Highways: Total identified needs (2015 – 2020) = $45 billion About $9 billion in anticipated revenues for this timeframe Non-highways: Total identified needs (2015 – 2020)   = $9 billion About $1.5 billion in available revenue for this timeframe Summary: $54 billion in total identified transportation needs (2015 – 2020)  Estimated $10.5 billion in available revenue for this timeframe Funding Snapshot
Strategic Prioritization Process Data-driven system created that evaluates all proposed TIP projects based  on a list of quantitative data; Traffic counts Congestion/capacity Local support Regional support Safety Projects are scored individually and then ranked.  Public meetings, aggressive community outreach Actively engaged local governments, MPO/RPOs and stakeholders
STIP Schedule Sept. – Oct.2010   MPO/RPO review Draft STIP Department requests feedback on initial process  March  2011 Public Meetings on Draft STIP July 2011   BOT adopts Final STIP  Sept. 2011 NCDOT submits revised STIP to FHWA  December 2011 Draft NCSTP released December 2011 Investment Strategy Process May 2012   Draft Policy to Projects document released
State Transportation Improvement Program Division 12: STIP 12-18 $ 479 Million 6.27% Equity Share Division 12 Ten Year Work Plan $864 Million Maintain 13712 Lane Miles of Roadway 5,827,646 Square Feet of Bridge Deck
R-2206 – NC 16 Bypass Lincoln and Catawba Counties Roadway is open to St James Church Road in Lincoln County Project scheduled for completion to NC 150 in Catawba County in Summer of 2011 Turnkey $161 Million
R-3833 – Brawley School Road Iredell County Widen to multi-lanes with new interchange at I-77 Section from Chuckwood Road at “The Point” to I-77 under construction with completion fall 2012 $124 million
I-3819 – Interchange Modifications  Iredell County Geometric improvements, widening and safety modifications to I-40/I-77 interchange and to US 21/I-40 interchange in Statesville Right of Way in progress Construction 2012 – 2015 $100 million
I-2707 – US 74 Bypass Cleveland County Right of Way purchase, Environmental Mitigation and Construction from 2011 to 2015 $326 million
I-5000 – I-85/US 321 Interchange Gaston County Geometric Safety Improvements to the existing interchange Right of Way in 2014 Construction 2015 $36 million
I-4750 – I-77 Widening Iredell and Mecklenburg Counties Widen and reconstruct I-77 from NC 73 to I-40 Right of Way 2016 Construction 2019 $526 million
R-3100 – NC 16 Widening Catawba County Widening of Existing NC 16 from Tower Road to Claremont Road $52 million
R-2307 – NC 150 Widening Iredell, Catawba, and Lincoln Counties Widening NC 150 from I-77 to Harvel Road in Catawba County Right of Way in 2017 Construction in 2020 $97 million
    Questions?

More Related Content

PDF
Transportation Milton, presentation by Tim Dennis, Halton Region
PPTX
Transit in the Charlotte Region
PPTX
Department of Works NIP - NIPA
PPTX
Greer board retreat gpats - keith brockington
PDF
2050 Long Range Transportation Plan Update April 2021 public meeting
PPTX
Roscoe mapd 6.7.12
PDF
23.05.2012, PRESENTATION, Creating financial partnerships to develop Mongolia...
PDF
2050 Long Range Transportation Plan Update October 2020 public meeting
Transportation Milton, presentation by Tim Dennis, Halton Region
Transit in the Charlotte Region
Department of Works NIP - NIPA
Greer board retreat gpats - keith brockington
2050 Long Range Transportation Plan Update April 2021 public meeting
Roscoe mapd 6.7.12
23.05.2012, PRESENTATION, Creating financial partnerships to develop Mongolia...
2050 Long Range Transportation Plan Update October 2020 public meeting

Similar to State and Local Road Project Updates: Part 3 (18)

PPTX
MSI Developer Council Presentation - February 2017: Regional Transportation D...
PPTX
State and Local Road Project Updates: Part 2
PPTX
NCDOT Master Plan Presentation
PPT
Transportation Funding Discussion: Board Retreat 2012
PDF
BHI_Carolinas Region_Newsletter Summer 2016
PPT
The Construction of the I-40/I-77 Interchange August 9, 2012
PPTX
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
PDF
CATS Update
PPTX
State and Local Road Project Updates: Part 1
PPT
WSDOT Keynote Presentation
PPTX
WakeTransit Survey Presentation
PDF
Tysons Transportation Infrastructure and Funding: March 12, 2015
PPT
Reach for the Sky!: Funding Opportunities – Programs, grants, innovative fund...
PPT
Funding Alternatives – Prop 12
PPT
Reach for the Sky!: Funding Opportunities – Programs, grants, innovative fund...
PPTX
WakeTransit Survey
PDF
International Logistics Park Of North Carolina
PDF
Infrastructure and General Governemnt Appropriations Subcommittee Oct 2011
MSI Developer Council Presentation - February 2017: Regional Transportation D...
State and Local Road Project Updates: Part 2
NCDOT Master Plan Presentation
Transportation Funding Discussion: Board Retreat 2012
BHI_Carolinas Region_Newsletter Summer 2016
The Construction of the I-40/I-77 Interchange August 9, 2012
Embark Richmond Highway Comprehensive Plan Amendment and Transportation Projects
CATS Update
State and Local Road Project Updates: Part 1
WSDOT Keynote Presentation
WakeTransit Survey Presentation
Tysons Transportation Infrastructure and Funding: March 12, 2015
Reach for the Sky!: Funding Opportunities – Programs, grants, innovative fund...
Funding Alternatives – Prop 12
Reach for the Sky!: Funding Opportunities – Programs, grants, innovative fund...
WakeTransit Survey
International Logistics Park Of North Carolina
Infrastructure and General Governemnt Appropriations Subcommittee Oct 2011
Ad

More from Charlotte Chamber (20)

PPTX
Tax Law Changes
PPTX
Changes in Environmental Laws and Regulations
PDF
Charlotte Chamber Inter City Visit 2013 - Recap
PPTX
2013 Charlotte Chamber Program of Work
PPTX
2012 Energy Summit: The Business of Sustainability
PPT
Charlotte chamberaugust2012 mcguirewoods
PPT
UNC Charlotte Economic Development
PPTX
Charlotte Creates @ Packard Place
PPT
What's Next for CMS?
PPT
Communication Strategies for Organizational Success
PDF
Meet the Primes - LYNX Blue Line Extension
PDF
Transportation and Quality of Life
PDF
Managed Lanes: More than a Revenue Tool
PDF
Sustainable Transit & The Role of the Master Developer
PDF
Implementing PLAN 2040
PDF
Charlotte Capital Improvement Program Proposal
PDF
NCDOT Rail Update
PDF
CLT Update
PPSX
GreenWorks April Meeting
PPTX
2011 Charlotte Chamber Energy Summit
Tax Law Changes
Changes in Environmental Laws and Regulations
Charlotte Chamber Inter City Visit 2013 - Recap
2013 Charlotte Chamber Program of Work
2012 Energy Summit: The Business of Sustainability
Charlotte chamberaugust2012 mcguirewoods
UNC Charlotte Economic Development
Charlotte Creates @ Packard Place
What's Next for CMS?
Communication Strategies for Organizational Success
Meet the Primes - LYNX Blue Line Extension
Transportation and Quality of Life
Managed Lanes: More than a Revenue Tool
Sustainable Transit & The Role of the Master Developer
Implementing PLAN 2040
Charlotte Capital Improvement Program Proposal
NCDOT Rail Update
CLT Update
GreenWorks April Meeting
2011 Charlotte Chamber Energy Summit
Ad

Recently uploaded (20)

PDF
Naya Bharat Vision 2047_ Key Takeaways from This Year’s Independence Day Them...
PPTX
India’s Response to the Rohingya Refugee Crisis: Balancing National Security,...
PDF
4th-president-of-the-Philippines-_20250 812_103637_0000.pdf
PDF
The Blogs_ Hamas’s Deflection Playbook _ Andy Blumenthal _ The Times of Israe...
PDF
Human Appeal in Gaza – Emergency Aid, Healthcare & Hope for Families.pdf
PDF
Naidu Pushes for Rs 36 Crore Subsidy to Support Farmers in Need
PDF
Pancasila & Citizen Resume PPT - Guest lecture
DOCX
End Of The Age TV Program: Depicting the Actual Truth in a World of Lies
PPTX
Rhythms of Freedom_ India Day Shines at Battery Dance Festival 2025.
PDF
424926802-1987-Constitution-as-Basis-of-Environmental-Laws.pdf
PPTX
The-Evolution-of-Public-Human-Resource-Management (1).pptx
PPTX
Sir Creek Conflict: History and its importance
PPTX
15 Years of Fraud The Shocking Case of CA Impersonation.pptx
PDF
Opher Bryer-The Rise and Fall of Opher Bryer How an AI Startup Turned from Pr...
DOCX
Memecoin memecoinist news site for trends and insights
PDF
Aron Govil on Why America Lacks Skilled Engineers.pdf
DOC
BU毕业证学历认证,阿什兰大学毕业证文凭证书
PDF
Mindanao Debate Lecture Presentation Outline 1.General Facts 2.Mindanao Histo...
PPTX
Pakistan movement part 2: story about Pakistan Movement
PDF
Samaya Jyothi Live News Telugu | Breaking & Trusted Updates
Naya Bharat Vision 2047_ Key Takeaways from This Year’s Independence Day Them...
India’s Response to the Rohingya Refugee Crisis: Balancing National Security,...
4th-president-of-the-Philippines-_20250 812_103637_0000.pdf
The Blogs_ Hamas’s Deflection Playbook _ Andy Blumenthal _ The Times of Israe...
Human Appeal in Gaza – Emergency Aid, Healthcare & Hope for Families.pdf
Naidu Pushes for Rs 36 Crore Subsidy to Support Farmers in Need
Pancasila & Citizen Resume PPT - Guest lecture
End Of The Age TV Program: Depicting the Actual Truth in a World of Lies
Rhythms of Freedom_ India Day Shines at Battery Dance Festival 2025.
424926802-1987-Constitution-as-Basis-of-Environmental-Laws.pdf
The-Evolution-of-Public-Human-Resource-Management (1).pptx
Sir Creek Conflict: History and its importance
15 Years of Fraud The Shocking Case of CA Impersonation.pptx
Opher Bryer-The Rise and Fall of Opher Bryer How an AI Startup Turned from Pr...
Memecoin memecoinist news site for trends and insights
Aron Govil on Why America Lacks Skilled Engineers.pdf
BU毕业证学历认证,阿什兰大学毕业证文凭证书
Mindanao Debate Lecture Presentation Outline 1.General Facts 2.Mindanao Histo...
Pakistan movement part 2: story about Pakistan Movement
Samaya Jyothi Live News Telugu | Breaking & Trusted Updates

State and Local Road Project Updates: Part 3

  • 1. Mike Holder Division 12 April 8 th , 2011 2011 Charlotte Chamber Transportation Summit
  • 2. Highways: Total identified needs (2015 – 2020) = $45 billion About $9 billion in anticipated revenues for this timeframe Non-highways: Total identified needs (2015 – 2020) = $9 billion About $1.5 billion in available revenue for this timeframe Summary: $54 billion in total identified transportation needs (2015 – 2020) Estimated $10.5 billion in available revenue for this timeframe Funding Snapshot
  • 3. Strategic Prioritization Process Data-driven system created that evaluates all proposed TIP projects based on a list of quantitative data; Traffic counts Congestion/capacity Local support Regional support Safety Projects are scored individually and then ranked. Public meetings, aggressive community outreach Actively engaged local governments, MPO/RPOs and stakeholders
  • 4. STIP Schedule Sept. – Oct.2010 MPO/RPO review Draft STIP Department requests feedback on initial process March 2011 Public Meetings on Draft STIP July 2011 BOT adopts Final STIP Sept. 2011 NCDOT submits revised STIP to FHWA December 2011 Draft NCSTP released December 2011 Investment Strategy Process May 2012 Draft Policy to Projects document released
  • 5. State Transportation Improvement Program Division 12: STIP 12-18 $ 479 Million 6.27% Equity Share Division 12 Ten Year Work Plan $864 Million Maintain 13712 Lane Miles of Roadway 5,827,646 Square Feet of Bridge Deck
  • 6. R-2206 – NC 16 Bypass Lincoln and Catawba Counties Roadway is open to St James Church Road in Lincoln County Project scheduled for completion to NC 150 in Catawba County in Summer of 2011 Turnkey $161 Million
  • 7. R-3833 – Brawley School Road Iredell County Widen to multi-lanes with new interchange at I-77 Section from Chuckwood Road at “The Point” to I-77 under construction with completion fall 2012 $124 million
  • 8. I-3819 – Interchange Modifications Iredell County Geometric improvements, widening and safety modifications to I-40/I-77 interchange and to US 21/I-40 interchange in Statesville Right of Way in progress Construction 2012 – 2015 $100 million
  • 9. I-2707 – US 74 Bypass Cleveland County Right of Way purchase, Environmental Mitigation and Construction from 2011 to 2015 $326 million
  • 10. I-5000 – I-85/US 321 Interchange Gaston County Geometric Safety Improvements to the existing interchange Right of Way in 2014 Construction 2015 $36 million
  • 11. I-4750 – I-77 Widening Iredell and Mecklenburg Counties Widen and reconstruct I-77 from NC 73 to I-40 Right of Way 2016 Construction 2019 $526 million
  • 12. R-3100 – NC 16 Widening Catawba County Widening of Existing NC 16 from Tower Road to Claremont Road $52 million
  • 13. R-2307 – NC 150 Widening Iredell, Catawba, and Lincoln Counties Widening NC 150 from I-77 to Harvel Road in Catawba County Right of Way in 2017 Construction in 2020 $97 million
  • 14. Questions?