Forth Replacement Crossing
relocation of the Port Edgar long sea outfall
by Marcus Black B.Eng (Hons) C.Eng MICE
A
s part of their Forth Replacement Crossing project, Transport Scotland requested that Scottish Water relocate
their infrastructure outwith the construction area for the new Forth Road bridge pier, to mitigate the potential
for damage during construction. Scottish Water approached Grontmij in late 2009 to assist in the investigation,
and undertake the detailed design of a replacement long sea outfall for the existing headworks at Port Edgar, South
Queensferry.
At an early meeting, Transport Scotland indicated their desire that
all works should be completed by the end of December 2010, to
tie in with the bridge construction programme. This milestone
necessitated design completion by the end of December 2009, with
a construction site start planned for summer 2010.
Scottish Water acted as client for the design and construction
works. The scope of the project was fixed to require a ‘like for like
replacement of the existing pipeline, and to ensure no impact on flow,
or detriment to the Port Edgar Marina’.
Background
The existing headworks and long sea outfall at Port Edgar were
constructed in the early 1990s. Through implementation of the
Urban Wastewater Treatment Regulations, Scottish Water later
constructed a new wastewater treatment works outwith the town,
transferring flows from Port Edgar.
Design investigations & development
Prior to undertaking the design of the replacement outfall, Grontmij
undertook substantial investigations to determine and review the
original design parameters. Through review of existing records,
discussions with Scottish Water and former employees of Lothian
Regional Council who had been engaged in the original outfall’s
construction supervision, the following was determined:
•	 The pipe material was a high specification armoured pipeline.
•	 During construction, the installation of the pipeline diffuser
proved onerous, due to the depth of installation, strong
currents and low visibility for divers.
Investigation by the design team indicated that the supply cost of
the armoured pipeline was estimated to be in excess of £1 million. In
addition,duetothespecialistnatureofthepipematerial,therewere
a limited number of vessels available which could undertake the
installation works. With respect to the diffuser end, the limitations
imposed on dive times at the working depth and the information
obtained on the previous construction works, indicated that health
and safety would play a significant part in the development of the
design to mitigate risks to construction operatives.
Further investigations were carried out with Scottish Water to
understand the reasons behind the original material selection,
however these proved inconclusive. Text books which contained
sections on the original installation and individual recollections
were at times conflicting.
Wastewater Treatment & Sewerage
Page 132	 UK Water Projects 2011
Concrete block mattress on barge prior to installation		 Courtesy of Scottish Water
Wastewater Treatment & Sewerage
UK Water Projects 2011 										 Page 133
The design team later determined that a combination of the
original method of installation (reel barge), which induces high
tensile forces, and the relatively untested nature of HDPE pipelines
in the early 1990s, were the most likely reasons for their selection.
As such, it was considered that a replacement pipeline constructed
from HDPE would yield significant costs savings, and leave the
installation methodology open, thereby reducing the risk of lack of
availability of installation vessels.
Single pipe solution
Following review of the existing twin pipeline and diffuser
arrangement and, with health and safety at the forefront, the design
team reviewed the pipeline hydraulics and proposed a single pipe
solution, as this would result in minimal diving requirements, and
in improved buildability.
From a review of bathymetric survey information, beyond 400m
from the shoreline the ground profile drops substantially, from
MLWS at -2.15m AOD to the discharge point at -30m AOD. At the
discharge point the profile remains relatively steep, however the
design incorporated a localised rock platform to flatten this section
and elevate the diffuser above the seabed, thereby reducing the
risk of sediment deposition.
The result of the change to the single pipe solution, and removal
of the complex diffuser arrangement, led to a reduced need for
potentially dangerous diving operations, and thereby substantially
mitigated health and safety risks during construction.
Following agreement from key Scottish Water stakeholders to the
single pipe option, the design progressed with the following key
activities being carried out:
•	 Geotechnical desk study utilising historical data and data
obtained from the bridge investigation works.
•	 Hydrodynamic modelling to prove no detriment in water
quality.
•	 Pipeline hydraulics. An existing hydraulic profile was not
available, therefore the system design was undertaken to
match an assessment made of existing system losses.
•	 Calculation of wave forces in the intertidal zone to consider
suitable pipeline protection.
•	 Development of the pipeline profile and backfill specification.
Undertakings
The tender design was completed in December 2009 and, following
approvalofcostestimatesbyScottishWaterandTransportScotland,
the contract was awarded to Farrans Construction in spring 2010.
Farrans engaged Grontmij to undertake finalisation of the detail
design. Through the incorporation of early Value Engineering,
Farrans identified further potential costs savings and programme
efficiencies through the use of concrete mattress protection below
the intertidal zone, and optimisation of excavations and backfill.
Construction works progressed through the summer, with the
pipeline being installed using conventional lay barge techniques.
The works was undertaken by AMC Subsea, a subcontractor
experienced in outfall construction, and completion was achieved
on programme in September 2010.
Despite the challenging design and construction programme,
the project highlighted the benefits of developing a thorough
understanding of the historical context, and the development
of the existing works, which when allied with appropriate Value
Engineering and scope challenge, can produce substantial cost
savings.
The Editor & Publishers wish to thank Marcus Black, Technical
Manager with Grontmij, for preparing the above article for
publication.
Installation of concrete block mattress to pipeline below MLWS		 Courtesy of Scottish Water

More Related Content

PDF
Subsea Pipeline Engineering
PDF
Submarine outfalls & intakes ppt
PDF
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
PDF
Tyler Hall - Project Experience
PDF
East Java Gas Pipeline
PPSX
Aoil profile 2016
PDF
Water dam versus Tailing Dam
PDF
2012 Network design
Subsea Pipeline Engineering
Submarine outfalls & intakes ppt
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
Tyler Hall - Project Experience
East Java Gas Pipeline
Aoil profile 2016
Water dam versus Tailing Dam
2012 Network design

What's hot (20)

PPT
Dubaidib Wellfield Sdc Presentation July2011
PPTX
modeling and analysis of subsea pipeline by fem
PDF
Contech DuroMaxx Steel Reinforced Polyethylene
PDF
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
PDF
OGJ Nordstream
PPTX
Doug Thiessen Outlook 2012
PPTX
Design of an Export Pipeline
PPTX
General Flood Resistant Bridge Design Guidelines
KEY
Exploring Tight Gas Reservoir Using Intelligent Well Technology
PDF
2016-07-28 Martin Jacobs
PDF
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
PDF
Flood Resistant Bridge Design in PNG rev0117 draft
PPTX
Case study on underwater pipieline leaks and its environmental impacts
DOC
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
PDF
Flood alleviationbrief170214
PDF
2000_Charleston_cement
DOCX
BLASE TOWNSING CV 2015
PDF
Nuts and Bolts of Restoration Implementation
PDF
Il materiale - CIPP, Timo Münstermann
Dubaidib Wellfield Sdc Presentation July2011
modeling and analysis of subsea pipeline by fem
Contech DuroMaxx Steel Reinforced Polyethylene
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
OGJ Nordstream
Doug Thiessen Outlook 2012
Design of an Export Pipeline
General Flood Resistant Bridge Design Guidelines
Exploring Tight Gas Reservoir Using Intelligent Well Technology
2016-07-28 Martin Jacobs
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
Flood Resistant Bridge Design in PNG rev0117 draft
Case study on underwater pipieline leaks and its environmental impacts
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
Flood alleviationbrief170214
2000_Charleston_cement
BLASE TOWNSING CV 2015
Nuts and Bolts of Restoration Implementation
Il materiale - CIPP, Timo Münstermann
Ad

Viewers also liked (9)

PPTX
SlideShow
PPT
Class #04
PPT
Class #05
PPTX
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
PPTX
English, a l'educació infantil
PPTX
Farmprojectslidehsow
PDF
World of Creative Designer & Front-end-Developer
PDF
Pakaagee
PPTX
Marine structures
SlideShow
Class #04
Class #05
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
English, a l'educació infantil
Farmprojectslidehsow
World of Creative Designer & Front-end-Developer
Pakaagee
Marine structures
Ad

Similar to Scottish_Forth_Crossing_2011 (20)

PDF
Scoping study for the installation of floating tidal stream in the Pentland F...
PDF
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
PDF
Overview
PDF
Installation challenges
PDF
Does Australia really need a pipeline repair club.... or are we the lucky cou...
DOCX
CHUKWURA ASHIMEDUA IFECHUKWUDE CV FOR LINKEDIN
PPTX
Richard Turnbull CV Supplement 2012
PDF
My university projects
PDF
Nisqually Delta Sediment Budget & Transport Dynamics
PDF
watercooling
PDF
Leffler 2003 deepwater petroleum exploration
PDF
HSH Elevated Highspeed Rail Proposal for Egypt 29January2018.pdf
DOCX
Asdso
PDF
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
PDF
Curricula Vitae - NVB
PDF
Sustinable Mainatenace of Navigation Channel
PDF
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway Authority
PDF
UKWP Case study - Mauchline Final copy 23 06 15
PPT
Mod subaqueous flowtite
PDF
26-grover-john-final
Scoping study for the installation of floating tidal stream in the Pentland F...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Overview
Installation challenges
Does Australia really need a pipeline repair club.... or are we the lucky cou...
CHUKWURA ASHIMEDUA IFECHUKWUDE CV FOR LINKEDIN
Richard Turnbull CV Supplement 2012
My university projects
Nisqually Delta Sediment Budget & Transport Dynamics
watercooling
Leffler 2003 deepwater petroleum exploration
HSH Elevated Highspeed Rail Proposal for Egypt 29January2018.pdf
Asdso
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Curricula Vitae - NVB
Sustinable Mainatenace of Navigation Channel
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway Authority
UKWP Case study - Mauchline Final copy 23 06 15
Mod subaqueous flowtite
26-grover-john-final

More from Mike Bisland (6)

PDF
B96-BULK-JETTY-DUBLIN-PORT
PDF
CORE LOC_Brochure_2015
PDF
Newbiggin_02
PDF
Anstruther Pier
PDF
Marine_Brochure_For_Web
PPTX
JAT4 Kick off Introduction - UAE Navy
B96-BULK-JETTY-DUBLIN-PORT
CORE LOC_Brochure_2015
Newbiggin_02
Anstruther Pier
Marine_Brochure_For_Web
JAT4 Kick off Introduction - UAE Navy

Scottish_Forth_Crossing_2011

  • 1. Forth Replacement Crossing relocation of the Port Edgar long sea outfall by Marcus Black B.Eng (Hons) C.Eng MICE A s part of their Forth Replacement Crossing project, Transport Scotland requested that Scottish Water relocate their infrastructure outwith the construction area for the new Forth Road bridge pier, to mitigate the potential for damage during construction. Scottish Water approached Grontmij in late 2009 to assist in the investigation, and undertake the detailed design of a replacement long sea outfall for the existing headworks at Port Edgar, South Queensferry. At an early meeting, Transport Scotland indicated their desire that all works should be completed by the end of December 2010, to tie in with the bridge construction programme. This milestone necessitated design completion by the end of December 2009, with a construction site start planned for summer 2010. Scottish Water acted as client for the design and construction works. The scope of the project was fixed to require a ‘like for like replacement of the existing pipeline, and to ensure no impact on flow, or detriment to the Port Edgar Marina’. Background The existing headworks and long sea outfall at Port Edgar were constructed in the early 1990s. Through implementation of the Urban Wastewater Treatment Regulations, Scottish Water later constructed a new wastewater treatment works outwith the town, transferring flows from Port Edgar. Design investigations & development Prior to undertaking the design of the replacement outfall, Grontmij undertook substantial investigations to determine and review the original design parameters. Through review of existing records, discussions with Scottish Water and former employees of Lothian Regional Council who had been engaged in the original outfall’s construction supervision, the following was determined: • The pipe material was a high specification armoured pipeline. • During construction, the installation of the pipeline diffuser proved onerous, due to the depth of installation, strong currents and low visibility for divers. Investigation by the design team indicated that the supply cost of the armoured pipeline was estimated to be in excess of £1 million. In addition,duetothespecialistnatureofthepipematerial,therewere a limited number of vessels available which could undertake the installation works. With respect to the diffuser end, the limitations imposed on dive times at the working depth and the information obtained on the previous construction works, indicated that health and safety would play a significant part in the development of the design to mitigate risks to construction operatives. Further investigations were carried out with Scottish Water to understand the reasons behind the original material selection, however these proved inconclusive. Text books which contained sections on the original installation and individual recollections were at times conflicting. Wastewater Treatment & Sewerage Page 132 UK Water Projects 2011 Concrete block mattress on barge prior to installation Courtesy of Scottish Water
  • 2. Wastewater Treatment & Sewerage UK Water Projects 2011 Page 133 The design team later determined that a combination of the original method of installation (reel barge), which induces high tensile forces, and the relatively untested nature of HDPE pipelines in the early 1990s, were the most likely reasons for their selection. As such, it was considered that a replacement pipeline constructed from HDPE would yield significant costs savings, and leave the installation methodology open, thereby reducing the risk of lack of availability of installation vessels. Single pipe solution Following review of the existing twin pipeline and diffuser arrangement and, with health and safety at the forefront, the design team reviewed the pipeline hydraulics and proposed a single pipe solution, as this would result in minimal diving requirements, and in improved buildability. From a review of bathymetric survey information, beyond 400m from the shoreline the ground profile drops substantially, from MLWS at -2.15m AOD to the discharge point at -30m AOD. At the discharge point the profile remains relatively steep, however the design incorporated a localised rock platform to flatten this section and elevate the diffuser above the seabed, thereby reducing the risk of sediment deposition. The result of the change to the single pipe solution, and removal of the complex diffuser arrangement, led to a reduced need for potentially dangerous diving operations, and thereby substantially mitigated health and safety risks during construction. Following agreement from key Scottish Water stakeholders to the single pipe option, the design progressed with the following key activities being carried out: • Geotechnical desk study utilising historical data and data obtained from the bridge investigation works. • Hydrodynamic modelling to prove no detriment in water quality. • Pipeline hydraulics. An existing hydraulic profile was not available, therefore the system design was undertaken to match an assessment made of existing system losses. • Calculation of wave forces in the intertidal zone to consider suitable pipeline protection. • Development of the pipeline profile and backfill specification. Undertakings The tender design was completed in December 2009 and, following approvalofcostestimatesbyScottishWaterandTransportScotland, the contract was awarded to Farrans Construction in spring 2010. Farrans engaged Grontmij to undertake finalisation of the detail design. Through the incorporation of early Value Engineering, Farrans identified further potential costs savings and programme efficiencies through the use of concrete mattress protection below the intertidal zone, and optimisation of excavations and backfill. Construction works progressed through the summer, with the pipeline being installed using conventional lay barge techniques. The works was undertaken by AMC Subsea, a subcontractor experienced in outfall construction, and completion was achieved on programme in September 2010. Despite the challenging design and construction programme, the project highlighted the benefits of developing a thorough understanding of the historical context, and the development of the existing works, which when allied with appropriate Value Engineering and scope challenge, can produce substantial cost savings. The Editor & Publishers wish to thank Marcus Black, Technical Manager with Grontmij, for preparing the above article for publication. Installation of concrete block mattress to pipeline below MLWS Courtesy of Scottish Water