THE FRESH
CONNECTION
BUSINESS GAME
ANA CORREA
CLAUDIA GOMEZ
KAMILA HURKOVA
MERVE NUR TAŞ
TOMMI VEROMAA
THE FRESH CONNECTION | TEAM 2 1
T E A M 2
EXECUTIVE SUMMARY
WHAT DID WE ACHIEVE:
✓ The company obtained profit in each period, growing uninterruptedly in the first 4 rounds and with
a slight decrease in the last 2 rounds.
✓ Since round 1, ROI has always been positive.
WHAT WAS THE GENERAL STRATEGY :
✓ Make decisions integrating all departments, evaluating the possible positive or negative effects on
them in order to minimize costs and maximize the benefit to the company.
✓ Evaluate the decisions made in each period, provide feedback and take corrective actions to make
better use of company resources.
PROBLEMS ENCOUNTERED:
✓ Difficulties in predicting how some decisions will impact the performance of the company.
(The simulator restrained some functionalities at the first stages of the game)
✓ Align strategic decisions of departments in a common goal
THE FRESH CONNECTION | TEAM 2 2
CONTENTS
TEAM & RESPONSIBILITIES
◦ SALES
◦ OPERATIONS
◦ SUPPLY CHAIN
◦ PURCHASING
FINANCIAL RESULTS & CONCLUSIONS
THE FRESH CONNECTION | TEAM 2 3
Cube utilization %
Prod.Plan Adherence %
Unused capacity %
Nr. of shifts
Responsibilities:
Optimize and control
production and
warehouses
Components %
Stock Components
Stock Products
Responsibilities:
Coordinate different
departments, inventory
control and production
Rejection Components %
Raw Material Costs %
Delivery Reliability
Suppliers
Responsibilities:
Purchasing components,
negotiating with suppliers
Service level %
Obsoletes %
Gross Margin
Responsibilities:
Sell all produced goods
with highest possible
price
TEAM & RESPONSIBILITIES
THE FRESH CONNECTION | TEAM 2 4
R O I %
PURCHASING
SUPPLY
CHAIN
OPERATIONSSALES
SALES – GROSS MARGIN
THE FRESH CONNECTION | TEAM 2 5
✓ Increase gross margin as much as possible
prioritizing biggest customers
✓ Try not to lose gross margin on smaller customers
significantly
✓ Introduce promotional pressure for customers
during later rounds
I. STRATEGY II. RESULTS
✓ Gross began to grow on F&C and Dominick’s during
round 3 when customer order priorization was
implemented
✓ Further increases in later rounds with promotional
pressure
✓ Overall increase in gross for F&C and Dominick’s
was attained without losing gross margin on Land
Market
✓ F&C gross increased by almost 5 000 and
Dominick’s by 3000 during 6 periods
III. ANALYSIS
11610
14510
22486
27303
SALES – NEGOTIATIONS
THE FRESH CONNECTION | TEAM 2 6
✓ Align capacity of SC and Operations to match
negotiated service and shelf life levels
✓ Take advantage of one customer with full product
range to decrease potential obsoletes
✓ Trade unit: Pallets for all and VMI for F&C and
Dominick’s to reduce outbound stress
✓ Customer priorities: 1. F&C, 2. Dominick’s, 3. LM
I. STRATEGY
✓ Obsoletes were solved with having LM with shelf
life of 62-65%
✓ Negotiated service level % was calculated and
estimated based on improvements in SC and
Operations
✓ Decision-making in Sales was first based on
improvements made in SC and Operations, further
the decisions in SC and Operations were changed
based on Sales.
III. ANALYSIS
II. RESULTS
900 900 920 900 900 900 900
1500
1200
1050
950 930
975 1000
98% 99%
94% 96% 97% 100%
108%
71%
79%
85%
95% 97%
101% 101%
0%
20%
40%
60%
80%
100%
120%
0
200
400
600
800
1000
1200
1400
Round 0 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6
CubeUtilisation
WarehouseCapacity
Inbound Capacity Outbound Capacity
Inbound Cube Utilisation Outbound Cube Utilisation
OPERATIONS - WAREHOUSES
THE FRESH CONNECTION | TEAM 2 7
✓ Optimise pallet allocations (to avoid overflow and
outsourcing / too large unsued capacity)
✓ Allocate adequate number of shifts
✓ Reduce variability in processes and smooth raw
materials income and finished goods storage (align
with Supply Chain and Purchasing)
✓ Be ready to handle all demand (align with Sales)
I. STRATEGY II. RESULTS
✓ Round 4 was the most successful
✓ Starting in Round 5, the demand overpassed the
warehouses‘ capacities and it was not adjusted
correctly
✓ Outsourcing of warehouses would lead to
significantly higher costs
III. ANALYSIS
79%
94%
87%
92% 93% 94%
89%
78%
58%
73% 73% 73%
53%
81%
5%
25%
6%
10% 11%
39%
10%
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
Round 0 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6
Production Plan Adherence Runtime Unused Capacity
OPERATIONS - PRODUCTION
THE FRESH CONNECTION | TEAM 2 8
´
✓ Allocate adequate number of shifts
✓ Select wisely new investments to smooth
production and increase ROI (mixing and botteling)
✓ Minimize production costs, unused capacity,
changeover and breakdown times
✓ Maximize production plan adherence
✓ Align with all other functions to be ready to satisfy
all demand at lowest cost
I. STRATEGY II. RESULTS
✓ In Round 5, the bottling line was changed and
shifts increased too much  this mistake was
corrected in round 6
✓ New investment lead to higher production costs
and consequently lower ROI (lack of alignment
with other functions)  on longterm, the company
would improve its business results (lower variability in
production, less rejection component rate, less breakdown,
low unused capcity, high runtime %, etc.)
III. ANALYSIS
98.8% 98.9%
99.6%
99.8% 99.9% 99.8%
90.0%
92.0%
94.0%
96.0%
98.0%
100.0%
102.0%
0
5
10
15
20
25
30
35
40
45
50
Round 1 Round 2 Round 3 Round 4 Round 5 Round 6
ANALYSIS PER COMPONENTS
Mango Orange Pack 1 liter
PET Vitamin C Stock Availability %
SUPPLY CHAIN - COMPONENTS
THE FRESH CONNECTION | TEAM 2 9
✓ Guarantee availability of components to meet
demand (depending on supplier reliability, lot sizes
and safety stock )
✓ Keep cost of stock at min level (in accordance with
operations decisions) – Pet and Pack 1L (1-2
rounds)
✓ Adequate lot sizes depending on the stock cost and
transport costs given by procurement
I. STRATEGY II. RESULTS
✓ It was possible to guarantee availability over 99%
but in some cases compromising average stock –
which increased the cost
✓ Increasing supplier reliability in some products
(vitamin C) was key to have a better stock control
✓ Round 3 and 4 best results obtained
✓ Round 6 problem lack alignment with other
departments
III. ANALYSIS
Low availability of Vitamin
C – High stock PET and
Pack 1
Adjust Pack 1 –
Reduction of lot sizes
Increased Stock
per Week PET –
increase demand
SUPPLY CHAIN – FINISHED GOODS
THE FRESH CONNECTION | TEAM 2 10
✓ Lower average stock weeks of demand and %
obsolete products without compromising service
level - in accordance with contract index per
customer
✓ Adjust production interval to decrease overall cost
and increase utilization rate (7 day)
✓ Frozen period allows to keep flexibility to react to
demand changes
I. STRATEGY II. RESULTS
✓ Achieved to keep obsoletes between (0%-1%) –
Round 6 increase -> due to plan adherence bottling
line involving PET related products and production
interval
(Increasing production due to increase in demand)
✓ Round 2 and Round 6 lowest prod plan adherence
– higher production interval increase average stock
III. ANALYSIS
5.64 5.24 5.50 5.56 5.67 5.32
20%
0% 0% 1% 1% 3%
97% 95% 96% 96% 98%
97%
94% 87% 92% 93%
94%
89%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
1
2
3
4
5
6
7
8
9
10
Round 1 Round 2 Round 3 Round 4 Round 5 Round 6
Stock(weeksofdemand) Stock per week Average % Obsoletes
Average % Service Level Average % Product Plan Adherance
PURCHASING –Component Focus
THE FRESH CONNECTION | TEAM 2 11
✓ Ensure high delivery reliability and low rejection
rates, for the best price.
✓ Make sure lead times & trade units and expected
amounts are planned and aligned with operations.
I. STRATEGY II. RESULTS
✓ Round 4: Supplier is changed
✓ Round 5: Supplier Development Plan is introduced
Lower rejection rate is obtained
Other benefits of the SDP may be observed in
further rounds
III. ANALYSIS
3.40% 3.50% 3.60% 3.20% 2.40% 2.30%
0.99
0.995
1
1.005
1.01
1.015
1.02
1.025
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
1 2 3 4 5 6
Pack 1 Liter
Delivery reliability (%) Rejection(%) Contract Index
PURCHASING – Component Focus
THE FRESH CONNECTION | TEAM 2 12
✓ Round 2: Trade unit is changed
✓ Round 3: Supplier is changed
✓ Round 5: Supplier is changed & Bottling Line is changed with a
more tolerant one.
✓ Round 2: Trade unit is changed
✓ Round 4: Higher delivery reliability rate is negotiated.
5.60% 5.70% 3.10% 3.30% 2.10% 2.00%
0.94
0.95
0.96
0.97
0.98
0.99
1
1.01
1.02
1.03
1.04
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
1 2 3 4 5 6
PET
Delivery reliability (%) Rejection(%) Contract Index
1.00% 1.00% 0.90% 0.90% 0.80% 0.70%
0.996
0.998
1
1.002
1.004
1.006
1.008
1.01
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
1 2 3 4 5 6
Orange
Delivery reliability (%) Rejection(%) Contract Index
PURCHASING – Component Focus
THE FRESH CONNECTION | TEAM 2 13
✓ Round 2: Higher delivery reliability rate is negotiated. ✓ Round 3: Supplier is changed & Higher deliveriy reliability
rate is negotiated.
PURCHASING – Raw Material Costs (%)
THE FRESH CONNECTION | TEAM 2 14
✓ Raw material cost (%) (purchase costs as a
percentage of total revenue) is one of the crucial
KPI’s of the company
✓ It is calculated taking into consideration the bonus
& penalties
✓ Strategy: Lower Values
I. STRATEGY II. RESULTS
✓ Decreasing Trend during the first 5 rounds
✓ High obsolete products in round 6 Causes
unnecessary purchases
✓ Unmatched Service Level Agreements in round 6
Causes high penalties
✓ Best performance: Round 4 & 5
III. ANALYSIS
1,014,346
857,446
828,373 839,319 840,809 861,096
37.48
34.14
32.47 32.14
30.96
31.70
10.00
15.00
20.00
25.00
30.00
35.00
40.00
1 2 3 4 5 6
500,000
600,000
700,000
800,000
900,000
1,000,000
1,100,000
Purchase Costs (%) - Purchase Value
Purchase Value Purchase Costs (%)
FINACIAL RESULTS & CONCLUSIONS
THE FRESH CONNECTION | TEAM 2 15
✓ The average of goods sold in the 6 rounds was $ 2.66 million. The periods
with the highest sales were rounds 1, 5 and 6.
✓ The cost of goods sold drastically influenced the gross margin, the average of
this in the 6 rounds was $ 1.37 million. It can be seen that the periods with
the highest cost of goods sold were 1 and 5.
✓ The ROI went from negative in the first period to positive in the second,
having the best percentages in periods 3 and 4 and lower results in periods 5
and 6 caused by lack of alignment on following factors:
• Change of filling line
• Increased demand
• Decreased production interval
• Not sufficiently increased warehouse capacity
Not allocating the capacity correctly lead to
• High obsoletes % and penalty costs
• High cube utilisation % in warehouses
• Low production plan adherence
✓ The weighted average was 4%
I. RESULTS
FINANCE
ROI EVOLUTION
II. CONCLUSIONS
BACK UP:
Decisions per each round
THE FRESH CONNECTION | TEAM 2 16
SALES - Decisions
THE FRESH CONNECTION | TEAM 2 17
ROUND 1
✓ Understand how the game works
✓ Use real life experience in decisions
✓ Find correlations between other
departments when making decisions
ROUND 2
✓ Get rid of high % of obsoletes by
drastically decreasing shelf life and
introducing FIFS shortage rule
✓ Calculate service level based on changes
made in SC and Operations
ROUND 3
✓ Calculate service level and shelf life based
on changes made in SC and Operations
✓ Obsoletes value at 0,2%
✓ Set goal to increase obsoletes to 1-2% in
order to find how much « air » is in
between actual capacity and negotiated
ROUND 4
✓ Obsoletes still at 0,2% -> Increase shelf
life more
✓ Calculate service level and shelf life based
on changes made in SC and Operations
ROUND 5
✓ Install VMI for 1 customer
✓ Trade unit to Pallet for all customers
✓ Communicate promotional pressure and
implemented changes VMI to SC and
Operations
ROUND 6
✓ Calculate service level to align with
achieved service levels from round 5
✓ VMI for 2 customers
✓ Communicate promotional pressure and
implemented VMI to SC and Operations
OPERATIONS - Decisions
THE FRESH CONNECTION | TEAM 2 18
Decision Period 0
Period 1
30.03.17
Period 2
06.04.17
Period 3
20.04.17
Period 4
20.04.17
Period 5
27.04.17
Period 6
27.04.17
Inbound
(Raw materials)
Pallets location 900 920 900
Shifts 5 3 2 3
IntakeTime days N/A 5 6
Inspection N/A No Pets,Pack 1 liter Pets, Plastics
Mixing Mixer Type Fruit Mix MQ
Bottling
Shifts 2 3 2 3 2
Projects - SMED - -
Preventive
Maintenance
N/A A little A lot
Solve
Breakdown
Training
N/A Yes No
Bottling Line Swiss Fill 2 Multi Flex 1
Outbound
(finished
goods)
Pallets location 1500 1200 1050 950 930 975 1000
Shifts 4 3 4
SUPPLY CHAIN - Decisions
THE FRESH CONNECTION | TEAM 2 19
ROUND 1
✓ Safety Stock: increased Vitamin C, decrease safety
for all finish products (depending on the shelf life)
✓ Lot Size: decreased for PET and Pack 1
✓ Production Interval: Increased production interval of
Freassie Orange/c-Power 1 liter, Fressie Orange PET,
Fressie Orange/C- power PET
✓ Frozen Period: 3
ROUND 2
✓ Safety Stock: reduced Pack 1L and brought back
Vitamin C , unified to 2 SS of finished goods
✓ Lot Size: Decreased Pack 1 liter, orange, mango and
Vitamin C
✓ Production Interval: unified to 8
✓ Frozen Period: 3
ROUND 3
✓ Safety Stock: increased Vitamin C, Fressie Orange/C-
power
✓ Lot Size: decrease Vitamin C
✓ Production Interval: Changed back to 7 Fressie
Orange 1 liter, Fressie Orange/c-Power 1 liter, Fressie
Orange/Mango PET, Fressie Orange/C - power PET
✓ Frozen Period: 4
ROUND 4
✓ Safety Stock: lower vitamin C
✓ Lot Size: no changes
✓ Production Interval: no changes
✓ Frozen Period: 3
ROUND 5
✓ Safety Stock: Fressie Orange 1 liter, Fressie Orange
/C-Power
✓ Lot Size: Reduced for orange and mango
✓ Production Interval: unified to 7
✓ Frozen Period: 3
ROUND 6
✓ Safety Stock: decreased orange, mango, vitamin c
✓ Lot Size: no changes
✓ Production Interval: no changes
✓ Frozen Period: 3
PURCHASING – Detailed Information
THE FRESH CONNECTION | TEAM 2 20
0.000
-0.024
-0.002
-0.013
0.035
0.183
0 0.004
0.064
0.004
0.007
0.000
-0.060
-0.030
0.000
0.030
0.060
0.090
0.120
0.150
0.180
0.210
1 2 3 4 5 6
Contract Index - Purchase Value Graph
Purchase Value (%D) Contract Indexes (%D)
20.00%
0.23% 0.22%
1.23% 0.95%
2.52%
0.00%
4.00%
8.00%
12.00%
16.00%
20.00%
24.00%
1 2 3 4 5 6
Obsolete Products (%) -Average
✓ Percentage Change Graph ✓ Obsolete Products

More Related Content

PPTX
DSO557b - Fresh Connection Final Presentation
PDF
Fresh Connection Level 2
PDF
Fresh Connection Tips
PDF
The Fresh Connection - Simulation based Supply Chain Learning Platform
PDF
Research Methodology Poster for research in Supply Chain Digital Twins
DOCX
Case study: Amazon improvement of customer service
PPTX
Brannigan Foods | Harvard Case
PPT
Global Supply Simulation Presentation - Team 14
DSO557b - Fresh Connection Final Presentation
Fresh Connection Level 2
Fresh Connection Tips
The Fresh Connection - Simulation based Supply Chain Learning Platform
Research Methodology Poster for research in Supply Chain Digital Twins
Case study: Amazon improvement of customer service
Brannigan Foods | Harvard Case
Global Supply Simulation Presentation - Team 14

What's hot (20)

PPTX
Barilla Spa: A case on Supply Chain Integration
PPT
Walmart scm
PDF
The Fresh Connection Business Game - Learnings
PPTX
Sport Obermeyer Case Study
PPTX
Global supply chain case study team8_submit v2
PPTX
American Connector Company
PPTX
Anshu amazon fresh case study
PDF
Supply Chain Management Training in Powerpoint | By ex-McKinsey Consultants
PPTX
Sainsbury in Egypt
PPTX
Goldman sachs ipo dilemma - case study
PPTX
Cola Wars Continue: Coke and Pepsi in 2010
PPTX
Itt global manufacturing strategy os
PPTX
Zappos.com: Developing a Supply Chain to Deliver WOW!
PPTX
Supply Chain Management chap 6
PPTX
CASE Reebok NFL Replica Jerseys
PPTX
The Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
PPTX
Li & Fung case study
PPTX
Cisco System Inc. Implementing ERP
PPTX
Kristin’s Cookie Company Production process and analysis case study
PPTX
Coordination in a supply chain
Barilla Spa: A case on Supply Chain Integration
Walmart scm
The Fresh Connection Business Game - Learnings
Sport Obermeyer Case Study
Global supply chain case study team8_submit v2
American Connector Company
Anshu amazon fresh case study
Supply Chain Management Training in Powerpoint | By ex-McKinsey Consultants
Sainsbury in Egypt
Goldman sachs ipo dilemma - case study
Cola Wars Continue: Coke and Pepsi in 2010
Itt global manufacturing strategy os
Zappos.com: Developing a Supply Chain to Deliver WOW!
Supply Chain Management chap 6
CASE Reebok NFL Replica Jerseys
The Walt Disney Company and Pixar Inc.: To Acquire or Not to Acquire
Li & Fung case study
Cisco System Inc. Implementing ERP
Kristin’s Cookie Company Production process and analysis case study
Coordination in a supply chain
Ad

Similar to The Fresh Connection Game (20)

PPTX
Six Sigma
PDF
Six Sigma- Define & Measure_Sudhanshu.pdf
PDF
PRODUCT AND SERVICES DESIGN USED IN PRODMAN
PPTX
EC plan 2014 Final Revision
PPTX
Supply Chain Basic
PDF
Webinar_DemandPlanning_Forecasting.pdf
PPTX
Deloitte & Touche Consulting Group Case Presentation.pptx
PPT
Asq int lss
PDF
Procurement : Resisting price increase
PPT
PPC Lect - Sales and Operations Planning.ppt
DOCX
Relationship between working capital management nd profitability
PPTX
Darren foster asb presentation 2017
PPT
13.ppt
PDF
PDF
Lean Six Sigma and the principles of Kaizen for your business
DOC
Sample sem 2 winter 2015
PDF
Upstream optimization: How continuous improvement methods are having a positi...
PDF
Upstream optimization: How continuous improvement methods are having a positi...
PDF
Business Performance Management - Process Approach
DOCX
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
Six Sigma
Six Sigma- Define & Measure_Sudhanshu.pdf
PRODUCT AND SERVICES DESIGN USED IN PRODMAN
EC plan 2014 Final Revision
Supply Chain Basic
Webinar_DemandPlanning_Forecasting.pdf
Deloitte & Touche Consulting Group Case Presentation.pptx
Asq int lss
Procurement : Resisting price increase
PPC Lect - Sales and Operations Planning.ppt
Relationship between working capital management nd profitability
Darren foster asb presentation 2017
13.ppt
Lean Six Sigma and the principles of Kaizen for your business
Sample sem 2 winter 2015
Upstream optimization: How continuous improvement methods are having a positi...
Upstream optimization: How continuous improvement methods are having a positi...
Business Performance Management - Process Approach
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
Ad

More from Merve Nur Taş (18)

PDF
Excel Tutorials - Finding & Removing the Duplicate Values
PDF
Strategic Dispatching System Design for Truckload Transportation
PDF
Strategic Dispatching System Design for Truckload Transportation
PDF
Excel Tutorials - Creating a Hyperlink in Excel
PDF
Losemili Cocuklar Haftasi
PDF
Excel Tutorials - Deleting the Empty Rows
PDF
Excel Tutorials - VLOOKUP and HLOOKUP Functions
PDF
Excel Tutorials - Random Value Selection from a List
PDF
Designing Control Algorithms with Gebhardt FlexConveyor Kit
PDF
E-commerce in Turkey
PDF
E-payments in B2B Commerce
PDF
E-payment systems in B2B commerce
PDF
Ramp up project
PDF
Ramp-up Challenges
PDF
Bibliometrics
PDF
Ishikawa Diagram, 6-3-5, 6 Thinking Hats
PDF
Smart Manufacturing & Manufacturing as a Service
PPTX
Smart Manufacturing Presentation
Excel Tutorials - Finding & Removing the Duplicate Values
Strategic Dispatching System Design for Truckload Transportation
Strategic Dispatching System Design for Truckload Transportation
Excel Tutorials - Creating a Hyperlink in Excel
Losemili Cocuklar Haftasi
Excel Tutorials - Deleting the Empty Rows
Excel Tutorials - VLOOKUP and HLOOKUP Functions
Excel Tutorials - Random Value Selection from a List
Designing Control Algorithms with Gebhardt FlexConveyor Kit
E-commerce in Turkey
E-payments in B2B Commerce
E-payment systems in B2B commerce
Ramp up project
Ramp-up Challenges
Bibliometrics
Ishikawa Diagram, 6-3-5, 6 Thinking Hats
Smart Manufacturing & Manufacturing as a Service
Smart Manufacturing Presentation

Recently uploaded (20)

PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
My India Quiz Book_20210205121199924.pdf
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
PDF
International_Financial_Reporting_Standa.pdf
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
Hazard Identification & Risk Assessment .pdf
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PPTX
Computer Architecture Input Output Memory.pptx
PDF
advance database management system book.pdf
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
Chinmaya Tiranga quiz Grand Finale.pdf
My India Quiz Book_20210205121199924.pdf
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
202450812 BayCHI UCSC-SV 20250812 v17.pptx
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
FORM 1 BIOLOGY MIND MAPS and their schemes
Paper A Mock Exam 9_ Attempt review.pdf.
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
International_Financial_Reporting_Standa.pdf
B.Sc. DS Unit 2 Software Engineering.pptx
Hazard Identification & Risk Assessment .pdf
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Virtual and Augmented Reality in Current Scenario
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
LDMMIA Reiki Yoga Finals Review Spring Summer
Practical Manual AGRO-233 Principles and Practices of Natural Farming
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
Computer Architecture Input Output Memory.pptx
advance database management system book.pdf
MBA _Common_ 2nd year Syllabus _2021-22_.pdf

The Fresh Connection Game

  • 1. THE FRESH CONNECTION BUSINESS GAME ANA CORREA CLAUDIA GOMEZ KAMILA HURKOVA MERVE NUR TAŞ TOMMI VEROMAA THE FRESH CONNECTION | TEAM 2 1 T E A M 2
  • 2. EXECUTIVE SUMMARY WHAT DID WE ACHIEVE: ✓ The company obtained profit in each period, growing uninterruptedly in the first 4 rounds and with a slight decrease in the last 2 rounds. ✓ Since round 1, ROI has always been positive. WHAT WAS THE GENERAL STRATEGY : ✓ Make decisions integrating all departments, evaluating the possible positive or negative effects on them in order to minimize costs and maximize the benefit to the company. ✓ Evaluate the decisions made in each period, provide feedback and take corrective actions to make better use of company resources. PROBLEMS ENCOUNTERED: ✓ Difficulties in predicting how some decisions will impact the performance of the company. (The simulator restrained some functionalities at the first stages of the game) ✓ Align strategic decisions of departments in a common goal THE FRESH CONNECTION | TEAM 2 2
  • 3. CONTENTS TEAM & RESPONSIBILITIES ◦ SALES ◦ OPERATIONS ◦ SUPPLY CHAIN ◦ PURCHASING FINANCIAL RESULTS & CONCLUSIONS THE FRESH CONNECTION | TEAM 2 3
  • 4. Cube utilization % Prod.Plan Adherence % Unused capacity % Nr. of shifts Responsibilities: Optimize and control production and warehouses Components % Stock Components Stock Products Responsibilities: Coordinate different departments, inventory control and production Rejection Components % Raw Material Costs % Delivery Reliability Suppliers Responsibilities: Purchasing components, negotiating with suppliers Service level % Obsoletes % Gross Margin Responsibilities: Sell all produced goods with highest possible price TEAM & RESPONSIBILITIES THE FRESH CONNECTION | TEAM 2 4 R O I % PURCHASING SUPPLY CHAIN OPERATIONSSALES
  • 5. SALES – GROSS MARGIN THE FRESH CONNECTION | TEAM 2 5 ✓ Increase gross margin as much as possible prioritizing biggest customers ✓ Try not to lose gross margin on smaller customers significantly ✓ Introduce promotional pressure for customers during later rounds I. STRATEGY II. RESULTS ✓ Gross began to grow on F&C and Dominick’s during round 3 when customer order priorization was implemented ✓ Further increases in later rounds with promotional pressure ✓ Overall increase in gross for F&C and Dominick’s was attained without losing gross margin on Land Market ✓ F&C gross increased by almost 5 000 and Dominick’s by 3000 during 6 periods III. ANALYSIS 11610 14510 22486 27303
  • 6. SALES – NEGOTIATIONS THE FRESH CONNECTION | TEAM 2 6 ✓ Align capacity of SC and Operations to match negotiated service and shelf life levels ✓ Take advantage of one customer with full product range to decrease potential obsoletes ✓ Trade unit: Pallets for all and VMI for F&C and Dominick’s to reduce outbound stress ✓ Customer priorities: 1. F&C, 2. Dominick’s, 3. LM I. STRATEGY ✓ Obsoletes were solved with having LM with shelf life of 62-65% ✓ Negotiated service level % was calculated and estimated based on improvements in SC and Operations ✓ Decision-making in Sales was first based on improvements made in SC and Operations, further the decisions in SC and Operations were changed based on Sales. III. ANALYSIS II. RESULTS
  • 7. 900 900 920 900 900 900 900 1500 1200 1050 950 930 975 1000 98% 99% 94% 96% 97% 100% 108% 71% 79% 85% 95% 97% 101% 101% 0% 20% 40% 60% 80% 100% 120% 0 200 400 600 800 1000 1200 1400 Round 0 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6 CubeUtilisation WarehouseCapacity Inbound Capacity Outbound Capacity Inbound Cube Utilisation Outbound Cube Utilisation OPERATIONS - WAREHOUSES THE FRESH CONNECTION | TEAM 2 7 ✓ Optimise pallet allocations (to avoid overflow and outsourcing / too large unsued capacity) ✓ Allocate adequate number of shifts ✓ Reduce variability in processes and smooth raw materials income and finished goods storage (align with Supply Chain and Purchasing) ✓ Be ready to handle all demand (align with Sales) I. STRATEGY II. RESULTS ✓ Round 4 was the most successful ✓ Starting in Round 5, the demand overpassed the warehouses‘ capacities and it was not adjusted correctly ✓ Outsourcing of warehouses would lead to significantly higher costs III. ANALYSIS
  • 8. 79% 94% 87% 92% 93% 94% 89% 78% 58% 73% 73% 73% 53% 81% 5% 25% 6% 10% 11% 39% 10% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Round 0 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6 Production Plan Adherence Runtime Unused Capacity OPERATIONS - PRODUCTION THE FRESH CONNECTION | TEAM 2 8 ´ ✓ Allocate adequate number of shifts ✓ Select wisely new investments to smooth production and increase ROI (mixing and botteling) ✓ Minimize production costs, unused capacity, changeover and breakdown times ✓ Maximize production plan adherence ✓ Align with all other functions to be ready to satisfy all demand at lowest cost I. STRATEGY II. RESULTS ✓ In Round 5, the bottling line was changed and shifts increased too much  this mistake was corrected in round 6 ✓ New investment lead to higher production costs and consequently lower ROI (lack of alignment with other functions)  on longterm, the company would improve its business results (lower variability in production, less rejection component rate, less breakdown, low unused capcity, high runtime %, etc.) III. ANALYSIS
  • 9. 98.8% 98.9% 99.6% 99.8% 99.9% 99.8% 90.0% 92.0% 94.0% 96.0% 98.0% 100.0% 102.0% 0 5 10 15 20 25 30 35 40 45 50 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6 ANALYSIS PER COMPONENTS Mango Orange Pack 1 liter PET Vitamin C Stock Availability % SUPPLY CHAIN - COMPONENTS THE FRESH CONNECTION | TEAM 2 9 ✓ Guarantee availability of components to meet demand (depending on supplier reliability, lot sizes and safety stock ) ✓ Keep cost of stock at min level (in accordance with operations decisions) – Pet and Pack 1L (1-2 rounds) ✓ Adequate lot sizes depending on the stock cost and transport costs given by procurement I. STRATEGY II. RESULTS ✓ It was possible to guarantee availability over 99% but in some cases compromising average stock – which increased the cost ✓ Increasing supplier reliability in some products (vitamin C) was key to have a better stock control ✓ Round 3 and 4 best results obtained ✓ Round 6 problem lack alignment with other departments III. ANALYSIS Low availability of Vitamin C – High stock PET and Pack 1 Adjust Pack 1 – Reduction of lot sizes Increased Stock per Week PET – increase demand
  • 10. SUPPLY CHAIN – FINISHED GOODS THE FRESH CONNECTION | TEAM 2 10 ✓ Lower average stock weeks of demand and % obsolete products without compromising service level - in accordance with contract index per customer ✓ Adjust production interval to decrease overall cost and increase utilization rate (7 day) ✓ Frozen period allows to keep flexibility to react to demand changes I. STRATEGY II. RESULTS ✓ Achieved to keep obsoletes between (0%-1%) – Round 6 increase -> due to plan adherence bottling line involving PET related products and production interval (Increasing production due to increase in demand) ✓ Round 2 and Round 6 lowest prod plan adherence – higher production interval increase average stock III. ANALYSIS 5.64 5.24 5.50 5.56 5.67 5.32 20% 0% 0% 1% 1% 3% 97% 95% 96% 96% 98% 97% 94% 87% 92% 93% 94% 89% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% 0 1 2 3 4 5 6 7 8 9 10 Round 1 Round 2 Round 3 Round 4 Round 5 Round 6 Stock(weeksofdemand) Stock per week Average % Obsoletes Average % Service Level Average % Product Plan Adherance
  • 11. PURCHASING –Component Focus THE FRESH CONNECTION | TEAM 2 11 ✓ Ensure high delivery reliability and low rejection rates, for the best price. ✓ Make sure lead times & trade units and expected amounts are planned and aligned with operations. I. STRATEGY II. RESULTS ✓ Round 4: Supplier is changed ✓ Round 5: Supplier Development Plan is introduced Lower rejection rate is obtained Other benefits of the SDP may be observed in further rounds III. ANALYSIS 3.40% 3.50% 3.60% 3.20% 2.40% 2.30% 0.99 0.995 1 1.005 1.01 1.015 1.02 1.025 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% 1 2 3 4 5 6 Pack 1 Liter Delivery reliability (%) Rejection(%) Contract Index
  • 12. PURCHASING – Component Focus THE FRESH CONNECTION | TEAM 2 12 ✓ Round 2: Trade unit is changed ✓ Round 3: Supplier is changed ✓ Round 5: Supplier is changed & Bottling Line is changed with a more tolerant one. ✓ Round 2: Trade unit is changed ✓ Round 4: Higher delivery reliability rate is negotiated. 5.60% 5.70% 3.10% 3.30% 2.10% 2.00% 0.94 0.95 0.96 0.97 0.98 0.99 1 1.01 1.02 1.03 1.04 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% 1 2 3 4 5 6 PET Delivery reliability (%) Rejection(%) Contract Index 1.00% 1.00% 0.90% 0.90% 0.80% 0.70% 0.996 0.998 1 1.002 1.004 1.006 1.008 1.01 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% 1 2 3 4 5 6 Orange Delivery reliability (%) Rejection(%) Contract Index
  • 13. PURCHASING – Component Focus THE FRESH CONNECTION | TEAM 2 13 ✓ Round 2: Higher delivery reliability rate is negotiated. ✓ Round 3: Supplier is changed & Higher deliveriy reliability rate is negotiated.
  • 14. PURCHASING – Raw Material Costs (%) THE FRESH CONNECTION | TEAM 2 14 ✓ Raw material cost (%) (purchase costs as a percentage of total revenue) is one of the crucial KPI’s of the company ✓ It is calculated taking into consideration the bonus & penalties ✓ Strategy: Lower Values I. STRATEGY II. RESULTS ✓ Decreasing Trend during the first 5 rounds ✓ High obsolete products in round 6 Causes unnecessary purchases ✓ Unmatched Service Level Agreements in round 6 Causes high penalties ✓ Best performance: Round 4 & 5 III. ANALYSIS 1,014,346 857,446 828,373 839,319 840,809 861,096 37.48 34.14 32.47 32.14 30.96 31.70 10.00 15.00 20.00 25.00 30.00 35.00 40.00 1 2 3 4 5 6 500,000 600,000 700,000 800,000 900,000 1,000,000 1,100,000 Purchase Costs (%) - Purchase Value Purchase Value Purchase Costs (%)
  • 15. FINACIAL RESULTS & CONCLUSIONS THE FRESH CONNECTION | TEAM 2 15 ✓ The average of goods sold in the 6 rounds was $ 2.66 million. The periods with the highest sales were rounds 1, 5 and 6. ✓ The cost of goods sold drastically influenced the gross margin, the average of this in the 6 rounds was $ 1.37 million. It can be seen that the periods with the highest cost of goods sold were 1 and 5. ✓ The ROI went from negative in the first period to positive in the second, having the best percentages in periods 3 and 4 and lower results in periods 5 and 6 caused by lack of alignment on following factors: • Change of filling line • Increased demand • Decreased production interval • Not sufficiently increased warehouse capacity Not allocating the capacity correctly lead to • High obsoletes % and penalty costs • High cube utilisation % in warehouses • Low production plan adherence ✓ The weighted average was 4% I. RESULTS FINANCE ROI EVOLUTION II. CONCLUSIONS
  • 16. BACK UP: Decisions per each round THE FRESH CONNECTION | TEAM 2 16
  • 17. SALES - Decisions THE FRESH CONNECTION | TEAM 2 17 ROUND 1 ✓ Understand how the game works ✓ Use real life experience in decisions ✓ Find correlations between other departments when making decisions ROUND 2 ✓ Get rid of high % of obsoletes by drastically decreasing shelf life and introducing FIFS shortage rule ✓ Calculate service level based on changes made in SC and Operations ROUND 3 ✓ Calculate service level and shelf life based on changes made in SC and Operations ✓ Obsoletes value at 0,2% ✓ Set goal to increase obsoletes to 1-2% in order to find how much « air » is in between actual capacity and negotiated ROUND 4 ✓ Obsoletes still at 0,2% -> Increase shelf life more ✓ Calculate service level and shelf life based on changes made in SC and Operations ROUND 5 ✓ Install VMI for 1 customer ✓ Trade unit to Pallet for all customers ✓ Communicate promotional pressure and implemented changes VMI to SC and Operations ROUND 6 ✓ Calculate service level to align with achieved service levels from round 5 ✓ VMI for 2 customers ✓ Communicate promotional pressure and implemented VMI to SC and Operations
  • 18. OPERATIONS - Decisions THE FRESH CONNECTION | TEAM 2 18 Decision Period 0 Period 1 30.03.17 Period 2 06.04.17 Period 3 20.04.17 Period 4 20.04.17 Period 5 27.04.17 Period 6 27.04.17 Inbound (Raw materials) Pallets location 900 920 900 Shifts 5 3 2 3 IntakeTime days N/A 5 6 Inspection N/A No Pets,Pack 1 liter Pets, Plastics Mixing Mixer Type Fruit Mix MQ Bottling Shifts 2 3 2 3 2 Projects - SMED - - Preventive Maintenance N/A A little A lot Solve Breakdown Training N/A Yes No Bottling Line Swiss Fill 2 Multi Flex 1 Outbound (finished goods) Pallets location 1500 1200 1050 950 930 975 1000 Shifts 4 3 4
  • 19. SUPPLY CHAIN - Decisions THE FRESH CONNECTION | TEAM 2 19 ROUND 1 ✓ Safety Stock: increased Vitamin C, decrease safety for all finish products (depending on the shelf life) ✓ Lot Size: decreased for PET and Pack 1 ✓ Production Interval: Increased production interval of Freassie Orange/c-Power 1 liter, Fressie Orange PET, Fressie Orange/C- power PET ✓ Frozen Period: 3 ROUND 2 ✓ Safety Stock: reduced Pack 1L and brought back Vitamin C , unified to 2 SS of finished goods ✓ Lot Size: Decreased Pack 1 liter, orange, mango and Vitamin C ✓ Production Interval: unified to 8 ✓ Frozen Period: 3 ROUND 3 ✓ Safety Stock: increased Vitamin C, Fressie Orange/C- power ✓ Lot Size: decrease Vitamin C ✓ Production Interval: Changed back to 7 Fressie Orange 1 liter, Fressie Orange/c-Power 1 liter, Fressie Orange/Mango PET, Fressie Orange/C - power PET ✓ Frozen Period: 4 ROUND 4 ✓ Safety Stock: lower vitamin C ✓ Lot Size: no changes ✓ Production Interval: no changes ✓ Frozen Period: 3 ROUND 5 ✓ Safety Stock: Fressie Orange 1 liter, Fressie Orange /C-Power ✓ Lot Size: Reduced for orange and mango ✓ Production Interval: unified to 7 ✓ Frozen Period: 3 ROUND 6 ✓ Safety Stock: decreased orange, mango, vitamin c ✓ Lot Size: no changes ✓ Production Interval: no changes ✓ Frozen Period: 3
  • 20. PURCHASING – Detailed Information THE FRESH CONNECTION | TEAM 2 20 0.000 -0.024 -0.002 -0.013 0.035 0.183 0 0.004 0.064 0.004 0.007 0.000 -0.060 -0.030 0.000 0.030 0.060 0.090 0.120 0.150 0.180 0.210 1 2 3 4 5 6 Contract Index - Purchase Value Graph Purchase Value (%D) Contract Indexes (%D) 20.00% 0.23% 0.22% 1.23% 0.95% 2.52% 0.00% 4.00% 8.00% 12.00% 16.00% 20.00% 24.00% 1 2 3 4 5 6 Obsolete Products (%) -Average ✓ Percentage Change Graph ✓ Obsolete Products