PMP Formulas
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
% COMPLETE = EV / BAC x 100
% SPENT = AC / BAC x 100
CV% = CV / EV x 100
SV% = SV / PV x 100
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT α = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = _sum((Pessimistic - Optimistic) / 6)^2
Classes of Estimates
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number.
ROI = Select biggest number.
IRR = Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial
investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Exp. Value = Probability % x Consequence $
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
SIGMA
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Important Values
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; less than the control limits
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical path.
JIT inventory = 0% (or very close to 0%.)
Network Diagram
Forward Pass
ES = EF of the predecessor node
EF = ES + Dur
Backward Pass
LF = LS of the Successor
LS = LF – Dur
Slack = LF – EF = LS – ES
Free Float = ES(Successor) - EF(Predecessor)
You need to understand the terms and the logic relationships between the inputs, outputs and tools&
techniques. Memorizing them is not enough and will lead you nowhere.
Refer to the PMBoK 5h Edition for more details. &
Please do not hesitate to contact me anytime if you have any questions, comments, and feedbacks.
Success is yours,
Prepared By: Amr Miqdadi, PMP
info@pmlead.net
http://www.pmlead.net
PMI®, PMP®, CAPM® and PMBOK® Guide are trademarks of the Project Management Institute, Inc.
PMI® has not endorsed and did not participate in the development of this product.
ES Dur EF
Node
LS Float LF

More Related Content

PDF
Pmp formulas v5
XLS
PMP - Math Formulas
PDF
PMP Exam Formulas
PDF
Pmp Formula Pocket_Guide
PDF
Pmp formulas
PPT
PMP Exam Formulas To Know
PDF
Formulas for pmp exam
PDF
Pmp formulas pmbok6
Pmp formulas v5
PMP - Math Formulas
PMP Exam Formulas
Pmp Formula Pocket_Guide
Pmp formulas
PMP Exam Formulas To Know
Formulas for pmp exam
Pmp formulas pmbok6

What's hot (9)

PDF
Pmp formulas pmbok5
PPTX
Earned Value Management (EVM) Limitations
PDF
Earned value analysis - presentation
PDF
Top metrics for Agile by Priyank
PDF
Earned value in five easy pieces
PPT
EVMS Gold Card
PPTX
Track Project Performance - Earned Value Management
PPTX
C H A P T E R 6 T H E O R Y O F C O S T
PDF
DPPM1
Pmp formulas pmbok5
Earned Value Management (EVM) Limitations
Earned value analysis - presentation
Top metrics for Agile by Priyank
Earned value in five easy pieces
EVMS Gold Card
Track Project Performance - Earned Value Management
C H A P T E R 6 T H E O R Y O F C O S T
DPPM1
Ad

Similar to Pmp formulas (20)

PDF
Pmp formula pocket guide
PDF
Formula pocket guide
PDF
Pmp formula pocket guide
PDF
Pmp formulas
PDF
PMBOK 6th ed Formulas.pdf
PPT
cheat sheet.ppt
PPT
Learning pmp formulas the easy way
PDF
fm_formula__ipcc-2.pdf
PPT
F0dd9 cost
PDF
Arithmetic Basics for banking aspirants in quants
PDF
2018-Level-I-Formula-Sheet-1.pdf
PDF
Important formules for ugc net commerce,management (most important) downl...
PPTX
object oriented programming presentation
PPT
Chapter 7 cost of production
PPT
C++ chapter 2
PPTX
Cost analysis
PPTX
Operators1.pptx
PPTX
Few Operator used in c++
PPTX
Variables, Data Types, Operator & Expression in c in detail
PPT
Programming
Pmp formula pocket guide
Formula pocket guide
Pmp formula pocket guide
Pmp formulas
PMBOK 6th ed Formulas.pdf
cheat sheet.ppt
Learning pmp formulas the easy way
fm_formula__ipcc-2.pdf
F0dd9 cost
Arithmetic Basics for banking aspirants in quants
2018-Level-I-Formula-Sheet-1.pdf
Important formules for ugc net commerce,management (most important) downl...
object oriented programming presentation
Chapter 7 cost of production
C++ chapter 2
Cost analysis
Operators1.pptx
Few Operator used in c++
Variables, Data Types, Operator & Expression in c in detail
Programming
Ad

Recently uploaded (20)

PDF
KodekX | Application Modernization Development
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Encapsulation theory and applications.pdf
PDF
Empathic Computing: Creating Shared Understanding
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
CIFDAQ's Market Insight: SEC Turns Pro Crypto
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PPTX
A Presentation on Artificial Intelligence
PDF
Encapsulation_ Review paper, used for researhc scholars
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPT
Teaching material agriculture food technology
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PDF
Reach Out and Touch Someone: Haptics and Empathic Computing
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PDF
Chapter 3 Spatial Domain Image Processing.pdf
KodekX | Application Modernization Development
“AI and Expert System Decision Support & Business Intelligence Systems”
20250228 LYD VKU AI Blended-Learning.pptx
Encapsulation theory and applications.pdf
Empathic Computing: Creating Shared Understanding
Dropbox Q2 2025 Financial Results & Investor Presentation
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Diabetes mellitus diagnosis method based random forest with bat algorithm
Shreyas Phanse Resume: Experienced Backend Engineer | Java • Spring Boot • Ka...
The AUB Centre for AI in Media Proposal.docx
CIFDAQ's Market Insight: SEC Turns Pro Crypto
The Rise and Fall of 3GPP – Time for a Sabbatical?
A Presentation on Artificial Intelligence
Encapsulation_ Review paper, used for researhc scholars
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Teaching material agriculture food technology
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Reach Out and Touch Someone: Haptics and Empathic Computing
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Chapter 3 Spatial Domain Image Processing.pdf

Pmp formulas

  • 1. PMP Formulas Earned Value CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV / EV x 100 SV% = SV / PV x 100 PERT PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT α = (Pessimistic - Optimistic) / 6 PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 PERT Variance all activities = _sum((Pessimistic - Optimistic) / 6)^2 Classes of Estimates Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0%
  • 2. Project Selection PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Select biggest number. ROI = Select biggest number. IRR = Select biggest number. Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. Exp. Value = Probability % x Consequence $ Communications Communication Channels = n * (n-1) / 2 Probability EMV = Probability * Impact in currency Procurement PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost Depreciation Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th) SIGMA 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.99% Important Values Control Limits = 3 sigma from mean Control Specifications = Defined by customer; less than the control limits Float on the critical path = 0 days
  • 3. Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%.) Network Diagram Forward Pass ES = EF of the predecessor node EF = ES + Dur Backward Pass LF = LS of the Successor LS = LF – Dur Slack = LF – EF = LS – ES Free Float = ES(Successor) - EF(Predecessor) You need to understand the terms and the logic relationships between the inputs, outputs and tools& techniques. Memorizing them is not enough and will lead you nowhere. Refer to the PMBoK 5h Edition for more details. & Please do not hesitate to contact me anytime if you have any questions, comments, and feedbacks. Success is yours, Prepared By: Amr Miqdadi, PMP info@pmlead.net http://www.pmlead.net PMI®, PMP®, CAPM® and PMBOK® Guide are trademarks of the Project Management Institute, Inc. PMI® has not endorsed and did not participate in the development of this product. ES Dur EF Node LS Float LF