Duration Types in Primavera P6
Duration Type is a setting which allows the user to control how the duration, resource units, and resource units/time are synchronized for activities, so that
the following equation is always true:

Original, Remaining or Planned Duration = (Budgeted, Remaining or Planned Units) / (Budgeted, Remaining or Planned Units/Time)

If the activity is not started, the names of the values are

: Original Duration x Budgeted Units/Time = Budgeted Units

If the activity has started, the names of the values are

: Remaining Duration x Remaining Units/Time = Remaining Units

The following table lists the value that changes to balance the equation
Duration x Units/Time = Units
The following table illustrates how the variables in the above equation changes when you change one among them in each of the Activity duration types.
Duration Type

Fixed Units/Time
Fixed Duration
and Units/Time
Fixed Units
Fixed Duration
and Units

When You Change
Duration, what
changes?
Units
Units

When you change
units/time,
what changes?
Duration
Units

When you change
units, what
changes?
Duration
Units/Time

When you add a
resource, what
changes?
Duration
Units

Units/Time
Units/Time

Duration
Units

Duration
Units/Time

Duration
Units/Time

Table 1. Activity duration types
The duration type is set at the Project Details level for the Project, but can be modified per activity. Your organization’s project
needs will help to determine which duration type to use. We’ll be discussing in the following section as of what situation forces you to
choose a particular Duration type.
As a hint, if you are adding resources to activities and you do NOT want P6 to recalculate the existing resources units, duration and
units/time, go to Edit, User Preferences from the Menu bar, select the Calculations tab and select the Preserve the Units, Duration and
Units/Time for existing assignments radio button.

Example:Now let us consider a Case and work on it to get a better understanding on the Activity duration types.
Given Case :Consider a software company where a resource is assigned design work of a particular website. It is estimated that the design
work would be completed within 5 working days of the resource. The particular resource has a regular shift duration of 8 hours /day.
Find what happens to values of the Original duration, budgeted units/time and Budgeted units when
i.

Original duration changes to 10 days

ii.

Budgeted units/time changes to 10hours/day

iii.

Budgeted units of work changes to 20 hours

In each of the activity duration types.
Findings:

Original Duration =5 days ,
Budgeted units/time = 8h/d

From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40 hours
Type I :-Fixed Units / Time
Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used when resources with
productivity output per time period is fixed. Mostly used when Activity type is Resource Dependent. This option is selected if your
organization is concerned with leveling resources and you assign resources specific hours per day on activities.
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Duration

Duration

changes?
Fixed Units/Time

Units

Table 1.1.1 Fixes Units / Time
Coming back to our case
Where Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
i.e. Original Duration = units / (units/time)  5= 40 / 8
We were asked to analyze what would happen if
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

80h
=>

from 8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes

8h/d

4d

40h

2.5d

8h/d

10=> 80/8

4 => 40/10

Table 1.1.2 Fixes Units / Time Workout

2.5 => 20/8
Type II: Fixed Duration & Units/Time
Activity duration and units / time remains fixed; even if remaining unit’s changes. Mostly used when Activity type is Task Dependent
Activity. Organizations which have the project deadline fixed and is also concerned with leveling resources used this activity duration type.
Organization may consider increasing number of resources to keep the resources leveled. Since this activity is Task dependant and activity
duration type is fixed duration & Units/time there would be no layoff in duration time.

Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Units

Units/Time

changes?
Fixed Duration and

Units

Units/Time
Table 1.2.1 Fixed Duration & Units/Time
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

80h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

8h/d

5d

50h

5d

4h/d

10=> 80/8

5 => 50/10

Table 1.2.2 Fixed Duration & Units/Time Workout

5 => 20/4*
Type III :-Fixed Units
This duration type is chosen if you want the activity units to be fixed even when duration or resource units per time changes. Total
amount of Work is fixed. Used when Activity type is Resource Dependent Activities. Unlike previous Duration types increasing resources
decreases the activity duration. Generally used when you have resource under contract basis and you have X units of work to get to be done
from that particular resource.
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Duration

Duration

changes?
Fixed Units

Units/Time

Table 1.3.1 Fixed Units
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

40h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

4h/d

4d

40h

2.5d

8h/d

10=> 40/4

4 => 40/4

2.5 => 20/8

Table 1.3.2 Fixed Units Workout

Type IV :-Fixed Duration & Units
Activity duration and Units to remain constant even when the units/time changes. Mostly used when time period and the total
amount of work are fixed. Used when Activity type is Task Dependent Activities. Rate at which a resource can work on the activity can be
changed. You could use this if your organization is more concerned about coming in on the schedule date and within the costs (which are
usually associated with the units)
Original Duration = Budgeted Units / Budgeted Units/Time
Duration Type

When You Change Duration,

When you change units/time,

When you change units, what

what

what changes?

changes?

Units

Units/Time

changes?
Fixed Duration and Units

Units/Time

Table 1.4.1 Fixed Duration & Units
Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours.
Changes made

(i) Original Duration Changes

duration

(Units )/
(Units/time)

from 40 to 20

Budgeted

Original

Budgeted

Original

Budgeted

units

units/time

Duration

units

Duration

units/time

40h
=>

8 to 10

Budgeted

Original

(iii) Units changes

from 5 to 10 days

Values changed

(ii) Units / time changes from

4h/d

5

50

5d

4h/d

10=> 40/4

5 => 50/5*

Table 1.4.2 Fixed Duration & Units Workout

5 => 20/4
Summary
Given Original Duration 5days; Budgeted Units 40hours; Budgeted Units/ time 8hours/day. The following table summarizes as of what
happens to the variables in each of the activity duration types.
Units / time changes from 8 to 10

Units changes from 40 to 20

Budgeted units

Budgeted

Original Duration

Budgeted units

Original Duration

Budgeted

(Or. Val:- 40h)

Type

Duration

Original Duration Changes from 5 to 10

units/time(Or. Val:-

(Or. Val:- 5d)

(Or. Val:- 40h)

(Or. Val:- 5d)

units/time

8h/d)

Fixed Units / Time

(Or. Val:- 8h/d)

80h

8h/d

4d

40h

2.5d

8h/d

80h

8h/d

5d

50h

5d

4h/d*

Fixed Units

40h

4h/d

4d

40h

2.5d

8h/d

Fixed Duration & Units

40h

4h/d

5d

50h*

5d

4h/d

Fixed Duration &
Units/Time

Table 2: Activity duration table chart
Or.Val - Original Value

* - in certain cases original duration remains fixed and the other fixed variable is forced to changed.

Reference:https://ccsspl123-public.sharepoint.com/Support%20Documents/duration%20types-Activity.pdf
http://www.projectcontrolsonline.com/Forum/tabid/65/forumid/13/threadid/529/scope/posts/Default.aspx

More Related Content

PDF
Primavera P6 manual
PPTX
MICROSOFT PROJECT TUTORIAL
DOC
Project Engineer and Deputy project manger
PPTX
Ms project training ppt
PPTX
MS Project Presentation
PDF
Project Scheduling & Controls
PDF
Ms Project 2010
PPTX
ppt for primevera
Primavera P6 manual
MICROSOFT PROJECT TUTORIAL
Project Engineer and Deputy project manger
Ms project training ppt
MS Project Presentation
Project Scheduling & Controls
Ms Project 2010
ppt for primevera

What's hot (20)

PPT
Wbs, estimation and scheduling
PDF
Primavera P6 Tips and Tricks
PDF
Understanding p6 dates
PPTX
Work breakdown structures
PDF
Primavera - Tutorial
PPTX
Primavera presentation
PDF
Pdf primavera tutorial
PPTX
Project Scheduling
PDF
MS Project
PDF
PM using P6
PDF
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
PPTX
Baseline schedule review and analysis
PDF
Schedule Updates
PPT
Project cost stimating
PPTX
PRIMAVERA P6 manual.pptx
PDF
Mega Project Management In The Oil & Gas Industry
PPTX
44259126 ms-project-presentation
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPT
Primavera Training P6
PDF
How to start primavera p6
Wbs, estimation and scheduling
Primavera P6 Tips and Tricks
Understanding p6 dates
Work breakdown structures
Primavera - Tutorial
Primavera presentation
Pdf primavera tutorial
Project Scheduling
MS Project
PM using P6
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Baseline schedule review and analysis
Schedule Updates
Project cost stimating
PRIMAVERA P6 manual.pptx
Mega Project Management In The Oil & Gas Industry
44259126 ms-project-presentation
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Primavera Training P6
How to start primavera p6
Ad

Viewers also liked (17)

PPTX
Understanding Constraints and Relationships in Primavera P6 8.2
PDF
Primavera Project Management
PDF
S Curves Made Easy With Primavera P6
PDF
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
PPSX
P6 Version 7 Tricks and Traps
PPTX
Activity Types and Relationships in Primavera p6
PPTX
Primavera p6 v8.2 session 1
PPTX
Authentic Global Connections Learning2 Saigon2016
PDF
P6 brief
PDF
Configuring Primavera Team Member for Project Updates
PDF
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
PDF
User preference Option in Oracle Primavera EPPM P6
PDF
Oracle PPM. What's new in P6release 8.2?
PDF
What's New in Primavera 15.2 Webcast
PDF
Primavera P6 EPPM Portlets Index
PDF
Primavera P6 Professional Windows 10 Installation Instructions
PDF
Whats new in Primavera P6 EPPM 15.2?
Understanding Constraints and Relationships in Primavera P6 8.2
Primavera Project Management
S Curves Made Easy With Primavera P6
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
P6 Version 7 Tricks and Traps
Activity Types and Relationships in Primavera p6
Primavera p6 v8.2 session 1
Authentic Global Connections Learning2 Saigon2016
P6 brief
Configuring Primavera Team Member for Project Updates
200850 oracle primavera p6 eppm performance tuning, testing, and monitoring
User preference Option in Oracle Primavera EPPM P6
Oracle PPM. What's new in P6release 8.2?
What's New in Primavera 15.2 Webcast
Primavera P6 EPPM Portlets Index
Primavera P6 Professional Windows 10 Installation Instructions
Whats new in Primavera P6 EPPM 15.2?
Ad

Similar to Activity Duration Types Explained with example in Primavera (20)

PPTX
How to choose the right task type in Microsoft Project?
PDF
Ms project2007 quickguide
PDF
Ms project2007 quickguide
PPT
Understanding How Microsoft Project Thinks
PPSX
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
PPS
100632 p6 v7 tricks and traps
PPTX
07 Fine-tuning Task Details
PDF
Estimating-Durations-Activities-EDGE.pdf
PPT
Ms project general introduction
PPT
Digging A Hole
PPTX
09 Fine-tuning Assignment Details
PPTX
Lecture 4 - Engineering project Scheduling.pptx
PPTX
Microsoft Project Foundations Course.pptx
PDF
Project 2007 full handout
PDF
How to change working days and time in MS Project?
PDF
Project Planning - Key Concepts for project scheduling
PDF
How Does MS Project Works 6- Task Controlling Factors
PDF
Pert techniques
PPT
Ms Project
DOCX
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
How to choose the right task type in Microsoft Project?
Ms project2007 quickguide
Ms project2007 quickguide
Understanding How Microsoft Project Thinks
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
100632 p6 v7 tricks and traps
07 Fine-tuning Task Details
Estimating-Durations-Activities-EDGE.pdf
Ms project general introduction
Digging A Hole
09 Fine-tuning Assignment Details
Lecture 4 - Engineering project Scheduling.pptx
Microsoft Project Foundations Course.pptx
Project 2007 full handout
How to change working days and time in MS Project?
Project Planning - Key Concepts for project scheduling
How Does MS Project Works 6- Task Controlling Factors
Pert techniques
Ms Project
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx

More from CADD Centre Software Solutions Private Limited (20)

PPTX
A b-c-d-(e) of ccsspl corporate presentation
PDF
Login methodology for Primavera V8.3 (EPPM)
PDF
Oracle Primavera Team member 8.3
PDF
PDF
Recurring task IN MS project
PDF
Oracle Primavera contract management
DOCX
Uses of Project Status field
PDF
Oracle primavera Universal content management
PPS
Pert master risk analysis tool
PDF
Oracle Primavera P6 PRO R8 Tips & tricks
PDF
Team member in iphones and android
PDF
Tested configuration for different Primavera versions
PDF
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
PDF
Features comparison between Primavera and Microsoft Project
PDF
Project management software consulting
PDF
Primavera vs microsoft project
A b-c-d-(e) of ccsspl corporate presentation
Login methodology for Primavera V8.3 (EPPM)
Oracle Primavera Team member 8.3
Recurring task IN MS project
Oracle Primavera contract management
Uses of Project Status field
Oracle primavera Universal content management
Pert master risk analysis tool
Oracle Primavera P6 PRO R8 Tips & tricks
Team member in iphones and android
Tested configuration for different Primavera versions
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Features comparison between Primavera and Microsoft Project
Project management software consulting
Primavera vs microsoft project

Recently uploaded (20)

PDF
PMB 401-Identification-of-Potential-Biotechnological-Products.pdf
PDF
Ron Thomas - Top Influential Business Leaders Shaping the Modern Industry – 2025
PPTX
Project Management_ SMART Projects Class.pptx
PPTX
CTG - Business Update 2Q2025 & 6M2025.pptx
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
DOCX
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
PDF
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
PDF
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
PDF
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
PDF
ICv2 White Paper - Gen Con Trade Day 2025
PPT
Lecture notes on Business Research Methods
PDF
Daniels 2024 Inclusive, Sustainable Development
DOCX
FINALS-BSHhchcuvivicucucucucM-Centro.docx
PPTX
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
PDF
533158074-Saudi-Arabia-Companies-List-Contact.pdf
PDF
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
PPTX
operations management : demand supply ch
DOCX
Hand book of Entrepreneurship 4 Chapters.docx
PMB 401-Identification-of-Potential-Biotechnological-Products.pdf
Ron Thomas - Top Influential Business Leaders Shaping the Modern Industry – 2025
Project Management_ SMART Projects Class.pptx
CTG - Business Update 2Q2025 & 6M2025.pptx
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Satish NS: Fostering Innovation and Sustainability: Haier India’s Customer-Ce...
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
Robin Fischer: A Visionary Leader Making a Difference in Healthcare, One Day ...
ICv2 White Paper - Gen Con Trade Day 2025
Lecture notes on Business Research Methods
Daniels 2024 Inclusive, Sustainable Development
FINALS-BSHhchcuvivicucucucucM-Centro.docx
2 - Self & Personality 587689213yiuedhwejbmansbeakjrk
533158074-Saudi-Arabia-Companies-List-Contact.pdf
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
operations management : demand supply ch
Hand book of Entrepreneurship 4 Chapters.docx

Activity Duration Types Explained with example in Primavera

  • 1. Duration Types in Primavera P6 Duration Type is a setting which allows the user to control how the duration, resource units, and resource units/time are synchronized for activities, so that the following equation is always true: Original, Remaining or Planned Duration = (Budgeted, Remaining or Planned Units) / (Budgeted, Remaining or Planned Units/Time) If the activity is not started, the names of the values are : Original Duration x Budgeted Units/Time = Budgeted Units If the activity has started, the names of the values are : Remaining Duration x Remaining Units/Time = Remaining Units The following table lists the value that changes to balance the equation Duration x Units/Time = Units The following table illustrates how the variables in the above equation changes when you change one among them in each of the Activity duration types. Duration Type Fixed Units/Time Fixed Duration and Units/Time Fixed Units Fixed Duration and Units When You Change Duration, what changes? Units Units When you change units/time, what changes? Duration Units When you change units, what changes? Duration Units/Time When you add a resource, what changes? Duration Units Units/Time Units/Time Duration Units Duration Units/Time Duration Units/Time Table 1. Activity duration types
  • 2. The duration type is set at the Project Details level for the Project, but can be modified per activity. Your organization’s project needs will help to determine which duration type to use. We’ll be discussing in the following section as of what situation forces you to choose a particular Duration type. As a hint, if you are adding resources to activities and you do NOT want P6 to recalculate the existing resources units, duration and units/time, go to Edit, User Preferences from the Menu bar, select the Calculations tab and select the Preserve the Units, Duration and Units/Time for existing assignments radio button. Example:Now let us consider a Case and work on it to get a better understanding on the Activity duration types. Given Case :Consider a software company where a resource is assigned design work of a particular website. It is estimated that the design work would be completed within 5 working days of the resource. The particular resource has a regular shift duration of 8 hours /day. Find what happens to values of the Original duration, budgeted units/time and Budgeted units when i. Original duration changes to 10 days ii. Budgeted units/time changes to 10hours/day iii. Budgeted units of work changes to 20 hours In each of the activity duration types.
  • 3. Findings: Original Duration =5 days , Budgeted units/time = 8h/d From the formula we know Budgeted units = Original Duration X Budgeted units/time = 8 x 5 = 40 hours Type I :-Fixed Units / Time Units/time for the resources remains fixed; Even when activity duration or budgeted units changes. Used when resources with productivity output per time period is fixed. Mostly used when Activity type is Resource Dependent. This option is selected if your organization is concerned with leveling resources and you assign resources specific hours per day on activities. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Duration Duration changes? Fixed Units/Time Units Table 1.1.1 Fixes Units / Time
  • 4. Coming back to our case Where Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. i.e. Original Duration = units / (units/time)  5= 40 / 8 We were asked to analyze what would happen if Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => from 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes 8h/d 4d 40h 2.5d 8h/d 10=> 80/8 4 => 40/10 Table 1.1.2 Fixes Units / Time Workout 2.5 => 20/8
  • 5. Type II: Fixed Duration & Units/Time Activity duration and units / time remains fixed; even if remaining unit’s changes. Mostly used when Activity type is Task Dependent Activity. Organizations which have the project deadline fixed and is also concerned with leveling resources used this activity duration type. Organization may consider increasing number of resources to keep the resources leveled. Since this activity is Task dependant and activity duration type is fixed duration & Units/time there would be no layoff in duration time. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time changes? Fixed Duration and Units Units/Time Table 1.2.1 Fixed Duration & Units/Time
  • 6. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 80h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 8h/d 5d 50h 5d 4h/d 10=> 80/8 5 => 50/10 Table 1.2.2 Fixed Duration & Units/Time Workout 5 => 20/4*
  • 7. Type III :-Fixed Units This duration type is chosen if you want the activity units to be fixed even when duration or resource units per time changes. Total amount of Work is fixed. Used when Activity type is Resource Dependent Activities. Unlike previous Duration types increasing resources decreases the activity duration. Generally used when you have resource under contract basis and you have X units of work to get to be done from that particular resource. Original Duration = Budgeted Units / Budgeted Units/Time Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Duration Duration changes? Fixed Units Units/Time Table 1.3.1 Fixed Units
  • 8. Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 4h/d 4d 40h 2.5d 8h/d 10=> 40/4 4 => 40/4 2.5 => 20/8 Table 1.3.2 Fixed Units Workout Type IV :-Fixed Duration & Units Activity duration and Units to remain constant even when the units/time changes. Mostly used when time period and the total amount of work are fixed. Used when Activity type is Task Dependent Activities. Rate at which a resource can work on the activity can be changed. You could use this if your organization is more concerned about coming in on the schedule date and within the costs (which are usually associated with the units) Original Duration = Budgeted Units / Budgeted Units/Time
  • 9. Duration Type When You Change Duration, When you change units/time, When you change units, what what what changes? changes? Units Units/Time changes? Fixed Duration and Units Units/Time Table 1.4.1 Fixed Duration & Units Given Original Duration =5 days ; Budgeted units/time = 8h/d And Budgeted units = 40 hours. Changes made (i) Original Duration Changes duration (Units )/ (Units/time) from 40 to 20 Budgeted Original Budgeted Original Budgeted units units/time Duration units Duration units/time 40h => 8 to 10 Budgeted Original (iii) Units changes from 5 to 10 days Values changed (ii) Units / time changes from 4h/d 5 50 5d 4h/d 10=> 40/4 5 => 50/5* Table 1.4.2 Fixed Duration & Units Workout 5 => 20/4
  • 10. Summary Given Original Duration 5days; Budgeted Units 40hours; Budgeted Units/ time 8hours/day. The following table summarizes as of what happens to the variables in each of the activity duration types. Units / time changes from 8 to 10 Units changes from 40 to 20 Budgeted units Budgeted Original Duration Budgeted units Original Duration Budgeted (Or. Val:- 40h) Type Duration Original Duration Changes from 5 to 10 units/time(Or. Val:- (Or. Val:- 5d) (Or. Val:- 40h) (Or. Val:- 5d) units/time 8h/d) Fixed Units / Time (Or. Val:- 8h/d) 80h 8h/d 4d 40h 2.5d 8h/d 80h 8h/d 5d 50h 5d 4h/d* Fixed Units 40h 4h/d 4d 40h 2.5d 8h/d Fixed Duration & Units 40h 4h/d 5d 50h* 5d 4h/d Fixed Duration & Units/Time Table 2: Activity duration table chart Or.Val - Original Value * - in certain cases original duration remains fixed and the other fixed variable is forced to changed. Reference:https://ccsspl123-public.sharepoint.com/Support%20Documents/duration%20types-Activity.pdf http://www.projectcontrolsonline.com/Forum/tabid/65/forumid/13/threadid/529/scope/posts/Default.aspx