Enhancements in Major Versions of Primavera
Version 6.0 -
P6.7 Service
Pack 2
Version 7.0 - P6
Version 7 SP3
(P6
Pro) Version 8.1
Version 8.2 Version 8.3
P6 Version 6.0 P6 Version 7 P6 Professional (P6
Pro) Version 8.1
P6 Pro Version 8.2 P6 EPPM Release R8.3
Total float is once
again blanked-out
for
Completed
activities.
User designated
hour/day
conversion factors
moved to
individual
calendars
Enhanced activity
filtering & grouping
MS Project import
enhancements
Team Member Enhancements.
iPhone app enables users to
communicate with their project
manager and other team
members about a task.
MS SQL Express
2005 is the stand-
alone
Database
Default Date/Time
issue partially fixed
Personalize Toolbars Ms Project 2010
XML support
Team Member – Discussion
Feature:- All comments are saved
with the task and are available for
Future reference. Discussion icon
available to begin and monitor a
discussion for a task.
Import & Export via
XML format (a bit
buggy)
Improved
summary duration
calculations
WBS/Activity tabs New Line
Numbering
Team Member – Discussion
Feature iPhone :- In the iPhone
app, discussions are also saved
with the task
Finish dates change
when durations are
Changed
Late Dates were
added to the S-
Curve report
Will not interface
with EPPM database
Time scaled Logic
Diagram
enhancements
• Enhanced filtering,
sightlines, activity
code color
coding, templates,
grouping, and
performance
Team Member – Work Distribution
Filter :- enables
a team member who is not the
activity owner or
resource to see a list of tasks that
he/she is responsible
for updating in the Team Member
interfaces (Team
Member Web, Team Member for
iPhone app, E-mail
Statusing Service).
Time scale in Gantt
Chart is made
adjustable
New Activity ID
renumbering
options
P6 EPPM 8.1 Both Pro & EPPM
use the same client
software
Team Member – Add/Delete Steps
:- enables users to add, delete, and
rename activity steps directly from
the task list. Use the Steps
panel to view assigned steps and
report progress. Select a task
In the list and type a % completes
value. If the step is finished,
Select the Complete Step check
mark.
P6 Service Pack 1
(P6.1)
Excel security
options separate
from XER
Phone App for Team
Members
P6 EPPM
Release 8.2
Team Member – Add/Delete Steps
iPhone : iPhone app enables you to
add,
delete, and rename activity steps
directly from the task list.
Major bugs in the
previous versions
fixed
committing &
refresh error fixed
scheduling
freezing at 95%
error fixed
XER causing
duplicate resource
assignment fixed
crashing when
modifying
sitelines/
timescale
Excel import of
constraints fixed
Report Editor bugs
fixed
Dates issues on
time sheets fixed
Oracle XE (g10) is
new stand-alone
database
Ability to status
tasks via E-mail
Team Member
Web Application :-
Enables Working
with Tasks
Team Member – Enhanced
Filtering of Tasks :- New Time
frame filter and a text
search field added.
Filter by
Projects/Status/Timeframe
P6 Service Pack 2
(P6.2)
P6 Version 7 SP3 User Interface
enhancements to
simplify navigation
New E-mail
Statusing Service
and P6 Team
Member for iPhone
App Support for
Activity
Owners
Team Member – Enhanced
Filtering of Tasks iPhone:- using
iPhone app, team members can
filter tasks
based on a timeframe of Today,
This Week, or Next Week.
Milestone ‘one
minute off’ problem
fixed
Time-scaled logic
diagrams added
Resource
improvements to
better support
staffing, assigning
and
monitoring of
project resources
Team members can
now update
activities that they
are assigned to as
activity owner. Prior
to 8.2, team
members could
update only
activities they were
assigned to as
resources.
Team Member – Updating User
Defined Fields
and Activity Codes :- P6 Team
Member Web, a new Codes and
UDFs detail panel
enables team members to view
and update up to 20 activity
codes and UDFs.
Secure resource,
project, & activity
codes
Expands Memo
Fields beyond 400
characters
Streamlined
reporting
architecture to
reduce cost of
ownership
& support of BI
Publisher 11g
P6 Team Member
Applications
Configuration
Options:- now users
can change Project
Preferences, Change
E-mail settings
Team Member – Updating User
Defined Fields
and Activity Codes iPhone3
Total Float can now
be calculated for a
Program of
schedules as a
group instead of
Singly
Sight Line added Support for Google
Chrome
Team Member
Status Approval :-
project managers
can Review
team members
status updates even
before the updates
are committed to
the schedule.
Team Member – Notebook Topics
enables users to view Notebook
topics assigned to activities in P6
or P6 Professional directly
from the task list
P6 Version 6.5
Fixes for
Scrambling WBS’s
after import
•Scrambling WBS’s
after import
Actuals not
being spread
correctly
• Update Baseline
with Activity Codes
&
relationships
missing from new
activities
• Update Baseline
not Updating
Existing
• Oracle XE not
starting for stand-
alone users
Status Update
History Detail
Window:- this
window is made
available in
Activities page.
Shows the history of
changes made to the
activity.
Team Member-Request updates
via mail. The Notify feature
enables project managers to
send an e-mail to the E-mail
Statusing Service address, set up
by
the P6 administrator,
leveling with
priorities issues
fixed.
P6 Enhancements:-
New Exclusive
Mode- provision
given for opening
multiple projects in
exclusive mode.
When you open a
project in exclusive
mode. only you can
Extended enterprise:
XML
Import/Export Enhancements:-
Enables a user to import or export
multiple projects
simultaneously. When exporting
multiple projects, the projects
are combined into a single XML
file.
edit it; other users
will have only read
access
Fixed actual units
spreading
incorrectly
Location Data:-
enables you to
create a list of
locations, including
the street
address and the
longitude and
latitude.
you can report on
data by
location in P6
Analytics. You can
also group, sort, and
filter by location in
various views. You
can also import
new locations into
P6 from a Microsoft
Excel (.xls) file
Control Over
Data During XML Import:-
This feature is especially useful to
project managers who import
third-party schedules that contain
unwanted data such as resources,
codes, and UDFs.
Fixed Project
Integrity removing
EPS codes
Microsoft Project
Integration:- When
importing a
Microsoft Project
XML file, you can
now update an
existing project. You
can control what
types of global and
project data to
overwrite when
Importing.
UN/CNFACT
XML Data:-
This XML schema is designed to
exchange schedule and
cost data in a software-neutral
format. This is an important
feature for customers who work
with U.S. Department of Defense
and other U.S. government
agencies.
Fixed Claim Digger
displaying wrong
Activity ID
Import/Export
Support for
Microsoft Project
2010
Usability Enhancements (Web):
Setting a Default Start Page:-
It provides a setting to specify the
default start page when a
user logs in.
Fixed XLS import
causing corrupted
relationships
Scaling Options
when Printing:-
Three new scaling
options are available
when printing from
the Activities, EPS,
and Assignments
pages.
Viewing the
Hierarchy for Activity, Project, and
Resource Codes:-
Displays the full hierarchical chain
for assigned project,
activity, and resource codes in the
Codes detail window.
Fixed Expected
Finish causing 0
duration activities
Event Functionality:-
Creating or updating
User Defined Field
(UDF) values now
trigger events, by
doing so the P6
Event Notification
system sends the
event message to a
user
configured message
queue. subsequent
actions can be
triggered using
events in the client
application.
Sorting on Multiple Columns:-
Enables a user to sort on multiple
columns on the
Activities, EPS, and Resources
Assignments pages.
Fixed Finish
Milestone
constrained 1
minute late
Enhanced Trending:-
Project history
now supports
dates and
durations.
Historical data
now includes
activity-level and
WBS-level data.
Relationships Detail Window on
Activities Page:-
Offers a new Relationships detail
window on the Activities page.
P6 Version 6.7 New Resource
Creation From Users
- Create Resource
from Selected User
action can be used
on the Users page to
create and
assign a resource to
an existing user in
one step.
Improved
Printing From the EPS and
Activities Pages:-
allows a user to print from the EPS
or Activities page and
Include only the Project or Activity
Table with no Gantt chart.
Improved summary
activity duration
calculations
Enhanced Copy User
Support – following
information is now
copied when
copying existing
users
Toolbars for
Activities, EPS,
and Assignments
views
Global user
preferences
Assigned user
interface views
Improved
Printing From the EPS and
Activities Pages:-
allows a user to print from the EPS
or Activities page and
include only the Project or Activity
Table with no Gantt chart.
P6.7 Service pack 2 “Is Under” Filtering
Support:- filtering is
more refined, you
can select a
Additional Baseline Fields:-
additional baseline fields are
available in the Customize
Columns dialog box for display on
particular EPS where
your filtering should
work on.
the Activities page after a baseline
is assigned to a project.
XER Import
Configuration
Layout
problems
Fixed.
Dissolve Activities
Support:- When you
delete an activity, a
chain of logical
activities might be
broken. You can use
the new Dissolve
option to delete the
activity but join the
predecessors and
successors and
create the
appropriate
relationships
between them
Find and Replace Option:-
It enables a user to find and
replace text in displayed columns
on the EPS, Activities, and
Resources Assignments pages,
making it
Easier to change items in the
project plan.
disappearing/non-
editable Notebook
topics
New Column
Search:- very handy
during customizing
columns
Discussion Feature:-
It provides a new Discussion
feature that enables team
members
and project managers to
communicate about specific
activities.
Multiple Float Paths
Errors fixed
Cut/Copy/Paste
WBS Support
VISUALIZER:
Visualizer is a new feature that
supports graphical reporting by
enabling users to create
customizable Gantt charts and
timescaled
logic diagrams (TSLDs).
When creating a layout in
Visualizer you can define
options, such as
filter, group, and sort criteria, to
customize the Gantt chart or
TSLD.
The layout below shows
activities color-coded by activity
code values with various shapes
for endpoints.
Display baseline bars to
compare schedules and stack
fields in the
activity table to save horizontal
space.
The screen below shows an
example of a TSLD with multiple
bars per
Activity and critical activities
coded in red.
Fixes error when
using two activity
issue forms are also
copied when you
. Online Help:
The Help menu in P6Professional
filters copy projects, create
templates, or create
projects from
templates.
8.3 contains two options: Local
Help and Online Help. The Online
Help feature displays P6
Professional help content in basic
HTML format, enabling people
with
disabilities to use the adaptive
features of their browsers.
Additional Fields in
Predecessor/Success
or Tabs:- Driving,
Critical, Total Float,
Free Float, Early
Start, Early Finish,
Late Start, and Late
Finish.
Primavera Unifier:
project portfolio
management application with cost
control and contract management
Capabilities, is now improved to
simplify setup and enhance
usability

More Related Content

PPT
Budowa miesni
PDF
Kelner 4.01
PDF
03 Charakteryzowanie oraz zastosowanie materiałów poligraficznych 311[28].Z1.03
PDF
PDF
What's New in Primavera P6 16.2
PDF
Hacking Primavera P6 - Creative Solutions to Common Problems From the Primave...
PDF
20160405 How to Install Primavera P6 16.1 Professional desktop
PDF
Oracle What's New In Primavera P6 16.2
Budowa miesni
Kelner 4.01
03 Charakteryzowanie oraz zastosowanie materiałów poligraficznych 311[28].Z1.03
What's New in Primavera P6 16.2
Hacking Primavera P6 - Creative Solutions to Common Problems From the Primave...
20160405 How to Install Primavera P6 16.1 Professional desktop
Oracle What's New In Primavera P6 16.2

Viewers also liked (20)

PDF
Pdf primavera tutorial
PDF
Oracle Primavera P6 16.1 Released - Everything You Need To Know
PDF
Oracle Primavera P6 R16.1
PDF
Primavera P6 Tips and Tricks
PPTX
Primavera vs Microsoft project
PDF
Features comparison between Primavera and Microsoft Project
PDF
Primavera Analytics 16.1 is Released - Everything You Need To Know
PDF
Oracle Primavera Roadmap 2015
PDF
Whats new in primavera p6 eppm 8.3.2 - Oracle Primavera P6 Collaborate 14
PDF
Oracle Primavera Unifier What's New in Release 16.2
PDF
206430 whats new in primavera p6 rel8 3
PDF
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
PPTX
Primavera vs Microsoft Project Professional
PPTX
Top 10 Microsoft Project Problems
PDF
Primavera vs microsoft project
PPTX
Importance of Microsoft Project and Primavera
PDF
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
PPTX
Primavera p6 v8.2 session 1
PDF
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
PDF
What's new in primavera p6 version 16.2
Pdf primavera tutorial
Oracle Primavera P6 16.1 Released - Everything You Need To Know
Oracle Primavera P6 R16.1
Primavera P6 Tips and Tricks
Primavera vs Microsoft project
Features comparison between Primavera and Microsoft Project
Primavera Analytics 16.1 is Released - Everything You Need To Know
Oracle Primavera Roadmap 2015
Whats new in primavera p6 eppm 8.3.2 - Oracle Primavera P6 Collaborate 14
Oracle Primavera Unifier What's New in Release 16.2
206430 whats new in primavera p6 rel8 3
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Primavera vs Microsoft Project Professional
Top 10 Microsoft Project Problems
Primavera vs microsoft project
Importance of Microsoft Project and Primavera
Successfully Manage Cost and Schedule with Primavera Unifier and Primavera P6
Primavera p6 v8.2 session 1
Primavera _ Mike Sicilia _ Orace Primavera vision and road ahead.pdf
What's new in primavera p6 version 16.2
Ad

Similar to Difference between versions of primavera 6,7,R8.1,R8.2,R8.3 (20)

PDF
Whats new in Primavera P6 EPPM 15.2?
PDF
Team Member Applications 8.2
PDF
Whats new-in-p6-eppm-1927798
PDF
Oracle Primavera Team member 8.3
PDF
P6 upgrade paths - Oracle Primavera P6 Collaborate 14
PDF
Say hola to new orange scrum enterprise updates
PPTX
P6 EPPM Functionality
PDF
Primavera roadmap 2012/2013
PDF
Primavera roadmap
PDF
206460 primavera mobile
PDF
Primavera Release Notes 8.1
PDF
Project portfolio management comparison of microsoft epm and primavera p6 v...
PDF
Project portfolio management comparison of microsoft epm and primavera p6 v...
PPTX
Principal Toolbox Release 6.5
PDF
Oracle Primavera P6 v7 Release Value Proposition
PDF
What's New In Primavera P6 EPPM 17.1
PDF
What's New in Primavera 15.2 Webcast
PPTX
Preview release 6.5
DOCX
Hyperion psb new featuers
PDF
Oracle PPM. What's new in P6release 8.2?
Whats new in Primavera P6 EPPM 15.2?
Team Member Applications 8.2
Whats new-in-p6-eppm-1927798
Oracle Primavera Team member 8.3
P6 upgrade paths - Oracle Primavera P6 Collaborate 14
Say hola to new orange scrum enterprise updates
P6 EPPM Functionality
Primavera roadmap 2012/2013
Primavera roadmap
206460 primavera mobile
Primavera Release Notes 8.1
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
Principal Toolbox Release 6.5
Oracle Primavera P6 v7 Release Value Proposition
What's New In Primavera P6 EPPM 17.1
What's New in Primavera 15.2 Webcast
Preview release 6.5
Hyperion psb new featuers
Oracle PPM. What's new in P6release 8.2?
Ad

More from CADD Centre Software Solutions Private Limited (19)

PPTX
A b-c-d-(e) of ccsspl corporate presentation
PDF
Login methodology for Primavera V8.3 (EPPM)
PDF
PDF
Recurring task IN MS project
PDF
Oracle Primavera contract management
DOCX
Uses of Project Status field
PDF
Oracle primavera Universal content management
PPS
Pert master risk analysis tool
PDF
Oracle Primavera P6 PRO R8 Tips & tricks
PDF
User preference Option in Oracle Primavera EPPM P6
PDF
Team member in iphones and android
PDF
Activity Duration Types Explained with example in Primavera
PDF
S Curves Made Easy With Primavera P6
PDF
Tested configuration for different Primavera versions
PDF
Project management software consulting
A b-c-d-(e) of ccsspl corporate presentation
Login methodology for Primavera V8.3 (EPPM)
Recurring task IN MS project
Oracle Primavera contract management
Uses of Project Status field
Oracle primavera Universal content management
Pert master risk analysis tool
Oracle Primavera P6 PRO R8 Tips & tricks
User preference Option in Oracle Primavera EPPM P6
Team member in iphones and android
Activity Duration Types Explained with example in Primavera
S Curves Made Easy With Primavera P6
Tested configuration for different Primavera versions
Project management software consulting

Recently uploaded (20)

PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Electronic commerce courselecture one. Pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Review of recent advances in non-invasive hemoglobin estimation
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPTX
MYSQL Presentation for SQL database connectivity
PDF
Encapsulation theory and applications.pdf
PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
NewMind AI Monthly Chronicles - July 2025
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PPT
Teaching material agriculture food technology
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
NewMind AI Weekly Chronicles - August'25 Week I
Advanced methodologies resolving dimensionality complications for autism neur...
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Electronic commerce courselecture one. Pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
Review of recent advances in non-invasive hemoglobin estimation
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
Mobile App Security Testing_ A Comprehensive Guide.pdf
MYSQL Presentation for SQL database connectivity
Encapsulation theory and applications.pdf
Network Security Unit 5.pdf for BCA BBA.
The Rise and Fall of 3GPP – Time for a Sabbatical?
Per capita expenditure prediction using model stacking based on satellite ima...
NewMind AI Monthly Chronicles - July 2025
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Teaching material agriculture food technology
Diabetes mellitus diagnosis method based random forest with bat algorithm
Understanding_Digital_Forensics_Presentation.pptx
NewMind AI Weekly Chronicles - August'25 Week I

Difference between versions of primavera 6,7,R8.1,R8.2,R8.3

  • 1. Enhancements in Major Versions of Primavera Version 6.0 - P6.7 Service Pack 2 Version 7.0 - P6 Version 7 SP3 (P6 Pro) Version 8.1 Version 8.2 Version 8.3 P6 Version 6.0 P6 Version 7 P6 Professional (P6 Pro) Version 8.1 P6 Pro Version 8.2 P6 EPPM Release R8.3 Total float is once again blanked-out for Completed activities. User designated hour/day conversion factors moved to individual calendars Enhanced activity filtering & grouping MS Project import enhancements Team Member Enhancements. iPhone app enables users to communicate with their project manager and other team members about a task. MS SQL Express 2005 is the stand- alone Database Default Date/Time issue partially fixed Personalize Toolbars Ms Project 2010 XML support Team Member – Discussion Feature:- All comments are saved with the task and are available for Future reference. Discussion icon available to begin and monitor a discussion for a task. Import & Export via XML format (a bit buggy) Improved summary duration calculations WBS/Activity tabs New Line Numbering Team Member – Discussion Feature iPhone :- In the iPhone app, discussions are also saved with the task
  • 2. Finish dates change when durations are Changed Late Dates were added to the S- Curve report Will not interface with EPPM database Time scaled Logic Diagram enhancements • Enhanced filtering, sightlines, activity code color coding, templates, grouping, and performance Team Member – Work Distribution Filter :- enables a team member who is not the activity owner or resource to see a list of tasks that he/she is responsible for updating in the Team Member interfaces (Team Member Web, Team Member for iPhone app, E-mail Statusing Service). Time scale in Gantt Chart is made adjustable New Activity ID renumbering options P6 EPPM 8.1 Both Pro & EPPM use the same client software Team Member – Add/Delete Steps :- enables users to add, delete, and rename activity steps directly from the task list. Use the Steps panel to view assigned steps and report progress. Select a task In the list and type a % completes value. If the step is finished, Select the Complete Step check mark. P6 Service Pack 1 (P6.1) Excel security options separate from XER Phone App for Team Members P6 EPPM Release 8.2 Team Member – Add/Delete Steps iPhone : iPhone app enables you to add, delete, and rename activity steps directly from the task list.
  • 3. Major bugs in the previous versions fixed committing & refresh error fixed scheduling freezing at 95% error fixed XER causing duplicate resource assignment fixed crashing when modifying sitelines/ timescale Excel import of constraints fixed Report Editor bugs fixed Dates issues on time sheets fixed Oracle XE (g10) is new stand-alone database Ability to status tasks via E-mail Team Member Web Application :- Enables Working with Tasks Team Member – Enhanced Filtering of Tasks :- New Time frame filter and a text search field added. Filter by Projects/Status/Timeframe P6 Service Pack 2 (P6.2) P6 Version 7 SP3 User Interface enhancements to simplify navigation New E-mail Statusing Service and P6 Team Member for iPhone App Support for Activity Owners Team Member – Enhanced Filtering of Tasks iPhone:- using iPhone app, team members can filter tasks based on a timeframe of Today, This Week, or Next Week.
  • 4. Milestone ‘one minute off’ problem fixed Time-scaled logic diagrams added Resource improvements to better support staffing, assigning and monitoring of project resources Team members can now update activities that they are assigned to as activity owner. Prior to 8.2, team members could update only activities they were assigned to as resources. Team Member – Updating User Defined Fields and Activity Codes :- P6 Team Member Web, a new Codes and UDFs detail panel enables team members to view and update up to 20 activity codes and UDFs. Secure resource, project, & activity codes Expands Memo Fields beyond 400 characters Streamlined reporting architecture to reduce cost of ownership & support of BI Publisher 11g P6 Team Member Applications Configuration Options:- now users can change Project Preferences, Change E-mail settings Team Member – Updating User Defined Fields and Activity Codes iPhone3 Total Float can now be calculated for a Program of schedules as a group instead of Singly Sight Line added Support for Google Chrome Team Member Status Approval :- project managers can Review team members status updates even before the updates are committed to the schedule. Team Member – Notebook Topics enables users to view Notebook topics assigned to activities in P6 or P6 Professional directly from the task list
  • 5. P6 Version 6.5 Fixes for Scrambling WBS’s after import •Scrambling WBS’s after import Actuals not being spread correctly • Update Baseline with Activity Codes & relationships missing from new activities • Update Baseline not Updating Existing • Oracle XE not starting for stand- alone users Status Update History Detail Window:- this window is made available in Activities page. Shows the history of changes made to the activity. Team Member-Request updates via mail. The Notify feature enables project managers to send an e-mail to the E-mail Statusing Service address, set up by the P6 administrator, leveling with priorities issues fixed. P6 Enhancements:- New Exclusive Mode- provision given for opening multiple projects in exclusive mode. When you open a project in exclusive mode. only you can Extended enterprise: XML Import/Export Enhancements:- Enables a user to import or export multiple projects simultaneously. When exporting multiple projects, the projects are combined into a single XML file.
  • 6. edit it; other users will have only read access Fixed actual units spreading incorrectly Location Data:- enables you to create a list of locations, including the street address and the longitude and latitude. you can report on data by location in P6 Analytics. You can also group, sort, and filter by location in various views. You can also import new locations into P6 from a Microsoft Excel (.xls) file Control Over Data During XML Import:- This feature is especially useful to project managers who import third-party schedules that contain unwanted data such as resources, codes, and UDFs.
  • 7. Fixed Project Integrity removing EPS codes Microsoft Project Integration:- When importing a Microsoft Project XML file, you can now update an existing project. You can control what types of global and project data to overwrite when Importing. UN/CNFACT XML Data:- This XML schema is designed to exchange schedule and cost data in a software-neutral format. This is an important feature for customers who work with U.S. Department of Defense and other U.S. government agencies. Fixed Claim Digger displaying wrong Activity ID Import/Export Support for Microsoft Project 2010 Usability Enhancements (Web): Setting a Default Start Page:- It provides a setting to specify the default start page when a user logs in. Fixed XLS import causing corrupted relationships Scaling Options when Printing:- Three new scaling options are available when printing from the Activities, EPS, and Assignments pages. Viewing the Hierarchy for Activity, Project, and Resource Codes:- Displays the full hierarchical chain for assigned project, activity, and resource codes in the Codes detail window.
  • 8. Fixed Expected Finish causing 0 duration activities Event Functionality:- Creating or updating User Defined Field (UDF) values now trigger events, by doing so the P6 Event Notification system sends the event message to a user configured message queue. subsequent actions can be triggered using events in the client application. Sorting on Multiple Columns:- Enables a user to sort on multiple columns on the Activities, EPS, and Resources Assignments pages. Fixed Finish Milestone constrained 1 minute late Enhanced Trending:- Project history now supports dates and durations. Historical data now includes activity-level and WBS-level data. Relationships Detail Window on Activities Page:- Offers a new Relationships detail window on the Activities page.
  • 9. P6 Version 6.7 New Resource Creation From Users - Create Resource from Selected User action can be used on the Users page to create and assign a resource to an existing user in one step. Improved Printing From the EPS and Activities Pages:- allows a user to print from the EPS or Activities page and Include only the Project or Activity Table with no Gantt chart. Improved summary activity duration calculations Enhanced Copy User Support – following information is now copied when copying existing users Toolbars for Activities, EPS, and Assignments views Global user preferences Assigned user interface views Improved Printing From the EPS and Activities Pages:- allows a user to print from the EPS or Activities page and include only the Project or Activity Table with no Gantt chart. P6.7 Service pack 2 “Is Under” Filtering Support:- filtering is more refined, you can select a Additional Baseline Fields:- additional baseline fields are available in the Customize Columns dialog box for display on
  • 10. particular EPS where your filtering should work on. the Activities page after a baseline is assigned to a project. XER Import Configuration Layout problems Fixed. Dissolve Activities Support:- When you delete an activity, a chain of logical activities might be broken. You can use the new Dissolve option to delete the activity but join the predecessors and successors and create the appropriate relationships between them Find and Replace Option:- It enables a user to find and replace text in displayed columns on the EPS, Activities, and Resources Assignments pages, making it Easier to change items in the project plan. disappearing/non- editable Notebook topics New Column Search:- very handy during customizing columns Discussion Feature:- It provides a new Discussion feature that enables team members and project managers to communicate about specific activities. Multiple Float Paths Errors fixed Cut/Copy/Paste WBS Support VISUALIZER: Visualizer is a new feature that
  • 11. supports graphical reporting by enabling users to create customizable Gantt charts and timescaled logic diagrams (TSLDs). When creating a layout in Visualizer you can define options, such as filter, group, and sort criteria, to customize the Gantt chart or TSLD. The layout below shows activities color-coded by activity code values with various shapes for endpoints. Display baseline bars to compare schedules and stack fields in the activity table to save horizontal space. The screen below shows an example of a TSLD with multiple bars per Activity and critical activities coded in red. Fixes error when using two activity issue forms are also copied when you . Online Help: The Help menu in P6Professional
  • 12. filters copy projects, create templates, or create projects from templates. 8.3 contains two options: Local Help and Online Help. The Online Help feature displays P6 Professional help content in basic HTML format, enabling people with disabilities to use the adaptive features of their browsers. Additional Fields in Predecessor/Success or Tabs:- Driving, Critical, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish. Primavera Unifier: project portfolio management application with cost control and contract management Capabilities, is now improved to simplify setup and enhance usability