1.0 INITIATING PROCESS GROUP
The purpose of the Initiating Process Group is to authorize a project, provide a high-level
definition of the project, and identify stakeholders. There are two processes in the Initiating
Process Group:
• Develop project charter
• Identify stakeholders
The intent of the Initiating Process Group is to at least:
• Authorize a project
• Identify project objectives
• Define the initial scope of the project
• Obtain organizational commitment
• Assign a project manager
• Identify project stakeholders
As the first processes in the project, the initiating processes are vital to starting a project
effectively.
These processes can be revisited throughout the project for validation and elaboration as needed.
The forms used to document initiating information include:
• Project charter
• Assumption log
• Stakeholder register
• Stakeholder analysis
Initiating
Forms
These forms are consistent with the information in the PMBOK®
Guide – Sixth Edition. Tailor
them to meet the needs of your project by editing, combining, or revising them.
2 Initiating Forms
1.1 PROJECT CHARTER
The project charter is a document that formally authorizes a project or phase. The project charter
defines the reason for the project and assigns a project manager and his or her authority level
for the project. The contents of the charter describe the project in high-level terms, such as:
• Project purpose
• High-level project description
• Project boundaries
• Key deliverables
• High-level requirements
• Overall project risk
• Project objectives and related success criteria
• Summary milestone schedule
• Preapproved financial resources
• Key stakeholder list
• Project approval requirements
• Project exit criteria
• Assigned project manager, responsibility, and authority level
• Name and authority of the sponsor or other person(s) authorizing the project
charter The project charter can receive information from:
• Agreements (contracts)
• Statements of work
• Business case
• Benefits management
plan It provides
information to:
• Stakeholder register
• Project management plan
• Scope management plan
• Requirements management plan
• Requirements documentation
• Requirements traceability matrix
• Project scope statement
• Schedule management plan
• Cost management plan
• Quality management plan
• Resource management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Stakeholder engagement plan
The project charter is an output from process 4.1 Develop Project Charter in the PMBOK
®
Guide – Sixth Edition. This document is developed once and is not usually changed unless there is
a significant change in the environment, scope, schedule, resources, budget, or stakeholders.
Initiating Forms 3
Tailoring Tips
Consider the following tips to help you tailor the project charter to meet your needs:
• Combine the project charter with the project scope statement, especially if your project is small
• If you are doing the project under contract you can use the statement of work as the project
charter in some cases
Alignment
The project charter should be aligned and consistent with the following documents:
• Business case
• Project scope statement
• Milestone schedule
• Budget
• Stakeholder register
• Risk register
Description
You can use the element descriptions in Table 1.1 to assist you in developing a project charter.
TABLE 1.1 Elements of a Project Charter
Document Element
Description
Project purpose The reason the project is being undertaken. May refer to a
business case, the organization’s strategic plan, external
factors, a contract agreement, or any other reason for
performing the project.
High-level project description A summary-level description of the project.
Project boundaries Limits to the project scope. May include scope exclusions, or
other limitations.
Key deliverables The high-level project and product deliverables. These will be
further elaborated in the project scope statement.
High-level requirements The high-level conditions or capabilities that must be met to satisfy
the
purpose of the project. Describe the product features and
functions that must be present to meet stakeholders’ needs
and expectations. These will be further elaborated in the
requirements documentation.
Overall project risk An assessment of the overall riskiness of the project. Overall risk
can include the underlying political, social, economic, and
technological volatility, uncertainty, complexity, and ambiguity.
It pertains to the stakeholder exposure to variations in the
project outcome.
Project objectives and related
success criteria
Project objectives are usually established for at least scope,
schedule, and cost. The success criteria identify the metrics or
measurements that will be used to measure success.
There may be additional objectives as well. Some organizations
include quality, safety, and stakeholder satisfaction objectives.
(continued)
4 Initiating Forms
Table 1.1 Elements of a Project Charter (continued)
Document Element Description
Summary milestone schedule Significant events in the project. Examples include the completion of
key deliverables, the beginning or completion of a project phase, or
product acceptance.
Preapproved financial resources The amount of funding available for the project. May include sources
of funding and annual funding limits.
Key stakeholder list An initial, high-level list of people or groups that have influenced
or can influence project success, as well as those who are
influenced by its success. This can be further elaborated in the
stakeholder register.
Project exit criteria The performance, metrics, conditions, or other measurements
that must be met to conclude the project.
Assigned project manager, responsibility,
and authority level
Name and authority of the sponsor or
other person(s) authorizing the project
charter
The authority of the project manager with regard to
staffing, bud- get management and variance, technical
decisions, and conflict resolution.
Examples of staffing authority include the power to hire, fire,
discipline, accept, or not accept project staff.
Budget management refers to the authority of the project
manager to commit, manage, and control project funds.
Variance refers to the variance level that requires escalation.
Technical decisions describe the authority of the project manager
to make technical decisions about deliverables or the project
approach.
Conflict resolution defines the degree to which the project
manager can resolve conflict within the team, within the
organization, and with external stakeholders.
The name, position, and authority of the person who oversees
the project manager for the purposes of the project. Common
types of authority include the ability to approve changes,
determine acceptable variance limits, resolve inter-project conflicts,
and champion the proj- ect at a senior management level.
PROJECT CHARTER
Project Title: HD X440 Bike Assembly Process Development at Hero Neemrana Plant
Project Sponsor: Manufacturing Head- Neemaran
Date Prepared: 30/09/22
Project Manager: Bhupinder Saini Project Customer: Despatch Team
Project Purpose:
 To Develop a Process for Vehicle assembly & Engine assembly for HD X440 for 50VPD
by Sept-23
 To Plan & Order the Infrastructure requirement for all 06 Manufactuirng shops by Jan-
23
 To Installed & Commissioned all the machines & equipment in all 06 shops by March-
23
 To successfully execute the PP1 & PP2 event in vehicle assembly on Jan-23 & March-24
High-Level Project Description:
 Process Development of HD X440 bike at Hero Motocorp Neemrna plant by aug-23.
Project Boundaries:
 No X440 Vehicle will be assembled on line-2.
 Vehicle Start of Production will be start after CIT approval area.
 Vehicle Dispatch will be started after dispatch evaluation apparoval.
Key Deliverables:
 Fuel Tank Welding Process machines tobe delivered within 3 months after order releaseing.
 Delivery of Tightening Tools for Engine & vehicle assembly within 2 months after the order
release.
 Delivery of Special Tooling & Fixtures for Subassembly process withi 15 days of order
released.
 Paint Shop Shade establishment within 3 days after approval of paint testing results
High-Level Requirements:
 X440 PP1 & PP2 event to be completed by Jan-23 & March-23 respectively.
 X440 vehicles dispatched must be start on or before 18th
October 2023.
 Overall Production Capcity of assembly line must be 50 vehicle per day.
 Manpower to be recruited & handover by Feb-23.
 Vehicle Quality Straight pass must be 100% from Day 1 of Start of Production (SOP)
Overall Project Risk
 Delay in Availbility of raw material from suppliers for starting of assembly.
 Delay in the Delivery of Tools & Fixture for assembly process.
 Engine performance parameters not meet the required standard during testing at R& D .
 Delay in the receiving of testing report form PDI Lab
Page 1 of 4
PROJECT CHARTER
Scope:
To assembled the HD X440 motorcycle with 04
nos.of variant on vehicle assembly line-1 at
neemrana plant by Oct2023.
Assembly of HD X440 vehicle with 100%
Qulality rate passing all CIT , IQC & ARAI test
by oct 23 with minimum development
rejection cost.
Time:
To complete the Project within schedule time of 12
months
Completion of HD X440 Vehicle assembly by
Oct2023 passed in all quality parameter
Cost:
To complete the project within Budget 120 Cr To attain a EBITA margin of 20%O
Other:
Summary Milestones Due Date
Technical Specification Finalization of All
Equipment
Within 15 days of final releasing of the drawings
Purchase Order Releasing Of all machines, Tools ,
Fixtures & machine Consumables
Witin 7 days after technical specification signedoff
Delivery of all Facilities Within 3 months of purchase order
Child Parts Availbility for Machine Trial 20 days before the machine delivery
Civil & Utilities Infrastructure Completion To be ready before machine delivery
Machine Layout & material Flow Finalization On or before machine Delivery
Installation & Commissioning of machines With 7 days after machine Delivery
Project Objectives Success Criteria
Page 2 of 4
PROJECT CHARTER
Preapproved Financial Resources:
100% Approved CAPEX from Central Team
Stakeholder(s
)
Role
Project Manager (New Model Coordinator) All Project Related Activites
Project Sponser (Manufactuing Head) Review progress of all activities
Release of funds for projects
Approval of all Procurement
Project Team All Project related activities
Machine Suppliers Machine Delivery & machines drawings as per
timeline .
Fixture & Tightening Tools Suppliers Delivery of Fixture & tightening tools as per timeline
ARAI To provide the necceasry approval for go ahead
Civil Contractor To get the civil drawings approval from Local
authorities
PDT Testing Divison To Provide the approval for Driveability test
Project Exit Criteria:
1. Handing Over of New Facility to respective shops for Vehicle assembly of X440
2. Assembly of 1st
50 nos. QC Ok Vehicles to dispatch team
Project Manager Authority Level:
Staffing Decisions:
Budget Management and Variance:
1.Assembly Process design Expert
2. Mitsuibuishi PLC Prorammer
3. Tools & Fixture Designer
2.
2.INR 150 cr ± 5%
Page 3 of 4
Technical Decisions:
PROJECT CHARTER
Conflict Resolution:
Sponsor Authority:
Approvals:
Project Manager Signature Sponsor or Originator Signature
Project Manager Name Sponsor or Originator Name
Date Date
1. Approval of Machine Layout
2. Machine Technical specification Finalization
3. Utility Layout Finaliation
4. Approval of Process flow
5. Supplier Recommendations
 Resolution of Conflict between project team members R&D ,Central Project team , Plant
team.
 Resolution of conflict between the civil contractor & other vendors for pricing
finalization.
 Resolution of conflict with machine supplier on technical issues.
 Deployment of Project team
 Releasing of funds for project
 Review of progress of project
 Approval of suppliers recommended by PM
Page 4 of 4
Initiating Forms 9
1.2 ASSUMPTION LOG
Assumptions are factors in the planning process that are considered to be true, real, or certain,
without proof or demonstration. Constraints are also documented in this log. Constraints are
limiting factors that affect the execution of the project. Typical constraints include a
predetermined budget or fixed milestones for deliverables. Information in the assumption log
includes:
• Identifier
• Category
• Assumption or constraint
• Responsible party
• Due date
• Actions
• Status
• Comments
Assumptions can come from any document in the project. They can also be determined by the
proj- ect team. Constraints may be documented in the project charter and are determined by the
customer, sponsor, or regulatory agencies.
The assumption log provides information to:
• Requirements documentation
• Project scope statement
• Network diagram
• Duration estimates
• Project schedule
• Quality management plan
• Resource estimates
• Risk register
• Stakeholder engagement plan
The assumption log is an output from the process 4.1 Develop Project Charter in the PMBOK®
Guide – Sixth Edition. This log is a dynamic document that is updated throughout the project.
Assumptions are progressively elaborated throughout the project and are eventually validated
and no longer assumptions.
Tailoring Tips
Consider the following tips to help you tailor the assumption log to meet your needs:
• Combine the assumption log with the issue register and the decision log, to create an
AID Log (A = assumption, I = issue, D = decision). You can create them in a spreadsheet with
each sheet dedicated to either assumptions, issues, or decisions.
• If you have a very large project you may want to keep the constraints in a separate log from
the assumptions.
10 Initiating Forms
Alignment
The assumption log should be aligned and consistent with the following documents:
• Project charter
• Issue log
• Risk register
Description
You can use the element descriptions in Table 1.2 to assist you in developing the assumption log.
TABLE 1.2 Elements of an Assumption Log
Document Element Description
ID Identifier
Category The category of the assumption or
constraint Assumption/constraint A description of the
assumption or constraint
Responsible party The person who is tasked with following up on the assumption to validate if
it is true or not
Due date The date by which the assumption needs to be validated
Actions Actions that need to be taken to validate assumptions
Status The status of the assumptions, such as active, transferred, or
closed Comments Any additional information regarding the assumption or
constraint
ASSUMPTION LOG
Project Title:Process Design of X440 Date Prepared: 30.09.2022
ID Category Assumption/Constraint Responsible Party Due Date Actions Status Comments
AX1.1 Finance Assumption is that Advance
Payment for Robot Suplier will
be released by finance team
Finance 30.12.2023 Timely
Releasing of
Payment as
per due date
Pending Urgent
AX1.2 Supply Chain Assumption is that initial parts
for machine trial will be
available by supply chain team
Supply Chain Team 20.01.2024 Parts
Availibility
as per
timeline
Pending Urgent
AX1.3 Top Managment Assumption is that all Puchase
orders value more than 20 lac
will be approved by Head of
Plant Operations
Top Management Within a week
after submission
of all Documents
Approval of
Purchase
orders
Pending Critical
AX1.4 R& D Assumption that R&D team will
share the testing report within a
week after receiving of initial lot
of vehciles.
R & D Within week
after receiving of
initial lot of
vehicle
Sharing of
testing report
Pending Semi-urgent
AX1.5 R&D Assumption is that all design
related open points of 1st
trial
event (PP1) vehicle will be
closed by R&D before next trial
event.(PP2)
R &D Before PP2 EventAll open
points of
PP1 to be
closed .
Pending Semi-urgent
Page 1 of 1
12 Initiating Forms
1.3 STAKEHOLDER REGISTER
The stakeholder register is used to identify those people and organizations impacted by the
project and to document relevant information about each stakeholder. Relevant information can
include:
• Name
• Position in the organization
• Role in the project
• Contact information
• List of stakeholder’s major requirements
• List of stakeholder’s expectations
• Classification of each stakeholder
Initially you will not have enough information to complete the stakeholder register. As the
project gets underway you will gain additional information and understanding about each
stakeholder’s requirements, expectations, and classification and the stakeholder register will
become more robust.
The stakeholder register receives information from:
• Project charter
• Procurement
documents It is related
to:
• Stakeholder analysis
matrix It provides
information to:
• Requirements documentation
• Quality management plan
• Communications management plan
• Risk management plan
• Risk register
• Stakeholder engagement plan
The stakeholder register is an output from the process 13.1 Identify Stakeholders in the
PMBOK®
Guide – Sixth Edition. The stakeholder register is a dynamic project document. The
stakeholders, their level of influence, requirements, and classification are likely to change
throughout the project.
Tailoring Tips
Consider the following tips to help you tailor the stakeholder register to meet your needs:
• Combine the position in the organization with the role on the project, especially if it is a smaller
project and everyone knows everyone else’s position.
• Combine the stakeholder analysis matrix information with the stakeholder register.
• Eliminate position, role, and contact information for small internal projects.
Initiating Forms 13
Alignment
The stakeholder register should be aligned and consistent with the following documents:
• Project charter
• Stakeholder analysis matrix
• Stakeholder engagement plan
Description
You can use the element descriptions in Table 1.3 to assist you in developing the stakeholder register.
TABLE 1.3 Elements of a Stakeholder Register
Document Element Description
Name Stakeholder’s name. If you don’t have a name you can substitute a position or
organization until you have more information
Position/Role The position and/or role the stakeholder holds in the organization. Examples of
positions include programmer, human resources analyst, or quality assurance
specialist. Roles indi- cate the function the stakeholder performs on the project team,
such as testing lead, Scrum Master, or scheduler
Contact information How to communicate with the stakeholder, such as their phone number, email
address, or physical address
Requirements High-level needs for the project and/or
product Expectations Main expectations of the project and/or
product
Classification Some projects may categorize stakeholders as friend, foe, or neutral; others may
classify them as high, medium, or low impact
STAKEHOLDER REGISTER
Project Title:HD X440 Vehicle Development Date Prepared: 30.09.2022
Name Position/Role Contact
Informati
on
Requirements (Resp) Expectations Classific
ation
PG Manufacturing
Head (Project Sponsor)
XXXXXX
XXXX
To review the project progress
on weekly basis
The project must be completed within decided
timeline within budget. There will be no
defects outflow from the process during
vehicle assembly.
High
Impact
AS Project Manager XXXXXX
XXXX
To overall review of the project
as per schedule , all activities
execution safely & alignment
of different stakeholders
Project must be completed within decided
schedule as per the scope , within budget .
There will be no impact on the quality of work.
There will be no accidents during
commissioning of machine during the project.
High
Impact
PK Research &
Development SPOC
XXXXXX
XXXX
Timely review of ECN
received
Timley review of Designed
related Points during 1st
vehicle
lot Production.
The updated drawings to be released as per the
received ECN.
All the design related points to be closed on or
before the SOP.
Timely Releasing of test reports
High
Impact
DC Civil Contractor XXXXXX
XXXX
Drawings approval fromLocal
Authority
Page 1 of 1
Initiating Forms 15
1.4 STAKEHOLDER ANALYSIS
Stakeholder analysis is used to classify stakeholders. It can be used to help fill in the stakeholder
register. Analyzing stakeholders can also help in planning stakeholder engagement for groups of
stakeholders.
The following example is used to assess the relative power (high or low), the relative interest
(high or low), and the attitude (friend or foe). There are many other ways to categorize
stakeholders. Some exam- ples include:
• Influence/impact
• Power/urgency/legitimacy
Stakeholder analysis receives information from:
• Project charter
• Procurement documents
Stakeholder analysis is a tool used in 13.1 Identify Stakeholders in the PMBOK®
Guide – Sixth
Edition.
Tailoring Tips
Consider the following tips to help you tailor the stakeholder analysis to meet your needs:
• For projects with relatively homogenous stakeholders you can use a 2 × 2 grid that only
considers two variables, such as interest and influence.
• For larger projects consider using a 3 × 3 stakeholder cube. Tailor the categories to reflect the
impor- tance of various stakeholder variables.
Alignment
The stakeholder analysis should be aligned and consistent with the following documents:
• Stakeholder register
• Stakeholder engagement plan
Description
You can use the element descriptions in Table 1.4 to assist you in developing a stakeholder analysis.
TABLE 1.4 Stakeholder Analysis
Document Element Description
Name or role The stakeholder name, organization, or group
Interest The level of concern the stakeholder has for the project
Influence The degree to which the stakeholder can drive or influence outcomes for the
project Attitude The degree to which the stakeholder supports the project
STAKEHOLDER ANALYSIS
Project Title: Date Prepared:
Name or Role Interest Influenc
e
Attitude
Page 1 of 1

More Related Content

PPT
PMP - Project Initiation Template for Professionals
PPTX
Creating the project charter
PPTX
Engineering Project Management Initiation Phase.pptx
PPTX
Project Planning and Development Intro.pptx
PPTX
The Project Charter Ensuring Quality
PPTX
The Project Charter in a Nutshell
PDF
PMP PMBOK5 Ch4 integration management
PPTX
Effective Project Integration Management
PMP - Project Initiation Template for Professionals
Creating the project charter
Engineering Project Management Initiation Phase.pptx
Project Planning and Development Intro.pptx
The Project Charter Ensuring Quality
The Project Charter in a Nutshell
PMP PMBOK5 Ch4 integration management
Effective Project Integration Management

Similar to Sample Project Charter in Project Management (20)

PDF
Develop project charter
PPTX
Project management processes Groups
PPTX
Project Management Training and aii.pptx
PPTX
Chapter 3 Project Management process Groups.pptx
PPTX
Introduction to Information Technology Project Management
PDF
Effective Handling of Project Artifacts for Successful Project Management.pdf
PPTX
Sample_Executive-Project-Kickoff.pptx
PPTX
Basic Project documents
DOCX
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PPTX
Construction company business plan
PPT
6396901
DOCX
Customerlogo hereProject Name Project CharterCompanylog
PDF
Introduction to Project Management
PDF
Project scope selection and management file.
PPT
Project management ALL ABOUT PROJECTS AND HIS
PDF
Project Planning and Estimation
PPTX
Project integration management
PPTX
Introduction to PM & Roles and responsibilities of project manager.pptx
PPTX
PMI Changes to PMP Exam Content 2015
PPSX
Planning and Resourcing a Project
Develop project charter
Project management processes Groups
Project Management Training and aii.pptx
Chapter 3 Project Management process Groups.pptx
Introduction to Information Technology Project Management
Effective Handling of Project Artifacts for Successful Project Management.pdf
Sample_Executive-Project-Kickoff.pptx
Basic Project documents
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
Construction company business plan
6396901
Customerlogo hereProject Name Project CharterCompanylog
Introduction to Project Management
Project scope selection and management file.
Project management ALL ABOUT PROJECTS AND HIS
Project Planning and Estimation
Project integration management
Introduction to PM & Roles and responsibilities of project manager.pptx
PMI Changes to PMP Exam Content 2015
Planning and Resourcing a Project
Ad

Recently uploaded (20)

PPTX
additive manufacturing of ss316l using mig welding
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
Well-logging-methods_new................
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
Project quality management in manufacturing
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPT
Total quality management ppt for engineering students
additive manufacturing of ss316l using mig welding
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Well-logging-methods_new................
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
UNIT 4 Total Quality Management .pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Categorization of Factors Affecting Classification Algorithms Selection
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Fundamentals of Mechanical Engineering.pptx
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Safety Seminar civil to be ensured for safe working.
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Automation-in-Manufacturing-Chapter-Introduction.pdf
Project quality management in manufacturing
Embodied AI: Ushering in the Next Era of Intelligent Systems
Total quality management ppt for engineering students
Ad

Sample Project Charter in Project Management

  • 1. 1 1.0 INITIATING PROCESS GROUP The purpose of the Initiating Process Group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are two processes in the Initiating Process Group: • Develop project charter • Identify stakeholders The intent of the Initiating Process Group is to at least: • Authorize a project • Identify project objectives • Define the initial scope of the project • Obtain organizational commitment • Assign a project manager • Identify project stakeholders As the first processes in the project, the initiating processes are vital to starting a project effectively. These processes can be revisited throughout the project for validation and elaboration as needed. The forms used to document initiating information include: • Project charter • Assumption log • Stakeholder register • Stakeholder analysis Initiating Forms
  • 2. These forms are consistent with the information in the PMBOK® Guide – Sixth Edition. Tailor them to meet the needs of your project by editing, combining, or revising them.
  • 3. 2 Initiating Forms 1.1 PROJECT CHARTER The project charter is a document that formally authorizes a project or phase. The project charter defines the reason for the project and assigns a project manager and his or her authority level for the project. The contents of the charter describe the project in high-level terms, such as: • Project purpose • High-level project description • Project boundaries • Key deliverables • High-level requirements • Overall project risk • Project objectives and related success criteria • Summary milestone schedule • Preapproved financial resources • Key stakeholder list • Project approval requirements • Project exit criteria • Assigned project manager, responsibility, and authority level • Name and authority of the sponsor or other person(s) authorizing the project charter The project charter can receive information from: • Agreements (contracts) • Statements of work • Business case • Benefits management plan It provides information to: • Stakeholder register • Project management plan • Scope management plan • Requirements management plan • Requirements documentation • Requirements traceability matrix • Project scope statement • Schedule management plan • Cost management plan • Quality management plan • Resource management plan • Communications management plan • Risk management plan • Procurement management plan • Stakeholder engagement plan The project charter is an output from process 4.1 Develop Project Charter in the PMBOK ® Guide – Sixth Edition. This document is developed once and is not usually changed unless there is
  • 4. a significant change in the environment, scope, schedule, resources, budget, or stakeholders.
  • 5. Initiating Forms 3 Tailoring Tips Consider the following tips to help you tailor the project charter to meet your needs: • Combine the project charter with the project scope statement, especially if your project is small • If you are doing the project under contract you can use the statement of work as the project charter in some cases Alignment The project charter should be aligned and consistent with the following documents: • Business case • Project scope statement • Milestone schedule • Budget • Stakeholder register • Risk register Description You can use the element descriptions in Table 1.1 to assist you in developing a project charter. TABLE 1.1 Elements of a Project Charter Document Element Description Project purpose The reason the project is being undertaken. May refer to a business case, the organization’s strategic plan, external factors, a contract agreement, or any other reason for performing the project. High-level project description A summary-level description of the project. Project boundaries Limits to the project scope. May include scope exclusions, or other limitations. Key deliverables The high-level project and product deliverables. These will be further elaborated in the project scope statement. High-level requirements The high-level conditions or capabilities that must be met to satisfy the purpose of the project. Describe the product features and functions that must be present to meet stakeholders’ needs and expectations. These will be further elaborated in the requirements documentation. Overall project risk An assessment of the overall riskiness of the project. Overall risk can include the underlying political, social, economic, and technological volatility, uncertainty, complexity, and ambiguity. It pertains to the stakeholder exposure to variations in the project outcome.
  • 6. Project objectives and related success criteria Project objectives are usually established for at least scope, schedule, and cost. The success criteria identify the metrics or measurements that will be used to measure success. There may be additional objectives as well. Some organizations include quality, safety, and stakeholder satisfaction objectives. (continued)
  • 7. 4 Initiating Forms Table 1.1 Elements of a Project Charter (continued) Document Element Description Summary milestone schedule Significant events in the project. Examples include the completion of key deliverables, the beginning or completion of a project phase, or product acceptance. Preapproved financial resources The amount of funding available for the project. May include sources of funding and annual funding limits. Key stakeholder list An initial, high-level list of people or groups that have influenced or can influence project success, as well as those who are influenced by its success. This can be further elaborated in the stakeholder register. Project exit criteria The performance, metrics, conditions, or other measurements that must be met to conclude the project. Assigned project manager, responsibility, and authority level Name and authority of the sponsor or other person(s) authorizing the project charter The authority of the project manager with regard to staffing, bud- get management and variance, technical decisions, and conflict resolution. Examples of staffing authority include the power to hire, fire, discipline, accept, or not accept project staff. Budget management refers to the authority of the project manager to commit, manage, and control project funds. Variance refers to the variance level that requires escalation. Technical decisions describe the authority of the project manager to make technical decisions about deliverables or the project approach. Conflict resolution defines the degree to which the project manager can resolve conflict within the team, within the organization, and with external stakeholders. The name, position, and authority of the person who oversees the project manager for the purposes of the project. Common types of authority include the ability to approve changes, determine acceptable variance limits, resolve inter-project conflicts, and champion the proj- ect at a senior management level.
  • 8. PROJECT CHARTER Project Title: HD X440 Bike Assembly Process Development at Hero Neemrana Plant Project Sponsor: Manufacturing Head- Neemaran Date Prepared: 30/09/22 Project Manager: Bhupinder Saini Project Customer: Despatch Team Project Purpose:  To Develop a Process for Vehicle assembly & Engine assembly for HD X440 for 50VPD by Sept-23  To Plan & Order the Infrastructure requirement for all 06 Manufactuirng shops by Jan- 23  To Installed & Commissioned all the machines & equipment in all 06 shops by March- 23  To successfully execute the PP1 & PP2 event in vehicle assembly on Jan-23 & March-24 High-Level Project Description:  Process Development of HD X440 bike at Hero Motocorp Neemrna plant by aug-23. Project Boundaries:  No X440 Vehicle will be assembled on line-2.  Vehicle Start of Production will be start after CIT approval area.  Vehicle Dispatch will be started after dispatch evaluation apparoval. Key Deliverables:  Fuel Tank Welding Process machines tobe delivered within 3 months after order releaseing.  Delivery of Tightening Tools for Engine & vehicle assembly within 2 months after the order release.  Delivery of Special Tooling & Fixtures for Subassembly process withi 15 days of order released.  Paint Shop Shade establishment within 3 days after approval of paint testing results High-Level Requirements:  X440 PP1 & PP2 event to be completed by Jan-23 & March-23 respectively.  X440 vehicles dispatched must be start on or before 18th October 2023.  Overall Production Capcity of assembly line must be 50 vehicle per day.  Manpower to be recruited & handover by Feb-23.  Vehicle Quality Straight pass must be 100% from Day 1 of Start of Production (SOP)
  • 9. Overall Project Risk  Delay in Availbility of raw material from suppliers for starting of assembly.  Delay in the Delivery of Tools & Fixture for assembly process.  Engine performance parameters not meet the required standard during testing at R& D .  Delay in the receiving of testing report form PDI Lab Page 1 of 4
  • 10. PROJECT CHARTER Scope: To assembled the HD X440 motorcycle with 04 nos.of variant on vehicle assembly line-1 at neemrana plant by Oct2023. Assembly of HD X440 vehicle with 100% Qulality rate passing all CIT , IQC & ARAI test by oct 23 with minimum development rejection cost. Time: To complete the Project within schedule time of 12 months Completion of HD X440 Vehicle assembly by Oct2023 passed in all quality parameter Cost: To complete the project within Budget 120 Cr To attain a EBITA margin of 20%O Other: Summary Milestones Due Date Technical Specification Finalization of All Equipment Within 15 days of final releasing of the drawings Purchase Order Releasing Of all machines, Tools , Fixtures & machine Consumables Witin 7 days after technical specification signedoff Delivery of all Facilities Within 3 months of purchase order Child Parts Availbility for Machine Trial 20 days before the machine delivery Civil & Utilities Infrastructure Completion To be ready before machine delivery Machine Layout & material Flow Finalization On or before machine Delivery Installation & Commissioning of machines With 7 days after machine Delivery Project Objectives Success Criteria
  • 12. PROJECT CHARTER Preapproved Financial Resources: 100% Approved CAPEX from Central Team Stakeholder(s ) Role Project Manager (New Model Coordinator) All Project Related Activites Project Sponser (Manufactuing Head) Review progress of all activities Release of funds for projects Approval of all Procurement Project Team All Project related activities Machine Suppliers Machine Delivery & machines drawings as per timeline . Fixture & Tightening Tools Suppliers Delivery of Fixture & tightening tools as per timeline ARAI To provide the necceasry approval for go ahead Civil Contractor To get the civil drawings approval from Local authorities PDT Testing Divison To Provide the approval for Driveability test Project Exit Criteria: 1. Handing Over of New Facility to respective shops for Vehicle assembly of X440 2. Assembly of 1st 50 nos. QC Ok Vehicles to dispatch team Project Manager Authority Level: Staffing Decisions: Budget Management and Variance: 1.Assembly Process design Expert 2. Mitsuibuishi PLC Prorammer 3. Tools & Fixture Designer 2. 2.INR 150 cr ± 5%
  • 14. Technical Decisions: PROJECT CHARTER Conflict Resolution: Sponsor Authority: Approvals: Project Manager Signature Sponsor or Originator Signature Project Manager Name Sponsor or Originator Name Date Date 1. Approval of Machine Layout 2. Machine Technical specification Finalization 3. Utility Layout Finaliation 4. Approval of Process flow 5. Supplier Recommendations  Resolution of Conflict between project team members R&D ,Central Project team , Plant team.  Resolution of conflict between the civil contractor & other vendors for pricing finalization.  Resolution of conflict with machine supplier on technical issues.  Deployment of Project team  Releasing of funds for project  Review of progress of project  Approval of suppliers recommended by PM
  • 16. Initiating Forms 9 1.2 ASSUMPTION LOG Assumptions are factors in the planning process that are considered to be true, real, or certain, without proof or demonstration. Constraints are also documented in this log. Constraints are limiting factors that affect the execution of the project. Typical constraints include a predetermined budget or fixed milestones for deliverables. Information in the assumption log includes: • Identifier • Category • Assumption or constraint • Responsible party • Due date • Actions • Status • Comments Assumptions can come from any document in the project. They can also be determined by the proj- ect team. Constraints may be documented in the project charter and are determined by the customer, sponsor, or regulatory agencies. The assumption log provides information to: • Requirements documentation • Project scope statement • Network diagram • Duration estimates • Project schedule • Quality management plan • Resource estimates • Risk register • Stakeholder engagement plan The assumption log is an output from the process 4.1 Develop Project Charter in the PMBOK® Guide – Sixth Edition. This log is a dynamic document that is updated throughout the project. Assumptions are progressively elaborated throughout the project and are eventually validated and no longer assumptions. Tailoring Tips Consider the following tips to help you tailor the assumption log to meet your needs: • Combine the assumption log with the issue register and the decision log, to create an AID Log (A = assumption, I = issue, D = decision). You can create them in a spreadsheet with each sheet dedicated to either assumptions, issues, or decisions. • If you have a very large project you may want to keep the constraints in a separate log from the assumptions.
  • 17. 10 Initiating Forms Alignment The assumption log should be aligned and consistent with the following documents: • Project charter • Issue log • Risk register Description You can use the element descriptions in Table 1.2 to assist you in developing the assumption log. TABLE 1.2 Elements of an Assumption Log Document Element Description ID Identifier Category The category of the assumption or constraint Assumption/constraint A description of the assumption or constraint Responsible party The person who is tasked with following up on the assumption to validate if it is true or not Due date The date by which the assumption needs to be validated Actions Actions that need to be taken to validate assumptions Status The status of the assumptions, such as active, transferred, or closed Comments Any additional information regarding the assumption or constraint
  • 18. ASSUMPTION LOG Project Title:Process Design of X440 Date Prepared: 30.09.2022 ID Category Assumption/Constraint Responsible Party Due Date Actions Status Comments AX1.1 Finance Assumption is that Advance Payment for Robot Suplier will be released by finance team Finance 30.12.2023 Timely Releasing of Payment as per due date Pending Urgent AX1.2 Supply Chain Assumption is that initial parts for machine trial will be available by supply chain team Supply Chain Team 20.01.2024 Parts Availibility as per timeline Pending Urgent AX1.3 Top Managment Assumption is that all Puchase orders value more than 20 lac will be approved by Head of Plant Operations Top Management Within a week after submission of all Documents Approval of Purchase orders Pending Critical AX1.4 R& D Assumption that R&D team will share the testing report within a week after receiving of initial lot of vehciles. R & D Within week after receiving of initial lot of vehicle Sharing of testing report Pending Semi-urgent AX1.5 R&D Assumption is that all design related open points of 1st trial event (PP1) vehicle will be closed by R&D before next trial event.(PP2) R &D Before PP2 EventAll open points of PP1 to be closed . Pending Semi-urgent
  • 20. 12 Initiating Forms 1.3 STAKEHOLDER REGISTER The stakeholder register is used to identify those people and organizations impacted by the project and to document relevant information about each stakeholder. Relevant information can include: • Name • Position in the organization • Role in the project • Contact information • List of stakeholder’s major requirements • List of stakeholder’s expectations • Classification of each stakeholder Initially you will not have enough information to complete the stakeholder register. As the project gets underway you will gain additional information and understanding about each stakeholder’s requirements, expectations, and classification and the stakeholder register will become more robust. The stakeholder register receives information from: • Project charter • Procurement documents It is related to: • Stakeholder analysis matrix It provides information to: • Requirements documentation • Quality management plan • Communications management plan • Risk management plan • Risk register • Stakeholder engagement plan The stakeholder register is an output from the process 13.1 Identify Stakeholders in the PMBOK® Guide – Sixth Edition. The stakeholder register is a dynamic project document. The stakeholders, their level of influence, requirements, and classification are likely to change throughout the project. Tailoring Tips
  • 21. Consider the following tips to help you tailor the stakeholder register to meet your needs: • Combine the position in the organization with the role on the project, especially if it is a smaller project and everyone knows everyone else’s position. • Combine the stakeholder analysis matrix information with the stakeholder register. • Eliminate position, role, and contact information for small internal projects.
  • 22. Initiating Forms 13 Alignment The stakeholder register should be aligned and consistent with the following documents: • Project charter • Stakeholder analysis matrix • Stakeholder engagement plan Description You can use the element descriptions in Table 1.3 to assist you in developing the stakeholder register. TABLE 1.3 Elements of a Stakeholder Register Document Element Description Name Stakeholder’s name. If you don’t have a name you can substitute a position or organization until you have more information Position/Role The position and/or role the stakeholder holds in the organization. Examples of positions include programmer, human resources analyst, or quality assurance specialist. Roles indi- cate the function the stakeholder performs on the project team, such as testing lead, Scrum Master, or scheduler Contact information How to communicate with the stakeholder, such as their phone number, email address, or physical address Requirements High-level needs for the project and/or product Expectations Main expectations of the project and/or product Classification Some projects may categorize stakeholders as friend, foe, or neutral; others may classify them as high, medium, or low impact
  • 23. STAKEHOLDER REGISTER Project Title:HD X440 Vehicle Development Date Prepared: 30.09.2022 Name Position/Role Contact Informati on Requirements (Resp) Expectations Classific ation PG Manufacturing Head (Project Sponsor) XXXXXX XXXX To review the project progress on weekly basis The project must be completed within decided timeline within budget. There will be no defects outflow from the process during vehicle assembly. High Impact AS Project Manager XXXXXX XXXX To overall review of the project as per schedule , all activities execution safely & alignment of different stakeholders Project must be completed within decided schedule as per the scope , within budget . There will be no impact on the quality of work. There will be no accidents during commissioning of machine during the project. High Impact PK Research & Development SPOC XXXXXX XXXX Timely review of ECN received Timley review of Designed related Points during 1st vehicle lot Production. The updated drawings to be released as per the received ECN. All the design related points to be closed on or before the SOP. Timely Releasing of test reports High Impact DC Civil Contractor XXXXXX XXXX Drawings approval fromLocal Authority
  • 25. Initiating Forms 15 1.4 STAKEHOLDER ANALYSIS Stakeholder analysis is used to classify stakeholders. It can be used to help fill in the stakeholder register. Analyzing stakeholders can also help in planning stakeholder engagement for groups of stakeholders. The following example is used to assess the relative power (high or low), the relative interest (high or low), and the attitude (friend or foe). There are many other ways to categorize stakeholders. Some exam- ples include: • Influence/impact • Power/urgency/legitimacy Stakeholder analysis receives information from: • Project charter • Procurement documents Stakeholder analysis is a tool used in 13.1 Identify Stakeholders in the PMBOK® Guide – Sixth Edition. Tailoring Tips Consider the following tips to help you tailor the stakeholder analysis to meet your needs: • For projects with relatively homogenous stakeholders you can use a 2 × 2 grid that only considers two variables, such as interest and influence. • For larger projects consider using a 3 × 3 stakeholder cube. Tailor the categories to reflect the impor- tance of various stakeholder variables. Alignment The stakeholder analysis should be aligned and consistent with the following documents: • Stakeholder register • Stakeholder engagement plan Description You can use the element descriptions in Table 1.4 to assist you in developing a stakeholder analysis. TABLE 1.4 Stakeholder Analysis Document Element Description Name or role The stakeholder name, organization, or group Interest The level of concern the stakeholder has for the project
  • 26. Influence The degree to which the stakeholder can drive or influence outcomes for the project Attitude The degree to which the stakeholder supports the project
  • 27. STAKEHOLDER ANALYSIS Project Title: Date Prepared: Name or Role Interest Influenc e Attitude