The Hard Side of Change
Management
(Sirkin, Keenan, Jackson, 2005)
Background
• Companies over-emphasize the soft side of change:
leadership style, corporate culture, employee motivation.
• Companies should address harder elements. (DICE)
• By assessing each DICE element before launching a
major change initiative, identifying potential problem
areas and make the necessary adjustments (such as
reconfiguring a project team’s composition or
reallocating resources) to ensure the program’s success.
• use DICE after launching a project—to make midcourse
corrections if the initiative veers off track.
The Four Key Factors
• time between milestone reviews—
the shorter, the betterDuration
• project teams’ skill
Integrity
• senior executives’ and line
managers’ dedication to the programCommitment
• The extra work must do to adopt
new processes—the less, the betterEffort
Duration
• A long project reviewed frequently stands
a far better chance of succeeding than a
short project reviewed infrequently.
• Problems can be identified at the first sign
of trouble, allowing for prompt corrective
actions.
• Review complex projects every two
weeks; more straightforward initiatives,
every six to eight weeks.
The duration of time until the change
program is completed if it has a short life
span; if not short, the amount of time
between reviews of milestones.
Integrity
• A change program’s success hinges on a
high integrity, high-quality project team.
• To identify team candidates with the right
portfolio of skills, solicit names from key
colleagues, including top performers in
functions other.
• Recruit people who have problem-solving
skills, are results oriented, and are
methodical but tolerate ambiguity.
• Look also for organizational savvy,
willingness to accept responsibility for
decisions, and a disdain for the limelight.
Its ability to complete the initiative on
time  depends on members’ skills &
traits relative to the project’s
requirements
Commitment
• If employees don’t see company leaders
supporting a change initiative, they won’t
change.
• Also continually communicate why the
change is needed and what it means for
employees.
• Ensure that all messages about the
change are consistent and clear. Reach
out to managers and employees through
one-one conversations to win them over.
Effort
• If adopting a change burdens employees
with too much additional effort, they’ll
resist.
• Calculate how much work employees will
have to do beyond their existing
responsibilities to implement the change.
• Ensure that no one’s workload increases
> 10%. If necessary, remove nonessential
regular work from employees with key
roles in the transformation project.
• Use temporary workers or outsource
some processes to accommodate
additional workload.
Calculating
DICE Scores
DURATION [D]
Do formal project reviews occur regularly? If
the project will take more than two months
to complete, what is the average time
between reviews?
INTEGRITY OF PERFORMANCE [ I ]
Is the team leader capable? How strong are
team members‘ skills and motivations? Do
they have sufficient time to spend on the
change initiative?
SENIOR MANAGEMENT COMMITMENT
[Ci]
Do senior executives regularly communicate
the reason for the change and the
importance of its success? Is the message
convincing? is the message consistent, both
across the top management team and
overtime? Has top management devoted
enough resources to the change program?
EFFORT [E]
What is the percentage of increased effort
that employees must make to implement the
change effort? Does the incremental effort
come on top of a heavy workload? Have
people strongly resisted the increased
demands on them?
ASK
DURATION [D]
Do formal project reviews occur
regularly? If the project will take more
than two months to complete, what is
the average time between reviews?
Score: If the
time between
project
reviews < 2
months 1
point
If the time is
between 2 - 4
months 2
points
between 4 - 8
months, 3
points
if reviews > 8
months apart,
 4 points
INTEGRITY OF PERFORMANCE [ I ]
Is the team leader capable? How
strong are team members‘ skills and
motivations? Do they have sufficient
time to spend on the change initiative?
The project team is led by a
highly capable leader who
is respected by peers
The members have the
skills and motivation to
complete the project in the
stipulated time frame
The company has assigned
at least 50% of the team
members' time to the
project
1 point
The team's capabilities are
somewhere in between,
assign the project
2 or 3 points
The team is lacking on all
those dimensions
4 points
LOCAL-LEVEL COMMITMENT [C2]
Do the employees most affected by the
change understand the reason for it and
believe it’s worthwhile? Are they enthusiastic
and supportive or worried and obstructive?
If employees
are eager to
take on the
change
initiative
1 point
if they are
just willing
2 points
If they're
reluctant or
strongly
reluctant
3 or 4
points.
SENIOR MANAGEMENT COMMITMENT [Ci]
Do senior executives regularly communicate the
reason for the change and the importance of its
success? Is the message convincing? is the message
consistent, both across the top management team and
overtime? Has top management devoted enough
resources to the change program?
Senior
management
has (actions and
words) clearly
communicated
the need for
change
1 point.
If senior
executives
appear to be
neutral,
2 or 3 points.
If managers
perceive senior
executives to be
reluctant to
support the
change
4 points.
EFFORT [E]
What is the percentage of increased effort that
employees must make to implement the change
effort? Does the incremental effort come on top
of a heavy workload? Have people strongly
resisted the increased demands on them?
If the project
requires less
than 10%
extra work by
employees,
you can give
it 1 point
. If it's 10% to
20% extra, it
should get 2
points. If it's
20% to 40%,
it must be 3
points.
if it's more
than 40%
additional
work, you
should give
the project 4
points.
DICE Score = D + (2 X I ) + (2 X C1) + C2 + E
Zones of project
• Scores between 7 and 14:
• The project is very likely to succeed.Win
• Scores higher than 14 but lower than 17:
• Risks to the project’s success are risingWorry
• The project is extremely risky.
• project scores over 17 and under 19 points, the
risks to success are very high. Beyond 19, the
project is unlikely to succeed.
Woe
• Conducting a DICE assessment fosters
successful change by sparking valuable
senior leadership debate about project
strategy It also improves change
effectiveness by enabling companies to
manage large portfolios of projects.
Applying the DICE Framework
Creating the Framework

More Related Content

PPTX
HRM Interventions
PPTX
Strategic Risk Management as a CFO: Getting Risk Management Right
PDF
Project Management and Change Management - Sean Low
PPT
Industrial disputes act, 1947
PPTX
How to motivate yourself!
PDF
Prosci Webinar - How to Integrate Change Management and Project Management
PDF
Emotional Intelligence (EI) in Leadership Development
PDF
8 Qualities of Exceptional Leaders
HRM Interventions
Strategic Risk Management as a CFO: Getting Risk Management Right
Project Management and Change Management - Sean Low
Industrial disputes act, 1947
How to motivate yourself!
Prosci Webinar - How to Integrate Change Management and Project Management
Emotional Intelligence (EI) in Leadership Development
8 Qualities of Exceptional Leaders

What's hot (20)

PPTX
Organizational Development - an introduction
PPTX
Change management
PPT
Managing Organisational Change
PPT
Change Management
PPTX
Current issues in hrd
PPT
Competency mapping ppt
PPTX
career planning &amp; succession planning
PDF
Evolution of OD in india
PPT
Acquiring human resources
PPTX
Employees empowerment.pdf
PDF
Promotion, Transfer And Seperation
PDF
Why is Change Management important?
PDF
114123215 promotion-transfer-and-demotion
 
PDF
(12) organizational change and development
PPTX
Balanced Score Card ppt
PPTX
The theory and practice of change managemen
PPTX
nature of planned change
DOCX
Change management case study
PPT
Change management
PPTX
Change management PMI
Organizational Development - an introduction
Change management
Managing Organisational Change
Change Management
Current issues in hrd
Competency mapping ppt
career planning &amp; succession planning
Evolution of OD in india
Acquiring human resources
Employees empowerment.pdf
Promotion, Transfer And Seperation
Why is Change Management important?
114123215 promotion-transfer-and-demotion
 
(12) organizational change and development
Balanced Score Card ppt
The theory and practice of change managemen
nature of planned change
Change management case study
Change management
Change management PMI
Ad

Viewers also liked (20)

PPT
Samsung final
PPTX
Everything Is Digital: Ten HR and Talent Predictions for 2020
PPTX
Change Management PPT Slides
PPTX
Change Management Models- a comparison
PDF
Lies, Damned Lies, and Pretty Pictures
PDF
Peter Fisk - Marketing Game-Changer
PPTX
Emotional Change
PDF
Internet firms --- what strategic changes have to be managed
PPTX
Why Technology Matters to Small Business
PPTX
Change management in hard times
PPT
Change Management The Human Factor
PPTX
Designing the perfect display monetization dashboard (public)
PDF
Strategic Customer Management Framework - My FISH Model
PPTX
Business continuity plan
PPTX
CHANGE MANAGEMENT IN VOLATILE ECONOMY
PPT
Evolution and Revolution as Organizations Grow
PPT
Greiner’s Growth Curve
PDF
Termination
PPTX
Employment termination
PDF
Individuelles Change Management
Samsung final
Everything Is Digital: Ten HR and Talent Predictions for 2020
Change Management PPT Slides
Change Management Models- a comparison
Lies, Damned Lies, and Pretty Pictures
Peter Fisk - Marketing Game-Changer
Emotional Change
Internet firms --- what strategic changes have to be managed
Why Technology Matters to Small Business
Change management in hard times
Change Management The Human Factor
Designing the perfect display monetization dashboard (public)
Strategic Customer Management Framework - My FISH Model
Business continuity plan
CHANGE MANAGEMENT IN VOLATILE ECONOMY
Evolution and Revolution as Organizations Grow
Greiner’s Growth Curve
Termination
Employment termination
Individuelles Change Management
Ad

Similar to The hard side of change management (20)

PPTX
the Hard Side of change managment.pptx
DOCX
Artk Consulting Change Management Program Model
PPTX
ClientSummit2010_AgileWorkshop
PPTX
Matinée PMI - Why so many technology projects failing
PDF
Managing Projects through Major Quality Changes-Casey Dusenbery, Ecolab
PPTX
The Hard Side of Change Management .pptx
DOC
Change Management Plan
PPTX
Chapter-5-implementation.pptx
PDF
Rtsundari ashutoshpandey-131008015758-phpapp02
PDF
Rt sundari ashutosh_pandey
PPSX
Executing and Managing a Project
PPTX
CMI Presentation on Organisational Change Maturity Model
PDF
Alignment Zavala Civitas 2013
PPTX
Unit-1.pptxgeyeuueueu7r7r7r77r7r7r7uriruru
PPTX
Change management in Project management d
PPTX
Organization Change Management for the handling change in organizations
PPTX
Organization Change Management.pptx
PPTX
Process Improvement Roadmap
PPTX
PMO17BR103PMOSym2017_171105_WassermanBarrows_FINAL copy.pptx
PDF
Project report submitted in IIM Calcutta
the Hard Side of change managment.pptx
Artk Consulting Change Management Program Model
ClientSummit2010_AgileWorkshop
Matinée PMI - Why so many technology projects failing
Managing Projects through Major Quality Changes-Casey Dusenbery, Ecolab
The Hard Side of Change Management .pptx
Change Management Plan
Chapter-5-implementation.pptx
Rtsundari ashutoshpandey-131008015758-phpapp02
Rt sundari ashutosh_pandey
Executing and Managing a Project
CMI Presentation on Organisational Change Maturity Model
Alignment Zavala Civitas 2013
Unit-1.pptxgeyeuueueu7r7r7r77r7r7r7uriruru
Change management in Project management d
Organization Change Management for the handling change in organizations
Organization Change Management.pptx
Process Improvement Roadmap
PMO17BR103PMOSym2017_171105_WassermanBarrows_FINAL copy.pptx
Project report submitted in IIM Calcutta

More from Diana Fajri (7)

DOCX
Ada kasus merger hp dan compaq
PDF
Plugin f2012072016143787625285
DOCX
PDF
Strategic
PDF
manajemen strategi perusahaan
DOC
Problems at china airlines indonesia
PDF
B0 d912d dd01
Ada kasus merger hp dan compaq
Plugin f2012072016143787625285
Strategic
manajemen strategi perusahaan
Problems at china airlines indonesia
B0 d912d dd01

Recently uploaded (20)

PDF
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
DOCX
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
PDF
ICv2 White Paper - Gen Con Trade Day 2025
PPTX
Slide gioi thieu VietinBank Quy 2 - 2025
PDF
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
DOCX
FINALS-BSHhchcuvivicucucucucM-Centro.docx
PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Keppel_Proposed Divestment of M1 Limited
PPT
Lecture notes on Business Research Methods
PPTX
Astra-Investor- business Presentation (1).pptx
PDF
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
Environmental Law Communication: Strategies for Advocacy (www.kiu.ac.ug)
PDF
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
PDF
PMB 401-Identification-of-Potential-Biotechnological-Products.pdf
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
PDF
Kishore Vora - Best CFO in India to watch in 2025.pdf
Tortilla Mexican Grill 发射点犯得上发射点发生发射点犯得上发生
80 DE ÔN VÀO 10 NĂM 2023vhkkkjjhhhhjjjj
ICv2 White Paper - Gen Con Trade Day 2025
Slide gioi thieu VietinBank Quy 2 - 2025
Susan Semmelmann: Enriching the Lives of others through her Talents and Bless...
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
NEW - FEES STRUCTURES (01-july-2024).pdf
FINALS-BSHhchcuvivicucucucucM-Centro.docx
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Keppel_Proposed Divestment of M1 Limited
Lecture notes on Business Research Methods
Astra-Investor- business Presentation (1).pptx
#1 Safe and Secure Verified Cash App Accounts for Purchase.pdf
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
Environmental Law Communication: Strategies for Advocacy (www.kiu.ac.ug)
THE COMPLETE GUIDE TO BUILDING PASSIVE INCOME ONLINE
PMB 401-Identification-of-Potential-Biotechnological-Products.pdf
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Nante Industrial Plug Factory: Engineering Quality for Modern Power Applications
Kishore Vora - Best CFO in India to watch in 2025.pdf

The hard side of change management

  • 1. The Hard Side of Change Management (Sirkin, Keenan, Jackson, 2005)
  • 2. Background • Companies over-emphasize the soft side of change: leadership style, corporate culture, employee motivation. • Companies should address harder elements. (DICE) • By assessing each DICE element before launching a major change initiative, identifying potential problem areas and make the necessary adjustments (such as reconfiguring a project team’s composition or reallocating resources) to ensure the program’s success. • use DICE after launching a project—to make midcourse corrections if the initiative veers off track.
  • 3. The Four Key Factors • time between milestone reviews— the shorter, the betterDuration • project teams’ skill Integrity • senior executives’ and line managers’ dedication to the programCommitment • The extra work must do to adopt new processes—the less, the betterEffort
  • 4. Duration • A long project reviewed frequently stands a far better chance of succeeding than a short project reviewed infrequently. • Problems can be identified at the first sign of trouble, allowing for prompt corrective actions. • Review complex projects every two weeks; more straightforward initiatives, every six to eight weeks. The duration of time until the change program is completed if it has a short life span; if not short, the amount of time between reviews of milestones.
  • 5. Integrity • A change program’s success hinges on a high integrity, high-quality project team. • To identify team candidates with the right portfolio of skills, solicit names from key colleagues, including top performers in functions other. • Recruit people who have problem-solving skills, are results oriented, and are methodical but tolerate ambiguity. • Look also for organizational savvy, willingness to accept responsibility for decisions, and a disdain for the limelight. Its ability to complete the initiative on time  depends on members’ skills & traits relative to the project’s requirements
  • 6. Commitment • If employees don’t see company leaders supporting a change initiative, they won’t change. • Also continually communicate why the change is needed and what it means for employees. • Ensure that all messages about the change are consistent and clear. Reach out to managers and employees through one-one conversations to win them over.
  • 7. Effort • If adopting a change burdens employees with too much additional effort, they’ll resist. • Calculate how much work employees will have to do beyond their existing responsibilities to implement the change. • Ensure that no one’s workload increases > 10%. If necessary, remove nonessential regular work from employees with key roles in the transformation project. • Use temporary workers or outsource some processes to accommodate additional workload.
  • 9. DURATION [D] Do formal project reviews occur regularly? If the project will take more than two months to complete, what is the average time between reviews? INTEGRITY OF PERFORMANCE [ I ] Is the team leader capable? How strong are team members‘ skills and motivations? Do they have sufficient time to spend on the change initiative? SENIOR MANAGEMENT COMMITMENT [Ci] Do senior executives regularly communicate the reason for the change and the importance of its success? Is the message convincing? is the message consistent, both across the top management team and overtime? Has top management devoted enough resources to the change program? EFFORT [E] What is the percentage of increased effort that employees must make to implement the change effort? Does the incremental effort come on top of a heavy workload? Have people strongly resisted the increased demands on them? ASK
  • 10. DURATION [D] Do formal project reviews occur regularly? If the project will take more than two months to complete, what is the average time between reviews? Score: If the time between project reviews < 2 months 1 point If the time is between 2 - 4 months 2 points between 4 - 8 months, 3 points if reviews > 8 months apart,  4 points
  • 11. INTEGRITY OF PERFORMANCE [ I ] Is the team leader capable? How strong are team members‘ skills and motivations? Do they have sufficient time to spend on the change initiative? The project team is led by a highly capable leader who is respected by peers The members have the skills and motivation to complete the project in the stipulated time frame The company has assigned at least 50% of the team members' time to the project 1 point The team's capabilities are somewhere in between, assign the project 2 or 3 points The team is lacking on all those dimensions 4 points
  • 12. LOCAL-LEVEL COMMITMENT [C2] Do the employees most affected by the change understand the reason for it and believe it’s worthwhile? Are they enthusiastic and supportive or worried and obstructive? If employees are eager to take on the change initiative 1 point if they are just willing 2 points If they're reluctant or strongly reluctant 3 or 4 points.
  • 13. SENIOR MANAGEMENT COMMITMENT [Ci] Do senior executives regularly communicate the reason for the change and the importance of its success? Is the message convincing? is the message consistent, both across the top management team and overtime? Has top management devoted enough resources to the change program? Senior management has (actions and words) clearly communicated the need for change 1 point. If senior executives appear to be neutral, 2 or 3 points. If managers perceive senior executives to be reluctant to support the change 4 points.
  • 14. EFFORT [E] What is the percentage of increased effort that employees must make to implement the change effort? Does the incremental effort come on top of a heavy workload? Have people strongly resisted the increased demands on them? If the project requires less than 10% extra work by employees, you can give it 1 point . If it's 10% to 20% extra, it should get 2 points. If it's 20% to 40%, it must be 3 points. if it's more than 40% additional work, you should give the project 4 points.
  • 15. DICE Score = D + (2 X I ) + (2 X C1) + C2 + E
  • 16. Zones of project • Scores between 7 and 14: • The project is very likely to succeed.Win • Scores higher than 14 but lower than 17: • Risks to the project’s success are risingWorry • The project is extremely risky. • project scores over 17 and under 19 points, the risks to success are very high. Beyond 19, the project is unlikely to succeed. Woe
  • 17. • Conducting a DICE assessment fosters successful change by sparking valuable senior leadership debate about project strategy It also improves change effectiveness by enabling companies to manage large portfolios of projects.
  • 18. Applying the DICE Framework