SlideShare a Scribd company logo
1
2
 To Improve Skills of participants on scaffolding safety requirements
 To Transfer Technical knowledge to participants and to make them
aware about Scaffolding Safety Practices
 To make participants familiar with International Scaffolding Standards /
practices
 To make them fully understand with types of scaffold , scaffolding
components / material
 To make participants familiar with hazards associated in erection /
dismantling and use of scaffolds
 Roles and responsibilities of Scaffold supervisor / Engineer
 Precautionary measure to be taken while erection / dismantling & use of
scaffold
Aim & Objectives of Trainings
3
Scaffolding Disasters Cont.….
4
Scaffolding Disasters Cont.….
5
Scaffolding Disasters Cont.….
6
Scaffolding Disasters Cont.….
7
Working at Heights accidents are usually serious
and often result in disabling injuries and even
death.
Many of us assume that working at heights injuries
and fatalities occur as a result of falls from high
buildings and structures, but they often occur from
falls of only two to four meters.
Scaffolding Disasters Cont.….
Cause?
Over confident / Smart
8
Working at Heights or Elevated Works is considered when
any work area 1.8 meters (6ft.) and higher or you are dealing
with one or more of the following:
1. Steel Erections
2. Roof Tops
3. Catwalks
4. Stairs
5. Scaffolds
6. Ladders
7. Floor Openings
8. Excavations
Five Most Serious WAH / Scaffold Hazards
9
10
 According to OSHA statistics 79 fatalities & 9,750 Injuries occurred in the year
from W@H / scaffolds,
 72% of workers affect in scaffold accidents due to erection & dismantling & use
of scaffolding
Scaffolding Facts
 Human Factor
88% of all accidents are caused by unsafe acts of people (Human error). Such as
improper attitude, lack of knowledge, lack of skills and inadequate physical and
mental condition).
 Engineering Factor
10% by unsafe Action / Conditions (Brakes failure, Hydraulic failure, Equipment
failure & Over Heating,
 Un inevitable event
2% by “Acts of God” (flood, Earthquake, Strom, volcano)
Accident Causation Theory
OSHA SCAFFOLD FATALITIES
STATCISTICS
11
SCAFFOLD FATALITIES HEIGHT
OF FALLS
12
Elapsed
Time
Distance
Traveled
Velocity
ft per
second
Speed
MPH
Force of
Impact
0.61 6 ft 20 14 2,400 lbs
Working at Height / PFAS
European standards state impact force
must not exceed 6kN=611 Kilograms
European standards state that ¼ Sec
required worker to have protect his self
from falling
Fixed Anchor Point
6.75
metres
Safety Margin=1.0m
Body Height = 2.0m
Shock Absorber =1.75m
Lanyard = 2.0m
Rule of Thumb: 100kg person that falls
1mtr will generate 10kN (1,000kg) of
force on the body
13
 Hard Hat / Safety Helmet
 Safety Glasses
 Safety Shoes
 Coverall / Overall
 Hand Gloves
 Safety Full body Harness
 Chin Strap
 Ear Plug
PPE,S (Personnel Protective
Equipments)
 Spanner
 Magnetic Level
 Measuring tape
 Tool Belt
 Material bag
 Manila rope
 Barricading tape
Tools / Equipments Requirement
Types of Scaffold
 Mobile Scaffolding
 Bracket Scaffold
Four basic types of scaffolds are following:
 Suspended / Hanging Scaffold
 Tower / Base Supported Scaffold
15
17
 Uncompacted ground / Soil
 Poor Initial Design
 Inadequate Bracing
 Overloading
 Obstructions at platform and access / egress blockage
 Un authorize alteration
 Impact from passing vehicles
 Inadequate Construction of Scaffold
 Working at Height / Falls from Height
 Manual material handling
 Electrical / Power lines
 Substandard material used for scaffold erection
 Scaffolding material dropped / dropped objects
 Potential Injuries due to above hazards ( Pinch point , hand injury , head injury , face
injury etc.)
Hazards in Scaffolding ( Erection, Dismantling, Use
18
Scaffolding Parts
1. Sole Board / Sill Sole Boards
2. Base Plates
3. Post Standards
4. Bearers ( Transoms)
5. Runner ( ledgers)
6. Base Lift ( Kicker Lift)
7. Scaffold Planks ( Boards)
8. Bracing Transverse
/diagonal
9. Top Rail
10. Mid Rail
11. Toe Board
12. Self Supporting Drop Bar
Scaffolds Terminology
Scaffolds Terminology
Of a minimum size 100 mm (4’’)high x 25 mm (1”) thick. (50 lbs)
General Note:
Top-rails, mid-rails and toe-boards are installed on the inside of support posts on
all open sides and ends of platforms.
The top horizontal rail of the
guard rail system to be
(38’’ – 45’’) above platform, it
should withstand 200 lbs of
horizontal force.
The horizontal rail installed midway
between the top rail and platform.
(150 lbs)
Guard Rail System
Top-
rail
Mid-
rail
Toe-board
Toe Board
Mid Rail
Top Rail
19
44
20’
5’
Scaffolds Terminology Cont.….
The height of the
scaffold should not
be more than four
(4) times its
minimum base
dimension unless
guys, ties, Out
riggers or braces
are used
Scaffolding Height
21
Scaffolds Terminology Cont.….
 The first vertical tie
must be
installed at a height
less than
4 times the minimum
base dimension.
 The tie must be
installed at a
horizontal member that
supports at every
30 ft.
22
Scaffolds Terminology Cont.….
Scaffolds Terminology Cont.….
All platforms
should be at least
450mm wide
Platform width
23
Scaffolds Terminology Cont.….
Brace: A tie that holds one
scaffold member in a fixed
position with respect to another
member. Brace also means a rigid
type of connection holding a
scaffold to a building or structure.
Type of Bracings
1-Diagonal Bracing
2-Transverse
3-Cross Bracing
4-Ledger Bracing
5-Zigzag Bracing
6-Longitudinal
7-Plan Bracing
24
All time most unstable scaffold!
26
Ø
Scaffold Components
27
Coupler: A device for locking
together the component tubes
of a tube and coupler scaffold.
Scaffolds Terminology Cont.….
Right Angle (Double) Coupler
For Bearers & Runners
Adjustable (swivel) Coupler
for Braces only
Bearers (Putlog) Couplers
Typical end to end
(sleeve) couplers
Joint pins (expanding spigot
couplers)
Metal / Steel Plank & Deck Identification
 Must incorporate a slip
resistant surface
 Must not be less than 6-
inches wide
 Commonly 12-inches to
32-inches wide
 Load rating must have a
4:1 ratio
T-2” X W-12” X L-12’
Scaffolds Terminology Cont.….
28
Electrical Clearance
30
Electrical clearance
from power lines must
be considered while
erecting / dismantling
scaffold.
Insulated lines:
300 Volts to 50 KV – 10 feet
More than 50 KV- 10 feet
plus 4 inches for each 1 KV
over 50 KV
Scaffolds Terminology Cont.….
A. Standards not centred on the baseplate or sole board
B. Soleboard not fully bedded
C. Standard not evenly bearing on baseplate, soleboard
and baseplate not horizontal
Improper techniques for scaffolding erection
Scaffolds Terminology Cont.….
31
Moving Mobile Scaffold
which could cause a person to fall
Scaffolds Terminology Cont.….
32
Green Tag:
A green tag must be placed on or near
access when :
 After the scaffold has been approved to
use by a competent person /
Scaffolding Inspector
 The green tag remains on the scaffold
and it would be used for inspections /
records
Scaffolds Terminology Cont.….
33
Yellow Tag:
A Yellow tag must be highlighted on or near
access when :
 After the scaffold has been approved to
use by a competent person /
Scaffolding Inspector
 While Yellow tag on scaffold full body
harness must be use for work at height
Red Tag:
The red tag must remain on the scaffold near
each access when:
 While the scaffold is under construction
 While the scaffold is under repair /
modification
 When a scaffold is incomplete
 At all times until the scaffold has been
inspected and approved for use officially
36
• Shall ensure compliance with current site scaffold design, erection and dismantling
practices and procedures .
• To Ensure his own safety and his fellows safety .
• To ensure areas below elevated scaffolds are adequately barricaded to safeguard
people walking below.
• Use full body harness while working on height
• To maintain good housekeeping of scaffolding and formwork materials at all times.
• Shall ensure use of inspected / standard components / material, and ground
condition is sound before starts erection of scaffold.
• Shall report any defects / dangerous condition of scaffold to supervisor
Scaffolding Erector Responsibilities
Scaffolds Terminology Cont.….
37
 Inspector have a responsibility to inspect scaffold as describe in company
procedure.
 If Scaffold meets the inspection criteria , inspector shall sign tag
authorizing continued to use scaffold for task.
 If Scaffold fails to meet inspection criteria , inspector shall remove
authorization tag , should notify to Supervisor / Engineer to fix the
problems , prior next inspection.
 Scaffolding Inspector should maintain log of scaffolds inspected in the
workplace.
Scaffolding Inspector Responsibilities
Scaffolds Terminology Cont.….
38
1 metre extension
past the landing
platform
Ladder set at a
4 to 1 ratio
Stile feet resting
on a firm and level
surface
Clamped or lashed
with rope to
prevent movement
Ladder Safety Cont.….
39
 Inspection of Ladder all time before use
 May be use for light tasks of low risk and short duration (in conjunction
with a safety harness); or access and egress to a work platform.
 Ladder should be on firm surface , must be secure with rope / clamps
 One person to climb at ladder one time
 Maintain three point contacts
 Ladder should be free from oil / grease / slipping agents
 Both hands should be free while climbing at ladder
FEET
ON THE RUNGS
OF LADDER
ONE HAND
HOLDING ON THE
RUNG OF LADDER
Ladder Safety Requirements:
Ladder Safety Cont.….
42
 Use of mechanical aid during manual
material shifting such as gen wheel
 Use material shifting bag to shift material
 Always Barricade the area while shifting
the material
 Use hand gloves to prevent any hand
injury
 Load should not be lift maximum 50kg
 Use safety signs around material shifting
area
 Make drop zone always to ensure no body
will come in that area
 16 mm rope should be used
Manual Material Handling
43
Unsafe Acts
44
Unsafe Acts
45
Unsafe Acts
 Ensure while working at height /
scaffold erection user / erector must
use Personnel fall arrest system to
avoid major injuries / death.
 Personnel fall arrest system must be
able to do following:
 Limit the arresting force to 1800 lbs.
 Allow neither a free fall of more than
6 feet nor contact with a lower level.
 Maximum deceleration distance of
3.5 feet.
Working at Height / PFAS
46
47
Shoulder
Strap
Adjustment element
Sit strap (Primary Strap)
Fall arrest attachment
element
Thigh strap
Marking
Working at Height / PFAS
Personal Energy Absorbers
49
 To reduce shock load from Fall Arrest.
 Will extend in length in operation.
 Up to 1.75 metres
 Starts to opening at 2 kN (200 kg) force
 Limits force to less than 6 kN (600 kg)
 Attach to rear “D” ONLY
2kN
6kN
Pendulum Effect
52
• The anchor point should
be above and vertical to
the harness attachment
point.
• Consideration should be
given to the pendulum
effect known as ‘swing
back’.
• Keep within 30 deg of
vertical
Consider W@H when
excavation depth is more
than 6 feet
Provide hard barrication
(1 Mtr) away from edge
Working at Height / PFAS
53
SUSPENSION TRAUMA
• Suspension trauma will affect anyone
hanging motionless with his legs dangling
• Suspension trauma can start within 5
minutes.
• unconscious within 10 minutes and can
die within 15 minutes due to the stale
blood returning from their legs and
stopping the heart
• The brain is starved of oxygen and begins
to die
• Maximum Retrieval time of causality is
10 ~ 20 minutes .
• After Retrieval, keep the person in
Crouching Position at least 30 minutes.
So the blood circulation may not start
immediately which can cause an impact
on his heart.
SUSPENSION
TRAUMA
SYMPTOMS:
 Hot flushes,
sweating,
anxiety,
numbness
 Rapid pulse
and breathing
 Sudden loss of
consciousness
(fainting)
Working at Height / PFAS
54 54
56

More Related Content

PPTX
Work at height safety
PPTX
Scaffolding safety at construction site
PPTX
SCAFFOLDING Safety Training
PPT
Working at height Fall Protection Presentation.ppt
PPT
Industrial safetY of height works
PPT
SCAFFOLDING SAFETY.ppt
PPT
Scaffolding awareness presentation
PPT
Ladder Safety
Work at height safety
Scaffolding safety at construction site
SCAFFOLDING Safety Training
Working at height Fall Protection Presentation.ppt
Industrial safetY of height works
SCAFFOLDING SAFETY.ppt
Scaffolding awareness presentation
Ladder Safety

What's hot (20)

PPT
Working at-height
PPTX
working at height
PPT
PDF
Eta Scaffold Training
PPT
Liftingproedure
PPT
Working at heights
PPTX
Lifting Operation Safety ppt.pptx
PPTX
Mewp training
PDF
Working at heights training powerpoint
PDF
scaffolding safety.pdf
PDF
TOOLBOX TALK | lifting & rigging operations
PPTX
Safety in Material Handling
PPTX
Lock-Out Tag-Out (LOTO) Training
PPT
Scaffold ladder
PPT
Power tools safety
PPT
LOTO Training.ppt
PPTX
Struck by hazards 2019
PDF
Working at height slides
PPT
Flagman-Training.ppt
PDF
Rigging and lifting
Working at-height
working at height
Eta Scaffold Training
Liftingproedure
Working at heights
Lifting Operation Safety ppt.pptx
Mewp training
Working at heights training powerpoint
scaffolding safety.pdf
TOOLBOX TALK | lifting & rigging operations
Safety in Material Handling
Lock-Out Tag-Out (LOTO) Training
Scaffold ladder
Power tools safety
LOTO Training.ppt
Struck by hazards 2019
Working at height slides
Flagman-Training.ppt
Rigging and lifting

Similar to Scaffolding safety training.ppt (20)

PPT
scaffoldingsafetytraining-221124050618-36ac1a86.ppt
PPT
Scaffold Safety (2).ppt
PPT
SCAFFOLDING SAFETY TRAINING PPT FOR EMPLOYEES
PPT
Work-at-Height-Training.ppt slides for sharing
PPT
Work at height at industries and PPE.ppt
PPT
SCAFFOLDING safety training PRESENTATION .ppt
PDF
Work at height procedure in relation of safety at construction projects.pdf
PPTX
CE153-COSH-SCAFFOLDING SAFETY-Engg Dept.pptx
PPTX
WORK AT HEIGHT TRAINING WORK AT HEIGHT TRAINING.pptx
PPTX
Scaffolding Training for Construction work.pptx
PDF
Scaffold Awareness Training Document.pdf
PPT
Scaffolding Safety Training.ppt For scaffolders
PPT
2. scaffolds amd ladders
PPT
222222222222222343566778788999000---=.ppt
PPTX
1926 Scaffolds
PPT
SCAFFOLD TRAINING.ppt
PPT
Scaffolding Powerpoint presentation for training
PPT
Scaffolding Safety Precaution Hazard Identification
PDF
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
PDF
Scaffolding Safety at construction area.
scaffoldingsafetytraining-221124050618-36ac1a86.ppt
Scaffold Safety (2).ppt
SCAFFOLDING SAFETY TRAINING PPT FOR EMPLOYEES
Work-at-Height-Training.ppt slides for sharing
Work at height at industries and PPE.ppt
SCAFFOLDING safety training PRESENTATION .ppt
Work at height procedure in relation of safety at construction projects.pdf
CE153-COSH-SCAFFOLDING SAFETY-Engg Dept.pptx
WORK AT HEIGHT TRAINING WORK AT HEIGHT TRAINING.pptx
Scaffolding Training for Construction work.pptx
Scaffold Awareness Training Document.pdf
Scaffolding Safety Training.ppt For scaffolders
2. scaffolds amd ladders
222222222222222343566778788999000---=.ppt
1926 Scaffolds
SCAFFOLD TRAINING.ppt
Scaffolding Powerpoint presentation for training
Scaffolding Safety Precaution Hazard Identification
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
Scaffolding Safety at construction area.

More from IrfanAwan25 (11)

PPT
cheat sheet.ppt
PPTX
Progress Pictures Aug-19.pptx
PPT
Das HSE.ppt
PPTX
Progress Pictures 07-Dec-2019.pptx
PPTX
product-development-roadmap-template.pptx
PPTX
Construction of Data Centre (Hemel Hempstead).pptx
PPTX
Colt Hayes Planning Approach v1 220121.pptx
PPTX
PECDisputeResolution25102018.pptx
PPTX
presentation.pptx
PPTX
Colt Hayes Planning Approach v2 220121.pptx
PPTX
Colt Hayes Planning Approach v1 220121.pptx
cheat sheet.ppt
Progress Pictures Aug-19.pptx
Das HSE.ppt
Progress Pictures 07-Dec-2019.pptx
product-development-roadmap-template.pptx
Construction of Data Centre (Hemel Hempstead).pptx
Colt Hayes Planning Approach v1 220121.pptx
PECDisputeResolution25102018.pptx
presentation.pptx
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx

Recently uploaded (20)

PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
OOP with Java - Java Introduction (Basics)
DOCX
573137875-Attendance-Management-System-original
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Lecture Notes Electrical Wiring System Components
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
composite construction of structures.pdf
PPTX
web development for engineering and engineering
PDF
Well-logging-methods_new................
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Digital Logic Computer Design lecture notes
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Foundation to blockchain - A guide to Blockchain Tech
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
OOP with Java - Java Introduction (Basics)
573137875-Attendance-Management-System-original
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Lesson 3_Tessellation.pptx finite Mathematics
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Mechanical Engineering MATERIALS Selection
Lecture Notes Electrical Wiring System Components
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
CYBER-CRIMES AND SECURITY A guide to understanding
Internet of Things (IOT) - A guide to understanding
Model Code of Practice - Construction Work - 21102022 .pdf
composite construction of structures.pdf
web development for engineering and engineering
Well-logging-methods_new................
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Digital Logic Computer Design lecture notes

Scaffolding safety training.ppt

  • 1. 1
  • 2. 2  To Improve Skills of participants on scaffolding safety requirements  To Transfer Technical knowledge to participants and to make them aware about Scaffolding Safety Practices  To make participants familiar with International Scaffolding Standards / practices  To make them fully understand with types of scaffold , scaffolding components / material  To make participants familiar with hazards associated in erection / dismantling and use of scaffolds  Roles and responsibilities of Scaffold supervisor / Engineer  Precautionary measure to be taken while erection / dismantling & use of scaffold Aim & Objectives of Trainings
  • 7. 7 Working at Heights accidents are usually serious and often result in disabling injuries and even death. Many of us assume that working at heights injuries and fatalities occur as a result of falls from high buildings and structures, but they often occur from falls of only two to four meters. Scaffolding Disasters Cont.…. Cause? Over confident / Smart
  • 8. 8 Working at Heights or Elevated Works is considered when any work area 1.8 meters (6ft.) and higher or you are dealing with one or more of the following: 1. Steel Erections 2. Roof Tops 3. Catwalks 4. Stairs 5. Scaffolds 6. Ladders 7. Floor Openings 8. Excavations
  • 9. Five Most Serious WAH / Scaffold Hazards 9
  • 10. 10  According to OSHA statistics 79 fatalities & 9,750 Injuries occurred in the year from W@H / scaffolds,  72% of workers affect in scaffold accidents due to erection & dismantling & use of scaffolding Scaffolding Facts  Human Factor 88% of all accidents are caused by unsafe acts of people (Human error). Such as improper attitude, lack of knowledge, lack of skills and inadequate physical and mental condition).  Engineering Factor 10% by unsafe Action / Conditions (Brakes failure, Hydraulic failure, Equipment failure & Over Heating,  Un inevitable event 2% by “Acts of God” (flood, Earthquake, Strom, volcano) Accident Causation Theory
  • 12. 12 Elapsed Time Distance Traveled Velocity ft per second Speed MPH Force of Impact 0.61 6 ft 20 14 2,400 lbs Working at Height / PFAS European standards state impact force must not exceed 6kN=611 Kilograms European standards state that ¼ Sec required worker to have protect his self from falling Fixed Anchor Point 6.75 metres Safety Margin=1.0m Body Height = 2.0m Shock Absorber =1.75m Lanyard = 2.0m Rule of Thumb: 100kg person that falls 1mtr will generate 10kN (1,000kg) of force on the body
  • 13. 13  Hard Hat / Safety Helmet  Safety Glasses  Safety Shoes  Coverall / Overall  Hand Gloves  Safety Full body Harness  Chin Strap  Ear Plug PPE,S (Personnel Protective Equipments)  Spanner  Magnetic Level  Measuring tape  Tool Belt  Material bag  Manila rope  Barricading tape Tools / Equipments Requirement
  • 14. Types of Scaffold  Mobile Scaffolding  Bracket Scaffold Four basic types of scaffolds are following:  Suspended / Hanging Scaffold  Tower / Base Supported Scaffold 15
  • 15. 17  Uncompacted ground / Soil  Poor Initial Design  Inadequate Bracing  Overloading  Obstructions at platform and access / egress blockage  Un authorize alteration  Impact from passing vehicles  Inadequate Construction of Scaffold  Working at Height / Falls from Height  Manual material handling  Electrical / Power lines  Substandard material used for scaffold erection  Scaffolding material dropped / dropped objects  Potential Injuries due to above hazards ( Pinch point , hand injury , head injury , face injury etc.) Hazards in Scaffolding ( Erection, Dismantling, Use
  • 16. 18 Scaffolding Parts 1. Sole Board / Sill Sole Boards 2. Base Plates 3. Post Standards 4. Bearers ( Transoms) 5. Runner ( ledgers) 6. Base Lift ( Kicker Lift) 7. Scaffold Planks ( Boards) 8. Bracing Transverse /diagonal 9. Top Rail 10. Mid Rail 11. Toe Board 12. Self Supporting Drop Bar Scaffolds Terminology
  • 17. Scaffolds Terminology Of a minimum size 100 mm (4’’)high x 25 mm (1”) thick. (50 lbs) General Note: Top-rails, mid-rails and toe-boards are installed on the inside of support posts on all open sides and ends of platforms. The top horizontal rail of the guard rail system to be (38’’ – 45’’) above platform, it should withstand 200 lbs of horizontal force. The horizontal rail installed midway between the top rail and platform. (150 lbs) Guard Rail System Top- rail Mid- rail Toe-board Toe Board Mid Rail Top Rail 19
  • 18. 44 20’ 5’ Scaffolds Terminology Cont.…. The height of the scaffold should not be more than four (4) times its minimum base dimension unless guys, ties, Out riggers or braces are used Scaffolding Height
  • 19. 21 Scaffolds Terminology Cont.….  The first vertical tie must be installed at a height less than 4 times the minimum base dimension.  The tie must be installed at a horizontal member that supports at every 30 ft.
  • 21. Scaffolds Terminology Cont.…. All platforms should be at least 450mm wide Platform width 23
  • 22. Scaffolds Terminology Cont.…. Brace: A tie that holds one scaffold member in a fixed position with respect to another member. Brace also means a rigid type of connection holding a scaffold to a building or structure. Type of Bracings 1-Diagonal Bracing 2-Transverse 3-Cross Bracing 4-Ledger Bracing 5-Zigzag Bracing 6-Longitudinal 7-Plan Bracing 24
  • 23. All time most unstable scaffold! 26 Ø
  • 24. Scaffold Components 27 Coupler: A device for locking together the component tubes of a tube and coupler scaffold. Scaffolds Terminology Cont.…. Right Angle (Double) Coupler For Bearers & Runners Adjustable (swivel) Coupler for Braces only Bearers (Putlog) Couplers Typical end to end (sleeve) couplers Joint pins (expanding spigot couplers)
  • 25. Metal / Steel Plank & Deck Identification  Must incorporate a slip resistant surface  Must not be less than 6- inches wide  Commonly 12-inches to 32-inches wide  Load rating must have a 4:1 ratio T-2” X W-12” X L-12’ Scaffolds Terminology Cont.…. 28
  • 26. Electrical Clearance 30 Electrical clearance from power lines must be considered while erecting / dismantling scaffold. Insulated lines: 300 Volts to 50 KV – 10 feet More than 50 KV- 10 feet plus 4 inches for each 1 KV over 50 KV Scaffolds Terminology Cont.….
  • 27. A. Standards not centred on the baseplate or sole board B. Soleboard not fully bedded C. Standard not evenly bearing on baseplate, soleboard and baseplate not horizontal Improper techniques for scaffolding erection Scaffolds Terminology Cont.…. 31
  • 28. Moving Mobile Scaffold which could cause a person to fall Scaffolds Terminology Cont.…. 32
  • 29. Green Tag: A green tag must be placed on or near access when :  After the scaffold has been approved to use by a competent person / Scaffolding Inspector  The green tag remains on the scaffold and it would be used for inspections / records Scaffolds Terminology Cont.…. 33 Yellow Tag: A Yellow tag must be highlighted on or near access when :  After the scaffold has been approved to use by a competent person / Scaffolding Inspector  While Yellow tag on scaffold full body harness must be use for work at height Red Tag: The red tag must remain on the scaffold near each access when:  While the scaffold is under construction  While the scaffold is under repair / modification  When a scaffold is incomplete  At all times until the scaffold has been inspected and approved for use officially
  • 30. 36 • Shall ensure compliance with current site scaffold design, erection and dismantling practices and procedures . • To Ensure his own safety and his fellows safety . • To ensure areas below elevated scaffolds are adequately barricaded to safeguard people walking below. • Use full body harness while working on height • To maintain good housekeeping of scaffolding and formwork materials at all times. • Shall ensure use of inspected / standard components / material, and ground condition is sound before starts erection of scaffold. • Shall report any defects / dangerous condition of scaffold to supervisor Scaffolding Erector Responsibilities Scaffolds Terminology Cont.….
  • 31. 37  Inspector have a responsibility to inspect scaffold as describe in company procedure.  If Scaffold meets the inspection criteria , inspector shall sign tag authorizing continued to use scaffold for task.  If Scaffold fails to meet inspection criteria , inspector shall remove authorization tag , should notify to Supervisor / Engineer to fix the problems , prior next inspection.  Scaffolding Inspector should maintain log of scaffolds inspected in the workplace. Scaffolding Inspector Responsibilities Scaffolds Terminology Cont.….
  • 32. 38 1 metre extension past the landing platform Ladder set at a 4 to 1 ratio Stile feet resting on a firm and level surface Clamped or lashed with rope to prevent movement Ladder Safety Cont.….
  • 33. 39  Inspection of Ladder all time before use  May be use for light tasks of low risk and short duration (in conjunction with a safety harness); or access and egress to a work platform.  Ladder should be on firm surface , must be secure with rope / clamps  One person to climb at ladder one time  Maintain three point contacts  Ladder should be free from oil / grease / slipping agents  Both hands should be free while climbing at ladder FEET ON THE RUNGS OF LADDER ONE HAND HOLDING ON THE RUNG OF LADDER Ladder Safety Requirements: Ladder Safety Cont.….
  • 34. 42  Use of mechanical aid during manual material shifting such as gen wheel  Use material shifting bag to shift material  Always Barricade the area while shifting the material  Use hand gloves to prevent any hand injury  Load should not be lift maximum 50kg  Use safety signs around material shifting area  Make drop zone always to ensure no body will come in that area  16 mm rope should be used Manual Material Handling
  • 38.  Ensure while working at height / scaffold erection user / erector must use Personnel fall arrest system to avoid major injuries / death.  Personnel fall arrest system must be able to do following:  Limit the arresting force to 1800 lbs.  Allow neither a free fall of more than 6 feet nor contact with a lower level.  Maximum deceleration distance of 3.5 feet. Working at Height / PFAS 46
  • 39. 47 Shoulder Strap Adjustment element Sit strap (Primary Strap) Fall arrest attachment element Thigh strap Marking Working at Height / PFAS
  • 40. Personal Energy Absorbers 49  To reduce shock load from Fall Arrest.  Will extend in length in operation.  Up to 1.75 metres  Starts to opening at 2 kN (200 kg) force  Limits force to less than 6 kN (600 kg)  Attach to rear “D” ONLY 2kN 6kN
  • 41. Pendulum Effect 52 • The anchor point should be above and vertical to the harness attachment point. • Consideration should be given to the pendulum effect known as ‘swing back’. • Keep within 30 deg of vertical
  • 42. Consider W@H when excavation depth is more than 6 feet Provide hard barrication (1 Mtr) away from edge Working at Height / PFAS 53
  • 43. SUSPENSION TRAUMA • Suspension trauma will affect anyone hanging motionless with his legs dangling • Suspension trauma can start within 5 minutes. • unconscious within 10 minutes and can die within 15 minutes due to the stale blood returning from their legs and stopping the heart • The brain is starved of oxygen and begins to die • Maximum Retrieval time of causality is 10 ~ 20 minutes . • After Retrieval, keep the person in Crouching Position at least 30 minutes. So the blood circulation may not start immediately which can cause an impact on his heart. SUSPENSION TRAUMA SYMPTOMS:  Hot flushes, sweating, anxiety, numbness  Rapid pulse and breathing  Sudden loss of consciousness (fainting) Working at Height / PFAS 54 54
  • 44. 56