SlideShare a Scribd company logo
Partnership To Advance Clean Energy-Deployment (PACE-D)
Technical Assistance Program
Presented by
USAID PACE-D TA Program
Apr-18
Solar PV Rooftop Training Program For Entrepreneurs
Session:
Contract Structure & Agreement
Contents
Key Agreements in an SPVRT project
Case Study - Agreements – Indian Railways, RESCO Model
Solar Lease / PPA – Contract Relationships
Rooftop Lease / Rent Agreement – Items to consider
Power Purchase Agreement- Operation, Financing, Risks
What is a Contract
A contract is a voluntary arrangement between two or more parties that is enforceable at
law as a binding legal agreement
A contractual relationship is evidenced by
 an offer
 acceptance of the offer
 and a valid (legal and valuable) consideration
 Each party to a contract acquires rights and duties relative to the rights and duties of
the other parties
 However, while all parties may expect a fair benefit from the contract
(otherwise courts may set it aside as inequitable) it does not follow that each party
will benefit to an equal extent
Contracts used for SPVRT Projects
CAPEX Model RESCOM Model
Agreement EPC Agreement Power Purchase Agreement
(PPA)
Scope Turnkey Agreement – Design,
Supply, Construction, Installation
Commissioning
Sale of Electricity from solar
rooftop project
Signatories Consumer/Buyer and Developer Consumer and Developer
Period of
Agreement
Short term
Execution of project (~3-6
months)
O&M (~1-5 years)
Long term – 10-25 years
Risk Profile Construction period – Developer
Operations – Developer to the
Construction period –
Developer
Key Features of EPC Contract
Scope of Work for Contract
Payment Terms with well defined
Milestones
 Advance, Supply, Installation,
Commissioning etc.
Warranties and Guarantees
 Warranties for equipment
 Generation/Performance ratio
guarantee
Obligations of each Party
 Obligations of Developer
 Obligations of Consumer
 Obligation of other parties like
Project Management Consultant
etc.
Key Features of EPC Contract
Project Schedule
 Define major (and
minor) milestones and
deadlines
Design Approvals
 Procedures for design
approvals
Quality of the Plant
 Standards and
certifications to be
followed
 Quality check process
Safety Features
 Earthing, lightning
protection, signage
etc.
Default Events
 For developer
 For consumer
Key Features of EPC Contract
Responsibility of
Net/Gross Metering
System
Unrestricted Access to Site
Penalties
 Project schedule
related
 Performance
standards related
 Default events
 Late payment
penalties
Dispute Resolution
Force Majeure Events and Action
Change of Law
Indemnity
Tenure of O&M
Documentation and Manuals
Key Features of PPA
 Scope of Work
 Tariff – Constant, Varying
 Tenure of agreement
 Billing and payment cycle
 Late payment penalty
 Payment security
 Deemed Generation
 Due to grid outage
 Due to shadow generating structures coming up in future
 Due to temporary restrictions
Key Features of PPA
 Obligations of each party
 Obligations of Developer
 Obligation of Consumer
 Obligation of other parties like Project Management Consultant etc
 Unrestricted access to roof
 Generation guarantee and penalties (Performance Bank Guarantee)
 Dispute Resolution
 Force Majeure
 Indemnity
 Buyback clause
Key Features of PPA
 Events of Default
 Events of default for Developer
 Events of default for Consumer
 Termination
 Events of termination for developer
 Events of termination for consumer
 Compensation for developer
 Compensation for consumer
 Responsibility of Net metering connection
 Damage to roof
 Due to consumer
 Due to developers
 Actions
Case Study – Agreements: Indian Railway, RESCO
Model
Solar Lease / PPA – Contract Relationships
The table below is showing various arrangements among the parties involved in
rooftop solar power and their contractual relationship in terms of Lease Agreement
or Power Purchase Agreement (PPA)
The third party in above table refers to the rooftop owner who is not the consumer
of electricity
What needs to be reviewed
 Does rooftop lease / rent agreement provides legal access to develop the solar project?
 What is the tenure of the agreement? If lesser than PPA, can it be extended? Extended
up to what tenure?
 Does the agreement clearly mentions the responsible party to repair the roof in case of
damage and maintain it?
 Is the rooftop owner willing go for net metering and grid interconnection?
 What are the termination clause and the penalties in case of early terminations? Are
they strong enough to safeguard the rooftop solar power project?
Solar Lease / PPA – Items to Consider
POWER PURCHASE AGREEMENTS
Conditions Precedent
Activities need to completed prior to the execution of PPA are listed as conditions
precedent. The conditions precedent is important to specify in PPA to indicate the
activities without the PPA can not be signed by the parties.
For example the model PPA by Indian Railways have following conditions precedent:
 Performance Security/Guarantee to Railways by developer
 Execution of Escrow and Substitution Agreement
 Drawings and Project completion schedule (Approved by Railways)
 Execute Financing Agreements (Deliver copies to Zonal Railway)
Payment Security Mechanism
A mechanism which is adopted to avoid the default against performance and
payment for solar power. It could be a Letter of Credit or a Bank Guarantee.
It gives the party the authority to retain the amount equivalent to the amount
defaulted by another party.
For Example:
 In the PPA of Indian Railways the Solar Power Developer will be providing Rs. 20
lakh per MW. This will be retained by Indian Railways for a specified period and
then returned to the solar power developer. This will protect Indian Railways
against generation below the promised benchmark due to poor performance
Right of Way
Some of the building, their premises and rooftops may not have a general access
due to security reasons. The installation and operation of the rooftop solar power
may require such access which shall be agreed in the PPA.
For Example:
 In the PPA of Indian Railways the Right of Way means the access to the site with
the intention of using it for installation of Project, including the way from the
entry point to the rooftop through the shortest accessible way, easements and
other rights of way, howsoever described, necessary for construction, operation
and maintenance of the Projects.
Deemed Generation
 This is a concept to address any loss of generation due to any reason beyond the
control of the rooftop developer and not covered under Force Majeure
 Deemed generation protects the developer and the lender from delays in the
repayment of the loan. It is crucial to assess whether the deemed generation
clause has been included in the contract and appropriately worded to cover all
eventualities
The key eventualities have been highlighted below:
 In the event of consumer failing to off-take the electricity generated due to non-
availability of reference voltage or lack of demand
 Non-availability of adequate space for solar rooftop installations or unplanned
displacement of the system
 Any loss of generation due to shadow by new buildings or objects in the future
Performance Indicators
 The project is structured based on an estimated revenue earned, based on certain
estimated performance of the rooftop solar power system. A minimum performance
level can be guaranteed as agreed under PPA
 This can be assured in terms of a benchmark Capacity Utilization Factor below which
the developer has to bear a penalty in addition to the loss
 This assures the developers implement best available technology in the market to
achieve the benchmark CUF. However the CUF of the project is also largely based on
the location of the project and the local weather conditions. Hence the benchmark
CUF shall be estimated carefully so as to be in the interest of both the parties
 Benchmark CUF/ Performance Ratio in the existing PPA in the location or CUF
calculated by State Electricity Regulatory Commission for solar could be a fair
indicator to derive the benchmark CUF
Tariff
The price agreed under PPA to be paid for a unit of electricity generated from rooftop
solar power plant is called the tariff.
It is applicable for the complete tenure of the PPA, however the structure of the tariff can
be combination or any of the following:
 Constant Tariff – Under this condition, a constant levelled tariff is agreed upon for the
tenure of the agreement
 Constant Escalation – A tariff structure which starts from a base tariff in year one and
escalates based on a predefined rate can also be used. For example the period of
escalation may vary in 5 years, 10 years, 15 years or for full tenure of PPA
 Variable Escalation – A variable tariff with variable escalation can also be used. For
example 5 per cent from 1st to 5th year, 6 per cent from 6th to 10th year, 7 per cent
from 11th to 15th years and so on
Central Financial Assistance (CFA), if Applicable
CFA is the support from Central Government in form of subsidies.
If applicable then following shall be included in the PPA
 Pre conditions to avail the CFA shall be indicated e.g. MNRE requirements on
Domestic Content ,Technical Specifications to be followed and empanelment
 The modalities of channelling and disbursal of CFA shall be indicated
Buy Back Option
In case the buyout condition is included in the contract, the contract will also clearly
define
 the circumstances situations where the Buyout Clause will be invoked
 and the price at which the buyout will be undertaken
Escrow Account
It means an Account which the Solar Power Developer shall open and maintain with a Bank in which
all inflows and outflows of cash on account of capital and revenue receipts and expenditures shall be
credited and debited, as the case may be, in accordance with the provisions of the PPA.
Example of deposits
 all funds constituting the Financial Package
 all payments on account of tariff and any other revenues from or in respect of the solar power
projects, including the proceeds of any rentals, deposits, capital receipts or insurance claims; and
 all payments by consumers, after deduction of any outstanding Agreement Fee
Example of the preference of withdrawals
 All taxes due and payable by the developer
 All payments relating to construction of the solar project system
 O&M Expenses
 Debt Service due in an Accounting Year etc.
Termination due to Default on PPA by Consumers
The occurrence of default on consumer side will not be limited to but cover the
following:
 How many months of delay after the credit period will be considered as default?
 For non-availability of synchronizing power, what per cent of operating hours
lost is considered as default?
 For non-availability of access to roof, what per cent of days in a year is
considered as default?
 In case of temporary non-availability of roof, what period of non-availability of
roof is considered as default?
 In case of damage of major equipment caused by consumer, to what extent of
damage leads to termination?
Termination due to Default on PPA by Sellers /
RESCO
The occurrence of default on seller / RESCO side will not be limited to but cover the
following:
 How many months of non-availability of solar plant will be considered default?
 How many years of not achieving minimum guaranteed (Benchmark) CUF leads
to default?
 Are there any pre mature termination clauses?
 What will be the impact of pre-mature termination on project feasibility?
 What is the compensation for pre mature termination?
 Are there any other termination clauses?
 What will be the impact of pre-mature termination on project feasibility?
Risk of Non-indemnity
 Indemnified clause is included to indemnify, hold harmless and defend the
parties to the agreement from and against any and all loss and/or damages.
situation where the indemnity clause is applicable will be clearly defined. For a
fair agreement it is important to assess that indemnity clauses adequately
indemnify both the parties.
Dispute Resolution
 The dispute resolution process will be clearly laid out in the agreement with the
appointment of authorities to resolve the dispute. The arbitration process will
also be clearly defined in case the dispute is not resolved in the given period.
Other Conditions to be Agreed to in PPA
 Technical specifications and standards agreed to be provided by seller/ RESCO
shall be clearly laid down in the agreement
 Grid Inter Connection if applicable shall be done following the applicable
regulations and codes
 All approvals, permits safety requirements shall be clearly laid down for the
project
27
Anurag Mishra
Senior Clean Energy Specialist
USAID/India
Email: amishra@usaid.gov
Disclaimer:
This training material is made possible by the support of the American
People through the United States Agency for International
Development (USAID). The contents of this material are the sole
responsibility of Nexant, Inc. and do not necessarily reflect the views of
USAID or the United States Government. This material was prepared
under Contract Number AID-386-C-12-00001.

More Related Content

PPTX
Session 01 Introduction to the course
PPTX
Session 18 tender preparation & evaluation
PPTX
Session 12 project costing & economics
PPTX
Session 21 preparation of techno commercial report
PPTX
Session 14 market trends & business proposals
PPTX
Session 20 interacting with the client
PPTX
Session 15 spvrt project financing
PPTX
Session 17 project management & monitoring
Session 01 Introduction to the course
Session 18 tender preparation & evaluation
Session 12 project costing & economics
Session 21 preparation of techno commercial report
Session 14 market trends & business proposals
Session 20 interacting with the client
Session 15 spvrt project financing
Session 17 project management & monitoring

What's hot (20)

PPTX
Session 09 spvrt business models
PPTX
Session 13 national policy & regulatory framework & available incentives
PPTX
Solar ppa guvnl final
PPTX
quiz Solar PV Rooftop Training Entrepreneurship Development
PDF
2 sun shot perspective-pathways to reducing pv lcoe
PPT
Solar PPA Presentation
PDF
9 incorporating energy storage into pv system design
PDF
Drafting and Negotiating the Optimal Power Purchase Agreement
PDF
Solar and wind power forecasting
PDF
Demand Response Electricity Markets Dallon Kay Diamond Energy Group 20111101
PDF
Energy Manager_MRV article pdf
PDF
World Bank: SBI Grid Connected Solar Rooftop PV (GRPV) Technical Assistance P...
PDF
Demand Response in the US
PDF
Agreements for Net metering, Net accounting, Net plus
PDF
Owner's engineer services - statement of capabilities
PPTX
Eai presentation investment challenges in small hydro in india delhi mar 2010
PDF
Ozone - Corporate Profile Detailed
PDF
Course on Regulation and Sustainable Energy in Developing Countries - Session 9
PPT
Top 10 Products That Save Money - David McDougall, EnerNOC
PDF
MARG-OPENACCESS
Session 09 spvrt business models
Session 13 national policy & regulatory framework & available incentives
Solar ppa guvnl final
quiz Solar PV Rooftop Training Entrepreneurship Development
2 sun shot perspective-pathways to reducing pv lcoe
Solar PPA Presentation
9 incorporating energy storage into pv system design
Drafting and Negotiating the Optimal Power Purchase Agreement
Solar and wind power forecasting
Demand Response Electricity Markets Dallon Kay Diamond Energy Group 20111101
Energy Manager_MRV article pdf
World Bank: SBI Grid Connected Solar Rooftop PV (GRPV) Technical Assistance P...
Demand Response in the US
Agreements for Net metering, Net accounting, Net plus
Owner's engineer services - statement of capabilities
Eai presentation investment challenges in small hydro in india delhi mar 2010
Ozone - Corporate Profile Detailed
Course on Regulation and Sustainable Energy in Developing Countries - Session 9
Top 10 Products That Save Money - David McDougall, EnerNOC
MARG-OPENACCESS
Ad

Similar to Session 16 contract structure & agreement (20)

PDF
Epc contracts-in-the-power-sector
PPTX
Sbi rooftop program
PPTX
Rooftop Solar-Program by SBI and World Bank
PDF
Potential next steps for developers if URD 14D/114 is passed
PDF
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
PDF
Solar Financing Models for Solar projects
PPT
Contracts for difference
PDF
PROJECT_STEPS
PDF
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
PPTX
Episode 28 : Project Management Contract
PPTX
KDC11- Anand Rohatgi, Synergy Consulting
PPT
Understanding Legal Issues in Solar PPAs
PPT
Solar PPA Presentation
PDF
Energy costs reduction through Energy Performance Contracting projects implem...
PPTX
POWER PURCHASE AGREEMENT.pptx
DOCX
Financing models for energy efficiency projects
PDF
Renewable Energy Feed-in Tarriff presentation
PDF
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
PDF
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
PDF
Ppa model presentation
Epc contracts-in-the-power-sector
Sbi rooftop program
Rooftop Solar-Program by SBI and World Bank
Potential next steps for developers if URD 14D/114 is passed
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
Solar Financing Models for Solar projects
Contracts for difference
PROJECT_STEPS
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Episode 28 : Project Management Contract
KDC11- Anand Rohatgi, Synergy Consulting
Understanding Legal Issues in Solar PPAs
Solar PPA Presentation
Energy costs reduction through Energy Performance Contracting projects implem...
POWER PURCHASE AGREEMENT.pptx
Financing models for energy efficiency projects
Renewable Energy Feed-in Tarriff presentation
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
Ppa model presentation
Ad

More from Chirag Jain (10)

PPTX
Session 19 project performance evaluation Operation & Maintenance planning
PPTX
Session 11 overview of simulation software
PPTX
Session 10 grid interconnections & commissioning test procedures
PPTX
Session 08 design & safety overview
PPTX
Session 07 site assessment & planning
PPTX
Session 06 balance of system components
PPTX
Session 05 grid connected inverter
PPTX
Session 04 solar pv modules
PPTX
Session 03 solar pv rooftop technology overview
PPTX
Session 02 solar energy technologies
Session 19 project performance evaluation Operation & Maintenance planning
Session 11 overview of simulation software
Session 10 grid interconnections & commissioning test procedures
Session 08 design & safety overview
Session 07 site assessment & planning
Session 06 balance of system components
Session 05 grid connected inverter
Session 04 solar pv modules
Session 03 solar pv rooftop technology overview
Session 02 solar energy technologies

Recently uploaded (20)

PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Indian roads congress 037 - 2012 Flexible pavement
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
Introduction to pro and eukaryotes and differences.pptx
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
Hazard Identification & Risk Assessment .pdf
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PDF
Computing-Curriculum for Schools in Ghana
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
advance database management system book.pdf
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
My India Quiz Book_20210205121199924.pdf
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Indian roads congress 037 - 2012 Flexible pavement
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Introduction to pro and eukaryotes and differences.pptx
Virtual and Augmented Reality in Current Scenario
Chinmaya Tiranga quiz Grand Finale.pdf
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Hazard Identification & Risk Assessment .pdf
Share_Module_2_Power_conflict_and_negotiation.pptx
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
Computing-Curriculum for Schools in Ghana
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
B.Sc. DS Unit 2 Software Engineering.pptx
advance database management system book.pdf
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Unit 4 Computer Architecture Multicore Processor.pptx
My India Quiz Book_20210205121199924.pdf

Session 16 contract structure & agreement

  • 1. Partnership To Advance Clean Energy-Deployment (PACE-D) Technical Assistance Program Presented by USAID PACE-D TA Program Apr-18 Solar PV Rooftop Training Program For Entrepreneurs Session: Contract Structure & Agreement
  • 2. Contents Key Agreements in an SPVRT project Case Study - Agreements – Indian Railways, RESCO Model Solar Lease / PPA – Contract Relationships Rooftop Lease / Rent Agreement – Items to consider Power Purchase Agreement- Operation, Financing, Risks
  • 3. What is a Contract A contract is a voluntary arrangement between two or more parties that is enforceable at law as a binding legal agreement A contractual relationship is evidenced by  an offer  acceptance of the offer  and a valid (legal and valuable) consideration  Each party to a contract acquires rights and duties relative to the rights and duties of the other parties  However, while all parties may expect a fair benefit from the contract (otherwise courts may set it aside as inequitable) it does not follow that each party will benefit to an equal extent
  • 4. Contracts used for SPVRT Projects CAPEX Model RESCOM Model Agreement EPC Agreement Power Purchase Agreement (PPA) Scope Turnkey Agreement – Design, Supply, Construction, Installation Commissioning Sale of Electricity from solar rooftop project Signatories Consumer/Buyer and Developer Consumer and Developer Period of Agreement Short term Execution of project (~3-6 months) O&M (~1-5 years) Long term – 10-25 years Risk Profile Construction period – Developer Operations – Developer to the Construction period – Developer
  • 5. Key Features of EPC Contract Scope of Work for Contract Payment Terms with well defined Milestones  Advance, Supply, Installation, Commissioning etc. Warranties and Guarantees  Warranties for equipment  Generation/Performance ratio guarantee Obligations of each Party  Obligations of Developer  Obligations of Consumer  Obligation of other parties like Project Management Consultant etc.
  • 6. Key Features of EPC Contract Project Schedule  Define major (and minor) milestones and deadlines Design Approvals  Procedures for design approvals Quality of the Plant  Standards and certifications to be followed  Quality check process Safety Features  Earthing, lightning protection, signage etc. Default Events  For developer  For consumer
  • 7. Key Features of EPC Contract Responsibility of Net/Gross Metering System Unrestricted Access to Site Penalties  Project schedule related  Performance standards related  Default events  Late payment penalties Dispute Resolution Force Majeure Events and Action Change of Law Indemnity Tenure of O&M Documentation and Manuals
  • 8. Key Features of PPA  Scope of Work  Tariff – Constant, Varying  Tenure of agreement  Billing and payment cycle  Late payment penalty  Payment security  Deemed Generation  Due to grid outage  Due to shadow generating structures coming up in future  Due to temporary restrictions
  • 9. Key Features of PPA  Obligations of each party  Obligations of Developer  Obligation of Consumer  Obligation of other parties like Project Management Consultant etc  Unrestricted access to roof  Generation guarantee and penalties (Performance Bank Guarantee)  Dispute Resolution  Force Majeure  Indemnity  Buyback clause
  • 10. Key Features of PPA  Events of Default  Events of default for Developer  Events of default for Consumer  Termination  Events of termination for developer  Events of termination for consumer  Compensation for developer  Compensation for consumer  Responsibility of Net metering connection  Damage to roof  Due to consumer  Due to developers  Actions
  • 11. Case Study – Agreements: Indian Railway, RESCO Model
  • 12. Solar Lease / PPA – Contract Relationships The table below is showing various arrangements among the parties involved in rooftop solar power and their contractual relationship in terms of Lease Agreement or Power Purchase Agreement (PPA) The third party in above table refers to the rooftop owner who is not the consumer of electricity
  • 13. What needs to be reviewed  Does rooftop lease / rent agreement provides legal access to develop the solar project?  What is the tenure of the agreement? If lesser than PPA, can it be extended? Extended up to what tenure?  Does the agreement clearly mentions the responsible party to repair the roof in case of damage and maintain it?  Is the rooftop owner willing go for net metering and grid interconnection?  What are the termination clause and the penalties in case of early terminations? Are they strong enough to safeguard the rooftop solar power project? Solar Lease / PPA – Items to Consider
  • 15. Conditions Precedent Activities need to completed prior to the execution of PPA are listed as conditions precedent. The conditions precedent is important to specify in PPA to indicate the activities without the PPA can not be signed by the parties. For example the model PPA by Indian Railways have following conditions precedent:  Performance Security/Guarantee to Railways by developer  Execution of Escrow and Substitution Agreement  Drawings and Project completion schedule (Approved by Railways)  Execute Financing Agreements (Deliver copies to Zonal Railway)
  • 16. Payment Security Mechanism A mechanism which is adopted to avoid the default against performance and payment for solar power. It could be a Letter of Credit or a Bank Guarantee. It gives the party the authority to retain the amount equivalent to the amount defaulted by another party. For Example:  In the PPA of Indian Railways the Solar Power Developer will be providing Rs. 20 lakh per MW. This will be retained by Indian Railways for a specified period and then returned to the solar power developer. This will protect Indian Railways against generation below the promised benchmark due to poor performance
  • 17. Right of Way Some of the building, their premises and rooftops may not have a general access due to security reasons. The installation and operation of the rooftop solar power may require such access which shall be agreed in the PPA. For Example:  In the PPA of Indian Railways the Right of Way means the access to the site with the intention of using it for installation of Project, including the way from the entry point to the rooftop through the shortest accessible way, easements and other rights of way, howsoever described, necessary for construction, operation and maintenance of the Projects.
  • 18. Deemed Generation  This is a concept to address any loss of generation due to any reason beyond the control of the rooftop developer and not covered under Force Majeure  Deemed generation protects the developer and the lender from delays in the repayment of the loan. It is crucial to assess whether the deemed generation clause has been included in the contract and appropriately worded to cover all eventualities The key eventualities have been highlighted below:  In the event of consumer failing to off-take the electricity generated due to non- availability of reference voltage or lack of demand  Non-availability of adequate space for solar rooftop installations or unplanned displacement of the system  Any loss of generation due to shadow by new buildings or objects in the future
  • 19. Performance Indicators  The project is structured based on an estimated revenue earned, based on certain estimated performance of the rooftop solar power system. A minimum performance level can be guaranteed as agreed under PPA  This can be assured in terms of a benchmark Capacity Utilization Factor below which the developer has to bear a penalty in addition to the loss  This assures the developers implement best available technology in the market to achieve the benchmark CUF. However the CUF of the project is also largely based on the location of the project and the local weather conditions. Hence the benchmark CUF shall be estimated carefully so as to be in the interest of both the parties  Benchmark CUF/ Performance Ratio in the existing PPA in the location or CUF calculated by State Electricity Regulatory Commission for solar could be a fair indicator to derive the benchmark CUF
  • 20. Tariff The price agreed under PPA to be paid for a unit of electricity generated from rooftop solar power plant is called the tariff. It is applicable for the complete tenure of the PPA, however the structure of the tariff can be combination or any of the following:  Constant Tariff – Under this condition, a constant levelled tariff is agreed upon for the tenure of the agreement  Constant Escalation – A tariff structure which starts from a base tariff in year one and escalates based on a predefined rate can also be used. For example the period of escalation may vary in 5 years, 10 years, 15 years or for full tenure of PPA  Variable Escalation – A variable tariff with variable escalation can also be used. For example 5 per cent from 1st to 5th year, 6 per cent from 6th to 10th year, 7 per cent from 11th to 15th years and so on
  • 21. Central Financial Assistance (CFA), if Applicable CFA is the support from Central Government in form of subsidies. If applicable then following shall be included in the PPA  Pre conditions to avail the CFA shall be indicated e.g. MNRE requirements on Domestic Content ,Technical Specifications to be followed and empanelment  The modalities of channelling and disbursal of CFA shall be indicated Buy Back Option In case the buyout condition is included in the contract, the contract will also clearly define  the circumstances situations where the Buyout Clause will be invoked  and the price at which the buyout will be undertaken
  • 22. Escrow Account It means an Account which the Solar Power Developer shall open and maintain with a Bank in which all inflows and outflows of cash on account of capital and revenue receipts and expenditures shall be credited and debited, as the case may be, in accordance with the provisions of the PPA. Example of deposits  all funds constituting the Financial Package  all payments on account of tariff and any other revenues from or in respect of the solar power projects, including the proceeds of any rentals, deposits, capital receipts or insurance claims; and  all payments by consumers, after deduction of any outstanding Agreement Fee Example of the preference of withdrawals  All taxes due and payable by the developer  All payments relating to construction of the solar project system  O&M Expenses  Debt Service due in an Accounting Year etc.
  • 23. Termination due to Default on PPA by Consumers The occurrence of default on consumer side will not be limited to but cover the following:  How many months of delay after the credit period will be considered as default?  For non-availability of synchronizing power, what per cent of operating hours lost is considered as default?  For non-availability of access to roof, what per cent of days in a year is considered as default?  In case of temporary non-availability of roof, what period of non-availability of roof is considered as default?  In case of damage of major equipment caused by consumer, to what extent of damage leads to termination?
  • 24. Termination due to Default on PPA by Sellers / RESCO The occurrence of default on seller / RESCO side will not be limited to but cover the following:  How many months of non-availability of solar plant will be considered default?  How many years of not achieving minimum guaranteed (Benchmark) CUF leads to default?  Are there any pre mature termination clauses?  What will be the impact of pre-mature termination on project feasibility?  What is the compensation for pre mature termination?  Are there any other termination clauses?  What will be the impact of pre-mature termination on project feasibility?
  • 25. Risk of Non-indemnity  Indemnified clause is included to indemnify, hold harmless and defend the parties to the agreement from and against any and all loss and/or damages. situation where the indemnity clause is applicable will be clearly defined. For a fair agreement it is important to assess that indemnity clauses adequately indemnify both the parties. Dispute Resolution  The dispute resolution process will be clearly laid out in the agreement with the appointment of authorities to resolve the dispute. The arbitration process will also be clearly defined in case the dispute is not resolved in the given period.
  • 26. Other Conditions to be Agreed to in PPA  Technical specifications and standards agreed to be provided by seller/ RESCO shall be clearly laid down in the agreement  Grid Inter Connection if applicable shall be done following the applicable regulations and codes  All approvals, permits safety requirements shall be clearly laid down for the project
  • 27. 27 Anurag Mishra Senior Clean Energy Specialist USAID/India Email: amishra@usaid.gov Disclaimer: This training material is made possible by the support of the American People through the United States Agency for International Development (USAID). The contents of this material are the sole responsibility of Nexant, Inc. and do not necessarily reflect the views of USAID or the United States Government. This material was prepared under Contract Number AID-386-C-12-00001.