IT Governance
Project Management Tool
Sample Decision Package
Review Date: October 14, 2003
Presentation Time: 9:00 – 10:00 AM CST
Presenters: PMO Manager and Director
2
IT Governance Review – PM Tool
 Purpose of this Review
 Provide Team recommendations to IT
Governance
 Review Pros/Cons of final 2 vendor solutions
 Obtain recommendation from IT Governance on
final tool
 Gain agreement from IT Governance to
purchase and implement a Portfolio /Project
Management Tool
3
Portfolio / Project Management Tool
 Executive Summary
 In today's business environment, organizations have to do
more with less. Improving processes is critical but is only
part of the total solution. People are a company’s number
one asset - managing them and the work they do is crucial
to organizational success. Many organizations have found
that utilizing a Portfolio & Project Management tool results
in decreased cost, by aiding management in understanding
and managing the complexity of costs and benefits,
resources, projects, risks, changes, and issues. They
have found many benefits and increased performance by
empowering everyone in the organization with collaboration
tools to improve teamwork and share best practices,
issues, and knowledge
4
IT Governance Review – PM Tool
 Technology or Architecture – Overview
 Problem State
 Inconsistent Project Management across IT
 Reinvention of PM processes and tools from project to project
 Time wasted
 Quality and completeness of artifacts vary
 Resources challenged to learn PM processes from project to project
 Past failures in managing large, cross-functional projects, costing the company
millions of dollars
 Inconsistent delivery of projects on-time and on-budget
 Limited ability to understand the entire portfolio of IT projects and cross-
functional dependencies (Initiatives, Business Support, Production Support in
Application Development)
 Inconsistent Project and Initiative Communications
 Goal State to Resolve
 Integrated repository which supports all levels of reporting, monitoring and
control for all IT projects
 Consistent Project Management processes across IT
 Onetime entry of critical information, closest to its source
 Integrated issue, scope, resource and risk management processes
 Quality Compliance Management
5
IT Governance Review – PM Tool
 Recommendation Team
 IT Groups on Tool Team
 Application Development
 Call Center Systems
 Payroll Systems
 Back Office Systems
 Lending Systems
 Loan Servicing
 Corporate Initiatives
 Shared Services
 Web Development
 IT Service Delivery
 Arch / Process Engineering
 Service Delivery PMO
 IT Infrastructure
 Process and Controls
 Quality Assurance
 Corporate PMD
 ITPO
6
IT Governance Review – PM Tool
 Detailed Recommendation Review
 Evaluation Team developed 118 specific requirements based on the
framework procedures and existing financial reporting requirements
 Use Cases developed based on these requirements and used as format for
vendor presentations
 Sent RFI to 5 vendors – completed vendor presentations for 6 vendors
 Received feedback (evaluation) from team participants
 Created Weighted Average Evaluation ( See attached)
 Project Team decision meeting
 Reviewed weighted average score for each vendor
 Discussed …
 complexity of tools and maturity of <Company>
 time to market – complexity of implementation
 technology
 total cost
 Training
 Completed Technical Platform Assessment
 Completed ROI
 Completed Due Diligence for final 2 vendors
 Architecture Review Committee Recommendation – Vendor 3
7
Vendor Comparison
Vendor 2
 Total Cost for solution (vendor 2): $147,000
 Hardware/Software for environment
(<Company>): $116,000 (estimated)
 Annual Support: Vendor – Free for first 12
months then option of $10,000 annual or fee
based <Company> $2,500
 More straightforward tool – more suited for
where we are today
 Small company willing to partner with
<Company> to make the tool what we need it to
be
 Vendor willing to host the pilot at no charge to
<Company>
 User friendly
 Provides functions to meet our requirements
 Vendor will provide more individualized support
– as a small company they have the flexibility to
make themselves available
 Support and any customization after
implementation are on a fee basis
Vendor 3
 Total Cost for Solution (vendor) 3: $496,820
 Hardware/Software for environment
(<Company>): $116,000 (estimated)
 Annual Support: Vendor $47,920 <Company>
$2,500
 More robust tool – can meet our needs today
but allow us to grow and expand our processes
 Large company with a focus on selling a World
Class solution
 Can implement just what we need today to
make it easier to embrace the change, but as
we grow the functions we need will be there to
support us.
 Client feedback indicates great support
 Tool supports CMM & SOP 98-1
(Capitalization) processes for several clients
 Vendor pricing includes basic support and
maintenance but they have giving <Company>
the Premium Support at no additional cost.
*Note: Detailed comparison provided in attached document. (ATC PM Tool Comparison.doc)
8
Vendor Comparison
 Vendor 3 Financials
 Gross Revenue (Last 3 Years)
 2002- $11,870,946
 2001- $17,917,318
 2000- $13,335,432
 Net Profit (Last 3 Years)
 2002- $1,604,743
 2001- $1,258,333
 2000- $1,056,839
 Staffing - Headcount :
 2002 - 202
 2001- 180
 2000- 149
 Gross Revenue-Projected (2003)
 *2003 - $26,500,000
 Cash On Hand
 2002 - $4,000,000
 2001- $2,996,000
 2000- $3,067,000
 R&D Expenditures
 2002 - $2,850,000
 2001 - $2,500,000
 2000 - $2,350,000
 Vendor 2 Financials
 Gross Revenue (Last 3 Years)
 2002- $2,100,000
 2001- $2,300,000
 2000- $3,100,000
 Staffing - Headcount :
 2003 - 20
 Vendor 2 was founded in 1998. The company
has been profitable each year of business and
is completely funded through the company’s
revenue. Vendor 2 was chosen as one of the
Sprint Winners in the St. Louis Regional
Technology Fast 50 awards program.
Recipients of this award are recognized as one
of the 50 fastest growing companies in the
region. For additional information please refer
to our Dunn and Bradstreet number
#########.
9
IT Governance Review – PM Tool
 Implementation Approach
 Will utilize vendor consulting services for implementation
 Will implement for a small pilot group first, complete assessment and setup for remaining IT
 Depending on the tool selected – will evaluate what functions need to be implemented to support the
Release 1 of the IT Operational Frameworks – will scale back as appropriate to lessen the impact of
change to the organization.
Success Criteria
 Support for all levels of project management (Portfolio, Program, Project and Sub-project)
 Automation support for the management of our defined processes in a practical and cost-
efficient manner
 Easy access to project, program and portfolio information across all IT resources and
locations, based on security authorization
 Comprehensive, integrated view of all IT work
 Scalable solution that will grow with our needs
 Solution that is consistent with our technology standards and is effectively integrated into our
operational environment
 Support of true “Portfolio Management Functions” as <Company> processes are defined and
implemented
10
IT Governance Review – PM Tool
 Risks
 Project Related
 With the existence of the <Company> Time Tracking tool utilized by IT today and the
implementation of a project management tool, we are creating an environment with
potentially two project databases. Projects will be planned, scheduled, managed and closed
out using the new tool, whereas time tracking and financial reporting will be functions of the
existing tool. The major risk with this environment is keeping the data and project status in
synch.
Note: Both tools being recommended provide time entry and financial reporting capabilities.
 Acceptance and use by IT user community.
 Potential learning curve associated with selected tool.
 Timing for Release 1 Implementation - can we procure hardware and software to meet the
11/17 pilot date
 Estimated 200 plus employees/contractors will need to attend a 1 day training class – will this
be possible given current project workload
 <Company> IT Architecture Related
 The tool selection team includes ITSD representation with technical knowledge of our
existing environment and standards to help mitigate risks in this area.
 <Company> IT Standard Software Related
 None identified
 Mitigation Plans
 To be determined based on tool selected.
 Time Tracking reports provided to each Project Manager.
 Communication and training for the IT user community.
 Vendor 2 has agreed to host the pilot to mitigate the risk of not meeting 11/17 date
11
IT Governance Review – PM Tool
 Next Steps
 IT Governance Approval
 Contract Negotiations
 Tool Configuration
 Time Line
 Complete “Next Steps”
 Requisition Request submitted by 10/15
 Implementation for small pilot group by 11/17
 Pilot with PM Frameworks 11/17
 Begin full rollout 01/04
12
IT Governance Review – PM Tool
 Supporting Documentation
 Detailed Vendor Comparison
 ROI
 IT Estimates
 Weighted Average Team Evaluation
 Vendor Due Diligence
 Vendor Financial Statements
 Vendor 2 Dunn & Bradstreet Report (Hard
copy only)

More Related Content

PDF
Enjoy immediate access to the full Solution Manual for Systems Analysis and D...
PDF
Solution Manual for Systems Analysis and Design, 7th Edition, Alan Dennis
PPTX
Building cbis, mis, csvtu
PDF
Solution Manual for Systems Analysis and Design, 7th Edition, Alan Dennis
PDF
IT Software Category
DOC
Print report
PPT
Feasibility Analysis.ppt
DOC
Andrew Thomson Resume
Enjoy immediate access to the full Solution Manual for Systems Analysis and D...
Solution Manual for Systems Analysis and Design, 7th Edition, Alan Dennis
Building cbis, mis, csvtu
Solution Manual for Systems Analysis and Design, 7th Edition, Alan Dennis
IT Software Category
Print report
Feasibility Analysis.ppt
Andrew Thomson Resume

Similar to SampleDecPkg.ppt (20)

DOCX
The renewed Importance of an Infrastructure Strategy
DOCX
DOCX
The renewed Importance of an Infrastructure Strategy
PDF
PAC Fast Track Implementation Program
PPT
ITSM Tool upgrade options
PPT
IT PMO Charter (Linkedin)
PPT
Digite Enterprise - Integrate ALM for Corporate IT
DOCX
235429094 jobportal-documentation
DOCX
IT Application Support Analyst Job Spec
PPT
It Sales Presentation 2010 03 31
PPTX
A Case Study on Business Process Management
DOCX
Matt Misiak 2016
PPTX
Enterprise architecture framework business case
PPT
Downloads abc 2006 presentation downloads-ramesh_babu
PPT
Agile Project Management Methods of ERP
PPT
An IT Governance program
DOC
KI_res_24_yrs_exp_big_6
PPTX
Deployment roadmap
DOC
Sai Krishna_Resume
PPTX
Day 1: ICT Strategic Planning, Mr. Soufiane Ben Moussa, CTO, House of Commons...
The renewed Importance of an Infrastructure Strategy
The renewed Importance of an Infrastructure Strategy
PAC Fast Track Implementation Program
ITSM Tool upgrade options
IT PMO Charter (Linkedin)
Digite Enterprise - Integrate ALM for Corporate IT
235429094 jobportal-documentation
IT Application Support Analyst Job Spec
It Sales Presentation 2010 03 31
A Case Study on Business Process Management
Matt Misiak 2016
Enterprise architecture framework business case
Downloads abc 2006 presentation downloads-ramesh_babu
Agile Project Management Methods of ERP
An IT Governance program
KI_res_24_yrs_exp_big_6
Deployment roadmap
Sai Krishna_Resume
Day 1: ICT Strategic Planning, Mr. Soufiane Ben Moussa, CTO, House of Commons...

More from Courtney Doutherd (6)

PPT
business-model-template-1.ppt
PPTX
SOMA-SOA-SERVICE.pptx
PDF
Performance evaluation report template
PPTX
Business Process As-Is
DOCX
Organizational Change Management Readiness Assessment
PPTX
Understanding and Implementing Organizational Change
business-model-template-1.ppt
SOMA-SOA-SERVICE.pptx
Performance evaluation report template
Business Process As-Is
Organizational Change Management Readiness Assessment
Understanding and Implementing Organizational Change

Recently uploaded (20)

PPTX
Benefits of Physical activity for teenagers.pptx
PDF
OpenACC and Open Hackathons Monthly Highlights July 2025
PDF
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
STKI Israel Market Study 2025 version august
PDF
Consumable AI The What, Why & How for Small Teams.pdf
PDF
Taming the Chaos: How to Turn Unstructured Data into Decisions
PPTX
Custom Battery Pack Design Considerations for Performance and Safety
PDF
Convolutional neural network based encoder-decoder for efficient real-time ob...
PDF
Comparative analysis of machine learning models for fake news detection in so...
DOCX
search engine optimization ppt fir known well about this
PPTX
Build Your First AI Agent with UiPath.pptx
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PDF
sustainability-14-14877-v2.pddhzftheheeeee
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PPTX
TEXTILE technology diploma scope and career opportunities
PPTX
The various Industrial Revolutions .pptx
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PPTX
2018-HIPAA-Renewal-Training for executives
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
Benefits of Physical activity for teenagers.pptx
OpenACC and Open Hackathons Monthly Highlights July 2025
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
Zenith AI: Advanced Artificial Intelligence
STKI Israel Market Study 2025 version august
Consumable AI The What, Why & How for Small Teams.pdf
Taming the Chaos: How to Turn Unstructured Data into Decisions
Custom Battery Pack Design Considerations for Performance and Safety
Convolutional neural network based encoder-decoder for efficient real-time ob...
Comparative analysis of machine learning models for fake news detection in so...
search engine optimization ppt fir known well about this
Build Your First AI Agent with UiPath.pptx
Final SEM Unit 1 for mit wpu at pune .pptx
sustainability-14-14877-v2.pddhzftheheeeee
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
TEXTILE technology diploma scope and career opportunities
The various Industrial Revolutions .pptx
NewMind AI Weekly Chronicles – August ’25 Week III
2018-HIPAA-Renewal-Training for executives
How ambidextrous entrepreneurial leaders react to the artificial intelligence...

SampleDecPkg.ppt

  • 1. IT Governance Project Management Tool Sample Decision Package Review Date: October 14, 2003 Presentation Time: 9:00 – 10:00 AM CST Presenters: PMO Manager and Director
  • 2. 2 IT Governance Review – PM Tool  Purpose of this Review  Provide Team recommendations to IT Governance  Review Pros/Cons of final 2 vendor solutions  Obtain recommendation from IT Governance on final tool  Gain agreement from IT Governance to purchase and implement a Portfolio /Project Management Tool
  • 3. 3 Portfolio / Project Management Tool  Executive Summary  In today's business environment, organizations have to do more with less. Improving processes is critical but is only part of the total solution. People are a company’s number one asset - managing them and the work they do is crucial to organizational success. Many organizations have found that utilizing a Portfolio & Project Management tool results in decreased cost, by aiding management in understanding and managing the complexity of costs and benefits, resources, projects, risks, changes, and issues. They have found many benefits and increased performance by empowering everyone in the organization with collaboration tools to improve teamwork and share best practices, issues, and knowledge
  • 4. 4 IT Governance Review – PM Tool  Technology or Architecture – Overview  Problem State  Inconsistent Project Management across IT  Reinvention of PM processes and tools from project to project  Time wasted  Quality and completeness of artifacts vary  Resources challenged to learn PM processes from project to project  Past failures in managing large, cross-functional projects, costing the company millions of dollars  Inconsistent delivery of projects on-time and on-budget  Limited ability to understand the entire portfolio of IT projects and cross- functional dependencies (Initiatives, Business Support, Production Support in Application Development)  Inconsistent Project and Initiative Communications  Goal State to Resolve  Integrated repository which supports all levels of reporting, monitoring and control for all IT projects  Consistent Project Management processes across IT  Onetime entry of critical information, closest to its source  Integrated issue, scope, resource and risk management processes  Quality Compliance Management
  • 5. 5 IT Governance Review – PM Tool  Recommendation Team  IT Groups on Tool Team  Application Development  Call Center Systems  Payroll Systems  Back Office Systems  Lending Systems  Loan Servicing  Corporate Initiatives  Shared Services  Web Development  IT Service Delivery  Arch / Process Engineering  Service Delivery PMO  IT Infrastructure  Process and Controls  Quality Assurance  Corporate PMD  ITPO
  • 6. 6 IT Governance Review – PM Tool  Detailed Recommendation Review  Evaluation Team developed 118 specific requirements based on the framework procedures and existing financial reporting requirements  Use Cases developed based on these requirements and used as format for vendor presentations  Sent RFI to 5 vendors – completed vendor presentations for 6 vendors  Received feedback (evaluation) from team participants  Created Weighted Average Evaluation ( See attached)  Project Team decision meeting  Reviewed weighted average score for each vendor  Discussed …  complexity of tools and maturity of <Company>  time to market – complexity of implementation  technology  total cost  Training  Completed Technical Platform Assessment  Completed ROI  Completed Due Diligence for final 2 vendors  Architecture Review Committee Recommendation – Vendor 3
  • 7. 7 Vendor Comparison Vendor 2  Total Cost for solution (vendor 2): $147,000  Hardware/Software for environment (<Company>): $116,000 (estimated)  Annual Support: Vendor – Free for first 12 months then option of $10,000 annual or fee based <Company> $2,500  More straightforward tool – more suited for where we are today  Small company willing to partner with <Company> to make the tool what we need it to be  Vendor willing to host the pilot at no charge to <Company>  User friendly  Provides functions to meet our requirements  Vendor will provide more individualized support – as a small company they have the flexibility to make themselves available  Support and any customization after implementation are on a fee basis Vendor 3  Total Cost for Solution (vendor) 3: $496,820  Hardware/Software for environment (<Company>): $116,000 (estimated)  Annual Support: Vendor $47,920 <Company> $2,500  More robust tool – can meet our needs today but allow us to grow and expand our processes  Large company with a focus on selling a World Class solution  Can implement just what we need today to make it easier to embrace the change, but as we grow the functions we need will be there to support us.  Client feedback indicates great support  Tool supports CMM & SOP 98-1 (Capitalization) processes for several clients  Vendor pricing includes basic support and maintenance but they have giving <Company> the Premium Support at no additional cost. *Note: Detailed comparison provided in attached document. (ATC PM Tool Comparison.doc)
  • 8. 8 Vendor Comparison  Vendor 3 Financials  Gross Revenue (Last 3 Years)  2002- $11,870,946  2001- $17,917,318  2000- $13,335,432  Net Profit (Last 3 Years)  2002- $1,604,743  2001- $1,258,333  2000- $1,056,839  Staffing - Headcount :  2002 - 202  2001- 180  2000- 149  Gross Revenue-Projected (2003)  *2003 - $26,500,000  Cash On Hand  2002 - $4,000,000  2001- $2,996,000  2000- $3,067,000  R&D Expenditures  2002 - $2,850,000  2001 - $2,500,000  2000 - $2,350,000  Vendor 2 Financials  Gross Revenue (Last 3 Years)  2002- $2,100,000  2001- $2,300,000  2000- $3,100,000  Staffing - Headcount :  2003 - 20  Vendor 2 was founded in 1998. The company has been profitable each year of business and is completely funded through the company’s revenue. Vendor 2 was chosen as one of the Sprint Winners in the St. Louis Regional Technology Fast 50 awards program. Recipients of this award are recognized as one of the 50 fastest growing companies in the region. For additional information please refer to our Dunn and Bradstreet number #########.
  • 9. 9 IT Governance Review – PM Tool  Implementation Approach  Will utilize vendor consulting services for implementation  Will implement for a small pilot group first, complete assessment and setup for remaining IT  Depending on the tool selected – will evaluate what functions need to be implemented to support the Release 1 of the IT Operational Frameworks – will scale back as appropriate to lessen the impact of change to the organization. Success Criteria  Support for all levels of project management (Portfolio, Program, Project and Sub-project)  Automation support for the management of our defined processes in a practical and cost- efficient manner  Easy access to project, program and portfolio information across all IT resources and locations, based on security authorization  Comprehensive, integrated view of all IT work  Scalable solution that will grow with our needs  Solution that is consistent with our technology standards and is effectively integrated into our operational environment  Support of true “Portfolio Management Functions” as <Company> processes are defined and implemented
  • 10. 10 IT Governance Review – PM Tool  Risks  Project Related  With the existence of the <Company> Time Tracking tool utilized by IT today and the implementation of a project management tool, we are creating an environment with potentially two project databases. Projects will be planned, scheduled, managed and closed out using the new tool, whereas time tracking and financial reporting will be functions of the existing tool. The major risk with this environment is keeping the data and project status in synch. Note: Both tools being recommended provide time entry and financial reporting capabilities.  Acceptance and use by IT user community.  Potential learning curve associated with selected tool.  Timing for Release 1 Implementation - can we procure hardware and software to meet the 11/17 pilot date  Estimated 200 plus employees/contractors will need to attend a 1 day training class – will this be possible given current project workload  <Company> IT Architecture Related  The tool selection team includes ITSD representation with technical knowledge of our existing environment and standards to help mitigate risks in this area.  <Company> IT Standard Software Related  None identified  Mitigation Plans  To be determined based on tool selected.  Time Tracking reports provided to each Project Manager.  Communication and training for the IT user community.  Vendor 2 has agreed to host the pilot to mitigate the risk of not meeting 11/17 date
  • 11. 11 IT Governance Review – PM Tool  Next Steps  IT Governance Approval  Contract Negotiations  Tool Configuration  Time Line  Complete “Next Steps”  Requisition Request submitted by 10/15  Implementation for small pilot group by 11/17  Pilot with PM Frameworks 11/17  Begin full rollout 01/04
  • 12. 12 IT Governance Review – PM Tool  Supporting Documentation  Detailed Vendor Comparison  ROI  IT Estimates  Weighted Average Team Evaluation  Vendor Due Diligence  Vendor Financial Statements  Vendor 2 Dunn & Bradstreet Report (Hard copy only)