Earned Value Formulas
PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
SV = EV – PV (minus is behind schedule)
CV = EV – AC (minus is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV) Use when variances are atypical
EAC = BAC/CPI Use when variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BAC – EAC
ETC = BAC – EV Use when variances are atypical
ETC = (BAC – EV)/CPI Use when variances are typical
ETC = EAC – AC Use when original estimates were flawed
Project Selection Financials
NPV (Net Present Value) = FV/(1+r)n
FV= Future Value, r= interest rate, n= no. of time periods
Higher NPV is better
IRR (Internal Rate of Return) = Solve the NPV equation for “r”
Also called Hurdle Rate
Higher IRR percentage is better
BCR (Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is better
Payback Period = Time to recover cost of the project
Lower payback period is better
Cash Flow = Cash In – Cash Out
Network Diagrams
Precedence Diagramming Method (PDM)
Also called Activity on Node (AON): Activities are in boxes
Most commonly used today
Has 4 relationships: F-S, S-S, F-F, S-F
No “dummies” (zero duration dependencies) allowed
Can analyze using either Three-Point Estimates or CPM
Arrow Diagramming Method (ADM)
Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have “dummies”
Can analyze using either Three-Point Estimates or CPM
Graphical Evaluation and Review Technique (GERT)
Allows loops and repetitive activities
Three Point Estimates, or PERT
PERT = PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic, Pessimistic, and Most Likely
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (σ) = (P – O)/6
Critical Path Method, CPM Analysis
1 bestimate per activity: the Most Likely estimate
Holds cost and lets schedule float
Calculating Slack or Float
Total Float (also called Slack, Float, or Project Float) is the
total amount of time an activity can be delayed without
delaying the project finish date.
Free Float/Slack is the amount of time an activity can be
delayed without delaying its successor (following
activity).
LS – ES: Calculates slack with forward pass
LF – EF: Calculates slack with backwards pass
Lag Time: Inserted wait time between activities
Lead Time: Overlapping activities, also called paralleling or
fast tracking.
“Lead In; Lag Out”
Accuracy of Estimates
Order of Magnitude: -25% to +75%
Budget Estimate: -10% to +25%
Definitive Estimate: -5% to +10%
Standard Deviations from the Norm
± 1 σ = 68.26%
± 2 σ = 95.46%
± 3 σ = 99.73%
± 6 σ = 99.99%
Powers of a Project Manager
1. Expert: Best, earned on your own
2. Reward: Next best. Based on PM position
3. Formal: Power, based on PM position
4. Referent: Referring to positions of others
5. Penalty: Worst. Based on PM position
Conflict Resolution (Best to Worst)
1. Problem Solving: Also called Confronting
2. Compromising: Solutions satisfy both parties
3. Withdrawal: Postponing a decision
4. Smoothing: Emphasis on agreement
5. Forcing: One viewpoint at expense of another.
Channels of Communication
Between Team Members = N(N-1)/2
Sources of Conflict (Order of Priority)
1. Schedules
2. Project Priorities
3. Resources
4. Technical Opinions
5. Administrative Procedures
6. Cost
7. Personality
Herzberg’s Motivators
1. Achievement
2. Recognition
3. Challenge of the work itself
4. Responsibility
5. Advancement
6. Growth
Also, remember Maslow’s Hierarchy of Needs
Closing
Project is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and
at the end of the Project.
Contract closure: verification that deliverables were acceptable; it
is done once at the end of the contract.
Contract Closure Procedure is produced under “Close Project”
PMP Test Preparation

More Related Content

PPTX
PMI Project Management Principles
PDF
Pmp Formula Pocket_Guide
PPT
Project Management PPT
PDF
Project Risk Management - PMBOK5
PPTX
Project integration management
PDF
Pmbok6 to 7 transformation
PDF
Conduct procurements
PPTX
Business case
PMI Project Management Principles
Pmp Formula Pocket_Guide
Project Management PPT
Project Risk Management - PMBOK5
Project integration management
Pmbok6 to 7 transformation
Conduct procurements
Business case

What's hot (20)

PDF
02 pmp project life cycle exam
PPTX
009. project communication management
PDF
PMP Chap 10 - Project Communication Management Details
PDF
Pmp formula pocket guide
PPS
Project Management Process Groups And Knowledge Areas
PPTX
Scrum & Sprint Planning.pptx
PDF
Agile Product Owner in Wonderland!
PDF
PMP Chap 5 - Project Scope Management - Part 2
PPTX
Project human resources management
PDF
Project Management Steps And Process PowerPoint Presentation Slides
PDF
PMP Chap 2- Org. Influence and Project Life Cycle
PDF
Fundamentals of project management
PPTX
Project integration management
PDF
Project Budget PowerPoint Presentation Slides
PPTX
Optimize Project Intake Approval and Prioritization
PDF
Project Management Professional (PMP)
PDF
Chap 13.1 Identify stakeholders
PDF
Project cost management
PPTX
12.2 Conduct Procurements
02 pmp project life cycle exam
009. project communication management
PMP Chap 10 - Project Communication Management Details
Pmp formula pocket guide
Project Management Process Groups And Knowledge Areas
Scrum & Sprint Planning.pptx
Agile Product Owner in Wonderland!
PMP Chap 5 - Project Scope Management - Part 2
Project human resources management
Project Management Steps And Process PowerPoint Presentation Slides
PMP Chap 2- Org. Influence and Project Life Cycle
Fundamentals of project management
Project integration management
Project Budget PowerPoint Presentation Slides
Optimize Project Intake Approval and Prioritization
Project Management Professional (PMP)
Chap 13.1 Identify stakeholders
Project cost management
12.2 Conduct Procurements
Ad

Similar to cheat sheet.ppt (20)

PDF
Pmp memory-sheets
PDF
Formulas for pmp exam
PPT
Software Project Management lecture 9
PDF
Pmp formulas
PPTX
07 projectcostmanagement
PPTX
PMP Training - 07 project cost management
PDF
Free pmp answers
PPT
PMP preparation and PMI Framework
PDF
PM Notebook - Appendix H - Formula Sheet
PDF
PMBOK 6th ed Formulas.pdf
PPTX
Project Cost Management
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PDF
Project Management_1.pdf
PPTX
Earned value for pmp and pmi acp exam
PDF
Formula pocket guide
PDF
Pmp formula pocket guide
PPT
Project cost management
PPTX
Earned Value Analysis
PPTX
Earned Value Management - Leading & Misleading in Project Control
PPTX
PMP COST FORMULAE
Pmp memory-sheets
Formulas for pmp exam
Software Project Management lecture 9
Pmp formulas
07 projectcostmanagement
PMP Training - 07 project cost management
Free pmp answers
PMP preparation and PMI Framework
PM Notebook - Appendix H - Formula Sheet
PMBOK 6th ed Formulas.pdf
Project Cost Management
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Project Management_1.pdf
Earned value for pmp and pmi acp exam
Formula pocket guide
Pmp formula pocket guide
Project cost management
Earned Value Analysis
Earned Value Management - Leading & Misleading in Project Control
PMP COST FORMULAE
Ad

More from IrfanAwan25 (11)

PPT
Scaffolding safety training.ppt
PPTX
Progress Pictures Aug-19.pptx
PPT
Das HSE.ppt
PPTX
Progress Pictures 07-Dec-2019.pptx
PPTX
product-development-roadmap-template.pptx
PPTX
Construction of Data Centre (Hemel Hempstead).pptx
PPTX
Colt Hayes Planning Approach v1 220121.pptx
PPTX
PECDisputeResolution25102018.pptx
PPTX
presentation.pptx
PPTX
Colt Hayes Planning Approach v2 220121.pptx
PPTX
Colt Hayes Planning Approach v1 220121.pptx
Scaffolding safety training.ppt
Progress Pictures Aug-19.pptx
Das HSE.ppt
Progress Pictures 07-Dec-2019.pptx
product-development-roadmap-template.pptx
Construction of Data Centre (Hemel Hempstead).pptx
Colt Hayes Planning Approach v1 220121.pptx
PECDisputeResolution25102018.pptx
presentation.pptx
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx

Recently uploaded (20)

PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
PPT on Performance Review to get promotions
PDF
Structs to JSON How Go Powers REST APIs.pdf
DOCX
573137875-Attendance-Management-System-original
PPTX
Construction Project Organization Group 2.pptx
PPTX
Sustainable Sites - Green Building Construction
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
UNIT 4 Total Quality Management .pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PDF
composite construction of structures.pdf
PPTX
Geodesy 1.pptx...............................................
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPT on Performance Review to get promotions
Structs to JSON How Go Powers REST APIs.pdf
573137875-Attendance-Management-System-original
Construction Project Organization Group 2.pptx
Sustainable Sites - Green Building Construction
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Arduino robotics embedded978-1-4302-3184-4.pdf
OOP with Java - Java Introduction (Basics)
UNIT 4 Total Quality Management .pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
composite construction of structures.pdf
Geodesy 1.pptx...............................................
Internet of Things (IOT) - A guide to understanding
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Foundation to blockchain - A guide to Blockchain Tech
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Model Code of Practice - Construction Work - 21102022 .pdf

cheat sheet.ppt

  • 1. Earned Value Formulas PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) SV = EV – PV (minus is behind schedule) CV = EV – AC (minus is over budget) SPI = EV/PV (Less than 1 is behind schedule) CPI = EV/AC (Less than 1 is over budget) EAC = AC + (BAC-EV) Use when variances are atypical EAC = BAC/CPI Use when variances are typical (Note: This is the same as EAC = BAC/CPI) VAC = BAC – EAC ETC = BAC – EV Use when variances are atypical ETC = (BAC – EV)/CPI Use when variances are typical ETC = EAC – AC Use when original estimates were flawed Project Selection Financials NPV (Net Present Value) = FV/(1+r)n FV= Future Value, r= interest rate, n= no. of time periods Higher NPV is better IRR (Internal Rate of Return) = Solve the NPV equation for “r” Also called Hurdle Rate Higher IRR percentage is better BCR (Benefit/Cost Ratio) Higher BCR is better. Beware, exam can call it CBR, where lower is better Payback Period = Time to recover cost of the project Lower payback period is better Cash Flow = Cash In – Cash Out Network Diagrams Precedence Diagramming Method (PDM) Also called Activity on Node (AON): Activities are in boxes Most commonly used today Has 4 relationships: F-S, S-S, F-F, S-F No “dummies” (zero duration dependencies) allowed Can analyze using either Three-Point Estimates or CPM Arrow Diagramming Method (ADM) Also called Activity on Arrow (AOA) Only 1 relationship: F-S Can have “dummies” Can analyze using either Three-Point Estimates or CPM Graphical Evaluation and Review Technique (GERT) Allows loops and repetitive activities Three Point Estimates, or PERT PERT = PROGRAM Evaluation and Review Technique Holds schedule and lets cost float 3 estimates for each task: Optimistic, Pessimistic, and Most Likely Mean Estimate = (O + 4*ML + P)/6 Standard Deviation (σ) = (P – O)/6 Critical Path Method, CPM Analysis 1 bestimate per activity: the Most Likely estimate Holds cost and lets schedule float Calculating Slack or Float Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date. Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity). LS – ES: Calculates slack with forward pass LF – EF: Calculates slack with backwards pass Lag Time: Inserted wait time between activities Lead Time: Overlapping activities, also called paralleling or fast tracking. “Lead In; Lag Out” Accuracy of Estimates Order of Magnitude: -25% to +75% Budget Estimate: -10% to +25% Definitive Estimate: -5% to +10% Standard Deviations from the Norm ± 1 σ = 68.26% ± 2 σ = 95.46% ± 3 σ = 99.73% ± 6 σ = 99.99% Powers of a Project Manager 1. Expert: Best, earned on your own 2. Reward: Next best. Based on PM position 3. Formal: Power, based on PM position 4. Referent: Referring to positions of others 5. Penalty: Worst. Based on PM position Conflict Resolution (Best to Worst) 1. Problem Solving: Also called Confronting 2. Compromising: Solutions satisfy both parties 3. Withdrawal: Postponing a decision 4. Smoothing: Emphasis on agreement 5. Forcing: One viewpoint at expense of another. Channels of Communication Between Team Members = N(N-1)/2 Sources of Conflict (Order of Priority) 1. Schedules 2. Project Priorities 3. Resources 4. Technical Opinions 5. Administrative Procedures 6. Cost 7. Personality Herzberg’s Motivators 1. Achievement 2. Recognition 3. Challenge of the work itself 4. Responsibility 5. Advancement 6. Growth Also, remember Maslow’s Hierarchy of Needs Closing Project is closed when administrative closure is complete. Administrative closure is done at end of each Project Phase and at the end of the Project. Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract. Contract Closure Procedure is produced under “Close Project” PMP Test Preparation