             Project evaluation – for the buyer, and for
             the vendor


             Prof. Dr. Thomas Bäck




System‘s Development and Project Management - Prof. Dr. Thomas Bäck   1
Leiden Institute of Advanced Computer Science


   0. Select project
                  1. Identify project objectives                      0. Select Project         2. Identify project infrastructure




                                                             3. Analyze pr. characteristics


                                                          4. Identify products and activities
                                Review lower
                                level detail
                                                             5. Estimate effort for activity
                                                                                                     For each activity

                                                                6. Identify activity risks


               10. Lower level planning                           7. Allocate resources


                    9. Execute plan                            8. Review / publicize plan




System‘s Development and Project Management - Prof. Dr. Thomas Bäck                                                        2
Leiden Institute of Advanced Computer Science




   Cost-benefit analysis
                !   Idea: If project requires investment, as a minimum, the project
                    must provide a greater benefit than putting that investment in a
                    bank account.
                !   Identify and estimate all costs and benefits of carrying out the
                    project and operating the system.
                !   Express costs and benefits in common units.

                •  Costs:                                             •  Benefits:
                    –  Development costs                                  –  Direct benefits
                    –  Setup costs                                        –  Assessable indirect benefits
                    –  Operational costs                                  –  Intangible benefits


                  Relatively easy to quantify                              Often difficult to quantify

System‘s Development and Project Management - Prof. Dr. Thomas Bäck                                      3
Leiden Institute of Advanced Computer Science



   Cash flow forecasting
                A typical product life cycle cash flow
                  Expenditure Income




                                                                              Time




System‘s Development and Project Management - Prof. Dr. Thomas Bäck              4
Leiden Institute of Advanced Computer Science


   Cash flow forecasting
                Four project examples:
                  Year                   Project 1               Project 2         Project 3     Project 4

                  0                             -100,000              -1,000,000      -100,000      -120,000

                  1                                10,000               200,000         30,000        30,000

                  2                                10,000               200,000         30,000        30,000

                  3                                10,000               200,000         30,000        30,000

                  4                                20,000               200,000         30,000        30,000

                  5                              100,000                300,000         30,000        75,000

                  Net profit                       50,000               100,000         50,000        75,000


System‘s Development and Project Management - Prof. Dr. Thomas Bäck                                          5
Leiden Institute of Advanced Computer Science




   Cost-benefit evaluation
           1.  Net profit
                  •      Difference between total costs and total income over the life of the
                         project
           2.  Payback period
                  •      Time to brake even or pay back the initial investment
           3.  Return on investment (ROI)
                  •      Net profitability of the investment required

                                          avg _ annual _ profit
                                    ROI =                       ⋅100%
                                           total _ investment

                  •      Popular, but: Takes no account of timing of cash flows !
           4.  Net present value
           5.  Internal rate of return

System‘s Development and Project Management - Prof. Dr. Thomas Bäck                         6
Leiden Institute of Advanced Computer Science




   Cost-benefit evaluation (cont‘d)
                Net present value
                        •     Considers profitability and cash flow timing
                        •     Discounting future cash flows by discount rate

                Present value of any future cash flow:

                                                           value _ in _ year   t
                               present _ value =
                                                                  (1 + r )t

                r: discount rate, t: number of years in future




System‘s Development and Project Management - Prof. Dr. Thomas Bäck                7
Leiden Institute of Advanced Computer Science


   Net present value: example
                Applying discount factors to project 1
                   Year        Project 1 cash                         Discount factor 10%    Discounted cash
                               flow                                                          flow
                   0                              -100,000                          1.0000            -100,000

                   1                                 10,000                         0.9091                 9,091

                   2                                 10,000                         0.8264                 8,264

                   3                                 10,000                         0.7513                 7,513

                   4                                 20,000                         0.6830                13,660

                   5                               100,000                          0.6209                62,090

                   Net                               50,000                                        NPV:        618
                   profit

System‘s Development and Project Management - Prof. Dr. Thomas Bäck                                        8
Leiden Institute of Advanced Computer Science



   Internal Rate of Return
               NPV is not directly comparable with earnings from other investments !
               IRR: Profitability measure directly comparable with interest rates
               IRR = percentage discount rate that would produce NPV = 0

           6000
                NPV




                            8                                     10   12 Discount rate (%)

          -6000




               Calculate NPV for two discount rates; plot gives IRR (10.25%)

System‘s Development and Project Management - Prof. Dr. Thomas Bäck                   9
Leiden Institute of Advanced Computer Science



                                                     Project cash flow treated as an investment at 10%
   IRR: Example
                   Year           Project             Capital at          Interest   Capital at   End of
                                cash flow              start of            during     end of       year
                                 forecast               year                year       year     withdrawal
                   0               -100,000                           -          -           -           -

                   1                  10,000              100,000          10,000      110,000      10,000

                   2                  10,000              100,000          10,000      110,000      10,000

                   3                  10,000              100,000          10,000      110,000      10,000

                   4                  20,000              100,000          10,000      110,000      20,000

                   5                  99,000                90,000           9,000      99,000      99,000

                   6                            0                     0          0           0          0

System‘s Development and Project Management - Prof. Dr. Thomas Bäck                                     10

More Related Content

PPTX
Managing Innovation_Introduction to Innovation
PPTX
Managing Innovation_innovation concepts
PDF
Requirements Engineering - Werkcollege 2012: 05-Estimating+Planning
PPTX
Managing Innovation_innovation system
PDF
SDPM - Lecture 4a - MS Project – High Level Introduction
PPTX
Session02 innovation concepts
PDF
Research Seminar - Thesis Projects for ICTiB
PDF
SDPM - Lecture 4 - Activity planning and resource allocation
Managing Innovation_Introduction to Innovation
Managing Innovation_innovation concepts
Requirements Engineering - Werkcollege 2012: 05-Estimating+Planning
Managing Innovation_innovation system
SDPM - Lecture 4a - MS Project – High Level Introduction
Session02 innovation concepts
Research Seminar - Thesis Projects for ICTiB
SDPM - Lecture 4 - Activity planning and resource allocation

Viewers also liked (19)

PDF
SDPM - Lecture 6 - Risk management and project escalation
PPTX
Managing Innovation_entrepreneurship and transformation
PPTX
Managing Innovation_organization of innovation
PDF
SDPM - Lecture 8 - Software quality assurance
PDF
SDPM - Lecture 1 - Introduction
PPTX
Session04 innovation system
PPT
Managing Innovation_innovation governance
PPTX
Session08 entrepreneurship andtransformation
PPTX
Session03 organization ofinnovation
PPT
Session05 innovation governance
PDF
SDPM - Lecture 5 - Software effort estimation
PPT
Session09 corporate andsocialentrepreneurship
PPT
Session06 introduction totheoryofentrepreneurship
PDF
SDPM - Lecture 10 - Contract management
PPT
Session01 innovation introduction
PDF
SDPM - Lecture 7 - Project monitoring and control
PDF
SDPM - Lecture 3 - Selecting an appropriate software development approach.pdf
PDF
SDPM - Lecture 9 - Managing people and organizing teams
PDF
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 6 - Risk management and project escalation
Managing Innovation_entrepreneurship and transformation
Managing Innovation_organization of innovation
SDPM - Lecture 8 - Software quality assurance
SDPM - Lecture 1 - Introduction
Session04 innovation system
Managing Innovation_innovation governance
Session08 entrepreneurship andtransformation
Session03 organization ofinnovation
Session05 innovation governance
SDPM - Lecture 5 - Software effort estimation
Session09 corporate andsocialentrepreneurship
Session06 introduction totheoryofentrepreneurship
SDPM - Lecture 10 - Contract management
Session01 innovation introduction
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 3 - Selecting an appropriate software development approach.pdf
SDPM - Lecture 9 - Managing people and organizing teams
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
Ad

Similar to SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor (20)

PDF
Micro Focus - Not only Cobol
PPTX
SPM Evaluation
DOCX
ERP/SAP Project Charter
PDF
20130411 velvet gloveagile
PPTX
Agility : a Velvet Glove in an Iron FIst
PPT
Project management
PDF
Economics of project evaluation for reference cpm module2
PPTX
Project management for the supply management professional rev. 5 13-13
PPT
Project_selectionProject_selectionnn.ppt
PPT
Project Management - Introduction
PPTX
Cloud project secrets of success
PDF
ESEconf2011 - Kaiser Traian: "How to measure productivity in software develop...
PDF
Gert Vilhelmballing | OIS 2012 | Como construir ambientes de transferência de...
PPTX
Sitex orbis a case study
PPTX
PETROLEUM PROJECT MANAGEMENT COURSE PART ONE.pptx
PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PDF
20130821 agility an_iron_fist_in_a_velvet_glove
PPT
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
DOCX
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
PDF
Open source for higher education
Micro Focus - Not only Cobol
SPM Evaluation
ERP/SAP Project Charter
20130411 velvet gloveagile
Agility : a Velvet Glove in an Iron FIst
Project management
Economics of project evaluation for reference cpm module2
Project management for the supply management professional rev. 5 13-13
Project_selectionProject_selectionnn.ppt
Project Management - Introduction
Cloud project secrets of success
ESEconf2011 - Kaiser Traian: "How to measure productivity in software develop...
Gert Vilhelmballing | OIS 2012 | Como construir ambientes de transferência de...
Sitex orbis a case study
PETROLEUM PROJECT MANAGEMENT COURSE PART ONE.pptx
MG6088 SOFTWARE PROJECT MANAGEMENT
20130821 agility an_iron_fist_in_a_velvet_glove
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
Open source for higher education
Ad

Recently uploaded (20)

PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PPTX
Introduction to Building Materials
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
Computing-Curriculum for Schools in Ghana
PPTX
TNA_Presentation-1-Final(SAVE)) (1).pptx
PDF
What if we spent less time fighting change, and more time building what’s rig...
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
1_English_Language_Set_2.pdf probationary
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
Trump Administration's workforce development strategy
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Unit 4 Computer Architecture Multicore Processor.pptx
Introduction to Building Materials
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Introduction to pro and eukaryotes and differences.pptx
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
Computing-Curriculum for Schools in Ghana
TNA_Presentation-1-Final(SAVE)) (1).pptx
What if we spent less time fighting change, and more time building what’s rig...
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
B.Sc. DS Unit 2 Software Engineering.pptx
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Weekly quiz Compilation Jan -July 25.pdf
1_English_Language_Set_2.pdf probationary
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
Trump Administration's workforce development strategy

SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor

  • 1. Leiden Institute of Advanced Computer Science Project evaluation – for the buyer, and for the vendor Prof. Dr. Thomas Bäck System‘s Development and Project Management - Prof. Dr. Thomas Bäck 1
  • 2. Leiden Institute of Advanced Computer Science 0. Select project 1. Identify project objectives 0. Select Project 2. Identify project infrastructure 3. Analyze pr. characteristics 4. Identify products and activities Review lower level detail 5. Estimate effort for activity For each activity 6. Identify activity risks 10. Lower level planning 7. Allocate resources 9. Execute plan 8. Review / publicize plan System‘s Development and Project Management - Prof. Dr. Thomas Bäck 2
  • 3. Leiden Institute of Advanced Computer Science Cost-benefit analysis !   Idea: If project requires investment, as a minimum, the project must provide a greater benefit than putting that investment in a bank account. !   Identify and estimate all costs and benefits of carrying out the project and operating the system. !   Express costs and benefits in common units. •  Costs: •  Benefits: –  Development costs –  Direct benefits –  Setup costs –  Assessable indirect benefits –  Operational costs –  Intangible benefits Relatively easy to quantify Often difficult to quantify System‘s Development and Project Management - Prof. Dr. Thomas Bäck 3
  • 4. Leiden Institute of Advanced Computer Science Cash flow forecasting A typical product life cycle cash flow Expenditure Income Time System‘s Development and Project Management - Prof. Dr. Thomas Bäck 4
  • 5. Leiden Institute of Advanced Computer Science Cash flow forecasting Four project examples: Year Project 1 Project 2 Project 3 Project 4 0 -100,000 -1,000,000 -100,000 -120,000 1 10,000 200,000 30,000 30,000 2 10,000 200,000 30,000 30,000 3 10,000 200,000 30,000 30,000 4 20,000 200,000 30,000 30,000 5 100,000 300,000 30,000 75,000 Net profit 50,000 100,000 50,000 75,000 System‘s Development and Project Management - Prof. Dr. Thomas Bäck 5
  • 6. Leiden Institute of Advanced Computer Science Cost-benefit evaluation 1.  Net profit •  Difference between total costs and total income over the life of the project 2.  Payback period •  Time to brake even or pay back the initial investment 3.  Return on investment (ROI) •  Net profitability of the investment required avg _ annual _ profit ROI = ⋅100% total _ investment •  Popular, but: Takes no account of timing of cash flows ! 4.  Net present value 5.  Internal rate of return System‘s Development and Project Management - Prof. Dr. Thomas Bäck 6
  • 7. Leiden Institute of Advanced Computer Science Cost-benefit evaluation (cont‘d) Net present value •  Considers profitability and cash flow timing •  Discounting future cash flows by discount rate Present value of any future cash flow: value _ in _ year t present _ value = (1 + r )t r: discount rate, t: number of years in future System‘s Development and Project Management - Prof. Dr. Thomas Bäck 7
  • 8. Leiden Institute of Advanced Computer Science Net present value: example Applying discount factors to project 1 Year Project 1 cash Discount factor 10% Discounted cash flow flow 0 -100,000 1.0000 -100,000 1 10,000 0.9091 9,091 2 10,000 0.8264 8,264 3 10,000 0.7513 7,513 4 20,000 0.6830 13,660 5 100,000 0.6209 62,090 Net 50,000 NPV: 618 profit System‘s Development and Project Management - Prof. Dr. Thomas Bäck 8
  • 9. Leiden Institute of Advanced Computer Science Internal Rate of Return NPV is not directly comparable with earnings from other investments ! IRR: Profitability measure directly comparable with interest rates IRR = percentage discount rate that would produce NPV = 0 6000 NPV 8 10 12 Discount rate (%) -6000 Calculate NPV for two discount rates; plot gives IRR (10.25%) System‘s Development and Project Management - Prof. Dr. Thomas Bäck 9
  • 10. Leiden Institute of Advanced Computer Science Project cash flow treated as an investment at 10% IRR: Example Year Project Capital at Interest Capital at End of cash flow start of during end of year forecast year year year withdrawal 0 -100,000 - - - - 1 10,000 100,000 10,000 110,000 10,000 2 10,000 100,000 10,000 110,000 10,000 3 10,000 100,000 10,000 110,000 10,000 4 20,000 100,000 10,000 110,000 20,000 5 99,000 90,000 9,000 99,000 99,000 6 0 0 0 0 0 System‘s Development and Project Management - Prof. Dr. Thomas Bäck 10