City of Charlotte Transportation Bond ProgramLiz Babson, P.E.CDOT Deputy DirectorPresentation to2011 Charlotte Regional Transportation SummitApril 8, 2011
Items to DiscussWho maintains which streets?Transportation bond historyTypical project scheduleFuture transportation bond funding and needs
Who is responsible for which streets?Green= CDOTRed = NCDOT
Charlotte Transportation Bond HistoryAlmost 50 years of voter approved bondsCity Growth Strategy and Transportation Action Plan (TAP) identify needsCapital Improvement Plan (CIP) sets prioritiesBonds fund street improvements, intersection improvements, sidewalks, street lights, bikeways, signal system, and other transportation needs2010 election results from Mecklenburg County Board of Elections website
Charlotte Transportation Bond History
2010 Transportation Bond ProjectsBeatties Ford Road wideningIdlewild Road wideningOakdale Road FTMScaleybark/South intersectionBallantyne Commons/Elm intersectionProvidence/McKee intersectionJohnston-Oehler Road FTM Planning & Design
What is a typical project schedule?Planning1 YearDesign1 yearReal Estate1 yearBid & Construction1 – 2 years$3-Year Vote to Drive$Typically 4 – 5 Years
Planning + Funding = Projects$390M in projects and programs (2006, 2008 and 2010 bonds)Dozens of projects “on the ground”Quality projects for all users – provide transportation choicesMaintenance of existing infrastructure
Transportation Projects Recently Completed or In Progress CompletedIn Progress
Future Transportation Funding – Some Uncertainty??????
Unfunded Transportation Needs    Unfunded Road                     Improvement Needs
ConclusionCharlotte remains in a growth mode (additional 300,000 people by 2030)With consistent funding, City has positive track record of getting projects on the ground – 3 year vote to driveSome uncertainty about future fundingCity has many identified transportation needs
Thank YouLiz Babson, P.E. CDOT Deputy Directorebabson@charlottenc.gov

More Related Content

PDF
First Hill Streetcar 6-9 CRC Presentation
PPTX
MSI Developer Council February 2017 Meeting: CRTPO Transportation Discussion
PPTX
MSI Developer Council Presentation - February 2017: Regional Transportation D...
PDF
Proposed service-adds-9-27-16
PDF
Moving Beyond Cost: Evaluating LRT & BRT options in Australian & NZ cities
PPT
PDF
Center City Streetcar Info Flyer
PPTX
Route 50 Sidewalk from Cherry Street to Linden Lane
First Hill Streetcar 6-9 CRC Presentation
MSI Developer Council February 2017 Meeting: CRTPO Transportation Discussion
MSI Developer Council Presentation - February 2017: Regional Transportation D...
Proposed service-adds-9-27-16
Moving Beyond Cost: Evaluating LRT & BRT options in Australian & NZ cities
Center City Streetcar Info Flyer
Route 50 Sidewalk from Cherry Street to Linden Lane

What's hot (14)

PPT
Transit Development for Central Texas
PDF
Dumbarton support letter oct 24
PDF
UDistrict Rezone Presentation - PLUZ Committee 9/20/2016
PPT
Mayor Kurt Alberts Presentation
PDF
FNK rev 06.08.15
PPT
Vision for UDOT's Future
PPTX
Bus Stop Safety and Accessibility Improvements
PDF
RV 2015: Art, Community Culture and TOD: Four Stories by Abigail Thorne-Lyman
PPT
Building Sustainable Communities: Urban Planning in the Portland Metro Regi...
PPTX
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
PPT
Adopting and Implementing a Metropolitan Plan: Portland Metro's Experience
PPT
Ar 1 august132012 710 freeway presentation
PDF
mpo fiscal priorities committee - building the future transportation system p...
PPTX
RV 2014: Public Officials Learning Network- The Challenge of Public Leadershi...
Transit Development for Central Texas
Dumbarton support letter oct 24
UDistrict Rezone Presentation - PLUZ Committee 9/20/2016
Mayor Kurt Alberts Presentation
FNK rev 06.08.15
Vision for UDOT's Future
Bus Stop Safety and Accessibility Improvements
RV 2015: Art, Community Culture and TOD: Four Stories by Abigail Thorne-Lyman
Building Sustainable Communities: Urban Planning in the Portland Metro Regi...
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
Adopting and Implementing a Metropolitan Plan: Portland Metro's Experience
Ar 1 august132012 710 freeway presentation
mpo fiscal priorities committee - building the future transportation system p...
RV 2014: Public Officials Learning Network- The Challenge of Public Leadershi...
Ad

Similar to State and Local Road Project Updates: Part 1 (20)

PPT
Garden Parkway and Monroe Connector Update
PPTX
Walter Brooks, New Orleans Regional Planning Commission
PDF
Transportation Milton, presentation by Tim Dennis, Halton Region
PPT
Transportation Funding Discussion: Board Retreat 2012
PPTX
Livability
PDF
Highland Creek Village Transportation Master Plan
PPT
State and Local Road Project Updates: Part 3
PPTX
Transit in the Charlotte Region
PPTX
Transit Ready Design - Pleasant CNU17
PPTX
Transit Ready Design Pleasant Cnu17
PDF
Portland's Complete Streets Policy - GSMSummit 2014, Bruce Hyman
PPT
9/9 FRI 11:00 | Getting It Done: Partnerships Now and for the Future 2
PDF
Understanding the Bicycle Project Planning and Implementation Process
PPTX
Burke Road Realignment-Citizen Information Meeting: June 1, 2017
PPT
South Fraser transit plan
PPTX
Atl bond presentation council retreat 10-17-14
PPTX
Cleveland Peer Exchange - National Perspective
PPTX
Sustainable Tulsa 8-1-2013
Garden Parkway and Monroe Connector Update
Walter Brooks, New Orleans Regional Planning Commission
Transportation Milton, presentation by Tim Dennis, Halton Region
Transportation Funding Discussion: Board Retreat 2012
Livability
Highland Creek Village Transportation Master Plan
State and Local Road Project Updates: Part 3
Transit in the Charlotte Region
Transit Ready Design - Pleasant CNU17
Transit Ready Design Pleasant Cnu17
Portland's Complete Streets Policy - GSMSummit 2014, Bruce Hyman
9/9 FRI 11:00 | Getting It Done: Partnerships Now and for the Future 2
Understanding the Bicycle Project Planning and Implementation Process
Burke Road Realignment-Citizen Information Meeting: June 1, 2017
South Fraser transit plan
Atl bond presentation council retreat 10-17-14
Cleveland Peer Exchange - National Perspective
Sustainable Tulsa 8-1-2013
Ad

More from Charlotte Chamber (20)

PPTX
Tax Law Changes
PPTX
Changes in Environmental Laws and Regulations
PDF
Charlotte Chamber Inter City Visit 2013 - Recap
PPTX
2013 Charlotte Chamber Program of Work
PPTX
2012 Energy Summit: The Business of Sustainability
PPT
Charlotte chamberaugust2012 mcguirewoods
PPT
UNC Charlotte Economic Development
PPTX
Charlotte Creates @ Packard Place
PPT
What's Next for CMS?
PPT
Communication Strategies for Organizational Success
PDF
Meet the Primes - LYNX Blue Line Extension
PDF
Transportation and Quality of Life
PDF
Managed Lanes: More than a Revenue Tool
PDF
Sustainable Transit & The Role of the Master Developer
PDF
Implementing PLAN 2040
PDF
Charlotte Capital Improvement Program Proposal
PDF
NCDOT Rail Update
PDF
CLT Update
PDF
CATS Update
PPSX
GreenWorks April Meeting
Tax Law Changes
Changes in Environmental Laws and Regulations
Charlotte Chamber Inter City Visit 2013 - Recap
2013 Charlotte Chamber Program of Work
2012 Energy Summit: The Business of Sustainability
Charlotte chamberaugust2012 mcguirewoods
UNC Charlotte Economic Development
Charlotte Creates @ Packard Place
What's Next for CMS?
Communication Strategies for Organizational Success
Meet the Primes - LYNX Blue Line Extension
Transportation and Quality of Life
Managed Lanes: More than a Revenue Tool
Sustainable Transit & The Role of the Master Developer
Implementing PLAN 2040
Charlotte Capital Improvement Program Proposal
NCDOT Rail Update
CLT Update
CATS Update
GreenWorks April Meeting

Recently uploaded (20)

PPTX
Sir Creek Conflict: History and its importance
PDF
Jim Stone Freelance Voterig August 13, 2025.pdf
PDF
Human Appeal in Gaza – Emergency Aid, Healthcare & Hope for Families.pdf
PDF
Pancasila & Citizen Resume PPT - Guest lecture
PDF
424926802-1987-Constitution-as-Basis-of-Environmental-Laws.pdf
PPTX
Pakistan movement part 2: story about Pakistan Movement
PDF
4th-president-of-the-Philippines-_20250 812_103637_0000.pdf
DOCX
End Of The Age TV Program: Depicting the Actual Truth in a World of Lies
PDF
9th-President-of-the-Philippines_lecture .pdf
PDF
How India’s First AI-Powered Anganwadi in Nagpur is Changing Education – As F...
PDF
Best 5 Sites for Verified Cash App Accounts – BTC & Instant Delivery.pdf
DOC
BU毕业证学历认证,阿什兰大学毕业证文凭证书
PPTX
India’s Response to the Rohingya Refugee Crisis: Balancing National Security,...
PPTX
POLY[1]....pptxtheiowqt4h3ioth4iofhe2toh42i0fhe2io3
PPTX
The-Evolution-of-Public-Human-Resource-Management (1).pptx
PDF
History ppt on World War 2 and its consequences
PDF
Reviving Regional Truths: AI-Powered Journalism in Bangladesh
DOCX
Memecoin memecoinist news site for trends and insights
PDF
Opher Bryer-The Rise and Fall of Opher Bryer How an AI Startup Turned from Pr...
PPTX
15 Years of Fraud The Shocking Case of CA Impersonation.pptx
Sir Creek Conflict: History and its importance
Jim Stone Freelance Voterig August 13, 2025.pdf
Human Appeal in Gaza – Emergency Aid, Healthcare & Hope for Families.pdf
Pancasila & Citizen Resume PPT - Guest lecture
424926802-1987-Constitution-as-Basis-of-Environmental-Laws.pdf
Pakistan movement part 2: story about Pakistan Movement
4th-president-of-the-Philippines-_20250 812_103637_0000.pdf
End Of The Age TV Program: Depicting the Actual Truth in a World of Lies
9th-President-of-the-Philippines_lecture .pdf
How India’s First AI-Powered Anganwadi in Nagpur is Changing Education – As F...
Best 5 Sites for Verified Cash App Accounts – BTC & Instant Delivery.pdf
BU毕业证学历认证,阿什兰大学毕业证文凭证书
India’s Response to the Rohingya Refugee Crisis: Balancing National Security,...
POLY[1]....pptxtheiowqt4h3ioth4iofhe2toh42i0fhe2io3
The-Evolution-of-Public-Human-Resource-Management (1).pptx
History ppt on World War 2 and its consequences
Reviving Regional Truths: AI-Powered Journalism in Bangladesh
Memecoin memecoinist news site for trends and insights
Opher Bryer-The Rise and Fall of Opher Bryer How an AI Startup Turned from Pr...
15 Years of Fraud The Shocking Case of CA Impersonation.pptx

State and Local Road Project Updates: Part 1

  • 1. City of Charlotte Transportation Bond ProgramLiz Babson, P.E.CDOT Deputy DirectorPresentation to2011 Charlotte Regional Transportation SummitApril 8, 2011
  • 2. Items to DiscussWho maintains which streets?Transportation bond historyTypical project scheduleFuture transportation bond funding and needs
  • 3. Who is responsible for which streets?Green= CDOTRed = NCDOT
  • 4. Charlotte Transportation Bond HistoryAlmost 50 years of voter approved bondsCity Growth Strategy and Transportation Action Plan (TAP) identify needsCapital Improvement Plan (CIP) sets prioritiesBonds fund street improvements, intersection improvements, sidewalks, street lights, bikeways, signal system, and other transportation needs2010 election results from Mecklenburg County Board of Elections website
  • 6. 2010 Transportation Bond ProjectsBeatties Ford Road wideningIdlewild Road wideningOakdale Road FTMScaleybark/South intersectionBallantyne Commons/Elm intersectionProvidence/McKee intersectionJohnston-Oehler Road FTM Planning & Design
  • 7. What is a typical project schedule?Planning1 YearDesign1 yearReal Estate1 yearBid & Construction1 – 2 years$3-Year Vote to Drive$Typically 4 – 5 Years
  • 8. Planning + Funding = Projects$390M in projects and programs (2006, 2008 and 2010 bonds)Dozens of projects “on the ground”Quality projects for all users – provide transportation choicesMaintenance of existing infrastructure
  • 9. Transportation Projects Recently Completed or In Progress CompletedIn Progress
  • 10. Future Transportation Funding – Some Uncertainty??????
  • 11. Unfunded Transportation Needs Unfunded Road Improvement Needs
  • 12. ConclusionCharlotte remains in a growth mode (additional 300,000 people by 2030)With consistent funding, City has positive track record of getting projects on the ground – 3 year vote to driveSome uncertainty about future fundingCity has many identified transportation needs
  • 13. Thank YouLiz Babson, P.E. CDOT Deputy Directorebabson@charlottenc.gov

Editor's Notes

  • #3: Share with you where we are currently with our transportation bond program…but before I go there, I want to give you some context that really demonstrates why the bond program is so important. who maintains which streets…transportation bond history…typical project schedule and how the bond program relates to that And then what do we see today when we look toward future transportation bond funding and those future transportation needs
  • #4: We are often asked which roads does CDOT maintain and which roads does NCDOT maintain. The green lines on the map are city maintained roads and the red lines are NCDOT maintained streets. The City is responsible for more than 2300 miles of streets, over 700 traffic signals and 175,000 street signs. There’s a lot we’re responsible for and likewise, there’s a lot of need.
  • #5: Long history of transportation bonds – almost 50 years! Needs are identified through the City Growth Strategy and TAP, which is the policy document that identifies transportation needs and aligns that with costs necessary to complete those projects. CIP which is a 5-year funding document adopted by Council and sets priorities for projects. Bonds fund many different types of transportation improvements. Even in difficult economic times, Charlotte voters approved the 2010 transportation bonds with 64% of voters voting for the bonds!
  • #6: Starting as far back as 1962, we began funding road improvements with transportation bonds and has been the primary source of funds for transportation capital projects. Our 2 largest bonds were the last 2 bond programs (2008, 2010).
  • #7: This a list of the road projects that were approved for funding in the 2010 bond. Represents various types of projects…widening, FTM projects which takes a 2-lane ditch section and builds a complete street with improvements for motor vehicles, as well as and pedestrians and bicyclists, intersection improvements, and moving 1 project into planning and design.
  • #8: We are often asked why does it take so long for a project to go from concept to construction. This diagram lays out that process and shows how bond funding is used to complete a project. For a project to happen we need funding committed twice from transportation bonds during the life of a project. The first commitment bond funds is used to advance Planning & Design for the project and the 2nd commitment of bond funds advances the project through Real Estate, Bid & Construction. Assuming funding is available at those two points, a project can be completed in as little as 4-5 years. This also supports a city commitment made many years ago for a 3-year vote to drive bond program. It’s important to note that the time to deliver a project is extended beyond 4-5 years when the pace of funding is inconsistent.
  • #9: When we have consistent transportation funding we are able to program and advance a significant number of projects. With the past three bonds, the City has programmed and advanced approximately $390M worth of transportation projects and programs and have dozens of projects on the ground. We are building quality projects for all users, not only as we complete road improvements for motor vehicles, but also sidewalks for pedestrians and bicycle accommodations for cyclists. And let’s not forget maintenance, while new projects are great, it is equally important to place emphasis on maintaining what we have. We do this through our street resurfacing effort, bridge maintenance and repairs, and traffic signal system improvements
  • #10: Just to show you what that progress looks like, this is a snapshot of projects that were either recently completed or in progress during design or construction. The orange projects are the road and intersection improvements that have been recently completed. The green projects are the projects that are already funded and in the process moving toward completion.
  • #11: The transportation bonds are really the only way the city is able to fund transportation capital projects. There is now some uncertainty as to whether the City can afford to have a 2012 transportation bond. – without bonds, there are no projects.
  • #12: But, we certainly have needs, this map shows the City’s thoroughfare and farm to market road improvements that have been identified as needing to be improved in the future. These projects are not currently funded. The inability to have consistent transportation bond funding will result in these projects being delayed until funding becomes available. The projects on this map are about $2.5B worth of thoroughfare and FTM improvements
  • #13: Charlotte remains in a growth mode. The recent census data indicates that we may even be growing at a slightly faster rate than previously estimated. With your support and voter approval, we’ve been able to complete some great things. When funding is consistent we have a great track record of getting projects on the ground There is some uncertainty when/if the City will have transportation bonds in the near-term which will impact our ability to advance projects. We have many identified transportation needs
  • #14: So, I hope I’ve left you with something to think about as you consider the future transportation needs and funding necessary to support those.