SlideShare a Scribd company logo
MS Project
Terms
 Duration
 Work
 Resource
 Resource Units
 Effort-Driven
 Fixed Duration
 Fixed Units
 Fixed Work
 Over-
allocation
 Leveling
Duration & Work
 Duration - The total span of working time or elapsed time required to
complete a task.
 Work - The total effort required to complete a task.
Resources
 Resources are the people, equipment and supplies used to
complete tasks in a project.
 Resources that are assigned to tasks but do not create work are
known as material resources.
 Resource Units indicate how much of a resource's available time,
according to the resource calendar, is being used to work on a
particular task. In a project schedule, resource effort is expressed
as assignment units or sometimes just as units.
Scheduling Formula
Duration = Work ÷ Resource Units
Fixed Units
 As the task's assigned units remain constant, an increase /
decrease in assigned work will result in a corresponding increase /
decrease in task duration.
 Fixed Units is the default task type for new tasks.
Fixed Work
 If assigned work should remain constant, then as a
task's duration goes up assigned units will go down
(and vice versa).
 If assigned units are greater than max units, a resource
over-allocation will arise.
 Duration = Work ÷
Resource Units
 or Duration = 1 ÷ Resource
Units
Fixed Duration
 For a constant task duration, as assigned work is
increased so will assigned units.
 Decrease the units and the work will correspondingly
reduce.
 Duration = Work ÷
Resource Units
 If assigned units are greater than max units, a resource
over-allocation will arise.
Effort-Driven
 Only comes into play after the initial resource assignments have been
made
 Work stays constant
 When resources (manpower) are assigned or removed from a task,
Microsoft Project will extend or shorten the duration of the task to
accommodate change in resources
 This is the default option for new tasks
Ms project general introduction
Over-allocation
 Situation when more hours of a resource are allocated
than are available
 Identifying Over-allocated Resources
 Special leveling indicator
 Resource Usage View – over-allocated resources are red
 Over-allocation can be resolved by leveling project
Leveling
 Resolving resource conflicts or over-
allocations by delaying or splitting certain
tasks.
 During leveling, assignments are
rescheduled according to the resource
availability profiles, assigned units, and
resource calendars, as well as the task's
duration and constraints.
 It is instigated either automatically or (more
commonly) by the command level now.
 Tools | Level Resources . . . (hour by hour)
Questions?

More Related Content

PPTX
How to choose the right task type in Microsoft Project?
PPTX
09 Fine-tuning Assignment Details
PPT
Ms Project 2007(advanced)
PPTX
10 Fine-tuning Project Plan
PPTX
06 Tracking Progress on Tasks
PPT
MS Project 2007 Tips and Tricks
PPT
Ms Project 2007(Basic)
PPTX
07 Fine-tuning Task Details
How to choose the right task type in Microsoft Project?
09 Fine-tuning Assignment Details
Ms Project 2007(advanced)
10 Fine-tuning Project Plan
06 Tracking Progress on Tasks
MS Project 2007 Tips and Tricks
Ms Project 2007(Basic)
07 Fine-tuning Task Details

What's hot (20)

PPTX
12 Tracking Progress on Tasks and Assignments
PPTX
02 Creating A Task List
PPT
Microsoft project 2010
PDF
Ms Project 2010 Application For PMP
PPTX
Software engineering 11 project scheduling
PPTX
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
PPSX
MS Project 2010 Training
PDF
sMs project tutorial_iit
PPSX
How to Create S-Curve by MS Project 2010
PDF
Project management by MS Project 2010
DOCX
Microsoft project calender
PPTX
04 Assigning Resources to Tasks
PDF
MS Project 2010 Quick Reference Card
PPTX
Project Scheduling
PDF
Ms project 2000 tutorial
PDF
MS Project
PPSX
Project network scheduling and S-curve
PPSX
How to Create S Curve by MS Project 2013
PDF
Practical Use of Microsoft Project for Project Managers
PDF
Scheduling by using microsoft project 2013
12 Tracking Progress on Tasks and Assignments
02 Creating A Task List
Microsoft project 2010
Ms Project 2010 Application For PMP
Software engineering 11 project scheduling
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
MS Project 2010 Training
sMs project tutorial_iit
How to Create S-Curve by MS Project 2010
Project management by MS Project 2010
Microsoft project calender
04 Assigning Resources to Tasks
MS Project 2010 Quick Reference Card
Project Scheduling
Ms project 2000 tutorial
MS Project
Project network scheduling and S-curve
How to Create S Curve by MS Project 2013
Practical Use of Microsoft Project for Project Managers
Scheduling by using microsoft project 2013
Ad

Viewers also liked (20)

PPTX
Survey responses
PPTX
Uts congestion components
PPTX
Key factors related to traffic crashes by Malyar Talash
PPT
Coordinate Systems
PPT
Section and development
PPT
Civil 3 d overview general
PPT
PPT
Scales in Engineering
PPTX
Acts & Plot points
PPTX
Moscow, ID case study traffic operation
PPTX
Presentation hcm 2010 case study
PPTX
Enviromental impact assesment for highway projects
PPTX
Tunnel example for road project by Malyar Talash
PPT
3 vertical alignment of road by Malyar Talash
PDF
Manual Civil 3d Ingles
PPTX
Land surveying software and design solution
PPT
Intersection and Penetration of Soilds
PPTX
Land Surveying Software(AutoCAD) Tutorial
PPT
Ms project working example
Survey responses
Uts congestion components
Key factors related to traffic crashes by Malyar Talash
Coordinate Systems
Section and development
Civil 3 d overview general
Scales in Engineering
Acts & Plot points
Moscow, ID case study traffic operation
Presentation hcm 2010 case study
Enviromental impact assesment for highway projects
Tunnel example for road project by Malyar Talash
3 vertical alignment of road by Malyar Talash
Manual Civil 3d Ingles
Land surveying software and design solution
Intersection and Penetration of Soilds
Land Surveying Software(AutoCAD) Tutorial
Ms project working example
Ad

Similar to Ms project general introduction (20)

PDF
Ms project2007 quickguide
PDF
Ms project2007 quickguide
PDF
How Does MS Project Works 6- Task Controlling Factors
PPT
Understanding How Microsoft Project Thinks
DOCX
Project Priority MatrixProject NameProject Priority MatrixConstrai.docx
DOCX
Sheet1Points0ENGL510 Grading Rubric Group .docx
PPTX
Allocating resources
DOC
Devry proj 586 week 3 project guidelines microsoft project new
PDF
B012440511
PDF
Activity Duration Types Explained with example in Primavera
PPT
project_management and its adoption_10.ppt
PPTX
MICROSOFT PROJECT TUTORIAL
PDF
Project Management - Report
DOCX
MGT 3302, Introduction to Project Management 1 Cou.docx
PDF
Ms project 2010 tutorial 2
DOC
2007 MS Project Training Instructors Manual (sample)
PPSX
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
PPTX
Duration - The Holy Grail of MS Project?
PPTX
03 Setting-up resources
DOCX
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
Ms project2007 quickguide
Ms project2007 quickguide
How Does MS Project Works 6- Task Controlling Factors
Understanding How Microsoft Project Thinks
Project Priority MatrixProject NameProject Priority MatrixConstrai.docx
Sheet1Points0ENGL510 Grading Rubric Group .docx
Allocating resources
Devry proj 586 week 3 project guidelines microsoft project new
B012440511
Activity Duration Types Explained with example in Primavera
project_management and its adoption_10.ppt
MICROSOFT PROJECT TUTORIAL
Project Management - Report
MGT 3302, Introduction to Project Management 1 Cou.docx
Ms project 2010 tutorial 2
2007 MS Project Training Instructors Manual (sample)
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
Duration - The Holy Grail of MS Project?
03 Setting-up resources
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx

More from Kushal Patel (9)

PDF
Design guidance for freeway mainline ramp terminals
PDF
Autodesk civil3 d_tutorail
PPTX
Types of bridge(theory.explanation)
PPT
Types of bridge(concept)
PPTX
Eia methods for transportation project
PPTX
Plane table survey
PPTX
Land use planning
PPTX
Airport lighting airport engineering
PPTX
Road geometrics
Design guidance for freeway mainline ramp terminals
Autodesk civil3 d_tutorail
Types of bridge(theory.explanation)
Types of bridge(concept)
Eia methods for transportation project
Plane table survey
Land use planning
Airport lighting airport engineering
Road geometrics

Recently uploaded (20)

PPTX
CHAPTER 2 - PM Management and IT Context
PDF
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
PDF
Nekopoi APK 2025 free lastest update
PDF
System and Network Administration Chapter 2
PDF
Softaken Excel to vCard Converter Software.pdf
PDF
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
PDF
EN-Survey-Report-SAP-LeanIX-EA-Insights-2025.pdf
PDF
Design an Analysis of Algorithms I-SECS-1021-03
PPTX
Reimagine Home Health with the Power of Agentic AI​
PDF
Upgrade and Innovation Strategies for SAP ERP Customers
PDF
Understanding Forklifts - TECH EHS Solution
PDF
medical staffing services at VALiNTRY
PPTX
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
PDF
2025 Textile ERP Trends: SAP, Odoo & Oracle
PDF
AI in Product Development-omnex systems
PDF
Adobe Premiere Pro 2025 (v24.5.0.057) Crack free
PDF
Why TechBuilder is the Future of Pickup and Delivery App Development (1).pdf
PDF
PTS Company Brochure 2025 (1).pdf.......
PDF
Digital Strategies for Manufacturing Companies
PDF
System and Network Administraation Chapter 3
CHAPTER 2 - PM Management and IT Context
Audit Checklist Design Aligning with ISO, IATF, and Industry Standards — Omne...
Nekopoi APK 2025 free lastest update
System and Network Administration Chapter 2
Softaken Excel to vCard Converter Software.pdf
Addressing The Cult of Project Management Tools-Why Disconnected Work is Hold...
EN-Survey-Report-SAP-LeanIX-EA-Insights-2025.pdf
Design an Analysis of Algorithms I-SECS-1021-03
Reimagine Home Health with the Power of Agentic AI​
Upgrade and Innovation Strategies for SAP ERP Customers
Understanding Forklifts - TECH EHS Solution
medical staffing services at VALiNTRY
Lecture 3: Operating Systems Introduction to Computer Hardware Systems
2025 Textile ERP Trends: SAP, Odoo & Oracle
AI in Product Development-omnex systems
Adobe Premiere Pro 2025 (v24.5.0.057) Crack free
Why TechBuilder is the Future of Pickup and Delivery App Development (1).pdf
PTS Company Brochure 2025 (1).pdf.......
Digital Strategies for Manufacturing Companies
System and Network Administraation Chapter 3

Ms project general introduction

  • 2. Terms  Duration  Work  Resource  Resource Units  Effort-Driven  Fixed Duration  Fixed Units  Fixed Work  Over- allocation  Leveling
  • 3. Duration & Work  Duration - The total span of working time or elapsed time required to complete a task.  Work - The total effort required to complete a task.
  • 4. Resources  Resources are the people, equipment and supplies used to complete tasks in a project.  Resources that are assigned to tasks but do not create work are known as material resources.  Resource Units indicate how much of a resource's available time, according to the resource calendar, is being used to work on a particular task. In a project schedule, resource effort is expressed as assignment units or sometimes just as units.
  • 5. Scheduling Formula Duration = Work ÷ Resource Units
  • 6. Fixed Units  As the task's assigned units remain constant, an increase / decrease in assigned work will result in a corresponding increase / decrease in task duration.  Fixed Units is the default task type for new tasks.
  • 7. Fixed Work  If assigned work should remain constant, then as a task's duration goes up assigned units will go down (and vice versa).  If assigned units are greater than max units, a resource over-allocation will arise.  Duration = Work ÷ Resource Units  or Duration = 1 ÷ Resource Units
  • 8. Fixed Duration  For a constant task duration, as assigned work is increased so will assigned units.  Decrease the units and the work will correspondingly reduce.  Duration = Work ÷ Resource Units  If assigned units are greater than max units, a resource over-allocation will arise.
  • 9. Effort-Driven  Only comes into play after the initial resource assignments have been made  Work stays constant  When resources (manpower) are assigned or removed from a task, Microsoft Project will extend or shorten the duration of the task to accommodate change in resources  This is the default option for new tasks
  • 11. Over-allocation  Situation when more hours of a resource are allocated than are available  Identifying Over-allocated Resources  Special leveling indicator  Resource Usage View – over-allocated resources are red  Over-allocation can be resolved by leveling project
  • 12. Leveling  Resolving resource conflicts or over- allocations by delaying or splitting certain tasks.  During leveling, assignments are rescheduled according to the resource availability profiles, assigned units, and resource calendars, as well as the task's duration and constraints.  It is instigated either automatically or (more commonly) by the command level now.  Tools | Level Resources . . . (hour by hour)