Karan Singh Khokhar
1891054
MBA (3RD A)
PROJECT CONTROL
CONTENS
Project Control01
Progress control02
Performance Control
03
Schedule Control04
Cost Control
05
PROJECT CONTROL
• Control is one of the key functions of any management process.
The uncontrolled or unexamined project is not worth much.
However effective the project plan may be without regular
reviews during the life of the project neither the project progress
nor the reality of the plan can be assessed. An effective and
efficient control system enables! the project manager to answer
the question. "How are we doing on the project ?" at any stage
of the project.
• According to Henry Fayol "The control means seeing that
everything occurs in conformity with established rules and
expressed command."
CONT
• Project control is the process of monitoring evaluating and
compared planned results with actual results to determine the
progress toward the project cost, schedule and technical
performance objectives, as well as the projects strategic fit with
the objectives of the organisation.
• Project control consists of two things:
1. Establishment of controls
2. Controlling the ongoing activities using above controls
Project control wps office
CONT
• The four steps should follow each other till the work is
completed. Scope of project control includes the following
Progress Control
Performance Control
Schedule Control
Cost Control
PART 01
PROGRESS CONTROL
• The primary objective of project control is completion of work. A
project has to be completed 100%, no lapse in this regard is
acceptable. The basis for progress control should be the control of
the tasks which occur at the last level of the work breakdown
structure. Completion of tasks leads to completion of next higher
level of work and ultimately the whole project. By ensuring
completion of the tasks, the completion of project itself can be
ensured
• Various instruments of progress control are
1. Task lists
2. Progress measurement
3. Expediting and follow up
4. Overall project progress control
PART 02
PERFORMANCE CONTROL
• After progress control, the most haunting thought in the minds of
project authorities is whether the project will perform ?" Failure of the
project to meet the time and budget standards may be condoned,
but failure to perform can never be condoned.
• Performance control starts with identification of performance
parameters. Which performance parameters are critical for viability of
the project must be established in' clear terms. Various performance
parameters can be
1. Output certainty
2. Raw material and power consumption per unit of production etc.
PART 03
SCHEDULE CONTROL
• Scheduling and scheduling system have to form an separate part of
the project execution for exercise of schedule control. Schedule
control is to ensures when adherence to the agreed time schedule of
the project. This is however not an independent activity, Schedule
has to be used as a basis of direction, coordination, communication
and progress control or else there can be no schedule control
exercise of schedule control.
• There are certain species which are required:
1. Predictive Schedule Control
2. Preventive Schedule Control
3. Schedule Status/Reviews
PART 04
Cost control
• Cost control calls for answering the following questions:
1. Has the cost of the project as a whole and its individual parts
been as per budget estimates, less than the budget estimates
or more than budget estimates?
2. If there is a variation, where did it occur, why did it occur?
3. Who is responsible for the variation ?
4. What would be the implications of the variation ?
CONT
• Budgeted Cost for Work Schedule (BCWS
BCWS represents the total of three component
1. Budgets of all schedules to be completed
2. Budgets for the portion of in-process work scheduled to be
accomplished
3. Budgets for the overheads of the project
• Budgeted Cost for Work Performed (BCWP)
BCWP is the sum total of three components
1. Budgets for work packages already completed
2. Budgets applicable to completed work in process
3. Overhead budgets
CONT
• Actual Cost of Work Performed (ACWP)
ACWP represents the actual cost incurred for accomplishing the
work performed during a particular period of time
• Budgeted Cost for Total Work (BCTW)
• Additional Cost for Completion (ACC)
ACC represents the estimate for the additional cost required, if
any, for completing the project as:
CONT
1. Cost Variance : BCWP - ACWP
2. Shedule Variance : BCWP-BCWS
3. Cost performance Index : BCWP/ACWP
4. Schedule Performance Index: BCWP/BCWS
• Estimated Cost Performance Index: BCTW/ACWP+ACC
THANKS

More Related Content

PDF
Scheduling by using microsoft project 2013
PPT
Project control
PPTX
Project management life cycle
PPTX
project management
PPTX
Project management
PDF
Ms Project Workshop
PPTX
Project control & Monitoring
Scheduling by using microsoft project 2013
Project control
Project management life cycle
project management
Project management
Ms Project Workshop
Project control & Monitoring

What's hot (20)

PDF
Project governance
PPT
09. Project Cost Management
PPTX
Brief introduction to project management and project management tools
PPTX
Project management
PDF
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
PDF
Project Management Concepts
PPTX
10 project management knowledge areas
PDF
Project Management Steps And Process PowerPoint Presentation Slides
PPT
Project Planning Scheduling
PPTX
Primavera presentation
PDF
Project Execution PowerPoint Presentation Slides
PPT
Lecture 2
DOC
Project management chapter 1 notes
PDF
MS Project
PPS
Critical Chain Project Management
PPTX
Presintation on Project constraint
PPTX
Project Execution
PDF
EVM of Project Management...
PPTX
Ms project 2016 overview
Project governance
09. Project Cost Management
Brief introduction to project management and project management tools
Project management
Project Management Kickoff Meeting Template Powerpoint Presentation Slides
Project Management Concepts
10 project management knowledge areas
Project Management Steps And Process PowerPoint Presentation Slides
Project Planning Scheduling
Primavera presentation
Project Execution PowerPoint Presentation Slides
Lecture 2
Project management chapter 1 notes
MS Project
Critical Chain Project Management
Presintation on Project constraint
Project Execution
EVM of Project Management...
Ms project 2016 overview
Ad

Similar to Project control wps office (20)

PPTX
Project scope management
PPTX
MONITORING AND CONTROLLING -1.pptx
PPTX
D22MB040_Unit_6.pptx
PPTX
project review.pptx
PDF
MandC.pdf
PPTX
project review.pptx
PPTX
project review.pptx
PPT
Project management-professional-free-sample
PPTX
schedule Management v4
PPTX
Chapter 3 Project Cost Control and Monitoring.pptx
PPTX
Project Tracking & SPC
PPTX
Software project management, computer science
PPTX
CE168P-5 Lecture 9 Project Monitoring & Control.pptx
PPTX
3 how to scope a project to achieve the quality
PDF
09_quality_resource_mgt_eval_control.pdf
PPTX
Projectcontrol
PPT
Project management-professional-free-sample
PPTX
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
PDF
Scope management
PPT
Project Management Ch 14.ppt
Project scope management
MONITORING AND CONTROLLING -1.pptx
D22MB040_Unit_6.pptx
project review.pptx
MandC.pdf
project review.pptx
project review.pptx
Project management-professional-free-sample
schedule Management v4
Chapter 3 Project Cost Control and Monitoring.pptx
Project Tracking & SPC
Software project management, computer science
CE168P-5 Lecture 9 Project Monitoring & Control.pptx
3 how to scope a project to achieve the quality
09_quality_resource_mgt_eval_control.pdf
Projectcontrol
Project management-professional-free-sample
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
Scope management
Project Management Ch 14.ppt
Ad

Recently uploaded (20)

PDF
01-Introduction-to-Information-Management.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
Complications of Minimal Access Surgery at WLH
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
PDF
Business Ethics Teaching Materials for college
PDF
Microbial disease of the cardiovascular and lymphatic systems
PPTX
Cell Types and Its function , kingdom of life
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
Week 4 Term 3 Study Techniques revisited.pptx
PDF
Classroom Observation Tools for Teachers
PDF
RMMM.pdf make it easy to upload and study
PPTX
Pharma ospi slides which help in ospi learning
PDF
Pre independence Education in Inndia.pdf
PPTX
Cell Structure & Organelles in detailed.
01-Introduction-to-Information-Management.pdf
Final Presentation General Medicine 03-08-2024.pptx
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
Complications of Minimal Access Surgery at WLH
Abdominal Access Techniques with Prof. Dr. R K Mishra
The Healthy Child – Unit II | Child Health Nursing I | B.Sc Nursing 5th Semester
Business Ethics Teaching Materials for college
Microbial disease of the cardiovascular and lymphatic systems
Cell Types and Its function , kingdom of life
Renaissance Architecture: A Journey from Faith to Humanism
102 student loan defaulters named and shamed – Is someone you know on the list?
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Physiotherapy_for_Respiratory_and_Cardiac_Problems WEBBER.pdf
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Week 4 Term 3 Study Techniques revisited.pptx
Classroom Observation Tools for Teachers
RMMM.pdf make it easy to upload and study
Pharma ospi slides which help in ospi learning
Pre independence Education in Inndia.pdf
Cell Structure & Organelles in detailed.

Project control wps office

  • 1. Karan Singh Khokhar 1891054 MBA (3RD A) PROJECT CONTROL
  • 2. CONTENS Project Control01 Progress control02 Performance Control 03 Schedule Control04 Cost Control 05
  • 3. PROJECT CONTROL • Control is one of the key functions of any management process. The uncontrolled or unexamined project is not worth much. However effective the project plan may be without regular reviews during the life of the project neither the project progress nor the reality of the plan can be assessed. An effective and efficient control system enables! the project manager to answer the question. "How are we doing on the project ?" at any stage of the project. • According to Henry Fayol "The control means seeing that everything occurs in conformity with established rules and expressed command."
  • 4. CONT • Project control is the process of monitoring evaluating and compared planned results with actual results to determine the progress toward the project cost, schedule and technical performance objectives, as well as the projects strategic fit with the objectives of the organisation. • Project control consists of two things: 1. Establishment of controls 2. Controlling the ongoing activities using above controls
  • 6. CONT • The four steps should follow each other till the work is completed. Scope of project control includes the following Progress Control Performance Control Schedule Control Cost Control
  • 8. PROGRESS CONTROL • The primary objective of project control is completion of work. A project has to be completed 100%, no lapse in this regard is acceptable. The basis for progress control should be the control of the tasks which occur at the last level of the work breakdown structure. Completion of tasks leads to completion of next higher level of work and ultimately the whole project. By ensuring completion of the tasks, the completion of project itself can be ensured • Various instruments of progress control are 1. Task lists 2. Progress measurement 3. Expediting and follow up 4. Overall project progress control
  • 10. PERFORMANCE CONTROL • After progress control, the most haunting thought in the minds of project authorities is whether the project will perform ?" Failure of the project to meet the time and budget standards may be condoned, but failure to perform can never be condoned. • Performance control starts with identification of performance parameters. Which performance parameters are critical for viability of the project must be established in' clear terms. Various performance parameters can be 1. Output certainty 2. Raw material and power consumption per unit of production etc.
  • 12. SCHEDULE CONTROL • Scheduling and scheduling system have to form an separate part of the project execution for exercise of schedule control. Schedule control is to ensures when adherence to the agreed time schedule of the project. This is however not an independent activity, Schedule has to be used as a basis of direction, coordination, communication and progress control or else there can be no schedule control exercise of schedule control. • There are certain species which are required: 1. Predictive Schedule Control 2. Preventive Schedule Control 3. Schedule Status/Reviews
  • 14. Cost control • Cost control calls for answering the following questions: 1. Has the cost of the project as a whole and its individual parts been as per budget estimates, less than the budget estimates or more than budget estimates? 2. If there is a variation, where did it occur, why did it occur? 3. Who is responsible for the variation ? 4. What would be the implications of the variation ?
  • 15. CONT • Budgeted Cost for Work Schedule (BCWS BCWS represents the total of three component 1. Budgets of all schedules to be completed 2. Budgets for the portion of in-process work scheduled to be accomplished 3. Budgets for the overheads of the project • Budgeted Cost for Work Performed (BCWP) BCWP is the sum total of three components 1. Budgets for work packages already completed 2. Budgets applicable to completed work in process 3. Overhead budgets
  • 16. CONT • Actual Cost of Work Performed (ACWP) ACWP represents the actual cost incurred for accomplishing the work performed during a particular period of time • Budgeted Cost for Total Work (BCTW) • Additional Cost for Completion (ACC) ACC represents the estimate for the additional cost required, if any, for completing the project as:
  • 17. CONT 1. Cost Variance : BCWP - ACWP 2. Shedule Variance : BCWP-BCWS 3. Cost performance Index : BCWP/ACWP 4. Schedule Performance Index: BCWP/BCWS • Estimated Cost Performance Index: BCTW/ACWP+ACC