SlideShare a Scribd company logo
Subpart H -  Material Handling
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
    1926.250 General requirements for storage
1926.250(a) General. (1) “All materials stored in tiers
shall be stacked, racked, blocked, interlocked, or
otherwise secured to prevent sliding, falling or
collapse.”

1926.250(a)(2) “Maximum safe load limits of floors
within buildings and structures, in pounds per square
foot, shall be conspicuously posted in all storage areas,
except for floor or slab on grade. Maximum safe loads
shall not be exceeded.”
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
    1926.250 General requirements for storage
1926.250(b)(6) “Brick stacks shall not be more than 7
feet in height. When a loose brick stack reaches a
height of 4 feet, it shall be tapered back 2 inches in
every foot of height above the 4-foot level.”

1926.250(b)(7) “When masonry blocks are stacked
higher than 6 feet, the stack shall be tapered back one-
half block per tier above the 6-foot level.”

                                                         3
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
    1926.250 General requirements for storage
1926.250(b)(8) “Lumber;”
1926.250(b)(8)(i) “Used lumber shall have all nails
withdrawn before stacking.”
1926.250(b)(8)(ii) “Lumber shall be stacked on level
and solidly supported sills.”
1926.250(b)(8)(iii) “Lumber shall be so stacked as to be
stable and self supporting.”
1926.250(b)(8)(iv) “Lumber piles shall not exceed 20
feet in height provided that lumber to be handled
manually shall not be stacked more than 16 feet high.”
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
   1926.250 General requirements for storage
1926.250(c) Housekeeping. “Storage areas shall be
kept free from accumulation of materials that
constitute hazards from tripping, fire, explosion, or
pest harborage. Vegetation control will be exercised
when necessary.”




                                                        5
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(a) General. (1) “Rigging equipment for
material handling shall be inspected prior to use on
each shift and as necessary during its use to ensure
that it is safe. Defective equipment shall be removed
from service.”




                                                        6
7
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

 Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(a)(6) Inspections. “Each day before being
used, the sling and all fastenings and attachments shall
be inspected for damage or defects by a competent
person designated by the employer. Additional
inspections shall be performed during sling use, where
service conditions warrant. Damaged or defective slings
shall be immediately removed from service.”


                                                        8
OSHA     OCCUPATIONAL SAFETY AND HEALTH
                         ADMINISTRATION



                     1926.251
          Rigging equipment for material
                     handling




Synthetic Fiber    Metal Mesh    Alloy Steel   Wire Rope
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(b) Alloy steel chains. (1) “Welded alloy steel
chain slings shall have permanently affixed
identification stating size, grade, rated capacity, and
sling manufacturer.”

1926.251(b)(3) “Job or shop hooks and links, or
makeshift fasteners, formed from bolts, rods, etc. or
other such attachments, shall not be used.”

                                                          10
11
It must be marked with grade or manufacturer's mark
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(b)(6) Inspections. (i) “In addition to the
inspection required by other paragraphs of this
section, a thorough periodic inspection of alloy steel
chain slings in use shall be made on a regular basis, to
be determined on the basis of (A) frequency of sling
use; (B) severity of service conditions; (C) nature of
lifts being made; and (D) experience gained on the
service life of slings used in similar circumstances.
Such inspections shall in no event be at intervals
greater than once every 12 months.”
14
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(b)(6)(ii) “The employer shall make and
maintain a record of the most recent month in which
each alloy steel chain sling was thoroughly inspected,
and shall make such record available for examination.”




                                                       15
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
 1926.251(c) Wire rope. (1) …………the safe working
 loads recommended by the manufacturer for specific,
 identifiable products shall be followed, provided that a
 safety factor of not less than 5 is maintained.

 1926.251(c)(2) “Protruding ends of strands in splices
 on slings and bridles shall be covered or blunted.”


                                                       16
Wire

    Core
                   Center




            Strand




Wire rope
Left Regular Lay


     Right Regular Lay


     Left Lang Lay


     Right Lang Lay
18
One Wire Rope Lay




One strand makes a 360 degree turn
                                 19
Dead End




       20
6 x 25 Wire Rope
Each strand
contains 25
   wires
                                 6 Strands
22
23
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(c)(4)(i) “An eye splice made in any wire rope
shall have not less than three full tucks. However, this
requirement shall not operate to preclude the use of
another form of splice or connection which can be
shown to be as efficient and which is not otherwise
prohibited.”



                                                       24
25
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(c)(5)((i) “When used for eye splices, the U-
bolt shall be applied so that the “U” section is in
contact with the dead end of the rope.”




                                                        26
Dead End




           27
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(c)(6) “Slings shall not be shortened with
knots or bolts or other makeshift devices.”

1926.251(c)(7) “Slings legs shall not be kinked.”

1926.251(c)(8) “Slings used in a basket hitch shall have
the loads balanced to prevent slippage.”

1926.251(c)(9) “Slings shall be padded or protected
from the sharp edges of their loads.”
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
1926.251 Rigging equipment for material handling
1926.251(c)(10) “Hands or fingers shall not be placed
between the sling and its load while the sling is being
tightened around the load.”

1926.251(c)(11) “Shock loading is prohibited.”

1926.251(c)(12) “A sling shall not be pulled from under
a load when the load is resting on the sling.”

                                                          29
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
          1926.251 Synthetic webbing
      (nylon, polyester, and polypropylene)
1926.251(e)(1) “The employer shall have each synthetic
web sling marked or coded to show:”
1926.251(e)(1)(i) “Name or trademark of
manufacturer.”
1926.251(e)(1)(ii) “Rated capacities for the type of
hitch.”
1926.251(e)(1)(iii) “ Type of material.”
                                                       30
31
32
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
           1926.251 Synthetic webbing
       (nylon, polyester, and polypropylene)
1926.251(e)(4) Fittings. “Fittings shall be:”
1926.251(e)(4)(i) “Of a minimum breaking strength
equal to that of the sling; and”
1926.251(e)(4)(ii) “Free of all sharp edges that could in
any way damage the webbing.”



                                                        33
34
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
           1926.251 Synthetic webbing
       (nylon, polyester, and polypropylene)
1926.251(e)(8) Removal from service. “Synthetic web
slings shall be immediately removed from service if any
of the following conditions are present:”
1926.251(e)(8)(i) “Acid or caustic burns;”
1926.251(e)(8)(ii) “Melting or charring of any part of
the sling surface;”
1926.251(e)(8)(iii) “Snags, punctures, tears or cuts;”
1926.251(e)(8)(iv) “Broken or worn stitches; or”
1926.251(e)(8)(v) “Distortion of fittings.”
36
37
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
        1926.252 Disposal of waste material
1926.252(a) “Whenever materials are dropped more
than 20 feet to any point lying outside the exterior
walls of the building, an enclosed chute of wood, or
equivalent material, shall be used. For the purpose of
this paragraph, an enclosed chute is a slide, closed in
on all sides, through which material is moved from a
high place to a lower one.”


                                                          38
39
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
        1926.252 Disposal of waste material
1926.252(b) “When debris is dropped through holes
in the floor without the use of chutes, the area onto
which the material is dropped shall be completely
enclosed with barricades not less than 42 inches high
and not less than 6 feet back from the projected edge
of the opening above. Signs warning of the hazard of
falling materials shall be posted at each level.
Removal shall not be permitted in this lower area
until debris handling ceases above.”
                                                        40
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

Subpart H – Materials Handling, Storage, Use, and Disposal
        1926.252 Disposal of waste material
1926.252(b) “Disposal of waste material or debris by
burning shall comply with local fire regulations.”

1926.252(e) “All solvent waste, oily rags, and
flammable liquids shall be kept in fire resistant
covered containers until removed from worksite.”



                                                       41
OCCUPATIONAL SAFETY AND HEALTH
    OSHA               ADMINISTRATION


     1926.850 Prepatory operations
1926.850(h) “When debris is dropped through holes
in the floor without the use of chutes, the area onto
which the material is dropped shall be completely
enclosed with barricades not less than 42 inches high
and not less than 6 feet back from the projected edge
of the opening above. Signs, warning of the hazard of
falling materials, shall be posted at each level.
Removal shall not be permitted in this lower area
until debris handling ceases above.”
                                                  42

More Related Content

PPS
Subpart J - Welding
PPS
Subpart H - Material Handling
PPS
Subpart R - Steel Erection
PPS
Subpart O - Motor Vehicles
PPS
Subpart N - Cranes
PPT
Subpart L - Scaffolding
PPT
Subpart K - Electrical
PPT
Subpart Q Concrete Written
Subpart J - Welding
Subpart H - Material Handling
Subpart R - Steel Erection
Subpart O - Motor Vehicles
Subpart N - Cranes
Subpart L - Scaffolding
Subpart K - Electrical
Subpart Q Concrete Written

Viewers also liked (20)

PPS
Subpart X - Ladders
PPTX
ppt on concrete (aabid)
PPT
Chapter 2
DOCX
Types of cranes
PPSX
Ambica Engineering: India's Leading Crane and Hoist Manufacturer
PPTX
BE A CONFIDENT SPEAKER
PDF
2009 Face Conference Orosha Cranes Wooley
PPTX
Slips trips falls
PPT
00999 Focus Four 131
PPTX
Being a good communicator
PPT
Type of EOT Crane
PPTX
STF quick trainer 7.22.15
PPTX
Example Original PowerPoint Presentation
PDF
Safe use of Mobile Cranes
PPS
Double Girder EOT Crane by Ganesh Engineering Company Ahmedabad
PDF
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
PPTX
Crane 123
ODP
Eot Cranes Types And Their Uses
PPTX
Amit crane ppt
Subpart X - Ladders
ppt on concrete (aabid)
Chapter 2
Types of cranes
Ambica Engineering: India's Leading Crane and Hoist Manufacturer
BE A CONFIDENT SPEAKER
2009 Face Conference Orosha Cranes Wooley
Slips trips falls
00999 Focus Four 131
Being a good communicator
Type of EOT Crane
STF quick trainer 7.22.15
Example Original PowerPoint Presentation
Safe use of Mobile Cranes
Double Girder EOT Crane by Ganesh Engineering Company Ahmedabad
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Crane 123
Eot Cranes Types And Their Uses
Amit crane ppt
Ad

Similar to Subpart H - Material Handling (20)

PPTX
510 material handling rigging 2015
PPT
Rigging_Equipment_for_Material_Handling_in_Construction.ppt
PPT
Lifting equipment Crane.ppt
PPS
Subpart P - Excavations
PPS
Subpart T - Demolition
PPT
Subpart C Safety And Health
PPT
MATERIAL.ppt
PPT
Subpart I - Tools
PPT
Material Handling safety as per standard_050449.ppt
PPTX
510 material handling rigging 2018
PPT
Materials handling, storage مناولة المواد والتخزين
PPTX
Gi 2016 industrial rigging safety
PPT
Ppe report
PPT
matl_handling_study material for study11
PPT
matl_handling_c.ppt
PPT
Slingsafety 1226191517188739-8
DOCX
Safe rigging training presentation transcript
PPT
Matl handling2
PPT
Materials Handling Ppt
510 material handling rigging 2015
Rigging_Equipment_for_Material_Handling_in_Construction.ppt
Lifting equipment Crane.ppt
Subpart P - Excavations
Subpart T - Demolition
Subpart C Safety And Health
MATERIAL.ppt
Subpart I - Tools
Material Handling safety as per standard_050449.ppt
510 material handling rigging 2018
Materials handling, storage مناولة المواد والتخزين
Gi 2016 industrial rigging safety
Ppe report
matl_handling_study material for study11
matl_handling_c.ppt
Slingsafety 1226191517188739-8
Safe rigging training presentation transcript
Matl handling2
Materials Handling Ppt
Ad

More from FFSafety (16)

PPT
S A F E T Y P H O T O S P R E S E N T A T I O N
PPT
Fall Protection, Gtech
PPT
Site Photos, 0608
PPT
Recordkeeping 00150 22
PPT
Subpart M - Fall Protection
PPS
Subpart G - Signs and Signals
PPT
Subpart F - Fire Protection
PPT
Subpart E - PPE
PPS
Subpart D - Health & Environment
ODP
Article
PPT
Focus Four Ppp
PPT
Ppe C
PPT
Scaffolding
PPT
Scaffolds C
PPT
Safetyorient
PPT
Scaffold 5
S A F E T Y P H O T O S P R E S E N T A T I O N
Fall Protection, Gtech
Site Photos, 0608
Recordkeeping 00150 22
Subpart M - Fall Protection
Subpart G - Signs and Signals
Subpart F - Fire Protection
Subpart E - PPE
Subpart D - Health & Environment
Article
Focus Four Ppp
Ppe C
Scaffolding
Scaffolds C
Safetyorient
Scaffold 5

Recently uploaded (20)

PPTX
Astra-Investor- business Presentation (1).pptx
PDF
Cours de Système d'information about ERP.pdf
PDF
Tata consultancy services case study shri Sharda college, basrur
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PPTX
sales presentation، Training Overview.pptx
PPTX
operations management : demand supply ch
PPTX
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
PDF
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
How to Get Business Funding for Small Business Fast
PDF
Introduction to Generative Engine Optimization (GEO)
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
1911 Gold Corporate Presentation Aug 2025.pdf
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
PDF
Deliverable file - Regulatory guideline analysis.pdf
Astra-Investor- business Presentation (1).pptx
Cours de Système d'information about ERP.pdf
Tata consultancy services case study shri Sharda college, basrur
Lecture 3344;;,,(,(((((((((((((((((((((((
sales presentation، Training Overview.pptx
operations management : demand supply ch
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
Ôn tập tiếng anh trong kinh doanh nâng cao
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
How to Get Business Funding for Small Business Fast
Introduction to Generative Engine Optimization (GEO)
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
1911 Gold Corporate Presentation Aug 2025.pdf
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
NewBase 12 August 2025 Energy News issue - 1812 by Khaled Al Awadi_compresse...
Deliverable file - Regulatory guideline analysis.pdf

Subpart H - Material Handling

  • 2. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.250 General requirements for storage 1926.250(a) General. (1) “All materials stored in tiers shall be stacked, racked, blocked, interlocked, or otherwise secured to prevent sliding, falling or collapse.” 1926.250(a)(2) “Maximum safe load limits of floors within buildings and structures, in pounds per square foot, shall be conspicuously posted in all storage areas, except for floor or slab on grade. Maximum safe loads shall not be exceeded.”
  • 3. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.250 General requirements for storage 1926.250(b)(6) “Brick stacks shall not be more than 7 feet in height. When a loose brick stack reaches a height of 4 feet, it shall be tapered back 2 inches in every foot of height above the 4-foot level.” 1926.250(b)(7) “When masonry blocks are stacked higher than 6 feet, the stack shall be tapered back one- half block per tier above the 6-foot level.” 3
  • 4. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.250 General requirements for storage 1926.250(b)(8) “Lumber;” 1926.250(b)(8)(i) “Used lumber shall have all nails withdrawn before stacking.” 1926.250(b)(8)(ii) “Lumber shall be stacked on level and solidly supported sills.” 1926.250(b)(8)(iii) “Lumber shall be so stacked as to be stable and self supporting.” 1926.250(b)(8)(iv) “Lumber piles shall not exceed 20 feet in height provided that lumber to be handled manually shall not be stacked more than 16 feet high.”
  • 5. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.250 General requirements for storage 1926.250(c) Housekeeping. “Storage areas shall be kept free from accumulation of materials that constitute hazards from tripping, fire, explosion, or pest harborage. Vegetation control will be exercised when necessary.” 5
  • 6. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(a) General. (1) “Rigging equipment for material handling shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe. Defective equipment shall be removed from service.” 6
  • 7. 7
  • 8. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(a)(6) Inspections. “Each day before being used, the sling and all fastenings and attachments shall be inspected for damage or defects by a competent person designated by the employer. Additional inspections shall be performed during sling use, where service conditions warrant. Damaged or defective slings shall be immediately removed from service.” 8
  • 9. OSHA OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION 1926.251 Rigging equipment for material handling Synthetic Fiber Metal Mesh Alloy Steel Wire Rope
  • 10. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(b) Alloy steel chains. (1) “Welded alloy steel chain slings shall have permanently affixed identification stating size, grade, rated capacity, and sling manufacturer.” 1926.251(b)(3) “Job or shop hooks and links, or makeshift fasteners, formed from bolts, rods, etc. or other such attachments, shall not be used.” 10
  • 11. 11
  • 12. It must be marked with grade or manufacturer's mark
  • 13. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(b)(6) Inspections. (i) “In addition to the inspection required by other paragraphs of this section, a thorough periodic inspection of alloy steel chain slings in use shall be made on a regular basis, to be determined on the basis of (A) frequency of sling use; (B) severity of service conditions; (C) nature of lifts being made; and (D) experience gained on the service life of slings used in similar circumstances. Such inspections shall in no event be at intervals greater than once every 12 months.”
  • 14. 14
  • 15. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(b)(6)(ii) “The employer shall make and maintain a record of the most recent month in which each alloy steel chain sling was thoroughly inspected, and shall make such record available for examination.” 15
  • 16. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(c) Wire rope. (1) …………the safe working loads recommended by the manufacturer for specific, identifiable products shall be followed, provided that a safety factor of not less than 5 is maintained. 1926.251(c)(2) “Protruding ends of strands in splices on slings and bridles shall be covered or blunted.” 16
  • 17. Wire Core Center Strand Wire rope
  • 18. Left Regular Lay Right Regular Lay Left Lang Lay Right Lang Lay 18
  • 19. One Wire Rope Lay One strand makes a 360 degree turn 19
  • 20. Dead End 20
  • 21. 6 x 25 Wire Rope Each strand contains 25 wires 6 Strands
  • 22. 22
  • 23. 23
  • 24. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(c)(4)(i) “An eye splice made in any wire rope shall have not less than three full tucks. However, this requirement shall not operate to preclude the use of another form of splice or connection which can be shown to be as efficient and which is not otherwise prohibited.” 24
  • 25. 25
  • 26. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(c)(5)((i) “When used for eye splices, the U- bolt shall be applied so that the “U” section is in contact with the dead end of the rope.” 26
  • 27. Dead End 27
  • 28. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(c)(6) “Slings shall not be shortened with knots or bolts or other makeshift devices.” 1926.251(c)(7) “Slings legs shall not be kinked.” 1926.251(c)(8) “Slings used in a basket hitch shall have the loads balanced to prevent slippage.” 1926.251(c)(9) “Slings shall be padded or protected from the sharp edges of their loads.”
  • 29. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Rigging equipment for material handling 1926.251(c)(10) “Hands or fingers shall not be placed between the sling and its load while the sling is being tightened around the load.” 1926.251(c)(11) “Shock loading is prohibited.” 1926.251(c)(12) “A sling shall not be pulled from under a load when the load is resting on the sling.” 29
  • 30. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Synthetic webbing (nylon, polyester, and polypropylene) 1926.251(e)(1) “The employer shall have each synthetic web sling marked or coded to show:” 1926.251(e)(1)(i) “Name or trademark of manufacturer.” 1926.251(e)(1)(ii) “Rated capacities for the type of hitch.” 1926.251(e)(1)(iii) “ Type of material.” 30
  • 31. 31
  • 32. 32
  • 33. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Synthetic webbing (nylon, polyester, and polypropylene) 1926.251(e)(4) Fittings. “Fittings shall be:” 1926.251(e)(4)(i) “Of a minimum breaking strength equal to that of the sling; and” 1926.251(e)(4)(ii) “Free of all sharp edges that could in any way damage the webbing.” 33
  • 34. 34
  • 35. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.251 Synthetic webbing (nylon, polyester, and polypropylene) 1926.251(e)(8) Removal from service. “Synthetic web slings shall be immediately removed from service if any of the following conditions are present:” 1926.251(e)(8)(i) “Acid or caustic burns;” 1926.251(e)(8)(ii) “Melting or charring of any part of the sling surface;” 1926.251(e)(8)(iii) “Snags, punctures, tears or cuts;” 1926.251(e)(8)(iv) “Broken or worn stitches; or” 1926.251(e)(8)(v) “Distortion of fittings.”
  • 36. 36
  • 37. 37
  • 38. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.252 Disposal of waste material 1926.252(a) “Whenever materials are dropped more than 20 feet to any point lying outside the exterior walls of the building, an enclosed chute of wood, or equivalent material, shall be used. For the purpose of this paragraph, an enclosed chute is a slide, closed in on all sides, through which material is moved from a high place to a lower one.” 38
  • 39. 39
  • 40. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.252 Disposal of waste material 1926.252(b) “When debris is dropped through holes in the floor without the use of chutes, the area onto which the material is dropped shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above. Signs warning of the hazard of falling materials shall be posted at each level. Removal shall not be permitted in this lower area until debris handling ceases above.” 40
  • 41. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart H – Materials Handling, Storage, Use, and Disposal 1926.252 Disposal of waste material 1926.252(b) “Disposal of waste material or debris by burning shall comply with local fire regulations.” 1926.252(e) “All solvent waste, oily rags, and flammable liquids shall be kept in fire resistant covered containers until removed from worksite.” 41
  • 42. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION 1926.850 Prepatory operations 1926.850(h) “When debris is dropped through holes in the floor without the use of chutes, the area onto which the material is dropped shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above. Signs, warning of the hazard of falling materials, shall be posted at each level. Removal shall not be permitted in this lower area until debris handling ceases above.” 42