Julian Griffiths Principal Consultant 7/15/2008
The Process The process described here is recommended when it is a significant project in terms of: budget the affect on the business In many cases a simplified approach can be adopted. Consider using a consultant for complex purchases. 7/15/2008
1. Specification Produce a system specification document to be agreed internally before external distribution. Outline your business strategy and vision. Consider likely future scenarios. Highlight your current systems weaknesses Determine the need for change and list key requirements 7/15/2008
2. Prepare a Request for Information (RFI) An extension of your approved specification document to be distributed to potential software solution providers to include: Specifications as above Platform and database requirements Estimates for capacity & transaction volumes Proposed timescales and milestones Decision making process Budgets Response process 7/15/2008
RFI Document This document will form the basis of your relationship with potential vendors. Once stage three starts you will have indicated your interest to suppliers so it should contain the ‘rules of engagement’ in the response process. 7/15/2008
3. Identify Potential Vendors Investigate industry specific software vendors. Find out which software your competition uses. Ask for advice from professional bodies. Visit exhibitions and conferences. Ask IT consultants. Search the Web and publications. Read white papers. Attend seminars and briefings. 7/15/2008
4. Distribute the RFI Limit the number of vendors to ~10. Enforce the rules of engagement and try to avoid meetings with vendors until responses are reviewed. Appoint a ‘gatekeeper’ to manage the potential barrage of calls. Clarify the response process 7/15/2008
5. Evaluate the responses This is the vendors first and sometimes only opportunity to impress you and make it to a shortlist. The vendor should have put a reasonable amount of time into reviewing your RFI and responding to your issues with a relevant solution. Ask the vendors to keep it to a reasonable length and send product literature separately. 7/15/2008
Evaluate the responses Review the company profile to ensure that you are confident that the company are able to support your organisation. Be alert to empty sales waffle. Confirm stability of small vendors. Ensure relevant references and case studies Do not accept ‘references available on request’ as you have asked them to be included as part of your evaluation process. 7/15/2008
Evaluate the responses Ensure a full cost estimate is included with: Initial software licence. Annual software licence. Annual maintenance. Consultancy (with detailed breakdown). Development. Customisation. 7/15/2008
6. Draw up a Short List for Demonstrations Try to limit to ~4 vendors. Meet with vendors before. demonstrations so they can understand the company and its operations. Produce an agenda. Control the demonstration. Ensure that it focuses on the key issues that you want to address. Provide dummy sample data as appropriate. 7/15/2008
7. Product / Vendor Demonstrations Schedule enough time. Consider complexity of software. Allow for questions and answers. Ensure that all decision makers for the process are available for all presentations. Formalise the selection team from key process owners and directors. 7/15/2008
Product / Vendor Demonstrations Do not delegate attendance to someone else at presentations. Control the meeting to ensure that all items are covered. A good salesperson will also ensure that any issues raised are covered at the end of the meeting or in a follow up session. Allow for a short follow up session before selecting preferred vendor if required. 7/15/2008
8. Take up References Ensure the references are in the same industry with a similar number of users. Ensure the reference has been live long enough to properly exercise the system. Obtain multiple contacts e.g.: Senior/expert users. IT Manager. Your equivalent 7/15/2008
Take up References Prepare questions in advance & cover issues that are important to you. Quality of project management and consultants. Was the project implemented on time? Was data migration successful and to what level of detail. How have upgrades affected the system? Are support calls answered in good time? Call the references. Calls are usually open and honest and a lot of information can be gleaned. 7/15/2008
9. Choose a preferred Vendor Consider everything. Initial proposal. Presentation. Follow up sessions. References. Involve all members of selection team. Be immune to personalities. Evaluate the software and the company as a whole, not just the sales team. 7/15/2008
10. Arrange a follow up meeting Time should be spent with key process owners in detailed workshop sessions to investigate installation, deployment & use processes. Involve as appropriate: board members managers technical/administrators day to day users Document as much as possible in sufficient detail. 7/15/2008
11. Consider wider implications Can your infrastructure support the new software? Server, storage, backup and network capacity Will staff need training? Is the software compatible with existing systems? 7/15/2008
12. Obtain a Final Proposal Your preferred vendor will now have a detailed understanding and be prepared to present a final proposal to include: Detailed software module and user requirements. Consultancy. Customisation. Updated proposed project plan. Identified resources. 7/15/2008
13. Negotiation The vendor will expect a negotiation and will have established their baseline. Be prepared to give something for discounts. Press release. Acting as a reference site. Consider leasing. Many leasing companies work with software vendors and offer good rates and sometimes no payment until going live. 7/15/2008
14. Implementation That’s another presentation 7/15/2008

More Related Content

PPTX
Best Practices in Software Vendor Selection
PPTX
52 Software Selection Tips to Pick the Best-Fit Software and Impress Your Col...
PDF
10 Steps To Successful Enterprise Software Selection
PPTX
The Vendor Selection Guide - How to on Assessing Vendor Viability
PPT
Business Alignment
PDF
Analysis & Business Requirements
PPSX
Requirement Management
PPT
System Design and Analysis 2
Best Practices in Software Vendor Selection
52 Software Selection Tips to Pick the Best-Fit Software and Impress Your Col...
10 Steps To Successful Enterprise Software Selection
The Vendor Selection Guide - How to on Assessing Vendor Viability
Business Alignment
Analysis & Business Requirements
Requirement Management
System Design and Analysis 2

What's hot (18)

PPTX
Trends in Software Outsourcing: Best Practices
PPT
Requirements Gathering And Management
PPTX
Requirements Gathering Best Practice Pack
PDF
Vendor Management: How Well Are You Managing Your Consultants and Appraisers?
 
PDF
Solution Architecture And (Robotic) Process Automation Solutions
PDF
Software Outsourcing: Outsource Your Project or Build a Team
PPTX
Ronan Consulting Group - Systems Selection and Implementation
PPT
Business user requirements for it development
PDF
Vendor Management Best Practices: Is Your Program Up to Par?
 
PPT
Downloads abc 2006 presentation downloads-ramesh_babu
PPTX
How to Gather Requirements
PDF
Building a bullet proof business case
PPTX
Innovation Lab Intake Project for LinkedIn
PPTX
Business process analysis and optimization: A pragmatic approach to business ...
PDF
The Mysterious Process of Business Analysis Solved
PDF
Equipment finance systems project guide "101"
PDF
Equipment finance systems project guide "101"
PDF
Equipment finance projects guide "101"
Trends in Software Outsourcing: Best Practices
Requirements Gathering And Management
Requirements Gathering Best Practice Pack
Vendor Management: How Well Are You Managing Your Consultants and Appraisers?
 
Solution Architecture And (Robotic) Process Automation Solutions
Software Outsourcing: Outsource Your Project or Build a Team
Ronan Consulting Group - Systems Selection and Implementation
Business user requirements for it development
Vendor Management Best Practices: Is Your Program Up to Par?
 
Downloads abc 2006 presentation downloads-ramesh_babu
How to Gather Requirements
Building a bullet proof business case
Innovation Lab Intake Project for LinkedIn
Business process analysis and optimization: A pragmatic approach to business ...
The Mysterious Process of Business Analysis Solved
Equipment finance systems project guide "101"
Equipment finance systems project guide "101"
Equipment finance projects guide "101"
Ad

Viewers also liked (12)

PPT
Brian Dirking Software Selection For Records Management
PPTX
Process of software selection
PDF
Software selection and implementation in the real world
PDF
Core Banking Transformation: Solutions to Standardize Processes and Cut Costs
PPTX
Recruitment process Of IBM
PDF
How Digital Has Changed These 7 Banking Roles
 
PDF
Creating a Digital Banking Strategy - 01.23.15
PDF
Bank: Trends, Tech and Future
PDF
Disruption in Digital Banking
PPTX
Digital Banking Strategy Roadmap - 3.24.15
PDF
Digital in 2016
Brian Dirking Software Selection For Records Management
Process of software selection
Software selection and implementation in the real world
Core Banking Transformation: Solutions to Standardize Processes and Cut Costs
Recruitment process Of IBM
How Digital Has Changed These 7 Banking Roles
 
Creating a Digital Banking Strategy - 01.23.15
Bank: Trends, Tech and Future
Disruption in Digital Banking
Digital Banking Strategy Roadmap - 3.24.15
Digital in 2016
Ad

Similar to Software Selection (20)

PPTX
Vendor Selection Process
PDF
Collaborative Technology Procurement
PPT
Content Marketing Software RFP: A Framework to Determine Marketer Needs & Sol...
PDF
Getting started with bi
PDF
Top 10 Tips
PPT
[Slides] Content Marketing Software RFP, by Altimeter Group
PPTX
Clarity It Sourcing Diagnostic Presentation
PPT
Reqs analysis
PPTX
Take The Highway To A Successful It Project
DOCX
40 JANUARYFEBRUARY 2010 INFORMATIONMANAGEMENTSelecting .docx
PPT
Business Process Management - Choosing The Right Supplier
PPT
Week8 Topic1 Translate Business Needs Into Technical Requirements
PPTX
Marketing Automation 101
PPTX
Final Presentation
PPTX
Hi600ch07_text_slides
PDF
Selecting a Software Solution: 13 Best Practices for Media and Entertainment ...
PPTX
Master Contract Review and Negotiation For Software Agreements-sample
PPTX
Cost of Poor quality
PDF
Top Software panies to Outsource.pdfTesting Com
PDF
UX STRAT Europe 2019: Nur Karadeniz, Fjord
Vendor Selection Process
Collaborative Technology Procurement
Content Marketing Software RFP: A Framework to Determine Marketer Needs & Sol...
Getting started with bi
Top 10 Tips
[Slides] Content Marketing Software RFP, by Altimeter Group
Clarity It Sourcing Diagnostic Presentation
Reqs analysis
Take The Highway To A Successful It Project
40 JANUARYFEBRUARY 2010 INFORMATIONMANAGEMENTSelecting .docx
Business Process Management - Choosing The Right Supplier
Week8 Topic1 Translate Business Needs Into Technical Requirements
Marketing Automation 101
Final Presentation
Hi600ch07_text_slides
Selecting a Software Solution: 13 Best Practices for Media and Entertainment ...
Master Contract Review and Negotiation For Software Agreements-sample
Cost of Poor quality
Top Software panies to Outsource.pdfTesting Com
UX STRAT Europe 2019: Nur Karadeniz, Fjord

Recently uploaded (20)

PDF
A Brief Introduction About Julia Allison
PDF
MSPs in 10 Words - Created by US MSP Network
PPTX
Business Ethics - An introduction and its overview.pptx
PDF
Business model innovation report 2022.pdf
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PPTX
5 Stages of group development guide.pptx
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
Training And Development of Employee .pdf
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
DOCX
Business Management - unit 1 and 2
PPT
Chapter four Project-Preparation material
PDF
How to Get Funding for Your Trucking Business
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
HR Introduction Slide (1).pptx on hr intro
DOCX
Euro SEO Services 1st 3 General Updates.docx
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
A Brief Introduction About Julia Allison
MSPs in 10 Words - Created by US MSP Network
Business Ethics - An introduction and its overview.pptx
Business model innovation report 2022.pdf
340036916-American-Literature-Literary-Period-Overview.ppt
Reconciliation AND MEMORANDUM RECONCILATION
5 Stages of group development guide.pptx
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
Training And Development of Employee .pdf
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Ôn tập tiếng anh trong kinh doanh nâng cao
Business Management - unit 1 and 2
Chapter four Project-Preparation material
How to Get Funding for Your Trucking Business
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
ICG2025_ICG 6th steering committee 30-8-24.pptx
Laughter Yoga Basic Learning Workshop Manual
HR Introduction Slide (1).pptx on hr intro
Euro SEO Services 1st 3 General Updates.docx
BsN 7th Sem Course GridNNNNNNNN CCN.pdf

Software Selection

  • 1. Julian Griffiths Principal Consultant 7/15/2008
  • 2. The Process The process described here is recommended when it is a significant project in terms of: budget the affect on the business In many cases a simplified approach can be adopted. Consider using a consultant for complex purchases. 7/15/2008
  • 3. 1. Specification Produce a system specification document to be agreed internally before external distribution. Outline your business strategy and vision. Consider likely future scenarios. Highlight your current systems weaknesses Determine the need for change and list key requirements 7/15/2008
  • 4. 2. Prepare a Request for Information (RFI) An extension of your approved specification document to be distributed to potential software solution providers to include: Specifications as above Platform and database requirements Estimates for capacity & transaction volumes Proposed timescales and milestones Decision making process Budgets Response process 7/15/2008
  • 5. RFI Document This document will form the basis of your relationship with potential vendors. Once stage three starts you will have indicated your interest to suppliers so it should contain the ‘rules of engagement’ in the response process. 7/15/2008
  • 6. 3. Identify Potential Vendors Investigate industry specific software vendors. Find out which software your competition uses. Ask for advice from professional bodies. Visit exhibitions and conferences. Ask IT consultants. Search the Web and publications. Read white papers. Attend seminars and briefings. 7/15/2008
  • 7. 4. Distribute the RFI Limit the number of vendors to ~10. Enforce the rules of engagement and try to avoid meetings with vendors until responses are reviewed. Appoint a ‘gatekeeper’ to manage the potential barrage of calls. Clarify the response process 7/15/2008
  • 8. 5. Evaluate the responses This is the vendors first and sometimes only opportunity to impress you and make it to a shortlist. The vendor should have put a reasonable amount of time into reviewing your RFI and responding to your issues with a relevant solution. Ask the vendors to keep it to a reasonable length and send product literature separately. 7/15/2008
  • 9. Evaluate the responses Review the company profile to ensure that you are confident that the company are able to support your organisation. Be alert to empty sales waffle. Confirm stability of small vendors. Ensure relevant references and case studies Do not accept ‘references available on request’ as you have asked them to be included as part of your evaluation process. 7/15/2008
  • 10. Evaluate the responses Ensure a full cost estimate is included with: Initial software licence. Annual software licence. Annual maintenance. Consultancy (with detailed breakdown). Development. Customisation. 7/15/2008
  • 11. 6. Draw up a Short List for Demonstrations Try to limit to ~4 vendors. Meet with vendors before. demonstrations so they can understand the company and its operations. Produce an agenda. Control the demonstration. Ensure that it focuses on the key issues that you want to address. Provide dummy sample data as appropriate. 7/15/2008
  • 12. 7. Product / Vendor Demonstrations Schedule enough time. Consider complexity of software. Allow for questions and answers. Ensure that all decision makers for the process are available for all presentations. Formalise the selection team from key process owners and directors. 7/15/2008
  • 13. Product / Vendor Demonstrations Do not delegate attendance to someone else at presentations. Control the meeting to ensure that all items are covered. A good salesperson will also ensure that any issues raised are covered at the end of the meeting or in a follow up session. Allow for a short follow up session before selecting preferred vendor if required. 7/15/2008
  • 14. 8. Take up References Ensure the references are in the same industry with a similar number of users. Ensure the reference has been live long enough to properly exercise the system. Obtain multiple contacts e.g.: Senior/expert users. IT Manager. Your equivalent 7/15/2008
  • 15. Take up References Prepare questions in advance & cover issues that are important to you. Quality of project management and consultants. Was the project implemented on time? Was data migration successful and to what level of detail. How have upgrades affected the system? Are support calls answered in good time? Call the references. Calls are usually open and honest and a lot of information can be gleaned. 7/15/2008
  • 16. 9. Choose a preferred Vendor Consider everything. Initial proposal. Presentation. Follow up sessions. References. Involve all members of selection team. Be immune to personalities. Evaluate the software and the company as a whole, not just the sales team. 7/15/2008
  • 17. 10. Arrange a follow up meeting Time should be spent with key process owners in detailed workshop sessions to investigate installation, deployment & use processes. Involve as appropriate: board members managers technical/administrators day to day users Document as much as possible in sufficient detail. 7/15/2008
  • 18. 11. Consider wider implications Can your infrastructure support the new software? Server, storage, backup and network capacity Will staff need training? Is the software compatible with existing systems? 7/15/2008
  • 19. 12. Obtain a Final Proposal Your preferred vendor will now have a detailed understanding and be prepared to present a final proposal to include: Detailed software module and user requirements. Consultancy. Customisation. Updated proposed project plan. Identified resources. 7/15/2008
  • 20. 13. Negotiation The vendor will expect a negotiation and will have established their baseline. Be prepared to give something for discounts. Press release. Acting as a reference site. Consider leasing. Many leasing companies work with software vendors and offer good rates and sometimes no payment until going live. 7/15/2008
  • 21. 14. Implementation That’s another presentation 7/15/2008