DEPD-PKT Software Team Process Improvement
I. Background
II. Current Situation
III. Proposed Countermeasure
IV. Schedule
Challenging PE
Business Plan
PKT Applications are a
Workforce Multiplier for PE
PKT
Apps
BuILD * ADTS * CBR * AMS * PSCS
PE T/Ms
PKT’s Software Team is Small
5 Contract
Software
Engineers
1 Specialist
Project Manager
Manpower is increasing, but demand is increasing faster.
Not
Sustainable
Customers
PJT Schedule
Management
?
Poor Visibility
of StatusDelays in
Delivery
PKT
BB
CC
AA
DD
Capacity
Control of Work
• Flow to Rank A work
• Ensure best quality
• Share best practices
• Cross-train
Customer Satisfaction, Visibility, and Accurate Time Est.
PJT
1
PJT
2
+400%
-400%
Traditional PJT estimation:
Accurate to +/- 400% at PJT start
´delivery is often late!
time
accuracy
Agile Values – set forth in the Agile Manifesto
´very short feedback cycles (PDCA)
´every cycle ends with a “shippable” product
Scrum is an agile method of project management
Workload for the
division is
increasing over the
next 3 years
CapacityControlofW
ork
Agility
Cust.Satisfaction
VisibilityAccurateTim
e
Est.
Single-Developer X â â
Team Growth
to team of 4
X â X
Formalized Project
Intake Process â X X
Customer-Focused
Project Mgmt â Current
BB
CC
AA
DD
One developer per PJT.
Can’t easily:
Prioritized
Product
Backlog
Sprint
Backlog
1d
1-2
weeks
Working
Product
Sprint
Daily
Scrum
Customer Feedback
Sprint
Planning
http://fast.wistia.net/embed/iframe/p7novk9lc6
Benefits of Scrum
1 “Embracing Agile,” Harvard Business Review, May 2016, https://hbr.org/2016/05/embracing-agile
2 “Scrum Metrics for Hyperproductinve Teams,” http://tinyurl.com/jxyf7qv
Velocity = amount of work
completed per sprint.
John Deere saw 200%
velocity increase w/ Scrum1
Scrum teams given a proper level of coaching
average 300% to 400% increase in velocity2
$$$$ $$$$
Currently
$$$$$$
In Annual
Business Value
$$$$
Classroom
training
Team
Coaching
Coaching for
Launch Planning
Total Cost: $$$$
(included in DEPD FY17 budget)
June 23-24 & July 7-8 June 23-24 & July 7-8 July 11 – August 19
New PKT Apps
200%
Increase
In Velocity
+ =
1300%
First Year
ROI
Mike Tromans
TEMA VPE-DEPD
June 6, 2016
Plan Do
Traditional Agile/Scrum
PGM MGR A/M
06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
November December JanuaryJune July August September October
Product Owner Training
Team Training
Launch Planning
Inception (Scrum Team Launch)
Coaching
Reflection
Yokoten Plan Starting with PKT Scrum Team #2
x =
Current
## Days Late!
Current
Average:
## Days Late!
##
##
##

More Related Content

PDF
Graphing stata (2 hour course)
PDF
Low Power Design Verification of Complex Chips
PDF
Operation of Sterility Testing Isolators and validation issues
PDF
Classical and Modern Control Theory
PPTX
Contoh untuk pptx PPS PAP akreditasi 2024
PPTX
CMII & Agile: There's a better way to do it - let's find it
PPTX
Agile 2013 presentation, tom grant
PDF
6.2 Cross-Functional Team Framework - v2.0
Graphing stata (2 hour course)
Low Power Design Verification of Complex Chips
Operation of Sterility Testing Isolators and validation issues
Classical and Modern Control Theory
Contoh untuk pptx PPS PAP akreditasi 2024
CMII & Agile: There's a better way to do it - let's find it
Agile 2013 presentation, tom grant
6.2 Cross-Functional Team Framework - v2.0

Similar to Scrum Proposal A3 - For External Distribution (20)

PDF
From 0 to 100 coaching 100+ teams in an agile transformation by Tolga Kombak...
PDF
A Very Large Enterprise Agile Transformation: Lessons Learned at Salesforce
PPTX
Agile Project Management Workshop.pptx
PDF
Enterprise Agile - Hybrid of Methods
PPTX
Erhan koseoglu Delighting vodafone turkey's customers via agile transformation
PDF
Discovering Scrum in Lisbon, Portugal
PDF
PDF
Agile Transformation - 4 Suggestions & Discussion
PDF
Introducing the Enterprise Transformation Meta Model
PDF
Scrum Checklist
PPTX
Introduction to Design Thinking & Correlation to Scrum
PDF
ANIn Coimbatore May 2023 | Agile and Beyond by Nithya Sitharam
PPTX
Oct 2012 Presentation for Agile NJ
PPTX
ANIn Coimbatore March 2023 | Agile-Making Product Development Better by Sarad...
PDF
Agile and scrum masterclass: review
PDF
Agility Transformations - Learn, Plan, Go!
PPTX
Agile-transformation&metrics
PPTX
Agile transformation by Gnanasambandham anbazhagan
From 0 to 100 coaching 100+ teams in an agile transformation by Tolga Kombak...
A Very Large Enterprise Agile Transformation: Lessons Learned at Salesforce
Agile Project Management Workshop.pptx
Enterprise Agile - Hybrid of Methods
Erhan koseoglu Delighting vodafone turkey's customers via agile transformation
Discovering Scrum in Lisbon, Portugal
Agile Transformation - 4 Suggestions & Discussion
Introducing the Enterprise Transformation Meta Model
Scrum Checklist
Introduction to Design Thinking & Correlation to Scrum
ANIn Coimbatore May 2023 | Agile and Beyond by Nithya Sitharam
Oct 2012 Presentation for Agile NJ
ANIn Coimbatore March 2023 | Agile-Making Product Development Better by Sarad...
Agile and scrum masterclass: review
Agility Transformations - Learn, Plan, Go!
Agile-transformation&metrics
Agile transformation by Gnanasambandham anbazhagan
Ad

Scrum Proposal A3 - For External Distribution

  • 1. DEPD-PKT Software Team Process Improvement I. Background II. Current Situation III. Proposed Countermeasure IV. Schedule Challenging PE Business Plan PKT Applications are a Workforce Multiplier for PE PKT Apps BuILD * ADTS * CBR * AMS * PSCS PE T/Ms PKT’s Software Team is Small 5 Contract Software Engineers 1 Specialist Project Manager Manpower is increasing, but demand is increasing faster. Not Sustainable Customers PJT Schedule Management ? Poor Visibility of StatusDelays in Delivery PKT BB CC AA DD Capacity Control of Work • Flow to Rank A work • Ensure best quality • Share best practices • Cross-train Customer Satisfaction, Visibility, and Accurate Time Est. PJT 1 PJT 2 +400% -400% Traditional PJT estimation: Accurate to +/- 400% at PJT start ´delivery is often late! time accuracy Agile Values – set forth in the Agile Manifesto ´very short feedback cycles (PDCA) ´every cycle ends with a “shippable” product Scrum is an agile method of project management Workload for the division is increasing over the next 3 years CapacityControlofW ork Agility Cust.Satisfaction VisibilityAccurateTim e Est. Single-Developer X â â Team Growth to team of 4 X â X Formalized Project Intake Process â X X Customer-Focused Project Mgmt â Current BB CC AA DD One developer per PJT. Can’t easily: Prioritized Product Backlog Sprint Backlog 1d 1-2 weeks Working Product Sprint Daily Scrum Customer Feedback Sprint Planning http://fast.wistia.net/embed/iframe/p7novk9lc6 Benefits of Scrum 1 “Embracing Agile,” Harvard Business Review, May 2016, https://hbr.org/2016/05/embracing-agile 2 “Scrum Metrics for Hyperproductinve Teams,” http://tinyurl.com/jxyf7qv Velocity = amount of work completed per sprint. John Deere saw 200% velocity increase w/ Scrum1 Scrum teams given a proper level of coaching average 300% to 400% increase in velocity2 $$$$ $$$$ Currently $$$$$$ In Annual Business Value $$$$ Classroom training Team Coaching Coaching for Launch Planning Total Cost: $$$$ (included in DEPD FY17 budget) June 23-24 & July 7-8 June 23-24 & July 7-8 July 11 – August 19 New PKT Apps 200% Increase In Velocity + = 1300% First Year ROI Mike Tromans TEMA VPE-DEPD June 6, 2016 Plan Do Traditional Agile/Scrum PGM MGR A/M 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 November December JanuaryJune July August September October Product Owner Training Team Training Launch Planning Inception (Scrum Team Launch) Coaching Reflection Yokoten Plan Starting with PKT Scrum Team #2 x = Current ## Days Late! Current Average: ## Days Late! ## ## ##