Presenter: Barb Waters, MBA, PMP
PMP® Exam Prep 6th Edition: Formulas
Net Present Value (NPV) used for project selection
Always select the project with the highest NPV.
Year 0 Initial Investment
Year 1 + Cash Flow 1 / (1 + Discount Rate) 1
Year 2 + Cash Flow 2 / (1 + Discount Rate) 2
Year 3 + Cash Flow 3 / (1 + Discount Rate) 3
(and so on for as many years as cash flow is given)
Program Evaluation and Review Technique (PERT)
PERT / Weighted Duration / 3-Point estimate
Triangular
distribution
Beta distribution Standard Deviation
[O+ML+P]/3 [O+ (4*ML) +P]/6 SD = (P-O)/6
Only use this if the
question specifies
that all inputs
should be weighted
equally
Default to this unless
question specifies that
all inputs are weighted
equally
Reserve time
Risk Rating (qualitative risk analysis)
Used during qualitative risk analysis
Risk Rating = Probability x Impact
Answer is expressed as a % or decimal
Expected Monetary Value (EMV)
Used during quantitative risk analysis
Expected Monetary Value = Probability x Impact
Answer is expressed as a $ amount
Communication Channels
Number of communication channels = n(n-1)/2
Remember, if you are working with “other” team
members, add 1 to count yourself
If the question asks you “how many more” you will
need to calculate twice. Once for the original state
and once for the new state. Subtract the two values.
Make or Buy Analysis
This is an equation rather than a formula.
Use the equation to find the break-even point.
Cost to Make = Cost to Buy (Lease)
To find the breakeven point, place the cost to make and the cost to buy on either side of the
equation. Solve for X, which is the variable (# of days).
e.g. Initial cost to make + (Daily cost to make* X) = Cost to lease + (Daily cost to lease * X)
Make Lease Total Make Total Lease
Initial Cost $12,000 $2,000 $12,000 $2,000
Day 1 $25 $350 $12,025 $2,350
Day 2 $25 $350 $12,050 $2,700
Day 3 $25 $350 $12,075 $3,050
…
Day 31 $25 $350 $12,775 $12,850
At day 31 the Lease
costs begin to
outstrip the Make
costs – this is the
“breakeven” point
Calculating Float
Float = Late Start - Early Start
(or)
Late Finish – Early Finish
Planned Value (PV)
PV = Budget at Completion * Percent of Time Passed
Earned Value (EV)
EV = Budget at Completion * Percent of Work Completed
Actual Cost (AC)
The amount of money spent on approved project work to-date.
This number is usually given to you. It may also be presented as
Budget at Completion (BAC) – Money Left = AC
Schedule Variance (SV)
SV = Earned Value (EV) – Planned Value (PV)
Schedule Performance Index (SPI)
SPI = Earned Value (EV) /Planned Value (PV)
Cost Variance (CV)
CV = Earned Value (EV) – Actual Cost (AC)
Cost Performance Index (CPI)
CPI= Earned Value (EV) /Actual Cost (AC)
Estimate at Completion (EAC)
There are four different formulas based on different scenarios
Scenario #1: Assumes the same rate of spending will continue
EAC = BAC/CPI
Scenario #2: Assumes you have deviated from the budget due to a one-time incident, but spending would
have otherwise been on track with the plan and will continue at the planned rate going forward
EAC = AC + (BAC – EV), or this formula can be formatted as
EAC = BAC – CV
Scenario #3: Cost performance has been poor and project deadline is firm
EAC = AC + {(BAC-EV)/(CPI x SPI)}
Scenario #4: Assumes the original budget was flawed. The formula considers actual cost, and reassesses
the cost of all remaining work (Estimate to Complete, or ETC).
EAC = AC + ETC
Estimate to Complete (ETC)
ETC = Estimate at Completion (EAC) –Actual Cost (AC)
To Complete Performance Index (TCPI)
“work left” / “money left”
TCPI = (BAC-EV)/ (BAC-AC)
or
TCPI = (BAC-EV)/ (EAC-AC)
Replace BAC with EAC if budget has been rebaselined
Variance at Completion (VAC)
VAC = Budget at Completion (BAC) – Estimate at Completion (EAC)
Burn Rate
Burn Rate = 1/Cost Performance Index (CPI)
Burn rate < 1 means budget is being utilized slower than planned
Burn rate > 1 means budget is being utilized faster than planned

More Related Content

PDF
Formulas for pmp exam
PDF
PM Notebook - Appendix H - Formula Sheet
DOCX
Earned Value AnalysisTracking Project ProgressWh.docx
PPT
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
PPT
Learning pmp formulas the easy way
PPTX
Earned value for pmp and pmi acp exam
PDF
Formula pocket guide
PDF
Pmp formula pocket guide
Formulas for pmp exam
PM Notebook - Appendix H - Formula Sheet
Earned Value AnalysisTracking Project ProgressWh.docx
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
Learning pmp formulas the easy way
Earned value for pmp and pmi acp exam
Formula pocket guide
Pmp formula pocket guide

Similar to PMBOK 6th ed Formulas.pdf (20)

PDF
Pmp formula pocket guide
PDF
Pmp Formula Pocket_Guide
PPT
cost-managementtttttttttttttttttttttttttttttt.ppt
PPTX
Earned Value Analysis
PPTX
Project monitoring & Earned Value Analysis
PPTX
Project Cost Management
PPT
L06 cost management
PDF
Pmp cost chapter 7
PPTX
Earned Value Analysis in construction projects
PPTX
Earned value management (EVM)
PDF
Earned value analysis - presentation
XLS
PMP - Math Formulas
PPT
PMP Exam Formulas To Know
PDF
Formulas for PMP exam
PDF
Earned value management
PPSX
Project Monitoring and Controlling Processes
PPT
Project cost management
PPTX
PMP COST FORMULAE
Pmp formula pocket guide
Pmp Formula Pocket_Guide
cost-managementtttttttttttttttttttttttttttttt.ppt
Earned Value Analysis
Project monitoring & Earned Value Analysis
Project Cost Management
L06 cost management
Pmp cost chapter 7
Earned Value Analysis in construction projects
Earned value management (EVM)
Earned value analysis - presentation
PMP - Math Formulas
PMP Exam Formulas To Know
Formulas for PMP exam
Earned value management
Project Monitoring and Controlling Processes
Project cost management
PMP COST FORMULAE
Ad

Recently uploaded (20)

PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
MSPs in 10 Words - Created by US MSP Network
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PPT
Data mining for business intelligence ch04 sharda
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
Amazon (Business Studies) management studies
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PPTX
HR Introduction Slide (1).pptx on hr intro
PDF
A Brief Introduction About Julia Allison
PDF
Business model innovation report 2022.pdf
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
How to Get Funding for Your Trucking Business
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PDF
WRN_Investor_Presentation_August 2025.pdf
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
MSPs in 10 Words - Created by US MSP Network
Ôn tập tiếng anh trong kinh doanh nâng cao
Data mining for business intelligence ch04 sharda
New Microsoft PowerPoint Presentation - Copy.pptx
ICG2025_ICG 6th steering committee 30-8-24.pptx
Chapter 5_Foreign Exchange Market in .pdf
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Amazon (Business Studies) management studies
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Roadmap Map-digital Banking feature MB,IB,AB
HR Introduction Slide (1).pptx on hr intro
A Brief Introduction About Julia Allison
Business model innovation report 2022.pdf
Power and position in leadershipDOC-20250808-WA0011..pdf
How to Get Funding for Your Trucking Business
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
DOC-20250806-WA0002._20250806_112011_0000.pdf
Reconciliation AND MEMORANDUM RECONCILATION
WRN_Investor_Presentation_August 2025.pdf
Ad

PMBOK 6th ed Formulas.pdf

  • 1. Presenter: Barb Waters, MBA, PMP PMP® Exam Prep 6th Edition: Formulas
  • 2. Net Present Value (NPV) used for project selection Always select the project with the highest NPV. Year 0 Initial Investment Year 1 + Cash Flow 1 / (1 + Discount Rate) 1 Year 2 + Cash Flow 2 / (1 + Discount Rate) 2 Year 3 + Cash Flow 3 / (1 + Discount Rate) 3 (and so on for as many years as cash flow is given)
  • 3. Program Evaluation and Review Technique (PERT) PERT / Weighted Duration / 3-Point estimate Triangular distribution Beta distribution Standard Deviation [O+ML+P]/3 [O+ (4*ML) +P]/6 SD = (P-O)/6 Only use this if the question specifies that all inputs should be weighted equally Default to this unless question specifies that all inputs are weighted equally Reserve time
  • 4. Risk Rating (qualitative risk analysis) Used during qualitative risk analysis Risk Rating = Probability x Impact Answer is expressed as a % or decimal
  • 5. Expected Monetary Value (EMV) Used during quantitative risk analysis Expected Monetary Value = Probability x Impact Answer is expressed as a $ amount
  • 6. Communication Channels Number of communication channels = n(n-1)/2 Remember, if you are working with “other” team members, add 1 to count yourself If the question asks you “how many more” you will need to calculate twice. Once for the original state and once for the new state. Subtract the two values.
  • 7. Make or Buy Analysis This is an equation rather than a formula. Use the equation to find the break-even point. Cost to Make = Cost to Buy (Lease) To find the breakeven point, place the cost to make and the cost to buy on either side of the equation. Solve for X, which is the variable (# of days). e.g. Initial cost to make + (Daily cost to make* X) = Cost to lease + (Daily cost to lease * X) Make Lease Total Make Total Lease Initial Cost $12,000 $2,000 $12,000 $2,000 Day 1 $25 $350 $12,025 $2,350 Day 2 $25 $350 $12,050 $2,700 Day 3 $25 $350 $12,075 $3,050 … Day 31 $25 $350 $12,775 $12,850 At day 31 the Lease costs begin to outstrip the Make costs – this is the “breakeven” point
  • 8. Calculating Float Float = Late Start - Early Start (or) Late Finish – Early Finish
  • 9. Planned Value (PV) PV = Budget at Completion * Percent of Time Passed
  • 10. Earned Value (EV) EV = Budget at Completion * Percent of Work Completed
  • 11. Actual Cost (AC) The amount of money spent on approved project work to-date. This number is usually given to you. It may also be presented as Budget at Completion (BAC) – Money Left = AC
  • 12. Schedule Variance (SV) SV = Earned Value (EV) – Planned Value (PV)
  • 13. Schedule Performance Index (SPI) SPI = Earned Value (EV) /Planned Value (PV)
  • 14. Cost Variance (CV) CV = Earned Value (EV) – Actual Cost (AC)
  • 15. Cost Performance Index (CPI) CPI= Earned Value (EV) /Actual Cost (AC)
  • 16. Estimate at Completion (EAC) There are four different formulas based on different scenarios Scenario #1: Assumes the same rate of spending will continue EAC = BAC/CPI Scenario #2: Assumes you have deviated from the budget due to a one-time incident, but spending would have otherwise been on track with the plan and will continue at the planned rate going forward EAC = AC + (BAC – EV), or this formula can be formatted as EAC = BAC – CV Scenario #3: Cost performance has been poor and project deadline is firm EAC = AC + {(BAC-EV)/(CPI x SPI)} Scenario #4: Assumes the original budget was flawed. The formula considers actual cost, and reassesses the cost of all remaining work (Estimate to Complete, or ETC). EAC = AC + ETC
  • 17. Estimate to Complete (ETC) ETC = Estimate at Completion (EAC) –Actual Cost (AC)
  • 18. To Complete Performance Index (TCPI) “work left” / “money left” TCPI = (BAC-EV)/ (BAC-AC) or TCPI = (BAC-EV)/ (EAC-AC) Replace BAC with EAC if budget has been rebaselined
  • 19. Variance at Completion (VAC) VAC = Budget at Completion (BAC) – Estimate at Completion (EAC)
  • 20. Burn Rate Burn Rate = 1/Cost Performance Index (CPI) Burn rate < 1 means budget is being utilized slower than planned Burn rate > 1 means budget is being utilized faster than planned