Evaluation of Immediate Impacts of Community
Physical Infrastructure (CPI) Projects under
Expanded Early Recovery Project (EERP)
Final Report June, 2013
Project funding by
Third party evaluation of SRSP programme (AusAid-EERP)
Evaluation of Immediate Impacts of Community
Physical Infrastructure (CPI) Projects under
Expanded Early Recovery Project (EERP)
Final Report June, 2013
Associates in Development (AiD) Pvt. Ltd, Pakistan
TABLE OF CONTENT
4
Executive Summary	 7
Conclusions and Recommendations	 13
1.	 Background and Context: Malakand Division and the EERP	 16
2.	 Objectives and Scope of Work	 17
3.	 Approach and Methodology	 18
3.1	 Stage 1 - Inception	 19
3.1.1	 Work Plan	19
3.1.2	 Tools	19
3.1.3	 Staffing	19
3.1.4	 QA Plan	 20
3.1.5	 Sampling	20
3.2	 Stage 2 – Field Work	 21
3.2.1	 Pre-testing and Finalization of tools	 21
3.2.2	 Field Activities	 22
3.2.3	 Challenges in the field	 22
3.3	 Stage 3	 22
3.3.1	 Data Entry, Analysis and report writing	 23
4.	 Findings:	24
4.1	 CPI documentation: Availability and Adequacy	 26
4.1.1	 Social Feasibility	 27
4.1.2	 Environmental Screening	 27
4.1.3	 Technical Feasibility:	 28
4.1.4	 Water Quality Test	 30
4.1.5	 Project Proposal	 30
4.1.6	 Project Approval	 30
4.1.7	 PI register	 30
4.1.8	 Project completion report	 31
4.1.9	 PI completion certificate	 31
4.1.10	 Handing and taking over certificate:	 31
4.2	 Design Validation	 32
4.2.1	 Scheme Layouts:	 32
4.2.2	 Design Validation:	 32
4.2.3	 The following is a type wise breakdown of the CPIs:	 33
4.3	 Relevance	34
4.3.1	 Priority	34
4.3.2	Participation	 34
4.3.3	 Community Contribution	 35
4.4	Effectiveness	 37
4.4.1	Functionality:	 37
4.4.2	 Benefits	39
4.4.3	 Problems	41
4.5	 Efficiency:	42
4.6	Sustainability	42
4.6.1	 Design and layout.	 42
4.6.2	 Quality	44
4.6.3	 O&M systems	 45
4.6.4	 Institutional Maturity	48
4.6.5	 Meetings	48
4.6.6	 Trainings	49
4.6.7	 Self-initiated community projects	 50
4.7	 Impact	52
4.7.1	 Overall impact analysis	 52
4.7.2	 Drinking Water Supply - CPI Scheme Impact	 53
4.7.3	 Street pavements and drainage	 55
4.7.4	 Link roads and bridges	 56
4.7.5	 Irrigation	57
4.8	 Conclusions and Recommendations	 58
LIST OF ABBREVIATIONS
5
AiD	 Associates in Development
AusAID	 the Australian Agency for International Development
CBR	 California Bearing Ratio Test
CO	 Community Organization
CPI	 Community Physical Infrastructure
DWSS	 Drinking Water Supply Scheme
ERP	 Early Recovery Programme
ER	 Environmental Review
EERP	 Expanded Early Recovery Programme
ES	 Environmental Screening
FGD	 Focus Group Discussion
GF	 Gravity Flow
GoKP	 Government of Khyber Pakhtunkhwa
GPS	 Global Positioning System
HH	Household
HO	 Head Office
IRR 	 Irrigation
KII	 Key Informant interviews
KP	 Khyber Pakhtunkhwa
MH/MHP/MHPP	 Micro Hydel / Micro Hydel Power / Micro Hydel Power Plant
MTDF	 Medium Term Development Framework
NGO	 Non-Governmental Organization
O&M	 Operations & Maintenance
PCC	 Plain Cement Concrete
PCNA	 Post-Crisis Needs Assessment
PCR	 Project Completion Report
PI	 Physical Infrastructure
QA	 Quality Assurance
RCC	 Reinforced Cement Concrete
SPD	 Street Pavement and Drainage
SRSP	 Sarhad Rural Support Programme
TOP	 Terms of Partnership
6
Line of Contro
l
Kasur
Thal
Tank
Bannu
Kotli
Punch
Saidu
Daggar
Gardez
Gujrat
Gilgit
Mardan
Peshawar
Chilas
Tithwal
Bhimbar
Faizabad
AsadabadCharikar
Sargodha
Mehtarlam
Jalalabad
Parachinar
Rawalpindi
Faisalabad
Jhang
Sadar
Muzaffarabad
Mahmud-e
Raqi
Dera Ismail Khan
Kabul
Islamabad
Zhob
Chenab
Ravi
Mangla
reservoir
Jhelum
Kunar
Kunar
Indus
Gilgit
Shunjigol
Zhob
Gumal
Amu darya
Indus
Gumal
Chitralr
iver
Indus
!Î
!Î
Chitral
Swat
Kohistan
Mansehra
Upper Dir
Shangla
Abbottabad
Batagram
Mohmand
Agency
Bajaur Agency
D.I. Khan
Kohat
Karak
Tank
Lakki Marwat
South Waziristan
Agency
Hangu
Kurram
Agency
Bannu
North Waziristan
Agency
Buner
Swabi
Haripur
Mardan
Nowshera
Peshawar
Malakand Pa
Tribal
Area
Adjacent
D.I. Khan
Tribal Area
Adjacent
Tank
Tribal Area
Adjacent
Bannu
Tribal Area
Adj. Kohat
Tribal Area
Adj. Peshawar
Tribal Area
Adj. Lakki
Marwat
Lower
Dir
Khyber Agency
Chitral
Swat
Kohistan
Mansehra
Upper Dir
ShanglaLower
Dir
Abbottabad
Batagram
Mohmand
Agency
Bajaur Agency
D.I. Khan
Kohat
Karak
Tank
Lakki Marwat
South Waziristan
Agency
Hangu
Kurram
Agency
Bannu
North Waziristan
Agency
rakzai
Agency
rakzai
Agency
Tribal
Area
Adjacent
D.I. Khan
Tribal Area
Adjacent
Tank
Tribal Area
Adjacent
Bannu
Tribal Area
Adj. Kohat
Tribal Area
Adj. Peshawar
Tribal Area
Adj. Lakki
Marwat
Buner
Swabi
Haripur
Mardan
Nowshera
Peshawar
Charsadda
KPK
PUNJAB
FATA
FANA
AJK
BALOCHISTAN
ISLAMABAD
KPK
PUNJAB
FATA
FANA
AJK
BALOCHISTAN
ISLAMABAD
Mingora
Sadda
Kohat
Gujranwala
Jamrud
Ghalanai
Attock
AFG A IS TA
PAKISTA
TAJIKISTA
I DI A
Location map of the expanded early recovery project area
(Pl see annex 9 for details district wise maps)
7
Background and Context
The 2010 floods affected large parts of Khyber Pakhtunkhwa.
Nearly 1,500 people lost their lives and 37,000 homes
were destroyed. Malakand Division was one of the worst
affected areas. During this period, AusAid funded Sarhad
Rural Support program (SRSP) for ‘an initial Early Recovery
Programme designed to target the flood affected districts
of Peshawar, Nowshera and Charsadda. However, based
on the PCNA1
findings and priorities identified for early
recovery, SRSP submitted a revised proposal to AusAid for
an Expanded Early Recovery Programme (EERP) that would
focus on reconstruction in the entire Malakand Division2
.
In 2011, AusAid earmarked AUS$ 3 million (PKR 255 million)
for EERP that aimed to re-build communities in areas hit by
floods and insurgency in Malakand Division3
. Focused on
immediate recovery and rehabilitation needs, the program
called for completing all identified targets within a nine
month period.
The challenging environment in Malakand was not new to
SRSP, which had been working in the project area since 2001.
As part of its development approach SRSP typically ensures
a long term engagement with the local communities and
maintains a presence even after the project implementation
comes to an end. This has enabled the organization to
continue supporting the capacity building and networking
needs of communities and also retain a knowledge base
of the area and its people. With this structure in place SRSP
has the potential to ensure sustainability by leveraging
additional resources for the communities, as and when the
opportunities arise.
The project area covered 191 villages (75 union councils) of
7 districts in the Malakand Division. The targeted districts
include, Chitral, Upper and Lower Dir, Swat, Buner, Malakand
Agency and Shangla The programme had 5 components
including Community Institutions and Networking,
Rebuilding Community Physical Infrastructure Improved
Livelihoods - through micro Enterprise, and through NRM-
based enterprises and Support to the local government.
Under its component on community institutions, the project
organized nearly 400 local community-based organizations.
The target group included people hit by insurgency and
floods, particularly the poor and marginalized, comprising
nearly 74,000 households.
The Community Infrastructure was the most visible and the
largest component of the project and consumed 93% of the
programme development budget. Specific interventions
included the restoration of community enabling
infrastructure, predominantly in the drinking water sector
but also link roads, micro hydro electricity projects, protective
works, bridges and sanitation projects. Approximately,
37,507 households gained access to clean drinking water
and improved services through rehabilitation/construction
of community-based physical infrastructure schemes. The
project also included enterprise and vocational training for
vulnerable groups particularly women. Over 700 households
were also provided access to improved livelihood
opportunities.
Scope of Work
The scope involved the assessment of 213 schemes
implemented by SRSP across the entire Malakand Division.
The objective of the study was the verification and validation
of the CPI schemes and an assessment of the relevance,
effectiveness, efficiency and immediate impact on the lives
of the local communities.
The geographic spread included all 7 districts of Malakand
division including Buner, Chitral, Lower Dir, Malakand,
Shangla, Swat and Upper Dir.
Approach and Methodology
The primary focus of the study was two pronged; an
engineering assessment and a structured community survey.
The engineering assessment focused on: i) an assessment
of the availability and adequacy of the various engineering
documentation required for the implementation of the
schemes; and ii) a physical verification of the schemes’
existence and the state of their functionality. The community
survey included: iii) a Household interviews and Focus
Group Discussions (FGDs) held with a sample of the direct
and indirect beneficiaries. . The survey, sample covered 60
schemes out of the total of 213 that were randomly selected
(proportional to the type and geographic spread of the
schemes in the districts covered). The sample size represents
a confidence Level of 93 % with less than 10% margin of error.
The study commenced in mid-February 20134
and was
completed by mid June 2013. Led by a an experienced team
leader, multiple field teams assisted with the assessment
to ensure timely completion of the full scope spread over
vast and a challenging terrain. Each team comprised a field
supervisor and two researchers. In addition, a short-term
advisor, a senior engineer, and short-term inputs from a
Social Sector/Gender Specialist, and Data Analyst were
tapped during implementation.
A variety of assessment tools helped generate the
quantitative and qualitative analysis that provided the basis
for this report.
Findings
The following sections summarize the key findings:
1.1 Documentation: Availability and Adequacy:
Except for a small number of CPIs, documentation showing
compliance with the SRSP processes such as social feasibility,
Terms of partnership (TOP), project completion reports
(PCRs), certificate of completion and handover documents
to the community were available and found to be adequate.
However the engineering design basis and calculations were
unavailableorinadequateforbulkofsampleCPIs,particularly
for the road infrastructure CPIs.
1.2 Design validation:
All the 60 schemes were visited and checked for variations
EXECUTIVE SUMMARY
1	 Post Conflict Needs Assessment: A multi-donor initiative.
2	 Livelihood Strengthening Programme - Expanded Early Recovery Project in Border Areas of Khyber Pakhtunkhwa (Malakand Division) – SRSP, April 2011
3	 Expanded Early Recovery Project (Livelihood Strengthening Programme) Project Completion Report - SRSP
4	 See Annex 7
8
in relation to the original plans and designs. The layout of 9
schemes had significant variations while the rest had minor
or no variations. The significant variations in layout were for
DWSS. They either had to do with lengths of pipe network
or the variations in the location/number of storage or supply
water tanks from what was originally planned.
Furthermore, the measurement of the structures showed
major variations for 12 schemes, whereas 21 schemes had
relatively minor variations.
Although a detailed investigation was not made on the
rationale for the change, however, it was reported that the
change was necessitated by site conditions.
1.3 Relevance
Relevance refers to whether or not the selected schemes
respondedtotheneedsandprioritiesofthetargetcommunity.
A number of indicators covered this important assessment
parameter and aimed at assessing the prioritization of the
CPI schemes; participation in planning and implementation;
and the community contributions towards the schemes.
1.3.1 CPI Prioritization
An overwhelming majority, (98 percent of all male
and females surveyed in all districts, except Lower Dir,
indicated that the schemes implemented under the EERP
addressed the priority needs of the communities.
1.3.2 Participation
The majority of respondents reported their own or
the household’s participation in the planning and
implementation of the CPIs. The highest participation in
planningandneedsassessmentofCPIschemeswasinthe
district of Chitral (100 %) and the least in Shangla where
it was 67 %. Given the social norms of the area it came
as no surprise that participation of females was found
to be low, however 32 % females indicated that they
or another female from their household did participate
in the needs assessment. Overall participation in the
implementation was reported as 82 %. Again the highest
level of participation was reported from Chitral and the
lowest in Shangla.
	 1.3.3 Community Contribution
Community contribution is an important indicator
of ownership. Nearly 77 percent of the respondents
(75 percent females; and 79 percent males) claimed
to have made contributions in cash and/or in kind
to the construction of CPI schemes, while the rest of
the 23 percent did not contribute. Relatively higher
contributions were made in Chitral, Upper Dir and Buner
(100, 92 and 83 percent, respectively). Interestingly, 77
percent of respondents which were non CO members
also contributed towards construction. Of the total
households that contributed, 17 percent contributed
in cash. The highest frequency of cash contributions
(30 percent) was witnessed in Shangla. 70 percent of
the contributions were in the form of labor whereas 20
percent contributed additional items in kind.
1.4 Effectiveness
EffectivenessreferstowhethertheCPIschemesarepractically
meeting the need for which they were designed and built.
Accordingly the indicators against which effectiveness has
been gauged are functionality and recurring benefits of the
CPI schemes. Except for an odd few cases, all the schemes
were found to be functioning well and providing the
anticipated benefit to their respective communities.
1.4.1 Functionality
From the community perspective, approximately
91 percent of the respondents across the 7 districts
acknowledged that the CPI schemes were working and
functional. Across the respondents, 86 % of the female
respondents believed that the schemes were 100 percent
functional, as compared to the more cautious replies of
male respondents, 61 % of whom felt that the schemes
were 100 % effectively working. FGD analysis supported
the overall satisfactory responses from majority of the
male and female participants.
Functionality on the ground was also verified by the field
engineers. Out of the total sample of 60 schemes, the
field engineers were able to inspect and verify that 52
schemes were fully functional.
Of the remaining 8 CPIs, 4 schemes were not operational
at the time of the visit. These schemes included
the MHPP scheme in Shao Kalam, district Swat, and
Khanabad, district Upper Dir; both of them had technical
breakdown and were in the process of being repaired
by the communities. Whereas, the Irrigation Channel in
Meragai Swat was not operational, since it was not an
irrigation season, whereas in the case of DWSS Dardyal,
Kabal Swat, the intake structure had been damaged due
to a snow slide and the communities were waiting for the
snow to melt before attempting any repairs.
The remaining 3 schemes namely Drainage CPI, Bazkhel,
DWSS Sher Khan, and Link Road Gujjer Tangi, were
partially functional. A major reason for this seemed to
be lack of an effective O&M system for these CPIs.
1.4.2 Scheme Benefits
Overall 90 percent of respondents claimed to be directly
benefitting from the CPI schemes. A relatively higher
percentageofpeople(100,97and80percent)werefound
to be benefiting from the CPI schemes in Shangla, Lower
Dir and Chitral, reinforcing the communities’ high levels
of participation in planning, implementation and cash
contribution in these 3 particular districts. Furthermore,
the schemes were benefiting members and nonmembers
alike as nearly 88 % of the non-members interviewed also
confirmed that they were directly benefitting.
1.5 Efficiency:
Bulks of the CPIs were implemented within the planned
budgets and time of completion. The review shows that
95% of the schemes were completed within the planned
timeframewhile87%ofthesampleschemeswerecompleted
within the estimated budgets. A relatively modest 7% of the
schemes exceeded the approved budget by 10% while 6%
of the scheme sample was completed under the estimated
budgets. It is noteworthy that in the case of budget overrun
it was the community which invariably contributed to meet
the shortfall.
Although hard comparative data is not available for similar
sized schemes which the GoKP or other organizations have
implemented, there is anecdotal evidence that cost per
beneficiary in the case of SRSP CPIs is relatively low. One
reason is community contributions which on average is at
least 20 % of the total cost of schemes
9
1.6 Sustainability
Sustainability of the schemes refers to whether i) the
schemes will fulfill its design life and ii) whether or not
communities will continue to maintain the systems
independent of any support from SRSP.The indicators for this
assessment parameter included quality of the CPI schemes;
and the Operations & Management (O&M) systems put in
place (including transparency), and the overall institutional
maturity of the community organization.
1.6.1	Quality
Despite the rough and remote mountain terrain, the
quality of schemes of the majority of schemes was
found to be good. Community perception in this regard
corroborated the engineering team’s findings. The focus
group discussions indicated that more than 91 percent of
the respondents were satisfied with the current condition
of the CPI schemes, out of these 87 % were non members.
In Buner, Chitral and Malakand Agency, nearly 100 % of
the male respondents showed satisfaction; while 86 to 97
% of the females indicated satisfaction with the quality
of work. Out of the 9 schemes which had quality issues,
most indicated quality of concrete in the PCC link roads
as an issue.
1.6.2	O&M systems
Knowledge of any O&M system was generally low. Almost
48 % of the respondents were not aware of any O&M
system. Of these 24 % were male and 79 % were female
respondents. Approximately 39 percent of respondents
claimed to have made contributions to O&M. The largest
contribution was in irrigation schemes (55 percent); and
‘others’ (77 percent). Of the contributors, 52 percent
were CO members, and 49 percent non-CO members.
Respondents acknowledged awareness that most of the
maintenance funds were being run through SRSP and
then CO bank accounts. The FGD analysis reflects that
about half the male respondents claimed to be satisfied
with the O&M system, however less than a quarter of
the females showed satisfaction with O&M.. Majority of
female respondents were unaware of any O&M system.
For the engineering team, verification of O&M involved
observation of how well the CPIs were being maintained
and discussed the functioning of the O&M committees.
It was reported that O&M committees for half the CPI
schemes were found fully functional; whereas it was
observed that O&M existed and functioned partially at 27
percent of the sites; while 24 percent cases there was no
functional system for O&M. From the engineering view
point a total of 14 schemes were not well maintained.
1.6.3	Institutional Maturity
Another indicator of ‘Sustainability’ is Institutional
Maturity, which assesses the capacity of the communities
to independently run the CPI schemes in the longer-run.
Indicators for this assessment are complex and tricky.
However some of these were captured during the field
survey. Among these include; Community meetings
during- and post-implementation of CPI schemes;
trainings of community of members; and community’s
local initiative.
1.6.3.1 Meetings
While 70 % of the respondents said that they met
either fortnightly or monthly before CPI completion,
only 12 % meet on a regular basis once the CPI was
completed. Most of the respondents however said
that they continue to meet on need basis.
1.6.3.2 Trainings
Nearly half the respondents, 46 % said that someone
from the community has been given trainings with
the lowest proportion in Dir and highest being
reported from Malakand. Most of these trainings
were in leadership and financial management, but
14% were on O&M, related which were all given to
the males of the community.
1.6.3.3 Self-initiated community projects
17 % of respondents indicated that they had
imitated other projects besides the CPI which was
assisted by SRSP. Of these, 67 % respondents were
CO members whereas, 33 were non-CO members.
Furthermore, the new indicatives by CO members
were predominantly donor assisted as compared
to the once implemented by the non CO members,
showing a greater capacity to network and leverage
external funds for local development.
Linking the above analysis to the subject of community’s
ability to self initiate projects and/or run existing schemes
independently, majority of the FGD responses endorsed the
confidence of the male and female participants claiming
that the CPI schemes could very well continue to run in
the absence of support from SRSP. However, scheme-wise
response from FGD participants believed that irrigation and
drinking water supply schemes respectively could not run
solely by the communities.
1.7 Immediate Impact
Overall the community felt a significant positive impact of
the schemes.
For the irrigation schemes include enhanced yields,
crop production and increase in overall farm incomes.
Construction of street pavements and drainage, and
implementation of improved drinking water supplies led
to a decrease in foul smells and a perception of decreased
waterborne diseases. With the construction of link roads and
bridges, approximately 68 percent of respondents across all
7 districts acknowledged a positive impact on women’s free
time, enabling them to manage their daily activities more
efficiently and productively. Some indirect benefits include
a significant positive impact on girls’ and boys’ education
reported by all respondents across all 7 districts, post
implementation of the various CPI schemes. More specifically,
this was in terms of greater access/lesser distances due to
the construction of link roads and bridges, etc. However,
the main immediate outcomes, as a direct result of the CPI
schemes are as follows:
1.7.1	 Drinking Water Supply - CPI Scheme Impact
Post implementation, the average time taken to reach the
water source decreased drastically, allowing community
members, particularly females, to allocate their time
more efficiently to other important daily tasks. The result
findings indicate that the responsibility of collecting
water is now being shared most often by the daughters
(21 percent), allowing the mothers to utilize their time
more efficiently. Satisfaction levels with the new DWS CPI
schemes were 100 percent for males and 97 percent for
females, implying lower risks of waterborne diseases.
10
1.7.2	 Street pavements and drainage
Majority of the respondents (92 percent) in the 3 districts
where the scheme was implemented, Malakand Agency,
Shangla and Swat agreed that post implementation
of the CPI; the issue of stagnant water in the streets
had either been completely or partially eliminated.
Additionally, post-SPD CPI, in Shangla and Swat, 75
and 93 percent respondents, respectively claimed high
incidences of reduction in foul smell, while only 50
percent respondents reported the same in Malakand
Agency. However, majority of the respondents from
Shangla (approximately 62 percent) are still claiming
that waste water is not disposed properly even after
implementation of the scheme. Post implementation of
the CPI scheme, nearly 50 percent of the respondents
in both Malakand Agency and Shangla perceived an
improvement and positive effect on the health of the
children as a result.
1.7.3	 Link roads and bridges
The new link roads and bridges/communication
infrastructure has remarkably decreased the average
timetakenforcommunityresidentstoavailessentialdaily
requirements including distances to the nearest drinking
water supply; grocery stores; girls’ and boys’ schools;
hospital; and the nearest local Tehsil administration. In
Malakand Agency, 3 percent respondents claimed to
not use it all. Of these 3 percent respondents, 33 percent
stated the reason that the new infrastructure was of
no use to them. The 8 percent respondents in Swat,
who claimed the same, all reported ‘poor quality’ as the
reason. In terms of overall traveling cost, it decreased by
25 percent for all respondents in Lower Dir and between
25 to 75 percent across all districts at varying levels.There
was an overall 75 percent decrease in the cost of freight
transport across all districts except Buner, where no
change was reported.
1.7.4	Irrigation
The household surveys show that there was a remarkable
increase in crop production. While 100 percent
respondents reported a 50 percent increase in wheat
production; between 50 to 80 percent reported a 100
percent increase in rice and grain production. Production
of maize also increased considerably. In vegetables, 100
percent increase in production of onions, tomatoes,
okra and garlic was also reported by all respondents.
With regards to the overall impact on farm income, 100
percent respondents reported a minimum of 50 percent
increase.
11
In view of the early recovery context and the difficult
terrain, SRSP’s outreach and successful conclusion of this
challenging project is commendable. The schemes have
been implemented in areas where the government had
limited outreach and other non-governmental players had no
presence. Working in the target areas meant many hours of
driving and trekking through often rugged and mountainous
terrain. Despite these difficulties, the overall quality of work
is of good standards. All project outputs were also achieved
within the agreed timelines. Thanks to a motivated team,
nearly 400 community organizations were formed, local
priorities identified and over 200 CPIs implemented within a
short span of 9 months.
•	 Overall the communities have reported a  very  positive
impact of the CPI program.
•	 Post   implementation of the DWSS, the average
time taken to reach the water source decreased
significantly, allowing community members,
particularly females, to allocate their time more
efficiently to other important daily tasks. Satisfaction
levels with the new DWS CPI schemes were 100
percent for males and 97 percent for females, also,
implying lower risks of waterborne diseases.
•	 In case of Sanitation and drainage CPIs, the majority
of the respondents (92%) in the 3 districts where
the scheme was implemented noted that the issue
of stagnant water in the streets had either been
completely or partially eliminated. Additionally, 75 and
93% respondents in Shangla and Swat, respectively
claimed reduction in foul smell, while 50 percent
respondents reported the same in Malakand Agency.
•	 The new link roads and bridges has remarkably
decreased the average time taken for community
residents to avail essential daily requirements; travel
tothenearestdrinkingwatersupplyschemes; grocery
stores; girls’ and boys’ schools; hospital; and the
nearest local Tehsil administration. The respondents
reported an overall 75 percent decrease in the cost
of freight transport across all districts except Buner,
where no change was reported.
•	 The survey also shows  considerable increase in crop
production due to the implementation of irrigation
schemes.Nearlyallrespondentsreporteda50percent
increase in wheat production; while between 50 to 80
percent reported a 100 percent increase in rice and
grain production. With regards to the overall impact
on farm income, 100 percent respondents reported a
minimum of 50 percent increase.
•	 Combined capacity of the 3 MHPs in Chitral, Swat and
Upper Dir has the designed capacity of 225 KW, which
will benefit approximately 600 HH. The MHP in Chitral
has been functioning at full capacity and is not only
supplying electricity to the communal HH’s, but also
to a local hotel, Bashalini(Menstruation/Maternity
Home), Jasthakhan (Funeral Dance Hall), a school and
also mosque.
CONCLUSIONS AND RECOMMENDATIONS
•	 All 60 schemes in the evaluation sample were physically
verified to be on the ground. Except for one scheme
all the rest have been identified by the local community
as fulfilling their priority need. Given the tight time lines
and the difficult terrain, this is a remarkable achievement
•	 Project documentation has been meticulously kept
in the regional office, showing detailed record of
community interaction and the field processes from
the ‘first dialogue’ to the handing of checks in the 3rd
dialogues and the subsequent installments. However
the technical documentation covering the design basis,
design calculations and the environmental assessment
remains a weak area. .
•	 The CPIs are predominantly functional , and have a
positive impact on the communities; however some
of these ( about 10 % ) are not delivering the required
benefits due to poor quality and/or weak O&M systems.
•	 A   majority of females in the sample confirmed that
the CPIs chosen represented their priority needs and
directly benefiting them. However CPI implementation
remained a predominantly male affair. Out of the 64
WCO which were formed, a total of 4 CPIs were for the
women organization, which is disproportionally low.
•	 Although CPIs such as DWSS  or sanitation and drainage
were being implemented there was little attempt to
build the capacity of the organizations on related issues
such as health and hygiene.
•	 SRSP’s presence in the project areas was a significant
factor in the rapid response and timely completion
of the project activities. Interviews with senior SRSP
managers suggest a continued interest in the region
and a commitment to maintain the needed support for
post project support through existing resources.
•	 CPIs are highly visible, ensure immediate benefits to
the community and also typically consume the largest
chunk of development budgets in any community
program. Accordingly these should receive a higher
level of attention from the feasibility through design,
implementation as well as the O&M. The survey shows
a generally good performance on the “implementation
fronts” however the design and O&M phases could
benefit from further attention. Among other areas of
focus the CPIs are generally small in scope, however a
rapid “environmentalscreeningandmitigation”protocol
could help some categories of schemes. Overall the
team recommends additional investments in staff skills
for field surveys and design; use of design standards
and guidelines and customized training modules for
O&M practices. This will allow SRSP to further build on
its current success and ensure that the CPIs continue
to yield long term dividends without the need for any
hand holding or follow up repairs in project areas that
are generally remote and difficult to access.
12
MALAKAND DIVISION AND THE EERP
The floods that affected large parts of Khyber Pakhtunkhwa
in 2010 only compounded the issues being faced by the
population; almost 1,500 people lost their lives and 37,000
homes were destroyed. Malakand Division was one of the
worst affected areas; the region had not yet recovered from
fundamentalist insurgency and the subsequent military
intervention that took place in 2009 and displaced over 2
million people5
.
AusAid development aid to Pakistan has burgeoned over
the last four to five years. In 2001-2002, AusAid donated an
estimated $4.5 million to Pakistan with the focus on increased
access to basic education for girls and better management
of the environment6
. In contrast, in 2010-11, assistance to
Pakistan soared to $67.5million, with a major chunk of the
budget being directed towards humanitarian assistance
and reconstruction7
. An initial Early Recovery Programme
was designed to target the flood affected districts of
Peshawar, Nowshera and Charsadda. Once the activities and
interventions for the three districts had been implemented,
SRSP, keeping in view the Pakistan governments plans for the
province, out lined in the PCNA, MTDF and Early Recovery
Priorities in KP, submitted a proposal to AusAid for the
Expanded Early Recovery Programme (EERP) which would
focus on reconstruction in Malakand Division8
.
In 2011, AusAid, as part of its mandate for reconstruction
of the Malakand region, earmarked AUS$ 3 million (PKR
255 million) for the Expanded Early Recovery Programme
(EERP). EERP is a nine month long initiative by Aus-AiD, in
collaboration with SRSP, whose overall objective is to “build
resilient communities in areas hit by floods and insurgency
in Malakand Division9
” . This objective was to be achieved
using a multi- pronged approach with the restoration of
Community Physical Infrastructure being a central focus of
the project, accounting for 93% of the financial outlay.
The challenging environment suited SRSP, which had been
working in the project area since 2001, with a long term
community based approach. Typically for SRSP, a basic
skeleton structure of the organization remains in the area
to interact with communities even after the project it
implements comes to an end. This Core enables SRSP to
continue to support the capacity building and networking of
communities and also retain a knowledge base of the area
and its people; with this structure in place SRSP leverages
additionalresourcesforthecommunitieswhenopportunities
arise. This is particularly important from sustainability point
of view, comparing it to other imitative which have a short
terms‘project specific’approach.
The overall impact of initiatives carried out under EERP is
significant; 74,385 men and women, representing individuals
from the 191 poorest and most vulnerable districts of
Malakand Division10
have benefitted from the programme.
The selection of schemes was to be carried out using the
platform of 395 community based organizations or COs.
The CO platform was chosen in order to make the process
a participatory and transparent one. The CO members were
to be trained and their capacities built in a bid to enable
them to organize themselves, voice their concerns and needs
collectively, and most importantly take collective ownership
of their schemes to achieve long term sustainability. The 395
CO’s formed for this purpose worked towards reconstructing/
rehabilitating 213 CPI schemes which were to benefit a
targeted 37,000 households.
The entire process, from the formation of the COs, to selection
of schemes, through to the implementation and eventual
handover of the schemes to communities was to be carried
out within the mandated timeframe of nine months, from
May 2011 to January 2012.
5	 Malakand Comprehensive Stabilization and Socio-Economic Development Strategy – GoNWFP, 2009
6	 Aid budget summary 2001-02http://www.ausaid.gov.au/Budgets/Pages/default.aspx
7	 Australia’s International Development Assistance Budget, 2010
8	 Livelihood Strengthening Programme - Expanded Early Recovery Project in Border Areas of Khyber Pakhtunkhwa (Malakand Division) – SRSP, April 2011
9	 Expanded Early Recovery Project (Livelihood Strengthening Programme) Project Completion Report - SRSP
10	ibid
13
SCOPE OF WORK
Associates in Development Pvt. Ltd. was contracted to carry
out an evaluation of the Community Physical Infrastructure
(CPI) Projects in order to establish the immediate impacts of
the schemes and validation of design and planned outcomes.
The scope of work is the evaluation of the 213 Community
Physical Infrastructure (CPI) projects implemented by
communities with SRSPs assistance under the EERP. The
majority of them, 40 % were built in Swat, followed by
Shangla, Lower dir and Malakand which had 12 %, and lastly,
Buner, Upper Dir and Chitral which had 5 % of the total11
.
Most of these schemes were to assist communities in
the provision of DWSS, followed by Road Infrastructure,
Sanitation, Bridges, Irrigation Schemes, and Micro Hydel.
There is an odd one CPI of a rehabilitation of a sports facility
as well.
Schemes range in costs from Rs 110,000 for a Hand pump
in Buner to Rs 8, 600,000, average cost of the different type
of schemes range from Rs 5.8 million for Bridges, to Rs 0.7
million for DWSS12
. Cost per beneficiary is most favorable
in the case of irrigation CPIs. At Rs 1977 per HH benefited,
where 4 irrigation related schemes are benefiting 463
beneficiaries as compared to soil conservation works where
2 schemes costing more that Rs 7 mill with an average cost of
Rs 23,675 per beneficiary.13
At the individual scheme level, the aim was to assess; i) the
Relevance of the CPI to the intended beneficiaries’ needs; ii)
the Efficiency with which the schemes were implemented,
in terms of costs and time; iii) assessment of the scheme
Effectiveness; iv) the direct and indirect Impacts of the
scheme and’ v) the Sustainability of the scheme14
. These
criterions were used to judge whether or not the expected
outcomes envisaged in the projects proposal/financing
agreement are being realized by the community built and
maintained infrastructure schemes.
11	 See Annex 2 CPI Distributions
12	 See Annex 2 CPI Distributions
13	 See Annex 2 CPI Distributions
14	 See Appendix 4 - Evaluation Matrix
14
3.	 APPROACH AND METHODOLOGY
The approach and methodology of the study revolved around the physical verification of the technical information and obtaining
a firsthand account of how the beneficiaries viewed this initiative.
The activities were divided into a three staged approach outlined below:
Stage1wastheinceptionphasewhichlastedfromthe8thAprilto17thApril2013.Thistimewasusedtodevelopanunderstanding
of the programme, review all relevant documentation and secondary data and to finalize the tools used in the field and the teams’
work plan. This stage culminated with the submission of the Inception.
Stage 2 was the Field research phase during which the teams were mobilized and they completed data collection in the targeted
villages. Key Informant interviews with Project staff, community members and other stakeholders, the household survey,
engineering field reports and FGDs were all conducted during this phase.
The final stage of the process, Stage 3, involved the entry and analysis of all the data collected and the preparation of the Final
Report. A draft of the Final Report is to be shared with SRSP, and the comments made by the client, if any, are to be incorporated
before the Report is handed over and the findings are presented.
3.1 Stage 1 - Inception
3.1.1 Work Plan
The field work was spread over 7 districts where drive time
over rugged mountain roads could take over 5 hours. The
entire evaluation was to be completed within a tight deadline
and the work plans for the teams were designed accordingly.
Initial work plans were submitted to SRSP along with the
original Technical Proposal and Inception report. These plans
had to be modified due to a number of factors, most crucially
due to the difficulty in finding female researchers willing and
able to work in the project areas. A final version of the work
plan was drafted near the close of the inception phase15
.
3.1.2 Tools
At this stage it was decided that the engineering focus
would be on i) a preliminary desk review which studies
the availability and adequacy of the documentation on
design estimation and the documentation on approvals of
the completion process. The data from the desk review has
been reported in the form of the “Desk Review Report”. ii)
The engineering team was to carry out extensive site visits
during which they would physically validate the design and
outcomes of the individual CPI schemes. Additionally, they
Inception/Desk review Field work Data analysis and report writing
•Understandstatedand
unstatedexpectationsofSRSP
•Reviewrelevantproject
documentsandreports
•Designchecklists,templates,
finalizedatagathering
instrumentsanddetailedwork
plan
•Submissionofinceptionreport
•DatacollectionfromtargetUCs
•Meetingswithandrelevant
stakeholdersandreviewof
recordsoffacilities
•IDIs&FocusGroupDiscussions
withwithProjectstaff,
communitymembersandother
stakeholders
•RecordFieldObservations
•Dataentryandanalysis
•Presentationtotheclienton
keyfindings
•PrepareDraftreportforsharing
withtheclient
•IncorporateFeedbackand
submitFinalreport
would verify the O&M systems and their effectiveness.
In addition, the tools for the social sector assessment
were drafted at this stage. An extensive review of material
available on CPI schemes and on other similar assessments
in the target districts, inputs from social sector specialists and
Aid’s extensive prior experience with similar assignments
were all drawn on to draft the initial tools which consisted of
a i) detailed household questionnaire and ii) a form for Focus
Group Discussions (FGDs).
3.1.3 Staffing
In order to carry out the work in the least amount of time and
maximize the use of available resources, it was decided that
two field teams would carry out operations simultaneously in
two clusters. Each field team comprised of a Field Supervisor
and two Researchers. The Researchers were responsible for
gathering qualitative and quantitative information from the
project sites using the purpose designed data gathering
forms. The team also included a short-term Advisor, a full
time Team Leader, a senior Engineer, and short terms inputs
from a Social Sector Specialist, Gender Specialist, and Data
Analyst.
TheFieldsupervisors,TeamLeaderandothersectorspecialists
15	 See Annex 7 – Work Plan
15
not only supervised these activities but also participated
actively in the data collection. The Field Supervisors were
the first level Quality Assurance; at the second tier, a Quality
Assurance Manager rechecked and validated the quality of
the data collected in the field.
The proposed Team Leader retained overall control of the
research operations and maintained close liaison with the
designated representatives of SRSP. The team was mobilized
immediatelyafterthecontractwassigned.Teamcoordination
was ensured through constant communication and contact
(including frequent meetings) between all team members;
head office staff and the field teams.
The team was fully mindful of the cultural sensitivities and
local norms which had to be adhered to when working in
the target areas. The team received the full support from
SRSP staff in terms of logistical arrangements, facilitation of
meetings and coordination at the field level.
3.1.4 QA Plan
In order to ensure that all tasks are completed with the
high standards quality that clients have come to expect. All
field work, data collection, results and reports were passed
through Aid’s comprehensive yet dynamic Quality Assurance
(QA) system.
At the inception stage, the top management at AiD,
along with the project Team Leader and senior Sector
Specialists designed QA policies which consist of specific
Key Performance Indicators (KPIs) used to gauge the level of
performance and resultantly, the quality and timeliness of
project delivery.
For the Evaluation of Immediate Impacts of CPIs under EERP,
a 4 tier QA approach was chosen which functioned in parallel
to Aid’s standard QA measures16
.
The first level of QA was the Field Supervisors who were
required to scrutinize all the primary data collected on a daily
basis. This was important for identifying, and subsequently
ratifying, any gaps or omissions in the questionnaire whilst
still in the field. Next, staff at Aid’s head office in Islamabad
reviewed the questionnaires sent in by the Field Supervisors
on a weekly basis. A third level of QA took place once the data
has been entered cleaned and analyzed.The sector specialists
then prepared a Final Report QA’d by the Project Advisor.
3.1.5 Sampling
In order to ensure that a representative sample was selected
for the study, a multi stage sampling method was used. In the
first stage the seven districts were divided into two clusters
namely Cluster A and Cluster B. Cluster A consists of Swat,
Shangla, Buner and Malakand while Cluster B consists of
Lower Dir, Upper Dir and Chitral. The sample was designed
with a view to capturing the diversity of the entire Project
area and the types of schemes.
A total sample of 60 schemes out of the total of 213 was
randomly selected; this represents a Confidence Level of 93%
with less than 10% margin of error.
The total sample was first distributed in terms of the
proportion of schemes in each district and then further
divided according to the number of each sub-type of scheme,
i.e. irrigation, drinking water supply, roads and drainage in
each region.
The second list for ‘types of schemes’ in each region was first
ranked in descending order of number of beneficiaries of the
scheme, then the nth scheme of each subtype was selected
based on an approximation of the sample/the population17
.
See fig 1.1 and 1.2
The field teams managed to look at 26 schemes in district
Swat, 7 each in district Shangla and Lower Dir, and Malakand,
6 in district Upper Dir, 4 in Buner and 3 in District Chitral.
Out of these 60 Schemes, 22 schemes were DWSS, 19 road
infrastructure, 7 Sanitation, 5 Bridges, 4 irrigation and 3 were
micro Hydel18
.
Ten additional schemes were chosen to replace any scheme
from the initial selection that could not be visited due
to unforeseen circumstances, such as security concerns,
inaccessibility etc. Eventually, four schemes were selected
from the list of ten to replace schemes that could not be
visited19
.
Fig 1.1: CPIs by District
Fig 1.2: CPIs by Type
Note:
Outside Ring: = Total EERP CPI s
Inside Ring: = Evaluation Sample
Note:
Outside Ring: = Total EERP CPI s
Inside Ring: = Evaluation Sample
Swat
Bunner
Malakand
Shangla
Lower Dir
Upper Dir
Chitral
43%
40%
5%
9%
10%
12% 12%
11%
12%
12%
12%
7%
10%
5%
40%36%
32%
12%
8%
7%
6%
4%
1%
5%
8%
11%
30%
16	 See Annex 5 – QA Diagram
17	 See fig 1.1 and 1.2
18	 See Annex 3 Sampled 60 CPIs
19	 This is further detailed in Stage 3: Challenges in the Field
16
3.2 Stage 2 – Field Work
3.2.1 Pre-testing and Finalization of tools
After all formats, sampling and work planning was finalized
the two teams were mobilized in the field. Initially, they were
accompanied by the Team Leader and sector specialists
who supervised activities at this stage. The data collection
tools were initially pre-tested at two schemes in Swat. The
team leader led the pre testing exercise and both teams
accompanied him for the exercise. After the pre-test, the
team held a session during which the forms were re-checked
for any inconsistencies, gaps or redundancies. The necessary
changes were made to the data collection tools and the
finalized forms were used for all subsequent data collection.
3.2.2 Field Activities
The field teams adhered strictly to a predefined protocol
for conducting visits to the CPI sites. Before each visit,
the engineers reviewed all available documentation for
the scheme to be assessed on that day. They extracted all
necessary information before the social and engineering
teams were taken together to the site by the local SRSP
representatives who were facilitating the visits.
Once the teams arrived at the village, the engineering and
social teams split up; the engineers went to the CPI to make
physical verifications and fill out the corresponding forms.
In the meanwhile, the social sector team dispersed in the
village; the females would fill questionnaires going from door
to door, whilst the men went to the hujra to meet with the
males. The females would continue on to conduct FGDs with
those women who had not been included in the HH survey.
Once the engineers had completed the physical inspection
of the schemes, the male researchers and the engineers
would gather the members and management of the all-
male COs. Together, they would go over all of the COs
documentation and interview the management to assess
the adequacy, or lack thereof, of the O&M system in place for
the scheme. Afterwards, the engineers and social researchers
would together to conduct an FGD with male members of
the community; ensuring both members and non-members
participated.
3.2.3	 Challenges in the field
The field teams faced a number of challenges working in
some very volatile areas. The sample schemes were spread
out over a sizeable area and many were located in remote
areas. SRSP’s outreach to these areas is commendable; the
schemes had been implemented in areas where no other
government or non-government entities had any presence.
This meant many hours of driving and trekking through often
rugged and mountainous terrain for the field teams.
Some of the schemes could not be visited. For instance, two
schemes from Swat; Chinawatt and Foladai were replaced, as
was one scheme in Buner. Chinawatt was replaced due to the
fact that it could only be reached after a three and a half hour
walk through treacherous, snow covered mountain paths; a
trip that locals said was only advisable for locals familiar with
the village. It was replaced with a scheme implemented in
Saidu Sharif. Foladai was replaced with a scheme in Deolai
because Foladai was rendered inaccessible due to torrential
rains. Similarly, Malikpur, a village in Buner could not be
visited because there were on-going military operations in
the area.
3.3 Stage 3
3.3.1 Data Entry, Analysis and report writing
Data from the field was periodically sent to the AiD Head
Office by the field teams for parallel data entry. The final
set of data from the field was received on 12th April when
the entire team held a collective work shop to discuss their
experiences, recommendations and the lessons learnt.
The forms had all been coded for ease of management and
to minimize the potential for errors. Nonetheless, as per QA
protocols, the forms received from the field were checked for
any major inconsistencies, missing information or collection
errors. These forms were then passed on to data entry
operators who used Microsoft Excel™ spreadsheets to record
the data.
The Excel™ spreadsheets were exported to Stata™ software
which was used to analyze the varied forms. After data
cleaning, the Data Analyst prepared an extensive list of tables
which were used to develop the results and findings for the
Final Report.
The final report is organized around the five Evaluation
Parameters initially decided upon. Each parameter has been
given a separate section and the CPI’s have been analyzed in
terms of each one in great detail.  
17
CPI DESCRIPTION
The evaluation team visited 60 CPI schemes, of these 43
% were in Swat, 12% in Shangla and Lower Dir, 11 % in
Malakand, 10 % in Upper Dir 7 % in Buner and 5 % in district
Chitral. Schemes costs range from Rs 0.22 million, hand pump
CPI in Mankass, Kabal Swat to Rs 8.6 million Micro-Hydel in
Shao, Swat.
Theseschemesreflectedthepriorityneedsofthecommunity.
Of the total 60 schemes 22 are DWSS, 19 were Road
infrastructure, 7 Sanitation, 5 Bridges, 4 Irrigation or 3 MHP.
DWSS
Aid looked at 22 DWS, 3 were in Buner, 2 in Chitral, 3 in Lower
Dir, 3 in Malakand, 1 in Shangla, 1 in Upper Dir, and 9 in Swat.
These schemes ranged in cost from Rs 1.2 million, for a Gravity
flow, scheme in Abbaseen Colony, district Shangla to Rs 0.22
million for a hand pump based scheme in Mankass Kabal,
district Swat. There were various subtypes, but the majority
was Gravity flow, i.e. in which case the water was stored in
large tanks which were supplied from natural springs and
fed into the communal areas by gravity flow by a distribution
network of pies. On the other hand 7 schemes were for hand
pumps.
In the 22 schemes which AiD looked at the planned
beneficiaries was 1700 whereas the actual beneficiaries were
reported to be 2600.
Cost per beneficiary house hold ranged from Rs 2000 to Rs
24000 for a HP scheme in Jabba, Swat and a Gravity flow
scheme e in Shaqi Ghawaljai also in swat respectively.
ROAD INFRASTRUCTURE
Road infrastructure included link road and causeways. Link
roads were either, what are called as PCC rigid pavement
or earthen rehabilitation works of existing alignments or
construction of causeways.
A total of 19 road infrastructure where constructed out which
2 was causeways and the rest were either rigid pavement or
earthen road improvements with retaining wall and cross
drainage structures. 8 schemes were in Swat, 4 in lower Dir,
2 each in Malakand and Upper Dir, and 3 were in Shangla
district.
Their cost ranged from Rs 1.33 million for a link road in Gujjer
Tangi Badro, Swat district to Rs 0.5mill road in Aminabad, also
in district Swat.
Total beneficiary household were shown as 2900, however an
estimate which the engineers gather after discussions in the
field indicated the figure to be close to 4000.
Cost per beneficiary ranged from Rs 1944 to Rs 9029 for
Akhun Baba, Pcc link road in district Swat, and Baghgay
Maloch, RCC cause way also in district Swat.
4. FINDINGS
BRIDGES
Out of the 18 bridges which SRSP assisted with under the
EERP project the team was able to see 5 bridges, 4 of which
were pedestrian suspension bridges whereas 1 was a RCC
bridge for regular traffic. One of the suspension foot bridge
were located in Buner, 2 were located in upper dir whereas 1
was in Shangla. The RCC Bridge in Kamay, Swat.,
The bridge CPIs cost from Rs 0.92 million for the suspension
bridge constructed in Bazarkot, district Buner to Rs 2.5
million for the RCC bridge, constructed in Kamay Swat.
Bridges like roads benefit not just the immediate community
which has been involved in the construction of the scheme
but any adjacent village or hamlet which is using it. In one
case however the team found that the HH reported were less
than what were planned.
Cost per beneficiary varied from Rs 4585 for the Pedestrian
suspension bridge in Swat to Rs 10123 for Malow, in Upper
dir.
SANITATION
7 schemes which addressed the sanitation and drainage
of the communities were built. 5 of these are in district
Swat, whereas 2 are in Shangla. These schemes are mainly
construction of drains and rigid pavement
The total cost of each sanitation related scheme ranged from
Rs 0.3 million for a drainage scheme in Bazkhelin district
Shangla , to Rs 1.2 million for the Street pavement and
drainage in Shagai, district Swat.
The total beneficiaries of the road infrastructure were
reported to be 1430 instead of the originally planned 1030.
The cost per beneficiary ranged from Rs 1717 in village Faqira;
district Swat, to Rs 11780 for Bazkhel, Drainage scheme where
the number of beneficiaries was very low.
IRRIGATION
Out of the total of 12 irrigation schemes which were done
under EERP, the evaluation team looked at 4. Most of them
wereinSwatdistrict,andoneinMalakand. Theschemesrange
from installation of a pump, to a construction of irrigation
channel to channel lining and in one case construction of a
retaining wall.
The cost of the schemes range from Rs 0.55 million for the
ram pump in Babu Maira in Swat to Rs 1.1 million for the
irrigation channel lining and construction of retaining wall,
in Meragai, Swat.
The total beneficiaries for the 4 schemes are around 800 HH.
MHP
The team visited 3 out of the 8 MHP done under EERP. One
of these was in Swat; the other two in Upper Dir and Chitral
18
respectively. MHP are technically complex and relatively
costly. The schemes cost ranged from Rs 2.7 million for the
50 Kw MHP in Khanabad, Upper Dir, to Rs 8.6 million for the
100 Kw MHP in Bhamborate, Chitral.
Twooftheschemesi.e.theoneinShao,SwatandBhamborate,
Chitral are being implemented using an innovative approach
of what is called a social enterprise in which both SRSP and
the community are co-managing the scheme.
Thenumberofbeneficiariesisaround900andthecostranges
from Rs 12176 per beneficiary to Rs 31300 per beneficiary.
4.1 CPI documentation: Availability and Adequacy
The Engineer’s Desk Review constituted the first level of
verification of the 60 CPI schemes mentioned above. Before
the schemes themselves were visited the engineering
team assessed the availability and adequacy of the CPIs’
documentation annexure 620
, shows a simplified diagram of
the PI process, and the various documentation required.
The process of implementation of any CPI is triggered by a
resolution from the Community Organization.This resolution
indicates that the community is interested in a development
partnership have reached a consensus on a priority problem
which they would like to address in the shape of a possible
CPI. This is also, what can be termed as the culmination of a
series of meetings called 1st dialogues.
Oncearesolutionispassedbythecommunity,itisreceivedby
the local social organizer(s) who prepare a Social Feasibility
for the scheme. Engineers, meanwhile, prepare the required
technical reports such as Design and Estimates and carry
out an Environmental Screening to ensure that there are no
major environmentally detrimental effects of the scheme.
If the results of the social and engineering reports and the
environmental screening are found to be positive and they
fall within the criterion set by EERP, the scheme is given a
formal approval for implementation by the SRSP Head Office.
Afterwards, SRSP representatives engage the community in
a ‘3rd dialogue’ during which a Terms of Partnership (TOP)
document is signed by the community. The TOP is included
in the final Project Proposal.
For record keeping, all copies of receipts, expenditures
as well as any and all other documentation pertaining to
the construction of the schemes are to be maintained in a
Physical Infrastructure (PI) Register by the CO’s secretary.
Once the scheme is completed a Project Completion Report
(PCR) showing the actual cost and date of completion is
prepared; the PCR also becomes part of the CO’s and SRSP’s
records. If the schemes is successful and is handed over to the
community, and a Project Completion Certificate is issued.
The evaluation team assessed the availability and adequacy
of this essential documentation for each of the sampled
schemes and has come up with the following result. The
detailed scheme wise summary is available in a tabular form
in the annexure21
.
4.1.1 Social Feasibility
A social feasibility report serves several functions; it shows
that the Community Organization exists on the ground, it
has an open bank account, and that there was no conflict
amongst the CO’s members in general or around the priority
ranking of the CPI itself.
Allthe60schemessampledhadtherequiredSocialFeasibility
documentation and it was found to be adequate.
4.1.2 Environmental Screening
Environmental Screenings were carried out using a simple
template developed by SRSP for its field staff. The screenings
were used indicate whether or not the proposed project is
safe for the environment and weather a detailed environment
assessment is to be made or not.
The Environmental Screening consists of a three stage
process. At the first level, an environmental sensitivity
assessment is carried out. Environmental sensitivity is taken
in terms of the proximity of the proposed scheme to natural
habitats/vegetation, slopes, populated areas, various kinds of
wetlands, historical and cultural sites, etc.
In the second stage, the level of environmental screening
required for the scheme is determined based on the results of
the environmental sensitivity assessment. An Environmental
Review (ER) is the basic minimum level of screening required
for all schemes, regardless of their ranking/categories from
the sensitivity assessments. Higher levels of screening;
those which are more detailed and are to be performed by
professional environmentalists are required for schemes
which rank poorly in the environmental sensitivity
assessment.
The Environmental Review is the third and final section of
the environmental screening. The ER is used to determine
the potential negative impacts of the scheme on the
environment and details the measures that must be taken to
mitigate those negative impacts. These mitigation measures
must be included in the schemes’proposals.
Environmental Screening documentation was available for
the first two stages, albeit partially in some cases for 49 of
the 60 schemes. The ES documentation for the remaining 11
schemes was either not available or had not been filled in.
Furthermore, the team was unable to see any Environmental
Review reports.
4.1.3 Technical Feasibility:
4.1.3.1 Design Basis
The most crucial aspect of any technical feasibility is the
design basis and assumptions on which the schemes has
actually been designed and estimated.
The table below shows some examples of the required
design basis which would necessary for a correct design.
Type of Scheme Required Design basis
Road/Bridge CBR or bearing capacity, Axle load, Details of
construction joints
Drinking Water Supply Capacity, HH requirements
Drainage Rainfall Intensity, Catchment area
Irrigation Crop water requirements/Soil type
The design basis for 27 of CPI’s was not available or
inadequate. Mostofthesewerelinkroadorstreetpavements.
Key information such as bearing capacities of soil and the
Axle loads were missing22
.
20	 See Annex 6
21	 See Annex 1A
22	 See Annex 1 A Table 1.2
19
4.1.3.2 Design Calculation
Once we have the design basis of any engineering structure or its component the next step is to calculate the design
parameters. Depending on weather a design is for a street pavements, roads or drinking water supply storage tanks, for the
engineer the design of the thickness, compaction of roads, tank wall thickness, concrete slab thickness or reinforcement
design, all need to be calculated. These calculations are made to ensure the integrity and efficiency of the structure and to
ensure that there is a backup in case of any liability
For the schemes implemented by SRSP, it was found that the design calculations for 32 schemes were not available. Of
the remaining 28 schemes the Calculations for 10 seemed inadequate. For instance, in the case of storage reservoirs, the
calculations for the determining the dimensions of water tanks were missing23
.
4.1.3.3 Construction Drawings:
Construction drawings are needed to ensure that the community and labor working on the ground are able to construct the
schemes in accordance to the designs envisioned.
Accept for one scheme namely Jabba in district Swat, all the CPI proposals reviewed had at least the basic schematic
construction drawings attached as part of the project proposals. See table 1.424
4.1.3.4 Material and works specifications
Material and works specifications must be detailed because they are essential for ensuring the quality of the construction is
up to the standard anticipated by the project proposal. The site engineer and the community must be very clear on what is
to be used for the construction of the schemes and how it is to be used.
All the CPIs mentioned what materials were required, such as bricks, sand and steel. However, it was observed that invariably,
there was no mention of the detailed specifications for these materials such as the standard quality of the bricks, the type of
sand or strength of the steel.
Detailed Material Specifications Should be:
Cement Grey Portland Cement shall be normal setting cement of make and source as approved by the Engineer. Cement shall conform to the
requirements of ASTM C 150 unless otherwise acceptable to the Engineer.
Fine Aggregates Fine Aggregate shall be clean River sand from an approved source of supply and of uniform quality having fineness modules between 2.3
and 3.10.Fine aggregates shall comply with the requirements of the relevant ASTM C-33 Specifications, and shall be graded as follows:
Sieve Number/Size	 %age (by weight) passing
9.50 mm 3/8”	 100
4.75 mm (No.4) 3/16”	 95-100
2.36 mm (No.8) 3/32”	 80-100
1.18 mm (No.16) 3/64”	 50-85
0.6 mm (No.30)	 25-60
0.3 mm (No.50)	 10-30
0.15 mm (No.100)	 2-10
Limits for deleterious substances of total sample shall be:
Clay lumps and friable particles	 Maximum 3% by weight
Material passing No.200 sieve	 Maximum 3% by weight
Coal and lignite	 Maximum 0.5% by weight
Weight loss of sand subjected to 5 cycles of soundness test when sodium sulphate is used shall not be greater than 10%.
Coarse Aggregates Coarse aggregate shall be 3/4“ down, hard crushed stone from a source approved by the Engineer. For members up to 3“ thickness, 1/2“
down crushed stone shall be used. Coarse aggregate shall comply with the graduation requirements of ASTM C-33 and shall be graded as
follows:
Nominal Size of Graded Aggregates shall be 19 mm (3/4”) down
Sieve Number/Size	 %age (by weight) passing
19.00 mm (3/4”)	 90-100
12.50 mm (1/2”)	 -
09.50 mm (3/8”)	 20-55
04.75 mm (3/16”)	 0-10
02.36 mm (3/32”)	 0-5
Weight loss of coarse aggregate when subjected to 5 cycles of soundness test using sodium sulphate shall not exceed 12% and %age loss
for Los Angles Abrasion (500 revolutions) not be greater than 50. Aggregates shall be screened and washed if required to the satisfaction
of the Engineer
Water Water to be used in the work shall be clean water or approved by the Engineer. The community shall supply sufficient water for all purposes
including mixing the concrete, curing, and cleaning plant and tools. It should be clean and free from injurious amounts of oils, acids, alkalis,
salts, organic materials or other substances that may be deleterious to concrete or reinforcement. Where doubt exists as to the suitability of
water, it should be tested in accordance with BS 3148.
Steel Unless otherwise specified, all deformed reinforcing bars shall comply with the requirements of ASTM 615 for deformed cold worked new
stock billet steel bars and shall have a minimum characteristic strength of 40,000 lb. per square inch.
23	 See Annex 1 A Table 1.3
24	 See Annex 1 A Table 1.4
20
4.1.3.5 Costing/Estimates
The costing and estimates for all 60 schemes were
checked and found to be correct.
4.1.4 Water Quality Test
Water Quality tests had to be carried out for DWS schemes to
ensure that the water from these schemes was potable.
Out of the 22 DWSS schemes Water Quality tests reports were
available for all the schemes.
4.1.5 Project Proposal
The project proposals are detailed documents that cover the
technical (engineering), social, procedural and management
aspects of the schemes. The engineering documentation
listed in the previous sections such as environmental
assessment reports and design and cost estimates are part of
this proposal. Similarly, the objectives of the project, the roles
of the key stakeholders and the protocols for management of
the project are all outlined in the proposal.
Project proposals for all 60 schemes were available, in the
regional offices albeit some were incomplete as mentioned
elsewhere in this section.
4.1.6 Project Approval
All the schemes had received formal approval by the
competent forum.
Project approval documentation was available for all
schemes.
4.1.7 PI register
A PI register is to be maintained by the CO, typically by the
CO’s secretary. The PI register contains all documentation
related to the implementation phase of the scheme, most
commonly the receipts for outlays during the construction
phase, or for O&M.
PI registers were available for 54 of the 60 schemes and most
were diligently maintained, however, the team was not able
to see the PI registers for 6 schemes25
.
4.1.8 Project completion report
The project completion report details the initially estimated
quantities of various materials and labor required for
implementation of the CPI and the actual quantities used as
well as the variation between the estimate and actual outlays.
The project completion reports were missing at 4 of the
schemes visited. Of the remaining 56, completion reports for
5 were deemed to be inadequate because they did not have
signatures of the community members26
.
4.1.9 PI completion certificate
A PI completion certificate is prepared by engineers once
the scheme is ready for hand over to the community. It lists
the contributions made by the stakeholders and the dates of
completion.
All of the CPI’s had completion certificates except Shao, MHP
in Swat, and Bazarkot and Riaz Ambela in district Buner27
.
4.1.10 Handing and taking over certificate:
The Handing and Taking over Certificate is signed by the
community members once the scheme has been completed
and is officially being handed over to them by SRSP. The
certificate is a crucial for ensuring the sustainability of the
scheme since it makes official the community’s ownership of
the scheme and lists the members of the O&M committee. It
also certifies that O&M systems have been put in place, such
as the opening of a bank account specifically to hold an O&M
fund.
The Handing and Taking Over certificates were available for
55 schemes. Out of the remaining 1 had failed, 2 schemes
had not yet been handed over and 2 schemes did not have a
certificate on file28
.
4.2 Design Validation
This section outlines the Engineering Team’s findings of
the physical validation of the various design parameters of
the CPI’s. The design parameters verified include scheme
layouts, design measurement, material specifications as well
as the workmanship, the scheme outcomes, environmental
screening, operation & maintenance, and finally the schemes
functionality, efficiency and effectiveness.
This section in particular covers the findings from the
layout and design, environmental screening, and material
validation, the rest of the findings from the engineers visit to
the site are in their relevant sections which follow.
4.2.1 Scheme Layouts
The scheme layout was verified on how the various CPI
components are laid physically on the ground. For example
the alignment of the road, or the location of the various
structures mentioned in the design.
The engineering team conducted site visits to all sample
schemes to validate the physical layout and schemes layout.
It was observed that except for 9 CPI29
all the rest were
implemented according to the planned layout.
The major problems either related to a difference of what
was observed in the pipe network, such as missing pipes or
tanks observed at Yakh Tangay village in Swat, Banjo Tangay
in Buner, Abbaseen village in Shangla and missing elements,
such as RCC culverts in village Gujjer Tangi Swat30
.
Five schemes were found to have minor problems. For
example the design of the Gravity Flow DWSS (GF) in Sory
Kad village, Swat, showed two supply lines were showing in
a schematic layout but it was observed that instead of two
lines, four lines were originating from the tank. However,
despite the deviation from the scheme layout, the desired
design discharge was acquired satisfactorily. In Asilo village,
Lower Dir, the designed/proposed layout of distribution
lines of the DWSS had not been adhered to on site. Similarly
the drawings of the Gravity Flow scheme in Ambela village,
Buner, indicated that 4 supply lines were originating from the
storage tank. However, it was observed that 05 distribution
lines were in connection with the storage tank.
4.2.2 Design Validation:
All the 60 schemes were checked to validate the design in
terms of the measurement of the structure, the material used
and its workmanship.
It was reported that 48 % of the schemes were found to be
exactly as per design, 34% had minor variations and were
marked as satisfactory. However, 18 % had major variations,
from what was originally planned.
25	 See Annex 1 A Table 1.5
26	 See Annex 1 A Table 1.6
27	 See Annex 1 A Table 1.7
28	 See Annex 1 A Table 1.8
29	 See Annex 1 B
30	 See Annex 1 B
21
The schemes with variations either had missing structures,
such as those at Sanam village in Shangla, Gujjer Tangi
& Mankass Kabal in Swat and Faqira, in Swat, or the
measurement of structures did not match as was the case in,
Banjo Tangy DWWS , district Buner, Abbaseen Colony, DWSS
in district Shangla, amongst other31
.
4.2.3 The following is a type wise breakdown of the CPIs:
4.2.3.1.1 Drinking Water supply Schemes
Out of the 22 schemes the design and layout of 4
schemes could not be validated on site. For e.g. In DWSS
Yakh Tangay, district Swat, Banjo Tangay, district Buner,
Abbaseen Colony in District Shangla, and Danwa, Lower
Dir, the original design has a different configuration than
what is on site. In Kuru Bala, Chitral, the community has
not built the Dug well where originally laid out by SRSP,
and as a result the scheme has failed.
4.2.3.1.2 Road Infrastructure:
Out of the 19 road infrastructures which were visited,
there was one scheme for which a layout could not
be seen. Only 2 were found to be out of sync with the
original layout. Gujjer Tangi, Islampur in district Swat,
did not have 7 culverts originally designed, similarly in
Baghgay Maloch, also in district Swat, the layout of the
culverts is different from what was shown in the project
proposals. See table for detail
Furthermore, the measurements of the structures in
road infrastructure CPI in village Samteer and Aminabad,
district Swat and village Sanam, district Shangla did not
match with was planned. See Table for details.
4.2.3.1.3 Bridges
All the bridges were on the spot which they were planned
for; however the design basis or calculation were missing.
Only in the case of Tangir we have some design however
the calculations were not adequate.
4.2.3.1.4 Sanitation
The layouts of all the schemes were found to be as
planned. However the design for drains and pavement
did not have a technical basis or any reference.
4.2.3.1.5 Irrigation
The layout of the schemes are fine, however there are
discrepancies in measurement of the structures in the
case of Meragai and Babu Maira scheme. In the case of
Babu Maria a tank has been constructed which is not
part of the original design and is not mentioned in the
documentation, where as in the case of Meragai, the
retaining wall is shorter and also lower than what was
proposed.
4.2.3.1.6 Micro Hydel Project
All the schemes have been constructed as per
documented layout and design
4.3 Relevance
From the GoKP’s viewpoint one key document which
indicates the priority areas of investment of the GOKP for
Malakand Division is the Malakand Strategy prepared in
200932
. It is noteworthy that one of the means to achieve
its objectives, the strategy envisions the rehabilitation or
building of road and bridges, water and sanitation, irrigation,
and power Infrastructure. The CPIs done under EERP closely
match the priority of the GoKP as it has set down in its
strategy document.
AusAid is concerned EERP comes under its objectives # 3 for
Pakistan as it is explained in the Pakistan Annual Program
Performance Report 201133
, this is;
•	 Sustainable economic development - through increasing
agricultural productivity and improving rural livelihoods.
All the CPIs contribute towards improving rural livelihoods;
on the other hand sustainable development requires
sustainable institutions which at the local level would require
a longer period of engagement with the communities than
the timeline available under the EERP. Perhaps SRSP would
needs to creatively develop a ‘sustainability’ pool towards
which any client contributes when engraining SRSP.
To directly gauge the perceptions of the local communities
both a HH survey and Group discussions with local
communities in all the 60 villages where the CPIs were
implemented.
To assess relevance, the HH survey grouped related questions
under 3 indicators one asked them directly about whether
the scheme was a priority for the whole community. The
second related to their participation in the implementation
process and third was about their contribution in cash or
kind.
4.3.1 Priority
An overwhelming majority, 98 percent of all people surveyed
in 6 districts said that they considered the CPIs which were
implemented by SRSP a priority. This response is more or
less the same across all the districts, and gender. What is
significant is that the response for non members is also very
similar and 97.3 % also said that the scheme was a priority
need of the community.
4.3.2 Participation
ThehighestparticipationwasindistrictsChitral(100percent),
where the community members felt they had participated
thought the implementation of the schemes. Whereas he
lowest level of participation about 60 % was reported from
Shangla.
Given the socio cultural norm of the area it was not surprising
that participation of females was low. Participation in
identification and planning /implementation ranged from a
very low of 6% for both Upper and Lower where around 11 %
of the respondents were members, to 67 % for Chitral where
membership for WO was 100 %.
Irrespective of that 96 % of the female respondents felt that
the CPI was a priority need.
The FGD analysis supports the findings of participation of
females,withmalesmoreinvolved.Approximately17percent
female participants claimed that ‘no one’ was involved and/
or interested in the project-related activities, as compared
to 3 percent males who reported the same. Another 23
percent females were unaware/unable to comment on the
query. While 63 percent male FGD participants claimed
that most and/or all members fully involved, only two-third
of the females (43 percent) thought the same. The highest
rate of responses regarding non-interest were from Swat
(23 percent), while FGD participants claimed high levels of
31	 See Annex 1 B
32	 Government of Pakistan’s Comprehensive Stabilization and Socio-Economic Development Strategy for Malakand Division. 2009
33	http://www.ausaid.gov.au/Publications/Documents/pakistan-appr-2011.pdf
22
full involvement in Buner, Malakand Agency and Shangla.
Scheme-wise, the FGD participants claimed to be most
involved in irrigation (71 percent).
Around 70 percent of the respondents (25 percent; CO
membersand15percent;non-COmembers)alsocontributed
in kind offering themselves for labor, mostly in Buner and
Malakand Agency (90 and 81 percent, respectively). The
average number of labor days contributed by both males and
females was 31, which was spent evenly on each CPI scheme.
Further, 20 percent of respondents contributed additional
items in kind, almost evenly (20 percent) across districts, with
the exception of Chitral (40 percent) and Malakand Agency
(no additional contribution). These included the following,
district- and CPI scheme-wise:
4.3.3 Community Contribution
One indicator on how relevant the community considers
initiation and implementation of any project can be
determined by how much they are willing to contribute
towards it – in terms of cash and/or in kind (labor, etc). This is
also an important indicator to ensure high (or low) levels of
ownership of the project, so that chances of its sustainability
are higher. In terms of community-based contribution to
the construction (cash and/or in kind), 77 percent of the
respondents claimed to have made contributions (75 percent
females; and 79 percent males). The highest amounts of
contributions were made in Chitral, Upper Dir and Buner
(100, 92 and 83 percent, respectively). Pl see the graph below
for contribution towards different CPI schemes.
Interestingly, an equal amount of non-CO members
(approximately 77 percent) as compared to their counterpart
members contributed towards the construction of CPI
schemes.
Graphs 3.3 & 3.4: Mean cash distributed by location and type of
CPI scheme (PKR):
8505
7000
6435
1543
900
120
100
80
60
40
20
Buner Chitral Lower Dir Malakand Shangala Swat Upper Dir
Identification ImplementationPlanning
0
HH Participation
120
100
80
60
40
20
Buner
Member of a WO
CPI is a priority
Participation in identification
Participation in planning & implementation
Chitral Lower Dir Malakand Shangala Swat Upper Dir
0
Women Response
Of the households that contributed positively, 17 percent
of them contributed cash. An average of PKR 5800 was
contributed these respondents, where the male average
was PKR 8000 and the female average was approximately
PKR 4500. The highest frequency of cash contributions (30
percent) was witnessed in Shangla; the highest amount in
Chitral (PKR 60000); and the CPI scheme contributed most
towards was street pavements and drainage (20 percent).
23
4.4 Effectiveness
The second evaluation parameter, effectiveness, was
evaluated in terms of weather it is fulfilling the needs it was
designed to meet, is it operational.
Accordingly, the indicators identified for Effectiveness were:
Functionality of the CPI schemes; benefits for community
members; and problems encountered with the schemes.
4.4.1 Functionality
As part of the approach, functionality of the scheme was also
checked on site by the field engineers. In this regard they
were able to check 55 CPIs out of the total sample of 60 and
found that 95 % of the CPIs were functioning well whereas
5% or 3 schemes had some problems.34
Out of the remaining 5 CPIs which could not be checked, 4
were not operational at the time of the visit and 1 dug well
DWSS, had been declared a failure due to unavailability of
groundwater.
The 4 schemes were not operational at the time of the visit
included the MHP scheme in Shao Kalam, district Swat and
Khanabad, district Upper Dir, Irrigation CPI in Meragai Swat
and DWSS Dardyal, district Swat. The two MHP had technical
breakdown and were in the process of being repaired by the
communities, whereas, the Irrigation Channel in Meragai
Swat was not operational, since it was not an irrigation
season, whereas in the case of DWSS Dardyal, Kabal Swat,
the intake structure had been damaged due to a snow slide
and the communities were waiting for the snow to melt
before attempting any repairs. schemes which were non
operational included the MHPP scheme in Shao Kalam
and Khanabad, in Upper Dir, both of them had technical
breakdown and were in the process of being repaired.
4.4.1.1 Functionality: DWSS
All the schemes were fully functional accept for 2. One of
them was a gravity flow scheme Dardyal, in Kabal, Swat
and the other was a hand pump scheme in Sher khan,
Swat, where out of 5 hand pumps of to 3 were working.
In the case of Kura Bala, the community decided to
relocate the originally location for the CPI to one which
was closer to them, however despite digging to a depth
of90’thewellremainsdryandhasbeenofficiallydeclared
as a failure
4.4.1.2 Functionality Road Infrastructure
Despite the problems mentioned, all the schemes were
functional albeit, in some cases partially as was the case
of Link Road in Gujjer Tangi, district Swat, Feza, and
Sur Kamar in District Shangla, where either the cross
drainage work were not functional or some portions of
the road had been severely eroded.
All bridges were found to be functional and effective.
From the HH survey, approximately 91 percent of the
respondents acknowledged that the CPI schemes
were functional across the 7 districts. When asked how
effectively the CPI schemes were delivering, the female
respondents gave more optimistic assessments stating
that 86 percent of the schemes were 100 percent
functional, as compared to the more cautious replies of
male respondents, claiming 61 percent of the schemes
to be fully functional. Another 3 and 26 percent females
and males, respectively stated that the schemes were
functioning above 75 percent, making the overall
gender-wise level of satisfaction equal. Scheme-wise, on
average, 72 percent of the schemes were termed fully
(100 percent delivery). Scheme-wise, on average, 72
percent of the schemes were fully (100 percent delivery)
and 15 percent partially functional (delivery above 75
percent) across the 7 districts (see Graph 3.6 below).
FGD analysis supported the overall satisfactory responses
from majority of the male and female participants. In
some cases, respondents gave mixed reviews, such as in
Chitral, where 33 percent reported that certain schemes
were currently not working, and 67 percent stated that
the schemes over there are working and they had no
further complaints. CPI scheme-wise, the data is reflected
in Table 3.1 (Annex: 1-C).
There appeared to be no bias in positive responses of
CO members who fully ‘owned’ the process, as opposed
to the opinions of non-CO members, where 89 and
87 percent of both types of respondents, respectively
acknowledged that the CPI schemes were between 75 to
100 percent functional.
% YES
% NO
Is the CPI functional at present?
71 80 75 75 50
% Delivering 100%
71 10 03 3
% Delivering 0%
102 51 7
% Delivering 50%
18 31 81 40 % Delivering 75%
2 656 0
% Delivering 25%
Graph 3.6: Level of functionality of CPI schemes
Total Drinking Water supply
Total irrigation
Total Link road/Bridges
Total Street Pavement and drainage
Total Other
34	 See Annex 1B Table 2.6
24
4.4.2 Benefits
Community response was close to what the engineers
found on the ground. The result of the HH survey Overall 90
percent of respondents claimed to be directly benefitting
from the CPI schemes; including 67 percent of CO members
and 58 percent of the non-CO members surveyed. Further,
responses reflected that 80 percent of the surveyed
people were benefiting from the CPI schemes in Chitral,
reinforcing this district’s high rates of proactively in planning,
implementation and cash contribution.
A gender-wise break down reflects 67 percent satisfied male
respondents and 100 percent females claiming to be directly
benefitting from the CPI schemes there. Approximately 87
percent of the females reported to be directly benefitting
from the CPI schemes, with 100 appreciations in Chitral,
Shangla and Upper Dir. All CPI schemes were allocated above
86 percent priority by females, with irrigation reported to be
100 percent important for them. Female priority, based on
CPI schemes is as follows:
Drinking
Water Supply
OtherLink road/
Bridges
Irrigation Street Pavement
and drainage
50
50
73.1
26.9
100 100
97.1
2.9
Respondents in Shangla and Lower Dir claimed to be the
most satisfied direct beneficiaries (100 and 97 percent,
respectively), consistent for both males and females. Of
the female respondents, 86 percent claimed to be direct
beneficiaries, as compared to 93 percent of males.
In terms of whether or not the respondents perceived the
projects as being cost effective, results from the FGDs reflect
a high level of unawareness of females as opposed to almost
all males 98 percent sharing their viewpoints, with male
perceptions spread out across the options. One female stated
during an FGD that‘this topic was male domain’. The projects
in Chitral were proclaimed most cost effective by 67 percent
respondents during the FGDs. Details are given in Table: 3.5
(see Annex 1-B).
4.5 Efficiency:
The efficiency of CPI construction has been evaluated with
regard to the completion of the CPIs within the specified time
and costs.
An enlightening aspect is that even a high number of non-
CO members (88 percent) were gaining positive externalities
from the implementation of the CPI schemes. Reasons for
respondents not
In terms of related responses of satisfaction levels through
the FGD analysis, 80 and 76 percent male and female
respondents, respectively claimed to be aware of and
receiving most and/or all the intended benefits of the CPI
schemes. Highest claims (above 80 percent responses)
were received in Lower Dir, Malakand Agency and Shangla;
and CPI scheme-wise for link roads and bridges; and street
pavements and drainage.
4.4.3 Problems
The highest complaints of problems were reported in Upper
Dir, followed by Shangla (19 and 11 percent, respectively).
Overall, 10 percent respondents identified the problems in
street pavements and drainage, and 7 percent in link roads
and bridges (and 55 percent in ‘other’ schemes). A list of
problems is given in Table 3.4 (see Annex 1-B). The following
graph shows the gender-wise break down of respondents’
reporting problems, if any, with the CPI schemes – less than
10 percent reported any complaints:
Type of CPI Drinking Water supply
Type of CPI irrigation
Total of CPI Link road/Bridges
Type of CPI Street Pavement
and drainage
21 12 0 81 7
No %
No %
79 88 100 93 83 Yes %
Yes %
Yes %
No %
CO/VO Membership Yes
CO/VO Membership No
8891
129
2
5
6
1
1
1
Have access to another source
The household is from another
caste/tribe/social class
Low quality of output form
the CPI
High cost/userfee of the CPI
The House is far away from
the CPI location
Other
7
9
7591
170
Graph 3.11: Gender-wise break down of respondents’ reports
of problems with CPI schemes
Sex Male Sex Female
Are there any problems/issues with the scheme at the time of interview?
Dont Know %
25
Intermsoftimetakenforcompletion,itwasfoundthat95%of
the schemes were completed within the planned timeframe.
In terms costs, 87 % of the sample schemes were completed
within the estimated budgets. . A relatively modest 7% of
the schemes were completed at over 10% of the estimated
cost while 6% were completed under the estimated budgets.
What is significant to note is that in case of cost overrun, local
communities contributed to cover the balance.
Assessment of the comparative beneficiary costs from earlier
studies show that SRSP investments are generally cost
effective.
As a comparison, one study done in Nov 2002, “Cost
and Impact Analysis of Water Supply and Environmental
Sanitation in Pakistan” by Pakistan Institute of Development
Economics Nov 2002, shows a figure of Rs 14228/HH for
Government of KP and Rs 5521/ HH for NGOs forWater supply
and Sanitation schemes. Adjusted for inflation this would be
close to Rs 13000 per HH today.
On the other hand, based on the data of the sample schemes
the average cost of the EERP Sanitation CPIs this comes to Rs
3430/ HH about 3-4 times less in terms of cost per beneficiary.
Although hard comparative data is not available for similar
sized schemes which the GoKP or other organizations have
implemented, there is anecdotal evidence that cost per
beneficiary in the case of SRSP CPIs is relatively low. One
reason is community contributions which on average is at
least 20 % of the total cost of schemes
4.6 Sustainability
The sustainability of EERP CPI and for that matter any
infrastructure relate to its technical design, quality of
construction and system of O&M. In case the scheme has
been poorly designed or constructed, even a good O&M
system will struggle to keep it going. On the other hand
even if the structure has been designed and built to the best
of standards, it will deteriorate over time if not maintained
properly.
4.6.1 Design and layout.
The CPI scheme designs invariably are based on the
traditional technologies and designs being used in the area.
Scheme design were available for more than half the schemes
however as mentioned earlier that there was no design
basis for 27 CPIs was either not available or inadequate and
similarly design calculations were missing from 32 schemes.
All the construction drawing were very basic and left the
details to the discretion of the technician on the ground.
About 15 percent of the schemes had changed the layout
significantly from what had been planned. Although this is
not a bad thing in itself, since for a community based project
needs to have an inbuilt flexibility to match the conditions
in the field. On the other hand this also reflects on the weak
feasibility and lack of time given to technical planning and
thinking.
Workmanship in a large number of schemes was found to
be excellent. This was despite the difficulty in carriage of
material and water for curing. One example is the RCC Bridge
in Kamay, in Swat district.
The quality of workmanship at the sites was also observed
in the field. It was found that, at 44% of the schemes
workmanship were ranked good and at 38% it was found to
be satisfactory. However, 18% of the schemes were ranked
as being poor quality work. Road alignments, wear and
tear, poor surface finishes and honey combing in concrete
structures resulting from poor quality of workmanship was
observed in villages Feza, Sanam & Sur Kamar in Shangla.
In Gujjer Tangi, Swat road cutting was carried out without
proper slope35
.
To further get some depth in understanding the key
indicators i.e. quality of the CPI schemes; and the Operations
& Management (O&M) systems put in place (including
transparency) were also explored in the HH survey and the
FGD.
4.6.2 Quality
When inquired, 91 percent of the respondents (92 and
89 percent, respectively) were satisfied with the current
condition of the CPI schemes. Other than only 84 percent
satisfaction in Swat (86 and 82 percent for males and females,
respectively), all respondents elsewhere claimed above
88 percent satisfaction, with 100 percent in Lower Dir. In
the districts of Buner, Chitral and Malakand Agency, while
male respondents were 100 percent satisfied, female rate of
satisfaction ranged between 86 to 97 percent. Approximately
9 and 14 percent of females were dissatisfied with drinking
water supply; and link roads and bridges, respectively and
above 93 percent satisfaction levels for the rest of the CPI
schemes. As for males, only 75 percent were satisfied with
the irrigation scheme; 92 percent with link roads and bridges,
and above 93 percent with the rest of the CPI schemes.
Interestingly, 87 percent of non-CO members showed
satisfaction with the CPI schemes, as opposed to 94 percent
of CO members.
In the household survey, fewer females (68 percent) rated
the material used in the CPI schemes as‘good’, as opposed to
males (89 percent). Additionally, 20 percent of females also
claimed to be unaware/unable to respond/make a judgment.
InUpperDir,only55percentoftherespondentsperceivedthe
material used to be as‘good’and 70 and 74 percent in Lower
Dir and Shangla, respectively, while the rest of the districts
received responses between 82 and 96 percent. Interestingly,
a considerable percentage (82) in Swat perceived the material
used as‘good’, despite overall satisfaction levels stated as low.
Overall 79 percent of the respondents termed the material as
‘good’. In the case of link roads and bridges, 77 percent of the
respondents perceived the material used as ‘good’; and 13
percent labeled it as‘average’or‘poor’; while 11 percent said
they ‘didn’t know’. A detailed CPI scheme-wise breakdown is
given in Annex: 1-C in Table 3.3, whereas the percentage of
respondents who considered the quality good is presented
in Graph 3.12.
53.3
80.4
85.7
76.6
89.7
Graph 3.12: Percentage of respondents who considered
good quality of CPI schemes
Drinking water supply
Irrigation
Link road/Bridges
Street pavement and drainage
Other
35	 See Annex 1-B Table 2.5
26
Once again, 79 percent of the non-CO members cautiously
rated the material used in CPI schemes as ‘good’, as opposed
to 86 percent of the CO members with the same rating.
Similarly,workmanshipoftheconstructionwasratedas‘good’
by 73 percent of the respondents; 59 percent by females and
85 percent by males. Only 36 percent of the respondents in
Upper Dir labeled the workmanship as‘good’; and overall 68
percent respondents’ perceiving the workmanship of link
roads and bridges as ‘good’; thus, both reflecting consistent
results as above.
Pre-testing of the scheme before hand over to the
community is another important aspect to ensure the quality
of the scheme. Overall 68 percent of the respondents (73
percent males; and 58 percent females) claimed that the CPI
schemes were tested before being handed over according to
their communities. Complete pre-testing was undertaken in
Buner.
4.6.3 O&M systems
The engineering reports suggest that for the schemes which
were functional, O&M existed and functioned only partially
at 22% of the sites, while at 30% there was no functional
system for O&M36
.
The 15 schemes which were not performing O&M works were
lacking in this regard because:
•	 No O&M committee existed in PI register Meragai, Gujjer
Tangi Badro & Khan Palao in Swat and Khan Abad in
Upper Dir.
•	 No O&M systems or protocols were available for the
implementation of maintenance works at a majority of
the schemes.
•	 In some villages, O&M committees existed but were not
performing their roles & responsibilities in this regard.
Bazkhel Sanam & Sur Kamar in Shangla are examples of
this case.
O & M problems were observed in Sher Khan Bazdara,
Malakand, Mankass, Kabal, and Swat. In all these schemes
there ‘seems’ to be no system to resolve the problems
because of which the scheme is non functional. As a result,
the whole community is suffering.
In the case of Bazkhel, district Shangla, the scheme is pretty
much non functional, since the drains a clogged and there
does not seem to be any organized effort towards making it
functional again.
Existence and functionality of O&M systems are indicators
Awareness of any O&M Committee  Males (YES)
Graphs 3.13 & 3.14: Awareness of O&M Committees – by gender
FEMALES
MALES
Burner
Chitral
Lower Dir
Malakand Agency
Swat
Upper Dir
0
29
3
100
8
8
23
that can determine community levels of ownership and
acceptability of the surrounding CPI schemes. Knowledge of
any O&M system was generally low with 76 percent males;
and only 20 percent females acknowledging them, with the
least amount of awareness in Lower and Upper Dir (overall 40
and 42 percent, respectively).
Approximately 39 percent of respondents claimed to
have made contributions to O&M; 32 percent males and
50 percent females; mostly in Chitral (overall 91 percent
contributions) and less than 45 percent elsewhere. The
largest contribution was in irrigation schemes (55 percent);
and ‘others’ (77 percent). While 52 percent of CO members
interviewed claimed to have contributed to the O&M of the
CPI schemes, even 49 percent of the non-CO members that
were surveyed claimed to have done so as well. Majority of
the respondents (overall 28 percent) claimed to pay for as
and when required. The high spirit of community members
to contribute and even take charge of maintenance was
quite apparent during the FGD sessions. The breakdown of
CPI scheme-wise contributions is as follows:
Additionally, overall 23 percent, but interestingly 29
percent females and only 18 males claimed knowledge of
the existence of an O&M committee. There were very stark
contrasts in female and male respondents in Malakand
Agency and Shangla, where awareness levels of female
respondents appeared to be comparatively very high.
Table 3.7: How do you pay money for maintenance?
Monthly Annually
When
Needed
Never
Don’t
know
% % % % %
Type
of
CPI
Drinking water supply 6.4 2.9 26.9 24.0 39.8
Irrigation 44.4 14.8 40.7
Link road/Bridges 30.3 46.1 23.6
Street pavement and
drainage
9.0 38.8 52.2
Other 39.3 42.9 14.3 3.6
3131
30
30
75
40
29
3
100
8
8
23
Burner
Chitral
Lower Dir
Malakand Agency
Swat
Upper Dir
36	 See Annex 1 Table 2.4
27
Graph 3.15: Performance rating of Project Committees (Good %)
Existence of maintenance funds were acknowledged for
drinking water and supply (33 percent); and link roads and
bridges (32 percent); and the rest for ‘others’ (90 percent).
Respondents stated they were aware that most of the
maintenance funds were being run through SRSP and
then CO bank accounts (Table: 3.8). Overall, 8 percent of
respondents believed that the O&M fund covers its own
maintenance costs, 44 percent believed that it covered none.
Approximately 39 percent of the respondents reported any
knowledge of an O&M Committee; 30 percent denied it; and
32 percent reported no knowledge whatsoever – 66 percent
females did not know, as compared to 12 percent male
respondents.
A gender-wise analysis of how decisions are made for the
fund shows that a very small percentage of females agreed
that they – the beneficiaries and/or the CO members - had
any say (5 percent); whereas SRSP and others were the
main decision-makers (see Table 3.9 in Annex 1-B for more
details). Approximately, 12 percent females and 25 percent
males claimed to be members of the O&M Committee.
Overall highest membership was in Shangla (41 percent).
Overall satisfaction with the Project Committee is provided
in Tables 3.10 and 3.11 in Annex 1-B, both district- and CPI
scheme-wise, with Chitral once again topping the list with
100 percent satisfaction (rated between ‘OK’ and ‘good’). The
highest level of satisfaction with the Project Committees was
reported in Street pavement and drainage, where 56 percent
rated it as ‘good’, and 44 percent selected, ‘OK’, ‘poor’, and/or
‘don’t know’.
With regards to their views on transparency in the planning,
development and O&M of the CPI schemes, the FGD analysis
reflects that 53 percent male respondents claimed to be
satisfied. Only 24 percent female respondents claimed the
same, but an additional 65 percent of them also stated that
they were unaware. Highest levels of efficiency with regards
to perception of transparency were found in Chitral (83
Table 3.8: How are the funds being maintained?
CO bank
Account
With
Project
Committee
With
the CO
Manager
With
the
SRSP
Don’t
Know
Own
help
% % % % % %
Dis-
trict
Buner 33.3 44.4 22.2
Chitral 68.8 6.3 18.8 6.3
Lower Dir 100.0
Malakand
Agency
16.7 41.7 41.7
Shangla 27.3 18.2 36.4 9.1 9.1
Swat 6.5 15.2 39.1 17.4 21.7
Upper Dir 100.0
Table 3.13: How often did you meet during the CPI
planning & construction stages?
Total
Fortnightly Monthly
On
need
basis
Never %
% % % % %
District Buner 42.3 11.5 38.5 7.7 100.0
Chitral 61.9 - 38.1 - 100.0
Lower Dir 9.1 33.3 42.4 15.2 100.0
Malakand Agency 69.4 13.9 16.7 - 100.0
Shangla 54.5 27.3 18.2 - 100.0
Swat 47.5 18.8 33.7 - 100.0
Upper Dir 13.3 36.7 33.3 16.7 100.0
24.6
20
21.1
56.1
Drinking Water Supply
Irrigation
Link road/Bridges
Street pavement and drainage
percent); and Buner (50 percent). The FGD respondents were
most satisfied with transparency and availability of records
in the CPI schemes of street pavement and drainage (64
percent). A detailed table (3.12) can be found in Annex 1-C.
4.6.4 Institutional Maturity
A follow-up to‘Sustainability’this is the evaluation parameter
addressed in this sub-section: Institutional Maturity of the CO,
which assesses the capacity building of the communities to
enable permanent running of the CPI schemes by themselves
in the long-run. Such an assessment can be determined with
the help of the following indicators: Community meetings
during- and post-implementation of CPI schemes; trainings
of community of members; and community’s ability to self-
initiate additional schemes.
4.6.5 Meetings
While 23 to 40 percent of all respondents claimed to have
met for planning and construction discussions on need-basis
for each CPI scheme; 67 percent of respondents claimed to
meet fortnightly on irrigation schemes, followed by 44 and
41 percent on street pavements and drainage; and drinking
water supply, respectively. Even non-CO members claimed
to participate in such discussions, mostly fortnightly (38
percent); and on need-basis (49 percent).
District-wise, respondents appeared the most active in
Malakand Agency, where 69 percent claimed to meet on a
fortnightly basis. In Swat and Lower Dir, the frequency was
more monthly and/or on need-basis:
In terms of frequency of meetings during the planning and
construction phases of CPI schemes, the gender breakdown
is as follows, with 47 percent males (females; 20 percent)
reporting to have gathered on a fortnightly basis, while 40
percent females (males; 20 percent) claimed to meet only on
needs-basis. Approximately 34 percent females claimed to
have ‘never’ participated. Understandably, given the cultural
constraints, once again, males appeared to be more active
and females perhaps being unaware or unable to participate
that constructively.
Withregardstofrequencyofmeetingsafterthecompletionof
the CPI schemes, the highest number of responses, scheme-,
gender- and district-wise were unanimously reported as on
‘need-basis’.
4.6.6 Trainings
In addition to membership, training can be another key
indicator of how active a CO is and the level of awareness of its
members. 46 percent of the respondents/members claimed
to have received any training in the Committee. Interestingly,
28
even non-CO37
members claimed to have received training.
The nature of training received, both gender- and CPI
scheme-wise is illustrated below. Females received the
highest amount of training in financial management, and
males in leadership. However no respondent or any female
member was given any O&M training as compared to male
15 % for male. Similarly, CPI scheme-wise, the greatest
amount of training was received for leadership and financial
management, according to 47 and 21 percent respondents,
respectively, with consistent male and female breakdown
below (and a CPI scheme-wise breakdown inTable 3.9: Annex
1-C):
4.6.7	 Self-initiated community projects
Assuming that the training and high participation of CO
members led to their improved skills and institutional
maturity, a greater percentage of them (27) were involved in
self initiated additional projects, as opposed to 14 percent of
non CO members involved in self help assignments and 86
percent in donor initiated projects.
On inquiry, 9 percent females and 19 percent males reported
that their communities had initiated other projects as well.
Approximately 19 percent CO members claimed to have
done so, as well as 10 percent non-CO members. The highest
response was found in Malakand Agency (43 percent),
followed by Buner and Swat (22 and 21 percent, respectively).
Scheme-wise, street pavements and drainage was reported
as the most popular (34 percent) additional project to have
been initiated. Of these additional projects, 28 percent
males proclaimed them as ‘self-help’, while 72 percent of the
projects were labeled as ‘donor initiated’. Of these projects
were in irrigation (100 percent); and street pavement
and drainage (92 percent). Chitral and Malakand Agency
witnessed 100 percent donor initiated additional projects,
and Buner reportedly had the highest rate (83 percent) of self
initiated projects undertaken.
Support from SRSP
With regards to support from SRSP on the functioning of
CPI schemes, 88 percent respondents were satisfied (50
percent ‘good’ and 38 percent ‘Satisfactory’); 1 percent were
dissatisfied; and 11 percent claimed to be unaware (largely
female respondents).
In terms of SRSP funds, in all the schemes it is mandatory that
15 to 20 percent of the budget comes from the community.
Most of the budget is spent and monitored by the SRSP staff,
but at times when the money is given to the community to
spend, proper records are maintained. Most of the laborers,
both skilled and unskilled, belong to the local community
and were paid by SRSP for their services. While majority of the
female respondents (approximately 80 percent) were largely
unaware (80 percent) of SRSP spending, male respondents
gave scattered views during the FGDs. Overall, 50 percent
of the respondents in Chitral claimed that greater than 50
percent of the funds were utilized within the community;
and 57 percent in Shangla; and less than 43 percent in all
the other 5 districts. CPI scheme-wise, 50 percent of the
respondents, the highest response, stated that greater than
Table 3.14: Nature of Trainings Gender breakdown Total
Disaster
Prepa-
redness
Financial
manage-
ment
Leader-
ship
O & M
Any
other
%
% % % % % %
Sex Male 3.5 15.8 50.9 13.2 16.7 100.0
Female - 56.3 18.8 - 25.0 100.0
Of the female respondents, 58 percent were aware of
SRSP and its work in their communities. Chitral witnessed
100 percent awareness; followed 82 percent of female
respondentsclaimingtobeawareinBuner;andawareness
levels between 46 to 68 percent in the rest of the districts.
Level of awareness of female non-CO members was also
considerably high at 57 percent of the non-members
surveyed.
A highly significant finding was that 64 percent of the
females who were CO members were also a part of
another organization, whereas the rate of participation
of non-CO member females was 10 percent. This could
positively indicate an increase in female mobilization in
local communities due to their involvement in the SRSP-
AusAid CPI schemes.
Whether or not the female respondents had been
actively involved as members, and/or in the planning and
construction phases, almost all of them (97 percent) were
fully aware of the existence of the CPI schemes in their
communities.
50 percent of the funds were utilized in street pavement and
drainage. Details are provided in Table 3.10 in Annex 1-C.
Cohesion and harmony within the CO can be understood
in terms of conflict between members with regard to the
project. A minor percent (3: both males and females) reported
any conflict concerning the CPI schemes, mainly in Buner and
Lower Dir in the following schemes: drinking water supply;
and street pavement and drainage.
19
20
23
23
15
Greater than 50% of SRSP money was utilized within the community (%)
Drinking Water and supply
Irrigation
Link roads and bridges
Street pavement and drainage
Other
Reasons for Conflict:
•	 A minor dispute related to a piece of land, but
resolved on time
•	 A minor issue of land piece bur resolved by the
community elders with in the week
•	 During the construction one household was
reluctant to provide a piece of land for the CPI,
but the issue was resolved immediately
•	 Land problem from the adjacent village arouse
but was resolved on time by the local Revenue
Department
•	 Two tribes are not ready to share the CPI
37	 Approximately 25 percent of non-CO members interviewed; possibly trainings under some other organizations.
29
Table 3.17: Do you think that the project can continue in the absence
of SRSP?
There is no
O&M system
and the com-
munity does
not have any
capacity
There is no
O&M system
but the com-
munity does
have some
capacity
There is no
O&M system
but the
community
has been
trained to
implement
There is
an O&M
system and the
community has
been trained to
implement
There is no
O&M system
and the
community
is actively
contribu-
ting
Don’t
know
% % % % % %
Scheme
type
Drinking
water
supply
28.6 4.8 4.8 33.3 7.1
21.4
Irrigation 42.9 14.3 28.6 14.3
Link road/
Bridges
20.9 18.6 16.3 23.3 4.7
16.3
Street
pavement
and
drainage
7.7 - 15.4 30.8 23.1
23.1
Other 33.3 16.7 16.7 33.3
Majority of the FGD responses endorsed the confidence
of the male and female participants claiming that the CPI
schemes could very well continue to run in the absence of
support from SRSP. However, scheme-wise response reflected
another story, where 43 and 27 percent FGD participants
believed that irrigation and drinking water supply schemes
could not run solely by the communities.
4.7 Impact
4.7.1 Overall impact analysis
All respondents across all 7 districts reported a significant
positive impact of the CPIs implemented under EERP by SRSP.
In the case of villages where a Link Road or a Bridge had been
constructed, respondents in Buner and Malakand Agency
reported a positive change in both cases, as high as, 80 and
77 percent, respectively. Even in a district as conservative as
Shangla respondents claimed that the impact led to between
13 to 16 percent positive changes in education for both girls’
and boys’
Similarly time to fetch water has been reduced by nearly 12
times due to the drinking water supply schemes and whereas
earlier only 34 % had access to drinking water 24 hr, now
nearly 93 % do.
While the survey results reflect that 97 percent respondents
acknowledged a stark positive change in female mobility,
as a result of the CPI schemes; however, findings across the
indicators reflect extreme lack of awareness and participation
on the part of women. They need to be mobilized and
encouraged to take greater initiative and be more involved in
the process for a greater sense of ownership of the schemes,
as well as, higher self-esteem and general knowledge. This is
their key to greater empowerment. Approximately 68 percent
of respondents across all 7 districts acknowledged a positive
impact on women’s free time, enabling them to manage
their daily activities more efficiently and productively. Some,
however, did state that no change was witnessed in this
regard:
With the exception of 23 and 7 percent respondents,
respectivelyinLowerandUpperDir,whoreportednobenefit/
change in marketing of agricultural surplus, 67 percent
respondents across all 7 districts reported a positive impact
in this regard as well. Same is the case with impact on cost of
farm input (and access to business opportunities): with the
exception of 50 (50), 23 (25) and 3 (6) percent respondents,
respectively in Buner, Lower and Upper Dir, who reported no
benefit/change, approximately 68 (89) percent respondents
across all districts reported a positive impact, respectively.
4.7.2 Drinking Water Supply - CPI Scheme Impact
This segment analyzes the immediate impact of the
Drinking Water Supply CPI on reducing the time and effort
taken to get to the water source. Overall, before DWSS CPI
implementation, the average time taken to reach the water
source and come back was 24 minutes for males, which,
after the implementation of the schemes, was cut down to
a fifth; to around 6 minutes. For females, an initial average
time of 47 minutes, was cut drastically to a twelfth of the
original amount of time taken; down to 4 minutes. Overall,
it now takes an average of 5 minutes to get to and from the
water source than the pre-CPI implementation estimate of
35 minutes, reflecting a major reduction in time, allowing
community members to allocate their time more efficiently
on other important daily tasks. The numbers now indicate
that this responsibility is now being shared amongst the rest
of the household members, most often the female child (21
percent), thus giving females higher opportunities utilize
their time efficiently since the CPI scheme implementation
has increased ease of accessibility.
Percentage distribution of tasks undertaken by community
members in a typical day shows that females now spend
approximately 90 percent of their time on other household
chores:
District-wise, drastic savings in time allocation have been
realized by beneficiaries due to DWS CPI. In Chitral and Upper
Dir, it now takes almost no time to reach the most utilized
water source. The time saved in Lower Dir, Swat and Shangla
is almost 12 times as little. However, it takes the beneficiaries
in Malakand longer to reach the DWS CPI source now than it
did before installation.
Table 3.18: Is there any change in women’s free time
Large
benefits
Some
benefits
No
benefit
Don’t
Know
District Buner 40.0% 10.0% 50.0%
Lower Dir 22.5% 32.5% 45.0%
Malakand Agency 50.0% 29.2% 20.8%
Shangla 14.3% 40.0% 42.9% 2.9%
Swat 32.4% 35.1% 5.4% 27.0%
Upper Dir 30.0% 66.7% 3.3%
Average minutes after CPI by
gender
Average minutes before CPI by gender
Mean Minutes Mean Minutes
Male 6 Male 24
Female 4 Female 47
Table 3.19: Average time taken to reach water source and return (in minutes),
before and after the implementation of DWS CPI schemes; by gender
Table 3.20: Average time taken to go to water source and come back (in minu-
tes), before and after the implementation of DWS CPI schemes; by District
Average minutes by location
District Mean Minutes District Mean Minutes
Buner 9.1 Buner 32.3
Chitral N/A Chitral 10.0
Lower Dir 4.2 Lower Dir 48.7
Malakand 11.4 Malakand 2.7
Shangla 2.1 Shangla 35.1
Swat 3.8 Swat 40.5
Upper Dir N/A Upper Dir 69.0
Total 4.8 Total 34.9
30
Before the implementation of DWS CPI schemes, 60 percent
of respondents from 6 out of the 7 districts reported that
mainly adult women would fetch water for the HH’s use. The
only exception was Malakand Agency, where water is most
often fetched by a female child (over 60 percent cases). After
the implementation of DWS CPI, the highest percentage is
still of adult women who fetch water, but this has almost
halved to approximately 34 percent; with the exception of
Chitral and Malakand Agency.
Satisfaction levels with the new DWS CPI schemes were 100
percent for males and 97 percent for females. In addition to
coverage of lesser distances now, another reason for high
satisfaction was that the frequency of water availability was
also raised by almost 100 percent after the implementation
of the DWS CPI schemes. The tables 3.21 and 3.33 reflect the
stark positive differences:
4.7.3 Street pavements and drainage
Analyzing the immediate impact of the Street Pavement
and Drainage CPI scheme, in terms of water disposal and
improvement in the local environment, will eventually help
to evaluate the current health scenario of the beneficiaries.
Majority of the respondents (96 percent) in the 3 districts:
Malakand Agency, Shangla and Swat agreed that their streets
had stagnant water with no effective way of its disposal. Post
SPD CPI, the situation positively reversed with approximately
92 percent of the respondents indicating that the issue of
stagnant water in the streets had either been completely or
partially eliminated, with majority leaning towards complete
elimination. Hence, the SPD CPI scheme has been a source
of great convenience for the beneficiaries. It not only saves
them transport time, but may also result in better health
as the diseases contracted from stagnant water might be
greatly reduced.
Approximately 96 percent of the respondents from the 3
districts reported a rampant foul smell due to improper
drainage systems. Post-SPD CPI, whereas in Shangla and
Swat the situation was quite favorable towards the SPD CPI,
with 75 and 93 percent respondents from both districts,
respectively claiming a reduction in foul smell, there was a
50/50 split in Malakand Agency. This calls for revisiting the
CPI scheme impact in Malakand.
In regards to domestic waste water’s appropriate disposal,
the responses generated have made for an interesting
analysis. Pre-SPD CPI, the distinction by sample district claims
that whereas in Shangla 100% of the respondents claimed
that the waste water was not being disposed properly; the
situation was relatively better in Swat with only half the
respondents claiming that it was not. Post-SPD CPI, the
scheme has performed well enough almost half the male
respondents to agree that domestic waste water is now
being disposed properly in contrast to 93 percent stating
the contrary before the implementation of the scheme.
In the same way, the percentage of female respondents
increased from 67 to approx 89 percent. In Swat, now up to
75 percent respondents are satisfied with the output of the
scheme, whereas majority of the respondents from Shangla
(approximately 62 percent) are still claiming that waste water
is not disposed properly.
Furthermore, the resulting answer to the question whether
there has been any significant decrease in Mosquitoes or flies
the answer was no from 100 % of the female beneficiaries,
whereas 7.5 % male said that it did. The answer to the query
of improved children health before the CPI scheme of street
pavement and drainage was a resounding 100 percent ‘No’
on all accounts. Similarly, to the Post implementation of the
CPI scheme, above 50 percent of the respondents in both
Malakand Agency and Shangla perceived an improvement
and positive effect on the health of the children as a result.
If this can assessed based on actual figures, this would
reflect the impact the CPI schemes have had on increased
life expectancy and economizing family budgets to save the
amount of money spent on health treatment.
With regards to households using any additional
water treatment method for drinking water after the
implementation of DWS CPI scheme; a 100 percent claim
of no water treatment was reported. Though, Malakand
and Swat still seemed to have its doubts about the purity
of water provided and thus continued to use some form of
water purification methodology. Once again, strengthening
the claim that whereas, other districts were saving time and
manual input, Malakand Agency was still struggling with
the concept. This highlights the need for further training
and follow-up with Cos in Malakand Agency. Similarly, while
almost 100 percent respondents from Malakand Agency
and Swat reported that the water from the CPI schemes
had a clear appearance, sweet taste and was odorless; they
reported cases of disease due to these water schemes (see
Table 3.11 in Annex 1-C). This rendition of doubt (still using
some form of water treatment) by Malakand and Swat would
be better explained if the quality of water provided by CPI
was unsatisfactory, but ironically both districts claim almost
zero percent dissatisfaction. There is however, one point that
may support their claim, that being the information that
Malakand and Swat both have reported a higher percentage
of diseases contracted through water (even after CPI) as
compared to other districts. This might be cause for worry,
hence, needs to be investigated.
Table 3.21: The frequency of water available to HH before implementation of
the DWS CPI scheme; by Gender
Before CPI? Male Female Total
Full time/24 hours 37.6 34.4 36.1
Daily intermittently 53.2 61.5 57.1
Alternate days 0.0 2.1 1.0
Twice a week 9.2 1.0 5.4
Others 0.0 1.0 0.5
Total 100.0 100.0 100.0
Table 3.22: The frequency of water available to HH after implementation of the
DWS CPI scheme; by Gender
After CPI? Male Female Total
Full time/24 hours 97.1 90.1 93.9
Daily intermittently 2.9 7.7 5.1
Alternate days 0.0 1.1 0.5
Twice a week - - 0
Others 0.0 1.1 0.5
Total 100.0 100.0 100.0
Table 3.24: Respondents claims of cases of elimination stagnant water after
CPI?
Yes No To some
extent
% % %
District Malakand 100.0 0 0
Shangla 50.0 25.0 25.0
Swat 97.7 2.3 0
31
Among the above listed facilities, a rather unique shift was
witnessed in the mode of transport used to gain access
the nearest general/grocery store. Comparing before- and
after- CPI construction cases, the mode of transport ‘on
foot’ surprisingly decreased (except in Buner); the usage of
motorbikes and four wheel engine vehicles increased (other
than in Lower Dir); and also witnessed was an increase in
usage of public transport across all districts. This is quite
alarming since the first assumption that can be made is
that the distance due to the link roads has in fact, expanded
4.7.4 Link roads and bridges
The impact of implementation of CPI schemes of link roads
and bridges, in other words, communication infrastructure
has remarkably decreased the average time taken for
community residents to avail essential daily requirements
including access to the nearest drinking water supply;
distance to grocery shopping; distance to girls’ and boys’
schools; access to hospital; and distance to the nearest local
Tehsil administration:
Table 3.25: Before CPI Schemes in Communication Infrastructure – Average
(mean) time taken to acquire the following facilities (minutes):
District Drin-
king
water
supply
Grocery
shopping
/ General
store
Boys’
school
Girls’
school
Hospital Local
Tehsil
administ-
ration
Buner 46.5 1 36.6 38.1 9.8 1
Lower Dir 17.8 33.4 13.2 16.3 13 1
Malakand 4.2 37.9 29.7 30.1 39.3 51.6
Shangla 15.6 145.4 115.3 123.9 197.4 133.3
Swat 110.6 151.6 126.3 121.6 162.8 54
Upper Dir 17 35.4 42.4 23.9 71.6 9.3
Total 39.7 84.1 67.2 61 97.3 49.2
Table 3.26: After CPI Schemes in Communication Infrastructure – Average
(mean) time taken to acquire the following facilities (minutes):
District Drin-
king
water
supply
Grocery
shopping
/ General
store
Boys’
school
Girls’
school
Hospital Local
Tehsil
administ-
ration
Buner 17.5 1 15.4 17.1 5.3 1
Lower Dir 9.3 17.4 6.7 8.6 6.1 1
Malakand 1.6 12.1 14.1 14.8 24 28.8
Shangla 9.6 36.9 12.6 14.8 43.9 19.1
Swat 28.9 41.7 27.6 24.8 52.7 46.2
Upper Dir 5.4 14 17.8 11.8 32.7 5.4
Total 12.9 25.1 15.6 14.3 30.3 16.4
rather than the reverse, which would placed the community
members at a greater convenience.
The usage and hence, relevance of the link roads and bridges
constructed under the CPI schemes is detailed inTable 3.12 in
Annex 1-C. Of the 3 percent respondents in Malakand Agency
who claimed to not use it all, 33 percent of them stated that
the new infrastructure was of no use to them. The 8 percent
(approximately) respondents in Swat who claimed the same
all reported‘poor quality’as the reason.The rest of the higher
majority of respondents, however, in both districts, and
elsewhere were highly satisfied with the quality of the new
communication infrastructure.
In terms of overall traveling cost, it decreased by 25 percent
for all respondents in Lower Dir and between 25 to 50 percent
for respondents in Upper Dir. As for the 5 districts, travel
cost decreased between 25 to 75 percent at varying levels.
Additionally, there was an overall 75 percent decrease in the
cost of freight transport due to the new CPI communication
infrastructure across all districts except Buner, where no
change was witnessed at all. The detailed breakdown of the
impact is illustrated in Table 3.12 in Annex 1-C.
4.7.5 Irrigation
The household survey results reflect that there was a
remarkable increase in crop production of community
members surveyed owing to the implementation of CPI
irrigation schemes. While 100 percent respondents reported
a 50 percent increase in wheat production; between 50 to
80 percent reported a 100 percent increase in rice and grain
production. Production of maize also increased considerably.
In vegetables, 100 percent increase in production of onions;
tomatoes; lady fingers; and garlic was also reported by all
respondents. Fruits such as apples; plums; and apricots
comparatively did not witness such levels of increase in
production. Production increments ranged between 50 to 70
percent. A 63 percent increase in rearing was also reported
by respondents; with 10 out of 16 respondents surveyed
claiming an increase, and 6 reporting no change.
With regards to the overall impact on farm revenue, as
indicated in the table below, 100 percent respondents
reported minimum 50 percent increase. This is a substantial
outcome of the irrigation CPI scheme, raising the economic
empowerment of beneficiaries working on agricultural land.
Table 3.29: Overall Farm Revenue
Farm revenue 50% 70% 80% Total
Overall Farm revenue 28.6 42.9 28.6 100
32
4.8 Conclusions and Recommendations
In view of the early recovery context and the difficult
terrain, SRSP’s outreach and successful conclusion of this
challenging project is commendable. The schemes have
been implemented in areas where the government had
limited outreach and other non-governmental players had no
presence. . Working in the target areas meant many hours of
driving and trekking through often rugged and mountainous
terrain. Despite these difficulties, the overall quality of work
is of good standards. All project outputs were also achieved
within the agreed timelines. Thanks to a motivated team,
nearly 400 community organizations were formed, local
priorities identified and over 200 CPIs implemented within a
short span of 9 months.
Overall the communities have reported a very positive
impact of the CPI program.
•	 Post implementation of the DWSS, the average time
taken to reach the water source decreased significantly,
allowing community members, particularly females, to
allocate their time more efficiently to other important
daily tasks. Satisfaction levels with the new DWS CPI
schemes were 100 percent for males and 97 percent for
females, also, implying lower risks of waterborne diseases.
•	 In case of Sanitation and drainage CPIs, the majority of
the respondents (92 percent) in the 3 districts where
the scheme was implemented noted that the issue of
stagnant water in the streets had either been completely
or partially eliminated. Additionally, 75 and 93 percent
respondents in Shangla and Swat, respectively claimed
reduction in foul smell, while 50 percent respondents
reported the same in Malakand Agency.
•	 The new link roads and bridges has remarkably decreased
the average time taken for community residents to
avail essential daily requirements; travel to the nearest
drinking water supply schemes; grocery stores; girls’
and boys’ schools; hospital; and the nearest local Tehsil
administration. The respondents reported an overall 75
percent decrease in the cost of freight transport across all
districts except Buner, where no change was reported.
•	 The survey also shows considerable increase in crop
production due to the implementation of irrigation
schemes. Nearly all respondents reported a 50 percent
increase in wheat production; while between 50 to 80
percent reported a 100 percent increase in rice and grain
production. With regards to the overall impact on farm
income, 100 percent respondents reported a minimum
of 50 percent increase.
•	 Combined capacity of the 3 MHPs in Chitral, Swat and
Upper Dir has the designed capacity of 225 KW, which
will benefit approximately 600 HH. It was reported that
the MHP in Bhamborate, Chitral has been functioning
at full capacity and is not only supplying electricity to
the communal HH’s, but also to a local hotel, Maternity
Home, Funeral Hall, a school and also mosque.
•	 All 60 schemes in the evaluation sample were physically
verified to be on the ground. Except for one scheme all
the rest have been identified by the local community as
fulfilling their priority need. Given the tight time lines and
the difficult terrain, this is a remarkable achievement
•	 Project documentation has been meticulously kept in the
regional office, showing detailed record of community
interaction and the field processes from the ‘first
dialogue’ to the handing of checks in the 3rd dialogues
and the subsequent installments. However the technical
documentation covering the design basis, design
calculations and the environmental assessment remains
a weak area. .
•	 The CPIs are predominantly functional, and have a
positive impact on the communities; however some
of these (about 10 %) are not delivering the required
benefits due to poor quality and/or weak O&M systems.
•	 A majority of females in the sample confirmed that
the CPIs chosen represented their priority needs and
directly benefiting them. However CPI implementation
remained a predominantly male affair. Out of the 64
WCO which were formed, a total of 4 CPIs were for the
women organization, which is disproportionally low.
•	 Although CPIs such as DWSS or sanitation and drainage
were being implemented there was little attempt to
build the capacity of the organizations on related issues
such as health and hygiene.
•	 SRSP’s presence in the project areas was a significant
factor in the rapid response and timely completion
of the project activities. Interviews with senior SRSP
managers suggest a continued interest in the region and
a commitment to maintain the needed support for post
project support through existing resources.
•	 CPIs are highly visible, ensure immediate benefits to
the community and also typically consume the largest
chunk of development budgets in any community
program. Accordingly these should receive a higher
level of attention from the feasibility through design,
implementation as well as the O&M. The survey shows
a generally good performance on the “implementation
fronts” however the design and O&M phases could
benefit from further attention. Among other areas of
focus the CPIs are generally small in scope, however a
rapid “environmental screening and mitigation” protocol
could help some categories of schemes. Overall the
team recommends additional investments in staff skills
for field surveys and design; use of design standards
and guidelines and customized training modules for
O&M practices. This will allow SRSP to further build on
its current success and ensure that the CPIs continue to
yield long term dividends without the need for any hand
holding or follow up repairs in project areas that are
generally remote and difficult to access.
Specific recommendations:
1. Improve Engineering technical feasibility:
1.1.	 Establish policy to adhere to basic technical
engineering standards.
1.2.	 Outsource technical assistance on engineering
complex structures
1.3.	 Outsource essential engineering tests.
1.4.	 Acquire modern survey and test equipment
	 1.4.1. Total Station
	 1.4.2. GPS enabled cameras
	 1.4.3. Use Google earth where possible, else develop
proper base map layout to ensure proper planning.
1.5.	 Establish Mobile lab for remote locations to ensure
that the necessary tests such as soil analysis, CBR are
carried out when necessary.
33
1.6.	 Staff training
2. Improve Environmental Feasibility
2.1.	 Revisit the Environmental review process
2.2.	 Hire an environmental engineer.
2.3.	 Staff training
3. Improve Quality of Scheme Construction
3.1.	 Establish quality standards
3.2.	 Training of project committee
3.3.	 Ensure a effective ratio of field engineers to scheme
ratio for effective field supervisor
3.4.	 Training of‘skilled’and unskilled local labor.
4. Improve O & M system
4.1.	 Develop scheme specific O&M schedules
4.2.	 Develop basic troubleshooting guidelines defining
what to do and when with clearly defined roles and
responsibilities.
4.3.	 Establish intensive training of O&M committee and
members and ensure refreshers.
4.4.	 Encourage an O&M fund and before hand-over of the
scheme.
4.5.	 Monitor outcomes instead of outputs.
4.6.	 Use of cell phone technology to monitor O&M
5. Focus on Female organization or investments:
5.1.	 Establish link between investment in CPI and female
activities.
	 5.1.1. Implement CPI’s only where WCO are formed or
at least where female SOs is given access.
6. Plan for CPI investments holistically.
6.1.	 This is especially important in the case of DWSS and
Sanitation CPIs where basic health and hygiene should
be seen as a overarching framework
6.2.	 Irrigation related schemes should be followed up with
water conservation and erosion control trainings.
34
ANNEXURES 1A
Table 1.1 Environmental Screening
Documentation not available/Inadequate
S.No. District Village Scheme Type
1 Swat Meragai Irrigation channel Lining & RT wall
2 Swat Aladand Dherai Irrigation (Gabion structure)
3 Swat Pengen Street pavement & Drainage
4 Swat Mankass Qabel DWSS (HP)
5 Swat Faqira Link Road Rehabilitation
6 Swat Kamay RCC Bridge
7 Swat Samteer Link road (Earthen)
8 Swat Kaho Link Road Rehabilitation)
9 Swat Babo Maira Irrigation (Ramp Pump)
10 Swat Pirkhel khass RCC cause way
11 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian)
Table 1.2 Design Basis
Unavailable/Inadequate
S.No. District Village Scheme Type
1 Swat Faqira Link Road Rehabilitation
2 Swat Kamay RCC Bridge
3 Swat Quanj Street pavement & Drainage
4 Swat Kokari Sar Link road (Earthen & PCC)
5 Swat Samteer Link road (Earthen)
6 Swat Kaho Link Road (Rehabilitation)
7 Swat Shagai Street pavement & Drainage
8 Swat Bar Jopeen Street pavement & Drainage
9 Swat Faqira Street pavement & Drainage
10 Swat Pirkhel khass RCC cause way
11 Swat Pengen Street pavement & Drainage
12 Malakand Palai khpa Link Road (PCC)
13 Shangla Sanam Link Road (PCC)
14 Shangla Sur Kumar Link Road (PCC)
15 Swat Gujer Tangi Badro Link Road
16 Shangla Sanila Street Pavement & Drainage
17 Lower Dir MataKhazana Link Road
18 Lower Dir Moranai Link Road
19 Lower Dir Munjay Link Road
20 Upper Dir Panakot Link Road
21 Lower Dir Shal Kandi Link Road
22 Swat Baghgay Maloch RCC Cause Way
23 Shangla Feza Link Road (PCC)
24 Upper Dir Malow Suspension Bridge(Pedestrian)
25 Upper Dir Shamorgar PCC Link Road
26 Swat Akhun Baba PCC Link Road
27 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian)
35
Table 1.3 Design Calculations
Not available
S.No. District Village Scheme Type
1 Swat Faqira Link Road Rehabilitation
2 Swat Kamay RCC Bridge
3 Swat Quanj Street pavement & Drainage
4 Swat Kokari Sar Link road (Earthen & PCC)
5 Swat Samteer Link road (Earthen)
6 Swat Sorykad DWSS (Gravity Flow)
7 Swat Kaho Link Road (Rehabilitation)
8 Swat Badardam DWSS (Gravity Flow)
9 Swat Shagai Street pavement & Drainage
10 Swat Bar Jopeen Street pavement & Drainage
11 Swat Faqira Street pavement & Drainage
12 Swat Pirkhel khass RCC cause way
13 Swat Pengen Street pavement & Drainage
14 Malakand Palai khpa Link Road (PCC)
15 Buner Banju Tangey DWSS (Gravity Flow)
16 Buner Ambela DWSS (Gravity Flow)
17 Shangla Sanam Link Road (PCC)
18 Shangla Sur Kumar Link Road (PCC)
19 Swat Gujer Tangi Badro, Islampur Link Road
20 Shangla Sanila Street Pavement & Drainage
21 Swat Dardyal,Qabel DWSS Graivty Flow
22 Lower Dir Inzaroo DWSS Graivty Flow
23 Lower Dir MataKhazana Link Road
24 Lower Dir Moranai Link Road
25 Lower Dir Munjay Link Road
26 Upper Dir Panakot Link Road
27 Lower Dir Shal Kandi Link Road
28 Swat Baghgay Maloch RCC Cause Way
29 Upper Dir Malow Suspension Bridge(Pedestrian)
30 Upper Dir Shamorgar PCC Link Road
31 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian)
32 Chitral Khoran dok DWSS Gravity flow
Inadequate
S.No. District Village Scheme Type Remarks
1 Swat Yakh Tangey DWSS (Gravity Flow) Missing for water storage reservoir
2 Swat Akhun Baba PCC Link Road Missing for axle loads etc.
3 Swat Shagai Ghwajalgai DWSS (Gravity Flow) Missing for water storage reservoir
4 Malakand Khan Palao DWSS (Hand pump) Missing for HP apron and foundation
5 Swat Amin Abad Link Road Missing for axle loads etc.
6 Malakand Sherkhan,Bazdara DWSS (Hand pump) Missing for HP apron and foundation
7 Shangla Tangir Suspension Bridge(Pedestrian) Load bearing not mentioned
8 Shangla Abbasin Colony Gravity Flow Missing for water storage reservoir
9 Shangla Feza Link Road (PCC) Missing for axle loads etc.
10 Lower Dir Asilo DWSS Gravity Flow Missing for water storage reservoir
11 Lower Dir Danwa DWSS Gravity Flow Missing for water storage reservoir
12 Upper Dir Doonpayeen DWSS Gravity Flow Missing for water storage reservoir
13 Swat Mankass Qabel DWSS (HP) Missing for HP apron and foundation
14 Swat Yakh Tangey DWSS (Gravity Flow) Missing for water storage reservoir
36
Table 1.4 Construction Drawings
Unavailable
S.No. District Village Scheme Type
1 Malakand Khar DWSS (Hand pump)
2 Swat Gujer Tangi Link Road
Inadequate
Sr. District Village Scheme type Remarks
1 Swat Jabba DWSS (Hand pump Plan shows 3 hand pumps, section shows a Dug well with a storage reservoir
Table 1.5 PI Register
Not available
Sr District Village Scheme type Remarks
1 Swat Jabba DWSS (Hand pump)
2 Swat Meragai Irrigation channel Lining & RT wall
3 Swat Khar DWSS (Hand pump)
4 Swat Gujer Tangi Badro, Islampur Link Road
5 Lower Dir MataKhazana Link Road
6 Lower Dir Moranai Link Road
Table 1.6 Project Completion Report
Not available
Sr District Village Scheme type Remarks
1 Swat Shao MHP 75Kw Project not handed over as yet
2 Buner Bazarkot Foot Bridge (Suspension) Not found in PI file
3 Buner Riaz Abad, Ambella DWSS (Hand Pumps) Not found in PI file
4 Chitral Khoran dok DWSS (Gravity flow) CPI Failed
Inadequate
Sr District Village Scheme type Remarks
1 Buner Banju Tangey DWSS (Gravity Flow) Date and signatures missing
2 Buner Ambela DWSS (Gravity Flow) Date and signatures missing
3 Shangla Abbasin Colony Gravity Flow Signatures are missing
4 Swat Lawar Deolai, Qabil Irrigation Channel Signatures are missing
5 Chitral Kuru Bala Dug Well CPI Failed; not completed
Table 1.7 Completion Certificate
Not available
Sr District Village Scheme type Remarks
1 Swat Shao MHP 75Kw Project not handed over as yet
2 Buner Bazarkot Foot Bridge (Suspension) Missing in PI file
3 Buner Riaz Ambella DWSS (Hand Pumps) Missing in PI file
Inadequate
Sr District Village Scheme type Remarks
1 Swat Banju Tangey DWSS (Gravity Flow) Dates and SRSP Officials’signatures missing
2 Buner Ambela DWSS (Gravity Flow) Dates and SRSP Officials’signatures missing
3 Chitral Kuru Bala Dug Well Completion certificate not made as CPI failed
37
Table 1.8 Handing over Certificate
Not available
Sr District Village Scheme type Remarks
1 Swat Shao MHP 75Kw Not Handed over
2 Buner Bazarkot Foot Bridge (Suspension) Not available in PI file
3 Chitral Bamburate MHP Not Handed Over
4 Chitral Kuru Bala Dug Well Scheme failed so not handed over.
5 Upper Dir Khan abad MHPP Not available in PI file
38
ANNEXURES 1B
Table 2.1 Scheme Layouts
Schemes with Layout differences
Sr District Village Scheme Remarks
1 Swat Yakh Tangey DWSS (Gravity Flow) •	 4 transmission lines detailed in plans, but 7 transmission lines
observed on site
•	 Plan described previously existing water tank in between intake
chamber and water storage tank; actually, there was a direct line
from the intake chamber to the main water storage tank.
•	 Planned main supply line was of 2‘’dia and 7290 rft length. On
ground a 1.25’’dia and 9000 rft length was observed
2 Buner Banju Tangey DWSS (Gravity Flow) •	 In the drawings, there was only 01 storage tank with 01 supply
line; 02 water storage tanks and 02 supply lines observed on site
3 Shangla Abbasin Colony DWSS (Gravity Flow) •	 Drawings showed two supply lines from the storage tank, how-
ever it was observed that only one line was in connection with
the storage tank while the second line was directly connected to
the main supply line.
4 Swat Gujer Tangi Badro,
Islampur
Link Road •	 In designs, 07 RCC culverts were shown; however no culverts
were constructed on site.
5 Lower Dir Danwa DWSS (Gravity Flow) •	 In designs, there was 1 source planned. However, 2 sources were
observed.
6 Swat Baghgay Maloch RCC Cause Way •	 In drawing, 06 pipe culverts were shown at one location. Howe-
ver 2 culverts were constructed in different location with 2 pipes
each.
7 Chitral Kuru Bala Dug Well •	 Site changed by community.
8 Lower Dir Asilo DWSS •	 The distribution network on site does not match the plans
•	 There is no Storage tank in the plan
•	 Planned number of lines from the distribution tanks are 3 vs 9
on site.
9 Swat Sorykad DWSS •	 4 distribution lines coming out of the tank vs planned 2
39
Table 2.2 Design Validation
Schemes‘not built as per approved design’
Sr District Village Scheme Remarks
1 Shangla Sanam Link Road (PCC) 850 rft of drains planned were not constructed at site.
Length of PCC pavement was changed compared to design
2 Swat Gujer Tangi Link Road None of the culverts were constructed
3 Swat Mankass Qabel DWSS (HP) 120ft drilling depth was mentioned, however no drilling was underta-
ken, and a Hand Pump was installed over an existing dug well
It was also noted that a 4“ dia PVC pipe of 124 rft had not been installed
at site
4 Chitral Kuru Bala Dug Well CPI failed/not completed. Resistivity test not conducted
5 Buner Banju Tangey DWSS (Gravity Flow) Length
Main Line 1
Main Line 1
Supply Line 1
Supply Line 2
Supply Line 3
Supply Line 4
Supply Line 5
Design
3608’
NA
2840’
1360’
2240’
2410’
NA
Actual
1700’
600’
1500’
2000’
1750’
1800’
1600’
6 Shangla Abbasin Colony DWSS (Gravity Flow) Length
Water Tank
Main S. Line
Supply line 1
Supply line 2
Design
14’
15000’
1200’
1400’
Actual
13.5’
19700’
550’
450’
7 Swat Amin abad Link Road Length
PCC Road
RT wall
Cutting
Design
800’
55’with 5’h
450’
Actual
150’
75’with 3.5’h
700’
8 Swat Samteer Link road (Earthen) Length
PCC
RT wall
Design
250’
160’
Actual
Not Done
750’
9 Shangla Sanam Link Road (PCC) Length
PCC Pavement
Side Drain
Design
850’
850’
Actual
1150’
NA
10 Swat Meragai Irrigation channel
Lining & RT wall
Length
Channel
RT wall 01
RT wall 02
Design
750’
70’
70’
Actual
880’
30’
25’
11 Swat Quanj Street pavement &
Drainage
Length
PCC Pavement
Side Drains
Stairs
Design
1482’
1482’
150’
Actual
1190’
464’
50’
12 Shangla Sanila Street Pavement &
Drainage
Length
PCC Stair (L)
PCC Street (L)
Side Drain (L)
Design
799’
1034’
1833’
Actual
975’
827’
780’
40
Table 2.3 Schemes Design & estimate II
Schemes with‘minor’variations
Sr District Village Scheme Remarks
1 Swat Faqira Link Road Rehabilitation •	 Length of PCC link road planned was 1200 ft. However, at site it was 1350ft. 80
ft of planned RW were not constructed.
•	 Design quantity of cutting was 600ft in BOQ; however at site 700ft of cutting
was noted
2 Swat Jabba DWSS (Hand pump) Drilling Depth
HP # 01
HP # 02
HP # 03
Design
150’
150’
150’
Actual
160’
85’
110’
3 Swat Khan Palao DWSS (Hand pump) Minor difference was observed in drilling depth
4 Swat Pengen Street pavement & Drainage Minor difference was observed in street pavement and drainage lengths
5 Swat Palai khpa Link Road (PCC) Length
Pavement
Side drain
Pavement width
Design
1400’
1400’
12’
Actual
1250’
1270’
14’
6 Swat Sherkhan,
Bazdara
DWSS (Hand pump) Drilling Depth
HP # 02
HP # 03
HP # 04
HP # 05
Design
150’
150’
150’
150’
Actual
135’
135’
70’
105’
7 Buner Ambela DWSS (Gravity Flow) Minor difference was observed in storage tank dimension and supply line length
8 Buner Bazarkot Foot Bridge (Suspension) Minor difference was observed in railing length
9 Shangla Feza Link Road (PCC)
Pavement (L)
Pavement (W)
Side Drain (L)
Design
900’
08’
900’
Actual
850’
09’
600’
10 Shangla Sur Kumar Link Road (PCC)
Pavement (L)
Pavement (W)
Side Drain (L)
Design
850’
08’
850’
Actual
900’
09’
500’
11 Buner Riaz Abad DWSS (Hand Pumps) Drilling Depth
HP # 01
HP # 02
HP # 03
Design
130’
130’
130’
Actual
155’
125’
139’
12 Shangla Sanila Street Pavement & Drainage
PCC Stair (L)
Pavement (W)
Side Drain (L)
Design
799’
04’
1833’
Actual
975’
05’
780’
13 Lower Dir Asilo DWSS Gravity Flow Minor difference was observed in storage tank dimensions and supply line length
14 Lower Dir Danwa DWSS Gravity Flow Minor difference was observed in storage tank dimensions and supply line length
15 Upper Dir Doonpa-
yeen
DWSS Gravity Flow Minor difference was observed in Intake chamber and storage tank dimensions
and supply line length
16 Lower Dir Mata Kha-
zana
Link Road
Link Road (L)
Link Road (W)
Side Drain (L)
Design
988’
10‘
700‘
Actual
1195’
08‘
280‘
17 Lower Dir Munjay Link Road
Link Road (L)
Link Road (W)
Side Drain (L)
Design
700’
10‘
500‘
Actual
740’
10‘
740‘
18 Upper Dir Panakot Link Road
Link Road (L)
Link Road (W)
RT Wall (L)
Design
1350’
10‘
275‘
Actual
1220’
10‘
252‘
19 Lower Dir Shal Kandi Link Road
Link Road (L)
Link Road (W)
Design
1100’
10‘
Actual
1126’
10‘
20 Upper Dir Shamorgar PCC Link Road
Link Road (L)
Link Road (W)
Design
1100’
10‘
Actual
1300’
10‘
21 Chitral Khoran dok DWSS gravity Flow Minor difference was observed in storage tank dimensions and supply line length
41
Table 2.4 Schemes O&M
Schemes with poor O&M
Sr District Village Scheme Remarks
1 Swat Faqira Link Road Rehabilitation There was no O&M committee
2 Swat Meragai Irrigation channel Lining &
RT wall
There was no O&M committee
3 Swat Samteer Link road (Earthen) No O&M system in place
4 Malakand Pengen Street pavement & Drainage There was no O&M committee
5 Malakand Sherkhan,
Bazdara
DWSS (Hand pump) O&M was deemed not functional since 02 HPs had been out of order for the last
one month
6 Shangla Bazkhel Drainage No O&M system in place
7 Shangla Feza Link Road (PCC) There was no O&M committee
8 Shangla Sanam Link Road (PCC) There was no O&M committee
9 Shangla Sur Kumar Link Road (PCC) There was no O&M committee
10 Swat Gujer Tangi
Badro
Link Road There was no O&M committee
11 Swat Sanila Street Pavement & Drainage There was no O&M committee
12 Swat Mankass
Qabel
DWSS (HP) There was no O&M committee
13 Swat Dardyal,
Qabel
DWSS Gravity Flow The scheme was not functional for the last two months because the water source
had frozen. Community members said that the source had been damaged and
that they plan to reconstruct a cut off wall once the snow melts fully. The team
was further informed that the source is currently inaccessible
14 Upper Dir Shamorgar PCC Link Road No O&M system in place
Table 2.5 Scheme Workmanship (Also See Annex 8 for pictures)
Schemes had Poor Workmanship
Sr District Village Scheme Remarks
1 Shangla Feza Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the
surfaces observed as well as honeycombing in concrete structure
2 Shangla Sanam Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the
surfaces observed as well as honeycombing in concrete structure
3 Shangla Sur Kumar Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the
surfaces observed as well as honeycombing in concrete structure
4 Swat Gujer Tangi Badro Link Road Cutting had been carried as preliminary work for the road, however, no
proper side slope was observed
5 Swat Samteer Link road (Earthen) Workmanship observed was very poor. There was an irregular finish to the
surfaces observed as well as honeycombing in concrete structure
6 Lower Dir Mata Khazana Link Road Workmanship observed was very poor. There was an irregular finish to the
surfaces observed as well as honeycombing in concrete structure
7 Swat Quanj Street pavement & Drainage Workmanship observed was very poor
8 Swat Sanila Street Pavement & Drainage Workmanship and quality of work observed was very poor
9 Upper Dir Khan abad MHPP Workmanship and quality of work in power house observed was very
poor
42
Table 2.6 Schemes Functionality
Schemes not verified physically as they were not operational at the time of visit
Sr District Village Scheme Remarks
1 Swat Meragai Irrigation channel Lining &
RT wall
•	 Irrigation was not needed during the time of the visit
•	 According to some community members the scheme was not
functional due to flood damages
•	 However, the community planned to repair
2 Upper Dir Khan abad MHP •	 The scheme had been recently repaired and was not ready to be
started.
3 Swat Shao MHP 75Kw •	 The day the of the site visit, the evaluation team was informed
that a bearing of the turbine needed repair and had been taken to
Mardan for repair.
4 Swat Dardyal, Qabel DWSS (Gravity Flow) •	 The scheme was not functional
•	 Community members stated that the source had been damaged
and the scheme had not functioned for the last two months, how-
ever they plan to repair it once the ice melts.
•	 The team could not visit the source due to the glacier, which made
it inaccessible.
Schemes which are partially functional
1 Shangla Bazkhel Drainage •	 The drains were blocked and water was overflowing from sides of
the drains
2 Swat Sherkhan,Bazdara DWSS (Hand pump) •	 Three hand pumps are functional and in satisfactory conditions.
•	 While two hand pump are not functional and need maintenance.
3 Swat Gujer Tangi Bad-
ro, Islampur
Link Road •	 Severe problems of erosion and cutting
•	 The designed pipe culverts have not been constructed.
•	 However, road is being used occasionally as no alternative is
available
Scheme Failed
1 Chitral Kuru Bala Dug Well •	 CPI failed as Water table was too low.
Table 2.7 Schemes completed over estimated cost
Schemes completed over estimated cost
Sr District Village Scheme Remarks
1 Malakand Khan Palao DWSS (Hand pump) Community informed the team that they had paid an extra 80,000 PKR for
the completion of scheme.
2 Malakand Sherkhan, Baz-
dara
DWSS (Hand pump) The community members said that an additional Rs. 20,000 had been
required for completion of the scheme.
3 Upper Dir Doonpayeen DWSS (Gravity Flow) The community members said that an additional Rs. 69,000 had been
required for completion of the scheme.
4 Upper Dir Malow Suspension Bridge (Pedest-
rian)
The community members said that an additional Rs. 60,000 had been
required for completion of the scheme.
Table 2.8 Schemes completed with Savings
Schemes completed with Savings
Sr District Village Scheme Remarks
1 Swat Mankass Qabel DWSS (HP) The scheme was completed within budget. Savings made were further
utilized for the construction of a PCC street pavement
2 Lower Dir Inzaroo DWSS Gravity Flow The scheme was completed with savings of approximately RS. 35,000
which were deposited in the CO’s bank account.
3 Swat Baghgay Maloch RCC Cause Way The scheme was completed with savings which were further utilized for
the construction of a 1,000 ft. link road
43
ANNEXURES 1C
Table 3. 1 Current condition of the CPI scheme - by Scheme Type
The sche-
me is not
working
currently
The scheme is
working but all
the participants
complained
The scheme is
working but most
of the participants
complained
The scheme is
working but some
of the participants
complained
Scheme is working
& no one comp-
lained about the
condition
Don’t know
% % % % % %
Drinking water supply 9.5 4.8 2.4 9.5 73.8 -
Irrigation 14.3 - 85.7 -
Link road/Bridges 4.7 9.3 18.6 65.1 2.3
Street pavement & drainage 7.1 7.1 78.6 7.1
Other 16.7 16.7 - 66.7 -
Total 5.4 4.5 5.4 11.6 71.4 1.8
Table 3.2 Was the project completed cost effectively? - by Gender
All the partici-
pants agreed that
the project was
not cost effective
Some (around 25%)
the participants ag-
reed that the project
was cost effective
Half (around 50%) of
the participants ag-
reed that the project
was cost effective
Most (around 75%) of
the participants ag-
reed that the project
was cost effective
All the participants
agreed that the
project was cost
effective
Don’t know
% % % % % %
Male 3.4 5.2 10.3 24.1 55.2 1.7
Female 3.8 7.7 5.8 82.7
Total 1.8 4.5 9.1 12.7 31.8 40.0
Table 3.3 How would you rate the material used in the CPI? - by Scheme Type
Good Average Poor Don’t know
% % % %
Drinking water supply 80.4 5.9 2.0 11.8
Irrigation 85.7 8.6 2.9 2.9
Link road/Bridges 76.6 10.5 2.4 10.5
Street pavement and drainage 89.7 9.0 1.3
Other 53.3 33.3 13.3
Total 79.1 9.7 1.8 9.4
Table 3.4 How decisions about the utilization of the O&M fund are made - by Gender
The O&M Committee The CO Leaders The SRSP staff All CO Members All Beneficiaries Contractor Other
% % % % % % %
Male 6.7 8.9 15.6 44.4 17.8 2.2 4.4
Female 3.2 28.6 63.5 1.6 3.2
Total 4.6 20.4 43.5 19.4 9.3 .9 1.9
44
Table 3.5 Performance rating of Project Committees – by District
Good OK Poor Don’t Know
% % % %
Buner 36.0 32.0 - 32.0
Chitral 50.0 50.0 - -
Lower Dir 15.1 22.6 - 62.3
Malakand Agency 35.6 24.4 - 40.0
Shangla 10.4 33.3 - 56.3
Swat 37.9 29.1 7.8 25.2
Upper Dir 25.0 18.2 2.3 54.5
Total 29.0 28.1 2.7 40.2
Table 3.6 Performance rating of Project Committees - by CPI Scheme
Good OK Poor Don’t Know
% % % %
Drinking water supply 24.6 32.2 2.5 40.7
Irrigation 20.0 40.0 30.0 10.0
Link road/Bridges 22.1 27.9 .6 49.4
Street pavement and
drainage
56.1 12.2 4.9 26.8
Other 66.7 33.3
Total 29.0 28.1 2.7 40.2
Table 3.7 Perception towards transparency in the planning/development/O&M of the scheme - by CPI Scheme
All the partici-
pants agreed
that there was no
record keeping
Records were
kept but there
was no transpa-
rency
Records were
kept but most of
the participants
still complained
Records were
kept but some of
the participants
still complained
Records were kept/
no one complai-
ned about lack of
transparency
Don’t know
% % % % % %
Drinking water supply 2.3 4.7 7.0 20.9 37.2 27.9
Irrigation 14.3 28.6 57.1
Link road/Bridges 7.0 4.7 7.0 11.6 32.6 37.2
Street pavement and
drainage
7.1 7.1 64.3 21.4
Other 20.0 60.0 20.0
Total 3.6 3.6 6.3 15.2 39.3 32.1
Table 3.8 Nature of Trainings - by Scheme Type
Disaster Preparedness Financial management Leadership O & M Any other Total (%)
% % % % %
Drinking water supply 2.3 27.3 27.3 11.4 31.8 100.0
Irrigation 100.0 100.0
Link road/Bridges 3.4 15.5 60.3 15.5 5.2 100.0
Street pavement and drainage 4.5 27.3 63.6 4.5 100.0
Total 3.1 20.8 46.9 11.5 17.7 100.0
45
Table 3.9 How did the SRSP contribution in direct cash help the local economy? - by Scheme Type
Greater than ¾ of
the SRSP money
was utilized within
the community
Between ½ and
¾ of SRSP money
was utilized
within the com-
munity
Between ¼ to ½ of
the SRSP money
was utilized within
the community
Less than ¼ of
SRSP money was
utilized within
the community
None of the
SRSP money was
utilized within
the community
Don’t know
% % % % % %
Drinking water
supply
20.7 10.3 13.8 6.9 3.4 44.8
Irrigation 40.0 60.0
Link road/Bridges 12.1 30.3 3.0 12.1 6.1 36.4
Street pavement
and drainage
33.3 16.7 50.0
Other 50.0 16.7 33.3
Total 21.5 17.7 6.3 8.9 41.8
Table 3.10 Diseases contracted from DWS CPI scheme’s water - by District
Had the diseases Buner Chitral Lower Dir Malakand Shangla Swat Upper Dir Total
Yes 15.4 10.0 0.0 23.5 10.0 25.0 0.0 15.5
No 84.6 90.0 81.3 35.3 90.0 35.0 80.0 60.3
Don’t know 0.0 0.0 18.8 41.2 0.0 40.0 20.0 24.1
Total 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
Table 3.11: How often do/did you use the road/bridge? - by District
Not at all Occasionally Often All the time
% % % %
Buner 50.0 0 0 50.0
Lower Dir 55.0 45.0
Malakand Agency 3.3 10.0 6.7 80.0
Shangla 0 17.5 32.5 50.0
Swat 7.8 11.8 29.4 51.0
Upper Dir 15.2 30.3 54.5
Total 7.4 7.8 30.4 54.4
Table 3.12: Decrease in cost of freight transport (% age of respondents)
District <=25% 26%-50% 51%-75% >=76% Total
Lower Dir 100 0 0 0 100
Malakand Agency 5 90 0 5 100
Shangla 16.67 56.67 23.33 3.33 100
Swat 4.88 95.12 0 0 100
Upper Dir 13.33 86.67 0 0 100
Total 17.95 74.36 5.98 1.71 100
46
TypeofSchemeSub-typeofSchemeNoTotalCost
Community
Contribution
NoofBenefici-
aryHHs
Community
Contribution
Costper
HH
Contribution
perHH
Typeofscheme
asa%ageoftotal
schemes
Costofschemeasa
%ageoftotalcost
BeneficiaryHHasa
%oftotalbenefici-
aryHHs
BRIDGERCCSMALLBRIDGE613,102,7002,620,6001,57420%8,32416652.85.64.2
SUSPENSIONBRIDGE35,309,1001,061,8001,00520%5,28310571.42.32.7
SUSPENSIONBRIDGEPEDESTRIAN910,206,9002,041,4001,56120%6,53913084.24.44.2
SubTotal1828,618,7005,723,8004,140120,1464,02981211
Average81,589,928317,9892306,9131,383
DWSSBOREWELL1423,00084,60041020%1,0322060.50.21.1
DUGWELL1298,32049,7203017%9,94416570.50.10.1
GRAVITYFLOW6349,680,2549,928,8905,09120%9,758195029.621.213.6
HANDPUMP209,510,1201,954,9502,17021%4,3839019.44.15.8
SubTotal8559,911,69412,018,1607,701125,1174,715402621
Average40704,843141,390917,7801,561
MHPMICROHYDROPOWERUNITS846,442,90012,408,8332,36227%201,92652543.819.86.3
45,805,3631,551,10429519,6635,254
IRRIGATIONGABIONSTRUCTURE1626,100146,2004,00023%157370.50.310.7
PIPEIRRIGATION21,435,000247,0007217%19,93134310.90.60.2
WATERCOURSELINING88,361,6001,672,2201,43020%5,84711693.83.63.8
WATERDRIVENPUMPSYSTEM1556,00026,000505%11,1205200.50.20.1
SubTotal1210,978,7002,091,4205,552137,0545,1566515
Average6914,892174,2854631,977377
COMMUNICATIONCAUSEWAY1722,300144,5006520%11,11222230.50.30.2
EARTHEN&PCC1012,218,8002,443,8002,15020%5,68311374.75.25.7
EARTHEN57,035,0001,408,3001,42020%4,9549922.33.03.8
PCC1916,142,6003,228,6203,15320%5,12010248.96.98.4
LINKROADEXTENSION11,079,700215,94015220%7,10314210.50.50.4
LINKROADPCC&R/W21,345,000269,00058020%2,3194640.90.61.5
LINKROADREHABILITATION2121,654,3004,331,0705,73020%3,7797569.99.215.3
RCCCAUSEWAY32,495,700499,00052620%4,7459491.41.11.4
BRIDALPATH(STONEPITCHING)1500,700100,10020020%2,5045010.50.20.5
RCCPIPECAUSEWAY1611,500122,30034520%1,7723540.50.30.9
subtotal6463,805,60012,762,63014,321249,0919,819302738
Average30996,963199,4162244,455891
SANITATIONDRAINAGE1294,50058,9009520%3,1006200.50.10.3
STREETPAVEMENT43,340,800668,04020020%16,70433401.91.40.5
STREETPAVEMENTANDDRAINAGE1812,855,4002,565,8202,59020%4,9639918.55.56.9
SubTotal2316,490,7003,292,7602,885124,7674,9511178
Average11916,150182,9311605,7161,141
SOILCONSERVATIONDRYSTONEPROTECTIONWALL11,550,700310,2009620%16,15332310.50.70.3
PROTECTIONWALL15,457,000909,50020017%27,28545480.52.30.5
SubTotal27,007,7001,219,700296043,4387,779131
Average13,503,850609,85014823,6754,121
UPGRADATIONUPGRADATIONOFSPORTSFACILITY1971,00002500%3,88400.50.40.7
TOTALS213234,226,99449,517,30337,5075405,42441,703
Annex 2: Total EERP CPI
47
Annex 3: Sampled CPI
S.No District Village Type of
Scheme
Scheme sub-
type
Date Beneficiaries HH Total Cost Cost per
Benefi-
ciary
Initiation Completion Planned Actual Estimated
1 Buner Riaz Abad, Ambella DWSS Hand Pumps 7/9/11 7/12/11 125 139 400,000 2878
2 Buner Banju Tangey DWSS Gravity Flow 12/9/11 12/12/11 113 130 652,400 5018
3 Buner Ambela DWSS Gravity Flow 9/23/11 23/12/2011 65 65 648,900 9983
4 Buner Bazarkot Bridge Foot Bridge
(Suspension)
7/9/11 7/12/11 128 200 917,000 4585
5 Chitral Kuru Bala DWSS Dug Well 12/12/11 12/3/12 60 60 310,800 5180
6 Chitral Khoran dok DWSS Gravity Flow 8/9/11 8/12/11 64 64 1,108,700 17323
7 Chitral Bamburate MHP MHPP 9/24/11 24/02/2012 457 500 6,736,700 13473
8 Lower Dir Munjay Road Infra-
structure
Link Road 11/11/11 11/2/12 100 150 610,700 4071
9 Lower Dir Inzaroo DWSS Gravity Flow 5/9/11 05/03/2013 90 100 457,500 4575
10 Lower Dir Moranai Road Infra-
structure
Link Road 12/12/11 12/3/12 69 120 645,200 5377
11 Lower Dir Danwa DWSS Gravity Flow missing missing 120 120 742,900 6191
12 Lower Dir Asilo DWSS Gravity Flow 1/11/11 01/02/2012 35 120 766,700 6389
13 Lower Dir MataKhazana Road Infra-
structure
Link Road 4/11/11 4/2/12 200 300 764,000 2547
14 Lower Dir Shal Kandi Road Infra-
structure
Link Road 10/30/11 1/30/12 200 300 769,400 2565
15 Malakand Khar DWSS Hand Pump 8/22/11 11/22/11 80 200 657,867 3289
16 Malakand Sherkhan,Bazdara DWSS Hand Pump 9/19/11 12/19/11 115 200 707,131 3536
17 Malakand Aladand Dherai Irrigation Gabion Structure 10/20/11 20/02/2012 455 455 626,100 1376
18 Malakand Khan Palao DWSS Hand Pump 8/15/11 11/15/11 45 120 634,865 5291
19 Malakand Pirkhel khass Road Infra-
structure
RCC cauce way 11/21/11 2/21/12 70 150 915,600 6104
20 Malakand Palai khpa Road Infra-
structure
Link Road (PCC) 11/29/11 29-01-2012 200 350 1,083,500 3096
34 Malakand Amin abad Road Infra-
structure
Link Road 10/21/11 1/21/11 45 120 524,800 4373
21 Shangla Abbasin Colony Sanitation Drainage 9/9/11 9/12/11 25 25 294,500 11780
22 Shangla Sanam Road Infra-
structure
Link Road (PCC) 8/30/11 11/30/11 34 110 759,414 6904
23 Shangla Sur Kumar Road Infra-
structure
Link Road (PCC) 6/9/11 6/11/11 54 125 765,417 6123
24 Shangla Abbasin Colony DWSS Gravity Flow 5/9/11 05/12/2011 45 100 1,194,500 11945
25 Shangla Feza Road Infra-
structure
Link Road (PCC) 8/28/11 11/28/11 44 120 883,761 7365
26 Shangla Sanila Sanitation Street pavement
& Drainage
6/9/11 6/12/11 56 200 916,200 4581
27 Shangla Tangir Bridge Suspension
Bridge (Pedes-
trian)
9/13/11 12/13/11 155 155 1,110,500 7165
28 Swat Quanj Sanitation Street Pavement
& Drainage
10/13/11 1/13/12 80 175 598,000 3417
29 Swat Jabba DWSS Hand Pump 11/21/11 1/21/12 140 200 402,850 2014
30 Swat Saidu Shareef DWSS Hand Pump 11/28/11 1/28/12 110 190 524,900 2763
31 Swat Mankass Kabel DWSS Hand Pump 11/24/11 2/24/12 52 80 223,244 2791
32 Swat Sorykad DWSS Gravity Flow 11/24/11 2/24/12 46 100 308,100 3081
33 Swat Faqira Sanitation Street pavement
& Drainage
2/15/12 5/15/12 250 300 515,000 1717
35 Swat Babo Maira Irrigation Ramp Pump 11/19/11 19/01/2012 44 44 556,000 12636
48
36 Swat Bar Jopeen Sanitation Street pavement
& Drainage
12/23/11 3/23/12 200 200 586,500 2933
37 Swat Dardyal,kabel DWSS Gravity Flow 5/9/11 05/03/2013 90 120 700,000 5833
38 Swat Baghgay Maloch Road Infra-
structure
RCC Cause Way 12/27/11 27/03/2012 65 80 722,300 9029
39 Swat Badardam DWSS Gravity Flow 11/28/11 2/28/12 50 80 853,500 10669
40 Swat Pengen Sanitation Street pavement
& Drainage
9/15/11 12/15/11 260 260 807,500 3106
41 Swat Faqira Road Infra-
structure
Link Road - Reha-
bilitation
6/9/11 6/2/12 65 125 832,300 6658
42 Swat Yakh Tangey DWSS Gravity Flow 8/27/11 11/27/11 60 60 838,600 13977
43 Swat Meradai DWSS Gravity Flow 10/30/11 1/30/12 40 40 667,500 16688
44 Swat Lawar Deolai, Qabil Irrigation Irrigation
Channel
6/11/11 6/1/12 180 180 1,062,200 5901
45 Swat Akhun Baba Road Infra-
structure
Link Road PCC 2/13/12 4/13/12 450 550 1,069,000 1944
46 Swat Kaho Road Infra-
structure
Link Road (Reha-
bilitation)
9/18/11 2/18/12 250 250 1,079,800 4319
47 Swat Meragai Irrigation Irrigation
channel Lining &
RT wall
12/8/11 12/11/11 120 25 1,086,300 43452
48 Swat Samteer Road Infra-
structure
Link road
(Earthen)
10/25/11 12/25/11 150 150 1,093,300 7289
49 Swat Shagai Ghwajalgai DWSS Gravity Flow 10/14/11 1/14/12 26 26 620,100 23850
50 Swat Shagai Sanitation Street pavement
& Drainage
8/22/11 11/22/12 160 275 1,201,000 4367
51 Swat Kokari Sar Road Infra-
structure
Link road (Earth-
en & PCC)
10/31/11 12/31/12 315 315 1,309,700 4158
52 Swat Gujer Tangi Badro,
Islampur
Road Infra-
structure
Link Road 3/2/12 3/5/12 400 425 1,333,000 3136
53 Swat Kamay Bridge RCC Bridge 10/25/11 1/25/12 300 450 2,561,500 5692
54 Swat Shao MHP MHPP 5/7/12 5/12/12 250 275 8,612,000 31316
55 Upper Dir Doonpayeen DWSS Gravity Flow 10/15/11 4/15/12 120 250 655,000 2620
56 Upper Dir Shamorgar Road Infra-
structure
Link Road (PCC) 1/11/11 1/2/12 145 145 823,400 5679
57 Upper Dir Panakot Road Infra-
structure
Link Road 10/30/11 4/30/11 67 40 1,250,700 31268
58 Upper Dir Malow Bridge Suspension
Bridge (Pedes-
trian)
1/16/11 4/16/12 332 150 1,518,500 10123
59 Upper Dir Qulandai Payeen Bridge Suspension
Bridge (Pedes-
trian)
1/9/11 1/3/12 170 225 1,540,800 6848
60 Upper Dir Khan abad MHP MHPP 10/13/11 3/13/12 218 218 2,654,300 12176
49
Evaluation
Parameters
Areas of focus Evaluation Tools
EERP Secondary
data
Engi-
neers
CPI Desk
Review
Report
Engi-
neers
CPI Field
Report
HH
Survey
Focus
Group
Discus-
sions
Meeting
with
GOKPK
Line
depart-
ments
and other
Key Infor-
mants
1 Relevance •	 Do the schemes respond to the
stated project objectives and
overall goals of AusAid?
•	 Do the selected CPIs reflect the felt
need of the community?
•	 Is it a priority
•	 Gender wise analysis
•	 GOKPK context
o	PCNA
o	 Malakand strategy
o	 Priority areas
o	 Post flood and Insurgency
•	 PCNA Report
•	 Malakand Strategy
•	 EERP proposal
•	 Completion Docu-
ment
•	 Monitoring Report
(H/O and District)
•	 AusAid Goals/ob-
jective (Website)
•	 CBO Files/record
P P P P
2 Effectiveness •	 Are the schemes functional?
•	 Are the schemes delivering the
designed services?
•	 Is the scheme benefitting all inten-
ded beneficiaries? (or some?)
•	 Whether the CPI schemes meet
the accepted engineering designs,
specs and standards?
•	 Actual design coverage vs.  Plan-
ned.
•	 Gender wise breakdown
•	 SRSP Monitoring
Reports
•	 CPI Completion
Reports
P P P P P
3 Efficiency •	 Cost and time comparison relative
to original timelines and budgets
•	 Unit scheme costs in relation to
other GOKP/SRSP/CSO schemes
•	 Cost per beneficiary for various
scheme types
•	 Illustrative Cost benefit analysis for
sample schemes
•	 P
•	 CSR comparative
GOKP
•	 SRSP non EERP CPI
proposal
•	 Other CSO costing
if available.
P P P
4 Immediate
Outcomes/
Impacts
•	 Reported direct benefits (additi-
onal land irrigated, greater yields,
additional drinking supplies,
enhanced land value, reduced
burden of disease, others
•	 Un-intended and/or indirect bene-
fits
•	 Gender wise breakdown
•	 P
•	 CPI Completion
reports
•	 Case studies by
SRSP
P P P P
5 Sustainability •	 Adequacy of design
•	 Quality of construction and work-
manship.
•	 Systems for  maintenance/O&M
•	 Government support?
•	 Current condition of schemes
•	 P
•	 CBO Files
P P P P P
Annex 4: Evaluation Matrix
50
Annex 5: QA Process
SRSP
AiD HO
Final Report Compilation,
Preparation and 4th Level QA
by Project Advisor
Compilation and Report Writing
by Sector Specialists
3rd Level QA and Compilation
at AiD’s HO.
Compilation and 2nd Level QA
At AiD’s HO
1st Level QA
by Field Supervisor
Engineer’s Field Visit
Focus Group Discussion
House Hold Survey
Field Supervisor
Field Plan
Data Entry, Cleaning and
Analyses by the Data Analyst
51
Annex 6: Physical Infrastructure-
( PI )- Implementation- Process
1st Dialogue
•	 Program Introduction
•	 Need Identification
Not Feasible
Audit Committee O&M Committee
Project Approval
CPI Construction
•	 Documentation of
Record in PI Register
Project Completion
•	 PI Completion Report
•	 PI CompletionCertificate
Handing Over to CO
•	 Handing and taking
over Certificate
Feasible
•	 Project Proposal
3rd Dialogue
•	 Terms of Partnership
Formation of
•	 Project Implementation
Committees
•	 Audit Committee
•	 O&M Committee
Environmental Feasibility
•	 Environment Screening
•	 Enviornmental Review
Social-Feasibility
•	 Formation of CO
•	 Opering of Bank Account
•	 Conflict free
Technical Feasibility
•	 Design
•	 Material Specifications
•	 Construction drawings
•	 Cost Estimates
•	 Water Quality test
2nd Dialogue
Type of Documentation
reviewed for Availability
and Adequacy
CO Resolution
52
Work Plan for the Evaluation of Imm
February March
Week 1 Week 2 Week 3 Week 4 We
18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2
Inception Phase Inception Phase
1 Contracts signed by
SRSP
8th
2 Contract Signed by
AiD Pvt Ltd
15th
3 Inception meeting
with SRSP
4 Team Mobilization
5 Development of
Evaluation Tools /
Sampling
6 Team’s orientation
and pre-testing of
evaluation tools
Field Work and Data Collec-
tion Phase Phase
Field Work and
Cluster A
1 Data Collection -
District Swat
2 Data Collection -
District Malakand
3 Data Collection -
District Buner
4 Data Collection -
District Shangla
Cluster B
5 Data Collection -
District Lower Dir
6 Data Collection -
District Upper Dir
7 Data Collection -
District Chitral
Data Analysis and Report
Writing Phase
1 Consolidation and
Clean up of Data
2 Data Analysis and
Draft Report prepar-
tion
3 Submission of First
Draft
4 Feed back by SRSP on
First Draft
5 Final report with
changes
Annex 7: W
mediate Impact of SRSP EERP CPIs
April
eek 5 Week 6 Week 7 Week 8 Week 9 Week 10
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Data Collection Phase Phase
Data Analysis and Report Writing
53
Work Plan
54
Annex 8: Community Infrastructure Pictures
Chitral
55
Swat
Dir Upper
Dir Lower
Malakand
Annex 9: EERP Maps
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Third party evaluation of SRSP programme (AusAid-EERP)
Sarhad Rural Support Programme
109, Street 2B, Defence Officers’Colony, Khyber Road, Peshawar
Telephone: 92-91-9211417, 5285389
Fax: 92-91-5276734
E-mail: srsp@srsp.org.pk
www.srsp.org.pk

More Related Content

PDF
NIST DRAFT -- Disaster resilience framework
PDF
Third party evaluation cm’s programme for poverty alleviation
PDF
Improving Sewerage Services for Baghdad
DOCX
CFW Final Report-1
DOCX
Abdul Basit
DOC
Annex 4 Paper NZ
PPT
Experiences on PCR of IFAD project in India
PDF
NAP-AG Webinar - Kenya Case Study
NIST DRAFT -- Disaster resilience framework
Third party evaluation cm’s programme for poverty alleviation
Improving Sewerage Services for Baghdad
CFW Final Report-1
Abdul Basit
Annex 4 Paper NZ
Experiences on PCR of IFAD project in India
NAP-AG Webinar - Kenya Case Study

Similar to Third party evaluation of SRSP programme (AusAid-EERP) (20)

PDF
Kenya – Capacity Assessment
 
PDF
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...
PDF
Community-Based Water Projects Sustainability: Lessons and Challenges-A Case ...
DOCX
Urban Unit
PDF
Waste water treatment plant business plan in Kigali
PDF
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
PPT
Community development and participatory approach concept (phase 2)
PPT
Community development and participatory approach concept (phase 2)
PPT
World bank mission_presentation final second-Overview of DWSS activities in L...
PPTX
Revised PPT_ Waste Management Proposal Submission ACT_HC 30 Nov 2022.pptx
PDF
Evaluation Report of Sustainable Land Management Program Phase II (SLMP-II) f...
PPTX
Menarid: Impact Study on Iran
PDF
Unit-4.pdf civilengineering college notes
PDF
TOR for EBA MTR 2014.pdf
PDF
Covid-free Village Program: Preliminary Assessment Report | Oct'21
PDF
Hmis newsetter 22
PDF
IRSP Annual Review 2013
PDF
IRSP Annual Review 2013
PDF
Background Material
PDF
Volume 1 - June Final
Kenya – Capacity Assessment
 
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...
Community-Based Water Projects Sustainability: Lessons and Challenges-A Case ...
Urban Unit
Waste water treatment plant business plan in Kigali
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
Community development and participatory approach concept (phase 2)
Community development and participatory approach concept (phase 2)
World bank mission_presentation final second-Overview of DWSS activities in L...
Revised PPT_ Waste Management Proposal Submission ACT_HC 30 Nov 2022.pptx
Evaluation Report of Sustainable Land Management Program Phase II (SLMP-II) f...
Menarid: Impact Study on Iran
Unit-4.pdf civilengineering college notes
TOR for EBA MTR 2014.pdf
Covid-free Village Program: Preliminary Assessment Report | Oct'21
Hmis newsetter 22
IRSP Annual Review 2013
IRSP Annual Review 2013
Background Material
Volume 1 - June Final
Ad

Recently uploaded (20)

PDF
sustainability-14-14877-v2.pddhzftheheeeee
PDF
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
PDF
A review of recent deep learning applications in wood surface defect identifi...
PDF
Architecture types and enterprise applications.pdf
PPTX
Tartificialntelligence_presentation.pptx
PDF
August Patch Tuesday
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PPTX
Benefits of Physical activity for teenagers.pptx
PDF
DP Operators-handbook-extract for the Mautical Institute
PDF
Taming the Chaos: How to Turn Unstructured Data into Decisions
PPT
What is a Computer? Input Devices /output devices
PDF
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
PDF
CloudStack 4.21: First Look Webinar slides
PDF
Hybrid horned lizard optimization algorithm-aquila optimizer for DC motor
PDF
STKI Israel Market Study 2025 version august
PDF
Getting Started with Data Integration: FME Form 101
PPTX
observCloud-Native Containerability and monitoring.pptx
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
PDF
1 - Historical Antecedents, Social Consideration.pdf
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
sustainability-14-14877-v2.pddhzftheheeeee
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
A review of recent deep learning applications in wood surface defect identifi...
Architecture types and enterprise applications.pdf
Tartificialntelligence_presentation.pptx
August Patch Tuesday
Assigned Numbers - 2025 - Bluetooth® Document
Benefits of Physical activity for teenagers.pptx
DP Operators-handbook-extract for the Mautical Institute
Taming the Chaos: How to Turn Unstructured Data into Decisions
What is a Computer? Input Devices /output devices
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
CloudStack 4.21: First Look Webinar slides
Hybrid horned lizard optimization algorithm-aquila optimizer for DC motor
STKI Israel Market Study 2025 version august
Getting Started with Data Integration: FME Form 101
observCloud-Native Containerability and monitoring.pptx
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
1 - Historical Antecedents, Social Consideration.pdf
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
Ad

Third party evaluation of SRSP programme (AusAid-EERP)

  • 1. www.srsp.org.pk Evaluation of Immediate Impacts of Community Physical Infrastructure (CPI) Projects under Expanded Early Recovery Project (EERP) Final Report June, 2013 Project funding by
  • 3. Evaluation of Immediate Impacts of Community Physical Infrastructure (CPI) Projects under Expanded Early Recovery Project (EERP) Final Report June, 2013 Associates in Development (AiD) Pvt. Ltd, Pakistan
  • 4. TABLE OF CONTENT 4 Executive Summary 7 Conclusions and Recommendations 13 1. Background and Context: Malakand Division and the EERP 16 2. Objectives and Scope of Work 17 3. Approach and Methodology 18 3.1 Stage 1 - Inception 19 3.1.1 Work Plan 19 3.1.2 Tools 19 3.1.3 Staffing 19 3.1.4 QA Plan 20 3.1.5 Sampling 20 3.2 Stage 2 – Field Work 21 3.2.1 Pre-testing and Finalization of tools 21 3.2.2 Field Activities 22 3.2.3 Challenges in the field 22 3.3 Stage 3 22 3.3.1 Data Entry, Analysis and report writing 23 4. Findings: 24 4.1 CPI documentation: Availability and Adequacy 26 4.1.1 Social Feasibility 27 4.1.2 Environmental Screening 27 4.1.3 Technical Feasibility: 28 4.1.4 Water Quality Test 30 4.1.5 Project Proposal 30 4.1.6 Project Approval 30 4.1.7 PI register 30 4.1.8 Project completion report 31 4.1.9 PI completion certificate 31 4.1.10 Handing and taking over certificate: 31 4.2 Design Validation 32 4.2.1 Scheme Layouts: 32 4.2.2 Design Validation: 32 4.2.3 The following is a type wise breakdown of the CPIs: 33 4.3 Relevance 34 4.3.1 Priority 34 4.3.2 Participation 34 4.3.3 Community Contribution 35 4.4 Effectiveness 37 4.4.1 Functionality: 37 4.4.2 Benefits 39 4.4.3 Problems 41 4.5 Efficiency: 42 4.6 Sustainability 42 4.6.1 Design and layout. 42 4.6.2 Quality 44 4.6.3 O&M systems 45 4.6.4 Institutional Maturity 48 4.6.5 Meetings 48 4.6.6 Trainings 49 4.6.7 Self-initiated community projects 50 4.7 Impact 52 4.7.1 Overall impact analysis 52 4.7.2 Drinking Water Supply - CPI Scheme Impact 53 4.7.3 Street pavements and drainage 55 4.7.4 Link roads and bridges 56 4.7.5 Irrigation 57 4.8 Conclusions and Recommendations 58
  • 5. LIST OF ABBREVIATIONS 5 AiD Associates in Development AusAID the Australian Agency for International Development CBR California Bearing Ratio Test CO Community Organization CPI Community Physical Infrastructure DWSS Drinking Water Supply Scheme ERP Early Recovery Programme ER Environmental Review EERP Expanded Early Recovery Programme ES Environmental Screening FGD Focus Group Discussion GF Gravity Flow GoKP Government of Khyber Pakhtunkhwa GPS Global Positioning System HH Household HO Head Office IRR Irrigation KII Key Informant interviews KP Khyber Pakhtunkhwa MH/MHP/MHPP Micro Hydel / Micro Hydel Power / Micro Hydel Power Plant MTDF Medium Term Development Framework NGO Non-Governmental Organization O&M Operations & Maintenance PCC Plain Cement Concrete PCNA Post-Crisis Needs Assessment PCR Project Completion Report PI Physical Infrastructure QA Quality Assurance RCC Reinforced Cement Concrete SPD Street Pavement and Drainage SRSP Sarhad Rural Support Programme TOP Terms of Partnership
  • 6. 6 Line of Contro l Kasur Thal Tank Bannu Kotli Punch Saidu Daggar Gardez Gujrat Gilgit Mardan Peshawar Chilas Tithwal Bhimbar Faizabad AsadabadCharikar Sargodha Mehtarlam Jalalabad Parachinar Rawalpindi Faisalabad Jhang Sadar Muzaffarabad Mahmud-e Raqi Dera Ismail Khan Kabul Islamabad Zhob Chenab Ravi Mangla reservoir Jhelum Kunar Kunar Indus Gilgit Shunjigol Zhob Gumal Amu darya Indus Gumal Chitralr iver Indus !Î !Î Chitral Swat Kohistan Mansehra Upper Dir Shangla Abbottabad Batagram Mohmand Agency Bajaur Agency D.I. Khan Kohat Karak Tank Lakki Marwat South Waziristan Agency Hangu Kurram Agency Bannu North Waziristan Agency Buner Swabi Haripur Mardan Nowshera Peshawar Malakand Pa Tribal Area Adjacent D.I. Khan Tribal Area Adjacent Tank Tribal Area Adjacent Bannu Tribal Area Adj. Kohat Tribal Area Adj. Peshawar Tribal Area Adj. Lakki Marwat Lower Dir Khyber Agency Chitral Swat Kohistan Mansehra Upper Dir ShanglaLower Dir Abbottabad Batagram Mohmand Agency Bajaur Agency D.I. Khan Kohat Karak Tank Lakki Marwat South Waziristan Agency Hangu Kurram Agency Bannu North Waziristan Agency rakzai Agency rakzai Agency Tribal Area Adjacent D.I. Khan Tribal Area Adjacent Tank Tribal Area Adjacent Bannu Tribal Area Adj. Kohat Tribal Area Adj. Peshawar Tribal Area Adj. Lakki Marwat Buner Swabi Haripur Mardan Nowshera Peshawar Charsadda KPK PUNJAB FATA FANA AJK BALOCHISTAN ISLAMABAD KPK PUNJAB FATA FANA AJK BALOCHISTAN ISLAMABAD Mingora Sadda Kohat Gujranwala Jamrud Ghalanai Attock AFG A IS TA PAKISTA TAJIKISTA I DI A Location map of the expanded early recovery project area (Pl see annex 9 for details district wise maps)
  • 7. 7 Background and Context The 2010 floods affected large parts of Khyber Pakhtunkhwa. Nearly 1,500 people lost their lives and 37,000 homes were destroyed. Malakand Division was one of the worst affected areas. During this period, AusAid funded Sarhad Rural Support program (SRSP) for ‘an initial Early Recovery Programme designed to target the flood affected districts of Peshawar, Nowshera and Charsadda. However, based on the PCNA1 findings and priorities identified for early recovery, SRSP submitted a revised proposal to AusAid for an Expanded Early Recovery Programme (EERP) that would focus on reconstruction in the entire Malakand Division2 . In 2011, AusAid earmarked AUS$ 3 million (PKR 255 million) for EERP that aimed to re-build communities in areas hit by floods and insurgency in Malakand Division3 . Focused on immediate recovery and rehabilitation needs, the program called for completing all identified targets within a nine month period. The challenging environment in Malakand was not new to SRSP, which had been working in the project area since 2001. As part of its development approach SRSP typically ensures a long term engagement with the local communities and maintains a presence even after the project implementation comes to an end. This has enabled the organization to continue supporting the capacity building and networking needs of communities and also retain a knowledge base of the area and its people. With this structure in place SRSP has the potential to ensure sustainability by leveraging additional resources for the communities, as and when the opportunities arise. The project area covered 191 villages (75 union councils) of 7 districts in the Malakand Division. The targeted districts include, Chitral, Upper and Lower Dir, Swat, Buner, Malakand Agency and Shangla The programme had 5 components including Community Institutions and Networking, Rebuilding Community Physical Infrastructure Improved Livelihoods - through micro Enterprise, and through NRM- based enterprises and Support to the local government. Under its component on community institutions, the project organized nearly 400 local community-based organizations. The target group included people hit by insurgency and floods, particularly the poor and marginalized, comprising nearly 74,000 households. The Community Infrastructure was the most visible and the largest component of the project and consumed 93% of the programme development budget. Specific interventions included the restoration of community enabling infrastructure, predominantly in the drinking water sector but also link roads, micro hydro electricity projects, protective works, bridges and sanitation projects. Approximately, 37,507 households gained access to clean drinking water and improved services through rehabilitation/construction of community-based physical infrastructure schemes. The project also included enterprise and vocational training for vulnerable groups particularly women. Over 700 households were also provided access to improved livelihood opportunities. Scope of Work The scope involved the assessment of 213 schemes implemented by SRSP across the entire Malakand Division. The objective of the study was the verification and validation of the CPI schemes and an assessment of the relevance, effectiveness, efficiency and immediate impact on the lives of the local communities. The geographic spread included all 7 districts of Malakand division including Buner, Chitral, Lower Dir, Malakand, Shangla, Swat and Upper Dir. Approach and Methodology The primary focus of the study was two pronged; an engineering assessment and a structured community survey. The engineering assessment focused on: i) an assessment of the availability and adequacy of the various engineering documentation required for the implementation of the schemes; and ii) a physical verification of the schemes’ existence and the state of their functionality. The community survey included: iii) a Household interviews and Focus Group Discussions (FGDs) held with a sample of the direct and indirect beneficiaries. . The survey, sample covered 60 schemes out of the total of 213 that were randomly selected (proportional to the type and geographic spread of the schemes in the districts covered). The sample size represents a confidence Level of 93 % with less than 10% margin of error. The study commenced in mid-February 20134 and was completed by mid June 2013. Led by a an experienced team leader, multiple field teams assisted with the assessment to ensure timely completion of the full scope spread over vast and a challenging terrain. Each team comprised a field supervisor and two researchers. In addition, a short-term advisor, a senior engineer, and short-term inputs from a Social Sector/Gender Specialist, and Data Analyst were tapped during implementation. A variety of assessment tools helped generate the quantitative and qualitative analysis that provided the basis for this report. Findings The following sections summarize the key findings: 1.1 Documentation: Availability and Adequacy: Except for a small number of CPIs, documentation showing compliance with the SRSP processes such as social feasibility, Terms of partnership (TOP), project completion reports (PCRs), certificate of completion and handover documents to the community were available and found to be adequate. However the engineering design basis and calculations were unavailableorinadequateforbulkofsampleCPIs,particularly for the road infrastructure CPIs. 1.2 Design validation: All the 60 schemes were visited and checked for variations EXECUTIVE SUMMARY 1 Post Conflict Needs Assessment: A multi-donor initiative. 2 Livelihood Strengthening Programme - Expanded Early Recovery Project in Border Areas of Khyber Pakhtunkhwa (Malakand Division) – SRSP, April 2011 3 Expanded Early Recovery Project (Livelihood Strengthening Programme) Project Completion Report - SRSP 4 See Annex 7
  • 8. 8 in relation to the original plans and designs. The layout of 9 schemes had significant variations while the rest had minor or no variations. The significant variations in layout were for DWSS. They either had to do with lengths of pipe network or the variations in the location/number of storage or supply water tanks from what was originally planned. Furthermore, the measurement of the structures showed major variations for 12 schemes, whereas 21 schemes had relatively minor variations. Although a detailed investigation was not made on the rationale for the change, however, it was reported that the change was necessitated by site conditions. 1.3 Relevance Relevance refers to whether or not the selected schemes respondedtotheneedsandprioritiesofthetargetcommunity. A number of indicators covered this important assessment parameter and aimed at assessing the prioritization of the CPI schemes; participation in planning and implementation; and the community contributions towards the schemes. 1.3.1 CPI Prioritization An overwhelming majority, (98 percent of all male and females surveyed in all districts, except Lower Dir, indicated that the schemes implemented under the EERP addressed the priority needs of the communities. 1.3.2 Participation The majority of respondents reported their own or the household’s participation in the planning and implementation of the CPIs. The highest participation in planningandneedsassessmentofCPIschemeswasinthe district of Chitral (100 %) and the least in Shangla where it was 67 %. Given the social norms of the area it came as no surprise that participation of females was found to be low, however 32 % females indicated that they or another female from their household did participate in the needs assessment. Overall participation in the implementation was reported as 82 %. Again the highest level of participation was reported from Chitral and the lowest in Shangla. 1.3.3 Community Contribution Community contribution is an important indicator of ownership. Nearly 77 percent of the respondents (75 percent females; and 79 percent males) claimed to have made contributions in cash and/or in kind to the construction of CPI schemes, while the rest of the 23 percent did not contribute. Relatively higher contributions were made in Chitral, Upper Dir and Buner (100, 92 and 83 percent, respectively). Interestingly, 77 percent of respondents which were non CO members also contributed towards construction. Of the total households that contributed, 17 percent contributed in cash. The highest frequency of cash contributions (30 percent) was witnessed in Shangla. 70 percent of the contributions were in the form of labor whereas 20 percent contributed additional items in kind. 1.4 Effectiveness EffectivenessreferstowhethertheCPIschemesarepractically meeting the need for which they were designed and built. Accordingly the indicators against which effectiveness has been gauged are functionality and recurring benefits of the CPI schemes. Except for an odd few cases, all the schemes were found to be functioning well and providing the anticipated benefit to their respective communities. 1.4.1 Functionality From the community perspective, approximately 91 percent of the respondents across the 7 districts acknowledged that the CPI schemes were working and functional. Across the respondents, 86 % of the female respondents believed that the schemes were 100 percent functional, as compared to the more cautious replies of male respondents, 61 % of whom felt that the schemes were 100 % effectively working. FGD analysis supported the overall satisfactory responses from majority of the male and female participants. Functionality on the ground was also verified by the field engineers. Out of the total sample of 60 schemes, the field engineers were able to inspect and verify that 52 schemes were fully functional. Of the remaining 8 CPIs, 4 schemes were not operational at the time of the visit. These schemes included the MHPP scheme in Shao Kalam, district Swat, and Khanabad, district Upper Dir; both of them had technical breakdown and were in the process of being repaired by the communities. Whereas, the Irrigation Channel in Meragai Swat was not operational, since it was not an irrigation season, whereas in the case of DWSS Dardyal, Kabal Swat, the intake structure had been damaged due to a snow slide and the communities were waiting for the snow to melt before attempting any repairs. The remaining 3 schemes namely Drainage CPI, Bazkhel, DWSS Sher Khan, and Link Road Gujjer Tangi, were partially functional. A major reason for this seemed to be lack of an effective O&M system for these CPIs. 1.4.2 Scheme Benefits Overall 90 percent of respondents claimed to be directly benefitting from the CPI schemes. A relatively higher percentageofpeople(100,97and80percent)werefound to be benefiting from the CPI schemes in Shangla, Lower Dir and Chitral, reinforcing the communities’ high levels of participation in planning, implementation and cash contribution in these 3 particular districts. Furthermore, the schemes were benefiting members and nonmembers alike as nearly 88 % of the non-members interviewed also confirmed that they were directly benefitting. 1.5 Efficiency: Bulks of the CPIs were implemented within the planned budgets and time of completion. The review shows that 95% of the schemes were completed within the planned timeframewhile87%ofthesampleschemeswerecompleted within the estimated budgets. A relatively modest 7% of the schemes exceeded the approved budget by 10% while 6% of the scheme sample was completed under the estimated budgets. It is noteworthy that in the case of budget overrun it was the community which invariably contributed to meet the shortfall. Although hard comparative data is not available for similar sized schemes which the GoKP or other organizations have implemented, there is anecdotal evidence that cost per beneficiary in the case of SRSP CPIs is relatively low. One reason is community contributions which on average is at least 20 % of the total cost of schemes
  • 9. 9 1.6 Sustainability Sustainability of the schemes refers to whether i) the schemes will fulfill its design life and ii) whether or not communities will continue to maintain the systems independent of any support from SRSP.The indicators for this assessment parameter included quality of the CPI schemes; and the Operations & Management (O&M) systems put in place (including transparency), and the overall institutional maturity of the community organization. 1.6.1 Quality Despite the rough and remote mountain terrain, the quality of schemes of the majority of schemes was found to be good. Community perception in this regard corroborated the engineering team’s findings. The focus group discussions indicated that more than 91 percent of the respondents were satisfied with the current condition of the CPI schemes, out of these 87 % were non members. In Buner, Chitral and Malakand Agency, nearly 100 % of the male respondents showed satisfaction; while 86 to 97 % of the females indicated satisfaction with the quality of work. Out of the 9 schemes which had quality issues, most indicated quality of concrete in the PCC link roads as an issue. 1.6.2 O&M systems Knowledge of any O&M system was generally low. Almost 48 % of the respondents were not aware of any O&M system. Of these 24 % were male and 79 % were female respondents. Approximately 39 percent of respondents claimed to have made contributions to O&M. The largest contribution was in irrigation schemes (55 percent); and ‘others’ (77 percent). Of the contributors, 52 percent were CO members, and 49 percent non-CO members. Respondents acknowledged awareness that most of the maintenance funds were being run through SRSP and then CO bank accounts. The FGD analysis reflects that about half the male respondents claimed to be satisfied with the O&M system, however less than a quarter of the females showed satisfaction with O&M.. Majority of female respondents were unaware of any O&M system. For the engineering team, verification of O&M involved observation of how well the CPIs were being maintained and discussed the functioning of the O&M committees. It was reported that O&M committees for half the CPI schemes were found fully functional; whereas it was observed that O&M existed and functioned partially at 27 percent of the sites; while 24 percent cases there was no functional system for O&M. From the engineering view point a total of 14 schemes were not well maintained. 1.6.3 Institutional Maturity Another indicator of ‘Sustainability’ is Institutional Maturity, which assesses the capacity of the communities to independently run the CPI schemes in the longer-run. Indicators for this assessment are complex and tricky. However some of these were captured during the field survey. Among these include; Community meetings during- and post-implementation of CPI schemes; trainings of community of members; and community’s local initiative. 1.6.3.1 Meetings While 70 % of the respondents said that they met either fortnightly or monthly before CPI completion, only 12 % meet on a regular basis once the CPI was completed. Most of the respondents however said that they continue to meet on need basis. 1.6.3.2 Trainings Nearly half the respondents, 46 % said that someone from the community has been given trainings with the lowest proportion in Dir and highest being reported from Malakand. Most of these trainings were in leadership and financial management, but 14% were on O&M, related which were all given to the males of the community. 1.6.3.3 Self-initiated community projects 17 % of respondents indicated that they had imitated other projects besides the CPI which was assisted by SRSP. Of these, 67 % respondents were CO members whereas, 33 were non-CO members. Furthermore, the new indicatives by CO members were predominantly donor assisted as compared to the once implemented by the non CO members, showing a greater capacity to network and leverage external funds for local development. Linking the above analysis to the subject of community’s ability to self initiate projects and/or run existing schemes independently, majority of the FGD responses endorsed the confidence of the male and female participants claiming that the CPI schemes could very well continue to run in the absence of support from SRSP. However, scheme-wise response from FGD participants believed that irrigation and drinking water supply schemes respectively could not run solely by the communities. 1.7 Immediate Impact Overall the community felt a significant positive impact of the schemes. For the irrigation schemes include enhanced yields, crop production and increase in overall farm incomes. Construction of street pavements and drainage, and implementation of improved drinking water supplies led to a decrease in foul smells and a perception of decreased waterborne diseases. With the construction of link roads and bridges, approximately 68 percent of respondents across all 7 districts acknowledged a positive impact on women’s free time, enabling them to manage their daily activities more efficiently and productively. Some indirect benefits include a significant positive impact on girls’ and boys’ education reported by all respondents across all 7 districts, post implementation of the various CPI schemes. More specifically, this was in terms of greater access/lesser distances due to the construction of link roads and bridges, etc. However, the main immediate outcomes, as a direct result of the CPI schemes are as follows: 1.7.1 Drinking Water Supply - CPI Scheme Impact Post implementation, the average time taken to reach the water source decreased drastically, allowing community members, particularly females, to allocate their time more efficiently to other important daily tasks. The result findings indicate that the responsibility of collecting water is now being shared most often by the daughters (21 percent), allowing the mothers to utilize their time more efficiently. Satisfaction levels with the new DWS CPI schemes were 100 percent for males and 97 percent for females, implying lower risks of waterborne diseases.
  • 10. 10 1.7.2 Street pavements and drainage Majority of the respondents (92 percent) in the 3 districts where the scheme was implemented, Malakand Agency, Shangla and Swat agreed that post implementation of the CPI; the issue of stagnant water in the streets had either been completely or partially eliminated. Additionally, post-SPD CPI, in Shangla and Swat, 75 and 93 percent respondents, respectively claimed high incidences of reduction in foul smell, while only 50 percent respondents reported the same in Malakand Agency. However, majority of the respondents from Shangla (approximately 62 percent) are still claiming that waste water is not disposed properly even after implementation of the scheme. Post implementation of the CPI scheme, nearly 50 percent of the respondents in both Malakand Agency and Shangla perceived an improvement and positive effect on the health of the children as a result. 1.7.3 Link roads and bridges The new link roads and bridges/communication infrastructure has remarkably decreased the average timetakenforcommunityresidentstoavailessentialdaily requirements including distances to the nearest drinking water supply; grocery stores; girls’ and boys’ schools; hospital; and the nearest local Tehsil administration. In Malakand Agency, 3 percent respondents claimed to not use it all. Of these 3 percent respondents, 33 percent stated the reason that the new infrastructure was of no use to them. The 8 percent respondents in Swat, who claimed the same, all reported ‘poor quality’ as the reason. In terms of overall traveling cost, it decreased by 25 percent for all respondents in Lower Dir and between 25 to 75 percent across all districts at varying levels.There was an overall 75 percent decrease in the cost of freight transport across all districts except Buner, where no change was reported. 1.7.4 Irrigation The household surveys show that there was a remarkable increase in crop production. While 100 percent respondents reported a 50 percent increase in wheat production; between 50 to 80 percent reported a 100 percent increase in rice and grain production. Production of maize also increased considerably. In vegetables, 100 percent increase in production of onions, tomatoes, okra and garlic was also reported by all respondents. With regards to the overall impact on farm income, 100 percent respondents reported a minimum of 50 percent increase.
  • 11. 11 In view of the early recovery context and the difficult terrain, SRSP’s outreach and successful conclusion of this challenging project is commendable. The schemes have been implemented in areas where the government had limited outreach and other non-governmental players had no presence. Working in the target areas meant many hours of driving and trekking through often rugged and mountainous terrain. Despite these difficulties, the overall quality of work is of good standards. All project outputs were also achieved within the agreed timelines. Thanks to a motivated team, nearly 400 community organizations were formed, local priorities identified and over 200 CPIs implemented within a short span of 9 months. • Overall the communities have reported a very positive impact of the CPI program. • Post implementation of the DWSS, the average time taken to reach the water source decreased significantly, allowing community members, particularly females, to allocate their time more efficiently to other important daily tasks. Satisfaction levels with the new DWS CPI schemes were 100 percent for males and 97 percent for females, also, implying lower risks of waterborne diseases. • In case of Sanitation and drainage CPIs, the majority of the respondents (92%) in the 3 districts where the scheme was implemented noted that the issue of stagnant water in the streets had either been completely or partially eliminated. Additionally, 75 and 93% respondents in Shangla and Swat, respectively claimed reduction in foul smell, while 50 percent respondents reported the same in Malakand Agency. • The new link roads and bridges has remarkably decreased the average time taken for community residents to avail essential daily requirements; travel tothenearestdrinkingwatersupplyschemes; grocery stores; girls’ and boys’ schools; hospital; and the nearest local Tehsil administration. The respondents reported an overall 75 percent decrease in the cost of freight transport across all districts except Buner, where no change was reported. • The survey also shows considerable increase in crop production due to the implementation of irrigation schemes.Nearlyallrespondentsreporteda50percent increase in wheat production; while between 50 to 80 percent reported a 100 percent increase in rice and grain production. With regards to the overall impact on farm income, 100 percent respondents reported a minimum of 50 percent increase. • Combined capacity of the 3 MHPs in Chitral, Swat and Upper Dir has the designed capacity of 225 KW, which will benefit approximately 600 HH. The MHP in Chitral has been functioning at full capacity and is not only supplying electricity to the communal HH’s, but also to a local hotel, Bashalini(Menstruation/Maternity Home), Jasthakhan (Funeral Dance Hall), a school and also mosque. CONCLUSIONS AND RECOMMENDATIONS • All 60 schemes in the evaluation sample were physically verified to be on the ground. Except for one scheme all the rest have been identified by the local community as fulfilling their priority need. Given the tight time lines and the difficult terrain, this is a remarkable achievement • Project documentation has been meticulously kept in the regional office, showing detailed record of community interaction and the field processes from the ‘first dialogue’ to the handing of checks in the 3rd dialogues and the subsequent installments. However the technical documentation covering the design basis, design calculations and the environmental assessment remains a weak area. . • The CPIs are predominantly functional , and have a positive impact on the communities; however some of these ( about 10 % ) are not delivering the required benefits due to poor quality and/or weak O&M systems. • A majority of females in the sample confirmed that the CPIs chosen represented their priority needs and directly benefiting them. However CPI implementation remained a predominantly male affair. Out of the 64 WCO which were formed, a total of 4 CPIs were for the women organization, which is disproportionally low. • Although CPIs such as DWSS or sanitation and drainage were being implemented there was little attempt to build the capacity of the organizations on related issues such as health and hygiene. • SRSP’s presence in the project areas was a significant factor in the rapid response and timely completion of the project activities. Interviews with senior SRSP managers suggest a continued interest in the region and a commitment to maintain the needed support for post project support through existing resources. • CPIs are highly visible, ensure immediate benefits to the community and also typically consume the largest chunk of development budgets in any community program. Accordingly these should receive a higher level of attention from the feasibility through design, implementation as well as the O&M. The survey shows a generally good performance on the “implementation fronts” however the design and O&M phases could benefit from further attention. Among other areas of focus the CPIs are generally small in scope, however a rapid “environmentalscreeningandmitigation”protocol could help some categories of schemes. Overall the team recommends additional investments in staff skills for field surveys and design; use of design standards and guidelines and customized training modules for O&M practices. This will allow SRSP to further build on its current success and ensure that the CPIs continue to yield long term dividends without the need for any hand holding or follow up repairs in project areas that are generally remote and difficult to access.
  • 12. 12 MALAKAND DIVISION AND THE EERP The floods that affected large parts of Khyber Pakhtunkhwa in 2010 only compounded the issues being faced by the population; almost 1,500 people lost their lives and 37,000 homes were destroyed. Malakand Division was one of the worst affected areas; the region had not yet recovered from fundamentalist insurgency and the subsequent military intervention that took place in 2009 and displaced over 2 million people5 . AusAid development aid to Pakistan has burgeoned over the last four to five years. In 2001-2002, AusAid donated an estimated $4.5 million to Pakistan with the focus on increased access to basic education for girls and better management of the environment6 . In contrast, in 2010-11, assistance to Pakistan soared to $67.5million, with a major chunk of the budget being directed towards humanitarian assistance and reconstruction7 . An initial Early Recovery Programme was designed to target the flood affected districts of Peshawar, Nowshera and Charsadda. Once the activities and interventions for the three districts had been implemented, SRSP, keeping in view the Pakistan governments plans for the province, out lined in the PCNA, MTDF and Early Recovery Priorities in KP, submitted a proposal to AusAid for the Expanded Early Recovery Programme (EERP) which would focus on reconstruction in Malakand Division8 . In 2011, AusAid, as part of its mandate for reconstruction of the Malakand region, earmarked AUS$ 3 million (PKR 255 million) for the Expanded Early Recovery Programme (EERP). EERP is a nine month long initiative by Aus-AiD, in collaboration with SRSP, whose overall objective is to “build resilient communities in areas hit by floods and insurgency in Malakand Division9 ” . This objective was to be achieved using a multi- pronged approach with the restoration of Community Physical Infrastructure being a central focus of the project, accounting for 93% of the financial outlay. The challenging environment suited SRSP, which had been working in the project area since 2001, with a long term community based approach. Typically for SRSP, a basic skeleton structure of the organization remains in the area to interact with communities even after the project it implements comes to an end. This Core enables SRSP to continue to support the capacity building and networking of communities and also retain a knowledge base of the area and its people; with this structure in place SRSP leverages additionalresourcesforthecommunitieswhenopportunities arise. This is particularly important from sustainability point of view, comparing it to other imitative which have a short terms‘project specific’approach. The overall impact of initiatives carried out under EERP is significant; 74,385 men and women, representing individuals from the 191 poorest and most vulnerable districts of Malakand Division10 have benefitted from the programme. The selection of schemes was to be carried out using the platform of 395 community based organizations or COs. The CO platform was chosen in order to make the process a participatory and transparent one. The CO members were to be trained and their capacities built in a bid to enable them to organize themselves, voice their concerns and needs collectively, and most importantly take collective ownership of their schemes to achieve long term sustainability. The 395 CO’s formed for this purpose worked towards reconstructing/ rehabilitating 213 CPI schemes which were to benefit a targeted 37,000 households. The entire process, from the formation of the COs, to selection of schemes, through to the implementation and eventual handover of the schemes to communities was to be carried out within the mandated timeframe of nine months, from May 2011 to January 2012. 5 Malakand Comprehensive Stabilization and Socio-Economic Development Strategy – GoNWFP, 2009 6 Aid budget summary 2001-02http://www.ausaid.gov.au/Budgets/Pages/default.aspx 7 Australia’s International Development Assistance Budget, 2010 8 Livelihood Strengthening Programme - Expanded Early Recovery Project in Border Areas of Khyber Pakhtunkhwa (Malakand Division) – SRSP, April 2011 9 Expanded Early Recovery Project (Livelihood Strengthening Programme) Project Completion Report - SRSP 10 ibid
  • 13. 13 SCOPE OF WORK Associates in Development Pvt. Ltd. was contracted to carry out an evaluation of the Community Physical Infrastructure (CPI) Projects in order to establish the immediate impacts of the schemes and validation of design and planned outcomes. The scope of work is the evaluation of the 213 Community Physical Infrastructure (CPI) projects implemented by communities with SRSPs assistance under the EERP. The majority of them, 40 % were built in Swat, followed by Shangla, Lower dir and Malakand which had 12 %, and lastly, Buner, Upper Dir and Chitral which had 5 % of the total11 . Most of these schemes were to assist communities in the provision of DWSS, followed by Road Infrastructure, Sanitation, Bridges, Irrigation Schemes, and Micro Hydel. There is an odd one CPI of a rehabilitation of a sports facility as well. Schemes range in costs from Rs 110,000 for a Hand pump in Buner to Rs 8, 600,000, average cost of the different type of schemes range from Rs 5.8 million for Bridges, to Rs 0.7 million for DWSS12 . Cost per beneficiary is most favorable in the case of irrigation CPIs. At Rs 1977 per HH benefited, where 4 irrigation related schemes are benefiting 463 beneficiaries as compared to soil conservation works where 2 schemes costing more that Rs 7 mill with an average cost of Rs 23,675 per beneficiary.13 At the individual scheme level, the aim was to assess; i) the Relevance of the CPI to the intended beneficiaries’ needs; ii) the Efficiency with which the schemes were implemented, in terms of costs and time; iii) assessment of the scheme Effectiveness; iv) the direct and indirect Impacts of the scheme and’ v) the Sustainability of the scheme14 . These criterions were used to judge whether or not the expected outcomes envisaged in the projects proposal/financing agreement are being realized by the community built and maintained infrastructure schemes. 11 See Annex 2 CPI Distributions 12 See Annex 2 CPI Distributions 13 See Annex 2 CPI Distributions 14 See Appendix 4 - Evaluation Matrix
  • 14. 14 3. APPROACH AND METHODOLOGY The approach and methodology of the study revolved around the physical verification of the technical information and obtaining a firsthand account of how the beneficiaries viewed this initiative. The activities were divided into a three staged approach outlined below: Stage1wastheinceptionphasewhichlastedfromthe8thAprilto17thApril2013.Thistimewasusedtodevelopanunderstanding of the programme, review all relevant documentation and secondary data and to finalize the tools used in the field and the teams’ work plan. This stage culminated with the submission of the Inception. Stage 2 was the Field research phase during which the teams were mobilized and they completed data collection in the targeted villages. Key Informant interviews with Project staff, community members and other stakeholders, the household survey, engineering field reports and FGDs were all conducted during this phase. The final stage of the process, Stage 3, involved the entry and analysis of all the data collected and the preparation of the Final Report. A draft of the Final Report is to be shared with SRSP, and the comments made by the client, if any, are to be incorporated before the Report is handed over and the findings are presented. 3.1 Stage 1 - Inception 3.1.1 Work Plan The field work was spread over 7 districts where drive time over rugged mountain roads could take over 5 hours. The entire evaluation was to be completed within a tight deadline and the work plans for the teams were designed accordingly. Initial work plans were submitted to SRSP along with the original Technical Proposal and Inception report. These plans had to be modified due to a number of factors, most crucially due to the difficulty in finding female researchers willing and able to work in the project areas. A final version of the work plan was drafted near the close of the inception phase15 . 3.1.2 Tools At this stage it was decided that the engineering focus would be on i) a preliminary desk review which studies the availability and adequacy of the documentation on design estimation and the documentation on approvals of the completion process. The data from the desk review has been reported in the form of the “Desk Review Report”. ii) The engineering team was to carry out extensive site visits during which they would physically validate the design and outcomes of the individual CPI schemes. Additionally, they Inception/Desk review Field work Data analysis and report writing •Understandstatedand unstatedexpectationsofSRSP •Reviewrelevantproject documentsandreports •Designchecklists,templates, finalizedatagathering instrumentsanddetailedwork plan •Submissionofinceptionreport •DatacollectionfromtargetUCs •Meetingswithandrelevant stakeholdersandreviewof recordsoffacilities •IDIs&FocusGroupDiscussions withwithProjectstaff, communitymembersandother stakeholders •RecordFieldObservations •Dataentryandanalysis •Presentationtotheclienton keyfindings •PrepareDraftreportforsharing withtheclient •IncorporateFeedbackand submitFinalreport would verify the O&M systems and their effectiveness. In addition, the tools for the social sector assessment were drafted at this stage. An extensive review of material available on CPI schemes and on other similar assessments in the target districts, inputs from social sector specialists and Aid’s extensive prior experience with similar assignments were all drawn on to draft the initial tools which consisted of a i) detailed household questionnaire and ii) a form for Focus Group Discussions (FGDs). 3.1.3 Staffing In order to carry out the work in the least amount of time and maximize the use of available resources, it was decided that two field teams would carry out operations simultaneously in two clusters. Each field team comprised of a Field Supervisor and two Researchers. The Researchers were responsible for gathering qualitative and quantitative information from the project sites using the purpose designed data gathering forms. The team also included a short-term Advisor, a full time Team Leader, a senior Engineer, and short terms inputs from a Social Sector Specialist, Gender Specialist, and Data Analyst. TheFieldsupervisors,TeamLeaderandothersectorspecialists 15 See Annex 7 – Work Plan
  • 15. 15 not only supervised these activities but also participated actively in the data collection. The Field Supervisors were the first level Quality Assurance; at the second tier, a Quality Assurance Manager rechecked and validated the quality of the data collected in the field. The proposed Team Leader retained overall control of the research operations and maintained close liaison with the designated representatives of SRSP. The team was mobilized immediatelyafterthecontractwassigned.Teamcoordination was ensured through constant communication and contact (including frequent meetings) between all team members; head office staff and the field teams. The team was fully mindful of the cultural sensitivities and local norms which had to be adhered to when working in the target areas. The team received the full support from SRSP staff in terms of logistical arrangements, facilitation of meetings and coordination at the field level. 3.1.4 QA Plan In order to ensure that all tasks are completed with the high standards quality that clients have come to expect. All field work, data collection, results and reports were passed through Aid’s comprehensive yet dynamic Quality Assurance (QA) system. At the inception stage, the top management at AiD, along with the project Team Leader and senior Sector Specialists designed QA policies which consist of specific Key Performance Indicators (KPIs) used to gauge the level of performance and resultantly, the quality and timeliness of project delivery. For the Evaluation of Immediate Impacts of CPIs under EERP, a 4 tier QA approach was chosen which functioned in parallel to Aid’s standard QA measures16 . The first level of QA was the Field Supervisors who were required to scrutinize all the primary data collected on a daily basis. This was important for identifying, and subsequently ratifying, any gaps or omissions in the questionnaire whilst still in the field. Next, staff at Aid’s head office in Islamabad reviewed the questionnaires sent in by the Field Supervisors on a weekly basis. A third level of QA took place once the data has been entered cleaned and analyzed.The sector specialists then prepared a Final Report QA’d by the Project Advisor. 3.1.5 Sampling In order to ensure that a representative sample was selected for the study, a multi stage sampling method was used. In the first stage the seven districts were divided into two clusters namely Cluster A and Cluster B. Cluster A consists of Swat, Shangla, Buner and Malakand while Cluster B consists of Lower Dir, Upper Dir and Chitral. The sample was designed with a view to capturing the diversity of the entire Project area and the types of schemes. A total sample of 60 schemes out of the total of 213 was randomly selected; this represents a Confidence Level of 93% with less than 10% margin of error. The total sample was first distributed in terms of the proportion of schemes in each district and then further divided according to the number of each sub-type of scheme, i.e. irrigation, drinking water supply, roads and drainage in each region. The second list for ‘types of schemes’ in each region was first ranked in descending order of number of beneficiaries of the scheme, then the nth scheme of each subtype was selected based on an approximation of the sample/the population17 . See fig 1.1 and 1.2 The field teams managed to look at 26 schemes in district Swat, 7 each in district Shangla and Lower Dir, and Malakand, 6 in district Upper Dir, 4 in Buner and 3 in District Chitral. Out of these 60 Schemes, 22 schemes were DWSS, 19 road infrastructure, 7 Sanitation, 5 Bridges, 4 irrigation and 3 were micro Hydel18 . Ten additional schemes were chosen to replace any scheme from the initial selection that could not be visited due to unforeseen circumstances, such as security concerns, inaccessibility etc. Eventually, four schemes were selected from the list of ten to replace schemes that could not be visited19 . Fig 1.1: CPIs by District Fig 1.2: CPIs by Type Note: Outside Ring: = Total EERP CPI s Inside Ring: = Evaluation Sample Note: Outside Ring: = Total EERP CPI s Inside Ring: = Evaluation Sample Swat Bunner Malakand Shangla Lower Dir Upper Dir Chitral 43% 40% 5% 9% 10% 12% 12% 11% 12% 12% 12% 7% 10% 5% 40%36% 32% 12% 8% 7% 6% 4% 1% 5% 8% 11% 30% 16 See Annex 5 – QA Diagram 17 See fig 1.1 and 1.2 18 See Annex 3 Sampled 60 CPIs 19 This is further detailed in Stage 3: Challenges in the Field
  • 16. 16 3.2 Stage 2 – Field Work 3.2.1 Pre-testing and Finalization of tools After all formats, sampling and work planning was finalized the two teams were mobilized in the field. Initially, they were accompanied by the Team Leader and sector specialists who supervised activities at this stage. The data collection tools were initially pre-tested at two schemes in Swat. The team leader led the pre testing exercise and both teams accompanied him for the exercise. After the pre-test, the team held a session during which the forms were re-checked for any inconsistencies, gaps or redundancies. The necessary changes were made to the data collection tools and the finalized forms were used for all subsequent data collection. 3.2.2 Field Activities The field teams adhered strictly to a predefined protocol for conducting visits to the CPI sites. Before each visit, the engineers reviewed all available documentation for the scheme to be assessed on that day. They extracted all necessary information before the social and engineering teams were taken together to the site by the local SRSP representatives who were facilitating the visits. Once the teams arrived at the village, the engineering and social teams split up; the engineers went to the CPI to make physical verifications and fill out the corresponding forms. In the meanwhile, the social sector team dispersed in the village; the females would fill questionnaires going from door to door, whilst the men went to the hujra to meet with the males. The females would continue on to conduct FGDs with those women who had not been included in the HH survey. Once the engineers had completed the physical inspection of the schemes, the male researchers and the engineers would gather the members and management of the all- male COs. Together, they would go over all of the COs documentation and interview the management to assess the adequacy, or lack thereof, of the O&M system in place for the scheme. Afterwards, the engineers and social researchers would together to conduct an FGD with male members of the community; ensuring both members and non-members participated. 3.2.3 Challenges in the field The field teams faced a number of challenges working in some very volatile areas. The sample schemes were spread out over a sizeable area and many were located in remote areas. SRSP’s outreach to these areas is commendable; the schemes had been implemented in areas where no other government or non-government entities had any presence. This meant many hours of driving and trekking through often rugged and mountainous terrain for the field teams. Some of the schemes could not be visited. For instance, two schemes from Swat; Chinawatt and Foladai were replaced, as was one scheme in Buner. Chinawatt was replaced due to the fact that it could only be reached after a three and a half hour walk through treacherous, snow covered mountain paths; a trip that locals said was only advisable for locals familiar with the village. It was replaced with a scheme implemented in Saidu Sharif. Foladai was replaced with a scheme in Deolai because Foladai was rendered inaccessible due to torrential rains. Similarly, Malikpur, a village in Buner could not be visited because there were on-going military operations in the area. 3.3 Stage 3 3.3.1 Data Entry, Analysis and report writing Data from the field was periodically sent to the AiD Head Office by the field teams for parallel data entry. The final set of data from the field was received on 12th April when the entire team held a collective work shop to discuss their experiences, recommendations and the lessons learnt. The forms had all been coded for ease of management and to minimize the potential for errors. Nonetheless, as per QA protocols, the forms received from the field were checked for any major inconsistencies, missing information or collection errors. These forms were then passed on to data entry operators who used Microsoft Excel™ spreadsheets to record the data. The Excel™ spreadsheets were exported to Stata™ software which was used to analyze the varied forms. After data cleaning, the Data Analyst prepared an extensive list of tables which were used to develop the results and findings for the Final Report. The final report is organized around the five Evaluation Parameters initially decided upon. Each parameter has been given a separate section and the CPI’s have been analyzed in terms of each one in great detail.  
  • 17. 17 CPI DESCRIPTION The evaluation team visited 60 CPI schemes, of these 43 % were in Swat, 12% in Shangla and Lower Dir, 11 % in Malakand, 10 % in Upper Dir 7 % in Buner and 5 % in district Chitral. Schemes costs range from Rs 0.22 million, hand pump CPI in Mankass, Kabal Swat to Rs 8.6 million Micro-Hydel in Shao, Swat. Theseschemesreflectedthepriorityneedsofthecommunity. Of the total 60 schemes 22 are DWSS, 19 were Road infrastructure, 7 Sanitation, 5 Bridges, 4 Irrigation or 3 MHP. DWSS Aid looked at 22 DWS, 3 were in Buner, 2 in Chitral, 3 in Lower Dir, 3 in Malakand, 1 in Shangla, 1 in Upper Dir, and 9 in Swat. These schemes ranged in cost from Rs 1.2 million, for a Gravity flow, scheme in Abbaseen Colony, district Shangla to Rs 0.22 million for a hand pump based scheme in Mankass Kabal, district Swat. There were various subtypes, but the majority was Gravity flow, i.e. in which case the water was stored in large tanks which were supplied from natural springs and fed into the communal areas by gravity flow by a distribution network of pies. On the other hand 7 schemes were for hand pumps. In the 22 schemes which AiD looked at the planned beneficiaries was 1700 whereas the actual beneficiaries were reported to be 2600. Cost per beneficiary house hold ranged from Rs 2000 to Rs 24000 for a HP scheme in Jabba, Swat and a Gravity flow scheme e in Shaqi Ghawaljai also in swat respectively. ROAD INFRASTRUCTURE Road infrastructure included link road and causeways. Link roads were either, what are called as PCC rigid pavement or earthen rehabilitation works of existing alignments or construction of causeways. A total of 19 road infrastructure where constructed out which 2 was causeways and the rest were either rigid pavement or earthen road improvements with retaining wall and cross drainage structures. 8 schemes were in Swat, 4 in lower Dir, 2 each in Malakand and Upper Dir, and 3 were in Shangla district. Their cost ranged from Rs 1.33 million for a link road in Gujjer Tangi Badro, Swat district to Rs 0.5mill road in Aminabad, also in district Swat. Total beneficiary household were shown as 2900, however an estimate which the engineers gather after discussions in the field indicated the figure to be close to 4000. Cost per beneficiary ranged from Rs 1944 to Rs 9029 for Akhun Baba, Pcc link road in district Swat, and Baghgay Maloch, RCC cause way also in district Swat. 4. FINDINGS BRIDGES Out of the 18 bridges which SRSP assisted with under the EERP project the team was able to see 5 bridges, 4 of which were pedestrian suspension bridges whereas 1 was a RCC bridge for regular traffic. One of the suspension foot bridge were located in Buner, 2 were located in upper dir whereas 1 was in Shangla. The RCC Bridge in Kamay, Swat., The bridge CPIs cost from Rs 0.92 million for the suspension bridge constructed in Bazarkot, district Buner to Rs 2.5 million for the RCC bridge, constructed in Kamay Swat. Bridges like roads benefit not just the immediate community which has been involved in the construction of the scheme but any adjacent village or hamlet which is using it. In one case however the team found that the HH reported were less than what were planned. Cost per beneficiary varied from Rs 4585 for the Pedestrian suspension bridge in Swat to Rs 10123 for Malow, in Upper dir. SANITATION 7 schemes which addressed the sanitation and drainage of the communities were built. 5 of these are in district Swat, whereas 2 are in Shangla. These schemes are mainly construction of drains and rigid pavement The total cost of each sanitation related scheme ranged from Rs 0.3 million for a drainage scheme in Bazkhelin district Shangla , to Rs 1.2 million for the Street pavement and drainage in Shagai, district Swat. The total beneficiaries of the road infrastructure were reported to be 1430 instead of the originally planned 1030. The cost per beneficiary ranged from Rs 1717 in village Faqira; district Swat, to Rs 11780 for Bazkhel, Drainage scheme where the number of beneficiaries was very low. IRRIGATION Out of the total of 12 irrigation schemes which were done under EERP, the evaluation team looked at 4. Most of them wereinSwatdistrict,andoneinMalakand. Theschemesrange from installation of a pump, to a construction of irrigation channel to channel lining and in one case construction of a retaining wall. The cost of the schemes range from Rs 0.55 million for the ram pump in Babu Maira in Swat to Rs 1.1 million for the irrigation channel lining and construction of retaining wall, in Meragai, Swat. The total beneficiaries for the 4 schemes are around 800 HH. MHP The team visited 3 out of the 8 MHP done under EERP. One of these was in Swat; the other two in Upper Dir and Chitral
  • 18. 18 respectively. MHP are technically complex and relatively costly. The schemes cost ranged from Rs 2.7 million for the 50 Kw MHP in Khanabad, Upper Dir, to Rs 8.6 million for the 100 Kw MHP in Bhamborate, Chitral. Twooftheschemesi.e.theoneinShao,SwatandBhamborate, Chitral are being implemented using an innovative approach of what is called a social enterprise in which both SRSP and the community are co-managing the scheme. Thenumberofbeneficiariesisaround900andthecostranges from Rs 12176 per beneficiary to Rs 31300 per beneficiary. 4.1 CPI documentation: Availability and Adequacy The Engineer’s Desk Review constituted the first level of verification of the 60 CPI schemes mentioned above. Before the schemes themselves were visited the engineering team assessed the availability and adequacy of the CPIs’ documentation annexure 620 , shows a simplified diagram of the PI process, and the various documentation required. The process of implementation of any CPI is triggered by a resolution from the Community Organization.This resolution indicates that the community is interested in a development partnership have reached a consensus on a priority problem which they would like to address in the shape of a possible CPI. This is also, what can be termed as the culmination of a series of meetings called 1st dialogues. Oncearesolutionispassedbythecommunity,itisreceivedby the local social organizer(s) who prepare a Social Feasibility for the scheme. Engineers, meanwhile, prepare the required technical reports such as Design and Estimates and carry out an Environmental Screening to ensure that there are no major environmentally detrimental effects of the scheme. If the results of the social and engineering reports and the environmental screening are found to be positive and they fall within the criterion set by EERP, the scheme is given a formal approval for implementation by the SRSP Head Office. Afterwards, SRSP representatives engage the community in a ‘3rd dialogue’ during which a Terms of Partnership (TOP) document is signed by the community. The TOP is included in the final Project Proposal. For record keeping, all copies of receipts, expenditures as well as any and all other documentation pertaining to the construction of the schemes are to be maintained in a Physical Infrastructure (PI) Register by the CO’s secretary. Once the scheme is completed a Project Completion Report (PCR) showing the actual cost and date of completion is prepared; the PCR also becomes part of the CO’s and SRSP’s records. If the schemes is successful and is handed over to the community, and a Project Completion Certificate is issued. The evaluation team assessed the availability and adequacy of this essential documentation for each of the sampled schemes and has come up with the following result. The detailed scheme wise summary is available in a tabular form in the annexure21 . 4.1.1 Social Feasibility A social feasibility report serves several functions; it shows that the Community Organization exists on the ground, it has an open bank account, and that there was no conflict amongst the CO’s members in general or around the priority ranking of the CPI itself. Allthe60schemessampledhadtherequiredSocialFeasibility documentation and it was found to be adequate. 4.1.2 Environmental Screening Environmental Screenings were carried out using a simple template developed by SRSP for its field staff. The screenings were used indicate whether or not the proposed project is safe for the environment and weather a detailed environment assessment is to be made or not. The Environmental Screening consists of a three stage process. At the first level, an environmental sensitivity assessment is carried out. Environmental sensitivity is taken in terms of the proximity of the proposed scheme to natural habitats/vegetation, slopes, populated areas, various kinds of wetlands, historical and cultural sites, etc. In the second stage, the level of environmental screening required for the scheme is determined based on the results of the environmental sensitivity assessment. An Environmental Review (ER) is the basic minimum level of screening required for all schemes, regardless of their ranking/categories from the sensitivity assessments. Higher levels of screening; those which are more detailed and are to be performed by professional environmentalists are required for schemes which rank poorly in the environmental sensitivity assessment. The Environmental Review is the third and final section of the environmental screening. The ER is used to determine the potential negative impacts of the scheme on the environment and details the measures that must be taken to mitigate those negative impacts. These mitigation measures must be included in the schemes’proposals. Environmental Screening documentation was available for the first two stages, albeit partially in some cases for 49 of the 60 schemes. The ES documentation for the remaining 11 schemes was either not available or had not been filled in. Furthermore, the team was unable to see any Environmental Review reports. 4.1.3 Technical Feasibility: 4.1.3.1 Design Basis The most crucial aspect of any technical feasibility is the design basis and assumptions on which the schemes has actually been designed and estimated. The table below shows some examples of the required design basis which would necessary for a correct design. Type of Scheme Required Design basis Road/Bridge CBR or bearing capacity, Axle load, Details of construction joints Drinking Water Supply Capacity, HH requirements Drainage Rainfall Intensity, Catchment area Irrigation Crop water requirements/Soil type The design basis for 27 of CPI’s was not available or inadequate. Mostofthesewerelinkroadorstreetpavements. Key information such as bearing capacities of soil and the Axle loads were missing22 . 20 See Annex 6 21 See Annex 1A 22 See Annex 1 A Table 1.2
  • 19. 19 4.1.3.2 Design Calculation Once we have the design basis of any engineering structure or its component the next step is to calculate the design parameters. Depending on weather a design is for a street pavements, roads or drinking water supply storage tanks, for the engineer the design of the thickness, compaction of roads, tank wall thickness, concrete slab thickness or reinforcement design, all need to be calculated. These calculations are made to ensure the integrity and efficiency of the structure and to ensure that there is a backup in case of any liability For the schemes implemented by SRSP, it was found that the design calculations for 32 schemes were not available. Of the remaining 28 schemes the Calculations for 10 seemed inadequate. For instance, in the case of storage reservoirs, the calculations for the determining the dimensions of water tanks were missing23 . 4.1.3.3 Construction Drawings: Construction drawings are needed to ensure that the community and labor working on the ground are able to construct the schemes in accordance to the designs envisioned. Accept for one scheme namely Jabba in district Swat, all the CPI proposals reviewed had at least the basic schematic construction drawings attached as part of the project proposals. See table 1.424 4.1.3.4 Material and works specifications Material and works specifications must be detailed because they are essential for ensuring the quality of the construction is up to the standard anticipated by the project proposal. The site engineer and the community must be very clear on what is to be used for the construction of the schemes and how it is to be used. All the CPIs mentioned what materials were required, such as bricks, sand and steel. However, it was observed that invariably, there was no mention of the detailed specifications for these materials such as the standard quality of the bricks, the type of sand or strength of the steel. Detailed Material Specifications Should be: Cement Grey Portland Cement shall be normal setting cement of make and source as approved by the Engineer. Cement shall conform to the requirements of ASTM C 150 unless otherwise acceptable to the Engineer. Fine Aggregates Fine Aggregate shall be clean River sand from an approved source of supply and of uniform quality having fineness modules between 2.3 and 3.10.Fine aggregates shall comply with the requirements of the relevant ASTM C-33 Specifications, and shall be graded as follows: Sieve Number/Size %age (by weight) passing 9.50 mm 3/8” 100 4.75 mm (No.4) 3/16” 95-100 2.36 mm (No.8) 3/32” 80-100 1.18 mm (No.16) 3/64” 50-85 0.6 mm (No.30) 25-60 0.3 mm (No.50) 10-30 0.15 mm (No.100) 2-10 Limits for deleterious substances of total sample shall be: Clay lumps and friable particles Maximum 3% by weight Material passing No.200 sieve Maximum 3% by weight Coal and lignite Maximum 0.5% by weight Weight loss of sand subjected to 5 cycles of soundness test when sodium sulphate is used shall not be greater than 10%. Coarse Aggregates Coarse aggregate shall be 3/4“ down, hard crushed stone from a source approved by the Engineer. For members up to 3“ thickness, 1/2“ down crushed stone shall be used. Coarse aggregate shall comply with the graduation requirements of ASTM C-33 and shall be graded as follows: Nominal Size of Graded Aggregates shall be 19 mm (3/4”) down Sieve Number/Size %age (by weight) passing 19.00 mm (3/4”) 90-100 12.50 mm (1/2”) - 09.50 mm (3/8”) 20-55 04.75 mm (3/16”) 0-10 02.36 mm (3/32”) 0-5 Weight loss of coarse aggregate when subjected to 5 cycles of soundness test using sodium sulphate shall not exceed 12% and %age loss for Los Angles Abrasion (500 revolutions) not be greater than 50. Aggregates shall be screened and washed if required to the satisfaction of the Engineer Water Water to be used in the work shall be clean water or approved by the Engineer. The community shall supply sufficient water for all purposes including mixing the concrete, curing, and cleaning plant and tools. It should be clean and free from injurious amounts of oils, acids, alkalis, salts, organic materials or other substances that may be deleterious to concrete or reinforcement. Where doubt exists as to the suitability of water, it should be tested in accordance with BS 3148. Steel Unless otherwise specified, all deformed reinforcing bars shall comply with the requirements of ASTM 615 for deformed cold worked new stock billet steel bars and shall have a minimum characteristic strength of 40,000 lb. per square inch. 23 See Annex 1 A Table 1.3 24 See Annex 1 A Table 1.4
  • 20. 20 4.1.3.5 Costing/Estimates The costing and estimates for all 60 schemes were checked and found to be correct. 4.1.4 Water Quality Test Water Quality tests had to be carried out for DWS schemes to ensure that the water from these schemes was potable. Out of the 22 DWSS schemes Water Quality tests reports were available for all the schemes. 4.1.5 Project Proposal The project proposals are detailed documents that cover the technical (engineering), social, procedural and management aspects of the schemes. The engineering documentation listed in the previous sections such as environmental assessment reports and design and cost estimates are part of this proposal. Similarly, the objectives of the project, the roles of the key stakeholders and the protocols for management of the project are all outlined in the proposal. Project proposals for all 60 schemes were available, in the regional offices albeit some were incomplete as mentioned elsewhere in this section. 4.1.6 Project Approval All the schemes had received formal approval by the competent forum. Project approval documentation was available for all schemes. 4.1.7 PI register A PI register is to be maintained by the CO, typically by the CO’s secretary. The PI register contains all documentation related to the implementation phase of the scheme, most commonly the receipts for outlays during the construction phase, or for O&M. PI registers were available for 54 of the 60 schemes and most were diligently maintained, however, the team was not able to see the PI registers for 6 schemes25 . 4.1.8 Project completion report The project completion report details the initially estimated quantities of various materials and labor required for implementation of the CPI and the actual quantities used as well as the variation between the estimate and actual outlays. The project completion reports were missing at 4 of the schemes visited. Of the remaining 56, completion reports for 5 were deemed to be inadequate because they did not have signatures of the community members26 . 4.1.9 PI completion certificate A PI completion certificate is prepared by engineers once the scheme is ready for hand over to the community. It lists the contributions made by the stakeholders and the dates of completion. All of the CPI’s had completion certificates except Shao, MHP in Swat, and Bazarkot and Riaz Ambela in district Buner27 . 4.1.10 Handing and taking over certificate: The Handing and Taking over Certificate is signed by the community members once the scheme has been completed and is officially being handed over to them by SRSP. The certificate is a crucial for ensuring the sustainability of the scheme since it makes official the community’s ownership of the scheme and lists the members of the O&M committee. It also certifies that O&M systems have been put in place, such as the opening of a bank account specifically to hold an O&M fund. The Handing and Taking Over certificates were available for 55 schemes. Out of the remaining 1 had failed, 2 schemes had not yet been handed over and 2 schemes did not have a certificate on file28 . 4.2 Design Validation This section outlines the Engineering Team’s findings of the physical validation of the various design parameters of the CPI’s. The design parameters verified include scheme layouts, design measurement, material specifications as well as the workmanship, the scheme outcomes, environmental screening, operation & maintenance, and finally the schemes functionality, efficiency and effectiveness. This section in particular covers the findings from the layout and design, environmental screening, and material validation, the rest of the findings from the engineers visit to the site are in their relevant sections which follow. 4.2.1 Scheme Layouts The scheme layout was verified on how the various CPI components are laid physically on the ground. For example the alignment of the road, or the location of the various structures mentioned in the design. The engineering team conducted site visits to all sample schemes to validate the physical layout and schemes layout. It was observed that except for 9 CPI29 all the rest were implemented according to the planned layout. The major problems either related to a difference of what was observed in the pipe network, such as missing pipes or tanks observed at Yakh Tangay village in Swat, Banjo Tangay in Buner, Abbaseen village in Shangla and missing elements, such as RCC culverts in village Gujjer Tangi Swat30 . Five schemes were found to have minor problems. For example the design of the Gravity Flow DWSS (GF) in Sory Kad village, Swat, showed two supply lines were showing in a schematic layout but it was observed that instead of two lines, four lines were originating from the tank. However, despite the deviation from the scheme layout, the desired design discharge was acquired satisfactorily. In Asilo village, Lower Dir, the designed/proposed layout of distribution lines of the DWSS had not been adhered to on site. Similarly the drawings of the Gravity Flow scheme in Ambela village, Buner, indicated that 4 supply lines were originating from the storage tank. However, it was observed that 05 distribution lines were in connection with the storage tank. 4.2.2 Design Validation: All the 60 schemes were checked to validate the design in terms of the measurement of the structure, the material used and its workmanship. It was reported that 48 % of the schemes were found to be exactly as per design, 34% had minor variations and were marked as satisfactory. However, 18 % had major variations, from what was originally planned. 25 See Annex 1 A Table 1.5 26 See Annex 1 A Table 1.6 27 See Annex 1 A Table 1.7 28 See Annex 1 A Table 1.8 29 See Annex 1 B 30 See Annex 1 B
  • 21. 21 The schemes with variations either had missing structures, such as those at Sanam village in Shangla, Gujjer Tangi & Mankass Kabal in Swat and Faqira, in Swat, or the measurement of structures did not match as was the case in, Banjo Tangy DWWS , district Buner, Abbaseen Colony, DWSS in district Shangla, amongst other31 . 4.2.3 The following is a type wise breakdown of the CPIs: 4.2.3.1.1 Drinking Water supply Schemes Out of the 22 schemes the design and layout of 4 schemes could not be validated on site. For e.g. In DWSS Yakh Tangay, district Swat, Banjo Tangay, district Buner, Abbaseen Colony in District Shangla, and Danwa, Lower Dir, the original design has a different configuration than what is on site. In Kuru Bala, Chitral, the community has not built the Dug well where originally laid out by SRSP, and as a result the scheme has failed. 4.2.3.1.2 Road Infrastructure: Out of the 19 road infrastructures which were visited, there was one scheme for which a layout could not be seen. Only 2 were found to be out of sync with the original layout. Gujjer Tangi, Islampur in district Swat, did not have 7 culverts originally designed, similarly in Baghgay Maloch, also in district Swat, the layout of the culverts is different from what was shown in the project proposals. See table for detail Furthermore, the measurements of the structures in road infrastructure CPI in village Samteer and Aminabad, district Swat and village Sanam, district Shangla did not match with was planned. See Table for details. 4.2.3.1.3 Bridges All the bridges were on the spot which they were planned for; however the design basis or calculation were missing. Only in the case of Tangir we have some design however the calculations were not adequate. 4.2.3.1.4 Sanitation The layouts of all the schemes were found to be as planned. However the design for drains and pavement did not have a technical basis or any reference. 4.2.3.1.5 Irrigation The layout of the schemes are fine, however there are discrepancies in measurement of the structures in the case of Meragai and Babu Maira scheme. In the case of Babu Maria a tank has been constructed which is not part of the original design and is not mentioned in the documentation, where as in the case of Meragai, the retaining wall is shorter and also lower than what was proposed. 4.2.3.1.6 Micro Hydel Project All the schemes have been constructed as per documented layout and design 4.3 Relevance From the GoKP’s viewpoint one key document which indicates the priority areas of investment of the GOKP for Malakand Division is the Malakand Strategy prepared in 200932 . It is noteworthy that one of the means to achieve its objectives, the strategy envisions the rehabilitation or building of road and bridges, water and sanitation, irrigation, and power Infrastructure. The CPIs done under EERP closely match the priority of the GoKP as it has set down in its strategy document. AusAid is concerned EERP comes under its objectives # 3 for Pakistan as it is explained in the Pakistan Annual Program Performance Report 201133 , this is; • Sustainable economic development - through increasing agricultural productivity and improving rural livelihoods. All the CPIs contribute towards improving rural livelihoods; on the other hand sustainable development requires sustainable institutions which at the local level would require a longer period of engagement with the communities than the timeline available under the EERP. Perhaps SRSP would needs to creatively develop a ‘sustainability’ pool towards which any client contributes when engraining SRSP. To directly gauge the perceptions of the local communities both a HH survey and Group discussions with local communities in all the 60 villages where the CPIs were implemented. To assess relevance, the HH survey grouped related questions under 3 indicators one asked them directly about whether the scheme was a priority for the whole community. The second related to their participation in the implementation process and third was about their contribution in cash or kind. 4.3.1 Priority An overwhelming majority, 98 percent of all people surveyed in 6 districts said that they considered the CPIs which were implemented by SRSP a priority. This response is more or less the same across all the districts, and gender. What is significant is that the response for non members is also very similar and 97.3 % also said that the scheme was a priority need of the community. 4.3.2 Participation ThehighestparticipationwasindistrictsChitral(100percent), where the community members felt they had participated thought the implementation of the schemes. Whereas he lowest level of participation about 60 % was reported from Shangla. Given the socio cultural norm of the area it was not surprising that participation of females was low. Participation in identification and planning /implementation ranged from a very low of 6% for both Upper and Lower where around 11 % of the respondents were members, to 67 % for Chitral where membership for WO was 100 %. Irrespective of that 96 % of the female respondents felt that the CPI was a priority need. The FGD analysis supports the findings of participation of females,withmalesmoreinvolved.Approximately17percent female participants claimed that ‘no one’ was involved and/ or interested in the project-related activities, as compared to 3 percent males who reported the same. Another 23 percent females were unaware/unable to comment on the query. While 63 percent male FGD participants claimed that most and/or all members fully involved, only two-third of the females (43 percent) thought the same. The highest rate of responses regarding non-interest were from Swat (23 percent), while FGD participants claimed high levels of 31 See Annex 1 B 32 Government of Pakistan’s Comprehensive Stabilization and Socio-Economic Development Strategy for Malakand Division. 2009 33 http://www.ausaid.gov.au/Publications/Documents/pakistan-appr-2011.pdf
  • 22. 22 full involvement in Buner, Malakand Agency and Shangla. Scheme-wise, the FGD participants claimed to be most involved in irrigation (71 percent). Around 70 percent of the respondents (25 percent; CO membersand15percent;non-COmembers)alsocontributed in kind offering themselves for labor, mostly in Buner and Malakand Agency (90 and 81 percent, respectively). The average number of labor days contributed by both males and females was 31, which was spent evenly on each CPI scheme. Further, 20 percent of respondents contributed additional items in kind, almost evenly (20 percent) across districts, with the exception of Chitral (40 percent) and Malakand Agency (no additional contribution). These included the following, district- and CPI scheme-wise: 4.3.3 Community Contribution One indicator on how relevant the community considers initiation and implementation of any project can be determined by how much they are willing to contribute towards it – in terms of cash and/or in kind (labor, etc). This is also an important indicator to ensure high (or low) levels of ownership of the project, so that chances of its sustainability are higher. In terms of community-based contribution to the construction (cash and/or in kind), 77 percent of the respondents claimed to have made contributions (75 percent females; and 79 percent males). The highest amounts of contributions were made in Chitral, Upper Dir and Buner (100, 92 and 83 percent, respectively). Pl see the graph below for contribution towards different CPI schemes. Interestingly, an equal amount of non-CO members (approximately 77 percent) as compared to their counterpart members contributed towards the construction of CPI schemes. Graphs 3.3 & 3.4: Mean cash distributed by location and type of CPI scheme (PKR): 8505 7000 6435 1543 900 120 100 80 60 40 20 Buner Chitral Lower Dir Malakand Shangala Swat Upper Dir Identification ImplementationPlanning 0 HH Participation 120 100 80 60 40 20 Buner Member of a WO CPI is a priority Participation in identification Participation in planning & implementation Chitral Lower Dir Malakand Shangala Swat Upper Dir 0 Women Response Of the households that contributed positively, 17 percent of them contributed cash. An average of PKR 5800 was contributed these respondents, where the male average was PKR 8000 and the female average was approximately PKR 4500. The highest frequency of cash contributions (30 percent) was witnessed in Shangla; the highest amount in Chitral (PKR 60000); and the CPI scheme contributed most towards was street pavements and drainage (20 percent).
  • 23. 23 4.4 Effectiveness The second evaluation parameter, effectiveness, was evaluated in terms of weather it is fulfilling the needs it was designed to meet, is it operational. Accordingly, the indicators identified for Effectiveness were: Functionality of the CPI schemes; benefits for community members; and problems encountered with the schemes. 4.4.1 Functionality As part of the approach, functionality of the scheme was also checked on site by the field engineers. In this regard they were able to check 55 CPIs out of the total sample of 60 and found that 95 % of the CPIs were functioning well whereas 5% or 3 schemes had some problems.34 Out of the remaining 5 CPIs which could not be checked, 4 were not operational at the time of the visit and 1 dug well DWSS, had been declared a failure due to unavailability of groundwater. The 4 schemes were not operational at the time of the visit included the MHP scheme in Shao Kalam, district Swat and Khanabad, district Upper Dir, Irrigation CPI in Meragai Swat and DWSS Dardyal, district Swat. The two MHP had technical breakdown and were in the process of being repaired by the communities, whereas, the Irrigation Channel in Meragai Swat was not operational, since it was not an irrigation season, whereas in the case of DWSS Dardyal, Kabal Swat, the intake structure had been damaged due to a snow slide and the communities were waiting for the snow to melt before attempting any repairs. schemes which were non operational included the MHPP scheme in Shao Kalam and Khanabad, in Upper Dir, both of them had technical breakdown and were in the process of being repaired. 4.4.1.1 Functionality: DWSS All the schemes were fully functional accept for 2. One of them was a gravity flow scheme Dardyal, in Kabal, Swat and the other was a hand pump scheme in Sher khan, Swat, where out of 5 hand pumps of to 3 were working. In the case of Kura Bala, the community decided to relocate the originally location for the CPI to one which was closer to them, however despite digging to a depth of90’thewellremainsdryandhasbeenofficiallydeclared as a failure 4.4.1.2 Functionality Road Infrastructure Despite the problems mentioned, all the schemes were functional albeit, in some cases partially as was the case of Link Road in Gujjer Tangi, district Swat, Feza, and Sur Kamar in District Shangla, where either the cross drainage work were not functional or some portions of the road had been severely eroded. All bridges were found to be functional and effective. From the HH survey, approximately 91 percent of the respondents acknowledged that the CPI schemes were functional across the 7 districts. When asked how effectively the CPI schemes were delivering, the female respondents gave more optimistic assessments stating that 86 percent of the schemes were 100 percent functional, as compared to the more cautious replies of male respondents, claiming 61 percent of the schemes to be fully functional. Another 3 and 26 percent females and males, respectively stated that the schemes were functioning above 75 percent, making the overall gender-wise level of satisfaction equal. Scheme-wise, on average, 72 percent of the schemes were termed fully (100 percent delivery). Scheme-wise, on average, 72 percent of the schemes were fully (100 percent delivery) and 15 percent partially functional (delivery above 75 percent) across the 7 districts (see Graph 3.6 below). FGD analysis supported the overall satisfactory responses from majority of the male and female participants. In some cases, respondents gave mixed reviews, such as in Chitral, where 33 percent reported that certain schemes were currently not working, and 67 percent stated that the schemes over there are working and they had no further complaints. CPI scheme-wise, the data is reflected in Table 3.1 (Annex: 1-C). There appeared to be no bias in positive responses of CO members who fully ‘owned’ the process, as opposed to the opinions of non-CO members, where 89 and 87 percent of both types of respondents, respectively acknowledged that the CPI schemes were between 75 to 100 percent functional. % YES % NO Is the CPI functional at present? 71 80 75 75 50 % Delivering 100% 71 10 03 3 % Delivering 0% 102 51 7 % Delivering 50% 18 31 81 40 % Delivering 75% 2 656 0 % Delivering 25% Graph 3.6: Level of functionality of CPI schemes Total Drinking Water supply Total irrigation Total Link road/Bridges Total Street Pavement and drainage Total Other 34 See Annex 1B Table 2.6
  • 24. 24 4.4.2 Benefits Community response was close to what the engineers found on the ground. The result of the HH survey Overall 90 percent of respondents claimed to be directly benefitting from the CPI schemes; including 67 percent of CO members and 58 percent of the non-CO members surveyed. Further, responses reflected that 80 percent of the surveyed people were benefiting from the CPI schemes in Chitral, reinforcing this district’s high rates of proactively in planning, implementation and cash contribution. A gender-wise break down reflects 67 percent satisfied male respondents and 100 percent females claiming to be directly benefitting from the CPI schemes there. Approximately 87 percent of the females reported to be directly benefitting from the CPI schemes, with 100 appreciations in Chitral, Shangla and Upper Dir. All CPI schemes were allocated above 86 percent priority by females, with irrigation reported to be 100 percent important for them. Female priority, based on CPI schemes is as follows: Drinking Water Supply OtherLink road/ Bridges Irrigation Street Pavement and drainage 50 50 73.1 26.9 100 100 97.1 2.9 Respondents in Shangla and Lower Dir claimed to be the most satisfied direct beneficiaries (100 and 97 percent, respectively), consistent for both males and females. Of the female respondents, 86 percent claimed to be direct beneficiaries, as compared to 93 percent of males. In terms of whether or not the respondents perceived the projects as being cost effective, results from the FGDs reflect a high level of unawareness of females as opposed to almost all males 98 percent sharing their viewpoints, with male perceptions spread out across the options. One female stated during an FGD that‘this topic was male domain’. The projects in Chitral were proclaimed most cost effective by 67 percent respondents during the FGDs. Details are given in Table: 3.5 (see Annex 1-B). 4.5 Efficiency: The efficiency of CPI construction has been evaluated with regard to the completion of the CPIs within the specified time and costs. An enlightening aspect is that even a high number of non- CO members (88 percent) were gaining positive externalities from the implementation of the CPI schemes. Reasons for respondents not In terms of related responses of satisfaction levels through the FGD analysis, 80 and 76 percent male and female respondents, respectively claimed to be aware of and receiving most and/or all the intended benefits of the CPI schemes. Highest claims (above 80 percent responses) were received in Lower Dir, Malakand Agency and Shangla; and CPI scheme-wise for link roads and bridges; and street pavements and drainage. 4.4.3 Problems The highest complaints of problems were reported in Upper Dir, followed by Shangla (19 and 11 percent, respectively). Overall, 10 percent respondents identified the problems in street pavements and drainage, and 7 percent in link roads and bridges (and 55 percent in ‘other’ schemes). A list of problems is given in Table 3.4 (see Annex 1-B). The following graph shows the gender-wise break down of respondents’ reporting problems, if any, with the CPI schemes – less than 10 percent reported any complaints: Type of CPI Drinking Water supply Type of CPI irrigation Total of CPI Link road/Bridges Type of CPI Street Pavement and drainage 21 12 0 81 7 No % No % 79 88 100 93 83 Yes % Yes % Yes % No % CO/VO Membership Yes CO/VO Membership No 8891 129 2 5 6 1 1 1 Have access to another source The household is from another caste/tribe/social class Low quality of output form the CPI High cost/userfee of the CPI The House is far away from the CPI location Other 7 9 7591 170 Graph 3.11: Gender-wise break down of respondents’ reports of problems with CPI schemes Sex Male Sex Female Are there any problems/issues with the scheme at the time of interview? Dont Know %
  • 25. 25 Intermsoftimetakenforcompletion,itwasfoundthat95%of the schemes were completed within the planned timeframe. In terms costs, 87 % of the sample schemes were completed within the estimated budgets. . A relatively modest 7% of the schemes were completed at over 10% of the estimated cost while 6% were completed under the estimated budgets. What is significant to note is that in case of cost overrun, local communities contributed to cover the balance. Assessment of the comparative beneficiary costs from earlier studies show that SRSP investments are generally cost effective. As a comparison, one study done in Nov 2002, “Cost and Impact Analysis of Water Supply and Environmental Sanitation in Pakistan” by Pakistan Institute of Development Economics Nov 2002, shows a figure of Rs 14228/HH for Government of KP and Rs 5521/ HH for NGOs forWater supply and Sanitation schemes. Adjusted for inflation this would be close to Rs 13000 per HH today. On the other hand, based on the data of the sample schemes the average cost of the EERP Sanitation CPIs this comes to Rs 3430/ HH about 3-4 times less in terms of cost per beneficiary. Although hard comparative data is not available for similar sized schemes which the GoKP or other organizations have implemented, there is anecdotal evidence that cost per beneficiary in the case of SRSP CPIs is relatively low. One reason is community contributions which on average is at least 20 % of the total cost of schemes 4.6 Sustainability The sustainability of EERP CPI and for that matter any infrastructure relate to its technical design, quality of construction and system of O&M. In case the scheme has been poorly designed or constructed, even a good O&M system will struggle to keep it going. On the other hand even if the structure has been designed and built to the best of standards, it will deteriorate over time if not maintained properly. 4.6.1 Design and layout. The CPI scheme designs invariably are based on the traditional technologies and designs being used in the area. Scheme design were available for more than half the schemes however as mentioned earlier that there was no design basis for 27 CPIs was either not available or inadequate and similarly design calculations were missing from 32 schemes. All the construction drawing were very basic and left the details to the discretion of the technician on the ground. About 15 percent of the schemes had changed the layout significantly from what had been planned. Although this is not a bad thing in itself, since for a community based project needs to have an inbuilt flexibility to match the conditions in the field. On the other hand this also reflects on the weak feasibility and lack of time given to technical planning and thinking. Workmanship in a large number of schemes was found to be excellent. This was despite the difficulty in carriage of material and water for curing. One example is the RCC Bridge in Kamay, in Swat district. The quality of workmanship at the sites was also observed in the field. It was found that, at 44% of the schemes workmanship were ranked good and at 38% it was found to be satisfactory. However, 18% of the schemes were ranked as being poor quality work. Road alignments, wear and tear, poor surface finishes and honey combing in concrete structures resulting from poor quality of workmanship was observed in villages Feza, Sanam & Sur Kamar in Shangla. In Gujjer Tangi, Swat road cutting was carried out without proper slope35 . To further get some depth in understanding the key indicators i.e. quality of the CPI schemes; and the Operations & Management (O&M) systems put in place (including transparency) were also explored in the HH survey and the FGD. 4.6.2 Quality When inquired, 91 percent of the respondents (92 and 89 percent, respectively) were satisfied with the current condition of the CPI schemes. Other than only 84 percent satisfaction in Swat (86 and 82 percent for males and females, respectively), all respondents elsewhere claimed above 88 percent satisfaction, with 100 percent in Lower Dir. In the districts of Buner, Chitral and Malakand Agency, while male respondents were 100 percent satisfied, female rate of satisfaction ranged between 86 to 97 percent. Approximately 9 and 14 percent of females were dissatisfied with drinking water supply; and link roads and bridges, respectively and above 93 percent satisfaction levels for the rest of the CPI schemes. As for males, only 75 percent were satisfied with the irrigation scheme; 92 percent with link roads and bridges, and above 93 percent with the rest of the CPI schemes. Interestingly, 87 percent of non-CO members showed satisfaction with the CPI schemes, as opposed to 94 percent of CO members. In the household survey, fewer females (68 percent) rated the material used in the CPI schemes as‘good’, as opposed to males (89 percent). Additionally, 20 percent of females also claimed to be unaware/unable to respond/make a judgment. InUpperDir,only55percentoftherespondentsperceivedthe material used to be as‘good’and 70 and 74 percent in Lower Dir and Shangla, respectively, while the rest of the districts received responses between 82 and 96 percent. Interestingly, a considerable percentage (82) in Swat perceived the material used as‘good’, despite overall satisfaction levels stated as low. Overall 79 percent of the respondents termed the material as ‘good’. In the case of link roads and bridges, 77 percent of the respondents perceived the material used as ‘good’; and 13 percent labeled it as‘average’or‘poor’; while 11 percent said they ‘didn’t know’. A detailed CPI scheme-wise breakdown is given in Annex: 1-C in Table 3.3, whereas the percentage of respondents who considered the quality good is presented in Graph 3.12. 53.3 80.4 85.7 76.6 89.7 Graph 3.12: Percentage of respondents who considered good quality of CPI schemes Drinking water supply Irrigation Link road/Bridges Street pavement and drainage Other 35 See Annex 1-B Table 2.5
  • 26. 26 Once again, 79 percent of the non-CO members cautiously rated the material used in CPI schemes as ‘good’, as opposed to 86 percent of the CO members with the same rating. Similarly,workmanshipoftheconstructionwasratedas‘good’ by 73 percent of the respondents; 59 percent by females and 85 percent by males. Only 36 percent of the respondents in Upper Dir labeled the workmanship as‘good’; and overall 68 percent respondents’ perceiving the workmanship of link roads and bridges as ‘good’; thus, both reflecting consistent results as above. Pre-testing of the scheme before hand over to the community is another important aspect to ensure the quality of the scheme. Overall 68 percent of the respondents (73 percent males; and 58 percent females) claimed that the CPI schemes were tested before being handed over according to their communities. Complete pre-testing was undertaken in Buner. 4.6.3 O&M systems The engineering reports suggest that for the schemes which were functional, O&M existed and functioned only partially at 22% of the sites, while at 30% there was no functional system for O&M36 . The 15 schemes which were not performing O&M works were lacking in this regard because: • No O&M committee existed in PI register Meragai, Gujjer Tangi Badro & Khan Palao in Swat and Khan Abad in Upper Dir. • No O&M systems or protocols were available for the implementation of maintenance works at a majority of the schemes. • In some villages, O&M committees existed but were not performing their roles & responsibilities in this regard. Bazkhel Sanam & Sur Kamar in Shangla are examples of this case. O & M problems were observed in Sher Khan Bazdara, Malakand, Mankass, Kabal, and Swat. In all these schemes there ‘seems’ to be no system to resolve the problems because of which the scheme is non functional. As a result, the whole community is suffering. In the case of Bazkhel, district Shangla, the scheme is pretty much non functional, since the drains a clogged and there does not seem to be any organized effort towards making it functional again. Existence and functionality of O&M systems are indicators Awareness of any O&M Committee  Males (YES) Graphs 3.13 & 3.14: Awareness of O&M Committees – by gender FEMALES MALES Burner Chitral Lower Dir Malakand Agency Swat Upper Dir 0 29 3 100 8 8 23 that can determine community levels of ownership and acceptability of the surrounding CPI schemes. Knowledge of any O&M system was generally low with 76 percent males; and only 20 percent females acknowledging them, with the least amount of awareness in Lower and Upper Dir (overall 40 and 42 percent, respectively). Approximately 39 percent of respondents claimed to have made contributions to O&M; 32 percent males and 50 percent females; mostly in Chitral (overall 91 percent contributions) and less than 45 percent elsewhere. The largest contribution was in irrigation schemes (55 percent); and ‘others’ (77 percent). While 52 percent of CO members interviewed claimed to have contributed to the O&M of the CPI schemes, even 49 percent of the non-CO members that were surveyed claimed to have done so as well. Majority of the respondents (overall 28 percent) claimed to pay for as and when required. The high spirit of community members to contribute and even take charge of maintenance was quite apparent during the FGD sessions. The breakdown of CPI scheme-wise contributions is as follows: Additionally, overall 23 percent, but interestingly 29 percent females and only 18 males claimed knowledge of the existence of an O&M committee. There were very stark contrasts in female and male respondents in Malakand Agency and Shangla, where awareness levels of female respondents appeared to be comparatively very high. Table 3.7: How do you pay money for maintenance? Monthly Annually When Needed Never Don’t know % % % % % Type of CPI Drinking water supply 6.4 2.9 26.9 24.0 39.8 Irrigation 44.4 14.8 40.7 Link road/Bridges 30.3 46.1 23.6 Street pavement and drainage 9.0 38.8 52.2 Other 39.3 42.9 14.3 3.6 3131 30 30 75 40 29 3 100 8 8 23 Burner Chitral Lower Dir Malakand Agency Swat Upper Dir 36 See Annex 1 Table 2.4
  • 27. 27 Graph 3.15: Performance rating of Project Committees (Good %) Existence of maintenance funds were acknowledged for drinking water and supply (33 percent); and link roads and bridges (32 percent); and the rest for ‘others’ (90 percent). Respondents stated they were aware that most of the maintenance funds were being run through SRSP and then CO bank accounts (Table: 3.8). Overall, 8 percent of respondents believed that the O&M fund covers its own maintenance costs, 44 percent believed that it covered none. Approximately 39 percent of the respondents reported any knowledge of an O&M Committee; 30 percent denied it; and 32 percent reported no knowledge whatsoever – 66 percent females did not know, as compared to 12 percent male respondents. A gender-wise analysis of how decisions are made for the fund shows that a very small percentage of females agreed that they – the beneficiaries and/or the CO members - had any say (5 percent); whereas SRSP and others were the main decision-makers (see Table 3.9 in Annex 1-B for more details). Approximately, 12 percent females and 25 percent males claimed to be members of the O&M Committee. Overall highest membership was in Shangla (41 percent). Overall satisfaction with the Project Committee is provided in Tables 3.10 and 3.11 in Annex 1-B, both district- and CPI scheme-wise, with Chitral once again topping the list with 100 percent satisfaction (rated between ‘OK’ and ‘good’). The highest level of satisfaction with the Project Committees was reported in Street pavement and drainage, where 56 percent rated it as ‘good’, and 44 percent selected, ‘OK’, ‘poor’, and/or ‘don’t know’. With regards to their views on transparency in the planning, development and O&M of the CPI schemes, the FGD analysis reflects that 53 percent male respondents claimed to be satisfied. Only 24 percent female respondents claimed the same, but an additional 65 percent of them also stated that they were unaware. Highest levels of efficiency with regards to perception of transparency were found in Chitral (83 Table 3.8: How are the funds being maintained? CO bank Account With Project Committee With the CO Manager With the SRSP Don’t Know Own help % % % % % % Dis- trict Buner 33.3 44.4 22.2 Chitral 68.8 6.3 18.8 6.3 Lower Dir 100.0 Malakand Agency 16.7 41.7 41.7 Shangla 27.3 18.2 36.4 9.1 9.1 Swat 6.5 15.2 39.1 17.4 21.7 Upper Dir 100.0 Table 3.13: How often did you meet during the CPI planning & construction stages? Total Fortnightly Monthly On need basis Never % % % % % % District Buner 42.3 11.5 38.5 7.7 100.0 Chitral 61.9 - 38.1 - 100.0 Lower Dir 9.1 33.3 42.4 15.2 100.0 Malakand Agency 69.4 13.9 16.7 - 100.0 Shangla 54.5 27.3 18.2 - 100.0 Swat 47.5 18.8 33.7 - 100.0 Upper Dir 13.3 36.7 33.3 16.7 100.0 24.6 20 21.1 56.1 Drinking Water Supply Irrigation Link road/Bridges Street pavement and drainage percent); and Buner (50 percent). The FGD respondents were most satisfied with transparency and availability of records in the CPI schemes of street pavement and drainage (64 percent). A detailed table (3.12) can be found in Annex 1-C. 4.6.4 Institutional Maturity A follow-up to‘Sustainability’this is the evaluation parameter addressed in this sub-section: Institutional Maturity of the CO, which assesses the capacity building of the communities to enable permanent running of the CPI schemes by themselves in the long-run. Such an assessment can be determined with the help of the following indicators: Community meetings during- and post-implementation of CPI schemes; trainings of community of members; and community’s ability to self- initiate additional schemes. 4.6.5 Meetings While 23 to 40 percent of all respondents claimed to have met for planning and construction discussions on need-basis for each CPI scheme; 67 percent of respondents claimed to meet fortnightly on irrigation schemes, followed by 44 and 41 percent on street pavements and drainage; and drinking water supply, respectively. Even non-CO members claimed to participate in such discussions, mostly fortnightly (38 percent); and on need-basis (49 percent). District-wise, respondents appeared the most active in Malakand Agency, where 69 percent claimed to meet on a fortnightly basis. In Swat and Lower Dir, the frequency was more monthly and/or on need-basis: In terms of frequency of meetings during the planning and construction phases of CPI schemes, the gender breakdown is as follows, with 47 percent males (females; 20 percent) reporting to have gathered on a fortnightly basis, while 40 percent females (males; 20 percent) claimed to meet only on needs-basis. Approximately 34 percent females claimed to have ‘never’ participated. Understandably, given the cultural constraints, once again, males appeared to be more active and females perhaps being unaware or unable to participate that constructively. Withregardstofrequencyofmeetingsafterthecompletionof the CPI schemes, the highest number of responses, scheme-, gender- and district-wise were unanimously reported as on ‘need-basis’. 4.6.6 Trainings In addition to membership, training can be another key indicator of how active a CO is and the level of awareness of its members. 46 percent of the respondents/members claimed to have received any training in the Committee. Interestingly,
  • 28. 28 even non-CO37 members claimed to have received training. The nature of training received, both gender- and CPI scheme-wise is illustrated below. Females received the highest amount of training in financial management, and males in leadership. However no respondent or any female member was given any O&M training as compared to male 15 % for male. Similarly, CPI scheme-wise, the greatest amount of training was received for leadership and financial management, according to 47 and 21 percent respondents, respectively, with consistent male and female breakdown below (and a CPI scheme-wise breakdown inTable 3.9: Annex 1-C): 4.6.7 Self-initiated community projects Assuming that the training and high participation of CO members led to their improved skills and institutional maturity, a greater percentage of them (27) were involved in self initiated additional projects, as opposed to 14 percent of non CO members involved in self help assignments and 86 percent in donor initiated projects. On inquiry, 9 percent females and 19 percent males reported that their communities had initiated other projects as well. Approximately 19 percent CO members claimed to have done so, as well as 10 percent non-CO members. The highest response was found in Malakand Agency (43 percent), followed by Buner and Swat (22 and 21 percent, respectively). Scheme-wise, street pavements and drainage was reported as the most popular (34 percent) additional project to have been initiated. Of these additional projects, 28 percent males proclaimed them as ‘self-help’, while 72 percent of the projects were labeled as ‘donor initiated’. Of these projects were in irrigation (100 percent); and street pavement and drainage (92 percent). Chitral and Malakand Agency witnessed 100 percent donor initiated additional projects, and Buner reportedly had the highest rate (83 percent) of self initiated projects undertaken. Support from SRSP With regards to support from SRSP on the functioning of CPI schemes, 88 percent respondents were satisfied (50 percent ‘good’ and 38 percent ‘Satisfactory’); 1 percent were dissatisfied; and 11 percent claimed to be unaware (largely female respondents). In terms of SRSP funds, in all the schemes it is mandatory that 15 to 20 percent of the budget comes from the community. Most of the budget is spent and monitored by the SRSP staff, but at times when the money is given to the community to spend, proper records are maintained. Most of the laborers, both skilled and unskilled, belong to the local community and were paid by SRSP for their services. While majority of the female respondents (approximately 80 percent) were largely unaware (80 percent) of SRSP spending, male respondents gave scattered views during the FGDs. Overall, 50 percent of the respondents in Chitral claimed that greater than 50 percent of the funds were utilized within the community; and 57 percent in Shangla; and less than 43 percent in all the other 5 districts. CPI scheme-wise, 50 percent of the respondents, the highest response, stated that greater than Table 3.14: Nature of Trainings Gender breakdown Total Disaster Prepa- redness Financial manage- ment Leader- ship O & M Any other % % % % % % % Sex Male 3.5 15.8 50.9 13.2 16.7 100.0 Female - 56.3 18.8 - 25.0 100.0 Of the female respondents, 58 percent were aware of SRSP and its work in their communities. Chitral witnessed 100 percent awareness; followed 82 percent of female respondentsclaimingtobeawareinBuner;andawareness levels between 46 to 68 percent in the rest of the districts. Level of awareness of female non-CO members was also considerably high at 57 percent of the non-members surveyed. A highly significant finding was that 64 percent of the females who were CO members were also a part of another organization, whereas the rate of participation of non-CO member females was 10 percent. This could positively indicate an increase in female mobilization in local communities due to their involvement in the SRSP- AusAid CPI schemes. Whether or not the female respondents had been actively involved as members, and/or in the planning and construction phases, almost all of them (97 percent) were fully aware of the existence of the CPI schemes in their communities. 50 percent of the funds were utilized in street pavement and drainage. Details are provided in Table 3.10 in Annex 1-C. Cohesion and harmony within the CO can be understood in terms of conflict between members with regard to the project. A minor percent (3: both males and females) reported any conflict concerning the CPI schemes, mainly in Buner and Lower Dir in the following schemes: drinking water supply; and street pavement and drainage. 19 20 23 23 15 Greater than 50% of SRSP money was utilized within the community (%) Drinking Water and supply Irrigation Link roads and bridges Street pavement and drainage Other Reasons for Conflict: • A minor dispute related to a piece of land, but resolved on time • A minor issue of land piece bur resolved by the community elders with in the week • During the construction one household was reluctant to provide a piece of land for the CPI, but the issue was resolved immediately • Land problem from the adjacent village arouse but was resolved on time by the local Revenue Department • Two tribes are not ready to share the CPI 37 Approximately 25 percent of non-CO members interviewed; possibly trainings under some other organizations.
  • 29. 29 Table 3.17: Do you think that the project can continue in the absence of SRSP? There is no O&M system and the com- munity does not have any capacity There is no O&M system but the com- munity does have some capacity There is no O&M system but the community has been trained to implement There is an O&M system and the community has been trained to implement There is no O&M system and the community is actively contribu- ting Don’t know % % % % % % Scheme type Drinking water supply 28.6 4.8 4.8 33.3 7.1 21.4 Irrigation 42.9 14.3 28.6 14.3 Link road/ Bridges 20.9 18.6 16.3 23.3 4.7 16.3 Street pavement and drainage 7.7 - 15.4 30.8 23.1 23.1 Other 33.3 16.7 16.7 33.3 Majority of the FGD responses endorsed the confidence of the male and female participants claiming that the CPI schemes could very well continue to run in the absence of support from SRSP. However, scheme-wise response reflected another story, where 43 and 27 percent FGD participants believed that irrigation and drinking water supply schemes could not run solely by the communities. 4.7 Impact 4.7.1 Overall impact analysis All respondents across all 7 districts reported a significant positive impact of the CPIs implemented under EERP by SRSP. In the case of villages where a Link Road or a Bridge had been constructed, respondents in Buner and Malakand Agency reported a positive change in both cases, as high as, 80 and 77 percent, respectively. Even in a district as conservative as Shangla respondents claimed that the impact led to between 13 to 16 percent positive changes in education for both girls’ and boys’ Similarly time to fetch water has been reduced by nearly 12 times due to the drinking water supply schemes and whereas earlier only 34 % had access to drinking water 24 hr, now nearly 93 % do. While the survey results reflect that 97 percent respondents acknowledged a stark positive change in female mobility, as a result of the CPI schemes; however, findings across the indicators reflect extreme lack of awareness and participation on the part of women. They need to be mobilized and encouraged to take greater initiative and be more involved in the process for a greater sense of ownership of the schemes, as well as, higher self-esteem and general knowledge. This is their key to greater empowerment. Approximately 68 percent of respondents across all 7 districts acknowledged a positive impact on women’s free time, enabling them to manage their daily activities more efficiently and productively. Some, however, did state that no change was witnessed in this regard: With the exception of 23 and 7 percent respondents, respectivelyinLowerandUpperDir,whoreportednobenefit/ change in marketing of agricultural surplus, 67 percent respondents across all 7 districts reported a positive impact in this regard as well. Same is the case with impact on cost of farm input (and access to business opportunities): with the exception of 50 (50), 23 (25) and 3 (6) percent respondents, respectively in Buner, Lower and Upper Dir, who reported no benefit/change, approximately 68 (89) percent respondents across all districts reported a positive impact, respectively. 4.7.2 Drinking Water Supply - CPI Scheme Impact This segment analyzes the immediate impact of the Drinking Water Supply CPI on reducing the time and effort taken to get to the water source. Overall, before DWSS CPI implementation, the average time taken to reach the water source and come back was 24 minutes for males, which, after the implementation of the schemes, was cut down to a fifth; to around 6 minutes. For females, an initial average time of 47 minutes, was cut drastically to a twelfth of the original amount of time taken; down to 4 minutes. Overall, it now takes an average of 5 minutes to get to and from the water source than the pre-CPI implementation estimate of 35 minutes, reflecting a major reduction in time, allowing community members to allocate their time more efficiently on other important daily tasks. The numbers now indicate that this responsibility is now being shared amongst the rest of the household members, most often the female child (21 percent), thus giving females higher opportunities utilize their time efficiently since the CPI scheme implementation has increased ease of accessibility. Percentage distribution of tasks undertaken by community members in a typical day shows that females now spend approximately 90 percent of their time on other household chores: District-wise, drastic savings in time allocation have been realized by beneficiaries due to DWS CPI. In Chitral and Upper Dir, it now takes almost no time to reach the most utilized water source. The time saved in Lower Dir, Swat and Shangla is almost 12 times as little. However, it takes the beneficiaries in Malakand longer to reach the DWS CPI source now than it did before installation. Table 3.18: Is there any change in women’s free time Large benefits Some benefits No benefit Don’t Know District Buner 40.0% 10.0% 50.0% Lower Dir 22.5% 32.5% 45.0% Malakand Agency 50.0% 29.2% 20.8% Shangla 14.3% 40.0% 42.9% 2.9% Swat 32.4% 35.1% 5.4% 27.0% Upper Dir 30.0% 66.7% 3.3% Average minutes after CPI by gender Average minutes before CPI by gender Mean Minutes Mean Minutes Male 6 Male 24 Female 4 Female 47 Table 3.19: Average time taken to reach water source and return (in minutes), before and after the implementation of DWS CPI schemes; by gender Table 3.20: Average time taken to go to water source and come back (in minu- tes), before and after the implementation of DWS CPI schemes; by District Average minutes by location District Mean Minutes District Mean Minutes Buner 9.1 Buner 32.3 Chitral N/A Chitral 10.0 Lower Dir 4.2 Lower Dir 48.7 Malakand 11.4 Malakand 2.7 Shangla 2.1 Shangla 35.1 Swat 3.8 Swat 40.5 Upper Dir N/A Upper Dir 69.0 Total 4.8 Total 34.9
  • 30. 30 Before the implementation of DWS CPI schemes, 60 percent of respondents from 6 out of the 7 districts reported that mainly adult women would fetch water for the HH’s use. The only exception was Malakand Agency, where water is most often fetched by a female child (over 60 percent cases). After the implementation of DWS CPI, the highest percentage is still of adult women who fetch water, but this has almost halved to approximately 34 percent; with the exception of Chitral and Malakand Agency. Satisfaction levels with the new DWS CPI schemes were 100 percent for males and 97 percent for females. In addition to coverage of lesser distances now, another reason for high satisfaction was that the frequency of water availability was also raised by almost 100 percent after the implementation of the DWS CPI schemes. The tables 3.21 and 3.33 reflect the stark positive differences: 4.7.3 Street pavements and drainage Analyzing the immediate impact of the Street Pavement and Drainage CPI scheme, in terms of water disposal and improvement in the local environment, will eventually help to evaluate the current health scenario of the beneficiaries. Majority of the respondents (96 percent) in the 3 districts: Malakand Agency, Shangla and Swat agreed that their streets had stagnant water with no effective way of its disposal. Post SPD CPI, the situation positively reversed with approximately 92 percent of the respondents indicating that the issue of stagnant water in the streets had either been completely or partially eliminated, with majority leaning towards complete elimination. Hence, the SPD CPI scheme has been a source of great convenience for the beneficiaries. It not only saves them transport time, but may also result in better health as the diseases contracted from stagnant water might be greatly reduced. Approximately 96 percent of the respondents from the 3 districts reported a rampant foul smell due to improper drainage systems. Post-SPD CPI, whereas in Shangla and Swat the situation was quite favorable towards the SPD CPI, with 75 and 93 percent respondents from both districts, respectively claiming a reduction in foul smell, there was a 50/50 split in Malakand Agency. This calls for revisiting the CPI scheme impact in Malakand. In regards to domestic waste water’s appropriate disposal, the responses generated have made for an interesting analysis. Pre-SPD CPI, the distinction by sample district claims that whereas in Shangla 100% of the respondents claimed that the waste water was not being disposed properly; the situation was relatively better in Swat with only half the respondents claiming that it was not. Post-SPD CPI, the scheme has performed well enough almost half the male respondents to agree that domestic waste water is now being disposed properly in contrast to 93 percent stating the contrary before the implementation of the scheme. In the same way, the percentage of female respondents increased from 67 to approx 89 percent. In Swat, now up to 75 percent respondents are satisfied with the output of the scheme, whereas majority of the respondents from Shangla (approximately 62 percent) are still claiming that waste water is not disposed properly. Furthermore, the resulting answer to the question whether there has been any significant decrease in Mosquitoes or flies the answer was no from 100 % of the female beneficiaries, whereas 7.5 % male said that it did. The answer to the query of improved children health before the CPI scheme of street pavement and drainage was a resounding 100 percent ‘No’ on all accounts. Similarly, to the Post implementation of the CPI scheme, above 50 percent of the respondents in both Malakand Agency and Shangla perceived an improvement and positive effect on the health of the children as a result. If this can assessed based on actual figures, this would reflect the impact the CPI schemes have had on increased life expectancy and economizing family budgets to save the amount of money spent on health treatment. With regards to households using any additional water treatment method for drinking water after the implementation of DWS CPI scheme; a 100 percent claim of no water treatment was reported. Though, Malakand and Swat still seemed to have its doubts about the purity of water provided and thus continued to use some form of water purification methodology. Once again, strengthening the claim that whereas, other districts were saving time and manual input, Malakand Agency was still struggling with the concept. This highlights the need for further training and follow-up with Cos in Malakand Agency. Similarly, while almost 100 percent respondents from Malakand Agency and Swat reported that the water from the CPI schemes had a clear appearance, sweet taste and was odorless; they reported cases of disease due to these water schemes (see Table 3.11 in Annex 1-C). This rendition of doubt (still using some form of water treatment) by Malakand and Swat would be better explained if the quality of water provided by CPI was unsatisfactory, but ironically both districts claim almost zero percent dissatisfaction. There is however, one point that may support their claim, that being the information that Malakand and Swat both have reported a higher percentage of diseases contracted through water (even after CPI) as compared to other districts. This might be cause for worry, hence, needs to be investigated. Table 3.21: The frequency of water available to HH before implementation of the DWS CPI scheme; by Gender Before CPI? Male Female Total Full time/24 hours 37.6 34.4 36.1 Daily intermittently 53.2 61.5 57.1 Alternate days 0.0 2.1 1.0 Twice a week 9.2 1.0 5.4 Others 0.0 1.0 0.5 Total 100.0 100.0 100.0 Table 3.22: The frequency of water available to HH after implementation of the DWS CPI scheme; by Gender After CPI? Male Female Total Full time/24 hours 97.1 90.1 93.9 Daily intermittently 2.9 7.7 5.1 Alternate days 0.0 1.1 0.5 Twice a week - - 0 Others 0.0 1.1 0.5 Total 100.0 100.0 100.0 Table 3.24: Respondents claims of cases of elimination stagnant water after CPI? Yes No To some extent % % % District Malakand 100.0 0 0 Shangla 50.0 25.0 25.0 Swat 97.7 2.3 0
  • 31. 31 Among the above listed facilities, a rather unique shift was witnessed in the mode of transport used to gain access the nearest general/grocery store. Comparing before- and after- CPI construction cases, the mode of transport ‘on foot’ surprisingly decreased (except in Buner); the usage of motorbikes and four wheel engine vehicles increased (other than in Lower Dir); and also witnessed was an increase in usage of public transport across all districts. This is quite alarming since the first assumption that can be made is that the distance due to the link roads has in fact, expanded 4.7.4 Link roads and bridges The impact of implementation of CPI schemes of link roads and bridges, in other words, communication infrastructure has remarkably decreased the average time taken for community residents to avail essential daily requirements including access to the nearest drinking water supply; distance to grocery shopping; distance to girls’ and boys’ schools; access to hospital; and distance to the nearest local Tehsil administration: Table 3.25: Before CPI Schemes in Communication Infrastructure – Average (mean) time taken to acquire the following facilities (minutes): District Drin- king water supply Grocery shopping / General store Boys’ school Girls’ school Hospital Local Tehsil administ- ration Buner 46.5 1 36.6 38.1 9.8 1 Lower Dir 17.8 33.4 13.2 16.3 13 1 Malakand 4.2 37.9 29.7 30.1 39.3 51.6 Shangla 15.6 145.4 115.3 123.9 197.4 133.3 Swat 110.6 151.6 126.3 121.6 162.8 54 Upper Dir 17 35.4 42.4 23.9 71.6 9.3 Total 39.7 84.1 67.2 61 97.3 49.2 Table 3.26: After CPI Schemes in Communication Infrastructure – Average (mean) time taken to acquire the following facilities (minutes): District Drin- king water supply Grocery shopping / General store Boys’ school Girls’ school Hospital Local Tehsil administ- ration Buner 17.5 1 15.4 17.1 5.3 1 Lower Dir 9.3 17.4 6.7 8.6 6.1 1 Malakand 1.6 12.1 14.1 14.8 24 28.8 Shangla 9.6 36.9 12.6 14.8 43.9 19.1 Swat 28.9 41.7 27.6 24.8 52.7 46.2 Upper Dir 5.4 14 17.8 11.8 32.7 5.4 Total 12.9 25.1 15.6 14.3 30.3 16.4 rather than the reverse, which would placed the community members at a greater convenience. The usage and hence, relevance of the link roads and bridges constructed under the CPI schemes is detailed inTable 3.12 in Annex 1-C. Of the 3 percent respondents in Malakand Agency who claimed to not use it all, 33 percent of them stated that the new infrastructure was of no use to them. The 8 percent (approximately) respondents in Swat who claimed the same all reported‘poor quality’as the reason.The rest of the higher majority of respondents, however, in both districts, and elsewhere were highly satisfied with the quality of the new communication infrastructure. In terms of overall traveling cost, it decreased by 25 percent for all respondents in Lower Dir and between 25 to 50 percent for respondents in Upper Dir. As for the 5 districts, travel cost decreased between 25 to 75 percent at varying levels. Additionally, there was an overall 75 percent decrease in the cost of freight transport due to the new CPI communication infrastructure across all districts except Buner, where no change was witnessed at all. The detailed breakdown of the impact is illustrated in Table 3.12 in Annex 1-C. 4.7.5 Irrigation The household survey results reflect that there was a remarkable increase in crop production of community members surveyed owing to the implementation of CPI irrigation schemes. While 100 percent respondents reported a 50 percent increase in wheat production; between 50 to 80 percent reported a 100 percent increase in rice and grain production. Production of maize also increased considerably. In vegetables, 100 percent increase in production of onions; tomatoes; lady fingers; and garlic was also reported by all respondents. Fruits such as apples; plums; and apricots comparatively did not witness such levels of increase in production. Production increments ranged between 50 to 70 percent. A 63 percent increase in rearing was also reported by respondents; with 10 out of 16 respondents surveyed claiming an increase, and 6 reporting no change. With regards to the overall impact on farm revenue, as indicated in the table below, 100 percent respondents reported minimum 50 percent increase. This is a substantial outcome of the irrigation CPI scheme, raising the economic empowerment of beneficiaries working on agricultural land. Table 3.29: Overall Farm Revenue Farm revenue 50% 70% 80% Total Overall Farm revenue 28.6 42.9 28.6 100
  • 32. 32 4.8 Conclusions and Recommendations In view of the early recovery context and the difficult terrain, SRSP’s outreach and successful conclusion of this challenging project is commendable. The schemes have been implemented in areas where the government had limited outreach and other non-governmental players had no presence. . Working in the target areas meant many hours of driving and trekking through often rugged and mountainous terrain. Despite these difficulties, the overall quality of work is of good standards. All project outputs were also achieved within the agreed timelines. Thanks to a motivated team, nearly 400 community organizations were formed, local priorities identified and over 200 CPIs implemented within a short span of 9 months. Overall the communities have reported a very positive impact of the CPI program. • Post implementation of the DWSS, the average time taken to reach the water source decreased significantly, allowing community members, particularly females, to allocate their time more efficiently to other important daily tasks. Satisfaction levels with the new DWS CPI schemes were 100 percent for males and 97 percent for females, also, implying lower risks of waterborne diseases. • In case of Sanitation and drainage CPIs, the majority of the respondents (92 percent) in the 3 districts where the scheme was implemented noted that the issue of stagnant water in the streets had either been completely or partially eliminated. Additionally, 75 and 93 percent respondents in Shangla and Swat, respectively claimed reduction in foul smell, while 50 percent respondents reported the same in Malakand Agency. • The new link roads and bridges has remarkably decreased the average time taken for community residents to avail essential daily requirements; travel to the nearest drinking water supply schemes; grocery stores; girls’ and boys’ schools; hospital; and the nearest local Tehsil administration. The respondents reported an overall 75 percent decrease in the cost of freight transport across all districts except Buner, where no change was reported. • The survey also shows considerable increase in crop production due to the implementation of irrigation schemes. Nearly all respondents reported a 50 percent increase in wheat production; while between 50 to 80 percent reported a 100 percent increase in rice and grain production. With regards to the overall impact on farm income, 100 percent respondents reported a minimum of 50 percent increase. • Combined capacity of the 3 MHPs in Chitral, Swat and Upper Dir has the designed capacity of 225 KW, which will benefit approximately 600 HH. It was reported that the MHP in Bhamborate, Chitral has been functioning at full capacity and is not only supplying electricity to the communal HH’s, but also to a local hotel, Maternity Home, Funeral Hall, a school and also mosque. • All 60 schemes in the evaluation sample were physically verified to be on the ground. Except for one scheme all the rest have been identified by the local community as fulfilling their priority need. Given the tight time lines and the difficult terrain, this is a remarkable achievement • Project documentation has been meticulously kept in the regional office, showing detailed record of community interaction and the field processes from the ‘first dialogue’ to the handing of checks in the 3rd dialogues and the subsequent installments. However the technical documentation covering the design basis, design calculations and the environmental assessment remains a weak area. . • The CPIs are predominantly functional, and have a positive impact on the communities; however some of these (about 10 %) are not delivering the required benefits due to poor quality and/or weak O&M systems. • A majority of females in the sample confirmed that the CPIs chosen represented their priority needs and directly benefiting them. However CPI implementation remained a predominantly male affair. Out of the 64 WCO which were formed, a total of 4 CPIs were for the women organization, which is disproportionally low. • Although CPIs such as DWSS or sanitation and drainage were being implemented there was little attempt to build the capacity of the organizations on related issues such as health and hygiene. • SRSP’s presence in the project areas was a significant factor in the rapid response and timely completion of the project activities. Interviews with senior SRSP managers suggest a continued interest in the region and a commitment to maintain the needed support for post project support through existing resources. • CPIs are highly visible, ensure immediate benefits to the community and also typically consume the largest chunk of development budgets in any community program. Accordingly these should receive a higher level of attention from the feasibility through design, implementation as well as the O&M. The survey shows a generally good performance on the “implementation fronts” however the design and O&M phases could benefit from further attention. Among other areas of focus the CPIs are generally small in scope, however a rapid “environmental screening and mitigation” protocol could help some categories of schemes. Overall the team recommends additional investments in staff skills for field surveys and design; use of design standards and guidelines and customized training modules for O&M practices. This will allow SRSP to further build on its current success and ensure that the CPIs continue to yield long term dividends without the need for any hand holding or follow up repairs in project areas that are generally remote and difficult to access. Specific recommendations: 1. Improve Engineering technical feasibility: 1.1. Establish policy to adhere to basic technical engineering standards. 1.2. Outsource technical assistance on engineering complex structures 1.3. Outsource essential engineering tests. 1.4. Acquire modern survey and test equipment 1.4.1. Total Station 1.4.2. GPS enabled cameras 1.4.3. Use Google earth where possible, else develop proper base map layout to ensure proper planning. 1.5. Establish Mobile lab for remote locations to ensure that the necessary tests such as soil analysis, CBR are carried out when necessary.
  • 33. 33 1.6. Staff training 2. Improve Environmental Feasibility 2.1. Revisit the Environmental review process 2.2. Hire an environmental engineer. 2.3. Staff training 3. Improve Quality of Scheme Construction 3.1. Establish quality standards 3.2. Training of project committee 3.3. Ensure a effective ratio of field engineers to scheme ratio for effective field supervisor 3.4. Training of‘skilled’and unskilled local labor. 4. Improve O & M system 4.1. Develop scheme specific O&M schedules 4.2. Develop basic troubleshooting guidelines defining what to do and when with clearly defined roles and responsibilities. 4.3. Establish intensive training of O&M committee and members and ensure refreshers. 4.4. Encourage an O&M fund and before hand-over of the scheme. 4.5. Monitor outcomes instead of outputs. 4.6. Use of cell phone technology to monitor O&M 5. Focus on Female organization or investments: 5.1. Establish link between investment in CPI and female activities. 5.1.1. Implement CPI’s only where WCO are formed or at least where female SOs is given access. 6. Plan for CPI investments holistically. 6.1. This is especially important in the case of DWSS and Sanitation CPIs where basic health and hygiene should be seen as a overarching framework 6.2. Irrigation related schemes should be followed up with water conservation and erosion control trainings.
  • 34. 34 ANNEXURES 1A Table 1.1 Environmental Screening Documentation not available/Inadequate S.No. District Village Scheme Type 1 Swat Meragai Irrigation channel Lining & RT wall 2 Swat Aladand Dherai Irrigation (Gabion structure) 3 Swat Pengen Street pavement & Drainage 4 Swat Mankass Qabel DWSS (HP) 5 Swat Faqira Link Road Rehabilitation 6 Swat Kamay RCC Bridge 7 Swat Samteer Link road (Earthen) 8 Swat Kaho Link Road Rehabilitation) 9 Swat Babo Maira Irrigation (Ramp Pump) 10 Swat Pirkhel khass RCC cause way 11 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian) Table 1.2 Design Basis Unavailable/Inadequate S.No. District Village Scheme Type 1 Swat Faqira Link Road Rehabilitation 2 Swat Kamay RCC Bridge 3 Swat Quanj Street pavement & Drainage 4 Swat Kokari Sar Link road (Earthen & PCC) 5 Swat Samteer Link road (Earthen) 6 Swat Kaho Link Road (Rehabilitation) 7 Swat Shagai Street pavement & Drainage 8 Swat Bar Jopeen Street pavement & Drainage 9 Swat Faqira Street pavement & Drainage 10 Swat Pirkhel khass RCC cause way 11 Swat Pengen Street pavement & Drainage 12 Malakand Palai khpa Link Road (PCC) 13 Shangla Sanam Link Road (PCC) 14 Shangla Sur Kumar Link Road (PCC) 15 Swat Gujer Tangi Badro Link Road 16 Shangla Sanila Street Pavement & Drainage 17 Lower Dir MataKhazana Link Road 18 Lower Dir Moranai Link Road 19 Lower Dir Munjay Link Road 20 Upper Dir Panakot Link Road 21 Lower Dir Shal Kandi Link Road 22 Swat Baghgay Maloch RCC Cause Way 23 Shangla Feza Link Road (PCC) 24 Upper Dir Malow Suspension Bridge(Pedestrian) 25 Upper Dir Shamorgar PCC Link Road 26 Swat Akhun Baba PCC Link Road 27 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian)
  • 35. 35 Table 1.3 Design Calculations Not available S.No. District Village Scheme Type 1 Swat Faqira Link Road Rehabilitation 2 Swat Kamay RCC Bridge 3 Swat Quanj Street pavement & Drainage 4 Swat Kokari Sar Link road (Earthen & PCC) 5 Swat Samteer Link road (Earthen) 6 Swat Sorykad DWSS (Gravity Flow) 7 Swat Kaho Link Road (Rehabilitation) 8 Swat Badardam DWSS (Gravity Flow) 9 Swat Shagai Street pavement & Drainage 10 Swat Bar Jopeen Street pavement & Drainage 11 Swat Faqira Street pavement & Drainage 12 Swat Pirkhel khass RCC cause way 13 Swat Pengen Street pavement & Drainage 14 Malakand Palai khpa Link Road (PCC) 15 Buner Banju Tangey DWSS (Gravity Flow) 16 Buner Ambela DWSS (Gravity Flow) 17 Shangla Sanam Link Road (PCC) 18 Shangla Sur Kumar Link Road (PCC) 19 Swat Gujer Tangi Badro, Islampur Link Road 20 Shangla Sanila Street Pavement & Drainage 21 Swat Dardyal,Qabel DWSS Graivty Flow 22 Lower Dir Inzaroo DWSS Graivty Flow 23 Lower Dir MataKhazana Link Road 24 Lower Dir Moranai Link Road 25 Lower Dir Munjay Link Road 26 Upper Dir Panakot Link Road 27 Lower Dir Shal Kandi Link Road 28 Swat Baghgay Maloch RCC Cause Way 29 Upper Dir Malow Suspension Bridge(Pedestrian) 30 Upper Dir Shamorgar PCC Link Road 31 Upper Dir Qulandai Payeen Suspension Bridge(Pedestrian) 32 Chitral Khoran dok DWSS Gravity flow Inadequate S.No. District Village Scheme Type Remarks 1 Swat Yakh Tangey DWSS (Gravity Flow) Missing for water storage reservoir 2 Swat Akhun Baba PCC Link Road Missing for axle loads etc. 3 Swat Shagai Ghwajalgai DWSS (Gravity Flow) Missing for water storage reservoir 4 Malakand Khan Palao DWSS (Hand pump) Missing for HP apron and foundation 5 Swat Amin Abad Link Road Missing for axle loads etc. 6 Malakand Sherkhan,Bazdara DWSS (Hand pump) Missing for HP apron and foundation 7 Shangla Tangir Suspension Bridge(Pedestrian) Load bearing not mentioned 8 Shangla Abbasin Colony Gravity Flow Missing for water storage reservoir 9 Shangla Feza Link Road (PCC) Missing for axle loads etc. 10 Lower Dir Asilo DWSS Gravity Flow Missing for water storage reservoir 11 Lower Dir Danwa DWSS Gravity Flow Missing for water storage reservoir 12 Upper Dir Doonpayeen DWSS Gravity Flow Missing for water storage reservoir 13 Swat Mankass Qabel DWSS (HP) Missing for HP apron and foundation 14 Swat Yakh Tangey DWSS (Gravity Flow) Missing for water storage reservoir
  • 36. 36 Table 1.4 Construction Drawings Unavailable S.No. District Village Scheme Type 1 Malakand Khar DWSS (Hand pump) 2 Swat Gujer Tangi Link Road Inadequate Sr. District Village Scheme type Remarks 1 Swat Jabba DWSS (Hand pump Plan shows 3 hand pumps, section shows a Dug well with a storage reservoir Table 1.5 PI Register Not available Sr District Village Scheme type Remarks 1 Swat Jabba DWSS (Hand pump) 2 Swat Meragai Irrigation channel Lining & RT wall 3 Swat Khar DWSS (Hand pump) 4 Swat Gujer Tangi Badro, Islampur Link Road 5 Lower Dir MataKhazana Link Road 6 Lower Dir Moranai Link Road Table 1.6 Project Completion Report Not available Sr District Village Scheme type Remarks 1 Swat Shao MHP 75Kw Project not handed over as yet 2 Buner Bazarkot Foot Bridge (Suspension) Not found in PI file 3 Buner Riaz Abad, Ambella DWSS (Hand Pumps) Not found in PI file 4 Chitral Khoran dok DWSS (Gravity flow) CPI Failed Inadequate Sr District Village Scheme type Remarks 1 Buner Banju Tangey DWSS (Gravity Flow) Date and signatures missing 2 Buner Ambela DWSS (Gravity Flow) Date and signatures missing 3 Shangla Abbasin Colony Gravity Flow Signatures are missing 4 Swat Lawar Deolai, Qabil Irrigation Channel Signatures are missing 5 Chitral Kuru Bala Dug Well CPI Failed; not completed Table 1.7 Completion Certificate Not available Sr District Village Scheme type Remarks 1 Swat Shao MHP 75Kw Project not handed over as yet 2 Buner Bazarkot Foot Bridge (Suspension) Missing in PI file 3 Buner Riaz Ambella DWSS (Hand Pumps) Missing in PI file Inadequate Sr District Village Scheme type Remarks 1 Swat Banju Tangey DWSS (Gravity Flow) Dates and SRSP Officials’signatures missing 2 Buner Ambela DWSS (Gravity Flow) Dates and SRSP Officials’signatures missing 3 Chitral Kuru Bala Dug Well Completion certificate not made as CPI failed
  • 37. 37 Table 1.8 Handing over Certificate Not available Sr District Village Scheme type Remarks 1 Swat Shao MHP 75Kw Not Handed over 2 Buner Bazarkot Foot Bridge (Suspension) Not available in PI file 3 Chitral Bamburate MHP Not Handed Over 4 Chitral Kuru Bala Dug Well Scheme failed so not handed over. 5 Upper Dir Khan abad MHPP Not available in PI file
  • 38. 38 ANNEXURES 1B Table 2.1 Scheme Layouts Schemes with Layout differences Sr District Village Scheme Remarks 1 Swat Yakh Tangey DWSS (Gravity Flow) • 4 transmission lines detailed in plans, but 7 transmission lines observed on site • Plan described previously existing water tank in between intake chamber and water storage tank; actually, there was a direct line from the intake chamber to the main water storage tank. • Planned main supply line was of 2‘’dia and 7290 rft length. On ground a 1.25’’dia and 9000 rft length was observed 2 Buner Banju Tangey DWSS (Gravity Flow) • In the drawings, there was only 01 storage tank with 01 supply line; 02 water storage tanks and 02 supply lines observed on site 3 Shangla Abbasin Colony DWSS (Gravity Flow) • Drawings showed two supply lines from the storage tank, how- ever it was observed that only one line was in connection with the storage tank while the second line was directly connected to the main supply line. 4 Swat Gujer Tangi Badro, Islampur Link Road • In designs, 07 RCC culverts were shown; however no culverts were constructed on site. 5 Lower Dir Danwa DWSS (Gravity Flow) • In designs, there was 1 source planned. However, 2 sources were observed. 6 Swat Baghgay Maloch RCC Cause Way • In drawing, 06 pipe culverts were shown at one location. Howe- ver 2 culverts were constructed in different location with 2 pipes each. 7 Chitral Kuru Bala Dug Well • Site changed by community. 8 Lower Dir Asilo DWSS • The distribution network on site does not match the plans • There is no Storage tank in the plan • Planned number of lines from the distribution tanks are 3 vs 9 on site. 9 Swat Sorykad DWSS • 4 distribution lines coming out of the tank vs planned 2
  • 39. 39 Table 2.2 Design Validation Schemes‘not built as per approved design’ Sr District Village Scheme Remarks 1 Shangla Sanam Link Road (PCC) 850 rft of drains planned were not constructed at site. Length of PCC pavement was changed compared to design 2 Swat Gujer Tangi Link Road None of the culverts were constructed 3 Swat Mankass Qabel DWSS (HP) 120ft drilling depth was mentioned, however no drilling was underta- ken, and a Hand Pump was installed over an existing dug well It was also noted that a 4“ dia PVC pipe of 124 rft had not been installed at site 4 Chitral Kuru Bala Dug Well CPI failed/not completed. Resistivity test not conducted 5 Buner Banju Tangey DWSS (Gravity Flow) Length Main Line 1 Main Line 1 Supply Line 1 Supply Line 2 Supply Line 3 Supply Line 4 Supply Line 5 Design 3608’ NA 2840’ 1360’ 2240’ 2410’ NA Actual 1700’ 600’ 1500’ 2000’ 1750’ 1800’ 1600’ 6 Shangla Abbasin Colony DWSS (Gravity Flow) Length Water Tank Main S. Line Supply line 1 Supply line 2 Design 14’ 15000’ 1200’ 1400’ Actual 13.5’ 19700’ 550’ 450’ 7 Swat Amin abad Link Road Length PCC Road RT wall Cutting Design 800’ 55’with 5’h 450’ Actual 150’ 75’with 3.5’h 700’ 8 Swat Samteer Link road (Earthen) Length PCC RT wall Design 250’ 160’ Actual Not Done 750’ 9 Shangla Sanam Link Road (PCC) Length PCC Pavement Side Drain Design 850’ 850’ Actual 1150’ NA 10 Swat Meragai Irrigation channel Lining & RT wall Length Channel RT wall 01 RT wall 02 Design 750’ 70’ 70’ Actual 880’ 30’ 25’ 11 Swat Quanj Street pavement & Drainage Length PCC Pavement Side Drains Stairs Design 1482’ 1482’ 150’ Actual 1190’ 464’ 50’ 12 Shangla Sanila Street Pavement & Drainage Length PCC Stair (L) PCC Street (L) Side Drain (L) Design 799’ 1034’ 1833’ Actual 975’ 827’ 780’
  • 40. 40 Table 2.3 Schemes Design & estimate II Schemes with‘minor’variations Sr District Village Scheme Remarks 1 Swat Faqira Link Road Rehabilitation • Length of PCC link road planned was 1200 ft. However, at site it was 1350ft. 80 ft of planned RW were not constructed. • Design quantity of cutting was 600ft in BOQ; however at site 700ft of cutting was noted 2 Swat Jabba DWSS (Hand pump) Drilling Depth HP # 01 HP # 02 HP # 03 Design 150’ 150’ 150’ Actual 160’ 85’ 110’ 3 Swat Khan Palao DWSS (Hand pump) Minor difference was observed in drilling depth 4 Swat Pengen Street pavement & Drainage Minor difference was observed in street pavement and drainage lengths 5 Swat Palai khpa Link Road (PCC) Length Pavement Side drain Pavement width Design 1400’ 1400’ 12’ Actual 1250’ 1270’ 14’ 6 Swat Sherkhan, Bazdara DWSS (Hand pump) Drilling Depth HP # 02 HP # 03 HP # 04 HP # 05 Design 150’ 150’ 150’ 150’ Actual 135’ 135’ 70’ 105’ 7 Buner Ambela DWSS (Gravity Flow) Minor difference was observed in storage tank dimension and supply line length 8 Buner Bazarkot Foot Bridge (Suspension) Minor difference was observed in railing length 9 Shangla Feza Link Road (PCC) Pavement (L) Pavement (W) Side Drain (L) Design 900’ 08’ 900’ Actual 850’ 09’ 600’ 10 Shangla Sur Kumar Link Road (PCC) Pavement (L) Pavement (W) Side Drain (L) Design 850’ 08’ 850’ Actual 900’ 09’ 500’ 11 Buner Riaz Abad DWSS (Hand Pumps) Drilling Depth HP # 01 HP # 02 HP # 03 Design 130’ 130’ 130’ Actual 155’ 125’ 139’ 12 Shangla Sanila Street Pavement & Drainage PCC Stair (L) Pavement (W) Side Drain (L) Design 799’ 04’ 1833’ Actual 975’ 05’ 780’ 13 Lower Dir Asilo DWSS Gravity Flow Minor difference was observed in storage tank dimensions and supply line length 14 Lower Dir Danwa DWSS Gravity Flow Minor difference was observed in storage tank dimensions and supply line length 15 Upper Dir Doonpa- yeen DWSS Gravity Flow Minor difference was observed in Intake chamber and storage tank dimensions and supply line length 16 Lower Dir Mata Kha- zana Link Road Link Road (L) Link Road (W) Side Drain (L) Design 988’ 10‘ 700‘ Actual 1195’ 08‘ 280‘ 17 Lower Dir Munjay Link Road Link Road (L) Link Road (W) Side Drain (L) Design 700’ 10‘ 500‘ Actual 740’ 10‘ 740‘ 18 Upper Dir Panakot Link Road Link Road (L) Link Road (W) RT Wall (L) Design 1350’ 10‘ 275‘ Actual 1220’ 10‘ 252‘ 19 Lower Dir Shal Kandi Link Road Link Road (L) Link Road (W) Design 1100’ 10‘ Actual 1126’ 10‘ 20 Upper Dir Shamorgar PCC Link Road Link Road (L) Link Road (W) Design 1100’ 10‘ Actual 1300’ 10‘ 21 Chitral Khoran dok DWSS gravity Flow Minor difference was observed in storage tank dimensions and supply line length
  • 41. 41 Table 2.4 Schemes O&M Schemes with poor O&M Sr District Village Scheme Remarks 1 Swat Faqira Link Road Rehabilitation There was no O&M committee 2 Swat Meragai Irrigation channel Lining & RT wall There was no O&M committee 3 Swat Samteer Link road (Earthen) No O&M system in place 4 Malakand Pengen Street pavement & Drainage There was no O&M committee 5 Malakand Sherkhan, Bazdara DWSS (Hand pump) O&M was deemed not functional since 02 HPs had been out of order for the last one month 6 Shangla Bazkhel Drainage No O&M system in place 7 Shangla Feza Link Road (PCC) There was no O&M committee 8 Shangla Sanam Link Road (PCC) There was no O&M committee 9 Shangla Sur Kumar Link Road (PCC) There was no O&M committee 10 Swat Gujer Tangi Badro Link Road There was no O&M committee 11 Swat Sanila Street Pavement & Drainage There was no O&M committee 12 Swat Mankass Qabel DWSS (HP) There was no O&M committee 13 Swat Dardyal, Qabel DWSS Gravity Flow The scheme was not functional for the last two months because the water source had frozen. Community members said that the source had been damaged and that they plan to reconstruct a cut off wall once the snow melts fully. The team was further informed that the source is currently inaccessible 14 Upper Dir Shamorgar PCC Link Road No O&M system in place Table 2.5 Scheme Workmanship (Also See Annex 8 for pictures) Schemes had Poor Workmanship Sr District Village Scheme Remarks 1 Shangla Feza Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the surfaces observed as well as honeycombing in concrete structure 2 Shangla Sanam Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the surfaces observed as well as honeycombing in concrete structure 3 Shangla Sur Kumar Link Road (PCC) Workmanship observed was very poor. There was an irregular finish to the surfaces observed as well as honeycombing in concrete structure 4 Swat Gujer Tangi Badro Link Road Cutting had been carried as preliminary work for the road, however, no proper side slope was observed 5 Swat Samteer Link road (Earthen) Workmanship observed was very poor. There was an irregular finish to the surfaces observed as well as honeycombing in concrete structure 6 Lower Dir Mata Khazana Link Road Workmanship observed was very poor. There was an irregular finish to the surfaces observed as well as honeycombing in concrete structure 7 Swat Quanj Street pavement & Drainage Workmanship observed was very poor 8 Swat Sanila Street Pavement & Drainage Workmanship and quality of work observed was very poor 9 Upper Dir Khan abad MHPP Workmanship and quality of work in power house observed was very poor
  • 42. 42 Table 2.6 Schemes Functionality Schemes not verified physically as they were not operational at the time of visit Sr District Village Scheme Remarks 1 Swat Meragai Irrigation channel Lining & RT wall • Irrigation was not needed during the time of the visit • According to some community members the scheme was not functional due to flood damages • However, the community planned to repair 2 Upper Dir Khan abad MHP • The scheme had been recently repaired and was not ready to be started. 3 Swat Shao MHP 75Kw • The day the of the site visit, the evaluation team was informed that a bearing of the turbine needed repair and had been taken to Mardan for repair. 4 Swat Dardyal, Qabel DWSS (Gravity Flow) • The scheme was not functional • Community members stated that the source had been damaged and the scheme had not functioned for the last two months, how- ever they plan to repair it once the ice melts. • The team could not visit the source due to the glacier, which made it inaccessible. Schemes which are partially functional 1 Shangla Bazkhel Drainage • The drains were blocked and water was overflowing from sides of the drains 2 Swat Sherkhan,Bazdara DWSS (Hand pump) • Three hand pumps are functional and in satisfactory conditions. • While two hand pump are not functional and need maintenance. 3 Swat Gujer Tangi Bad- ro, Islampur Link Road • Severe problems of erosion and cutting • The designed pipe culverts have not been constructed. • However, road is being used occasionally as no alternative is available Scheme Failed 1 Chitral Kuru Bala Dug Well • CPI failed as Water table was too low. Table 2.7 Schemes completed over estimated cost Schemes completed over estimated cost Sr District Village Scheme Remarks 1 Malakand Khan Palao DWSS (Hand pump) Community informed the team that they had paid an extra 80,000 PKR for the completion of scheme. 2 Malakand Sherkhan, Baz- dara DWSS (Hand pump) The community members said that an additional Rs. 20,000 had been required for completion of the scheme. 3 Upper Dir Doonpayeen DWSS (Gravity Flow) The community members said that an additional Rs. 69,000 had been required for completion of the scheme. 4 Upper Dir Malow Suspension Bridge (Pedest- rian) The community members said that an additional Rs. 60,000 had been required for completion of the scheme. Table 2.8 Schemes completed with Savings Schemes completed with Savings Sr District Village Scheme Remarks 1 Swat Mankass Qabel DWSS (HP) The scheme was completed within budget. Savings made were further utilized for the construction of a PCC street pavement 2 Lower Dir Inzaroo DWSS Gravity Flow The scheme was completed with savings of approximately RS. 35,000 which were deposited in the CO’s bank account. 3 Swat Baghgay Maloch RCC Cause Way The scheme was completed with savings which were further utilized for the construction of a 1,000 ft. link road
  • 43. 43 ANNEXURES 1C Table 3. 1 Current condition of the CPI scheme - by Scheme Type The sche- me is not working currently The scheme is working but all the participants complained The scheme is working but most of the participants complained The scheme is working but some of the participants complained Scheme is working & no one comp- lained about the condition Don’t know % % % % % % Drinking water supply 9.5 4.8 2.4 9.5 73.8 - Irrigation 14.3 - 85.7 - Link road/Bridges 4.7 9.3 18.6 65.1 2.3 Street pavement & drainage 7.1 7.1 78.6 7.1 Other 16.7 16.7 - 66.7 - Total 5.4 4.5 5.4 11.6 71.4 1.8 Table 3.2 Was the project completed cost effectively? - by Gender All the partici- pants agreed that the project was not cost effective Some (around 25%) the participants ag- reed that the project was cost effective Half (around 50%) of the participants ag- reed that the project was cost effective Most (around 75%) of the participants ag- reed that the project was cost effective All the participants agreed that the project was cost effective Don’t know % % % % % % Male 3.4 5.2 10.3 24.1 55.2 1.7 Female 3.8 7.7 5.8 82.7 Total 1.8 4.5 9.1 12.7 31.8 40.0 Table 3.3 How would you rate the material used in the CPI? - by Scheme Type Good Average Poor Don’t know % % % % Drinking water supply 80.4 5.9 2.0 11.8 Irrigation 85.7 8.6 2.9 2.9 Link road/Bridges 76.6 10.5 2.4 10.5 Street pavement and drainage 89.7 9.0 1.3 Other 53.3 33.3 13.3 Total 79.1 9.7 1.8 9.4 Table 3.4 How decisions about the utilization of the O&M fund are made - by Gender The O&M Committee The CO Leaders The SRSP staff All CO Members All Beneficiaries Contractor Other % % % % % % % Male 6.7 8.9 15.6 44.4 17.8 2.2 4.4 Female 3.2 28.6 63.5 1.6 3.2 Total 4.6 20.4 43.5 19.4 9.3 .9 1.9
  • 44. 44 Table 3.5 Performance rating of Project Committees – by District Good OK Poor Don’t Know % % % % Buner 36.0 32.0 - 32.0 Chitral 50.0 50.0 - - Lower Dir 15.1 22.6 - 62.3 Malakand Agency 35.6 24.4 - 40.0 Shangla 10.4 33.3 - 56.3 Swat 37.9 29.1 7.8 25.2 Upper Dir 25.0 18.2 2.3 54.5 Total 29.0 28.1 2.7 40.2 Table 3.6 Performance rating of Project Committees - by CPI Scheme Good OK Poor Don’t Know % % % % Drinking water supply 24.6 32.2 2.5 40.7 Irrigation 20.0 40.0 30.0 10.0 Link road/Bridges 22.1 27.9 .6 49.4 Street pavement and drainage 56.1 12.2 4.9 26.8 Other 66.7 33.3 Total 29.0 28.1 2.7 40.2 Table 3.7 Perception towards transparency in the planning/development/O&M of the scheme - by CPI Scheme All the partici- pants agreed that there was no record keeping Records were kept but there was no transpa- rency Records were kept but most of the participants still complained Records were kept but some of the participants still complained Records were kept/ no one complai- ned about lack of transparency Don’t know % % % % % % Drinking water supply 2.3 4.7 7.0 20.9 37.2 27.9 Irrigation 14.3 28.6 57.1 Link road/Bridges 7.0 4.7 7.0 11.6 32.6 37.2 Street pavement and drainage 7.1 7.1 64.3 21.4 Other 20.0 60.0 20.0 Total 3.6 3.6 6.3 15.2 39.3 32.1 Table 3.8 Nature of Trainings - by Scheme Type Disaster Preparedness Financial management Leadership O & M Any other Total (%) % % % % % Drinking water supply 2.3 27.3 27.3 11.4 31.8 100.0 Irrigation 100.0 100.0 Link road/Bridges 3.4 15.5 60.3 15.5 5.2 100.0 Street pavement and drainage 4.5 27.3 63.6 4.5 100.0 Total 3.1 20.8 46.9 11.5 17.7 100.0
  • 45. 45 Table 3.9 How did the SRSP contribution in direct cash help the local economy? - by Scheme Type Greater than ¾ of the SRSP money was utilized within the community Between ½ and ¾ of SRSP money was utilized within the com- munity Between ¼ to ½ of the SRSP money was utilized within the community Less than ¼ of SRSP money was utilized within the community None of the SRSP money was utilized within the community Don’t know % % % % % % Drinking water supply 20.7 10.3 13.8 6.9 3.4 44.8 Irrigation 40.0 60.0 Link road/Bridges 12.1 30.3 3.0 12.1 6.1 36.4 Street pavement and drainage 33.3 16.7 50.0 Other 50.0 16.7 33.3 Total 21.5 17.7 6.3 8.9 41.8 Table 3.10 Diseases contracted from DWS CPI scheme’s water - by District Had the diseases Buner Chitral Lower Dir Malakand Shangla Swat Upper Dir Total Yes 15.4 10.0 0.0 23.5 10.0 25.0 0.0 15.5 No 84.6 90.0 81.3 35.3 90.0 35.0 80.0 60.3 Don’t know 0.0 0.0 18.8 41.2 0.0 40.0 20.0 24.1 Total 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 Table 3.11: How often do/did you use the road/bridge? - by District Not at all Occasionally Often All the time % % % % Buner 50.0 0 0 50.0 Lower Dir 55.0 45.0 Malakand Agency 3.3 10.0 6.7 80.0 Shangla 0 17.5 32.5 50.0 Swat 7.8 11.8 29.4 51.0 Upper Dir 15.2 30.3 54.5 Total 7.4 7.8 30.4 54.4 Table 3.12: Decrease in cost of freight transport (% age of respondents) District <=25% 26%-50% 51%-75% >=76% Total Lower Dir 100 0 0 0 100 Malakand Agency 5 90 0 5 100 Shangla 16.67 56.67 23.33 3.33 100 Swat 4.88 95.12 0 0 100 Upper Dir 13.33 86.67 0 0 100 Total 17.95 74.36 5.98 1.71 100
  • 46. 46 TypeofSchemeSub-typeofSchemeNoTotalCost Community Contribution NoofBenefici- aryHHs Community Contribution Costper HH Contribution perHH Typeofscheme asa%ageoftotal schemes Costofschemeasa %ageoftotalcost BeneficiaryHHasa %oftotalbenefici- aryHHs BRIDGERCCSMALLBRIDGE613,102,7002,620,6001,57420%8,32416652.85.64.2 SUSPENSIONBRIDGE35,309,1001,061,8001,00520%5,28310571.42.32.7 SUSPENSIONBRIDGEPEDESTRIAN910,206,9002,041,4001,56120%6,53913084.24.44.2 SubTotal1828,618,7005,723,8004,140120,1464,02981211 Average81,589,928317,9892306,9131,383 DWSSBOREWELL1423,00084,60041020%1,0322060.50.21.1 DUGWELL1298,32049,7203017%9,94416570.50.10.1 GRAVITYFLOW6349,680,2549,928,8905,09120%9,758195029.621.213.6 HANDPUMP209,510,1201,954,9502,17021%4,3839019.44.15.8 SubTotal8559,911,69412,018,1607,701125,1174,715402621 Average40704,843141,390917,7801,561 MHPMICROHYDROPOWERUNITS846,442,90012,408,8332,36227%201,92652543.819.86.3 45,805,3631,551,10429519,6635,254 IRRIGATIONGABIONSTRUCTURE1626,100146,2004,00023%157370.50.310.7 PIPEIRRIGATION21,435,000247,0007217%19,93134310.90.60.2 WATERCOURSELINING88,361,6001,672,2201,43020%5,84711693.83.63.8 WATERDRIVENPUMPSYSTEM1556,00026,000505%11,1205200.50.20.1 SubTotal1210,978,7002,091,4205,552137,0545,1566515 Average6914,892174,2854631,977377 COMMUNICATIONCAUSEWAY1722,300144,5006520%11,11222230.50.30.2 EARTHEN&PCC1012,218,8002,443,8002,15020%5,68311374.75.25.7 EARTHEN57,035,0001,408,3001,42020%4,9549922.33.03.8 PCC1916,142,6003,228,6203,15320%5,12010248.96.98.4 LINKROADEXTENSION11,079,700215,94015220%7,10314210.50.50.4 LINKROADPCC&R/W21,345,000269,00058020%2,3194640.90.61.5 LINKROADREHABILITATION2121,654,3004,331,0705,73020%3,7797569.99.215.3 RCCCAUSEWAY32,495,700499,00052620%4,7459491.41.11.4 BRIDALPATH(STONEPITCHING)1500,700100,10020020%2,5045010.50.20.5 RCCPIPECAUSEWAY1611,500122,30034520%1,7723540.50.30.9 subtotal6463,805,60012,762,63014,321249,0919,819302738 Average30996,963199,4162244,455891 SANITATIONDRAINAGE1294,50058,9009520%3,1006200.50.10.3 STREETPAVEMENT43,340,800668,04020020%16,70433401.91.40.5 STREETPAVEMENTANDDRAINAGE1812,855,4002,565,8202,59020%4,9639918.55.56.9 SubTotal2316,490,7003,292,7602,885124,7674,9511178 Average11916,150182,9311605,7161,141 SOILCONSERVATIONDRYSTONEPROTECTIONWALL11,550,700310,2009620%16,15332310.50.70.3 PROTECTIONWALL15,457,000909,50020017%27,28545480.52.30.5 SubTotal27,007,7001,219,700296043,4387,779131 Average13,503,850609,85014823,6754,121 UPGRADATIONUPGRADATIONOFSPORTSFACILITY1971,00002500%3,88400.50.40.7 TOTALS213234,226,99449,517,30337,5075405,42441,703 Annex 2: Total EERP CPI
  • 47. 47 Annex 3: Sampled CPI S.No District Village Type of Scheme Scheme sub- type Date Beneficiaries HH Total Cost Cost per Benefi- ciary Initiation Completion Planned Actual Estimated 1 Buner Riaz Abad, Ambella DWSS Hand Pumps 7/9/11 7/12/11 125 139 400,000 2878 2 Buner Banju Tangey DWSS Gravity Flow 12/9/11 12/12/11 113 130 652,400 5018 3 Buner Ambela DWSS Gravity Flow 9/23/11 23/12/2011 65 65 648,900 9983 4 Buner Bazarkot Bridge Foot Bridge (Suspension) 7/9/11 7/12/11 128 200 917,000 4585 5 Chitral Kuru Bala DWSS Dug Well 12/12/11 12/3/12 60 60 310,800 5180 6 Chitral Khoran dok DWSS Gravity Flow 8/9/11 8/12/11 64 64 1,108,700 17323 7 Chitral Bamburate MHP MHPP 9/24/11 24/02/2012 457 500 6,736,700 13473 8 Lower Dir Munjay Road Infra- structure Link Road 11/11/11 11/2/12 100 150 610,700 4071 9 Lower Dir Inzaroo DWSS Gravity Flow 5/9/11 05/03/2013 90 100 457,500 4575 10 Lower Dir Moranai Road Infra- structure Link Road 12/12/11 12/3/12 69 120 645,200 5377 11 Lower Dir Danwa DWSS Gravity Flow missing missing 120 120 742,900 6191 12 Lower Dir Asilo DWSS Gravity Flow 1/11/11 01/02/2012 35 120 766,700 6389 13 Lower Dir MataKhazana Road Infra- structure Link Road 4/11/11 4/2/12 200 300 764,000 2547 14 Lower Dir Shal Kandi Road Infra- structure Link Road 10/30/11 1/30/12 200 300 769,400 2565 15 Malakand Khar DWSS Hand Pump 8/22/11 11/22/11 80 200 657,867 3289 16 Malakand Sherkhan,Bazdara DWSS Hand Pump 9/19/11 12/19/11 115 200 707,131 3536 17 Malakand Aladand Dherai Irrigation Gabion Structure 10/20/11 20/02/2012 455 455 626,100 1376 18 Malakand Khan Palao DWSS Hand Pump 8/15/11 11/15/11 45 120 634,865 5291 19 Malakand Pirkhel khass Road Infra- structure RCC cauce way 11/21/11 2/21/12 70 150 915,600 6104 20 Malakand Palai khpa Road Infra- structure Link Road (PCC) 11/29/11 29-01-2012 200 350 1,083,500 3096 34 Malakand Amin abad Road Infra- structure Link Road 10/21/11 1/21/11 45 120 524,800 4373 21 Shangla Abbasin Colony Sanitation Drainage 9/9/11 9/12/11 25 25 294,500 11780 22 Shangla Sanam Road Infra- structure Link Road (PCC) 8/30/11 11/30/11 34 110 759,414 6904 23 Shangla Sur Kumar Road Infra- structure Link Road (PCC) 6/9/11 6/11/11 54 125 765,417 6123 24 Shangla Abbasin Colony DWSS Gravity Flow 5/9/11 05/12/2011 45 100 1,194,500 11945 25 Shangla Feza Road Infra- structure Link Road (PCC) 8/28/11 11/28/11 44 120 883,761 7365 26 Shangla Sanila Sanitation Street pavement & Drainage 6/9/11 6/12/11 56 200 916,200 4581 27 Shangla Tangir Bridge Suspension Bridge (Pedes- trian) 9/13/11 12/13/11 155 155 1,110,500 7165 28 Swat Quanj Sanitation Street Pavement & Drainage 10/13/11 1/13/12 80 175 598,000 3417 29 Swat Jabba DWSS Hand Pump 11/21/11 1/21/12 140 200 402,850 2014 30 Swat Saidu Shareef DWSS Hand Pump 11/28/11 1/28/12 110 190 524,900 2763 31 Swat Mankass Kabel DWSS Hand Pump 11/24/11 2/24/12 52 80 223,244 2791 32 Swat Sorykad DWSS Gravity Flow 11/24/11 2/24/12 46 100 308,100 3081 33 Swat Faqira Sanitation Street pavement & Drainage 2/15/12 5/15/12 250 300 515,000 1717 35 Swat Babo Maira Irrigation Ramp Pump 11/19/11 19/01/2012 44 44 556,000 12636
  • 48. 48 36 Swat Bar Jopeen Sanitation Street pavement & Drainage 12/23/11 3/23/12 200 200 586,500 2933 37 Swat Dardyal,kabel DWSS Gravity Flow 5/9/11 05/03/2013 90 120 700,000 5833 38 Swat Baghgay Maloch Road Infra- structure RCC Cause Way 12/27/11 27/03/2012 65 80 722,300 9029 39 Swat Badardam DWSS Gravity Flow 11/28/11 2/28/12 50 80 853,500 10669 40 Swat Pengen Sanitation Street pavement & Drainage 9/15/11 12/15/11 260 260 807,500 3106 41 Swat Faqira Road Infra- structure Link Road - Reha- bilitation 6/9/11 6/2/12 65 125 832,300 6658 42 Swat Yakh Tangey DWSS Gravity Flow 8/27/11 11/27/11 60 60 838,600 13977 43 Swat Meradai DWSS Gravity Flow 10/30/11 1/30/12 40 40 667,500 16688 44 Swat Lawar Deolai, Qabil Irrigation Irrigation Channel 6/11/11 6/1/12 180 180 1,062,200 5901 45 Swat Akhun Baba Road Infra- structure Link Road PCC 2/13/12 4/13/12 450 550 1,069,000 1944 46 Swat Kaho Road Infra- structure Link Road (Reha- bilitation) 9/18/11 2/18/12 250 250 1,079,800 4319 47 Swat Meragai Irrigation Irrigation channel Lining & RT wall 12/8/11 12/11/11 120 25 1,086,300 43452 48 Swat Samteer Road Infra- structure Link road (Earthen) 10/25/11 12/25/11 150 150 1,093,300 7289 49 Swat Shagai Ghwajalgai DWSS Gravity Flow 10/14/11 1/14/12 26 26 620,100 23850 50 Swat Shagai Sanitation Street pavement & Drainage 8/22/11 11/22/12 160 275 1,201,000 4367 51 Swat Kokari Sar Road Infra- structure Link road (Earth- en & PCC) 10/31/11 12/31/12 315 315 1,309,700 4158 52 Swat Gujer Tangi Badro, Islampur Road Infra- structure Link Road 3/2/12 3/5/12 400 425 1,333,000 3136 53 Swat Kamay Bridge RCC Bridge 10/25/11 1/25/12 300 450 2,561,500 5692 54 Swat Shao MHP MHPP 5/7/12 5/12/12 250 275 8,612,000 31316 55 Upper Dir Doonpayeen DWSS Gravity Flow 10/15/11 4/15/12 120 250 655,000 2620 56 Upper Dir Shamorgar Road Infra- structure Link Road (PCC) 1/11/11 1/2/12 145 145 823,400 5679 57 Upper Dir Panakot Road Infra- structure Link Road 10/30/11 4/30/11 67 40 1,250,700 31268 58 Upper Dir Malow Bridge Suspension Bridge (Pedes- trian) 1/16/11 4/16/12 332 150 1,518,500 10123 59 Upper Dir Qulandai Payeen Bridge Suspension Bridge (Pedes- trian) 1/9/11 1/3/12 170 225 1,540,800 6848 60 Upper Dir Khan abad MHP MHPP 10/13/11 3/13/12 218 218 2,654,300 12176
  • 49. 49 Evaluation Parameters Areas of focus Evaluation Tools EERP Secondary data Engi- neers CPI Desk Review Report Engi- neers CPI Field Report HH Survey Focus Group Discus- sions Meeting with GOKPK Line depart- ments and other Key Infor- mants 1 Relevance • Do the schemes respond to the stated project objectives and overall goals of AusAid? • Do the selected CPIs reflect the felt need of the community? • Is it a priority • Gender wise analysis • GOKPK context o PCNA o Malakand strategy o Priority areas o Post flood and Insurgency • PCNA Report • Malakand Strategy • EERP proposal • Completion Docu- ment • Monitoring Report (H/O and District) • AusAid Goals/ob- jective (Website) • CBO Files/record P P P P 2 Effectiveness • Are the schemes functional? • Are the schemes delivering the designed services? • Is the scheme benefitting all inten- ded beneficiaries? (or some?) • Whether the CPI schemes meet the accepted engineering designs, specs and standards? • Actual design coverage vs. Plan- ned. • Gender wise breakdown • SRSP Monitoring Reports • CPI Completion Reports P P P P P 3 Efficiency • Cost and time comparison relative to original timelines and budgets • Unit scheme costs in relation to other GOKP/SRSP/CSO schemes • Cost per beneficiary for various scheme types • Illustrative Cost benefit analysis for sample schemes • P • CSR comparative GOKP • SRSP non EERP CPI proposal • Other CSO costing if available. P P P 4 Immediate Outcomes/ Impacts • Reported direct benefits (additi- onal land irrigated, greater yields, additional drinking supplies, enhanced land value, reduced burden of disease, others • Un-intended and/or indirect bene- fits • Gender wise breakdown • P • CPI Completion reports • Case studies by SRSP P P P P 5 Sustainability • Adequacy of design • Quality of construction and work- manship. • Systems for maintenance/O&M • Government support? • Current condition of schemes • P • CBO Files P P P P P Annex 4: Evaluation Matrix
  • 50. 50 Annex 5: QA Process SRSP AiD HO Final Report Compilation, Preparation and 4th Level QA by Project Advisor Compilation and Report Writing by Sector Specialists 3rd Level QA and Compilation at AiD’s HO. Compilation and 2nd Level QA At AiD’s HO 1st Level QA by Field Supervisor Engineer’s Field Visit Focus Group Discussion House Hold Survey Field Supervisor Field Plan Data Entry, Cleaning and Analyses by the Data Analyst
  • 51. 51 Annex 6: Physical Infrastructure- ( PI )- Implementation- Process 1st Dialogue • Program Introduction • Need Identification Not Feasible Audit Committee O&M Committee Project Approval CPI Construction • Documentation of Record in PI Register Project Completion • PI Completion Report • PI CompletionCertificate Handing Over to CO • Handing and taking over Certificate Feasible • Project Proposal 3rd Dialogue • Terms of Partnership Formation of • Project Implementation Committees • Audit Committee • O&M Committee Environmental Feasibility • Environment Screening • Enviornmental Review Social-Feasibility • Formation of CO • Opering of Bank Account • Conflict free Technical Feasibility • Design • Material Specifications • Construction drawings • Cost Estimates • Water Quality test 2nd Dialogue Type of Documentation reviewed for Availability and Adequacy CO Resolution
  • 52. 52 Work Plan for the Evaluation of Imm February March Week 1 Week 2 Week 3 Week 4 We 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2 Inception Phase Inception Phase 1 Contracts signed by SRSP 8th 2 Contract Signed by AiD Pvt Ltd 15th 3 Inception meeting with SRSP 4 Team Mobilization 5 Development of Evaluation Tools / Sampling 6 Team’s orientation and pre-testing of evaluation tools Field Work and Data Collec- tion Phase Phase Field Work and Cluster A 1 Data Collection - District Swat 2 Data Collection - District Malakand 3 Data Collection - District Buner 4 Data Collection - District Shangla Cluster B 5 Data Collection - District Lower Dir 6 Data Collection - District Upper Dir 7 Data Collection - District Chitral Data Analysis and Report Writing Phase 1 Consolidation and Clean up of Data 2 Data Analysis and Draft Report prepar- tion 3 Submission of First Draft 4 Feed back by SRSP on First Draft 5 Final report with changes Annex 7: W
  • 53. mediate Impact of SRSP EERP CPIs April eek 5 Week 6 Week 7 Week 8 Week 9 Week 10 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Data Collection Phase Phase Data Analysis and Report Writing 53 Work Plan
  • 54. 54 Annex 8: Community Infrastructure Pictures Chitral
  • 66. Sarhad Rural Support Programme 109, Street 2B, Defence Officers’Colony, Khyber Road, Peshawar Telephone: 92-91-9211417, 5285389 Fax: 92-91-5276734 E-mail: srsp@srsp.org.pk www.srsp.org.pk