Published Since 1993                                           Report #TCG2009040LI                           September 21, 2009


   IBM Takes Command of the UNIX Data Center —
       POWER7 Enables Growth, Lower Costs
                                                          Analyst: David Reine

 Management Summary
      Striving for excellence is a human trait shared by many, as we all try to be the best that we can in at least
 one area under our control. Achieving excellence is a little harder to accomplish; it requires an amount of hard
 work and dedication that only a select few are willing to deliver. Improving on excellence, on the other hand,
 requires that rare individual who sets his sights on being the best in the world at whatever he attempts and
 continues to work harder than everyone else, even after he has arrived at the pinnacle of his quest. Individuals
 like Olympic athletes Michael Phelps and Usain Bolt each set world records (in swimming and track), yet each
 continues to train even harder to break their own records and reap the rewards of these continuing efforts.
      This same quality of continuing to improve on success is an essential requirement for every enterprise data
 center looking to improve upon the performance of its IT infrastructure, ensure the security and reliability of its
 environment, and continue to lower the total cost of ownership (TCO) of that infrastructure in the face of
 increasing demands. The deployment of new applications on new servers and the continuing explosion of data,
 which tends to be doubling every 12-to-18 months, are putting a strain on the budgets of every enterprise data
 center around the globe. Programs are being implemented to consolidate and virtualize both servers and storage
 to reduce the TCO and preserve valuable resources, both human and natural. By reducing the number of
 physical servers populating the data center, the CIO can reduce the number of systems administrators required
 to drive the IT infrastructure, as well as reducing the amount of energy necessary to power the data center, and
 the amount of floor space required to house it. These last two points are especially critical as enterprise
 data centers approach maximum capacity in both of these categories. In fact, if either is exceeded, the
 enterprise may be forced to build out a brand new data center at a cost of millions of dollars.
      For decades, UNIX systems vendors have been providing continual and timely upgrades, enabling cus-
 tomers to run more applications, respond faster, and/or process more data without having to worry about
 architecture compatibility. Either the UNIX vendor delivered higher performance, expanded memory, and
 improved RAS, etc., or the customer would eventually migrate to a better platform. For decades, UNIX server
 vendors have provided the data center with continual, and timely, upgrade paths. This enables them to replace
 existing legacy environments with fully compatible servers that run the same operating environments on the
 same IT architectures with higher performance, expanded memory capacity, and improved RAS (reliability,
 availability, and serviceability) characteristics. In recent years, this cut-throat battle left three UNIX vendors
 focused on scale-up, UNIX applications dominating the landscape: IBM, with AIX running on POWER systems,
 HP with HP-UX on Integrity, and Sun, with Solaris running on SPARC systems. For some, expected upgrade
 plans have hit a major hurdle; however, with customers now assessing Oracle’s acquisition of Sun, putting the
 future of SPARC under the microscope, and continued
 delays in the next generation of Intel’s Itanium archi-                      IN THIS ISSUE
 tecture (Tukwila), putting the future of Integrity in
 question, as well. Only IBM continues to provide the           Enterprise Data Center Requirements .. 2
 scale-up UNIX data center with a plan, and a predic-
                                                                A History of POWER ............................... 2
 table drumbeat, for the future. To learn more about
 IBM’s forthcoming POWER7 and AIX7, please read                 POWER7 Takes Command..................... 3
 on.                                                            Conclusion .............................................. 4

   The Clipper Group, Inc. - Technology Acquisition Consultants Strategic Advisors
     888 Worcester Street Suite 140 Wellesley, Massachusetts 02482 U.S.A. 781-235-0085 781-235-5454 FAX
                        Visit Clipper at www.clipper.com Send comments to editor@clipper.com
The Clipper Group Navigator
                                                                                     TM
September 21, 2009                                                                                                  Page 2

Enterprise Data Center Requirements                              Systems are designed for RAS; designed, by the
     In the past, the data center had simply needed to           same team that defined what “mainframe-class”
go faster and be less expensive. Now, however, the               really means. Power Systems are deployed with
enterprise requires the data center to also run                  RAS at every level: from the processor, to memory,
smarter. Medical facilities need to use IT to im-                to I/O, to the system itself.
prove health care; the weather bureau needs to be                     Every UNIX-involved CIO needs to ask, “How
able to make better predictions, especially as the               does Xeon 5500 stack up against today’s UNIX/
next hurricane is headed toward the U.S. coastline.              RISC engines? How does it stack up against IBM’s
Furthermore, every data center needs to improve its              POWER architecture?” The reality is that IBM’s
energy efficiency with more intelligence being used              POWER6-based platforms exceed the capability of
to protect our natural resources.                                servers built with the Xeon 5500, or for that matter
     In order to increase performance, lower cost,               Intel’s Itanium microprocessor, in terms of database
and run smarter, today’s CIOs are looking to                     transactions, OLTP, integer throughput, and floating
consolidate their mission-critical applications on               point capabilities. POWER6 also leads in terms of
fewer, faster servers and to virtualize those appli-             memory capacity per core, memory bandwidth per
cations to make more efficient utilization of their              core, I/O bandwidth, and L2, L3 cache.
data center resources, both human and natural.                        Over the past two decades, IBM has used its
With the typical scale-out server operating at less              POWER architecture continually to improve the
than 20% utilization, the data center has to change              performance level of its Power Systems to improve
the operational paradigm to make better use of                   the mission-critical application environment for the
enterprise resources. To do this, the data center                enterprise. Now, once again, IBM has announced
is looking for the server platform that has,                     further innovations in this architecture to enable
among other requirements, the highest perfor-                    more consolidation and better virtualization in order
mance level in a virtualized environment. Typi-                  to encapsulate more workloads within each virtual
cally, that can be measured in terms of the number               machine, improving energy efficiency, and lowering
of cores available per processor, the number of                  TCO. As the leading world-class athlete in these
threads available per core, the bandwidth on a CPU-              arenas, when it arrives, POWER7 is expected to
to-CPU basis, the amount of shared cache, the                    make its debut in the data center with perfor-
amount of memory supported and the memory                        mance and functionality to blow away the re-
bandwidth, and the I/O bandwidth capability, not to              cords set by POWER6.
mention the server scalability and RAS functionality.
     In response to these requirements, Intel focused            A History of POWER
its efforts on improving its Xeon architecture to                     IBM has always exhibited a regular develop-
meet the data center needs for consolidation and                 ment schedule for the POWER3 architecture, from
virtualization. Specifically, it has announced the               its inception in 1990, with improvements in
Xeon 5500 (Nehalem) to achieve this functionality                performance and functionality at every step of the
and reduce data center TCO. And, in fact, com-                   way. Over the past decade, POWER4 added LPARs
pared to the Xeon 5400, Nehalem can be considered                (Logical Partitions) to the architecture in 2001;
an unqualified success, with significant improve-                POWER5 introduced Advanced POWER Virtuali-
ments in database transaction count, integer and                 zation in 2004; and POWER6 provided Live Parti-
floating-point throughput, memory scalability, and               tion Mobility in 2007. Like a Swiss clock, every
memory bandwidth. Unfortunately for Xeon, the                    three years IBM has delivered innovations to the
traditional enterprise data center has not been de-              POWER architecture, including improved vir-
ploying an x86 environment for the past 40 years; it             tualization through PowerVM, along with corres-
has been deploying applications based on main-                   ponding improvements in the operating environ-
frames, UNIX, or AS/400 (System i). One of the                   ment and systems management. It must be noted
reasons for that is reliability, with Windows-based              here that IBM has a history of leadership in
servers exhibiting over 150 minutes of unscheduled               virtualization, dating back to the origins of the
outages per year, compared to, for example, only 15              first hypervisor providing full virtualization –
minutes per year for AIX1 -based Power Systems                   over 40 years ago – on the mainframe, which led
with less than one outage per year2 . IBM’s Power                to today’s z/VM.

1
  AIX is the IBM version of UNIX that runs on all POWER
systems.
2                                                                3
  Source: IBM.                                                       Performance Optimized With Enhanced RISC.

Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
The Clipper Group Navigator
                                                                                    TM
September 21, 2009                                                                                                    Page 3

     Every iteration of the POWER architecture has                            Exhibit 1 – Emerging
delivered improvements in the primary require-                               Benefits of Virtualization
ments for large scale computing for the data center.
These include scalability, performance, RAS, and                     • Reduced IT management costs
manageability. Equally important, however, are the                   • Better Software investment protection
improvements to the bottom line in lowering the                      • Dynamic energy optimization
TCO of the IT infrastructure. These improvements                     • Simplified High Availability and Disaster
include:                                                              Recovery solutions
• The virtualization of the AIX application suite –                  • Improved resource optimization
  improving the utilization of Power servers up to                   • Greater IT agility
  60 to 80% along with the capability for rapid                      • Turnkey packaged applications
  deployment and dynamic change;
                                                                     • Improved security foundation
• Energy Efficiency to lower power consumption
  and reduce energy cost by up to 90%, delivering
  more work per watt with each new release of                    processor at 5.0GHz, along with the only tpmC4
  Power;                                                         result over six million transactions/minute. With
• Providing Business Resiliency for continuous                   POWER6, IBM introduced Live Partition Mobility,
  availability and to dynamically respond to a                   Workload Partitions, Active Memory Sharing, and
  changing business environment with no down-                    multiple shared memory pools, along with Active
  time or manual intervention, maintaining                       Energy Manager: EnergyScale, and IBM Systems
  99.997% uptime with only 15 minutes of un-                     Director VMControl providing a consistent cross-
  scheduled outage per year; and                                 platform management for physical and virtual en-
• Simplification of Management through an ever-                  vironments. POWER7 will extend those capabil-
  evolving IBM Systems Director, enabling control                ities to take a clear leadership role in the deploy-
  over deployments and energy usage.                             ment of UNIX systems in the data center.
     Delivering a fully integrated solution gives IBM            POWER7 also will enable IBM to supercharge the
a tremendous advantage in consolidation and vir-                 System i platform, enabling them to deliver more
tualization, enabling them to remove complexity                  performance and functionality for Linux on Power
from the IT environment and simplify data center                 Systems5 .
operations before the platform is even deployed.                      With the looming probability of the sun setting
Power Systems are designed, developed, and tested                on SPARC, and HP experiencing delays in the
as an integrated server platform with a balanced                 availability of the next version of Integrity due to
systems design, enabling linear performance as                   delays in Tukwila, the quad-core Itanium pro-
core-count and utilization increase. Functionality is            cessor6 , IBM, with POWER7 is in the right place at
optimized across the layers of the system stack,                 the right time. It has been reported as recently as
including hardware, hypervisor, operating system                 this past June that Sun has officially killed off the
(AIX, i, or Linux), middleware, and Systems Direc-               16-core UltraSPARC-RK processor, known inter-
tor management software. This enables Power Sys-                 nally as Rock, which has been in development for
tems to deliver virtualization capabilities and attri-           more than five years. In the meantime, Intel has
butes that are generally unmatched in an x86 server              indicated that RAS functionality from Itanium is
environment, including performance scalability,                  being added to Nehalem-EX, perhaps signaling an
RAS, energy efficiency, and security. Simply put,                end of life for Itanium.
the integrated combination of POWER architecture                      With a similar portfolio of modular, scalable
and PowerVM enables Power Systems to enjoy a                     offerings as POWER6, POWER7 will be able to
higher consolidation ratio than any x86 server                   deliver a multi-core processor with a higher perfor-
running VMware’s vSphere, with up to 64 virtual                  mance/watt, higher per core performance and more
CPUs and 4096GB of memory per VM under                           total systems performance. It is estimated that a
PowerVM compared with only 8 virtual CPUs with                   Power7 System will have 2-to-5 times the total
255GB of memory with VMware ESX 4.0. For a
more complete list of the emerging benefits of                   4
                                                                    The Transaction Processing Council’s performance bench-
virtualization, see Exhibit 1, above.                            mark.
                                                                 5
                                                                    IBM has Power7 Systems running in the lab with AIX, IBM
POWER7 Takes Command                                             i, and Linux, all operational.
                                                                 6
                                                                    It has been reported that the quad-core Itanium may not be
    With POWER6, IBM has the world’s fastest                     available until 1Q10, two years later than originally planned.

Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
The Clipper Group Navigator
                                                                                      TM
September 21, 2009                                                                                                    Page 4

system aggregate throughput plus a simplified, non-                               Exhibit 2 –
disruptive upgrade path through binary compati-                             POWER Virtualization Today
bility with POWER6 and Live Partition Mobility.
Power7 Systems will possess greater levels of con-                    • Fine-grained dynamic sharing of processors,
solidation, up to 1000 virtual machines per system                      memory, and I/O
and better resource utilization than Power6 Systems                   • Optional dedicated resources
due to dynamic, policy-based energy management                        • Shared dedicated processors
and a single Systems Director console to manage                       • Extreme scalability and robustness
the server and storage network. IBM has already                       • Integrated firmware hypervisor
announced the ability to upgrade a Power 595                          • Virtual I/O Servers layer
system by simply replacing the processor books,
                                                                      • Hardware enforced isolation
including memory, and the system controllers. The
12X I/O drawers and GX adapters will migrate from                     • LPARs and WPARs
Power6 to Power7 servers, preserving earlier in-                      • DLPAR and Processor Folding
vestments.                                                            • Capacity on Demand
     Specifically, the POWER7 processor features                      • Partition Mobility
eight processor cores to deliver four times the per-
formance of POWER6 within the same power
envelope. Each core will have 12 execution units,                servers7 . In fact, IBM has reported that its Migra-
4-way symmetrical multi-threading, and 256KB of                  tion Factory is responsible for more than 1,750
L2 cache per core. Each processor will have 32MB                 migrations from Sun and HP platforms to IBM
of on chip eDRAM for L3 cache to be shared by the                POWER systems over the past three years. Com-
32 threads. This eDRAM is nearly as fast as con-                 bined with the innovations in POWER7 and AIX,
ventional SRAM, but requires far less space and                  Systems Director and Tivoli, IBM cannot help but
standby power. There are dual DDR3 memory con-                   extend its lead in traditional IT environments and
trollers, with four channels per controller, with a              break new ground in Cloud Computing.
sustained memory bandwidth of 100GB/s and a                           With better utilization of hardware, IBM is
scalability of up to 32 sockets, providing 360GB/s               driving down the cost of software licensing, main-
of SMP bandwidth. In addition, POWER7 includes                   tenance, floor space, and energy. It is reducing the
a long list of RAS features to ensure application                TCO for Power Systems throughout the enterprise.
availability.                                                    Despite the turmoil in the rest of the UNIX market,
     The major features of POWER7 Systems in-                    IBM continues to outdo itself in
clude linear scalability, PowerVM virtualization,                delivering a high-performance,
both physical and virtual management, along with                 low-cost application solution to
energy/thermal management. See Exhibit 2, above,                 the data center. If your enterprise
for a list of virtualization features expected in                needs to improve the perfor-
POWER 7.                                                         mance and lower the cost of your
                                                                 IT environment, IBM’s Power
Conclusion                                                       Systems may be just the over-
                                                                 achieving world-record holder
     It is clear to even the most casual observer that           that you seek.                                             SM

IBM’s Power Systems are in a league of their own
today in providing the performance and advanced
virtualization capabilities that are required for
today’s mission- and business-critical workloads.
With over 40 years of virtualization experience and
a commitment to integrate solutions across the sys-
tems stack, IBM continues to maintain a leadership
position in the enterprise data center, even as others
fade into IT history.
     AIX, i, and Linux all run on the POWER archi-
tecture. These three operating environments re-
present almost half of all data center spending on

                                                                 7
                                                                     Other spending is on Windows, Netware, z/OS, and others.

Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
The Clipper Group Navigator
                                                                                    TM
September 21, 2009                                                                                                  Page 5


                               About The Clipper Group, Inc.
    The Clipper Group, Inc., is an independent consulting firm specializing in acquisition
    decisions and strategic advice regarding complex, enterprise-class information tech-
    nologies. Our team of industry professionals averages more than 25 years of real-world
    experience. A team of staff consultants augments our capabilities, with significant
    experience across a broad spectrum of applications and environments.
        The Clipper Group can be reached at 781-235-0085 and found on the web at
        www.clipper.com.
                                                About the Author
    David Reine is Director, Enterprise Systems for The Clipper Group. Mr. Reine
    specializes in enterprise servers, storage, and software, strategic business solutions, and
    trends in open systems architectures. He joined The Clipper Group after three decades in
    server and storage product marketing and program management for Groupe Bull, Zenith
    Data Systems, and Honeywell Information Systems. Mr. Reine earned a Bachelor of
    Arts degree from Tufts University, and an MBA from Northeastern University.
        Reach David Reine via e-mail at dave.reine@clipper.com or at 781-235-0085 Ext.
        123. (Please dial “123” when you hear the automated attendant.)

                          Regarding Trademarks and Service Marks
    The Clipper Group Navigator, The Clipper Group Explorer, The Clipper
    Group Observer, The Clipper Group Captain’s Log, The Clipper Group Voyager,
    Clipper Notes, and “clipper.com” are trademarks of The Clipper Group, Inc., and the
    clipper ship drawings, “Navigating Information Technology Horizons”, and
    “teraproductivity” are service marks of The Clipper Group, Inc. The Clipper Group,
    Inc., reserves all rights regarding its trademarks and service marks. All other trademarks,
    etc., belong to their respective owners.

                                          Disclosure
    Officers and/or employees of The Clipper Group may own as individuals, directly or
    indirectly, shares in one or more companies discussed in this bulletin. Company policy
    prohibits any officer or employee from holding more than one percent of the outstanding
    shares of any company covered by The Clipper Group. The Clipper Group, Inc., has no
    such equity holdings.

                         Regarding the Information in this Issue
    The Clipper Group believes the information included in this report to be accurate. Data
    has been received from a variety of sources, which we believe to be reliable, including
    manufacturers, distributors, or users of the products discussed herein. The Clipper
    Group, Inc., cannot be held responsible for any consequential damages resulting from the
    application of information or opinions contained in this report.




Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.

More Related Content

PDF
System z Technology Summit Streamlining Utilities
PDF
Smart analytic optimizer how it works
PDF
IBM Power Event, Keynote Presentation Doug Davis
PDF
Idc Reducing It Costs With Blades
PPT
Sean hobday strategic accounts 04-12-2010
PDF
PDF
IBM i + POWER7
PDF
IBM Upgrades SVC with Solid State Drives — Achieves Better Storage Utilization
System z Technology Summit Streamlining Utilities
Smart analytic optimizer how it works
IBM Power Event, Keynote Presentation Doug Davis
Idc Reducing It Costs With Blades
Sean hobday strategic accounts 04-12-2010
IBM i + POWER7
IBM Upgrades SVC with Solid State Drives — Achieves Better Storage Utilization

What's hot (17)

PDF
Présentation IBM DB2 Blu - Fabrizio DANUSSO
PDF
Case study 1
PDF
Ibm i (i5/os) 7.1 overview
PDF
Ugif 04 2011 france ug04042011-jroy_part1
PDF
Jamaica Public Service Company, Ltd. cuts costs, simplifies management with I...
PDF
INTERSPORT improves fitness and business flexibility
PDF
Imex Research Virtualization Executive Summary On Slideshare
PDF
IBM e x5 Brochure
PDF
IBM Deep Computing for Education Indusrty
PDF
IBMSystem x3850 X5and x3950 X5 IBMSystems and TechnologyData Sheet
PPT
Zu e x5 training 04 06-2010
PDF
Tachion
PDF
Next-Gen Data Center Virtualization: Studies in Implementation
PDF
Architecting Next Generation Enterprise Network Storage
PDF
Virtualization Performance on the IBM PureFlex System
PDF
How to enhance performance and reduce energy costs in the midmarket with ibm ...
PDF
IBM zEnterprise 114 (z114)
Présentation IBM DB2 Blu - Fabrizio DANUSSO
Case study 1
Ibm i (i5/os) 7.1 overview
Ugif 04 2011 france ug04042011-jroy_part1
Jamaica Public Service Company, Ltd. cuts costs, simplifies management with I...
INTERSPORT improves fitness and business flexibility
Imex Research Virtualization Executive Summary On Slideshare
IBM e x5 Brochure
IBM Deep Computing for Education Indusrty
IBMSystem x3850 X5and x3950 X5 IBMSystems and TechnologyData Sheet
Zu e x5 training 04 06-2010
Tachion
Next-Gen Data Center Virtualization: Studies in Implementation
Architecting Next Generation Enterprise Network Storage
Virtualization Performance on the IBM PureFlex System
How to enhance performance and reduce energy costs in the midmarket with ibm ...
IBM zEnterprise 114 (z114)
Ad

Similar to IBM Takes Command of the UNIX Data Center — POWER7 Enables Growth and Lower Costs (Clipper) (20)

PDF
IBM 'After 5' Session - IBM System X
PDF
Superior Cloud Economics with Power Systems
PDF
IBM’s zEnterprise Really Stretches Its Boundaries — New Windows Are Opened
PDF
SUSE Linux Enterprise Server for IBM Power
PDF
Ibm Power System E850 pod03108 usen
PDF
The Value Of Memory-Dense Servers IBM’s System X Max5 For Its Ex5 Server Family
PDF
The Value of Memory-Dense Servers IBMs System x MAX5 for Its eX5 Server Family
PDF
BM Brings Enterprise Functionality to Mid-Range Storage
PPTX
Dell - 8dec2010
PDF
Open Innovation with Power Systems
PPT
IBM Special Announcement session Intel #IDF2013 September 10, 2013
PPT
transform your busines with superior cloud economics
PPTX
IBM Power Systems Update
PDF
zEnterpise integration of Linux and traditional workload
PDF
Managing change in the data center network
PPT
Aix The Future of UNIX
PDF
IBM Upgrades SVC with Solid State Drives — Achieves Better Storage Utilization
PPTX
Infrastructure Matters
PDF
It's time to optimize
PPT
Key Note Speech A Stepanek 1106
IBM 'After 5' Session - IBM System X
Superior Cloud Economics with Power Systems
IBM’s zEnterprise Really Stretches Its Boundaries — New Windows Are Opened
SUSE Linux Enterprise Server for IBM Power
Ibm Power System E850 pod03108 usen
The Value Of Memory-Dense Servers IBM’s System X Max5 For Its Ex5 Server Family
The Value of Memory-Dense Servers IBMs System x MAX5 for Its eX5 Server Family
BM Brings Enterprise Functionality to Mid-Range Storage
Dell - 8dec2010
Open Innovation with Power Systems
IBM Special Announcement session Intel #IDF2013 September 10, 2013
transform your busines with superior cloud economics
IBM Power Systems Update
zEnterpise integration of Linux and traditional workload
Managing change in the data center network
Aix The Future of UNIX
IBM Upgrades SVC with Solid State Drives — Achieves Better Storage Utilization
Infrastructure Matters
It's time to optimize
Key Note Speech A Stepanek 1106
Ad

More from IBM India Smarter Computing (20)

PDF
Using the IBM XIV Storage System in OpenStack Cloud Environments
PDF
All-flash Needs End to End Storage Efficiency
PDF
TSL03104USEN Exploring VMware vSphere Storage API for Array Integration on th...
PDF
IBM FlashSystem 840 Product Guide
PDF
IBM System x3250 M5
PDF
IBM NeXtScale nx360 M4
PDF
IBM System x3650 M4 HD
PDF
IBM System x3300 M4
PDF
IBM System x iDataPlex dx360 M4
PDF
IBM System x3500 M4
PDF
IBM System x3550 M4
PDF
IBM System x3650 M4
PDF
IBM System x3500 M3
PDF
IBM System x3400 M3
PDF
IBM System x3250 M3
PDF
IBM System x3200 M3
PDF
IBM PowerVC Introduction and Configuration
PDF
A Comparison of PowerVM and Vmware Virtualization Performance
PDF
IBM pureflex system and vmware vcloud enterprise suite reference architecture
PDF
X6: The sixth generation of EXA Technology
Using the IBM XIV Storage System in OpenStack Cloud Environments
All-flash Needs End to End Storage Efficiency
TSL03104USEN Exploring VMware vSphere Storage API for Array Integration on th...
IBM FlashSystem 840 Product Guide
IBM System x3250 M5
IBM NeXtScale nx360 M4
IBM System x3650 M4 HD
IBM System x3300 M4
IBM System x iDataPlex dx360 M4
IBM System x3500 M4
IBM System x3550 M4
IBM System x3650 M4
IBM System x3500 M3
IBM System x3400 M3
IBM System x3250 M3
IBM System x3200 M3
IBM PowerVC Introduction and Configuration
A Comparison of PowerVM and Vmware Virtualization Performance
IBM pureflex system and vmware vcloud enterprise suite reference architecture
X6: The sixth generation of EXA Technology

Recently uploaded (20)

PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Review of recent advances in non-invasive hemoglobin estimation
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PDF
Electronic commerce courselecture one. Pdf
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
NewMind AI Monthly Chronicles - July 2025
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PPT
Teaching material agriculture food technology
PDF
Machine learning based COVID-19 study performance prediction
PPTX
MYSQL Presentation for SQL database connectivity
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Encapsulation_ Review paper, used for researhc scholars
PDF
Modernizing your data center with Dell and AMD
Digital-Transformation-Roadmap-for-Companies.pptx
Unlocking AI with Model Context Protocol (MCP)
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Review of recent advances in non-invasive hemoglobin estimation
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
Electronic commerce courselecture one. Pdf
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Advanced methodologies resolving dimensionality complications for autism neur...
NewMind AI Monthly Chronicles - July 2025
The Rise and Fall of 3GPP – Time for a Sabbatical?
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Teaching material agriculture food technology
Machine learning based COVID-19 study performance prediction
MYSQL Presentation for SQL database connectivity
20250228 LYD VKU AI Blended-Learning.pptx
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Encapsulation_ Review paper, used for researhc scholars
Modernizing your data center with Dell and AMD

IBM Takes Command of the UNIX Data Center — POWER7 Enables Growth and Lower Costs (Clipper)

  • 1. IBM Takes Command of the UNIX Data Center - POWER7 Enables Growth, Lower Cost THE CLIPPER GROUP Navigator TM SM SM Navigating Information Technology Horizons Published Since 1993 Report #TCG2009040LI September 21, 2009 IBM Takes Command of the UNIX Data Center — POWER7 Enables Growth, Lower Costs Analyst: David Reine Management Summary Striving for excellence is a human trait shared by many, as we all try to be the best that we can in at least one area under our control. Achieving excellence is a little harder to accomplish; it requires an amount of hard work and dedication that only a select few are willing to deliver. Improving on excellence, on the other hand, requires that rare individual who sets his sights on being the best in the world at whatever he attempts and continues to work harder than everyone else, even after he has arrived at the pinnacle of his quest. Individuals like Olympic athletes Michael Phelps and Usain Bolt each set world records (in swimming and track), yet each continues to train even harder to break their own records and reap the rewards of these continuing efforts. This same quality of continuing to improve on success is an essential requirement for every enterprise data center looking to improve upon the performance of its IT infrastructure, ensure the security and reliability of its environment, and continue to lower the total cost of ownership (TCO) of that infrastructure in the face of increasing demands. The deployment of new applications on new servers and the continuing explosion of data, which tends to be doubling every 12-to-18 months, are putting a strain on the budgets of every enterprise data center around the globe. Programs are being implemented to consolidate and virtualize both servers and storage to reduce the TCO and preserve valuable resources, both human and natural. By reducing the number of physical servers populating the data center, the CIO can reduce the number of systems administrators required to drive the IT infrastructure, as well as reducing the amount of energy necessary to power the data center, and the amount of floor space required to house it. These last two points are especially critical as enterprise data centers approach maximum capacity in both of these categories. In fact, if either is exceeded, the enterprise may be forced to build out a brand new data center at a cost of millions of dollars. For decades, UNIX systems vendors have been providing continual and timely upgrades, enabling cus- tomers to run more applications, respond faster, and/or process more data without having to worry about architecture compatibility. Either the UNIX vendor delivered higher performance, expanded memory, and improved RAS, etc., or the customer would eventually migrate to a better platform. For decades, UNIX server vendors have provided the data center with continual, and timely, upgrade paths. This enables them to replace existing legacy environments with fully compatible servers that run the same operating environments on the same IT architectures with higher performance, expanded memory capacity, and improved RAS (reliability, availability, and serviceability) characteristics. In recent years, this cut-throat battle left three UNIX vendors focused on scale-up, UNIX applications dominating the landscape: IBM, with AIX running on POWER systems, HP with HP-UX on Integrity, and Sun, with Solaris running on SPARC systems. For some, expected upgrade plans have hit a major hurdle; however, with customers now assessing Oracle’s acquisition of Sun, putting the future of SPARC under the microscope, and continued delays in the next generation of Intel’s Itanium archi- IN THIS ISSUE tecture (Tukwila), putting the future of Integrity in question, as well. Only IBM continues to provide the Enterprise Data Center Requirements .. 2 scale-up UNIX data center with a plan, and a predic- A History of POWER ............................... 2 table drumbeat, for the future. To learn more about IBM’s forthcoming POWER7 and AIX7, please read POWER7 Takes Command..................... 3 on. Conclusion .............................................. 4 The Clipper Group, Inc. - Technology Acquisition Consultants Strategic Advisors 888 Worcester Street Suite 140 Wellesley, Massachusetts 02482 U.S.A. 781-235-0085 781-235-5454 FAX Visit Clipper at www.clipper.com Send comments to editor@clipper.com
  • 2. The Clipper Group Navigator TM September 21, 2009 Page 2 Enterprise Data Center Requirements Systems are designed for RAS; designed, by the In the past, the data center had simply needed to same team that defined what “mainframe-class” go faster and be less expensive. Now, however, the really means. Power Systems are deployed with enterprise requires the data center to also run RAS at every level: from the processor, to memory, smarter. Medical facilities need to use IT to im- to I/O, to the system itself. prove health care; the weather bureau needs to be Every UNIX-involved CIO needs to ask, “How able to make better predictions, especially as the does Xeon 5500 stack up against today’s UNIX/ next hurricane is headed toward the U.S. coastline. RISC engines? How does it stack up against IBM’s Furthermore, every data center needs to improve its POWER architecture?” The reality is that IBM’s energy efficiency with more intelligence being used POWER6-based platforms exceed the capability of to protect our natural resources. servers built with the Xeon 5500, or for that matter In order to increase performance, lower cost, Intel’s Itanium microprocessor, in terms of database and run smarter, today’s CIOs are looking to transactions, OLTP, integer throughput, and floating consolidate their mission-critical applications on point capabilities. POWER6 also leads in terms of fewer, faster servers and to virtualize those appli- memory capacity per core, memory bandwidth per cations to make more efficient utilization of their core, I/O bandwidth, and L2, L3 cache. data center resources, both human and natural. Over the past two decades, IBM has used its With the typical scale-out server operating at less POWER architecture continually to improve the than 20% utilization, the data center has to change performance level of its Power Systems to improve the operational paradigm to make better use of the mission-critical application environment for the enterprise resources. To do this, the data center enterprise. Now, once again, IBM has announced is looking for the server platform that has, further innovations in this architecture to enable among other requirements, the highest perfor- more consolidation and better virtualization in order mance level in a virtualized environment. Typi- to encapsulate more workloads within each virtual cally, that can be measured in terms of the number machine, improving energy efficiency, and lowering of cores available per processor, the number of TCO. As the leading world-class athlete in these threads available per core, the bandwidth on a CPU- arenas, when it arrives, POWER7 is expected to to-CPU basis, the amount of shared cache, the make its debut in the data center with perfor- amount of memory supported and the memory mance and functionality to blow away the re- bandwidth, and the I/O bandwidth capability, not to cords set by POWER6. mention the server scalability and RAS functionality. In response to these requirements, Intel focused A History of POWER its efforts on improving its Xeon architecture to IBM has always exhibited a regular develop- meet the data center needs for consolidation and ment schedule for the POWER3 architecture, from virtualization. Specifically, it has announced the its inception in 1990, with improvements in Xeon 5500 (Nehalem) to achieve this functionality performance and functionality at every step of the and reduce data center TCO. And, in fact, com- way. Over the past decade, POWER4 added LPARs pared to the Xeon 5400, Nehalem can be considered (Logical Partitions) to the architecture in 2001; an unqualified success, with significant improve- POWER5 introduced Advanced POWER Virtuali- ments in database transaction count, integer and zation in 2004; and POWER6 provided Live Parti- floating-point throughput, memory scalability, and tion Mobility in 2007. Like a Swiss clock, every memory bandwidth. Unfortunately for Xeon, the three years IBM has delivered innovations to the traditional enterprise data center has not been de- POWER architecture, including improved vir- ploying an x86 environment for the past 40 years; it tualization through PowerVM, along with corres- has been deploying applications based on main- ponding improvements in the operating environ- frames, UNIX, or AS/400 (System i). One of the ment and systems management. It must be noted reasons for that is reliability, with Windows-based here that IBM has a history of leadership in servers exhibiting over 150 minutes of unscheduled virtualization, dating back to the origins of the outages per year, compared to, for example, only 15 first hypervisor providing full virtualization – minutes per year for AIX1 -based Power Systems over 40 years ago – on the mainframe, which led with less than one outage per year2 . IBM’s Power to today’s z/VM. 1 AIX is the IBM version of UNIX that runs on all POWER systems. 2 3 Source: IBM. Performance Optimized With Enhanced RISC. Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
  • 3. The Clipper Group Navigator TM September 21, 2009 Page 3 Every iteration of the POWER architecture has Exhibit 1 – Emerging delivered improvements in the primary require- Benefits of Virtualization ments for large scale computing for the data center. These include scalability, performance, RAS, and • Reduced IT management costs manageability. Equally important, however, are the • Better Software investment protection improvements to the bottom line in lowering the • Dynamic energy optimization TCO of the IT infrastructure. These improvements • Simplified High Availability and Disaster include: Recovery solutions • The virtualization of the AIX application suite – • Improved resource optimization improving the utilization of Power servers up to • Greater IT agility 60 to 80% along with the capability for rapid • Turnkey packaged applications deployment and dynamic change; • Improved security foundation • Energy Efficiency to lower power consumption and reduce energy cost by up to 90%, delivering more work per watt with each new release of processor at 5.0GHz, along with the only tpmC4 Power; result over six million transactions/minute. With • Providing Business Resiliency for continuous POWER6, IBM introduced Live Partition Mobility, availability and to dynamically respond to a Workload Partitions, Active Memory Sharing, and changing business environment with no down- multiple shared memory pools, along with Active time or manual intervention, maintaining Energy Manager: EnergyScale, and IBM Systems 99.997% uptime with only 15 minutes of un- Director VMControl providing a consistent cross- scheduled outage per year; and platform management for physical and virtual en- • Simplification of Management through an ever- vironments. POWER7 will extend those capabil- evolving IBM Systems Director, enabling control ities to take a clear leadership role in the deploy- over deployments and energy usage. ment of UNIX systems in the data center. Delivering a fully integrated solution gives IBM POWER7 also will enable IBM to supercharge the a tremendous advantage in consolidation and vir- System i platform, enabling them to deliver more tualization, enabling them to remove complexity performance and functionality for Linux on Power from the IT environment and simplify data center Systems5 . operations before the platform is even deployed. With the looming probability of the sun setting Power Systems are designed, developed, and tested on SPARC, and HP experiencing delays in the as an integrated server platform with a balanced availability of the next version of Integrity due to systems design, enabling linear performance as delays in Tukwila, the quad-core Itanium pro- core-count and utilization increase. Functionality is cessor6 , IBM, with POWER7 is in the right place at optimized across the layers of the system stack, the right time. It has been reported as recently as including hardware, hypervisor, operating system this past June that Sun has officially killed off the (AIX, i, or Linux), middleware, and Systems Direc- 16-core UltraSPARC-RK processor, known inter- tor management software. This enables Power Sys- nally as Rock, which has been in development for tems to deliver virtualization capabilities and attri- more than five years. In the meantime, Intel has butes that are generally unmatched in an x86 server indicated that RAS functionality from Itanium is environment, including performance scalability, being added to Nehalem-EX, perhaps signaling an RAS, energy efficiency, and security. Simply put, end of life for Itanium. the integrated combination of POWER architecture With a similar portfolio of modular, scalable and PowerVM enables Power Systems to enjoy a offerings as POWER6, POWER7 will be able to higher consolidation ratio than any x86 server deliver a multi-core processor with a higher perfor- running VMware’s vSphere, with up to 64 virtual mance/watt, higher per core performance and more CPUs and 4096GB of memory per VM under total systems performance. It is estimated that a PowerVM compared with only 8 virtual CPUs with Power7 System will have 2-to-5 times the total 255GB of memory with VMware ESX 4.0. For a more complete list of the emerging benefits of 4 The Transaction Processing Council’s performance bench- virtualization, see Exhibit 1, above. mark. 5 IBM has Power7 Systems running in the lab with AIX, IBM POWER7 Takes Command i, and Linux, all operational. 6 It has been reported that the quad-core Itanium may not be With POWER6, IBM has the world’s fastest available until 1Q10, two years later than originally planned. Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
  • 4. The Clipper Group Navigator TM September 21, 2009 Page 4 system aggregate throughput plus a simplified, non- Exhibit 2 – disruptive upgrade path through binary compati- POWER Virtualization Today bility with POWER6 and Live Partition Mobility. Power7 Systems will possess greater levels of con- • Fine-grained dynamic sharing of processors, solidation, up to 1000 virtual machines per system memory, and I/O and better resource utilization than Power6 Systems • Optional dedicated resources due to dynamic, policy-based energy management • Shared dedicated processors and a single Systems Director console to manage • Extreme scalability and robustness the server and storage network. IBM has already • Integrated firmware hypervisor announced the ability to upgrade a Power 595 • Virtual I/O Servers layer system by simply replacing the processor books, • Hardware enforced isolation including memory, and the system controllers. The 12X I/O drawers and GX adapters will migrate from • LPARs and WPARs Power6 to Power7 servers, preserving earlier in- • DLPAR and Processor Folding vestments. • Capacity on Demand Specifically, the POWER7 processor features • Partition Mobility eight processor cores to deliver four times the per- formance of POWER6 within the same power envelope. Each core will have 12 execution units, servers7 . In fact, IBM has reported that its Migra- 4-way symmetrical multi-threading, and 256KB of tion Factory is responsible for more than 1,750 L2 cache per core. Each processor will have 32MB migrations from Sun and HP platforms to IBM of on chip eDRAM for L3 cache to be shared by the POWER systems over the past three years. Com- 32 threads. This eDRAM is nearly as fast as con- bined with the innovations in POWER7 and AIX, ventional SRAM, but requires far less space and Systems Director and Tivoli, IBM cannot help but standby power. There are dual DDR3 memory con- extend its lead in traditional IT environments and trollers, with four channels per controller, with a break new ground in Cloud Computing. sustained memory bandwidth of 100GB/s and a With better utilization of hardware, IBM is scalability of up to 32 sockets, providing 360GB/s driving down the cost of software licensing, main- of SMP bandwidth. In addition, POWER7 includes tenance, floor space, and energy. It is reducing the a long list of RAS features to ensure application TCO for Power Systems throughout the enterprise. availability. Despite the turmoil in the rest of the UNIX market, The major features of POWER7 Systems in- IBM continues to outdo itself in clude linear scalability, PowerVM virtualization, delivering a high-performance, both physical and virtual management, along with low-cost application solution to energy/thermal management. See Exhibit 2, above, the data center. If your enterprise for a list of virtualization features expected in needs to improve the perfor- POWER 7. mance and lower the cost of your IT environment, IBM’s Power Conclusion Systems may be just the over- achieving world-record holder It is clear to even the most casual observer that that you seek. SM IBM’s Power Systems are in a league of their own today in providing the performance and advanced virtualization capabilities that are required for today’s mission- and business-critical workloads. With over 40 years of virtualization experience and a commitment to integrate solutions across the sys- tems stack, IBM continues to maintain a leadership position in the enterprise data center, even as others fade into IT history. AIX, i, and Linux all run on the POWER archi- tecture. These three operating environments re- present almost half of all data center spending on 7 Other spending is on Windows, Netware, z/OS, and others. Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.
  • 5. The Clipper Group Navigator TM September 21, 2009 Page 5 About The Clipper Group, Inc. The Clipper Group, Inc., is an independent consulting firm specializing in acquisition decisions and strategic advice regarding complex, enterprise-class information tech- nologies. Our team of industry professionals averages more than 25 years of real-world experience. A team of staff consultants augments our capabilities, with significant experience across a broad spectrum of applications and environments. The Clipper Group can be reached at 781-235-0085 and found on the web at www.clipper.com. About the Author David Reine is Director, Enterprise Systems for The Clipper Group. Mr. Reine specializes in enterprise servers, storage, and software, strategic business solutions, and trends in open systems architectures. He joined The Clipper Group after three decades in server and storage product marketing and program management for Groupe Bull, Zenith Data Systems, and Honeywell Information Systems. Mr. Reine earned a Bachelor of Arts degree from Tufts University, and an MBA from Northeastern University. Reach David Reine via e-mail at dave.reine@clipper.com or at 781-235-0085 Ext. 123. (Please dial “123” when you hear the automated attendant.) Regarding Trademarks and Service Marks The Clipper Group Navigator, The Clipper Group Explorer, The Clipper Group Observer, The Clipper Group Captain’s Log, The Clipper Group Voyager, Clipper Notes, and “clipper.com” are trademarks of The Clipper Group, Inc., and the clipper ship drawings, “Navigating Information Technology Horizons”, and “teraproductivity” are service marks of The Clipper Group, Inc. The Clipper Group, Inc., reserves all rights regarding its trademarks and service marks. All other trademarks, etc., belong to their respective owners. Disclosure Officers and/or employees of The Clipper Group may own as individuals, directly or indirectly, shares in one or more companies discussed in this bulletin. Company policy prohibits any officer or employee from holding more than one percent of the outstanding shares of any company covered by The Clipper Group. The Clipper Group, Inc., has no such equity holdings. Regarding the Information in this Issue The Clipper Group believes the information included in this report to be accurate. Data has been received from a variety of sources, which we believe to be reliable, including manufacturers, distributors, or users of the products discussed herein. The Clipper Group, Inc., cannot be held responsible for any consequential damages resulting from the application of information or opinions contained in this report. Copyright © 2009 by The Clipper Group, Inc. Reproduction prohibited without advance written permission. All rights reserved.