Draft




                  BASIC PRINCIPLES OF SHUTDOWN
                        SCHEDULING IN SAP

           ______________________________________________________________________




Printed: February 5, 2011
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc
Last Modified: 2/3/2011 01:07:00 AM                            Draft
Gentile Consulting Inc.


Table of Contents
1.0Purpose                                                                               2

2.0Scope                                                                                 2

3.0Discussion                                                                            3

4.0Summary/Conclusions                                                                  12




1.0 Purpose
The purpose of this document is to introduce the concepts and techniques required to
effectively schedule shutdown work entirely within SAP. It is not intended to be a step by
step instruction manual. Specific business processes are developed in detail for each
organization however, it is important for everyone to understand the concepts involved and
how their everyday activities affect the schedule. Using SAP will allow live real-time
schedule reports and status to be available to everyone with access to SAP.
2.0      Scope

This document will cover the following topics:

    •    Why it is necessary to schedule work in SAP
    •    Introduction to the “WINDOWS” concept of scheduling.
    •    Introduction to SAP “Networks”
    •    Integration of SAP Networks and Work Orders to create a schedule.
    •    Introduction to on-line reports for all levels of the organization.




Printed: February 5, 2011                                   2
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




3.0      Discussion


Why schedule in SAP

SAP is a fully integrated software system in which various modules share a common
database. This means that the information that a planner puts on a work order provides
data that is used by all modules of the program. The system will automatically order parts
and services, make demands on work groups resources, provide input to the financial
planning groups, all based on the dates of the work order operations.

If the dates on the work order are incorrect, the basic functionality of SAP is diminished
and the company cannot realize the improvements and benefits it expected when it made
the investment in SAP. Incorrect dates on the work order will supply incorrect data to all
the modules seen below.




Printed: February 5, 2011                                   3
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




The “WINDOWS” concept of scheduling

Window scheduling is a technique that is used by many industries regardless of the
scheduling tool being used. Consider the following sequence of events.


       Reduce Steam Demand to                Secure Boiler Feed Pump                                     Reduce Steam Demand to
                           50%                                         #1                                                    10%




                                                                                           Boiler Feed
                                                                                         Pump #1 Work
                                                                                              Window




  Secure Main Steam Header            Hydro Main Steam Header               Increase Steam Demand to
                                                                                                                                   Start Boiler Feed Pump #1
                             #1                                 #1                                50%




The scenario in the above illustration describes reducing the output of a boiler to facilitate
the hydrostatic testing of a steam header. The “Work Window” depicted in red is that
period in time when #1 Boiler Feed Pump is available for maintenance without effecting
the overall duration of the hydrostatic testing evolution.




Printed: February 5, 2011                                   4
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Project Systems Networks

A network is a structure the Project Systems module that contains specific work
instructions similar to the work order in the Plant Maintenance module. These work
instructions are referred to as activities. The network activities may be logic tied and
scheduled. A simple network is illustrated graphically below.




Printed: February 5, 2011                                   5
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Subnetworks


It is possible to add more details to your network by creating subnetworks to
network activities. In the example below a project network was created with the
high level network consisting of design, installation and closeout activities. More
detail was added by adding a subnetwork to the installation activity.




You can use subnetworks to refine and detail your networks as planning
progresses. You create subnetworks by breaking down a network activity into one
or more subnetworks. The system treats subnetworks and networks the same, that
is, you can plan dates, capacities, costs, materials and production resource/tools
also with a subnetwork.




Printed: February 5, 2011                                   6
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Network Activities

Network Activities are discrete tasks similar to work order operations with the following
characteristics:

•   They have duration.
•   They have a defined start and a defined finish.
•   Resources are needed to execute them.
•   They incur costs.
•   They are worked without interruption.

There are the following types of activities in Project Systems:

• Internal processed activities (work performed by internal employees)
• Externally processed activities (work performed by external employees)
• Primary costs activities (activity costs that are expected to arise through the
  consumption of goods and services that originate from outside the company




Printed: February 5, 2011                                   7
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


         Integration of SAP Networks and Work Orders

         PM work orders can be linked to any network or subnetwork activity. When they are
         linked the dates on the work order will be derived from the activity date. When the
         network is scheduled all work orders attached will also be scheduled. This allows
         scheduling personnel to maintain the dates of many orders at once by using a single
         transaction.




Operative Network
Operative Network



Sub Networks
Sub Networks


PM Orders
PM Orders




Printed: February 5, 2011                                   8
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



         Project Systems Reporting



         Now that the PS and PM modules are linked through the networks reports
         can be generated through the PS module that can be used by all levels and
         departments in the organization via a single source. Illustrated below are
         some reports generated by the system.


                                                         Gant Charts




Printed: February 5, 2011                                   9
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                          Work Center Schedules




                                                    Material Reports



Printed: February 5, 2011                                   10
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                              Real Time Cost Reports



Printed: February 5, 2011                                   11
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




         Hundreds of reports involving all work groups can be generated from a
         single transaction in the PS module. Any report generated by external
         scheduling software can be duplicated in SAP.




4.0      Summary/Conclusions

The integration of the PS and PM modules will provide a scheduling capability
previously impossible in the company. This scheduling capability will require little or
no input from the individuals performing the work since all schedule updates occur
through the already implemented conformation process.

The critical success factors involved in this process are:



Printed: February 5, 2011                                   12
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



            • All work planned and managed within SAP (Capital, Maintenance,
              Operations)
            • Work orders must contain detailed planning
            • Accurate and timely confirmations of all operations




Printed: February 5, 2011                                   13
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM

More Related Content

PDF
Sap mm-end-user-manual
PDF
Green field project making of production plant
PDF
SAP PS overview
PDF
Introduction to sap project systems
PPTX
Erp sap mm procure to pay process cycle
PDF
SAP PM Plant Maintenance Overview
PPT
Detial process description inter company stock transfer
PDF
Repair process-in-sap-cs-customer-service--part-ii
Sap mm-end-user-manual
Green field project making of production plant
SAP PS overview
Introduction to sap project systems
Erp sap mm procure to pay process cycle
SAP PM Plant Maintenance Overview
Detial process description inter company stock transfer
Repair process-in-sap-cs-customer-service--part-ii

What's hot (20)

PPTX
Framework of sap mm blueprint by pennonsoft
PPT
SAP Production Planning
DOCX
SAP PM - WCM: Enhanced Model - Entire process flow with SAP screenshots
PPT
IBM Maximo for Utilities
PDF
Dissertation Presentation Powerpoint Presentation Slides
PPT
Pm overview comprehensive_1
PPTX
PS Module Overview
PDF
SAP PM Master Data Training Guide
DOCX
SAP PM: Test Equipment Management/Calibration process
PDF
Field failure analysis using root cause pattern diagrams
PPTX
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
PPTX
Validação de Sistemas Computadorizados - Pebbian/ActionCompliance
PPT
SAP PM Plant Maintenance Training
PDF
Time based progress analysis in project system (revenue recognition) sap blogs
PPT
SAP PP Case study by Murali Krishna Nookella
PDF
SAP SD Variant configuration-training-document 2
PPTX
The procure to pay process
PDF
SAP MM Configuration - Real Project Documentation
PDF
Front-End Loading in the Oil and Gas Industry
PDF
SAP Plant Maintenance Training Material | www.sapdocs.info
Framework of sap mm blueprint by pennonsoft
SAP Production Planning
SAP PM - WCM: Enhanced Model - Entire process flow with SAP screenshots
IBM Maximo for Utilities
Dissertation Presentation Powerpoint Presentation Slides
Pm overview comprehensive_1
PS Module Overview
SAP PM Master Data Training Guide
SAP PM: Test Equipment Management/Calibration process
Field failure analysis using root cause pattern diagrams
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
Validação de Sistemas Computadorizados - Pebbian/ActionCompliance
SAP PM Plant Maintenance Training
Time based progress analysis in project system (revenue recognition) sap blogs
SAP PP Case study by Murali Krishna Nookella
SAP SD Variant configuration-training-document 2
The procure to pay process
SAP MM Configuration - Real Project Documentation
Front-End Loading in the Oil and Gas Industry
SAP Plant Maintenance Training Material | www.sapdocs.info
Ad

Viewers also liked (20)

PDF
Turnaround Project Planner Primer
PPTX
Plant shutdown
PDF
technical services for turnarounds in petrochemical plants in western europe
PPTX
Planning for Shutdowns, Turnarounds and Outages Workshop
PPT
Scheduled Shutdown Maintenance
PPT
Managing A Synergistic Shutdown Team
PDF
Turnarounds for process plants/ Industry Services
PPTX
Employee benefits in oil & energy industry
PPT
Safe work procedure1
PDF
Smart Asset Solution for Oil and Gas
PPTX
Arcadis capabillity statement summary feb 2017
PDF
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
PDF
IBM Maximo Asset Management solutions for the oil and gas industry
PPTX
Data - the Oil & Gas asset that isn’t managed like one
PDF
Shutdown Turnaround & Outage management courses
PPTX
Maintenance Management Certification
PPTX
Shutdown Turnaround and Outage Competency Improvement Program
PPTX
Introduction to Reliability Excellence
PDF
Heat-exchanger-manual
Turnaround Project Planner Primer
Plant shutdown
technical services for turnarounds in petrochemical plants in western europe
Planning for Shutdowns, Turnarounds and Outages Workshop
Scheduled Shutdown Maintenance
Managing A Synergistic Shutdown Team
Turnarounds for process plants/ Industry Services
Employee benefits in oil & energy industry
Safe work procedure1
Smart Asset Solution for Oil and Gas
Arcadis capabillity statement summary feb 2017
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
IBM Maximo Asset Management solutions for the oil and gas industry
Data - the Oil & Gas asset that isn’t managed like one
Shutdown Turnaround & Outage management courses
Maintenance Management Certification
Shutdown Turnaround and Outage Competency Improvement Program
Introduction to Reliability Excellence
Heat-exchanger-manual
Ad

Similar to Shutdown Scheduling (20)

PDF
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PDF
Web Based Reporting
PPT
System integration challanges in Workforce Management
PDF
How to Do Capacity Planning
PPTX
Bpp 3213 lecture 2
PDF
I heat 2012-philipgaffney-l2s2
PPTX
Bpr in it
PDF
The Railpocket Wifi Project Anonymous
PDF
Lesson02 - Network Design & LAN
PDF
CSC1100 - Chapter10 - Information System
PDF
Real-time Data Distribution: When Tomorrow is Too Late
PDF
System Design
PDF
Semantic Enterprise Architecture
DOCX
Production mgmt
PPT
Heizer 15
PDF
Unit 5- Architectural Design in software engineering
PDF
Industrial Control System Cyber Security and the Employment of Industrial Fir...
PPTX
Unit 7 production scheduling
PDF
PPT
Sysdev
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
Web Based Reporting
System integration challanges in Workforce Management
How to Do Capacity Planning
Bpp 3213 lecture 2
I heat 2012-philipgaffney-l2s2
Bpr in it
The Railpocket Wifi Project Anonymous
Lesson02 - Network Design & LAN
CSC1100 - Chapter10 - Information System
Real-time Data Distribution: When Tomorrow is Too Late
System Design
Semantic Enterprise Architecture
Production mgmt
Heizer 15
Unit 5- Architectural Design in software engineering
Industrial Control System Cyber Security and the Employment of Industrial Fir...
Unit 7 production scheduling
Sysdev

Shutdown Scheduling

  • 1. Draft BASIC PRINCIPLES OF SHUTDOWN SCHEDULING IN SAP ______________________________________________________________________ Printed: February 5, 2011 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM Draft
  • 2. Gentile Consulting Inc. Table of Contents 1.0Purpose 2 2.0Scope 2 3.0Discussion 3 4.0Summary/Conclusions 12 1.0 Purpose The purpose of this document is to introduce the concepts and techniques required to effectively schedule shutdown work entirely within SAP. It is not intended to be a step by step instruction manual. Specific business processes are developed in detail for each organization however, it is important for everyone to understand the concepts involved and how their everyday activities affect the schedule. Using SAP will allow live real-time schedule reports and status to be available to everyone with access to SAP. 2.0 Scope This document will cover the following topics: • Why it is necessary to schedule work in SAP • Introduction to the “WINDOWS” concept of scheduling. • Introduction to SAP “Networks” • Integration of SAP Networks and Work Orders to create a schedule. • Introduction to on-line reports for all levels of the organization. Printed: February 5, 2011 2 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 3. Gentile Consulting Inc. 3.0 Discussion Why schedule in SAP SAP is a fully integrated software system in which various modules share a common database. This means that the information that a planner puts on a work order provides data that is used by all modules of the program. The system will automatically order parts and services, make demands on work groups resources, provide input to the financial planning groups, all based on the dates of the work order operations. If the dates on the work order are incorrect, the basic functionality of SAP is diminished and the company cannot realize the improvements and benefits it expected when it made the investment in SAP. Incorrect dates on the work order will supply incorrect data to all the modules seen below. Printed: February 5, 2011 3 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 4. Gentile Consulting Inc. The “WINDOWS” concept of scheduling Window scheduling is a technique that is used by many industries regardless of the scheduling tool being used. Consider the following sequence of events. Reduce Steam Demand to Secure Boiler Feed Pump Reduce Steam Demand to 50% #1 10% Boiler Feed Pump #1 Work Window Secure Main Steam Header Hydro Main Steam Header Increase Steam Demand to Start Boiler Feed Pump #1 #1 #1 50% The scenario in the above illustration describes reducing the output of a boiler to facilitate the hydrostatic testing of a steam header. The “Work Window” depicted in red is that period in time when #1 Boiler Feed Pump is available for maintenance without effecting the overall duration of the hydrostatic testing evolution. Printed: February 5, 2011 4 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 5. Gentile Consulting Inc. Project Systems Networks A network is a structure the Project Systems module that contains specific work instructions similar to the work order in the Plant Maintenance module. These work instructions are referred to as activities. The network activities may be logic tied and scheduled. A simple network is illustrated graphically below. Printed: February 5, 2011 5 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 6. Gentile Consulting Inc. Subnetworks It is possible to add more details to your network by creating subnetworks to network activities. In the example below a project network was created with the high level network consisting of design, installation and closeout activities. More detail was added by adding a subnetwork to the installation activity. You can use subnetworks to refine and detail your networks as planning progresses. You create subnetworks by breaking down a network activity into one or more subnetworks. The system treats subnetworks and networks the same, that is, you can plan dates, capacities, costs, materials and production resource/tools also with a subnetwork. Printed: February 5, 2011 6 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 7. Gentile Consulting Inc. Network Activities Network Activities are discrete tasks similar to work order operations with the following characteristics: • They have duration. • They have a defined start and a defined finish. • Resources are needed to execute them. • They incur costs. • They are worked without interruption. There are the following types of activities in Project Systems: • Internal processed activities (work performed by internal employees) • Externally processed activities (work performed by external employees) • Primary costs activities (activity costs that are expected to arise through the consumption of goods and services that originate from outside the company Printed: February 5, 2011 7 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 8. Gentile Consulting Inc. Integration of SAP Networks and Work Orders PM work orders can be linked to any network or subnetwork activity. When they are linked the dates on the work order will be derived from the activity date. When the network is scheduled all work orders attached will also be scheduled. This allows scheduling personnel to maintain the dates of many orders at once by using a single transaction. Operative Network Operative Network Sub Networks Sub Networks PM Orders PM Orders Printed: February 5, 2011 8 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 9. Gentile Consulting Inc. Project Systems Reporting Now that the PS and PM modules are linked through the networks reports can be generated through the PS module that can be used by all levels and departments in the organization via a single source. Illustrated below are some reports generated by the system. Gant Charts Printed: February 5, 2011 9 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 10. Gentile Consulting Inc. Work Center Schedules Material Reports Printed: February 5, 2011 10 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 11. Gentile Consulting Inc. Real Time Cost Reports Printed: February 5, 2011 11 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 12. Gentile Consulting Inc. Hundreds of reports involving all work groups can be generated from a single transaction in the PS module. Any report generated by external scheduling software can be duplicated in SAP. 4.0 Summary/Conclusions The integration of the PS and PM modules will provide a scheduling capability previously impossible in the company. This scheduling capability will require little or no input from the individuals performing the work since all schedule updates occur through the already implemented conformation process. The critical success factors involved in this process are: Printed: February 5, 2011 12 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 13. Gentile Consulting Inc. • All work planned and managed within SAP (Capital, Maintenance, Operations) • Work orders must contain detailed planning • Accurate and timely confirmations of all operations Printed: February 5, 2011 13 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM