SlideShare a Scribd company logo
{
“The Softer Side of Scheduling”
How simple, non electronic, collaborative efforts
make for a more robust, accurate and better
functioning project schedule.
Sreedhar “Sree” Yedavalli, PMP
Technical Project Manager
Samsung-WorldLink
Thursday, February 18, 2016, 5:01PM
• Temporary - Defined Start and End dates
• Unique deliverables (Product, service result)Project
•Group of similar, but distinct, projectsProgram
• Collection of programs and projectsPortfolio
About Projects
XYVEX Labs
Products
STM LITHOGRAPHY
CONTROL SYSTEM
Project 1 – New
HDL Scripting
Project 2 –
Position
Controls
upgrade
mechanism
ZETCHER™
Project 1 –
Software
Customization -
UTD
Project 2 –
Hardware
Upgrade
Services
Project 1 –
Stainless Steel
metalworking
for SY, Inc.
Project 2 – At
installation
materials,
Dallas Art
Festival
Research
Grant#1 –
DoE Nanite
manipulation
SBIR to DoD
Application
Portfolio List?
Portfolio
Programs
& Projects
Projects
Master
Schedule
6.6.3.2
Stakeholders
2.2.1
WBS
5.4
Activity List
and Gantt
6.2.3.1
Project
Charter
4.1
About Scheduling
Work Breakdown Structure
 WBS = Hierarchical decomposition of the TOTAL SCOPE OF WORK
to be carried out for the project.
 100% Rule = the WBS includes 100% of the work defined by the
project scope and captures all deliverables – internal, external,
interim – in terms of the work to be completed, including project
management.
 Key project deliverable that organizes the team's work into
manageable sections
 PMBOK & MIL-STD-881C
 WBS Will help you organize
 Personnel assignments
 Activity List - Major and minor tasks
 Material acquisition – when and how
much
 Asset allocation – the tools you need and
when you need them.
Why a WBS?
 “The Group Hug”
 All stakeholders, management and key
personnel involved in the project
 Representatives from consultants or
vendors
 One room, one day, all out free for all
 (Example on Whiteboard)
Who does the WBS?
 Creates a hierarchy within the project.
 Defines the “Project Manager”
 Defines the “Project Sponsor”
 Defines deliverables
How WBS benefits you?
The Softer Side of Scheduling
 Complete – make sure that we do not forget anything (what we
forget here will not be part of further project planning, and
thus, can cause time delays and additional costs).
 Free of contradictions – check if the WBS contains any work
packages with contradicting or inconsistent specifications or
descriptions (of pre-conditions, expected results, etc.), and
revise accordingly.
 Work packages on lowest level - clearly specifying
responsibility, pre-conditions, expected results, necessary skill
levels, special expertise, so that we have a reliable basis for
estimation of effort and duration (minimum requirement: verb
+ object).
Criteria of a WBS
 "80 hour rule – no activity at the lowest level to produce a
single deliverable, should be more than 80 hours of effort.
 If the project team is reporting progress monthly, then no
single activity or series of activities should be longer than
one month long.
 “Common sense" when creating the duration of a single
activity or group of activities.
Level of Detail
Other Benefits to WBS & PM
 Better project budgeting – complete projects in less time with less money
 Predictability – reduce unknowns in project process
 Control scope – reduce the risk of adding unnecessary scope to an ongoing project -
“Scope Creep”.
 Better solutions – planning with client or stakeholders leads to better outcomes that
weren’t originally understood.
 Resolve problems more quickly – stick to the plan!
 Resolve future risk before problems start.
 Better product, better service, better outcome.
 Avoids “bad” projects
 More metrics and fact based decision making
 Improved work flow and work environment

More Related Content

PPTX
Session 5 4th edition PMP
PPTX
Project Management Tool & Technique of Online Bookstore
PPTX
Schedule Training
PPT
SapSchedule
PPTX
Primavera presentation
PPTX
Project Management Tools
DOCX
Project mangement part 1
PPTX
Project Time Management
Session 5 4th edition PMP
Project Management Tool & Technique of Online Bookstore
Schedule Training
SapSchedule
Primavera presentation
Project Management Tools
Project mangement part 1
Project Time Management

What's hot (20)

PPT
Project Time Management
PPTX
project time management
PPTX
Software project management tools
PPT
Primavera Training P6
PPT
Mkcl Project Management Session 3
PDF
Benefits of implementing primavera p6 r8.1 and integration to oracle ppt
PPTX
CPM/PERT and Gantt charts
PPTX
PROJECT SCHEDULE
PPTX
Time Management within IT Project Management
PPTX
Task management
PPT
Project time management
DOCX
Project schedule Management - PMP/CAPM
PPT
NCV 4 Project Management Hands-On Support Slide Show - Module 2
PPTX
Project Scheduling
PPT
Project time management
PPTX
Understanding Constraints and Relationships in Primavera P6 8.2
PPTX
Presintation on Project constraint
PPTX
Project milestone
PPTX
Project control wps office
PPTX
Inputs
Project Time Management
project time management
Software project management tools
Primavera Training P6
Mkcl Project Management Session 3
Benefits of implementing primavera p6 r8.1 and integration to oracle ppt
CPM/PERT and Gantt charts
PROJECT SCHEDULE
Time Management within IT Project Management
Task management
Project time management
Project schedule Management - PMP/CAPM
NCV 4 Project Management Hands-On Support Slide Show - Module 2
Project Scheduling
Project time management
Understanding Constraints and Relationships in Primavera P6 8.2
Presintation on Project constraint
Project milestone
Project control wps office
Inputs
Ad

Viewers also liked (17)

PPTX
5S Improvement
PPT
Mobicom (Mobitex) Presentation (1998)
DOCX
Maono ya bwana kuhusu kanisa la tanzania
PPT
Prryavzla man mdv
DOCX
Reem-Eses-CV-Draft 2 (003)
PDF
Meu Bairro Centro - Setembro
PDF
Programa fiestas de_julio_2015
PDF
Especial IFA
PDF
clyde m Seruelo project portfolio 2015
PDF
Final salary pension transfer - Time For A Re-Think
PDF
Costume Designer
PPTX
Steam
PDF
Adote Pet
PPTX
Audience Research
PDF
Delhi Metro Case Study
PDF
Eleições 2016 - 2 turno
5S Improvement
Mobicom (Mobitex) Presentation (1998)
Maono ya bwana kuhusu kanisa la tanzania
Prryavzla man mdv
Reem-Eses-CV-Draft 2 (003)
Meu Bairro Centro - Setembro
Programa fiestas de_julio_2015
Especial IFA
clyde m Seruelo project portfolio 2015
Final salary pension transfer - Time For A Re-Think
Costume Designer
Steam
Adote Pet
Audience Research
Delhi Metro Case Study
Eleições 2016 - 2 turno
Ad

Similar to The Softer Side of Scheduling (20)

PPTX
Presentation - Scope and Schedule Management of Business Analytics Project
PPT
Qimonda Pm Foils
PPT
Software Engineering (Project Scheduling)
PPT
lecture8-190719030939.ppthjtyuiytiytiyti
PPTX
Project-Management.pptx
DOCX
Project TimeIST4055Chapter 6Now that you have the Sc.docx
PPTX
Project Management.pptx
PPT
PMP Exam Prep - Time Management
PPT
How to build up a plan in Technical Drawing
DOCX
ESTIMATION techniques analogy advantages
PPT
Definition Of Project Management
PPTX
1587310189-week6.pptx
PPTX
Time management pressent
PPTX
SEN-22413 - UNIT - V.pptx
PPT
Project management
PPTX
4) PTM & PCM .pptx
PPT
SDPM (Success Driven Project Management)
PPTX
Project Scope Management.pptxUnderstand the importance of project schedules a...
PPTX
Project scheduling
PPT
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Presentation - Scope and Schedule Management of Business Analytics Project
Qimonda Pm Foils
Software Engineering (Project Scheduling)
lecture8-190719030939.ppthjtyuiytiytiyti
Project-Management.pptx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project Management.pptx
PMP Exam Prep - Time Management
How to build up a plan in Technical Drawing
ESTIMATION techniques analogy advantages
Definition Of Project Management
1587310189-week6.pptx
Time management pressent
SEN-22413 - UNIT - V.pptx
Project management
4) PTM & PCM .pptx
SDPM (Success Driven Project Management)
Project Scope Management.pptxUnderstand the importance of project schedules a...
Project scheduling
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...

The Softer Side of Scheduling

  • 1. { “The Softer Side of Scheduling” How simple, non electronic, collaborative efforts make for a more robust, accurate and better functioning project schedule. Sreedhar “Sree” Yedavalli, PMP Technical Project Manager Samsung-WorldLink Thursday, February 18, 2016, 5:01PM
  • 2. • Temporary - Defined Start and End dates • Unique deliverables (Product, service result)Project •Group of similar, but distinct, projectsProgram • Collection of programs and projectsPortfolio About Projects
  • 3. XYVEX Labs Products STM LITHOGRAPHY CONTROL SYSTEM Project 1 – New HDL Scripting Project 2 – Position Controls upgrade mechanism ZETCHER™ Project 1 – Software Customization - UTD Project 2 – Hardware Upgrade Services Project 1 – Stainless Steel metalworking for SY, Inc. Project 2 – At installation materials, Dallas Art Festival Research Grant#1 – DoE Nanite manipulation SBIR to DoD Application Portfolio List? Portfolio Programs & Projects Projects
  • 5. Work Breakdown Structure  WBS = Hierarchical decomposition of the TOTAL SCOPE OF WORK to be carried out for the project.  100% Rule = the WBS includes 100% of the work defined by the project scope and captures all deliverables – internal, external, interim – in terms of the work to be completed, including project management.  Key project deliverable that organizes the team's work into manageable sections  PMBOK & MIL-STD-881C
  • 6.  WBS Will help you organize  Personnel assignments  Activity List - Major and minor tasks  Material acquisition – when and how much  Asset allocation – the tools you need and when you need them. Why a WBS?
  • 7.  “The Group Hug”  All stakeholders, management and key personnel involved in the project  Representatives from consultants or vendors  One room, one day, all out free for all  (Example on Whiteboard) Who does the WBS?
  • 8.  Creates a hierarchy within the project.  Defines the “Project Manager”  Defines the “Project Sponsor”  Defines deliverables How WBS benefits you?
  • 10.  Complete – make sure that we do not forget anything (what we forget here will not be part of further project planning, and thus, can cause time delays and additional costs).  Free of contradictions – check if the WBS contains any work packages with contradicting or inconsistent specifications or descriptions (of pre-conditions, expected results, etc.), and revise accordingly.  Work packages on lowest level - clearly specifying responsibility, pre-conditions, expected results, necessary skill levels, special expertise, so that we have a reliable basis for estimation of effort and duration (minimum requirement: verb + object). Criteria of a WBS
  • 11.  "80 hour rule – no activity at the lowest level to produce a single deliverable, should be more than 80 hours of effort.  If the project team is reporting progress monthly, then no single activity or series of activities should be longer than one month long.  “Common sense" when creating the duration of a single activity or group of activities. Level of Detail
  • 12. Other Benefits to WBS & PM  Better project budgeting – complete projects in less time with less money  Predictability – reduce unknowns in project process  Control scope – reduce the risk of adding unnecessary scope to an ongoing project - “Scope Creep”.  Better solutions – planning with client or stakeholders leads to better outcomes that weren’t originally understood.  Resolve problems more quickly – stick to the plan!  Resolve future risk before problems start.  Better product, better service, better outcome.  Avoids “bad” projects  More metrics and fact based decision making  Improved work flow and work environment