SlideShare a Scribd company logo
Schedule Delay Analysis
Jack A. Lazarczyk, CPA, CCC
Senior Consultant
Types of Construction Delay
Basic Distinctions:
• Excusable and Non-Excusable
• Compensable and Non-Compensable
• Concurrent and Non-Concurrent
• Critical versus Non-Critical
Types of Construction Delay
Excusable Delays:
• General labor strikes
• Fires, floods and other natural disasters
• Owner directed changes
• Errors and omissions in the plans and specifications
• Differing site conditions or concealed conditions
• Lack of action by government bodies
• Intervention by outside agencies
Types of Construction Delay
Excusable Delays (defined):
“Excusable delays are caused by conditions that are
reasonably unforseeable and not within the contractor’s
control”
Note: Always check the particular construction contract
documents for valid delay factors and limitations.
Types of Construction Delay
Non-Excusable Delays:
• Late performance of subcontractors
• Late performance by suppliers
• Faulty workmanship by the contractor or subcontractors
• A project specific labor strike caused by either the
contractor’s unwillingness to negotiate or by unfair job
practices
Types of Construction Delay
Non-Excusable Delays:
Again: Verify the particular contract
language for definitions and limitations!
Categories of Delays
Is the delay excusable?
compensable
nonexcusable
Is the delay compensable
noncompensable
excusable
Assess delay
Critical Documentation
As Planned Schedule:
• Detailed Critical Path Method schedule;
or
• Bar chart schedule;
or
• Narrative schedule
Critical Documentation
As Built Schedule:
• Final as-built CPM schedule with periodic updates;
and
• Project daily reports;
• Meeting minutes;
• Inspection reports by the designer, owner, bldg inspector
• Correspondence
• Memos to file
As Planned Schedule
(Sample Project)
As Built Schedule
(Sample Project)
Schedule Analysis Methods
1. As Planned versus As Built Comparison
2. The Impacted As Planned Method
3. Collapsed (But for) As Built Method
4. Contemporaneous Period (Windows)
Analysis
As Planned versus As Built
Comparison
As Planned versus As Built
Comparison
Benefits:
• Simple to Prepare:
168 actual days – 112 planned days = 56 delay days
Shortcomings:
• No information on particular delay events;
• Similar to “Total Cost” approach
Impacted As Planned Method
• Begin with As Planned Schedule
• Add Owner or Contractor Delays
• Compute Owner caused delay and
Contractor caused delay
As Built with Delays
As Planned with Owner Delays
As Planned with Owner Delays
• Total duration of As Built = 168 days
• Total duration of As Planned with Owner Delays = 154
days
• Total duration of original As Planned = 112 days
• The Owner is responsible for the difference between
impacted and the original as planned:
154 – 112 = 42 days
• Contractor is responsible for the remaining difference:
168 – 154 = 14 days
As Planned with Contractor Delays
As Planned with Contractor Delays
• Total duration of As Built = 168 days
• Total duration of As Planned with Contractor Delays =
140 days
• Total duration of original As Planned = 112 days
• The Contractor is responsible for the difference between
impacted and the original as planned:
140 – 112 = 28 days
• The Owner is responsible for the remaining difference:
168 – 140 = 28 days
As Planned Method Discussion
Benefits:
• Relatively simple to implement
• Allows for mitigation of delays
Shortcomings:
• Highly subjective
• Assumes as-planned (baseline) logic holds.
Collapsed (But For) As Built Method
• Begin with As Built Schedule, including;
• Owner and Contractor Delays.
• Remove Owner (Contractor) caused
delays.
• Resulting schedule shows when
Contractor (Owner) would have finished
“but for” Owner (Contractor) delays.
As Built with Delays
Collapsed As Built without (but for)
Owner Delays
Collapsed As Built without (but for)
Owner Delays
• Total duration of As Built = 168 days
• Total duration of Collapsed As Built without Owner’s
Delays = 147 days
• Total duration of original As Planned = 112 days
• The Owner is responsible for the difference between
collapsed as built and the as built schedules:
168 – 147 = 21 days
• The Contractor is responsible for the remaining
difference between collapsed as built and as planned:
147 – 112 = 35 days
Collapsed As Built Discussion
Benefits:
• Very good accuracy
Shortcomings:
• No allowance for mitigation of delays
Contemporaneous Period Analysis
(Windows)
• Begin with As Planned Schedule;
• Select periods (windows) to analyze;
• Enter actual progress and delay activities using
contemporaneous project documents;
• Calculate the schedule;
• Repeat the process for the next window
CPA Method – Window 1
CPA Method – Window 1
• The first update is compared to the original schedule.
• Delays in that period are analyzed using “but for”
method.
• The first update becomes the new baseline for
subsequent window.
• Evaluation of non-excusable, compensable and non-
compensable delays performed at each update
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
CPA Method – Window 2
CPA Method – Window 2
• No delays during 2nd window
• Note activities that were supposed to start by now.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
CPA Method – Window 3
CPA Method – Window 3
• Two overlapping delays
• 2 weeks charged to concurrent delay (excusable and
non-compensable)
• 1 week charged to contractor (non-excusable)
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
CPA Method – Window 4
CPA Method – Window 4
• Contractor-caused delay not on critical path.
• As long as the delay is within available float there is no
effect on the final completion date.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
4 16 154 0 0 0 0
Garage walls delay; not on critical
path.
CPA Method – Window 5
CPA Method – Window 5
• Owner’s delay of 4 weeks in Garage door revision.
• Net change to the project is only 2 weeks; other 2 weeks
absorbed by available float.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
4 16 154 0 0 0 0
Garage walls delay; not on critical
path.
5 20 168 14 0 0 14 Owner's revision to Garage doors
TOTALS 56 7 14 35
Contemporaneous Period Analysis
(Windows) Discussion
Benefits:
• Most accurate results
• Considers dynamic nature of the critical path
Shortcomings
• Time consuming
• Costly to prepare
Comparison of Results
Delays
Method Non Excusable Excusable
Excusable Noncompensable Compensable
Comparison Method (Total Time) 1
56 (0) 0 (56)
Impacted As-Planned (Owner Delays) 14 42
Impacted As-Planned (Contractor Delays) 28 28
Collapsed As-Built (But For) 35 21
Contemporaneous Period (Windows) Analysis 7 14 35
1. Schedule comparison itself does not indicate which party is
responsible for the delay.
Method Selection Criteria
METHOD Data Required Effort/Cost Accuracy Expected
Comparison Method (Total Time) Low $ Poor
Impacted As-Planned (Owner Delays) Moderate $$ Good
Impacted As-Planned (Contractor Delays) Moderate $$ Good
Collapsed As-Built (But For) Above Moderate $$$ Very Good
Contemporaneous Period (Windows) Analysis Extensive $$$$$ Excellent

More Related Content

PDF
A Fresh Take on Project Forensics
PDF
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
PPTX
Eot claims hr__may2012
PDF
Claims
PPTX
Extension of time Analysis
PPTX
3 Refresher Course 3_Time Impact Analysis.pptx
PPTX
Forensic schedule analysis acesss
PPTX
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A Fresh Take on Project Forensics
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
Eot claims hr__may2012
Claims
Extension of time Analysis
3 Refresher Course 3_Time Impact Analysis.pptx
Forensic schedule analysis acesss
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...

Similar to Schedule_Class_Delay Analysis Tutorial to learn (20)

PDF
IRJET- Delay in Construction its Causes and Mitigation: A Review
PDF
Delay Analysis Techniques that is used i
PDF
Delay Analysis in Construction of Redevelopment Residential Project
PPTX
Enhanced_Forensic_Schedule_Analysis_Presentation.pptx
PDF
Concurrent_Delay_Analysis_Best_Practice_1631211329.pdf
PPTX
Quantify Construction Damages related to Delay, disruption, and inefficiencies
PDF
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
PDF
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
PDF
A study on the analysis and evaluation of delays in private construction Proj...
PPTX
Construction Delay Analysis, Simplified
PPTX
Delay analysis of raw water reservoir and pumping Station
PDF
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
PDF
Delay Analysis for an On-Going Residential Project
PPTX
Managing Risk of Delay in Construction Projects Erfan & Basharat.pptx
PDF
Statistical Methods for Construction Delay Analysis
PDF
Causes of delays on Construction Projects in Kuwait according to opinion of e...
PDF
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
PDF
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
PPTX
Extension of time (E.O.T) By Ahmed Ibarhim
PDF
Study on the analysis and evaluation of delays in public sector construction ...
IRJET- Delay in Construction its Causes and Mitigation: A Review
Delay Analysis Techniques that is used i
Delay Analysis in Construction of Redevelopment Residential Project
Enhanced_Forensic_Schedule_Analysis_Presentation.pptx
Concurrent_Delay_Analysis_Best_Practice_1631211329.pdf
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
A study on the analysis and evaluation of delays in private construction Proj...
Construction Delay Analysis, Simplified
Delay analysis of raw water reservoir and pumping Station
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Delay Analysis for an On-Going Residential Project
Managing Risk of Delay in Construction Projects Erfan & Basharat.pptx
Statistical Methods for Construction Delay Analysis
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
Extension of time (E.O.T) By Ahmed Ibarhim
Study on the analysis and evaluation of delays in public sector construction ...
Ad

Recently uploaded (20)

PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
additive manufacturing of ss316l using mig welding
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPT
Project quality management in manufacturing
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Digital Logic Computer Design lecture notes
PDF
PPT on Performance Review to get promotions
PDF
Well-logging-methods_new................
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
bas. eng. economics group 4 presentation 1.pptx
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
additive manufacturing of ss316l using mig welding
Mechanical Engineering MATERIALS Selection
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Project quality management in manufacturing
Arduino robotics embedded978-1-4302-3184-4.pdf
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Operating System & Kernel Study Guide-1 - converted.pdf
Lesson 3_Tessellation.pptx finite Mathematics
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Digital Logic Computer Design lecture notes
PPT on Performance Review to get promotions
Well-logging-methods_new................
Strings in CPP - Strings in C++ are sequences of characters used to store and...
bas. eng. economics group 4 presentation 1.pptx
Ad

Schedule_Class_Delay Analysis Tutorial to learn

  • 1. Schedule Delay Analysis Jack A. Lazarczyk, CPA, CCC Senior Consultant
  • 2. Types of Construction Delay Basic Distinctions: • Excusable and Non-Excusable • Compensable and Non-Compensable • Concurrent and Non-Concurrent • Critical versus Non-Critical
  • 3. Types of Construction Delay Excusable Delays: • General labor strikes • Fires, floods and other natural disasters • Owner directed changes • Errors and omissions in the plans and specifications • Differing site conditions or concealed conditions • Lack of action by government bodies • Intervention by outside agencies
  • 4. Types of Construction Delay Excusable Delays (defined): “Excusable delays are caused by conditions that are reasonably unforseeable and not within the contractor’s control” Note: Always check the particular construction contract documents for valid delay factors and limitations.
  • 5. Types of Construction Delay Non-Excusable Delays: • Late performance of subcontractors • Late performance by suppliers • Faulty workmanship by the contractor or subcontractors • A project specific labor strike caused by either the contractor’s unwillingness to negotiate or by unfair job practices
  • 6. Types of Construction Delay Non-Excusable Delays: Again: Verify the particular contract language for definitions and limitations!
  • 7. Categories of Delays Is the delay excusable? compensable nonexcusable Is the delay compensable noncompensable excusable Assess delay
  • 8. Critical Documentation As Planned Schedule: • Detailed Critical Path Method schedule; or • Bar chart schedule; or • Narrative schedule
  • 9. Critical Documentation As Built Schedule: • Final as-built CPM schedule with periodic updates; and • Project daily reports; • Meeting minutes; • Inspection reports by the designer, owner, bldg inspector • Correspondence • Memos to file
  • 12. Schedule Analysis Methods 1. As Planned versus As Built Comparison 2. The Impacted As Planned Method 3. Collapsed (But for) As Built Method 4. Contemporaneous Period (Windows) Analysis
  • 13. As Planned versus As Built Comparison
  • 14. As Planned versus As Built Comparison Benefits: • Simple to Prepare: 168 actual days – 112 planned days = 56 delay days Shortcomings: • No information on particular delay events; • Similar to “Total Cost” approach
  • 15. Impacted As Planned Method • Begin with As Planned Schedule • Add Owner or Contractor Delays • Compute Owner caused delay and Contractor caused delay
  • 16. As Built with Delays
  • 17. As Planned with Owner Delays
  • 18. As Planned with Owner Delays • Total duration of As Built = 168 days • Total duration of As Planned with Owner Delays = 154 days • Total duration of original As Planned = 112 days • The Owner is responsible for the difference between impacted and the original as planned: 154 – 112 = 42 days • Contractor is responsible for the remaining difference: 168 – 154 = 14 days
  • 19. As Planned with Contractor Delays
  • 20. As Planned with Contractor Delays • Total duration of As Built = 168 days • Total duration of As Planned with Contractor Delays = 140 days • Total duration of original As Planned = 112 days • The Contractor is responsible for the difference between impacted and the original as planned: 140 – 112 = 28 days • The Owner is responsible for the remaining difference: 168 – 140 = 28 days
  • 21. As Planned Method Discussion Benefits: • Relatively simple to implement • Allows for mitigation of delays Shortcomings: • Highly subjective • Assumes as-planned (baseline) logic holds.
  • 22. Collapsed (But For) As Built Method • Begin with As Built Schedule, including; • Owner and Contractor Delays. • Remove Owner (Contractor) caused delays. • Resulting schedule shows when Contractor (Owner) would have finished “but for” Owner (Contractor) delays.
  • 23. As Built with Delays
  • 24. Collapsed As Built without (but for) Owner Delays
  • 25. Collapsed As Built without (but for) Owner Delays • Total duration of As Built = 168 days • Total duration of Collapsed As Built without Owner’s Delays = 147 days • Total duration of original As Planned = 112 days • The Owner is responsible for the difference between collapsed as built and the as built schedules: 168 – 147 = 21 days • The Contractor is responsible for the remaining difference between collapsed as built and as planned: 147 – 112 = 35 days
  • 26. Collapsed As Built Discussion Benefits: • Very good accuracy Shortcomings: • No allowance for mitigation of delays
  • 27. Contemporaneous Period Analysis (Windows) • Begin with As Planned Schedule; • Select periods (windows) to analyze; • Enter actual progress and delay activities using contemporaneous project documents; • Calculate the schedule; • Repeat the process for the next window
  • 28. CPA Method – Window 1
  • 29. CPA Method – Window 1 • The first update is compared to the original schedule. • Delays in that period are analyzed using “but for” method. • The first update becomes the new baseline for subsequent window. • Evaluation of non-excusable, compensable and non- compensable delays performed at each update Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition
  • 30. CPA Method – Window 2
  • 31. CPA Method – Window 2 • No delays during 2nd window • Note activities that were supposed to start by now. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay
  • 32. CPA Method – Window 3
  • 33. CPA Method – Window 3 • Two overlapping delays • 2 weeks charged to concurrent delay (excusable and non-compensable) • 1 week charged to contractor (non-excusable) Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design
  • 34. CPA Method – Window 4
  • 35. CPA Method – Window 4 • Contractor-caused delay not on critical path. • As long as the delay is within available float there is no effect on the final completion date. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design 4 16 154 0 0 0 0 Garage walls delay; not on critical path.
  • 36. CPA Method – Window 5
  • 37. CPA Method – Window 5 • Owner’s delay of 4 weeks in Garage door revision. • Net change to the project is only 2 weeks; other 2 weeks absorbed by available float. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design 4 16 154 0 0 0 0 Garage walls delay; not on critical path. 5 20 168 14 0 0 14 Owner's revision to Garage doors TOTALS 56 7 14 35
  • 38. Contemporaneous Period Analysis (Windows) Discussion Benefits: • Most accurate results • Considers dynamic nature of the critical path Shortcomings • Time consuming • Costly to prepare
  • 39. Comparison of Results Delays Method Non Excusable Excusable Excusable Noncompensable Compensable Comparison Method (Total Time) 1 56 (0) 0 (56) Impacted As-Planned (Owner Delays) 14 42 Impacted As-Planned (Contractor Delays) 28 28 Collapsed As-Built (But For) 35 21 Contemporaneous Period (Windows) Analysis 7 14 35 1. Schedule comparison itself does not indicate which party is responsible for the delay.
  • 40. Method Selection Criteria METHOD Data Required Effort/Cost Accuracy Expected Comparison Method (Total Time) Low $ Poor Impacted As-Planned (Owner Delays) Moderate $$ Good Impacted As-Planned (Contractor Delays) Moderate $$ Good Collapsed As-Built (But For) Above Moderate $$$ Very Good Contemporaneous Period (Windows) Analysis Extensive $$$$$ Excellent