of 110
  • 489.                                                                                                                                Page 61 of 110
  • 490.                                                                                                                                                                                                                              Page 62 of 110
  • 491.                                                                                                                                                                                     Page 63 of 110
  • 492.                                                                                                                                                                                                                        Page 64 of 110
  • 493.                                                                                                                                                                Page 65 of 110
  • 494.                                               Page 66 of 110
  • 495.                                                                         Page 67 of 110
  • 496.                                           Page 68 of 110
  • 497.                                                      Page 69 of 110
  • 498.                                                      Page 70 of 110
  • 499.                                                      Page 71 of 110
  • 500.                                         Page 72 of 110
  • 501.                                                                                                                                                                                                                Page 73 of 110
  • 502.                                                                                      Page 74 of 110
  • 503.                                                                                                                                                                                        Page 75 of 110
  • 504.                                                                                                                             Page 76 of 110
  • 505.                                                                                                                                 Page 77 of 110
  • 506.                                                                                                                           Page 78 of 110
  • 507.                                                  Page 79 of 110
  • 508.                                                                                                         Page 80 of 110
  • 509.                                                                                                                               Page 81 of 110
  • 510.                                                                                                                                    Page 82 of 110
  • 511.                                                                                                                                 Page 83 of 110
  • 512.                                                                                                                                                                                                                  Page 84 of 110
  • 513.                                                                                                                                                                          Page 85 of 110
  • 514.                                                                                                                                              Page 86 of 110
  • 515.                                                                                                                                               Page 87 of 110
  • 516.                                                                                                                                     Page 88 of 110
  • 517.                                                                                                                                                                           Page 89 of 110
  • 518.                                                                                                                                      Page 90 of 110
  • 519.                                                                                                                                                        Page 91 of 110
  • 520.                                                                                                                                               Page 92 of 110
  • 521.                                                                                   Page 93 of 110
  • 522.                                                                                                                                                                                               Page 94 of 110
  • 523.                                                                                                                                                 Page 95 of 110
  • 524.                                                      Page 96 of 110
  • 525.                                                                                                                                      Page 97 of 110
  • 526.                                                Page 98 of 110
  • 527.                                       Page 99 of 110
  • 528.                                                                                                                                                                                                                                                                                    Page 100 of 110
  • 529.                                                                                                                            Page 101 of 110
  • 530.                                                                                                                                                                                                                                                                                           Page 102 of 110
  • 531.                                                                                                                                                                                                                                                         Page 103 of 110
  • 532.                                                                                                                                                                                                                                                         Page 104 of 110
  • 533.                                                                                                                                                                                                                                                                                                                                                    Page 105 of 110
  • 534.                                                                                                                                                                                                                                                                                Page 106 of 110
  • 535.                                                                               Page 107 of 110
  • 538.                                                                          Page 110 of 110
  • 539. 180 Grand Ave, Ste 1410 Oakland, California 94612 510-350-2900 FAX 510-350-2901 February 21, 2011 Project Number 070181 Waste Management Richard T. Von Pein, P. E. Director of Engineering, Western Group 6640 Amber Lane Pleasanton, CA 94566 Subject: Work Plan for Sedimentation Basin Restoration- Waimanalo Gulch Sanitary Landfill, Ewa Beach, Oahu, HI Dear Mr. Von Pein, As requested, GEI Consultants (GEI) has prepared a work plan to restore the sediment basin system to its intended capacity and function after the occurrence of the recent storm events in December 2010 and January 2011. Sedimentation Basin Features The sedimentation basin was originally designed and constructed in the late 1980’s. Recently (2006-2007), there were several modifications made to the basin including the placement of an interior pond retention berm, swale energy dissipation improvements, installation of a subdrain system, and replacement of the two 42-inch corrugated metal riser pipes with concrete risers. Attachment A includes a copy of the design drawings by Shimabukuro, Endo, and Yoshizaki, Inc. showing the original basin design, and EarthTech drawings showing the recent modifications. Attachment B includes photographs of the basin in October 2007 after construction of the basin modifications. The sedimentation basin currently receives drainage that is collected in the western concrete-lined drainage channel immediately upstream of the basin. The sedimentation basin consists of the following elements, described in an upstream to downstream direction: Sedimentation Basin Inlet Apron - The inlet located at the downstream end of the western concrete lined drainage channel consists of a 30-foot long rock riprap apron. The rock riprap sizes are approximately 18 to 24 inches in diameter.
  • 540. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill 2 2/21/11 Northern Basin and Interior Berm Area – A riprapped interior berm is located in the northern (upstream) portion of the basin. The interior berm is approximately 4 feet high. The northern basin area and interior berm function as a pre-holding area to reduce the amount of coarser sediment that will continue to travel downstream in the basin, and possibly reduce the hydraulic mixing and churning of the finer sediment in the southern basin. The approximate elevation of the basin floor in this area is El. 65. The basin side slopes adjacent to the floor are inclined at 2 horizontal to 1 vertical (H: V), and the total depth of the basin in this area is approximately 18 feet. There is also a riprapped energy dissipator at the northeast corner of the basin to reduce exit velocities from 18-inch and 42- inch storm water pipes exiting into the basin at this location. Southern Basin Area - The southern portion of the basin contains a subdrain system beneath the basin floor to lower and discharge the standing water in the basin during low flow events. The subdrain system and consists of 6-inch, perforated high density polyethylene (HPDE) pipes placed in an 18-inch wide by 24-inch deep infiltration trench wrapped in a filter cloth. The trench is backfilled with ½ to ¾-inch drain rock with an overlying 6-inch sand bedding layer at the base of the sedimentation basin. The HDPE pipes are connected directly to the CMP outlet pipes (described below) to allow for conveyance of drainage from the subdrain system. The basin side slopes adjacent to the floor are inclined at 2 horizontal to 1 vertical, and the total depth of the basin in this area is approximately 18 feet. However, the earthen embankment at the downstream end of the pond is approximately 4.5 to 5 feet lower, to form an emergency spillway crest for the sedimentation basin (see riprapped embankment and spillway description below). Outlet Riser Pipes - There are two reinforced 48-inch diameter concrete inlet riser pipes that function as principal outlets for the sedimentation basin. The riser pipes were constructed without intermediate orifice openings, so drainage of basin inflow will be through the overflow outlet at the top of the riser or through the underlying subdrain system described previously. The vertical riser pipes outlets connect via a concrete box to 42-inch diameter horizontal corrugated metal pipes (CMP’s) located at the base of the embankment at the downstream end of the sedimentation basin. The CMP’s outlet on the spillway apron at the downstream toe of the embankment. Riprapped Embankment and Spillway - An earthfill embankment was constructed at the south end of the basin to provide containment on the downstream side of the pond. The embankment is armored with a 2’ thick layer of grouted riprap. The crest and downstream slope of the embankment functions as an emergency spillway apron to discharge storm water downstream from the basin. The embankment was constructed with 2 H to 1 V sideslopes and a crest width of approximately 19 feet. The inboard sideslope of the embankment is
  • 541. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill 3 2/21/11 approximately 14 feet high. The outboard side of the embankment is approximately 21 feet high. Vegetated Drainage Corridor - A vegetated area is located downstream of the spillway apron and the 42-inch CMP pipe outlets. The vegetated area is approximately 200 feet long by 50 to 100 feet wide and conveys storm water flows downstream to three CMP culvert outfalls beneath Farrington Highway. Work Plan Activities In order to restore the basin to its intended capacity and function, specific activities will be performed for the features described previously. These activities are described in more detail and are currently being implemented or will be implemented as soon as possible after the basin is dewatered. Basin Pumping - Prior to cleaning and inspection of the sedimentation basin features, all standing water will be pumped from the basin and discharged at a POTW designated by the City and County of Honolulu. Basin Inlet Apron - All sediment and debris on top of the energy dissipator and interior berm will be removed until the underlying riprap apron and berm armoring are exposed. Any riprap missing from this area will be replaced with 18-inch to 24-inch diameter rock. The riprap will consist of basalt material with good rock quality obtained from the on-site excavation activities within the landfill. Northern Basin and Interior Berm Area - The sediment and debris from the basin will be removed to restore the basin floor to the design elevation of El.65.0. Any sediment that collected against the toe or side slopes of the basin will be removed to restore the basin slopes to their design 2 H to 1V inclination and the basin floor width to the design dimensions shown in Attachment A. The riprap armoring on the interior berm and energy dissipation swales will be fully uncovered and inspected to determine if there are areas of dislodged or missing riprap. Any areas of missing riprap will be replaced. The riprap will consist of on-site material as described previously. After drying, sediment will be used for daily cover and debris will be disposed in the landfill. Southern Basin Area - The sediment and debris from the basin will be removed to restore the basin floor to the design elevation of El.65.0. Any sediment that collected against the toe or side slopes of the basin will be removed to restore the basin slopes to their design 2 H to 1V inclination and the basin floor width to the dimensions shown in Attachment A. After removing sediment from the basin floor the subdrain trenches will be located and the 6” washed sand layer on the basin floor covering the subdrain system should be replaced. The concrete inlet riser pipes and steel trash racks will be visually inspected for debris or sediment blockage. If blockages are observed, they will be removed from the risers and
  • 542. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill 4 2/21/11 trash racks. The 42-inch CMP outfall beneath the embankment will be visually inspected for debris or sediment blockage. All sediment and debris should be removed from the CMP outfall pipes. After drying, sediment will be used for daily cover and debris will be disposed in the landfill Riprapped Embankment and Spillway - As a result of the December 2010- January 2011 storm events, sediment may have accumulated against the grouted riprap on the inboard and outboard faces of the embankment and spillway area. Any accumulated sediment in these areas will be removed and disposed properly in the landfill. Disposal may include using the material for daily cover. The overflow spillway will also be visually inspected for signs of debris that is blocking the overflow weir or that has migrated on the downstream face of the weir. All debris in the spillway will be collected and deposited in the landfill. Vegetated Drainage Corridor - The area immediately downstream of 42-inch CMP pipe outfalls and riprap apron was protected in the past with rock riprap. The riprap was placed to allow for storm water discharge to dissipate and spread throughout the vegetated area before leaving the site. These riprap areas will be inspected, and any missing or dislodged riprap will be replaced. On-site rock material will be used as described previously. All debris that migrated into the drainage corridor will be removed and disposed in the landfill. There may be bare soils areas within the vegetated drainage corridor that require short term erosion protection measures. These areas will be protected by seeding with erosion resistant vegetation and placement of temporary erosion control matting where necessary. We note that surface soils in the vegetated drainage corridor will be disturbed in order to construct the stilling basin outlet for the Western Surface Water Drainage System. Longer term erosion control measures for the vegetated drainage corridor will be considered during construction of the stilling basin structure. Sediment and Debris Disposal - All sediment and debris removed from the areas described previously should be disposed in the landfill. Sediment will be stockpiled and allowed to dry. The dried sediment material can then be utilized as daily and intermediate cover during landfilling operations. Implementation of Work Plan - Waste Management will implement the work plan described using available site personnel and contractors. Inspection will be performed by AECOM engineers as required. Documentation of Work Plan Activities - Photo-documentation and field reports will be prepared by landfill personnel during and after restoration activities to support final reporting efforts of work plan implementation to the USEPA.
  • 543. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill 5 2/21/11 Schedule – Liquids are scheduled to be removed from the pond by February 14th provided there is no additional rainfall. After liquids are removed removing sediment, debris and silted-in underdrain material will occur. As soon as all material is removed from the pond, the underdrain will be reconstructed, other necessary repairs made and the pond put back into service. We anticipate removing the sediment and debris, and reconstructing the pond will take approximately 4 weeks and should be completed by March 14, provided we do not receive significant additional rainfall. If storm water enters the basin prior to the removal of the sediments, we would not discharge it as storm water, except in an emergency and only after consultation with the Hawaii Department of Health and the USEPA. The water will be removed and transported to a POTW designated by the City and County of Honolulu. Very truly yours, GEI Consultants, Inc. William A. Rettberg, P.E. Vice President Attachment A: Drawings by Shimabukuro, Endo, &Yoshizaki, Inc. and Earth Tech Depicting Basin Configuration and Features Attachment B: Photographs of the Sedimentation Basin Area in October 2007 After Construction of Modifications
  • 544.  
  • 545. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill ATTACHMENT A Drawings by Shimabukuro, Endo & Yoshizaki, Inc. and EarthTech Depicting Basin Configuration and Features
  • 546.  
  • 547. 42-Inch CMP Outfall Locations 48-Inch RCP Risers Northern Basin and Interior Southern Basin Riprap Energy Berm Area Area Dissipator and Outfall Pipes Riprapped Embankment and Spillway Vegetated Drainage Corridor (Farrington Hwy. Culverts Approx. 200 Ft. Downstream)
  • 549. Riprapped Embankment and Spillway Original CMP Riser Pipe Replaced with Concrete Riser (See EarthTech Drawing C-11) 42-inch CMP Outlet Typical Section Across Sedimentation Basin
  • 551. Work Plan for Sedimentation Basin Restoration Waimanalo Gulch Sanitary Landfill ATTACHMENT B Photographs of Sedimentation Basin Area in October 2007 After Construction of Modifications
  • 552.  
  • 553. View of Basin Looking South Along the Western Concrete Lined Drainage Channel
  • 554. Western Drainage Channel Northern Basin and Southern Basin Area Interior Berm With Subdrains Inlet Riser View of Sedimentation Basin Looking North
  • 555. 42 Inch CMP Pipe Outlets View along Riprapped Embankment Crest Looking West
  • 556. Riprapped Interior Berm Riprap Energy Dissipator Southern Basin Area 48 inch Concrete Riser on West Side f Basin W t Sid of B i View of Basin Looking Northeast from Riprapped Embankment Crest
  • 557. Waimanalo Gulch Sanitary Landfill Stormwater Management Update and Contingency Plan 2-1-11 (Revised 2-18-11)     Following  the  recent  major  storm  events,  Waste  Management  of  Hawaii  (WMH)  has  assessed   and  evaluated  its  stormwater  control  systems  for  effectiveness.    Below  is  an  update  of  ongoing   measures  being  taken  to  prevent  future  storm  damage  at  the  site,  and  document  efforts  to  further   contain  potential  storm  water.    WM  believes  that  these  measures  will  prevent  waste  material  and  storm   water  that  may  have  come  into  contact  with  waste  from  exiting  the  facility  in  the  event  of  a  major   storm.     1) The  36-­‐inch  drain  was  designed  to  handle  water  falling  within  the  landfill  footprint,  upstream  of   the  waste  disposal  area,  during  landfilling  operations.    It  was  also  intended  to  mitigate  runon   during  small  storms  until  the  diversion  channels  are  in  place.    The  west  side  drainage  channel   has  been  designed  to  control  the  100-­‐year  storm  and  will  mitigate  the  impact  of  storms  with   higher  return  periods.       The  effectiveness  of  36-­‐inch  inlet  structure  for  the  up  canyon  drainage  system  has  been   restored  and  improved.  The  area  immediately  surrounding  the  inlet  structure  has  been   re-­‐graded  and  armored  with  large  boulders  to  prevent  high  sediment  loading  from   clogging  the  inlet.  A  diversion  berm  immediately  downstream  of  this  diversion  structure   has  been  reinforced  and  re-­‐built  to  further  direct  any  stormwater  into  the  inlet   structure.     The  area  surrounding  the  future  Cell  E-­‐8  is  being  excavated  down  to  the  elevation  of  the   36-­‐inch  pipe  inlet  structure.  This  effort  will  help  to  create  stormwater  retention,   dissipate  stormwater  velocities,  and  drop  out  sediment  as  it  moves  from  the  upper   ongoing  since  1/18.           2) Temporary  containment  berm  directly  south  of  Cell  E6   12-­‐19-­‐10  storm  to  contain   large  stormwater  flows  originating  from  up  canyon  and  prevent  a  catastrophic  discharge   from  exiting  the  site.  The  berm  did  safely  contain  this  storm,  and  was  subsequently   substantially  reinforced  prior  to  the  storm  that  occurred  on  1-­‐13-­‐11.      The  storm  water   that  was  contained  behind  the  berm  has  now  been  removed,  creating  a  storage  area   capable  of  containing  water  from  a  similar  rainfall  event.  Preliminary  stability  analysis   indicates  the  berm  has  adequate  strength  to  contain  the  runoff.     3) Establish  a  functioning  Western  Drainage  System.   In  order  to  establish  a  functioning  Western  Drainage  System,  the  up  canyon  conveyance   structure  must  be  in  place  to  divert  storm  water  into  the  box  culvert  and  fiberglass   piping  system.  Additionally,  the  box  culvert  invert  that  originates  at  the  diversion   above  Cell  E-­‐ A  functioning  Western  Drainage  System  is  now  in  place  and  successfully  diverting   potential  storm  water  originating  from  up  canyon  around  the  active  portion  of  the   landfill.        
  • 558.   4) WM  employees  monitor  weather  conditions  routinely,  in  order  to  prepare  for  and  take   emergency  action  in  the  event  of  a  major  storm  event  affecting  the  site.      Storm    preparations   include,  but  not  limited  to  the  following:   Inspect  existing  storm  water  culverts  and  drains  to  verify  that  they  are  working  properly.   Inspect  and  verify  that  the  newly  constructed  up  canyon  diversion  channel  is  functional.   Inspect  and  verify  that  all  pumps  and  associated  storm  water  support  related  equipment   are  in  place  and  functional.   Relocate  non  essential  construction  equipment  to  a  location  outside  of  the  influence  of   the  potential  storm.   Inspect  and  verify  that  daily  cover  in  the  working  area  has  been  placed  properly  .  WMH  has   reviewed  our  Storm  water  Pollution  Control  Plan  (SPCC)  and  will  update  accordingly  as  the   western  storm  water  diversion  project  progresses.   5)    Interim    storm  event    management   resumption  of  landfill   operations  within  specified  areas  of  Cell  E6,  contains  a  requirement  that  WMH  list  available   equipment  and  personnel  to  be  deployed  in  response  to  major  storm  events  that  may  occur   prior  to  the  functional  completion  of  the  west  side  drainage  diversion  project.    These  capabilities   are  listed  below.    The  WMH  general  contractor  for  the  west  side  drainage  diversion  project  maintains  on   site  six  excavators,  six  articulated  dump  trucks,  four  bulldozers,  three  front  end  loaders,   two  8  inch  diameter  and  one  twelve  inch  diameter  pumps.    In  addition  WMH  maintains   three  bull  dozers,  one  front  end  loader,  one  road  grader,  two  articulated  dump  trucks,   one  backhoe,  one  fuel  truck,  one  lube  truck,  and  one  six  inch  diameter  pump.   Joe  Whelan,  Justin  Lottig,  Jesse  Frey,  and  Rick  Kahalewai  are  available  to  assist  in   managing  storm  water  management,  in  addition  to  four  equipment  operators  and  two   maintenance  technicians.    Additionally,  the  general  contractor  maintains  appropriate   operators  for  all  equipment  listed  above.   WMH  employs  a  security  service  which  is  on  site  after  business  hours    seven  days  per   week    who  are  responsible  for  alerting  WMH  management  in  the  event  of  a  major  after   hours  storm  event.    During  business  hours  the  above  listed  WMH  employees  and  the   general  contractor  maintain  sufficient  trained  employees  to  respond  to  storm  events.   The  sedimentation  basin,  temporary  berm  in  the  Cell  E6  area,  36  inch  storm  water   diversion  piping,  and  general  facility  drainage  ditches  will  be  monitored  and  maintained   during  potential  storm  events.    These  activities  include,  but  are  not  limited  to:   i. Inspect  the  sedimentation  basin  for  available  free  board,  and  verify  that  the   existing  floating  debris  skimming  barrier  is  in  place  and  functional.  
  • 559. ii. Inspect  the  termporary  berm  in  the  cell  6  area    for  damage  and  general   structural  integrity.       iii. Inspect  the  existing  storm  water  culverts  and  drains  to  verify  that  they  are   working  properly.   iv. Inspect  and  verify  that  the  newly  constructed  up  canyon  diversion  channel  is   functional.   v. Inspect  and  verify  that  all  pumps  and  associated  storm  water  support  related   equipment  are  in  place  and  functional.   These  measures  will  be  performed  by  site  personnel  and  representatives  of  the  on  site   contractor  responsible  for  new  cell  and  storm  water  construction,  prior  to  the  onset  of  a   major  storm  and  throughout  the  storm  event,  as  long  as  conditions  remain  safe.   In  the  event  of  a  major  storm  event,  WMH  employees  and  contractors  will  assess  on  site   conditions  to  determine  if  there  is  a  potential  threat  to  human  life  or  injury,  as  well  as   equipment  damage,  or  environmental  harm  as  a  result  of  the  storm.    WMH  will  take   appropriate  actions  to  keep  all  ditches  and  storm  water  conveyance  structures   operational  and  free  of  debris,  once  it  is  determined  that  these  activities  can  be   performed  safely.    WMH  will  monitor  the  condition  of  the  Cell  E6  berm  in  relation  to  the   amount  of  storm  water  that  may  have  ponded  behind  this  dam.   Operations  within  the  Cell  6  area  may  be  suspended  due  to  a  severe  storm  event  if   conditions    jeopardize  the  safety  of  employees  or  customers,  such  as,  roadways  into  or   out  of  the  cell  become  impassible  or  WMH  employee  are  not  able  to  process  and   compact  the  waste  material  in  a  safe  and  efficient  manner.    Should  a  shut  down  of   operations  be  deemed  necessary,  WMH  will  complete  unloading  of  trucks  located  in  the   off  loading  area,  compact  the  waste,  and  initiate  daily  cover  of  the  in  place  waste,  as   quickly  as  possible.    As  previously  noted,  WMH  will  inspect  and  maintain  the  various   storm  water  conveyance  systems  in  order  to  minimize  the  exposure  of  any  waste   material.   Should  a  release  of  solid  waste  material  occur,  WMH  employees  will  monitor  the   existing  storm  water  outfall  location  and  initiate  beach  assessments,  clean  up  activities,   and  post  signs  in  those  areas  likely  to  be  affected  by  a  release.    
  • 560.  
  • 561.   Appendix  C   Heath  and  Safety  Plan      
  • 562.  
  • 599. SECTION I - PART E EMERGENCY ACTION PLAN
  • 601. Program: EMERGENCY ACTION PLAN Facility: Waimanalo Gulch Sanitary Landfill (WGSL) Location: 92-460 Farrington Highway, Kapolei, HI 96707 Date: February 2011 TABLE OF CONTENTS 1.0 INTRODUCTION .............................................................................................. 1 1.1 EMERGENCY RESPONSE PERSONNEL .................................................................... 1 1.2 RELEASE OF INFORMATION TO THE PUBLIC / MEDIA................................................ 1 1.3 SITE MAP ............................................................................................................. 1 1.4 ALTERNATE WASTE DISPOSAL PLAN...................................................................... 2 2.0 EMERGENCY RESPONSE AGENCIES / TELEPHONE NUMBERS:........... 17 3.0 EMERGENCY PROCEDURES ...................................................................... 21 3.1 EVACUATION PROCEDURE................................................................................... 21 3.2 FIRE PROCEDURE ............................................................................................... 22 3.2.1 Structure Fire or Surface Fire ................................................................ 22 3.2.2 Buffer Zone or Brush Fire ...................................................................... 23 3.2.3 Incoming Waste Load Fires ................................................................... 23 3.2.4 Vehicle or Equipment Fire ..................................................................... 24 3.2.5 Landfill Subsurface Fire ......................................................................... 24 3.3 MEDICAL EMERGENCY PROCEDURE .................................................................... 26 3.3.1 Injury Accident Response Procedures ................................................... 26 3.4 SPILL/RELEASE RESPONSE PROCEDURE ............................................................. 27 3.4.1 Minor Spill .............................................................................................. 27 3.4.2 Major Spill .............................................................................................. 27 3.5 EARTHQUAKE ..................................................................................................... 28 3.6 SEVERE STORM RESPONSE PROCEDURES .......................................................... 30 3.7 HURRICANES ...................................................................................................... 30 3.8 BOMB THREAT (PHONE CALL) ............................................................................. 33 3.9 CIVIL DISTURBANCE/DEMONSTRATION................................................................. 33 3.10 ARMED ROBBERY ............................................................................................... 34 3.11 TERRORIST THREATS .......................................................................................... 37 4.0 EMERGENCY EQUIPMENT & PPE .............................................................. 39 5.0 ADMINISTRATIVE PROCEDURES............................................................... 41 5.1 EMERGENCY REPORTING .................................................................................... 41 5.2 TRAINING ............................................................................................................ 41 5.3 PLAN UPDATE AND DISTRIBUTION ........................................................................ 42 ©2011, Waste Management Page i
  • 602. Figures FIGURE 1: WGSL SITE LOCATION MAP FIGURE 2: EVACUATION ROUTE MAP FIGURE 2A: SHOP FLOOR PLAN FIGURE 2b: EMPLOYEE LOUNGE FIGURE 2c: ADMINISTRATION BUILDING – FIRST FLOOR FIGURE 2d: ADMINISTRATION BUILDING – SECOND FLOOR FIGURE 2e: SCALE HOUSE FIGURE 3: DIRECTIONS TO ST. FRANCIS MEDICAL CENTER APPENDIX A: FIRE PREVENTION PLAN TABLE A-1: SITE LOCATIONS WITH POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES TABLE A-2: CONTROL PROCEDURES AND FIRE PROTECTION EQUIPMENT FOR POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES APPENDIX B: POST EARTHQUAKE FORMS & POST HURRICANE / SEVERE STORM FORMS ©2011, Waste Management Page ii
  • 603. 1.0 INTRODUCTION This Emergency Action Plan was prepared by Waste Management of Hawaii (WMH) for the Waimanalo Gulch Sanitary Landfill (WGSL) and contains procedures to be implemented in the event of an emergency at the WGSL. All personnel on-site at the WGSL, including contractors and subcontractors, will be informed of the procedures and requirements of this Plan, as they relate to potential fire, explosion, health, safety, or other hazards. A Fire Prevention Plan is included in Appendix A that evaluates and identifies potential fire hazards, ignition sources, on-site fire fighting equipment, and the proper handling of combustible materials. If there are any questions regarding the procedures described in these plans, please contact WGSL / WMH Management. 1.1 EMERGENCY RESPONSE PERSONNEL In the event of an emergency, the Emergency Coordinator (EC) has primary responsibility for responding to correcting, and documenting and reporting emergency situations. This includes taking appropriate measures to ensure the safety of WGSL personnel and the public. Possible actions may involve evacuation from the site or evacuation of adjacent residents. Section 2.0 contains a list of emergency response telephone numbers, including the EC and key WGSL / WMH personnel (alternate ECs). This list is posted in the lounge, main administration office (upstairs and downstairs), in the scale house, and in the parts container at the maintenance shop. The first person on the scene will follow the normal procedures for emergency response, as outlined in this Plan, until the designated EC (or alternate) arrives at the scene. All EC's will be properly trained in this procedure. In some cases, Waste Management, Inc. (WM) West Group personnel will need to be called upon for assistance during emergency situations. Refer to Section 2.0 below, for a list of key WM West Group personnel who may be notified in the event of an emergency at the WGSL, if deemed necessary. 1.2 RELEASE OF INFORMATION TO THE PUBLIC / MEDIA Inquires from the media are likely in the event of an emergency. The WMH Vice President / General Manger or other designated spokesperson will coordinate all media relations and responses to any media request, as well as contact the necessary WM West Group personnel. If approached or contacted by the press, unauthorized personnel should not answer any questions or make any statement to the media – please refer them to the general manager. 1.3 SITE MAP ©2011, Waste Management Page 1
  • 604. A WGSL site location map (Figure 1), evacuation route map (Figure 2), and building floor plans for the maintenance shop area (Figure 2a), employee lounge (Figure 2b) main administration office (Figures 2c & 2d), and scale house (Figure 2e) and are attached to this Plan. These figures detail exits, evacuation routes, fire extinguisher and fire alarm locations, emergency shut-offs, and the designated WGSL evacuation area, which is currently THE GRASS AREA BY THE GUARD SHACK, NEAR FARRINGTON HIGHWAY (see Figure 1). 1.4 ALTERNATE WASTE DISPOSAL PLAN In the event the liner associated with any landfill cell is damaged, the alternate waste disposal plan is to seek authorization to temporarily landfill MSW and ash in other areas of the landfill that will have minimal impact on the damaged portion of the landfill, and if that alternative is not available, to temporarily utilize other landfills and off-island shipping options as appropriate. ©2011, Waste Management Page 2
  • 619. 2.0 EMERGENCY RESPONSE AGENCIES / TELEPHONE NUMBERS: AMBULANCE 911 FIRE DEPARTMENT 911 POLICE DEPARTMENT 911 HOSPITAL: St. Francis Medical Center - West 91-2141 Ft. Weaver Road Ewa Beach, HI 96706 (808) 678-7000 A map and driving directions to St. Francis Medical Center are included in this Plan (see Figure 3). WGSL / WMH KEY PERSONNEL: PRIMARY EMERGENCY COORDINATOR (EC): Joseph R. Whelan (WMH Vice President / General Manager) Office: (808) 668-2985 ext 15 Mobile: (808) 479-4612 ALTERNATE ECS: Justin Lottig (WMH Environmental Protection Manager) Office: (808) 668-2985 ext 16 Mobile: (808) 479-0749 Jesse Frey (WMH Engineer) Office: (808) 668-2985 ext 22 Mobile: (808) 250-0574 Rick Kahalewai (WGSL Foreman) Mobile: (808) 368-4717 Direct Connect: 184*2*54571 Natalie Corella (WGSL Operations Specialist) Office: (808) 668-2985 ext 10 Mobile: (808) 306-5419 ©2011, Waste Management Page 17
  • 620. WM WEST GROUP KEY PERSONNEL: Donny Carder (Safety Manager) Office: (616) 810-9270 Rodney Walter (Director of Engineering) Office: (480) 624-8480 Mobile: (661) 645-7665 Christian Colline (Director of Air Programs) Mobile: (925) 890-2746 Brian Bowen (Director of Environmental Protection) Office: (916) 552-5859 Mobile: (916) 704-0971 OTHER AGENCIES, UTILITIES AND RESPONSE SUPPORT PROVIDERS: State Civil Defense: (808) 733-4300 Oahu Civil Defense: (808) 527-5476 American Red Cross: (808) 734-2101 U.S. Coast Guard Terrorist Incident Reporting: (808) 541-2450 Poison Center: (800) 222-1222 Gas Company: (808) 526-0066 Hawaiian Electric Company: (808) 548-7961 EPA: (415) 947-8000 FBI: (808) 566-4300 Board of Water Supply: (808) 748-5010 Environmental Response (Pacific Commercial Services): (808) 545-4599 Ext. # 2 National Spill Response Center: (800) 424-8802 State of Hawaii - Clean Air Branch: (808) 586-4200 Clean Water Branch: (808) 586-4309 Environmental Management: (808) 586-4337 Solid & Hazardous Waste: (808) 586-4266 Hazard Evaluation & Emergency Response (HEER): (808) 586-4249 After hours HEER number: (808) 247-2191 ©2011, Waste Management Page 18
  • 621. Figure 3: Directions to St. Francis Medical Center ©2011, Waste Management Page 19
  • 623. 3.0 EMERGENCY PROCEDURES Listed below are specific types of emergencies and detailed procedures to be followed by site personnel in the event of an emergency. After an emergency, waste disposal will resume at the WGSL only after key WM personnel have deemed the situation to be safe. WMH will ensure that human health and the environment are protected prior to restoring disposal services / operations in the aftermath of an emergency or disaster. 3.1 EVACUATION PROCEDURE All personnel on-site will be notified of the evacuation via telephones, cell phones, and/or hand-held two-way radios. If radios/phones are not operational, personnel will be alerted verbally (the EC and/or EC alternates will verbally alert all WGSL personnel). EVACUATING THE BUILDINGS: Walk, don't run to the nearest exit. Personnel and visitors will be directed to immediately reconvene at the WGSL evacuation area (via the safest route), which is the GRASS AREA BY THE GUARD SHACK, NEAR FARRINGTON HIGHWAY (see Figure 1). Upon evacuation, the Operations Specialist will bring the contractor sign-in log to the evacuation point (located in the office reception area, on the counter in front of the Operations Specialist). This to identify any visitors present on-site. EC Alternates will be responsible for checking the facilities to insure that everyone leaves the buildings. If outside emergency support is required, call 911 and report the emergency. Inform the 911 operator that there is an emergency and give the following information: Caller’s name and location. Type of emergency. Type of emergency aid required. Answer any questions that the emergency operator asks. Stay on the phone with the operator until told to hang up. EVACUATING THE LANDFILL: Administration personnel will contact the on-site Goodfellow Bros. construction office at via cellular phones and Goodfellow Bros. will then radio their personnel & give the order to evacuate. Site personnel will coordinate movement of landfill customers/ waste haulers from the disposal area onto the main haul road. Construction personnel will do the same. All persons will then proceed to the designated evacuation area at the GRASS AREA BY THE GUARD SHACK, NEAR FARRINGTON HIGHWAY (see Figure 1). ©2011, Waste Management Page 21
  • 624. The EC (or Alternate EC) will be responsible for: Coordinate evacuation of the WGSL including notification of adjacent property owners/tenants, as required. Coordinate with incoming emergency response personnel. Conduct a head count at the designated assembly area/evacuation point. Notify incoming drivers/haulers via radio or cell phone to avoid the site. Notify WGSL / WMH Management of the emergency. Notify WM Safety personnel of the emergency (if appropriate) - determine if a 24- Hour Report is required. Determine when the “all clear” signal can be given to return to the site. 3.2 FIRE PROCEDURE Procedures outlined below will be followed for emergencies involving fire, including structure of large surface fires, buffer zone fires, incoming waste load fires, landfill subsurface fires, and equipment fires. A 2,000-gallon water truck and bulldozers are available 24-hours a day to aid in fire fighting. Fire extinguishers are provided in all buildings and site vehicles for use in extinguishing small fires. 3.2.1 STRUCTURE FIRE OR SURFACE FIRE The EC will notify all personnel on-site at the WGSL of the fire via oral information and/or hand- held radios. If possible, cell phone communication will be established. In the event of a LARGE STRUCTURE FIRE or SURFACE FIRE: 1) Assess the fire - Identify its location, source and size. 2) If the fire is SMALL (less than 1 cubic yard), can be approached safely with an evacuation route, and available personnel are trained in the appropriate use of fire equipment, an attempt can be made to put it out with a fire extinguisher. DO NOT ATTEMPT TO FIGHT THE FIRE ALONE. 3) If the fire is LARGE, EVACUATE THE BUILDING IMMEDIATELY and proceed to the designated evacuation area. Avoid entering a burning structure for any reason. 4) Call 911 to report the fire. Inform the 911 operator that there is a fire emergency and give the following information: Caller’s name and location. Location of fire. Materials involved, if known. Whether medical aid is required. 5) Limit access to area and isolate electrical power at main breaker 6) Remove vehicles from the area if time allows and does not present a risk to personnel. ©2011, Waste Management Page 22
  • 625. 7) Remove fuel sources (i.e. flammables from shop) if time allows and does not present risk personnel. Upon arrival of local Fire Department personnel, direct them to the fire and provide assistance as appropriate. 3.2.2 BUFFER ZONE OR BRUSH FIRE If a brush fire / buffer zone fire exists in the area surrounding the landfill, maximum effort will be made to prevent the fire from reaching refuse fill areas by utilizing on-site assets. IN THE EVENT OF A BUFFER ZONE OR BRUSH FIRE: 1) Maintain existing firebreaks between waste fill areas and surrounding vegetation. Roads are maintained on the landfill perimeters, which also serve as a firebreak. 2) Excavate additional firebreaks between the landfill and the oncoming fire. Excavated soils will be bermed on the fire side of the firebreak for additional protection. 3) Water down areas between the firebreak and the disposal area using the on-site water trucks. 4) If fire threatens the landfill, daily cover will be put on the active face and it will be wetted down to prevent a landfill fire caused from flying cinders. 5) Equipment and fuel sources will be moved to safe locations as practicable 6) Unnecessary personnel will be evacuated from the site/area. 7) The local Fire Department will be summoned if site personnel and equipment cannot extinguish the fire. 3.2.3 INCOMING WASTE LOAD FIRES Scale house attendants and WGSL operations personnel are trained and directed to notice any smoke, steam, heat, or burning material in incoming waste loads, and prevent it from contacting combustible materials or being buried at the working face before all combustion is extinguished. If there is a FIRE IN AN INCOMING WASTE LOAD or if a FIRE OCCURS AT THE DISPOSAL AREA: 1) Determine the source of the fire. 2) If fire is small put out with fire extinguisher. 3) Cut the fire out the active face with a dozer (excavate) and move (separate) burning waste from the disposal area to the table. Isolate the fire before it spreads. 4) Smother the fire by covering it with soil. The faster that soil can be placed over the fire, the more effective this method will be in controlling and extinguishing the fire. 5) If necessary, apply water from the on-site water truck to soak the fire. 6) Spread the to ensure fire is out and does not reflash. ©2011, Waste Management Page 23
  • 626. 7) Call 911 and summon the local Fire Department if site personnel and equipment cannot extinguish the fire. 3.2.4 VEHICLE OR EQUIPMENT FIRE To avoid equipment fires, do not operate equipment with trash, paper or other objects in or near the engine compartment. Always stay alert – watch for hot spots in the equipment, blistering paint, or other signs of a fire (smoke or the smell of smoke). If detected, contact WGSL Management or other operations personnel via two-way radio immediately. In the event of a VEHICLE OR EQUIPMENT FIRE, the operator will: 1) Alert WGSL Management / personnel via two-way radio immediately. 2) Bring the vehicle or equipment to a safe stop. If safe to do so, the vehicle/equipment should be parked away from fuel supplies, uncovered solid wastes, or other machinery. 3) Immediately (or as soon as possible) shut off the engine and engage the brake to prevent movement of the vehicle / equipment. 4) Get out of the equipment. 5) Attempt to control the fire using fire extinguishers or an on-site water truck (depending on the size of the fire). If unable to control the fire, follow the procedures for calling 911 as detailed in Section 3.2.1 above, and summon the help of the local fire department. In the event of any of the above-mentioned fires, the EC will: Assess the situation and possible hazards that may result. Order evacuations, medical care, shutdowns, etc. (as necessary). Notify adjacent property owners/tenants (as necessary). Coordinate with incoming emergency response personnel. Conduct a head count at the designated evacuation point. Notify incoming drivers/haulers via radio or cell phone to avoid the site. Notify WGSL / WMH Management of the emergency. Notify WM Safety personnel of the emergency (if appropriate) - determine if a 24- Hour Report is required. Determine when the “all clear” signal can be given to return to the site. 3.2.5 LANDFILL SUBSURFACE FIRE There are two primary causes of subsurface fires at landfills: 1) When smoldering waste is buried at the working face. Typically, this occurs at relatively shallow depths and is detected by surface expression such as visible smoke or depressions forming in recently placed waste. 2) When excess oxygen is allowed to enter the waste mass. This may occur at any depth depending on the oxygen source. At relatively shallow depths, visible smoke and surface depressions are likely. If the fire is deep, it is more likely to burn slowly without visible flame ©2011, Waste Management Page 24
  • 627. or large quantities of smoke, and is characterized by rapid oxidation of an organic waste. The only evidence may be elevated temperatures within the landfill gas (LFG) collection wells, which are generally accompanied by elevated carbon monoxide levels, high balance gas-to-methane ratios, low methane-to-carbon dioxide ratios, and increased oxygen levels. Underground combustion/oxidation may go undetected until a sinkhole or smoke appears. The methods used to EXTINGUISH THE NEAR SURFACE FIRE may include: (1) Cutting off the oxygen supply by smothering with fine-grained soil and/or the use of plastic membranes; or (2) Physically putting the fire out, which involves excavating down to the fire, removing and extinguishing burning material, confirming that all burning material is extinguished, and placing waste back into the excavation area. This procedure should only be done under supervision of personnel experienced with extinguishing landfill fires. The primary method used to EXTINGUISH SUBSURFACE COMBUSTION WITHIN THE LANDFILL is to smother the smoldering area. Typically this can be accomplished by reducing or cutting off vacuum to any affected LFG control well(s). Normally this is sufficient to suffocate the fire and no further steps are required. At the same time, the landfill surface should be inspected to verify that cover thickness is adequate and that excess air is not entering the landfill. If excess air entry is suspected, additional cover should be placed or a reinforced geomembrane liner used. The geomembrane, once installed, will significantly reduce the flow of air into the landfill. Combustion is considered extinguished when temperatures begin to decrease, coupled with a decreasing balance gas-to-methane ratio, and an increasing methane-to-carbon dioxide ratio. Due to a decreasing oxygen supply, carbon monoxide levels may increase during this period. In the event of deep combustion, limiting access to the affected area is not necessary provided there are no visible surface indications of the fire (subsidence or smoke). No new waste may be placed within 250 feet of the suspected combustion area, unless separated from the surrounding waste by 3 feet of soil or other nonflammable material. If a landfill subsurface fire is suspected at the WGSL, WM’s West Group Director of Engineering, Director of Environmental Protection, and Director of Air Programs will be notified. CRITERIA FOR INTERNAL& DOH NOTIFICATION: The presence of smoke coming from the landfill (requires immediate notification). The presence of visible fire (requires immediate notification). Sudden subsidence, typically less than 25 feet across, particularly in areas recently filled. Irregular subsidence due to factors other than fires is common at landfills. When there is any doubt regarding why an area has subsided, WM West Group Engineering and Environmental Protection will be consulted to determine whether the presence of a fire is likely. Carbon monoxide concentrations > 200 ppm in any LFG collection well. Methane-to-carbon dioxide ratio less than 1.0. ©2011, Waste Management Page 25
  • 628. LFG well head temperatures over 160 °F. Balance gas-to-methane levels above 0.6. Once a fire has been verified, the Hawaii Department of Health (DOH) shall be notified orally within 24 hours and a detailed plan outlining steps to control the fire shall be provided, in writing, within 7 days. The response required will be determined by the location of the fire. No personnel shall be permitted within the area until it is confirmed that the fire is extinguished, and the area is determined to be safe. No waste may be placed within 200 feet of the suspected fire area (without Group Engineering approval) until it is confirmed that a fire is not present or that the fire has been extinguished. 3.3 MEDICAL EMERGENCY PROCEDURE 3.3.1 INJURY ACCIDENT RESPONSE PROCEDURES If an accident occurs, WGSL Management should be notified immediately. First aid kits are maintained in all buildings on-site, at the maintenance shop, and in all site vehicles (see Figures 2a-2e). If you are properly certified, begin first aid (e.g. stop bleeding, begin CPR, etc.). Do not move the victim unless necessary to prevent further injury. If the nature of an injury requires additional treatment, the local emergency response provider is to be notified by dialing 911. The person making the call should inform the operator of: a) The nature and location of the emergency; b) What first aid measures have been initiated; c) The need for any special equipment, i.e. hazardous materials response, confined space rescue, or vehicle extrication. Persons with major injuries should never be moved without professional assistance. Major injuries include second or third degree burns, unconsciousness, severe bleeding, broken limbs, and any head, back, or neck injury. Records of all site accidents and first aid treatments will be maintained at the WGSL office. Accident reports will be filed with insurance companies and State agencies as required. After the situation has stabilized, WGSL Management will arrange for investigation of the cause of the accident. A complete investigation report should be completed within seven days of the incident. The report should include a review of the actions leading up to the incident, factors that contributed to or mitigated the severity of the incident, and recommendations to prevent reoccurrence. The EC will be responsible for: Coordinating with incoming emergency response personnel. Notifying WGSL / WMH Management of the emergency. ©2011, Waste Management Page 26
  • 629. Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24 Hour Report is required. Notifying OSHA or other regulatory agency if required. 3.4 SPILL/RELEASE RESPONSE PROCEDURE In the event of a spill/release, immediately alert all personnel in the area and notify the EC (WGSL District Manager) and/or WGSL Management. If necessary, secure the facility and evacuate to an upwind area or designated evacuation point. The WGSL has a low potential for spills of hazardous materials, but incidents are possible in the event of vehicle accidents or malfunctions that could cause spills of coolant, fuel, or lubricants. 3.4.1 MINOR SPILL A release is considered “minor” if it extends outside the secondary containment provisions and the spill/release is limited to the immediate area with no potential for it to enter into the existing drainage facilities or for it to present an immediate fire hazard or exposure danger. In the event of a minor spill/release, WGSL personnel will: 1. Secure the area to protect all personnel and public from any immediate danger. 2. Extinguish any sources of ignition. Vehicles should be turned off. Avoid sparks, movement, or any activity that may create static electricity. 3. ENSURE THAT NO DANGER TO HUMAN HEALTH EXISTS, and then stop the flow at the source only if it is safe to do so (e.g., shut off power, turn off valves, plug leaks). No site personnel shall come into contact with unknown or hazardous substances that have been brought into the facility. 4. If it is safe to do so and available personnel are trained in the proper use of required personal protective equipment (PPE), contain the spill with soil berms, equipment from the spill kit (i.e., absorbent pads, particulate sorbent, shovels, hand tools, etc.) and /or block off drains downstream. Used sorbent pads will be collected in a drum for proper disposal. 3.4.2 MAJOR SPILL WGSL personnel are not trained as first responders in the event of a major spill/release. A spill/release is considered “major” if it extends outside the secondary containment provisions and the spill has traveled beyond the immediate area or if the spill/release has entered the existing drainage facilities. In the event of a major spill/release of petroleum products, WGSL personnel will: 1. Secure the area to protect all employees and public from any immediate danger. 2. Extinguish any sources of ignition. Vehicles should be turned off. Avoid sparks, movement, or any activity that may create static electricity. ©2011, Waste Management Page 27
  • 630. 3. ENSURE THAT NO DANGER TO HUMAN HEALTH EXISTS, and then stop the flow at the source only if it is safe to do so (e.g., shut off power, turn off valves, plug leaks). 4. Call 911 to alert the fire department or the emergency response clean-up contractor (Pacific Commercial Services): (808) 545-4599 Ext. # 2 and give the following information: Caller’s name and location. Location of spill. If known, materials and volumes involved. Whether medical aid is required. Whether fire hazard exists. The EC (or manager in charge) will be responsible for: Coordinating with incoming emergency response personnel. Notifying WGSL / WMH Management of the emergency. Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24 Hour Report is required. Notifying the WMH Environmental Protection Manager who will then report the incident to the proper regulatory agencies and arrange for the proper disposal of any waste materials (if necessary). The waste material from the cleanup will be characterized, transported, and disposed of according to State and Federal Regulations. Refer to the WGSL SPCC Plan (Volume I – Section IV) for more information regarding spills and spill response. 3.5 EARTHQUAKE A “significant earthquake” is defined here as one that produces any sign of damage to on-site structures, including but not limited to, overturned furniture, wall cracks, or structural shifts. DURING A SIGNIFICANT EARTHQUAKE: Remain calm. Immediately cease or limit landfilling operations. If indoors, stay there. Hazards and injuries are generally caused by objects that fall due to the shaking. Move quickly away from windows, shelves, cabinets and glass partitions. Get under a desk or table, or sit in an interior doorway or corner. Do not leave the building unless the building is unsafe. If outdoors, get to an open area away from structures, power lines, and trees. If driving, pull over to the side of the road and stop. Avoid overpasses and power lines. Stay inside vehicle until shaking has stopped. If in a crowded public place, do not rush for the doors. Crouch and cover head with hands and arms. ©2011, Waste Management Page 28
  • 631. AFTER THE EARTHQUAKE: Unless there is an immediate life-threatening emergency, do not attempt to use the telephone. Promptly (when it is safe to do so) conduct a visual survey of the site to identify any slope failures, downed power lines, gas and water leaks, broken electrical wiring or sewage lines fires, LFG system failures, tank leaks/spills, or other conditions that could threaten worker or public safety. If there is damage, turn the utility off at the source. Immediately report gas leaks to the utility company. Do not re-open gas valve until the utility company has checked the system. Warn others to stay away. If fires occur, follow the procedures set forth in Section 3.2. If injuries occur, follow the procedures set forth in Section 3.3. In the event of inoperable telephone systems, notification of the appropriate agencies/businesses will be accomplished in the most expedient manner available (cellular/mobile phones, person to person, overnight mail, etc.). Check buildings for cracks and damage including the roof and foundation. Turn on portable radio for instructions and news reports. Cooperate fully with public safety officials and instructions. Do not use vehicles unless there is an emergency. Keep the streets clear for emergency vehicles. Be prepared for aftershocks. Remain calm and lend a hand to others. If the site is evacuated, leave a message telling others where personnel can be found. The EC (or manager in charge) will be responsible for: Coordinating evacuation of the WGSL including notification of adjacent property owners/tenants, as required. Coordinating with incoming emergency response personnel. Conducting a head count at the designated evacuation point. Notifying incoming drivers/haulers via radio or cell phone to avoid the site. Notifying WGSL / WMH Management of the emergency. Notifying WM Safety personnel of the emergency (if appropriate) - determine if a 24- Hour Report is required. Determining when the “all clear” signal can be given to return to the site. Notifying the WMH Environmental Protection Manager who will fill out Post- Earthquake Forms (Appendix B) and report the incident to the proper regulatory agencies (if necessary). ©2011, Waste Management Page 29
  • 632. 3.6 SEVERE STORM RESPONSE PROCEDURES The WGSL is not located within a 100-year floodplain area as delineated by the Federal Emergency Management Agency (FEMA) of the Federal Insurance Administration (Floodplains), or within a tsunami hazard or floodway. The following measures will be taken to protect against excessive erosion, flooding, and wind damage before and during severe storms. PRIOR TO A FORECASTED STORM: WGSL personnel will inspect all drainage on-site structures to verify that they are in working order. Excessive silt in ditches and basins will be removed and the condition of pipes and discharge structures from basins will be verified. Diversion berms will be constructed around the current disposal area as needed to prevent run-on from entering the waste fill, and to prevent runoff from the waste fill areas of the site. Interim cover will be placed over exposed waste at the end of the working day prior to the forecasted beginning of a severe storm. At the discretion of WMH Management, the site may be closed for business during storm periods. In this event, the working face will be closed and covered with interim cover and graded to direct run-off to the drainage features of the surface water management system. The WMH Environmental Protection Manager conducts monthly surface water and storm water inspections, which include checking and monitoring the integrity of the site’s drainage systems. A Severe Storm Inspection (Post-Hurricane / Severe Storm Forms [Appendix B]) will be conducted, if necessary, during any prolonged storm event to correct or repair any conditions that have been damaged or that may cause damage to on-site or off-site facilities. Excessive silt/sediment will be excavated out of the sedimentation basin and drainage channel/ditches as necessary. 3.7 HURRICANES Hurricane season occurs from June through November in the northern hemisphere. Typically, the National Weather Service provides 24 to 48 hour warnings before a hurricane is likely to approach. There are two types of warnings – “Hurricane Watch” is notice that is given when hurricane conditions threaten within 24 to 26 hours; “Hurricane Warning” is notice that is given when hurricane conditions are expected within 24 hours or less. Typically, waste management facilities support cleanup efforts by providing disposal capacity for debris and other solid wastes generated by the hurricane. Demands on solid waste management facilities are highest immediately following the hurricane and through the early phase of recovery. Local authorities and emergency coordinators rely on waste management facilities to provide capabilities and capacities for waste management so a prioritized and coordinated cleanup can begin as quickly as possible. ©2011, Waste Management Page 30
  • 633. ONCE A “HURRICANE WATCH” IS ISSUED: Hurricanes and storms may generate contaminated debris or other atypical wastes that require special handling, processing, or disposal procedures that are not addressed by the facility permit and require special approval for disposal from the DOH SWS. After the potential effects of a hurricane are verified by local authorities (i.e., severe flooding, storm surge, high winds, etc.), the WGSL will consider acquiring supplies and materials (fuel, additional soil cover or alternate material, vehicles, heavy equipment, grinder/chippers, auxiliary lighting, pumps, generators, fire suppressant equipment, rain gear, personnel protective equipment, etc.) to ensure adequate equipment to handle the increase in waste and ensure airspace availability. In the event of a hurricane making landfall on the island of Oahu, WGSL personnel will perform the following as preparation: Conduct a briefing to entire staff on the status of conditions & severity of the hurricane and how it may impact the facility and service area / region. Discuss emergency operating procedures for facility. Power outages should be anticipated and procedures will be employed (when the WGSL re-opens to accept waste) as needed to manually track the date the waste was received, the quantity by weight or volume, and the origin of the waste. Inspect all drainage on-site structures to verify that they are in working order. Excessive silt in ditches and basins will be removed and the condition of pipes and discharge structures from basins will be verified. Diversion berms will be constructed around the current disposal area as needed to prevent run-on from entering the waste fill, and to prevent runoff from the waste fill areas of the site. Interim cover will be placed over exposed waste at the end of the working day. Holding capacity of leachate tanks and/or ponds will be increased to ensure additional volumes added during storm events can be accommodated. ONCE A “HURRICANE WARNING” IS ISSUED: The EC (or manager in charge) will track the hurricane front (via radio, television, internet, etc.) and implement the following procedures to properly shutdown all operations at the WGSL: If possible, all electrical lines/breakers/gas valves should be shut down to prevent any potential fires. Unplug all appliances. Secure facility property, structures, landfill equipment, and office (preserve records and data [electronic and hard copies]) in case of flooding or power failure. Anything that is not secured may become a damaging projectile in the event of high winds. Cover all windows with wood panels (if possible). Check batteries and stock up on canned food, first aid supplies, and drinking water. Gas up vehicles, generators, and emergency tanks. ©2011, Waste Management Page 31
  • 634. WGSL Management will require that site personnel return to their homes. If on-site, evacuate to the main office building and stay there (shelter in place) – stay away from windows. AFTER THE HURRICANE: WGSL / WMH Management will promptly (when it is safe to do so) conduct a visual survey & damage assessment of the site to identify any compromised building structures, slope failures, downed power lines, gas and water leaks, broken electrical wiring or sewage lines fires, LFG system failures, tank leaks/spills, or other conditions that could threaten worker or public safety. If you smell gas, leave the area immediately, notify the utility company, and warn others to stay away. Do not re-open gas valve until the utility company has checked the system. Do not go wading through high waters – power / electrical lines may be down in the water. If fires occur, follow the procedures set forth in Section 3.2. If injuries occur, follow the procedures set forth in Section 3.3. Turn on portable radio for instructions and news reports. Cooperate fully with public safety officials and instructions. Do not use vehicles unless there is an emergency. Keep the streets clear for emergency vehicles. Remain calm and lend a hand to others. If the site is evacuated, leave a message telling others where personnel can be found. The EC (or manager in charge) will be responsible for: Ensuring that WGSL safety programs are fully implemented. Coordinating evacuation of the WGSL including notification of adjacent property owners/tenants, as required. Communicating with the City & County of Honolulu and the State of Hawaii, as well as local authorities and emergency response personnel to inform them: 1) When the WGSL becomes operational after the storm; 2) The situation at the WGSL, such as waste storage capacity, transportation coordination, site conditions, personnel status, etc. In the event of inoperable telephone systems, notification of the appropriate agencies/businesses will be accomplished in the most expedient manner available (cellular/mobile phones, person to person, overnight mail, etc.). Notifying incoming drivers/haulers via radio or cell phone to avoid the site. Notifying WM Safety personnel of the emergency - determine whether a 24-Hour Report is required. ©2011, Waste Management Page 32
  • 635. Conducting a Post-Hurricane Inspection (Post-Hurricane / Severe Storm Forms [Appendix B]). Hurricanes leave behind debris made up of construction materials, damaged buildings, sediments, green waste, and personal property. Hurricane debris obstructs roads and disables electrical power and communication systems over wide areas. The goals of post-hurricane efforts will be to increase debris diversion rates, minimize environmental impacts, reduce waste management costs, minimize threats to health and safety, and shorten the duration of the cleanup effort. WMH may be asked to provide assistance at collection sites across the island to monitor incoming debris. These efforts will be coordinated with the DOH or emergency response personnel. 3.8 BOMB THREAT (PHONE CALL) The most basic preventative measures are properly securing a facility so that an explosive device cannot be easily placed without detection. A higher probability of bomb threats due to a history of past threats, a neighborhood or community trend, or a situation involving a particularly vengeful individual may warrant more extensive measures such as more stringent security, training programs, package instructions, more involved search and evacuation procedures, and recorders on appropriate telephones. Such a high probability will also warrant more contact with local law enforcement authorities. The WGSL does not have a high probability of bomb threats. WHEN THE THREAT IS CALLED IN: a) Listen while the caller talks and fill out the attached bomb threat call checklist. b) Inform the caller that the building is occupied and that the detonation of a bomb could result in death or serious injury to many innocent people. c) Attempt to determine the location and description of the bomb and time of detonation. Obtain as much information as possible including time of call, background noise, etc. d) Notify the WGSL District Manager or other on-site manager. e) WGSL Management will report the bomb threat to local police department. f) Search the area if time permits. Do not touch any suspicious items. Report any suspicious items to the WGSL District Manager and the local police department. g) Evacuate the area where any suspicious items are located. 3.9 CIVIL DISTURBANCE/DEMONSTRATION Do not become a spectator. Leave the area of the disturbance to avoid injury or arrest. Lock all doors, gates, and windows. Close all drapes and avoid window areas. Do not argue with or agitate the participants. Remain calm, be courteous and do not do anything to provoke an incident. ©2011, Waste Management Page 33
  • 636. Contact the WGSL District Manager and local police department as soon as possible. If required to protect employees and company property, service may have to be limited and/or access to the building may have to be restricted. Keep telephone lines open and avoid unnecessary inquiries regarding the incident. 3.10 ARMED ROBBERY If confronted by an armed robber, do not argue with the individual. Give the individual what he wants. Do not block his option to escape. Remember what you can about the incident including individual’s height, weight, hair length, color of eyes, color of hair, race, distinguishing marks or scars. If a weapon or vehicle is visible, try to remember as much detail about it as possible. After the incident is over, call the police immediately. Under no circumstances should you try to intercede or stop the robbers involved in the incident. ©2011, Waste Management Page 34
  • 637. BOMB THREAT CALL CHECKLIST: Date: _______________ Time: _______________ A.M. / P.M. Call Received by: ____________________________________________________________ Exact words of caller: ________________________________________________________ ___________________________________________________________________________ ___________________________________________________________________________ ___________________________________________________________________________ Questions to Ask: When will bomb explode? ______________________________________________ Where is the bomb located? _______________________________________________ What does the bomb look like? _____________________________________________ What kind of bomb is it? __________________________________________________ Why did you place the bomb? ______________________________________________ What do you hope to accomplish by this action? ________________________________ What is your name? ______________________________________________________ Where are you calling from? _______________________________________________ Voice Characteristics: Male ____ Female ____ Child ____ Loud ____ Soft ____ Nasal ____ Raspy ____ High ____ Low ____ Familiar ____ Pleasant ____ Other ______________________________________________________________________ Speech Characteristics: Fast ____ Slow ____ Stutter ____ Slurred ____ Intoxicated ____ ©2011, Waste Management Page 35
  • 638. Other ______________________________________________________________________ Accent Characteristics: Local ____ Region ____ Foreign ____ Other _____________________________________________________________________ Manner of Caller: Calm ____ Angry ____ Deliberate ____ Emotional ____ Laughing ____ Incoherent ____ Other ______________________________________ Background Noises: Office Machines ____ Street Traffic ____ Factory Machines ____ Music ____ Airplanes ____ Trains ____ Trucks ____ Animals ____ Other ______________________________________________________________________ Origin of Call: Internal ____ External ____ Local ____ Long Distance ____ Did caller appear to be familiar with the facility? ____________________________________ Number/extension at which call was received: ______________________________________ Contacts Made: Operations/District Manager: Date __________________ @ _______ am / pm Police Department: Date __________________ @ _______ am / pm Fire Department: Date __________________ @ _______ am / pm Other: Date __________________ @ _______ am / pm Other: Date __________________ @ _______ am / pm ©2011, Waste Management Page 36
  • 639. 3.11 TERRORIST THREATS IN THE OFFICE: Close business. If there are customers or visitors in the building, provide for their safety by asking them to stay – not leave. When authorities provide directions to shelter-in-place*, they want everyone to take those steps immediately, where they are, and not drive or walk outdoors. *Note: One of the instructions you may be given in an emergency where hazardous materials may have been released into the atmosphere is to shelter-in-place. This is a precaution aimed to keep you safe while remaining indoors (this is not the same thing as going to a shelter in case of a storm). Shelter-in-place means selecting a small, interior room, with no or few windows, and taking refuge there. It does not mean sealing off your entire home or office building. Unless there is an imminent threat, ask employees, customers, and visitors to call their emergency contact to let them know were they are and that they are safe. Turn on call- forwarding or alternative telephone answering systems. Change the recording on voice mail to indicate that the business is closed, and that staff and visitors are remaining in the building until authorities advise it is safe to leave. Close and lock all windows, exterior doors, and any other openings to the outside. If you are told there is danger of explosion, close window shades, blinds, or curtains. Have employees familiar with your building’s mechanical systems turn off all fans and heating and air conditioning systems. Some systems automatically provide for exchange of inside air with outside air – these systems in particular need to be turned off, sealed, or disabled. Gather essential disaster supplies, such as nonperishable food, bottled water, battery- powered radios, first aid supplies, flashlights, batteries, duct tape, plastic sheeting, and plastic garbage bags. Select interior room(s) above the ground floor, with the fewest windows or vents. The room(s) should have adequate space for everyone to be able to sit in. Avoid overcrowding by selecting several rooms if necessary. Large storage closets, utility rooms, pantries, copy and conference rooms without exterior windows will work well. Avoid selecting a room with mechanical equipment like ventilation blowers or pipes, because this equipment may not be able to be sealed from the outdoors. It is ideal to have a hard-wired telephone in the room(s) you select. Call emergency contacts and have the phone available if you need to report a life-threatening condition. Cellular telephone equipment may be overwhelmed or damaged during an emergency. Use duct tape and plastic sheeting (heavier than food wrap) to seal all cracks around the door(s) and any vents into the room. ©2011, Waste Management Page 37
  • 640. Bring everyone into the room(s). Shut and lock the door(s). Write down the names of everyone in the room, and call your business’ designated emergency contact to report who is in the room with you, and their affiliation with your business (employee, visitor, customer). Keep listening to the radio or television until you are told all is safe or you are told to evacuate. Local officials may call for evacuation in specific areas at greatest risk in your community. IN A VEHICLE: If you are driving a vehicle and hear advice to shelter-in-place on the radio, take these steps: If you are very close to home, your office, or a public building, go there immediately and go inside. Follow the shelter-in-place recommendations for the place you pick described above. If you are unable to get to a home or building quickly and safely, pull over to the side of the road. Stop your vehicle in the safest place possible. If it is sunny outside, it is preferable to stop under a bridge or in a shady spot, to avoid being overheated. Turn off the engine. Close windows and vents. If possible, seal the heating/air conditioning vents with duct tape. Listen to the radio regularly for updated advice and instructions. Stay where you are until you are told it is safe to get back on the road. Be aware that some roads may be closed or traffic detoured. Follow the directions of law enforcement officials. Local officials on the scene are the best source of information for your particular situation. Following their instructions during and after emergencies regarding sheltering, food, water, and clean up methods is your safest choice. Remember that instructions to shelter-in-place are usually provided for a duration of a few hours, not days or weeks. There is little danger that the room in which you are taking shelter will run out of oxygen – suffocation is not likely. ©2011, Waste Management Page 38
  • 641. 4.0 EMERGENCY EQUIPMENT & PPE The EC monitors and stores all emergency equipment and PPE supplies stocked. Any deficiencies in supply or operation are corrected as soon as possible. WGSL emergency equipment (and locations [see Figures 2a-2e]) consists of: Eye wash station (maintenance shop) Shovels Spill kit - contains absorbent (kitty litter), containment booms, sorbent pads (maintenance shop & mobile tank trucks) First aid kits (site vehicles & buildings) Fire extinguishers (all buildings, site vehicles & landfill equipment) WGSL PPE includes: Hard hats High visibility safety vests dust masks Ear plugs Steel toe work boots Safety glasses (as needed) Gloves ©2011, Waste Management Page 39
  • 643. 5.0 ADMINISTRATIVE PROCEDURES The WMH Environmental Protection Manager will work with the EC to ensure that corrective measures (if necessary) are implemented, follow-up reports / inspections are completed, and that the appropriate agencies and parties are notified. 5.1 EMERGENCY REPORTING Emergency reporting will be in compliance with federal, state, local and WM requirements. WGSL reporting includes: Reporting of significant events/emergency incidents to the EC (or manager in charge), WMH Market Area Management, and to the WM Safety & Environmental Protection representatives. Reporting of significant events/emergency incidents to the proper agencies (if necessary) as soon as possible. If it is determined that the WGSL has had a release, fire, or explosion involving hazardous materials that could threaten human health, or the environment outside the facility, the following actions should be taken: The EC shall immediately notify the appropriate local authorities and help these local officials decide whether local areas should be evacuated. The Environmental Protection Manager will immediately notify the DOH HEER Office. This report shall include: name and telephone number of reporter; name and address of facility; time and type of incident; name and quantity of material(s) involved to the extent known; the extent of injuries, if any; and the possible hazards to human health, or the environment, outside the facility. 5.2 TRAINING In accordance with federal, state, local and WM requirements, WGSL personnel are trained annually on the Emergency Action Plan and what their roles/responsibilities are in the event of an emergency. The WGSL emergency training requirements include: As required, testing of the plan by key staff. Semi-annual drills with all employees (documentation form attached). Location of all emergency shut down and main electrical power switches. Fire hazards of the materials and hazards to which employees are exposed. Location and operation of fire extinguishers. Proper and safe handling of gasoline and other petroleum products including cleanup of minor spills. ©2011, Waste Management Page 41
  • 644. Location of the WGSL Emergency Action Plan. Location of evacuation routes and re-assembly/evacuation points for the site. All trainings and drills are documented and placed in the WGSL Operating Record/Files. 5.3 PLAN UPDATE AND DISTRIBUTION The Emergency Action Plan is a living document and will be reviewed at least annually for accuracy and relevance and updated as warranted by changes in site conditions or procedures. Updates to this plan will be submitted to appropriate agencies in a timely manner. - The Emergency Action Plan is part of the WGSL Site Operations Manual, of which there are four controlled copies - Two (2) copies remain on-site at the WGSL, one (1) copy will be submitted to the DOH, and one (1) copy will be submitted to the City & County of Honolulu. Copies of the Plan will also be distributed to the following personnel/locations: WGSL District Manager WGSL Operations Specialist (Reception desk) WMH Environmental Protection Manager A copy will be placed in the lounge ©2011, Waste Management Page 42
  • 645. APPENDIX A FIRE PREVENTION PLAN ©2011, Waste Management Page A-1
  • 647. APPENDIX A - FIRE PREVENTION PLAN This Fire Prevention Plan for the Waimanalo Gulch Sanitary Landfill (WGSL) designates: Housekeeping procedures that help to prevent fires Potential fire hazards Proper handling and storage procedures for combustible materials Potential ignition sources and their control procedures Type of fire protection equipment available to control fire hazards The names and job titles of personnel responsible for maintenance of equipment and systems installed to prevent or control ignition of fires and control of accumulation of flammable or combustible waste materials are: WGSL District Manager WGSL Emergency Coordinator WGSL Mechanic WMH Director of Operations WMH Environmental Protection Manager HOUSEKEEPING PROCEDURES FOR FIRE PREVENTION: Avoid the accumulation of combustible materials. Keep flammable and combustible materials away from ignition sources. Keep all stairways, fire fighting equipment locations, and exit paths clear. Report spill/leaks promptly to management to assure corrective action is taken. Remove all waste at the end of each shift and placing it in the appropriate waste receptacles. Store all oily rags in an approved receptacle. Store flammables in an approved flammable cabinet a minimum of 25 feet from sources of ignition; Store work clothes in metal lockers; Use correct cleaning agents and avoiding the use of flammable/combustible materials for cleaning. Contain and clean up fuel spills immediately. Soil contaminated with spilled fuel will be excavated and, if authorized, disposed of at the working face. POTENTIAL FIRE HAZARDS, POTENTIAL IGNITION SOURCES, PROPER HANDLING/STORAGE PROCEDURES, AND FIRE PROTECTION EQUIPMENT Tables 1 and 2 list the potential fire hazards, potential ignition sources, proper handling/storage procedures, and fire protection equipment that can control these hazards. ©2011, Waste Management Page A-3
  • 649. EMERGENCY ACTION PLAN TABLE A-1 SITE LOCATIONS WITH POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES LOCATION POTENTIAL FIRE HAZARDS POTENTIAL IGNITION SOURCES Administrative Offices Combustible materials (e.g. paper, cardboard, etc.) Open flames (e.g. smoking materials, etc.) Electrical cords/outlets/wiring Hot surfaces (e.g. appliances, electrical wiring, etc.) Flammable/combustible liquids (e.g. aerosol cans, solvents, etc.) Open flames (e.g. smoking materials, etc.) Flammable/oxidizing gases (e.g. hydrogen, methane, etc.) Static electricity Maintenance Shop Flammable/combustible liquids (e.g. diesel, solvents, product oils, etc.) Open flames (e.g. welding, smoking materials, etc.) Combustible materials (e.g. paper, cardboard, etc.) Sparks from friction (e.g. grinding) Electrical cords/outlets/wiring Hot surfaces (e.g. power tools, electrical wiring, etc.) Flammable/oxidizing gases (e.g. acetylene, oxygen, etc.) Static electricity Open flames (e.g. welding, cutting, etc.) Internal combustion engines (e.g. vehicles, forklifts, etc.) Contaminated materials (e.g. oily rags, etc.) Open flames (e.g. welding, smoking materials, etc.) Storage Containers Flammable/combustible liquids (e.g. paints, solvents, etc.) Open flames (e.g. welding, smoking materials, etc.) Combustible materials (e.g. paper, cardboard, etc.) Sparks from friction (e.g. grinding) Electrical cords/outlets/wiring Hot surfaces (e.g. power tools, electrical wiring, etc.) Flammable/oxidizing gases (e.g. acetylene, oxygen, etc.) Static electricity Open flames (e.g. welding, cutting, etc.) Internal combustion engines (e.g. vehicles, forklifts, etc.) Contaminated materials (e.g. oily rags, etc.) Open flames (e.g. welding, smoking materials, etc.) ©2011, Waste Management Page A-5
  • 650. EMERGENCY ACTION PLAN TABLE A-2 CONTROL PROCEDURES AND FIRE PROTECTION EQUIPMENT FOR POTENTIAL FIRE HAZARDS AND POTENTIAL IGNITION SOURCES POTENTIAL FIRE HAZARDS/ IGNITION SOURCES CONTROL PROCEDURE/FIRE PROTECTION EQUIPMENT Combustible materials Avoid accumulation of combustible materials (e.g. empty boxes, cartons, loose paper, etc.) Keep combustible materials away from ignition sources including establishment/enforcement of no smoking/no open flame areas Keep all stairways, firefighting equipment locations and exit paths clear Remove all waste (e.g. dust, lint, loose paper, etc.) at the end of each shift in each work area (including floors, ceilings, walls, ledges, beams, and equipment) and place in appropriate waste receptacle Store work clothes in metal lockers Maintain fire extinguishing equipment capable of handling Class A fires within 75 feet of combustible materials Perform annual maintenance and monthly inspections on fire extinguishing equipment Train personnel in use of fire extinguishing equipment Electrical cords/outlets/wiring Inspect power cords for damaged insulation and damaged plugs Discontinue use of a power cord that gets warm Maintain electrical motors in good operating condition Do not overload motors, cords or other electrical equipment Maintain fire-extinguishing equipment capable of handling Class C fires near electrical equipment Perform annual maintenance and monthly inspections on fire extinguishing equipment Train personnel in use of fire extinguishing equipment ©2011, Waste Management Page A-6
  • 651. EMERGENCY ACTION PLAN Flammable/combustible liquids Keep materials in covered containers when not in use Do not transport materials in open containers Store flammable liquids in containers with appropriate warning labels Do not store near sources of heat/ignition Inert and verify inert atmosphere of containers, piping, tanks that have contained flammable/combustible liquids prior to exposure to heat/flame Maintain fire-extinguishing equipment capable of handling Class B fires within 50 feet of flammable/combustible liquids Perform annual maintenance and monthly inspections on fire extinguishing equipment Train personnel in use of fire extinguishing equipment Welding/cutting operations Establish approved areas for cutting and welding Establish approved procedures for a hot work program to restrict cutting/welding in all other areas along with a designated individual for approving such cutting/welding Utilize only approved equipment for cutting/welding Train all personnel that perform cutting/welding Verify training of contractors who perform cutting/welding Provide contractor orientation of potential fire hazards on-site Do not perform cutting/welding within 35 feet of combustible materials Implement hot work permit program Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near the welding operation Perform annual maintenance and monthly inspections on fire extinguishing equipment Train personnel in use of fire extinguishing equipment Flammable/oxidizing gas cylinders Do not store cylinders near sources of heat/flame Cylinders stored inside buildings will be in a well-protected, well-ventilated, dry location at least 20 feet from highly combustible materials Cylinders storage will be located where passing/falling objects will not damage cylinders Do not sore cylinders where they could be subject to tampering by unauthorized personnel Do not store cylinders near elevators, stairs or passageways Do not store cylinders in unventilated enclosures Do not store oxygen cylinders near highly combustible materials such as oil/grease ©2011, Waste Management Page A-7
  • 652. EMERGENCY ACTION PLAN Maintain fire extinguishing equipment capable of handling Class A, B, and C fires within 75 feet of welding areas Open flames Keep sources of ignition including open flames away from combustible materials Establish and enforce no smoking/no open flame areas Establish and enforce a hot work program Maintain fire extinguishing equipment capable of handling Class A, B, C fire near areas with open flames Contaminated materials Keep sources of ignition away from contaminated materials Store contaminated materials in appropriate waste receptacle (e.g. oil rag container) Maintain fire extinguishing equipment capable of handling Class A, B, and C fires where contaminated materials are stored Hot surfaces Keep sources of ignition including hot surfaces away from combustible materials Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near areas with hot surfaces Sparks from friction Keep sources of ignition including sparks from friction away from combustible materials Maintain fire extinguishing equipment capable of handling Class A, B, and C fires near areas where sparks from friction may occur Static electricity Utilize proper grounding/bonding procedures when moving volatile liquids Verify continuity of grounds on a regular basis Maintain fire extinguishing equipment capable of handling Class A, B, and C fires within 50 feet of flammable/combustible liquid storage Internal combustion engines Maintain internal combustion engines in good repair Clean up spills/leaks from internal combustion engines promptly and store contaminated material safely Report spills/leaks from internal combustion engines promptly to supervision to assure corrective action is taken Maintain fire extinguishing equipment capable of handling Class A, B, and C fires on all vehicles ©2011, Waste Management Page A-8
  • 653. EMERGENCY ACTION PLAN ©2011, Waste Management Page A-9
  • 654. EMERGENCY ACTION PLAN FIRE PROTECTION EQUIPMENT The WGSL is equipped with fire extinguishers that are fully charged and ready for use at all times. Each extinguisher is inspected on an annual basis and recharged as necessary. A qualified service company performs the annual inspections, and all extinguishers display a current inspection tag. Inspection and recharging will be performed following each use. The main office, scale house, all landfill equipment, and landfill vehicles are equipped with fire extinguishers. The fire prevention plan and fire control procedures for the WGSL will be revisited following the occurrence of a significant fire to determine if modifications are warranted. FIRE EXTINGUISHER USE All WGSL equipment operators are trained annually on the proper usage of fire extinguishers. Documentation of training sessions are kept on-site as part of the WGSL Operating Record/Files. All landfill equipment has a charged ABC fire extinguisher with at least a 20-pound rating. This type of extinguisher is good for: A – Ordinary combustibles (paper, leaves, general trash, etc.) B – Flammable liquids (diesel fuel, hydraulic oil, motor oil, etc.) C – Electrical equipment (electrical wiring system on the equipment) Use the P.A.S.S. method for extinguishing a small fire: P ull the pin. A im at the base of the flame. S queeze the handle. S weeping motion from side-to-side. If the fire has grown beyond a small fire, clear the area and allow the fire department to extinguish the fire. ©2011, Waste Management Page A-10
  • 655. EMERGENCY ACTION PLAN APPENDIX B POST EARTHQUAKE FORMS & POST HURRICANE / SEVERE STORM FORMS ©2011, Waste Management Page B-1
  • 657. EMERGENCY ACTION PLAN WAIMANALO GULCH SANITARY LANDFILL POST EARTHQUAKE INSPECTION SHEET Date of Earthquake: Date of Inspection: Distance from Epicenter: Epicenter Location: . Time of Earthquake: Time of Inspection: Person(s) Conducting Inspection: Damage Evident Yes No Drainage Structures west side rip-rap head of drainage channel interceptor drains down drains sedimentation basin inlet/outlet structures (risers) Fueling / Maintenance Area 600-gallon (diesel) mobile lube truck 5000-gallon (diesel) truck (stationary) maintenance buildings/containers 360-gallon waste oil AST (Above Ground Storage Tank) 360-gallon hydraulic oil AST miscellaneous 55-gallon drums Any leaks/spills?_______________ ©2011, Waste Management Page B-3
  • 658. EMERGENCY ACTION PLAN Side Slopes Landfill Cover Access Roads Landfill Heavy Equipment Fencing Damage Evident Yes No Facility Buildings admin office scale house telephones lounge/ breaker trailer computers scales parking lot Water Supply main water meter mainline water truck backflow preventer Sewer Line(s) Power Line(s) Leachate Collection Systems E1 riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms Ash riser o frac tank ©2011, Waste Management Page B-4
  • 659. EMERGENCY ACTION PLAN o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms 4B riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms E6 riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms Any leaks/spills?_______________ Any vapors evident?______________ Damage Evident Yes No Flare Station /System concrete pad/skid condensate injection system condensate poly tank(s) gas header pipe gas wells power supply system panel flare stack Any leaks/spills?_______________ ©2011, Waste Management Page B-5
  • 660. EMERGENCY ACTION PLAN Any evidence of physical change around the gas wells such as: differential settlement? ___________________ compromised seal integrity?_________________ Perimeter Gas Probes Groundwater Wells concrete pads housing casing guard posts/fencing Any evidence of damage to wells such as: ponded water?________________ settlement around the wells? ____________ Was there any damage to landfill structures, cover or systems caused by the above seismic event? YES NO If yes, complete an Earthquake Damage Report Form. ©2011, Waste Management Page B-6
  • 661. EMERGENCY ACTION PLAN WAIMANALO GULCH SANITARY LANDFILL 92-460 Farrington Highway Kapolei, HI 96707 EARTHQUAKE DAMAGE REPORT FORM Date / Time of Seismic Event: Date / Time of Inspection: Note: Fill out one form for each damage observation. 1. What is damaged? 2. Location of damage: 3. Description of Damage: Log of Corrective Actions Implemented: Date damage was repaired: Damage repaired by: ©2011, Waste Management Page B-7
  • 662. EMERGENCY ACTION PLAN ©2011, Waste Management Page B-8
  • 663. EMERGENCY ACTION PLAN WAIMANALO GULCH SANITARY LANDFILL POST HURRICANE / SEVERE STORM INSPECTION SHEET Type of Storm (Depression, Tropical Storm, Hurricane): ______________________ Date of Storm: ____ Date of Inspection: ____ Category of Hurricane (if applicable): ____ Recorded Wind Speed(s): . Time of Hurricane: Time of Inspection: Person(s) Conducting Inspection: Damage Evident Yes No Drainage Structures west side drainage rip-rap head of drainage channel interceptor drains down drains sedimentation basin inlet/outlet structures (risers) Fueling / Maintenance Area 600-gallon (diesel) mobile lube truck 5000-gallon (diesel) truck (stationary) maintenance buildings/containers 360-gallon waste oil AST (Above Ground Storage Tank) 360-gallon hydraulic oil AST miscellaneous 55-gallon drums Any leaks/spills?_______________ ©2011, Waste Management Page B-9
  • 664. EMERGENCY ACTION PLAN Side Slopes Landfill Cover Access Roads Landfill Heavy Equipment Fencing Damage Evident Yes No Facility Buildings admin office scale house telephones lounge/ breaker trailer computers scales parking lot Water Supply main water meter mainline water truck backflow preventer Sewer Line(s) Power Line(s) Leachate Collection Systems E1 riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms ©2011, Waste Management Page B-10
  • 665. EMERGENCY ACTION PLAN Ash riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms 4B riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms E6 riser o frac tank o sump/riser o transducer system/panel o pipes/hoses o pumps o power o berms Any leaks/spills?_______________ Any vapors evident?______________ Damage Evident Yes No Flare Station /System concrete pad/skid condensate injection system condensate poly tank(s) gas header pipe gas wells power supply system panel flare stack ©2011, Waste Management Page B-11
  • 666. EMERGENCY ACTION PLAN Any leaks/spills?_______________ Any evidence of physical change around the gas wells such as: differential settlement? ___________________ compromised seal integrity?_________________ Perimeter Gas Probes Groundwater Wells concrete pads housing casing guard posts/fencing Any evidence of damage to wells such as: ponded water?________________ settlement around the wells? ____________ Was there any damage to landfill structures, cover or systems caused by the above storm event? YES NO If yes, complete a Hurricane / Severe Storm Damage Report Form. ©2011, Waste Management Page B-12
  • 667. EMERGENCY ACTION PLAN WAIMANALO GULCH SANITARY LANDFILL 92-460 Farrington Highway Kapolei, HI 96707 POST HURRICANE / SEVERE STORM DAMAGE REPORT FORM Type of Storm (Depression, Tropical Storm, Hurricane): ______________________ Date / Time / Duration: ________________ Date / Time of Inspection: ________________ Note: Fill out one form for each damage observation. 1. What is damaged? 2. Location of damage: 3. Description of Damage: Log of Corrective Actions Implemented: Date damage was repaired: Damage repaired by: ©2011, Waste Management Page B-13
  • 668. EMERGENCY ACTION PLAN ©2011, Waste Management Page B-14
  • 669. EMERGENCY ACTION PLAN TRAINING Training will be per the “Training” subsection of the Emergency Action Plan and Fire Prevention Plan. This Program is hereby approved: _________________________________ ____________________________ SIGNATURE DATE ©2011, Waste Management Page B-15
  • 671. EMERGENCY ACTION PLAN DOCUMENTATION OF SEMI-ANNUAL DRILL Date Performed_________________________________________________________ Facility Name___________________________________________________________ Certified By __________________________ Title ____________________________ Comments_____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ©2011, Waste Management Page B-17
  • 673. EMERGENCY ACTION PLAN ACKNOWLEDGEMENT FORM I, (print name) ________________________________________ have received training on the Waimanalo Gulch Sanitary Landfill Emergency Action Plan Program. I had the opportunity to have questions answered pertaining to the training material and instructions that were presented to me by the Company. I understand the training I have received and agree to abide by the standards presented. _________________________________________ (Employee) Print Name _________________________________________ (Employee) Signature _________________________________________ (Instructor) Print Name _________________________________________ (Instructor) Signature _________________________________________ Date ©2011, Waste Management Page B-19
  • 675. Personal Protective Equipment Program Program: Personal Protective Equipment Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 Introduction Personal protective equipment (PPE) is used in the workplace to protect employees from hazards to the eyes, face, hands, skin, head, and feet when engineering and administrative controls are not feasible. PPE can also provide protection against heat or cold and hazardous chemicals. It can act as a shield or barrier between the worker and the hazardous chemical. PPE does not remove the hazard from the workplace, so it is the last line of defense before the hazard reaches the employee. Do not rely on PPE alone to provide protection against hazards. PPE should be used in conjunction with guards, engineering controls, and sound operational practices. PPE is only as good as the consistency with which employees wear it. PPE effectiveness relies on the fit, use and maintenance by the employees. PPE is effective only if it is properly selected based on the hazards present and it is worn in the way it has been designed to be used. Performed by a person who can assess the hazards carefully, it is important for everyone to know the hazards in their area, and to use and take care of the PPE that is selected to protect them. OSHA regulations 29 CFR 1910.132-133 and 135-138 cover personal protective equipment. CORE PROGRAM Responsibility Joe Whelan, Donny Carder or designee, is responsible for administering the personal protective equipment program. These duties include: Implementing the program. Ensuring that a hazard assessment is conducted. Ensuring that personal protective equipment is available. Reviewing the program on an annual basis. Ensuring that employee training is conducted. Supervisors are responsible for ensuring employees wear personal protective equipment in required areas and that they wear their personal protective equipment properly. Employees must wear personal protective equipment where required. They must learn how to wear it properly, and keep it clean and well maintained. Job Hazard Assessment (JHA) The general requirements for personal protective equipment are in 29 CFR 1910.132. This standard requires the completion of a Job Hazard Assessment, sometimes referred to as a Job Safety Analysis Personal Protective Equipment Page 1 ©2011, Waste Management January 2011
  • 676. Personal Protective Equipment Program (JSA). The Job Hazard Assessment identifies hazards present or likely to be present that require the use of personal protective equipment (PPE). The written Job Hazard Assessment, must include the following: The specific tasks evaluated The name of the person verifying that the hazard assessment was performed The date of the hazard assessment Indication that the purpose of the hazard assessment is determining PPE requirements Perform a hazard assessment using the PPE assessment form in the appendix or an equivalent form. Use this form to select PPE based on the identified hazards. (See Attachment A: Job Hazard Analysis 2004) Once the facility performs the Job Hazard Assessment and selects and makes available PPE, training must be conducted to: Inform the affected employees of the PPE required for each hazard and its limitations. Select PPE that properly fits each employee. Inform of the proper use, care, cleaning and maintenance of the PPE. It is important to remember that anyone who enters the area where employees are required to wear PPE must wear the same type of PPE. For example, office personnel should be required to wear traffic safety vests and appropriate footwear whenever they enter the tipping floor, as they are exposed to similar vehicle traffic and material hazards as the workers who are spotting trucks. Similarly, supervisors and contractors should be required to wear, at a minimum, the same PPE as the other workers in their immediate work area. A good practice is to have boxes with at least eye and hearing protection located at the entrance to shop areas, tipping floor, landfill office. Office personnel or visitors can don the PPE and return it when finished. Eye and Face Protection OSHA requires the use of eye and face protection (29 CFR 1910.133). Employees exposed to flying materials must use eye protection, such as safety glasses with side protection Permanently attached side shields are preferred, however, slide on side shields are acceptable if they meet the ANSI standards. Employees must use safety glasses with side shields for the following hazards: Flying particles Compressed air Impact Safety glasses and a face shield are required when exposed to: Liquid chemicals Acids or other chemicals that can burn, corrode, or dissolve Debris as in construction and/or demolition Personal Protective Equipment Page 2 ©2011, Waste Management January 2011
  • 677. Personal Protective Equipment Program Goggles to protect against: Chemical gases or vapors Light radiation (with the proper filter shade) All eye and face protection must: Provide adequate protection for the hazards in the work area. Fit properly and comfortably. Be kept in a clean condition. Be kept in good repair. Meet the American National Standard practice for occupational and educational eye protection. If exposed to light radiation, use the appropriate eye PPE, as indicated in the table under 29 CFR 1910.133 (a) 5. A copy of the table can be found in the Appendices. If employees must wear corrective lenses and eye/face protection, provide them with: Eye protection that has corrective lenses built in, or Eye protection that can be worn over corrective lenses without interfering with the position of the lenses or the protection. All eye and face protection purchased after July 5, 1994, must comply with ANSI Z87.1-1989, the American National Standard practice for occupational and educational eye and face protection. Any eye protection purchased before July 5, 1994 must comply with ANSI Z87.1-1968, the USA Standard for Occupational and Educational Eye and Face Protection. Head Protection Head protection is required to be worn to prevent injury to the head from falling objects or from striking the head against hard surfaces. Refuse can fall from elevated truck bodies, conveyors and work platforms, creating an impact hazard. Low-hanging surfaces, such as walkways under conveyors and roof supports on elevated sorting platforms, can present bump hazards. Hard hats must be worn where impact and penetration hazards can occur from falling objects. They are generally worn at landfills in the active disposal and borrow areas. Hard hats are also worn at material recovery facilities (MRFs) on the tipping floor and in locations where employees are assigned to work below sorting platforms and conveyors. Bump caps provide protection from head bumps, but do not provide impact or penetration protection. Application of bump caps should be limited in the refuse industry. Most exposures in the industry that involve head protection require the use of hard hats. Bump protection may be appropriate for work performed under vehicles and in work, or passage to work areas, involving low overhead clearances. When selecting head protection, know if there are potential electrical hazards in the work area. Special non-conductive head protection must be worn if electrical hazards are present. All head protection must meet the requirements of ANSI Z89.1-1986, the American National Standard for Personnel Assurance Protection-Protective Headwear for Industrial Workers requirements. Personal Protective Equipment Page 3 ©2011, Waste Management January 2011
  • 678. Personal Protective Equipment Program Foot Protection Protective footwear should be worn when working in areas where there is a danger of foot injuries due to falling or rolling objects or objects piercing the sole, and where there may be electrical hazards. Safety footwear is labeled to show that it meets the requirements and specifications in the "American National Standard for Personal Protection - Protective Footwear" ANSI Z41-1991 and OSHA 29 CFR 1910.136. Work boots with puncture and oil resistant, slip resistant soles and a minimum six-inch high lace-up ankle support are acceptable for drivers and residential helpers. Where employees are assigned or allowed to walk on refuse, such as when tarping a load or working in the active area of a landfill or on a transfer station tipping floor, they should be required to wear work boots with steel mid-sole. Steel shank protection in work boots provides limited protection of the soles and may not be used in place of steel mid-soles. In some cases, metatarsal protection or chemical impermeability may be prescribed for drum handling. Steel toe safety shoes are required when it is necessary to protect an employee's feet from injury from heavy material rolling over or dropping on toes. Mechanics, and other employees, who are involved in work with moving heavy objects, such as commercial containers on casters, should be required to wear steel-toed safety shoes. Minimum acceptable footwear for hauling, landfill, transfer and MRF workers is a substantial shoe. A substantial shoe is one that is constructed of leather or leathher like materials and covers the foot and ankle above the anklebone. Tennis shoes are not considered to be substantial shoes. Hand Protection Employees whose hands are exposed to hazards must be provided hand protection as required by 29 CFR 1910.138. Employees must use hand protection when conditions may cause: Exposure to hazardous substances, which can damage or be absorbed through the skin Cuts/scrapes/abrasions Punctures (such as needle sticks). Injury from extreme temperatures (hot or cold) No single type of glove will provide protection against all hand hazards. Most glove materials provide only limited protection against many chemicals. Therefore, it is important to select the most appropriate glove for a particular application and to determine how long it can be worn, and whether it can be reused. It may be more cost effective to regularly change cheaper gloves than to clean and reuse more expensive types. It is also important to know how the gloves perform against the specific hazard; e.g., chemical hazards, cuts, heat, etc. Glove manufacturers have standard test procedures to assess these performance characteristics. Before selecting gloves, request documentation from the manufacturer that the gloves meet the appropriate test standard(s) for the hazard(s) anticipated. For chemicals, consult the material safety data sheet or other health and safety references to identify the compatible material. Many refuse collection; recycling, transfer and disposal employees will be provided with or will choose to wear leather gloves. Leather gloves generally offer durable protection for material handling tasks. However, leather gloves do not grip well when neither wet, nor do they withstand repeated decontamination or cleaning. Palm-dipped (canvas backed) nitrile gloves and other similar gloves coated with synthetic and natural rubbers can provide acceptable alternatives to leather. Arm protection is used in recycle sorting and other operations where employees may be exposed to cuts and abrasions to the forearms. Exposure can occur when employees are reaching across conveyors, into Personal Protective Equipment Page 4 ©2011, Waste Management January 2011
  • 679. Personal Protective Equipment Program mixed refuse/recyclables and into refuse containers. Sleeves made of Kevlar and/or PVC can be used as protection. Where there is a potential for exposure to the forearms from chemicals (e.g., reaching into chemical detergent containers), cold, or heat (e.g., from welding or cutting) appropriate protective sleeves may also be worn. Select hand protection based on the hazards identified. Protective Clothing Protective clothing can include the following: Uniforms Enhanced visibility clothing/accessories Chemical protective clothing Welders / painters cottons Residential drivers and helpers, landfill spotters, and employees working in or near motor vehicle traffic should wear enhanced visibility uniforms obtained through the company yellow sheet program. Enhanced visibility elements must appear on the outer most layer of clothing to be effective. Periodic monitoring of employee use of enhanced visibility clothing by supervisors is an important component in ensuring that employees wear enhanced visibility clothing when it is required. Employees potentially exposed to hazardous chemicals, extreme heat, or cold should use protective clothing appropriate to the hazard. Selection of protective clothing requires a clear understanding of the potential hazards and the limitations of the protective clothing. For chemicals, consult the Material Safety Data Sheet (MSDS) or other toxicology references to identify compatible materials. Wear rain gear as needed. Incorporate enhanced visibility into the rain gear as required. Respiratory Protection Refer Respiratory Protection Program. Hearing Protection Refer Hearing Conservation Program. Control the Hazard Control the hazards at the source, if possible. Rely on PPE as the last line of defense in controlling hazards. PPE should be used as a supplement to guards, engineering controls, and sound operational practices. Care Of PPE Some of the PPE, such as earplugs, coveralls, and gloves, may be disposable. Ensure that non-disposable PPE is carefully maintained so that it continues to give full protection. Recognize Limitations of PPE PPE provides important protection, but it has limitations. PPE can be hot, bulky, and heavy. It can make it harder to move freely while doing a job. It can increase fatigue and cut down on the ability to see, hear, and feel. All of these limitations can create stress. The best PPE selection minimizes stress and maximizes protection. Personal Protective Equipment Page 5 ©2011, Waste Management January 2011
  • 680. Personal Protective Equipment Program Defective PPE Damaged, defective, or worn out PPE cannot provide the necessary protection. PPE must be inspected before each use to see if it has been degraded or weakened by contact with a chemical, excessive wear or abuse. Look for holes, defects, rips, or seam openings in the PPE that could let a chemical penetrate. Training Employee training must include the following information: Where and when to wear PPE What PPE to wear How to properly don, doff, adjust, and wear PPE How to properly care for and maintain PPE What the limitations of PPE are How to identify when PPE is no longer usable All employees required to wear PPE must demonstrate that they understand how to properly wear, use, clean, and maintain their PPE. Employees require retraining when: They improperly wear, use, clean, or maintain PPE, or otherwise show that they lack these skills. Whenever there are new work practices or equipment, or requirements for PPE have changed. Whenever a worker is assigned to a task that requires different PPE or places additional limitations on the PPE that the worker is already trained to use. Record Keeping Document training in the employee training record. The record should include the following information: A statement that each employee has received and understands the PPE training The content of the training The names and signatures of the employee The date(s) of training The name of the person who provided the training DEFINITIONS Administrative Controls: Controls such as job rotation, different work assignments, or time away from the hazard. Engineering Controls: Methods of controlling employee exposures by modifying the source or reducing the quantity of contaminants released into the work environment. Job Hazard Assessment: A process used to identify hazards present or likely to be present, to determine the proper PPE usage when performing job related tasks. Personal Protective Equipment (PPE): Equipment worn by the worker to protect against hazards. Examples include gloves, respirators, and hearing protection. Personal Protective Equipment Page 6 ©2011, Waste Management January 2011
  • 681. Personal Protective Equipment Program _________________________________________________________________________ Reviewed by: Date: Date of Print Name Signature Comments – Changes to Program Review Personal Protective Equipment Page 7 ©2011, Waste Management January 2011
  • 682. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Delivery Driver Drives flat bed truck, box type truck, pick up truck with trailer, trucks adapted with Job Description container forks. Delivers and retrieves a variety of containers (bins, carts, toters). Loads and unloads truck manually, with dollies, lift gates. Check All That Apply Tasks Conducts pre/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Communicates via two-way radio with dispatch and co-workers Paperwork daily Daily sequencing of route Drives to various customer locations, post collection facility to/from office and route Loads and unloads truck/trailer by hand, with dolly or with lift gate. Places containers at customer location or at company facility Additional Tasks Personal Protective Equipment Page 8 ©2011, Waste Management January 2011
  • 683. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Delivery Driver Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 9 ©2011, Waste Management January 2011
  • 684. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Driver - Commercial Drives front loading truck; collects refuse from commercial customers at various Job locations throughout the day; loads and compacts refuse using hand controls until Description truck is full then drives to post collection facility (landfill, transfer station, MRF, etc.) for emptying of truck 1-3 times per day. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at landfill to dump out truck contents Cleans out behind packer blade after dumping out Cleans off debris from apron or hopper area Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (1yd-4yd) by hand to load onto lifting forks and back to original position Communicates via two-way radio with dispatch and co-workers Operates MCC (onboard computer system) by hand Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Cleans/shovels spillage at customer location May also lift various types of trash cans/roller carts to dump into bin or attach to tipper on lifting forks of vehicle (weight of cans/carts can be up to 60 lbs and occasionally more) Additional Tasks Personal Protective Equipment Page 10 ©2011, Waste Management January 2011
  • 685. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Driver - Commercial Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling Debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 11 ©2011, Waste Management January 2011
  • 686. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Helper - Commercial Assists Front End Loader Driver collecting refuse from commercial customers at Job Description various locations throughout the day. Pushes bins, loads and compacts refuse using hand controls until truck is full. Relocates bins back to original position. Check All That Apply Tasks Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Cleans off debris from apron or hopper area Walks to/from office to vehicle parking lot, around vehicle at landfill , at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (1yd-4yd) by hand to load onto lifting forks and back to original position Communicates via two-way radio with dispatch and co-workers Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily (as required) Daily sequencing of route (as required) Cleans/shovels spillage at customer location May also lift various types of trash cans/roller carts to dump into bin or attach to tipper on lifting forks of vehicle (weight of cans/carts can be up to 60 lbs and occasionally more) Additional Tasks Personal Protective Equipment Page 12 ©2011, Waste Management January 2011
  • 687. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Helper - Commercial Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 13 ©2011, Waste Management January 2011
  • 688. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Rear End Loader Driver – Residential/Commercial Drives rear loading truck; collects refuse from residential and commercial customers on a route throughout the day. Loads rear hopper of truck either manually or with Job Description tippers until truck is full. May empty commercial bins if truck is equipped. Then drives to post collection facility (landfill, transfer station, MRF, etc.) for emptying of truck 1-3 times per day. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at landfill to dump out truck contents Cleans out behind packer blade after dumping out Cleans off debris from hopper area Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into rear hopper of truck either manually or using the tipper. May also load bags, boxes and other bulky items. May also push/pull larger bins (1/2 to 4 yard) to rear of truck for tipping if truck is equipped Communicates via two-way radio with dispatch and co-workers Operates MCC (onboard computer system) by hand Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 14 ©2011, Waste Management January 2011
  • 689. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Rear End Loader Driver – Residential/Commercial Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 15 ©2011, Waste Management January 2011
  • 690. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Rear End Loader Helper – Residential / Commercial Assists driver of rear loading truck. Collects refuse from residential and commercial customers on a route throughout the day. Loads rear hopper of truck either Job Description manually or with tippers until truck is full. May empty commercial bins if truck is equipped. Helpers are not allowed to drive the truck or perform tasks requiring the truck to locked and tagged out. Check All That Apply Tasks Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Cleans off debris from hopper area Walks to/from office to vehicle parking lot, and at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into rear hopper of truck either manually or using the tipper. May also load bags, boxes and other bulky items May also push/pull larger bins (1/2 to 4 yard) to rear of truck for tipping if truck is equipped Communicates via two-way radio with dispatch and co-workers Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily (as required) Daily sequencing of route (as required) Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 16 ©2011, Waste Management January 2011
  • 691. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Rear End Loader Helper – Residential / Commercial Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 17 ©2011, Waste Management January 2011
  • 692. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Roll Off Driver Job Description Drives roll off truck; delivers and/or picks up containers of various sizes (4 to 50 yard including compactors) from various types of customers. Disconnects and reconnects compactor receiving boxes. Operates hoist and cable controls on truck to load refuse container onto truck at each stop; drives truck with full container to post collection facility (landfill, MRF, transfer station, etc.) and empties container; returns emptied container to customer location; goes on to next stop and repeats process 8-12 times daily. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Loosens and detaches two turnbuckles weighing 25-50 lbs, which secure compactor to container for transport to dump site; attaches compactor turnbuckles to container and tightens upon return to customer location Releases chain and latching device to open container doors, guides door to side of container and secures in place with a chain; returns door to closed position, latches and chains upon completion of dump out Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Communicates via two-way radio with dispatch and co-workers Occasionally places stickers on containers of company name/phone number Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Manually (or automatically) tarps loaded container for transport Climbs 3-8 feet on top of container to even out load for tarping Covers compactor container ends with tarpaulin (referred to as a “diaper”) Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 18 ©2011, Waste Management January 2011
  • 693. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Roll Off Driver Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 19 ©2011, Waste Management January 2011
  • 694. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Side Loader Driver – Residential Job Description Drives side loading truck; collects refuse residential customers on a route throughout the day. Loads side mounted hopper of truck either manually, with tippers or with automated arm until truck is full. Then drives to post collection facility (landfill, transfer station, MRF, etc.) for emptying of truck 1-3 times per day. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at landfill to dump out truck contents Cleans out behind packer blade after dumping out Cleans off debris from hopper area Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into side hopper of truck either manually, using the tipper or the automated arm. May also load bags, boxes and other bulky items. Communicates via two-way radio with dispatch and co-workers Operates MCC (onboard computer system) by hand Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 20 ©2011, Waste Management January 2011
  • 695. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Side Loader Driver – Residential Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 21 ©2011, Waste Management January 2011
  • 696. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Side Loader Helper – Residential Job Description Assists side load driver; collects refuse from residential customers on a route throughout the day. Loads side mounted hopper of truck either manually, with tippers or with automated arm until truck is full. Helpers are not allowed to drive the truck or perform tasks requiring the truck to locked and tagged out. Check All That Apply Tasks Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Cleans off debris from hopper area Walks to/from office to vehicle parking lot, and at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into side hopper of truck either manually, using the tipper or the automated arm. May also load bags, boxes and other bulky items Communicates via two-way radio with dispatch and co-workers Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily (as required) Daily sequencing of route (as required) Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 22 ©2011, Waste Management January 2011
  • 697. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Side Loader Helper – Residential Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 23 ©2011, Waste Management January 2011
  • 698. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Driver - Residential Job Description Drives front loading truck; collects refuse from residential customers on a route throughout the day. Loads bucket attached to the front forks of truck either manually or with tippers, and dumps buckets into truck until truck is full. Then drives to post collection facility (landfill, transfer station, MRF, etc.) for emptying of truck 1-3 times per day. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Lock/unlocks turnbuckle, locking pins or other devices that secure the rear door while at landfill to dump out truck contents Cleans out behind packer blade after dumping out Cleans off debris from apron or hopper area Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into bin on front of truck either manually or using the tipper. May also load bags, boxes and other bulky items Communicates via two-way radio with dispatch and co-workers Operates MCC (onboard computer system) by hand Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 24 ©2011, Waste Management January 2011
  • 699. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Driver - Residential Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 25 ©2011, Waste Management January 2011
  • 700. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Helper - Residential Job Description Assists residential front load driver collecting refuse and/or recyclables from residential customers on a route throughout the day. Loads bucket attached to the front forks of truck either manually or with tippers, and dumps buckets into truck until truck is full. May also load bags, boxes or other containers manually. Check All That Apply Tasks Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons Cleans off debris from apron or hopper area Walks to/from office to vehicle parking lot, and at customer location Pushes, pulls, rolls loaded/empty containers of various sizes (30 to 90 gallon) by hand to load into bin on front of truck either manually or using the tipper. May also load bags, boxes and other bulky items Communicates via two-way radio with dispatch and co-workers Occasionally places stickers on containers of company name/phone number and potential safety hazards Occasionally repairs/replaces broken/worn wheels on containers Paperwork daily (as required) Daily sequencing of route (as required) Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 26 ©2011, Waste Management January 2011
  • 701. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Front End Loader Helper - Residential Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 27 ©2011, Waste Management January 2011
  • 702. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Transfer/Tractor Trailer Driver Job Description Drives tractor-trailer hauling material from post collection processing plants (transfer stations, MRF’s, etc.) to landfills, other processing plants and shipping destinations. Trailers vary from box type, open tops, end dumps, to live/walking floors. Some units are emptied at landfills, and other destinations, on large tippers that lift the truck. Some drivers operate these tippers. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates hydraulic control levers while seated in cab for various reasons Operates hydraulic control levers while standing outside of vehicle for various reasons May operate hydraulic control levers inside the tipper Opens a variety of trailer doors by using levers, pins, latches, turn buckles, etc. Checks/fills fluid levels twice daily as part of pre/post trip inspections Fuels vehicle Walks to/from office to vehicle parking lot, at landfill around vehicle, at customer location Communicates via two-way radio with dispatch and co-workers Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Manually (or automatically) tarps loaded trailer for transport Cleans/shovels spillage at customer location Additional Tasks Personal Protective Equipment Page 28 ©2011, Waste Management January 2011
  • 703. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Transfer/Tractor Trailer Driver Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Cuts/Lacerations/Abrasion Opening doors Gloves, work boots s Compacting materials, falling and airborne debris Eye Injury when outside truck on Safety glasses route or at post collection facility Falling debris at post Overhead Hardhat collection facilities Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 29 ©2011, Waste Management January 2011
  • 704. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Driver Vacuum Truck (Port-o-Let®) Job Description Drives a vacuum truck and services portable toilets at various locations. A suction hose is used to transfer contents of holding tank to the truck. The driver also is responsible for cleaning and replenishing the toilets. The material is discharged at permitted facilities. Check All That Apply Tasks Conducts pre-trip/in-route/post trips inspections daily on vehicles driven Ascends/descends cab of vehicle throughout day for various reasons Operates vacuum pump Suctions out portable toilets Removes miscellaneous foreign objects Pumps water into buckets and adds cleaning agents Scrubs and cleans portable toilet Replaces deodorant solution into toilet basin Replaces tissues Inspects units and makes simple repairs Returns to facility and dumps waste into designated receptacle Paperwork daily Daily sequencing of route Drives to various customer locations, dump site, to/from office and route Transports individual units to customers Lowers unit to ground and moves it to proper location Additional Tasks Personal Protective Equipment Page 30 ©2011, Waste Management January 2011
  • 705. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Driver Vacuum Truck (Port-o-let®) Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots inspecting truck Biohazards Portable Toilets Chemical resistant gloves, goggles, boots Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Splashes as a result of Eye Injury Goggles collection / discharge. Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Outside of truck, high traffic areas, on route, at Traffic Exposure ANSI Class II high visibility clothing post collection facility and in yard Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 31 ©2011, Waste Management January 2011
  • 706. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Utility Maintenance Worker Job Description Performs non-mechanical maintenance such as cleaning, parts storage and retrieval, etc. Check All That Apply Tasks Maintains housekeeping in maintenance shops Containing and cleaning up spillage in shops Facility cleaning (break rooms, rest rooms) Operates fork trucks when indicated Use of hand and power tools Vehicle/Equipment washing Additional Tasks Personal Protective Equipment Page 32 ©2011, Waste Management January 2011
  • 707. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Utility Maintenance Worker Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure Gloves, work boots cleaning Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Working in shop or task Eye Injury Safety glasses specific Overhead Overhead hazards Hardhat Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Traffic Exposure Working in yard ANSI Class II high visibility clothing Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 33 ©2011, Waste Management January 2011
  • 708. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Washer Job Description Washes containers of various sizes and styles with pressure washer and deodorizes containers in preparation for customer use; organizes container storage area of yard Check All That Apply Tasks Operates Forklift to transport containers to/from wash area and storage yard Uses container tipper to turn containers for washing Washes containers (about 30 per day) with pressure washer (no soap) Reorganizes yard to separate full container from empty ones Stacks roller carts after washing for storage yard (stacks two carts high) Shovels excess waste into yard container from containers to be washed Cleans wash area of all excess waste that came out of containers Additional Tasks Personal Protective Equipment Page 34 ©2011, Waste Management January 2011
  • 709. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Washer Hazard Source Minimum Required Protection Hot Objects/Fluids while Burn Exposure inspecting and handling Gloves, work boots cleaning equipment Cuts/Lacerations/Abrasion Handling containers Gloves, work boots s Airborne debris from Eye Injury Goggles pressure washer Overhead Overhead hazard Hardhat Wet, uneven surfaces, Slips, Trips and Falls Boots, gloves obstacles Traffic Exposure In yard ANSI Class II high visibility clothing Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 35 ©2011, Waste Management January 2011
  • 710. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Maintenance Technician Job Performs servicing and repairs on company vehicles and equipment at facility; makes Description service calls to trucks in need of repairs at post collection facilities or on route Check All That Apply Tasks Changes and repairs tires Adjusts brakes and clutch Checks battery and starter system Repairs electrical wiring system Makes up and installs continuity cables Replaces wheel seals and bearings Replaces drive lines and U-joints Replaces air lines and brake diaphragms Renews hydraulic hoses Exchanges components Adjusts cycle speeds Tunes up and overhaul engines Analyzes, diagnoses, and repairs problems with fuel, air and electrical system Relines brakes Exchanges clutch and transmissions Exchange differentials Rebushes kingpins Repairs suspensions Rebuilds transmissions Tests, diagnoses, and repairs hydraulic systems Performs service calls to make repairs as needed on route or at landfill Welding Parts cleaning Use of various hand held and electrical tools Cleans up work area Paperwork Other miscellaneous maintenance tasks Additional Tasks Personal Protective Equipment Page 36 ©2011, Waste Management January 2011
  • 711. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Maintenance Technician Hazard Source Minimum Required Protection Burn Exposure Welding, Cutting, Hot Welding gloves, welding apron, welding Liquids, Hot Objects helmet, boots, coveralls Chemical Exposure Chemical use part of tasks Safety glasses, goggles or face shields, chemical resistant gloves, coveralls and respirators. Protection based upon task and MSDS. Cuts/Lacerations/Abrasion Working with tools on Gloves, work boots s equipment Extreme Cold LNG/CNG Fueling Cryogenic gloves, goggles, face shield, long sleeve shirt or overalls, Eye Injury Airborne debris Safety glasses, goggles or face shield Noise Operating tools, working Ear plugs, canal caps, ear muffs where required with metal Overhead Falling Debris, overhead Hard hat hazard in Shop or Yard. Slips, Trips and Falls Wet, uneven surfaces, Boots, gloves obstacles Traffic Exposure Outside of service truck on route, high traffic areas, at ANSI Class II high visibility clothing post collection facility and in yard Welding Fumes Welding When air testing indicates the need, a full or half face respirator with appropriate cartridges. Additional ventilation evaluations may be required. Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Personal Protective Equipment Page 37 ©2011, Waste Management January 2011
  • 712. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Shop Repair / Welder Job Description Repairs refuse containers in accordance with company specifications and work orders Check All That Apply Tasks Conducts pre/post-trip inspection on Forklift Transports containers to/from shop and yard via forklift Uses forklift for raising/holding, lowering containers for repair Repairs casters Repairs lock bars, pockets, rails, doors, walls, etc. of front load, rear load and roll-off containers. Repairs/replaces lids (plastic and occasionally metal lids) Patches damaged metal parts Repairs/replaces container bottoms Use of impact wrench to remove nuts and bolts on containers Uses portable grinders for grinding all surfaces to be welded Repairs containers by dismantling, straightening, reshaping, or assembling parts using cutting torch Shapes metal using, sledgehammer, steel power saw and power shears Transports and positions containers and repair parts by hand or with the use of a forklift truck, cranes, hoists, etc. Sets up equipment and welds parts using arc, C02, gas, or wire feed welding equipment Bolts, clamps, and tack-welds parts to secure in position for welding Sands containers using portable air sander Paints containers Uses various type electrical and hand tools Paperwork Occasionally performs repair work to containers at customer locations Occasionally performs welding tasks to repair damaged metal parts on vehicles Additional Tasks Personal Protective Equipment Page 38 ©2011, Waste Management January 2011
  • 713. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Container Shop Repair / Welder Hazard Source Minimum Required Protection Burn Exposure Welding, Cutting, Hot Welding gloves, welding apron, welding Liquids, Hot Objects helmet, boots, coveralls Chemical Exposure Chemical use part of tasks Safety glasses, goggles or face shields, chemical resistant gloves, coveralls and respirators. Protection based upon task and MSDS. Dust Particulate Exposure Resulting from grinding, Safety glasses. Nuisance dust mask available. sanding, etc. Respirator required when applicable. Eye Injury Airborne debris Safety glasses, goggles, face shield, welding helmet Noise Operating tools, working Ear plugs, canal caps, ear muffs where required with metal Overhead Falling Debris, overhead Hard hat hazard in Shop or Yard. Paint Spray Spray Painting Full and half face respirator when necessary Slips, Trips and Falls Wet, uneven surfaces, Boots and gloves obstacles Traffic Exposure Working at customer ANSI Class II high visibility clothing locations, on route or at post collection facility Welding Fumes Welding When air testing indicates the need, a full or half face respirator with appropriate cartridges. Additional ventilation evaluations may be required. Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 39 ©2011, Waste Management January 2011
  • 714. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Equipment Operator Job Description Drives/operates mobile equipment (e.g. forklifts, loaders, dozers, compactors, scrapers) to consolidate of Assessment/move waste/recyclable materials as well as landfill cover/construction materials (dirt, rock, etc.) Check All That Apply Tasks Ascends/descends cab of vehicle throughout day for various reasons Cleans out radiator as needed with compressed air Communicates via two-way radio with co-workers Conducts pre-trip/in-route/post trips inspections daily on vehicles driven When possible, visual inspection of waste to help ensure prohibited materials are not received Fuels equipment Operates controls, pedals and/or levers from inside of cab Paperwork daily Replaces equipment fluids as needed Walks to and from equipment Additional Tasks Personal Protective Equipment Page 40 ©2011, Waste Management January 2011
  • 715. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Equipment Operator Hazard Source Minimum Required Protection Burn Exposure Hot Objects/Fluids while Gloves, work boots inspecting equipment Cuts/Lacerations/Abrasion Incidental Gloves, work boots s Eye Injury Airborne debris Safety glasses Foot puncture Walking at Post Collection Puncture Resistant Boots Facilities Overhead Falling Debris Hard hat when outside of cab or operating open cab equipment Slips, Trips and Falls Wet, uneven surfaces, Boots, gloves obstacles Traffic Exposure Vehicular traffic at Post ANSI Class II high visibility clothing Collection facilities Additional Hazards Noise from Equipment exceeding threshold levels Noise Exposure outlined in Hearing Ear Plugs/Ear Muffs in required Equipment Conservation Program Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 41 ©2011, Waste Management January 2011
  • 716. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Laborer Job Description Performs routine cleanup and yard maintenance Check All That Apply Tasks Clean roadways Pick up litter as assigned Respond to specific labor needs Perform weed abatement/landscaping as indicated Lift and stack items Additional Tasks Personal Protective Equipment Page 42 ©2011, Waste Management January 2011
  • 717. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Laborer Hazard Source Minimum Required Protection Cuts/Lacerations/Abrasion Material handling Gloves, work boots s Eye Injury Airborne debris Safety glasses, or goggles, or face shield Foot puncture Walking at Post Collection Puncture Resistant Boots Facilities Overhead Falling Debris at post Hard hat collection facility Slips, Trips and Falls Wet, uneven surfaces, Boots, gloves obstacles Traffic Exposure Vehicular traffic at Post ANSI Class II high visibility clothing Collection facilities Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 43 ©2011, Waste Management January 2011
  • 718. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Sorter Job Description Sorts recyclable materials into applicable components Check All That Apply Tasks Sorts materials off of conveyor or on ground Places materials in appropriate chute or receptacle Operates conveying equipment Operates bailing equipment Maintains housekeeping in active area Additional Tasks Personal Protective Equipment Page 44 ©2011, Waste Management January 2011
  • 719. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Sorter Hazard Source Minimum Required Protection Cuts/Lacerations/Abrasion Material handling Gloves and work boots s Eye Injury Airborne debris Safety glasses Noise Sorting Equipment Ear plugs or canal caps Overhead Falling Debris Hard hat Slips, Trips and Falls Wet, uneven surfaces, Boots, gloves obstacles Traffic Exposure Truck and forklift traffic at ANSI Class II high visibility clothing facility. Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 45 ©2011, Waste Management January 2011
  • 720. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Traffic Director Job Performs traffic control at landfills, transfer stations and waste/recyclable consolidation Description facilities Check All That Apply Tasks Interacts with truck drivers and equipment operators to direct trucks into proper areas Collects unloading tickets (if necessary) From a protected area, directs trucks to unloading positions based on size and content of loads Paperwork Assists in keeping area clean Monitors the activity of heavy equipment working in immediate area Watches that no prohibited materials are offloaded in non-restricted areas Communicates with management, equipment operators and other site personnel with 2 way radios Walks to and from working area Additional Tasks Personal Protective Equipment Page 46 ©2011, Waste Management January 2011
  • 721. Personal Protective Equipment Program CERTIFICATION OF HAZARD ASSESSMENT Job Title: Traffic Director Hazard Source Minimum Required Protection Eye Injury Airborne debris Safety glasses Foot puncture Walking at Post Collection Puncture Resistant Boots Facilities Overhead Falling debris at post Hardhat collection facilities Slips, Trips and Falls Wet, uneven surfaces, Boots, gloves obstacles Traffic Exposure Vehicular traffic at Post ANSI Class II high visibility clothing Collection facilities Additional Hazards Tasks or hazards not listed must be added to this form. This is to certify that I have performed a hazard assessment at this workplace as required by 29CFR1910.132(d), through an observation of persons performing the above job descriptions. Certified by Title Date of Assessment Site Name Site Address Personal Protective Equipment Page 47 ©2011, Waste Management January 2011
  • 722.  
  • 723. Confined Space Program Program: Confined Space Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 PURPOSE To describe the requirements to identify, evaluate and plan for the safe entry into confined spaces and permit-required confined spaces. REQUIREMENTS 1. Identify and prepare a written list of all confined spaces within your operations. 2. If employees have access to confined spaces, implement the attached confined space program. Complete the facility-specific information. 3. Any employee, who enters the permit space, or that employee’s authorized representative, shall be provided any opportunity to observe all pre-entry and any subsequent testing or monitoring of permit spaces. 4. Using the attached evaluation form, determine which type of confined spaces and entry conditions constitute permit-required spaces. 5. Update the list of confined spaces on an annual basis and when a new confined space is introduced into the operations. Perform an evaluation for new confined spaces. 6. Provide awareness training to all employees about the hazards associated with confined spaces and to stay out of them unless trained as entrants. 7. Provide detailed training for employees and supervisors (entrants, attendants, and entry supervisors) who may be involved in permit-required confined space entries. 8. Evaluate a prospective rescuer’s ability to respond to a rescue summons in a timely manner, considering the hazard(s) identified. 9. Ensure that rescue personnel receive initial and annual training, including drills. PERMIT-CONFINED SPACES 1. Label all permit-required confined spaces. An alternative means of communicating the danger and identifying confined spaces may be used if labeling is impossible or impractical. Document the rationale for utilizing the alternative methodology. 2. Develop a system to restrict entry into permit- required confined spaces. 3. Utilize the permit for all permit-required confined space entries. Confined Space Page 1 ©2011, Waste Management January 2011
  • 724. CONFINED SPACE PROGRAM (continued) 4. For locations where permit confined spaces must be entered, ensure atmospheric testing equipment is available, maintained, and used. Note: Under certain circumstances ventilation may allow reclassification of a permit space to a non-permit required confined space. 5. Make emergency rescue personnel (or local emergency responders) available during permit- required space entry. GENERAL A confined space is any space that is large enough and configured so that an employee can bodily enter and perform assigned work, has limited means for entry or exit, and is not designed for continuous employee occupancy. Examples are pump-pits, sewer manholes, tanker trucks and storage tanks. There are two types of confined spaces – permit required and non-permit required. All confined spaces are considered to be permit required confined spaces until evaluations determine that the space is a non-permit-required space. A non-permit required confined space means a confined space that does not contain or have the potential to contain any hazard capable of causing death or serious physical harm. Under normal solid waste collection activities, we have determined that there is no potential for a hazardous atmosphere inside truck bodies. When the physical hazards have been locked out following proper procedures, the truck body may then be considered a non-permit required confined space and entered without a permit. In addition, by blocking open a truck body tailgate for entry and exit, the truck body may then be configured so that it no longer is considered a confined space. A permit-required confined space is a confined space that has one or more of the following characteristics: (1) Contains or has the potential to contain a hazardous atmosphere; (2) Contains a material that has the potential for engulfing an entrant; (3) Has an internal configuration such that an entrant could be trapped by inwardly converging walls or by a floor which slopes downward and tapers to a smaller cross-section, or; (4) Contains any other recognized serious safety or health hazard, (5) has the potential to contain (1) through (4) and has not be evaluated. A permit-required (attendant-required) confined space is a space that has been evaluated and engineering controls or lockout could not eliminate the hazard. It is the policy of Waimanalo Gulch Sanitary Landfill employees to avoid entry into confined spaces whenever possible. Employees follow this program if confined spaces must be entered. Confined Space Page 2 ©2011, Waste Management January 2011
  • 725. CONFINED SPACE PROGRAM (continued) CORE PROGRAM When these hazards are not completely controlled or eliminated prior to entry, an attendant is required before entry. Two employees are needed for entry into a permit-required confined space (also called an attendant-required confined space), one to enter the space (Entrant), and one to stay outside and watch over the safety of the entrant (Attendant). Responsibility Management is responsible for administering the confined space entry program. This person identifies confined spaces, coordinates all training, and ensures that the program is implemented. The confined space entry program administrator appoints an individual to be an Entry Supervisor. The Entry Supervisor approves, issues, and signs all entry permits, authorizes entry into permit areas, identifies additional confined spaces, and maintains documentation of all entries. The Entry Supervisor may also act as an attendant for employees making entry into confined spaces. Management is responsible for conducting work area surveys to identify potential confined spaces, ensuring permit-required confined spaces are labeled, and ensuring the program is implemented for all work in confined spaces. Attendants are responsible for maintaining constant contact with persons in the confined space, and are also responsible for calling for help. Emergency rescue team is responsible for being in a standby condition when notified by the entry supervisor that a confined space entry is underway. In the event the rescue team must respond to another call or cannot be on standby, the rescue team must inform the entry supervisor. The supervisor shall terminate the confined space entry until the emergency rescue team is available. Employees who are trained and authorized may enter confined spaces when the requirements of this program have been satisfied. Employees who are trained as entry supervisors or attendants can also perform this role. Identify and Post Signs on Confined Spaces Management or management designees identify and evaluate confined spaces in work areas. See the Appendices for a list of confined spaces at the facility. Post signs or apply labels identifying confined spaces at the entry points for each space. Confined Space Page 3 ©2011, Waste Management January 2011
  • 726. CONFINED SPACE PROGRAM (continued) Identify the Confined Space and the Work to be done. Determine whether it is safe to remove the cover to the confined space. If required, lockout and tagout sources of hazardous energy into the space using the facility lockout and tagout program. If possible, test the initial air before removing the cover. Where practical, the temperature and pressure inside the confined space should approximate the temperature and pressure outside the confined space. Excess pressure can blow the cover off and result in splash or injury. Prior to the entry, put the following information on the permit: The confined space to be entered The purpose of the entry Hazardous materials to be taken into or hazardous work to be done in the space The length of time the permit is in effect. Note: It is very important to review the hazardous materials taken into or hazardous work done in the confined space. Atmospheric and physical hazards can arise from the work inside the confined space. As an example, chemical solvent vapor concentration could increase and cause someone to pass out and welding could produce a hazardous atmosphere or fire hazard. Identify Potential Atmospheric and Physical Hazards Evaluate the confined space for internal and external hazards. Internal hazards include both atmospheric hazards (unsafe or lack of air) and physical hazards. Atmospheric hazards may include: Hydrogen sulfide, methane, and oxygen deficiency from decaying waste, sewage, or stagnant water Air contaminants from chemicals used or stored in the space Excess oxygen (makes things burn easily) Flammable atmospheres containing methane, propane, or other explosive gases Combustion by-products like carbon monoxide Explosive dust atmospheres Acceptable levels of atmospheric hazards are listed on the permit. Do not enter confined spaces where air quality is different from normal air (see permit) without first investigating the cause of the problem. Physical hazards in confined spaces may include: Mechanical hazards from fans and other moving parts Engulfment, which is being trapped by a liquid or solid material Confined Space Page 4 ©2011, Waste Management January 2011
  • 727. CONFINED SPACE PROGRAM (continued) Internal structures that could trap an entrant or impair his/her ability to exit the space quickly Electrical hazards from unguarded conductors or power sources Excessive heat or cold Entry Procedures The confined space entry procedures are designed to reduce or eliminate the hazards and if at all possible, reclassify the permit space to a non-permit space. If the space cannot be reclassified to a non-permit space, the permit identifies those items, conditions, and controls necessary to make the entry safe. The basic process for entry into confined spaces is to: Identify the confined space and the work to be done. Evaluate the feasibility of performing the work from outside the confined space. If the confined space must be entered, determine if the space is a permit required or non- permit required confined space by identifying potential atmospheric and physical hazards. Test the space for atmospheric hazards to determine the classification of the space. Also test before entry and regularly during entry. Make the space safe for entry by eliminating atmospheric and physical hazards. Certify control measures taken, classify the space based on whether hazards have been eliminated, and post the permit if a permit required space. Ensure additional controls for attendant-required spaces. Authorize entry by Entry Supervisor. Do the work safely and, End the permit if applicable. These steps are also on the permit. The rest of this program explains each of these steps. Permit vs. Non-Permit Confined Spaces If any hazards remain that you cannot eliminate or control by ventilation alone, or if work releases additional hazards, the space is classified as a permit-required confined space and requires an Attendant. Provisions for rescue are also necessary. If hazards remain, only authorized and trained Entrants can enter the Attendant-required confined space. The Entry Supervisor lists the Entrants on the Confined Space Entry Authorization Permit. Confined Space Page 5 ©2011, Waste Management January 2011
  • 728. CONFINED SPACE PROGRAM (continued) The Entry Supervisor must inform employees of the hazards present. The Entry Supervisors briefs the Entrant(s) and Attendant on planned emergency rescue methods and verifies that rescue equipment, procedures, and rescue personnel are available. Entrant(s) must read the permit and sign the permit before entry and entrants must evacuate the confined space when: Atmospheric monitoring alarms sound Respirators fail Forced-air ventilation stops The Attendant tells them to leave the space The Attendant informs them of problems Entrants must promptly begin self-rescue when any of the above occurs. Test the Space for Atmospheric Hazards before Entry Without entering the confined space, test in the following order the internal atmosphere for the presence of: Oxygen Flammable gas Toxic substances (what to test for depends on the hazard assessment) For each atmospheric test, monitor the space at different levels and in any unusual configurations. The shape of a space may trap gases in unexpected areas. Record test results on the permit. As part of the testing process, the Entry Supervisor must identify safe conditions for entry. Hazardous conditions that prohibit entry include: An oxygen-deficient (less than 19.5%) atmosphere, which can cause suffocation. An oxygen-enriched (more than 23.5%) atmosphere, which can cause an extreme fire hazard. A potentially explosive atmosphere caused by the presence of combustible gases, liquids, vapors, or dust at greater that 10% of their lower flammable limit (LFL). A concentration of any hazardous substance above its OSHA permissible exposure limit (PEL) or above the exposure limit given on the MSDS. The presence of a physical hazard that is not controlled and immediately dangerous to life or health (IDLH) such as a liquid or solid that may engulf, exposed conductors that may electrocute, or uncontrolled energy that may escape. Note: Only qualified and authorized individuals can operate monitoring instruments. Regularly field-calibrate the instruments. Follow the manufacturers written operating instructions and calibration procedures. Confined Space Page 6 ©2011, Waste Management January 2011
  • 729. CONFINED SPACE PROGRAM (continued) Make Space Safe For Entry Do not enter the confined space if there is an uncontrolled hazardous atmosphere or physical hazard. If any readings are out of the normal range, identify the cause and perform corrective actions before entry. Perform tests again following the completion of control measure implementation. Before entry, control or isolate all energy sources. Use the facility lockout and tagout program. Verify lockout by testing. Drain, pump out, or otherwise empty the material in the space before entering. Use the best and most practical method to clean it. Do not use protective clothing and respiratory protection as substitutes for cleaning and ventilating the confined space. Where practical, use forced-air ventilation whenever employees are inside of any confined space. Use only clean air supplies for continuous forced-air ventilation so you do not increase the hazards in the confined space. Do not contaminate the air supply with engine exhaust. Never use oxygen to purge or ventilate any confined space. Injury or death may occur from the highly explosive atmosphere generated. Other important control measures prior to entry include: Briefing entrants on hazards and control measures. Notifying contractors of the permit space and hazardous conditions. Testing and verifying lockout and tagout of known and potential hazardous energy sources. Certify Control Measures, Obtain Approval and Post Permit After certification by the Entry Supervisor that conditions are now acceptable, it is safe to enter the hazard-controlled confined space. Post the permit as a certification to those entering the confined space that the hazards have been eliminated. Normal work activities can proceed as long as there are no hazards present in the space. Do not take hazardous materials into the confined space or carry out welding activities or open flame work that could introduce new hazards or cause existing hazards to intensify. Conduct continuous air monitoring while an Entrant is in any confined space. Confined Space Page 7 ©2011, Waste Management January 2011
  • 730. CONFINED SPACE PROGRAM (continued) Allow Entry after Supervisor Reviews and Approves Permit The Entry Supervisor authorizes entry into the confined space only after all safeguards have been executed. The Entry Supervisor must review the permit before allowing employees into the permit-required confined space. In the review, the Entry Supervisor must: Identify the confined space and work to be done. Anticipate and protect against hazards that the work might create (solvent use, hot work, and paint/coating removal or application). Identify the permit-required confined space hazards. Determine and identify on the permit the actual and potential hazards of the entry. Test the atmosphere in the space before initial entry and ensure continuous monitoring. Ensure that a safe atmosphere is maintained inside the space by testing and inspecting. Make the space safe before entry. Ensure control measures are taken to reduce and eliminate atmospheric and physical hazards. Certify the control measures taken and classify the space. Classify the space as hazard-controlled, forced-ventilation, or attendant-required. List the authorized Entrants. Tell the Entrants of the hazards involved and precautions to follow before entry. List the authorized Attendant(s). Ensure the Attendant knows the work, can summon help, and can communicate with the Entrants inside. Ensure the availability of an emergency rescue team. Verify that rescue services and an operating means for summoning them are available. Obtain the equipment required for entry and safe work practices. Ensure necessary equipment and work practices are used to maintain the safe conditions the permit requires. Issue and post a confined space entry permit at the entrance of the confined space before allowing Entrants to enter the space. Notify the emergency rescue team when the confined space entry is completed. End the Entry The Entry Supervisor ends the entry upon work completion, if unsafe conditions are detected, or an emergency rescue team is unavailable. Upon work completion, the Entrant(s), retrieves tools or equipment and cleans up the space as necessary before ending the entry. Check to make sure no one is in the confined space and all measures required to bring the confined space back to normal service have been performed and notifies the Entry Supervisor. Confined Space Page 8 ©2011, Waste Management January 2011
  • 731. CONFINED SPACE PROGRAM (continued) Reversing lockout or other safety procedures may be necessary. This may include: Unblocking mechanical parts so they can move freely. Securing the hatch or manhole cover. Removing blinds from lines and pipes. Removing locks and tags from energy sources. Testing to be sure sources are working. After ensuring the space has been returned to the proper conditions, the Entry Leader: Removes the permit. Signs and dates the permit. Documents problems encountered during the entry and provides suggestions to avoid these problems. Returns the completed permit to the Confined Space Program Administrator. Notifies the emergency rescue team that the confined space entry has been completed. Perform Work Safely in Hazard-Controlled and Forced Ventilation Spaces The Entry Supervisor may limit the number of Entrants and restrict activities within the confined space in order to maintain the initial level of safety. The Entrant(s) must immediately notify the Entry Supervisor and leave the confined space if the continuous air monitoring detects a hazard or if additional hazards are discovered or created, or if the ventilator stops operating. If any of these occur, treat the confined space as a permit-required confined space until safe conditions can be restored and are documented on the permit. Welding in Confined Spaces You must use continuous forced-air ventilation whenever you weld or burn inside a permit required confined space or use other oxygen-consuming equipment. You must also complete a hot work permit. When you use continuous forced-air ventilation, begin ventilation before entering and direct it to the work area. Ventilating must continue until all employees leave the confined space. Confined Space Page 9 ©2011, Waste Management January 2011
  • 732. CONFINED SPACE PROGRAM (continued) Provide an Attendant During Entry An Attendant stays outside the entrance to the confined space and performs no other tasks whenever Entrant(s) is inside an attendant-required confined space. The Entry Supervisor lists the Attendant on the Confined Space Entry Authorization Permit. Attendants must read and sign the permit. Entrants and Attendants may rotate duties if trained in both designations. The Entry Supervisor may also be the Attendant. The Attendant’s duties include: Establishing and maintaining communication with the Entrant(s) at all times. Monitoring the Entrant(s) for signs of illness, overexposure, or other hazardous conditions. Informing Entrant(s) of changes in hazardous conditions so they can leave. Having a means to summon help in an emergency. Calling the rescue team when self-rescue by the Entrant(s) is not possible. Calling the appropriate Entry Supervisor to announce the location and the extent of the problem. The Attendant and/or Entry Supervisor directs the rescue team to the confined space location. Never entering the confined space for any reason. Informing the rescue team of the hazards present. Provide Personal Protective Equipment, Lifeline and Harness A non-entry rescue is the safest and fastest method for Entrant rescue because the rescuer does not enter the confined space. To perform a non-entry rescue, attach a body harness and a retrieval line to the Entrant(s) before he or she enters the confined space. Use a mechanical winch to raise an Entrant out of the confined space. Note: Although the Attendant is not allowed to enter the confined space, he or she can perform a non-entry rescue. Notify Contractors Give contractors a copy of this program and hold them responsible for following an equivalent program of their own. Ensure that contractors will not enter confined spaces without proper precautions, or create confined space hazards for Waimanalo Gulch Sanitary Landfill employees. Confined Space Page 10 ©2011, Waste Management January 2011
  • 733. CONFINED SPACE PROGRAM (continued) Train Entrants, Attendants, and Entry Supervisors Waimanalo Gulch Sanitary Landfill ensures that all affected employees receive training. Employees who do not enter confined spaces are trained to identify confined spaces and stay out of them unless the hazards have been eliminated. Employees receive training prior to assignment as Attendants, Entrants, and Entry Supervisors. Training provides the understanding, knowledge, and skills necessary for the safe performance of the duties assigned. Waimanalo Gulch Sanitary Landfill provides training at the following times: Before the employee is first assigned confined space duties. Whenever there is reason to believe there are inadequacies in the employee’s knowledge. Waimanalo Gulch Sanitary Landfill documents the training using Safety Training Attendance Form. Documentation includes: The date of training. A brief description of the material covered. The names and signatures of the employees trained. The name of the individual conducting the training. Responsibility Identify the name and the title of the person responsible for the facility confined space entry program and reviewing and updating the confined space entry program annually: Name: Joseph Whelan Title: Site Manager List all confined spaces present at the facility including their locations: WGSL Flare Condensate Tanks Leachate Tanks Wastewater Tank Fuel Tanks Petroleum Tanks Confined Space Page 11 ©2011, Waste Management January 2011
  • 734. CONFINED SPACE PROGRAM (continued) Briefly describe criteria used to determine if a confined space did not require permit for entry spaces at the facility: WM only uses contractors to perform confined space entry. Contractors will determine if confined spaces are permit required or non-permit required confined space. Briefly describe the procedures followed to assure that the non-permit spaces will remain non- permit spaces during entry procedure: WM only uses contractors to perform confined space entry. Identify the name(s) and title(s) of the person(s) who perform the above hazardous assessments: Various contractors with confined space entry experience. The remainder of this plan must be completed for facilities with permit required confined space only. Activities may, however, change the status of the space (permit versus non- permit). Acceptable Entry Conditions Briefly describe the tests performed (or data available) to ensure that conditions in confined spaces are acceptable for entry: WM only uses contractors to perform confined space entry. Contractors will determine if confined spaces are permit required or non-permit required confined space. Confined Space Page 12 ©2011, Waste Management January 2011
  • 735. CONFINED SPACE PROGRAM (continued) Identification and Labeling of Confined Spaces Describe the signs, labels or markings used to identify permit required confined spaces at the facility: “Confined Space” signs are posted on confined spaces. All confined spaces are further evaluated by the contractor to determine if the space is permit required or non-permit required. Ventilation Identify the ventilation equipment used at the facility: Contractor to provide. Air Monitoring Identify any facility-specific contaminants that are monitored in confined spaces: Contractor to determine based on actual confined space. List the monitor(s) that must be present in confined spaces when Authorized Entrants occupy them: Contractor to provide own certified and calibrated monitoring device. Monitor:N/A Model:N/A Calibration Date:N/A Confined Space Page 13 ©2011, Waste Management January 2011
  • 736. CONFINED SPACE PROGRAM (continued) Confined Space Page 14 ©2011, Waste Management January 2011
  • 737. CONFINED SPACE PROGRAM (continued) Personnel Roles Identify the titles used for confined space personnel if different from those used to in this program: Contractor to provide. Confined Space Entry Permit Attach the confined space entry permit used at the facility if different from the one provided in the Appendix. Emergency Procedures Briefly describe emergency procedures followed at the facility for confined space accidents, injuries or illnesses: All accidents or illnesses should be reported to a supervisor. Supervisor will determine what if any first aid is necessary. If medical attention is necessary, supervisor or others will call ambulance (911). If the emergency rescue team is contacted by phone, include the phone number dialed to reach the team: 911 Confined Space Page 15 ©2011, Waste Management January 2011
  • 738. CONFINED SPACE PROGRAM (continued) Training Briefly describe the topics covered and materials used to train: To be determined by confined space entry contractor. Briefly describe simulated rescues performed as part of training for all team members: To be performed by confined space contractor. Contractor Provisions Describe any facility-specific procedures or policies regarding contractors and leased employees who perform work in confined spaces at the facility: Contractor must have health and safety plan that includes confined space training. Confined Space Page 16 ©2011, Waste Management January 2011
  • 739. CONFINED SPACE PROGRAM (continued) List all printed materials provided to contractors or leased employees who performed confined space entry at the facility: Copy of this program for contractor’s review. Recordkeeping Location of the confined space permit file at facility: Contractors retain records of confined space entry. Location of training records for the confined space program at the facility: File cabinet on second floor of office. Contractors keep own confined space training records. DEFINITIONS Acceptable entry conditions: The conditions that must exist in a confined space to allow entry and to ensure that employees involved in a permit-required confined space entry can safely enter into and work within the space. Forced-Ventilation Confined Space: A confined space where the only hazard remaining is one that can be controlled by forced ventilation. Non-Permit Confined Space: A confined space where all the hazards are controlled prior to entry, and none are brought into the space. Combustible Dust: A dust capable of undergoing combustion or burning when subjected to a source of ignition. Engulfment: the surrounding and effective capture of a person by a liquid or finely divided (flow able) solid substance that can be aspirated to cause death by filling or plugging the respiratory system or that can exert enough force on the body to cause death by strangulation, constriction, or crushing. Confined Space Page 17 ©2011, Waste Management January 2011
  • 740. CONFINED SPACE PROGRAM (continued) Entry: The action by which a person passes through an opening into a permit-required confined space. Entry includes work activities in the space and is considered to have occurred as soon as any part of the Entrant’s body breaks the plane of an opening into the confined space. Entry Permit: The written or printed document that the employer provides which contains the necessary information to allow and control entry into a permit space. Hot Work: Any work involving burning, welding, riveting, or similar fire-producing operations, as well as work which produces a source of ignition, such as drilling, abrasive blasting, and space heating. Hazardous Atmosphere: An atmosphere that may expose employees to the risk of death, incapacitation, impairment or ability to self-rescue injury, or acute illness from one or more of the following causes: A flammable atmosphere in excess of 10% of the LFL (lower flammable limit) for the material. Airborne combustible dust at a concentration that meets or exceeds its LFL. Atmospheric oxygen concentration below 19.5% or above 23.5%. Exposure to an atmospheric concentration of any substance that a dose or PEL is published by the Occupational Safety and Health Administration (OSHA) that may result in employee exposure to the substance in excess of that dose or PEL. Any other atmospheric condition that is immediately dangerous to life or health. Isolation: A process whereby the confined space is removed from service and completely protected against the inadvertent release of material and hazardous energy by the following: blanking off (skillet type metal blank between flanges), misaligning sections of all lines and pipes, locking out all sources of power, and blocking or disconnecting all mechanical linkages. Lower Flammable Limit (LFL): The lower limit of flammability of a gas or vapor at ordinary ambient temperature expressed in a percentage of the gas or vapor in air by volume. Oxygen Deficiency: Refers to an atmosphere containing less than 19.5% oxygen. Oxygen Enriched: An atmosphere containing an oxygen concentration greater than 23.5%. Threshold Limit Value (TLV): The airborne concentration of a substance established by the American Conference of Governmental Hygienists (ACGIH) representing a condition under which it is believed that nearly all workers may be repeatedly exposed without adverse effect. Confined Space Page 18 ©2011, Waste Management January 2011
  • 741. CONFINED SPACE PROGRAM (continued) District WAIMANALO GULCH SANITARY LANDFILL Comb. by Decay Pressure/ Permit Not Location / Description Products Chemical Mechanical Engulfment Entrapment Electrical Waste Heat Other Required Required Confined Space Page 19 ©2011, Waste Management January 2011
  • 743. PERMIT-REQUIRED CONFINED SPACE DETERMINATION WORKSHEET Space Being Evaluated: ___________________________________________________ Work To Be Performed: ___________________________________________________ Step 1. Is the space… Yes No 1) Large enough for a body to enter 2) Limited or restricted means of entry or exit 3) Not designated for continuous occupancy If the answer to ALL three questions above is “Yes,” it is a “Confined Space” - Go to Step 2. If the answer to any of the questions is “No,” it is not a confined space – Proceed to Step 3, Sign, Date and Keep On File. Step 2. Does the confined space have one or more of the following: Yes No 1) Contains or has a potential to contain hazardous atmosphere (OR) a) 10% LEL (Lower Explosion Limit) – Flammable/Combustible gasses b) Dust Concentrations > LEL Dust c) O2 level is > 19.5% or < 23.5% d) OSHA PEL (Permissible Exposure Limit) Exceeded e) IDLH (Immediately-Dangerous-to-life-or-Health) Atmosphere (See Definitions for further detail) 2) Engulfment (completely surrounded by)examples – cave-in, drowning, buried 3) Trapped or asphyxiated by inwardly converging walls 4) Is there a serious safety of health hazard that cannot be completely eliminated through lockout/tagout? Attach Lockout/Tagout Procedure to this document. If the answer to ANY of the above questions in Step 2 is “Yes,” the space is considered to be a “Permit Required Confined Space.” Contact your Regional or Corporate Safety Manager to discuss requirements for entry into the space. If the answer to ALL of the questions is “no,” the space is considered to be a “Confined Space” only. In either case, proceed to Step 3 of the Worksheet, Sign, Date, Keep On File. Step 3. Check the appropriate box Not A Confined Space Confined Space Permit-Required Space ____________________________ ________________________ _____________ Signature Print Name Date Comments:____________________________________________________ __________________________________________________________ __________________________________________________________ __________________________________________________________ __________________________________________________________ Confined Space Page 21 ©2011, Waste Management January 2011
  • 744. CONFINED SPACE ENTRY PERMIT PERMIT NO. 1. Identify Space And Work To Be Done Space to Be Entered Location/Building Hazardous Materials to be Taken Into or Hazardous Work to Be Done in Space Purpose of Entry Authorization Duration From To From To of Permit Date: Time: 2. Identify Permit Space Hazards 4. Make Space Before Entry (Indicate Specific Hazards Which May be Present) (Check After Steps Have Been Taken) Unsafe to Remove Cover, Excess Pressure Notify Affected Department of Service Excess Heat Interruption Oxygen Deficiency (Less than 19.5%) Isolation Methods Oxygen Enrichment (Greater than 23.5%) Blank/Blind Clearance Procedure Flammable Gasses or Vapors Inert Purge/Clean (Greater than 10% of LEL) Lockout/Tagout Airborne Combustible Dust Other: Atmospheric Test (Greater than 10% of LEL) Continuous Barriers Toxic Gases or Vapors (Greater than PEL) Ventilation Mechanical Hazards Electrical Shock Materials Harmful to Skin Personal Awareness Engulfment, Falling Slag Pre-entry Briefing on Specific Hazards, Control Other: Methods and Emergency Action Plan Notify Contractors of Permit and Hazard Conditions Test/Verify Hazard Energy Control Other Additional Permits Required and/or Attached Hot work Other 3. TEST SPACE BEFORE INITIAL ENTRY & REGULARLY THEREAFTER (And Before Open Flame Work) Acceptable Entry Initial Test Result Result Material Normal Air Conditions : AM/PM : AM/PM : AM/PM Oxygen-min/max 20.9 > 19.5% < 23.5% _________ flammability 0 < 10% LEL/LFL _________ Hydrogen Sulfide 0 < 10 ppm _________ Carbon monoxide 0 < 50 ppm _________ Chlorine 0 < 0.5 ppm _________ Sulfur dioxide 0 < 2 ppm _________ Other (Specify) _________ Tester Initials _________ Always investigate before entry if conditions do not match normal air. 5. Certify Control Measures Taken, Classify Space, And Post Permit Low Hazard – All hazards are eliminated; none to be released by work. Follow basic safety precautions for the work. Ventilation Controlled – Only environmental hazards remain or will be released by work, which are controllable by ventilation. Ventilate before and during entry, with regular tests to ensure safety of air in the space. Attendant Required – Atmospheric and/or physical hazard remains. SKIP SECTIONS 6 & 7 BELOW; GO TO PAGE 2 AND COMPLETE Confined Space Page 22 ©2011, Waste Management January 2011
  • 745. Entry Leader Printed Name Date Entry Leader Signature 6. Authorization By Entry Supervisor To Enter Reclassified Nonpermit-Required Space I certify that all required precautions have been taken and necessary equipment is provided for safe entry and work in this confined space, and that the space is not attendant-required. Printed Name Date Signature 7. End Entry (For All Spaces) I have checked the space to make sure no one is in it, and all measures required to return it back to normal service have been performed. I authorize the return of this space to normal service. Problems That Occurred Suggestions Entry Supervisor Printed Name Date Entry Supervisor Signature THIS PERMIT MUST BE POSTED AT SPACE ENTRANCE PERMIT GOOD ONLY FOR THE DURATION OF THE JOB NO LIMIT ON HAZARD-CONTROLLED OR FORCED-VENTILATION SPACE UNLESS HAZARDS CHANGE CHECK BEFORE ENTRY 8. List/Signature Of Authorized Entrants (List by Name or Attach Roster) 9. List/Signature of Authorized Attendants (List by Name) 10. Ensure Emergency Rescue Available Control Room Notified Prior to Entry (Plants) Rescue Phone Number Method of Contact Confined Space Page 23 ©2011, Waste Management January 2011
  • 746. 11. Authorization by Entry Supervisor to Enter Attendant-Required Space I certify that all required precautions have been taken and necessary equipment is provided for safe entry and work in this confined space, and that the space is not attendant-required. Printed Name Date Signature 12. Obtain Equipment Required for Entry and Work Establish Communication Procedures to be Used by Attendants and Entrants Specify as Required: Personal Protective Equipment Continuous or Period Atmospheric Testing/Monitoring Respiratory Protection Equipment Rescue Equipment Other 13. End Entry (For All Spaces) I have checked the space to make sure no one is in it, and all measures required to return it back to normal service have been performed. I authorize the return of this space to normal service. Problems that Occurred Suggestions Entry Supervisor Printed Name Date Signature THIS PERMIT MUST BE POSTED AT SPACE ENTRANCE PERMIT GOOD ONLY FOR THE DURATION OF THE JOB NO LIMIT ON HAZARD-CONTROLLED OR VENTILATION-VENTILATION SPACE UNLESS HAZARDS CHANGE CHECK BEFORE ENTRY Confined Space Page 24 ©2011, Waste Management January 2011
  • 747. SUBSTANCE ABUSE PROGRAM FOR COMPANY EMPLOYEES AND CANDIDATES FOR EMPLOYMENT
  • 748. CONTENTS Page Drug and Alcohol Policy Statement ................................................................................... 1 Introduction ...............................................................................................................1 Substance Abuse Policy .............................................................................................. 1 Preventing Substance Abuse ....................................................................................... 4 Where to get Help ...................................................................................................... 6 Summary.................................................................................................................... 6 Drug Testing Policy for All Candidates ..............................................................................8 Policy Statement ........................................................................................................8 Drug Testing ..............................................................................................................8 Withdrawal of Job Offer ............................................................................................. 9 Drug and Alcohol Testing Policy for Employees in DOT-Regulated Positions................. 10 Policy Statement ...................................................................................................... 10 DOT- Covered Employees ....................................................................................... 10 Prohibited Conduct .................................................................................................. 11 Drug and Alcohol Testing ........................................................................................ 11 Refusal To Test ........................................................................................................ 14 Consequences of a POSITIVE Drug or Alcohol Test ............................................... 14 Drug and Alcohol Testing Policy for Employees in Non-DOT Positions ......................... 17 Policy Statement ...................................................................................................... 17 Drug and Alcohol Testing ........................................................................................ 17 Refusal to Test ......................................................................................................... 19 Consequences of a POSITIVE Drug or Alcohol Test ............................................... 19 Adulterated or Substituted Results ........................................................................... 20 Definitions ....................................................................................................................... 22 Appendix A: Non-DOT Safety Sensitive Positions Appendix B: Physician Statement Regarding Prescription Medication Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates for E mployment Revised September 2008 Page i
  • 749. DRUG AND ALCOHOL POLICY STATEMENT INTRODUCTION Waste Management (WM or Company) is committed to providing employees with a safe and healthy work environment. To ensure safety for employees, customers and the communities in which it operates, WM has taken a zero tolerance approach to substance abuse. Substance abuse Increases the risk of workplace injuries and incidents Affects the health and well being of the user Lowers productivity and quality WM uses the federal drug-testing model for its Substance Abuse Program. This federal drug testing model is detailed in 49 CFR, Parts 40 and 382. Some states or locales may have certain limits on drug and/or alcohol testing not covered by federal drug testing policy. Where needed, this policy will be changed as required by local and/or state laws. W AST E M A N A G E M E N T IS C O M M I T T E D T O M A IN T A I N I N G A W O R K P L A C E T H A T IS F R E E F R O M T H E I N F L U E N C E O F D R U GS A N D A L C O H O L A B USE. SUBSTANCE No person may ABUSE POLICY use transfer sell possess make consume handle inhale purchase transport or otherwise be involved with drugs or alcohol while on WM property or while operating WM vehicles. controlled substances illegal drugs legal drugs illegally used intoxicants drug paraphernalia alcohol In addition, no employee may work while under the influence of alcohol or test as determined by the testing lab. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 1
  • 750. MEDICATIONS Employees taking medication that will affect their ability to work safely are required to give their supervisor a statement from the doctor who prescribed the medication. This statement must: say that the medication was prescribed with full knowledge of their job duties and give recommendations for appropriate work modification WM does not want to know the name of the medication or why it was prescribed. Employees should have their doctor sign the form included at the end of this document. (See Appendix B for Physician Statement Regarding Prescription Medication) medication. Doing so is illegal. In addition, this might result in a positive drug test and corrective action will result. LEGAL DRUGS Legal drugs illegally used means ILLEGALLY drugs that are not prescribed for the employee or USED drugs that are not doctor DRUG Drug Paraphernalia means any item used to perform any of the actions PARAPHERNALIA listed below with regard to drugs. use possess sell consume make inhale handle transport W ASTE WM has the right, at all times, to inspect MANAGEMENT S all persons, RIGHTS their property, and WM provided property prior to entering, while on, and when leaving WM property. Illegal drugs found in or on WM property or vehicles will be turned over to the appropriate law enforcement officials. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 2
  • 751. DEFINITION OF DRUGS controlled substances illegal drugs legal drugs illegally used drug paraphernalia intoxicant alcohol prescription medication over-the-counter medication that if abused, may lead to physical or psychological dependence. ADULTERATED OR Adulterated means contaminated. Substituted means replaced. If a urine SUBSTITUTED Medical Review Officer (MRO) will report it to the Designated Employee RESULTS Representative (DER) as a refusal to test. A refusal to test is considered the same as a positive test. REFUSAL TO Employees who refuse to take a drug or alcohol test upon request or TEST when scheduled are terminated.1 EXCEPTIONS WM may allow alcohol to be used at WM functions. An employee may work while taking a drug IF the drug has been prescribed by a doctor, is being used as directed by the doctor, does not reduce the ability to work safely and efficiently, and does not pose a risk to workplace safety. If the drug could prevent the employee from working safely and efficiently, he or she must tell his or her supervisor or Human Resources Representative without delay. In some instances, the employee may be required to provide a medical statement regarding their ability to safely perform job duties. COST WM pays all costs for drug and alcohol testing required by WM. This includes pre-employment testing for candidates. 1 unless otherwise directed in any collective bargaining agreement Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 3
  • 752. PREVENTING To maintain a workplace that is free from drugs and alcohol, WM uses a SUBSTANCE Substance Abuse Program. This program includes: ABUSE education, training, and drug and alcohol testing EDUCATION Employees learn about The health effects of drugs and alcohol. substance abuse problems. See below for more information on the EFAP. TRAINING WM provides training for supervisors so they can recognize early warning signs, symptoms, and behavior that might indicate a use/abuse problem. Supervisors also learn how to address performance problems resulting from substance abuse. DRUG AND WM has developed a drug and alcohol testing program. The basics of this ALCOHOL program are described in this document. TESTING Test results are confidential. The donor is identified at the testing laboratory (lab) with a number only. The results are not made known to anyone except WM employees with a legitimate, business-related reason to know. The MRO receives the test results from the lab. An MRO is a licensed doctor who knows how to read substance-abuse tests. The MRO sends the results to the Designated Employee Representative (DER). The DER shares the information only as corrective action is required. The results can only be released outside of WM with written permission. DRUG TESTING Urine is tested for controlled substance use. Listed below are the substances the test covers. Marijuana Phencyclidine (PCP) Cocaine Amphetamines Opiates Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 4
  • 753. DRUG TESTING The urine is sent to a lab that is certified by the Department of Health and (CONTD.) Human Services. The collector has been qualified according to DOT Custody and Control Form (CCF) or Chain of Custody Form (COC) identifies and stays with the specimen. This makes sure that no once can tamper with the urine. It ensures that the urine provided is the urine that is tested. Custody and Control begins when the urine is collected and ends when it is 1. A sample is provided. 2. The sample is labeled with an assigned number. The number is bar It is sealed in a tamper-evident container. This kind of container shows evidence of any attempt to tamper with the seal. 3. The sample is sent to the lab for analysis. Security is very high at the lab. The lab documents everything it does with the specimen. The lab computer confirms that the specimen matches its Custody and Control Form (CCF)/Chain of Custody Form (COC). At the lab, the urine is screened. If it is positive, then it is tested again. This test is completely separate from the first test. It uses a different technique. It uses a different chemical principle. If this test is negative, no further testing is done. If this test is positive for drugs, a confirmation test is done. If that test is positive for drugs, it will be referred to the MRO for handling. The lab stores the specimen in a secure refrigerator. Negative specimens are discarded within 5 days. Positive specimens are held for one year. ALCOHOL The first screening is performed on saliva or breath. A qualified Saliva Test or TESTING Breath Alcohol Technician collects the test sample. The technician analyzes the sample right away. If the first screening is positive (at or above 0.02), a second test is done after 15 minutes to confirm the result. This second test is on breath only. It is done with a device approved by the federal government. It shows breath alcohol concentration (BAC). If this test is negative, no further testing is done. Alcohol testing is done just before, during, or just after on-duty or Company time. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 5
  • 754. IF AN EMPLOYEE Employees with substance abuse problems should get help before those NEEDS HELP problems affect their job performance. Substance abuse problems can also affect qualifications to operate commercial motor vehicles. Employees are not penalized for seeking assistance. However, corrective action up to and including termination may be taken for poor job performance, regardless of the reason. THE EFAP The Employee Family Assistance Program (EFAP) provides assessment, counseling, and treatment services for employees who have substance abuse problems. These services are confidential. employees recover from the illness of substance abuse while they continue to meet the duties of their jobs. Getting help is the first step towards regaining control, rebuilding relationships, and resuming good performance. If an employee, any of their family members, or any of their co-workers need help, they should contact the EFAP at 1.800.852.7461. EDUCATION The EFAP also provides employees education about substance abuse. Employees can learn to recognize early warning signs, symptoms, and behavior that might indicate a use/abuse problem. Employees can also learn about the harmful effects of substance abuse. The EFAP can also provide employees with community resources and referrals for help. OTHER HELP other WM policies, such as leave-of-absence policies. SUMMARY The Drug and Alcohol Policy applies to all WM employees and candidates. To be hired and to remain employed by WM, everyone must comply with the Substance Abuse Program. This includes drug and alcohol testing when requested. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 6
  • 755. SUMMARY Any employee (CONTD.) whose test is positive for the presence of a prohibited substance, who refuses to test, who acts in a way that clearly obstructs the testing process, or who refuses to cooperate in an investigation of a policy violation E M P L O Y E ES W H O V I O L A T E T H E D R U G A N D A L C O H O L PO L I C Y W I L L B E SU BJ E C T T O C O R R E C T I V E A C T I O N UP T O A N D I N C L U D I N G T E R M I N A T I O N. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 7
  • 756. DRUG TESTING POLICY FOR ALL CANDIDATES POLICY It STATEMENT provides for drug testing of all candidates for all positions at WM. Applicants who are offered a job with WM become job candidates. DRUG TESTING All candidates must pass a pre-employment urinalysis drug test before being hired. This applies to all jobs at WM. Applicants are told about this requirement in writing when they first apply for employment. Applicants who are offered a job must submit a urine sample. This sample is tested for illegal drugs. Candidates cannot begin work at WM until they receive a negative test. DOT APPLICANTS Applicants who apply for DOT positions must provide to WM drug and alcohol violations and DOT reportable accidents for the previous 36- months. A positive drug or alcohol result or a refusal to test within the past 36 months will disqualify the applicant for employment. DILUTE SPECIMEN A dilute specimen is one where creatinine and specific gravity levels are lower than expected for human urine. WM uses the following guidelines for dilute specimens C reatinine L evel: L ab Reports As: Action Required: Less than 5mg Substituted Same as a positive/refusal to test 2-5mg Cancelled-Dilute Immediate observed re- test required. Greater than 5mg Negative-Dilute Immediate non-observed re-test required If the result of the second test is also negative dilute WM policy does not allow for a third test to be conducted. A negative dilute re-test is considered a negative test. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 8
  • 757. W ITHDRAWAL OF If a candidate JOB OFFER fails to provide the 36-month history of drug and alcohol violations and DOT reportable accidents, misses the appointment for collection, refuses to sign a consent form, refuses to submit to the drug test, or fails the drug test any offers of employment will be withdrawn. Candidates who test positive for drugs may request a copy of the test result. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 9
  • 758. DRUG AND ALCOHOL TESTING POLICY FOR EMPLOYEES IN DOT-REGULATED POSITIONS POLICY STATEMENT provides for drug and alcohol testing of WM employees who are covered by the drug and alcohol testing requirements of the Federal Motor Carrier Safety Administration (FMCSA), part of the U.S. Department of Transportation (DOT). Its purpose is to reduce employee substance abuse and to prevent incidents in the workplace related to substance abuse. All DOT employees must follow this Policy to remain employed. Employees who violate this Policy are removed from performing safety sensitive functions. They are also subject to corrective action up to and including termination. Violation includes refusing to take a drug or alcohol test upon request.1 All drug and alcohol tests conducted pursuant to this Policy are done in procedures c alcohol testing regulations. This Policy may be changed without notice if necessary to comply with current or future DOT regulations. DOT COVERED Employees who EMPLOYEES operate commercial motor vehicles and must follow this Policy. DOT covered employees include the types of drivers listed below. full-time part-time casual intermittent occasional 1 Corrective action measures described in any collective bargaining agreement may also apply. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 10
  • 759. PROHIBITED DOT employees must N O T CONDUCT report to duty or remain on duty requiring the performance of safety sensitive functions while having a BAC of 0.02 or higher. be on duty or operate a commercial motor vehicle while possessing alcohol. use alcohol while performing safety sensitive functions. perform safety sensitive functions within 4 hours after using alcohol. report for duty or remain on duty requiring the performance of safety sensitive functions when the driver uses any drug. This does not apply if the driver is taking medication under a doctor ability to safely operate a commercial motor vehicle. DRUG AND DOT employees are required to take a urinalysis drug test and an ALCOHOL TESTING alcohol test under the conditions listed below: Pre-Employment (urine test only) Pre-Use (urine test only, prior to beginning or upon transfer to a DOT or non-DOT safety sensitive position) Reasonable Suspicion Post Accident Random Return-to-Duty Follow-Up PRE-EMPLOYMENT All candidates must pass a pre-employment urinalysis drug test before AND PRE-USE being hired. This applies to all jobs at WM. Applicants are told about this requirement in writing when they first apply for employment. Applicants who are offered a job must submit a urine sample. This sample is tested for illegal drugs. All employees transferring into DOT or non-DOT safety sensitive positions must pass a urinalysis drug test. REASONABLE Reasonable suspicion occurs when a supervisor who is trained to detect SUSPICION the signs of alcohol and drug use has reason to believe that the driver performed any of the actions listed under Prohibited Conduct on this page. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 11
  • 760. BASIS OF REASONABLE alcohol use on observations. These observations must be about appearance, behavior, speech or body odor that is SUSPICION specific, current (happening from recent past and continuing), and can be described in words. The observations may also include indications of the chronic use and/or withdrawal effects of drugs or alcohol. However alcohol tests are conducted only just before, while, or just after the driver performs safety sensitive functions. The supervisor making the observation makes a written record of those observations. POST ACCIDENT A DOT employee must take a drug and alcohol test following an accident involving a commercial motor vehicle. This applies only in the situations listed below. 1. The driver is involved in an accident that results in a fatality. 2. The driver is involved in an accident that results in a citation for a moving violation and medical treatment away from the scene of the accident. 3. The driver is involved in an accident that results in a citation for a moving violation and one or more damaged vehicles that must be towed. Employees who must take a post-accident test must remain readily available for a test following the accident. If they do not, they are judged to have refused to take the test. DOT employees required to take a post accident test must not use alcohol for eight hours after the accident or until undergoing the post accident test, whichever occurs first. Post accident drug and alcohol testing conducted by the authorities is NOT a substitute for conducting our own post accident test (or, if applicable, reasonable suspicion). In cases where the authorities have conducted their own test, this will require the driver to provide a separate specimen for the WM required test. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 12
  • 761. RANDOM DOT employees are required to submit to random drug and alcohol testing upon request. Random drug tests are unannounced and occur periodically throughout the year. However, alcohol tests are conducted only just before, while, or just after the driver performs safety sensitive functions. TEST RATES Random drug testing is conducted at the annual rate of 50% of the average number of DOT positions. Random alcohol testing is conducted at the annual rate of 10% of the average number of DOT positions. Test rates may be adjusted by DOT. EMPLOYEE Employees are selected for random testing by a scientifically valid SELECTION FOR method. This method ensures that each DOT employee has an equal chance of being selected each time selections are made. RANDOM TESTING RETURN-TO-DUTY An employee who is not terminated after a positive urine drug test or AND FOLLOW -UP breath alcohol test, per state law or a collective bargaining agreement, must TESTING sign a Last Chance Agreement, be evaluated by a Substance Abuse Professional (SAP), have negative test results before returning to duty, and be in compliance with whatever treatment plan the SAP requires. The employee may return to duty only after a SAP releases him or her for return. After the required evaluation, the SAP writes a letter confirming that he or she may return to duty. The employee will also be required to take random drug and alcohol tests no fewer than six times throughout the next year. Follow-up alcohol testing is conducted only just before, while, or just after the employee performs safety sensitive functions. All return-to-duty and follow-up tests must be performed using observed collection. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 13
  • 762. REFUSAL TO TEST Employees who refuse to take a drug or alcohol test upon request or when scheduled are terminated.1 A refusal to test is considered the same as a positive result. Any conduct that interferes with the testing process is considered a refusal to test, and therefore, a positive result. Examples of this are missing the appointment and going the next day because of personal preference. Refusing to sign step 4 of the Alcohol Testing Form is considered a refusal to test when the employee takes an alcohol confirmation test. In this case the employee will be terminated.1 CONSEQUENCES DOT employees will be terminated if OF A POSITIVE alcohol test shows a BAC of 0.04 or higher or DRUG OR urine test shows the presence of drugs as determined by the ALCOHOL TEST1 2 MRO. DOT employees with a BAC between 0.02 and 0.039 will be removed from safety sensitive duties for a minimum of 24 hours and suspended, pending an evaluation and return-to-duty recommendation from a SAP. will be terminated if they refuse to go to a SAP for evaluation and comply with the follow-up recommendations an/or treatment. must pass a return-to-duty breath alcohol and urine drug test, sign a Last Chance Agreement, and undergo follow-up testing for up to 60 months if requested by the SAP, including no less than 6 random tests in the first year. A second test of 0.02 or higher or a positive urine test will lead to termination as required by the terms of the Last Chance Agreement. An employee may take sick time, vacation time or any other accrued time and/or apply for short-term disability (STD) to cover lost wages. 1 Consequences of a positive drug or alcohol test or a refusal to test for employees covered by a collective bargaining agreement may differ from other employees. 2 In accordance with California State Law, all Commercial Drivers with a BAC of 0.01 or higher must be placed out of service for 24 hours. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 14
  • 763. CONSEQUENCES DOT candidates are also subject to the rules and regulations of the OF A POSITIVE Department of Transportation. These rules and regulations are DRUG OR ALCOHOL TEST (CONTD.) WM is required by DOT regulations to obtain a three-year history of a lcohol testing and accident history from the provide and drug and alcohol testing and accident records they have from previous employers. Therefore, if a DOT employee tests positive on a drug or alcohol tests, that will follow the person for at least three years. Candidates who have tested positive for drugs or alcohol at a prior employer must provide documentation that they have successfully completed a SAP evaluation and are following the recommended course of treatment. DILUTE SPECIMENS A dilute specimen is one with creatinine and specific gravity levels that are lower than expected for human urine. The DOT has established the following guidelines for dilute specimens C reatinine L evel: L ab Reports As: Action Required: Less than 2mg Substituted Same as positive/refusal to test 2-5mg Cancelled- Dilute Immediate observed re- test required Greater than 5mg Negative Dilute Immediate non-observed re-test required If the result of the second test is also negative dilute, WM policy does not allow for a third test to be conducted. A negative dilute re-test is considered a negative test. ADULTERATED OR Adulterated means contaminated. Substituted means replaced. If a SUBSTITUTED urine specimen has been contaminated, tampered with, or replaced, the MRO will report it to the Designated Employee Representative (DER) RESULTS as a refusal to test. A refusal to test is considered the same as a positive test. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 15
  • 764. SPLIT SAMPLE DOT employees or candidates who have a verified positive, adulterated TEST or substituted test result will be contacted by the MRO. They may explain the test result or disclose any prescription medication that they are taking that may have caused the result. This information will remain confidential. They may also request a split sample test. The split sample is a portion of the original specimen that has been stored at the lab. The sample will be sent to a different lab for testing and the employee or candidate is responsible for the cost of the test. The result of the split sample test will be the test result of record. The employee or candidate will not be able to provide a new specimen. GETTING HELP If the SAP determines that the employee needs assistance with a substance abuse problem, the employee must follow any treatment program recommended by the SAP. Employees can get information from the EFAP or a SAP about available experts, treatment, and rehabilitation programs. FOLLOW -UP Employees who have been identified by a SAP as needing help must TESTING undergo follow-up testing when they return to safety sensitive functions. Follow-up testing consists of at least six tests in the first 12 months, may continue for up to 60 months, and may include both drug and alcohol testing. Per DOT regulations, all follow-up tests will be done under observed collection. Testing Policy may contact the Background Screening and Drug Testing Unit (BDU) at 866-875-4884. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 16
  • 765. DRUG AND ALCOHOL TESTING POLICY FOR EMPLOYEES IN NON-DOT POSITIONS POLICY STATEMENT provides for the drug and alcohol testing of WM employees under certain circumstances. Its purpose is to reduce employee substance abuse and to prevent incidents in the workplace related to substance abuse. WM believes that drug and alcohol testing is a valuable and appropriate way to address safety concerns. All non-DOT employees must follow this Policy to remain employed. Violation includes refusing to take a drug or alcohol test when scheduled or upon request. Some states and locales may have certain restrictions on drug and/or alcohol testing. This policy will be modified to the extent that local and/or state laws require. E M P L O Y E ES W H O V I O L A T E T H IS PO L I C Y A R E SU BJ E C T T O C O R R E C T I V E A C T I O N UP T O A N D I N C L U D I N G T E R M I N A T I O N. DRUG AND Non-DOT employees are required to take a urinalysis drug test and ALCOHOL alcohol breath test under the conditions listed below: TESTING Pre-employment (urine test only) Pre-use (urine test only, prior to beginning or upon transfer to a DOT or non-DOT safety sensitive position) Reasonable Suspicion Post accident Random Return-to-duty Follow-up These situations are explained below. PRE- All candidates must pass a pre-employment urinalysis drug test before EMPLOYMENT AND being hired. This applies to all jobs at WM. Applicants are told about this in writing when they first apply for employment. Applicants who are PRE-USE offered a job must submit a urine sample. This sample is tested for illegal drugs. All employees transferring into DOT or non-DOT safety sensitive positions must pass a urinalysis drug test. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 17
  • 766. REASONABLE Reasonable suspicion occurs when a supervisor has reason to suspect SUSPICION that the employee has used drugs or alcohol or is under the influence of drugs or alcohol performance. BASIS OF REASONABLE alcohol use on observations. These observations must be about appearance, behavior, speech or body odor that is SUSPICION specific, current (happening in recent past and continuing), and can be described in words. The observations may also include indications of the chronic use and/or withdrawal effects of drugs or alcohol. POST ACCIDENT Reasonable suspicion guidelines must be followed when deciding whether a drug and/or alcohol test should be performed after an on-the- job accident. Post accident drug and alcohol testing conducted by the authorities is NOT a substitute for conducting our own post accident (or, if applicable, reasonable suspicion) test. In cases where the authorities have conducted their own test, this will require the driver to provide a separate specimen for the WM required test. RANDOM Non-DOT employees are required to submit to random drug and alcohol testing upon request. Random drug tests are unannounced and occur periodically throughout the year, however alcohol tests are only conducted just before, while, or just after the employee performs his/her job functions. TEST RATES Random drug and alcohol testing is conducted at the rate of 10% of the average number employees in safety sensitive positions and non-safety sensitive positions. Tests rates may be adjusted by WM. EMPLOYEE Employees are selected for random testing by a scientifically valid SELECTION FOR method. This method ensures that each safety sensitive employee has an equal chance of being selected each time selections are made. RANDOM TESTING Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 18
  • 767. RETURN-TO-DUTY Non-DOT employees who are not terminated after a positive urine drug AND FOLLOW -UP test or alcohol test, per state law or a collective bargaining agreement, must TESTING sign a Last Chance Agreement, be evaluated by a Substance Abuse Professional (SAP), have negative test results before returning to duty, and be in compliance with whatever treatment plan the SAP requires. The employee may return to duty only after a SAP releases him or her for return. After the required evaluation, the SAP writes a letter confirming that he or she may return to duty. The employee will also be required to take random drug and alcohol tests no fewer than six times throughout the next year. Follow-up alcohol testing is conducted only just before, while, or just after the employee performs his/her job functions. All return-to-duty and follow-up tests must be performed using observed collection. REFUSAL TO TEST Employees who refuse to take drug or alcohol random tests are terminated immediately. A refusal to test is considered the same as a positive result. Any conduct that interferes with the testing process is considered a refusal to test, and therefore a positive result. Examples are missing the appointment and going the next day because of personal preference. Refusing to sign Step 4 of the Alcohol Testing Form is considered a refusal to test when the employee takes an alcohol confirmation tests. In this case the employee is terminated. CONSEQUENCES Non-DOT employees will be terminated if OF A POSITIVE alcohol test shows a BAC of 0.04 or higher or DRUG OR urine test shows the presence of drugs as determined by the MRO. ALCOHOL TEST Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 19
  • 768. CONSEQUENCES Non-DOT employees with a BAC between 0.02 and 0.039 OF A POSITIVE will be removed from duty for a minimum of 24 hours and DRUG OR suspended, pending an evaluation and return-to-work recommendation from a SAP. ALCOHOL TEST will be terminated if they refuse to go to a SAP for evaluation and (CONTD.) comply with follow-up recommendations and/or treatment. must pass return-to-duty breath alcohol and urine drug test, sign a Last Chance Agreement, and undergo random testing for up to 60 months if requested by the SAP, including no less than 6 random tests in the first year. A second test of 0.02 or higher or a positive urine drug test will lead to termination as required by the terms of the Last Chance Agreement. An employee may take sick time, vacation time or any accrued time and/or apply for short-term disability (STD) to cover lost wages. DILUTE A dilute specimen is one where creatinine and specific gravity levels are SPECIMENS lower than expected for human urine. WM has established the following guidelines for dilute specimens C reatinine L evel L ab Reports As: Action Required: Less than 2mg Substituted Same as positive/refusal to test 2-5mg Cancelled-Dilute Immediate observed re- test required Greater than 5mg Negative Dilute Immediate non-observed re-test required If the result of the second test is also negative dilute, WM policy does not allow for a third test to be conducted. A negative dilute re-test is considered a negative test. ADULTERATED OR Adulterated means contaminated. Substituted means replaced. If a urine SUBSTITUTED specimen has been contaminated, tampered with, or replaced, the MRO will report it to the Designated Employee Representative (DER) as a RESULTS refusal to test. A refusal to test is considered the same as a positive result. For employees, a positive test results in corrective action up to and including termination. For candidates, WM withdraws any job offer. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 20
  • 769. SPLIT SAMPLE Non-DOT employees or candidates who have a verified positive, TEST adulterated or substituted test result will be contacted by the MRO. They may explain the test result or disclose any prescription medication that they are taking which may have caused the result. This information will remain confidential. They may also request a split sample test. The split sample is a portion of the original specimen that has been stored at the lab. The sample will be sent to a different lab for testing and the employee or candidate is responsible for the cost of the test. The result of the split sample test will be the test result of record. The employee or candidate will not be able to provide a new specimen. -DOT Drug and Alcohol Testing Policy may contact the Background Screening and Drug Testing Unit (BDU) at 866-875-4884. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 21
  • 770. DEFINITIONS Several of the terms used throughout this Policy are defined below. A chain of custody tracks the handling and storage of a urine specimen. CHAIN OF The tracking begins when the urine is collected. It ends when the urine is CUSTODY discarded. That way, the urine tested is the urine provided. This procedure makes sure that no one can tamper with the specimen. COMMERCIAL MOTOR 1. Vehicles with a gross combination weight rating of 26,001 or more pounds. This includes a towed unit with a gross vehicle weight VEHICLE rating of more than 10,000 pounds. 2. Vehicles with a gross vehicle weight rating of 26,001 or more pounds. 3. Vehicles that are designed to transport 16 or more passengers including the driver. 4. Vehicles that are used in the transportation of hazardous materials that require a warning placard. A confirmatory test is done if the first test is positive (shows drug or alcohol CONFIRMATORY use). Its purpose is to make sure the first test is correct. It shows the TEST presence of a drug or alcohol. At this time, the method to confirm positive drug tests is GC/MS. This FOR DRUGS This test is performed on all urine specimens that test positive on the first test. It can detect a drug or other substances that show the drug is present (drug metabolite). This test is completely separate from the first test. It uses a different technique. It also uses a different chemical principle. If this test is negative, no further testing is done. A positive test results in corrective action up to and including termination. F OR A LC O H OL If a first test shows a BAC of 0.02 or higher, a second Breathalyzer test is used to make sure the first test was correct. If this test is negative, no further testing is done. A positive test results in corrective action up to and including termination. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 22
  • 771. DEFINITIONS (CONTD.) DRUG A drug metabolite is the specific substance produced when a given drug METABOLITE passes through the body and leaves in the urine. In other words, the body re other substances that end up in the urine. EMPLOYEE EFAP is a program provided through a contracted service. It assists FAMILY employees in dealing with drug or alcohol dependency. It can also help employees with other personal problems. ASSISTANCE PROGRAM (EFAP) INITIAL TEST OR See also Confirmatory Test. SCREENING TEST F OR D RUG S The fist test is a urine test. An immunoassay screen is used. If the test is negative then no further testing is done. If the test is positive, a Confirmatory Test is done. F OR A LC O H OL The first test for alcohol is a Breathalyzer test. If the test is negative, then no further screening is done. If the test is positive (BAC of 0.02 or higher), a Confirmatory Test is done. This second test uses a Breathalyzer. MEDICAL A MRO is a licensed doctor. The MRO receives the lab results from the REVIEW drug testing program. MROs know about substance abuse problems. They also have medical training to interpret and evaluate positive test results OFFICER along wit (MRO) DOT SAFETY The following functions are considered DOT safety sensitive functions when SENSITIVE performed by a driver of a commercial motor vehicle. 1. Waiting to be dispatched or to operate a commercial motor vehicle. FUNCTIONS 2. Inspecting, conditioning, or servicing a commercial motor vehicle. 3. Driving a commercial motor vehicle. 4. Loading or unloading (or assisting or supervising loading or unloading) a commercial motor vehicle. 5. Repairing, obtaining assistance, or remaining in attendance upon a disabled commercial motor vehicle. Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 23
  • 772. DEFINITIONS (CONTD.) NON-DOT A non-DOT safety sensitive position requires the performance of specific SAFETY physical or supervisory tasks. If these tasks are done incorrectly, injury or death to employees or others could result. In addition, significant property SENSITIVE or environmental damage could occur. POSITION Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 24
  • 773. APPENDIX A: NON-DOT SAFETY-SENSITIVE POSITIONS Definition: A non-DOT safety sensitive position requires the performance of specific physical or supervisory tasks. If these tasks are done incorrectly, injury or death to employees or others could result. In addition, significant property or environmental damage could occur. L andfill T ransfer Station Mechanic / Fueler Mechanic Tire Replacer Tire Replacer Parts Runner Parts Runner Heavy Equipment Operator Transfer Truck Driver Spotter Heavy Equipment Operator Wood Chipper / Grinder Spotter Tipper Operator Helper Helper MRF H auling Mechanic Vehicle Mechanic Heavy Equipment Operator Fabricator / Container Repair Spotter Tire Replacer Helper Parts Runner Bin Delivery Portalet Driver Helper M ISC Any employee who drives regularly and on a consistent basis as part of his or her job duties (includes employees who receive a car allowance, are issued a company vehicle, or who participate in the Runzheimers Program) Workers running mobile machinery Mechanics Helpers Substance A buse Program 2002, W aste M anagement for Company E mployees and C andidates Revised September 2008 Page 25
  • 774. APPENDIX B: PHYSICIAN STATEMENT REGARDING PRESCRIPTION MEDICATION
  • 775. W AST E M A N A G E M E N T 1001 FANNIN, SUITE4000 HOUSTON, TX 77002 (713) 512-6000 Physician Statement Regar ding Prescription M edication Supervisor completes this section. W M Site ________________________________ Date E mployee Name ________________________ A ddress State/Zip Code ________________ Telephone Number Job T itle ______________________ Supervisor Name Physician Instructions: Your assistance is needed to determine if the above named individual can safely perform the essential functions of his or her job. Please complete the section below and select the appropriate recommendation. Thank you for your help and cooperation.   Physician Name Address State/Zip Code Telephone Number The employee whose name appears above is under my care. I have prescribed medication (s) for this employee. I The medication(s) I have prescribed will not affect the safe performance of those job duties. The medication(s) I have prescribed will affect the safe performance of those job duties. The employee is unable to return to work at this time. Next medical evaluation is The medication(s) I have prescribed will affect the safe performance of those job duties; therefore, I am recommending the following activity restriction(s): Expected duration of activity restrictions: Physician Signature_______________________________________Date__________________ Please do not reve community.
  • 776.  
  • 777. LOCK-OUT/TAG-OUT PROGRAM Program: Control of Hazardous Energy – Lock-out/tag-out Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 PURPOSE Requirements for the use of lock-out / tag-out techniques to protect personnel exposed to potentially hazardous energy sources during inspection, service or maintenance of vehicles, heavy equipment, machines or equipment (collectively referred to as equipment in this document). EXCLUSIONS This standard does not apply to work on cord and plug connected electrical equipment where exposure to the hazard is controlled by removing the plug that then remains under exclusive control of the employee performing the service or maintenance. REQUIREMENTS 1. Identify and prepare a list of vehicles, equipment and machine types requiring lock-out/tag- out. 2. Identify affected employees (those who operate or work near equipment where LO/TO may be used) and authorized employees (those who install LO/TO devices). 3. Ensure new or modified equipment is capable of being locked out. 4. Provide lockout devices, including uniquely keyed locks used only for lockout purposes. Locks must be unique in size, shape or color. Provide tag-out devices if used. 5. Develop operational and/or equipment specific energy control procedures for the equipment and operations, listed in the proceeding. Prepare a procedure for each group of similar equipment where practical (same energy sources and same energy controls). 6. Require supervisors to observe, on an annual basis, lock-out/tag-out performed by every authorized employee and certify their competence. Document the observation results. The observation record must include the machines or equipment, the names of the employees, the date of the observation and certification by the observer. 7. Notify contractors of the lock-out/tag-out program, making them aware of the district requirements. Ensure contractors notify the district of the contractor’s lock-out/tag-out procedures. LOCK-OUT/TAG-OUT Page 1 ©2011, Waste Management January 2011
  • 778. LOCK-OUT/TAG-OUT PROGRAM 8. Review the program annually, including review of procedures and implementation. 9. Train authorized employees to properly lock-out/tag-out the specific equipment they service or maintain. 10. OSHA also specifies the training of “other” employees – simply, those who may walk through or visit an area where lock-out/tag-out is ongoing, but employees who do not fall under the “affected” category. 11. Provide training for supervisors and employees responsible for developing equipment- specific procedures. 12. Retrain employees when there are changes affecting lock-out/tag-out, or changes in job assignments, equipment, operations, or procedures. 13. Document training using the Safety Training Attendance Form. INTRODUCTION Lockout and tag-out are safety procedures to protect employees from hazardous energy during inspecting, maintenance, servicing, and troubleshooting of equipment, machinery, vehicles and heavy equipment. The lock-out/tag-out program contains the following elements: Core program. Provides the standard method for complying with the company and regulatory requirements. Facility-specific information. Identifies information such as responsibilities, site-specific equipment, and location of procedures, training details, etc. CORE PROGRAM This program covers how to shut down equipment, isolate energy sources, apply and remove locks and tags, and verify that stored hazardous energy is not present. The types of energy release that could cause injury when released include: Air pressure Mechanical Chemical reaction Flammability Hydraulic pressure Gravity Electrical Equipment can have more than a single energy source. For example, an air compressor could have main power, control power, and stored air pressure. That is why this standard requires a written equipment-specific procedure for equipment. Certain types of equipment do not require equipment-specific procedures LOCK-OUT/TAG-OUT Page 2 ©2011, Waste Management January 2011
  • 779. LOCK-OUT/TAG-OUT PROGRAM The basic protective mechanism is to shut down the equipment, set all controls in the “off” position and lock each control. Each employee has his or her own unique key(s) and lock(s) that must be applied to each control. Authorized employees may use a tag to warn others not to start equipment only when controls cannot be locked. In this case, the employer has the responsibility to secure the equipment to protect it from being accidentally energized. (For example, placing a responsible person at the switch for the entire maintenance activity to ensure no one touches the switch.) Responsibility Program Administrator: Ensures operational or equipment-specific energy control procedures are prepared and revised, as needed. Makes sure workers follow established lock-out/tag-out practices. Ensures that employees receive appropriate training. Performs an annual review of program effectiveness. Authorized employees are those who directly participate in the use of lock-out/tag-out procedures. Authorized employees: Are responsible for following the lock-out/tag-out procedures described in this program and equipment-specific energy control procedures. Authorized employees must place and remove their own locks. No one is allowed to place or remove someone else's lock. Are issued individual locks, tags, and lockout devices. Receive training in the general requirements of the program, as well as, the established equipment-specific procedures. Affected employees are those who operate or use machines or equipment subject to lockout/tag- out procedures, or those who work in an area where servicing or maintenance is being performed under lockout/tag-out. Affected employees are responsible for staying away from equipment that has been locked out. Provide Uniquely Keyed Locks for Each Authorized Employee All authorized employees are issued their own individually keyed lock(s) to lock out equipment. When locking out equipment is not possible, employees will use a tag to warn others not to start equipment. LOCK-OUT/TAG-OUT Page 3 ©2011, Waste Management January 2011
  • 780. LOCK-OUT/TAG-OUT PROGRAM Prepare Equipment-Specific Procedures Develop and provide written operational or equipment-specific procedural steps for shutting down, isolating, blocking, and securing a machine or piece of equipment that ensures the control of all sources of hazardous energy. District must: Develop written equipment-specific procedures. Ensure employee usage through periodic reviews. Written equipment-specific procedures are not required when all of the following exist: The machine or equipment has no potential for stored or residual or accumulation of energy after shutdown. The machine or equipment has a single energy source that can be readily identified and isolated. The isolation and locking out completely de-energizes and deactivates the machine or equipment. The machine or equipment is isolated from the energy source and locked out during service or maintenance. A single lockout device achieves a locked-out condition. The authorized employee has exclusive control of the lockout device. The servicing or maintenance does not create hazards for other employees. There have not been any accidents involving the unexpected activation or energizing of the piece of equipment or machine during service or maintenance. If all of the above conditions exist, lock-out/tag-out must still be used, except written equipment- specific procedures are not required. When to Use Lockout and Tag-out Use lockout whenever you inspect, repair or maintain equipment, machinery, vehicles, heavy equipment that could cause injury by an unexpected start-up of the equipment or release of stored energy. For example: During pre/post trip inspection When removing guards or other safety devices. When moving machinery could come in contact with employees. When repairing electrical circuits. When clearing jammed mechanisms. When cleaning or oiling machinery with moving parts where an employee may get caught within the equipment. LOCK-OUT/TAG-OUT Page 4 ©2011, Waste Management January 2011
  • 781. LOCK-OUT/TAG-OUT PROGRAM Shutdown Preparation Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. Shut down Equipment Authorized employees will: Check with the supervisor if unfamiliar with the operation and shutdown of the equipment. Shut down operating equipment using the normal means. Follow the correct equipment-specific energy control procedure for each piece of equipment. Isolate the Equipment Authorized employees will: Isolate the equipment from its energy sources by using the switch, valve, or other energy- isolating device. Isolate all energy sources, including secondary sources. Apply Lock-out/tag-out Devices Authorized employees will: Place a lock on each energy-isolating device (authorized employees may need more than one lock to do this). If the authorized employee is not identified by other means, use an identifying approved tag with the following information: a) Name of authorized employee. b) The date. c) A warning of the hazardous condition. Ensure each worker in the crew attaches his or her personal lock if more than one person is servicing the equipment. Remember that the individual assigned to a lock has the only key. Workers must have their locks and keys available at the work site. LOCK-OUT/TAG-OUT Page 5 ©2011, Waste Management January 2011
  • 782. LOCK-OUT/TAG-OUT PROGRAM Control Stored Energy Release or restrain any stored energy by methods such as blocking, bleeding down, and discharging energy stored in capacitors or other effective methods. If necessary, make equipment safe by disconnecting wiring, removing fuses, uncoupling drive shafts, removing belts, or by using other means. Use danger tags in these cases. Verify Isolation of Equipment Authorized employees will: Make sure no one is exposed to any areas of danger. Verify using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. Do the Work Safely Each authorized employee will: Not do anything that could restart the equipment. Not bypass the lockout, for example, by putting in new wiring or piping. Shift or Personnel Change Each authorized employee will ensure: Locks and tags remain in place until the job is completed. At shift or personnel change, an incoming authorized employee attaches their lock or tag as the outgoing employee removes theirs. OR An OUT OF SERVICE shop Lock is used during periods of incomplete work or shift change. Properly Remove Locks and Tags Following Maintenance Work Each authorized employee will: Inspect the work area and clean up all rags, tools, and materials. Replace guards on machines and equipment. Conduct a head count and make sure all employees are in a safe position. LOCK-OUT/TAG-OUT Page 6 ©2011, Waste Management January 2011
  • 783. LOCK-OUT/TAG-OUT PROGRAM Notify affected employees that the lock-out or tag-out device is being removed. Remove only their own locks or tags. This is the key OSHA required step for preventing injuries. Temporary Removal Workers must follow all of the above procedures before temporarily removing locks and tags to test equipment. Emergency Removal Only a supervisor, in the presence of another employee, can CUT another person's lock(s) and tags. This activity is permitted only under the following conditions: see page 20 of this program. Notify Contractors Give contractors a copy of this program and hold them responsible for following an equivalent program of their own. Ensure that a contractor's employees will not bypass the protective devices and endanger workers at the facility. Group Lock-out/tag-out Procedures If group lockout/tag-out procedures will be used, each authorized employee must place their own lock and completed tag to each multiple lock hasp device used. Exclusions from Lockout or Tag-out Permitted by OSHA OSHA permits the exclusion of the following operations from lockout/tag-out procedures: Normal production operations including repetitive minor adjustments and maintenance covered under OSHA’s machine guarding standards. Work on electrical equipment containing a cord and plug as its only energy source, when it is unplugged and being serviced or maintained and the worker has exclusive control over the plug. LOCK-OUT/TAG-OUT Page 7 ©2011, Waste Management January 2011
  • 784. LOCK-OUT/TAG-OUT PROGRAM Train Employees Each authorized employee receives instruction in the following: Recognition of hazardous energy source type and magnitude. Methods and means for energy isolation and control. The purpose, procedures, and use of the energy control procedure. Instruction on the prohibition relating to attempts to start or energize locked or tagged out equipment. The limitations of tags. Methods and means for verifying no hazardous energy are present. Each affected employee receives instruction in the purpose and use of the energy control procedure, the prohibition of removing locks or tags or attempts to restart equipment that has been locked out or tagged. Authorized and affected employees are retrained whenever: There is a change in job assignment; or There is a change in equipment, machinery, or a process that could present new hazards. There are reasons to believe there are inadequacies in an employee’s knowledge or use of the energy control procedures. Supervisors of authorized employees will be trained to the level of an authorized employee, as well as trained in supervisor responsibilities for lock-out/tag-out compliance. Conduct Periodic Inspections The Program Administrator and/or Supervisor conducts periodic inspections to determine if the authorized personnel are performing adequately. The inspection consists of: A review of work practices, the machines that were locked out/tagged out, names of the employees and dates observed. Deviations from procedures. Corrective actions taken. A review with each affected employee on the use and limitations of tags. Documentation of inspection. Specific Information Prepared by: Justin Lottig Date: January 2011 Approved by: Joe Whelan Date: January 2011 LOCK-OUT/TAG-OUT Page 8 ©2011, Waste Management January 2011
  • 785. LOCK-OUT/TAG-OUT PROGRAM Responsibility Name: Joe Whelan Title: Site Manager LOCK-OUT/TAG-OUT PROCEDURES AT FACILITY Identify the equipment-specific lock-out/tag-out procedures at the facility: See attached protocols….. Requirements for Locks and Tags Describe the method used to identify locks and tags used exclusively for the lock-out/tag-out program: Standardized lockout/tag-out devices will be used so that all employees will be able to recognize a locked out piece of equipment. Individual tags which identify the person(s) servicing the equipment will be used. Each person is assigned his or her own lock and it is labeled. Describe how the identity of the employee applying the lock or tag is indicated on the lock or tag: The person’s name is on the tag. Removing Locks Identify the name(s) and title(s) of person(s) authorized to remove the locks of other employees: Name: NONE LOCK-OUT/TAG-OUT Page 9 ©2011, Waste Management January 2011
  • 786. LOCK-OUT/TAG-OUT PROGRAM Annual Certification Describe the frequency and techniques to be used for the annual certification. Annually, the Program Administrator will review the lock-out/tag-out program, procedures and best management practices. Training Describe the materials used and topics covered for training authorized employees: Attach the training material to the Safety Attendance Form Describe the materials used and topics covered for training affected employees: Attach the training material to the Safety Attendance Form Describe the materials used and topics covered for training other employees: Attach the training materials to the Safety Attendance Form Identify location of training records WGSL Office DEFINITIONS Affected Employee: An employee whose job requires them to operate or use machinery, vehicles, or heavy equipment; on which servicing or maintenance is being performed under lockout or tag-out; or whose job requires him/her to work in an area in which such servicing or maintenance is being performed. Authorized Employee: A person who locks out or tags out machines, vehicles, or heavy equipment; in order to perform servicing or maintenance on that machine or equipment. Bleeding: To slowly empty a liquid or gas from a container or system. Blocking/Bracing: to fasten, secure, support, or provide with a block Energized: Connected to an energy source or containing residual or stored energy. Chock: The use of a blocking device to prevent vehicles and equipment from moving. Double Chocking: Any combination of – One front wheel and one set of duals, both front wheels, or both sides of rear duals LOCK-OUT/TAG-OUT Page 10 ©2011, Waste Management January 2011
  • 787. LOCK-OUT/TAG-OUT PROGRAM Energy Isolating Device: A mechanical device that physically prevents the transmission or release of energy such as a manually operated circuit breaker and a disconnect switch. Push buttons and selector switches are not energy isolating devices. Energy Source: Any source of electrical, mechanical, hydraulic, pneumatic, chemical, thermal, or other energy. Isolate: To set apart from its energy sources. Lockout: The placement of a lockout device on an energy-isolating device, in accordance with an established procedure, ensuring that the energy isolating device and the equipment being controlled cannot be operated until the lockout device is removed. Lockout Device: A device that utilizes a positive means such as a lock, to hold an energy- isolating device in the safe position and prevent the energizing of a machine or equipment. Included are blank flanges and bolted slip blinds. Other Employees: Those employees who may walk through or visit an area where lockout/tag- out is ongoing, but who do not fall under the “affected” category. Tag-out: The placement of a tag-out device on an energy-isolating device, in accordance with an established procedure, ensuring that the energy isolating device and the equipment being controlled cannot be operated until the tag-out device is removed. Tag-out Device: A prominent warning device, such as a tag, which can be securely fastened to an energy-isolating device. BELOW ARE SOME GENERAL LO/TO PROCEDURES, YOU ARE RESPONSIBLE FOR REVIEWING THE EQUIPMENT SPECIFIC PROCEDURES FOR EACH PIECE OF EQUIPMENT YOU WORK ON OR OPERATE: 1. Set the parking brake. 2. Release stored energy. 3. Shut the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Use any necessary stands for trucks with bodies or rails in the air: The stands on the front load trucks with tilt bodies are only approved if there is no load in the body. If there is a load, use additional stands. The stands for the rails on the roll-off trucks are only approved if there is no box on the truck. If there is a box on the truck use additional stands. 8. Cab-over -- secure cabs forward, if necessary. LOCK-OUT/TAG-OUT Page 11 ©2011, Waste Management January 2011
  • 788. LOCK-OUT/TAG-OUT PROGRAM TIRE REPLACEMENT 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove ignition key. 4. Place steering wheel cover over steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Use properly rated jack to lift the unit. 8. Use properly rated jack stand(s) to support the unit in the raised position. ELECTRICAL SYSTEM REPAIRS 1. Turn engine “off” (Exception: Engine may need to be running to check alternator or other dependent system). Place key in pocket. 2. Place steering wheel cover on steering wheel. 3. Double chock the wheels. PERFORM WORK IN THE BODY OF THE TRUCK 1. Set parking brake. 2. Release stored energy. 3. Shut the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Use any necessary stands or sleeves for trucks with bodies or rails in the air: The stands on the front load trucks with tilt bodies are only approved if there is no load in the body. If there is a load, use additional stands. The stands for the rails on the roll-off trucks are only approved if there is no box on the truck. If there is a box on the truck, use additional stands. 8. Be certain that there is no force being exerted by trash on the packer blades. 9. If entering through an open tailgate or hopper, be certain they are properly braced with stands. WORK DONE UNDERNEATH THE TRUCK 1. Set the parking brake. 2. Release stored energy. 3. Place steering wheel cover over steering wheel. 4. Turn battery disconnect off and lock/tag-out the disconnect. 5. Double chock/block the wheels. 6. Use any necessary stands for trucks with bodies or rails in the air: The stands on the front load trucks with tilt bodies are only approved if there is no load in the body. If there is a load, use additional stands. The stands for the rails on the roll-off trucks are only approved if there is no box on the truck. If there is a box on the truck, use additional stands. Use hydraulic jacks which may be pinned (to prevent accidents caused by leaking hydraulic jacks) or jack stands, if the truck is going to be off of the ground. LOCK-OUT/TAG-OUT Page 12 ©2011, Waste Management January 2011
  • 789. LOCK-OUT/TAG-OUT PROGRAM WORK DONE UNDERNEATH THE TAILGATE OR HOPPER 1. Set the parking brake. 2. Release stored energy. 3. Shut engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Double chock/block the wheels. 6. Use any necessary stands or sleeves for trucks with bodies or rails in the air: The stands on the front load trucks with tilt bodies are only approved if there is no load in the body. If there is a load, use additional stands. The stands for the rails on the roll-off trucks are only approved if there is no box on the truck. If there is a box on the truck, use additional stands. Be certain that tailgate or hopper is properly braced with stands. WORKING ON TRUCK WITH CAB IN RAISED POSITION 1. Set the parking brake. 2. Release stored energy. 3. Shut of the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag out the disconnect. 6. Double chock/block the wheels. 7. Use hydraulic jacks which may be pinned (to prevent accidents caused by leaking hydraulic jacks) or jack stands if the truck is going to be off of the ground. WORKING ON AIR COMPRESSORS 1. Turn “off” air compressor at the circuit breaker or remove plug. 2. Install a circuit breaker lockout or plug lockout device and lock/tag-out. 3. If servicing just the compressor, turn airline valve “off” and place valve lockout device and lock/tag-out valve. 4. Drain system (lines and tank) of any pressurized air. 5. Test the equipment to be certain there is no electricity present before working on it. Try the switch to be certain that it will not turn on. PERFORMING MAINTENANCE, REPAIR, SERVICE OR INSPECTING OF D-8 DOZER 1. Set the parking brake. 2. Lower blade to floor. 3. Neutralize all hydraulics. 4. Shut off the engine and remove the ignition key. 5. Turn battery disconnect off and lock/tag out the disconnect. 6. Place warning tag on equipment. 7. Block the tracks. LOCK-OUT/TAG-OUT Page 13 ©2011, Waste Management January 2011
  • 790. LOCK-OUT/TAG-OUT PROGRAM MECHANICS Remember that each person working on a piece of equipment must have their own individual lock that no one else can open, on that piece of equipment. Use a multiple lock hasp if more than one person works on the vehicle. WHEN ANY PART OF A DRIVER'S BODY IS GOING TO BE UNDERNEATH THE RAISED RAILS ON A ROLL-OFF TRUCK 1. Set the parking brake. 2. Release stored energy. 3. Turn the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Chock/block the wheels. 7. Use the body stands attached to the body: The stands for the rails on the roll-off trucks are only approved if there is no box on the truck. If there is a box on the truck use additional stands. SWITCHING OUT A COMPACTOR BOX 1. Disconnect and lockout and tag-out the power to the compactor before the ratchets are loosened. (Turn power off, Disconnect hydraulic hoses or loosen turn buckles) 2. Leave the compactors power supply Locked out and tagged out until the box is returned and secured. Turn power back on. DISLODGING CARDBOARD OR OTHER DEBRIS FROM ROLL-OFF BOX WHILE THE BOX IS ATTACHED TO THE VEHICLE IN ANY WAY 1. Set the parking brake. 2. Release stored energy. 3. Turn off the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock / tag out the disconnect. 6. Chock/block wheels. CRAWLING UNDERNEATH A TRUCK FOR ANY REASON 1. Set the parking brake. 2. Release stored energy. 3. Turn off the engine and remove the ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Chock/block the wheels. LOCK-OUT/TAG-OUT Page 14 ©2011, Waste Management January 2011
  • 791. LOCK-OUT/TAG-OUT PROGRAM CLEANING OUT FROM BEHIND THE PUSH BLADE 1. Set the parking brake. 2. Bring blade forward (towards cab) to relieve any pressure caused by compacted waste. 3. Turn the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Chock/block the wheels. CLEANING OUT THE TOP OF THE HOPPER 1. Set the parking brake. 2. Released stored energy. 3. Turn the engine off and remove ignition key. 4. Turn battery disconnect off and lock/tag-out the disconnect. 5. Chock/block the wheels. 6. Be certain that the blade is completely in the down position so that there is no stored energy in the blade should a hydraulic hose break. ALL DRIVERS: PARK OVER LEVEL SURFACE - PULL PARKING BRAKE WHEN PARKING ON A GRADE, CHOCK WHEELS SWEEPING OUT TRAILERS AT THE LANDFILL 1. Set the parking brake. 2. Turn the engine off and remove ignition key. 3. Place steering wheel cover on steering wheel. 4. Turn battery disconnect off and lock/tag-out the disconnect. 5. Chock/block wheels. CRAWLING UNDERNEATH DETACHED TRAILERS OR UNLOADING TRAILERS 1. Chock at least 2 wheels 2. Place kingpin jack under trailer (do not rely on dolly legs to support trailer). CRAWLING UNDERNEATH A TRUCK FOR ANY REASON 1. Set the parking brake. 2. Release stored energy. 3. Turn off the engine and remove the ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Chock/block the wheels. LOCK-OUT/TAG-OUT Page 15 ©2011, Waste Management January 2011
  • 792. LOCK-OUT/TAG-OUT PROGRAM ALL OPERATORS: PARK VEHICLE ON LEVEL SURFACE ANY WORK BEING DONE ON OR AROUND ONE OF THESE VEHICLES WHEN THE FORKS OR BUCKET IS IN THE AIR 1. Set the parking brake. 2. Turn the engine off and remove ignition key. 3. Turn battery disconnect off and lock/tag-out the disconnect. 4. Put stands underneath the bucket or forks to prevent it from falling to the ground should a hydraulic hose break. CRAWLING UNDERNEATH EQUIPMENT FOR ANY REASON 1. Set the parking brake. 2. Release stored energy. 3. Turn off the engine and remove the ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Chock/block the wheels. WHEN BALER IS NOT IN USE 1. Lockout and tag-out the power supply in the electrical breaker room. 2. Try the on/off switch on the baler to be certain that the power is off. 3. Remove the key from the baler - put key in pocket. WHEN BALER BECOMES JAMMED AND YOU MUST ENTER BALER 1. Lockout and tag-out the power supply in the electrical breaker room. 2. Try the on/off switch on the baler to be certain that the power is off. 3. Remove the key from the baler - put key in pocket. WHEN NORMAL MAINTENANCE MUST BE PERFORMED ON BALER 1. Lockout and tag-out the power supply in the electrical breaker room. 2. Try the on/off switch on the baler to be certain that the power is off. 3. Remove the key from the baler - put key in pocket. LOCK-OUT/TAG-OUT Page 16 ©2011, Waste Management January 2011
  • 793. LOCK-OUT/TAG-OUT PROGRAM AUTHORIZED EMPLOYEES INDEPENDENT AND GROUP LOCK-OUT/TAG-OUT 1. Name: Title: Area: 2. Name: Title: Area: 3. Name: Title: Area: 4. Name: Title: Area: 5. Name: Title: Area: 6. Name: Title: Area: 7. Name: Title: Area: 8. Name: Title: Area: 9. Name: Title: Area: 10. Name: Title: Area: 11. Name: Title: Area: LOCK-OUT/TAG-OUT Page 17 ©2011, Waste Management January 2011
  • 794. LOCK-OUT/TAG-OUT PROGRAM 12. Name: Title: Area: 13. Name: Title: Area: 14. Name: Title: Area: 15. Name: Title: Area: 16. Name: Title: Area: 17. Name: Title: Area: 18. Name: Title: Area: 19. Name: Title: Area: 20. Name: Title: Area: 21. Name: Title: Area: 22. Name: Title: Area: 23. Name: Title: LOCK-OUT/TAG-OUT Page 18 ©2011, Waste Management January 2011
  • 795. LOCK-OUT/TAG-OUT PROGRAM Area: LOCK-OUT/TAG-OUT Page 19 ©2011, Waste Management January 2011
  • 796. ANNUAL OBSERVATION FORM ANNUAL ENERGY CONTROL (LOCK-OUT/TAG-OUT) PROCEDURE REVIEW/OBSERVATION Date of review/observation: _____________________________________________________________ Employee implementing energy control procedure: ___________________________________________ Responsibilities under energy control procedure reviewed: _____________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ Machine/equipment on which energy control was being utilized: _________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ Recommended follow-up: _______________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ____________________________________________________________________________________ ANY DEFICIENCIES NOTED - REQUIRE IMMEDIATE RETRAINING I certify that this inspection was performed as described above. _______________________________________ __________________________________ Printed Name Signature _______________________________ Date LOCK-OUT/TAG-OUT Page 20 ©2011, Waste Management January 2011
  • 797. EMERGENCY REMOVAL OF LOCKS/TAGS EMERGENCY REMOVAL OF LOCKS/TAGS There are occasions that require a lock/tag to be removed from equipment in the absence of the employee that placed that particular lock/tag. The emergency lock/tag removal procedure will be performed by a Manager/Supervisor for the following reasons: 1. Employee calls in sick. 2. The equipment needs to be repaired immediately. 3. Employee sustains an injury and can’t come to work. 4. Suspension/termination from work. 5. Employee is disqualified from his present duties. 6. For any other reason that the Manager/Supervisor deems necessary. In order for a lock/tag to be removed from an equipment when the employee that placed it is not present, the following criteria MUST be fully met: 1. Only a Manager or a Supervisor with the consent of his Manager may remove the lock/tag. 2. The employee that placed the lock/tag MUST be notified of this action prior to the removal if possible; otherwise an attempt has to be made to contact the employee in the presence of a witness and documented. 3. A duplicate key or a master key may not be used. 4. A lock maybe removed only by cutting it. A new lock(s) SHALL be issued when the affected employee returns to duty. The procedures stated above will ensure that the Waste Management employees are fully protected from accidental start up while performing maintenance duties. LOCK-OUT/TAG-OUT Page 21 ©2011, Waste Management January 2011
  • 798. EMERGENCY REMOVAL FORM EMERGENCY REMOVAL FORM In the case where it is necessary to remove an employee’s lock-out/tag-out devise from a piece of equipment or machinery, the following procedure MUST be followed. Only a supervisor, in the presence of another employee, can remove another person's locks and tags. This activity is permitted only under the following conditions: d) Supervisor must verify the employee who put the lock or tag on the equipment is not at the facility. e) The supervisor must inform the employee or make 2-3 attempts by phone that their lock is going to be removed before the employee resumes work at the facility. f) The supervisor must prepare a report explaining why the protective device was removed, when and where it occurred, and how the affected employee was informed prior to starting work. The lock must be removed by way of cutting. At no time is a spare key allowed by any other person other than the person assigned the lock. The cut lock is to be placed into a baggy or envelope including documentation of emergency removal attempt and procedures. The employee must receive a new lock and key upon returning to work. EMPLOYEE CONTACT—1st ATTEMPT ______________________________________ ________________________________________________ Time & Date Phone # Called ______________________________________ ________________________________________________ Signature of manager/supervisor Witness signature EMPLOYEE CONTACT—2nd ATTEMPT ______________________________________ ________________________________________________ Time & Date Phone # Called ______________________________________ ________________________________________________ Signature of manager/supervisor Witness signature CUTTING LOCK ______________________________________ _________________________________________________ Date Removed Time Removed ______________________________________ _________________________________________________ Signature of manager/supervisor cutting lock Witness signature _______________________________________ _________________________________________________ District/Facility Manager Signature Date LOCK-OUT/TAG-OUT Page 22 ©2011, Waste Management January 2011
  • 799. TABLE OF CONTENTS LOCK-OUT/TAG-OUT PROTOCOLS ATTACHMENT DEPARTMENT Pre/Post Trip Inspection (Commercial Vehicles) 1 Operation Working on Truck with Cab in the Raised Position 2 Maintenance Working on Rear of a Rear Loader with the Tailgate in the 3 Maintenance Raised Position Working Under the Raised Tilt Frame of a Roll-Off Truck 4 Maintenance or Trailer Tire Replacement 5 Maintenance Changing Hydraulic or Air Lines 6 Maintenance Working Inside the Body of a Rear Loader 7 Maintenance Performing Various Functions Working Under the 8 Maintenance Vehicle Maintenance, Repairs, or Servicing Recycle Trucks with 9 Operation Bins or Tailgate in the Raised Position Performing Maintenance, Repairs, or Servicing of Trailers 10 Maintenance (Disconnected From Tractor) Performing Maintenance, Repairs, or Servicing of 11 Maintenance Heavy Equipment with Hydraulic Attachments in the Raised Position Performing Maintenance, Repairs, or Servicing on 910, 12 Maintenance 936,966, 980, 988 or any other Loaders with the Bucket in the Lowered Position Performing Maintenance, Repairs, or Servicing on 910, 13 Maintenance 936, 966, 980, 988 or any other Loaders with the Bucket in the Raised Position Performing Maintenance, Repairs, or Servicing of D-8 14 Maintenance Dozer Performing Maintenance, Repairs, or Servicing of D-8 15 Maintenance Dozer with Blade in the Raised Position Performing Maintenance, Repairs, or Servicing of 245 16 Maintenance Excavator Performing Maintenance, Repairs, or Servicing of 17 Maintenance Heavy Equipment with Hydraulic Attachments in the Lowered Position Performing Maintenance, Repairs, or Servicing of 18 Maintenance HI/LO Forklift with Forks in the Lowered Position Performing Maintenance, Repairs, or Servicing of 19 Maintenance HI/LO Forklift with Forks in the Raised Position Performing Maintenance, Repairs, or Servicing of Street 20 Maintenance Sweeper Performing Maintenance, Repairs, or Servicing 21 Maintenance of Street Sweeper with the Hopper in the Raised (Dump) Position LOCK-OUT/TAG-OUT Page 23 ©2011, Waste Management January 2011
  • 800. TABLE OF CONTENTS Performing Maintenance, Repairs, or Servicing Man Lifts 22 Maintenance Performing Maintenance, Repairs, or Servicing on 23 Maintenance Dump Body Trailers with the Box in the Lowered Position Performing Maintenance, Repairs, or Servicing on 24 Maintenance Dump Body Trailers with the Box in the Raised (Dump) Position (EMPTY ONLY) Performing Maintenance, Repairs, or Servicing of 25 Maintenance Wood Grinder Cleaning out Behind the Blade On All Trucks 26 Operation Cleaning Tailgate Seal 27 Operation Cleaning Out Compactor Machine 28 Operation Crawling Under Detached Trailers or Unloading 29 Operation Trailer Roll Off/Drop Box Removing Debris from Box 30 Operation Portable Heater 31 Maintenance Performing Maintenance, Repairs, Servicing or 32 Maintenance Cleaning of Fans Performing Maintenance or Repairs on Building 33 Maintenance Electrical Circuits Ladders 34 Maintenance High PressureToilet 35 Maintenance Residential One Pass Truck Mechanics 36 Maintenance Performing Repairs, Servicing or Cleaning of Impact 37 Maintenance Crusher Unjamming Conveyor Belt or Performing Maintenance, 38 Maintenance Repair, Servicing, or Cleaning Conveyor Pressure Washer 39 Maintenance Residential One Pass Truck When Any Parts of 40 Operation the Drivers’ Body is Going to be Underneath the Raised Tailgate and/or Dislodging Jammed Recyclables Residential One Pass Truck Cleaning Out the Traps on 41 Operation Route or at Disposal Roll Up Bay Doors 42 Maintenance Performing Maintenance, Repairs, or Cleaning of 43 Maintenance Electrical Powered Equipment Air Compressor / Air Lines 44 Maintenance Baler 45 Maintenance Chop Saw 46 Maintenance Crimp Machine 47 Maintenance Drill Press 48 Maintenance Drop Lights 49 Maintenance Filter Buggy 50 Maintenance Floor Buffer 51 Maintenance Floor Scrubber 52 Maintenance Floor Sweeper 53 Maintenance LOCK-OUT/TAG-OUT Page 24 ©2011, Waste Management January 2011
  • 801. TABLE OF CONTENTS Floor, Transmission & Rear Jacks 54 Maintenance Grinders (Air, Bench, Hand) 55 Maintenance Parts Cleaner 56 Maintenance Steam Cleaners 57 Maintenance The Fuel Island 58 Maintenance Tire Brander 59 Maintenance Torches 60 Maintenance Vacuum Cleaner 61 Maintenance Vises 62 Maintenance Welders 63 Maintenance Pickup & Service Trucks 64 Maintenance Roll Off / Drop Box Trucks 65 Operation Sample Lock-out/tag-out Protocol Template 66 Operation/Maint. Training Acknowledgement for Affected Employees 67 Program Administrator Program Review 68 Program Administrator LOCK-OUT/TAG-OUT Page 25 ©2011, Waste Management January 2011
  • 802. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 1 Pre/Post Trip Inspection (Commercial Vehicles) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Chock wheels 6. Turn battery disconnect off and lock/tag-out the disconnect. VERIFY ISOLATION OF EQUIPMENT: Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 26 ©2011, Waste Management January 2011
  • 803. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 2 WORKING ON TRUCK WITH CAB IN THE RAISED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Raise the cab to its full-extended position or utilize the safety legs. VERIFY ISOLATION OF EQUIPMENT: Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 27 ©2011, Waste Management January 2011
  • 804. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 3 WORKING ON REAR OF A REAR LOADER WITH THE TAILGATE IN THE RAISED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Support tailgate with an appropriately rated chain fall or; install cylinder safety lock (sleeve) or; use tailgate stand with adequate base or; use the tailgate props supplied by the manufacturer. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ________________________________________ LOCK-OUT/TAG-OUT Page 28 ©2011, Waste Management January 2011
  • 805. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 4 WORKING UNDER THE RAISED TILT FRAME OF A ROLL OFF TRUCK OR TRAILER. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks lock tilt frame safety leg TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut of the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Lock tilt frame safety leg into place and place a 6” X 6” wood block between the tilt frame and the chassis; or, use the safety leg supplied by the manufacturer and de-energize the hydraulic cylinders. VERIFY ISOLATION OF EQUIPMENT: Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 29 ©2011, Waste Management January 2011
  • 806. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 5 TIRE REPLACEMENT POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Use properly rated jack to lift the unit. 8. Use properly rated jack stand to support the unit in the raised position. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 30 ©2011, Waste Management January 2011
  • 807. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 6 CHANGING HYDRAULIC OR AIR LINES POTENTIAL ENERGY SOURCES: pneumatic chemical reaction electrical flammability heat hydraulic pressure mechanical LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Lock tilt frame safety leg into place and place a 6” X 6” wood block between the tilt frame and the chassis, or; use the safety leg supplied by the manufacturer and de-energize the hydraulic cylinders, or; de-energize the air pressure at its source. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 31 ©2011, Waste Management January 2011
  • 808. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 7 WORKING INSIDE THE BODY OF A REAR LOADER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove the ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 32 ©2011, Waste Management January 2011
  • 809. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 8 PERFORMING VARIOUS FUNCTIONS WORKING UNDER THE VEHICLE POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE VEHICLE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ___________________________________ LOCK-OUT/TAG-OUT Page 33 ©2011, Waste Management January 2011
  • 810. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 9 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING RECYCLE TRUCKS WITH BINS OR TAILGATE IN THE RAISED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut off engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Support bin or tailgate with: a) Appropriately rated chain fall, or; b) Install cylinder safety lock (sleeve), or; c) Use tailgate stand with adequate base, or; d) Block with 6 X 6 wood blocks, or; e) Use the safety pins provided by the manufacturer. **UNDER NO CIRCUMSTANCES ARE DRIVERS/HELPERS ALLOWED TO GO UNDER THE SIDE BINS. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE RECYCLE TRUCK BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 34 ©2011, Waste Management January 2011
  • 811. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 10 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF TRAILERS (Disconnected from Tractor) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Double chock/block the wheels. 2. Place warning tag on equipment. 3. Support with additional jack stands. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE TRAILERS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 35 ©2011, Waste Management January 2011
  • 812. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 11 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF ANY EQUIPMENT WITH HYDRAULIC ATTACHMENTS IN THE RAISED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Shut the engine off and remove ignition key. 4. Place warning tag on equipment. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock or block wheels. 7. Support attachment with; a) appropriately rated chain fall, or; b) install cylinder safety lock (sleeve), or; c) safety stands/wood blocks. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE HEAVY EQUIPMENT BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _______________________________ LOCK-OUT/TAG-OUT Page 36 ©2011, Waste Management January 2011
  • 813. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 12 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING ON 910, 936, 966, 980, 988, OR ANY WHEEL LOADERS WITH THE BUCKET IN THE LOWERED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Lower bucket to the floor. 3. Release stored energy. 4. Turn the engine off and remove ignition key. 5. Place steering wheel cover on steering wheel. 6. Turn battery disconnect off and lock/tag-out the disconnect. 7. Double chock or block wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE 910,936,966,980,988 LOADERS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _______________________________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 37 ©2011, Waste Management January 2011
  • 814. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 13 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING ON 910, 936, 966, 980, 988, OR ANY WHEEL LOADERS WITH THE BUCKET IN THE RAISED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Raise bucket to the desired position, put stand under bucket and lower bucket to the stand or use overhead crane to support the bucket. 3. Install cylinder safety lock (sleeve). 4. If necessary, de-energize all hydraulics. 5. Turn the engine off and remove ignition key. 6. Turn battery disconnect off and lock/tag-out the disconnect. 7. Place steering wheel cover on steering wheel. 8. Double chock or block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE 910,936,966,980,988 LOADERS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: __________________________________ LOCK-OUT/TAG-OUT Page 38 ©2011, Waste Management January 2011
  • 815. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 14 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF D-8 DOZER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set parking brake. 2. Lower the blade to the floor. 3. Neutralize all hydraulics. 4. Shut off the engine and remove ignition key. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Place warning tag on equipment. 7. Block the tracks. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE D-8 DOZER BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: ___________________________________ LOCK-OUT/TAG-OUT Page 39 ©2011, Waste Management January 2011
  • 816. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 15 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF D-8 DOZER WITH THE BLADE IN THE RAISED POSITION. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Raise blade to the desired height. 3. Block up the arms with jack stands or with wood blocks. 4. Lower the arms. 5. If necessary, neutralize the hydraulics. 6. Shut the engine off and remove ignition key. 7. Place out of service tag on equipment. 8. Turn battery disconnect off and lock/tag-out the disconnect. 9. Block the tracks. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE D-8 DOZER BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 3. Notify affected employees that the lock-out/tag-out is being removed. 4. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _________________________________ LOCK-OUT/TAG-OUT Page 40 ©2011, Waste Management January 2011
  • 817. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 16 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF 245 EXCAVATOR POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Lower boom to the ground. 3. Put hydraulic control level to the “off” position (down). 4. De-energize all hydraulics 5. Shut the engine off and remove the ignition key. 6. Turn battery disconnect off and lock/tag-out the disconnect. 7. Place warning tag on equipment. 8. Block tracks. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE EXCAVATOR BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 3. Notify affected employees that the lock-out/tag-out is being removed. 4. Remove lockout devices along with their own locks and tags. Date: _____________________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 41 ©2005, Waste Management January 1, 2005
  • 818. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 17 PERFORMING MAINTENANCE, REPAIRS, OR SERVICING OF HEAVY EQUIPMENT WITH HYDRAULIC ATTACHMENTS IN THE LOWERED POSITION POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Lower boom, or bucket to the ground. 3. De-energize any stored pressure. 4. Shut down the engine and remove keys from the ignition. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Place warning tag on equipment. 7. Double chock/block wheels/tracks. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE HEAVY EQUIPMENT BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 42 ©2005, Waste Management January 1, 2005
  • 819. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 18 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF HI/LO FORKLIFT WITH FORKS IN THE LOWERED POSITION. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Lower forks to the floor. 2. De-energize all hydraulics. 3. Shut down the engine and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. 7. Shut off propane valve at the tank (if equipped). VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE HI/LO FORKLIFT BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ____________________________________ LOCK-OUT/TAG-OUT Page 43 ©2005, Waste Management January 1, 2005
  • 820. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 19 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF HI/LO FORKLIFT WITH FORKS IN THE RAISED POSITION. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Raise forks to the desired height. 3. Support forks with an appropriately rated chain fall, or appropriately rated jack stands. 4. De-energize the hydraulics. 5. Shut down the engine and remove the ignition key. 6. Place steering wheel cover on steering wheel. 7. Turn battery disconnect off and lock/tag-out the disconnect. 8. Double chock/block the wheels. 9. Shut off propane valve at the tank (if equipped). VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE HI/LO FORKLIFT BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date ______________________ Signature__________________________________ LOCK-OUT/TAG-OUT Page 44 ©2005, Waste Management January 1, 2005
  • 821. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 20 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF STREET SWEEPER. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set parking brake. 3. Release stored energy. 4. Shut down the engine and remove ignition key. 5. Place steering wheel cover on steering wheel. 6. Turn battery disconnect off and lock/tag-out the disconnect. 7. Double chock or block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE STREET SWEEPER IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: ___________________________________ LOCK-OUT/TAG-OUT Page 45 ©2005, Waste Management January 1, 2005
  • 822. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 21 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF STREET SWEEPER WITH THE HOPPER IN THE RAISED (DUMP) POSITION. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set parking brake. 2. Raise hopper to the dump position. 3. Install safety legs and lower to its resting position. 4. Release stored energy. 5. Turn of the engine and remove ignition key. 6. Place steering wheel cover on steering wheel. 7. Turn battery disconnect off and lock/tag-out the disconnect. 8. Double chock or block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE STREET SWEEPER IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 46 ©2005, Waste Management January 1, 2005
  • 823. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 22 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF MAN LIFTS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Chock/block/block wheels. 2. Extend boom and lower to the ground. 3. If necessary, release stored energy. 4. Shut down and remove key. 5. Turn battery disconnect off and lock/tag-out the disconnect. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE MAN LIFTS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: ___________________________________ LOCK-OUT/TAG-OUT Page 47 ©2005, Waste Management January 1, 2005
  • 824. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 23 PERFORMING MAINTENANCE, REPAIR OR SERVICING ON DUMP BODY TRAILERS WITH THE BOX IN THE LOWERED POSITION. (Disconnected from Tractor) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Double chock/block wheels. 2. Install safety stand under fifth wheel plate. 3. Place warning tag on equipment. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE DUMP BODY TRAILERS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 48 ©2005, Waste Management January 1, 2005
  • 825. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 24 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF DUMP BODY TRAILERS WITH THE BOX IN THE RAISED (DUMP) POSITION (EMPTY ONLY) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Raise box to the desired height. 3. Install appropriately rated stands under the body. 4. Lower the body onto the stands. 5. Shut the engine off and remove ignition key. 6. De-energize all hydraulics. 7. Place steering wheel cover on steering wheel of tractor. 8. Turn battery disconnect off and lock/tag-out the disconnect. 9. Double chock/block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE DUMP BODY TRAILERS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Signature: __________________ Date: ________________________________________ LOCK-OUT/TAG-OUT Page 49 ©2005, Waste Management January 1, 2005
  • 826. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 25 PERFORMING MAINTENANCE, REPAIR OR SERVICING OF WOOD GRINDER. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Shut down the unit. 2. Remove key at the control panel. 3. Shut down and lock-out/tag-out the main power disconnect. 4. Shut down and lock-out/tag-out the power disconnect at the unit. 5. Install lock-out/tag-out at the control panel. 6. Block or Brace all prime movers, drums, and gears VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE WOOD GRINDER BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Signature: ___________________ Date: _________________________________________ LOCK-OUT/TAG-OUT Page 50 ©2005, Waste Management January 1, 2005
  • 827. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 26 CLEANING OUT BEHIND THE BLADE ON ALL TRUCKS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Extend blade cylinder as far out as possible. 3. Place body on stands (Manual Side Load) 4. Shut down hydraulic pump. 5. Relieve hydraulic pressure from all cylinders. 6. Shut the engine off and remove ignition key. 7. Place steering wheel cover on steering wheel. 8. Chock/block the wheels. 9. Turn battery disconnect off and lock/tag-out the disconnect. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BLADE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 51 ©2005, Waste Management January 1, 2005
  • 828. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 27 CLEANING TAILGATE SEAL POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Extend prop rod to support tailgate. 3. Lower tailgate until it is supported only by the prop rod. 4. Shut the engine off and remove ignition key. 5. Place steering wheel cover on steering wheel. 6. Chock/block the wheels 7. Turn battery disconnect off and lock/tag-out the disconnect. 8. Use a shovel, broom or stick to clean. NEVER GO UNDER A RAISED TAILGATE FOR ANY REASON UNTIL IT IS SUPPORTED. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE: BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: ________________________________________ LOCK-OUT/TAG-OUT Page 52 ©2005, Waste Management January 1, 2005
  • 829. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 28 CLEANING OUT COMPACTOR MACHINE POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Retract ram to the home or fully retracted position. 2. Put blade in the forward position. 3. Release stored energy. 4. Shut down compactor and remove key. 5. Lock-out/tag-out all energy sources. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. 4. Turn circuit breaker “on” and/or plug in equipment. Date: ___________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 53 ©2005, Waste Management January 1, 2005
  • 830. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 29 CRAWLING UNDER DETACHED TRAILERS OR UNLOADING TRAILER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Chock/block at least 2 wheels. 2. Place kingpin jack under trailer (do not rely on dolly legs to support trailer). VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Signature: ____________________ Date: ________________________________________ LOCK-OUT/TAG-OUT Page 54 ©2005, Waste Management January 1, 2005
  • 831. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 30 ROLL OFF /DROP BOX REMOVING DEBRIS FROM BOX POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Lower box to ground. 2. Set the parking brake. 3. Release stored energy including all tension from cable. 4. Turn the engine off and remove the ignition key. 5. Place steering wheel cover on steering wheel. 6. Turn battery disconnect off and lock/tag-out the battery disconnect. 7. Double chock/block the wheels. NEVER ENTER ANY BOX WHILE ELEVATED VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE COMPACTOR BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. 4. Turn circuit breaker “on” and/or plug in equipment. Date: ________________________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 55 ©2005, Waste Management January 1, 2005
  • 832. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 31 PORTABLE HEATER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn “off” the heater and unplug the unit. 2. Place lockout plug device and lockout. 3. Place an “out of service” sign on unit. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove the plug lock out device. 4. Remove the “out of service” sign. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 56 ©2005, Waste Management January 1, 2005
  • 833. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 32 PERFORMING MAINTENANCE, REPAIR, SERVICING, OR CLEANING OF FANS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn “off” fan. 2. Turn “off” circuit breaker or unplug and utilize the appropriate lock-out/tag-out device. 3. Test lockout by turning fan “on” and verify that the fan is de-energized. 4. Place an “out of service” tag on the fan. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE THE FAN BACK IN SERVICE: Inspect the equipment to be sure that: 1. All tools and other materials are removed. 2. Machine/equipment is fully reassembled. 3. Guards and other safety devices are installed. 4. Remove the lockout device and plug in or turn “on” circuit breaker for the fan. 5. Remove the “out of service” tag. Date: ___________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 57 ©2005, Waste Management January 1, 2005
  • 834. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 33 PERFORMING MAINTENANCE OR REPAIR ON BUILDING ELECTRICAL CIRCUITS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Shut off electricity at the circuit breaker. 2. Install circuit breaker lockout cleat. 3. Install lockout tag on circuit panel. 4. Test circuit breaker to ensure power is off. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BUILDING ELECTRICAL CIRCUITS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. 4. Turn circuit breaker in the “on” position. Date: ______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 58 ©2005, Waste Management January 1, 2005
  • 835. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 34 LADDERS Mechanical Gravity LOCKOUT METHOD(S): Chain Tape TAG-OUT METHOD(S): Out of service tag/sign Caution tape SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Wrap a chain or tape around the ladder in such a way as to render it unusable. 2. Tag “out of service.” ****NOTE:**** If the ladder cannot be placed back in service, destroy it and throw it out. g) h) PROCEDURES TO PLACE LADDERS BACK IN SERVICE: Inspect the ladder to be sure it’s safe to put back in service. Remove the tape or chain. Remove the “out of service” tag. Signature: _____________________________________ Date: ________________________________________ LOCK-OUT/TAG-OUT Page 59 ©2005, Waste Management January 1, 2005
  • 836. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 35 HIGH PRESSURE TOILET POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical water pressure LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn “off” water at the valve closest to the toilet. 2. Install the valve lockout device and lockout. 3. Drain the tank. 4. Tag the toilet “out of service” or cord off the area with caution tape. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO THE TOILET BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Remove the valve lockout device and turn the valve “on”. 3. Remove the “out of service” sign and/or caution tape. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 60 ©2005, Waste Management January 1, 2005
  • 837. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 36 RESIDENTIAL ONE PASS TRUCK (MECHANICS) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Turn the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the disconnect. 6. Double chock/block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 61 ©2005, Waste Management January 1, 2005
  • 838. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 37 PERFORMING REPAIR, SERVICING, OR CLEANING OF IMPACT CRUSHER. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Shut down main control panel and apply lock-out/tag-out. 2. Shut down the main electrical box and apply lock-out/tag-out. 3. Release stored energy. 4. Try the “on/off” switch on crusher to be certain power is “off”. 5. Place “out of service” sign and if necessary use caution tape. 6. Block or Brace all prime movers, drums, and gears VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE IMPACT CRUSHER BACK IN SERVICE: 1. Inspect the Crusher to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 62 ©2005, Waste Management January 1, 2005
  • 839. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 38 UNJAMMING CONVEYOR BELT OR PERFORMING MAINTENANCE, REPAIR, SERVICING OR CLEANING OF CONVEYOR. POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Shut down main control panel and apply lock-out/tag-out. 2. Shut down the main electrical box and apply lock-out/tag-out. 3. Release stored energy. 4. Try the “on/off” switch on crusher to be certain power is “off”. 5. Place “out of service” sign and if necessary use caution tape. 6. Block or Brace all prime movers, drums, and gears VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE CONVEYOR BELT BACK IN SERVICE: 1. Inspect the conveyor belt to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 63 ©2005, Waste Management January 1, 2005
  • 840. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 38 LOCK-OUT/TAG-OUT Page 64 ©2005, Waste Management January 1, 2005
  • 841. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 39 PRESSURE WASHER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical water pressure LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks remove spark plug and gas TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn pressure washer “off”. 2. Turn off soap and water supply valves and place valve lock-out/tag-out. 3. Relieve any existing pressure in the spray hose or nozzle. 4. Remove spark plug and, if necessary, the gas. 5. Place an “out of service” sign. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 65 ©2005, Waste Management January 1, 2005
  • 842. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 40 RESIDENTIAL ONE PASS TRUCK WHEN ANY PART OF THE DRIVERS’ BODY IS GOING TO BE UNDERNEATH THE RAISED TAILGATE AND/OR DISLODGING JAMMED RECYCLABLES POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Shut engine off and remove ignition key. 3. Place steering wheel cover on steering wheel. 4. Chock/block the wheels 5. Turn battery disconnect off and lock-out/tag-out disconnect. 6. Support bin or tailgate with: a) Appropriately rated chain fall, or; b) Install cylinder safety lock (sleeve), or; c) Use tailgate stand with adequate base, or; d) Block with 6 X 6 wood blocks, or; e) Use the safety pins provided by the manufacturer. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 66 ©2005, Waste Management January 1, 2005
  • 843. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 41 RESIDENTIAL ONE PASS TRUCK CLEANING OUT THE TRAPS ON ROUTE OR AT DISPOSAL POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Place the trucks safety props in the stands. 3. Release stored energy. 4. Turn of the engine and remove the ignition key. 5. Place steering wheel cover on steering wheel. 6. Chock/block the wheels. 7. Turn battery disconnect off and lock/tag-out the disconnect. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE VEHICLE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: ___________________________________ LOCK-OUT/TAG-OUT Page 67 ©2005, Waste Management January 1, 2005
  • 844. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 42 ROLL UP BAY DOORS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: ** Note ** Service on doors will primarily be conducted by an outside contractor. 1. Place door in the desired servicing position. 2. Turn “off” the circuit breaker and place a circuit breaker lockout device and lock-out/tag-out. 3. Place a mechanical locking rod in position to stop door from moving. 4. Place an “out of service” sign and if necessary use caution tape. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the roll up bay door to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Remove the mechanical locking rod. 3. Remove the circuit breaker lockout device and turn circuit breaker to “on.” 4. Remove “out of service” sign and caution tape. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 68 ©2005, Waste Management January 1, 2005
  • 845. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 43 PERFORMING MAINTENANCE, REPAIR, OR CLEANING OF ELECTRICAL POWERED EQUIPMENT POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Unplug equipment and/or shut down electricity at the circuit breaker. 2. Install plug lock-out/tag-out or circuit breaker lockout cleat. 3. Test equipment by turning switch to the “on” position. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. 4. Turn circuit breaker “on” and/or plug in equipment. Date: ______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 69 ©2005, Waste Management January 1, 2005
  • 846. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 44 AIR COMPRESSORS/AIR LINES POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn “off” air compressor at the circuit breaker or remove plug. 2. Install a circuit breaker lockout device or plug lockout device and lock out. 3. If servicing just the compressor, turn air line valve “off” and place valve lockout device and lock out/tag-out. 4. Drain system (lines and tank) of any pressurized air. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 70 ©2005, Waste Management January 1, 2005
  • 847. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 45 BALER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks remove key TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Shut down power supply and lock-out/tag-out. 2. Try the “on/off” switch on the baler to be certain that the power is “off.” 3. Remove the key from the baler – put key in pocket. 4. install “out of service” tag 5. Block or Brace all prime movers, drums, and gears VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 71 ©2005, Waste Management January 1, 2005
  • 848. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 46 CHOP SAW POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn chop saw off. 2. Unplug chop saw and place the plug into a plug lockout device. Test the lockout by depressing the trigger. 3. Place an “out of service” tag on the chop saw. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE CHOP SAW BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 72 ©2005, Waste Management January 1, 2005
  • 849. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 47 CRIMP MACHINE POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off the crimp machine. 2. Unplug the crimp machine and place the plug in a plug lockout device. 3. Place an “out of service” sign on the crimper. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 73 ©2005, Waste Management January 1, 2005
  • 850. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 48 DRILL PRESS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off the drill press and let it return to the stop. 2. Unplug the press and place plug in a plug lockout device. 3. Place and “out of service” sign on the drill press. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE DRILL PRESS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 74 ©2005, Waste Management January 1, 2005
  • 851. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 49 DROP LIGHTS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off the droplight. 2. Unplug or turn off circuit breaker and utilize the appropriate lockout device. Verify lockout by turning light on. 3. Tag the light “out of service.” VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE DROP LIGHTS BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 75 ©2005, Waste Management January 1, 2005
  • 852. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 50 FILTER BUGGY POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off the filter buggy. 2. Unplug the filter buggy and place plug in a plug lockout device. 3. Place an “out of service” tag on the filter buggy. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE FILTER BUGGY BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 76 ©2005, Waste Management January 1, 2005
  • 853. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 51 FLOOR BUFFER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Unplug the floor buffer and place plug in a plug lockout device. 2. Place an “out of service” tag on the floor buffer. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ signature: _____________________________________ LOCK-OUT/TAG-OUT Page 77 ©2005, Waste Management January 1, 2005
  • 854. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 52 FLOOR SCRUBBER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks disconnect battery cable TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn floor scrubber off. 2. Disconnect the battery cables and place them in a plug lockout device. 3. Place an “out of service” sign on the floor scrubber. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE FLOOR SCRUBBER BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 78 ©2005, Waste Management January 1, 2005
  • 855. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 53 FLOOR SWEEPER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks remove battery cables TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn floor sweeper off. 2. Disconnect battery cables and place them in a plug lockout device. 3. Place an “out of service” sign on the sweeper. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE FLOOR SWEEPER BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 79 ©2005, Waste Management January 1, 2005
  • 856. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 54 FLOOR, TRANSMISSION & REAR JACKS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks chain TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Lower jack all the way by opening the bleeder valve. 2. Remove the air nipple if jack is air activated. If not, wrap a chain around the jack in such a way as to make it impossible to use. 3. Tag the jack “out of service.” VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 80 ©2005, Waste Management January 1, 2005
  • 857. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 55 GRINDERS (AIR/BENCH/HAND) POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off grinder. 2. Unplug (electric) and place plug in a plug lockout device or disconnect the air supply line (pneumatic) and remove the air nipple. 3. Verify that the grinder is not energized by turning on or depressing the trigger. 4. Tag grinder “out of service.” VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 81 ©2005, Waste Management January 1, 2005
  • 858. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 56 PARTS CLEANER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout plug lockout remove air fitting/nipple wheel chock/blocks chain/tape shut TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off solvent circulator pump. 2. Unplug pump and place plug in a plug lockout device. 3. Remove parts cleaner machine from the solvent storage drum, cover drum. 4. Tag “out of service.” VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ___________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 82 ©2005, Waste Management January 1, 2005
  • 859. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 57 STEAM CLEANERS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical water pressure LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn steam cleaner off. 2. Turn off the circuit breaker and the water, natural gas and soap supply valves. 3. Place a lock on the circuit breaker box and valve lockout devices on the soap and water supply valves. 4. Place an “out of service” tag on the steam cleaner. 5. Drain the system of any pressurized water. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 3. Notify affected employees that the lock-out/tag-out is being removed. 4. Remove lockout devices along with their own locks and tags. Date: __________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 83 ©2005, Waste Management January 1, 2005
  • 860. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 58 THE FUEL ISLAND POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Turn off pump and shut off circuit breaker. 2. Place a circuit breaker lockout device on the circuit breaker. 3. Verify that the pump is locked out using the pump-dispensing nozzle into an approved container. If appropriate, lockout dispensing nozzles. 4. Place an “out of service” sign at the fuel island. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 84 ©2005, Waste Management January 1, 2005
  • 861. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 59 TIRE BRANDER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Unplug tire brander and allow to cool. 2. Place the plug in a plug lockout device. 3. Place an “out of service” tag on the tire brander. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 85 ©2005, Waste Management January 1, 2005
  • 862. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 60 TORCHES POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. install “out of service” tag 2. Remove torch head from hoses. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 86 ©2005, Waste Management January 1, 2005
  • 863. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 61 VACUUM CLEANER POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. install “out of service” Tag 2. Disconnect power cord and lock out with lock out device. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _____________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 87 ©2005, Waste Management January 1, 2005
  • 864. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 62 VISES POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. install “out of service” sign 2. Remove from work area. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 88 ©2005, Waste Management January 1, 2005
  • 865. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 63 WELDERS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Disconnect power source. 2. Place “out of service” tag 3. Test unit for any stored energy VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: ________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 89 ©2005, Waste Management January 1, 2005
  • 866. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 64 PICKUP & SERVICE TRUCKS POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Shut the engine off and remove ignition key. 3. Place steering wheel cover on steering wheel. 4. Double chock/block wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _________________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 90 ©2005, Waste Management January 1, 2005
  • 867. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 65 Roll off / Drop box Trucks POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. Set the parking brake. 2. Release stored energy. 3. Turn the engine off and remove ignition key. 4. Place steering wheel cover on steering wheel. 5. Turn battery disconnect off and lock/tag-out the battery disconnect. 6. Double chock/block the wheels. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. Inspect the equipment to be sure that: a. All tools and other materials are removed. b. Machine/equipment is fully reassembled. c. Guards and other safety devices are installed. 2. Notify affected employees that the lock-out/tag-out is being removed. 3. Remove lockout devices along with their own locks and tags. Date: _______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 91 ©2005, Waste Management January 1, 2005
  • 868. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 66 Template POTENTIAL ENERGY SOURCES: air pressure chemical reaction electrical flammability heat hydraulic pressure mechanical gravity LOCKOUT METHOD(S): battery disconnect circuit lockout handle/valve lockout remove air fitting/nipple wheel chock/blocks plug lockout TAG-OUT METHOD(S): Do Not Start Tag Do Not Energize Tag Do Not Open Tag Do Not Operate Tag Do Not Close Tag Steering Wheel Cover (Do Not Operate or Start) SHUTDOWN PREPARATION: Authorized employees will: Identify all sources of energy supplying the system, the types of hazards they present, how to control them, and how to verify the hazardous energy is not present. Notify all affected employees about the lockout. SPECIFIC LOCK-OUT/TAG-OUT PROCEDURES: 1. 2. 3. 4. VERIFY ISOLATION OF EQUIPMENT Authorized employees will: Make sure no one is exposed to any areas of danger. Verify, using appropriate test equipment, or other means, that all the energy sources are controlled, dissipated, and disconnected, including the main disconnect switch or circuit breaker. Operate the start buttons and other equipment controls to make certain the equipment will not operate. Return all operating controls to their “off” or safe position after the test is completed. PROCEDURES TO PLACE BACK IN SERVICE: 1. 2. 3. Date: _______________________ Signature: _____________________________________ LOCK-OUT/TAG-OUT Page 92 ©2005, Waste Management January 1, 2005
  • 869. CONTROL OF HAZARDOUS ENERGY-LOCK-OUT/TAG-OUT Lock Out Tag Out Training Acknowledgement for Affected Employees I understand that as an affected employee I have received instruction in the purpose and use of the energy control procedure, the prohibition of removing locks or tags or attempts to restart equipment that has been locked out or tagged. _______________________________ _____________________________ Employee Name Employee Signature ___________________________ Date ____________________________ Trainer CONTROL OF HAZARDOUS ENERGY-LOCK-OUT/TAG-OUT Page 93 ©2005, Waste Management January 1, 2005
  • 870. CONTROL OF HAZARDOUS ENERGY PROTOCOLS – ATTACHMENT 66 Date of Signature Comments – Changes to Program Review LOCK-OUT/TAG-OUT Page 94 ©2005, Waste Management January 1, 2005
  • 871. HEARING CONSERVATION PROGRAM Program: Hearing Conservation Program Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 Site Manager: Joe Whelan PURPOSE To describe the Hearing Conservation Program requirements when employees are exposed to noise in excess of levels specified by OSHA 1910.95 Occupation Noise Exposure. SCOPE This procedure applies to all employees who may be exposed to noise levels above what OSHA regulatory requirements specify. EXCLUSIONS Employees whose noise exposure is less than 85-dBA time weighted over an 8-hour day or 50% equivalent dose. DOT regulated drivers are excluded from requirements for wearing hearing protectors and participating in OSHA Hearing Conservation Programs. DOT requires interior cab noise levels to be 90 dBA or less. This does not preclude the facility from implementing appropriate practices. RESPONSIBILITIES The District Manager is responsible for administering the Hearing Conservation Program. This person: Oversees the program. Ensures that hearing protection is available. Arranges for noise monitoring and audiometric tests as needed. Reviews the program on an annual basis. Provides employee training. Posts notification in areas requiring hearing protection. Checks that employees wear their hearing protection properly. Waste Management supervisors are responsible for ensuring employees properly wears hearing protection in required areas, ensuring noisy areas are posted and personnel are following the requirements of this program. Hearing Conservation Program Page 1 ©2011, Waste Management January 2011
  • 872. HEARING CONSERVATION PROGRAM Waste Management employees must wear hearing protection properly where required and keep it clean and well maintained. Employees should tell their supervisors about work areas they believe are too noisy that may need monitoring or posting. NOISE MONITORING Waste Management conducts personal and/or area noise monitoring as needed to determine which areas have noise levels above eighty-five dBA or above a fifty percent dose for an eight- hour shift. A noise survey to determine areas of potential over-exposure should be conducted prior to personal noise dosimetry. OSHA requires use of the A-weighted decibel scale to determine compliance. Area monitoring may be used to identify work areas, such as areas around pumps, motors, heavy equipment, or compressors, where workers must wear hearing protection. Personal noise monitoring determines which employees to include in the Hearing Conservation Program. Noise monitoring is important in determining which type of hearing protection will best protect hearing. Until or unless site specific monitoring finds differently, all monitoring for site specific tasks performed by Waste Managment that indicate exposures above or equal to 85dBA TWA or equivalent will take precedence. Each employee exposed at or above an 8-hour time-weighted average of 85 decibels will be notified of the results of the monitoring. CONTROL MEASURES The permissible noise level for OSHA compliance is ninety decibels on the A-weighted scale for an eight-hour, time-weighted average (TWA). If the noise levels exceed ninety dBA, Waste Management must implement appropriate administrative or engineering controls. The OSHA action level for noise exposure is eighty-five dBA for an eight-hour TWA. If any Waste Management employee has a noise exposure that equals or exceeds the action level, a Hearing Conservation Program is mandatory. The facility will maintain a list of employees entered into the Hearing Conservation Program. The list is located with the Hearing Conservation Program binder. Employees in areas of the facility where the eight-hour TWA noise level equals or exceeds eighty-five dBA, but is below ninety dBA, receive hearing protection. Use of hearing protection is recommended. However, if annual audiometric examination reveals a decline in the employee's hearing ability, the use of hearing protection becomes mandatory. Any employee who is exposed to an eight-hour TWA of eighty-five dBA or greater who has not yet had a baseline audiogram, must wear hearing protection. Hearing Conservation Program Page 2 ©2011, Waste Management January 2011
  • 873. HEARING CONSERVATION PROGRAM Employees working in areas of the plant where the eight-hour TWA is ninety dBA or higher must wear appropriate hearing protection at all times. AUDIOMETRIC TESTING TESTING Employees exposed above the action level will be included in Waste Management Hearing Conservation Program and given a baseline audiogram within 180 days of beginning work. An audiogram is a chart, graph, or table that displays the results of an audiometric test. Audiograms show an individual’s hearing threshold levels as a function of frequency. The initial audiogram becomes a baseline against which future audiograms are compared to determine if hearing loss has occurred. An employee’s annual audiogram is compared to the baseline audiogram to determine if loss constitutes a standard threshold shift (STS). An STS is a change in hearing threshold relative to the baseline audiogram of more than ten dB or more at 2000, 3000, and 4000-hertz (Hz) in either ear. OSHA requires reporting of all work-related STS's with an average of ten dB or more at 2000, 3000, and 4000 Hz in either ear on the OSHA 300 log as an occupational illness. In determining whether a standard threshold shift has occurred, allowance may be made for the contribution of aging (presbycusis) to the change in hearing level by correcting the annual audiogram. A licensed or certified audiologist, or a physician or technician who is certified by the Council of Accreditation in Occupational Hearing Conservation, must perform the audiogram. MAINTAINING RECORDS Waste Management is responsible for maintaining records of noise measurements and audiometric testing for prescribed lengths of time: Area noise measurements—two years. Audiometric test records—the duration of the worker’s employment. The audiometric test provider should maintain these records for Waste Management. Audiometric test records must include: The name and job classification of the employee The date of the test The audiometric examiner’s name The date of acoustic calibration Measurements of background sound pressure levels in audiometric test rooms. (The testing company usually retains this information). If an employee incurred hearing loss prior to employment, proper medical documentation must be on file. Hearing Conservation Program Page 3 ©2011, Waste Management January 2011
  • 874. HEARING CONSERVATION PROGRAM EMPLOYEE NOTIFICATION Waste Management must notify all affected employees of personal and area monitoring results. The contract physician provides interpretation of the audiometric test results to the employee. Retain copies of this form in the employee’s personnel file. If the comparison of the annual audiogram to the baseline audiogram indicates an STS has occurred, Waste Management must inform the employee in writing within twenty-one days. The audiometric tester should explain the results of the audiogram to each employee. Any employee whose audiogram indicates an STS may be re-tested within thirty days. Waste Management can use the results from the retest as the annual audiogram. If a physician determines the STS is work related, the supervisor must take the following steps: Fit and train an employee who has not been wearing hearing protectors in the use and care of hearing protection. Refit an employee already wearing protection with protectors with a higher level of protection (attenuation) and retrain him or her in the proper use of hearing protection. Refer the employee for a clinical audiological evaluation if wearing hearing protection causes or aggravates the problem. If subsequent audiometric testing of an employee indicates that an STS is not persistent, Waste Management must inform the employee of this. HEARING PROTECTORS Waste Management employees in work areas where the noise level is over the action level (eighty-five dBA, eight-hour TWA) receive hearing protection. Workers can select hearing protection from a variety of types with the proper attenuation. The hearing protectors are available at each work location. All hearing protection devices will have a noise reduction rating (NRR) of twenty or greater. Hearing protection must reduce employee exposure to less than eight-five dBA. Hearing protectors are: Supplied at no cost to employees in the Hearing Conservation Program. Replaced as necessary. Hearing Conservation Program Page 4 ©2011, Waste Management January 2011
  • 875. HEARING CONSERVATION PROGRAM EMPLOYEE INFORMATION As part of the Hearing Conservation Program, Waste Management will post signs at the entrance to all rooms or work areas where the noise level exceeds eighty-five dBA. The signs say: Hearing Protection Required Beyond This Point, or equivalent. Waste Management will provide access to a copy of the OSHA Noise Standard by posting it in a prominent location. Supervisors should instruct employees who operate mobile equipment (such as drilling or trenching equipment) to wear hearing protection. Affected employees or their representatives have access to copies of this standard and a copy of the standard is also posted at the work location. TRAINING (Refer to Appendix A) Employees exposed to noise above eighty-five dBA will be trained annually. Training is to cover all of the requirements of the OSHA noise standard, including: The effects of noise on hearing The purpose, advantages, and disadvantages of various types of hearing protectors The selection, fitting, and care of protectors The purpose and procedures of audiometric testing The attenuation of different types of protection and what this means in terms of noise reduction. RECORDKEEPING RETENTION Waste Management shall retain records required in this program for at least the following periods: Noise exposure measurement records shall be retained for two (2) years. Audiometric tests records shall be retained for the duration of the affected employee’s employment. ACCESS All records required by this section shall be provided upon request to employees, former employees, and representatives designated by the individual employee. Hearing Conservation Program Page 5 ©2011, Waste Management January 2011
  • 876. HEARING CONSERVATION PROGRAM ENFORCE THE PROGRAM Consistent enforcement of the Hearing Conservation Program is important. The message needs to be conveyed that the use of hearing protection is strictly required in some areas. All persons in hearing protection areas, including visitors, managers, and office employees, must wear required hearing protection devices. REVIEW THE PROGRAM ANNUALLY The program administrator conducts an annual review of the Hearing Conservation Program. The review addresses the following: Monitoring Review previous monitoring results. Identify areas with altered or changed equipment or processes and arrange for monitoring in these areas. Arrange for monitoring in these areas and areas where monitoring has not been performed within a year. Audiometric Testing Review audiometric results for all employees. Check to determine if repeat testing for employees who show an STS has been performed. If not, arrange for repeat testing. Arrange for all employees working in areas where the noise level is above the action level to have audiometric testing annually. Review Hearing Loss Patterns Recognize jobs that seem to cause hearing loss. List employees who show a loss of hearing above twenty-five dB (Standard Threshold Shift) on the OSHA 300 log as an occupational illness. Identify Potential Hearing Loss Causes Do employees wear their hearing protection? Do they wear hearing protection properly? Is the protection sufficient? Has noise increased in the work area? Was this increase caused by the addition of new equipment? Was this increase caused by old equipment becoming noisier? Implement Additional Controls Reduce noise sources with an engineering control. Document any noise abatement activity. Get different hearing protectors. Conduct additional training in the correct use of hearing protection. Hearing Conservation Program Page 6 ©2011, Waste Management January 2011
  • 877. HEARING CONSERVATION PROGRAM Enforce the use of hearing protection. Retrain and issue hearing protection with a higher protection level to any employee showing hearing loss. If these employees continue to show an occupationally related hearing loss over two consecutive years, place them in a new job without a noise hazard. Make a list of the names of the persons included in the Hearing Conservation Program. Hearing Conservation Program Page 7 ©2011, Waste Management January 2011
  • 878. HISTORICAL NOISE LEVEL AND EXPOSURE DATA Average Exposure Exposure Range (dBA) (dBA) Avg. Dose % Dose Range % Hauling Driver – Commercial 86 76 – 90 79 19 - 151 Driver – Dump Truck 78 69 – 88 27 5 – 34 Driver – Recycle 85 81 – 91 70 9 – 138 Driver – REL 85 83 – 87 57 42 – 81 Driver – Residential 87 82 – 99 92 2 – 481 Driver – Roll-Off 87 76 – 92 103 18 – 191 Driver – Semi-Truck 86 83 – 88 68 28 – 101 Driver – Sweeper 86 83 – 90 80 39 – 119 Drivers – Overall 86 71 – 99 78 2 – 481 Landfill/Transfer Driver – Site Truck 84 78 – 89 43 18 – 85 Driver – Water Truck 84 70 – 91 103 18 – 192 Gas Plant/Gas Recovery 90 82 – 98 102 22 – 316 Laboratory Personnel 78 56 – 90 36 0.4 – 299 Loaders – Transfer/Tipping 86 70 – 95 71 4 – 299 Operator – Compactor 91 91 115 96 – 134 Operator – Landfill Equip. 85 64 – 99 79 3 – 319 Spotter – Transfer / Tipping 85 71 – 93 57 6 – 131 Maintenance Mechanic – Hauling/Landfill 81 69 – 96 35.8 3 – 236 Mechanic – MRF 83 69 – 89 52 4 – 94 Tire Men 83 71 – 88 57 8 – 91 Material Recovery Facility Baler Operator 87 76 – 104 77 13 – 200 Forklift/Bobcat Operator 87 81 – 93 73 54 – 187 Sorters 88 72 – 103 101 1.9 – 1243 Ticket Collector MRF 87 86 – 87 69 56 – 88 Note: 8-Hour Average Exposures of 85 dBA or Greater (or 50% of the Allowable Dose) Require Hearing Conservation Training, Audiograms and the Availability of Hearing Protection. 8-Hour Average Exposures of 90 dBA or Greater (or 100% of the Allowable Dose) Require Mandatory Use of Hearing Protection in Addition to Other Hearing Conservation Program Requirements. If the Data Above Indicates Excessive Exposures, Implement Hearing Conservation OR Conduct Monitoring to Determine the Specific Exposures at Your Location. Send a Copy of the Results to Corporate Safety. DOT Drivers are Covered by 49 CFR 394 Inside of Their Cabs, and Not 29 CFR 1910.95. They Must Not Wear Hearing Protection While Driving on Public Roadways Hearing Conservation Program Page 8 ©2011, Waste Management January 2011
  • 879. HISTORICAL NOISE LEVEL AND EXPOSURE DATA DOCUMENT REVIEW RECORD Use this form to document plan reviews and plan revisions. Date Reviewer’s Signature Plan Revisions Made Hearing Conservation Program Page 9 ©2011, Waste Management January 2011
  • 880. HEARING CONSERVATION PROGRAM §29 CFR 1910.95 OCCUPATIONAL NOISE EXPOSURE. (a) Protection against the effects of noise exposure shall be provided when the sound levels exceed those shown in Table G-16 when measured on the A scale of a standard sound level meter at slow response. When noise levels are determined by octave band analysis, the equivalent A-weighted sound level may be determined as follows: Equivalent sound level contours. Octave band sound pressure levels may be converted to the equivalent A-weighted sound level by plotting them on the graph and noting the A-weighted sound level corresponding to the point of highest penetration into the sound level contours. This equivalent A-weighted sound level, which may differ from the actual A-weighted sound level of the noise, is used to determine exposure limits from Table 1.G-16. (b)(1) When employees are subjected to sound exceeding those listed in Table G-16, feasible administrative or engineering controls shall be utilized. If such controls fail to reduce sound levels within the levels of Table G-16, personal protective equipment shall be provided and used to reduce sound levels within the levels of the table. (2) If the variations in noise level involve maximums at intervals of 1 second or less, it is to be considered continuous. Table G-16. -- Permissible Noise Exposures{1}. ------------------------------------------------------------ Sound level dBA Duration per day, hours slow response ------------------------------------------------------------ 8 90 6 92 4 95 3 97 2 100 1 1/2 102 1 105 1/2 110 1/4 or less 115 ---------------------------------------------------------------------- {1} When the daily noise exposure is composed of two or more periods of noise exposure of different levels, their combined effect should be considered, rather than the individual effect of each. If the sum of the following factions: C(1) / T(1) + C(2) / T(2) C(n) / T(n) exceeds unity, then the mixed exposure should be considered to exceed the limit value. C(n) indicates the total time of exposure at a specified noise level, and T(n) indicates the total time of exposure permitted at the level. Exposure to impulsive or impact noise should not exceed 140 dB peak sound pressure level. (b) Hearing Conservation Program. Hearing Conservation Program Page 10 ©2011, Waste Management January 2011
  • 881. HEARING CONSERVATION PROGRAM (1) The employer shall administer a continuing, effective Hearing Conservation Program, as described in paragraphs (c) through (o) of this section, whenever employee noise exposures equal or exceed an 8-hour time-weighted average sound level (TWA) of 85 decibels (2) measures on the A scale (slow response) or, equivalently, a dose of fifty percent. For purposes of the Hearing Conservation Program, employee noise exposures shall be computed in accordance with Appendix A and Table G-16a, and without regard to any attenuation provided by the use of personal protective equipment. (3) For purposes of paragraphs (c) through (n) of this section, an 8-hour time-weighted average of 85 decibels or a dose of fifty percent shall also be referred to as the action level. (d) Monitoring. (1) When information indicates that any employee's exposure may equal or exceed an 8-hour time-weighted average of 85 decibels, the employer shall develop and implement a monitoring program. (i) The sampling strategy shall be designed to identify employees for inclusion in the hearing conservation program and to enable the proper selection of hearing protectors. (ii) Where circumstances such as high worker mobility, significant component of impulse noise make area monitoring generally inappropriate, the employer shall use representative personal sampling to comply with the monitoring requirements of this paragraph unless the employer can show that area sampling produces equivalent results. (2) (i) All continuous, intermittent and impulsive sound levels from 80 decibels to 130 decibels shall be integrated into the noise measurements. (ii) Instruments used to measure employee noise exposure shall be calibrated to ensure measurement accuracy. (3) Monitoring shall be repeated whenever a change in production, process, equipment or controls increases noise exposures to the extent that: (i) Additional employees may be exposed at or above the action level; or (ii) The attenuation provided by hearing protectors being used by employees may be rendered inadequate to meet the requirements of paragraph (j) of this section. (e) Employee notification. The employer shall notify each employee exposed at or above an 8- hour time-weighted average of 85 decibels of the results of the monitoring. (f) Observation of monitoring. The employer shall provide affected employees or their representatives with an opportunity to observe any noise measurements conducted pursuant to this section. (g) Audiometric testing program. (1) The employer shall establish and maintain an Audiometric testing program as provided in this paragraph by making Audiometric testing available to all employees whose exposures equal or exceed an 8-hour time-weighted average of 85 decibels. (2) The program shall be provided at no cost to employees. Audiometric tests shall be performed by a licensed or certified audiologist, otolaryngologist, or other physician, or by a technician who is certified by the Council of Accreditation in Occupational Hearing Conservation, or who has satisfactorily demonstrated competence in administering Audiometric examinations, obtaining valid Audiograms, and properly using, maintaining and checking calibration and proper functioning of the audiometers being used. Hearing Conservation Program Page 11 ©2011, Waste Management January 2011
  • 882. HEARING CONSERVATION PROGRAM (3) A technician who operates microprocessor audiometers does not need to be certified. A technician who performs Audiometric tests must be responsible to an audiologist, otolaryngologist or physician. (4) All Audiograms obtained pursuant to this section shall meet the requirements of Appendix C: Audiometric Measuring Instruments. (5) Baseline Audiogram. (i) Within 6 months of an employee's first exposure at or above the action level, the employer shall establish a valid baseline Audiogram against which subsequent Audiograms can be compared. (ii) Mobile test van exception. Where mobile test vans are used to meet the Audiometric testing obligation, the employer shall obtain a valid baseline Audiogram within 1 year of an employee's first exposure at or above the action level. Where baseline Audiograms are obtained more than 6 months after the employee's first exposure at or above the action level, employees shall wearing hearing protectors for any period exceeding six months after first exposure until the baseline Audiogram is obtained. (iii) Testing to establish a baseline Audiogram shall be preceded by at least 14 hours without exposure to workplace noise. Hearing protectors may be used as a substitute for the requirement that baseline Audiograms be preceded by 14 hours without exposure to workplace noise. (iv) The employer shall notify employees of the need to avoid high levels of non- occupational noise exposure during the 14-hour period immediately preceding the Audiometric examination. (6) Annual Audiogram. At least annually after obtaining the baseline Audiogram, the employer shall obtain a new Audiogram for each employee exposed at or above an 8- hour time-weighted average of 85 decibels. (7) Evaluation of Audiogram. (i) Each employee's annual Audiogram shall be compared to that employee's baseline Audiogram to determine if the Audiogram is valid and if a standard threshold shift as defined in paragraph (g)(10) of this section has occurred. This comparison may be done by a technician. (ii) If the annual Audiogram shows that an employee has suffered a standard threshold shift, the employer may obtain a retest within 30 days and consider the retest the results of the retest as the annual Audiogram. (iii) The audiologist, otolaryngologist, or physician shall review problem Audiograms and shall determine whether there is a need for further evaluation. The employer shall provide to the person performing this evaluation the following information: (A) A copy of the requirements for hearing conservation as set forth in paragraphs (c) through (n) of this section; (B) The baseline Audiogram and most recent Audiogram of the employee to be evaluated; (C) Measurements of background sound pressure levels in the Audiometric test room as required in Appendix D; Audiometric Test Rooms. (D) Records of audiometer calibrations required by paragraph (h)(5) of this section. Hearing Conservation Program Page 12 ©2011, Waste Management January 2011
  • 883. Appendix A (8) Follow-up procedures. (i) if a comparison of the annual Audiogram to the baseline Audiogram indicates a standard threshold shift as defined in paragraph (g)(10) of this section has occurred, the employee shall be informed of this fact in writing, within 21 days of the determination. (ii) Unless a physician determines that the standard threshold shift is not work related or aggravated by occupational noise exposure, the employer shall ensure that the following steps are taken when a standard threshold shift occurs: (A) Employees not using hearing protectors shall be refitted and retrained in the use of hearing protectors and provided with hearing protectors offering greater attenuation if necessary. (B) Employees already using hearing protectors shall be refitted and retrained in the use of hearing protectors and provided with hearing protectors offering greater attenuation if necessary. (C) The employee shall be referred for a clinical audiological evaluation or an otological examination, as appropriate, if additional testing is necessary or if the employer suspects that a medical pathology of the ear is caused or aggravated by the wearing of hearing protectors. (D) The employee is informed of the need for an otological examination if a medical pathology of the ear that is unrelated to the use of hearing protectors is suspected. (iii) If subsequent Audiometric testing of an employee whose exposure to noise is less than an 8-hour TWA of 90 decibels indicates that a standard threshold shift is not persistent, the employer: (A) Shall inform the employee of the new Audiometric interpretation; and (B) May discontinue the required use of hearing protectors for that employee. (9) Revised baseline. An annual Audiogram may be substituted for the baseline Audiogram when, in the judgment of the audiologist, otolaryngologist or physician who is evaluating the Audiogram: (i) The standard threshold shift revealed by the Audiogram is persistent; or (ii) The hearing threshold shown in the annual Audiogram indicates significant improvement over the baseline Audiogram. (10) Standard threshold shift. (i) As used in this section, a standard threshold shift is a change in hearing threshold relative to the baseline Audiogram of an average of 10 dB or more at 2000, 3000, and 4000 Hz in either ear. (ii) In determining whether a standard threshold shift has occurred, allowance may be made for the contribution of aging (presbycusis) to the change in hearing level by correcting the annual Audiogram according to the procedure described in Appendix F: Calculation and Application of Age Correction to Audiograms. (h) Audiometric test requirements. (1) Audiometric tests shall be pure tone, air conduction, hearing threshold examinations, with test frequencies including as a minimum 500, 1000, 2000, 3000, 4000, and 6000 Hz. Tests at each frequency shall be taken separately for each ear. Hearing Conservation Program Page 13 ©2011, Waste Management January 2011
  • 884. Appendix A (2) Audiometric tests shall be conducted with audiometers (including microprocessor audiometers) that meet the specifications of, and are maintained and used in accordance with, American National Standard Specification for Audiometers, S3.6-1969, which is incorporated by reference as specified in § 1910.6. (3) Pulsed-tone and self-recording audiometers, if used, shall meet the requirements specified in Appendix C: Audiometric Measuring Instruments. (4) Audiometric examinations shall be administered in a room meeting the requirements listed in Appendix D: Audiometric Test Rooms. (5) Audiometer calibration. (i) The functional operation of the audiometer shall be checked before each day's use by testing a person with known, stable hearing threshold's output to make sure that the output is free from distorted or unwanted sounds. Deviations of 10 decibels or greater require an acoustic calibration. (ii) Audiometer calibration shall be checked acoustically at least annually in accordance with Appendix E: Acoustic Calibration of Audiometers. Test frequencies below 500 Hz and above 6000 Hz may be omitted from this check. Deviations of 15 decibels or greater require an exhaustive calibration. (iii) An exhaustive calibration shall be performed at least every two years in accordance with sections 4.1.2; 4.1.3; 4.1.4.3; 4.2; 4.4.1; 4.4.2; 4.4.3; and 4.5 of the American National Standard Specification for Audiometers, S3.6-1969. Test frequencies below 500 Hz and above 6000 Hz may be omitted from this calibration. (i) Hearing protectors. (1) Employers shall make hearing protectors available to all employees exposed to an 8-hour time-weighted average of 85 decibels or greater at no cost to the employees. Hearing protectors shall be replaced as necessary. (2) Employers shall ensure that hearing protectors are worn: (i) By an employee who is required by paragraph (b)(1) of this section to wear personal protective equipment; and (ii) By any employee who is exposed to an 8-hour time-weighted average of 85 decibels or greater, and who: (A) Has not yet had a baseline Audiogram established pursuant to paragraph (g)(5)(ii); or (B) Has experienced a standard threshold shift. (3) Employees shall be given the opportunity to select their hearing protectors from a variety of suitable hearing protectors provided by the employer. (4) The employer shall provide training in the use and care of all hearing protectors provided to employees. (5) The employer shall ensure proper initial fitting and supervise the correct use of all hearing protectors. (j) Hearing protector attenuation. (1) The employer shall evaluate hearing protector attenuation for the specific noise environments in which the protector will be used. The employer shall use one of the evaluation methods described in Appendix B: Methods for Estimating the Adequacy of Hearing Protection Attenuation. Hearing Conservation Program Page 14 ©2011, Waste Management January 2011
  • 885. Appendix A (2) Hearing protectors must attenuate employee exposure at least to an 8-hour time-weighted average of 90 decibels are required by paragraph (b) of this section. (3) For employees who have experienced a standard threshold shift, hearing protectors must attenuate employee exposure to an 8-hour time-weighted average of 85 decibels or below. (4) The adequacy of hearing protector attenuation shall be re-evaluated whenever employee noise exposures increase to the extent that the hearing protectors provided may no longer provide adequate attenuation. The employer shall provide more effective hearing protectors where necessary. (k) Training program. (1) The employer shall institute a training program for all employees who are exposed to noise at or above an 8-hour time-weighted average of 85 decibels, and shall ensure employee participation in such program. (2) The training program shall be repeated annually for each employee included in the Hearing Conservation Program. Information provided in the training program shall be updated to be consistent with changes in protective equipment and work processes. (3) The employer shall ensure that each employee is informed of the following: (i) The effects of noise on hearing; (ii) The purpose of hearing protectors, the advantages, disadvantages, and attenuation of various types, and instructions on selection, fitting, use, and care; and (iii) The purposes of Audiometric testing, and an explanation of the test procedures. (l) Access to information and training materials. (1) The employer shall make available to affected employees or their representatives copies of this standard and shall also post a copy in the workplace. (2) The employer shall provide to affected employees any informational materials pertaining to the standard that are supplied to the employer by the Assistant Secretary. (3) The employer shall provide, upon request, all materials related to the employer's training and education program pertaining to the standard to the Assistant Secretary and the Director. (m) Recordkeeping (1) Exposure measurements. The employer shall maintain an accurate record of all employee exposure measurements required by paragraph (d) of this section. (2) Audiometric tests. (i) The employer shall retain all employee Audiometric test records obtained pursuant to paragraph (g) of this section: (ii) This record shall include: (A) Name and job classification of the employee; (B) Date of the Audiogram; (C) The examiner's name; (D) Date of the last acoustic or exhaustive calibration of the audiometer; and (E) Employee's most recent noise exposure assessment. (F) The employer shall maintain accurate records of the measurements of the background sound pressure levels in Audiometric test rooms. Hearing Conservation Program Page 15 ©2011, Waste Management January 2011
  • 886. Appendix A (3) Record retention. The employer shall retain records required in this paragraph (m) for at least the following periods. (i) Noise exposure measurement records shall be retained for two years. (ii) Audiometric test records shall be retained for the duration of the affected employee's employment. (4) Access to records. All records required by this section shall be provided upon request to employees, former employees, representatives designated by the individual employee, and the Assistant Secretary. The provisions of 29 CFR 1910.20(a) - (e) and (g) - (i) apply to access to records under this section. (5) Transfer of records. If the employer ceases to do business, the employer shall transfer to the successor employer all records required to be maintained by this section, and the successor employer shall retain them for the remainder of the period prescribed in paragraph (m)(3) of this section. (n) Appendices. (1) Appendices A, B, C, D, and E to this section are incorporated as part of this section and the contents of these Appendices are mandatory. (2) Appendices F and G to this section are informational and are not intended to create any additional obligations not otherwise imposed or to detract from any existing obligation. (o) Exemptions. Paragraphs (c) through (n) of this section shall not apply to employers engaged in oil and gas well drilling and servicing operations. (p) Startup date. Baseline Audiograms required by paragraph (g) of this section shall be completed within six months of hire date. Purpose The purpose of this training is to give you the basic knowledge needed to understand why hearing conservation is an important part of the safety and health equation. Objectives: By the end of this training, participants should be able to understand: 1. The Effects of noise on hearing; 2. The purpose of hearing protectors. 3. The advantages, disadvantages, of various types of hearing protection. 4. Selection, use and care of hearing protection. 5. The purpose of audiometric testing. It’s as simple as 1, 2, 3... 1) Your outer ear, called the pinna, collects sound waves and channels them down the ear canal to a thin, tight piece of skin called the tympanic membrane (eardrum). 2) The eardrum vibrates in response to these pressure waves and pushes on the small bones of your middle ear. These bones act like a set of levers, transferring their mechanical motion to a fluid-filled structure in the inner ear, called the cochlea. Hearing Conservation Program Page 16 ©2011, Waste Management January 2011
  • 887. Appendix A In the cochlea, cells with tiny sensing hairs transform the fluid movement into electrical signals. These signals travel along the auditory nerve to your brain. Once in the brain, the nerve signals are decoded and processed into what we recognize as sound. EFFECTS OF NOISE ON HEARING Prolonged exposure to excessive noise levels can cause a noise-induced hearing loss. When you are exposed to excessive noise levels, the first effect usually is a temporary hearing loss. You may have difficulty in conversation or the ears may feel “plugged and “ring.” Over a period of time, an individual who experiences repeated temporary hearing loss will have gradual, permanent, irreversible hearing loss. Noise-induced hearing loss (called “acoustic trauma”) involves damage to the receptor cells in the inner ear and is classified as sensori-neural impairment. A noise-induced hearing loss typically begins with a drop in hearing level at the higher frequencies of sound. As the hearing loss increases, it includes the lower sound frequencies that include speech. Early noise-induced hearing loss normally is not detected by an individual, since it occurs above the speech range. By the time an individual is aware of a hearing loss, the amount of loss may be significant. Noise exposure is cumulative. So the noise at home or at play must be counted in the total exposure during any one day. If the maximum allowable noise level is reached while on the job, any following exposure during non-working hours, such as a noisy lawnmower or loud music will may cause you to exceed the safe daily limit. Hearing Conservation Program Page 17 ©2011, Waste Management January 2011
  • 888. Appendix A PICTURE THIS: (similarity to hairs cells in your ears) You take a shortcut across a luxuriant green lawn with tall, healthy blades of grass reaching proudly toward the sky. Where you have walked, the blades are trampled, bent over, bruised and damaged. You can see the outline of each of your steps in the thick carpet of grass. Tomorrow, you decide to take the same shortcut. As you look, there is no sign you passed this way yesterday. This time, however, some of your co-workers see you and decide to do the same thing. Soon, many people begin taking this route, not just once a day but throughout the day as well. Before long, bicyclists are using the path. Eventually, the blades of grass have no time to repair themselves between uses. Gradually, some of the blades break off, and then more as time progresses. Eventually, where once there was a beautiful lawn, there now is a dirt trail with only a blade or two of grass here and there. PURPOSE OF HEARING PROTECTORS Hearing protectors either are plugs of various shapes and sizes that are inserted into the ear canals or muffs that are placed over the ears. In either case, their job is to reduce the intensity of sound that reaches the ear so as to protect the ear from potentially damaging noise. Advantage and Disadvantage of Hearing Protectors: Foam Hearing A cylinder of sound-attenuating foam. The foam is compressed and Protectors: inserted in the ear canal, where the foam expands to fill the canal. Advantages: Readily available, inexpensive, disposable, adequately comfortable, lightweight. Disadvantages: Requires regular replacement, can become uncomfortable with prolonged wear. Ribbed Hearing Made of rubber in a "one size fits all" shape. They are inserted in the ear Protectors: canal as deeply as possible. Advantages: Generally available, durable, lightweight, washable. Disadvantages: Slip easily, uncomfortable, may not provide tight fit. Muff Hearing Resemble stereo head sets that completely cover the ears. Protectors: Advantages: Good noise reduction, hard to lose, more durable with infrequent replacement. Disadvantages: Heavy and cumbersome, more expensive, hot, uncomfortable. Hearing Conservation Program Page 18 ©2011, Waste Management January 2011
  • 889. Appendix A Custom Molded Made of silicone and are molded to exactly fit the individual's ear. Protectors: Advantages: Good noise rating, durable, very comfortable for long periods of time. Disadvantages: Requires initial impression of ear, more expensive, possible replacement. Attenuation of Hearing Protectors (Noise Reduction by Hearing Protectors) Manufacturers of hearing protection assign a Noise Reduction Rating (NRR) to each type of hearing protector. The NRR is an indication of the relative level of protection provided by the plug or muff. The higher the NRR, the more protection the equipment provides. The NRR is determined under ideal laboratory conditions and should not be used as a direct measurement of the protection that each wearer will receive. Field Attenuation of Hearing Protection: To estimate the attenuation afforded to a noise- exposed employee in an actual work environment by muffs, plugs, or a combination of both, proceed as follows. a. For muffs or plugs: Determine the laboratory-based noise attenuation afforded by the given hearing protector. This is based on laboratory testing using human subjects and is provided by the manufacturer. It is referred to as the Noise Reduction Rating or NRR and should be on the packaging. Subtract 7dB from the NRR to correct for using A-weighted measurements. To adjust for workplace conditions, applying a safety factor of 50% is recommended. This is because the field use of ear protectors does not afford the same degree of protection achieved in the laboratory using well-trained subjects under ideal test conditions. b. For dual protection (i.e. muffs and plugs): Determine the laboratory-based noise attenuation (NRR) for the higher rated hearing protector, subtract 7dB, and (it is recommended that you) apply a safety factor of 50%. Then add 5 dB to the field-adjusted NRR to account for the use of the second hearing protector. Example 1: TWA = 100 dBA and Muff NRR = 19 dB Approximate Field Attenuation is: (19-7) × 50% = 6 dB 100 dBA TWA - 6 dB = 94 dBA Conclusion: The protected TWA can be assumed to be 94 dBA. Feasible engineering controls must be implemented. Since the HCA does not require applying a 50% correction factor, the protected TWA is 88 dBA. Therefore, better hearing protection (with greater attenuation) is not required by the standard. If an employee exhibits an STS, better hearing protection may be required. Example 2: Given TWA = 98 dBA and Plug NRR = 29 dB Approximate Field Attenuation is: (29-7) × 50% = 11 dB 98 dBA TWA - 11 dB = 87 dBA Conclusion: The protected TWA can be assumed to be 87 dBA. Unless the employee exhibits Hearing Conservation Program Page 19 ©2011, Waste Management January 2011
  • 890. Appendix A an STS, the employer meets one of the necessary conditions for being excused from the requirement to implement engineering controls. Better hearing protection (with greater attenuation) is not required since the protected TWA, without the safety factor, is 76 dBA. If an employee exhibits an STS, better hearing protection should be recommended. Example 3: Given TWA8 = 110 dBA, Plug NRR = 29 and Muff NRR = 25 dB Employer requires dual protection. Calculate field-adjusted NRR for the higher-rated protector: (29-7) × 50% = 11 dB Add 5 dB to this field-adjusted NRR: 11+5 = 16 dB Calculate the protected TWA8: 110 dBA TWA8 - 16 dB = 94 dBA Conclusion: The protected TWA8 can be assumed to be 94 dBA. If feasible, engineering controls must be implemented. The protected TWA8, without using the 50% safety factor, is 83 dBA. Therefore, better hearing protection is not required by the HCA. Hearing protectors with greater attenuation should be recommended. SELECTION OF EAR PROTECTORS Ear protector selection should be based on employee convenience, comfort, and proper degree of attenuation. Under attenuation would lead to excessive noise exposure. Over attenuation in moderate noise levels can lead to a feeling of isolation and, consequently, poor acceptance of the protectors. Fitting Earplugs must fit tightly to provide a good seal. Grasping the ear with the opposite hand, pulling it up and out to open the ear canal and then inserting the plug with the other hand insert the earplug. Muffs will normally fit all people without any difficulty. Eyeglasses may interfere with the proper fitting of the muff. Muffs that attach directly to hard hats are also available. Ear stoppers are usually easy to position. The headband can be worn on top of or behind the head, or under the chin. When hearing protectors are initially worn, it may take a short time for the employee to adjust to the new level of sound. The same sounds are heard, but at a lower intensity. Hearing Conservation Program Page 20 ©2011, Waste Management January 2011
  • 891. Appendix A Care and Use of Protectors Ear protectors must be maintained in sanitary condition. It is important that earplugs be clean when inserted into the ears. If plugs are dirty when inserted, they may cause irritation, which could lead to infection of the ear canal. The same applies to stoppers. Earplugs, when not in use, should be stored in some type of container that can be closed to seal out dust or dirt. Earplugs should be replaced when they no longer can be cleaned or loose their pliability. Earmuffs have a replaceable seal, which should be kept clean. The seal should be replace whenever it becomes stiff or cracked. AUDIOMETRIC TESTING Audiometric testing is a means of determining your hearing ability. “Normal” hearing includes the median hearing level of a large group of American adults between 18 and 25 years of age, having no known history of ear disease and no appreciable high-level noise exposure. The accepted normal range of hearing is between 0 and 25 decibels. The audiometric test consists of exposing each ear separately to sound at six different frequencies. The audiometric test will indicate the amount of hearing loss, if any, of an individual. The higher the decibel reading, the greater the hearing loss. As an individual ages there is a natural hearing loss, which takes place. This is called presbycusis. A cold, an ear infection, or recent high noise exposure can cause a temporary hearing loss, which would produce poor test results. Tests should not be administered to anybody with a cold or an ear infection. Test will need to be administered once cold or ear infection has passed. Audiogram should be preceded by at least 14 hours of quiet. If audiogram is to be administered during work shift the supervisor should require it mandatory for employees to wear hearing protectors prior to taking audiogram test. RIGHT TO ACCESS RECORDS All records required by this section shall be provided upon request to employees, former employees, representatives designated by the individual employee, and the director. Conclusion The more intense or louder the noise, the more likely it will contribute to hearing loss. The longer an employee is exposed to a particular noise at work or at home, the greater the chance an injury will occur to the auditory system. To minimize the risk of hearing loss occurring it is up to each employee to take responsibility and wear hearing protectors at work or at home. Hearing Conservation Program Page 21 ©2011, Waste Management January 2011
  • 892. Appendix A Glossary (1) Audiogram - A chart, graph, or table resulting from an audiometric test showing an individual's hearing threshold levels as a function of frequency. (2) Audiologist - A professional, specializing in the study and rehabilitation of hearing, who is certified by the American Speech, Hearing, and Language Association or licensed by a state board of examiners. (3) Baseline audiogram - The audiogram against which future audiograms are compared. (4) Criterion sound level - A sound level of 90 decibels. (5) Decibel (dB) - Unit of measurement of sound level. (6) Hertz (Hz) - Unit of measurement of frequency, numerically equal to cycles per second. (7) Impulsive or impact noise - Noise levels which involve maxima at intervals greater than one second. Where the intervals are less than one second, the noise levels shall be considered continuous. (8) Medical pathology - A disorder or disease. For purposes of this regulation, a condition or disease affecting the ear, which should be treated by a physician specialist. (9) Noise dose - The ratio, expressed as a percentage, of (a) the time integral, over a stated time or event, of the 0.6 power of the measured SLOW exponential time-averaged, squared A- weighted sound pressure and (b) the product of the criterion duration (8 hours) and the 0.6 power of the squared sound pressure corresponding to the criterion sound level (90 dB). (10) Noise dosimeter - An instrument that integrates a function of sound pressure over a period of time in such a manner that it directly indicates a noise dose. (11) Otolaryngologist - A physician specializing in diagnosis and treatment of disorders of the ear, nose and throat. (12) Representative exposure - Measurements of an employee's noise dose or 8-hour time- weighted average sound level that the employer deems to be representative of the exposure of other employees in the workplace. (13) Standard threshold shift - A hearing level change, relative to the baseline audiogram, of an average of 10 dB or more at 2000, 3000, and 4000 Hz in either ear. (14) Sound level - Ten times the common logarithm of the ratio of the the square of the measured A-weighted sound pressure to the square of the standard reference pressure of 20 micropascals. Unit: Decibels (dB). For use with this regulation, SLOW time response, in accordance with ANSI S1.4.1971 (R1976), is required unless specifically specified otherwise. (15) Sound level meter - An instrument for the measurement of sound level. (16) Time-weighted average sound level - That sound level, which if constant over an 8-hour period, would result in the same noise dose as if measured in the time varying noise level environment. A sound’s volume level, which your brain perceives as loudness, is measured in deciBels. Hearing Conservation Program Page 22 ©2011, Waste Management January 2011
  • 893. Appendix A RELATION SHIP OF THE DECIBEL TO SOUND INTENSITY IN NON-LOGARITHMIC UNITS Decibels Units 0 1 10 10 20 100 (102=100) 30 1,000 40 10,000 50 100,000 100 10,000,000,000 150 1,000,000,000,000,00 Hearing Conservation Program Page 23 ©2011, Waste Management January 2011
  • 894.  
  • 895. HAZARD COMMUNICATION PROGRAM Program: Hazard Communication Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 PURPOSE Employees at our facilities use certain materials requiring specific precautions. It is the policy of WGSL to communicate any known hazards associated with these materials and to train our employees in safe handling techniques. DEFINITIONS Chemical – any element, chemical compound or mixture of elements and/or compounds. Chemical manufacture – an employer with a workplace where chemical(s) are produced for distribution or us. Combustible liquid – any liquid having a flashpoint at or above 100 degree F (37.8 degree C), but below 200 degree F (93.3 degree C), except any mixture having components with flashpoints of 200 degree F (93.3 degree C), or higher, the total volume of which make up 99 percent or more the total volume of the mixture. Common name- any designation or identification such as code name, code number, trade name, brand name, or generic name used to identify a chemical other than by its chemical name. Container – any bag, barrel, bottle, box, can, cylinder, drum, reaction vessel, storage tank, or the like that contains a hazardous chemical. Explosive – a chemical that causes a sudden, almost instantaneous release of pressure, gas, and heat when subjected to sudden shock, pressure, or high temperature. Exposure or exposed – an employee is subjected in the course of employment to a chemical that is a physical or health hazard, and includes potential (e.g., accidental or possible) exposure. Flashpoint – the minimum temperature at which a liquid gives off a vapor in sufficient concentration to ignite when tested. Health hazard – includes chemicals which are carcinogens, toxic or highly toxic agents, reproductive toxins, irritants, corrosives, sensitizers, hepatotoxins, neurotoxins, agents which act Hazard Communication Program Page 1 ©2011, Waste Management January 2011
  • 896. HAZARD COMMUNICATION PROGRAM on the hematopoietic system, and agents which damage the lungs, skin, eyes, or mucous membranes. Labels – any written, printed, or graphic material displayed on or affixed to containers of hazardous chemicals. Physical hazard – a chemical for which there is scientifically valid evidence that it is a combustible liquid, a compressed gas, explosive, flammable, an organic peroxide, an oxidizer, pyrophoric, unstable (reactive) or water-reactive. Trade secret – any confidential formula, pattern, process, device, information or compilation of information that is used in an employer’s business, and that gives the employer an opportunity to obtain an advantage over competitors who do not know or use it. Unstable – a chemical which in pure state, or as produced or transported, will vigorously polymerize, decompose, condense, or will become self-reactive under conditions of shocks, pressure or transfer. Water-reactive – a chemical that reacts with water to release a gas that is either flammable or presents a health hazard. Work area – a room or defined space in a workplace where hazardous chemicals are produced or used, and where employees are present. Workplace – an establishment, job site, or project, at one geographical location containing one or more work areas. RESPONSIBILITIES Management and supervisors must ensure that proper information is obtained and communicated to appropriate employees. Employees must follow the safe work practices outlined in training sessions, Material Safety Data Sheets, warning labels, and/or operating procedures. The effectiveness and success of this program depend on the active support and involvement of all personnel. MATERIAL SAFETY DATA SHEETS (MSDS) Material Safety Data Sheets (MSDS’s) contain information necessary to safely handle specific materials. It is important for WGSL to obtain the MSDS’s from suppliers concerning hazardous materials purchased. Workers are advised of the following information: Name, address, and telephone number of manufacturer, distributor or importer. Hazard Communication Program Page 2 ©2011, Waste Management January 2011
  • 897. HAZARD COMMUNICATION PROGRAM Chemical name and/or common name of material. Chemical analysis or formula. Ingredients and hazards associated with chemicals used. Physical data. Fire and explosion hazard data. Reactive data. Health hazard data. Spill leak, and disposal data. Special protection information. Special precautions and comments. MSDS identification number. Vendors are required to provide MSDS’s for all hazardous materials including solvents, soaps, oils, maintenance supplies, lubricants, cleaners, compressed gases, welding and brazing wires and rods, fluxes, etc. These sheets should be sent to the District Manager. Records should be maintained of all verbal and written requests for MSDS’s from suppliers of hazardous materials. Records of verbal requests must include date of request, supplier’s name, product for which the sheet is being requested, name of person from whom sheet is being requested, and name of the person making the request. Written requests can be kept in a separate file. Hazard Communication Program Page 3 ©2011, Waste Management January 2011
  • 898. HAZARD COMMUNICATION PROGRAM A file of location specific MSDS’s used will be maintained at the following locations: SHOP WGSL OFFice A master copy of all MSDS’s will be maintained in the Maintenance Managers office. STATE SPECIFIC ITEMS Each MSDS will be maintained for at least 30 years. These MSDS’s are available for review by any employee upon request. In addition, the Maintenance Manager will screen all MSDS’s received to insure that the information listed above is included. If sheets are incomplete, the supplier will be notified and an updated and/or complete MSDS will be requested. Records of these requests will be maintained also. Generally, the Company does not become aware of new and significant health hazards associated with materials used in our facilities unless notified by the supplier or manufacturer. Upon receipt of updated MSDS’s Maintenance Manager replaces outdated MSDS’s with the new ones, and Informs employees of the changes. WORKPLACE CHEMICAL LIST The Maintenance Managers will be responsible for maintaining a Workplace Chemical List of all hazardous materials used at WGSL. A separate form will be used for each facility. The Workplace Chemical List will be available for review by employees of a facility upon request. The Workplace Chemical List constitutes the official list of all hazardous materials approved for use at WGSL. The Maintenance Manager must approve materials not on the list before being received. Once a year, each department will conduct a physical inventory of chemicals and materials in use in its area and report the results to Joe Whelan, program manager. The results will be compared with the Workplace Chemical List to insure that it is complete and accurate. Hazard Communication Program Page 4 ©2011, Waste Management January 2011
  • 899. HAZARD COMMUNICATION PROGRAM LABELS AND OTHER FORMS OF WARNING Labels and similar forms of warning list any hazards associated with containerized materials. Therefore, all hazardous materials will be placed in labeled containers. Labels must not be defaced or removed. Labeled containers must always be positioned with the labels clearly visible. If a container is without a label, it must be labeled immediately. Until the container is properly labeled, the materials will not be use Labels are to include: A list of hazardous materials within the container. Appropriate hazard warnings. Name, address and phone number of the manufacturer, distributor, or importer. Labels are to be in English, with other languages optional. Labels will contain the material’s name. If the chemical name is used, the common name can be found by referring to the Workplace Chemical List. Employees are trained not to rely solely on the information inscribed on a label, but also to read the MSDS for additional information. TRAINING AND LOCATION OF HAZARD DATA A program has been established to ensure that all employees are trained prior to beginning work with hazardous materials. Procedures have also been established to train new hires and transferred employees. This training is to inform employees of any hazardous materials known to be present in the workplace. This written program and copies of MSDS’s covering hazardous materials in a specific work area are maintained by the Maintenance Manager and supervisors in appropriate places to permit ready access to employees, physicians, and employee representatives at all times. (A location within a locked office or filing cabinet and not readily accessible is unacceptable.) The Maintenance Manager maintains the facilities Workplace Chemical List and a master copy of all MSDS’s. MSDS’s from this file are not to be removed from the facility. Employees may review this information at any time. Employee training includes, as a minimum: - A briefing on the OSHA Hazard Communication Standard concerning employee and company rights and responsibilities. - Identification of hazardous materials in the employee’s work area, and potential dangers associated with them. Hazard Communication Program Page 5 ©2011, Waste Management January 2011
  • 900. HAZARD COMMUNICATION PROGRAM Location of the written program and MSDS’s appropriate to the employee’s work area. - How to use MSDS’s (e.g., what information they contain, where to find the information, how to use it). - How to use labels and other forms of warning—what information they communicate, and how to use that information for protection. - Specific training appropriate to the employee. - Methods and observations that may be used to detect the presence or release of a hazardous chemical in the work area (such as monitoring conducted by the employer, continuous monitoring devices, visual appearance or odor of hazardous chemicals when being released, etc.) - The measures employees can take to protect themselves from these hazards, including specific procedures the employer has implemented to protect employees from exposure to hazardous chemicals, such as appropriate work practices, emergency procedures, and PPE to be used. - Employee’s protection against discharge or other discrimination due to the employee’s exercise of the rights afforded pursuant to the provisions of the Hazardous Substances Information and Training Act. - Whenever WGSL receives a new or revised MSDS, such information will be provided on a timely basis not to exceed 30 days after receipt, if the new information indicates significantly increased risk to, or measures necessary to protect, employee health as compared to those stated on a MSDS previously provided. Schedule - All new employees will be trained prior to working with hazardous materials. - All transferred employees will be trained prior to assignment in an area where hazardous materials are used. - All employees will be trained on the hazards of materials at the time they are introduced into their work area. - All employees, prior to being assigned to a non-routine task involving hazardous materials, will receive special training. - All employees will be retrained annually. - The District Manager will schedule such annual training as a safety-meeting topic. Ongoing responsibility for training employees in the situations described above rests with the supervisor of the applicable work area. Documentation All training is to be documented and the information kept at the facility site. Documentation will show the following: Hazard Communication Program Page 6 ©2011, Waste Management January 2011
  • 901. HAZARD COMMUNICATION PROGRAM - Date of training session. - Type of training given (brief description or outline) - Name and signature of employees receiving the training. - Name(s) of instructor(s). HAZARD DETERMINATION AND EVALUATION WGSL will accept the hazard determination and evaluation conducted by the supplier. EMPLOYEE HAZARD COMMUNICATION REGARDING NON- ROUTINE TASKS WGSL recognizes that employees will be required to perform non-routine tasks (emergency repairs and/or clean-up of chemical spills, etc.), which could expose them to unusual risks from hazardous materials. Therefore, special attention will be given by the District Manager and supervisors to instruct employees on how to protect themselves in the performance of these tasks. Instructions by the supervisor take place immediately before the employee(s) perform(s) the non-routine task. Written records are kept by the supervisor showing: - Date - Non-routine task involved - Name(s) of employee(s) involved - Name of person doing the communication and training Employees are issued special protective equipment and instructions for its use in the performance of non-routine tasks. Hazard Communication Program Page 7 ©2011, Waste Management January 2011
  • 902. HAZARD COMMUNICATION PROGRAM INFORMING CONTRACTORS The following information will be communicated to all contractors: - Hazardous chemicals to which they may be exposed while on the job site. - Precautions the contractor’s employees may take to lessen the possibility of exposure by usage of appropriate protective measures. It is the responsibility of the contractor to communicate this information to their employees and to sign and return the attached acknowledgment form. Contractors must provide a copy of each MSDS for chemicals they bring to our site. Hazard Communication Program Page 8 ©2011, Waste Management January 2011
  • 903. INFORMATION SUMMARY ACKNOWLEDGMENT OF CONTRACTOR RESPONSIBILITY FOR HAZARD COMMUNICATION I, ________________________________________, representing the company named _________________________________________, do acknowledge receipt of the contractor portion of the WGSL and Resource Recovery Facility Hazard Communication Program. I understand the responsibility of my Company under this program. I will insure that the personnel of my company comply with all applicable provisions while at the WGSL. ________________________________ ________________ Signature Date Hazard Communication Program Page 9 ©2011, Waste Management January 2011
  • 904. INFORMATION SUMMARY Work Area: _____________________________________ Date Prepared: _____/_____/______ Name of Physical Hazards Health Hazards Special handling Precautions Product/Material F= Flammable C= Cancer (label/MSDS name, C= Combustible R= Reproductive Harm if different) R= Reactive S= Skin Hazard NA= None Applicable T= Toxin (target organ) Hazard Communication Page 10 ©2011, Waste Management January 2011
  • 905. HAZARD COMMUNICATION PROGRAM Employee Hazard Communication Regarding Non-Routine Tasks Date Non-routine task involved Name(s) of Name of employee(s) Supervisor involved conducting training Hazard Communication Page 11 ©2011, Waste Management January 2011
  • 906.  
  • 907. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES Program: Welding, Cutting, Brazing & Hot Work Guidelines Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 PURPOSE Describe the requirements when welding, burning, brazing, cutting or performing other "hot" work. REQUIREMENTS 1. Only trained authorized personnel may weld at WGSL or use Waste Management equipment. 2. Designate areas for welding, brazing, and cutting. 3. Use general or local exhaust ventilation to keep the concentration of toxic fumes, gases, or dusts below the OSHA Permissible Exposure Limits. Refer to the Industrial Hygiene database for information about exposures to welders. 4. Provide, and require the use of, flameproof screens or shields around designated welding or burning areas or move all combustible materials at least 35 feet from the welding/burning area or cover the materials with welding blankets. 5. Provide, and require the use of, personal protective equipment (PPE) as specified in the PPE hazard assessment. 6. Protect welding cables and cylinders from damage. 7. Use only approved cutting and welding equipment. 8. Use a check valve for each of the acetylene and oxygen cylinders and use a flashback arrestor at the acetylene or gas regulator. COMPRESSED GASES 1. Oxygen, fuel gas and acetylene cylinders must be shut off when not in use. 2. Pressure should not remain in the hoses when not in use. 3. Store cylinders upright and away from flame and heat sources. 4. Maintain labels on cylinders. 5. Separate oxygen from acetylene or fuel gases in storage by 20 feet or a 1/2-hour fire-rated non-combustible barrier 5 feet in height. 6. Segregate empty and full containers in storage. WELDING, CUTTING, BRAZING & HOT WORK Page 1 ©2011, Waste Management January 2011
  • 908. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES HOT WORK PERMITS 1. Hot Work means working with materials or equipment or in conditions which could result in fire or explosion. 2. Hot work permits must be used when welding, brazing, or cutting outside of designated areas. 3. Train and authorize an individual to issue hot work permits. 4. Use a fire watch when welding, burning or brazing outside of the designated welding area. The fire watch should man the fire extinguisher when hot work is in progress. 5. Use the hot work permit and require forced air ventilation for any welding, cutting, or brazing works inside confined spaces. 6. Hot work permits should be kept on file for one year. INTRODUCTION The Waste Management written Welding Brazing/ Cutting/Compressed Gas and "Hot Work" guidelines include the following: Safety Procedures for arc welding Safety Procedures for gas welding and cutting Using compressed gas cylinders Fire prevention and protection Hot work control program Maintenance of welding equipment Welding in confined spaces Ventilation during welding Personal protective equipment (PPE) Respiratory and hearing protection Training The following sections describe how WGSL addresses each of these topics. HEALTH EFFECTS ASSOCIATED WITH WELDING Welding produces different fumes and dusts depending on the metal being welded, the kind of welding, and the electrode coatings on the metal. Welding also produces gases. Gases such as nitrogen oxide, nitrogen dioxide, and ozone may irritate the respiratory tract and mucous membranes. Chronic exposure can lead to respiratory disease. Carbon monoxide may cause headaches and dizziness and at high level leads to oxygen deprivation. Argon, carbon dioxide, helium, and nitrogen deplete the atmosphere of oxygen. Arc welding can generate these gases as well. WELDING, CUTTING, BRAZING & HOT WORK Page 2 ©2011, Waste Management January 2011
  • 909. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES Welding produces intense light and heat. Electric welding can cause electric shock and burns. The intensely bright light produced by welding can burn the eyes and skin very quickly. Fumes from welding steel products can irritate the lungs. The excessive breathing in of fumes can cause the flu-like symptoms of metal fume fever. Nickel fumes also irritate the lungs, and skin contact can produce an allergic reaction. Airborne nickel dusts can be cancer causing when breathed in. Airborne chromium dust can be toxic. However, nickel and chromium fumes are not considered cancer causing. GENERAL SAFETY GUIDELINES Follow these guidelines when welding: Avoid prolonged breathing of gases, fumes, and dust. Never weld in damp or wet areas without protective equipment. Wear safety glasses, leather welding gloves, a welding helmet, and protective clothing. Keep the area clear of combustibles (at least 35 feet from the hot work area). Regularly inspect all equipment to ensure that it is in good working condition. Use an NIOSH-approved respirator for fumes when other controls do not bring fumes, dusts, or other contaminants down to safe levels. Use fire-resistant welding curtains or shields constructed of noncombustible materials positioned so that others do not see the welding arc. ARC WELDING Cover welding cables located on the floor or ground so they don’t cause a tripping hazard. Don’t overload cables. Don’t use worn or poorly connected cables. Inspect the cables and connections frequently. Don’t operate or move the polarity switch under the load of a welding current. Do not leave the electrode in the lead when it is not in use. Shut off the welder when not in use. Never weld on trucks that have the motor running. Disconnect the vehicle battery cables before welding. Don’t operate the range switch under load. Follow lockout/tagout procedures when performing servicing or maintenance on machines. (Note: Repairs are to be made only by qualified persons.) Never leave an uninsulated electrode holder or a “live” electrode on the tabletop in contact with a grounded metallic surface. Ensure that welding leads are free of cracks or cuts in the insulation. WELDING, CUTTING, BRAZING & HOT WORK Page 3 ©2011, Waste Management January 2011
  • 910. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES GAS WELDING Use welding and cutting torches equipped with antiflashback valves. Follow the safe handling and use procedures for compressed gas cylinders detailed in these guidelines. NON-FLAMMABLE GAS FLAMMABLE GAS 2 2 COMPRESSED GAS CYLINDERS The gas in cylinders like the ones used for welding is highly pressurized and can create a potentially hazardous situation. Cylinders exposed to heat, fire, or rough handling can explode with great force. For this reason, store cylinders in a cool, dry place. Chain and cap them when they are not in use. Before you use a cylinder, read the label to verify the contents. Report illegible labels to your supervisor. WELDING, CUTTING, BRAZING & HOT WORK Page 4 ©2011, Waste Management January 2011
  • 911. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES SAFE HANDLING REQUIREMENTS Wear safety glasses and insulated neoprene gloves when transporting or exchanging cylinders, or when connecting or disconnecting regulators. Use a hand truck to transport cylinders. Check hoses for leaks. Shut off the cylinders when hoses are connected but not in use. Check regulators when changing cylinders to be sure they are free of dust and oil. Inspect cylinders for defects, corrosion, and dents. Isolate and mark any defective cylinders, and contact the vendor immediately for pick-up. Store filled cylinders inside in a well-protected, well-ventilated, dry location. They must be at least 20 feet from highly combustible materials, sparks, open flames, excessive heat, and away from elevators, stairs, or gangways. Keep cylinders secured to prevent them from falling over. Separate stored oxygen cylinders from stored fuel gas cylinders or combustible material (especially oil or grease) by at least 20 feet or by a noncombustible barrier. This barrier must be at least 5 feet high and have a fire resistance rating of one-half hour. Mark all cylinders legibly to identify their contents. If the cylinder is unmarked, do not use it. If a cylinder is leaking, close the valve, cap, and move to a well-ventilated area. Contact the supplier immediately. For cylinders that are flammable, use a non-sparking wrench when changing. Be careful that cylinders are not placed so as to become part of an electrical circuit. Never try to mix any gases in a cylinder. Never try to refill a cylinder. Mark empty tanks “MT,” close the valves, and replace valve caps securely. Separate “MT” and full tanks. FLAMM ABLE GAS FLAMMABLE GAS FLAMM ABLE GAS 2 2 2 2 FLAMMABLE G 2 AS FLAMMABLE G AS ATTACHING REGULATORS Handle the regulator carefully at all times. Do not use pipe wrenches or pliers for attaching regulators to cylinders. Use an open-end wrench of the proper size instead. Use a close-fitting wrench to avoid stripping the threads Hammers or wrenches must not be used to open or close cylinder valves that are fitted with hand wheels. When opening the valves, never stand in front of the regulators. The tanks are under pressure and the regulators may explode when opened. WELDING, CUTTING, BRAZING & HOT WORK Page 5 ©2011, Waste Management January 2011
  • 912. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES REQUIREMENTS FOR HOSES, TORCH VALVES, AND CONNECTIONS Replace or repair hoses showing leaks, burns or worn places. Color-code hoses to avoid accidental mixing. Connect hoses to regulator properly. Check hose connections for proper threading. Standard hose connections are threaded right-hand for oxygen and left-hand for acetylene or other fuel gas. This helps prevent an accidental switch of oxygen and fuel-gas hoses. Use only approved bronze or brass fittings. Copper fittings must never be used on acetylene cylinders. Under certain conditions, the acetylene might react with the copper to produce an explosive compound. Do not use oil, grease, or similar substances on any torch or regulator. Oil and grease in the presence of oxygen may burn with explosive force, if ignited. TESTING FOR LEAKS To test for leaks, open the fuel and oxygen cylinder valves with the needle on the torch closed. Adjust the regulator to normal working pressures, and apply soapy water to connections and hose with a brush. If bubbles form, a leak is present. Correct condition as necessary. Do not try to repair hoses with tape. Do not use any other testing method. GAS WELDING AND CUTTING Lighting and Shutting Off the Torch Ensure the proper welding or cutting tip is selected and installed. Purge the hoses by opening the valve on the acetylene cylinder. This should never be opened more than one and one-half turns. Three-fourths of a turn is preferable. Open the acetylene torch valve one-fourth turn. Adjust the acetylene to working pressure with the gas regulator screw. Close the acetylene torch valve. Slowly open the oxygen cylinder valve all the way. Open the oxygen torch valve one-half turn. Adjust the oxygen to working pressure with the gas regulator screw. Turn off the oxygen torch valve. The final steps are the actual lighting of the torch. Reopen the acetylene torch valve one-fourth to three-quarters turn and light the gas with a spark lighter. (NEVER USE MATCHES.) Increase the fuel supply until the flame has a slight tendency to jump away from the tip. Gradually open the oxygen needle. Follow the procedures below for shutting off the torch: Close the torch valves acetylene first, then oxygen. Close the cylinder valves acetylene first, then oxygen. WELDING, CUTTING, BRAZING & HOT WORK Page 6 ©2011, Waste Management January 2011
  • 913. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES Open both torch valves to release the pressure. Shut off the regulator-adjusting handle until you no longer feel any spring tension. Close the torch valves. This procedure reduces the possibility of regulator fires when the oxygen cylinder valve is open again. It will also prevent leaks of acetylene or oxygen while the equipment is not in use. A leak could cause a serious fire. FIRE PREVENTION AND PROTECTION The site program administrator designates safe areas for welding, brazing, and cutting free of combustible and flammable materials. Welding and cutting in these areas should not pose a hazard to welders or workers in nearby areas. Work site preparation to avoid fires and/or explosions includes ensuring all combustibles are at least 35 feet from the work area. If this is not possible, protect combustibles using flameproof covers, and complete a Hot Work Permit [HOT WORK PERMIT FORM]. Follow these safe work practices when welding to prevent fires and/or explosions: Know the location of nearby fire extinguishers and know how to use them. Do not weld in locations close to chlorinated hydrocarbon vapors coming from degreasing, cleaning, or spraying operations. Heat or rays from the arc can react with solvent vapors to form a highly toxic gas and other irritating products. Do not weld on containers or barrels which have held combustible or flammable materials or materials which, when heated, give off toxic vapors. Perform cleaning, purging, or inerting first. Do not weld on a closed container unless the contents have been identified and found to be non-flammable. CLEANING CONTAINERS When you know the container held a gas or liquid which will readily dissolve in water, use the following method: Flush out the container with water several times, and then fill the container with water. Before welding, be sure there is a vent or opening on the container to provide for release of air pressure. WELDING, CUTTING, BRAZING & HOT WORK Page 7 ©2011, Waste Management January 2011
  • 914. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES When you know the container held a gas or liquid that will not readily dissolve in water, perform the following procedure: Clean out the container thoroughly with steam or a compatible-cleansing agent. Purge all air or inert materials with a gas such as carbon dioxide or nitrogen before repairing. Carbon dioxide is heavier than air and will tend to remain in the container if the opening is at the top. Use steam to clean out light material. Use a strong caustic soda solution to clean out heavy oils or grease. Don’t clean where there is poor ventilation. Ventilation is necessary to carry away harmful or explosive vapors. Don’t clean near any open flames. When scraping or hammering to remove heavy sludge or scale use a spark resistant tool and keep the tool wet to avoid sparks. Keep your head and arms as far away from your work as possible. HOT WORK CONTROL PROGRAM To minimize the potential for employee injury from fires/explosions arising from unsafe cutting and welding practices, and in certain conditions such as confined spaces, a hot work control program must be implemented. At a minimum, the program must include the following elements: Where cutting, welding or other hot work is performed on a regular basis, one or more permanent designated areas must be established for this work. A permit system for authorizing the temporary use of portable cutting and welding equipment outside of designated areas must be used. Document precautions on [HOT WORK PERMIT FORM]. A permit must not be issued if the work can be moved to a designated hot work area. A supervisor must inspect the area to verify that all necessary precautions have been taken before filling out and signing the permit. The welder must post a signed permit in the area where the hot work will be done before commencing work. The welder must return the permit to the supervisor when the work has been completed, signing off on the permit to indicate that a final check-up was conducted. HOT WORK SAFETY RULES Obtain a permit before performing hot work outside of designated areas. Check the condition of hot work equipment prior to each use. (Note: A visual inspection should be made with special attention to electrical cables and gas hoses. A soap solution should be used to check for leaks at valves and connections of oxygen-acetylene sets, especially after changing cylinders.) WELDING, CUTTING, BRAZING & HOT WORK Page 8 ©2011, Waste Management January 2011
  • 915. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES Protect floor and wall openings within 35 feet. Ensure automatic sprinklers (when installed) are functional. Ensure that portable fire extinguishers of the proper type are in the immediate vicinity. (Note: "A" rating for ordinary combustibles; "B" rating for flammable and combustible liquid and gases; "C" rating for energized electrical equipment.) Protect welding hoses against physical damage. (Note: Use UL approved welding hose reels, when appropriate.) Ensure a fire watch is present during hot work activities. Check the area 30 minutes after the work is completed for hazardous conditions or fire. WHEN WELDING IS PROHIBITED You must never weld or cut in the following situations: If you have not been trained and authorized by management. If the building you are working in has sprinkler systems that are not working. In the presence of explosive atmospheres. Near large quantities of highly ignitable materials VENTILATION Four main factors in arc and gas welding affect the potential for air contamination. These factors are: The size of the space The gross volume of work The number of welders working at one time The size of the welding rod Provide adequate ventilation for protection against potentially excessive concentrations of airborne contaminants (for example, welding, fumes, and carbon monoxide gas) and oxygen deficient atmospheres. Local exhaust may be needed when welding, cutting or brazing is done on materials which contain or are coated (treated) with fluorides, zinc, lead, copper, beryllium, cadmium, mercury, or residual chlorinated solvents (such as perchloretheylene). Engine-driven welding equipment used indoors is to have exhaust gases piped to suitable exhaust ducts or directly outdoors. Never locate engine exhaust on or near an air conditioning intake. WELDING, CUTTING, BRAZING & HOT WORK Page 9 ©2011, Waste Management January 2011
  • 916. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES WELDING MACHINE USE Welding machines must meet safety and design requirements. Observe the following guidelines when using arc-welding equipment: Be properly trained. Do not exceed voltage limits. Ground the frame or case of the welding machine. Ground the ground cable of every power circuit to prevent accidental shock by stray current. Do not ground to pipelines carrying gases or flammable liquids, or conduits carrying electrical conductors. Do not use chains, wire ropes, crane hoists, and elevators carry a welding current. Check ground connections. Provide disconnecting switches or controllers as part of the welding machines or have them near the machines. Do not use a welding machine to thaw out frozen water or pipes. Fire, explosion, or damage to the welding machine may result. Follow safe maintenance practices. These practices include: Reporting all equipment defects or hazards to your supervisor. Remove defective equipment immediately from service. Have all repairs made by qualified personnel. Thoroughly dry and test machines that have become wet before using again. Replace cables with damaged insulation or exposed bare conductors. PERSONAL PROTECTION Welders must wear the appropriate personal protective equipment. Specific requirements are detailed below. EYE AND FACE PROTECTION Select the proper eye protection based on the welding operation. During arc welding or cutting operations, use a welding helmet. Helmets must have filter and cover plates designed for easy removal, and be fitted with a double lens color arc ray lens inside and clear plastic outside. Flash goggles should be used under the welding helmet, particularly while welding using a gas- shielded arc welder. The shaded lens used in the welder’s helmet must meet the test for transmission of radiant energy prescribed in ANSI Z87-1-1989. Select the correct shade of filter lens using the following chart: WELDING, CUTTING, BRAZING & HOT WORK Page 10 ©2011, Waste Management January 2011
  • 917. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES LENS FILTER SHADE GUIDELINES Type of Operation Shade Number Gas Torch Light Cutting - up to one inch 3 or 4 Medium Cutting- one to six inches 4 or 5 Heavy cutting -More than six inches 5 or 6 Gas Welding - Up to 1/8” thickness 4 or 5 Gas Welding -1/8” to ½” thickness 5 or 6 Gas Welding- More than ½” thickness 6 or 8 Arc Welding Up to 30 amps 12 or 14 Shielded metal arc welding (Greater than 5/16” Electrodes) 30 to 74 amps 10 Shielded Metal Arc Welding (Less than 55/32” Electrodes) 75 to 200 amps 11 Gas Shielded Arc Welding (Non Ferrous) 200 to 400 amps 12 Gas Shielded Arc Welding (Ferrous) Helpers or others who normally work near welding operations should also wear shaded eye protection (such as goggles). Selection of the darkness of the lens shade depends on the degree of the helper’s exposure to the welding “flash.” Often the helper must wear shaded goggles that are the same shade that the welder wears. For welding, the best protection is provided by welding hoods. Welding hoods can be worn with safety hats by adding special fittings to the safety hats. For grinding, chipping, or cleaning, use protective goggles. Inspect eye and face protection for welding before each use. Inspect helmets for cracks or defects. Replace cracked or poorly fitting filter plates. Keep a cover glass in front of the filter plate. WELDING, CUTTING, BRAZING & HOT WORK Page 11 ©2011, Waste Management January 2011
  • 918. WELDING, CUTTING, BRAZING & HOT WORK GUIDELINES PROTECTIVE CLOTHING Supervisors must ensure that protective clothing is inspected, maintained, and worn properly to preserve its effectiveness. Additionally, employees should: Wear long-sleeved shirts and pants. Keep clothing reasonably free of oil or grease. Not roll-up sleeves or cuffs when welding. Button sleeves and collars. TRAINING Welders and their Supervisors must be: Trained in the safe operation of their equipment and emergency procedures in the event of a fire. Properly trained before entering to weld in a confined space. Trained in health hazards associated with welding. DEFINITIONS Arc cutting: cutting processes that melt the metals with the heat of an arc between an electrode and the base metal. Gas metal arc welding (MIG): an arc welding process that produces coalescence of metals by heating them with an arc between a continuous filler metal (consumable) electrode and the work. Shielding is obtained entirely from an externally supplied gas or gas mixture. Gas tungsten arc welding (TIG): an arc welding process that produces coalescence of metals by heating them with an arc between a tungsten (non-consumable) electrode and the work. Shielding is obtained from a gas or gas mixture. Pressure and filler metal may or may not be used. Welder and welder operator: any operator of electric or gas welding and cutting equipment. WELDING, CUTTING, BRAZING & HOT WORK Page 12 ©2011, Waste Management January 2011
  • 919. HOT WORK PERMIT Date Time Started Estimated Completion Time Department Floor Building Work to Be Done Permit Expires: Date Time All items following have been completed. Therefore, permission is granted for this work. Signed Title PRECAUTIONS Do not cut, weld, or use other open flame or spark-producing equipment until the following precautions have been taken: Check Each Item Work on Enclosed Equipment (Tanks, Containers, Ducts, Dust Collectors, Etc.) Work Location has Been Personally Examined. Equipment Cleaned of All Combustibles. Sprinklers, Where Provided, are in Working Order. Containers Purged of All Flammable Liquids. Cutting and Welding Equipment is in Good Condition. Explosion Meter Used to Monitor Presence of Flammable Vapors. Work on Walls or Ceiling Floors Swept Clean of Combustibles. The Construction is Non-Combustible and Without Combustible Floors Have Been Wet Down, Covered Combustible Covering or Insulation. with Damp Sand, Metal or Flame Resistant Sheets. Combustibles Have Been Moved Away from Opposite Side of the Wall Fire Watch All combustibles Have Been Located Outside a Radius Provided for a Least 30 Minutes After Operation is of 35’ from the Operation. Completed or Stopped Proper Fire Extinguishers or Small Hose at Site. Flame Resistant Tarp Suspended from Work to Collect Trained in the Use of Extinguishing Equipment. Sparks. PPE and Flash Screens Erected as Required. FINAL CHECK UP Work areas and all adjacent areas to which sparks and heat might have spread (such as floors above and below and on opposite side of walls) were inspected for at least 30 minutes after the work was completed, and were found fire safe. Signed Title After Signing, Return Permit to Person Who Issued It WELDING, CUTTING, BRAZING & HOT WORK Page 13 ©2011, Waste Management January 2011
  • 920.  
  • 921. RESPIRATORY PROTECTION PROGRAM TABLE OF CONTENTS Definitions Intro 1, 2 Respiratory Hazards and Respirator Selection 3 Medical Evaluation 3, 4 Fit-Testing 4 Training 5 Cleaning, Storage and Maintenance of Respirators 6 Air Quality for Self-Contained Air Line Devices 7 Compressor Systems 7 Voluntary Respiratory Use 8 Change Schedule 8 Policy of Providing Respirators and Medical Evaluation at No Cost to the Employee 9 Annual Program Evaluation 10 Recordkeeping Appendix A Respirator Medical Evaluation Questionnaire Appendix B Employee Annual Respirator Fit-Test and Training Record Appendix C User Seal Check Appendix D Respirator Cleaning Procedures Appendix E Information for Employees Using Respirators When not Required Appendix F Periodic Respirator Program Evaluation Appendix G Respiratory Protection Based on Historical Air Monitoring Respiratory Protection Intro ©2011, Waste Management January 2011
  • 922. RESPIRATORY PROTECTION PROGRAM Definitions Definitions. The following definitions are important terms used in the respiratory protection program. Air-purifying respirator means a respirator with an air-purifying filter, cartridge, or canister that removes specific air contaminants by passing ambient air through the air-purifying element. Atmosphere-supplying respirator means a respirator that supplies the respirator user with breathing air from a source independent of the ambient atmosphere, and includes supplied-air respirators (SARs) and self-contained breathing apparatus (SCBA) units. Canister or cartridge means a container with a filter, sorbent, or catalyst, or combination of these items, which removes specific contaminants from the air passed through the container. Demand respirator means an atmosphere-supplying respirator that admits breathing air to the face piece only when a negative pressure is created inside the face piece by inhalation. Emergency situation means any occurrence such as, but not limited to, equipment failure, rupture of containers, or failure of control equipment that may or does result in an uncontrolled significant release of an airborne contaminant. Employee exposure means exposure to a concentration of an airborne contaminant that would occur if the employee were not using respiratory protection. End-of-service-life indicator (ESLI) means a system that warns the respirator user of the approach of the end of adequate respiratory protection, for example, that the sorbent is approaching saturation or is no longer effective. Escape-only respirator means a respirator intended to be used only for emergency exit. Filter or air purifying element means a component used in respirators to remove solid or liquid aerosols from the inspired air. Filtering face piece (dust mask) means a negative pressure particulate respirator with a filter as an integral part of the face piece or with the entire face piece composed of the filtering medium. Fit factor means a quantitative estimate of the fit of a particular respirator to a specific individual, and typically estimates the ratio of the concentration of a substance in ambient air to its concentration inside the respirator when worn. Fit test means the use of a protocol to qualitatively or quantitatively evaluate the fit of a respirator on an individual. (See also Qualitative fit test QLFT and Quantitative fit test QNFT.) Respiratory Protection Intro ©2011, Waste Management January 2011
  • 923. RESPIRATORY PROTECTION PROGRAM High efficiency particulate air (HEPA) filter means a filter that is at least 99.97% efficient in removing monodisperse particles of 0.3 micrometers in diameter. The equivalent NIOSH 42 CFR 84 particulate filters are the N100, R100, and P100 filters. Immediately dangerous to life or health (IDLH) means an atmosphere that poses an immediate threat to life, would cause irreversible adverse health effects, or would impair an individual's ability to escape from a dangerous atmosphere. Loose-fitting face piece means a respiratory inlet covering that is designed to form a partial seal with the face. Negative pressure respirator (tight fitting) means a respirator in which the air pressure inside the face piece is negative during inhalation with respect to the ambient air pressure outside the respirator. Oxygen deficient atmosphere means an atmosphere with an oxygen content below 19.5% by volume. Physician or other licensed health care professional (PLHCP) means an individual whose legally permitted scope or practice (i.e., license, registration, or certification) allows him or her to independently provide, or be delegated the responsibility to provide, some or all of the health care services required by subsection (e). Positive pressure respirator means a respirator in which the pressure inside the respiratory inlet covering exceeds the ambient air pressure outside the respirator. Powered air-purifying respirator (PAPR) means an air-purifying respirator that uses a blower to force the ambient air through air-purifying elements to the inlet covering. Pressure demand respirator means a positive pressure atmosphere-supplying respirator that admits breathing air to the face piece when the positive pressure is reduced inside the face piece by inhalation. Qualitative fit test (QLFT) means a pass/fail fit test to assess the adequacy of respirator fit that relies on the individual's response to the test agent. Quantitative fit test (QNFT) means an assessment of the adequacy of respirator fit by numerically measuring the amount of leakage into the respirator. Respiratory inlet covering means that portion of a respirator that forms the protective barrier between the user's respiratory tract and an air-purifying device or breathing air source, or both. It may be a face piece, helmet, hood, suit, or a mouthpiece respirator with nose clamp. Self-contained breathing apparatus (SCBA) means an atmosphere-supplying respirator for which the breathing air source is designed to be carried by the user. Respiratory Protection Intro ©2011, Waste Management January 2011
  • 924. RESPIRATORY PROTECTION PROGRAM Service life means the period of time that a respirator, filter or sorbent, or other respiratory equipment provides adequate protection to the wearer. Supplied-air respirator (SAR) or airline respirator means an atmosphere-supplying respirator for which the source of breathing air is not designed to be carried by the user. Tight-fitting face piece means a respiratory inlet covering that forms a complete seal with the face. User seal check means an action conducted by the respirator user to determine if the respirator is properly seated to the face. Respiratory Protection Intro ©2011, Waste Management January 2011
  • 925. RESPIRATORY PROTECTION PROGRAM Program: Respiratory Protection Program Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI96707 Respiratory Protection Program This Respiratory Protection Program sets forth the policies and procedures implementing the Cal/OSHA Respirator Standard [8 CCR § 5144] at Waimanalo Gulch Sanitary Landfill (WGSL). The Respiratory Protection Program Administrator is Joe Whelan OR Donny Carder. This person is responsible for all facets of the program and has full authority to make necessary decisions to ensure success of this program. His/her authority includes hiring personnel and purchasing equipment necessary to implement and operate the program. Respiratory Hazards and Respirator Selection WGSL has conducted exposure monitoring and/or made reasonable estimation of potential exposures to hazardous substances and their exposure limits in our workplace. We have selected the following respiratory protection devices for routine operations, maintenance and other non- routine activities, and variable situations. Routine Operations Work Area Operation Chemical/Substance PEL/STEL Exposure Estimates Respirator and Cartridge Respiratory Protection Program Page 1 ©2011, Waste Management January 2011
  • 926. RESPIRATORY PROTECTION PROGRAM Respiratory Protection Program Page 2 ©2011, Waste Management January 2011
  • 927. RESPIRATORY PROTECTION PROGRAM Maintenance and Other Non-Routine Tasks Work Area Operation Chemical/Substance PEL/STEL Exposure Estimates Respirator and Cartridge Variable Situations The Respirator Program Administrator will prepare a reasonable exposure estimate and select an appropriate respirator based on the maximum, following protection factors: up to 10 X PEL/STEL half-face air purifying; up to 50 X PEL/STEL full-face air purifying; and 50 X PEL/STEL SCBA with pressure demand air supply. Emergency Respirator Use In the event of an emergency, the following respiratory protection will be used: Work Area/Operation Chemical/Emergency Respirator Required Respiratory Protection Program Page 3 ©2011, Waste Management January 2011
  • 928. RESPIRATORY PROTECTION PROGRAM Medical Evaluation All employees who are assigned to wear respirators (except for employees who voluntarily use filtering dust masks) will be provided and receive medical evaluation initially upon assignment of the respiratory protection device and periodically thereafter as directed by a physician or other licensed health care professional (PLHCP). Medical evaluations will be conducted using the following procedures: 1) Employees will complete [Respirator Medical Evaluation Questionnaire--Appendix A] Assistance will be available, however WGSL will not review any of the information recorded on the form. We will provide the completed questionnaires to the PLHCP in a sealed envelope. 2) We will schedule employees for PLHCP examinations. The PLHCP will provide a completed Respirator User Medical Evaluation Report or its equivalent directly to the employer. 3) Employees will be assigned to respirator use positions based on the results of the medical evaluation. 4) Periodic medical evaluations will be based on Dr. TBD recommendation or whenever an employee answers questions 1 through 8 in Section 2 Part A of the Respirator Medical Evaluation Questionnaire positively. 5) The following items will be provided to the physician: a. The type and weight of the respirator to be used by the employee; b. The duration and frequency of respirator us; c. The expected physical work effort; d. Additional protective clothing and equipment to be worn; e. Temperature and humidity extremes that may be encountered; and f. A copy of this written program. Fit-Testing Respirators must fit properly to provide protection. If a tight seal is not maintained between the face piece and the employee's face, contaminated air will be drawn into the face piece and be inhaled by the employee. Fit testing seeks to protect the employee against inhaled contaminated ambient air and is one of the core provisions of our respirator program. In general, fit testing may be either qualitative or quantitative. Qualitative fit testing (QLFT) involves the introduction of a gas, vapor, or aerosol test agent into an area around the head of the respirator user. If that user can detect the presence of the test agent through subjective means, such as odor, taste, or irritation, the respirator fit is inadequate. In a quantitative respirator fit test (QNFT), the adequacy of respirator fit is assessed by measuring the amount of leakage into the respirator, either by generating a test aerosol as a test atmosphere, using ambient aerosol as a test agent, or using controlled negative pressure to measure the volumetric leak rate. Appropriate instrumentation is required to quantify respirator fit in QNFT. Respiratory Protection Program Page 4 ©2011, Waste Management January 2011
  • 929. RESPIRATORY PROTECTION PROGRAM Employees are fit tested at the following times with the same make, model, style, and size of respirator that will be used: Before any of our employees are required to use any respirator with a negative or positive pressure tight-fitting face piece; Whenever a different respirator face piece (size, style, model, or make) is used; At least annually; Whenever the employee reports, or our company, PLHCP, supervisor, or Program Administrator makes visual observations of changes in the employee's physical condition that could affect respirator fit. Such conditions include, but are not limited to, facial scarring, dental changes, cosmetic surgery, or an obvious change in body weight; and When the employee, subsequently after passing a QLFT or QNFT, notifies the company, Program Administrator, supervisor, or PLHCP that the fit of the respirator is unacceptable. That employee will be retested with a different respirator face piece. Employees must pass one of the following fit test types that follow the protocols and procedures: QLFT (Only used to fit test negative pressure air-purifying respirators that must achieve a fit factor of 100 or less. May be used to test tight-fitting atmosphere-supplying respirators and tight-fitting powered air-purifying respirators if tested in the negative pressure mode); or QNFT (May be used to fit test a tight-fitting half face piece respirator that must achieve a fit factor of 100 or greater OR a tight-fitting full face piece respirator that must achieve a fit factor of 500 or greater OR tight-fitting atmosphere-supplying respirators and tight-fitting powered air-purifying respirators if tested in the negative pressure mode). Our workplace-specific fit testing procedures include the following: Qualitative fit testing (QLFT) Fit testing will be documented using [Employee Annual Respirator Fit-Test and Training Record--Appendix B] on an annual basis. Training Employees who are assigned to wear respirators will be provided annual training at or about the time of fit testing. This training will include the following elements: Why the respirator is necessary and how improper fit, usage, or maintenance can compromise the protective effect of the respirator; The limitations and capabilities of each respirator used; How to use the respirator effectively in emergency situations, including situations where the respirator malfunctions; How to inspect, don and remove, use, and check the seals of the respirator; The procedures for maintenance and storage of the respirator; Respiratory Protection Program Page 5 ©2011, Waste Management January 2011
  • 930. RESPIRATORY PROTECTION PROGRAM Recognition of medical signs and symptoms that may limit or prevent the effective use of respirators; The general requirements of our company’s program and the standard. This training will be repeated at least annually and will be documented using an Employee Annual Respirator Fit-Test and Training Record. Supplement training will be provided as necessary based on the following factors: Changes in the workplace or a new type of respirator; Demonstrated inadequacies in an employee’s knowledge or use of the respirator; or Any other situation in which retraining appears necessary to ensure safe respirator use. Individuals using a tight-fitting respirator will be trained on [User Seal Check Procedures-- Appendix C]. Cleaning, Storage and Maintenance of Respirators Routine-Use Respirators (individually assigned respirators) We will provide supplies and parts necessary to assure proper sanitation and maintenance of any respirator assigned to an individual employee. Employees will keep their respirators clean and disinfected at all times. [Respirator Cleaning Procedures--Appendix D]. Each respirator must be inspected before each use and during cleaning for proper functioning of all parts and components: 1. A check of respirator function, tightness of connections, and the condition of the various parts including, but not limited to, the face piece, head straps, valves, connecting tube, and cartridges, canisters or filters; and 2. A check of elastic parts for pliability and signs of deterioration. Non-Routine Use Respirator (emergency and non-individually assigned respirators). WGSL will provide each respirator user with a respirator that is clean, sanitary, and in good working order. Respirators will be cleaned and disinfected before being worn by different individuals. Respirators maintained for emergency use will be cleaned and disinfected after each use and respirators used in fit testing training will be cleaned and disinfected after each use. Storage of Routine-Use Respirators All respirators will be stored to protect them from damage, contamination, dust, sunlight, extreme temperatures, excessive moisture, and damaging chemicals, and they will be packed or stored to prevent deformation of the face piece and exhalation valve. Respiratory Protection Program Page 6 ©2011, Waste Management January 2011
  • 931. RESPIRATORY PROTECTION PROGRAM Storage of Emergency Respirators Emergency respirators will be: Kept accessible to the work area; Stored in compartments or in covers that are clearly marked as containing emergency respirators; Stored in accordance with any applicable manufacture instructions; All respirators maintained for use in emergency situations will be inspected at least monthly and in accordance with the manufacture’s recommendations, and will be checked for proper function before and after each use; Emergency escape-only respirators will be inspected before being carried into the workplace for use; and Inspections are documented by a tag or written/electronic inspection record. Inspection and Maintenance of Self-Contained Breathing Apparatus (SCBA) SCBA devices (emergency and non-emergency) will be inspected monthly. Air and oxygen cylinders will be maintained in a fully charged state and will be recharged when the pressure falls to 90% of the manufacture’s recommended pressure level. WGSL will determine that the regulator and warning devices function properly. Air Quality for Self-Contained and Air Line Devices Compressed and liquid oxygen (if used) must meet the United State Pharmacopoeia requirements for medical or breathing oxygen. Compressed breathing air will meet at least the requirements for Grade D breathing air described in the ANSI/Compressed Gas Association Commodity Specification for Air, G-7.1-1989, including: oxygen content (v/v) of 19.5-23.5%; hydrocarbon (condensed) content of 5 milligrams per cubic meter of air or less; carbon monoxide (CO) content of 10 ppm or less; carbon dioxide content of 1,000 ppm or less; and lack of noticeable odor. Compressed oxygen will not be used in atmosphere-supply respirators that have previously been used for compressed air. Oxygen concentrations greater than 23.5% are used only in equipment designed for oxygen service or distribution. Cylinders are tested and maintained as prescribed in the Shipping Container Specification Regulations of the Department of Transportation (49 CFR part 173 and part 178). Cylinders of purchased breathing air have a certificate of analysis from the supplier that the breathing air meets the requirements of Grade D breathing air. The moisture content in the cylinder does not exceed a dew point of -50 deg. F (-45.6 deg. C) at a 1-atmosphere pressure. Respiratory Protection Program Page 7 ©2011, Waste Management January 2011
  • 932. RESPIRATORY PROTECTION PROGRAM Compressor Systems Compressors used to supply breathing air to respirators are constructed and situated so as to: Prevent entry of contaminated air into the air-supply systems. Minimize moisture content so that the dew point at 1 atmosphere pressure is 10 deg. F (-5.56 deg. C) below the ambient temperature. Have suitable in-line air-purifying sorbent beds and filters to further ensure that the quality of breathing air is maintained by following the manufacturer's instructions. Have a tag maintained at the compressor that contains the most recent change date and the signature of the person authorized by the company to perform the change. For compressors that are not oil-lubricated, a means to assure that carbon monoxide levels in the breathing air do not exceed 10 ppm. For oil-lubricated compressors, a high-temperature or carbon monoxide alarm, or both, is used to monitor carbon monoxide levels. If only high-temperature alarms are used, the air supply will be monitored at intervals sufficient to prevent carbon monoxide in the breathing air from exceeding 10 ppm. Breathing air couplings are incompatible with outlets for non-respirable worksite air or other gas systems. No asphyxiating substance will be introduced into breathing air lines. Only breathing gas containers marked in accordance with the NIOSH respirator certification standard [42 CFR §84] are used. Voluntary Respirator Use Filtering Masks Employees who use filtering masks in situations that do not otherwise require the use of a respirator are not covered by this program. Tight-fitting Respirators Employees who use tight-fitting respirators when respirators are not otherwise required are subject only to the following provisions of this program: Medical evaluation; Cleaning and sanitation; Storage; and [Information for Employees Using Respirators When Not Required Under the Standard--Appendix E] Respiratory Protection Program Page 8 ©2011, Waste Management January 2011
  • 933. RESPIRATORY PROTECTION PROGRAM Change Schedule For vapor or gas air purifying respirators the two systems in place to warn respirator wearers of contaminant breakthrough include using respirator cartridges equipped with an end-of-service life indicator (ESLI) or using a cartridge replacement schedule based on manufacturer breakthrough test data. Employees using cartridges not equipped with ESLIs must replace cartridges in accordance with the instruction. When air purifying respirators with cartridges are used the cartridges must be changed out: A minimum of every 30 days; or Whenever an employee feels that they have become saturated and / or experiences breakthrough. At the beginning of each shift. At more frequent intervals. Air purifying cartridges absorb moisture and / or contaminants once they are exposed to the atmosphere. Respirators should not be stored with air purifying cartridges attached. Once opened, a package of cartridges should be considered reliable for one work shift (8 hours). Protection for Particulates, Mists, and Fumes: Either atmosphere-supplying respirators or air purifying respirators with appropriate filters may be used for protection from particulates, mists, and fumes. When air purifying respirators with filters are used the filters must be changed out: Whenever an employee feels the filters have become clogged and / or experiences difficulty breathing. For respirators worn exclusively for protection against particles, filters will be changed per the manufacturer’s specification and whenever the wearer detects a change in breathing resistance. Air supply unit will have filter replaced at manufacturer specified times and documented Policy of Providing Respirators and Medical Evaluations at No Cost to the Employee Employees will be provided respirators, medical evaluations and other requirements of the respirator standard at no cost to them. Annual Program Evaluation An annual evaluation of the respirator program will be conducted by the WGSL. The evaluation will be conducted by the Respirator Program Administrator and will consist of: Respiratory Protection Program Page 9 ©2011, Waste Management January 2011
  • 934. RESPIRATORY PROTECTION PROGRAM A review of the written respiratory protection program to assure that it is up-to-date, effective and is being properly implemented; Observation to ensure that employees are using the respirators properly; Consultation with an employee representative to assess the employees' views on program effectiveness and to identify any problems; Checking respirator fit (including the ability to use the respirator without interfering with effective workplace performance); Checking appropriate respirator selection for the hazards to which employees are exposed; Requiring proper respirator use under the workplace conditions the employee encounters; and Proper respirator maintenance. Any problems that are identified during this assessment will be corrected. Periodic Evaluations will be documented using the [Periodic Respirator Program Evaluation Form--Attachment F]. Respiratory Protection Program Page 10 ©2011, Waste Management January 2011
  • 935. RESPIRATORY PROTECTION PROGRAM Recordkeeping Compliance with the elements of the standard including medical evaluations, fit testing, training, and periodic evaluation of the respirator program will be maintained for a minimum of three (3) years. The program will be located in the WGSL office. Approved by: Title: __________________________________________ Print Name ___________________________________________ Signature ___________________________________________ Date Respiratory Protection Program Page 11 ©2011, Waste Management January 2011
  • 936. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE OSHA RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE (MANDATORY) To the employer: Answers to questions in Section 1, and to question 9 in Section 2 of Part A, do not require a medical examination. To the employee: Can you read (circle one): Yes/No Your employer must allow you to answer this questionnaire during normal working hours, or at a time and place that is convenient to you. To maintain your confidentiality, your employer or supervisor must not look at or review your answers, and your employer must tell you how to deliver or send this questionnaire to the health care professional who will review it. Part A. Section 1. (Mandatory) The following information must be provided by every employee who has been selected to use any type of respirator (please print). 1. Today's Date: _________________________ 2. Your name: __________________________ 3. Your age (to nearest year) :______________ 4. Sex (circle one): Male/Female 5. Your height: __________ ft. __________ in. 6. Your weight: ____________ lbs. 7. Your job title:_________________________ 8. A phone number where you can be reached by the health care professional who reviews this questionnaire (include the Area Code): ____________________ 9. The best time to phone you at this number: ________________ 10. Has your employer told you how to contact the health care professional who will review this questionnaire (circle one): Yes/No 11. Check the type of respirator you will use (you can check more than one category): a. ______ N, R, or P disposable respirator (filter-mask, non- cartridge type only). b. ______ Other type (for example, half- or full-face piece type, powered-air purifying, supplied-air, self- contained breathing apparatus). 12. Have you worn a respirator (circle one): Yes/No If "yes," what type(s): __________________________________________________________________________________________ __________________________________________________________________________________________ Part A. Section 2. (Mandatory) Questions 1 through 9 below must be answered by every employee who has been selected to use any type of respirator (please circle "yes" or "no"). Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 937. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE 1. Do you currently smoke tobacco, or have you smoked tobacco in the last month: Yes/No 2. Have you ever had any of the following conditions? a. Seizures (fits): Yes/No b. Diabetes (sugar disease): Yes/No c. Allergic reactions that interfere with your breathing: Yes/No d. Claustrophobia (fear of closed-in places): Yes/No e. Trouble smelling odors: Yes/No 3. Have you ever had any of the following pulmonary or lung problems? a. Asbestosis: Yes/No b. Asthma: Yes/No c. Chronic bronchitis: Yes/No d. Emphysema: Yes/No e. Pneumonia: Yes/No f. Tuberculosis: Yes/No g. Silicosis: Yes/No h. Pneumothorax (collapsed lung): Yes/No i. Lung cancer: Yes/No j. Broken ribs: Yes/No k. Any chest injuries or surgeries: Yes/No l. Any other lung problem that you've been told about: Yes/No 4. Do you currently have any of the following symptoms of pulmonary or lung illness? a. Shortness of breath: Yes/No b. Shortness of breath when walking fast on level ground or walking up a slight hill or incline: Yes/No c. Shortness of breath when walking with other people at an ordinary pace on level ground: Yes/No d. Have to stop for breath when walking at your own pace on level ground: Yes/No e. Shortness of breath when washing or dressing yourself: Yes/No f. Shortness of breath that interferes with your job: Yes/No g. Coughing that produces phlegm (thick sputum): Yes/No h. Coughing that wakes you early in the morning: Yes/No i. Coughing that occurs mostly when you are lying down: Yes/No j. Coughing up blood in the last month: Yes/No k. Wheezing: Yes/No l. Wheezing that interferes with your job: Yes/No m. Chest pain when you breathe deeply: Yes/No n. Any other symptoms that you think may be related to lung problems: Yes/No 5. Have you ever had any of the following cardiovascular or heart problems? a. Heart attack: Yes/No b. Stroke: Yes/No c. Angina: Yes/No d. Heart failure: Yes/No e. Swelling in your legs or feet (not caused by walking): Yes/No f. Heart arrhythmia (heart beating irregularly): Yes/No g. High blood pressure: Yes/No h. Any other heart problem that you've been told about: Yes/No 6. Have you ever had any of the following cardiovascular or heart symptoms? a. Frequent pain or tightness in your chest: Yes/No b. Pain or tightness in your chest during physical activity: Yes/No c. Pain or tightness in your chest that interferes with your job: Yes/No Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 938. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE d. In the past two years, have you noticed your heart skipping or missing a beat: Yes/No e. Heartburn or indigestion that is not related to eating: Yes/ No f. Any other symptoms that you think may be related to heart or circulation problems: Yes/No 7. Do you currently take medication for any of the following problems? a. Breathing or lung problems: Yes/No b. Heart trouble: Yes/No c. Blood pressure: Yes/No d. Seizures (fits): Yes/No 8. If you've used a respirator, have you ever had any of the following problems? (If you've never used a respirator, check the following space and go to question 9:) a. Eye irritation: Yes/No b. Skin allergies or rashes: Yes/No c. Anxiety: Yes/No d. General weakness or fatigue: Yes/No e. Any other problem that interferes with your use of a respirator: Yes/No 9. Would you like to talk to the health care professional who will review this questionnaire about your answers to this questionnaire: Yes/No Questions 10 to 15 below must be answered by every employee who has been selected to use either a full-face piece respirator or a self-contained breathing apparatus (SCBA). For employees who have been selected to use other types of respirators, answering these questions is voluntary. 10. Have you ever-lost vision in either eye (temporarily or permanently): Yes/No 11. Do you currently have any of the following vision problems? a. Wear contact lenses: Yes/No b. Wear glasses: Yes/No c. Color blind: Yes/No d. Any other eye or vision problem: Yes/No 12. Have you ever had an injury to your ears, including a broken ear drum: Yes/No 13. Do you currently have any of the following hearing problems? a. Difficulty hearing: Yes/No b. Wear a hearing aid: Yes/No c. Any other hearing or ear problem: Yes/No 14. Have you ever had a back injury: Yes/No 15. Do you currently have any of the following musculoskeletal problems? a. Weakness in any of your arms, hands, legs, or feet: Yes/No b. Back pain: Yes/No c. Difficulty fully moving your arms and legs: Yes/No d. Pain or stiffness when you lean forward or backward at the waist: Yes/No e. Difficulty fully moving your head up or down: Yes/No f. Difficulty fully moving your head side to side: Yes/No g. Difficulty bending at your knees: Yes/No h. Difficulty squatting to the ground: Yes/No i. Climbing a flight of stairs or a ladder carrying more than 25 lbs.: Yes/No j. Any other muscle or skeletal problem that interferes with using a respirator: Yes/No Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 939. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE Part B Any of the following questions, and other questions not listed, may be added to the questionnaire at the discretion of the health care professional who will review the questionnaire. 1. In your present job, are you working at high altitudes (over 5,000 feet) or in a place that has lower than normal amounts of oxygen: Yes/No If "yes," do you have feelings of dizziness, shortness of breath, pounding in your chest, or other symptoms when you're working under these conditions: Yes/No 2. At work or at home, have you ever been exposed to hazardous solvents, hazardous airborne chemicals (e.g., gases, fumes, or dust), or have you come into skin contact with hazardous chemicals: Yes/No If "yes," name the chemicals if you know them: __________________________________________________________________________________________ __________________________________________________________________________________________ __________________________________________________________________________________________ 3. Have you ever worked with any of the materials, or under any of the conditions, listed below: a. Asbestos: Yes/No b. Silica (e.g., in sandblasting): Yes/No c. Tungsten/cobalt (e.g., grinding or welding this material): Yes/No d. Beryllium: Yes/No e. Aluminum: Yes/No f. Coal (for example, mining): Yes/No g. Iron: Yes/No h. Tin: Yes/No i. Dusty environments: Yes/No j. Any other hazardous exposures: Yes/No If "yes," describe these exposures: ______________________________________________________________________________________ __________________________________________________________________________________________ __________________________________________________________________________________________ 4. List any second jobs or side businesses you have: _________________________________________________ __________________________________________________________________________________________ 5. List your previous occupations: __________________________________________________________________________________________ __________________________________________________________________________________________ 6. List your current and previous hobbies: __________________________________________________________ __________________________________________________________________________________________ 7. Have you been in the military services? Yes/No If "yes," were you exposed to biological or chemical agents (either in training or combat): Yes/No Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 940. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE 8. Have you ever worked on a HAZMAT team? Yes/No 9. Other than medications for breathing and lung problems, heart trouble, blood pressure, and seizures mentioned earlier in this questionnaire, are you taking any other medications for any reason (including over-the-counter medications): Yes/No If "yes," name the medications if you know them:________________________________ 10. Will you be using any of the following items with your respirator(s)? a. HEPA Filters: Yes/No b. Canisters (for example, gas masks): Yes/No c. Cartridges: Yes/No 11. How often are you expected to use the respirator(s) (circle "yes" or "no" for all answers that apply to you)?: a. Escape only (no rescue): Yes/No b. Emergency rescue only: Yes/No c. Less than 5 hours per week: Yes/No d. Less than 2 hours per day: Yes/No e. 2 to 4 hours per day: Yes/No f. Over 4 hours per day: Yes/No 12. During the period you are using the respirator(s), is your work effort: a. Light (less than 200 kcal per hour): Yes/No If "yes," how long does this period last during the average shift:____________hrs.____________mins. Examples of a light work effort are sitting while writing, typing, drafting, or performing light assembly work; or standing while operating a drill press (1-3 lbs.) or controlling machines. b. Moderate (200 to 350 kcal per hour): Yes/No If "yes," how long does this period last during the average shift:____________hrs.____________mn. Examples of moderate work effort are sitting while nailing or filing; driving a truck or bus in urban traffic; standing while drilling, nailing, performing assembly work, or transferring a moderate load (about 35 lbs.) at trunk level; walking on a level surface about 2 mph or down a 5-degree grade about 3 mph; or pushing a wheelbarrow with a heavy load (about 100 lbs.) on a level surface. c. Heavy (above 350 kcal per hour): Yes/No If "yes," how long does this period last during the average shift:____________hrs.____________mn. Examples of heavy work are lifting a heavy load (about 50 lbs.) from the floor to your waist or shoulder; working on a loading dock; shoveling; standing while bricklaying or chipping castings; walking up an 8- degree grade about 2 mph; climbing stairs with a heavy load (about 50 lbs.). 13. Will you be wearing protective clothing and/or equipment (other than the respirator) when you're using your respirator: Yes/No If "yes," describe this protective clothing and/or equipment: _______________________________________ _______________________________________________________________________________________ 14. Will you be working under hot conditions (temperature exceeding 77 deg. F): Yes/No 15. Will you be working under humid conditions: Yes/No Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 941. RESPIRATOR MEDICAL EVALUATION QUESTIONNAIRE 16. Describe the work you'll be doing while you're using your respirator(s): __________________________________________________________________________________________ __________________________________________________________________________________________ 17. Describe any special or hazardous conditions you might encounter when you're using your respirator(s) (for example, confined spaces, life-threatening gases): __________________________________________________________________________________________ __________________________________________________________________________________________ 1. Provide the following information, if you know it, for each toxic substance that you'll be exposed to when you're using your respirator(s): Name of the first toxic substance: _____________________________________ Estimated maximum exposure level per shift: _____________________________________ Duration of exposure per shift: ___________________________________________________________________ Name of the second toxic substance: _____________________________________ Estimated maximum exposure level per shift: ___________________________________________________________________ Duration of exposure per shift: ___________________________________________________________________ Name of the third toxic substance: ___________________________________________________________________ Estimated maximum exposure level per shift: ___________________________________________________________________ Duration of exposure per shift: ___________________________________________________________________ The name of any other toxic substances that you'll be exposed to while using your respirator:_________________________________________________________________________________ __________________________________________________________________________________________ __________________________________________________________________________________________ 19. Describe any special responsibilities you'll have while using your respirator(s) that may affect the safety and well being of others (for example, rescue, security): __________________________________________________________________________________________ ___________________________________________________________________________ Respiratory Protection Attachment A ©2011, Waste Management January 2011
  • 942. EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD District Name: ___________________________________________________ Employee Name: ___________________________________________________ Occupation/Job: ___________________________________________________ Respirator Use Information Work Area(s) _____________________________________________________________________ _____________________________________________________________________ Exposure Conditions Chemicals Exposure Estimate and PEL/STEL Emergency Use of Respirators (Member of HAZMAT Team) Yes No Type(s) of Respirator Used Voluntary air purifying ( half-face or full-face) Half-face air purifying Full-face air purifying Self-contained breathing apparatus (pressure demand) Airline breathing apparatus (pressure demand) Other; specify what type: ___________________________________________ Air Purifying Cartridges Used Contaminant Cartridge Name and Color Code Respiratory Protection Attachment B ©2005, Waste Management January 1, 2005
  • 943. EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD Fit-Testing Record Fit-test Protocol Used (indicate each used if more than one) Qualitative; Test Substance: ____________________________________________________________ Other: ____________________________________________________________ Quantitative; Test Method: ____________________________________________________________ Other: ____________________________________________________________ Respirator(s) Successfully Fitted Type of Respirator Brand Model Size Half-face air purifying Full-face air purifying Self-contained breathing apparatus Supplied-air breathing apparatus Other, specify: Fit Test Certification Respirator fit testing for the devices indicated in was successfully completed. Employee: ________________________________________ Signature: ________________________________________________ Date: _______________________ Tester: ________________________________________ Signature: ________________________________________________ Date: _______________________ Respiratory Protection Attachment B ©2005, Waste Management January 1, 2005
  • 944. EMPLOYEE ANNUAL RESPIRATOR FIT-TEST AND TRAINING RECORD Training Record Training Subjects Covered Purpose and conditions of respirator use (nature and concentrations of air contaminants known or anticipated). Requirements for use--when respirator(s) are required. How the device operates--its components and their maintenance. Respirator inspection and cleaning procedures and employee obligation for cleaning and maintenance as applicable. Chemical cartridge selection criteria, change out frequency and warning signs for break-through and other failures. Instruction to terminate exposure if a problem is detected. [If air-supplied or self-contained, the air supply (pressure gauge) and low pressure alarm should be described and demonstrated.] How to properly don each respirator to be used. How to conduct self-seal check and that this is mandatory upon each use. An explanation of fit-testing procedures. An explanation of medical surveillance and procedures. Other warnings and precautions as set forth in the manufacturer's instruction, including emphasis that air- purifying respirators do not supply breathing air and must not be used in an oxygen-deficient atmosphere. Training Certification Training in all of the above topics was successfully completed. Employee: ________________________________________ Signature: ________________________________________________ Date: _______________________ Trainer: ________________________________________ Signature: ________________________________________________ Date: _______________________ Respiratory Protection Attachment B ©2005, Waste Management January 1, 2005
  • 945. USER SEAL CHECK Appendix B-1. to Section 5144: User Seal Check Procedures (Mandatory) The individual who uses a tight-fitting respirator is to perform a user seal check to ensure that an adequate seal is achieved each time the respirator is put on. Either the positive and negative pressure checks listed in this appendix, or the respirator manufacturer's recommended user seal check method will be used. User seal checks are not substitutes for qualitative or quantitative fit tests. Face piece Positive and/or Negative Pressure Checks. 1. Positive pressure check. Close off the exhalation valve and exhale gently into the face piece. The face fit is considered satisfactory if a slight positive pressure can be built up inside the face piece without any evidence of outward leakage of air at the seal. For most respirators this method of leak testing requires the wearer to first remove the exhalation valve cover before closing off the exhalation valve and then carefully replacing it after the test. 2. Negative pressure check. Close off the inlet opening of the canister or cartridge(s) by covering with the palm of the hand(s) or by replacing the filter seal(s), inhale gently so that the face piece collapses slightly, and hold the breath for ten seconds. The design of the inlet opening of some cartridges cannot be effectively covered with the palm of the hand. The test can be performed by covering the inlet opening of the cartridge with a thin latex or nitrile glove. If the face piece remains in its slightly collapsed condition and no inward leakage of air is detected, the tightness of the respirator is considered satisfactory. Manufacturer's Recommended User Seal Check Procedures. The respirator manufacturer's recommended procedures for performing a user seal check may be used instead of the positive and/or negative pressure check procedures provided that the employer demonstrates that the manufacturer's procedures are equally effective. Respiratory Protection Attachment C ©2005, Waste Management January 1, 2005
  • 946. RESPIRATOR CLEANING PROCEDURES Appendix B-2. to Section 5144: Respirator Cleaning Procedures (Mandatory) Guide to Respiratory Protection at Work These procedures are provided for employer use when cleaning respirators. They are general in nature, and the employer as an alternative may use the cleaning recommendations provided by the manufacturer of the respirators used by their employees, provided such procedures are as effective as those listed here in Appendix B-2. Equivalent effectiveness simply means that the procedures used must accomplish the objectives set forth in Appendix B-2, i.e., must ensure that the respirator is properly cleaned and disinfected in a manner that prevents damage to the respirator and does not cause harm to the user. Procedures for Cleaning Respirators. 1. Remove filters, cartridges, or canisters. Disassemble face pieces by removing speaking diaphragms, demand and pressure-demand valve assemblies, hoses, or any components recommended by the manufacturer. Discard or repair any defective parts. 2. Wash components in warm (43 deg. C [110 deg. F] maximum) water with a mild detergent or with a cleaner recommended by the manufacturer. A stiff bristle (not wire) brush may be used to facilitate the removal of dirt. 3. Rinse components thoroughly in clean, warm (43 deg. C [110 deg. F] maximum), preferably running water. Drain. 4. When the cleaner used does not contain a disinfecting agent, respirator components should be immersed for two minutes in one of the following: 5. Hypochlorite solution (50 ppm of chlorine) made by adding approximately one milliliter of laundry bleach to one liter of water at 43 deg. C (110 deg. F); or, 6. Aqueous solution of iodine (50 ppm iodine) made by adding approximately 0.8 milliliters of tincture of iodine (6-8 grams ammonium and/or potassium iodide/100 cc of 45% alcohol) to one liter of water at 43 deg. C (110 deg. F); or, 7. Other commercially available cleansers of equivalent disinfectant quality when used as directed, if their use is recommended or approved by the respirator manufacturer. 8. Rinse components thoroughly in clean, warm (43 deg. C [110 deg. F] maximum), preferably running water. Drain. The importance of thorough rinsing cannot be overemphasized. Detergents or disinfectants that dry on face pieces may result in dermatitis. In addition, some disinfectants may cause deterioration of rubber or corrosion of metal parts if not completely removed. 9. Components should be hand-dried with a clean lint-free cloth or air-dried. 10. Reassemble face piece, replacing filters, cartridges, and canisters where necessary. Test the respirator to ensure that all components work properly. Respiratory Protection Attachment D ©2005, Waste Management January 1, 2005
  • 947. INFORMATION FOR EMPLOYEES USING RESPIRATORS WHEN NOT REQUIREDUNDER THE STANDAR Appendix D to Section 5144: (Mandatory) Information for Employees Using Respirators When Not Required Under the Standard Respirators are an effective method of protection against designated hazards when properly selected and worn. Respirator use is encouraged even when exposures are below the exposure limit, to provide an additional level of comfort and protection for workers. However, if a respirator is used improperly or not kept clean, the respirator itself can become a hazard to the worker. Sometimes, workers may wear respirators to avoid exposures to hazards, even if the amount of hazardous substance does not exceed the limits set by OSHA standards. If your employer provides respirators for your voluntary use, or if you provide your own respirator, you need to take certain precautions to be sure that the respirator itself does not present a hazard. You should do the following: 1. Read and heed all instructions provided by the manufacturer on use, maintenance, cleaning and care, and warnings regarding the respirators limitations. 2. Choose respirators certified for use to protect against the contaminant of concern. NIOSH, the National Institute for Occupational Safety and Health of the U.S. Department of Health and Human Services, certifies respirators. A label or statement of certification should appear on the respirator or respirator packaging. It will tell you what the respirator is designed for and how much it will protect you. 3. Do not wear your respirator into atmospheres containing contaminants for which your respirator is not designated to protect against. For example, a respirator designed to filter dust particles will not protect you against gases, vapors or very small solid particles of fumes or smoke. 4. Keep track of your respirator so that you do not mistakenly use someone else's respirator. Respiratory Protection Attachment E ©2005, Waste Management January 1, 2005
  • 948. PERIODIC RESPIRATOR PROGRAM EVALUATION Person Performing Evaluation: ________________________________________ Program Administrator: ________________________________________ Date of Last Evaluation: ____/_____/______ Date of This Evaluation: ____/_____/_______ Review of Written Program Is written program up-to-date? Yes No If no, what changes are needed? _________________________________________________________________________________________ _________________________________________________________________________________________ Have there been any changes in respirator use or exposure conditions since the last review? Yes No If yes, summarize the changes: _________________________________________________________________________________________ _________________________________________________________________________________________ Are all personnel responsible for the respirator program properly listed? Yes No If no, what changes should be made? _________________________________________________________________________________________ _________________________________________________________________________________________ Observation of Respirator-using Employees When asked, are employees satisfied and comfortable with respirator use and the employer's program? Yes No If no, what problems need to be corrected? _________________________________________________________________________________________ _________________________________________________________________________________________ Are respirators in use, properly fitted (check for obvious poor fits, facial hair, other interferences)? Yes No If no, fit-testing should be required: _________________________________________________________________________________________ _________________________________________________________________________________________ Are respirators in use, appropriate for exposure conditions and required work? Yes No If no, what problems should be corrected? _________________________________________________________________________________________ _________________________________________________________________________________________ Are respirators in use, fitted with the proper cartridges? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ Respiratory Protection Attachment F ©2005, Waste Management January 1, 2005
  • 949. PERIODIC RESPIRATOR PROGRAM EVALUATION Are respirators in use, properly maintained in terms of sanitation, parts in place, etc.? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ Respirators In Storage Are all respirators in storage in sealed plastic bags and properly stored? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ If an emergency device, is the unit being inspected monthly, and is this inspection specifically documented with a tag or otherwise? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ Are all SCBA air tanks on devices not in use and tanks in storage filled to 90% of capacity? Yes No If no: __________________________________________________________________________________________ __________________________________________________________________________________________ Documentation Review Are records available indicating initial and/or respirator fit-testing and training for all users within the past 12 months? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ Are there initial medical evaluation documents for all employees who use respirators? Yes No If no: _________________________________________________________________________________________ _________________________________________________________________________________________ Is there a need for more frequent periodic evaluations for any employee or group of employees? Yes No If yes: _________________________________________________________________________________________ _________________________________________________________________________________________ Signed: __________________________________________________ Date: __________________________ Respiratory Protection Attachment F ©2005, Waste Management January 1, 2005
  • 950. RESPIRATORY PROTECTION BASED ON HISTORICAL AIR MONITORING Note: Evaluate All Operations Not Listed Below And Those Utilizing Technology Applied Developed After June 1998 OPERATION HAZARD ASSESSED RESPIRATORY RESPIRATORY PROTECTION PROTECTION REQUIRED NOT REQUIRED Hauling Driver - Special Wastes new materials X Driver - Asbestos as needed X Dusts X Landfill / Transfer Driver site truck dust/silica X Driver water truck dust/silica X Gas plant / gas recovery X Laboratory personnel methylene chloride NA NA Loaders - transfer / tipping dust/silica X Operator compactor NA NA Operator landfill equipment dust/silica X Spotter - transfer / tipping dust/silica X Operator track loader/transfer new methods (non-friable NA NA asbestos) Maintenance Mechanic - hauling lead in old container paint X Container Repair Mechanic - hauling fume, copper electrodes inside X Truck Body Repair bodies (inside truck bodies) Painter - Water Reducible Paint X Painter - Solvent based Paint solvents X Mechanic -landfill X Mechanic - MRF X Material Recovery Facility Baler operator dusts NA NA Forklift/bobcat operator dusts X Sorters - Recycle Line dusts NA NA Sorters - Commingle MRF dusts X Ticket collector MRF dusts/silica X Note: Data collected in over ten years of monitoring routine, non-routine and “worst case” workplace exposures show results of airborne concentrations of dusts, mists, fumes, vapors and gases are routinely below 10% of their respective PELs. Exposures may exceed action levels or PELs from solvent based paint, carbon arc welding inside truck bodies, and in dusty areas where high levels of airborne road dust contain 10% silica sand (on some landfill haul roads and on some tipping floors). Continue to assess non-routine operations and new methods to ensure sampling results are representative, adequate engineering controls are in place and proper PPE is selected. NA=SUFFICIENT DATA TO EVALUATE NOT AVAILABLE Respiratory Protection Attachment G ©2005, Waste Management January 1, 2005
  • 951. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Program: Industrial Lift Truck (Forklift) Facility: Waimanalo Gulch Sanitary Landfill Facility Location: 92-460 Farrington Highway, Kapolei, HI 96707 PURPOSE This program defines the safety requirements and responsibilities for operating forklifts and powered industrial trucks. Safe use of industrial trucks prevents injuries, property damage, and excessive maintenance. The powered industrial trucks program contains method for complying with company and regulatory requirements and explains the who, what, when, where, and how of implementing the powered industrial trucks program. Nameplates and Markings Label, or identify with a marking, all powered industrial trucks approved in a nationally recognized testing laboratory (DS, DY, EE and EX). Maintain all nameplates in legible condition and ensure they are firmly affixed to the powered industrial truck. If the powered industrial truck is equipped with front-end attachments other than factory installed attachments, which is approved by the manufacturer, have the truck marked to identify the attachments and show the approximate weight of the truck and attachment combination. Inspections Inspect all powered industrial trucks before placing them in service. Do not place a truck into service if the truck inspection shows any condition that could adversely affect the safety of the vehicle. Perform an inspection of each powered industrial truck at the start of each work shift. The pre-operation inspection should determine the condition of the vehicle or mobile unit before operation by the next employee. Any damage must be noted and reported to the supervisor. Document all inspections. Inspect the controls, brakes, tires, load-engaging mechanism; lift systems, steering mechanism, lights, horn, oil and water. Keep an inspection and repair record for each truck. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 1 ©2011, Waste Management January 2011
  • 952. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Safely move any powered industrial trucks to an out of the way, safe location until repaired, and label it “Out-of-service, do not operate”. Caution: Moving a vehicle with an identified brake problem could be a safety issue. Inspect each industrial truck before each shift. Report and correct any defects as needed before using again. Training Train employees expected to operate a powered industrial truck, forklift, and hand-powered trucks. Establish a facility training program to train and certify powered industrial truck operators in the safe operation of powered industrial trucks and forklifts. The following is a list of required subjects to cover in employee/operator training that shall consist of formal classroom instruction, practical instruction (instructor demonstrations) and practical exercises: Truck related topics shall include: Operating instructions, warnings and precautions for the type of truck used. Differences between the truck and an automobile. Truck controls and instrumentation, where located and how they work. Engine or motor operation. Steering and maneuvering. Visibility including restrictions when loaded. Fork and attachment adaptation. Vehicle capacity and vehicle stability. Vehicle inspection and maintenance that the operator must perform. Refueling, charging or recharging batteries. Operating limitations and other instructions or warnings peculiar to the vehicle. Work related topics. Surface conditions where the vehicle will be operated. Composition and stability of loads to be moved. Load manipulation, stacking and unstacking. Pedestrian traffic in the vehicle operating area. Narrow aisles or other restricted areas. Hazardous areas of operation. Ramps and other sloped surfaces. Environments where exhaust gases could build-up. Other unique or potentially hazardous environments. In addition the requirements of 29 CFR 1910.178 must be covered in the training. Supervisor training should cover the following: INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 2 ©2011, Waste Management January 2011
  • 953. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Employee/operator training program. Attention to clearances, load restrictions, additional safety factors. Reporting of industrial lift truck problems. Evaluate and certify employees upon completion of training. Provide written training certification that includes the name of the operator, the date of training, the date of the evaluation, and the name(s) of the person performing the training and evaluation. Refresher Training Refresher training shall be provided to the operator when: The operator is observed operating in an unsafe manner. The operator is involved in an accident or near-miss incident. An operator evaluation reveals deficiencies in operating techniques, skills or practices. The operator is assigned a different type vehicle. Workplace conditions change so as to affect the safe operation of the truck. Out of Service Criteria Take any powered industrial truck out of service that is found to be in need of repair, defective or in any way unsafe, until it has been restored to a safe operating condition. “Out of Service” criteria include items affecting the safety of the truck (for example, non-functional back-up alarms, broken rollover bars or worn brakes). Lock or tag the truck out of operation. Maintenance If at any time a powered industrial truck is found to be in need of repair, defective, or in any way unsafe, take it out of service and label “Out-of-service” until it has been restored to safe operating condition. Ensure that all repairs are made only by facility authorized personnel. Ensure that any repairs to the fuel and ignition systems of powered industrial trucks are conducted only in locations designated by the facility safety coordinator for these types of repairs. Disconnect the battery before making electrical system repairs to the trucks. Replace any parts only with parts meeting the safety requirements of the original part. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 3 ©2011, Waste Management January 2011
  • 954. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Do not provide additional counterweighing of fork trucks unless approved by the powered industrial truck manufacturer in writing. When the temperature of any part of any powered industrial truck is found to be in excess of its normal operating temperature, remove the vehicle from service and tag “Out-of-service”. Do not return it to service until the cause of the overheating has been eliminated. Keep powered industrial trucks in a clean condition; free of dust, excess oil, and grease. Seat Belts Equip all vehicles that have rollover bars with seat belts and if it is a modification to install the seat belts, obtain manufacturers approval in writing. It is required that seat belts be worn at all times when operating a forklift or powered industrial truck equipped with seat belts. Powered Industrial Truck Operations Follow these safety requirements: 1. Do not allow persons to stand or pass under the elevated portion of any truck, loaded or empty. 2. Do not permit unauthorized personnel to ride on powered industrial trucks. 3. Set the forks to the maximum possible spread for each load to be carried. 4. Keep arms or legs inside the running lines of the truck. Do not place arms and legs between the uprights of the masts. 5. When a powered industrial truck is left unattended, fully lower the load engaging means, neutralize the controls, shut the power off, and set the brakes. It is a recommended practice to chock the wheels when the powered industrial truck is parked on an incline. A powered industrial truck is considered to be “unattended” when the vehicle is in view of the operator but the operator is more than 25 feet from the vehicle, or whenever the operator leaves the vehicle, and it is not in his or her view. 6. Keep at least two feet away from the edge of the ramps or platforms. 7. When loading and unloading a trailer, set the brakes (if coupled to the truck), and place chocks under the rear wheels to prevent the trailer from moving. 8. When the trailer is not coupled to the truck, use fixed jacks to support the trailer and prevent upending during loading or unloading. 9. Ensure that there is sufficient headroom under overhead installations, lights, entranceways, etc. 10. Use an overhead guard, where overhead lifting is performed, to protect against falling objects. The guard offers protection from impact from small packages, boxes, bagged material, etc. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 4 ©2011, Waste Management January 2011
  • 955. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM 11. Use a load backrest extension to minimize the possibility of part, or the entire load, falling rearward. 12. Slow down and sound the horn at cross aisles, corners and other locations where vision is obstructed. 13. Make certain the back-up alarm is in good, working order. 14. When the load being carried forward obstructs the view, turn around the forklift and travel with the load trailing. 15. Always look in the direction of travel. 16. Ascend or descend grades slowly. When ascending or descending slope grades in excess of ten percent, drive loaded trucks with the load upgrade. On all grades, tilt back and raise the load and load engaging means only as far as necessary to clear the road surface. 17. Properly secure dockboards or bridge plates before driving over them. 18. Slow down for wet and slippery floors. 19. Establish speed limits, where necessary, and post speed limit signs. 20. Define and mark designated travel routes. Loading Handle only stable and safely arranged loads. Exercise caution when handling off-center loads that cannot be centered. Loads must not exceed the rated capacity of the truck. When carrying loads, place the load engaging means under the load as far as possible and carefully tilt the mast backward to stabilize the load. Carry the load as close to the floor as possible. When traveling with a load, start and stop trucks gradually, and always look around before starting to move. If loading or unloading a trailer connected to a vehicle, all of the following precautions must be taken: Turn the vehicle engine off. Set the brakes of highway trucks and chock the rear wheels to prevent the trucks from rolling while they are boarded with powered industrial trucks. Set brakes and put wheel blocks in place to prevent movement of trucks, trailers, or railroad cars while loading or unloading. Fixed jacks may be necessary to support a semi trailer during loading or unloading when the trailer is not coupled to a tractor. Check the flooring of trucks, trailers, and railroad cars for breaks and weakness before they are driven onto. Secure dockboard or bridgeplates before they are driven over. Carefully and slowly drive over dockboard or bridgeplates and never exceed their rated capacity. Handle only stable or safely arranged loads. Use caution when handling off-center loads, which cannot be centered. Handle only loads within the rated capacity of the truck. Also take at least one of the following precautions: INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 5 ©2011, Waste Management January 2011
  • 956. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Place the vehicle’s ignition key in the possession of the person boarding the vehicle or trailer. Place the vehicle’s ignition key in a “lock box” and give the person boarding the vehicle possession of the “lock box” key. Actively secure the vehicle or trailer to a loading dock with a device that prevents powered or unpowered vehicle movement. The person boarding the vehicle or trailer must solely control the device. Note: if this option is used, tire chocks are not required. Hazards When operating lift trucks, the primary danger is colliding or overturning the truck. Always be aware of obstacles in the path of the truck, especially when backing up. Make sure there is enough clearance between the truck and other objects. When on a ramp or platform, stay at least two feet from the edge. Lift trucks can be overturned if they are not handled correctly on steep grades or if they are driven off the sides of platforms or ramps. Movement or collapse of bridge plates or dockboards causes another hazardous condition. Ensure that bags, cartons, boxes or other articles are secure. If these items fall from lift vehicles, they can cause severe injuries to the truck drivers and pedestrians, and financial loss due to damage. Battery Charging Only trained and authorized employees may change and/or charge batteries. Wear acid-resistant clothing, acid-resistant gloves, goggles and a face shield when changing the electrolyte solution in the battery. Charge or install batteries only in areas designated for this purpose. These areas have facilities for flushing and neutralizing spilled electrolytes, fire protection, protecting charging apparatus from damage from lift trucks, ventilation to reduce the potential for hydrogen gas buildup, and emergency drenching facilities. When charging batteries, require these safe work practices: Put on personal protective equipment. Properly position lift trucks, and apply brakes before charging. Use a carboy, tilter or siphon for handling the electrolyte. Pour acid into water. Do not pour water into acid. Open the battery compartments/covers to dissipate heat. Ensure that the vent caps are functioning. Designate the charging area as a “No Smoking” area and post signs. Take precautions to prevent open flames, sparks, or electric arcs in the charging area. Keep tools and other metallic objects away from the top of uncovered batteries. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 6 ©2011, Waste Management January 2011
  • 957. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Gasoline, Diesel and Liquefied Petroleum Gas Vehicles Gasoline, diesel or liquefied petroleum gas-powered trucks have the potential to catch fire if repaired or refueled incorrectly. Only trained authorized personnel are permitted to refuel or repair these trucks. Powered industrial trucks that use gas or diesel have internal combustion engines. The exhaust from combustion engines contains carbon monoxide, which is a chemical asphyxiant. Only use this equipment in areas where there is good ventilation. Fuel Storage The storage and handling of liquid fuels such as gasoline and diesel fuel must be in accordance with NFPA Flammable and Combustible Liquids Code (NFPA No. 30-1969). The storage and handling of liquefied petroleum gas fuel must be in accordance with NFPA Storage and Handling of Liquefied Petroleum Gases (NFPA No. 58-1969). Powered Hand Trucks There are two types of powered hand trucks: low-lift and high-lift. Low-lift trucks are used only for moving the material horizontally. Powered hand trucks are operated by electric motors. Only authorized personnel may charge batteries. Recharge the batteries only at a fixed battery charging facility. See the section on battery charging for safety instructions. The hazards of operating powered hand trucks include: Contact with the powered hand truck’s moving parts, such as wheels and lifting mechanisms. Loads falling due to incorrect operation. Collision between the powered hand truck and fixed objects, other trucks, or employees. Collision with a person caused by the operator riding the powered hand truck. Follow these safety practices when operating the powered hand trucks: 1. Lead the truck from either the right or left side of the handle, and face the direction of travel. 2. Walk ahead of the truck, except when it must be run close to a wall or other obstruction, or when driven down an incline. In such instances, operate the truck in reverse and walk behind it, facing the direction of travel. 3. Back the truck into a confined location to avoid being caught between the truck and the walls. 4. Give pedestrians the right of way at all times. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 7 ©2011, Waste Management January 2011
  • 958. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM 5. To prevent collisions, come to a full stop at blind corners, doorways and aisle intersections, and sound the warning device. 6. Operate the truck at a safe speed for existing conditions. It should never be operated at a speed greater than that of a normal walk. 7. Maintain a firm grip on the operating handle, keeping hands free of grease and water. 8. Never ride the truck unless it is specifically designed for the operator to ride. 9. Never permit other employees to ride the truck. 10. When going uphill on a ramp or slope, always travel with the load upgrade so it does not spill. 11. Keep loads low so the operator’s view is not obstructed. Operator Safety Instructions Never use the equipment without instructions. See machine signs (decals) Operation & Maintenance Manual and Handbook. Fasten seat belt snugly. Always keep feet on the pedals when operating loader. Never use equipment as man lift or elevating device for personnel. Never use equipment without operator cab with ROPS and FOPS approval. Do not use equipment in atmosphere with explosive dust or gas or where exhaust can contact flammable material. Never carry riders. Keep bystanders away from work area. Always carry bucket or attachments as low as possible. Do not travel or turn with lift arms up. Load, unload and turn on flat level ground. Never exceed rated operating capacity. Never modify equipment. Use only attachments approved for the model loader. Never leave loader with engine running or with lift arms up. To park, engage parking brake and put attachment flat on the ground. Prepare for Safe Operation 1. Check the Safety Equipment Falling Object Protective Structure (FOPS). Rollover Protective Structure (ROPS). Seat Belts. Operator Seat Bar(s). Side Shields, Screens or Cab. Grab Handles. Lift Arm Restraining Device(s). Lights. Anti-skid Tread/Steps. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 8 ©2011, Waste Management January 2011
  • 959. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Safety Signs. Horn. Guards. Back-up Alarm. Fire Extinguisher. 2. Never remove or disconnect any safety device. 3. Check the Machine Check for broken, missing or damaged parts. Make necessary repairs. Check the tires for cuts, bulges and correct pressure. Replace badly worn or damaged tires. Check the parking brake for proper operation. Perform all maintenance procedures outlined by the manufacturer of the machine. Check the hydraulic system. Have any leaks repaired. 4. Clean Machine 5. Windshield, Lights and Safety Signs. 6. Operator’s Area. 7. Steering levers. 8. Pedals steps. 9. Grab handles. 10. Remove snow, ice, mud, oil and grease. 11. 12. Use Caution when fueling 13. Don’t over fill tank. 14. Use correct type and grade of fuel. 15. Don’t fill the tank with the engine running. 16. Know the Working Area 17. Inspect the surface, ground, and floor levels. 18. Check for hidden obstacles, weak spots, and wet floors. 19. Know Clearances 20. Overhead doorway. 21. Aisles. 22. Weight limitations of machine, ramps, and floors. 23. Rules Of the Road 24. Slow moving vehicle emblem in place. 25. Check reflectors. 26. Mount Safely 27. Maintain a three-point contact with the steps and grab handles provided. 28. Face the machine. 29. Never jump on or off the machine. Never attempt to mount or dismount a moving machine. Definitions Approved Truck or Approved Industrial Trucks: A truck that is listed or approved, under nationally recognized testing standards, as fire safe for its intended use. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 9 ©2011, Waste Management January 2011
  • 960. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Powered Hand Truck: Any self-propelled truck that is controlled by a walking operator and is used to lift, carry, stack or tier material. Driver: An employee trained to properly operate a powered industrial truck, and trained to follow safety procedures and avoid hazards while operating the truck. Load Engaging Means: The part of the powered industrial truck that picks up the load. DS: Diesel-powered units with safeguards on the exhaust, fuel and electrical systems against inherent fire hazards. DY: Diesel-powered units with safeguards on the exhaust, fuel and electrical systems against inherent fire hazards. In addition these units do not have any electrical equipment, including the ignition, and are equipped with temperature limitation features. EX: Electric-powered units with specially designed, constructed and assembled electrical fittings for use in atmospheres containing flammable vapors and dusts and under certain conditions, fibers. EE: Electric-powered hand trucks with safeguards against inherent fire and electrical shock hazards. In addition, these units have enclosed electrical systems to prevent emission of hazardous sparks and to limit surface temperature. Powered Industrial Trucks: Specialized industrial trucks powered by electric motors or internal combustion including, but not limited to, fork trucks, tractors, platform lift trucks, and motorized hand trucks. INDUSTRIAL LIFT TRUCK (FORKLIFT) PROGRAM Page 10 ©2011, Waste Management January 2011