Sample Template for Project Estimating
This template is intended to provide an example breakdown of hours and effort associated with a given project. The
comments listed in the boxes to the right highlight the various benefits associated with this particular template. The
more detail you put into the estimate, the better your estimate will be.
Line Task Description Frequency Hours Iterations Total Comment
1 Build Project Schedule One Time 12 1 12
2 Update Project Schedule Monthly 4 11 44
3 Manage Project Financials Biweekly 4 26 104
4 Produce Project Reports Monthly 4 12 48
5 Customer Status Meeting Weekly 1.5 52 78
6 Executive Presentations Quarterly 2 4 8 Preparation and Presentation
Project Management Total 294
Line Task Description Frequency Hours Iterations Total Comment
7 Conceptual Designs One Time 60 2 120
8 Development Design One Time 250 1 250
9 Design Review Preparation Quarterly 20 4 80
10 Design Reviews Quarterly 25 4 100
11 Schematic Development One Time 3 40 120 Assume 40 schematics
12 Prototype Development One Time 80 1 80
13 Test Planning One Time 40 1 40
14 Prototype Testing Monthly 2 12 24
15 Test Report One Time 6 1 6
16 Final Design and Closeout One Time 75 1 75
Product Development Total 820
Line Task Description Frequency Hours Iterations Total Comment
17 Order Raw Materials One Time 4 1 4
18 Update Manufacturing Plan Monthly 2 12 24
19 Build Prototype One Time 24 1 24
20 Build Test Rig One Time 12 1 12
Manufacturing Total 64
Line Task Description Frequency Hours Iterations Total Comment
21 Team Meetings (1 Hour) Weekly 5 50 250 Assume 5 member team
22 Update Project Team Template Weekly 1 50 50
23 Customer Visit Monthly 8 12 96
Administrative Total 396
Line Function Hours Rate Total Comment
24 Project Management 294 50 € 14,700
25 Product Development 820 47 € 38,540
26 Manufacturing 64 45 € 2,880
27 Administrative 396 48 € 19,008 Averaged Team Rate
Total Labor Cost € 75,128
Assumptions
28
29
30 Assumes customer does not change initial requirements
Total Labor Costs
Product Development
Manufacturing
Administrative
Project Management
Project assumed to be 1 year long (52 weeks)
Assume a 5 member project team, including project manager
Break the Estimated Effort Into
Subgroups to Help Apply the Correct
Costs Values. It Also Helps Outline
How Much Effort Is Required From
Each Department
State the Assumptions You Made In
Establishing The Estimate. Should
Anything Change That Affects
Assumptions, You Will Know How To
Update the Estimate. They Also Help
You Refesh Your Memory Many
Months Later!
Include A Task Description and the
Frequency at Which the Task Will be
Performed. This Helps Capture
Hours Associated with Multiple
Iterations
Define Each Task to be Performed.
This Helps Establish a Bottoms-Up
Estimate Of What is Required
Include Comments as Appropriate to
Add Any Detail Necessary to Explain
the Numbers
Include a Cost Roll Up Based on the
Labor Rate Of Each Department.
Outline the Number of Hours You
Anticipate Each Task Will Take.

More Related Content

PPTX
Implementing infinity hr (katie cuthriell)
PPTX
TOLULOPE Viva
PDF
Implementing InfinityHR
PPTX
Agile metrics
PDF
CEI-BEI Dashboard
PDF
Lean Process Improvement Techniques
PPTX
6.1 Continuous Performance Improvement
PDF
Six Sigma Overview
Implementing infinity hr (katie cuthriell)
TOLULOPE Viva
Implementing InfinityHR
Agile metrics
CEI-BEI Dashboard
Lean Process Improvement Techniques
6.1 Continuous Performance Improvement
Six Sigma Overview

What's hot (20)

PPTX
Estimation & project planning
PPT
Improving Quality
PDF
Six Sigma overview for Grad School
POT
Milestone Summary Report
PDF
Free PMP Sample Q & A
PDF
Free PMP Sample Q & A
PDF
The Lean Strategic Challenge
PDF
A holistic approach to enabling people, processes and product development
PPTX
Agile updates
PPTX
Agile updates
PPTX
Why does agile need unit testing
PPTX
PMP CERTIFICATION TRAINING
PDF
Free PMP Sample Q & A
PDF
Free PMP Sample Q & A
PPTX
Agile project management at primavera
PDF
PDCA: Plan-Do-Check-Act
PPT
PDCA(slides)
PPT
Ms project general introduction
PDF
Project Status Report With Budget Estimation And Milestones Printable Report ...
PDF
Free PMP Sample Q & A
Estimation & project planning
Improving Quality
Six Sigma overview for Grad School
Milestone Summary Report
Free PMP Sample Q & A
Free PMP Sample Q & A
The Lean Strategic Challenge
A holistic approach to enabling people, processes and product development
Agile updates
Agile updates
Why does agile need unit testing
PMP CERTIFICATION TRAINING
Free PMP Sample Q & A
Free PMP Sample Q & A
Agile project management at primavera
PDCA: Plan-Do-Check-Act
PDCA(slides)
Ms project general introduction
Project Status Report With Budget Estimation And Milestones Printable Report ...
Free PMP Sample Q & A
Ad

Viewers also liked (17)

PDF
RISE OF THE MARKETING TECHNOLOGIST [INBOUND 2014]
PDF
PUT DOWN YOUR PHONE AND START A MOVEMENT! [INBOUND 2014]
PDF
10 Lessons for Managing in Tough Times
PPT
Team Effectiveness Model
PPT
Creating effective teams ppt
PDF
10 Lessons for New Managers
PDF
50 Best Motivational Quotes to Ignite Your Sales Drive
PDF
2016 A-Z Culture Glossary
PDF
Team Effectiveness
PPT
Team Building PowerPoint PPT Content Modern Sample
PDF
A-Z Culture Glossary 2017
PDF
Melt (Beta)
PPT
TEAM BUILDING POWERPOINT
PDF
Design Your Career 2018
PDF
Behind the Scenes: Launching HubSpot Tokyo
PPTX
10 Powerful Body Language Tips for your next Presentation
PDF
What Would Steve Do? 10 Lessons from the World's Most Captivating Presenters
RISE OF THE MARKETING TECHNOLOGIST [INBOUND 2014]
PUT DOWN YOUR PHONE AND START A MOVEMENT! [INBOUND 2014]
10 Lessons for Managing in Tough Times
Team Effectiveness Model
Creating effective teams ppt
10 Lessons for New Managers
50 Best Motivational Quotes to Ignite Your Sales Drive
2016 A-Z Culture Glossary
Team Effectiveness
Team Building PowerPoint PPT Content Modern Sample
A-Z Culture Glossary 2017
Melt (Beta)
TEAM BUILDING POWERPOINT
Design Your Career 2018
Behind the Scenes: Launching HubSpot Tokyo
10 Powerful Body Language Tips for your next Presentation
What Would Steve Do? 10 Lessons from the World's Most Captivating Presenters
Ad

Similar to Project Estimating Example (20)

PDF
Van heeringen estimate faster, cheaper, better
PPT
ISPA/SCEA conference Brussels 2012
PDF
Estimation guidelines and templates
PPTX
Agile work estimation template
PPTX
1587310189-week6.pptx
PDF
Software_effort_estimation for Software engineering.pdf
PDF
Project Duration Estimation
PPTX
Effort estimation( software Engineering)
PPTX
Estimations: hit the target. Tips & Technics
PPTX
3. Lect 29_ 30_ 32 Project Planning.pptx
PDF
Estimating 101
PDF
7 Signs of Bad Project Estimates - And How You Can Fix It
PPT
Software Project Estimation Survival Guide
PPTX
Estimation Protips
PPTX
Test estimation session
PPTX
Estimation Protips - NCDevCon 2014
DOCX
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
PPTX
Estimation - web software development estimation DrupalCon and DrupalCamp pre...
PPTX
Measuring Product Management/Ownership Effectiveness in a Lean/Agile world
PPTX
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Van heeringen estimate faster, cheaper, better
ISPA/SCEA conference Brussels 2012
Estimation guidelines and templates
Agile work estimation template
1587310189-week6.pptx
Software_effort_estimation for Software engineering.pdf
Project Duration Estimation
Effort estimation( software Engineering)
Estimations: hit the target. Tips & Technics
3. Lect 29_ 30_ 32 Project Planning.pptx
Estimating 101
7 Signs of Bad Project Estimates - And How You Can Fix It
Software Project Estimation Survival Guide
Estimation Protips
Test estimation session
Estimation Protips - NCDevCon 2014
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
Estimation - web software development estimation DrupalCon and DrupalCamp pre...
Measuring Product Management/Ownership Effectiveness in a Lean/Agile world
Project Schedule Management - Estimate Activity Durations - PMP Workgroup

Recently uploaded (20)

PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PPT
Chapter four Project-Preparation material
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Chapter 5_Foreign Exchange Market in .pdf
DOCX
Business Management - unit 1 and 2
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PDF
Cours de Système d'information about ERP.pdf
PDF
Roadmap Map-digital Banking feature MB,IB,AB
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Power and position in leadershipDOC-20250808-WA0011..pdf
Daniels 2024 Inclusive, Sustainable Development
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Chapter four Project-Preparation material
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Lecture 3344;;,,(,(((((((((((((((((((((((
unit 1 COST ACCOUNTING AND COST SHEET
Ôn tập tiếng anh trong kinh doanh nâng cao
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Chapter 5_Foreign Exchange Market in .pdf
Business Management - unit 1 and 2
COST SHEET- Tender and Quotation unit 2.pdf
Cours de Système d'information about ERP.pdf
Roadmap Map-digital Banking feature MB,IB,AB
Deliverable file - Regulatory guideline analysis.pdf
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
340036916-American-Literature-Literary-Period-Overview.ppt

Project Estimating Example

  • 1. www.managersresourcehandbook.com P a g e | 1 Rev. 1 Helping Managers and Businesses Succeed Through Real Experience Sample Template for Project Estimating This template is intended to provide an example breakdown of hours and effort associated with a given project. The comments listed in the boxes to the right highlight the various benefits associated with this particular template. The more detail you put into the estimate, the better your estimate will be. Line Task Description Frequency Hours Iterations Total Comment 1 Build Project Schedule One Time 12 1 12 2 Update Project Schedule Monthly 4 11 44 3 Manage Project Financials Biweekly 4 26 104 4 Produce Project Reports Monthly 4 12 48 5 Customer Status Meeting Weekly 1.5 52 78 6 Executive Presentations Quarterly 2 4 8 Preparation and Presentation Project Management Total 294 Line Task Description Frequency Hours Iterations Total Comment 7 Conceptual Designs One Time 60 2 120 8 Development Design One Time 250 1 250 9 Design Review Preparation Quarterly 20 4 80 10 Design Reviews Quarterly 25 4 100 11 Schematic Development One Time 3 40 120 Assume 40 schematics 12 Prototype Development One Time 80 1 80 13 Test Planning One Time 40 1 40 14 Prototype Testing Monthly 2 12 24 15 Test Report One Time 6 1 6 16 Final Design and Closeout One Time 75 1 75 Product Development Total 820 Line Task Description Frequency Hours Iterations Total Comment 17 Order Raw Materials One Time 4 1 4 18 Update Manufacturing Plan Monthly 2 12 24 19 Build Prototype One Time 24 1 24 20 Build Test Rig One Time 12 1 12 Manufacturing Total 64 Line Task Description Frequency Hours Iterations Total Comment 21 Team Meetings (1 Hour) Weekly 5 50 250 Assume 5 member team 22 Update Project Team Template Weekly 1 50 50 23 Customer Visit Monthly 8 12 96 Administrative Total 396 Line Function Hours Rate Total Comment 24 Project Management 294 50 € 14,700 25 Product Development 820 47 € 38,540 26 Manufacturing 64 45 € 2,880 27 Administrative 396 48 € 19,008 Averaged Team Rate Total Labor Cost € 75,128 Assumptions 28 29 30 Assumes customer does not change initial requirements Total Labor Costs Product Development Manufacturing Administrative Project Management Project assumed to be 1 year long (52 weeks) Assume a 5 member project team, including project manager Break the Estimated Effort Into Subgroups to Help Apply the Correct Costs Values. It Also Helps Outline How Much Effort Is Required From Each Department State the Assumptions You Made In Establishing The Estimate. Should Anything Change That Affects Assumptions, You Will Know How To Update the Estimate. They Also Help You Refesh Your Memory Many Months Later! Include A Task Description and the Frequency at Which the Task Will be Performed. This Helps Capture Hours Associated with Multiple Iterations Define Each Task to be Performed. This Helps Establish a Bottoms-Up Estimate Of What is Required Include Comments as Appropriate to Add Any Detail Necessary to Explain the Numbers Include a Cost Roll Up Based on the Labor Rate Of Each Department. Outline the Number of Hours You Anticipate Each Task Will Take.