The S Curves Made easy with Oracle Primavera P6
1. Introduction
The first time most project managers become aware of the existence of S Curves is when
they are requested by the client or senior management to include one in their next progress report.
These S Curve are made just clicks away for Oracle Primavera P6 users.
Before getting into implementing such S Curves in Primavera P6 Lets get to know what a S Curve is?
A S Curve is defined as "a display of cumulative costs, labour hours or other quantities
plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning
and end and steeper in the middle, which is typical of most projects. The beginning represents a
slow, deliberate but accelerating start, while the end represents a deceleration as the work runs
out."Source: Wideman Comparative Glossary of Common Project Management Terms v2.1
Copyright R. Max Wideman, May 2001
2. Generating S curves with Oracle Primavera P6
2.1 Analysis of the project Activity wise
In addition to the copulatives’ described in the definition of S-Curve Primavera P6 helps
design a lot more Curves which are essential to Project Management. Here are the steps to get into
the Activity usage profile window to do the analysis activity vise and generate curves for activities.
Select and open the project you want to do the S Curve analysis on. Make sure you are in
the activity tab. Now in the menu bar choose View-> show on bottom -> Activity usage Profile.
Now you get a new view at the right bottom of your Window. Here is where you get all your S
Curves.
Right click on the Activity usage profile window and choose -> activity usage profile options
If you have followed along close you would be getting this window in the middle of your
Screen, yes of-course without those blue markers and with some checkboxes clicked enabled by
default.
Fig 1 : Activity Usage profile window
As per the definition for S Curve(cumulative costs, labour hours or other quantities plotted
against time) shown in the beginning of this article.
To show the Cumulative cost S curves select the 1. Cost Radio button and enable the
check box from 18. To 22. to show the cumulative of all the defined variables.
Selecting check box from 23. to 25. Shows the Earned value cost curves.
To show the Cumulative labor hours S curves select the 2. Units Radio button and
enable the check box from 18. To 22. to show the cumulative of all the defined
variables. Selecting check boxes from 23. to 25 shows the Earned value curves in
terms of labor units.
2.2 Analysis of the project Resource wise
Select and open the project you want to do the S Curve analysis on. Make sure you are in
the activity tab. Now in the menu bar choose View-> show on bottom ->Resource usage Profile.
Now you get a new view at the right bottom of your Window. Here is where you get all your
S Curves.
Right click on the Resource usage profile window and choose ->Resource usage profile options

Fig 2 : Resource Usage profile window

To show the cumulative curves for resources in terms of cost and labor units , tick
the checkbox from 8. through 11.By checking radio button 1. Or 2. For units and cost respectively.
Click on apply to have a preview of the resource curve according to your settings in the
Activity usage profile option /Resource usage profile option window. And click on OK to close the
Activity usage profile option /Resource usage profile option window.
Now we are half way done. You would now have your S curves ready to show it to your
clients / senior management. The S Curve generated would look like something below.

Fig 3 Sample S Curve

Review those curves and various analysis could be made with your project such as
determining growth , determining Slippage ,determining Progress and many more.
3. Analysis made from S Curves
3.1 Determining Growth
Comparison of the Baseline and Target S-curves quickly reveals if the project has grown
(Target S-curve finishes above Baseline S-curve) or contracted (Target S-curve finishes below
Baseline S-curve) in scope. A change in the project's scopes implies a re-allocation of resources
(increase or decrease), and the very possible requirement to raise contract variations. If the
resources are fixed, then the duration of the project will increase (finish later) or decrease (finish
earlier), possibly leading to the need to submit an extension of time claim.
Figure 4: Calculating Project Growth using S-curves
3.2 Determining Slippage
Slippage is defined as:
"The amount of time a task has been delayed from its original baseline schedule. The
slippage is the difference between the scheduled start or finish date for a task and the baseline
start or finish date. Slippage can occur when a baseline plan is set and the actual dates
subsequently entered for tasks are later than the baseline dates or the actual durations are longer
than the baseline schedule durations".
Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage (i.e. the
Target S-curve finishes to the right of the Baseline S-curve). Additional resources will need to be
allocated or additional hours worked in order to eliminate (or at least reduce) the slippage. An
extension of time claim may need to be submitted if the slippage cannot be eliminated or reduced
to an acceptable level.
Figure 5: Calculating Project Slippage using S-curves
3.3 Determining Progress
Comparison of the Target S-curve and Actual S-curve reveals the progress of the project
over time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority of the
project (due to many factors, including delays in updating the production schedule). Only towards
the end of the project will the curves converge and finally meet. The Actual S-curve can never finish
above the Target S-curve. If the Actual S-curve sits above the Target S-curve at the Cut Off Date, the
Production Schedule should be examined to determine if the project is truly ahead of schedule, or
if the Production Schedule contains unrealistic percentage complete values for ongoing tasks.

Figure 6: Calculating Project Progress using S-curves
4. Publishing S Curves as Print or as Web page
Now comes the very important stage in generating S Curves. Yes of course , showing it to
the management /clients who have asked for it. Primavera P6 provides option to print high quality
images or to convert the S Curves into html pages so that you can directly embed those in your
webpage. You just have to make the following settings in the page setup for printing in primavera.

Fig 7. Page setup window
After making the above settings go to print preview option to ensure you get the required
curves. From this you could either print the S curves, save them as Image files or publish them as
Html files.

References:
1. http://www.planningplanet.com/forums/planning-scheduling-programmingdiscussion/416820/develop-s-curve-primavera-p6
2. http://www.planningplanet.com/forums/planning-scheduling-programmingdiscussion/502846/what-s-curve-and-how-do-calculate-work-prog
3. http://www.maxwideman.com/guests/s-curve/using.htm

More Related Content

PDF
Loading cost in primavera schedule using resources and expenses r01
PDF
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
PDF
Primavera P6 User guide.pdf
PPTX
tcc primavera
PPTX
Primavara
 
PDF
Primavera p6 advanced project planning
PDF
PM using P6
PDF
Primavera P6
Loading cost in primavera schedule using resources and expenses r01
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
Primavera P6 User guide.pdf
tcc primavera
Primavara
 
Primavera p6 advanced project planning
PM using P6
Primavera P6

What's hot (20)

PDF
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
PDF
Primavera p6 18.8 planning and scheduling guide r3
PDF
Introduction, development and analysis of banana curve in project management....
PDF
Project Scheduling & Controls
PDF
Oracle primavera eppm presentation
PPT
Primavera Training P6
PDF
Primavera - Tutorial
PDF
How to prepare recovery or revised schedule rev.2
PDF
MS Project
PPTX
Introduction To Primavera (P6)
PPTX
ppt for primevera
PDF
Schedule Updates
PDF
Scheduling by using microsoft project 2013
PPTX
Microsoft Project
PDF
Understanding p6 dates
PDF
Primavera P6 manual
PPTX
Planning_and_scheduling.pptx
PPSX
Introduction to MS project
PPSX
Project network scheduling and S-curve
PDF
Promo_Epc project rule of credit and progress measurement
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Primavera p6 18.8 planning and scheduling guide r3
Introduction, development and analysis of banana curve in project management....
Project Scheduling & Controls
Oracle primavera eppm presentation
Primavera Training P6
Primavera - Tutorial
How to prepare recovery or revised schedule rev.2
MS Project
Introduction To Primavera (P6)
ppt for primevera
Schedule Updates
Scheduling by using microsoft project 2013
Microsoft Project
Understanding p6 dates
Primavera P6 manual
Planning_and_scheduling.pptx
Introduction to MS project
Project network scheduling and S-curve
Promo_Epc project rule of credit and progress measurement
Ad

Viewers also liked (20)

PDF
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
PDF
Primavera P6 Tips and Tricks
PDF
Activity Duration Types Explained with example in Primavera
PPSX
P6 Version 7 Tricks and Traps
PPTX
Activity Types and Relationships in Primavera p6
PPTX
Understanding Constraints and Relationships in Primavera P6 8.2
PPTX
Primavera Project Management P6 Course Session 1
PDF
Primavera Project Management
PDF
Pdf primavera tutorial
PPTX
Authentic Global Connections Learning2 Saigon2016
PDF
204380 capital project delivery using primavera
PPTX
CAPEX Case Study
PDF
Oracle PPM. What's new in P6release 8.2?
PDF
Primavera P6 EPPM Portlets Index
PDF
What's New in Primavera 15.2 Webcast
PDF
Primavera P6 Professional Windows 10 Installation Instructions
PDF
Primavera P6 8.1. What’s new
PDF
Whats new in Primavera P6 EPPM 15.2?
PDF
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
PDF
P6 Release 8 Installation Orientation
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Primavera P6 Tips and Tricks
Activity Duration Types Explained with example in Primavera
P6 Version 7 Tricks and Traps
Activity Types and Relationships in Primavera p6
Understanding Constraints and Relationships in Primavera P6 8.2
Primavera Project Management P6 Course Session 1
Primavera Project Management
Pdf primavera tutorial
Authentic Global Connections Learning2 Saigon2016
204380 capital project delivery using primavera
CAPEX Case Study
Oracle PPM. What's new in P6release 8.2?
Primavera P6 EPPM Portlets Index
What's New in Primavera 15.2 Webcast
Primavera P6 Professional Windows 10 Installation Instructions
Primavera P6 8.1. What’s new
Whats new in Primavera P6 EPPM 15.2?
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
P6 Release 8 Installation Orientation
Ad

Similar to S Curves Made Easy With Primavera P6 (20)

PPTX
S curves
PDF
S curv detail information for project.pdf
PPT
progect managment implmentation introduction
PPTX
1612170840-s-curve.pptx.................
PDF
PDF
DOC
Project management
PDF
The mysterious s_curve
PDF
The mysterious s_curve
PDF
The mysterious s_curve
PPTX
TM tools (1)- S-Curve.pptx
PPTX
lecture # 08.pptx
PDF
Operations Management for MBAs 5th Edition Meredith Solutions Manual
PDF
Operations Management for MBAs 5th Edition Meredith Solutions Manual
PDF
Scheduling minimizing the input while maximizing the output ppt
PDF
M06. 99 Tricks and Traps for Microssoft Project 2013 _ 2016.pdf
PDF
Operations Management for MBAs 5th Edition Meredith Solutions Manual
PPT
Project time management
PDF
Operations Management for MBAs 5th Edition Meredith Solutions Manual
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
S curves
S curv detail information for project.pdf
progect managment implmentation introduction
1612170840-s-curve.pptx.................
Project management
The mysterious s_curve
The mysterious s_curve
The mysterious s_curve
TM tools (1)- S-Curve.pptx
lecture # 08.pptx
Operations Management for MBAs 5th Edition Meredith Solutions Manual
Operations Management for MBAs 5th Edition Meredith Solutions Manual
Scheduling minimizing the input while maximizing the output ppt
M06. 99 Tricks and Traps for Microssoft Project 2013 _ 2016.pdf
Operations Management for MBAs 5th Edition Meredith Solutions Manual
Project time management
Operations Management for MBAs 5th Edition Meredith Solutions Manual
Information Technology Project Management 5th Edition Marchewka Solutions Manual

More from CADD Centre Software Solutions Private Limited (20)

PPTX
A b-c-d-(e) of ccsspl corporate presentation
PDF
Login methodology for Primavera V8.3 (EPPM)
PDF
Oracle Primavera Team member 8.3
PDF
Oracle Primavera contractor
PDF
Recurring task IN MS project
PDF
Oracle Primavera contract management
DOCX
Uses of Project Status field
PDF
Oracle primavera Universal content management
PPS
Pert master risk analysis tool
PDF
Oracle Primavera P6 PRO R8 Tips & tricks
PDF
User preference Option in Oracle Primavera EPPM P6
PDF
Team member in iphones and android
PDF
Tested configuration for different Primavera versions
PDF
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
PDF
Features comparison between Primavera and Microsoft Project
PDF
Project management software consulting
A b-c-d-(e) of ccsspl corporate presentation
Login methodology for Primavera V8.3 (EPPM)
Oracle Primavera Team member 8.3
Oracle Primavera contractor
Recurring task IN MS project
Oracle Primavera contract management
Uses of Project Status field
Oracle primavera Universal content management
Pert master risk analysis tool
Oracle Primavera P6 PRO R8 Tips & tricks
User preference Option in Oracle Primavera EPPM P6
Team member in iphones and android
Tested configuration for different Primavera versions
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Features comparison between Primavera and Microsoft Project
Project management software consulting

Recently uploaded (20)

PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PDF
Nidhal Samdaie CV - International Business Consultant
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
How to Get Business Funding for Small Business Fast
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Solaris Resources Presentation - Corporate August 2025.pdf
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PDF
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Keppel_Proposed Divestment of M1 Limited
PDF
How to Get Funding for Your Trucking Business
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Hindu Circuler Economy - Model (Concept)
PDF
IFRS Notes in your pocket for study all the time
PDF
Module 2 - Modern Supervison Challenges - Student Resource.pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
ICG2025_ICG 6th steering committee 30-8-24.pptx
Nidhal Samdaie CV - International Business Consultant
Power and position in leadershipDOC-20250808-WA0011..pdf
How to Get Business Funding for Small Business Fast
Probability Distribution, binomial distribution, poisson distribution
Lecture 3344;;,,(,(((((((((((((((((((((((
Solaris Resources Presentation - Corporate August 2025.pdf
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
340036916-American-Literature-Literary-Period-Overview.ppt
TyAnn Osborn: A Visionary Leader Shaping Corporate Workforce Dynamics
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Keppel_Proposed Divestment of M1 Limited
How to Get Funding for Your Trucking Business
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Hindu Circuler Economy - Model (Concept)
IFRS Notes in your pocket for study all the time
Module 2 - Modern Supervison Challenges - Student Resource.pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx

S Curves Made Easy With Primavera P6

  • 1. The S Curves Made easy with Oracle Primavera P6 1. Introduction The first time most project managers become aware of the existence of S Curves is when they are requested by the client or senior management to include one in their next progress report. These S Curve are made just clicks away for Oracle Primavera P6 users. Before getting into implementing such S Curves in Primavera P6 Lets get to know what a S Curve is? A S Curve is defined as "a display of cumulative costs, labour hours or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, which is typical of most projects. The beginning represents a slow, deliberate but accelerating start, while the end represents a deceleration as the work runs out."Source: Wideman Comparative Glossary of Common Project Management Terms v2.1 Copyright R. Max Wideman, May 2001 2. Generating S curves with Oracle Primavera P6 2.1 Analysis of the project Activity wise In addition to the copulatives’ described in the definition of S-Curve Primavera P6 helps design a lot more Curves which are essential to Project Management. Here are the steps to get into the Activity usage profile window to do the analysis activity vise and generate curves for activities. Select and open the project you want to do the S Curve analysis on. Make sure you are in the activity tab. Now in the menu bar choose View-> show on bottom -> Activity usage Profile. Now you get a new view at the right bottom of your Window. Here is where you get all your S Curves. Right click on the Activity usage profile window and choose -> activity usage profile options If you have followed along close you would be getting this window in the middle of your Screen, yes of-course without those blue markers and with some checkboxes clicked enabled by default.
  • 2. Fig 1 : Activity Usage profile window As per the definition for S Curve(cumulative costs, labour hours or other quantities plotted against time) shown in the beginning of this article. To show the Cumulative cost S curves select the 1. Cost Radio button and enable the check box from 18. To 22. to show the cumulative of all the defined variables. Selecting check box from 23. to 25. Shows the Earned value cost curves. To show the Cumulative labor hours S curves select the 2. Units Radio button and enable the check box from 18. To 22. to show the cumulative of all the defined variables. Selecting check boxes from 23. to 25 shows the Earned value curves in terms of labor units.
  • 3. 2.2 Analysis of the project Resource wise Select and open the project you want to do the S Curve analysis on. Make sure you are in the activity tab. Now in the menu bar choose View-> show on bottom ->Resource usage Profile. Now you get a new view at the right bottom of your Window. Here is where you get all your S Curves. Right click on the Resource usage profile window and choose ->Resource usage profile options Fig 2 : Resource Usage profile window To show the cumulative curves for resources in terms of cost and labor units , tick the checkbox from 8. through 11.By checking radio button 1. Or 2. For units and cost respectively.
  • 4. Click on apply to have a preview of the resource curve according to your settings in the Activity usage profile option /Resource usage profile option window. And click on OK to close the Activity usage profile option /Resource usage profile option window. Now we are half way done. You would now have your S curves ready to show it to your clients / senior management. The S Curve generated would look like something below. Fig 3 Sample S Curve Review those curves and various analysis could be made with your project such as determining growth , determining Slippage ,determining Progress and many more. 3. Analysis made from S Curves 3.1 Determining Growth Comparison of the Baseline and Target S-curves quickly reveals if the project has grown (Target S-curve finishes above Baseline S-curve) or contracted (Target S-curve finishes below Baseline S-curve) in scope. A change in the project's scopes implies a re-allocation of resources (increase or decrease), and the very possible requirement to raise contract variations. If the resources are fixed, then the duration of the project will increase (finish later) or decrease (finish earlier), possibly leading to the need to submit an extension of time claim.
  • 5. Figure 4: Calculating Project Growth using S-curves 3.2 Determining Slippage Slippage is defined as: "The amount of time a task has been delayed from its original baseline schedule. The slippage is the difference between the scheduled start or finish date for a task and the baseline start or finish date. Slippage can occur when a baseline plan is set and the actual dates subsequently entered for tasks are later than the baseline dates or the actual durations are longer than the baseline schedule durations". Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage (i.e. the Target S-curve finishes to the right of the Baseline S-curve). Additional resources will need to be allocated or additional hours worked in order to eliminate (or at least reduce) the slippage. An extension of time claim may need to be submitted if the slippage cannot be eliminated or reduced to an acceptable level.
  • 6. Figure 5: Calculating Project Slippage using S-curves 3.3 Determining Progress Comparison of the Target S-curve and Actual S-curve reveals the progress of the project over time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority of the project (due to many factors, including delays in updating the production schedule). Only towards the end of the project will the curves converge and finally meet. The Actual S-curve can never finish above the Target S-curve. If the Actual S-curve sits above the Target S-curve at the Cut Off Date, the Production Schedule should be examined to determine if the project is truly ahead of schedule, or if the Production Schedule contains unrealistic percentage complete values for ongoing tasks. Figure 6: Calculating Project Progress using S-curves
  • 7. 4. Publishing S Curves as Print or as Web page Now comes the very important stage in generating S Curves. Yes of course , showing it to the management /clients who have asked for it. Primavera P6 provides option to print high quality images or to convert the S Curves into html pages so that you can directly embed those in your webpage. You just have to make the following settings in the page setup for printing in primavera. Fig 7. Page setup window After making the above settings go to print preview option to ensure you get the required curves. From this you could either print the S curves, save them as Image files or publish them as Html files. References: 1. http://www.planningplanet.com/forums/planning-scheduling-programmingdiscussion/416820/develop-s-curve-primavera-p6 2. http://www.planningplanet.com/forums/planning-scheduling-programmingdiscussion/502846/what-s-curve-and-how-do-calculate-work-prog 3. http://www.maxwideman.com/guests/s-curve/using.htm