Software Project Management
Indu Sharma
HOD(CSE)
CPTC,Rajsamand
2
Introduction
 Project Management is an integrated part of software
development.
 It refers to manage the complete software project.
 The goal is to provide the necessary support for
development to proceed smoothly and reduce any
development problem. Its basic task is to ensure that,
once a development process is chosen, it is
implemented optimally.
 Effective s/w project management focuses on the 4
P’s: The People, The Product, The Process, and The
Project.
3
Introduction
I. The People:
 People-intensive
 SEI has developed a “People Management-
Capability Maturity Model” (PM-CMM):
 This model defines the key practice areas for s/w
people: recruitment, selection, performance
management, training, compensation, career
development, organization and work design, and
team/culture development.
 Team leaders: Motivation, Innovative, Problem
solving, influence and team building.
4
Introduction
II. The Product:

Product objectives: Overall goals (from the
customer’s point of view) without considering
how these goals will be achieved.

Scope: identifies its primary data, functions, and
behaviors.

Alternative Solutions: Once the project objectives
and scope are understood, alternative solutions
are considered. The alternative solutions enable
managers to select a “best” approach, given the
constraints imposed by the delivery deadlines,
budgetary restrictions, personnel availability,
technical interfaces etc.
5
Introduction
III. The Process:
 The way in which we produce the software.
 Provides a framework from which a comprehensive
plan for s/w development can be established.
 Problem is to select the appropriate process model.
 The project manager must decide which process
model is appropriate for:

The customer who have requested the product

The characteristics of the product itself, and

The projcect environment in which the s/w team
works.
6
Introduction
IV. The Project:
 In order to manage successful s/w projects, we must
understand what can go wrong and how to do it
right. Ten signs that indicate the project is in danger:
i. S/w people don’t understand their customer’s need.
ii. The product scope is poorly defined.
iii. Changes are managed poorly.
iv. The chosen technology changes.
v. Business needs change (or ill defined).
7
Introduction
vi. Deadlines are unrealistic.
vii. Users are resistant.
viii. Sponsorship is lost ( or was never properly obtained)
ix. The project team lacks people with appropriate skills.
x. Managers avoid practices and lessones learned.
8
Introduction
 Five commonsense approach to avoid problems to s/w
projects:

Start on the right foot:
 Working hard to understand the problem.
 Building the right team and giving the team
autonomy, authority, and technology needed to
the job.

Maintain Momentum:
 Good start and then slowly disintegrate
 To maintain momentum, the project manager
must provide incentives, should emphasize
quality in every task it performs etc.

Track progress:
 Progress is tracked as work products.
9
Introduction

Make smart decisions:
 Keep it simple.
 Use of existing s/w components
 Decide to avoid custom interfaces when standard
approaches are available.
 Decide to identify and then avoid obvious risks.
 Decide to allocate more time than you think is
needed to complex or risky tasks.
10
Introduction

Conduct a postmortem analysis:
 Establish consistent mechanism for extracting
lessons learned for each project.
 Evaluate the planned and actual schedules,
collect and analyze s/w project metrics, get
feedback from team members and customers,
and record finding is in written form.
11
Activities
 The activities in the management
process for a project can be grouped
broadly into three phases:
 Project planning
 Project Monitoring & Control
 Project Termination
12
Project Planning
 Project management begins with planning,
which is the perhaps most critical project
management activity.
 Lack of proper planning is sure ticket to
failure for a large s/w project.
 A s/w plan is usually produced before the
development activity begins and is updated
as development proceeds and data about
progress of the project becomes available.
13
Project Planning
 The major issues project planning
addresses are:
I. Process Planning
II. Effort estimation
III. Project scheduling and staffing
IV. Configuration Management Plan
V. Quality Plans
VI. Risk Management
VII. Project Monitoring plans
14
I Process Planning
 For a project during planning, a key activity is
to plan and specify the process that should
be used in the project.
 It means the various stages in the process,
the entry criteria for each stage, the exit
criteria, the verification activities that will be
done at the end of the stage.
 Some standard process model may be used
as a standard process and tailored to suit the
needs of the project.
15
II Effort Estimation
 For a given set of requirements it is desirable
to know how much it will cost to develop the
s/w and how much time the development will
take. These estimates are needed before
development is initiated.
 The primary reason for cost and schedule
estimation are:
 Cost and benefit analysis
 Project monitoring and control
 More practical use: bidding for s/w projects
16
Effort Estimation
 Because the s/w development is labour-
intensive(i.e. human resources), most cost
estimation procedures focuses on estimating
effort in terms of Person-Months(PM).
 Effort and schedule estimation is required to
answer the questions like:
 Is the project late?
 Are there cost overruns?
 When is the project likely to complete?
 What staffing level is required during different
phases?
17
Effort Estimation
 To achieve reliable effort estimation in terms of
cost , a no. of options arise:
a) Delay estimates until late in the project.
Not practical, as cost estimation must be provided “up-
front”
b) Base estimates on similar projects that have already
been completed
Can work reasonably well, if the current project is quite
similar to past efforts.
c) Use relatively simple decomposition techniques to
generate project cost and effort estimation.
d) Use one or more empirical models for s/w cost and effort
estimation.
(c) And (d) are viable approaches to s/w project estimation.
18
Measure, Measurement, Metrics
and Indicators
 Although, the terms measure, measurement, and
metrics are often used interchangeably, but it is
important to note the subtle differences between
them.
 Measure: A measure provides a quantitative
indication of the extent, amount, dimension, capacity,
or size of some attributes of a product or process.
 Measurement: Measurement is the act of determining
a measure.
 Metric: A quantitative measure of the degree to which
a system, component, or process possesses a given
attribute.
19
Measure, Measurement, Metrics
and Indicators
 Example:
 When a single data point has been collected (e.g.,
the number of errors uncovered in the review of a
single module), a measure has been established.
Measurement occurs as the result of the collection
of one or more data points (e.g., a number of
module reviews are investigated to collect
measures of the number of errors in each
module). A software metric relates the individual
measures in some way (e.g., the average number
of errors found per review).
20
Measure, Measurement, Metrics
and Indicators
 A software engineer collects measures and
develops metrics so that indicators will be
obtained. An indicator is a metric or
combination of metrics that provide insight
into the software process, a software project,
or the product itself.
 An indicator provides insight that enables the
project manager or software engineers to
adjust the process, the project, or the process
to make things better.
21
Measure, Measurement, Metrics
and Indicators
 For example, four software teams are working on a
large software project. Each team must conduct
design reviews but is allowed to select the type of
review that it will use. Upon examination of the
metric, errors found per person-hour expended, the
project manager notices that the two teams using
more formal review methods exhibits an errors found
per person-hour expended that is 40% higher than
the other teams. Assuming all parameters are equal,
this provides the project manager with an indicator
that formal review methods may provide a higher
return on time investment than another, less formal
review approach. She may decide to suggest that all
teams use the more formal approach.
22
Metrics
 Because the s/w has not physical attributes,
conventional metrics are not much help in
designing metrics of s/w. A number of metrics
have been proposed to quantify things like
the size, complexity, and reliability of a s/w
product.
 A s/w metrics relates the individual
measures in some way.
Eg. Avg lines of code: KLOC per module
Avg number of errors found per module
23
Metrics
 There are three types of metrics:
 Product Metrics: Product metrics are used to
quantify characteristics of the product being
developed i.e. Software. Eg. Size, complexity,
performance, efficiency, portability, reliability etc.
 Process Metrics: Process metrics are used to
quantify characteristics of the process being used
to develop the s/w. Eg. Effort required in the
process, time to produce the product, effect of
development techniques and tools, no. of defects
found during testing etc.
24
Metrics
 Project Metrics: are used for strategic
purposes. That is, project metrics and indicators
derived from them are used by a project manager
and a software team to adapt project work flow
and technical activities.
 Two purpose:

First, to minimize the development schedule by making
necessary adjustments in order to avoid delays and
alleviate potential risks and problems.

Secondly, these metrics are used to assess the product
quality on a regular basis and modify the technical issues
if required. As the quality improves, the number of errors
and defects are reduced, which in turn leads to a
decrease in the overall cost of a software project.
25
Metrics
 Values of metrics can be measured directly
or indirectly.
 Directly:
 eg. Distance can be directly measured.
 eg. Size of the s/w (LOC), cost, execution
speed etc.
 Indirectly:
 eg. Distance = speed * time
 eg. Reliability has to be estimated from
other possible measurements, quality,
complexity, maintainability etc.
26
Decomposition Techniques
 Decomposition techniques take a “divide and
conquer” approach to s/w project estimation.
 Decomposition techniques are used to estimate cost
and effort by decomposing the complete project
problem into subsequent parts. Now, first these parts
or subdivisions are solved one-by-one and after their
solutions can be combined to form a whole.
 The s/w size is the most important factor that effects
the cost. LOC and FP-Based are distinct estimate
techniques for s/w size.
 If a direct approach is chosen, size can be measured
in LOC. If an indirect approach is chosen, size is
represented in FP.
27
LOC-Based Estimation
 It simply refers to the no. of lines of the
delivered source code.
 Eg. 5000 KLOC
 LOC
 From this a set of simple size-oriented
metrics can be developed:
 Errors / KLOC, Defects / KLOC, $ / KLOC
 Other Metrics:
 Errors / person-month
 LOC / Person-month
 $ / page of documentation
28
LOC-Based Estimation
 Advantages:
 Simple to measure
 It can be determined uniquely by automated tools
once the project is completed.
 Drawbacks:
 It is defined on code. For example it can’t measure
the size of specification.
 It characterize only one specific view of size, name
length, it takes no account of functionality or
complexity.
 Bad s/w design may cause excessive line of code
 It is language dependent.

More Related Content

PDF
Chapter 01 - Introduction to Software Project Management
PPTX
What is Agile Project Management? | Agile Project Management | Invensis Learn...
PDF
Agile Methodology
PPTX
Feature driven development (FDD)
PPT
Agile Project Management for IT Projects
PPT
Software Project Managment
PPTX
The Extreme Programming (XP) Model
PDF
Agile Fundamentals
Chapter 01 - Introduction to Software Project Management
What is Agile Project Management? | Agile Project Management | Invensis Learn...
Agile Methodology
Feature driven development (FDD)
Agile Project Management for IT Projects
Software Project Managment
The Extreme Programming (XP) Model
Agile Fundamentals

What's hot (20)

PPT
Programme management and project evaluation
PPT
PRINCE2 - Presentation
PPTX
Project Management Tools
PPTX
SPM_UNIT-1(1).pptx
PPTX
Agile Methodology and Tools
PPTX
Agile-overview: Agile Manifesto, Agile principles and Agile Methodologies
PPTX
Introduction to Scrum.ppt
PDF
Agile & SCRUM basics
PDF
Agile sdlc
PPTX
project management
PPT
PPT
What Is Agile Scrum
PPT
PPTX
Software Project Management ppt
ODP
Introduction To Agile
PPT
Agile testing
PPTX
Waterfall Model
PPTX
PPTX
2. project initiation
PDF
Introduction agile scrum methodology
Programme management and project evaluation
PRINCE2 - Presentation
Project Management Tools
SPM_UNIT-1(1).pptx
Agile Methodology and Tools
Agile-overview: Agile Manifesto, Agile principles and Agile Methodologies
Introduction to Scrum.ppt
Agile & SCRUM basics
Agile sdlc
project management
What Is Agile Scrum
Software Project Management ppt
Introduction To Agile
Agile testing
Waterfall Model
2. project initiation
Introduction agile scrum methodology
Ad

Viewers also liked (20)

PPTX
software project management
PDF
Project management
PPSX
Project management
PPTX
Software Project Management Slide
DOC
An Introduction to Project management(project management tutorials)
PPT
Project managemen concept
PPT
Software Project Management (lecture 2)
PPT
Software Project Management
PPTX
CSC426 - Software Engineering Lecture Note
PPTX
CSC426 - Software Engineering Lecture Note Cont'd
PPSX
Maria Managment Spectrum
PPTX
Function Points
PDF
Software engineering
PPT
Managing software project, software engineering
PPT
Project Management and Process
PPTX
Different types of wbs structures
PPT
Software project management 3
PPTX
5 Basic Phases of Project Management
PPTX
4 P’s of Marketing Plan for Medical Practices
PDF
Function Points
software project management
Project management
Project management
Software Project Management Slide
An Introduction to Project management(project management tutorials)
Project managemen concept
Software Project Management (lecture 2)
Software Project Management
CSC426 - Software Engineering Lecture Note
CSC426 - Software Engineering Lecture Note Cont'd
Maria Managment Spectrum
Function Points
Software engineering
Managing software project, software engineering
Project Management and Process
Different types of wbs structures
Software project management 3
5 Basic Phases of Project Management
4 P’s of Marketing Plan for Medical Practices
Function Points
Ad

Similar to Software project management (20)

PPT
Shot note about project management
DOCX
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
PPT
Revised CHAPTER-TWO.pptppppppppppppppppp
PPTX
Basics in Project Management
PPT
PM-1 Overview.ppt
PDF
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
PDF
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
PDF
Asset Finance Systems: Project Initiation "101"
PPTX
1_slides bài giảng - SoftwareProjectManagement.pptx
PPTX
Software metrics in software engineering
PDF
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
PDF
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
PPTX
Project planning.pptx
PPTX
Project planning.pptx
PPTX
04. Project planning and management.pptx
PPT
223417 Diploma_Sem4_software_engg-chap-05.ppt
PDF
Software Project Management | An Overview of the Software Project Management
PDF
significance_of_test_estimating_in_the_software_development.pdf
PDF
Asset Finance Systems: Project Initiation "101"
DOCX
Project management
Shot note about project management
Mb0049 (2) May 2012 Master of Business Administration - MBA Semester 2 MB0049...
Revised CHAPTER-TWO.pptppppppppppppppppp
Basics in Project Management
PM-1 Overview.ppt
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
Asset Finance Systems: Project Initiation "101"
1_slides bài giảng - SoftwareProjectManagement.pptx
Software metrics in software engineering
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
Project Management A Managerial Approach 8th Edition Meredith Solutions Manual
Project planning.pptx
Project planning.pptx
04. Project planning and management.pptx
223417 Diploma_Sem4_software_engg-chap-05.ppt
Software Project Management | An Overview of the Software Project Management
significance_of_test_estimating_in_the_software_development.pdf
Asset Finance Systems: Project Initiation "101"
Project management

More from Indu Sharma Bhardwaj (17)

PPTX
PPT
Ui design final
PPT
Software re engineering
PPT
Software process and project metrics
PPT
Software maintenance
PPT
Software resuse
PPT
Risk analysis
PPT
Design final
PPT
PPTX
10 common english mistakes
PPTX
6. static keyword
PPTX
4. method overloading
PPTX
2. hello java
PPTX
1 .java basic
Ui design final
Software re engineering
Software process and project metrics
Software maintenance
Software resuse
Risk analysis
Design final
10 common english mistakes
6. static keyword
4. method overloading
2. hello java
1 .java basic

Recently uploaded (20)

PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
Cell Structure & Organelles in detailed.
PDF
Pre independence Education in Inndia.pdf
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PPTX
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
PDF
VCE English Exam - Section C Student Revision Booklet
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Module 4: Burden of Disease Tutorial Slides S2 2025
102 student loan defaulters named and shamed – Is someone you know on the list?
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
O7-L3 Supply Chain Operations - ICLT Program
Cell Structure & Organelles in detailed.
Pre independence Education in Inndia.pdf
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
TR - Agricultural Crops Production NC III.pdf
Microbial disease of the cardiovascular and lymphatic systems
O5-L3 Freight Transport Ops (International) V1.pdf
PPH.pptx obstetrics and gynecology in nursing
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
STATICS OF THE RIGID BODIES Hibbelers.pdf
Introduction to Child Health Nursing – Unit I | Child Health Nursing I | B.Sc...
VCE English Exam - Section C Student Revision Booklet

Software project management

  • 1. 1 Software Project Management Indu Sharma HOD(CSE) CPTC,Rajsamand
  • 2. 2 Introduction  Project Management is an integrated part of software development.  It refers to manage the complete software project.  The goal is to provide the necessary support for development to proceed smoothly and reduce any development problem. Its basic task is to ensure that, once a development process is chosen, it is implemented optimally.  Effective s/w project management focuses on the 4 P’s: The People, The Product, The Process, and The Project.
  • 3. 3 Introduction I. The People:  People-intensive  SEI has developed a “People Management- Capability Maturity Model” (PM-CMM):  This model defines the key practice areas for s/w people: recruitment, selection, performance management, training, compensation, career development, organization and work design, and team/culture development.  Team leaders: Motivation, Innovative, Problem solving, influence and team building.
  • 4. 4 Introduction II. The Product:  Product objectives: Overall goals (from the customer’s point of view) without considering how these goals will be achieved.  Scope: identifies its primary data, functions, and behaviors.  Alternative Solutions: Once the project objectives and scope are understood, alternative solutions are considered. The alternative solutions enable managers to select a “best” approach, given the constraints imposed by the delivery deadlines, budgetary restrictions, personnel availability, technical interfaces etc.
  • 5. 5 Introduction III. The Process:  The way in which we produce the software.  Provides a framework from which a comprehensive plan for s/w development can be established.  Problem is to select the appropriate process model.  The project manager must decide which process model is appropriate for:  The customer who have requested the product  The characteristics of the product itself, and  The projcect environment in which the s/w team works.
  • 6. 6 Introduction IV. The Project:  In order to manage successful s/w projects, we must understand what can go wrong and how to do it right. Ten signs that indicate the project is in danger: i. S/w people don’t understand their customer’s need. ii. The product scope is poorly defined. iii. Changes are managed poorly. iv. The chosen technology changes. v. Business needs change (or ill defined).
  • 7. 7 Introduction vi. Deadlines are unrealistic. vii. Users are resistant. viii. Sponsorship is lost ( or was never properly obtained) ix. The project team lacks people with appropriate skills. x. Managers avoid practices and lessones learned.
  • 8. 8 Introduction  Five commonsense approach to avoid problems to s/w projects:  Start on the right foot:  Working hard to understand the problem.  Building the right team and giving the team autonomy, authority, and technology needed to the job.  Maintain Momentum:  Good start and then slowly disintegrate  To maintain momentum, the project manager must provide incentives, should emphasize quality in every task it performs etc.  Track progress:  Progress is tracked as work products.
  • 9. 9 Introduction  Make smart decisions:  Keep it simple.  Use of existing s/w components  Decide to avoid custom interfaces when standard approaches are available.  Decide to identify and then avoid obvious risks.  Decide to allocate more time than you think is needed to complex or risky tasks.
  • 10. 10 Introduction  Conduct a postmortem analysis:  Establish consistent mechanism for extracting lessons learned for each project.  Evaluate the planned and actual schedules, collect and analyze s/w project metrics, get feedback from team members and customers, and record finding is in written form.
  • 11. 11 Activities  The activities in the management process for a project can be grouped broadly into three phases:  Project planning  Project Monitoring & Control  Project Termination
  • 12. 12 Project Planning  Project management begins with planning, which is the perhaps most critical project management activity.  Lack of proper planning is sure ticket to failure for a large s/w project.  A s/w plan is usually produced before the development activity begins and is updated as development proceeds and data about progress of the project becomes available.
  • 13. 13 Project Planning  The major issues project planning addresses are: I. Process Planning II. Effort estimation III. Project scheduling and staffing IV. Configuration Management Plan V. Quality Plans VI. Risk Management VII. Project Monitoring plans
  • 14. 14 I Process Planning  For a project during planning, a key activity is to plan and specify the process that should be used in the project.  It means the various stages in the process, the entry criteria for each stage, the exit criteria, the verification activities that will be done at the end of the stage.  Some standard process model may be used as a standard process and tailored to suit the needs of the project.
  • 15. 15 II Effort Estimation  For a given set of requirements it is desirable to know how much it will cost to develop the s/w and how much time the development will take. These estimates are needed before development is initiated.  The primary reason for cost and schedule estimation are:  Cost and benefit analysis  Project monitoring and control  More practical use: bidding for s/w projects
  • 16. 16 Effort Estimation  Because the s/w development is labour- intensive(i.e. human resources), most cost estimation procedures focuses on estimating effort in terms of Person-Months(PM).  Effort and schedule estimation is required to answer the questions like:  Is the project late?  Are there cost overruns?  When is the project likely to complete?  What staffing level is required during different phases?
  • 17. 17 Effort Estimation  To achieve reliable effort estimation in terms of cost , a no. of options arise: a) Delay estimates until late in the project. Not practical, as cost estimation must be provided “up- front” b) Base estimates on similar projects that have already been completed Can work reasonably well, if the current project is quite similar to past efforts. c) Use relatively simple decomposition techniques to generate project cost and effort estimation. d) Use one or more empirical models for s/w cost and effort estimation. (c) And (d) are viable approaches to s/w project estimation.
  • 18. 18 Measure, Measurement, Metrics and Indicators  Although, the terms measure, measurement, and metrics are often used interchangeably, but it is important to note the subtle differences between them.  Measure: A measure provides a quantitative indication of the extent, amount, dimension, capacity, or size of some attributes of a product or process.  Measurement: Measurement is the act of determining a measure.  Metric: A quantitative measure of the degree to which a system, component, or process possesses a given attribute.
  • 19. 19 Measure, Measurement, Metrics and Indicators  Example:  When a single data point has been collected (e.g., the number of errors uncovered in the review of a single module), a measure has been established. Measurement occurs as the result of the collection of one or more data points (e.g., a number of module reviews are investigated to collect measures of the number of errors in each module). A software metric relates the individual measures in some way (e.g., the average number of errors found per review).
  • 20. 20 Measure, Measurement, Metrics and Indicators  A software engineer collects measures and develops metrics so that indicators will be obtained. An indicator is a metric or combination of metrics that provide insight into the software process, a software project, or the product itself.  An indicator provides insight that enables the project manager or software engineers to adjust the process, the project, or the process to make things better.
  • 21. 21 Measure, Measurement, Metrics and Indicators  For example, four software teams are working on a large software project. Each team must conduct design reviews but is allowed to select the type of review that it will use. Upon examination of the metric, errors found per person-hour expended, the project manager notices that the two teams using more formal review methods exhibits an errors found per person-hour expended that is 40% higher than the other teams. Assuming all parameters are equal, this provides the project manager with an indicator that formal review methods may provide a higher return on time investment than another, less formal review approach. She may decide to suggest that all teams use the more formal approach.
  • 22. 22 Metrics  Because the s/w has not physical attributes, conventional metrics are not much help in designing metrics of s/w. A number of metrics have been proposed to quantify things like the size, complexity, and reliability of a s/w product.  A s/w metrics relates the individual measures in some way. Eg. Avg lines of code: KLOC per module Avg number of errors found per module
  • 23. 23 Metrics  There are three types of metrics:  Product Metrics: Product metrics are used to quantify characteristics of the product being developed i.e. Software. Eg. Size, complexity, performance, efficiency, portability, reliability etc.  Process Metrics: Process metrics are used to quantify characteristics of the process being used to develop the s/w. Eg. Effort required in the process, time to produce the product, effect of development techniques and tools, no. of defects found during testing etc.
  • 24. 24 Metrics  Project Metrics: are used for strategic purposes. That is, project metrics and indicators derived from them are used by a project manager and a software team to adapt project work flow and technical activities.  Two purpose:  First, to minimize the development schedule by making necessary adjustments in order to avoid delays and alleviate potential risks and problems.  Secondly, these metrics are used to assess the product quality on a regular basis and modify the technical issues if required. As the quality improves, the number of errors and defects are reduced, which in turn leads to a decrease in the overall cost of a software project.
  • 25. 25 Metrics  Values of metrics can be measured directly or indirectly.  Directly:  eg. Distance can be directly measured.  eg. Size of the s/w (LOC), cost, execution speed etc.  Indirectly:  eg. Distance = speed * time  eg. Reliability has to be estimated from other possible measurements, quality, complexity, maintainability etc.
  • 26. 26 Decomposition Techniques  Decomposition techniques take a “divide and conquer” approach to s/w project estimation.  Decomposition techniques are used to estimate cost and effort by decomposing the complete project problem into subsequent parts. Now, first these parts or subdivisions are solved one-by-one and after their solutions can be combined to form a whole.  The s/w size is the most important factor that effects the cost. LOC and FP-Based are distinct estimate techniques for s/w size.  If a direct approach is chosen, size can be measured in LOC. If an indirect approach is chosen, size is represented in FP.
  • 27. 27 LOC-Based Estimation  It simply refers to the no. of lines of the delivered source code.  Eg. 5000 KLOC  LOC  From this a set of simple size-oriented metrics can be developed:  Errors / KLOC, Defects / KLOC, $ / KLOC  Other Metrics:  Errors / person-month  LOC / Person-month  $ / page of documentation
  • 28. 28 LOC-Based Estimation  Advantages:  Simple to measure  It can be determined uniquely by automated tools once the project is completed.  Drawbacks:  It is defined on code. For example it can’t measure the size of specification.  It characterize only one specific view of size, name length, it takes no account of functionality or complexity.  Bad s/w design may cause excessive line of code  It is language dependent.