Running Head PROJECT PLAN PART 3PROJECT PLAN PART 35.docx
1. Running Head: PROJECT PLAN PART 3
PROJECT PLAN PART 3 5
Work Management Plan
The work management plan is a plan put together by the project
manager at the beginning of the project. It contains all of the
steps needed to complete the project and who is responsible for
the tasks. The work management plan can be used in
conjunction with the work breakdown structure, but does not
need to contain the directions of how to accomplish the tasks.
“Work plans document all activities to be undertaken, keep
everyone moving in the same direction, and allow for
comparison with and prioritizing against competing projects. If
we do not know where we are in our work at any given point in
2. time, we cannot accurately plan, schedule, or proceed with
future efforts. Once projects are under way, we need a map to
remind us of what is next, when it is due, and who is
responsible for it.” (Burgher & Snyder, 2012)
In the project of The Cheesecake Factory delivery service,
the project manager will be responsible for creating the work
management plan. Since the timeline of the project is primarily
within 60 days for most deliverables, the work management plan
will be updated on a weekly basis and discussed at project
meetings. Each task within the project will be outlined to
include what is to be done and by whom. The person responsible
for each action item will be asked to update the work plan
weekly with their progress as to the status. However, the only
person that will be permitted to add new tasks or change
existing tasks will be the project manager. Having a plan that is
accessible and visible to the team will aide in keeping the
project within scope and on schedule. Additionally, with only
the project manager being able to make changes, it will prevent
chaos within the project planning.
Quality Assurance
Quality assurance is part of the planned activities to ensure the
project is meeting the objectives that it is supposed to. They are
“the things that the project team will do to determine if project
performance is meeting the requirements of quality and other
standards. The activities are the things the project team will do
to check project performance against the project plan using
specifications as the targets.” (Rose, 2014)
As part of the quality assurance with The Cheesecake
Factory delivery service project, there will be several
inspections along the course of the project. There will be
project team members from marketing and operations that will
be responsible for inspecting the final product of the customized
delivery vehicles to ensure they are within the guidelines of
what was ordered and agreed upon. There will also be a specific
marketing team in place to review marketing materials after
printing to ensure everything was processed correctly on that
3. end.
Communication Management
When looking for software for project communication that can
be used to coordinate data, for resource management,
scheduling and communication, Microsoft SharePoint is a clear
choice. “SharePoint is a robust collaboration platform for
helping people work together in more effective ways, while
controlling costs and reducing IT risks.” (Treumann, 2014)
SharePoint houses documents of all formats, includes a calendar
and scheduling function, and even has a forum for team
discussion.
For the purposes of The Cheesecake Factory Delivery service,
because many of the project team members are remote, the work
management plan, WBS, and other project documents will be
house on a SharePoint site that can be accessed by everyone.
This was all can stay abreast of project status and requirements.
Below is also a communication plan matrix outlining the
frequency of meetings and briefings about the project. The
SharePoint will serve as a central location for project
information needed outside of the scheduled project meetings.
Communication Plan Matrix
Audience
Information
Method
Frequency
Who is Responsible
Project Team Members
Project Status Updates
Email
Weekly
Project Team Leads
Project Team Leads
Project Status Updates
Webex Call
Weekly
Project Manager
4. Project Team Members
Collaboration
Call
As needed
Project Team Leads
Project Team Leads
Collaboration
Call
As needed
Project Manager
Executive Leadership
Project Status Updates
Email
Monthly
Project Manager
Lower Level Employees
Project Status Updates
Email
Monthly
Project Manager
Facilities Personnel
Collaboration
Call
Biweekly/As needed
Project Team Leads and Members
Vendors
Collaboration
Call
As needed
Project Team Leads and Members
Contractors
Collaboration
Call
As needed
Project Team Leads and Members
5. Documenting Progress
For The Cheesecake Factory Delivery service project, the
documentation of project status will be a combination of efforts
by the project team members and the project manager. As
discussed above, the work management plan will be updated
weekly by the member responsible for the action as to the
status. Additionally, the project manager will be the primary
person responsible for keeping the work breakdown structure
updated frequently and accurately. This will ensure that all
tasks are on track and any additional resources that are added to
the project will be able to recap up to that point.
Change Request Management
As part of the change management process, a Change
Management Team is put into place. This review board is
primarily comprised of key stakeholders or leaders in the
industry that pertains to the project. Any changes that arise
during the project are vetted through the Change Management
Team to determine whether the change is beneficial to the
project, or should be refined or possibly even abandoned.
Crucial elements to the success of the project such as timeline,
budget, and resources are examined from every possible angle
to try and prepare for every piece of the project that will be
affected by the change. The Change Management Team is an
integral part of any change that happens during a project,
however, ultimately it is up to the project manager as to how to
proceed or not proceed with the proposed change. Because the
Change Management Team is not usually comprised of actual
project team members, there may be a lot of front line work or
repercussions that are not realized by those stakeholders that the
project manager might be aware of and can bring to the table.
An example of the Change Management process is
included below, and this would be used by the Change
Management Team to determine whether or not to implement a
suggested change.
Contingency Plans
6. Contingency planning for The Cheesecake Factory
Delivery Service project will be based upon risk assessment.
Qualitative risk assessment will be used to determine the
severity of the primary and secondary risks. The risks will then
be treated according to the risk management plan which will
also include contingency plans if a risk cannot be treated. A risk
register will also be kept by the project manager and updated
frequently as the project progresses to ensure that all risks are
monitored and treated accordingly.
References
Burgher, K. E., & Snyder, M. (2012). Non-Profit/Higher
education project management
series: The project plan. College and University, 88(1), 53-61.
Retrieved from
http://search.proquest.com/docview/1239088138?accountid=458
Rose, Kenneth H.. Project Quality Management. Boca Raton,
US: J. Ross Publishing,
Incorporated, 2014. ProQuest ebrary. Web. 6 June 2016.
Treumann, R. (2014, February 11). Top 10 Benefits of
Microsoft SharePoint Server.
Retrieved June 6, 2016, from http://www.arielmis.com/top-10-
benefits-of-
microsoft-sharepoint-server/
Running Head: PROJECT PLAN PART 2
PROJECT PLAN PART 2 5
7. Project Budget
“The budget is the amount of money that has been
authorized to be spent on the completion of the project.
Irrespective of the project measurement indications and the fact
that the total project cost may exceed this amount the budget
remains the same” (Marks, 2012). During the initial phases of a
project, the budget for the project is of the utmost importance.
There are essentially two budgets, the capital budget and the
labor, or operating budget. The capital budget is for those
expenditures that will result in a tangible asset for the company.
The labor budget is for those expenditures that have to be made
throughout the course of the project, but not necessarily yield
an asset. For example, in The Cheesecake Factory delivery
service project, the budget for the delivery fleet would be
considered part of the capital budget whereas the hourly wage
for the delivery drivers or marketing materials would be
considered the labor budget. Below are the budgets allocated
for both capital and labor:
Capital Budget
Vendor
Amount
Total
210 Customized Delivery Vehicles (200 locations, 10 spare)
Lugoff Toyota
25,000 per
$5.25 M
Warming & Cooling bags for delivery vehicles (4 per location)
Amazon
$20 per bag
$16,000
8. $5.27 M
Labor Budget
Amount
Total
Marketing (flyers/radio/TV)
$30,000
$30,000
Background/driving checks
$50 per driver
$10,000
Delivery driver Insurance costs
$100/car/month
$20,000
Hourly wages (vary by market)
Average $10/hr, 5 hrs/day*200 locations
$300,000
$360,000
Between the two, this yields a total project budget of $5.625
million. Purchasing in a bulk fleet has lessened the cost of the
delivery fleet, and using existing relationship with current
marketing partners will result in a lower cost there as well.
Project Scope and Schedule Aligned with Budget
The scope of this project includes the planning, execution,
control and closing of the project to implement a delivery
service within branches of The Cheesecake Factory. This
project will not affect any ongoing policies or procedures within
current business operations. The scope of the project includes
establishing guidelines/minimums for delivery orders,
establishing delivery routes, contracting with a vendor for
delivery vehicles, legal policies for insuring drivers and
9. liability control, and budgeting for equipment such as warmers
and coolers within the delivery cars to maintain product quality.
The launch of the delivery service is scheduled to begin
8/15/16.
The above budget shall be submitted to finance for
approval 6/1/16 per the schedule below as the budget is based
on quotes received from potential vendors. Once approved,
purchase orders to take delivery of the fleet by 7/31/16 will be
submitted by 6/30/16. Additionally, once the labor budget is
approved, marketing creation will commence to have launch
materials ready and approved by 7/31/16.
Schedule Baseline and Work Breakdown Structure
Milestone
ask
Team Member
Date
Initial Project Meeting with Project Team
To determine information/resources needed
PM
5/23/2016
Budget Proposal to Finance
Submission of project budget to finance for approval
PM
6/1/2016
Quotes from vendors vehicles
Operations
Quotes from vendors warming/cooling units
Operations
Quotes from legal if additional insurance needed
Legal
10. Quotes for marketing materials
Marketing
Final budget draft
Project Team
Purchase of delivery vehicles from vendor
Order placed to take delivery of vehicle fleet
Operations
6/30/2016
Legal requirements met
From an HR/liability perspective with delivery drivers
employed
Legal
6/30/2016
Marketing campaigns launched
TV/radio ad creation
Marketing
7/31/2016
Flyers/handout creation
Marketing
Delivery materials ordered (bags, boxes, etc)
Marketing
Advertising complete
Marketing
Staff hired/realigned
Hiring
HR
11. 7/31/2016
Pay scale creation
HR
Background/driving record checks
HR
Initial Product Rollout
Begin delivery service
Locations
8/15/2016
Initial Results Review/Adjustments Made
After 3 months of the service, actual ROI, tweaks made where
necessary
Project Team
12/1/2016
Project Complete
Final adjustments made to project, product complete and fully
implemented
Project Team
12/31/2016
Project Risks and Budget of Contingencies
“A risk is anything that could adversely affect your
schedule, costs, quality, or scope. That is, a risk may impact
your PCTS targets. Simply put, either you manage risks or they
will manage you” (Lewis, 2011). For The Cheesecake Factory
delivery service project, the main risk is the delivery vehicle
fleet not being delivered on time for the launch of the delivery
service. Secondary risks include an accident involving a
delivery driver that results in a liability for the company, and
customer satisfaction not as high concerning food quality
resulting in low use of the delivery service. The risk strategy
used will be risk prevention. Risk monitoring for the primary
12. risk of the fleet not being ready for delivery will be to maintain
biweekly contact with the vendor, Lugoff Toyota, to ensure the
product manufacturing is on target. Any possible delays
identified during these communications will be adjusted
accordingly in the project budget, schedule, and scope. All
risks, primary and secondary, will be monitored on the risk
register and updated regularly as the project develops.
Risk
Contingency Plan
Adjustment to Budget
Delivery Fleet not available for launch
Expect delivery by 7/31 for launch 8/15. If delivery not taken
launch pushed back accordingly.
Loss of revenue in determining ROI, market materials will need
to be adjusted for launch date
Accident liability
Rely on driving records for hiring
No impact to project budget, however could be loss to company
if occurs
Decreased customer satisfaction
Customer surveys, what can be improved, offer frequent
delivery customer discount rewards program
No impact to project budget
References
Lewis, J. P. (2011). Project planning, scheduling, and control: A
hands-on guide to
bringing projects in on time and on budget. (5th ed.). New
13. York, NY: McGraw-Hill.
Marks, Tony. 20:20 Project Management : How to Deliver on
Time, on Budget and on
Spec. London, GBR: Kogan Page Ltd., 2012. ProQuest ebrary.
Web. 30 May
2016.
Running Head: PROJECT PLAN PART 1
PROJECT PLAN PART 1 6
Introduction
This project plan will facilitate the implementation of a
delivery service within all locations of The Cheesecake Factory.
The restaurant chain currently does not offer this service, and
adding this option for dining to guests within a 15 mile radius
of existing locations would increase the customer base, and
14. cater to those patrons that may prefer to dine in the comfort of
their home. The service would also be used for business
consumers, offering a catering menu as well.
Project Management Approach
For the project management of this project, I will be using
the Lewis method, which is “a practical, no-nonsense approach
that, when followed, helps managers avoid many of the pitfalls
that cause projects to fail.” (Lewis, 2011, p. 51) The main
components of this project management methodology are
initiation, planning, execution, control, and closeout. Each
component has several layers within that stage of planning.
The project manager, Laurie McKenzie, will oversee all
aspects of the project. The project team will consist of current
The Cheesecake Factory employees from human resources,
marketing, finance, legal, and operations. During the initiation
phase of the project, the scope/goal of the project is defined.
Once the overarching goal is determined, and during what
timeline it should be completed in, the planning stage begins.
This is where the project manager along with the project team
detail out the pieces of the project that need to be accomplished.
Specific tasks are created with timelines and responsible parties
to complete the task. Risks are identified and strategies are put
into place to mitigate the risks. The execution phase is when
the plans are carried out and put into action. Should any
obstacles arise, plans are adjusted and reorganized as necessary
within the scope of the project. The control part of the project
method involves the documentation, risk management, and
overall how metrics are going to be assessed and accountability
held for the various parts of the project. Closeout of the project
will be one the delivery product has been successfully
implemented, there is a quarters worth of results to build upon,
and the project is complete.
Project Scope
The scope of this project includes the planning, execution,
control and closing of the project to implement a delivery
service within branches of The Cheesecake Factory. This
15. project will not affect any ongoing policies or procedures within
current business operations. The scope of the project includes
establishing guidelines/minimums for delivery orders,
establishing delivery routes, contracting with a vendor for
delivery vehicles, legal policies for insuring drivers and
liability control, and budgeting for equipment such as warmers
and coolers within the delivery cars to maintain product quality.
Milestone List
The milestone list contains all of the main activities during
the course of the project. Should there be any change in date,
this would be communicated to the project team during the
weekly meetings and adjusted accordingly.
Milestone
Description
Date
Initial Project Meeting with Project Team
To determine information/resources needed
5/23/2016
Budget Proposal to Finance
Submission of project budget to finance for approval
6/1/2016
Purchase of delivery vehicles from vendor
Order placed to take delivery of vehicle fleet
6/30/2016
Legal requirements met
From an HR/liability perspective with delivery drivers
employed
6/30/2016
Marketing campaigns launched
Advertising complete
7/31/2016
Staff hired/realigned
Drivers hired in heavier markets, or staff realigned where
available
7/31/2016
Initial Product Rollout
16. Begin delivery service
8/15/2016
Initial Results Review/Adjustments Made
After 3 months of the service, actual ROI, tweaks made where
necessary
12/1/2016
Project Complete
Final adjustments made to project, product complete and fully
implemented
12/31/2016
Schedule Baseline and Work Breakdown Structure
Milestone
ask
Team Member
Date
Initial Project Meeting with Project Team
To determine information/resources needed
PM
5/23/2016
Budget Proposal to Finance
Submission of project budget to finance for approval
PM
6/1/2016
Quotes from vendors vehicles
Operations
Quotes from vendors warming/cooling units
Operations
Quotes from legal if additional insurance needed
Legal
17. Quotes for marketing materials
Marketing
Final budget draft
Project Team
Purchase of delivery vehicles from vendor
Order placed to take delivery of vehicle fleet
Operations
6/30/2016
Legal requirements met
From an HR/liability perspective with delivery drivers
employed
Legal
6/30/2016
Marketing campaigns launched
TV/radio ad creation
Marketing
7/31/2016
Flyers/handout creation
Marketing
Delivery materials ordered (bags, boxes, etc)
Marketing
Advertising complete
Marketing
Staff hired/realigned
Hiring
HR
18. 7/31/2016
Pay scale creation
HR
Background/driving record checks
HR
Initial Product Rollout
Begin delivery service
Locations
8/15/2016
Initial Results Review/Adjustments Made
After 3 months of the service, actual ROI, tweaks made where
necessary
Project Team
12/1/2016
Project Complete
Final adjustments made to project, product complete and fully
implemented
Project Team
12/31/2016
19. References
Lewis, J. P. (2011). Project planning, scheduling, and control: A
hands-on guide to
bringing projects in on time and on budget. (5th ed.). New
York, NY: McGraw-Hill.