Software Project Management
WBS, Estimation & Scheduling
The information contained in this presentation was obtained from the public domain
Reminders
• Best way to learn the most from SPM
course is not to behave like a student but
to think like a SPM.
Planning, Estimating, Scheduling
• What’s the difference?
• Plan: Identify activities. No specific start and end
dates.
• Estimating: Determining the size & duration of
activities.
• Schedule: Adds specific start and end dates,
relationships, and resources.
Project Planning: A 12 Step
Program
1) Set goal and scope
2) Select lifecycle
3) Set org./team form
4) Start team selection
5) Determine risks
6) Create WBS*
* Relatively an old technique
7) Identify tasks
8) Estimate size
9) Estimate effort
10)Identify task
dependencies
11)Assign resources
12)Schedule work
How To Schedule
• 1. Identify “what” needs to be done
– Work Breakdown Structure (WBS)
• 2. Identify “how much” (the size)
– Size estimation techniques
• 3. Identify the dependency between tasks
– Dependency graph, network diagram
• 4. Estimate total duration of the work to be done
– The actual schedule
Partitioning Your Project
• You need to decompose your project into
manageable chunks
• All projects need this step
• Divide & Conquer
• Two main causes of project failure
– Forgetting something critical
– Ballpark estimates become targets
• How does partitioning help this?
Work Breakdown Structure: WBS
• Hierarchical list of project’s work activities
• 2 Formats
– Outline (indented format)
– Graphical Tree (Organizational Chart)
• Uses a decimal numbering system
– Ex: 3.1.5
– 0 is typically top level
WBS
• Contract WBS (CWBS)
– First 2 or 3 levels
– High-level tracking
• Project WBS (PWBS)
– Defined by PM and team members
– Tasks tied to deliverables
– Lowest level tracking
A Full WBS Structure
• Up to six levels (3-6 usually) such as
WBS Chart Example
WBS Outline Example
0.0 Retail Web Site
1.0 Project Management
2.0 Requirements Gathering
3.0 Analysis & Design
4.0 Site Software Development
4.1 HTML Design and Creation
4.2 Backend Software
4.2.1 Database Implementation
4.2.2 Middleware Development
4.2.3 Security Subsystems
4.2.4 Catalog Engine
4.2.5 Transaction Processing
4.3 Graphics and Interface
4.4 Content Creation
5.0 Testing and Production
WBS Types
• Process WBS
• Activity-oriented
• Ex: Requirements, Analysis, Design, Testing
• Typically used by PM
• Product WBS
• Entity-oriented
• Ex: Financial engine, Interface system, DB
• Typically used by engineering manager
WBS Techniques
• Top-Down
• Bottom-Up
• Analogy
• Post-its on a wall
WBS Techniques
• Top-down
– Start at highest level
– Systematically develop increasing level of
detail
– Best if
• The problem is well understood
• Technology and methodology are not new
• This is similar to an earlier project or problem
– But is also applied in majority of situations
WBS Techniques
• Bottom-up
– Start at lowest level tasks
– Aggregate into summaries and higher levels
– Cons
• Time consuming
• Needs more requirements complete
– Pros
• Detailed
WBS Techniques
• Analogy
– Base WBS upon that of a “similar” project
– Use a template
– Analogy also can be estimation basis
– Pros
• Based on past actual experience
– Cons
• Needs comparable project
WBS Techniques
• Brainstorming
– Generate all activities you can think of that
need to be done
– Group them into categories
WBS – Basis of Many Things
• Network scheduling
• Costing
• Risk analysis
• Organizational structure
• Control
• Measurement
WBS Guidelines Part 1
• Should be easy to understand
• Some companies have corporate standards for
these schemes
• Some top-level items, like Project Mgmt. are in
WBS for each project
– Others vary by project
• What often hurts most is what’s missing
• Break down until you can generate accurate
time & cost estimates
• Ensure each element corresponds to a
deliverable
WBS Guidelines Part 2
• How detailed should it be?
– Each level should have no more than 7 items
– It can evolve over time
• What tool should you use?
– Excel, Word, Project
– Org chart diagramming tool (Visio, etc)
– Specialized commercial apps
• Re-use a “template” if you have one
Estimations
• Very difficult to do, but needed often
• Basic process
1) Estimate the size of the product
2) Estimate the effort (man-months)
3) Estimate the schedule
– NOTE: Not all of these steps are always
explicitly performed
Estimations
• Remember, an “exact estimate” is difficult
• Estimate how long will it take you to get
home from class tonight
– On what basis did you do that?
– Experience right?
– Likely as an “average” probability
Estimation
• Target vs. Committed Dates
• Target: Proposed by business or marketing
• Do not commit to this too soon!
• Committed: Team agrees to this
• After you’ve developed a schedule
Estimation (Software)
• Size:
– Small projects (10-99 FPs), variance of 7%
from post-requirements estimates
– Medium (100-999 FPs), 22% variance
– Large (1000-9999 FPs) 38% variance
– Very large (> 10K FPs) 51% variance
Estimation Methodologies
• Top-down
• Bottom-up
• Analogy
• Expert Judgment
• Priced to Win
• Parametric or Algorithmic Method
– Using formulas and equations
Algorithmic Measures
• Lines of Code (LOC)
• Function points
• Feature points or object points
• Other possible
– Number of processes on a structure chart
• LOC and function points most common
– (of the algorithmic approaches)
Code Reuse & Estimation
• Does not come for free
• Code types: New, Modified, Reused
• If code is more than 50% modified, it’s “new”
• Reuse factors have wide range
– Reused code takes 30% effort of new
– Modified is 60% of new
• Integration effort with reused code almost as
expensive as with new code
Effort Estimation
• Now that you know the “size”, determine the
“effort” needed to build it
• Various models: empirical, mathematical,
subjective
• Expressed in units of duration
– Man-months (or ‘staff-months’ now)
Effort Estimation
• As with parametric size estimation, these
techniques perform better with historical
data
• Again, not seen in ‘average’ projects
• Often the size and effort estimation steps
are combined (not that this is
recommended, but is what often is done)
COCOMO
• COnstructive COst MOdel
• Allows for the type of application, size, and “Cost
Drivers”
• Outputs in Person Months
• Cost drivers using High/Med/Low & include
– Motivation
– Ability of team
– Application experience
• Biggest weakness?
– Requires input of a product size estimate in LOC
Know Your Deadlines
• Are they ‘Real Deadlines’?
– Tied to an external event
– Have to be met for project to be a success
– Ex: end of financial year, contractual deadline, Y2K
• Or ‘Artificial Deadlines’?
– Set by arbitrary authority
– May have some flexibility (if pushed)

More Related Content

PDF
Project Control Handbook
PDF
CCP_SEC2_ Cost Estimating
PPT
7. (lecture 5) Project scheduling..ppt
PDF
PMP Chap 10 - Project Communication Management Details
PPTX
Project time management
PDF
How to Choose a Project Delivery Method
PPTX
Project management
PPTX
Project Scheduling
Project Control Handbook
CCP_SEC2_ Cost Estimating
7. (lecture 5) Project scheduling..ppt
PMP Chap 10 - Project Communication Management Details
Project time management
How to Choose a Project Delivery Method
Project management
Project Scheduling

What's hot (20)

PPTX
Project Risk Management
PPTX
Work Breakdown Structures (WBS)
PPT
Project management (1)
PDF
Earned Value Management
PDF
Project Scheduling
PPTX
Work breakdown structure
PPTX
2. project initiation
PDF
Software Project Management (SPM)
PDF
10 Project Management Knowledge Areas
PPTX
Project Management Best Practices - Tips and Techniques
PPTX
Work breakdown structure ppt
PDF
Project Risk Management
PPTX
Triple constraint
PPT
Project Management - Basic Concepts
PDF
Work Breakdown Structure
PPTX
Construction management
PPTX
Role and Responsibilities of Project Manager
PPT
Project Planning Scheduling
PPT
Ch 9 project monitoring & control updated
Project Risk Management
Work Breakdown Structures (WBS)
Project management (1)
Earned Value Management
Project Scheduling
Work breakdown structure
2. project initiation
Software Project Management (SPM)
10 Project Management Knowledge Areas
Project Management Best Practices - Tips and Techniques
Work breakdown structure ppt
Project Risk Management
Triple constraint
Project Management - Basic Concepts
Work Breakdown Structure
Construction management
Role and Responsibilities of Project Manager
Project Planning Scheduling
Ch 9 project monitoring & control updated
Ad

Similar to Wbs, estimation and scheduling (20)

PPT
Software Project Management (lecture 4)
PPT
project on software industry
PPTX
SE2023 0301 Software Project Management.pptx
PPT
Intro to PM.ppt
PDF
Lect-5: Work Breakdown Structure and Project Cost Estimation
PPT
WBS PROJECT
PPTX
project time management
PPTX
Project-Management.pptx
DOCX
Using the work breakdown structure to plan a project
PDF
Project Management and Organization
PPTX
MIS Project management
DOCX
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
PPT
wbs.ppt
PPT
Work Breakdown Structure in Construction Cost Engineering.ppt
PPT
Wbs & Project Scheduling
PPTX
SPM_UNIT-2.pptx
PPSX
ABCs Of Project Time Management Planning Slides
PPTX
PROJECT MANAGEMENT Work Breakdown Structure
PDF
Project Management Essentials Materials_0.pdf
Software Project Management (lecture 4)
project on software industry
SE2023 0301 Software Project Management.pptx
Intro to PM.ppt
Lect-5: Work Breakdown Structure and Project Cost Estimation
WBS PROJECT
project time management
Project-Management.pptx
Using the work breakdown structure to plan a project
Project Management and Organization
MIS Project management
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
wbs.ppt
Work Breakdown Structure in Construction Cost Engineering.ppt
Wbs & Project Scheduling
SPM_UNIT-2.pptx
ABCs Of Project Time Management Planning Slides
PROJECT MANAGEMENT Work Breakdown Structure
Project Management Essentials Materials_0.pdf
Ad

More from Sulman Ahmed (20)

PPT
Entrepreneurial Strategy Generating and Exploiting new entries
PPT
Entrepreneurial Intentions and corporate entrepreneurship
PPT
Entrepreneurship main concepts and description
PPTX
Run time Verification using formal methods
PPTX
Use of Formal Methods at Amazon Web Services
PPTX
student learning App
PPTX
Software Engineering Economics Life Cycle.
PPTX
Data mining Techniques
PPTX
Rules of data mining
PPTX
Rules of data mining
PPTX
Classification in data mining
PPTX
Data mining Basics and complete description
PPTX
Data mining Basics and complete description onword
PPT
Dwh lecture-07-denormalization
PPT
Dwh lecture-06-normalization
PPT
Dwh lecture 12-dm
PPT
Dwh lecture 13-process dm
PPT
Dwh lecture 11-molap
PPT
Dwh lecture 10-olap
PPT
Dwh lecture 08-denormalization tech
Entrepreneurial Strategy Generating and Exploiting new entries
Entrepreneurial Intentions and corporate entrepreneurship
Entrepreneurship main concepts and description
Run time Verification using formal methods
Use of Formal Methods at Amazon Web Services
student learning App
Software Engineering Economics Life Cycle.
Data mining Techniques
Rules of data mining
Rules of data mining
Classification in data mining
Data mining Basics and complete description
Data mining Basics and complete description onword
Dwh lecture-07-denormalization
Dwh lecture-06-normalization
Dwh lecture 12-dm
Dwh lecture 13-process dm
Dwh lecture 11-molap
Dwh lecture 10-olap
Dwh lecture 08-denormalization tech

Recently uploaded (20)

PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PPTX
Cell Types and Its function , kingdom of life
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
01-Introduction-to-Information-Management.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
RMMM.pdf make it easy to upload and study
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
Classroom Observation Tools for Teachers
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Lesson notes of climatology university.
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PPTX
Institutional Correction lecture only . . .
Chinmaya Tiranga quiz Grand Finale.pdf
Cell Types and Its function , kingdom of life
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
01-Introduction-to-Information-Management.pdf
Final Presentation General Medicine 03-08-2024.pptx
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
human mycosis Human fungal infections are called human mycosis..pptx
O5-L3 Freight Transport Ops (International) V1.pdf
RMMM.pdf make it easy to upload and study
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Classroom Observation Tools for Teachers
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Computing-Curriculum for Schools in Ghana
Lesson notes of climatology university.
Anesthesia in Laparoscopic Surgery in India
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Institutional Correction lecture only . . .

Wbs, estimation and scheduling

  • 1. Software Project Management WBS, Estimation & Scheduling The information contained in this presentation was obtained from the public domain
  • 2. Reminders • Best way to learn the most from SPM course is not to behave like a student but to think like a SPM.
  • 3. Planning, Estimating, Scheduling • What’s the difference? • Plan: Identify activities. No specific start and end dates. • Estimating: Determining the size & duration of activities. • Schedule: Adds specific start and end dates, relationships, and resources.
  • 4. Project Planning: A 12 Step Program 1) Set goal and scope 2) Select lifecycle 3) Set org./team form 4) Start team selection 5) Determine risks 6) Create WBS* * Relatively an old technique 7) Identify tasks 8) Estimate size 9) Estimate effort 10)Identify task dependencies 11)Assign resources 12)Schedule work
  • 5. How To Schedule • 1. Identify “what” needs to be done – Work Breakdown Structure (WBS) • 2. Identify “how much” (the size) – Size estimation techniques • 3. Identify the dependency between tasks – Dependency graph, network diagram • 4. Estimate total duration of the work to be done – The actual schedule
  • 6. Partitioning Your Project • You need to decompose your project into manageable chunks • All projects need this step • Divide & Conquer • Two main causes of project failure – Forgetting something critical – Ballpark estimates become targets • How does partitioning help this?
  • 7. Work Breakdown Structure: WBS • Hierarchical list of project’s work activities • 2 Formats – Outline (indented format) – Graphical Tree (Organizational Chart) • Uses a decimal numbering system – Ex: 3.1.5 – 0 is typically top level
  • 8. WBS • Contract WBS (CWBS) – First 2 or 3 levels – High-level tracking • Project WBS (PWBS) – Defined by PM and team members – Tasks tied to deliverables – Lowest level tracking
  • 9. A Full WBS Structure • Up to six levels (3-6 usually) such as
  • 11. WBS Outline Example 0.0 Retail Web Site 1.0 Project Management 2.0 Requirements Gathering 3.0 Analysis & Design 4.0 Site Software Development 4.1 HTML Design and Creation 4.2 Backend Software 4.2.1 Database Implementation 4.2.2 Middleware Development 4.2.3 Security Subsystems 4.2.4 Catalog Engine 4.2.5 Transaction Processing 4.3 Graphics and Interface 4.4 Content Creation 5.0 Testing and Production
  • 12. WBS Types • Process WBS • Activity-oriented • Ex: Requirements, Analysis, Design, Testing • Typically used by PM • Product WBS • Entity-oriented • Ex: Financial engine, Interface system, DB • Typically used by engineering manager
  • 13. WBS Techniques • Top-Down • Bottom-Up • Analogy • Post-its on a wall
  • 14. WBS Techniques • Top-down – Start at highest level – Systematically develop increasing level of detail – Best if • The problem is well understood • Technology and methodology are not new • This is similar to an earlier project or problem – But is also applied in majority of situations
  • 15. WBS Techniques • Bottom-up – Start at lowest level tasks – Aggregate into summaries and higher levels – Cons • Time consuming • Needs more requirements complete – Pros • Detailed
  • 16. WBS Techniques • Analogy – Base WBS upon that of a “similar” project – Use a template – Analogy also can be estimation basis – Pros • Based on past actual experience – Cons • Needs comparable project
  • 17. WBS Techniques • Brainstorming – Generate all activities you can think of that need to be done – Group them into categories
  • 18. WBS – Basis of Many Things • Network scheduling • Costing • Risk analysis • Organizational structure • Control • Measurement
  • 19. WBS Guidelines Part 1 • Should be easy to understand • Some companies have corporate standards for these schemes • Some top-level items, like Project Mgmt. are in WBS for each project – Others vary by project • What often hurts most is what’s missing • Break down until you can generate accurate time & cost estimates • Ensure each element corresponds to a deliverable
  • 20. WBS Guidelines Part 2 • How detailed should it be? – Each level should have no more than 7 items – It can evolve over time • What tool should you use? – Excel, Word, Project – Org chart diagramming tool (Visio, etc) – Specialized commercial apps • Re-use a “template” if you have one
  • 21. Estimations • Very difficult to do, but needed often • Basic process 1) Estimate the size of the product 2) Estimate the effort (man-months) 3) Estimate the schedule – NOTE: Not all of these steps are always explicitly performed
  • 22. Estimations • Remember, an “exact estimate” is difficult • Estimate how long will it take you to get home from class tonight – On what basis did you do that? – Experience right? – Likely as an “average” probability
  • 23. Estimation • Target vs. Committed Dates • Target: Proposed by business or marketing • Do not commit to this too soon! • Committed: Team agrees to this • After you’ve developed a schedule
  • 24. Estimation (Software) • Size: – Small projects (10-99 FPs), variance of 7% from post-requirements estimates – Medium (100-999 FPs), 22% variance – Large (1000-9999 FPs) 38% variance – Very large (> 10K FPs) 51% variance
  • 25. Estimation Methodologies • Top-down • Bottom-up • Analogy • Expert Judgment • Priced to Win • Parametric or Algorithmic Method – Using formulas and equations
  • 26. Algorithmic Measures • Lines of Code (LOC) • Function points • Feature points or object points • Other possible – Number of processes on a structure chart • LOC and function points most common – (of the algorithmic approaches)
  • 27. Code Reuse & Estimation • Does not come for free • Code types: New, Modified, Reused • If code is more than 50% modified, it’s “new” • Reuse factors have wide range – Reused code takes 30% effort of new – Modified is 60% of new • Integration effort with reused code almost as expensive as with new code
  • 28. Effort Estimation • Now that you know the “size”, determine the “effort” needed to build it • Various models: empirical, mathematical, subjective • Expressed in units of duration – Man-months (or ‘staff-months’ now)
  • 29. Effort Estimation • As with parametric size estimation, these techniques perform better with historical data • Again, not seen in ‘average’ projects • Often the size and effort estimation steps are combined (not that this is recommended, but is what often is done)
  • 30. COCOMO • COnstructive COst MOdel • Allows for the type of application, size, and “Cost Drivers” • Outputs in Person Months • Cost drivers using High/Med/Low & include – Motivation – Ability of team – Application experience • Biggest weakness? – Requires input of a product size estimate in LOC
  • 31. Know Your Deadlines • Are they ‘Real Deadlines’? – Tied to an external event – Have to be met for project to be a success – Ex: end of financial year, contractual deadline, Y2K • Or ‘Artificial Deadlines’? – Set by arbitrary authority – May have some flexibility (if pushed)