Scope: Mastering 
the 
Fuzzy 
Constraint 
Brad Bigelow 
First delivered to the PMI Global Congress EMEA 2012
Outline 
• Introduction: The Triple Constraints 
• What Makes Scope “Fuzzy”? 
• The Multiple Dimensions of Scope 
• Scope Change: Good or Bad? 
• Looking at Scope Change from Different Angles 
• Conclusion: The Need for Perspective
The Triple Constraint 
Time 
Cost Scope
Or, Put Another Way … 
Pick any two: 
__ Better 
__ Faster 
__ Cheaper
The Triple Constraints 
Project Management, by John Stanley Baumgartner, 1963
Time 
Start 
Planned 
Actual 
Finish 
Start Finish 
Early Late 
200 days 
200 days 
210 days
Cost 
Planned Actual 
Under Over 
$200,000 
$200,000 
$225,000
What is Scope, Anyway? 
“The sum of the products, 
services, and results to be 
provided as a project.” 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Scope? 
Planned Actual 
Under Over 
??? 
What number 
would apply?
How Do You Define the Boundary of 
Scope? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
A Fuzzy Set: Tall Basketball Players 
Manute Bol 
7 ft. 7 in. 
Muggsy Bogues 
5 ft. 3 in. 
Jason Kidd 
6 ft. 4in. 
Dirk Nowitski 
7 ft. 
Josh Howard 
6 ft. 7 in. 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
A Set with a Clear Boundary 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
A Set with a Fuzzy Boundary 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Boundaries Alone Don’t Always Help 
Is the Glass Half Empty? 
Half Full? 
Or is the Glass Too Big? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Three Key Aspects of Scope 
• Output (products, deliverables) 
• Work 
• Boundaries 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Still a Triangle? 
Time 
Cost 
Products 
Work 
Boundaries 
Scope 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Product Breakdown Structure 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Work Breakdown Structure 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Boundaries 
• Authority 
– What Project Manager has authority to decide 
• Legal 
– What means are considered legal? 
• Regulatory 
– Are there health and safety constraints? 
• Interfaces 
– Do the products have to work with other systems? 
• Policy 
– Are there policy constraints on how the work is done? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Still a Triangle? 
Time 
Cost 
Products 
Scope 
Work 
Boundaries 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
And Yet Other Aspects of Scope 
 Quantity 
 Location 
 Functional requirements 
 Non-Functional 
requirements 
 Modes of operation 
 Production methods and 
facilities 
 Test or certification 
requirements 
 Intended users 
 Procurement 
 Transparency 
 Look and feel/Appearance 
 Resources 
 Raw materials 
 Environmental factors 
 Standardization 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Still a Triangle? 
Time 
Cost 
Products 
Scope 
Work 
Boundaries 
Other Factors 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Scope: Mastering the Fuzzy Constraint
How to Tame the Scope Beast 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only 
Presentation Title
MoSCoW Analysis 
• Must Have 
• Should Have 
• Could Have 
• Won’t Have 
Scope 
Definitely In 
Definitely Out 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
The Most Important Aspect of Scope 
Change? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
The Traditional Approach 
#1. 
Plan 
the 
Work 
#2. 
Work 
the 
Plan 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
The Traditional Approach 
Scope Change 
= 
Deviation from the Plan 
Change? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Scope 
Change 
= 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
The Adaptive Approach 
#1. 
Plan 
the 
Work 
#4: Adapt the Plan 
#2. 
Work 
the 
Plan 
#3. 
Compare 
with 
Reality 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Obeng Matrix 
Know What Don’t Know What 
Quest 
Painting by 
Numbers 
Lost in a Fog 
Making a Movie 
Know How Don’t Know How 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Rationale for Change 
Unsound Sound 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Impact of Duration 
Planning Completion 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Impact of Duration 
Planning Completion 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
The Project is Not the Center of the Universe 
You are Here 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Third Law of Motion 
Rejecting a change has a consequence 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only 
Presentation Title
What Happens to Change 
that Falls Out of Scope? 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only
Summary 
• Project Scope is Inherently Fuzzy 
• Break it Down into as Many Aspects as Relevant 
• Find out preference and priorities (MoSCoW) 
• Understand the Appetite for Change 
• Don’t Lose Sight of the Big Picture 
“PMI” is a registered trade and service mark of the Project Management Institute, Inc. 
©2010 Permission is granted to PMI for PMI® Marketplace use only

More Related Content

PDF
SigOpt at Uber Science Symposium - Exploring the spectrum of black-box optimi...
PPTX
Click with Ease
PPT
GOV05-final-ppt
PPT
GOV05-final-ppt
PPTX
PMI Global Congress 2012
PDF
PMI Global Congress North America 2015 - Change the system, not the people.
PDF
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...
PPTX
SigOpt at Uber Science Symposium - Exploring the spectrum of black-box optimi...
Click with Ease
GOV05-final-ppt
GOV05-final-ppt
PMI Global Congress 2012
PMI Global Congress North America 2015 - Change the system, not the people.
Lessons (really) Learned? How to Retain Project Knowledge and Avoid Recurring...

Similar to Scope: Mastering the Fuzzy Constraint (20)

PPTX
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
PPTX
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
PDF
Sneak peek na15 agl01 leading construction industry to lean-agile (leagile)...
PDF
Pmi lebanon conference workshop-initiating proftiable projects-saadi adra
PDF
Managing the People Side of Change: An Applied Framework
PPTX
Project management and organizational change management
PPTX
Managing an ITIL SaaS implementation IT program
PPTX
Agile Collaboration in a Virtual World: Harnessing Social Media, Web 2.0 and ...
PDF
Na15 agl01 leading construction industry to lean-agile (leagile) project ma...
PDF
PMI NA Global congress 2011
PPTX
Gartner BPM Summit Keynote - Adoption Drives ROI
PPT
The Evolving Role of the Business Analyst
PPT
Structuring Iiba For 2010 And Beyond V6 3
PDF
Test Design Essentials for Great Test Automation - Hans
PPT
Ev08 sep17 pmi_virtual_teams(final)1 (2)
PPTX
SFMUG April 2020
PDF
Bridging business analysis and business architecture - The Open Group webinar
PPTX
Spectra Presentation Final
PDF
Silicon Valley Marketo User Group Meeting August 23, 2012
PPTX
AIPMM Webinar: Developing A Compelling Product Business Case
Climbing the Ladder Means Letting Go: Attributes that make you good at one le...
Scheduling Optimization with Line of Balance and Start-to-Finish Relations
Sneak peek na15 agl01 leading construction industry to lean-agile (leagile)...
Pmi lebanon conference workshop-initiating proftiable projects-saadi adra
Managing the People Side of Change: An Applied Framework
Project management and organizational change management
Managing an ITIL SaaS implementation IT program
Agile Collaboration in a Virtual World: Harnessing Social Media, Web 2.0 and ...
Na15 agl01 leading construction industry to lean-agile (leagile) project ma...
PMI NA Global congress 2011
Gartner BPM Summit Keynote - Adoption Drives ROI
The Evolving Role of the Business Analyst
Structuring Iiba For 2010 And Beyond V6 3
Test Design Essentials for Great Test Automation - Hans
Ev08 sep17 pmi_virtual_teams(final)1 (2)
SFMUG April 2020
Bridging business analysis and business architecture - The Open Group webinar
Spectra Presentation Final
Silicon Valley Marketo User Group Meeting August 23, 2012
AIPMM Webinar: Developing A Compelling Product Business Case
Ad

Recently uploaded (20)

PPTX
Improved_Leadership_in_Total_Quality_Lesson.pptx
PDF
CISSP Domain 5: Identity and Access Management (IAM)
PDF
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
PDF
Contemporary management and it's content
PPTX
Mangeroal Finance for Strategic Management
PPTX
Human Resource Management | Introduction,Meaning and Definition
PPTX
BASIC H2S TRAINING for oil and gas industries
PDF
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
PPTX
_ISO_Presentation_ISO 9001 and 45001.pptx
PPTX
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
PPTX
MY GOLDEN RULES la regla de oro jhonatan requena
PPTX
Supervisory Styles and When to Use Them!
PPTX
Effective_communication._(strategy).pptx
PDF
Phillips model training for evaluation pdf
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PDF
The-Power-of-Communication (1).pdf......
PPTX
Human resources management -job perception concept
PDF
1_Corporate Goverance presentation topic
PPTX
Course Overview of the Course Titled.pptx
PDF
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
Improved_Leadership_in_Total_Quality_Lesson.pptx
CISSP Domain 5: Identity and Access Management (IAM)
Maintaining a Quality Culture - Performance Metrics, Best Practices and QMS E...
Contemporary management and it's content
Mangeroal Finance for Strategic Management
Human Resource Management | Introduction,Meaning and Definition
BASIC H2S TRAINING for oil and gas industries
Leveraging Intangible Assets Through Campus Entrepreneurship and Tech Transfer
_ISO_Presentation_ISO 9001 and 45001.pptx
Concluding Session_Wrapup-NA May 5 2024-Oct 10 2025 ZS.pptx
MY GOLDEN RULES la regla de oro jhonatan requena
Supervisory Styles and When to Use Them!
Effective_communication._(strategy).pptx
Phillips model training for evaluation pdf
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
The-Power-of-Communication (1).pdf......
Human resources management -job perception concept
1_Corporate Goverance presentation topic
Course Overview of the Course Titled.pptx
The Sustainable Site: Boosting Productivity in Construction – Pipe Dream or P...
Ad

Scope: Mastering the Fuzzy Constraint

  • 1. Scope: Mastering the Fuzzy Constraint Brad Bigelow First delivered to the PMI Global Congress EMEA 2012
  • 2. Outline • Introduction: The Triple Constraints • What Makes Scope “Fuzzy”? • The Multiple Dimensions of Scope • Scope Change: Good or Bad? • Looking at Scope Change from Different Angles • Conclusion: The Need for Perspective
  • 3. The Triple Constraint Time Cost Scope
  • 4. Or, Put Another Way … Pick any two: __ Better __ Faster __ Cheaper
  • 5. The Triple Constraints Project Management, by John Stanley Baumgartner, 1963
  • 6. Time Start Planned Actual Finish Start Finish Early Late 200 days 200 days 210 days
  • 7. Cost Planned Actual Under Over $200,000 $200,000 $225,000
  • 8. What is Scope, Anyway? “The sum of the products, services, and results to be provided as a project.” “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 9. Scope? Planned Actual Under Over ??? What number would apply?
  • 10. How Do You Define the Boundary of Scope? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 11. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 12. A Fuzzy Set: Tall Basketball Players Manute Bol 7 ft. 7 in. Muggsy Bogues 5 ft. 3 in. Jason Kidd 6 ft. 4in. Dirk Nowitski 7 ft. Josh Howard 6 ft. 7 in. “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 13. A Set with a Clear Boundary “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 14. A Set with a Fuzzy Boundary “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 15. Boundaries Alone Don’t Always Help Is the Glass Half Empty? Half Full? Or is the Glass Too Big? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 16. Three Key Aspects of Scope • Output (products, deliverables) • Work • Boundaries “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 17. Still a Triangle? Time Cost Products Work Boundaries Scope “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 18. Product Breakdown Structure “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 19. Work Breakdown Structure “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 20. Boundaries • Authority – What Project Manager has authority to decide • Legal – What means are considered legal? • Regulatory – Are there health and safety constraints? • Interfaces – Do the products have to work with other systems? • Policy – Are there policy constraints on how the work is done? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 21. Still a Triangle? Time Cost Products Scope Work Boundaries “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 22. And Yet Other Aspects of Scope  Quantity  Location  Functional requirements  Non-Functional requirements  Modes of operation  Production methods and facilities  Test or certification requirements  Intended users  Procurement  Transparency  Look and feel/Appearance  Resources  Raw materials  Environmental factors  Standardization “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 23. Still a Triangle? Time Cost Products Scope Work Boundaries Other Factors “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 25. How to Tame the Scope Beast “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only Presentation Title
  • 26. MoSCoW Analysis • Must Have • Should Have • Could Have • Won’t Have Scope Definitely In Definitely Out “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 27. The Most Important Aspect of Scope Change? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 28. The Traditional Approach #1. Plan the Work #2. Work the Plan “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 29. The Traditional Approach Scope Change = Deviation from the Plan Change? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 30. Scope Change = “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 31. The Adaptive Approach #1. Plan the Work #4: Adapt the Plan #2. Work the Plan #3. Compare with Reality “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 32. Obeng Matrix Know What Don’t Know What Quest Painting by Numbers Lost in a Fog Making a Movie Know How Don’t Know How “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 33. Rationale for Change Unsound Sound “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 34. Impact of Duration Planning Completion “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 35. Impact of Duration Planning Completion “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 36. The Project is Not the Center of the Universe You are Here “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 37. Third Law of Motion Rejecting a change has a consequence “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only Presentation Title
  • 38. What Happens to Change that Falls Out of Scope? “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only
  • 39. Summary • Project Scope is Inherently Fuzzy • Break it Down into as Many Aspects as Relevant • Find out preference and priorities (MoSCoW) • Understand the Appetite for Change • Don’t Lose Sight of the Big Picture “PMI” is a registered trade and service mark of the Project Management Institute, Inc. ©2010 Permission is granted to PMI for PMI® Marketplace use only