There are four duration types in Primavera P6 that control how duration, resource units, and resource units/time are synchronized for activities:
1) Fixed Units/Time: Units/time remains fixed while duration or units may change
2) Fixed Duration and Units/Time: Duration and units/time remain fixed while units may change
3) Fixed Units: Units remain fixed while duration or units/time may change
4) Fixed Duration and Units: Duration and units remain fixed while units/time may change
The duration type balances the equation of Duration x Units/Time = Units and determines which variable(s) change when another is modified. The appropriate duration type depends on whether the project priorities are